4.1 This Section presents an assessment of the potential airborne noise impacts associated with the construction and operation of the Project. The noise impact assessment was conducted in accordance with the requirements of Annex 5 and Annex 13 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) as well as the requirements set out under Clause 3.4.2 of the EIA Study Brief. Ground-borne noise impact associated with the operation of powered mechanical equipment, in particular, tunnel boring machine, was also assessed, and the findings are presented in Section 5 of this EIA Report.
4.2
Noise
impacts were assessed in accordance with the criteria and methodology given in
the Technical
4.3
The
NCO provides the statutory framework for noise control. This defines statutory
limits applicable to equipment used during the construction and operation
phases of the proposed works in the study area. The NCO invokes four Technical
·
Technical
·
Technical
·
Technical
·
Technical
4.4
The
NCO and the accompanying Technical
4.5
With
regard to the assessments of the construction noise impact during restricted
hours and operational noise impact, the NCO designates acceptable noise levels
for Noise Sensitive Receivers (NSRs) on the basis of an Area Sensitivity Rating
(ASR), based on the characteristics of the area within which they are located
such as rural, village, low-density residential, or urban (see Table 4.1). Within these areas, the
presence of "influencing factors" (such as the presence of industrial
activities or major roads) can further affect the ASR and hence the acceptable
noise level.
Table 4.1 Area Sensitivity Ratings (ASRs)
Type of Area Containing
NSR |
Degree to which NSR is
affected by Influencing Factor |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
Rural Area |
A |
B |
B |
Urban Area |
B |
C |
C |
Low density residential
area consisting of low-rise or isolated high-rise developments |
A |
B |
C |
Area other than those
above |
B |
B |
C |
4.6
The
NCO provides the statutory framework for noise control of construction work,
other than percussive piling, using powered mechanical equipment (PME) between
the hours of 1900 and 0700 hours or at any time on Sundays and general holiday
(that is, restricted hours). Noise
control on construction activities taking place at other times is subject to
the Criteria for Evaluating Noise Impact stated in Table 1B of Annex 5 in the
EIAO-TM. The noise limit is Leq
(30 minutes) 75 dB(A) at the façades of dwellings and Leq (30
minutes) 70 dB(A) at the façade of schools (Leq (30
minutes) 65 dB(A) during examinations).
4.7
Between
1900 and 0700 hours and all day on Sundays and public holidays, activities
involving the use of PME for the purpose of carrying out construction work is
prohibited unless a construction noise permit (CNP) has been obtained. A CNP may be granted provided that the
Acceptable Noise Level (ANL) for the NSRs can be complied with. ANLs are assigned depending upon
the area sensitive rating (ASR).
The corresponding basic noise levels (BNLs) for evening and night time
periods are given in Table 4.2.
Table 4.2 Construction Noise Criteria for Activity other than Percussive Piling
Time Period |
Basic Noise Level (BNLs) |
||
ASR A |
ASR B |
ASR C |
|
Evening
(1900 to 2300 hours) (1) |
60 |
65 |
70 |
Night
(2300 to 0700 hours) |
45 |
50 |
55 |
Note: (1) Includes Sundays and Public
Holidays during daytime and evening
4.8
For
the purpose of assessing the feasibility of carrying out construction works during
restricted hours, if any, the ASRs for noise sensitive receivers in the Study
Area are assumed (see Table 4.3)
depending on the type of area within which the NSR is located and the degree of
the effect on the NSR of influencing factors.
Table 4.3 Area Sensitivity Rating (ASR) for NSRs in the Close Vicinity of Project Sites
Area |
ASR |
Rationales for Assigned ASR |
North Point PTW |
B |
Urban area. Not
affected by Influencing Factors (IFs). |
Wan Chai East PTW |
C |
Urban area. Directly affected
by the major road (i.e. |
|
C |
Urban area. Directly
affected by the major road (i.e. |
Sai Ying Pun |
C |
Urban area. Directly
affected by the major road (i.e. |
|
A |
Low density residential
area consisting of low-rise or isolated high-rise developments. Not affected
by IFs. |
Cyberport PTW |
B |
Area other than rural area,
low density residential area and urban area. Not affected by IFs. |
Wah Fu PTW |
B |
Area other than rural
area, low density residential area and urban area. Not affected by IFs. |
|
B |
Area other than rural area,
low density residential area and urban area. Not affected by IFs. |
Ap Lei Chau PTW |
B |
Area other than rural
area, low density residential area and urban area. Not affected by IFs. |
Stage 2A Disinfection
Facilities |
C |
Area other than rural area,
low density residential area and urban area. Directly affected by the major
road (i.e. |
|
C |
Area other than rural
area, low density residential area and urban area. Directly affected by
industrial operations (e.g. shipyards, dockyard, refuse transfer station, bus
depot, etc.). |
Note: PTW = Preliminary Treatment
Works
4.9
The Area Sensitivity Ratings
assumed in this EIA Report are for indicative assessment only. Despite any
description or assessment made in this EIA Report on construction noise
aspects, there is no guarantee that a Construction Noise Permit (CNP) will be
issued for the project construction. The Noise Control Authority will consider
a well-justified CNP application, once filed, for construction works within
restricted hours as guided by the relevant Technical Memoranda issued under the
Noise Control Ordinance. The Noise Control Authority will take into account
contemporary conditions/ situations of adjoining land uses and any previous
complaints against construction activities at the site before making his
decision in granting a CNP. Nothing in this EIA Report shall bind the Noise
Control Authority in making his decision. If a CNP is to be issued, the Noise
Control Authority shall include in it any Condition he thinks fit. Failure to
comply with any such conditions will lead to cancellation of the CNP and
prosecution action under the NCO.
4.10
Percussive
piling is prohibited between 1900 and 0700 hours on any weekday not being a
general holiday and at any time on Sunday or general holiday. A CNP is required for the carrying out
of percussive piling between 0700 and 1900 hours on any day not being a general
holiday. PP-TM sets out the
requirements for working and determination of the permitted hours of
operations. ANLs for percussive
piling for different types of NSRs are shown in Table 4.4.
Table 4.4 Acceptable Noise Levels for Percussive Piling
NSR Window Type or Means of Ventilation |
ANL, dB(A) |
NSR
(or part of NSR) with no windows or other opening |
100 |
NSR
with central air conditioning system |
90 |
NSR
with windows or other openings but without central air conditioning system |
85 |
Note: 10
dB(A) shall be subtracted from the ANLs shown above for NSRs which are
hospitals, medical clinics, educational institutes, courts of law or other NSRs
which are considered by the Authority to be particularly sensitive to noise.
4.11
Under
the TM on Noise from Construction Work in Designated Areas, the use of five
types of Specified Powered Mechanical Equipment (SPME) and three types of
Prescribed Construction Work (PCW) within a designated area during restricted
hours would require a valid CNP.
