5                     GROUNDBORNE NOISE impact assessment

 

Introduction

 

5.1               As part of the HATS Stage 2A project, vertical shafts and deep sewage conveyance system (or tunnels) will be constructed along densely populated districts such as North Point, Causeway Bay, Wanchai and Central of Hong Kong Island to convey screened sewage collected from different Preliminary Treatment Works (PTW) to Stonecutters Island Sewage Treatment Works (SCISTW) for centralised treatment. Besides, a deep effluent conveyance system will also be constructed to connect the flow distribution chamber at SCISTW to the outfall. There are mainly three types of construction methods for tunnelling, including Tunnel Boring Machine (TBM), Raise Boring Machine (RBM), Horizontal Directional Drilling (HDD) and Drill and Blast (D&B). Powered mechanical equipment (PME) would also be employed for construction of vertical shafts. In this Section, groundborne noise impacts induced by the tunneling and shafting activities were assessed in accordance with Clause 3.4.2 of the EIA Study Brief.

 

5.2               No groundborne noise would be expected during operation of the Project and hence no operational impact assessment was carried out under this Section.

 

Environmental Legislation and Criteria

 

5.3               With reference to the Technical Memorandum for the Assessment of Noise from Places Other Than Domestic Premises, Public Places or Construction Sites (TM-Places) under the Noise Control Ordinance (NCO), the criteria for noise transmitted primarily through the structural elements of the building or buildings should be 10dB(A) less than the relevant acceptable noise levels (ANL). These criteria apply to all residential buildings, schools, hospital, temple and church in accordance to the Area Sensitivity Rating (ASR). These groundborne noise criteria have been adopted in the “Project Profile for Development of the Former Marine Police Headquarter (FMPHQ) for direct application of Environmental Permit” and “Kowloon Southern Link” (KSL) by Kowloon-Canton Railway Corporation (KCRC) with the EIA report (Application No. EIA-098/2004) approved by Environmental Protection Department (EPD) in March 2005.

 

5.4               For any construction work with the restricted hours period (1900-0700) a construction noise permit must be applied in accordance to the Technical Memorandum of NCO.

 

5.5               The construction groundborne noise criteria for the representative noise sensitive receiver(s) (NSR) for ASR along HATS 2A deep tunnel alignments are tabulated in Table 5.1 below.

Table 5.1          Construction Groundborne Noise Criteria for Schools, Hospital, Hotel Guestrooms and Domestic Premises

 

Groundborne Noise Criteria, dB(A)


NSR Description

Daytime
(except General Holidays & Sunday)

Daytime during General Holidays and Sundays and All Days during Evening
(1900 to 2300 hrs)

Night-time
(2300 to 0700 hrs)

 

All ASR

ASR “A”

ASR “B”

ASR “A”

ASR “B”

School (Classrooms)

60/55*

50

55

-

-

Hotel guestrooms and Domestic premises

65

50

55

35

40

*For schools during examination period

 

Description of the Environment

 

5.6               The proposed deep tunnel alignments will run from North Point to Sai Ying Pun, Ap Lei Chau to Sai Ying Pun and then from Sai Ying Pun to Stonecutters Island. It is a 3.5 - 5m diameter tunnel at an average depth of over 100 m in bedrock under the ground level. Construction of tunnels by either TBM or D&B will go underneath some densely populated areas including residential buildings and school blocks. HDD would also be used for construction of the tunnel section from Ap Lei Chau to Aberdeen underneath seabed. Deep tunnels are divided into sections according to districts and their corresponding depths are summarized in Table 5.2. The tunneling activities would be operated 24 hours (i.e. including restricted hours from 7:00pm to 7:00am).

Table 5.2          Tunnel Depth with respect to District

Tunnel ID

District

Depth (mPD)

Construction Method

J

North Point to Wanchai

-160

TBM or D&B

K

Wanchai to Sai Ying Pun

-150

TBM or D&B

L

Sai Ying Pun to Stonecutters Island (under sea)

-140

TBM or D&B

M

Sai Ying Pun to Sandy Bay

-120

TBM or D&B

N

Sandy Bay to Cyberport

-70

TBM or D&B

P

Cyberport via Wah Fu to Aberdeen

-80

TBM or D&B

Q

Ap Lei Chau to Aberdeen (under sea)

-60

HDD

Effluent Tunnel

Flow Distribution Chamber at SCISTW to Outfall

-50

TBM or D&B

Notes: Locations of the tunnel sections can be referred to the figures in Section 2.

