15.1
The cultural heritage impact assessment
(CHIA) shall include i) built heritage impact assessment and ii) marine
archaeology impact assessment in accordance with Clause 3.4.9 of the EIA Study
Brief (No. ESB-129/2005).
15.2 It should be noted that no marine works would be required under this Project, except reconstruction of small part of the seawall (~53m) near the Aberdeen PTW to facilitate the PTW upgrading works. The scope of the seawall reconstruction works as shown in Figure 2.7b mainly involves two sections, including
· ~29m long of seawall required modification works due to construction of seawater intake pipeline and other PTW upgrading works (excavation proposed down to ~8m below existing ground level for construction works)
· ~24m long of seawall required minor modification works due to PTW upgrading (excavation proposed down to ~3m below existing ground level for construction works)
15.3
As indicated in the old as-constructed
drawings[1] (Appendix 15.4), the
15.4
In this Section, potential impacts on
built heritage resources during construction and operation phases were
assessed. Mitigation measures required to ameliorate the potential impacts to
acceptable levels have been recommended, where appropriate.
15.5
Legislation, Standards, Guidelines and Criteria relevant to the
consideration of Cultural Heritage impacts under this Project include the
following:
· Antiquities and Monuments Ordinance
· Environmental Impact Assessment Ordinance
·
· Technical Memorandum on Environmental Impact Assessment Process
·
Criteria for Cultural Heritage Impact
Assessment
15.6
The Antiquities and Monuments Ordinance
(the Ordinance) provides the statutory framework to provide for the
preservation of objects of historical, archaeological and palaeontological
interest. The Ordinance contains the statutory procedures for the Declaration
of Monuments. Under the Ordinance, monument means a
place, building, site or structure which is declared to be a monument,
historical building or archaeological or palaeontological site or structure by
reason of its historical, archaeological or palaeontological significance under
section 3 of the Ordinance.
15.7
Under section 6 and subject to
subsection (4) of the Ordinance, the following acts are prohibited except in
accordance with a permit granted by the Antiques Authority (presently the
Secretary for Development);,Under section 6 and subject to subsection (4) of
the Ordinance, the following acts are prohibited in relation to certain
monuments, except under permit:
· To excavate, carry out building or other works, plant or fell trees or deposit earth or refuse on or in a proposed monument or monument
·
To demolish, remove, obstruct, deface or
interfere with a proposed monument or monument
15.8
The discovery of an Antiquity, as
defined in the Ordinance must be reported to the Antiquities Authority (the
Authority), or a designated person. The Ordinance also provides that, the
ownership of every relic discovered in
15.9
No archaeological excavation may be
carried out by any person, other than the Authority and the designated person,
without a license issued by the Authority. A licence will only be issued if the
Authority is satisfied that the applicant has sufficient scientific training or
experience to enable him to carry out the excavation and search satisfactorily,
is able to conduct, or arrange for, a proper scientific study of any antiquities
discovered as a result of the excavation and search and has sufficient staff
and financial support.
15.10 The Environmental Impact Assessment Ordinance (EIAO) was implemented on 1 April 1998. Its purpose is to avoid, minimize and control the adverse impact on the environment of designated projects, through the application of the EIA process and the Environmental Permit (EP) system.
15.11
Chapter 10 of the Hong Kong Planning
Standards and Guidelines (HKPSG) details the principles of conservation, the
conservation of natural landscape and habitats, historic buildings and
archaeological sites. It also addresses the issue of enforcement. The
appendices list the legislation and administrative controls for conservation,
other conservation related measures in
15.12
The general criteria and guidelines for
evaluating and assessing impacts to cultural heritage are listed in Annexes 10
and 19 of the Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM). The guidelines state that preservation in totality and measures for
the integration of sites of cultural heritage into the proposed project will be
a beneficial impact. It also states that destruction of a site of cultural
heritage must only be undertaken as a last resort.
15.13
This document, as issued by the
Antiquities and Monuments Office (AMO), outlines the specific technical
requirement for conducting terrestrial archaeological and built heritage impact
assessments (BHIA). It includes the parameters and scope for the Baseline
Study, specifically desk-based research, field survey and the reporting
requirements. Besides, the prerequisite conditions for conducting impact
assessment and mitigation measures are presented in detail.
15.14
A desk-based study was undertaken to
determine the presence of historical occupation of the Study Area and thus to
assess the potential for built heritage resources to be present. Information
were gathered from the following sources; the AMO published and unpublished
papers and studies; publications on relevant historical, anthropological and
other cultural studies; unpublished archival, papers, records; collections and
libraries of tertiary institutions; historical documents which can be found in
Public Records Office, Lands Registry, District Lands Office, District Office,
Museum of History; cartographic and pictorial documentation.