The SPME includes hand-held breaker, bulldozer, concrete lorry mixer,
dump truck and hand-held vibratory poker.
The PCW are:
erecting or dismantling of formwork
or scaffolding;
loading, unloading or handling of
rubble, wooden boards, steel bars, wood or scaffolding material;
hammering.
4.12 In general, it should not be presumed that a CNP would be granted for carrying out PCW within a designated area during the restricted hours. The CNP may be granted for the execution of construction works during restricted hours involving the use of PME and / or SPME if the relevant Acceptable Noise Levels and criteria stipulated in the GW-TM and DA-TM can be met.
4.13
Fixed
noise sources associated with the Project would be controlled by the NCO and
IND-TM. The Acceptable Noise Levels (ANL) is a function of the type of area
within which the NSRs are located, and the degree of the effect on the NSRs of
influencing factors such as major roads and industrial areas. According to the
IND-TM, the ANLs for different Area Sensitivity Ratings (ASRs) are given in Table 4.5.
Table 4.5 Acceptable Noise Levels for Fixed Noise Sources
Time Period |
Acceptable Noise Level (ANLs) |
||
ASR A |
ASR B |
ASR C |
|
Daytime and Evening (0700 to 2300 hours) |
60 |
65 |
70 |
Night (2300
to 0700 hours) |
50 |
55 |
60 |
4.14 In any event, the Area Sensitivity Rating assumed in the EIA Report is for indicative assessment only. It should be noted that the fixed noise sources are controlled under section 13 of the NCO. At the time of investigation, the Noise Control Authority shall determine noise impact from concerned fixed noise sources on the basis of prevailing legislation and practices being in force, and taking account of contemporary conditions/situations of adjoining land uses. Nothing in the EIA Report shall bind the Noise Control Authority in the context of law enforcement against all the fixed noise sources being assessed.
4.15 While the noise impact arising from newly proposed fixed plant would be assessed against the planning criterion stipulated in EIAO-TM, the cumulative noise impact arising from both new and existing fixed plant would be assessed against ANL under NCO. This approach was adopted in an EIA Study for Tai Po Sewage Treatment Works Stage V which was approved by EPD under EIAO in October 2004.
Noise Criteria for Newly
Proposed Equipment
4.16 Taking into account the type of area within which the NSR is located and the degree of the effect on the NSR of influencing factors, the ASRs for the NSRs in the vicinity of the proposed Project sites have been assumed as shown in Table 4.3 above. The EIAO-TM recommends that the level of the intruding noise at the façade of the nearest sensitive use should be at least 5 dB(A) below the appropriate ANL or, in the case of background noise being 5 dB(A) lower than the ANL, the predicted noise level arising from the operation of the proposed Project at the façade of the nearest sensitive use should not exceed the background noise level. In this regard, on-site background noise measurements have been carried out to determine the recommended noise criteria for each Project site.
Noise
Criteria for Cumulative Noise Impact
4.17 Cumulative noise impacts arising from all items of equipment including new equipment and existing equipment would be calculated and compared against relevant ANL criteria as shown in Table 4.5.
4.18
Appendix 4.1 has summarized the prevailing noise levels at representative
measurement locations. The assessment criteria for newly proposed fixed noise
sources and cumulative impact, as adopted in this EIA Study, have also been
presented.
4.19
A
noise survey was undertaken in October and November 2006 to determine the
background noise levels. Prevailing background noise levels were obtained
through on-site noise measurements at thirteen representative noise measurement
locations near the PTWs/SCISTW/Stage 2A Disinfection Facilities. All the noise
measurements were conducted in accordance with IND-TM. A summary of prevailing
noise levels at representative measurement locations is shown in Appendix 4.1. A Background Noise Survey
Report is presented in Appendix 4.2.
4.20 The Study Area for noise impact assessment is defined by a distance of 300m from the boundary of the Project site. In accordance with Annex 13 of the EIAO-TM, the representative NSRs within the Study Area, including residential premises, schools, home for the aged and institutional uses, have been identified and summarized in Table 4.6 for construction noise and fixed plant noise assessments. Only the first layer of NSRs has been identified for assessment because it would provide acoustic shielding to those receivers at further distance behind. Locations of these NSRs are depicted in Figures 4.1 to 4.9. The noise assessment points have been agreed with Environmental Protection Department.
4.21
A
number of relevant Outline Zoning Plans (OZPs) have been studied. These OZPs
include: S/H5/24, S/H25/1, S/H3/21, S/H10/15, S/H15/24, S/H8/19 and S/SC/8. Except
the planned FSD Diving Rescue and Diving Training Centre at
4.22
With reference to an EIA Study for the Provision of Disinfection Facilities at
4.23
The
Project is tentatively scheduled to be commenced in February 2009 and to be
completed in December 2013.
According to the construction programme, there are three major
construction tasks. Some individual
tasks have different stages. Table 4.7
summarises the different tasks and phasing. General above-ground construction
tasks are planned to be carried out during unrestricted hours.
