17                 CONCLUSIONS & SUMMARY OF ENVIRONMENTAL OUTCOMES

 

Summary of EIA Findings

 

17.1            This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the HATS Stage 2A Project. The assessment has been conducted, in accordance with the Study brief No. ESB-129/2005 under the EIAO for the Project, covering the following environmental issues:

n                      Air Quality

n                      Airborne Noise

n                      Ground-borne Noise

n                      Water Quality

n                      Human Health Risk and Ecological Risk

n                      Waste Management Implications

n                      Terrestrial Ecology

n                      Marine Ecology

n                      Fisheries

n                      Landscape and Visual

n                      Hazard to Life

n                      Cultural Heritage

 

Air Quality

 

Construction Phase

 

17.2            Air quality impact from the construction of the Project has been modelled using the FDM model.  No exceedances of hourly and daily TSP criteria to occur at ASRs in the vicinity during construction with implementation of recommended watering frequency of work site.  The dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation are recommended to be implemented during construction of the Project.  There would be no adverse residual air quality impact due to the Project during construction phase.

 

Operation Phase

 

17.3            Odour emission from the PTWs and SCISTW would be the main concern during the operation phase.  Air dispersion modelling (ISCST3) was conducted to simulate the potential odour impacts of the SCISTW and the PTWs on the ASRs.  All the identified odour sources in the PTWs and SCISTW should all be properly enclosed or covered, with the foul air drawn through deodorization units and discharged after treatment.  The odour removal efficiencies of the proposed one stage and two stages deodorization system should achieve 80% to 90% and 97% respectively as detailed in this EIA study.  Good house keeping (regular cleansing schedule) should be conducted to minimize odour generation from the PTWs and SCISTW.  With the proposed mitigation, the residual odour impacts at the ASRs were predicted to be in compliance with the odour criterion.  It is also recommended that odour monitoring should be carried out during the operation phase to ensure that the odour criteria are satisfied at the ASRs.

 

Airborne Noise

 

Construction Phase

 

17.4            This assessment has predicted the construction noise impacts of the Project during normal daytime working hours, taking into account other concurrent projects including Sun Yat Sen Memorial Park (Phase II) project, Western Cross Harbour Main project, the WDII, CWB & IECL project and Hong Kong West Drainage Tunnel. The predicted unmitigated noise levels would range from 56 to 89 dB(A) at the representative NSRs. With the use of quiet PME, movable barriers and acoustic mats for construction tasks under the Project, the noise levels at all representative NSRs except N1 during the examination periods would comply with the construction noise standards.

 

17.5            Assessing against the noise standard of 65 dB(A) during examination periods, the predicted noise level at NSR N1 (i.e. Madam Chan Wai Chow Memorial School) would exceed the noise standard by up to 5 dB(A), The on-site survey has revealed that NSR N1 has already been noise insulated with air-conditioners, therefore no adverse noise impact would be expected at the indoor environment. Notwithstanding this, it is recommended that the particularly noisy construction activities should be scheduled to be undertaken during the summer vacation period as far as practicable.

 

17.6            An indicative assessment has been undertaken for possible construction activities within the tunnel and bottom of shaft during restricted hours. Based on information provided by the Engineer, no major items of PME except ventilation fans and gantry crane would be operated above ground during restricted hours (1900 to 0700 hours). The assessment results show that the predicted construction noise levels at representative NSRs during restricted hours would comply with the corresponding noise limits, provided that the ventilation fans and motors of gantry at the production shafts of Sandy Bay PTW would be properly housed and the silencers would be installed at outlet and inlet of the enclosure for ventilation fans. It should be noted that the results of the construction noise impact assessment for restricted hours are for indicative purposes, the Noise Control Authority will process any CNP application based on the NCO and the relevant technical memoranda in addition to considering the contemporary situations / conditions.

 

17.7            A construction noise EM&A programme is recommended to check the compliance of the noise criteria during normal daytime working hours.

 

Operation Phase

 

17.8            The noise impact associated with the operation of the Project was assessed. For newly proposed equipment, the predicted noise levels at all representative NSRs except N12, N13, N14, N15a, N15b, N16, N17 and N20 would comply with the night-time planning noise criteria. The noise levels at these affected NSRs would exceed the planning noise criterion by 1 to 13 dB(A). For cumulative noise impact, the predicted noise levels at all representative NSRs except N13, N15a and N15b would comply with the night-time ANL. The cumulative noise level at N13, N15a and N15b would exceed the night-time ANL of 50 dB(A) by up to 8 dB(A). 

 

17.9            To mitigate the noise impact at the affected NSRs, acoustic louvers have been proposed for air supply fans/extraction fans of transfer pumping stations and ventilation fans of deodourization unit at Sandy Bay PTW, Cyberport PTW and Wah Fu PTW. Besides, it is recommended that the maximum allowable sound power level (SWL) of each new transformer at Sandy Bay PTW shall be limited to 89 dB(A) during the detailed design stage. With such proper designs, the predicted noise levels at all representative NSRs would comply with both the night-time ANL and night-time planning noise criteria. No residual operation noise impact arising from the Project is anticipated.  