 

Noise Sensitive Receivers

 

5.7               Representative noise sensitive receivers (NSRs) located closest to each tunnel section, which are supposed to receive the highest vibration impacts imposed by construction works, are presented in Table 5.3.

Table 5.3         Summary of Identified Noise Sensitive Receivers

Tunnel Section

NSRs

Noise Criteria (ASR)

Rock head depth (mPD)

Tunnel Depth (mPD)

Horizontal Distance from Tunnel to NSR

(m)

NSR Height (mPD)

Slant Distance from Tunnel to Piles/ Foundation of NSR

(m)

J

Henittetta Secondary School, North Point

B

-40

-160

38

+4.0

126

Hoi Kung Court,

Causeway Bay

B

-40

-160

32

+4.0

124

K

Hong Kong Convention & Exhibition Center I, Wan Chai

C

-40

-150

51

+4.0

121

Hong Kong Convention & Exhibition Center II Wan Chai

C

-40

-150

77

+4.0

134

Grand Hyatt, Wan Chai

C

-40

-150

70

+4.0

130

M

Merton Block 1,

Kennedy Town

B

-45

-120

6.5

+4.1

75

N

SAGE Madam Ho Sin Hang Home for the Elderly

Sandy Bay

A

-25

-70

95

+5.4

105

P

Tsui Tsin Tong School,

Wah Fu

B

-10

-80

17

+25

72

Le Meridien Hotel, Cyberport

B

-30

-75

31

+5.4

56

Q

South Horizons Block 10,

Ap Lei Chau

B

-20

-60

116

+14.3

123

Effluent Tunnel

Ngong Shuen Chau Barracks

C

-30

-50

335

+4.0

336

Notes: Locations of the tunnel sections can be referred to the Figure 2.9 in Section 2.

 

5.8               Not all foundation details of the above identified noise sensitive receivers were provided for the assessment during the study. Therefore, for conservative analysis, it is assumed that all NSRs are having piles rested on rock head level which give a worst case on vibration transmission path. Because of this, the distance from the piles to the tunnel is taken as the slant distance with shortest vibration path.

 

5.9               In this groundborne noise assessment, distance attenuation is the dominant factor affecting the predicted result. From Table 5.3 the shortest slant distance from tunnel to the foundation/piles appears in Le Meridien Hotel, Cyberport.

 

Assessment Methodology

 

Groundborne Noise Sources from Construction Activities

 

5.10            As mentioned above, TBM or D&B would be adopted for tunneling at most of the tunnel sections. However, D&B is not considered with respect to noise annoyance since the duration of blasting is very short and infrequent. Therefore, as the worst case scenario, TBM was assumed to be the construction method all along the tunnel alignment for groundborne noise assessment. In principle, vibration would be transmitted from the operation of TBM via bedrock or soil to the nearby foundations of the NSR, and it would then be transmitted primarily through the structural elements of the buildings, resulting in groundborne noise to the NSR.

 

5.11            HDD would be employed as micro-tunneling method for the tunnel section from Aberdeen PTW towards Ap Lei Chau PTW. It would start from the surface with maximum inclined angle of 25 degrees to the lowest level of about -76mPD under the sea. After keeping this level along the tunnel alignment, the HDD would then go upwards with the existing angle maximum of 25 degrees to the surface. The drilling process would be carried out in several stages, the first pilot hole with about 300 mm diameter would be firstly finished and then reamed to large hole by several stages up to approximately 1.5 m. Since the size of the HDD is relatively small when comparing with the TBM, and its alignment is about -76mPD under sea which is far away from residential buildings (around 100 m from the nearest South Horizon), it was predicted that groundborne noise generated from this activity would be minimal and hence was not considered in the groundborne noise assessment.

 

5.12            Other than tunneling, drop/riser/production shafts would also be constructed by mechanical excavation and boring. In particular, the lower shaft at the rock layer would be constructed by means of PME for rock breaking. Hydraulic breaker and RBM will be the major PME to generate groundborne noise affecting the nearby NSRs during lower shaft construction and tunnel drilling. Other construction activities such as lorry movement and concreting etc are unlikely to generate adverse groundborne noise.