Table 4.6 Noise Sensitive Receivers
Area |
NSR ID |
Description |
Use |
NSR for Assessment |
|
Construction |
Fixed Noise |
||||
North
Point PTW |
N1 |
|
Educational |
Ö |
Ö |
N2 |
Block C,
Healthy Gardens |
Residential |
Ö |
Ö |
|
N3 |
Block A,
Elegance House |
Residential |
Ö |
Ö |
|
N4 |
|
Residential |
Ö |
Ö |
|
N5 |
Kar Fu Building |
Residential |
Ö |
Ö |
|
Wan Chai
East PTW |
N6 |
|
Residential |
Ö |
Ö |
N7 |
Elizabeth
House |
Residential |
Ö |
Ö |
|
|
N8 |
Block A,
|
Residential |
Ö |
Ö |
N9 |
Block 1,
|
Residential |
Ö |
Ö |
|
|
N10 |
|
Residential |
Ö |
Ö |
N11 |
|
Residential |
Ö |
Ö |
|
|
N12 |
|
Residential |
Ö |
Ö |
N13 |
Chuk Lam
Ming Tong |
Homes for the Aged |
Ö |
Ö |
|
N14 |
Block C-D, Scenic Villa |
Residential |
Ö |
Ö |
|
N15 |
Block 2,
La Mer |
Residential |
Ö |
Ö |
|
N15a |
SAGE
Madam Ho Sin Hang Home for the Elderly |
Home for the Aged |
Ö |
Ö |
|
N15b |
Block B,
The Duchess of Kent Children’s Hospital at |
Hospital |
Ö |
Ö |
|
Cyberport
PTW |
N16 |
Point
Breeze |
Residential |
Ö |
Ö |
N17 |
Aegean
Terrace |
Residential |
Ö |
Ö |
|
N18 |
Block
18, |
Residential |
Ö |
Ö |
|
Wa Fu PTW |
N19 |
|
Educational |
Ö |
Ö |
N20 |
Wah Ming
House, Wah Fu Estate |
Residential |
Ö |
Ö |
|
|
N21 |
Wah Lai
House, Wah Kwai Estate |
Residential |
Ö |
Ö |
N22 |
Waterfront
South |
Residential |
Ö |
|
|
N23 |
Po |
Educational |
Ö |
|
|
Ap Lei
Chau PTW |
N24 |
|
Residential |
Ö |
Ö |
Stage 2A
Disinfection Facilities SCISTW |
N25 |
Naval
Base Barrack |
Residential |
Ö |
Ö |
N26 |
Naval
Base Barrack |
Residential |
Ö |
Ö |
|
N27 |
Planned
FSD Diving Rescue and Diving Training Centre |
Institutional |
Ö |
Ö |
Table 4.7 Summary of Construction Tasks and Stages
Item |
Tasks and Stages |
Construction Period |
Main Construction
Elements |
1. North Point PTW |
|||
Barging Facilities |
n/a |
February 2009 – July
2009 |
Construction of ramp and
tipping hall |
Barging Facilities |
n/a |
August 2009 – September
2013 |
Barging activities |
Drop Shaft |
Phase I, II, III # |
February 2009 – December
2013 |
Construction of upper
and lower shaft; PTW upgrading; Drop shaft finishing works |
Production Shaft |
n/a |
February 2009 –
September 2013 |
Construction of upper / lower
shaft; Tunnel construction |
2. Wan Chai East PTW |
|||
Drop/Riser Shaft |
n/a |
February 2009 –
September 2013 |
Construction of upper
and lower shaft; Drop/riser shaft finishing works |
Production Shaft |
n/a |
February 2009 –
September 2013 |
Construction of upper
and lower shaft; Tunnel construction |
PTW Upgrading |
n/a |
January 2011 – December
2013 |
PTW upgrading works |
3. |
|||
Barging Facilities |
n/a |
February 2009 – July
2009 June 2009 – November
2009 |
Construction of ramps
and tipping halls for two sets of barging facilities |
Barging Facilities |
n/a |
August 2009 – February
2013 December 2009 – February
2013 |
Barging activities at
two barging facilities |
Production Shaft / Drop
Shaft |
n/a |
February 2009 –
September 2013 |
Construction of upper
and lower shaft; Tunnel construction; Conversion to drop shaft |
Production Shaft / Riser
Shaft |
n/a |
June 2009 – September
2013 |
Construction of upper
and lower shaft; Tunnel construction; Conversion to riser shaft |
4. |
|||
Drop Shaft |
Phase I, II, III # |
February 2009 – December
2013 |
Construction of upper
and lower shaft; PTW upgrading; Drop shaft finishing works |
5. Sandy Bay PTW |
|||
Production Shaft /
Drop/Riser Shaft |
n/a |
June 2009 – September
2013 |
Construction of upper
and lower shaft; Tunnel construction; Conversion to drop/riser shaft |
Production Shaft |
n/a |
June 2009 – September
2013 |
Construction of upper /
lower shaft; Tunnel construction |
PTW Upgrading |
n/a |
September 2010 –
December 2013 |
PTW upgrading works |
6. Cyberport PTW |
|||
Production Shaft /
Drop/Riser Shaft |
n/a |
June 2009 – September
2013 |
Construction of upper and
lower shaft; Tunnel construction; Conversion to drop/riser shaft |
PTW Upgrading |
n/a |
March 2011 – December
2013 |
PTW upgrading works |
7. Wan Fu PTW |
|||
Drop Shaft |
Phase I, II, III #
|
June 2009 – December
2013 |
Construction of upper and
lower shaft; PTW upgrading; Drop shaft finishing works |
8. |
|||
Drop Shaft |
Phase I, II, III # |
June 2009 – December
2013 |
Construction of upper
and lower shaft; PTW upgrading; Drop shaft finishing works |
Production Shaft |
n/a |
June 2009 – September
2013 |
Construction of upper /
lower shaft; Tunnel construction |
Tunnel Q |
n/a |
June 2009 – September
2013 |
Tunnel construction
(Horizontal Directional Drilling) |
9. Ap Lei Chau PTW |
|||
Drop Shaft |
n/a |
June 2009 – September
2013 |
Construction of upper
and lower shaft; Drop shaft finishing works |
PTW Upgrading |
n/a |
September 2010 –
December 2013 |
PTW upgrading works |
10. Stage 2A
Disinfection Facilities |
|||
New Chlorine Contact
Tank |
n/a |
February 2011 – March
2013 |
Excavation / Foundation
/ Civil / E&M Works |
New Effluent Culvert |
n/a |
November 2011 – January
2013 |
Excavation / Civil Works |
Modification of Flow
Distribution Chamber, Chamber 15 and Construction of Chamber |
n/a |
November 2011 – April
2013 |
Excavation / Civil Works |
11. SCISTW |
|||
Riser Shaft |
n/a |
February 2009 –
September 2013 |
Construction of upper
and lower shaft; Remaining civil works |
Production Shaft |
n/a |
February 2009 –
September 2013 |
Construction of upper /
lower shaft; Tunnel construction |
SCISTW Upgrading |
n/a |
September 2010 –
February 2014 |
Construction of main
pumping station, CEPT tanks, sludge treatment facilities, effluent tunnel,
odour control facility and miscellaneous works |
Note: # Phase I – Construction of upper
shaft and lower shaft
Phase II – PTW upgrading
Phase III – both PTW upgrading and drop
shaft finishing works
4.24
The
construction noise assessment has been carried out on a monthly basis from the
commencement of the Project. The construction tasks of the Project taking place
concurrently within 300m of a given NSR are considered to contribute to the
cumulative impact at that NSR. Noise sources from the areas greater than this
distance have been excluded from the assessment.
4.25
In
accordance with the EIAO-TM, the methodology outlined in the GW-TM has been used
for the construction noise assessment. The general approach is summarized
below:
·
Locate the NSRs which would most likely be affected by noise
from the construction work
·
Determine the items of Powered Mechanical Equipment (PME)
for each discrete construction activity, based on available information or
agreed plant inventories
·
Assign sound power levels (SWLs) to the proposed PME
according to the GW-TM or other sources
·
Calculate distance attenuation and screening effects to NSRs
from notional noise source
·
Predict construction noise levels at NSRs in the absence of
any mitigation measures
·
Include a +3 dB(A) façade correction to the predicted noise
levels in order to account for the façade effect at each NSR.
4.26
Sound
Power Levels (SWLs) of the equipment were taken from Table 3 of the GW-TM. Where no SWL was supplied in the GW-TM,
reference was made to BS 5228, previous similar studies or from measurements
taken at other sites in
4.27
It
was assumed that all PME items required for a particular construction activity
would be located at the notional or probable source position where such
activities are to be performed for PTWs & SCISTW upgrading works. For shaft
construction activities including drop/riser shaft, production shaft and
junction shaft, the exact locations would be considered instead of the notional
source point since some of the shafts are located at the edge of the site
boundary. The assessment was based on the cumulative SWLs of PME likely to be
used at each location.
