6.1
Stage 1 of HATS, comprising
the Stonecutters Island Sewage Treatment Works (SCISTW) and the deep tunnels,
was commissioned in late 2001 to bring early improvement to the harbour water
quality. The deep tunnels collect
sewage from Kwai Chung, Tsing Yi, Tseung Kwan O, parts of eastern
6.2 This Project involves the construction and operation of Stage 2A. Construction of the Project (i.e. Stage 2A) is tentatively scheduled to commence in 2009 for commissioning the Stage 2A scheme by 2014.The scope of Stage 2A includes the following:
·
Upgrading of existing preliminary treatment works (PTW) at
North Point, Wan Chai East, Central, Sandy Bay, Cyberport, Wah Fu, Aberdeen and
Ap Lei Chau on Hong Kong Island;
·
Extension of the deep tunnel network to collect and transfer
sewage from the above mentioned PTWs to SCISTW for treatment and disposal;
·
Expansion of the existing CEPT capacity at SCISTW to
meet the demands of both existing and future developments; and
·
Provision of disinfection to all HATS effluent before
discharging into the harbour.
6.3 Based on the technical review of disinfection technologies and option evaluation as well as the technical environmental assessment conducted under the EIA study for “Provision of Disinfection Facilities at Stonecutters Island STW – Investigation (ADF)”, the purchase of sodium hypochlorite solution for chlorination and sodium bisulphite for dechlorination was recommended as the disinfection technology for SCISTW. Based on the current programme, construction of the chlorination plant would commence in April 2008 for commissioning the advance disinfection facilities (ADF) in October 2009. As for the dechlorination plant, construction would commence in September 2008 for completion in September 2009.
6.4
During the ADF stage, use of
the existing effluent culvert as the chlorine contact tank is proposed. At
Stage
6.5 This Section evaluates the potential water quality impacts that are likely to be generated during the construction and operation of Stage 2A. The water quality impacts of Stage 1, Stage 2A and Stage 2B of the HATS have also been taken into consideration in this water quality impact assessment. Appropriate mitigation measures were identified, where necessary, to mitigate the potential water quality impacts.
6.6
To evaluate the potential water
quality impacts from the Project, water sensitive receivers within the North Western,
Western Buffer,
·
Cooling Water Intakes;
·
WSD
·
Fish Culture Zones (FCZ);
·
Beaches;
·
Sites of Special Scientific
Interest (SSSI);
·
·
Seagrass Beds;
·
Artificial Reefs;
·
Corals;
·
Chinese White Dolphins; and
·
Green Turtle Nesting Grounds
6.7 Figure 6.1 shows the locations of the ecological resources and water sensitive receivers.
6.8 During the operational phase, the potential water quality impacts will be mainly related to the treated effluent discharge from the HATS Stage 2A. Key concerns are:
·
Effects on marine water quality
and sediment quality due to the discharge of disinfected CEPT effluent from
SCISTW at different time horizons under normal plant operation.
·
Water quality effects of occasional
overflow of screened (or untreated) effluent at individual PTW during extreme
storm event under normal plant operation.
·
Water quality impacts of emergency
sewage discharges due to the failure of equipment or power supply or as a
result of treatment process failure.
6.9
The water quality parameters
considered for the assessment of water quality impact from the HATS Stage 2A
effluent include pH, temperature, dissolved oxygen (DO), salinity, suspended
solids (SS), biochemical oxygen demand (BOD), nutrients, chlorophyll, E.coli, sedimentation rates,
chlorination by-products (CBP) and toxic chemicals such as metals, total
residual chlorine (TRC) and unionized ammonia etc.
6.10
A comprehensive review and identification of toxic
contaminants of concern (COC) in the HATS effluent and their respective
assessment criteria and detailed assessment of the toxic effects of the
identified COC were conducted under the human health and marine ecological risk
assessment in Section 7 and Section 8.
6.11
No dredging and filling
activity would be anticipated for the tunnel construction. The general construction activities that
will be undertaken for the upgrading works will be primarily land-based. Key water quality issues associated with
land-based construction would include the impacts from site run-off, sewage
from workforce, accidental spillage and discharges of wastewater from various
construction activities.
6.12
Based on the preliminary
engineering design
6.13 Temporary bypass of sewage effluent via seawall or submarine outfalls of SCISTW and individual PTW would be required during the construction stage. The temporary sewage bypass would cause transient increase of pollution level in the receiving marine water.
6.14 Key water quality impacts related to the provision of disinfection facilities at the SCISTW include:
·
The
reduction of faecal bacteria in the effluent after disinfection.
·
The potential generation of
low-level total residual chlorine (TRC) and chlorination by-products (CBP) in
the effluent due to chlorination of the sewage effluent.
·
The potential impact of TRC in the
event of dechlorination plant failure.
·
The potential impact of faecal
pollution in the event of chlorination plant failure.
·
The potential minor oxygen
depletion impact due to addition of dechlorination chemical.
6.15
Total residual chlorine
(TRC) and chlorination by-products (CBP) are major concerns of chlorination.
TRC includes free chlorine residuals such as hypochlorous acid (HOCl) and
dissolved hypochlorite ion (OCl-) after chlorine is added to water, plus
combined chlorine residuals such as chloramines formed by the reaction of free
residuals with ammonia present in the sewage. CBP refer to chlorinated organic
compounds (or total organic halogen) formed by the reaction of chlorine (mainly
free chlorine residuals) with some specific organic compounds such as humic
substances, which generally are not present in any large quantity in CEPT
effluent. CBP consist of a whole range of halogenated organic compounds, and
are generally considered of concern to human health. Examples of CBP formed
during chlorination include trihalomethanes (THM) and haloacetic acids (HAA).
THM are suspected as being carcinogens and are strictly monitored in drinking
water. CBP concentrations may vary
in orders of magnitude during different chlorination processes. Typical concentrations
of THM and HAA in chlorinated drinking water are usually in the range 1-100 mg/l ([1]). Range of concentrations in chlorinated
sewage effluent for specific CBP compounds has been identified under the EIA
study for ADF and is also presented in this EIA report for completeness.
6.16
Water
quality impacts in relation to the chlorination and
dechlorination of the HATS effluent have been quantitatively assessed
by mathematical modelling under the EIA study for the ADF. Details of the
assessment results are presented in the separate EIA report for ADF. Under the ADF study, water quality model
simulations were performed for 30 days (excluding the spin-up time) each under
the typical wet and dry seasons for normal operation scenarios and 15 days
(excluding the spin-up time) each under the typical wet and dry seasons for
emergency situations (due to temporary failure of chlorination or
dechlorination plant) in accordance with the EIA Study Brief for ADF.
6.17
The
EIA Study Brief for this Project (i.e. Stage 2A) requires that the model
simulations shall be performed for at least one complete calendar year under
normal operation scenarios. As such, the water quality impacts in
relation to the normal operation of the disinfection facilities for HATS have
been re-examined under this EIA based on a series of 1-year model simulations
incorporating monthly variations in Pearl River discharges, solar radiation,
water temperature and wind velocity to confirm the findings of the ADF study.
6.18
According
to the EIA Study Brief for this Project, assessment of temporary or emergency
discharges as well as the short-term construction phase impacts may be assessed
by simulating typical spring-neap cycles (at least 15 days) in the dry and wet
seasons. Furthermore, the HATS flow rates adopted in the EIA study for ADF were
more conservative as compared to the latest flow projections adopted in this
EIA. It is considered that the water quality impacts in relation to the
temporary failure of chlorination or dechlorination plant have been fully
quantified and assessed under the ADF study.
6.19 The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) is issued by the EPD under Section 16 of the EIAO. It specifies the assessment method and criteria that need to be followed in the EIA. Reference sections in the EIAO-TM provide the details of the assessment criteria and guidelines that are relevant to the water quality impact assessment, including:
·
Annex 6 Criteria for Evaluating
Water Pollution
·
Annex 14 Guidelines for Assessment
of Water Pollution
6.20
The Water Pollution Control
Ordinance (WPCO) provides the major statutory framework for the protection and
control of water quality in
Table 6.1 Summary of Water
Quality Objectives for North
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0 mg/l |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones,
water gathering ground subzones and other inland waters |
Not less than 4.0 mg/l for 90 % sample |
Marine waters |
|
pH |
To be in the range of 6.5 - 8.5, change due to human activity
not to exceed 0.2 |
Marine waters excepting bathing beach subzones |
To be in the range of 6.5 – 8.5 |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and
water gathering ground subzones |
|
To be in the range of 6.0 –9.0 |
Other inland waters |
|
To be in the range of 6.0 –9.0 for 95% samples |
Bathing beach subzones |
|
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by human
activity |
Marine waters |
Change due to waste discharges not to exceed 20 mg/l of
annual median |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and water
gathering ground subzones |
|
Change due to waste discharges not to exceed 25 mg/l of
annual median |
Inland waters |
|
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021 mg(N)/l as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to
exceed 0.3 mg(N)/l |
|
Annual mean depth-averaged inorganic nitrogen not to exceed
0.5 mg(N)/l |
Marine waters excepting castle peak bay subzone |
|
E.coli |
Not exceed 610 per 100 ml, calculated as the geometric
mean of all samples collected in one calendar year |
Secondary contact recreation subzones |
Should be less than 1 per 100 ml, calculated as the geometric mean of the most recent 5
consecutive samples taken between 7 and 21 days. |
Tuen Mun (A) and Tuen Mun (B) subzones and water gathering
ground subzones |
|
Not exceed 1000 per 100 ml, calculated as the geometric mean of the most recent 5
consecutive samples taken between 7 and 21 days |
Tuen Mun (C) subzone and other inland waters |
|
Not exceed 180 per 100 ml, calculated as the geometric
mean of all samples collected from March to October inclusive. |
Bathing beach subzones |
|
Colour |
Change due to waste discharges not to exceed 30 Hazen
units |
Tuen Mun (A) and Tuen Mun (B) subzones and water gathering
ground subzones |
Change due to waste discharges not to exceed 50 Hazen
units |
Tuen Mun (C) subzone and other inland waters |
|
5-Day biochemical oxygen demand (BOD5) |
Change due to waste discharges not to exceed 3 mg/l |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and
water gathering ground subzones |
Change due to waste discharges not to exceed 5 mg/l |
Inland waters |
|
Chemical oxygen demand (COD) |
Change due to waste discharges not to exceed 15 mg/l |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) subzones and
water gathering ground subzones |
Change due to waste discharges not to exceed 30 mg/l |
Inland waters |
|
Toxins |
Should not cause a risk to any beneficial uses of the
aquatic environment |
Whole zone |
Waste discharge shall not cause the toxins in water significant
to produce toxic carcinogenic, mutagenic or teratogenic effects in humans,
fish or any other aquatic organisms. |
Whole zone |
|
Phenol |
Quantities shall not sufficient to produce a specific
odour or more than 0.05 mg/l as C6 H5OH |
Bathing beach subzones |
Turbidity |
Shall not reduce light transmission substantially from the
normal level |
Bathing beach subzones |
Source: Statement of Water Quality
Objectives (North Western Water Control Zone).
Table 6.2 Summary of Water Quality Objectives for Western Buffer WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0 mg/l for 90% of samples |
Marine waters excepting fish culture subzones |
Not less than 5.0 mg/l for 90% of samples |
Fish culture subzones |
|
Not less than 4.0 mg/l |
Water gathering ground subzone and other Inland waters |
|
5-Day biochemical oxygen demand (BOD5) |
Change due to waste discharges not to exceed 3 mg/l |
Water gathering ground subzones |
Change due to waste discharges not to exceed 5 mg/l |
Inland waters |
|
Chemical oxygen demand (COD) |
Change due to waste discharges not to exceed 15 mg/l |
Water gathering ground subzones |
Change due to waste discharges not to exceed 30 mg/l |
Inland waters |
|
pH |
To be in the range of 6.5 – 8.5, change due to waste
discharges not to exceed 0.2 |
Marine waters |
To be in the range of 6.5 – 8.5 |
Water gathering ground subzones |
|
To be in the range of 6.0 – 9.0 |
Inland waters |
|
Salinity |
Change due to waste discharges not to exceed 10% of
ambient |
Whole zone |
Temperature |
Change due to waste discharges not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by waste
discharges and shall not affect aquatic communities |
Marine waters |
Change due to waste discharges not to exceed 20 mg/l of
annual median |
Water gathering ground subzones |
|
Change due to waste discharges not to exceed 25 mg/l of
annual median |
Inland waters |
|
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021 mg(N)/l as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to
exceed 0.4 mg(N)/l |
Marine waters |
Toxic substances |
Should not attain such levels as to produce significant
toxic effects in humans, fish or any other aquatic organisms |
Whole zone |
Waste discharges should not cause a risk to any beneficial
use of the aquatic environment |
Whole zone |
|
E.coli |
Not exceed 610 per 100 ml, calculated as the geometric
mean of all samples collected in one calendar year |
Secondary contact recreation subzones and fish culture
subzones |
Not exceed 180 per 100 ml, calculated as the geometric
mean of all samples collected from March to October inclusive in 1 calendar
year. Samples should be taken at least 3 times in 1 calendar month at
intervals of between 3 and 14 days |
Bathing beach subzones |
|
Less than 1 per 100 ml, calculated as the geometric mean
of the most recent 5 consecutive samples taken at intervals of between 7 and
21 days |
Water gathering ground subzones |
|
Not exceed 1000 per 100 ml, calculated as the geometric
mean of the most recent 5 consecutive samples taken at intervals of between 7
and 21 days |
Inland waters |
|
Colour |
Change due to waste discharges not to exceed 30 Hazen
units |
Water gathering round |
Change due to waste discharges not to exceed 50 Hazen
units |
Inland waters |
|
Turbidity |
Shall not reduce light transmission substantially from the
normal level |
Bathing beach subzones |
Source: Statement of Water Quality
Objectives (Western Buffer Water Control Zone).
Table 6.3 Summary
of Water Quality Objectives for
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
E coli |
Not to exceed 1000 per 100 mL, calculated as the geometric
mean of the most recent 5 consecutive samples taken at intervals between 7
and 21 days |
Inland waters |
Dissolved oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0 mg/l for 90% of samples |
Marine waters |
DO |
Not less than 4.0 mg/l |
Inland waters |
pH |
To be in the range of 6.5 - 8.5, change due to human
activity not to exceed 0.2 |
Marine waters |
Not to exceed the range of 6.0 - 9.0 due to human activity |
Inland waters |
|
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by human
activity |
Marine waters |
Annual median not to exceed 25 mg/l due to human activity |
Inland waters |
|
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021 mg(N)/l as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to
exceed 0.4 mg(N)/l |
Marine waters |
5-Day biochemical oxygen demand (BOD5) |
Not to exceed 5 mg/l |
Inland waters |
Chemical Oxygen Demand (COD) |
Not to exceed 30 mg/l |
Inland waters |
Toxic substances |
Should not attain such levels as to produce significant
toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any
other aquatic organisms. |
Whole zone |
Human activity should not cause a risk to any beneficial
use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality
Objectives (
Table 6.4 Summary of Water Quality Objectives for Eastern Buffer WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0 mg/l for 90% of samples |
Marine waters excepting fish culture subzones |
Not less than 5.0 mg/l for 90% of samples |
Fish culture subzones |
|
Not less than 4.0 mg/l |
Water gathering ground subzone and other Inland waters |
|
5-Bay biochemical oxygen demand (BOD5) |
Change due to waste discharges not to exceed 3 mg/l |
Water gathering ground subzones |
Change due to waste discharges not to exceed 5 mg/l |
Inland waters |
|
Chemical oxygen demand (COD) |
Change due to waste discharges not to exceed 15 mg/l |
Water gathering ground subzones |
Change due to waste discharges not to exceed 30 mg/l |
Inland waters |
|
pH |
To be in the range of 6.5 – 8.5, change due to waste
discharges not to exceed 0.2 |
Marine waters |
To be in the range of 6.5 – 8.5 |
Water gathering ground subzones |
|
To be in the range of 6.0 – 9.0 |
Inland waters |
|
Salinity |
Change due to waste discharges not to exceed 10% of
ambient |
Whole zone |
Temperature |
Change due to waste discharges not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by waste
discharges and shall not affect aquatic communities |
Marine waters |
Change due to waste discharges not to exceed 20 mg/l of
annual median |
Water gathering ground subzones |
|
Change due to waste discharges not to exceed 25 mg/l of
annual median |
Inland waters |
|
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021 mg(N)/l as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to
exceed 0.4 mg(N)/l |
Marine waters |
Dangerous substances |
Should not attain such levels as to produce significant
toxic effects in humans, fish or any other aquatic organisms |
Whole zone |
Waste discharges should not cause a risk to any beneficial
use of the aquatic environment |
Whole zone |
|
E.coli |
Not exceed 610 per 100 ml, calculated as the geometric
mean of all samples collected in one calendar year |
Fish culture subzones |
Less than 1 per 100 ml, calculated as the geometric mean of
the most recent 5 consecutive samples taken at intervals of between 7 and 21
days |
Water gathering ground subzones |
|
Not exceed 1000 per 100 ml, calculated as the geometric
mean of the most recent 5 consecutive samples taken at intervals of between 7
and 21 days |
Inland waters |
|
Colour |
Change due to waste discharges not to exceed 30 Hazen
units |
Water gathering ground |
Change due to waste discharges not to exceed 50 Hazen
units |
Inland waters |
Source: Statement of Water Quality
Objectives (Eastern Buffer Water Control Zone).
Table 6.5 Summary of Water Quality Objectives for Junk Bay WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0 mg/l for 90% of samples |
Marine waters excepting fish culture subzones |
Not less than 5.0 mg/l for 90% of samples |
Fish culture subzones |
|
Not less than 4.0 mg/l |
Inland waters |
|
5-Bay biochemical oxygen demand (BOD5) |
Change due to waste discharges not to exceed 5 mg/l |
Inland waters |
Chemical oxygen demand (COD) |
Change due to waste discharges not to exceed 30 mg/l |
Inland waters |
pH |
To be in the range of 6.5 - 8.5, change due to waste
discharges not to exceed 0.2 |
Marine waters |
To be in the range of 6.0 –9.0 |
Inland waters |
|
Salinity |
Change due to waste discharges not to exceed 10% of
ambient |
Whole zone |
Temperature |
Change due to waste discharges not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by waste
discharges and shall not affect aquatic communities |
Marine waters |
Change due to waste discharges not to exceed 25 mg/l of
annual median |
Inland waters |
|
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021 mg(N)/l as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to
exceed 0.3 mg(N)/l |
Marine waters |
Dangerous substances |
Should not attain such levels as to produce significant
toxic effects in humans, fish or any other aquatic organisms |
Whole zone |
Waste discharges should not cause a risk to any beneficial
use of the aquatic environment |
Whole zone |
|
E.coli |
Not exceed 610 per 100 ml, calculated as the geometric
mean of all samples collected in one calendar year |
Secondary contact recreation subzones and fish culture
subzones |
Not exceed 1000 per 100 ml, calculated as the geometric
mean of the most recent 5 consecutive samples taken at intervals of between 7
and 21 days |
Inland waters |
|
Colour |
Change due to waste discharges not to exceed 50 Hazen
units |
Inland waters |
Source: Statement of Water Quality
Objectives (Junk Bay Water Control Zone).
Table
6.6 Summary
of Water Quality Objectives for
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2 m of the seabed |
Not less than 2.0 mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0 mg/l for 90 % sample |
Marine waters excepting fish culture subzones |
Not less than 5.0 mg/l for 90% of samples |
Fish culture subzones |
|
Not less than 4.0 mg/l |
Inland waters |
|
pH |
To be in the range of 6.5 - 8.5, change due to human
activity not to exceed 0.2 |
Marine waters excepting bathing beach subzones; Mui Wo
(A), Mui Wo (B), Mui Wo (C), Mui Wo (E) and Mui Wo (F) subzones |
To be in the range of 6.0 – 9.0 |
Mui Wo (D) sub-zone and other inland waters. |
|
To be in the range of 6.0 –9.0 for 95% of samples, change
due to human activity not to exceed 0.5 |
Bathing beach subzones |
|
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by human
activity |
Marine waters |
Change due to waste discharges not to exceed 20 mg/l of
annual median |
Mui Wo (A), Mui Wo (B), Mui Wo (C), Mui Wo (E) and Mui Wo
(F) subzones |
|
Change due to waste discharges not to exceed 25 mg/l of
annual median |
Mui Wo (D) subzone and other inland waters |
|
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021 mg(N)/l as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to
exceed 0.1 mg(N)/l |
Marine waters |
E.coli |
Not exceed 610 per 100 ml, calculated as the geometric mean
of all samples collected in one calendar year |
Secondary contact recreation subzones and fish culture subzones |
Not exceed 180 per 100 ml, calculated as the geometric
mean of all samples collected from March to October inclusive in 1 calendar
year. Samples should be taken at least 3 times in 1 calendar month at
intervals of between 3 and 14 days. |
Bathing beach subzones |
|
5-Day biochemical oxygen demand (BOD5) |
Change due to waste discharges not to exceed 5 mg/l |
Inland waters |
Chemical oxygen demand (COD) |
Change due to waste discharges not to exceed 30 mg/l |
Inland waters |
Dangerous substances |
Should not attain such levels as to produce significant
toxic effects in humans, fish or any other aquatic organisms |
Whole zone |
Waste discharges should not cause a risk to any beneficial
use of the aquatic environment |
Whole zone |
Source: Statement
of Water Quality Objectives (Southern Water Control Zone).
6.21 Besides the WQO set under the WPCO, the WSD has specified a set of objectives for water quality at flushing water intakes as listed in Table 6.7.
Table 6.7 WSD
Standards at
Parameter (in mg/l unless otherwise
stated) |
WSD Target Limit |
Colour (Hazen Unit) |
< 20 |
Turbidity (NTU) |
< 10 |
Threshold Odour Number (odour unit) |
< 100 |
Ammoniacal Nitrogen |
< 1 |
Suspended Solids |
< 10 |
Dissolved Oxygen |
> 2 |
Biochemical Oxygen Demand |
< 10 |
Synthetic Detergents |
< 5 |
E.coli (no. per 100 ml) |
< 20000 |
6.22 A practice note for professional persons has been issued by the EPD to provide guidelines for handling and disposal of construction site discharges. The ProPECC PN 1/94 “Construction Site Drainage” provides good practice guidelines for dealing with ten types of discharge from a construction site. These include surface runoff, groundwater, boring and drilling water, bentonite slurry, water for testing and sterilisation of water retaining structures and water pipes, wastewater from building construction, acid cleaning, etching and pickling wastewater, and wastewater from site facilities. Practices given in the ProPECC PN 1/94 should be followed as far as possible during construction to minimize the water quality impact due to construction site drainage.
6.23 Discharges of effluents are subject to control under the WPCO. The Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS) gives guidance on permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters). The limits control the physical, chemical and microbial quality of effluent. Any effluent discharge from the proposed construction activities must comply with the standards for effluent discharged into the foul sewers, inshore waters and marine waters of the Victoria Harbour WCZ and Western Buffer WCZ, as given in the TM-DSS.
6.24 Potential impacts on benthic organisms, including corals, may arise through excessive sediment deposition. The magnitude of impacts on marine ecological sensitive receivers was assessed based on the predicted sedimentation rate. According to Pastorok and Bilyard ([2]) and Hawker and Connell ([3]), a sedimentation rate higher than 0.1 kg/m2/day would introduce moderate to severe impact upon corals. This criterion has been adopted for protecting the corals in Hong Kong under other approved EIAs such as Tai Po Sewage Treatment Works Stage 5 EIA ([4]), Further Development of Tseung Kwan O Feasibility Study EIA, Wan Chai Reclamation Phase II EIA, Eastern Waters MBA Study ([5]), West Po Toi MBA Study ([6]) and Tai Po Gas Pipeline Study ([7]). This sedimentation rate was used as the assessment criterion to guard against unacceptable impacts on marine ecological sensitive receivers.