 

17.10        Proper designs of PTWs, SCISTW and disinfection facilities would control the potential noise impact at noise sensitive receivers within acceptable levels, operational noise monitoring is not considered necessary.

 

Groundborne Noise

 

Construction Phase

 

17.11        The major activities inducing potential groundborne noise impacts are from operation of TBM and hydraulic breaker during tunneling and rock breaking. The noise impacts on the closest sensitive receiver was assessed and the predicated unmitigated noise levels of TBM and hydraulic breaker were 33 and 34 dB(A) at the worst affected NSRs respectively which are well within the statutory requirements. As such, all NSRs along the proposed tunnel alignment would not be adversely affected by groundborne noise generated by the construction of the Project, and mitigation measures as well as monitoring programme would not be necessary.

 

Operation Phase

 

17.12        No groundborne noise would be expected during operation of the Project and hence no mitigation measures would be recommended.

 

Water Quality

 

Construction Phase

 

17.13        The general construction works for the Project would be land-based except seawall re-construction at the Aberdeen PTW. No dredging activities would be required for the Project. The fine content in the fill material during seawall re-construction at the Aberdeen PTW should be negligible. Key water quality issues associated with land-based construction would include the impacts from site run-off, sewage from workforce, accidental spillage and discharges of wastewater from various construction activities. With well maintained site drainage and the implementation of good site practices, impacts would be controlled to comply with the WPCO standards by implementing the recommended mitigation measures. No unacceptable water quality impact would therefore be expected.

 

17.14        Temporary bypass of sewage effluent via individual PTW would be required during the construction stage.  The water quality impacts during the temporary sewage bypass were assessed using the Delft3D model.  The predicted water quality impact associated with the temporary discharge would be short-term and the water quality would return to the normal condition quickly after the sewage bypass period. Water quality monitoring is recommended to be carried out during the temporary sewage bypass to quantify the water quality impacts and to determine when the baseline water quality conditions are restored.  Also, a framework of the response procedures has been formulated to minimize the impact of temporary discharges. No insurmountable water quality impact would be expected.

 

Operation Phase

 

17.15        The water quality impacts during operation of the Project were assessed using the Delft3D model.  Impacts were assessed over a series of one-year simulation periods.  The assessment area included the Victoria Harbour, Western Buffer, Eastern Buffer, Junk Bay, Northwestern, and Southern Water Control Zones.  Sensitive receivers within the assessment area identified for water quality impact assessment included cooling water intakes, flushing water intakes, fish culture zones, beaches, sites of special scientific interest, marine parks, marine reserves, seagrass beds, artificial reefs, corals, the Chinese White Dolphin and Green Turtle nesting grounds.

 

17.16        The water quality modelling results showed that the Project would not cause any adverse impact on the marine water quality and on the identified sensitive receivers during normal operations of the SCISTW.  The total residual chlorine from the chlorination/dechlorination disinfection process would meet the criterion set for the edge of the zone of initial dilution, with a large safety margin.  Whole effluent toxicity tests showed that the chlorination/dechlorination disinfection process did not introduce additional toxic effects to the test organisms.  A Post Project Monitoring (PPM) programme was proposed to confirm the model predictions made in this EIA.

 

17.17        Overflow at PTW may occasionally occur only during storm events and the extent of impact was predicted to be minor and acceptable.  Mitigation measures, including dual power supply, standby pumps, treatment units and equipment, would be provided at SCISTW to minimize the occurrence of emergency discharge. Standby unit(s) and dual (backup) power supply would also be provided at all the Stage 2 PTWs to reduce the risk of equipment breakdown at the PTWs. The model suggested that the water quality impacts associated with power or equipment failure at SCISTW and the Stage 2 PTWs would be short term. The water quality would return to the normal condition quickly after the emergency sewage. In case of power outage of the dechlorination plant, the uninterruptible power supply (UPS) system to be provided would switch the power supply of the sodium bisulphite dosing pump to a backup battery almost instantaneously, allowing continuous dosage of sodium bisulphite for at least half an hour so that sufficient time can be provided for shutting down the chlorination plant to avoid the possibility of discharge of chlorinated effluent. An emergency contingency plan has been formulated to minimise the impact of emergency discharges and facilitate subsequent management of the emergency.  An event and action plan and a detailed EM&A programme are recommended to collect water quality information and to mitigate the potential impact due to emergency discharge. The monitoring results shall be employed to identify areas for any further necessary mitigation measures to avoid, rectify and eliminate environmental damage associated with the Project.

 

Human Health and Ecological Risk

 

17.18        A detailed risk assessment was conducted to assess the potential adverse human health and ecological effects that may result from exposure of toxic substances due to HATS effluent discharge. 

 

Risk to Human Health

 

17.19        Potential risk/hazard impact due to potential chlorination by-products and other contaminants present in the chlorinated/dechlorinated HATS effluent would be acceptable under established assessment criteria in all the three Project Scenarios. According to the risk assessment results, the Project would not cause unacceptable risk to human health.  Therefore, the Project would be considered to be environmentally acceptable in terms of risks/impacts to human health.