4.28
To
predict the noise level, PME was divided into groups required for each discrete
construction task in Phase I works.
The objective was to identify the worst case scenario representing those
items of PME that would be in use concurrently at any given time.
4.29
Taking into account the works
sequence, PME grouping would be implemented for excavation works in PTW
upgrading works and drop shaft finishing works. Either Group 1 or Group 2 PME
for excavation works and drop shaft finishing works would be operated at any
one time under the construction schedule. Being the worst case scenario, the
construction activities with highest SWL for PTW upgrading works and drop shaft
finishing works were adopted for assessment throughout the whole corresponding
construction periods.
4.30
In
addition to drop shaft finishing work, the following construction tasks of PTW
upgrading works at North Point, Central, Aberdeen and Wah Fu PTWs, being the
worst case scenario with the highest SWL, have been adopted for cumulative
noise assessment in Phase III works.
North Point PTW –
excavation work for seawater pumping station
Wah Fu PTW – landscape
work and roadwork
4.31
In
view of the limited site area of Wah Fu PTW, it is anticipated that less
numbers of PMEs would be employed for Phase II construction work.
4.32
Upon
commissioning of HATS Stage 2A, demolition of the existing CEPT complex at
Cyberport PTW has been tentatively scheduled to be commenced in May 2014 for 6
months. The noise impact arising from such demolition work has also been
included in the assessment.
4.33
Based
on the latest design information, barging facilities would not be required for
the Project. The barging activities
near North Point and
4.34
The
noise levels at NSRs were then predicted by adding up the SWLs of all
concurrent construction tasks, taking into account the distance attenuation. A
positive 3 dB(A) façade correction was added to the predicted noise levels in
order to account for the facade effect at each NSR. A 10 dB(A) reduction was applied to the
noise levels at NSR N27
(i.e. planned FSD Diving Rescue and Diving Training Centre) due to the
screening of line of sight by the structure of FSD Diving Training Centre
itself.
4.35
The
Project is scheduled to be commenced in February 2009 and to be completed in
December 2013. All concurrent projects, which may have cumulative environmental
impacts during its construction period, have been identified. Table 4.8 summarises the concurrent
projects that would have cumulative noise impacts during the construction phase
of the Project.
Table 4.8 Concurrent Projects for Construction Noise Assessment
Area |
Projects |
Remarks |
North
Point PTW |
N/A |
N/A |
Wan
Chai East PTW |
-
Wan Chai Development Phase II (WDII) and - Shatin to Central Link - MTRC |
-
The construction progamme for WDII and CWB & IECL is from 2009 to 2016.
It would interface with the Project. The predicted noise impacts arising from
WDII and CWB & IECL are extracted from WDII draft EIA report. -
No available information -
Alignment selection still under consideration (Information is not available) |
|
-
-
Reprovisioning of Central District Headquarters and Central Divisional Police
Station at |
-
No interface with -
The construction activities would be internal fitting-out works during the
overlap period. Therefore, cumulative construction noise impact would be
insignificant. |
|
-
-
Laying of -
|
-
No interface with Fung Mat Road Site (the alignment and worksite are outside
our study area). -
Trench dredging, pipe laying, backfilling and seawall reinstatement would
interface with the Project. The predicted noise impacts arising from these
works are extracted from approved EIA Report (Register No.: AEIAR-109/2007). -
Construction work is scheduled to be commenced in March 2008 and completed in
April 2011. It would interface with the Project. Typical SWL of the
construction activities would be adopted to predict cumulative noise impact. |
|
N/A |
N/A |
Cyberport
PTW |
-
MTRC -
Drainage Improvement in Northern |
-
Alignment selection still under consideration (Information is not available). -
TBM supporting activities and finalized stage works for western portal of
drainage tunnel would interface with the Project. The predicted noise impacts
arising from these works are extracted from approved EIA Report (Register
No.: AEIAR-099/2006) |
Wah
Fu PTW |
-
MTRC |
-
Alignment selection still under consideration (Information is not available). |
|
-
MTRC -
Route 4 (formerly known as Route 7) |
-
Alignment selection still under consideration (Information is not available). -
No programme (Information is not available). |
Ap
Lei Chau PTW |
N/A |
N/A |
SCISTW
and Disinfection Facilities |
-
Route 8 Ngong Shuen Chau Viaduct |
-
Based on the latest information available (updated as at 31 August 2007) on
the contract web site of Highways Department, Route 8 Ngong Shuen Chau
Viaduct has bee scheduled to be completed in early 2008. There would be no
interface with the Project. |
4.36
Based
on the currently available information, the noise impact arising from dredging
works at temporary public cargo working area under WDII, CWB & IECL project
was considered in cumulative noise assessment for NSRs N6 and N7 near Wan Chai
East PTW throughout the overlapping period.
4.37
For
4.38
Besides,
with reference to an approved EIA Reports for Hong Kong West Drainage Tunnel
and Laying of Western
Cross Harbour Main and Associated Land Mains from
Hong Kong West Drainage Tunnel
(Western Portal)
TBM Supporting
Activities (June 2008 – June 2011)
Finalized Stage -
General Works, Concreting, Marine Transport (April 2011 – November 2011)
Laying of
Trench Dredging (February
2009 – August 2009)
Pipe laying (September
2009 – November 2009)
Backfilling (December
2009 – February 2010)
Seawall Reinstatement
(February 2010 – March 2010)
4.39
The
predicted noise impacts arising from the above-mentioned concurrent projects
are extracted from the relevant EIA Reports. Construction
tasks for the Project and other concurrent projects, within 300m of a given NSR
at the same period, are considered to contribute to the cumulative impact at
that NSR. Noise sources from the areas greater than this distance will be
excluded from the assessment.
4.40
For the assessment of noise
from fixed plant, the noise level at NSR was predicted using the standard
acoustic principle:
Predicted Noise Level = Sound Power Level
of Equipment - Distance Attenuation - Enclosure Reduction (if any) - Screening
Reduction (if any) + Facade Correction
Where Distance
Attenuation = 20 log D + 8 [where D
is the distance in meters]
Façade Correction = 3 dB(A)
4.41
Specifications and noise data
for the existing noise sources within the PTWs is not available at the time of
carrying out this EIA. Based on information provided by the Designer, no
existing equipment at Wah Fu PTW and Ap Lei Chau PTW will be retained after PTW
upgrading works. In order to assess the cumulative fixed noise impact (i.e.
existing equipment + new equipment) on the nearby representative NSRs, on-site
noise measurements were carried out at other six PTWs for those equipment to be
retained after PTW upgrading works. As advised by DSD, the period with most of
the pumps in operation would be
SWL = SPL + Distance Attenuation – Façade Correction (if façade measurement was undertaken)
4.42
With
reference to the EIA Study for the
Provision of Disinfection Facilities at
4.43 The tentative plant inventories and the corresponding SWLs have been presented in Appendix 4.5. As confirmed by the Designer, the plant inventory used for prediction of operation noise impact is practical and realistic.