6.25
The
potential impacts on corals were also assessed with reference to the WQO of 30%
from the ambient levels. However, in Eastern Buffer,
6.26 In addition to the statutory WQO stipulated under the WPCO, a set of water quality criteria (WQC) established under the “Environmental and Engineering Feasibility Assessment Studies in relation to the Way Forward of the HATS (EEFS)” was used as reference guidelines to assess the water quality impacts as per the requirement in Section 3.4.3.5 (iv) of the EIA Study Brief.
6.27
The HATS is an overall sewage
collection and treatment scheme for areas on both sides of
6.28 In 2004, the Government of the Hong Kong SAR completed trials and studies on environmental impacts and engineering feasibility to assist in deciding the best way forward for the remaining stages of HATS. Detailed marine water quality, ecological and fisheries assessments were performed as part of the EEFS with the objective of assessing the potential impacts of different treatment and disposal schemes proposed for the remaining stages of HATS and the associated construction activities. The recommended option for HATS Stage 2 is to convey all sewage from the harbour area to SCISTW for centralized treatment. The EEFS recommended that biological treatment plus disinfection should be provided for the HATS on a long-term basis. The marine water quality, ecological and fisheries assessment conducted as part of the EEFS followed the guidelines set forth in the EIAO-TM. The potential water quality impacts were quantitatively assessed using various WQC outlined for the EEFS with a further qualitative assessment based on the collective professional opinion of a team of local and international experts in marine sciences and water quality management.
6.29 Setting of WQC has been recognized from the start of the EEFS as a key to assessing the acceptability and performance of different HATS options. In support of criteria setting, an extensive public consultation exercise on the proposed WQC for HATS was conducted in 2002 as part of the EEFS. These WQC were based on the statutory WQO stipulated under the WPCO, originally developed in the late 1980’s, and further refined by the consultant of the EEFS using the results of the Environmental Impact Assessment of the Strategic Sewage Disposal Scheme (SSDS EIA) and other recently completed studies. The set of HATS specific WQC, developed as a part of the EEFS, has integrated the concerns of various interested stakeholders and the general public through a presentation and briefing with the Advisory Council on the Environment and the Monitoring Group for HATS, public view-sharing workshops and receipt of public comments.
6.30 The findings of this consultation exercise and a full set of the proposed final WQC are documented in the “Report on Community Consultation for the Proposed Water Quality Criteria (October 2002)” prepared under the EEFS.
6.31 The WQC as shown in Table 6.8 and Table 6.9 were used as reference guidelines for far field and near field impact assessment respectively. The far field water quality impact assessment and far field modelling performed under this EIA covered the North Western, Western Buffer, Victoria Harbour, Eastern Buffer, Junk Bay and Southern WCZ as well as the adjacent outer water to take into account all the major pollution sources (including the Pearl River) that may have a bearing on the environmental acceptability of the Project as required by the EIA Study Brief. The near field impact assessment was conducted by mathematical modelling to simulate the characteristics of the sewage plume in the vicinity of the submarine outfall to determine the zone of initial dilution (ZID), plume dimensions, rise height, merging and trapping in various flow and ambient conditions.
6.32
Relevant WQC were derived under
the EEFS for Western Buffer, Eastern Buffer,
Table
6.8 Reference
Marine Water Quality Criteria for Far Field Water Quality Assessment
Parameter |
Value |
Type
/ Period |
Applicable
Zones / Uses (1) |
E.coli |
≤
180/100ml |
Geometric mean for
bathing season (March to October) |
Bathing waters |
≤
610/100ml |
Annual
geometric mean |
Secondary
contact recreation zones and mariculture zones |
|
≤
20,000/100ml |
≥ 90%
of occasions |
Sea
water intakes for flushing and industrial use |
|
Dissolved
oxygen (DO) |
≥ 4 mg/l (water column average) |
≥ 90%
of occasions |
Western
Buffer, Eastern Buffer, |
≥
2 mg/l |
at
all times |
All
WCZ (except mariculture zones) |
|
≥
5 mg/l (water column average) |
Monthly
average |
|
|
≥
5 mg/l (water column average) |
≥ 90%
of occasions |
Mariculture
zones only |
|
≥
2 mg/l (bottom DO within 2 m from the seabed) |
≥ 90%
of occasions |
Mariculture
zones only |
|
Depth-averaged
total inorganic nitrogen (TIN) |
≤
0.2 mg(N)/l |
Annual
mean |
|
≤
0.4 mg(N)/l |
Annual
mean |
Western
Buffer, Eastern Buffer and Victoria Harbour WCZ (except fish spawning ground)
(Figure 6.2) |
|
≤
0.3 mg(N)/l |
Annual
mean |
Junk
Bay WCZ (Figure 6.2) |
|
≤
0.1 mg(N)/l |
Annual
mean |
Semi-enclosed
bays (Figure 6.3) |
|
Depth-averaged
Unionized Ammonia (UIA) |
≤
0.021 mg(N)/l |
Annual
mean |
All
WCZ |
Depth-averaged
total inorganic phosphorus (PO4) |
≤
0.02 mg(P)/l |
Annual
mean |
|
≤
0.04 mg(P)/l |
Annual
mean |
Western
Buffer, Eastern Buffer and Victoria Harbour WCZ (except fish spawning ground)
(Figure 6.2) |
|
≤
0.03 mg(P)/l |
Annual
mean |
Junk
Bay WCZ (Figure 6.2) |
|
≤
0.01 mg(P)/l |
Annual
mean |
Semi-enclosed
bays (Figure 6.3) |
|
Total
residual chlorine (TRC) |
≤
0.008 mg/l |
Daily maximum |
All
WCZ |
Chronic
toxicity |
≤
one chronic toxicity unit (TUc), (derived from NOEC values based on whole effluent
toxicity tests) (2) |
4-day
average chronic toxicity exposure |
All
WCZ |
(Source: EEFS
Report on Community Consultation for the Proposed Water Quality Criteria)
(1) EEFS did not derive WQC for the North Western
WCZ.
(2) USEPA
Technical Support Document for Water Quality-Based Toxics Control (March 1991),
from which one chronic Toxicity Unit (TUc) is defined TUc = 100/NOEC, where
NOEC = % of effluent which gives no observed effect on the most sensitive of
the range of species tested.
Table 6.9 Reference
Marine Water Quality Criteria for Near
Field Water Quality Assessment
Parameter |
Value |
Type / Period |
Applicable Zones / Uses |
Unionized ammonia (UIA) |
≤ 0.021 mg/l (as N) (2) |
Annual average |
At edge of ZID (1) |
≤ 0.035 mg/l (as NH3)
(3) |
4-day average |
At edge of ZID (1) |
|
≤ 0.233 mg/l (as NH3)
(3) |
1-hour average |
At edge of ZID (1) |
|
pH |
6.5 – 8.5, and change ≤ 0.2 |
≥ 90% of occasions |
At edge of ZID (1) |
Temperature |
change ≤ 2 oC |
≥ 90% of occasions |
At edge of ZID (1) |
Sulphide |
≤
0.02 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Cyanide |
≤
0.005 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Total residual chlorine
(TRC) |
≤ 0.013 mg/l |
Daily Maximum |
At edge of ZID (1) |
Surfactants |
≤
0.03 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Copper |
≤
0.005 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Nickel |
≤
0.005 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Total chromium |
≤
0.05 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Zinc |
≤
0.02 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Mercury |
≤
0.00021 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Arsenic |
≤
0.02 mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Phenol |
≤ 0.005
mg/l |
≥ 90% of occasions |
At edge of ZID (1) |
Acute Toxicity |
0.3 acute toxicity units (TUa) (derived from
LC50 values based on whole effluent toxicity tests) (4) |
One hour average condition not to exceed this
value |
At edge of ZID (1) |
(Source: EEFS
Report on Community Consultation for the Proposed Water Quality Criteria)
(1) For a surface plume, initial dilution is
defined as the dilution obtained at the centre line of the plume when the
sewage reaches the surface. For a trapped
plume, initial dilution is defined as the dilution obtained at the center line
of the plume where the plume reaches the maximum rise height when the vertical
momentum / buoyancy of the plume becomes zero.
(2)
The WQC for annual averaged UIA was derived with reference to the WQO under
WPCO which is expressed as N.
(3)
The WQC for 1-hour and 4-day averaged UIA was derived with reference to the
USEPA which is expressed as NH3.
(4) USEPA
Technical Support Document for Water Quality-Based Toxics Control (March 1991),
from which one acute Toxicity Unit (TUa) is defined as TUa = 100/LC50, where
LC50 = % of effluent which gives 50% survival of the most sensitive of the
range of species tested.
6.33 The chronic and acute toxicity criteria as shown in Table 6.8 and Table 6.9 respectively were used to assess the toxicity of the sewage effluent with reference to the results of the whole effluent toxicity test (WETT). Details of the WETT results are given in Table 6.33 to Table 6.36.
6.34 Table 6.10 compares the WQC derived under the EEFS (in Table 6.8 and Table 6.9) with the statutory requirements stipulated under the WPCO (in Table 6.1 to Table 6.6) as well as the water quality criteria specified by WSD (in Table 6.7). It should be noted that some parameters considered under the EEFS for far field water quality assessment as listed in Table 6.8, including PO4, TRC and chronic toxicity, are not controlled under the WPCO. In addition, most of the parameters considered under the EEFS for near field water quality assessment (in Table 6.9) are not controlled under the WPCO except for pH and temperature.
Table 6.10 Comparison
of Marine Water Quality Criteria for Water
Quality Assessment
Applicable zones/uses (1) |
Parameters |
EEFS WQC |
WPCO WQO |
WSD Criteria (2) |
||||
Value |
Type/ Period |
Value |
Type/ Period |
Value |
Type/ Period |
|||
Far Field Water Quality Criteria |
||||||||
Bathing waters |
E.coli |
≤ 180/ 100ml |
Geometric mean for the period from March to October |
≤ 180/ 100ml |
Geometric mean for the period from March to October |
Not applicable |
Not applicable |
|
Secondary
contact zones |
E.coli |
≤ 610/
100ml |
Annual
Geometric mean |
≤ 610/
100ml |
Annual
geometric mean |
Not
applicable |
Not
applicable |
|
WSD
flushing water intakes |
E.coli |
≤ 20,000/ 100ml |
≥ 90% of
occasions |
Not
specified |
Not
specified |
≤
20,000/ 100ml |
at all
times |
|
Seawater
intakes for industrial use |
E.coli |
≤
20,000/ 100ml |
≥ 90% of
occasions |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
|
Mariculture
zones |
E.coli |
≤ 610/
100ml |
Geometric
mean |
≤ 610/
100ml |
Annual
geometric mean |
Not
applicable |
Not
applicable |
|
DO |
Depth- averaged |
≥ 5 mg/l |
≥90% of
occasions |
≥ 5 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not
applicable |
|
within
2m from the seabed |
≥ 2 mg/l |
≥ 90% of
occasions |
≥ 2 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not applicable |
||
Semi-enclosed
bays |
TIN |
≤0.1
mg/l (as N) |
Annual
mean |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
|
PO4 |
≤ 0.01
mg/l (as P) |
Annual
mean |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
||
Western
Buffer, Eastern Buffer, and Victoria Harbour WCZ (except fish spawning
ground) |
DO |
Depth- averaged |
≥ 4 mg/l |
≥ 90% of
occasions |
≥ 4 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not
applicable |
within
2m from the seabed |
Not specified |
Not specified |
≥ 2 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not
applicable |
||
TIN |
≤ 0.4
mg/l (as N) |
Annual
mean |
≤ 0.4
mg/l |
Annual
mean |
Not
applicable |
Not
applicable |
||
PO4 |
≤ 0.04
mg/l (as P) |
Annual
mean |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
||
|
DO |
Depth- averaged |
≥ 5 mg/l |
Monthly
average |
≥ 4 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not
applicable |
within
2m from the seabed |
Not specified |
Not specified |
≥ 2 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not
applicable |
||
TIN |
≤ 0.2
mg/l (as N) |
Annual
mean |
≤ 0.1
mg/l |
Annual
mean |
Not
applicable |
Not
applicable |
||
PO4 |
≤ 0.02
mg/l (as P) |
Annual
mean |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
||
Junk Bay
WCZ |
DO |
Depth-averaged |
≥ 4 mg/l |
≥ 90% of
occasions |
≥ 4 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not
applicable |
within
2m from the seabed |
Not specified |
Not specified |
≥ 2 mg/l |
≥ 90% of
occasions |
Not
applicable |
Not
applicable |
||
TIN |
≤ 0.3
mg/l (as N) |
Annual
mean |
≤ 0.3
mg/l |
Annual
mean |
Not
applicable |
Not
applicable |
||
PO4 |
≤ 0.03
mg/l (as P) |
Annual
mean |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
||
All WCZ |
DO at
any depth |
≥ 2 mg/l |
at all
times |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
|
All WCZ |
UIA |
≤
0.021 mg/l (as N) |
Annual
mean |
≤
0.021 mg/l |
Annual
mean |
Not
applicable |
Not
applicable |
|
All WCZ |
TRC |
≤
0.008 mg/l |
Daily
maximum |
Not specified |
Not specified |
Not
applicable |
Not
applicable |
|
Near
Field Water Quality Criteria |
||||||||
At edge
of Initial dilution zone |
pH (3) |
6.5 –
8.5, and
change ≤ 0.2 |
≥ 90% of
occasions |
6.5 –
8.5, and
change ≤ 0.2 |
at all
times |
Not
applicable |
Not
applicable |
|
Temperature
(3) |
change ≤
2oC |
≥ 90% of
occasions |
change ≤
2oC |
at all
times |
Not
applicable |
Not
applicable |
(1) EEFS
did not derive WQC for the North Western WCZ.
(2) The
WSD criteria are applicable to the WSD flushing water intakes only.
(3) The
rest of the parameters listed in Table
6.9 are not presented for comparison as they are not controlled under the
WPCO and the WSD criteria.
6.35 The key differences between the WQC and the statutory requirements for far field water quality assessment are listed below:
·
The TIN criterion derived under
the EEFS for
·
The DO criterion derived under
the EEFS for
· A new DO requirement was derived under the EEFS that the minimum DO level at any location of the water control zone should not be less than 2 mg/l at all the times which is more stringent than the WPCO requirement that only the bottom DO (within 2 m from the seabed) should meet the value of 2 mg/l for 90% of occasions.
· New requirements were derived under the EEFS for TRC and PO4.
6.36 Moreover, additional requirements for UIA, metals, sulphide, TRC, surfactants and phenol etc. were derived under the EEFS for near field water quality assessment (Table 6.9). In particular, the UIA level should not be more than 0.035 mg/l and 0.233 mg/l for 4-day average and 1-hour average respectively based on the WQC. The acceptability of the water quality impacts have also been assessed based on both the WQO stipulated under the WPCO and the WQC established under the EEFS.
6.37 Chlorination is proposed as the disinfection technology for the HATS which would potentially lead to the formation of total residual chlorine (TRC) and chlorination by-products (CBP) in the effluent. Dechlorination will applied to minimize the discharge of TRC into the marine environment.
6.38
The proposed assessment
criteria for TRC are covered by the WQC derived under the EEFS. Based on a CBP selection exercise
conducted under the ADF study, 34 CBP compounds (as listed in Table 6.11 below) were identified for
impact assessment. The CBP
selection process is described in Appendix
7.1 of Section 7 under the human health risk assessment. Water quality
criteria/standards of
·
Rule 1: Criteria from
· Rule 2: Criteria/standards for protection of marine water/saltwater biota were preferred to that of freshwater or that without clear specification (e.g. protection of aquatic environment)
· Rule 3: Chronic criteria/standards specified with averaging time period were preferred and adopted whenever possible.
· Rule 4: National criteria/standards were preferred to local criteria/standards
· Rule 5: If more than one criteria/standards for the same chemical of concern (COC) satisfied the above rules, then the most stringent criterion/standard was adopted to provide conservatism
6.39 The relevant CBP criteria/standards reviewed are provided in Appendix 8.4 of Section 8 under the ecological risk assessment. A summary of the adopted values are given in Table 6.11.
Table 6.11 Marine Water Quality Criteria for CBP
CBP |
Water Quality Criteria (µg/l) |
Bromodichloromethane |
|
Bromoform |
|
Chloroform |
12b (marine water, annual
avg.) |
Dibromochloromethane |
|
Bromoacetic acid |
See Note 1 |
Chloroacetic acid |
See Note 1 |
Dibromoacetic acid |
See Note 1 |
Dichloroacetic acid |
See Note 1 |
Trichloroacetic acid |
See Note 1 |
Methylene chloride |
|
Carbon tetrachloride |
12 b (marine, annual avg.) |
Chlorobenzene |
|
1,1-dichloroethane |
See Note 1 |
1,2-dichloroethane |
10 b (marine, annual avg.) |
1,1-dichloroethylene |
|
1,2-dichloropropane |
See Note 1 |
Tetrachloroethylene |
|
1,1,1-trichloroethane |
100 b (marine annual avg.) |
1,1,2-trichloroethane |
100 b (marine annual avg.) |
Trichloroethylene |
10 b (marine annual avg.) |
2-chlorophenol |
50 b (marine annual avg.) |
2,4-dichlorophenol |
20 b (marine annual avg.) |
p-chloro-m-cresol |
40 b (marine annual avg.) |
Pentachlorophenol |
2 b (marine annual avg.) |
2,4,6-trichlorophenol |
See Note 1 |
Bis(2-chloroethoxy)methane |
See Note 1 |
1,4-dichlorobenzene |
See Note 1 |
Hexachlorobenzene |
0.03 b (marine, annual avg.) |
Hexachlorocyclopentadiene |
See Note 1 |
Hexachloroethane |
See Note 1 |
1,2,4-trichlorobenzene |
|
Alpha-BHC |
See Note 1 |
Beta-BHC |
|
Gamma-BHC |
|
Notes:
1 No criteria/standard was found from literature
review.
a USEPA. www.epa.gov/waterscience/standards/states
b Cole
S.,
c The Canadian
Council of Ministers of the Environment (2005).
d USEPA (2004).
6.40 Environment, Transport and Works Bureau (ETWB) Technical Circular Works (TCW) No. 34/2002 “Management of dredged/excavated sediment” sets out the procedure for seeking approval to dredge / excavate sediment and the management framework for marine disposal of dredged / excavated sediment. This Technical Circular outlines the requirements to be followed in assessing and classifying the sediment. Sediments are categorized with reference to the Lower Chemical Exceedance Level (LCEL) and Upper Chemical Exceedance Level (UCEL), as follows:
Category L Sediment with all contaminant levels not
exceeding the LCEL. The material
must be dredged, transported and disposed of in a manner that minimizes the
loss of contaminants either into solution or by suspension.
Category M Sediment with any one or more contaminant levels
exceeding the LCEL and none exceeding the UCEL. The material must be dredged and
transported with care, and must be effectively isolated from the environment
upon final disposal unless appropriate biological tests demonstrate that the
material will not adversely affect the marine environment.
Category H Sediment with any one or more contaminant
levels exceeding the UCEL. The
material must be dredged and transported with great care, and must be
effectively isolated from the environment upon final disposal.
6.41
The
sediment quality criteria for the classification of sediment are presented in Table 6.12.
Table 6.12 Sediment Quality Criteria for the Classification of Sediment
Contaminants |
LCEL |
UCEL |
Heavy
Metal (mg/kg dry weight) |
||
Cadmium
(Cd) |
1.5 |
4 |
Chromium
(Cr) |
80 |
160 |
Copper
(Cu) |
65 |
110 |
Mercury
(Hg) |
0.5 |
1 |
Nickel
(Ni) |
40 |
40 |
Lead
(Pb) |
75 |
110 |
Silver
(Ag) |
1 |
2 |
Zinc
(Zn) |
200 |
270 |
Metalloid
(mg/kg dry weight) |
||
Arsenic |
12 |
42 |
Organic-PAHs
(µg/kg dry weight) |
||
PAHs
(Low Molecular Weight) |
550 |
3160 |
PAHs
(High Molecular Weight) |
1700 |
9600 |
Organic-non-PAHs
(µg/kg dry weight) |
||
Total
PCBs |
23 |
180 |
Source: Appendix A of ETWB TCW No. 34/2002 Management of Dredged
/ Excavated Sediment
Note: LCEL – Lower Chemical
Exceedance Level
UCEL
– Upper Chemical Exceedance Level
6.42
The
marine water quality monitoring data
routinely collected by EPD were used to establish the baseline
condition. Marine
water quality monitoring is conducted by EPD on a monthly basis. Water samples
are taken at three water depths, namely,
6.43
As the HATS Stage I was
commissioned in late 2001, the data shown in Table 6.13 to Table 6.17
represent the situation after the commissioning of HATS Stage I. The relevant WQO and WQC are included in
Table 6.13 to Table 6.17 for comparison.
It should be noted that WQO for E.coli
is only applicable to stations SM10 and SM11 because only these two selected
stations are located in secondary contact recreation subzones. Descriptions of
the baseline conditions for individual WCZ provided in the subsequent sections
are extracted from the EPD’s report “Marine Water Quality Monitoring in Hong Kong
2006” issued in 2007 which contains the latest information published by EPD on
marine water quality at the moment of preparing this EIA report.
6.44
Due to the effect of the
6.45
Over the years that the EPD has
monitored this WCZ, it has recorded long-term increases in ammonia nitrogen and
TIN at its stations along the
6.46
The levels of E.coli at stations NM1,
NM2, NM3 and NM5 located nearer the local effluent discharges (from SCISTW,
Pillar Point and San Wai Sewage Treatment Works) were generally higher compared
with other stations. Except for the
two western-most stations (nearest to the
6.47
The Central Waters refers to
the
6.48
Commissioning of HATS Stage 1
in late 2001 has brought large and sustained improvements to the water quality
of the Central Waters, especially that of the eastern
6.49 However, water quality improvements were less noticeable in the western harbour area which was still subject to the sewage discharges from local PTW (Central, Wan Chai West and Wan Chai East). Because the Stage 1 effluent has not been disinfected, E.coli levels rose in the vicinity of the SCISTW outfall. As a result, the western harbour (Western Buffer WCZ and northern part of the Southern WCZ), including the water around Tsing Yi and the Tsuen Wan beaches, has experienced increased E.coli counts after commissioning of HATS Stage 1.
6.50
In 2006, the marked water
quality improvements in eastern
6.51
The water quality in Western Buffer WCZ was
largely stable in 2006 as compared to that in 2005 except that there were some
decreases of DO at the western-most station (WM4) causing a non-compliance with
the WQO for DO at this station.
This was due to the lower DO level at the western-most station closest
to the
6.52
The
water quality at
6.53
The Southern Waters consist of
one large WCZ, the Southern WCZ, which covers an area located to the south of
6.54
In terms of WQO compliance, as
the TIN levels at most stations in the WCZ were relatively high, especially in
the summer, they exceeded the WQO for this parameter. In the 1990s, the WQO
compliance rate for TIN was consistently below 20%, and even in 2006 the only
two stations (namely SM1 and SM19 as shown in Figure
6.1) that complied with the WQO were situated in the far eastern side
of the WCZ. When compared to the
less stringent WQC for TIN, about half of the stations still failed to comply
with the TIN standard. Similar TIN levels have been recorded since 1991. In
2006, full compliance with WQO (for DO and UIA) and WQC (for DO, UIA and PO4)
was achieved in the
6.55
E.coli levels were generally low and stable across the WCZ. However, in
some places the bacteriological water quality was affected by coastal sewage
discharges. For example, long-term increases in E.coli levels were recorded at stations (SM7 and SM9) near the
discharge from the SCISTW, in connection with the implementation of HATS Stage
1. Only four stations (SM7, SM9, SM10 and SM11) closest
to the SCISTW outfall were selected for presentation in Table 6.17.