               

Risk to Aquatic Life

 

17.20        Potential risk to aquatic life due to CBPs present in C/D HATS effluent would be lower than the screening value and considered acceptable.  Cumulative risk assessment revealed that CBPs and other pollutants present in the C/D HATS effluent, together with the pollutants present in the ambient water, may induce a total hazard index level above the screening value of 1.0.  It is noted that hazard index to aquatic life due to pollutants present in the background already exceeds the screening value.  Effluent discharge from SCISTW would only induce low incremental risk (i.e. hazard quotient < 1) at edge of mixing zone for all pollutants considered, indicating that concentration of CBPs and pollutants would be complied with available local/overseas water quality standards at the edge of mixing zone.

 

17.21        According to USEPA (2005), the calculated HI exceeding the screening value would not indicate that the proposed action is not safe or that it presents an unacceptable risk.  Rather, it triggers further investigation.  Further investigation is carried out based on the results of WETT, which is able to assess the impacts caused by aggregate toxic effects of the mixture of pollutants in effluent.

 

17.22        Results of WETT on C/D effluent are used to supplement the findings of ERA – Aquatic Life and determine whether the C/D effluent would induce adverse effects to aquatic life.  Statistical analysis of WETT data revealed that C/D process does not induce additional toxicity to the sewage effluent.  Also, it is found that the established toxicity criteria are well complied with at both edge of ZID and edge of mixing zone in all Project Scenarios.  With the comfortable margin (about 4/5 of the toxicity criteria value) to the established toxicity criteria, it is expected that the aquatic life present in the receiving water would not experience unacceptable toxicity even taking into account the background seawater conditions.  This is supported by the assessment results that concentration of all COCs would be complied with available local/overseas water quality standards at the edge of mixing zone.  Therefore, the potential risks due to C/D effluent imposed to aquatic life are expected to be acceptable.

 

Ecological Risk – Marine Mammals

 

17.23        Potential risk to marine mammals due to CBPs present in C/D HATS effluent would be lower than the screening value and considered acceptable.  Cumulative risk assessment revealed that CBPs and other pollutants present in the C/D HATS effluent in all the three Project Scenarios (Hazard Index from 0.126 to 0.129 for dolphins; Hazard Index from 0.0757 to 0.0800 for porpoises) would also be lower than the screening level and considered acceptable.

 

17.24        According to the risk assessment results, the Project would not cause unacceptable risk to ecological resources.  Therefore, the Project is considered to be environmentally acceptable in terms of risks/impacts to marine ecological resources.

 

Waste Management Implications

 

17.25        Waste types generated by the construction activities are likely to include C&D material (from excavation and tunnelling works), general refuse from the workforce, and chemical waste from the maintenance of construction plant and equipment.  Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts are not expected during the construction phase.

 

17.26        The main waste types to be generated during the operation phase would be grit and screenings collected at the upgraded PTWs and the SCISTW, and sewage sludge collected at the SCISTW.  The collection, transportation and disposal practices of the grit and screenings would follow the existing arrangements currently in operation at the PTWs and SCISTW.  The dewatered sludge from the SCISTW would be disposed of to the proposed Sludge Treatment Facilities which would be commissioned in 2012 under the current planned arrangement.

 

Terrestrial Ecology

 

17.27        Literature review and recent reconnaissance visits on terrestrial ecological resources identified seven habitat types within the Assessment Areas of this Project, including developed area, wasteland, woodland, plantation, shrubland, grassland and watercourse. The identified natural woodland habitat were found to have moderate / moderate to high ecological value while all other habitats, plantation woodland, shrubland and grassland of low value, and developed area, wasteland and watercourse of very low value.

 

17.28        Two sites of conservation importance, the existing Pok Fu Lam Country Park and the coincided Pok Fu Lam Reservoir Catchment Area Site of Special Scientific Interest (SSSI), falls partly within the Assessment Area at Aberdeen. Whilst, natural woodlands of ecological importance were recorded in the Assessment Areas at North Point, Sandy Bay, Cyberport, Wah Fu, Aberdeen, Ap Lei Chau and Stonecutters Island. However, as the Country Park / SSSI and most of the natural woodlands were on upland area and far away from the PTW / SCISTW sites and proposed project works, ecological impact on these habitats of conservation importance and the associated community resulted from the Project should be minimal.

 

17.29        Three faunal species of conservation interest, including Black Kite, Common Buzzard and Pallas’s Squirrel, were recorded in the Assessment Areas during the recent visits of the Project. As all the three fauna of conservation interest are not recorded within the project site / works areas boundary, there would be no direct impact resulting from construction works on these species of conservation importance. Hence, adverse impact on these species of conservation importance was not expected.