15.15
In addition to the desk-based review,
in case where the sources of information proved to be inadequate or where the
project area had not been adequately studied before, field survey was conducted
to assemble the necessary data.
15.16
The Study Area for the built heritage
impact assessment (BHIA) includes all Project Areas as well as areas within 300
metres from the Project Areas’ boundaries. Specifically, the projects areas (Figures 2.1 to 2.10
refer) include:
i) Proposed deep underground sewage conveyance system (SCS) with 7 tunnel sub-sections, including
-
Tunnel J (from North Point PTW to Wan Chai East PTW)
-
Tunnel K (Wan Chai East PTW to Sai Ying Pun)
-
Tunnel L (from Sai Ying Pun to
-
Tunnel M (from
-
Tunnel N (from Cyberport PTW to
-
Tunnel P (from
-
Tunnel Q (from Ap Lei Chau PTW to
ii)
18 SCS permanent/temporary works areas mainly for
shaft construction and storage/stockpiling purposes.
iii)
8 Preliminary Treatment Works (PTW) including North
Point, Wan Chai East, Central,
iv)
Sites within or close to Stonecutters Island Sewage Treatment
Works (SCISTW) for expansion works and construction of effluent conveyance
system & disinfection facilities; as well as 2 temporary works areas close
to SCISTW for storage/stockpiling purposes .
15.17
Resources to be covered in the BHIA
field survey shall include, but are not limited to, the followings:
· All pre 1950 structures, which include any built feature (apart from graves and historical land use features, which are dealt with separately), such as domestic structures, ancestral halls, temples, shrines, monasteries and nunneries, village gates, wells, schools, historic walls, bridges and stone tablets;
· Any post 1950 structure deemed to possess features containing architectural or cultural merit;
· All pre-war clan graves; and
·
Cultural landscape features,
such as fung shui woods and ponds, historical tracks and pathways, stone walls and terraces, ponds and
other agricultural features.
North Point and
15.18
Eastern District was an area of
scattered rural communities in the 19th Century.
Wan Chai
15.19
Prior to the British arrival in Hong
Kong, the coast at Wan Chai was occupied by local fishing families and the
Sheung Wan, Sai Ying Pun and
15.20
Possession Point in Sheung Wan was the
landing site of the British Troops in 1841 and the site was used as a defensive
position. During the middle to late part of the 19th Century, the areas were
developed for commercial and residential purposes (Leung, 1998). After the
Second World War, these areas were rapidly developed and today the area
contains a mixture of residential, commercial and wholesale businesses.
15.21
Cyberport (Kong Sin Wan/ Telegraph Bay)
15.22
15.23
Both of these locations have long
historical associations with fishing families. There is an historic Tin Hau
temple in
15.24
15.25
A Chinese map dating to 1730 indicates
the location of the
15.26
15.27
In the past the island has been used as
the site of a prison, contagious diseases quarantine area, and for military
usage, containing military barracks, armament depots, batteries and underground
magazines and tunnels.
15.28
During the 1920’s and 30’s, an
ammunition depot and transmitting station were constructed and used by the Royal
Navy and there were also some coastal artillery batteries constructed before
the World War II (WWII). The island and its facilities were seized by the
Japanese during WWII and they built additional ammunition depots, a series of
tunnels, gun emplacements, batteries, administration centres, residences,
parade grounds and firing ranges (AMO Files). The island went back under the
control of the Royal Navy and remained so until it was handed over to the
British Army in 1957 (Ko and Wordie 1996). The site was handed over to the Hong
Kong Garrison of the People's Liberation Army (PLA) in July 1997 and named as Ngong Shuen Chau Barracks. The
Barracks is one of the military closed areas declared under the Military Installations Closed Areas Order (Cap. 245B).
15.29
A list of historical sites in the
project study area, as contained in AMO files on
(i) Old Prison Area (1863 – 1866) - The prison was constructed in reaction to a crime wave in the early 1860’s, but it was never used as a prison as there were not enough prisoners by the time it was finished. In 1871, the government announced that it would be used as a smallpox quarantine area and the prison hospital and chapel were used to house the patients. Most of the prison was destroyed by a typhoon in 1875. However, two watch towers, the gate house and parts of the enclosing wall survived (AMO Files).