 

5.13            In summary, the major vibration generating equipment relevant to tunneling and shafting works would be TBM, RBM and hydraulic breaker.  However, at the time of preparation of this report, there was no available information on the relevant models and vibration source levels of both types of PME (i.e. TBM and hydraulic breaker) from the tunnel design engineers. To assess the groundborne noise generated from the PME, the most relevant source levels for TBM and hydraulic breakers were derived by making reference to the vibration source data from other similar tunneling project – ‘Kowloon Southern Link’ (KSL EIA) by KCRC.  The source level of the TBM extracted from KSL EIA is shown in Appendix 5.1.

 

Groundborne Noise Prediction Methodology

 

5.14            Groundborne construction noise was predicted based on the methodology as described in the US Department of Transportation “High-Speed Ground Transportation Noise and Vibration Impact Assessment”.

 

5.15            Groundborne noise was assessed by using the following formula taking into account relevant source data, geological profile and foundation structure of the NSR. The geological profile for selected NSR for calculation is shown in Figure 5.2.

 

5.16            The predicted groundborne noise level Lp inside the noise sensitive rooms is given by the following equation.

Lp = Lv,rms + Cdist + Cdamping + Cbuilding + Cfloor + Cnoise + Cmulti + Ccum

Cdist:             Distance attenuation

Cdamping:         Soil damping loss across the geological media

Cbuilding: Coupling loss into building foundation

Cfloor:             Coupling loss per floor

Cnoise:            Conversion factor from floor vibration levels to noise levels

Cmulti:            Noise level increase due to multiple sources

Ccum:             Cumulative effect due to neighbouring sites

 

Soil Damping

 

5.17            Internal losses of soil would cause the vibration amplitude to decay against the propagation distance and the decay relationship is based on the equation set out in the Transportation Noise Reference Book[1]

V(R) = V(Ro) ´ e-2pf h R/2c.

5.18            The velocity amplitude V is dependent on the frequency f in Hz, the soil loss factorh, the wave speed c in m/s, the distance R from the source to the NSR.  The properties of soil materials are shown in Table 5.4.

Table 5.4          Wave Propagation Properties of Soil

Soil Type

Longitudinal Wave Speed c, m/s

Loss Factor, h

Density, g/cm3

Soil

1500

0.5

1.7

 

5.19            No damping attenuation was applied for propagation in rocks. If the vibration propagation through rock with a distance more than 100 m, a –6 dB of attenuation due to joints in the rock for each 100m from source was applied in accordance with a reference “TRL Report 429 by Transport Research Laboratory of UK”

Coupling Loss into Building Structures

5.20            The coupling loss into building structures represents the change in the incident ground-surface vibration due to the presence of the piled building foundation.  The empirical values with reference to the “Transportation Noise Reference Book”, 1987 are given in Table 5.5.

 

Table 5.5          Loss factor for Coupling into Building Foundation

Frequency

Octave Band Frequencies, Hz

16

31.5

63

125

250

500

Loss factor for coupling into building foundation, dB

-7

-7

-10

-13

-14

-14

Coupling Loss Per Floor

5.21            The coupling loss per floor represents the floor-to-floor vibration transmission attenuation.  For multi-storey buildings, a common value for the attenuation of vibration from floor-to-floor is approximately 1 dB attenuation in the upper floor regions and greater than 3 dB attenuation at lower floors.  Coupling loss of 1 dB reduction per floor was assumed in this report for a conservative assessment to account for any possible amplification due to resonance effects.

Conversion from Floor Vibration to Noise Levels

5.22            Conversion from floor vibration levels to indoor reverberant noise levels is based on standard acoustic principles.  The conversion factor is dependent on the surface area S of the room in m2, the radiation efficiencys, the volume of the room V in m3 and the room reverberation time RT in seconds.  Conversion factors from floor vibration levels to indoor reverberant noise levels is 26 dB(A) for residential units and 27 dB(A) for hotel guest rooms as mention in the KSL EIA report.

 

Identification of Environmental Impacts

 

5.23            From the formula in Section 5.13, groundborne noise was assessed based on the following factors:

l                   Vibration source strength

l                   Vibration transmission media

l                   Distance from the source to the NSR

l                   Floor level of NSR

l                   Standard factors such as building coupling loss and acoustic conversion

 

5.24            The NSR closest to each of the tunnel alignments was identified as shown in Table 5.3. It was assumed that greater vibration impacts would be anticipated at the NSR with shorter distance from foundation to the tunnel alignment. In this case, Le Meridien Hotel at Cyberport with distance of 56m to Tunnel P would be the worst affected NSR for TBM operation and therefore selected for the assessment of worst case scenario. Key assumptions made in the calculation of groundborne noise at the worst affected NSR are summarized in Table 5.6 below.