 

17.30        The key direct ecological impacts of the Project would be the habitat loss on 18.6 ha of developed area and 4.5 ha of wasteland in the existing eight PTWs, SCISTW and proposed work areas at North Point, Wan Chai East, Central, Sai Ying Pun, Sandy Bay, Cyberport, Wah Fu, Aberdeen Ap Lei Chau and Stonecutter Island. These habitats were ranked as very low in ecological value and support no floral and faunal species of conservation importance. The impact of habitat loss was would be very minor in nature.

 

17.31        Other impact of the Project would be the removal (to be transplanted / fell) of 376 trees located within the footprint of the proposed project works. However, as all of the affected trees are common and widespread species of low ecological importance, potential impact to the vegetation was considered low. No protected species or other flora of conservation interest would be affected under this Project. Compensatory planting would be provided in a ratio not less than 1:1 in terms of quality and quantity. To minimize direct loss of individual trees, transplantation would also be conducted.

 

17.32        With the proposed mitigation measures in place, including noise mitigation measures and good site practice, indirect disturbance to adjacent habitats and associated wildlife resulting from the construction noise and human activities during the construction phase of the Project would be mitigated to acceptable and minor level. No adverse indirect impact on those habitat / species of conservation interest adjacent to the Project sites and proposed works areas would be expected under this Project.

 

Marine Ecology

 

17.33        A literature review of previous studies and EIA reports was initially conducted to establish the baseline conditions of the Assessment Area. In areas that were identified to be directly impacted by the project, i.e. Aberdeen PTW, ecological surveys (intertidal and dive surveys) were conducted to gather up to date, detailed information on the baseline condition of the affected site. The assessment of potential impacts was then conducted in accordance with the EIAO TM requirements.

 

Construction Phase

 

17.34        Few marine works are necessary during the upgrade of PTWs however, indirect impacts on water quality may result from site run-off, sewage from workforce, accidental spillage and discharges of wastewater associated with land based construction activities. If standard good site practice and the mitigation measures, proposed in Water Quality Section 6, such as the use of silt/sediment and grease traps, effective site drainage and provision of chemical toilets are implemented properly then no significant adverse impact on water quality would be expected.

 

17.35        Although no marine works are involved during the upgrade of the majority of PTWs, a small area of seawall (approx.50m) would be demolished and reconstructed at the Aberdeen PTW site to complete the construction works. As confirmed by dive surveys, the subject site supported very limited marine life. Only 3 colonies of a common hard coral species (Oulastrea crispata), all in small size (3 to 5cm) and of low coverage were found in the potentially affected areas. All were attached to moveable boulders < 50cm diameter and thus feasible for translocation. Coral translocation and post translocation monitoring is proposed to minimise the adverse impacts on these corals

 

Operational Phase

 

17.36        The water quality impact modeling results in Section 6 indicated that the potential impact zone during operation of the project would be restricted to the Victoria Harbour and Western Buffer WCZs.  No significant impacts on ecological resources outside of this zone are expected.

 

17.37        However, it should be noted that exceedances of Total Inorganic Nitrogen (TIN) and Orthophosphate do occur in Southern and North Western WCZs which are outside the impact areas stated above. These WCZs are not considered to be impacted by the operation of the project because water quality modeling predicts similar levels of these nutrients with and without implementation of the project. Additionally, the ambient nutrient levels of Southern and North Western WCZ already exceed the relevant WQO/WQC suggesting that exceedances of WQO/WQC for these nutrients are likely due to non-HATS sources.

 

17.38        The existing SCISTW outfall location was chosen specifically to be in an area with low value ecological resources.  No significant adverse ecological impacts are anticipated during operation of the Project because:

 

·         Disinfection process will result in improvement of water quality with reduction in E. coli levels in Western Buffer WCZ and western Victoria Harbour WCZ;

·         Only localized and small changes in TRC, CBPs and DO around the existing SCISTW outfall;

·         No unacceptable ecological risk on marine mammal and marine life in relation to acute and chronic effects;

·         Water quality criteria for unionized ammonia is met at the edge of the ZID and this is out of the normal distribution range of dolphins, porpoises and green turtles;

·         Unionized ammonia levels would be improved in the North Western, Western Buffer and Victoria Harbour WCZ;

·         Oxygen depletion is minimal and highly localized around the SCISTW outfall;

·         Improved DO levels in the Victoria Harbour, Eastern Buffer and Junk Bay WCZs;

·         Highly localised salinity and temperature changes would not have adverse impacts on the ecological habitats identified;

·         Increases in the levels of TIN and Orthophosphate predicted are not significant enough to have direct impacts on identified ecological communities;

·         There is no documented data on the specific conditions leading to HABs and they have been documented in polluted and un-polluted water. Increases in nutrient levels during discharge of sewage effluent would be unlikely to trigger HAB events;

·         TIN and Orthophosphate levels have increased in the Assessment Area since the implementation of HATS Stage 1, but no increase in the number of HAB events has been observed;

·         Water quality modelling predicts little difference in levels of TIN and Orthophosphate with or without the implementation of the project. Additionally, with the implementation of HATS Stage 2B, TIN and phosphate discharge will be reduced;

·         Western Buffer WCZ and western Victoria Harbour WCZ, the areas affected by the effluent, generally support low to moderate ecological resources;