(i)
Albion
(ii) Stonecutters
(iii) Stonecutters
15.30
One
15.31
Graded Buildings in the Study Area were
identified on
Table 15.1 Graded Buildings Identified on
Graded
Building |
Location |
Grade |
Map
Reference |
Former
Clubhouse of the Royal |
|
II |
Appendix
15.1 (4) |
Queen’s
Pier* |
Central |
I |
Appendix
15.1 (5) |
Lo
|
15
Ching Ling Terrace in |
I |
Appendix
15.1 (6) |
Ex-Western
Fire Station |
|
III |
Appendix
15.1 (22) |
* The present
status of Queen’s Pier is that it has been dismantled pending reconstruction
15.32
According to the desk-based study, there are some graded buildings and structures
in the Old Prison Area and
Table 15.2 List of Graded Buildings/Structures in Ngong Shuen Chau Barracks with field survey
Resource* |
Grade |
Old Prison Area, Block 318 |
I |
Old Prison Area, Block 319 |
I |
Old Prison Area, Block 322 |
III |
Old Prison Area, Block A |
II |
Old Stonecutters |
II |
Old Stonecutters |
III |
Old Stonecutters |
III |
Old Stonecutters |
III |
Old Stonecutters |
II |
Old Stonecutters |
II |
Old Stonecutters |
III |
Old Stonecutters |
III |
Old Stonecutters West
Battery, Ruins of |
II |
* Access
to the Old Prison Area, Block H (Grade II) and Old Stonecutters West Battery
Block 25 A-D (Grade III) was not available.
15.33
Field surveys were conducted from November
2006 to November 2007 at the project areas of 8 PTW, SCS works areas, SCS
alignments, SCISTW expansion areas as well as areas of 300 metres away from the
project area boundary. The results of the field surveys are presented below.
All catalogue reference numbers (HATS-#) detailing the historical
building information as stated below should be referred to Appendix 15.3.
15.34
The non-graded built heritage resources
as listed in Table 15.3 were
identified in the field survey.
Table
15.3 List of Non-Graded Built
Heritage Resources Identified in the Project Study Area
Resource |
Location |
Reference No. in Appendix
15.3 |
Map Reference |
|
Fortress Hill |
HATS-02 |
Appendix 15.1 (8) |
Shophouse |
Sai Ying Pun |
HATS-03 |
Appendix 15.1 (9) |
Shophouses |
Western District |
HATS-04 |
Appendix 15.1 (10) |
|
|
HATS-07 |
Appendix 15.1 (11) |
Noonday Gun |
|
HATS-29 |
Appendix 15.1 (24) |
Felix Villas |
|
HATS-23 |
Appendix 15.1 (20) |
Jubilee |
|
HATS-24 |
Appendix
15.1 (21) |
|
|
HATS-26 |
Appendix 15.1 (23) |
Arch and Foundation Stone of the Tung Wah |
Near |
HATS-27 |
Appendix
15.1 (23) |
(To Che Fat
She) |
Near |
HATS-28 |
Appendix
15.1 (23) |
Fok Hing
Tong |
|
HATS-31 |
Appendix
15.1 (6) |
|
Southern District |
N/A |
Appendix 15.1(25) |
|
Southern District |
N/A |
Appendix 15.1 (25) |
City of |
|
HATS-30 |
Appendix 15.1 (26) |
Note:
N/A = Access was not granted to the private properties. Therefore, no catalogue
form is available in Appendix 15.3.
North Point
15.35
Construction works (including
construction of a drop shaft, a seawater pumping station and other associated upgrading
works) would be conducted inside the existing PTW. A production shaft would be constructed at a
temporary works area (NP-viii) next to the existing PTW which is currently a
parking area for Towngas. No built heritage resources were identified in the
Study Area in North Point. Appendix 15.2
(Plate1) displays photograph of the North Point PTW.
Wan Chai East
15.36
Construction works (including
construction of a drop/riser shaft, a transfer pumping station and other sewage
treatment upgrading works) would be conducted inside the PTW site. The
photograph in Appendix 15.2 (Plate 2)
shows the Wan Chai East PTW. A production shaft would be constructed at a
temporary works area (WCE-i) immediately adjacent to the existing PTW site. The
PTW site lies next to a sport ground and is adjacent to the Wan Chai
interchange. There are also two nearby temporary works areas (WCE-vi and WCE-v)
associated with the project and they would be mainly for storage purpose. No
built heritage resources were identified in the Study Area of Wan Chai East.