Table 6.13 Baseline
Water Quality Condition for North
Parameter |
Lantau Island (North) |
|
Pillar Point |
|
Chek Lap Kok |
WPCO WQO (in marine waters) |
EEFS WQC (in marine waters) |
||
NM1 |
NM2 |
NM3 |
NM5 |
NM6 |
NM8 |
||||
Temperature (oC) |
23.7 |
23.8 |
23.7 |
24.0 |
24.0 |
23.8 |
Not more than 2 oC in
daily temperature range |
Not available |
|
Salinity |
29.6 (22.2 – 33.1) |
28.6 |
29.4 |
27.2 |
26.0 |
27.6 |
Not to cause more than 10% change |
Not available |
|
Dissolved Oxygen
(DO) (mg/l) |
Depth average |
6.3 |
6.5 |
6.3 |
6.3 |
6.7 |
6.8 |
Not less than 4 mg/l for 90% of the samples |
Not available |
Bottom |
5.9 |
6.3 |
6.1 |
5.9 |
6.6 |
6.7 |
Not less than 2 mg/l for 90% of the samples |
Not available |
|
Dissolved Oxygen (DO) (%
Saturation) |
Depth average |
87 |
90 |
88 |
87 |
92 |
94 |
Not available |
Not available |
Bottom |
82 |
88 |
85 |
83 |
92 |
94 (63 – 118) |
Not available |
Not available |
|
PH |
7.9 |
7.9 |
7.9 |
7.9 |
7.9 |
7.9 |
6.5 - 8.5 (± 0.2 from natural range) |
Not available |
|
Secchi disc Depth (m) |
1.6 (0.9 – 2.5) |
1.7 |
1.5 |
1.4 |
1.2 |
1.3 |
Not available |
Not available |
|
Turbidity (NTU) |
20.3 |
18.0 (5.8 – 75.3) |
18.7 (8.1 – 55.8) |
25.8 |
22.9 |
23.8 |
Not available |
Not available |
|
Suspended Solids (SS)
(mg/l) |
7.4 |
6.4 |
8.1 |
15.7 |
12.6 |
15.8 |
Not more than 30% increase
|
Not available |
|
5-day Biochemical Oxygen
Demand (BOD5) (mg/l) |
0.6 |
0.6 (0.2 – 1.0) |
0.7 |
0.7 |
0.7 |
0.7 |
Not available |
Not available |
|
Ammonia Nitrogen (NH3-N)
(mgN/l) |
0.15 |
0.15 |
0.15 |
0.22 |
0.17 |
0.10 (0.01 – 0.35) |
Not available |
Not available |
|
Unionised Ammonia (UIA) (mgN/l) |
0.005 |
0.005 |
0.005 |
0.008 |
0.006 |
0.004 |
Not more than 0.021 mg/l
for annual mean |
Not available |
|
Nitrite Nitrogen (NO2-N)
(mgN/l) |
0.056 |
0.064 |
0.064 |
0.091 |
0.093 |
0.066 (0.009 – 0.150) |
Not available |
Not available |
|
Nitrate Nitrogen (NO3-N)
(mgN/l) |
0.23 |
0.28 |
0.28 |
0.37 |
0.39 |
0.28 |
Not available |
Not available |
|
Total Inorganic
Nitrogen (TIN) (mgN/l) |
0.43 |
0.49 |
0.50 |
0.67 |
0.66 |
0.44 |
Not more than 0.5 mg/l
for annual mean |
Not available |
|
Total Nitrogen (TN)
(mgN/l) |
0.60 |
0.65 |
0.66 |
0.86 |
0.84 |
0.62 |
Not available |
Not available |
|
Orthophosphate
Phosphorus (PO4) (mgP/l) |
0.03 |
0.03 |
0.03 |
0.03 |
0.02 |
0.02 |
Not available |
Not available |
|
Total Phosphorus (TP)
(mgP/l) |
0.05 |
0.04 |
0.05 |
0.07 |
0.05 |
0.04 |
Not available |
Not available |
|
Chlorophyll-a (µg/L) |
3.6 |
2.8 |
3.3 |
4.2 |
3.9 |
3.5 (1.3 – 14.7) |
Not available |
Not available |
|
E.coli (cfu/100 ml) |
1100 |
470 |
500 |
900 |
64 |
5 |
Not available |
Not available |
|
Faecal Coliforms (cfu/100 ml) |
2800 |
1100 |
1300 |
2300 |
140 (8 – 3600) |
13 |
Not available |
Not available |
Note: 1.
Except as specified, data presented are depth-averaged values calculated by taking
the means of three depths: Surface, mid-depth, bottom.
2. Data presented are annual
arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
3. Data in brackets indicate the
ranges.
4. EEFS did not derive WQC for North
Western WCZ.
Table 6.14 Baseline
Water Quality Condition for
Parameter |
|
|
|
|
Rambler Channel |
WPCO WQO (in marine waters) |
EEFS WQC (in marine waters) |
||||||
VM1 |
VM2 |
VM4 |
VM5 |
VM6 |
VM7 |
VM8 |
VM15 |
VM12 |
VM14 |
||||
Temperature (oC) |
23.2 |
23.5 |
23.6 |
23.7 |
23.6 |
23.8 |
23.8 |
23.7 |
23.8 |
24.2 |
Not more than 2 oC in
daily temperature range |
Not available |
|
Salinity |
32.2 (29.5 – 33.4) |
31.7 |
31.6 |
31.4 |
31.5 |
30.8 |
20.7 |
31.1 |
30.8 |
28.7 |
Not to cause more than 10% change |
Not available |
|
Dissolved Oxygen (DO) (% Saturation) |
Depth average |
82 |
81 |
80 |
77 |
78 |
80 |
85 |
80 |
77 |
84 |
Not available |
Not available |
Bottom |
80 |
81 |
79 |
76 |
75 |
77 |
82 |
78 |
75 |
83 |
Not available |
Not available |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
5.9 |
5.8 |
5.7 |
5.5 |
5.5 |
5.7 |
6.0 |
5.7 |
5.5 |
6.0 |
Not less than 4 mg/l for 90% of the samples |
Not less than 4 mg/l for 90% of the samples |
Bottom |
5.7 |
5.8 |
5.6 |
5.4 |
5.4 |
5.5 |
5.8 |
5.5 |
5.3 |
5.9 |
Not less than 2 mg/l for 90% of the samples |
Not less than 2 mg/l at all times |
|
pH |
7.9 |
7.9 |
7.9 |
7.9 |
7.9 |
8.0 |
8.0 |
7.9 |
8.0 |
8.0 |
6.5 - 8.5 (± 0.2 from natural range) |
Not available |
|
Secchi disc Depth (m) |
2.1 |
2.0 |
2.0 |
1.8 |
2.1 |
2.0 |
1.9 |
2.0 |
1.5 |
1.5 |
Not available |
Not available |
|
Turbidity (NTU) |
12.6 |
11.2 |
12.1 |
11.6 |
11.1 |
11.5 |
11.9 |
12.4 |
15.6 |
12..6 |
Not available |
Not available |
|
Suspended Solids (SS)
(mg/l) |
5.5 |
4.2 |
4.9 |
4.6 |
4.5 |
5.5 |
5.9 |
6.1 |
11.0 |
5.9 |
Not more than 30%
increase |
Not available |
|
5-day Biochemical Oxygen
Demand (BOD5) (mg/l) |
0.6 |
0.6 |
0.7 |
1.0 |
0.8 |
0.8 |
0.7 |
0.7 |
0.7 |
0.7 |
Not available |
Not available |
|
Nitrite Nitrogen (NO2-N) (mgN/l) |
0.019 |
0.024 |
0.024 |
0.027 |
0.027 |
0.033 |
0.035 |
0.033 |
0.036 |
0.053 |
Not available |
Not available |
|
Nitrate Nitrogen (NO3-N)
(mgN/l) |
0.08 |
0.10 |
0.11 |
0.12 |
0.13 |
0.16 |
0.16 |
0.15 |
0.17 |
0.27 |
Not available |
Not available |
|
Ammonia Nitrogen (NH3-N)
(mgN/l) |
0.07 |
0.11 |
0.13 |
0.16 |
0.16 |
0.21 |
0.17 |
0.18 |
0.18 |
0.16 |
Not available |
Not available |
|
Unionised Ammonia (UIA) (mgN/l) |
0.002 |
0.004 |
0.004 (0.002 – 0.007) |
0.005 |
0.005 (0.003 – 0.007) |
0.008 |
0.007 |
0.006 |
0.006 |
0.007 |
Not more than 0.021 mg/l
for annual mean |
Not available |
|
Total Inorganic Nitrogen
(TIN) (mgN/l) |
0.18 |
0.23 |
0.26 (0.08 – 0.44) |
0.31 (0.14 – 0.50) |
0.32 |
0.40 |
0.37 |
0.36 |
0.39 |
0.48 |
Not more than 0.4 mg/l
for annual mean |
Not more than 0.4 mg/l
for annual mean |
|
Total Nitrogen (TN)
(mgN/l) |
0.34 |
0.42 (0.20 – 0.64) |
0.47 |
0.55 |
0.53 |
0.58 |
0.53 |
0.58 (0.35 – 0.86) |
0.57 |
0.64 |
Not available |
Not available |
|
Orthophosphate
Phosphorus (PO4) (mgP/l) |
0.02 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
Not available |
Not more than 0.04 mg/l
for annual mean |
|
Total Phosphorus (TP)
(mgP/l) |
0.04 |
0.05 |
0.05 |
0.06 |
0.06 |
0.05 |
0.04 |
0.06 |
0.05 |
0.04 |
Not available |
Not available |
|
Chlorophyll-a (µg/L) |
2.6 |
3.0 |
2.9 (1.0 – 9.2) |
2.8 |
2.9 |
2.6 |
2.7 |
3.5 |
2.1 |
3.4 |
Not available |
Not available |
|
E coli (cfu/100 ml) |
440 |
1100 |
2600 |
7700 |
5500 |
9400 |
6100 |
1800 |
3400 |
1300 |
Not available |
Not available |
|
Faecal Coliforms (cfu/100 ml) |
940 |
2600 |
6500 |
19000 |
13000 |
23000 |
15000 |
4800 |
8100 (4200 – 14000) |
2800 (460 – 13000) |
Not available |
Not available |
Note: 1.
Except as specified, data presented are depth-averaged values calculated by
taking the means of three depths: Surface, mid-depth, bottom.
2. Data presented are annual
arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
3. Data in brackets indicate the
ranges.
Table 6.15 Baseline Water Quality Condition for Western Buffer WCZ in 2006
Parameter |
|
Tsing Yi (South) |
Tsing Yi (West) |
WPCO WQO (in marine waters) |
EEFS WQC (in marine waters) |
|
WM2 |
WM3 |
WM4 |
||||
Temperature (oC) |
23.8 |
23.6 |
23.6 |
Not more than 2 oC in
daily temperature range |
Not available |
|
Salinity |
30.9 |
31.5 |
31.0 |
Not to cause more than 10% change |
Not available |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
6.1 |
5.8 |
5.7 |
Not less than
4 mg/l for 90% of the samples |
Not less than 4 mg/l for 90% of the samples |
Bottom |
6.0 |
5.7 |
5.4 |
Not less than
2 mg/l for 90% of the samples |
Not less than 2 mg/l at all times |
|
Dissolved Oxygen (DO) (%
Saturation) |
Depth average |
86 |
82 |
80 |
Not available |
Not available |
Bottom |
84 |
80 |
76 |
Not available |
Not available |
|
pH |
8.0 |
8.0 |
8.0 |
6.5 - 8.5 (± 0.2 from natural range) |
Not available |
|
Secchi disc Depth (m) |
2.0 |
1.7 |
1.7 |
Not available |
Not available |
|
Turbidity (NTU) |
12.0 |
13.8 |
14.3 |
Not available |
Not available |
|
Suspended Solids (SS)
(mg/l) |
4.8 |
7.7 |
7.6 |
Not more than 30%
increase |
Not available |
|
5-day Biochemical Oxygen
Demand (BOD5) (mg/l) |
0.6 |
0.7 |
0.6 |
Not available |
Not available |
|
Ammonia Nitrogen (NH3-N)
(mgN/l) |
0.10 |
0.13 |
0.12 |
Not available |
Not available |
|
Unionised Ammonia (UIA) (mgN/l) |
0.004 (0.001 – 0.009) |
0.005 |
0.005 |
Not more than 0.021 mg/l
for annual mean |
Not available |
|
Nitrite Nitrogen (NO2-N)
(mgN/l) |
0.034 |
0.032 |
0.037 |
Not available |
Not available |
|
Nitrate Nitrogen (NO3-N)
(mgN/l) |
0.16 |
0.14 |
0.17 |
Not available |
Not available |
|
Total Inorganic Nitrogen
(TIN) (mgN/l) |
0.29 |
0.30 |
0.32 |
Not more than 0.4 mg/l
for annual mean |
Not more than 0.4 mg/l
for annual mean |
|
Total Nitrogen (TN)
(mgN/l) |
0.43 |
0.45 |
0.47 |
Not available |
Not available |
|
Orthophosphate
Phosphorus (PO4) (mgP/l) |
0.02 |
0.02 |
0.02 |
Not available |
Not more than 0.04 mg/l
for annual mean |
|
Total Phosphorus (TP)
(mgP/l) |
0.04 |
0.04 |
0.04 |
Not available |
Not available |
|
Chlorophyll-a (µg/L) |
2.8 |
2.0 |
2.4 |
Not available |
Not available |
|
E coli (cfu/100 ml) |
910 |
3600 |
1400 |
Not available |
Not available |
|
Faecal Coliforms (cfu/100 ml) |
2000 |
8600 |
3000 |
Not available |
Not available |
Note: 1.
Except as specified, data presented are depth-averaged values calculated by taking
the means of three depths: Surface, mid-depth, bottom.
2. Data presented are annual
arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
3. Data in brackets indicate the
ranges.
Table 6.16 Baseline
Water Quality Condition for
Parameter |
Junk Bay WCZ |
Eastern Buffer WCZ |
|||||||
JM3 |
JM4 |
WPCO WQO (in marine waters) |
EEFS WQO (in marine
waters) |
EM1 |
EM2 |
WPCO WQO (in marine waters) |
EEFS WQC (in marine
waters) |
||
Temperature (oC) |
23.7 |
23.5 |
Not more than 2 oC in
daily temperature range |
Not available |
23.4 |
23.4 |
Not more than 2 oC in
daily temperature range |
Not available |
|
Salinity |
31.8 |
32.3 |
Not to cause more than 10% change |
Not available |
32.2 |
32.3 |
Not to cause more than 10% change |
Not available |
|
Dissolved Oxygen (DO) (% Saturation) |
Depth average |
93 |
91 |
Not available |
Not available |
88 |
92 |
Not available |
Not available |
Bottom |
90 |
88 |
Not available |
Not available |
84 |
88 |
Not available |
Not available |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
6.6 |
6.4 |
Not less than
4 mg/l for 90% of the samples |
Not less than 4 mg/l for 90% of the samples |
6.2 |
6.5 |
Not less than
4 mg/l for 90% of the samples |
Not less than 4 mg/l for 90% of the samples |
Bottom |
6.4 |
6.2 |
Not less than
2 mg/l for 90% of the samples |
Not less than 2 mg/l at all times |
6.0 |
6.3 |
Not less than
2 mg/l for 90% of the samples |
Not less than 2 mg/l at all times |
|
pH |
7.9 |
8.0 |
6.5 - 8.5 (± 0.2 from natural range) |
Not available |
8.0 |
8.0 |
6.5 - 8.5 (± 0.2 from natural range) |
Not available |
|
Secchi disc Depth (m) |
2.2 |
2.2 |
Not available |
Not available |
2.2 |
2.1 |
Not available |
Not available |
|
Turbidity (NTU) |
10.0 |
10.9 |
Not available |
Not available |
12.0 |
10.8 |
Not available |
Not available |
|
Suspended Solids (SS)
(mg/l) |
3.2 |
4.5 |
Not more than 30%
increase |
Not available |
3.9 |
3.9 |
Not more than 30%
increase |
Not available |
|
5-day Biochemical Oxygen
Demand (BOD5) (mg/l) |
0.7 |
0.6 |
Not available |
Not available |
0.6 |
0.5 |
Not available |
Not available |
|
Nitrite Nitrogen (NO2-N)
(mgN/l) |
0.02 |
0.018 |
Not available |
Not available |
0.017 |
0.016 |
Not available |
Not available |
|
Nitrate Nitrogen (NO3-N)
(mgN/l) |
0.09 |
0.07 |
Not available |
Not available |
0.07 |
0.07 |
Not available |
Not available |
|
Ammonia Nitrogen (NH3-N)
(mgN/l) |
0.07 |
0.06 |
Not available |
Not available |
0.06 |
0.05 |
Not available |
Not available |
|
Unionised Ammonia (UIA) (mgN/l) |
0.003 |
0.002 |
Not more than 0.021 mg/l
for annual mean |
Not available |
0.003 |
0.002 |
Not more than 0.021 mg/l
for annual mean |
Not available |
|
Total Inorganic Nitrogen
(TIN) (mgN/l) |
0.18 |
0.15 |
Not more than 0.3 mg/l
for annual mean |
Not more than 0.3 mg/l
for annual mean |
0.15 |
0.13 |
Not more than 0.4 mg/l
for annual mean |
Not more than 0.4 mg/l
for annual mean |
|
Total Nitrogen (TN)
(mgN/l) |
0.34 |
0.31 |
Not available |
Not available |
0.29 |
0.28 |
Not available |
Not available |
|
Orthophosphate
Phosphorus (PO4) (mgP/l) |
0.01 |
0.01 |
Not available |
Not more than 0.03 mg/l
for annual mean |
0.02 |
0.01 |
Not available |
Not more than 0.04 mg/l
for annual mean |
|
Total Phosphorus (TP)
(mgP/l) |
0.03 |
0.03 |
Not available |
Not available |
0.03 |
0.03 |
Not available |
Not available |
|
Chlorophyll-a (µg/L) |
4.8 |
3.6 |
Not available |
Not available |
3.3 |
3.3 |
Not available |
Not available |
|
E coli (cfu/100 ml) |
38 |
76 |
Not available |
Not available |
74 |
21 |
Not available |
Not available |
|
Faecal Coliforms (cfu/100 ml) |
140 |
220 |
Not available |
Not available |
190 |
80 |
Not available |
Not available |
Note: 1.
Except as specified, data presented are depth-averaged values calculated by
taking the means of three depths: Surface, mid-depth, bottom.
2. Data presented are annual
arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
3. Data in brackets indicate the
ranges.
Table 6.17 Baseline
Water Quality Condition for
Parameter |
West Lamma Channel |
Lantau Island (East) |
WPCO WQO (in marine waters) |
EEFS WQC (in marine waters) |
|||
SM7 |
SM9 |
SM10 |
SM11 |
||||
Temperature (oC) |
24.3 |
24.0 |
24.3 |
24.3 |
Not more than 2 oC in
daily temperature range |
Not available |
|
Salinity |
31.1 |
30.8 |
30.4 |
30.7 |
Not to cause more than 10% change |
Not available |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
6.8 (5.1 – 9.3) |
6.3 |
6.9 |
7.5 |
Not less than
4 mg/l for 90% of the samples |
Not less than 5 mg/l for monthly average |
Bottom |
6.8 |
6.3 |
6.9 |
7.3 |
Not less than
2 mg/l for 90% of the samples |
Not less than 2 mg/l at all times |
|
Dissolved Oxygen (DO) (%
Saturation) |
Depth average |
97 |
89 |
98 |
107 |
Not available |
Not available |
Bottom |
96 |
89 |
98 |
104 |
Not available |
Not available |
|
pH |
8.2 |
8.1 |
8.1 |
8.1 |
6.5 - 8.5 (± 0.2 from natural range) |
Not available |
|
Secchi disc Depth (m) |
2.0 |
1.5 |
1.2 |
1.5 |
Not available |
Not available |
|
Turbidity (NTU) |
13.3 |
14.7 |
16.2 |
12.3 |
Not available |
Not available |
|
Suspended Solids (SS)
(mg/l) |
4.8 |
8.0 |
9.1 |
6.0 |
Not more than 30%
increase |
Not available |
|
5-day Biochemical Oxygen
Demand (BOD5) (mg/l) |
0.8 |
0.5 |
0.8 |
0.9 |
Not to
exceed 5 mg/l |
Not available |
|
Ammonia Nitrogen (NH3-N)
(mgN/l) |
0.07 |
0.13 |
0.11 |
0.09 |
Not available |
Not available |
|
Unionised Ammonia (UIA) (mgN/l) |
0.004 |
0.006 |
0.006 |
0.005 |
Not more than 0.021 mg/l
for annual mean |
Not available |
|
Nitrite Nitrogen (NO2-N)
(mgN/l) |
0.027 (0.002 – 0.071) |
0.040 (0.007 – 0.110) |
0.038 |
0.035 |
Not available |
Not available |
|
Nitrate Nitrogen (NO3-N)
(mgN/l) |
0.13 |
0.17 |
0.17 |
0.15 |
Not available |
Not available |
|
Total Inorganic Nitrogen
(TIN) (mgN/l) |
0.23 |
0.34 |
0.32 |
0.28 |
Not more than 0.1 mg/l
for annual mean |
Not more than 0.2 mg/l
for annual mean |
|
Total
Kjeldahl Nitrogen (TKN) (mgN/l) |
0.23 |
0.28 |
0.28 |
0.28 |
Not available |
Not available |
|
Total Nitrogen (TN)
(mgN/l) |
0.39 |
0.49 |
0.49 |
0.46 |
Not available |
Not available |
|
Orthophosphate
Phosphorus (PO4) (mgP/l) |
0.01 |
0.02 |
0.02 |
0.02 (<0.01 – 0.03) |
Not available |
Not more than 0.02 mg/l
for annual mean |
|
Total Phosphorus (TP)
(mgO/l) |
0.03 |
0.05 |
0.05 |
0.04 |
Not available |
Not available |
|
Chlorophyll-a (µg/L) |
4.4 |
2.7 |
7.4 |
9.1 |
Not available |
Not available |
|
E coli (cfu/100 ml) |
17 |
170 |
19 |
6 |
Not more than 610 per 100
ml for annual geometric mean, applicable to secondary contact recreation
subzone (SM10 and SM11) only |
Not more than 610 per
100 ml for annual geometric mean, applicable to secondary contact recreation
subzone (SM10 and SM11) only |
|
Faecal Coliforms (cfu/100 ml) |
37 |
380 |
58 |
19 |
Not available |
Not available |
Note: 1.
Except as specified, data presented are depth-averaged values calculated by taking
the means of three depths: Surface, mid-depth, bottom.