 

17.39        Emergency discharge of sewage effluent at PTW and SCISTW may occur during periods of heavy rain when inflow exceeds the capacity of the system or as a result of power/equipment failure. This would result in a rise in the level of E. coli in the receiving water body and thus a subsequent deterioration in water quality which would potentially cause adverse impacts to marine ecological resources. Water quality modelling showed that pollution levels for parameters such as nutrients and DO were not predicted to be adversely affected by emergency discharges. Additionally modelling predicted that increases in the level of suspended sediment resulting from emergency discharges would not exceed the assessment criteria at coral sites. Water quality was also predicted to return to normal condition 1 to 2 days after emergency discharges. Due to the highly transient nature of potential emergency discharges and the ability of marine organisms to naturally resist pathogenic strains of E. coli (Hang et al., 2000) no insurmountable impact on water quality is predicted to result from emergency discharges.

 

17.40        Environmental monitoring and auditing requirements relevant to ecological resources protection are described in detail in the in the standalone EM&A Manual.

 

Fisheries

 

17.41        The existing SCISTW outfall location was chosen in the area where fisheries resources were considered to be of low value.  No significant adverse fisheries impact is anticipated, considering the reasons below:

 

·         Improvement in water quality with reduction in E. coli levels in Western Buffer WCZ and western Victoria Harbour WCZ

·         Only localized and small changes in TRC, CBPs and DO around the existing SCISTW outfall

·         No exceedance of unionized ammonia levels, which can be toxic to fish

·         Oxygen depletion would be minimal and highly localized

·         There is no documented data on the specific conditions leading to HABs and they have been documented in polluted and un-polluted water. Increases in nutrient levels would be unlikely to trigger HAB events

·         TIN and Orthophosphate levels have increased in the Assessment Area since the implementation of HATS Stage 1, but no increase in the number of HAB events has been observed

·         Water quality modeling predicted little difference in levels of TIN and Orthophosphate with or without the implementation of the project

·         Water quality objectives would be met at Ma Wan FCZ

·         Planned temporary bypass of sewage during construction will be carried out during the dry season to avoid adverse impacts on culture fisheries resources

·         Emergency discharges of sewage effluent at SCISTW or PTW seawall bypass due to heavy rainfall or power/equipment failure would only cause marginal exceedance of criteria value for E. coli. However, as the exceedances would only occur for a very short period (a few hours only), non-compliance with the WQO/WQC for E.coli (which is an annual geometric mean value) was not predicted. The emergency discharge would be rare and very short term, thus no insurmountable impact is expected on fisheries resources.

 

17.42        As there would be no significant adverse impacts on fisheries resources from the proposed disinfection or discharge of effluent during normal operation of the project, no fisheries specific mitigation measure would be required. Environmental monitoring and auditing requirements relevant to fisheries protection during emergency discharge of planned bypass of sewage are covered in the water quality assessment, Section 6, ecological risk assessment, Section 8 and the stand alone EM&A Manual.

 

Landscape and Visual Impact

 

17.43        The proposed scheme and associated works are predominated zoned as Other Specified Use (OU), Government, Institution or Community (GIC) or Open Space (O). Details OZPs and zoning of related site is listed in Table 13.2. It is considered to be compatible with the surrounding in principle following the planning intentions for the study areas as set out in the OZPs. There also have PTWs or work area located in the zone of open space and residenctial. Mitigation measures will be applied to avoid the adverse landscape and visual impacts in consideration with the surrounding environment.

 

Residual Landscape Impacts

 

17.44        Tree survey results indicated that approximately 376 trees would be affected by the proposed works at the PTWs, SCISTW and associated works areas.  No potential LCSD Champion Trees or Registered Old and Valuable Trees are found. There are no rare species or endangered specie but common species. All the trees with high amenity value which are unavoidably affected by the works would be transplanted where possible.  Detailed tree preservation, transplanting and felling including compensatory planting proposals shall be submitted to relevant government departments for approval in accordance with ETWB TC no. 3/2006 and ETWB TCW No. 29/2004.  Since trees would be planted within the PTWs/SCISTW and works areas to compensate for the loss of existing trees, and roof greening will be adopted for the provision of more greening to enhance the landscape quality and waterfront character, the overall residual impacts on existing trees are considered as slight with mitigation measures.

 

Residual Visual Impacts

 

17.45        With implementation of mitigation measures during construction, there would still be some moderate adverse visual impact on the VSRs adjacent or close to the Project. Residual impacts on VSRs further away the works area would become slight to insubstantial.

 

17.46        With implementation of mitigation measures during operation, there would be slight adverse impact on VSRs facing the PTW site and associated structures. However, the residual impacts on remaining VSRs would become insubstantial.

 

17.47        Overall, it is considered that the residual landscape and visual impacts of the proposed development are considered as acceptable with mitigation measures during construction and operation phases.

 

Hazard to Life

 

17.48        Hazard to life impact associated with the two Potential Hazardous Installations (PHIs), namely the Hong Kong & China Gas Company’s Gas Holder Depot and the Shell LPG Transit Depot/Bulk Domestic Supply were quantitatively assessed. Mitigation and monitoring measures have been proposed to reduce risk of adverse impact to PHIs.