Central
15.37
Construction works (including
construction of drop shaft and other sewage treatment upgrading works) would be
conducted within the
15.38
The
15.39
The PTW site is situated between a
sports ground and medical facility buildings. A temporary works area (SB-i) and
a permanent works area (SB-PS) with construction of transfer pumping station,
shafts and other upgrading works are located just to the North of the PTW site
on vacant land. No built heritage resources were identified in the Study Area
of Sandy Bay. The photograph in Appendix
15.2 (Plate 5) shows the location of the Sandy Bay PTW and the works areas.
Cyberport
15.40
Construction of a shaft and a transfer
pumping station would be conducted at the existing PTW. Appendix 15.2 (Plate 6) shows a photograph of the Cyberport PTW.
One built heritage resource was identified in the Study Area of Cyberport which
is the old cable house in Kong Sin Wan (
15.41
The Wah Fu PTW is located on
15.42
Aberdeen PTW site located on
Ap
Lei Chau
15.43
Construction of a transfer pumping
station, a drop shaft and other associated PTW upgrading works would be within
the existing Ap Lei Chau PTW on
Tunnel
J
15.44
This tunnel runs from the North Point
PTW to the Wan Chai East PTW. The following resources were identified in the
Study Area: the former clubhouse of the Royal Hong Kong Yacht Club (HATS-01),
the Noonday Gun (HATS-29)
and the
Tunnel
K
15.45
This tunnel runs from the Wan Chai East
PTW to the
Tunnel
L
15.46
This tunnel runs from the
Tunnel
M
15.47
This tunnel runs from the
Tunnel
N
15.48
This tunnel runs from Cyberport PTW to
Sandy Bay PTW. Two built heritage resources were identified in the desk-based
survey, Pre-1945 residential buildings at
Tunnel
P
15.49
This tunnel runs from Aberdeen PTW via
Wah Fu PTW to Cyberport PTW. One built heritage resource, the old cable house
at Kong Sin Wan (HATS-09), was identified during the field survey and
the location is shown in Appendix
15.1(19).
Tunnel
Q
15.50
This tunnel runs from Ap Lei Chau PTW
to Aberdeen PTW. No built heritage resources were identified in the field
survey.
15.51
Construction works would be conducted
at the existing SCISTW and the nearby area for proposed disinfection facilities
and effluent conveyance system, as shown in Appendix 15.2 (Plate 10). Historical sites of Ruins of the West
Battery, Ruins of the Generator House, Old West Battery and the Old Central Battery, as shown in Appendix 15.1(16) were identified
within 300 metres of the proposed facilities during the field survey.
Works associated with
Preliminary Treatment Works
15.52
Three built heritage resources,
including Western Market, Old Cable House and Noonday Gun, were identified
280m, 300m and 280m from the
Works associated with
Sewage Conveyance System
15.53
As mentioned in Section 2, other than
Horizontal Directional Drilling (HDD) to be used for construction of Tunnel Q
from
15.54
Construction of SCS would comprise the
components of vertical shaft & horizontal tunnel. Blasting at shafts would
be at variable depths depending on the rockhead level at each location. In
general, the range of rockhead would be ranging from 10m to 80m below ground.
The level of proposed sewage tunnels would be from 75m to 160m below
ground. As such, the levels of ground
vibration due to blasting works are expected to be higher during construction
of shafts than that of sewage tunnels.
15.55
In order to prevent potential damage to historical buildings and structures,
maximum limits for safe vibration levels have been set at 25 mm/s. This vibration limit has been applied in controlling
vibrations due to blasting operations in
Expansion Works on SCISTW
15.56
On Stonecutters Island,
construction of the new structures, including deep excavation and bore piling
works within the existing SCISTW, the proposed areas for disinfection
facilities on the northwestern side of the SCISTW, and the effluent tunnel as
part of the effluent conveyance system connecting the SCISTW via the
disinfection facilities to the outfall, may have potential to cause structural
damage to any remaining historical features through vibration damage.
15.57
Operation of HATS Stage 2A would have
no impact on the built heritage resources based upon the fact that proposed
construction works on
15.58
According to the latest
engineering design for PTWs, SCISTW and SCS, no declared monuments, graded or
non-graded historic buildings were found within the project boundary. Hence, It
is envisaged that there would not be any direct impact (e.g. demolition) on the
identified heritage resources. Any heritage resources located in close proximity to the project areas
may be impacted through indirect vibration impact induced by the activities
e.g. tunnel boring or drill and blast activities during construction phase.
Preliminary
Treatment Works
15.59
Two of the PTW sites, including Central
PTW and Cyberport PTW, were found to have historical structures within the 300m
Study Area. Details of the assessment are presented in Table 15.4.