2. Data presented are annual
arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
3. Data in brackets indicate the
ranges
6.56
Two marine water sampling
events were conducted under the Minor Works Contract ([10]) in December 2004 and May 2005 respectively
to collect marine water samples for chemical analysis of nine CBP compounds
(namely bromoform, chloroform, bromodichloromethane, dibromochloromethane,
bromoacetic acid, chloroacetic acid, dibromoacetic acid, dichloroacetic acid
and trichloroacetic acid). During each sampling event, replicate
depth-integrated samples (composite of samples from near-surface, mid-depth and
near-bottom) were collected at two marine stations, one near the existing
outfall of SCISTW, namely SCI-1, and one at EPD’s monitoring station, namely
SM18, in
6.57 In February 2006, triplicate depth-integrated samples were collected at SCI-1 and SM18 under the ADF study for laboratory analysis of TRC and the other 25 identified CBP compounds.
6.58
Total (soluble plus insoluble)
concentrations of CBP were measured in the marine water samples. Table 6.18 shows the maximum values
measured in the samples. All the
maximum levels were below the detection limits except for methylene chloride
where its maximum level measured at station SM18 was
Table 6.18 Maximum Ambient Concentrations for TRC and CBP
Parameters |
Station SCI-1 |
Station SM18 |
Total residual chlorine
(mg/l) |
<20 |
<20 |
Bromoform (mg/l) |
<5 |
<5 |
Bromodichloromethane (mg/l) |
<5 |
<5 |
Chloroform (mg/l) |
<5 |
<5 |
Dibromochloromethane (mg/l) |
<5 |
<5 |
Bromoacetic acid (mg/l) |
<2 |
<2 |
Chloroacetic acid (mg/l) |
<2 |
<2 |
Dibromoacetic acid (mg/l) |
<2 |
<2 |
Dichloroacetic acid (mg/l) |
<2 |
<2 |
Trichloroacetic acid (mg/l) |
<2 |
<2 |
Methylene chloride (mg/l) |
<20 |
55 |
Carbon tetrachloride (mg/l) |
<0.5 |
<0.5 |
Chlorobenzene (mg/l) |
<0.5 |
<0.5 |
1,1-dichloroethane (mg/l) |
<0.5 |
<0.5 |
1,2-dichloroethane (mg/l) |
<0.5 |
<0.5 |
1,1-dichloroethylene (mg/l) |
<0.5 |
<0.5 |
1,2-dichloropropane (mg/l) |
<0.5 |
<0.5 |
Tetrachloroethylene (mg/l) |
<0.5 |
<0.5 |
1,1,1-trichloroethane (mg/l) |
<0.5 |
<0.5 |
1,1,2-trichloroethane (mg/l) |
<0.5 |
<0.5 |
Trichloroethylene (mg/l) |
<0.5 |
<0.5 |
2-chlorophenol (mg/l) |
<0.5 |
<0.5 |
2,4-dichlorophenol (mg/l) |
<0.5 |
<0.5 |
p-chloro-m-cresol (mg/l) |
<0.5 |
<0.5 |
Pentachlorophenol (mg/l) |
<2.5 |
<2.5 |
2,4,6-trichlorophenol (mg/l) |
<0.5 |
<0.5 |
Bis(2-chloroethoxy)methane (mg/l) |
<0.5 |
<0.5 |
1,4-dichlorobenzene (mg/l) |
<0.5 |
<0.5 |
Hexachlorobenzene (mg/l) |
<0.5 |
<0.5 |
Hexachlorocyclopentadiene (mg/l) |
<2.5 |
<2.5 |
Hexachloroethane (mg/l) |
<0.5 |
<0.5 |
1,2,4-trichlorobenzene (mg/l) |
<0.5 |
<0.5 |
Alpha-BHC (mg/l) |
<0.5 |
<0.5 |
Beta-BHC (mg/l) |
<1 |
<1 |
Gamma-BHC (mg/l) |
<1 |
<1 |
6.59 Under the EEFS, marine water samples were collected in 2002 for laboratory analysis of toxic contaminants that are not routinely monitored by EPD. Two water sampling events were conducted in October and December respectively. Replicate depth-integrated water samples were collected at stations SCI-1 and SM18, as shown in Figure 6.1. Table 6.19 shows the maximum values measured in the marine water samples.
Table 6.19 Maximum
Total Contaminant Concentrations in Ambient Marine Water
Parameters |
Station SCI-1 |
Station SM18 |
Arsenic (mg/l) |
1.38 |
1.48 |
Chromium, total (mg/l) |
0.55 |
0.41 |
Copper (mg/l) |
2.25 |
0.64 |
Mercury (ng/l) |
0.06 |
0.06 |
Nickel (mg/l) |
1.02 |
0.68 |
Zinc (mg/l) |
3.54 |
1.2 |
Sulphide (mg/l) |
48 |
44 |
Surfactants (mg/l) |
400 |
390 |
Phenol (mg/l) |
<1 |
<1 |
Cyanide (mg/l) |
<2 |
<2 |
6.60 As shown in Table 6.19, most of the contaminants were detected in the samples except for phenol and cyanide which were not detected in all the collected water samples which indicated that these 2 chemicals would be negligible in the ambient water. No far field assessment criterion is available for these contaminants. When compared to the near field assessment criteria (Table 6.9), only the measured sulphide level exceeded the criteria value of 20 μg/l. The measured levels for the remaining contaminants were well below the near field criteria values.
6.61
The EIA study for ADF has
concluded that provision of disinfection facilities would be needed for the
HATS effluent in order to satisfy the requirement for protection of the
identified water sensitive receivers and help to improve water quality in the
Western Buffer water control zone (WCZ) and western
6.62 Chlorination has been proposed as the disinfection technology for the HATS. Dechlorination would be applied to eliminate the discharge of total residual chlorine (TRC) into the marine environment. Sodium hypochlorite and sodium bisulphite would be adopted as the chlorination agent and dechlorination agent respectively in the latest scheme of HATS.
6.63 Detailed assessment was performed under the EIA study for ADF to estimate the optimum disinfection levels for the disinfection facilities, on one hand, to safeguard the beneficial uses of nearby water sensitive receivers and, on the other hand, to minimize the chlorine dose and thus the potential generation of chlorination by-products (CBP). Based on the findings of the ADF study, discharge standards for E.coli and TRC are recommended for the disinfected HATS effluent as shown in Table 6.20.
Table 6.20 Effluent Standards for the
HATS Recommended under the ADF Study
Stage |
E.coli (no. per 100 ml) (1) |
TRC (mg/l) |
||
Geometric Mean |
95 Percentile |
95 Percentile |
Maximum |
|
HATS – ADF Stage |
200,000 |
3,000,000 |
0.2 |
0.4 |
HATS – Stage |
20,000 |
300,000 |
0.2 |
0.4 |
HATS – Stage 2B |
20,000 |
300,000 |
0.2 |
0.4 |
Note:
(1) The effluent standards
for E.coli are equivalent to 99% or
above E.coli removal.
6.64 The EIA study for ADF concluded that, with the adoption of effluent standards recommended in Table 6.20, the discharge of HATS effluent after chlorination and dechlorination would not cause adverse environmental impact. This recommendation is based on detailed modelling assessment conducted under the ADF study. Details of the modelling assessment results can be referred to the separate EIA report for ADF. This water quality impact assessment is based on the effluent standards recommended under the ADF study to confirm their environmental acceptability. A summary of the key findings of the ADF study including the required chlorine dosage and the characteristics of chlorinated and dechlorinated (C/D) effluent is given in the subsequent sections.
6.65 Bench-scale tests were conducted to estimate the chlorine demand and chlorine residual for meeting the geometric mean E.coli standards of 20,000 and 200,000 counts per 100 ml. The tests were conducted by HOKLAS accredited laboratories appointed by DSD in 2002 and 2005. Based on the data of the bench-scale chlorination studies, the recommended sodium hypochlorite and sodium bisulphite dosages for chlorination / dechlorination under different phases of HATS are summarized in Table 6.21.
Table 6.21 Recommended
Sodium Hypochlorite and Sodium Bisulphite Dosages for HATS
Description |
Operational Range |
|
Advance Disinfection
Facilities (ADF) Stage to meet the E.coli
standard of 200,000 counts per 100 ml |
||
Minimum Chlorine Contact Time |
6.6 minutes (under peak flow condition) |
|
Sodium Hypochlorite Dosage
(mgCl2/L) |
11 - 15 |
|
Sodium Bisulphite Dosage(mgNaHSO3/l) |
Automatic Mode |
4 – 7 |
Manual Mode |
8 – 11 |
|
Stage |
||
Minimum Chlorine Contact Time |
20 minutes (under peak flow
condition) |
|
Sodium Hypochlorite Dosage
(mgCl2/L) |
10 – 14 |
|
Sodium Bisulphite Dosage (mgNaHSO3/l) |
Automatic Mode |
2 – 4 |
Stage 2B Disinfection
Facilities to meet the E.coli standard
of 20,000 counts per 100 ml |
||
Minimum Chlorine Contact Time |
20 minutes (under peak flow
condition) |
|
Sodium Hypochlorite Dosage
(mgCl2/L) |
2 - 3 |
|
Sodium Bisulphite Dosage (mgNaHSO3/l) |
Automatic Mode |
1 - 2 |
6.66 Under the ADF stage, two operation modes were developed for the control of chemical dosages – Manual Operation Mode and Automatic Operation Mode. The difference between the two operation modes is the methods for measuring the TRC levels at the outlet of the chlorination system. Under the Automatic Operation Mode, dosages of dechlorination agent (i.e. sodium bisulphite) would be adjusted automatically following sewage flow rate and online TRC measurements at the outlet of the chlorination system. The TRC measurements would be conducted continuously e.g. at 15-min intervals. Thus, dechlorination chemical can be adjusted based on the TRC data every 15 minutes. Under the Manual Operation Mode, chemical dosages would be adjusted based on sewage flow rate and manual TRC measurement. Practically, hourly TRC measurements would be conducted during the Manual Operation Mode and dechlorination chemical would be adjusted based on the TRC data every hour. A higher dechlorination chemical would be provided to achieve zero TRC in the discharge during the Manual Operation Mode and to allow sufficient safety margin to offset the potential fluctuation of TRC between the hourly measurements. Automatic Operation Mode would be the key control mode for SCISTW chlorination system, while Manual Operation Mode would be provided to allow operation flexibility and reliability in case of online TRC analyzer failure. As a conservative approach, the assessment of water quality impacts at the ADF stage has been based on the chemical dosages under Manual Operation Mode. Automatic operation mode will be used in the permanent disinfection facilities to be built for the HATS Stage 2. The design chemical dosage for Stage 2A and Stage 2B adopted in the EIA was therefore based on the automatic operation mode only.
6.67
At the ADF stage, the existing
effluent culvert system would be used for chlorine contact at the ADF stage and
the chlorine contact times would be less than 10 minutes. At Stage
6.68
Laboratory pilot tests were
conducted for the CEPT effluent from SCISTW and the secondary treated effluent
from Tai
6.69 Of the 34 CBP’s tested, only 8 were detected in the C/D CEPT effluent, the concentrations of 6 were less than 10 parts per billion while those for the remaining 2 were in the 10-50 parts per billion range. However, 5 of these 8 CBPs were also detected in the CEPT effluent before chlorination and dechlorination. Of these 5, the concentrations of 3 were less than 10 parts per billion while the remaining two had concentrations in the 10-50 parts per billion range. These results indicated that of the few CBP’s detected, the majority was already present in the CEPT effluent before chlorination and dechlorination, and the chlorination and dechlorination process introduced 3 CBP’s all showing concentrations of less than 10 parts per billion. The laboratory results also showed that the THM and HAA formed were in the parts per billion concentration range, well below USEPA’s drinking water standard for THM and HAA.
6.70 The laboratory results for C/D CEPT effluent were used to assess the water quality impacts due to the effluent discharged from SCISTW during ADF stage (Stage 1) and Stage 2A. The results for C/D secondary treated effluent were used to assess the water quality impacts during Stage 2B where the SCISTW would be upgraded to secondary treatment. The pilot tests were performed using a chlorine dosage of 15 and 20 mg/l for the CEPT effluent and 5 and 9 mg/l for the secondary treated effluent. The chlorine dosages adopted in the pilot tests are larger than the recommended dosages as shown in Table 6.21, which would provide conservative assessment.
Table 6.22 Summary
of Chemical Analysis Results
Parameters |
Raw
CEPT Effluent |
C/D
CEPT Effluent |
Raw
Secondary Treated Effluent |
C/D
Secondary Treated Effluent |
Ammonia
(mg/l) |
18 - 30 |
(17.4 – 21.5) |
1.27 – 1.41 |
(0.43 – 1.16) |
Sulfite
(mg/l) |
<0.1 – 1.5 |
(<0.1 – 1.5) |
<0.1 |
0.7 |
Total
residual chlorine (mg/l) |
<0.02 |
(0.02 - 0.1) |
<0.02 |
<0.02 |
Bromoform
(mg/L) |
<5 |
<5 |
<5 |
(32 – 49) |
Bromodichloromethane
(mg/L) |
<5 |
<5 |
<5 |
<5 |
Chloroform
(mg/L) |
<5 to 5 |
(<5 – 7) |
<5 |
<5 |
Dibromochloromethane
(mg/L) |
<5 |
<5 |
<5 |
(<5 – 8) |
Bromoacetic
acid (mg/L) |
<2 |
<2 |
<2 |
<2 |
Chloroacetic
acid (mg/L) |
<2 |
(<2 – 4) |
<2 |
<2 |
Dibromoacetic
acid (mg/L) |
<2 |
(<2 – 4) |
<2 |
(6 – 10) |
Dichloroacetic
acid (mg/L) |
11 to 17.3 |
(20 - 45.9) |
<2 |
<2 - 3 |
Trichlroacetic
acid (mg/L) |
4.7 to 10 |
(7.19 – 22) |
<2 to 2 |
(4 – 7) |
Methylene
chloride (mg/L) |
<20 |
<20 |
<20 |
<20 |
Carbon
tetrachloride (mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Chlorobenzene
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1,1-dichloroethane
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1,2-dichloroethane
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1,1-dichloroethylene
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1,2-dichloropropane
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Tetrachloroethylene
(mg/L) |
1.0 to 1.3 |
(0.5 - 1.3) |
<0.5 |
<0.5 |
1,1,1-trichloroethane
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1,1,2-trichloroethane
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Trichloroethylene
(mg/L) |
1.5 to 1.9 |
(1.1 – 2) |
<0.5 |
<0.5 |
2-chlorophenol
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
2,4-dichlorophenol
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
p-chloro-m-cresol
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Pentachlorophenol
(mg/L) |
<2.5 |
<2.5 |
<2.5 |
<2.5 |
2,4,6-trichlorophenol
(mg/L) |
<0.5 |
(1 – 2) |
<0.5 |
<0.5 |
Bis(2-chloroethoxy)methane
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1,4-dichlorobenzene
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Hexachlorobenzene
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Hexachlorocyclopentadiene
(mg/L) |
<2.5 |
<2.5 |
<2.5 |
<2.5 |
Hexachloroethane
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1,2,4-trichlorobenzene
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Alpha-BHC
(mg/L) |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Beta-BHC
(mg/L) |
<1 |
<1 |
<1 |
<1 |
Gamma-BHC
(mg/L) |
<1 |
<1 |
<1 |
<1 |
Note: Data in brackets indicate the
ranges.
6.71
The water quality impact assessment was conducted on two different scales – one in very close proximity
to the point of discharge, which is usually called the near field and another
across a larger area that ranges from the upper reaches of the Pearl River
Estuary to points well offshore of
6.72
Near field modeling
was conducted using the VISJET developed by the
6.73 The near field methodology and approach including the details of modelling tools, model input and modelling scenarios, are presented in Appendix 6.1. To compare the near field modelled results with the WQC derived under the EEFS, the concentration of a particular contaminant at the edge of the ZID was calculated by:
C zid = C background (Dilution -1) + C effluent
Dilution Dilution
Where
C zid = Concentration of the contaminant at the edge of ZID (and is the concentration to be compared with the WQC)
C background = Background or ambient concentration without the HATS discharge
C effluent = HATS effluent concentration
Dilution = Minimum dilution rate predicted by the near field model at the edge of ZID
6.74 The maximum contaminant concentrations measured under the HATS baseline survey (refer to Table 6.19) were used as the background concentrations for near field assessment. The maximum values for metals, sulphide, surfactants, cyanide and phenol were recorded at Station SCI-1 whilst the maximum value for arsenic was recorded at Station SM18. The measured ambient levels of phenol and cyanide were all under the detection limits of 1 mg/l and 2 mg/l respectively. It was assumed that the ambient concentrations of phenol and cyanide would be equal to one half of their detection limits, following the approach adopted under the EEFS.
6.75 As these baseline water quality data were collected in 2002 after the implementation of HATS Stage 1, some chemicals detected in the marine water during the sampling events would be associated with the existing HATS discharge (i.e. the CEPT effluent of SCISTW). Using these ambient data for near field assessment was therefore a conservative approach.
6.76 Based on the HATS survey data, the measured TRC levels in the marine water were all under the detection limit (refer to Table 6.18). Given the fact that TRC would undergo decay in marine water, it is anticipated that the ambient TRC concentration, if any, would be minimal. Thus, for the purpose of near field assessment, the ambient TRC concentration was assumed to be negligible.
6.77 The WQC was derived for pH and temperature for 90% of occasions (Table 6.9). There are also WQO available for pH, temperature and salinity which should be complied at all times (Table 6.1 to Table 6.6). In addition, two WQC for UIA would need to be compared with the predicted near field concentrations for 1-hour average and 4-day average respectively. For the purpose of near field impact assessment, the ambient levels of pH, salinity, temperature and UIA were compiled using the field data collected at EPD station WM3 in 2000. Year 2000 represents the pre-HATS situation without the SCISTW effluent discharge. Table 6.23 shows the assumed ambient values.
Table 6.23 Ambient
Values for pH, Temperature, Salinity and Unionized Ammonia
Parameters |
Ambient Concentrations |
||
Mean |
90 Percentile |
Range |
|
Temperature (oC)
|
22.8 |
26.5 |
16.3 – 27.2 |
Salinity (ppt) |
31.0 |
32.0 |
29.0 – 32.8 |
Unionized ammonia (mg/l
as N) |
0.0030 |
0.0040 |
0.0020 – 0.0093 |
pH |
7.9 |
8.1 |
7.6 – 8.1 |
6.78
Sampling and analysis of toxic
chemicals in sewage effluent was conducted under the EEFS in 2002. Under the EEFS, biological aerated
filter (BAF) was assumed as the secondary treatment process for the HATS. Effluent
samples were collected from the BAF pilot plant constructed under the Compact
Sewage Treatment Technology Pilot Plant Trial Project (CSTTT), as well as the
existing SCISTW for laboratory analysis.
The CEPT plus BAF was assumed under the EEFS as the ultimate treatment
process train for the HATS. The CEPT effluents were used as the influent of the
BAF pilot plant under the CSTTT.
Replicate samples were collected at each site from 31 October to
Table 6.24 Maximum
Total Contaminant Concentrations in Effluent Samples
Parameters |
CEPT
Effluent (Stage 1 and
Stage 2A) |
Secondary
Treated Effluent (Stage 2B) |
Arsenic (mg/l) |
1.49 |
0.88 |
Chromium, total (mg/l) |
18.2 |
8.45 |
Copper (mg/l) |
55.7 |
9.98 |
Mercury (ng/l) |
29.4 |
3.48 |
Nickel (mg/l) |
28.5 |
22.3 |
Zinc (mg/l) |
44.1 |
11.8 |
Sulphide (mg/l) |
4900 |
53 |
Surfactants (mg/l) |
4600 |
380 |
Phenol (mg/l) |
<1 |
<1 |
Cyanide (mg/l) |
<2 |
<2 |
6.79
Ammonia concentrations in the
CEPT effluent of SCISTW are routinely measured by DSD. Effluent sampling
results for ammonia are presented for a one-year period from September 2005 to
August
Table 6.25 Assumed
Effluent Concentrations for Ammonia
Parameters |
Type/
Period |
CEPT
Effluent (Stage 1
and Stage 2A) |
Secondary
Treated Effluent (Stage 2B) |
Ammonia (mg/l as N) |
1-hour
average |
29 (1) |
4.2 (3) |
4-day
average |
25 (2) |
(1) Maximum
effluent value based on actual measurements of CEPT effluent at SCISTW from
September 2005 to August 2006 (The data are graphically presented in Figure
6.4).
(2) Maximum
4-day running average value based on actual measurements of CEPT effluent at
SCISTW from September 2005 to August 2006 (The data are graphically presented
in Figure 6.4).
(3) Maximum concentration measured in the
BAF effluent collected under the EEFS for whole effluent toxicity testing.
6.80 The EEFS included an assessment of the toxicity of BAF effluent as measured by whole effluent toxicity testing. The ammonia concentration assumed for the secondary treated effluent (Stage 2B) was based on the maximum value measured in the BAF effluent collected under the EEFS for whole effluent toxicity testing. Based on the review of measured ammonia concentrations in the effluent of existing secondary treatment plants (Sha Tin STW and Tai Po STW), this EEFS value was considered to be conservative.
6.81 The assumed effluent values for pH, salinity and temperature were based on the historical effluent data collected at SCISTW (see Figure 6.4). As the measured pH values for both CEPT effluent (Figure 6.4) and ambient water (Table 6.23) were all within 6.5 to 8.5, there would be no exceedance of the WQO and WQC for pH under all the assessment scenarios. The assumed effluent and ambient values for salinity and temperature adopted in the near field assessment are detailed in Table 6.39 and Table 6.40.
6.82 Following the approach adopted under the ADF study, the 95th percentile value of the TRC standards (i.e. 0.2 mg/l) was used as the effluent TRC concentration. This model input was conservative, given that 95%ile of the TRC loads were usually about twice their mean values. Dechlorination would be applied to eliminate the TRC contents in the HATS effluent discharge. Also, the pilot test data presented in Table 6.22 showed a lower TRC range of 0.02 to 0.1 mg/l only. Thus, use of the 95th percentile TRC standard for near field assessment would be conservative.
6.83 Comprehensive review and identification of the contaminants of concerns (COC) in the SCISTW effluent and quantification of the adverse effects on the communities potentially at risk from exposure to the identified COC in marine water are provided under the human health and marine ecological risk assessment in Section 7 and Section 8 respectively.
6.84
Computer modelling was used to
assess the potential impacts on marine water quality associated with the
Project. The Delft3D suite of
models, namely Delft3D-FLOW and Delft3D-WAQ, developed by
6.85 Delft3D-FLOW is a 3-dimensional hydrodynamic simulation programme with applications for coastal, river and estuarine areas. The model calculates non-steady flow and transport phenomena that result from tidal and meteorological forcing on a curvilinear, boundary fitted grid.
6.86
Delft3D-WAQ is a water quality
model framework for numerical simulation of various physical, biological and
chemical processes in 3 dimensions.
It solves the advection-diffusion-reaction equation for a predefined
computational grid and for a
6.87 In the present Study, the detailed HATS model developed using Delft3D-FLOW and Delft3D-WAQ was employed for simulation of the water quality changes due to the Project. The detailed HATS model was originally developed and applied under the EEFS to assess the potential water quality impacts of different treatment and disposal scheme proposed for the HATS and the associated construction activities.