4.44 Noise impact was assessed on the basis of the following three conservative assumptions:
·
All items of operational plant required for operation of the
proposed facilities would be located at the probable source positions.
·
A +3 dB(A) façade correction was added to the predicted
noise levels to account for the façade effect at each NSR.
·
Noise impacts at the nearest façades of the NSRs to the
source positions were assessed.
4.45 Major potential noise impacts arising from the Project would be:
·
Construction noise
·
Operation noise
4.46
The
potential source of noise impact during the construction phase of the Project
would be the use of PME for various construction activities. The construction
noise impact arising from the proposed Project is discussed in Section 4.52.
The major scopes of
this Project include construction of drop/riser shaft, production shaft, tunnel
construction and upgrading works of PTWs/SCISTW.
4.47
The
construction works of
4.48
A
sewage conveyance system (or tunnels) would be constructed by either Drill and Blast (D&B) or Tunnel
Boring Machine (TBM). These options would be determined by the Engineer
and specified in the tender document at the later stage. Should D&B method be adopted, all the
detonation will be conducted underground within the tunnel. As blasting is
under the control of the Dangerous Goods Ordinance, the contractor shall obtain
a valid blasting permit from the Mines Division of CEDD before carrying out the
blasting. The contractor shall enclose a method statement including manner of
working and protective measures to protect adjacent land and property when
blasting is carried out. It is noted that each blast would last for a few
seconds. Considering the duration of blasting is very
short and infrequent, TBM would be assumed as the construction method all along
the tunnel alignment for the worst case noise assessment.
4.49
Airborne
noise impacts arising from operation of PME during the construction of
drop/riser shafts, production shafts, tunnels construction and PTW/SCISTW
upgrading works would be assessed in the following sections, while groundborne noise induced by the tunneling and
shafting activities would be assessed in Section 5 of this EIA Report.
4.50
The potential source of noise
impact during the operation phase of the PTWs, SCISTW and disinfection
facilities would be the use of ventilation fans and various pumpsets. The operation noise impacts arising
from the proposed Project are discussed in Sections 4.53 to 4.55.
4.51
As part of Stage 2A disinfection
facilities, a new chamber no. 15A will be located adjacent to the existing drop
shaft and chamber no. 15 on the
4.52
For
normal daytime working hours, exceedences of the construction noise criteria (Leq
(30 minutes) 75 dB(A) for residential uses and 70 dB(A) for educational institutions
(65 dB(A) during examinations)) would be predicted at representative NSRs in
the absence of mitigation measures.
Details of construction noise calculations and results are presented in Appendix 4.6. Results show that the predicted noise
levels related to the Project and other concurrent projects are in the range of
56 to 89 dB(A). A summary of the
unmitigated construction noise levels of the representative NSRs during normal
daytime working hours within the construction period of the Project is shown in
Table 4.9. Noise mitigation measures
would therefore be required to reduce noise levels to the stipulated noise
standards.
Table 4.9 Summary
of Unmitigated Construction Noise Levels at Representative NSRs During
Representative
NSRs |
Predicted
Unmitigated Construction Noise Levels during |
N1# |
68 - 78 |
N2 |
67 - 85 |
N3 |
65 - 80 |
N4 |
63
- 77 |
N5 |
71
- 78 |
N6 |
71 - 76 |
N7 |
72
- 77 |
N8 |
71 - 76 |
N9 |
70
- 75 |
N10 |
67
- 77 |
N11 |
67 - 76 |
N12 |
64
- 75 |
N13 |
67 - 87 |
N14 |
62
- 78 |
N15 |
59 - 73 |
N15a |
69
- 87 |
N15b |
72
- 85 |
N16 |
66
- 74 |
N17 |
69 - 78 |
N18 |
61 - 73 |
N19# |
71
- 77 |
N20 |
81 - 89 |
N21 |
61
- 74 |
N22 |
58 - 69 |
N23# |
57
- 68 |
N24 |
62
- 74 |
N25 |
60
- 85 |
N26 |
63
- 84 |
N27 |
56
- 71 |
Note:
# For normal daytime working
hours, the noise criteria are 70 dB(A) and 65 dB(A) for normal teaching periods
and examination periods, respectively.
4.53
The tentative plant inventory
and the corresponding SWL are summarised in Appendix 4.5. To represent the worst case scenario, all items of
equipment were assumed to operate concurrently 24 hours a day and the
directivity was not included in the calculation. For conservative assessment,
the noise impact has been assessed against a more stringent night-time noise
criteria.
4.54
Based
on the information provided by the Designer, most of the newly proposed equipment
would be housed/enclosed in a concrete structure. With reference to “Good
Practices on Pumping System Noise Control” and “Good Practices on Ventilation
System Noise Control” published by Environmental Protection Department,
facilities that would be enclosed in a concrete structure were assumed to have
a 20 dB(A) reduction of noise emitted from the source due to transmission loss
of the wall. Besides, the grit trap’s equipment would be partially enclosed to
avoid line of sight between the noise source and the receiver, and a noise
reduction of 20 dB(A) was assumed in accordance with the aforesaid booklets.
For the proposed Stage 2A SCISTW, items of equipment
would be screened from the line-of-sight of NSR by the structure of planned FSD
diving training centre itself. This allowed a 10 dB(A) reduction in accordance
with the relevant Technical
4.55
According to the plant
inventory for the proposed Project, the predicted noise levels at
representative NSRs in the close vicinity of PTWs, SCISTW and disinfection
facilities are presented in Table 4.10.