Table 15.4 Assessment of the Impacts to Resources
within 300m of PTW Sites
Resource |
Nearest PTW
Site |
Minimum Distance to
Project Area |
Map Reference |
Impact
Assessment |
Western Market (HATS-05) |
|
280m |
Appendix 15.1 (3 & 14) |
Conventional construction
plant/ equipment and non-percussive piling methods would be used for
construction of PTW upgrading works. Adverse impact on the resource is
therefore not expected. The shaft at the PTW may be
conducted by blasting at rock layer. This structure has been identified as
sensitive to damage from blasting. |
Old Cable House (HATS-09) |
Cyberport PTW |
300m |
Appendix 15.1 (7 & 19) |
Conventional construction
plant/ equipment and non-percussive piling methods would be used for
construction of PTW upgrading works. Adverse impact on the resource is not
expected. The shaft at the PTW may be
conducted by blasting at rock layer. This structure has been identified as
sensitive to damage from blasting. |
Sewage Conveyance
System
15.60
Construction of riser shaft and
production shaft would be within the existing SCISTW. The riser shaft would be
connected to the deep SCS (140 metres below sea level) under the harbour
skirting the rest of
15.61
The tunnel at Sai Ying Pun would then
run both i) to the east until reaching the North Point PTW and ii) to the west
until reaching the Ap Lei Chau PTW. Construction of the tunnel may have
potential impacts on the nearby heritage resources on the
Table 15.5 Assessment of the Impacts to Resources
within 300m of SCS
Resource |
Nearest SCS
Section |
Minimum Distance to SCS |
Map Reference |
Impact
Assessment |
Former
Clubhouse of the Royal |
Tunnel J |
300m |
Appendix 15.1 (4 & 12) |
The structure is historical
and as such is susceptible to vibration damage from blasting. |
|
Tunnel J |
300m |
Appendix 15.1 (8 & 12) |
The structure is not
historical and is not especially susceptible to vibration damage from
blasting. |
Noonday
Gun (HATS-29)
|
Tunnel J |
10m |
Appendix 15.1 (24 & 31) |
The noonday gun is a non
structural heritage resource and would not be impacted by the proposed works. |
Old
Shophouse at |
Tunnel K |
100m |
Appendix 15.1 (9 & 13) |
The structure is historical and
as such is susceptible to vibration damage from blasting. |
Two old
Shophouses at 67 & |
Tunnel K |
100m |
Appendix 15.1 (10 & 14) |
The structures are historical
and as such are susceptible to vibration damage from blasting. |
Western
Market (HATS-05) |
Tunnel K |
160m |
Appendix 15.1 (3 & 14) |
The structure is historical
and as such has been identified as sensitive to vibration damage from
blasting. |
Queen’s
Pier (HATS-06) |
Tunnel K |
100m |
Appendix 15.1 (5 & 15) |
Queen’s pier has been
dismantled subsequent to the original survey for this project and will not be
impacted by the proposed works. |
Mount |
Tunnel M |
155m |
Appendix 15.1 (11 & 17a) for northern section
& (17b) for southern section |
The structure is historical
and as such is susceptible to vibration damage from blasting. |
Lo |
Tunnel M |
280m |
Appendix 15.1 (6 & 18) |
The structure is historical
and as such is susceptible to vibration damage from blasting. |
Old
Cable House at Kong
Sin Wan (HATS-09) |
Tunnel M |
250m |
Appendix 15.1 (7 & 19) |
The structure is historical and
as such is susceptible to vibration damage from blasting. |
Felix
Villas (HATS-23) |
Tunnel M |
110m |
Appendix 15.1 (20 &27) |
The structure is historical
and as such is susceptible to vibration damage from blasting. |
Jubilee |
Tunnel M |
20m |
Appendix 15.1 (21 & 28) |
The structures are historical
and as such are susceptible to vibration damage from blasting. |
Ex-Western
Fire Station
(HATS-25) |
Tunnel M |
160m |
Appendix 15.1 (22 & 29) |
The structure is historical
and as such is susceptible to vibration damage from blasting. |
(HATS-26) |
Tunnel M |
35m |
Appendix 15.1 (23 & 30) |
The structure is historical
and as such is susceptible to vibration damage from blasting. |
Arch and
Foundation Stone of
the Tung |
Tunnel M |
10m |
Appendix 15.1 (23 &30) |
The structure is historical
and as such is susceptible to vibration damage from blasting. |
(To Chi
Fat She) (HATS-28) |