6.88
The detailed HATS model covers
the North Western, Western Buffer,
6.89
Set up of the detailed HATS
model such as the meteorological forcing, flow aggregation, wind condition,
initial and boundary conditions was based on the EEFS. The detailed HATS Model was linked to
the regional Update Model, which was constructed, calibrated and verified under
the project “CE42/97 Update on Cumulative Water Quality and Hydrological Effect
of Coastal Development and Upgrading of Assessment Tool” (Update study)”. Computations were first carried out using
the Update Model to provide open boundary conditions to the detailed HATS
Model. The Update model covers the
whole Hong Kong and the adjacent Mainland waters including discharges from the
6.90 For each assessment scenario, the simulation period of the hydrodynamic model covered two 15-day full spring-neap cycles (excluding the spin-up period) for dry and wet seasons respectively. The hydrodynamic results were used repeatedly to drive the water quality simulations for one complete calendar year (excluding the spin-up period) as specified in the EIA Study Brief. A spin-up period of 8 days and 30 days was provided for hydrodynamic simulation and water quality simulation respectively. These spin-up periods were tested under the EEFS and the ADF study and were found to be sufficient.
6.91
The
6.92 The diurnal flow variation of the Project effluent was incorporated in both the hydrodynamic and water quality model. The daily flow patterns measured at the SCISTW during August 2004 and January 2005 were reviewed. The review indicated that there was no substantial change in the diurnal patterns between the dry and wet seasons. The typical diurnal flow pattern measured at the SCISTW as shown in Table 6.28 below was applied to the projected daily Project flow and load to derive the hourly diurnal flow and load for different year horizons as model inputs. The same 24-hour diurnal flow pattern was used in the model throughout the simulation period. The exact vertical and horizontal grid cell(s) of the 3D far field model into which the Project flow and pollution loading were allocated were determined by the near field modelling as detailed in Appendix 6.1.
Table 6.28 Typical
Hourly Flow Pattern for the SCISTW Effluent
Hour |
% of Daily
Flow |
Hour |
% of
Daily Flow |
Hour |
% of
Daily Flow |
Hour |
% of
Daily Flow |
0:00 |
4.45% |
|
2.53% |
|
5.03% |
|
4.83% |
|
3.70% |
|
2.74% |
|
4.94% |
|
4.90% |
|
3.48% |
|
3.32% |
|
4.81% |
|
4.96% |
|
3.17% |
|
3.89% |
|
4.27% |
|
5.94% |
|
2.90% |
|
4.80% |
|
4.29% |
|
5.06% |
|
2.66% |
|
4.86% |
|
4.40% |
|
4.07% |
6.93
Loading from the rest of the sewage outfalls was allocated in the bottom
water layer. Pollution loads from storm outfalls and other point source
discharges were included in the water quality model and were specified in the
middle layer of the model. The loading
from the
6.94
All sensitive receiver
points and monitoring stations as shown in Figure 6.1 were defined as
observation points in the HATS model to store the simulated water quality
results as a function of time.
6.95
Annual model simulations are
required under the EIA Study Brief. The seasonal change in the measured SCISTW
effluent concentrations is illustrated in Figure 6.4. To provide a realistic prediction of the
water quality impacts of HATS Stage
6.96 The measured CEPT effluent data for BOD5, TSS, TKN, NH3-N and TP were available for one complete year (from September 2005 to August 2006) as shown in Figure 6.4 for annual model simulations. The measured effluent data for the period from January 2006 to August 2006 were applied for the simulation period from January to August whilst the measured effluent data for the period from September 2005 to December 2005 were applied for the simulation period from September to December. As shown in Figure 6.4, the effluent sampling frequency varied from daily to weekly. For the purpose of model input, it was assumed that the effluent concentrations would be uniform over the period between two successive sampling occasions. The effluent concentration available for a particular sampling time was also used for the subsequent time period until the next sampling occasion.
6.97 The historical data for PO4 were only available for eight months from January 2006 to August 2006. The historical data indicated that there was no obvious difference in the trend of effluent quality for PO4 between the wet and dry seasons. For the purpose of modelling assessment, the measured 6-month effluent profile for PO4 was used repeatedly for annual simulations.
6.98 Changes of salinity (in 2006) and temperature (in 2002 – 2003) in the SCISTW effluent were also analyzed in Figure 6.4. Some changes in the salinity and temperature values were observed between the dry and wet seasons. The mean seasonal values were used for salinity and temperature. Table 6.29 summarizes the effluent values adopted for far field modelling.
Table 6.29 Effluent
Characteristics Assumed for Far Field Water Quality Modelling
Parameters |
HATS Stage 1 and HATS
Stage 2A |
HATS Stage 2B |
||
Dry |
Wet |
Dry |
Wet |
|
Temperature (oC) |
20 |
24 |
20 |
24 |
Salinity (ppt) |
12 |
9.5 |
12 |
9.5 |
5-day Biochemical Oxygen Demand
(mg/l) |
43 (mean) and 64
(95%ile)(1) (EEFS value: 68)(2) |
24(4) |
||
Suspended Solids (mg/l) |
37 (mean) and 48
(95%ile)(1)
(EEFS value: 42)(2) |
16(4) |
||
Total
Kjeldahl Nitrogen (mgN/l) |
26 (mean) and 31
(95%ile)(1)
(EEFS value: 28)(2) |
10.5(4) |
||
Ammonia Nitrogen (mgN/l) |
20 (mean) and 25
(95%ile)(1)
(EEFS value: 18)(2) |
7 (4) |
||
Total Phosphorus (mgP/l) |
2.5 (mean) and 3.1
(95%ile)(1)
(EEFS value: 3)(2) |
2(4) |
||
Orthophosphate (mgP/l) |
1.6 (mean) and 2
(95%ile)(1)
(EEFS value: 2)(2) |
1.3(4) |
||
Total Oxidized Nitrogen (mgN/l) |
0(3) |
23(3) |
||
Copper (mg/l) |
0.023(3) |
0.012(3) |
||
Silicate (mgSiO2/l) |
8.6(3) |
8.6(3) |
||
E.coli (no./100ml) |
200,000 (at Stage 1) and
20,000 (at Stage 2A) (5) |
20,000 (5) |
Notes:
(1)
Time varying effluent concentrations as seen in Figure 6.4 were used for
model input. The mean and 95
percentile values of the effluent profiles are provided in the table for
reference.
(2)
Values used under the EEFS are included in the
table for reference.
(3)
Based on assumptions used under the EEFS.
(4)
Based on the EEFS’s recommendations.
(5)
Based on the findings of the EIA Study for ADF.
6.99 For the rest of the parameters (total oxidized nitrogen and silicate) where no past effluent record was available, average values as adopted in the EEFS were used as the effluent concentrations for model input.
6.100
The effluent values for Stage
2B adopted under this EIA were based on the effluent standards recommended
under the EEFS for CEPT plus nitrification. The treatment process requirements for
Stage 2B will be confirmed by detailed investigation to be carried out at a
later stage under separate study. The effluent values for Stage 2B as shown in Table 6.29 were input to the model
constantly over the entire simulation period.
6.101 Whole Effluent Toxicity Test (WETT) is a technique to directly measure the aggregate toxic effect of an effluent. In WETT, groups of organisms of a particular species are held in test chambers and exposed to different concentrations of an aqueous test sample (i.e. effluent). Observations are made at predetermined exposure periods. At the end of the test, the responses of test organisms are used to estimate the effects of the test sample.
6.102 Two phases of WETT were conducted in December 2004 and May/June 2005 under the Minor Works Contract to determine the whole effluent toxicity of composite CEPT effluent from SCISTW and chlorinated/ dechlorinated (C/D) CEPT effluent.
6.103 Two other phases of WETT were also conducted in December 2004 and April 2005 under a separate study ([12]) to determine the whole effluent toxicity of composite secondary treated combined effluent from Tai Po Sewage Treatment Works and Sha Tin Sewage Treatment Works and (C/D) secondary treated effluent.
6.104 Five local species as listed below were used in the WETT which were considered as the “representative local species” of ecological and fisheries significance:
· Amphipod (Melita longidactyla), with 48-hour survival test
· Barnacle larvae (Balanus amphitrite), with 48-hour survival test
· Fish (Lutjanus malabaricus), with 48-hour survival test
· Shrimp (Metapenaeus ensis), with 48-hour survival test
· Diatom (Skeletonema costatum), with 7-day growth inhibition test
6.105 The toxicity tests for amphipod, barnacle larvae, fish and shrimp were to determine the acute toxicity of the effluents to the 4 animal species while the toxicity tests for diatom were to determine the chronic toxicity of the effluents to the plant species.
6.106 The species chosen and the testing protocols used for the WETT were developed by a previous study commissioned by the Agriculture, Fisheries and Conservation Department (AFCD) and were accepted by EPD and AFCD. It should be noted that the WETT results reflected the cumulative effects of all CBP species and other toxic contaminants (such as ammonia and heavy metals) that may be present in the CEPT and secondary treated effluent.
6.107 After the toxicity data for each species were obtained, the Lethal Concentration LC50 (for amphipod, barnacle larvae, fish and shrimp) and Inhibition Concentration IC50 (for diatom) value and the No-Observable-Effect-Concentration (NOEC) of both raw effluent and (C/D) effluent were determined. The WETT results are presented and assessed in later sections.
6.108
The assessment covers the impacts from HATS Stage 1, Stage 2A and
Stage 2B. According to the Brief, construction of the Project (i.e. Stage 2A)
is tentatively scheduled to commence in 2009 for
commissioning the Stage 2A scheme by 2014.
Construction of the advance disinfection facilities (before
commissioning of Stage 2A) is tentatively scheduled to commence in 2008 for
completion by 2009. The schedule of
Stage 2B implementation would be subject to the review on population / flow
build-ups and water quality conditions to be conducted in 2010/2011. For the purpose of water quality
modelling, it was assumed under the base case scenarios that Stage 2B would be
implemented in 2021. Sensitivity tests were conducted to address the possible changes of the schedule of Stage 2B implementation. The time horizons and projected HATS
flows for operational phase assessment are shown in Table 6.30.
Table 6.30 Modelling Scenarios for
Operational Phase Impact Assessment
Scenario |
Year |
Description |
Projected SCISTW Flow Rate (m3/day) |
Remarks |
1a |
2014 |
“Without Stage 2A” condition |
1550000 (A) |
Condition in 2014 under HATS Stage 1 |
1b |
2014 |
Early phase of Stage 2A |
2064000 |
|
2a |
2021 |
“Without Stage 2A” condition |
1628000 (A) |
Condition in 2021 under HATS Stage 1 |
2b |
2021 |
Late phase of Stage 2A |
2170000 |
|
2c (Sensitivity Test) |
2021 |
Late phase of Stage 2A |
2170000 |
Use less conservative storm pollution loading
(refer to S6.114 - 6.116) |
2d (Sensitivity Test) |
2021 |
Late phase of Stage 2A |
1953000 |
Use less conservative flow rate for Stage 2A
(refer to S6.117 - 6.118) |
2e (Sensitivity Test) |
Ultimate |
Stage 2A under ultimate flow |
2447000 |
Use design flow rate for Stage 2A |
2f (Sensitivity Test) |
2021 |
Late phase of Stage 2A |
2170000 |
Use of enhanced phosphate removal |
3a |
2021 |
Early phase of Stage 2B |
2170000 |
|
3b |
Ultimate |
Late phase of Stage 2B |
2447000 |
|
Note:
(A)
It is assumed that flows generated from HATS Stage
2 catchments are discharged into the marine waters via local PTW of individual
catchments.
6.109
The Project flow rates were
estimated under this Study using the latest population and employment forecast
provided by the Planning Department and the approach from the GESF ([13]). As the latest population
forecasts provided by Planning Department were only available for 2010, 2020
and 2030, the flow rates were also compiled for 2010, 2020 and 2030 only. The
ultimate flow was based on a 5% extrapolation of the projected flow for 2030.
Safety margin was included in the flow projections for all the scenarios in Table 6.30 to address the uncertainties
on the accuracy of the flow projection method. Based on the projected flows for 2010,
2020 and 2030, linear interpolation was used to determine the flow rates for
2014 and 2021.
6.110
Scenario 1a, Scenario 1b, Scenario 2a, Scenario 2b, Scenario 3a and Scenario
3b as shown in Table 6.30 were the
base case scenarios for water quality modelling. Scenario 1a was to address the water
quality impacts in 2014 without the implementation of HATS Stage 2A. This
scenario represented a condition with HATS Stage 1 in 2014. On the other hand,
Scenario 1b represented the condition during early commissioning of Stage 2A in
2014. It is anticipated that the HATS
Stage 2A would bring water quality improvement in
6.111
Scenario 2b was to address the water quality impacts under Stage 2A in
2021 just before the commissioning of Stage 2B. Year 2021 was selected as the time
horizon for modelling as it represented the worst case condition in terms of
the pollution loading in the Stage 2A effluent for organic pollutants, toxic
contaminants and nutrients etc. On
the other hand, Scenario 2a represented the “without Project” condition to
investigate the water quality impacts in the Study Area with no implementation
of Stage 2 in 2021. Scenario 3a
represented the condition during early commissioning of Stage 2B in 2021. The model results were compared between
Scenario 3a and Scenario 2b to quantify the water quality improvement due to
the implementation of Stage 2B.
Scenario 3b represents the late phase of Stage 2B under the ultimate
condition.
6.112
It was assumed that CEPT with disinfection would be provided for the HATS
effluent under Stage 1 and Stage 2A.
In addition, secondary treatment with disinfection would be provided
under Stage 2B.
6.113
The impact and toxicity of the SCISTW effluent were assessed in detail
under the human health and ecological risk assessment in Section 7 and Section
8 of this EIA report. Impacts on
the marine ecological resources due to the potential changes of water quality
at different stages of the HATS are assessed in detail under the marine
ecological impact assessment in Section 11 of this EIA report.
6.114
Domestic, commercial and industrial activities are the principal
wastewater sources in the HATS catchments.
At present, a portion of the waste load enters the coastal waters via
storm water drains. The waste load
in the storm systems is contributed from unsewered developments as well as
expedient connections from trade and residential premises and integrity
problems of aged drainage and sewerage system. There should be a continuous reduction
on the proportion of wastewater flow entering the storm system in future years
due to the progressive works on sewerage connection and rectification of
expedient connection being implemented by the HKSAR Government.
6.115 To address the uncertainties about the programme for implementing sewerage improvement and water pollution control measures in the catchments, it was assumed under the base case modelling scenarios that 10% of the pollution loads generated within the HATS catchments (except Tseung Kwan O) would be lost to the storm drainage network in all the future years. The sewerage network in Tseung Kwan O (TKO) is relatively new compared with other HATS catchments and only 5% of the load generated in the TKO area was assumed as the residual load in the storm system. The assumed proportions of sewage flow from domestic, commercial and industrial activities that would enter the storm system are given in Table 6.31. These assumptions are consistent with that adopted under other similar studies including the EIA Study for ADF and EEFS. Based on the approach of using a constant percentage of sewage interception for all the future years, the estimated storm loading would continue to increase as a result of future population growth.
Table 6.31 Assumed % of Pollution Load in the Storm System in Future Years
HATS Catchments |
2014 /
2021 / Ultimate Year |
Stage 1 |
|
Tseung Kwan O |
5% |
Chai Wan |
10% |
Shau Kei Wan |
10% |
Kwun Tong |
10% |
To Kwa Wan |
10% |
|
10% |
Kwai Chung |
10% |
Tsing Yi |
10% |
Stage 2 |
|
|
10% |
Cyberport |
10% |
Wah Fu |
10% |
|
10% |
Ap Lei Chau |
10% |
North Point |
10% |
Wan Chai |
10% |
Central |
10% |
6.116
The HATS Stage 2A effluent may contribute cumulative water quality impacts
with the storm loading discharged into the Rambler Channel (from Tsuen Wan and
Kwai Tsing) and the coastal water of West Kowloon (from
6.117
Under the base case scenarios, it was assumed that the sewage flow
discharged from the catchments of HATS would be more than 100% of the total
estimated flow that would be generated in the catchments for conservative
assessment. For example, it was
assumed that 10% of the total sewage flow generated in the Wan Chai area would
be lost to the storm drainage network.
On the other hand, the HATS flow rates were projected based on the
assumption that 100% of the total flow generated in the Wan Chai area would be
discharged to the SCISTW for treatment (i.e. 110% of the total flow generated
in Wan Chai would be discharged into the marine water). This was a conservative approach to
address the uncertainty on the amount of residual load in the storm systems
under the future conditions.
6.118
A sensitivity test, namely Scenario 2d (in Table 6.30), was conducted using a less conservative HATS flow
rate. For example, to take account
of the waste load lost to the storm as shown in Table 6.31, it was assumed that only 90% of the total sewage flow
generated in the Wan Chai area would be diverted to the SCISTW. The adjusted HATS flow rate was adopted
for the 2021 scenario as a sensitivity test to investigate the water quality
changes. As previously mentioned, safety margin was included in the flow projections for all scenarios
(including Scenario 2d) in Table 6.30
to address the uncertainties on the accuracy of the flow projection
method. Let alone these safety
factors, the 2021 base case scenarios (i.e. Scenario 2b) in Table 6.30 assumed that 100% of the
wastewater generated in the HATS catchment would be discharged into the
sewerage system. Under this sensitivity analysis (Scenario 2d), it was assumed
that only about 90% of the wastewater generated in the HATS catchment would be
discharged into the sewerage system and the rest would be lost to the storm
systems. The flow rate proposed for
Scenario 2d (1,953,000 m3/d) was therefore about 90% of the flow
rate for Scenario 2b (2,170,000 m3/d).
6.119
The EEFS concluded that secondary treatment (Stage 2B) would be needed for
the HATS in order to protect the
6.120 This sensitivity test, namely Scenario 2f, was to investigate the water quality change due to an enhanced phosphate removal of up to 80% from the Stage 2A effluent in 2021. The phosphate removal rate from the current CEPT process at SCISTW was around 40% to 50% (equivalent to an effluent PO4 concentration of about 2 mg/l). With an 80% enhanced P removal rate, the PO4 concentration in the HATS effluent could be reduced to 0.6 mg/l (based on Table 2.16 of the EEFS Final Report). The recent sewage characterization exercise conducted under this EIA study indicated that 80% removal of PO4 would be achievable from the CEPT process by increasing the ferric chloride dosage from the existing level of 10 mg/L to 40 mg/L. According to the test results, increasing the ferric chloride dosage to 40 mg/L would result in the PO4 removal percentages of about 83% in the wet season and about 94% in the dry season and the corresponding PO4 concentrations in the CEPT effluent were down to about 0.4 mg/L in the wet season and less than 0.2 mg/L in the dry season, which are generally in line with the effluent value of 0.6 mg/L assumed under the EEFS for 80% enhanced P removal. For the purpose of this sensitivity test, the EEFS value of 0.6 mg/L was assumed for conservative assessment.
6.121 The potential emergency discharges or temporary bypass of sewage effluent from HATS, which may arise during the operation and construction phase of the Project have been identified and discussed in detail in Appendix 6.1a.
6.122
Emergency discharges of diluted
preliminarily treated effluent from the PTWs to the Harbour may occur during
heavy rainfall via submarine outfalls or seawall bypasses when the existing
submarine outfalls are no longer serviceable. Based on the historical records,
emergency overflow due to heavy rainfall are low and the discharge volume is
insignificant when compared with the total sewage from HATS. As a very conservative assumption, the volume
and rate of emergency discharge at the PTWs due to heavy rainfall is calculated
using the projected peak design flow of the PTWs as well as the design capacity
difference between the PTWs and the tunnel segments. The duration of emergency
discharge associated with heavy rainfall from PTWs is assumed to be 8 hours,
which is made reference to the historical records (details refer to Appendix 6.1a). Emergency discharge via
the submarine outfall of the PTW would achieve a greater dilution and
dispersion effect as compared to the scenario via the seawall bypass. For the
purpose of this EIA, it is assumed that all the emergency discharges occur at
the PTWs during the operational phase would be via the seawall bypass for
conservative assessment. The total volume of overflow discharge
assumed in the modelling exercise was 358,848 m3.
6.123
The
North West Kowloon Pumping Station (NWKPS) is physically distinct from the
Stage 1 tunnel system. Under the upgrading of SCISTW, improvement measures to
control emergency overflow of preliminary treated effluent associated with
heavy rainfall will be provided. It is expected that the frequency and volume
of emergency overflow of preliminary treated effluent associated with heavy
rainfall from NWKPS will be significantly reduced after the upgrading of
SCISTW. For assessment purpose, the maximum discharge rate of 12,000 m3/hr
based on the historical overflow records is adopted as a worst-case scenario
(details refer to Appendix 6.1a).
Discharge duration of 8 hours is assumed based on the historical overflow
records.
6.124
One
modelling scenario,
namely Scenario A, is
proposed to address the worst case impacts for emergency overflow associated
with heavy rainfall at the late phase of Stage 2A in 2021. Scenario A assumes that sewage overflow
from the NWKPS for discharge at seawall bypass at Stonecutters Island (refer to
Section 6.123) would occur together with the sewage overflow at the seawall
bypass of all the Stages 1 & 2 PTWs (refer to Section 6.122) for a period
of 8 hours to address the worst-case impact due to the capacity constraints as
a result of heavy rain. The water
quality of the discharge is calculated based on the 3:1 mix ratio of
preliminary treated effluent and rain water following the approach adopted
under the EEFS.
6.125
Four separate model runs have been conducted to simulate the impacts for
four temporary discharge periods centred at namely neap tide high water, neap
tide low water, spring tide mid-flood and spring tide mid-ebb respectively
under both wet and dry seasons. The
model results have been analyzed to determine the sensitivity of the water
quality impacts under different discharge times. The sensitivity results indicated that
the water quality impact at the identified sensitive receivers would be similar
under the four discharge periods. Therefore only two tide conditions,
namely neap tide low water and spring tide mid-ebb respectively, are selected
for presentation. Thus, impact results are presented for four tidal statuses,
namely neap low water in dry season, spring mid-ebb in dry season, neap low
water in wet season and spring mid-ebb in wet season respectively.
6.126
The modelling scenarios have taken into account the discharge of TRC and
CBP from the disinfection facilities.
A tracer was defined at the discharge location of the Project to
determine the dilution in the vicinity of the discharge point. Tracers were also defined at other
identified concurrent discharges for cumulative impact assessment. The dilution information was used to
determine the decreases in the concentrations and to evaluate the potential
impacts. The modelling of TRC was conducted using a decay rate of 24 per day ([14])
which was based on the assumption used under the approved EIA for “Tai Po
Sewage Treatment Works Stage 5” and was also used under the ADF study. Upon our review of relevant past EIA
studies, this decay rate was the most conservative value. An even more
conservative assumption of zero decay rate was applied to the CBP discharges.
6.127
Four major sewage effluent discharges were considered in the TRC and CBP
modelling. They were the effluent
from SCISTW, Pillar Point Sewage Treatment Works (PPSTW), Tai
6.128
The initial TRC levels assumed in the effluent from TPSTW and STSTW as well
as in the cooling water discharges were based on the assumptions adopted in the
approved EIA for “Tai Po Sewage Treatment Works Stage 5”. The initial concentrations of CBP
assumed in the TPSTW and STSTW effluents and the cooling water discharges were
based on the maximum CBP levels measured in the C/D secondary treated effluent
samples as shown in Table 6.22. As the SCISTW would eventually be
upgraded to secondary treatment, the initial CBP levels in the SCISTW effluent
under Stage 2B were also based on the maximum values measured in the C/D
secondary treated effluent. The
initial CBP levels in the HATS effluent during ADF stage (Stage 1) and Stage
6.129
Modelling of TRC and CBP was to evaluate whether the Project discharges
would cause any cumulative water quality impact with other concurrent
discharges and to determine the size of the mixing zone for these
compounds. The assumptions adopted
for modelling of TRC and CBP represented the worst case scenarios for water
quality impact assessment. Assessments of the acute and chronic toxicity of TRC
and CBP were conducted under the Human Health and Ecological Risk Assessment in
Section 7 and Section 8 of this EIA report.