For newly proposed equipment, the predicted noise levels at all representative
NSRs except N12, N13, N14, N15a, N15b, N16, N17 and N20 would comply with the
night-time planning noise criteria. The noise levels at these affected NSRs
would exceed the planning noise criterion by 1 to 13 dB(A). For cumulative
noise impact, the predicted noise levels at all representative NSRs except N13,
N15a and N15b would comply with the night-time ANL. The cumulative noise level
at N13, N15a and N15b would exceed the night-time ANL of 50 dB(A) by up to 8
dB(A). As a result, further specific noise mitigation measures would be
required for Sandy Bay PTW, Cyberport PTW and Wah Fu PTW. Details of the fixed
plant noise calculations under unmitigated scenario are presented in Appendix 4.7
Table 4.10 Predicted Fixed Plant Noise Levels at Representative Noise Sensitive Receivers (Unmitigated Scenario)
Area |
NSR ID |
Newly Proposed Equipment |
Cumulative Impact (Existing
Equipment + New Equipment) |
||
Noise Criterion * |
Predicted Noise Level |
Noise Criterion * |
Predicted Noise Level |
||
North Point PTW |
N1 |
50 |
45 |
55 |
47 |
N2 |
50 |
48 |
55 |
52 |
|
N3 |
50 |
45 |
55 |
49 |
|
N4 |
50 |
41 |
55 |
44 |
|
N5 |
50 |
42 |
55 |
44 |
|
Wan Chai East PTW |
N6 |
55 |
45 |
60 |
56 |
N7 |
55 |
46 |
60 |
56 |
|
|
N8 |
55 |
37 |
60 |
37 |
N9 |
55 |
36 |
60 |
36 |
|
|
N10 |
55 |
43 |
60 |
53 |
N11 |
55 |
43 |
60 |
54 |
|
|
N12 |
45 |
47 |
50 |
47 |
N13 |
45 |
54 |
50 |
55 |
|
N14 |
45 |
47 |
50 |
48 |
|
N15 |
45 |
43 |
50 |
44 |
|
|
N15a |
45 |
57 |
50 |
57 |
|
N15b |
45 |
58 |
50 |
58 |
Cyberport PTW |
N16 |
43 |
44 |
55 |
51 |
N17 |
43 |
48 |
55 |
54 |
|
N18 |
43 |
43 |
55 |
47 |
|
Wa Fu PTW |
N19 |
50 |
43 |
55 |
43 |
N20 |
50 |
53 |
55 |
53 |
|
|
N21 |
50 |
40 |
55 |
49 |
Ap Lei Chau PTW |
N24 |
50 |
45 |
55 |
45 |
Stage 2A Disinfection Facilities |
N25 |
55 |
32 |
60 |
32 |
N26 |
55 |
35 |
60 |
35 |
|
SCISTW |
N27 |
55 |
30 |
60 |
48 |
Note: * A more
stringent night-time noise criterion has been adopted for conservative
assessment.
4.56 In order to reduce the excessive noise impacts at the affected NSRs during normal daytime working hours, mitigation measures such as adopting quiet powered mechanical equipment, movable noise barriers and acoustic mats are recommended (see Appendix 4.8). The above mitigation measures have been confirmed by the Engineer as being practicable in completing the works within scheduled timeframe. The Contractor may be able to obtain particular models of plant that are quieter than the PMEs given in GW-TM. It is considered too restrictive to specify that a Contractor has to use specific items of plant for the construction operations. It is practical to specify the total SWL of all plant to be used on site so that the Contractor is allowed some flexibility to select plant to suit his needs.
4.57
In
this assessment, the recommended quiet PME are taken from the BS 5228: Part 1:
1997, and the PME are known to be available in
4.58 For the following construction tasks of the Project, it is considered necessary to adopt quiet PME:
Drop/Riser Shaft
· Construction of upper shaft, Diaphragm wall at shaft
· Construction of upper shaft, Excavation at shaft
· Construction of lower shaft
· Drop shaft finishing works
Production Shaft
· Construction of upper shaft, Diaphragm wall at shaft
· Construction of upper shaft, Excavation at shaft
· Construction of lower shaft
· Tunnel construction
PTW Upgrading Works
· Piling (socket H-piles)
· Excavation (shallow excavation with sheet piling)
· Concreting
· Demolition Works
· Roadwork
SCISTW Upgrading Works
· Site clearance and setup site office
· Shallow excavation
· Drill and blast excavation
· Deep excavation
· Civil works
· Pipeworks
· Demolition works
4.59
To alleviate the construction
noise impact on the affected NSRs, movable noise barriers and acoustic mats are
proposed to be provided for particular items of plant and construction works.
With a surface mass of not less than 2.5 kg/m2, it is anticipated
that the acoustic mats can provide 5 dB(A) noise reduction. Besides, it is
anticipated that a movable noise barrier with a cantilevered upper portion
located within
4.60 For the following construction tasks of the Project, it is considered necessary to adopt movable noise barrier:
Drop/Riser Shaft
· Construction of upper shaft, Diaphragm wall at shaft
· Construction of upper shaft, Excavation at shaft
· Construction of lower shaft
· Drop shaft finishing works
Production Shaft
· Construction of upper shaft, Diaphragm wall at shaft
· Construction of upper shaft, Excavation at shaft
· Construction of lower shaft
· Tunnel construction
PTW Upgrading Works
· Piling (socket H-piles)
· Concreting
SCISTW Upgrading Works
· Site clearance and setup site office
· Shallow excavation
· Drill and blast excavation
· Deep excavation
· Civil works
· Pipeworks
· Demolition works
4.61 Besides, use of acoustic mats is recommended for the following construction tasks of the Project. Figure 4.13 illustrates the practical way of using acoustic mat for bored piling chisel during the construction of upper shaft.
Drop/Riser Shaft
· Construction of upper shaft, Diaphragm wall at shaft
Production Shaft
· Construction of upper shaft, Diaphragm wall at shaft
· Construction of upper shaft, install pipe pile wall
PTW Upgrading Works
· Piling (socket H-piles)
· Excavation (shallow excavation with sheet piling)
SCISTW Upgrading Works
· Deep excavation with diaphragm wall
4.62
As shown in Appendix 4.9, with the use of quiet
equipment, movable noise barriers and acoustic mats, the overall noise levels
at NSRs would be reduced by up to 14 dB(A), depending on the type of
construction activities. The predicted mitigated construction noise levels at
representative NSRs would range from 47 to 75 dB(A). With the exception of NSRs
N1 during examination periods, the predicted construction noise levels arising
from the Project at all representative NSRs would comply with the EIAO-TM
construction noise criteria. Assessing against the noise standard of 65 dB(A)
during examination periods, the predicted noise level at NSR N1 (i.e.
Table 4.11 Summary of Mitigated
Construction Noise Levels at Representative NSRs during
Representative
NSRs |
Predicted
Mitigated Construction Noise Levels during |
N1# |
65 - 70 |
N2 |
66 - 74 |
N3 |
64 - 70 |
N4 |
63
- 68 |
N5 |
63
- 73 |
N6 |
67 - 68 |
N7 |
61
- 68 |
N8 |
62 - 73 |
N9 |
61
- 73 |
N10 |
58
- 73 |
N11 |
60 - 70 |
N12 |
59
- 67 |
N13 |
63 - 74 |
N14 |
57
- 65 |
N15 |
54 - 62 |
N15a |
64 - 74 |
N15b |
67 - 75 |
N16 |
58
- 68 |
N17 |
62 - 71 |
N18 |
57 - 63 |
N19# |
62
- 65 |
N20 |
73 - 75 |
N21 |
56
- 64 |
N22 |
53 - 61 |
N23# |
52
- 61 |
N24 |
57
- 61 |
N25 |
48
- 71 |
N26 |
51
- 71 |
N27 |
47
- 62 |
Note:
# For normal daytime working
hours, the noise criteria are 70 dB(A) and 65 dB(A) for normal teaching periods
and examination periods, respectively.