Tunnel M |
20m |
Appendix 15.1 (23 & 30) |
The structure is not
historical and is not especially susceptible to vibration damage from
blasting. |
City of (HATS-30) |
Tunnel M |
180m |
Appendix 15.1 (26 & 33) |
The stone is a single piece of
granite and is not especially
susceptible to vibration damage from blasting. |
Fok Hing
Tong (HATS-31) |
Tunnel M |
240m |
Appendix 15.1 (6 &18) |
The structures are historical
and as such are susceptible to vibration damage from blasting. |
|
Tunnel M |
115 m |
Appendix 15.1 (25 & 32) |
|
|
Tunnel M |
75 m |
Appendix 15.1 (25 & 32) |
|
Old
Prison Area, Block 318 (HATS-10) |
Tunnel L |
~300m |
Appendix 15.1 (16) |
|
Old
Prison Area, Block 319(HATS-11) |
Tunnel L |
|||
Old
Prison Area, Block A (HATS-12) |
Tunnel L |
|||
Old
Prison Area, Block 322 (HATS-13) |
Tunnel L |
|||
Old
Prison Area, Block H |
Tunnel L |
Stonecutters
Existing
SCISTW
15.62
The works proposed for the existing
SCISTW site involve deep excavation for influent pumping station and
construction of other facilities e.g. additional sedimentation tanks and sludge processing facilities. Construction would involve piling to
form foundations. These may have potential to cause
structural damage to any remaining historical features through vibration
damage. Details of the assessment are presented in Table 15.6.
Table 15.6 Assessment of the Impacts from Existing
SCISTW to Graded Buildings on
Resource |
Minimum Distance to
Project Area |
Map Reference |
Impact
Assessment |
Old |
215m |
Appendix 15.1 (16) |
The structure is historical
and as such is susceptible to vibration damage due to drill & blast for
effluent conveyance system connecting from distribution chamber at existing
SCISTW to the chlorine contact tank. |
Area for Disinfection
Facilities
15.63
On the proposed areas for disinfection
facilities to the northwestern side of the SCISTW, construction of effluent
tunnel & associated chambers as well as other disinfection facilities which
involve excavation, bore piling works and possibly drill and blast may have
potential to cause structural damage to any remaining historical features
through vibration damage. Details of the assessment are presented in Table 15.7.
Table 15.7 Assessment of the Impacts from works
within the Proposed Area for Disinfection Facilities to Graded Buildings on
Resource |
Minimum Distance to
Project Area |
Map Reference |
Impact
Assessment |
Old *Block 25 A-D Block 29 (HATS-14) Block 35 (HATS-15) Block 36 (HATS-16) Block 37 (HATS-17) Block 41 (HATS-18) Block 43 (HATS-19) |
100m to 190m |
Appendix 15.1 (16) |
The structures are historical and as
such are susceptible to damage from vibration during blasting for
disinfection facilities. |
Ruins of the Generator
House(HATS-20) |
240m |
Appendix 15.1 (16) |
|
Ruins of the (HATS-21) |
140m |
Appendix 15.1 (16) |
* Access was not available
to Block 25 A-D and therefore they were not included in the field survey.
Temporary Works Areas
on
15.64
Two temporary works areas (SCI-i and
SCI-ii) are located some 500 metres to the northeast of SCISTW (Figure 2.9 – sheet 19 of 19
refers). As the works areas would not involve any construction activities
(mainly for stockpiling/storage purpose) and hence no adverse impact on the
historical structures on the island from these two works areas would be
expected.
Acceptability
of the Vibration Impact on Heritage Resources
15.65
The peak particle velocity (ppv) levels
predicted at the Arch and Foundation Stone of the
Table 15.7a Calculated Peak Particle Velocity for Selected Heritage Resources
Resource |
Nearest SCS Tunnel |
Minimum Distance to
Project Area |
Calculated ppv
(mm/s) |
Case 1 - Allowable Charge Weight Per Delay for Heritage with
Shallow Foundation founded on soil * |
|||
Arch and Foundation Stone of
the |
Tunnel M |
10m |
5.1 |
Case 2 - Allowable Charge Weight Per Delay for Heritage assumed
with Deep Foundation founded on rock** |
|||
Arch and Foundation Stone of
the |
Tunnel M |
10m |
6.8 |
*: Assume the heritage structure to be
founded on shallow foundation near to ground surface.
**: Assume the heritage structure to be
founded with deep foundation on rockhead.