 

17.49        Potential damages to HKCG Gas Holder and Shell Depot can be avoided with implementation of safety measures and close monitoring procedures during construction phase. Operation of these PHIs would not be disturbed and gas supply would not be disrupted provided that vibration and ground settlement caused by construction works can be controlled within allowable limits. Societal risk for the HKCG Gas Holder and the LPG Compound can be maintained to acceptable level throughout construction and operation phase of the Aberdeen PTW and Ap Lei Chau PTW. Frequency of accidents for the LPG Transit Depot does not increase during construction of Ap Lei Chau PTW. However, installation of gas detection system can bring the risk level further down as an early warning to safeguard construction workers at the project site. Both Aberdeen and Ap Lei Chau projects would not introduce addition risk factor to the nearby PHIs. Besides, operation mode of the upgraded PTWs would be very similar to the existing one. Societal risk would only be increased during construction phase which is mainly due to the increase in population within the two project sites. Recommendations for limiting vibration levels have been set for construction works in vicinity of PHI facilities and a monitoring programme will be set in place by the contractor to ensure that the limits are not exceeded.

 

17.50        Given that there would be no overnight explosives storage expected according to the latest construction programme, the hazard assessment for overnight storage of explosives is considered not applicable in this EIA.

 

17.51        Hazard to life impact associated with the proposed disinfection facilities at SCISTW was quantitatively assessed, with consideration of identified precautionary measures/ operation procedures that minimize the risks associated with the chemicals related operations.  The individual risk and societal risk associated with the chemicals related operations were found to be acceptable in accordance with the risk guidelines stipulated in the Annex 4 of the EIAO TM.  Hence, the hazard to life impact due to the proposed disinfection facilities at SCISTW is considered to be low and acceptable.

 

Cultural Heritage

 

17.52        Based on the desk-based study and field survey findings, none of the heritage resources would be directly impacted by the proposed project. Indirect impacts that have been identified would arise from blasting for tunnel, shafts, effluent conveyance system and disinfection facilities. Recommendations for limiting the peak particle velocity to 25mm/s have been set for historical structures. A monitoring programme will be set in place by the Project Proponent to ensure that the limits are kept within acceptable limits during blasting for tunnel, shafts, effluent conveyance system and disinfection facilities in the vicinity of the buildings/structures.

 

Overall Conclusion

 

17.53        The findings of this EIA Study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation phases of the Project.  Where appropriate, the EIA has identified mitigation measures to ensure compliance with environmental legislation and standards. The feasibility, practicability, programming and effectiveness of the mitigation measures have been assessed and determined.

 

17.54        Overall, the EIA Study for the proposed HATS Stage 2A has predicted that the Project, with the implementation of the proposed mitigation measures for construction and operation phases, would comply with all applicable environmental standards and legislation.  This EIA has also demonstrated the acceptability of the residual impacts from the Project and the protection of the population and environmentally sensitive resources. 

 

17.55        A summary of the key environmental outcomes arising from the EIA study, including the population and environmentally sensitive areas protected, environmentally friendly designs recommended, key environmental problems avoided, compensation areas included and the environmental benefits of environmental protection measures recommended are presented in Table 17.1 below.

 

Table 17.1    Summary of Key Environmental Outcomes / Benefits

 

Area/Issue

Environmental Outcomes / Benefits

Major environmental

benefits of the Project

·    The current design scheme to collect sewage from upgraded PTWs through deep tunnel system for centralised treatment at SCISTW would provide the following major benefits in terms of the pollution loading reduction:

 

-    Prevent another 190 to 500 tonnes of sewage sludge (depending on sewage quantity) from being dumped into the harbour each day

-    Reduce toxic ammonia by 10% on average

-    Reduce total inorganic nitrogen and phosphorus by 5% and 8% respectively

-    Increase dissolved oxygen levels by 5%

 

·    As part of Stage 2A, advanced disinfection facilities by means of chlorination/  dechlorination can reduce pathogen discharge from un-disinfected effluent and enable the closed Tsuen Wan beaches to be re-opened at the earliest opportunity.

 

·    Overall, the project can significantly improve baseline water-quality conditions compared to the scenario of “no HATS Stage 2A”.

 

Environmentally friendly designs recommended

 

Key environmental

problems avoided

 

 

·    Environmental factors have been taken into consideration in the design of SCS, PTWs and SCISTW to avoid key environmental problems.  

 

SCS Alignment Design & Construction

 

·    Deep tunneling instead of open trench excavation for the SCS construction can minimize significant environmental, community and traffic impacts in dense urban areas during construction stage.

 

·    Tunnel alignment to be running offshore can minimise impacts on land-based environmental sensitive receivers.

 

·    Curved alignment design can:-

 

-    Avoid passing through reclaimed lands with sensitive structures/old built-up areas so that heritage resources can be protected from vibration impacts.