4.63 As mentioned in Section 4.55, the predicted noise levels at NSRs N12, N13, N14, N15a, N15b, N16, N17 and 20 would exceed the night-time planning noise criteria by 1 to 13 dB(A) due to the newly proposed equipment at Sandy Bay PTW, Cyberport PTW and Wah Fu PTW, while the cumulative noise level at N13, N15a and N15b would exceed the night-time ANL of 50 dB(A) by up to 8 dB(A). Air supply fans/extraction fans of transfer pumping stations and ventilation fans for deodourization unit would be the dominant noise sources causing noise exceedance at these affected NSRs. In this regard, acoustic louvers have been proposed for these fans to mitigate the noise impact. With reference to EIA Report for Siu Ho Wan Water Treatment Works Extension, a noise reduction of 20 dB(A) would be achieved with acoustic louvers. As shown in Table 4.12, Except N15a due to the newly proposed equipment at Sandy Bay PTW, the predicted noise levels at these affected NSRs would comply with both the night-time ANL and night-time planning noise criteria with acoustic louvers in place. Details of noise calculations under mitigated scenario are presented in Appendix 4.10
Area |
NSR ID |
Newly
Proposed Equipment |
Cumulative
Impact (Existing Equipment + New Equipment) |
||
Noise
Criterion * |
Predicted
Noise Level |
Noise
Criterion * |
Predicted
Noise Level |
||
|
N12 |
45 |
35 |
50 |
39 |
N13 |
45 |
42 |
50 |
49 |
|
N14 |
45 |
35 |
50 |
42 |
|
N15 |
45 |
31 |
50 |
37 |
|
N15a |
45 |
46 |
50 |
50 |
|
N15b |
45 |
45 |
50 |
49 |
|
Cyberport
PTW |
N16 |
43 |
33 |
55 |
49 |
N17 |
43 |
37 |
55 |
53 |
|
N18 |
43 |
31 |
55 |
45 |
|
Wa Fu
PTW |
N19 |
50 |
34 |
55 |
34 |
N20 |
50 |
44 |
55 |
44 |
Note: * A more
stringent night-time noise criterion has been adopted for conservative
assessment
4.64 To further mitigate the noise impact at N15a due to the newly proposed equipment at Sandy Bay PTW, it is recommended that the maximum allowable sound power level (SWL) of each new transformer at Sandy Bay PTW shall be limited to 89 dB(A) during the detailed design stage. With the control of SWL of the transformer, the predicted noise level at N15a would be 45 dB(A) which comply with the relevant night-time planning noise criterion.
4.65 With the implementation of the above-mentioned mitigation measures, the construction noise levels at all representative NSRs except N1 are predicted to comply with the noise standards stipulated in the EIAO-TM. Residual impacts at NSR N1 are summarised in Table 4.13.
4.66
The
on-site survey has revealed that NSR N1 (i.e.
Table 4.13 Construction Noise Residual Impacts
NSR |
Exceedance of the
EIAO-TM Noise Criterion * |
Construction Activity
Causing Exceedance |
Approximate duration
of Exceedance # |
N1 |
5 dB(A) 5 dB(A) 4 - 5 dB(A) 4 dB(A) 4 dB(A) 4 dB(A) 4 dB(A) 5 dB(A) 5 dB(A) |
Diaphragm wall (drop shaft and production shaft), lower
shaft, Phase III works and baraging activities |
4 months(March – June 2009) 1 month (December 2009) 4 months (March - June 2010) 1 month (December 2010) 4 months (March - June 2011) 1 month (December 2011) 4 months (March - June 2012) 1 month (December 2012) 4 months (March – June 2013) |
Notes:
* Against the noise EIAO-TM noise
criterion of 65 dB(A) for examination periods.
# Public examination is assumed to be held
in March, April and May, while school examination is assumed to be held in
December and June of each year.
4.67
In addition to the above-mentioned mitigation measures,
the good site practices listed below shall be adopted by all the Contractors to
further ameliorate the noise impacts.
Although the noise mitigating effects are not easily quantifiable and
the benefits may vary with the site conditions and operating conditions, good site
practices are easy to implement and do not impact upon the works schedule.
·
Only well-maintained plant shall be
operated on-site and plant shall be serviced regularly during the construction
program.
·
Silencers or mufflers on construction
equipment shall be utilised and shall be properly maintained during the
construction program.
·
Mobile plant, if any, shall be sited
as far away from NSRs as possible.
·
Machines and plant (such as trucks)
that may be in intermittent use shall be shut down between works periods or
shall be throttled down to a minimum.
·
Plant known to emit noise strongly in
one direction shall, wherever possible, be orientated so that the noise is
directed away from the nearby NSRs.
·
Material stockpiles and other
structures shall be effectively utilised, wherever practicable, in screening
noise from on-site construction activities.
4.68 Based on the information provided by the Designer, most of the newly proposed equipment would be housed/enclosed in a concrete structure. In addition, acoustic louvers have been proposed for air supply fans/extraction fans of transfer pumping stations and ventilation fans of deodourization unit at Sandy Bay PTW, Cyberport PTW and Wah Fu PTW. It is recommended that the maximum allowable sound power level (SWL) of each new transformer at Sandy Bay PTW shall be limited to 89 dB(A) during the detailed design stage. With such proper designs, no adverse residual operation noise impact arising from the Project is expected.
4.69
The
construction programme for the Project takes into account the likelihood that
the contractor will, if permitted, undertake the construction works within the
tunnel and bottom of shaft over a 24-hour working day. The tunnels would be constructed by either D&B or TBM. For TBM
method, no noisy PME
except ventilation fans would be operated above ground during restricted hours
(1900 to 0700 hours) according
to information
provided by the Engineer. The tunnel spoil would be conveyed to the ground
surface for collection and disposal of during non-restricted hours (0700 – 1900
hours).
4.70
For
D&B method, there would be two times of blasting per day (i.e. one in
daytime and one in night-time) for the tunnel construction. During restricted
hours, in addition to the ventilation fans, only a gantry crane will be
operated on ground to lift up the spoil to the shaft top and dump at the
stockpile area adjacent to the production shaft. The spoil will then be
disposed of off site during non-restricted hours.
4.71
For
the purpose of this indicative assessment, D&B method would be adopted for
the worst case noise assessment taking into account the items of PME to be
involved. At each production shaft, the items of PME to be operated on ground
for tunnel construction using D&B method during restricted hours are
presented in Table 4.14. Appropriate
on-time percentage for the items of PME was reasonably assumed. According to
information provided by the Engineer, four ventilation fans with volume flow
rate of 10,800 m3/hour each would be required for each production
shaft at North Point, Wan Chai East,
Powered Mechanical Equipment |
No. of Items |
SWL/Item dB(A) |
Total SWL dB(A) |
Gantry crane |
1 |
95 |
95 |
Ventilation fan |
4 |
85 |
91 |
4.72
The noise impact has been assessed against a more stringent
night-time noise criteria. The assessment results are presented in Appendix
4.11. A summary of unmitigated
noise levels at these representative NSRs is presented in Table 4.15.