15.66
In order to prevent potential damage to historical buildings and structures,
maximum limits for safe vibration levels have been set at 25 mm/s. This vibration limit has been applied in controlling
vibrations due to blasting operations in
15.67 Given that all proposed mitigation measures (that is monitoring of vibration levels to ensure that they do not exceed the set limits) are properly implemented, there would be no adverse impacts associated with the project works anticipated (as the monitoring will ensure that limits are not exceeded.)
Preliminary Treatment Works
Table 15.8 Mitigation Recommended for Resources
near PTW Sites
Resource |
Nearest PTW Site |
Recommended Mitigation Measures |
Western Market (HATS-05) |
|
It has been determined that
the maximum vibration level should be limited to a peak particle velocity
(ppv) limit of 25mm/s. During
the blasting for shaft construction at the nearest PTW (as listed in the
second column of this table), monitoring of the vibration levels should be
undertaken through the use of measures such as fixing approved tell tales and
tilting monitoring points to the historic buildings and structures on a
weekly basis. The proposed monitoring points shall be submitted to AMO for
agreement before commencement of the construction work. If vibration levels
are found to exceed the limit of 25 mm/s, the Project Proponent shall take
immediate corrective action by reducing the rate of forward progress, as
necessary, to bring PPV levels within compliance. Monitoring results should be
submitted to the engineer in an agreed format within two days of each
monitoring undertaken. A permit under
section 6 of the Antiquities & Monuments Ordinance (Cap. 53) is required
before installation work of monitoring instruments may commence at Western
Market, a |
Old Cable House (HATS-09) |
Cyberport PTW |
Sewage Conveyance System
Table 15.9 Mitigation Recommended for Resources
near Sewage Conveyance System
Resource |
Nearest Tunnel Section |
Recommended Mitigation Measures |
Former Clubhouse of the Royal Street (HATS-01) |
Tunnel J |
It has been determined that
the maximum vibration level should be limited to a peak particle velocity
(ppv) limit of 25mm/s. During
the blasting for construction of Tunnel J, monitoring of the vibration levels
should be undertaken through the use of measures such as fixing approved tell
tales and tilting monitoring points to the historic buildings and structures
on a weekly basis. The proposed monitoring points shall be submitted to AMO
for agreement before commencement of the construction work. If vibration
levels are found to exceed the limit of 25 mm/s, the Project Proponent shall take
immediate corrective action by reducing the rate of forward progress, as
necessary, to bring PPV levels within compliance. Monitoring
results should be submitted to the engineer in an agreed format within two
days of each monitoring undertaken. |
Old Shophouse at |
Tunnel K |
It has been
determined that the maximum vibration level should be limited to a peak particle
velocity (ppv) limit of 25mm/s. During
the blasting for construction of the nearest tunnel (as listed in the second
column of this table), monitoring of the vibration levels should be
undertaken through the use of measures such as fixing approved tell tales and
tilting monitoring points to the historic buildings and structures on a
weekly basis. The proposed monitoring points shall be submitted to AMO for
agreement before commencement of the construction work. If vibration levels
are found to exceed the limit of 25 mm/s, the Project Proponent shall take
immediate corrective action by reducing the rate of forward progress, as
necessary, to bring PPV levels within compliance. Monitoring results
should be submitted to the engineer in an agreed format within two days of
each monitoring undertaken. A
permit under section 6 of the Antiquities & Monuments Ordinance (Cap. 53)
is required before installation work of monitoring instruments may commence
at Western Market, a |
Two old Shophouses at 67
& |
Tunnel K |
|
Western Market (HATS-05) |
Tunnel K |
|
Mount |
Tunnel M |
|
Lo |
Tunnel M |
|
Old Cable House in Kong Sin
Wan ( (HATS-09) |
Tunnel M |
|
Felix Villas (HATS-23) |
Tunnel M |
|
Jubilee |
Tunnel M |
|
Ex-Western Fire Station (HATS-25) |
Tunnel M |
|
|
Tunnel M |
|
Arch
and Foundation Stone of the |
Tunnel M |
|
Fok Hing Tong (HATS-31) |
Tunnel M |
|
50 – |
Tunnel M |
|
|
Tunnel M |
|
Ngong Shuen Chau Barracks,
Old Prison Area Block 318 (HATS-10) Block 319 (HATS-11) Block A (HATS-12) Block 322 (HATS-13) Block H |
Tunnel L |
Stonecutters
Table 15.10 Mitigation Recommended for Resources near
existing SCISTW
Resource |
Recommended Mitigation Measures |
Old |
It has been
determined that the maximum vibration level should be limited to a peak particle
velocity (ppv) limit of 25mm/s. During
the blasting for construction of the effluent conveyance system, monitoring of the vibration levels should be