6.130
Sodium hypochlorite and sodium bisulphite would be adopted as the
chlorination agent and dechlorination agent respectively. The operational range of sodium
bisulphite dosage was derived from the data obtained from the bench-scale tests
as shown in Table 6.21. The upper
limits of operational range for sodium bisulphite dosage would be 11 mg/l, 4
mg/l and 2 mg/l for ADF (Stage 1), Stage
6.131
The sodium bisulphite concentrations predicted by the far field water
quality model were used to estimate the oxygen depletion in the marine
water. For conservative assessment,
all sodium bisulphate was assumed to undergo the following reaction with the
oxygen in marine water:
6.132
On a weight to weight basis, approximately 6.5 parts of sodium bisulphite
would consume 1 part of oxygen. The
level of oxygen depletion was calculated by dividing the predicted sodium
bisulphite concentration in the marine water with a factor of 6.5. The level of oxygen depletion was then
compared with the ambient DO levels to determine the extent of the potential
impact. The assessment focused on
areas in the vicinity of the Project discharge point.
Description of Emergency
Situations
6.133
Under
the current design, in the emergency
event when the tunnel systems or the submarine outfall at
6.134
Item (1) – Provision of standby unit(s)
would reduce the risk of equipment breakdown at the PTWs. In the emergency
discharge event when one or two equipment are out of operation the raw sewage
will be discharged directly to the Harbour via seawall bypass. A 50% of the
projected ultimate flow (e.g. one unit is out of service) of each PTW is
assumed to be the emergency discharge volume with a discharge duration of 8
hours.
6.135 Item (2) – In the emergency discharge event when power failure occurs at PTWs the raw sewage will be discharged directly to the Harbour via seawall bypass. It should be noted that no power failure has occurred at the PTWs since its commissioning. Discharge duration of 6 hours is assumed for EIA purpose based on the experience of other sewage treatment works e.g. Tai Po STW. The occurrence of this scenario is remote as dual power supply will be provided at all the PTWs.
6.136
Item (3) – When power failure occurs at
SCISTW, the preliminary treated effluent will be discharged directly to the
Harbour via seawall bypass at the PTWs. Discharge duration of 6 hours is
assumed based on the experience of other sewage treatment works. It should be
noted that no power failure has been occurred at SCISTW since its
commissioning. The occurrence of this scenario is remote as dual power supply
is provided at SCISTW.
6.137
Item (4) - Sufficient standby equipment and standby
treatment facilities will be provided at the SCISTW. Emergency discharge due to equipment malfunction
at SCISTW would be remote. It should be noted that no emergency discharge due
to equipment failure has been occurred at SCISTW since its commissioning.
Discharge duration of 6 hours is assumed based on the experience of other
sewage treatment works. Discharge
of the preliminary treated effluent directly to the Harbour via seawall bypass
at the PTWs would cover the worst-case impact due to equipment failure at
SCISTW.
6.138 Item (5) – Failure of dechlorination could be caused by the malfunction of the pumping system or power failure at the dechlorination unit. It is considered that the plant operator would be notified immediately after any power failure or pump failure via the control system of the treatment plant. It is also considered that the chlorination dosing process could be practically stopped within 30 minutes upon notification of the dechlorination plant failure. Thus, when failure of dechlorination occurs, the reaction time to shut down the chlorination unit to avoid excessive discharge of TRC into the marine environment would be about 30 minutes. During the period when the dechlorination unit is failed, a higher level of TRC would be present in the effluent.
Modelling Scenarios for Power /
Equipment Failure
6.139
Two modelling scenarios, namely
Scenarios B and C respectively, were simulated to address the worst case
impacts for emergency discharge due to equipment or power failure at SCISTW or
at individual Stage 2 PTWs during operational phase.
6.140
Scenario B covers the worst-case impact due to power or equipment failure at
SCISTW as described in Item (3) and Item (4) above. This scenario assumes that
the discharge of screened sewage at the seawall bypass of all the PTWs would
occur at the same time in 2021 for a period of 6 hours. The projected ultimate flow was used to
calculate the pollution loading of the emergency discharge of 6 hours
(equivalent to a total discharge volume of 612,000 m3) for
conservative assessment.
6.141
Scenario C is to address the worst-case impact from seawall bypass of raw
sewage at individual PTW within the Stage 2 catchment due to power or equipment
failure assuming that 100% of the ultimate flow would be discharged at the
seawall bypass for a period of 8 hours in 2021 to cover the impacts described
in Item (1) and Item (2) above.
Based on the past records, power / equipment failure has not happened
simultaneously at more than one PTW before. Therefore, model simulation was
performed for only one PTW at a time to evaluate the extent of impact due to
the sewage bypass at one individual PTW alone. The model simulation was
performed for each of the Stage 2 PTW. The projected average ultimate flow for
each PTW was used for model simulation.
6.142
Under
each modelling scenario, four separate model runs were conducted to simulate
the impacts for four temporary discharge periods centred at (i) neap tide low
water in dry season, (ii) neap tide low water in wet season, (iii) spring tide
mid-ebb in dry season and (iv) spring tide mid-ebb in wet season respectively.
6.143
More
details of the emergency discharge scenarios are given in the TN3 in Appendix 6.1a.
Modelling Scenarios for Temporary
Failure of Disinfection Facilities
6.144
Water
quality impacts in relation to the temporary failure of disinfection
facilities, refer to Item (5) above, have been fully assessed under the
separate EIA for “HATS Provision of Disinfection Facilities at SCISTW (ADF)”
and are therefore not re-modelled under this EIA (also see Section 6.18).
Temporary Discharge of
Undisinfected Effluent
6.145
Water quality modelling was carried out under the ADF EIA to address the impact
from the discharge of undisinfected effluent under temporary failure of
disinfection facilities due to the lack of power supply as well as other
incidents such as pump or equipment failure. The modelling also addressed the impacts
from the discharge of undisinfected effluent in the event of temporary failure
of dechlorination where the chlorination plant would need to be shutdown to
avoid excessive discharge of TRC. In the event of emergency situations when the disinfection facilities fail or are shutdown, treated (but undisinfected) effluent
would be discharged into the sea via the submarine outfall of SCISTW. Modelling was carried out under the ADF
EIA for six scenarios as shown in Table 6.31a to simulate the impact due to the shutdown
of the disinfection facilities.
Table 6.31a Modelling Scenarios for Emergency Discharge of Undisinfected CEPT Effluent
Scenario modelled under
the ADF EIA |
Stage |
Total
Discharge Period (hours) |
Assumed E.coli Concentration in Undisinfected
CEPT Effluent (no. per 100 ml) |
5a |
Early phase of ADF stage |
6 |
1.0E+7 (2) |
5b |
Early phase of ADF stage |
24 (1) |
|
6a |
Late phase of ADF stage |
6 |
|
6b |
Late phase of ADF stage |
24 (1) |
|
7a |
Late phase of Stage 2A |
6 |
|
7b |
Late phase of Stage 2A |
24 (1) |
Notes:
(1)
Past emergency discharge records available from various
sewage treatment works indicated that the longest period of emergency discharge
would be less than 6 hours. Thus,
emergency discharge for 24 hours is an extremely remote scenario for the
purpose of worst-case assessment only.
(2)
The assumed E.coli
level in undisinfected CEPT are based on the bench-scale chlorination tests
conducted by DSD in 2002 and 2005.
6.146
Late phase of Stage 2A (Scenarios 7a and 7b) represents the worst case in
terms of the E.coli loading from the
undisinfected CEPT effluent. Scenarios
5a, 5b, 6a and 6b are selected to address the effect during the ADF stage.
Although the HATS flow under the ultimate scenario would be larger than that
under Stage 2A, the E.coli
concentration in the undisinfected secondary treated effluent would be much
smaller than that in the undisinfected CEPT effluent. The impact due to emergency discharge
under the ultimate scenario was therefore not assessed. More detailed
description of the modelling scenarios can be referred to the approved EIA
report for ADF.
Temporary Discharge of Chlorinated
Effluent
6.147
Table 6.31b shows the scenarios modelled under the EIA Study for ADF for temporary
failure of dechlorination plant. Scenario 8a and Scenario 9a covered an emergency
discharge period of 40 minutes which takes into account the reaction time for
DSD to shut down the chlorination plant (30 minutes) plus the assumed chlorine
retention time of 10 minutes. Scenario 10a covered an emergency discharge
period of 60 minutes which takes into account the reaction time for DSD to shut
down the chlorination plant (30 minutes) plus the assumed chlorine retention
time of 30 minutes. Stage 2B was not assessed as Stage 2A already
represents the worst case in terms of the Project discharge.
Table 6.31b Modelling Scenarios for Emergency Discharge of TRC
Scenario modelled under the ADF EIA |
Stage |
Assumed Chlorine Retention Time (minute) |
Reaction Time to Shut Down the Chlorination Plant
(minutes) |
Total Discharge Period |
Assumed Chlorine Residuals without Dechlorination
(mg/l) |
8a |
Early phase of ADF stage |
10 |
30 |
40 minutes |
6.7 |
9a |
Late phase of ADF stage |
10 |
30 |
40 minutes |
6.7 |
10a |
Late phase of Stage 2A |
30 |
30 |
60 minutes |
5.5 |
6.148
Based on data from the
bench-scale chlorination studies, the maximum chlorine residuals at the ADF
stage and Stage 2A would be in the range of 4.8 - 6.3 mg/l and 4.3 – 5.3 mg/l respectively.
The ranges identified from the bench-scale studies are based on the chlorine
dosage of 15 and 20 mg/l. The chorine residuals assumed for the emergency
scenarios as shown in Table 6.31b are 6.7 and 5.5 mg/l for ADF and Stage
2A respectively which are slightly higher than the ranges identified from the
bench-scale studies. Based on the updated design information, the operational
chlorine dosage would range from 11 to 15 mg/l to achieve geometric mean E.coli
standard of 200,000 no. per 100ml for ADF and 10 to 14 mg/l to achieve the
geometric mean standard of 20,000 no. per 100 ml for Stage 2A as shown in
Table 6.21. The TRC at the dechlorination point of SCISTW will be
controlled within range of 1 to 4 mg/l during the operation. The maximum chlorine
dosage of 20 mg/l adopted in the bench-scale studies and the chlorine residuals
adopted under the modelling scenarios are therefore conservative.
6.149
No dredging and filling activity
would be needed for Stage 2A construction.
The general construction works would be primarily land-based. Key water quality issues associated with
the land-based construction would include the impacts from site run-off, sewage
from workforce, accidental spillage and discharges of wastewater from various
construction activities.
6.150 The proposed upgrading works at Aberdeen PTW would require seawall re-construction. The seawall re-construction works would involve excavation of seawall and no dredging would be required. Excavation of the existing seawall would involve removal of seawall blocks and gravel only, which would not create adverse SS impact. Fines content in the filling materials in the seawall would be negligible and loss of fill material during seawall demolition was not expected.
6.151 The implementation of measures to control runoff and drainage would be important for the construction works adjacent to the marine water in order to prevent runoff and drainage water with high levels of SS from entering the water environment. Practical water pollution control measures / mitigation proposals were recommended to prevent construction materials from discharging into the sea, so that any effluent discharged from the construction site would comply with the criteria of WPCO.
6.152
During
the design stage of the Project, there is a need for the design
consultant to prepare a construction sequence plan for the upgrading of SCISTW
and the PTWs on
6.153
Based
on the requirements specified in the Consultancy Brief of the design
consultancy “HATS Stage
·
Item (a) - Modification works required
for the existing main pumping station and Northwest Kowloon Pumping Station
(NWKPS) at SCISTW to enhance maintainability, reliability, operational
flexibility and pumping capacity for proper integration with the new works to
be constructed under HATS Stage
· Item (b) - Provision of an interconnection between the existing main influent pumping station and the new influent pumping station on Stonecutters Island to enhance system reliability, flexibility and maintainability of the E&M equipment inside the pumping stations.
·
It should be noted that Item
(a) and Item (b) can be implemented at the same time. When the above
modification works are required, sewage bypass from the Stage 1 tunnel system
to
·
Item (c) - The existing NWKPS will be inadequate
to handle the future projected flow. Upgrading of the existing NWKPS or
diversion of excess flow to the new influent pumping station would be required.
Discharge of preliminarily treated sewage from
6.154
It
should be noted that the upgrading scheme for the upgrading of SCISTW has not
been formulated at this EIA stage. The temporary sewage bypass, if needed,
would be scheduled to occur during the construction phase of the Project or
early commissioning of the Project.
For allowing more flexibility to the design consultant in formulating
the upgrading scheme for SCISTW, the worst-case water quality impacts arising
from the temporary sewage bypass in 2014 without the HATS Stage 2A have been
assessed in this EIA assuming that the discharge of preliminary treated
effluent at Stage 2 PTWs would occur together with the temporary sewage bypass
at Stage 1 PTWs or NWK PTW. The water quality impact is considered smaller if
the temporary bypass is scheduled after commissioning of Stage 2A in 2014 as
the background water quality would be improved after the sewage effluents from
the Stage 2 PTWs are intercepted to the SCISTW for treatment. In order to
assess the magnitude of the worst-case water quality impacts, the predicted
results from the sewage bypass scenarios are compared with the scenario under
the normal condition in 2014 (without the HATS Stage 2A). The discharge
duration and timing of the temporary sewage bypass are summarized in the table
below.
Item |
Expected
Duration / Timing and Discharge Routes |
Modelling Scenario |
(a) Modification to the existing main
pumping station (refer to Figure 6.4c) See
Note 1 |
Option 1: Expected timing & duration: Two weeks in dry season
at late phase of HATS Stage 1 in or before 2014 Discharge routes:
Preliminary treated effluent ® submarine outfalls at the Stage 1 PTWs (except for NWK PTW) and Stage 2 PTWs Sewage flow from NWK PTW will be
under CEPT process at SCISTW and discharged via the submarine outfall of
SCISTW |
Water quality impact was
modelled under Scenario D (refer to Section 6.157). Option 1 (i.e. discharge
of preliminary treated effluent from Stage 1 and Stage 2 PTWs) with projected
flow and load in 2014 was assumed under Scenario D for worst-case assessment. |
Option 2: Expected timing &
duration:
Two weeks in dry season during early commissioning of HATS Stage 2A in 2014 Discharge
routes: Preliminary treated effluent ®
submarine outfalls at the Stage 1 PTWs
(except for NWK PTW) Sewage
flow from NWK PTW and all the Stage 2 PTWs will be under CEPT process at
SCISTW and discharged via the submarine outfall of SCISTW |
||
(b)
Interconnection between the existing main pumping station and the new pumping
station (refer to Figure 6.4c) See
Note 1 |
Option 1: Expected timing &
duration:
Two weeks in dry season at late phase of HATS Stage 1 in or before 2014 Discharge
routes: Preliminary treated effluent ®
submarine outfalls at the Stage 1 PTWs
and Stage 2 PTWs (except for NWK PTW) Sewage
flow from NWK PTW will be under CEPT process at SCISTW and discharged via the
submarine outfall of SCISTW |
Water quality impact was
modelled under Scenario D (refer to Section 6.157). Option 1 (i.e. discharge
of preliminary treated effluent from Stage 1 and Stage 2 PTWs) with projected
flow and load in 2014 was assumed under Scenario D for worst-case assessment. |
Option 2: Expected timing &
duration:
Two weeks in dry season during early commissioning of HATS Stage 2A in 2014 Discharge
routes: Preliminary treated effluent ®
submarine outfalls at the Stage 1 PTWs
(except for NWK PTW) Sewage
flow from NWK PTW and all the Stage 2 PTWs will be under CEPT process at
SCISTW and discharged via the submarine outfall of SCISTW |
||
(c)
Modification to the existing Northwest Kowloon Pumping Station (refer to Figure 6.4b) |
Option 1: Expected timing &
duration:
Two weeks at late phase of HATS Stage 1 in or before 2014 Discharge
routes: Preliminary treated effluent from NWK PTW ®
seawall bypass at Sewage
flow from Stage 1 PTWs (except NWK PTW) will be under CEPT process at SCISTW
and discharged via the submarine outfall of SCISTW Preliminary
Treated effluent from Stage 2 catchments ®
submarine outfalls of Stage 2 PTWs |
Water quality impact was
modelled under Scenario E (refer to Section 6.158). Option 1 (i.e. discharge
of preliminary treated effluent from Stage 2 PTWs) with projected flow and
load in 2014 was assumed under Scenario E for worst-case assessment. |
Option 2: Expected timing &
duration:
Two weeks during early commissioning of HATS Stage 2A in 2014 Discharge
routes: Preliminary treated effluent from NWK PTW ®
seawall bypass at Sewage
flow from Stage 1 PTWs (except NWK PTW) and all the Stage 2 PTWs will be
under CEPT process at SCISTW and discharged via the submarine outfall of
SCISTW |
Note 1: Item (a) and
Item (b) could occur together at the same time or separately at different
timing. As confirmed by the model
prediction, water quality impact due to the temporary sewage bypass would
return to normal condition quickly (within a few days) after the temporary
sewage bypass. The water quality impact due to Item (a) alone, Item (b) alone
and Item (a) and Item (b) together would be the same and covered under Scenario
D.
6.155
As
a worst-case scenario, the discharge duration of 2 weeks is assumed for the above
temporary sewage bypass scenarios, based on the latest information provided by
the design consultant of this Project. The design consultancy should take
effort to schedule the modification and interconnection works, if needed, at
the same time in order to minimise the discharge duration. The design
consultancy should also take effort to reduce the discharge duration for the
modification to the existing NWKPS e.g. by diverting the flow from NWK PTW to
the new influent pumping station before constructing the modification works for
the NWKPS. It is also recommended that the temporary
sewage bypass at the Stage 1 PTWs should be scheduled in the dry season or low
flow period (November to February) to minimize the potential water quality
impact. For conservative
sake, the total flow from NWK PTW is assumed to be discharged to the Harbour
via the seawall bypass at
6.156
Two
worst-case modelling scenarios have been assessed for the temporary sewage
bypass, namely Scenario D and Scenario E respectively.
Scenario D
6.157
Scenario
D aims to assess the worst-case sewage bypass of screened sewage at the
submarine outfalls ([15])
of all the Stage 1 PTWs (except for NWK PTW) for a period of 2 weeks in 2014
during the construction phase. It should be noted that periodic flushing of these existing submarine outfalls is being
carried out by DSD to maintain the serviceability of these outfalls. Sewage
flow from NWK PTW will be under CEPT process at SCISTW and discharged via the
submarine outfall of SCISTW during the sewage bypass period (refer to Figure 6.4c).
Scenario D addresses the water quality impacts due to the modification works at
the existing main pumping station and the interconnection between the existing
main pumping station and the new pumping station, i.e. Items (a) and (b)
respectively in Section 6.153. The projected average flow in 2014 for the Stage
1 PTWs was used to calculate the pollution loading for model input. It is
assumed that the sewage bypass event will occur for a period of 2 weeks
covering a typical spring-neap tidal cycle in the dry season.
Scenario E
6.158
Scenario
E covers the worst-case impact due to the modification work at the existing NWK
PTW during the late phase of Stage 1, i.e. Item (c) in Section 6.151. It is
assumed that the sewage flow from the NWK PTW would be discharged to the
Harbour via the seawall bypass at
6.159
More
details of the sewage bypass scenarios are given in the TN3 in Appendix 6.1a.
6.160 The coastline configurations adopted for the 2014 scenario are shown in Figure 6.5. The assumed coastline configurations for 2021 and ultimate stage are shown in Figure 6.6. Based on the latest information from the “Agreement No. CE54/2001 Wan Chai Development Phase II (WDII) Planning and Engineering Review”, construction of WDII is scheduled for commencement in 2009 for completion by 2016. Based on the construction programme, seawall construction for most of the WDII reclamation stages would be completed before 2014. Thus, the reclamation limit for WDII was included in the 2014, 2021 and ultimate coastline.
6.161 The reclamations for South East Kowloon Development (SEKD) and Yau Tong Bay Reclamation (YTBR) were excluded as their concept plans were not yet confirmed. It should be noted that the “no reclamation” scenario is being considered for the SEKD but the feasibility of such scenario is still subject to detailed investigation. Table 6.32 indicates the reclamation projects to be included in the far field model at different time horizon. The reclamation limit for each specific project can be referred to Figure 6.5 and Figure 6.6.
6.162
The methodology for compiling the pollution
loading inventory followed that adopted under the ADF study except that the
latest planning data obtained under this EIA for 2010, 2020 and 2030 were
used. Based
on the planning data, the pollution loading generated in different catchments
were compiled for 2010, 2020 and 2030 only. Loading for the ultimate scenario was
based on a 5% extrapolation of the 2030 loading. Linear interpolation was adopted to
determine the loading for 2014 and 2021. The inventory incorporated all possible
pollution sources within the
6.163 Whole effluent toxicity tests (WETT) were conducted to determine the whole effluent toxicity of C/D CEPT effluent from SCISTW and C/D secondary treated effluent from Tai Po Sewage Treatment Works (TPSTW) and Sha Tin Sewage Treatment Works (STSTW) for the following five local marine species:
l Amphipod (Melita longidactyla), with 48-hour survival test
l Barnacle larvae (Balanus amphitrite), with 48-hour survival test
l Fish (Lutjanus malabaricus), with 48-hour survival test
l Shrimp (Metapenaeus ensis), with 48-hour survival test
l Diatom (Skeletonema costatum), with 7-day growth inhibition test
6.164 The toxicity tests for amphipod, barnacle larvae, fish and shrimp were conducted to determine the acute toxicity of the effluents to the 4 animal species while the toxicity tests for diatom were to determine the chronic toxicity of the effluents to plants. Table 6.33 and Table 6.34 summarize the results obtained in the WETT for CEPT effluent whilst Table 6.35 and Table 6.36 give the results for secondary treated effluent.
Table 6.33 Summary of WETT Result for CEPT Effluent (Acute Toxicity)
NOEC b |
48-hr LC |
NOEC b |
||
Notes: a 48-hr LC50, the
lethal concentration of effluent to 50% of test animals after 48 hours of
exposure.
b No-Observable-Effect-Concentration,
the highest concentration of effluent producing effects not significantly
different from responses to controls
N.D = Not Determined, less than 50%
mortality was recorded when animal species were exposed to the highest
concentration of effluent
Table 6.34 Summary of WETT Result for CEPT Effluent (Chronic Toxicity)
NOEC b |
7-day IC50a |
NOEC b |
||
Notes: a 7-day IC50, the inhibition
concentration to 50% of organisms after 7 days of exposure.
b
No-Observable-Effect-Concentration, the highest concentration of effluent
producing effects not significantly different from responses to controls
Table 6.35 Summary of WETT Result for Secondary Treated Effluent (Acute Toxicity)
Test Species |
Chlorinated/Dechlorinated
Secondary Treated Effluent |
|||
48-hr LC |
NOEC |
|||
N.D1 |
N.D2 |
|||
N.D1 |
N.D2 |
N.D1 |
N.D2 |
|
N.D1 |
N.D2 |
N.D1 |
N.D2 |
|
N.D1 |
N.D2 |
N.D1 |
N.D2 |
N.D = Not Determined,
1 LC50 could not be
determined - less than 50% mortality was recorded when animal species were
exposed to the highest concentration of effluent
2 NOEC could not be determined - the
highest concentration of effluent did not produce effects significantly
different from controls
Table
6.36 Summary of WETT
Result for Secondary Treated Effluent (Chronic Toxicity)
Test Species |
||||
NOEC |
7-day IC50 |
NOEC |
||
N.D1 |
N.D2 |
N.D1 |
N.D2 |
N.D = Not
Determined,
1 IC50 could not
be determined - less than 50% growth inhibition was recorded when plant species
were exposed to the highest concentration of effluent
2 NOEC could not be
determined - the highest concentration of effluent did not produce effects
significantly different from controls
6.165 The WETT results indicated that both CEPT effluent with no C/D and CEPT effluent with C/D did not exert acute toxicity effect to amphipod, fish and shrimp as no 48-hr LC50 was found (Table 6.33). However, LC50 and IC50 were observed for barnacle larvae and diatom respectively which implied that some degree of acute and chronic toxicity effect was exerted on barnacle larvae and diatom respectively from both the CEPT effluent with no C/D and CEPT effluent wth C/D.