 

-    Avoid encroachment on private lots and thereby eliminates interfaces with private properties. This would be resulting in reduction of programming risk and hence duration of environmental impacts to the public.

 

·    Design with minimised tunnel excavated span can reduce waste generation.

 

·    Either drill & blast or mechanical boring methods will be the major tunnel construction method. Recommended measures e.g. control of quantity of explosives or speed of mechanical boring can effectively control vibration, groundborne noise impacts and ground settlement due to groundwater ingress.

 

PTW & SCISTW Design & Construction

 

·    Enclosed sewage treatment units with exhaust air control can minimize odour and noise impacts during operation stage.

 

·    Landscape and aesthetic considerations incorporated to the PTW/SCISTW design can minimise visual impacts and to beautify the landscape of the local environs, especially for the PTWs located along the harbour-front.

 

·    Adjusted/oriented footprints of proposed sewage treatment facilities to reduce conflict with the existing trees.

 

·    Effluent conveyance system at SCI proposed as a deep tunnel can reduce environmental impacts e.g. dust, noise & visual compared to the open trench excavation method.

 

·    Non-percussive bored pile techniques proposed for PTW/SCISTW construction can minimise noise and vibration impacts.

 

·    Construction works or packages for PTWs/SCISTW in phases can minimize magnitude of the construction stage impacts e.g. noise and dust.

  

Air Quality

Environmental benefits of environmental protection measures recommended

 

·    ASRs identified near the construction sites are protected through implementation of dust suppression measures i.e. regular watering during construction phase.

 

·    ASRs identified near the PTWs and SCISTW are protected from the following proposed odour control measures during operation phase:

 

-          Properly enclosed or covered the identified odour sources

-          Foul air drawn through deodorization units and discharged after treatment by biofilter and/or activated carbon

-          Good house keeping (regular cleansing schedule) to minimize odour generation

 

   Population and environmental sensitive receivers protected

 

·    Existing ASRs & planned developments, including residential, commercial and recreational areas within 500m from SCISTW and PTWs.

 

 

Airborne Noise

Environmental benefits of environmental protection measures recommended

 

·    NSRs are protected with implementation of quiet PME, movable barriers, acoustic mats as well as good site practices during construction stage. The predicted mitigated noise levels complied with the noise standards at all NSRs except N1 (Madam Chan Wai Chow Memorial School) in North Point.

 

·    At N1, the proposed mitigation measures already reduced the noise level from 78 dB(A) to 70 dB(A). It only exceeded the noise limit 65dB(A) during exams period. Particularly noisy construction activities were recommended to be undertaken during summer vacation period to further reduce the construction noise impact. 

 

·    Acoustic louvers were proposed for air supply fans/extraction fans of transfer pumping stations and ventilation fans of deodourization unit at Sandy Bay PTW, Cyberport PTW and Wah Fu PTW. Besides, it is recommended that the maximum allowable sound power level (SWL) of each new transformer at Sandy Bay PTW shall be limited to 89 dB(A) during the detailed design stage. With proper designs of PTWs, SCISTW and disinfection facilities, no residual operation noise impact is anticipated.

 

Population and environmental sensitive receivers protected

 

·    Existing and planned NSRs within 300m of the project boundary, including residential premises, schools, homes for the aged and institutional uses.

 

Water Quality

Environmental benefits of environmental protection measures recommended

 

·    Control construction site runoff and various construction activities as outlined in ProPECC PN 1/94 Construction Site Drainage would reduce the water quality impact to an acceptable level.

 

·    The Project would bring water quality improvements at the identified water sensitive receivers including the beaches, the fish culture zones (FCZ) and the secondary contact recreation subzones as well as the seawater intakes in western Victoria Harbour. 

 

·    Operation of HATS 2A would result in water quality improvements at the identified water sensitive receivers, including the beaches, the fish culture zones (FCZ) and the secondary contact recreation subzones as well as the seawater intakes in western Victoria Harbour as the pollution levels for all the concerned parameters including all the concentration of nutrients in the receiving marine water bodies would be reduced.

 

·    Provision of dual power supply and standby facilities proposed at the SCISTW and PTWs can minimize the potential water quality impacts upon the water sensitive receivers due to emergency discharge.

 

·    In case of total power outage of the dechlorination plant, the uninterruptible power supply (UPS) system to be provided would switch the power supply of the sodium bisulphite dosing pump to a backup battery almost instantaneously, allowing continuous dosage of sodium bisulphite for at least half an hour so that sufficient time can be provided for shutting down the chlorination plant to avoid the possibility of discharge of chlorinated effluent. 

 

·    With proper implementation of these mitigation measures, the occurrence of discharge of non-dechlorinated effluent would be very remote.  In case that the dechlorination process fails, the chlorination process could be practically stopped within 30 minutes to avoid discharge of total residual chlorine into the marine water. 

 

Population and environmental sensitive receivers protected

 

·    All the water sensitive receivers identified in the Western Buffer, North Western, Victoria Harbour and Southern WCZ.