Representative
NSRs |
Noise
Criterion * |
Predicted
Unmitigated Construction Noise Levels (Leq
(30-min) dB(A)) |
N1 |
50 |
47 |
N2 |
50 |
44 |
N3 |
50 |
42 |
N4 |
50 |
40 |
N5 |
50 |
50 |
N6 |
55 |
44 |
N7 |
55 |
43 |
N8 |
55 |
46 - 49 |
N9 |
55 |
45 - 48 |
N12 |
45 |
46 - 49 |
N13 |
45 |
49 - 53 |
N14 |
45 |
44 - 48 |
N15 |
45 |
41 - 44 |
N16 |
50 |
43 |
N17 |
50 |
48 |
N18 |
50 |
42 |
N21 |
50 |
41 |
N22 |
50 |
40 |
N23 |
50 |
40 |
N27 |
55 |
41 |
Note: * A more
stringent night-time noise criterion has been adopted for conservative
assessment
4.73
As
shown in Table 4.15, with the
exception of representative NSRs near Sandy Bay PTW (i.e. N12 to N14), the
predicted construction noise levels at other representative NSRs during
restricted hours would comply with the corresponding noise limits.
4.74
To
mitigate the noise impact at NSRs N12 to N14, ventilation fans and motors of
gantry at the production shafts of Sandy Bay PTW shall be properly housed. Silencers
shall also been installed at outlet and inlet of the enclosure for ventilation
fans. A 10 dB(A) noise screening reduction for both
the motors of gantry and ventilation fans was assumed in the assessment. Predicted noise levels after mitigation at representative NSRs are
shown in Appendix 4.12. A summary of
mitigated noise levels at representative NSRs is presented in Table 4.16.
Representative
NSRs |
Noise
Criterion * |
Predicted
Unmitigated Construction Noise Levels (Leq
(30-min) dB(A)) |
N12 |
45 |
36 - 39 |
N13 |
45 |
39 - 43 |
N14 |
45 |
34 - 38 |
Note: * A more stringent
night-time noise criterion has been adopted for conservative assessment
4.75
With
the adoption of the recommended mitigation measures, the predicted noise levels
at NSRs N12 to N14 would comply with the construction noise criterion of 45
dB(A) during restricted hours. In
applying for a Construction Noise Permit, the Applicant (that is, the
Contractor) shall be required to demonstrate to the satisfaction of the Noise
Control Authority the noise reduction effect of mitigation measures to be
adopted. Otherwise, values in the GW-TM will be used in assessing the
application.
4.76
The
above assessment only demonstrates that the construction works in restricted
hours would be feasible in the context of programming construction work. If the
Contractor considers that there is a need to carry out construction works
during restricted hours, a Construction Noise Permit shall be obtained from the
Noise Control Authority prior to commencement of such works. There are some factors affecting the
assessment results of a CNP application, such as the assigning of Area
Sensitivity Rating, Acceptable Noise Levels etc. The Noise Control Authority would decide
these at the time of assessment of such application based on the contemporary
situations / conditions. It should
be noted that the situations / conditions around the sites may change from time
to time. The Authority may make
correction for multiple permit situations if in the opinion of the Authority
the NSR will be materially affected by noise from construction work associated
with more than one CNP, and the Authority may make such correction to the
relevant noise level as it considers appropriate having regard to standard
acoustical principles and practices. The Area Sensitivity Ratings assumed in
this EIA Report are for indicative assessment only.
4.77 It is recommended to establish an Environmental Monitoring and Audit (EM&A) programme for control of construction noise. The recommended mitigation measures should be incorporated into the EM&A programme for implementation during the construction period. Details of the programme are provided in a stand-alone EM&A Manual.
4.78
The EIA findings confirmed that
proper designs of PTWs, SCISTW and disinfection facilities would control the
potential noise impact at noise sensitive receivers within acceptable levels,
operational noise monitoring is not considered necessary.
4.79
This assessment has predicted the construction noise
impacts of the Project during normal daytime working hours, taking into account
other concurrent projects including
4.80
Assessing against the noise
standard of 65 dB(A) during examination periods, the predicted noise level at
NSR N1 (i.e.
4.81
An indicative assessment has been undertaken for
possible construction activities within the tunnel and bottom of shaft during
restricted hours. Based
on information provided by the Engineer, no major items of PME except
ventilation fans and gantry crane would be operated above ground during
restricted hours (1900 to 0700 hours). The assessment results show that the
predicted construction noise levels at representative NSRs during restricted
hours would comply with the corresponding noise limits, provided that the ventilation fans and motors of
gantry at the production shafts of Sandy Bay PTW would be properly housed and
the silencers would be installed at outlet and inlet of the enclosure for
ventilation fans. It should be noted that the results of the
construction noise impact assessment for restricted hours are for indicative
purposes, the Noise Control Authority will process any CNP application based on
the NCO and the relevant technical memoranda in addition to considering the
contemporary situations / conditions.
4.82
A construction noise EM&A programme is recommended
to check the compliance of the noise criteria during normal daytime working hours.
4.83
The
noise impact associated with the operation of the Project was assessed. For newly proposed equipment, the predicted noise levels at all
representative NSRs except N12, N13, N14, N15a, N15b, N16, N17 and N20 would
comply with the night-time planning noise criteria. The noise levels at these
affected NSRs would exceed the planning noise criterion by 1 to 13 dB(A). For
cumulative noise impact, the predicted noise levels at all representative NSRs
except N13, N15a and N15b would comply with the night-time ANL. The cumulative
noise level at N13, N15a and N15b would exceed the night-time ANL of 50 dB(A)
by up to 8 dB(A).
4.84
To mitigate the noise impact at
the affected NSRs, acoustic louvers have been proposed for air supply
fans/extraction fans of transfer pumping stations and ventilation fans of deodourization unit at
Sandy Bay PTW, Cyberport PTW and Wah Fu PTW. Besides,
it is recommended that the maximum allowable sound power level (SWL) of each
new transformer at Sandy Bay PTW shall be limited to 89 dB(A) during the
detailed design stage. With such proper designs, the predicted noise levels at
all representative NSRs would comply with both the night-time ANL and
night-time planning noise criteria. No residual operation noise impact arising
from the Project is anticipated.
4.85
Proper designs of PTWs, SCISTW
and disinfection facilities would control the potential noise impact at noise
sensitive receivers within acceptable levels, operational noise monitoring is
not considered necessary.