Table 5.6          Summary of Assumptions Applied in Calculation Factors in the Worst Case NSR for TBM operation

Factors

Description

Worst Case Assumption

Identification of NSR

Le Meridien Hotel at Cyberport

In principal, the shortest distance from the tunnel to the foundation of NSR would receive the worst groundborne noise impact. According to the depth of the tunnel alignment and the distance between the NSR’s foundation & the tunnel (see Table 5.3), NSRs near Tunnel P running from Cyberport all along to Aberdeen are the most sensitive to groundborne noise than in other districts. Le Meridien Hotel is the NSR which foundation is closest to the proposed tunnel P alignment and the Cyberport drop / riser shaft (56m). Therefore, it was chosen as the worst NSR in the assessment. Figure 5.1 shows the location of the Hotel and tunnel alignment.

 

Source Term

The TBM working geology would be granite which is similar to that of the Canton Road section of the KSL Project as well as the Kwai Tsing Tunnel of the KCRC West Rail Project. The vibration source terms for TBM adopted for the KSL EIA which were derived from the vibration measurement for TBM operation for the Kwai Tsing Tunnel were used in this assessment.

 

The size of the TBM to be used for this Project would be expected to be half of the KSL Project. Therefore, the assumed vibration source term was sufficiently conservative.

Soil Damping

No damping attenuation was applied to propagation in rocks. If the vibration propagation through rock with a distance more than 100 m, a –6 dB of attenuation due to joints in the rock for each 100m from source was applied in accordance with the reference “TRL Report 429 by Transport Research Laboratory of UK”

In this Project, the TBM will operate in rock level and the vibration will transmit from rock to the foundation pile of the NSR. Therefore, by assuming the whole transmission process in rock media without faults and joints as the worst case scenario, zero damping effect was therefore adopted.

 

Floor to Floor Attenuation

Loss of 1 dB reduction per floor

The hotel guest rooms were assumed to be located at the third level of the hotel. Therefore, a floor to floor attenuation factor of -3dB(A) was applied in the calculation.

 

Distance Attenuation

Standard acoustic principle for determining distance attenuation was adopted in the present assessment.

 

Assuming the tunnel alignment is directly under the NSR, no offset was applied.

Building Coupling Loss

Standard acoustic principle for determining building coupling loss was adopted in the present assessment.

 

Standard conversion

Coupling Loss from Bedrock to Pile

In the KSL EIA, a 18 dB(A) reduction was applied for the coupling Loss from bedrock to pile.

When the TBM is drilling through the bed rock, the vibration will be transmitted along the rock mass to the piles of nearby buildings if the piles rest on bed rock directly.  When the vibration hits the piles of the buildings, it will be transferred without loss.  Therefore, no bed rock to pile loss was applied in this assessment.

 

Conversion from Vibration to Noise

Standard acoustic principle for converting vibration levels to noise levels was adopted in the present assessment.

 

Standard conversion

Conversion to A-weighted Noise

Standard acoustic principle for converting vibration levels to noise levels was adopted in the present assessment.

Standard conversion

 

5.25            The NSR closest to the drop shaft is Wah Ming House of Wah Fu Estate which is around 38m. Operation of hydraulic breaker and the raise boring machine (RBM) at the shaft will generate vibration which consequently transfers to groundborne noise inside domestic premises. Key assumptions made in the calculation of groundborne noise at the worst affected NSR are summarized in Table 5.7 below.

Table 5.7          Summary of Assumptions Applied in Calculation Factors in the Worst Case NSR for hydraulic breaker / RBM operation

Factors

Description

Worst Case Assumption

Identification of NSR

Wah Ming House of Wah Fu Estate

Wah Ming House is only 38m away from the proposed drop shaft.

 

Source Term

Hydraulic Breaker - Refer to Appendix 7-1 of EIA report of KSL project.

RBM assumed to be the same as TBM operation but working vertically. Reference is also to KSL project.