 

Human Health Risk and Ecological Risk

Environmental benefits of environmental protection measures recommended

 

·    Chlorination by-products present in the HATS effluent would not induce unacceptable human health risk and ecological risk.

 

·    A monitoring programme would be implemented to protect human health and ecological resources from increased TRC and CBP concentrations in seawater.

 

 

Population and environmental sensitive receivers protected

 

·    Population and ecological resources associated with the exposure to toxic substance from effluent discharges of the Project.

 

Waste Management Implications

Environmental benefits of environmental protection measures recommended

 

·    On-site re-use of excavated materials, e.g. backfilling of trenches for SCISTW expansion, would reduce waste generation.  Grade I/II granite generated form SCS construction delivered to Lam Tei Quarry would be crushed as aggregates, other surplus inert C&D material delivered to public filling reception facilities can be reused for other projects.

 

·    Implementation of the proposed waste control and mitigation measures would avoid the potential water quality, dust, odour, and noise impacts associated with handling, transportation and disposal of the identified wastes arising from the Project.

 

Population and environmental sensitive receivers protected

 

·    Water quality, air, and noise sensitive receivers at or near the Project site, the waste transportation routes and the waste disposal site.

 

Terrestrial Ecology

Environmental benefits of environmental protection measures recommended

 

·    All construction works would be confined to very low-valued habitats (developed area and wasteland) and potential direct impact to nearby habitats of ecological importance would be avoided.

 

·    Noise and dust control measures would minimise indirect impact on adjacent terrestrial habitats and associated wildlife during the construction phase.

 

Compensation areas included

 

·    Direct loss of ~376 individual trees would be mitigated by compensatory planting of similar native species at not less than 1:1 ratio in terms of quality and quantity

 

Population and environmental sensitive receivers protected

 

·    Terrestrial ecological resources near the Project site

 

Marine Ecology

Environmental benefits of environmental protection measures recommended

 

·    All the marine habitats and associated flora and fauna that would be directly impacted due to this Project are considered to have low ecological values.

 

·    Coral colonies at Aberdeen PTW (only 3 colonies found, all small size, low coverage and attached on moveable boulder) that would be directly affected would be translocated to nearby suitable habitats. Coral translocation and post-translocation monitoring will be carried out to further protect the corals. This would mitigate the direct impact imposed on these corals as a result of the project.

 

·    Water quality control measures would minimise potential indirect impacts on marine habitats and associated life throughout the study area that may result from a deterioration of water quality during construction.

 

Compensation areas included

 

·    Intertidal habitat (seawalls) directly affected by construction works at Aberdeen PTW would be reconstructed.

 

Population and environmental sensitive receivers protected

 

·    Ecological resources at and near the Project site.

 

 

Fisheries

Environmental benefits of environmental protection measures recommended

 

·    Fisheries resources would be protected by implementation of water quality control measures

 

Population and environmental sensitive receivers protected

 

·    Fisheries resources at and near the Project site.

 

Landscape and Visual

Environmental benefits of environmental protection measures recommended

 

·    Landscape and visual sensitive receivers would be protected by implementation of the measures, such as tree transplantation, compensatory tree planting, control of light-time lighting and erection of decorative screen hoarding compatible with the surrounding setting during construction phase.

 

·    Mitigation measures such as aesthetic design of PTW / SCISTW and associated structures; shrub and climbing plants to soften proposed structures; buffer tree and shrub planting to screen proposed associated structures etc. would lessen the landscape & visual impacts to the sensitive receivers during operation stage.

 

Compensation areas included

 

·    Compensatory planting for loss of ~376 trees would be equal or not less than 1:1 ratio within the Project Boundary or proximity areas.

 

Population and environmental sensitive receivers protected

 

·    All VSRs identified within the Zone of Visual Influence from the Project.

 

Cultural Heritage

Environmental benefits of environmental protection measures recommended

 

·    Control of vibration limit through a monitoring programme to protect historical structures against groundbourne vibration generated from construction activities e.g. tunnel blasting.

 

Population and environmental sensitive receivers protected

 

·    Heritage resources identified close to the Project site which are sensitive to vibration damage.

 

Hazard to Life

  (i) Assessment for Potential Hazardous Installations (PHIs)

 

Environmental benefits of environmental protection measures recommended

 

·    With implementation of safety measures and close monitoring procedures, vibration and ground settlement caused by construction works can be controlled within allowable limits. Operation of HKCG Gas Holder at Aberdeen and Shell Depot at Ap Lei Chau would not be disturbed and gas supply would not be disrupted. Besides, surrounding population would not be subject to level of risk more than the existing one. 

 

Population and environmental sensitive receivers protected

 

·    Construction workers at the Project work sites and population in vicinity of HKCG Gas Holder and Shell Depot. 

 

  (ii) Assessment for Disinfection Facilities

 

Environmental benefits of environmental protection measures recommended

 

·    Implementation of the proposed precautionary measures including special arrangement on chemicals-related operations to avoid chemical unloading errors and mitigation measures during construction phase would minimize the risks to acceptable level.

 

Population and environmental sensitive receivers protected

·    Population near the SCISTW.