6.166 Statistical analysis was conducted for the toxicity test data of barnacle larvae and diatom to determine whether the C/D process induced additional toxicity in the CEPT effluent. Two-way analysis of variance (ANOVA) test using software SigmaStat was conducted, which compared the difference between the toxicity data of composite CEPT effluent with no C/D and CEPT effluent with C/D. The analysis showed that the C/D process did not induce statistically significant difference to the toxic effect in CEPT effluent to barnacle larvae and diatom, i.e. the C/D process did not induce additional toxicity.
6.167
Based on the WETT
tests conducted for the effluent from TPSTW and STSTW, no LC50
values could be derived for fish, shrimp, amphipod and barnacle larvae (Table 6.35). Also, no IC50 value could
be calculated as the maximum growth inhibition for diatoms was low (Table 6.36). Based on the statistical tests, no
significant difference was found between the seawater control and various
strengths (up to 100%) of secondary treated effluent samples with and without
C/D. Hence, it was concluded that
the C/D secondary treated effluent samples would not pose any acute or chronic
toxicity to the test organisms.
6.168 Only four scenarios, namely 1b, 2b, 2e and 3b (refer to Table 6.30), were presented for near field water quality assessment as they represented the worst-case in terms of the HATS pollution loading in 2014, 2021 and ultimate stage. Full description of the near field modelling approach and results are provided in Appendix 6.1.
6.169 Concentrations of TRC at the edge of the zone of initial dilution (ZID) were calculated based on the near field modelling results. The TRC standard of 0.2 mg/l (at 95%ile) was assumed as the TRC concentration in the C/D HATS effluent for the purpose of near field modelling.
6.170 Based on the HATS survey data, the measured ambient TRC levels in the marine water were all under the detection limit. Given the fact that TRC would undergo decay in marine water, it was anticipated that the ambient TRC concentration, if any, would be minimal. For the purpose of calculation, the ambient TRC concentration was assumed to be negligible.
6.171 Based on the minimum initial dilutions predicted by the near field model, the TRC concentration at the edge of the ZID was calculated and the results are summarized in Table 6.37.
Table 6.37 Predicted
TRC at Edge of ZID
Scenario (refer to Table 6.30) |
Description |
Minimum Initial Dilution |
TRC concentration at Effluent
(mg/l)1 |
Predicted Concentration at Edge of
ZID (mg/l) 2 |
Criterion (mg/l) 3 |
% of Criterion |
1b |
2014 – Early Stage 2A |
39 |
0.2 |
0.0051 |
<0.013 |
39% |
2b |
2021 – Late Phase of
Stage 2A |
38 |
0.0053 |
41% |
||
2e (sensitivity Test) |
Stage 2A at Design Flow |
35 |
0.0057 |
44% |
||
3b |
Ultimate - Stage 2B |
35 |
0.0057 |
44% |
Notes: 1. TRC standard
at 95%ile
2.
TRC at edge of ZID = TRC at effluent
/ minimum initial dilution
3. TRC
criterion at edge of ZID, daily maximum (see Table 6.9)
6.172 As shown in Table 6.37, with TRC concentration at effluent as 0.2 mg/l, the predicted TRC concentrations at the edge of ZID for the 2014, 2021 and ultimate scenarios would be 0.0051, 0.0053 and 0.0057 mg/l respectively which were well below the criterion of 0.013 mg/l.
6.173 Concentrations of UIA at the edge of the zone of initial dilution (ZID) were calculated for 1-hour average and 4-day average based on the minimum initial dilutions predicted by the near field model, and the results are summarized in Table 6.38. The annual mean UIA levels were assessed using the far field water quality modeling results provided in later sections.
Table 6.38 Predicted
Unionized Ammonia at edge of ZID
UIA |
Minimum
Initial Dilution |
Effluent
Concentration |
Ambient
Concentration |
Predicted
Concentration at Edge of ZID |
Criteria |
Contribution
from HATS |
Scenario 1b – 2014 Early Phase of HATS Stage
2A |
||||||
1-hour
average (mg/l as NH3) |
39 |
2.08 Notes 1, 6 |
0.0093 Note 4 |
0.062 |
0.233 |
85% |
4-day
average (mg/l as NH3) |
39 |
1.79 Notes 2, 6 |
0.0040 Note 5 |
0.050 |
0.035 |
92% |
Scenario 2b – 2021 Late Phase of HATS
Stage 2A |
||||||
1-hour
average (mg/l as NH3) |
38 |
2.08 Notes 1, 6 |
0.0093 Note 4 |
0.064 |
0.233 |
85% |
4-day
average (mg/l as NH3) |
38 |
1.79 Notes 2, 6 |
0.0040 Note 5 |
0.051 |
0.035 |
92% |
Scenario 2e – Sensitivity Test - HATS Stage
2A at Design Flow Rate |
||||||
1-hour
average (mg/l as NH3) |
35 |
2.08 Notes 1, 6 |
0.0093 Note 4 |
0.068 |
0.233 |
86% |
4-day
average (mg/l as NH3) |
35 |
1.79 Notes 2, 6 |
0.0040 Note 5 |
0.055 |
0.035 |
93% |
Scenario 3b – Ultimate Stage of HATS Stage
2B |
||||||
1-hour
average (mg/l as NH3) |
35 |
0.30 Notes 3, 6 |
0.0093 Note 4 |
0.018 |
0.233 |
48% |
4-day
average (mg/l as NH3) |
35 |
0.30 Notes 3, 6 |
0.0040 Note 5 |
0.012 |
0.035 |
67% |
Notes: 1. Maximum value
from actual measurements of CEPT effluent at SCISTW from September 2005 to
August 2006 (Table 6.25).
2. Maximum 4-day
running average value from actual measurements of CEPT effluent at SCISTW from
September 2005 to August 2006 (Table
6.25).
3. Maximum concentration measured in the BAF effluent collected under
the EEFS for whole effluent toxicity testing.
4. Maximum value from actual measurements at
EPD station WM3 in 2000 (during the pre-HATS period) (Table 6.23).
5. 90th
percentile value from
actual measurements at EPD station WM3 in 2000 (during the pre-HATS period) (Table 6.23).
6. The
total ammonia is converted to unionized ammonia by applying a contribution of
unionised ammonia in total ammonia of 5.9% (based on 90th percentile ambient
values of 26.5 oC, 32.0 ppt and pH 8.1 in Table 6.23). The unionized ammonia level is converted from N to NH3 by dividing the measured level (as N)
by a factor of 0.822.
6.174 The near field assessment results indicated that the Project effluent would not comply with the WQC for 4-day average UIA during the Stage 2A.
6.175 Based on the WQO, changes in salinity due to human activity should not exceed 10% of ambient. Changes in pH and temperature should not exceed 0.2 and 2oC respectively and the pH values should be within the range of 6.5 to 8.5. The EEFS also established the same criteria for pH and temperature. As the measured pH values for both CEPT effluent (Figure 6.4) and ambient water (Table 6.23) were all within 6.5 to 8.5, there would be no exceedance of the WQO and WQC for pH under all the assessment scenarios. The minimum initial dilution rates predicted by the near field model were used to calculate the maximum changes in salinity and temperature at the edge of the ZID and the results are given in Table 6.39 to Table 6.40.
Table 6.39 Predicted
Salinity at Edge of ZID
Scenario |
Description |
Minimum Initial Dilution |
Minimum Salinity at Effluent
(ppt)1 |
Maximum Ambient
Salinity (ppt)2 |
Maximum change in
Salinity from Ambient 2 |
Criterion |
1b |
2014 – Early Stage 2A |
39 |
8.27 |
32.8 |
1.9% |
<10% |
2b |
2021 – Late Phase Stage
2A |
38 |
2.0% |
|||
2e (sensitivity Test) |
Stage 2A at Design Flow |
35 |
2.1% |
|||
3b |
Ultimate - Stage 2B |
35 |
2.1% |
Notes: 1
Minimum value from actual measurements of CEPT effluent at SCISTW from
September 2005 to August 2006 (Figure 6.4).
2 Maximum
value from actual measurements at EPD
station WM3 in 2000 (Table 6.23).
Table 6.40 Predicted
Temperature at Edge of ZID
Scenario |
Description |
Minimum Initial Dilution |
Maximum Value at Effluent (oC)
1 |
Minimum Ambient Value (oC) 2 |
Maximum change from
Ambient (oC) 2 |
Criterion (oC) |
1b |
2014 – Early Stage 2A |
39 |
29 |
16.3 |
0.33 |
<2 |
2b |
2021 – Late Phase Stage
2A |
38 |
0.33 |
|||
2e (sensitivity Test) |
Stage 2A at Design Flow |
35 |
0.36 |
|||
3b |
Ultimate - Stage 2B |
35 |
0.36 |
Notes: 1 Maximum value from actual measurements of
CEPT effluent at SCISTW from September 2005 to August 2006 (Figure 6.4).
2 Minimum value from actual measurements at EPD station WM3 in 2000 (Table 6.23).
6.176 The near field assessment results indicated that full compliance with the WQO and WQC for salinity and temperature would be achieved under all the assessment scenarios.
6.177 The near field water quality criteria provided for metals and other selected organic and inorganic contaminants were based on 90% of occurrences. The contaminant levels at the edge of the ZID were calculated by applying the 10th percentile initial dilutions predicted by the near field model and the results are summarized in Table 6.41 and Table 6.42 for Stage 2A and Stage 2B respectively.
6.178 The concentrations predicted at the edge of the ZID for all selected parameters (except sulphide and surfactants) complied with their respective criteria. For sulphide (under Stage 2B) and surfactant (under Stage 2A and Stage 2B) in which the criteria were exceeded, the ambient concentrations exceeded the criteria themselves, and the amount contributed by the HATS effluent was small. The extent of sulphide exceedance contributed by the Stage 2A effluent was however larger than that by the Stage 2B effluent.
Table 6.41 Predicted
Contaminant Concentrations at the edge of the ZID for Stage 2A
Parameter |
Maximum Effluent Value (mg/l) 1 |
10th Percentile
Initial Dilution |
Maximum Background Value (mg/l) 2 |
Predicted Concentration at
Edge of ZID (mg/l) |
Criteria (mg/l) |
Contribution from HATS
Discharge |
||||||
Scenario 1b – 2014 Early Phase of Stage 2A |
Scenario 2b – 2021Late Phase of Stage 2A |
Scenario2e – Sensitivity Test – Stage 2A at Design Flow |
Scenario 1b – 2014 Early Phase of Stage 2A |
Scenario 2b – 2021 Late Phase of Stage 2A |
Scenario2e – Sensitivity Test – Stage 2A at Design Flow |
Scenario 1b – 2014 Early Phase of Stage 2A |
Scenario 2b – 2021Late Phase of Stage 2A |
Scenario2e – Sensitivity Test – Stage 2A at Design Flow |
||||
Arsenic |
1.49 |
52 |
53 |
49 |
1.48 |
1.48 |
1.48 |
1.48 |
20 |
0.01% |
0.01% |
0.01% |
Chromium, total |
18.2 |
0.55 |
0.89 |
0.88 |
0.91 |
50 |
38% |
38% |
40% |
|||
Copper |
55.7 |
2.25 |
3.28 |
3.26 |
3.34 |
5 |
31% |
31% |
33% |
|||
Mercury |
0.0294 |
0.00006 |
0.0006 |
0.0006 |
0.0007 |
0.21 |
90% |
90% |
91% |
|||
Nickel |
28.5 |
1.02 |
1.55 |
1.54 |
1.58 |
5 |
34% |
34% |
35% |
|||
Zinc |
44.1 |
3.54 |
4.32 |
4.31 |
4.37 |
20 |
18% |
18% |
19% |
|||
Sulphide |
4900 |
48 |
141 |
140 |
147 |
20 |
66% |
66% |
67% |
|||
Surfactants |
4600 |
400 |
481 |
479 |
486 |
30 |
17% |
16% |
18% |
|||
Phenol |
< 1 |
< 1 |
< 1 |
< 1 |
< 1 |
5 |
0% |
0% |
0% |
|||
Cyanide |
< 2 |
< 2 |
< 2 |
< 2 |
< 2 |
5 |
0% |
0% |
0% |
Notes: 1. Maximum concentration measured in
the CEPT effluent (Table 6.24).
2.
Maximum
concentration measured in the ambient water (Table 6.19).
Table 6.42 Predicted
Contaminant Concentrations at the edge of the ZID for Stage 2B
Parameter |
Maximum Effluent Value (mg/l) 1 |
10th Percentile
Initial Dilution (Stage 2B at Design Flow) |
Maximum Background Value (mg/l) 2 |
Predicted Concentration at
Edge of ZID (mg/l) |
Criteria (mg/l) |
Contribution from HATS
Discharge |
Arsenic |
0.88 |
49 |
1.48 |
1.47 |
20 |
-0.83% |
Chromium, total |
8.45 |
0.55 |
0.71 |
50 |
23% |
|
Copper |
9.98 |
2.25 |
2.41 |
5 |
7% |
|
Mercury |
0.00348 |
0.00006 |
0.00013 |
0.21 |
54% |
|
Nickel |
22.3 |
1.02 |
1.45 |
5 |
30% |
|
Zinc |
11.8 |
3.54 |
3.71 |
20 |
5% |
|
Sulphide |
53 |
48 |
48 |
20 |
0% |
|
Surfactants |
380 |
400 |
400 |
30 |
0% |
|
Phenol |
< 1 |
< 1 |
< 1 |
5 |
0% |
|
Cyanide |
< 2 |
< 2 |
< 2 |
5 |
0% |
Notes: 1. Maximum concentration measured in
the secondary treated effluent (Table
6.24).
2.
Maximum
concentration measured in the ambient water (Table 6.19).
6.179
Based on the minimum initial
dilutions predicted by the near field model, the acute toxicity unit (TUa) ([16])
at the edge of the ZID was calculated and the results are summarized in Table 6.43.
Table
6.43 Summary of Acute
Toxicity Unit (TUa) at Edge of ZID
Scenario |
Minimum Initial Dilution |
LC50 Detected for Barnacle Larvae in the WETT 1 |
TUa at Effluent 2 |
Predicted TUa at Edge of ZID (mg/l) 3 |
Criterion 4 |
% of Criterion |
1b – 2014 Early Stage 2A
|
39 |
40.2% |
2.49 |
0.064 |
<0.3 |
21% |
2b – 2021 Late Phase
Stage 2A |
38 |
0.065 |
22% |
|||
2e – Stage 2A at Design
Flow |
35 |
0.071 |
24% |
Note:
1.
Lowest LC50 of 40.2% was detected
in C/D CEPT effluent for barnacle larva (see Table 6.33)
2.
TUa = 100/LC50
3.
TUa at edge of ZID = TUa at
effluent / minimum initial dilution
4.
Toxicity criterion for near field
modelling (see Table 6.9)
6.180 As shown in Table 6.43, the predicted TUa at the edge of ZID for Stage 2A were well below the criterion of 0.3. As discussed before, the C/D secondary treated effluent samples would not pose any acute toxicity to the test organisms. Therefore, there was no TUa for the C/D secondary treated effluent.
6.181
As indicated in Appendix 6.1, the average dimension of
the ZID would be about 1220 m x 100 m.
It should be noted that the length of ZID (
6.182 Exceedances of the near field water quality criteria at the edge of the ZID were predicted for three parameters (UIA, surfactants and sulphide respectively) under Stage 2A. The whole effluent toxicity tests (which reflected the cumulative effects of all toxic contaminants that may be present in the CEPT effluent) were conducted to determine whether the CEPT effluent would induce any adverse effects on aquatic life and the results were used to supplement the near field water quality modelling. It was found that the acute toxicity of the CEPT effluent would comply well with the established criteria under Stage 2A. There was a great safety margin of over 75% between the predicted acute toxicity unit and the criterion value at the edge of the ZID (Table 6.43). Based on the near field modelling results, only three isolated water quality criteria (UIA, surfactants and sulphide) established under the EEFS were exceeded at the edge of the ZID. As demonstrated by the results of the whole effluent toxicity test, no adverse cumulative impacts upon the aquatic life would be expected from exposure to all potential contaminants (including the three parameters that exceeded the WQC) present in the CEPT effluent at the edge of the ZID. The potential impacts on marine resources due to the CEPT effluent discharges have also been confirmed by the ecological risk assessment conducted under this EIA to be acceptable (details refer to Section 8). Therefore, the near field water quality impacts are considered acceptable.
6.183 To assess the impacts of CEPT effluent upon the receiving water, EPD’s routine water quality monitoring data collected in the Study Area were analyzed for the pre-HATS and post-HATS period (1997 – 2005) and compared with the WQO and WQC for total inorganic nitrogen (TIN), unionized ammonia (UIA), ortho-phosphate (PO4), dissolved oxygen (DO) and E.coli.
6.184 Only representative EPD stations with greatest influence from the HATS Stage 1 implementation were assessed, including JM3, JM4 (Junk Bay), EM1, EM2 (Eastern Buffer), WM1, WM2, WM3, WM4 (Western Buffer), VM1, VM2 (eastern Victoria Harbour), VM4, VM5, VM6 (central Victoria Harbour), VM7, VM8, VM12, VM14 (western Victoria Harbour), NM1, NM2, NM3 (eastern part of North Western WCZ) and NM5, NM6 (western part of North Western WCZ). For the Southern waters, only selected stations closest to the SCISTW outfall were assessed, including SM7, SM9, SM10 (in the upper part of Southern WCZ) and SM6, SM18 (in the lower part of Southern WCZ). Locations of EPD’s water quality monitoring stations are shown in Figure 6.1.
6.185 Total inorganic nitrogen (TIN) consists of ammonia nitrogen (NH3-N) and total oxidized nitrogen (TON). As level of TON would be low in raw sewage and CEPT effluent, the change of TIN induced by the HATS Stage 1 implementation should mainly be caused by the change of NH3-N. Changes of annual mean values for TIN and NH3-N before and after the HATS Stage 1 implementation are illustrated in Figure 6.7 and Figure 6.8. The background TON levels (for nitrate NO3 and nitrite NO2) are shown in Figure 6.9 and Figure 6.10.
6.186
The
6.187
As compared to the North
Western stations, the background annual mean NO3 levels measured in
the upper part of the
6.188 The contribution of NO2 in the TIN is lower as compared to the contribution of NO3. The NO2 levels measured in all the selected stations (except for the North Western stations) were below or around 0.05 mg/l (Figure 6.10). In the North Western stations, the measured NO2 levels were relatively higher (over 0.07 mg/l) but their contributions to the TIN levels were still considered low as compared to NO3.
6.189
Noticeable reduction of NH3-N
(Figure 6.8) was observed in
Junk Bay (JM3, JM4), Eastern Buffer (EM1, EM2, EM3), eastern and central
Victoria Harbour (VM1, VM2, VM4, VM5, VM6) after decommissioning of five local
sewage outfalls (Kwun Tong, To Kwa Wan, Shau Kei Wan, Chai Wan and Tseung Kwan
O) in late 2001 after HATS Stage 1 implementation, resulting a similar decrease
of TIN (Figure 6.7). The improvement of NH3-N and
TIN in the central Victoria Harbour (VM4, VM5, VM6) was however less as
compared to the eastern stations (VM1, VM2) because the central stations were
still subject to the influences of several local sewage outfalls, including Wan
Chai East and Wan Chai West PTW outfall (close to VM5), Central PTW outfall
(close to VM6), North Point PTW outfall (close to VM4). Full compliance with
the WQO and WQC for TIN was achieved in
6.190
Although two local PTW outfalls
(Tsing Yi and Kwai Chung) close to VM12 were decommissioned under the HATS
Stage 1, no noticeable improvement in terms of NH3-N and TIN was
observed in the western Victoria Harbour (VM7, VM8, VM12, VM14) after 2001 (Figure 6.7 and Figure 6.8). The western
6.191 In Western Buffer (WM1, WM2, WM3, WM4) where the SCISTW outfall is located, full compliance with the WQO and WQC for TIN (0.4 mg/l) was achieved. Also, no obvious increase of NH3-N and TIN was identified in this WCZ after the HATS Stage 1 implementation (Figure 6.7 and Figure 6.8).
6.192
The NH3-N and TIN in
North Western and Southern waters were largely stable over the period between
1997 and 2005 (Figure 6.7 and Figure 6.8). Exceedances of the
WQO for TIN (0.5 mg/l) were observed in the western part of the North Western
WCZ (NM5, NM6). The annual mean TIN
levels measured in the upper part of
6.193 Similar to TIN, there has been noticeable decrease of UIA in Junk Bay (JM3, JM4), Eastern Buffer (EM1, EM2, EM3), eastern and central Victoria Harbour (VM1, VM2, VM4, VM5, VM6) after commissioning of HATS Stage 1 in 2001 (Figure 6.11). For the rest of selected stations, the UIA levels were similar between the pre-HATS and post-HATS periods. The annual mean UIA values recorded in all the selected stations were below 0.015 mg/l which complied with the WQO and WQC of 0.021 mg/l.
6.194
The PO4 levels
recorded in the pre-HATS period were generally higher than those in the
post-HATS period (Figure 6.12). Before the HATS Stage 1 implementation, the annual mean PO4
values exceeded the WQC of 0.04 mg/l (in
6.195 A slight increasing trend of DO was generally observed in Eastern Buffer, Junk Bay, Victoria Harbour and Southern WCZ where all the DO values measured after the HATS Stage 1 implementation in 2001 complied with the WQO of 4 mg/l (for 10th percentile depth-averaged DO) and 2 mg/l (for 10th percentile bottom DO) as shown in Figure 6.13 and Figure 6.14 respectively.
6.196 The WQO for depth-averaged DO was marginally exceeded at some stations in North Western WCZ during the post-HATS period. However, similar exceedances were recorded before the HATS Stage 1 implementation. These exceedances were unlikely to be related to the HATS Stage 1 effluent. Full compliance with the WQO was achieved in the Western Buffer after the Stage 1 implementation in 2001 except for only one occasion in 2006 at WM4 where the DO level marginally breached the WQO.
6.197 Based on the WQC, the DO levels measured at the WCZ should not be less than 2 mg/l at all times. Comparison of DO recorded at each sampling occasion during the pre-HATS and post-HATS periods with the WQC in Figure 6.15 for selected EPD stations showed that oxygen depletion (with DO > 2 mg/l) was not a key concern within the Study Area.
6.198
There has been substantial
reduction in the measured levels of E.coli
in
6.199
However, noticeable increases
of E.coli were observed after the
HATS Stage 1 implementation in areas close to the SCISTW outfall including WM2,
WM3, WM4 (in Western Buffer), NM1 (in North Western), VM7 (in western
6.200
Commissioning of HATS Stage 1
in late 2001 has brought large and sustained improvements to the water quality
of the eastern
6.201
Because the SCISTW effluent has
not been disinfected, E.coli levels
rose in the vicinity of the SCISTW outfall. As a result of the HATS
implementation, the western harbour (Western Buffer WCZ and northern part of
the
6.202
From the EPD monitoring data,
there was no evidence that the CEPT effluent from HATS Stage 1 has caused any
water quality deterioration in the receiving water for other parameters of
concern (TIN, UIA, PO4 and DO). The review has covered all EPD
stations close to the SCISTW outfall.