 

The size of the RBM to be used for this Project would be expected to be half of the KSL Project. Therefore, the assumed vibration source term was sufficiently conservative.

Soil Damping

No damping attenuation was applied to propagation in rocks. If the vibration propagation through rock with a distance more than 100 m, a –6 dB of attenuation due to joints in the rock for each 100m from source was applied in accordance with the reference “TRL Report 429 by Transport Research Laboratory of UK”

Assuming the whole transmission process in rock media without faults and joints as the worst case scenario, zero damping effect was therefore adopted.

 

Floor to Floor Attenuation

Loss of 1 dB reduction per floor

The residential units were assumed to be located at the second level of the hotel. Therefore, a floor to floor attenuation factor of -2dB(A) was applied in the calculation.

 

Distance Attenuation

Standard acoustic principle for determining distance attenuation was adopted in the present assessment.

 

Horizontal plan distance is assumed from the hydraulic breaker / RBM to the NSR

Building Coupling Loss

Standard acoustic principle for determining building coupling loss was adopted in the present assessment.

 

Standard conversion

Coupling Loss from Bedrock to Pile

In the KSL EIA, a 18 dB(A) reduction was applied for the coupling Loss from bedrock to pile.

When the hydraulic breaker / RBM is breaking the rock, the vibration will be transmitted along the rock mass to the piles of nearby buildings if the piles rest on bed rock directly.  When the vibration hits the piles of the buildings, it will be transferred without loss.  Therefore, no bed rock to pile loss was applied in this assessment.

 

Conversion from Vibration to Noise

Standard acoustic principle for converting vibration levels to noise levels was adopted in the present assessment.

 

Standard conversion

Conversion to A-weighted Noise

Standard acoustic principle for converting vibration levels to noise levels was adopted in the present assessment.

Standard conversion

 

Prediction and Evaluation of Environmental Impacts

 

5.26            Based on the vibration source data and the existing geological profile available at the time of reporting, a worst case scenario for potential groundborne construction noise impact was assessed using methodology as presented above.  Unmitigated groundborne noise levels predicted at the worst affected NSR (Le Meridien Hotel and Wah Ming House) is shown in Table 5.8.  Details calculations of groundborne noise levels are presented in Appendix 5.2.

Table 5.8          Unmitigated Groundborne Construction Noise Levels at the Worst Affected NSR

Construction Activities

NSR

Predicted Groundborne Noise Level at NSR, dB(A)

Noise Criterion, dB(A) of ASR “B”

0700-1900

1900-2300

2300-0700

Hydraulic Breaker at Wah Fu Drop Shaft

Wah Ming House

40

65

55

40

Raise Boring Machine at Wah Fu Drop Shaft

Wah Ming House

40

TBM under Cyberport

Le Meridien Hotel

36

Note:      According to the preliminary construction programme available at the time of reporting, no simultaneous operations of the TBM, RBM and hydraulic breaker would be expected.

 

5.27            As shown in the table above, the predicted groundborne noise levels generated by using TBM, RBM or hydraulic breaker during construction phase of the Project would be below the relevant noise assessment criterion at the worst affected NSR. Hence, adverse groundborne noise impact associated with the construction of the Project would not be expected.

 

Mitigation Measures

 

5.28            No mitigation measures would be recommended as no adverse groundborne noise impact was expected in the unmitigated scenario during construction stage of the Project.

 

Evaluation of Residual Impacts

 

5.29            The groundborne noise level at the worst affected NSR was predicted to be well below the relevant noise criterion. No residual groundborne noise impact would therefore be anticipated during the construction phase of the Project.

 

Conclusion

 

5.30            Potential groundborne noise sources during the construction phase of the Project have been identified. The major activities inducing potential groundborne noise impacts are from operation of TBM, RBM and hydraulic breaker during tunneling and rock breaking. The noise impact on the closest sensitive receiver was assessed and the results indicated that the predicted impacts would be within the statutory requirements. In other words, all NSRs along the proposed tunnel alignment would not be adversely affected by groundborne noise generated by the construction of the Project, and mitigation measures as well as monitoring programme would not be necessary. Regardless of the results of the groundbornes noise assessment for restricted hours (1900-0700), it is emphasis that a construction noise permit must be applied in accordance to the Technical Memorandum of NCO for any construction work within the restricted hours period.


 



[1] P. M. Nelson. Transportation Noise Reference Book. 1987.