undertaken through the use of measures such as fixing approved tell tales and
tilting monitoring points to the historic buildings and structures on a
weekly basis. The proposed monitoring points shall be submitted to AMO for
agreement before commencement of the construction work. If vibration levels
are found to exceed the limit of 25 mm/s, the Project Proponent shall take
immediate corrective action by reducing the rate of forward progress, as
necessary, to bring PPV levels within compliance. Monitoring results
should be submitted to the engineer in an agreed format within two days of
each monitoring undertaken. |
Area for Disinfection Facilities
Table 15.11 Mitigation
Recommended for Resources near Area for Disinfection Facilities
Resource |
Recommended Mitigation Measures |
Old Block 25 A-D Block 29 (HATS-14) Block 35 (HATS-15) Block 36 (HATS-16) Block 37 (HATS-17) Block 41 (HATS-18) Block 43 (HATS-19) Ruins of the Generator House
(HATS-20) Ruins of the |
It has been
determined that the maximum vibration level should be limited to a peak particle
velocity (ppv) limit of 25mm/s. During
the proposed blasting work at the area for disinfection facilities, monitoring of the vibration levels
should be undertaken through the use of measures such as fixing approved tell
tales and tilting monitoring points to the historic buildings and structures
on a weekly basis. The proposed monitoring points shall be submitted to AMO
for agreement before commencement of the construction work. If vibration
levels are found to exceed the limit of 25 mm/s, the Project Proponent shall take
immediate corrective action by reducing the rate of forward progress, as
necessary, to bring PPV levels within compliance. Monitoring results should be submitted
to the engineer in an agreed format within two days of each monitoring
undertaken. |
15.68
There would be no adverse impacts
associated with the operational phase of the Project and no mitigation measures
would be required.
15.69
With the implementation of the proposed
mitigation measures, no residual impacts on the heritage buildings/structures
are expected during construction and operation phases of the Project.
15.70
During blasting for tunnel, shafts,
effluent conveyance system and disinfection facilities in the vicinity of the
buildings/structures, the Project Proponent must design the method of
construction and undertake vibration monitoring at the identified sensitive
historical structures as a requirement of EM&A
programme in such a way that a maximum vibration level of 25
mm/s is not exceeded. To ensure that this maximum limit is not exceeded, the Project Proponent must
implement a monitoring schedule. The monitoring should be undertaken through
the use of measures such as tell tales and tilting monitoring points to the
historic buildings and structures on a weekly basis. If vibration levels are
found to exceed the maximum limit of 25 mm/s, the Project Proponent shall
take immediate corrective action by reducing the rate of forward progress, as
necessary, to bring PPV levels within compliance. Monitoring results should be
submitted to the engineer in an agreed format within two days of each
monitoring undertaken.
15.71
Based on the desk-based study and field
survey findings, none of the heritage resources would be directly impacted by
the proposed project. The impacts that have been identified would arise from
blasting for tunnel, shafts, effluent conveyance system and disinfection
facilities. Impact assessment results indicated that exceedance of the
vibration limit of 25 mm/s would not be expected at all the identified cultural
heritage sites. An environmental monitoring and audit programme will be
implemented by the Project
Proponent to ensure that the vibration levels are kept
within acceptable limits during blasting for tunnel, shafts, effluent
conveyance system and disinfection facilities in the vicinity of the
buildings/structures.
15.72
In all, the HATS Stage 2A Project would
not cause any insurmountable impacts to heritage resources in the Study Area
during construction phase if the recommended mitigation measures are properly
implemented. There will be no impact to the heritage during operation phase.
1.
AMO Files,
2.
Cheung P.H (ED.) 2000, A Century of Hong Kong Roads and Streets,
Joint Publishing,
3.
Eastern District Board, 1994, Eastern
4.
Empson, H., 1992, Mapping
5.
Ko, T. K. and Wordie J., 1996, Ruins of War
A Guide to Hong Kong’s Battlefields and Wartime Sites, Joint Publishing,
6.
Leung, P.W., 1998, Heritage of the Central and Western District, Hong Kong;
Central and Western Provisional District Board;
7.
Proceedings of the
8.
Ratings and Valuation Department Hong Kong SAR Government 2005,
Names of Buildings: Volume 1
9.
Starling, A.E. Plague, 2006, SARS and the
History of Medicine in Hong Kong,
[1] The as-constructed
drawings provided by Civil Engineering and Development Department. were
prepared under the ‘Contract no. 454 of 1974 - Construction of Seawall Fronting