The closest stations analyzed are VM12 and WM3 which are located about
1400 m and 2100 m away from the HATS outfall diffuser respectively.
6.203
The sediment quality in the Study Area is under the
influences of sediment loading discharges. Before commissioning of the HATS
Stage 1, screened (or untreated) sewage generated from the dense urban areas on
both sides of the
6.204
EPD
routine sediment quality monitoring data collected at Stations WS1, VS9, VS6
and NS1 were analyzed for the pre-HATS and post HATS period in Figure 6.17 to Figure 6.20 respectively. Figure 6.1 shows the locations of these
sediment quality monitoring stations. At WS1 (close to the SCISTW outfall),
the level of copper and silver exceeded the sediment quality criteria (LCEL)
during the pre-HATS period but was found to decrease and comply with the LCEL
during the post-HATS period. The
levels of other metals and trace organics (PCBs and PAHs) measured at WS1
complied well with the sediment quality criteria during both pre-HATS and
post-HATS periods. For VS9 (also close to the SCISTW outfall), the levels of
all metals (except copper and silver) and trace organics complied with the
sediment quality criteria during the post-HATS period. For copper and silver where the levels
exceeded the criteria at the post-HATS stage, similar degree of exceedance was
also found at the pre-HATS period which implies that the exceedance was not
caused by the HATS Stage 1 outfall.
In general, the level of metal contaminant at both WS1 and
VS9 (close to the SCISTW outfall) showed a decreasing trend during the period
from 1997 to 2005.
6.205
The
level of contaminant at VS6 (close to the
6.206
Station
NS2 is located further away from the SCISTW outfall in the North Western
WCZ. The sediment contaminant level
at NS2 was the lowest (amongst the four selected stations) and complied well
with the sediment quality criteria (except for arsenic at the pre-HATS stage
only). The past measurement data
indicated that the CEPT effluent from SCISTW has not caused any deterioration
to the sediment quality at the stations close to the SCISTW outfall since the
commissioning of HATS Stage 1.
6.207
Under Stage 2A, all the remaining PTW outfalls in the
harbour (including the PTW outfalls of North Point, Central, Wan Chai West and
Wan Chai East etc.) would be decommissioned and all the sediment loading
currently discharged via the local PTW outfalls would be diverted to the SCISTW
for CEPT treatment. As the SS removal rate from the CEPT
process is typically around 80%, there
should be an overall reduction in the SS loading and sediment deposition in the
western
6.208 Under the HATS Stage 1 outfall baseline monitoring and performance verification programme ([17]), water quality and sediment quality monitoring were performed under the pre-HATS period (1996 – 1999), the initial commissioning of Stage 1 (1999 - 2000) and the full commissioning of Stage 1 (2001 – 2003). Field data were collected at 16 water quality stations and 16 sediment quality stations distributed over the HKSAR waters as shown in Appendix 6.2. The monitoring parameters covered under the outfall performance verification include all the parameters routinely monitored by EPD.
6.209 Based on the findings of the outfall performance verification, the only water quality impacts caused by the Stage 1 outfall were related to increases in E.coli and ammonia concentrations. Increases in ammonia levels close to the Stage 1 outfall were however found to be small and of limited extent but increases in E.coli concentrations covered a larger area extending to the beaches in the Tsuen Wan District. Apart from the WQO with respect to E.coli concentrations at bathing beaches (which would be reduced once disinfection is implemented), there was no indication that the achievement of the WQO for all other relevant parameters would be compromised by the CEPT effluent from the Stage 1 outfall. No deterioration in sediment quality was identified in the vicinity of the Stage 1 outfall at the post-HATS stage. It was also concluded that sewage solids deposition was not occurring to the extent that it could be detected. The findings of the outfall performance verification are consistent with the findings from review of past EPD routine monitoring data conducted under this EIA.
6.210
Based
on the review of EPD monitoring data, the WQO and WQC for TIN are currently
exceeded in the western
6.211
Both nitrogen and phosphorus are essential components of phytoplankton biomass. Inorganic
nutrients such as TIN and PO4 can therefore be taken up by
phytoplankton. Excessive nutrients
in water could enhance excessive phytoplankton growth (often called algal
bloom), which may adversely affect marine life because the
water can become completely deprived of oxygen when a bloom declines rapidly,
since the biological degradation of dead algal material consumes large amounts
of oxygen. Marine water in hypoxic condition (DO < 2
mg/l) is often considered as one of the signals for excess algal formation.
Although the primary concern would be oxygen depletion, algal bloom could also
cause other side effects such as discoloration of marine water. Some species of phytoplankton may also
produce toxins and induce toxic effect on marine life and cultured fish.
However, only a minority of blooms consist of species that synthesize
toxins. In actuality, most algal blooms would be non-toxic.
6.212
Inorganic
nitrogen could exist in water in two different forms, namely ammonia and
nitrate both of which can support algae growth. As ammonia is the preferred
nitrogen nutrients over nitrate for phytoplankton growth, the presence of a
certain level of algae in water may in fact be beneficial to the environment by
consuming the ammonia which could be toxic to marine life. It should therefore
be highlighted that the presence of algae in water is generally not harmful.
Only their uncontrolled growth as algal bloom would adversely affect the
environment.
6.213 Phytoplankton requires considerable amounts of sunlight (solar energy) and nutrients. In theory both of these factors could become limiting. The sun provides the energy which must be shared among all the phytoplankton cells floating in the water column, with an allowance set aside for reflection from the water surface and absorption by the bulk water and its contents other than phytoplankton. The more phytoplankton there is, the less solar energy is available for each, until the energy per phytoplankton cell is too small to sustain growth. At that point, solar energy becomes limiting to the phytoplankton biomass.
6.214 Three inorganic nutrients (nitrogen, phosphorus, and silicon) are often reported as potential biomass limiting factors for phytoplankton, along with solar energy. Nitrogen and phosphorus are vital to all phytoplankton species. Silicon is essential to only one phytoplankton group, diatoms. When sunlight is not a limiting factor, the bloom is usually terminated when algal growth reduces one of the nutrients below the level necessary to sustain growth. This is designated as the most limiting nutrient.
6.215 Redfield ([18]) described that the atomic ratio of silicon, nitrogen and phosphorus (Si:N:P) in most phytoplankton would be 15:16:1. However, it has been discovered in later researches that phytoplankton may have large variations in the N:P composition, and the N:P ratio of 16:1 as reported by Redfield would be a general average rather than specific requirement for phytoplankton growth ([19]). The growth of most red tide causative species in Hong Kong coastal water has been reported to be optimized at a low N:P (atomic) ratio of between 6 and 15 ([20]).
6.216
The monthly averaged atomic ratios of N:P and Si:P
recorded in the marine water within
the Study Area are illustrated in Figure
6.21 and Figure
6.22
respectively. These atomic ratios are the averaged ratios over the period from
1997 to 2005 and were calculated using the EPD routine marine water quality
monitoring data for silica (SiO2), TIN and PO4. It was found that both the N:P ratios
and Si:P ratios generally increased during the summer months (April to
September) when the
6.217 As sewage effluent usually contains high N and P relative to Si, Si would be potentially the most limiting nutrient (for diatoms) during dry season when the influence from sewage effluent was dominant. In wet season when the influence of river discharge (with high N and Si relative to P) was large, P would be potentially the most limiting nutrient for diatoms. The N:P ratios recorded at the selected stations are generally higher than 20:1 in both winter and summer months (Figure 6.21), suggesting that P would be potentially the most limiting nutrient all year round for non-diatom species. As the Study Area was generally rich in N relative to P, algal growth may in theory respond to small amounts of P additions provided that the environmental condition is suitable. By contract, further increase in N from sewage effluent may not easily cause further effects on algal formation given the abundant N but with limited P in the water. Similarly, small addition of Si loading may potentially simulate the formation of diatom species in the dry season, given the right environmental condition.
6.218
Red
tides and algal blooms are natural phenomena which occur seasonally in both
polluted and unpolluted waters.Table 6.44 shows the occurrence and distribution
of red tides in
Table 6.44 Occurrence
and Distribution of Red Tides in
WQC |
Occurrence of Red Tide (1980 – 2006) ** |
Occurrence of Red Tide in 2006 ** |
Occurrence of Red Tide Species (1980 – 2006) ** |
Pollution Levels in 2006 (Annual Mean) |
||||||||
No. |
% Contribution |
No. |
%
Contribution |
Diatom |
Dinoflagellates |
Other
Species |
TIN (mg/l) |
PO4 (mg/l) |
SiO2 (mg/l) |
SS (mg/l) |
Chlorophyll-a (μg/l) |
|
Western Buffer |
20 |
3% |
1 |
8% |
12 |
7 |
0 |
0.19 – 0.32 |
0.01 – 0.02 |
0.9 – 1.2 |
4.7 – 7.7 |
2.0 – 2.8 |
|
14 |
2% |
0 |
0% |
11 |
2 |
0 |
0.18 – 0.48 |
0.02 - 0.03 |
0.7 – 1.6 |
4.2 – 11.0 |
2.1 – 3.5 |
|
6 |
1% |
0 |
0% |
5 |
0 |
2 |
0.15 – 0.18 |
0.01 |
0.6 |
3.2 – 4.5 |
3.6 – 4.8 |
Eastern Buffer |
1 |
0% |
0 |
0% |
1 |
0 |
0 |
0.12 – 0.15 |
0.01 – 0.02 |
0.6 – 0.7 |
3.9 – 5.0 |
3.0 – 3.3 |
Southern |
126 |
17% |
3 |
23% |
26 |
67 |
29 |
0.11 – 0.34 |
<0.01 – 0.02 |
0.6 – 1.1 |
3.4 – 13.4 |
2.5 – 9.1 |
North Western |
25 |
3% |
1 |
8% |
4 |
12 |
9 |
0.43 – 0.67 |
0.02 – 0.03 |
1.4 – 2.4 |
6.4 – 15.8 |
2.8 – 4.2 |
|
9 |
1% |
0 |
0% |
3 |
2 |
4 |
0.83 – 3.86 |
0.04 – 0.35 |
2.4 – 4.9 |
8.3 – 58.5 |
2.13 – 25.5 |
Port Shelter |
108 |
14% |
5 |
38% |
3 |
89 |
17 |
0.03 – 0.05 |
<0.01 |
0.5 – 0.6 |
2.2 – 4.5 |
2.3 – 3.3 |
|
139 |
18% |
1 |
8% |
10 |
106 |
24 |
0.04 – 0.13 |
<0.01 |
0.5 – 0.6 |
1.5 – 5.0 |
2.0 – 7.7 |
|
315 |
41% |
2 |
15% |
75 |
241 |
60 |
0.06 – 0.18 |
<0.01 – 0.01 |
0.6 – 1.2 |
1.7 – 5.3 |
2.3 – 9.5 |
Total |
763 |
100% |
13 |
100% |
150 |
526 |
145 |
- |
- |
- |
- |
- |
Note: ** A red tide
incident may involve more than one causative species.
6.219
From the 2006 records for Port
Shelter,
6.220
Recent research studies on
algal blooms indicated that red tides would be optimized in poorly flushed
coastal water under calm wind condition (20). In the open water environment within the North Western and Western
Buffer WCZ, the effect of tidal flushing was high.As these waters were frequently
diluted by horizontal advection or vertical mixing, the accumulation of algal
biomass and hence the chance of algal bloom were more effectively minimized. Although the nutrient level in
6.221
Species
of algae differ greatly in their nutrient requirements and
efficiency in solar energy fixation (photosynthesis). A bloom of a species would depend on a combination of
different environmental factors such as the flow condition, light penetration, salinity
distribution, nutrient concentrations, nutrient ratios and species
competition. The fact that 75% of
past red tides in Hong Kong occurred in eastern waters with comparatively low
nutrient levels implies that nutrient may not be a critical limiting factor for
triggering red tide formation in
6.222
In
6.223
Figure 6.23 to Figure 6.25 illustrate the monthly variation of
ammonia nitrogen, phosphate and silica contents in the receiving water before
and after commissioning of HATS Stage 1.
Only ammonia nitrogen is shown because the CEPT effluent contains
minimal nitrate and nitrite. The current P removal rate from the CEPT process
at the SCISTW was around 40% to 50%. As a result, there has been an overall
reduction of the P loading in the receiving waters. The removal rate for
ammonia nitrogen from the CEPT process would be lower (typically around 10%).
As shown in Figure 6.23 to Figure 6.25), the CEPT effluent from Stage 1
outfall has not caused any obvious increase in the nutrient (ammonia nitrogen,
phosphate and silica) contents in the Western Buffer and western Victoria
Harbour where the SCISTW outfall is located.
6.224
In
terms of the effect on DO level, monitoring results (Figure 6.15) indicated that the DO levels in
the Study Area were not depleted during both the pre-HATS and post-HATS stages
and no obvious decrease in the DO level was observed in the receiving water
after the HATS Stage 1 implementation.
So far, there has not been any sign of increasing red tide occurrence
resulted from the CEPT discharge from HATS Stage 1. Though the TIN level
currently exceeds the WQC and WQO in western
6.225
As
previously mentioned, Si would be potentially the most limiting nutrient (for
diatoms only). However, the Si
limiting condition would potentially occur in dry season only, when all
concentrations of nutrients were also low. The bioassays conducted under the
EEFS by adding CEPT effluent in ambient water samples collected from different
water sources within the Study Area indicated that the addition of CEPT
effluent caused Si in the water samples to become limiting since CEPT effluent
contains higher N and P, but relatively low Si. Therefore, addition of CEPT
effluent may further enhance the potential Si limitation and slow the growth of
diatoms which could allow dinoflagellates to become more dominant. However, the
bioassays did not take into account the dilution and hydrodynamics effects in
the water environment. In
actuality, the Stage 2A implementation would involve the change of distribution
for sewage effluent only (from the local PTWs to the SCISTW outfall). Due to
the better flushing achieved at the SCISTW outfall than that at the local PTW
outfalls, the pollution levels including all the concentrations of nutrients
would be reduced in the whole Study Area after the Stage 2A implementation as
demonstrated by the modelling assessment conducted under this EIA. Although the
CEPT effluent contains high N and P relatively to Si, the overall load
reduction for P in the water environment would in fact be greater than that for
N and Si as a result of the diversion of sewage effluent from the local PTWs to
the SCISTW for CEPT treatment (the CEPT process would typically remove about
40% to 50% of the P loading in the sewage effluent whilst the load reduction
for N and Si would be minimal from the CEPT process). In view of the above, it can be
concluded that (i) the Stage 2A implementation would not increase the risk of
diatom blooms because all concentrations of nutrients would be reduced after
the Project completion whilst all the other environmental factors such as the
hydrodynamic condition would remain unchanged (details refer to the modelling
results presented in the subsequent sections); (ii) the Project would not
further enhance the current Si limitation as the Stage 2A implementation would
result in a higher load reduction for P as compared to Si; and (iii) the
reduction of overall P loading achieved from the Stage 2A would further enhance
the P limiting condition in the Study Area (as demonstrated by the modelling
assessment) and minimize the growth of all phytoplankton species including both
diatoms and dinoflagellates (as they all require P for growth). As such, no adverse effect on algal
blooms would be expected from the Stage 2A implementation. The model results
for different assessment scenarios are compared with the WQO and WQC in the
subsequent sections. Chlorophyll-a
was not modelled because although it is often used as an indicator in measuring
phytoplankton biomass, it is not representative of potential algal bloom since
a dominant algal bloom phytoplankton group, the dinoflagellates, has no
chlorophyll.
6.226 An assessment of water quality impact due to the operation of the Project was made using the Delft3D model. The far field water quality modelling scenarios are summarized in Table 6.30. The predicted water flow pattern was compared between different assessment scenarios in Figure 6.26 to Figure 6.28. The model results are also presented as contour plots for TIN (Figure 6.29 and Figure 6.30), PO4 (Figure 6.31), UIA (Figure 6.32 to Figure 6.34), E.coli (Figure 6.35), DO (Figure 6.36 to Figure 6.37), BOD5 (Figure 6.40), SS (Figure 6.41), sedimentation rate (Figure 6.42), TRC (Figure 6.43) and CBP (Figure 6.44 to Figure 6.46). The contour plots are presented as annual arithmetic averages for TIN (as N), PO4 (as P), SS and BOD5 and annual geometric means for E.coli. The UIA levels are presented as annual mean (as N), 4-day maximum (as NH3) and hourly maximum values (as NH3) for comparison with the relevant WQO and WQC. The contour plots for DO are presented as 10th percentile depth-averaged values, 10th percentile bottom values, annual minimum values and minimum monthly averaged values. The results for sedimentation rate, TRC and CBP are presented as maximum values over the simulation period. The flow pattern is presented as vector plots under typical flood and ebb tide conditions. Appendix 6.3 to Appendix 6.5 show the modelling results at identified water and marine ecological sensitive receivers.
6.227 The HATS effluent flow was included in the far field hydrodynamic model to assess the effect on the flow regime due to the increase in the effluent flow rate under Stage 2A and Stage 2B. The predicted flow patterns were compared between different assessment scenarios in Figure 6.26 to Figure 6.28. The model results showed that the increase in the effluent flow under Stage 2A and Stage 2B would not change the general flow pattern in the receiving water. There is no assessment criterion available for water flow and current in marine water.
6.228
The predicted TIN levels
exceeded the WQO and WQC of 0.4 mg/l in
6.229
Under HATS Stage 1 (without Stage 2A) in 2014, the predicted TIN levels marginally exceeded
the WQO and WQC at the Rambler Channel to the east of Tsing Yi Island (Figure 6.29 and Figure 6.30). Recent EPD monitoring data
indicated that the TIN levels measured at Rambler Channel (VM12 and VM14) also
exceeded the WQO under the 2005/2006 condition. The model predicted that the TIN
exceedances at Rambler Channel would greatly reduce
after decommissioning of all the PTWs in
6.230 Although additional TIN loading would be transferred to the SCISTW outfall under Stage 2A, discharge from the SCISTW outfall would achieve better dilution and flushing in the open water of Western Buffer WCZ as compared to the local PTW outfalls in the harbour channel. Besides, the CEPT process at the SCISTW would typically remove about 40% of organic nitrogen, which is a key source of ammonia nitrogen in marine water via the mineralization process. Implementation of Stage 2A would therefore indirectly reduce the overall ammonia nitrogen level in the marine environment (via the reduction of the organic nitrogen loading) and would improve the overall TIN levels in the western Victoria Harbour and Western Buffer WCZ as compared to the “without Stage 2A” scenarios in 2014 and 2021. Implementation of Stage 2B (with nitrification process) would however increase the TIN levels in the receiving waters due to the substantial increase in the oxidized nitrogen loading in the BAF effluent (refer to Table 6.29). The mixing zone for TIN was quantified and compared between different assessment scenarios in Table 6.45.
6.231
The model results showed that
implementation of HATS Stage 2A would cause an overall reduction of PO4 levels in the Study Area due to
the reduction of P loading from the CEPT process and the hydrodynamic effects
as discussed in the above paragraph.
As shown in Figure 6.31, the level of PO4 exceedance in the semi-enclosed
bay at the east of
6.232
Based on the model assumption
in Table 6.29, the PO4
concentration in the HATS effluent would be further reduced from the BAF
process at Stage 2B. As shown in Figure 6.31, the exceendance at the
east of
6.233 Some exceedances were predicted inside the marine embayments after commissioning of Stage 2A. However, similar or greater level of exceedance was also predicted under the baseline “without Stage 2A” scenarios. The predicted exceedances were not caused by the Stage 2A implementation. The Stage 2A implementation would in fact reduce the PO4 level from the baseline (Stage 1) condition (Appendix 6.4 and Appendix 6.5).
6.234 The predicted annual mean unionized ammonia (UIA) levels exceeded the WQO and WQC of 0.021 mg/l at area in close vicinity of the SCISTW outfall under both the “with Stage 2A” and the “without Stage 2A” scenarios (Figure 6.32). The model results show that implementation of Stage 2A would reduce the annual mean UIA exceedances in the SCISTW outfall area. For annual mean UIA, the mixing zone of HATS effluent would be reduced by about 50% after the Stage 2A implementation (refer to Table 6.45).
6.235
The predicted maximum 4-day
averaged UIA levels exceeded the WQC in the
6.236
Some non-compliances of UIA
levels were predicted in the
6.237 In general, the UIA levels would be improved in the North Western, Western Buffer and Victoria Harbour WCZ after commissioning of Stage 2A. Implementation of Stage 2B would further improve the UIA levels within the Study Area and remove the UIA exceedances at the HATS outfall area. The UIA exceedances were predicted in area close to the SCISTW outfall under the Stage 2A condition. Full compliances with the WQO and WQC for UIA would be achieved at all the identified marine ecological receivers which were farther away from the SCISTW outfall (Appendix 6.5). The level of ammonia nitrogen predicted at all the flushing water intakes also complied well with the WSD criterion of ≤ 1 mg/l under all the assessment scenarios (Appendix 6.3).
6.238
With the provision of
disinfection facilities at SCISTW, the E.coli removal efficiency of HATS would be equivalent to 99% or above. Comparison between
the modelling results of baseline scenario (without Stage 2A) and operation phase
scenario (with Stage 2A) indicated that Stage 2A implementation would improve
the E.coli levels in Victoria Harbour
and Western Buffer WCZ by transferring the untreated sewage from local PTWs to
SCISTW for CEPT treatment and disinfection. Also, implementation of Stage 2B
would cause only minor difference from the Stage 2A condition in terms of the
predicted E.coli levels in the
receiving waters (Figure 6.35). The influence of the E.coli impact from the disinfected HATS
effluent would be localized and confined within the
6.239
The WQO and WQC for E.coli are geometric mean values which
are only applicable to bathing beaches (≤ 180 E.coli per 100 ml), secondary contact recreation subzones (≤ 610 E.coli per 100 ml) and fish culture
zones (≤ 610 E.coli per 100 ml). Based on the WSD criteria, the target
level of E.coli at any flushing water
intake should not be over 20,000 per 100 ml. Within the influence zone of the
disinfected SCISTW effluent (i.e. Victoria Harbour and Western Buffer WCZ),
full compliance with the above assessment criteria would be achieved under the
Stage 2A and Stage 2B scenarios except that the predicted E.coli levels at Cheung Sha Wan flushing water intake and Approach
Beach would marginally exceed the assessment criteria of 20,000 per 100 ml (for
maximum value) and 180 per 100 ml (for geometric mean value) respectively as
shown in Appendix 6.3 and Appendix 6.4. These exceedances were
however not related to the effluent discharged from HATS and were caused by the
background storm pollution loading assumed in the modelling exercise. The
background storm loading was input into the model to assess the worst case
cumulative effect with the HATS effluent.
6.240
The model results indicated
that implementation of HATS Stage 2A would improve the DO levels in the
6.241
The WQO for 10th
percentile depth-averaged DO and 10th percentile
bottom DO (≥4 mg/l and ≥2 mg/l respectively) are applicable to the whole Study
Area except for mariculture zones where the 10th percentile
depth-averaged DO should be ≥5 mg/l.
The WQC for 10th percentile depth-averaged DO (≥4 mg/l) is applicable to Western
Buffer, Eastern Buffer,
6.242
Non-compliance with the WQO and
WQC was only predicted at a few marine embayments in
6.243
The BOD and SS removal rate from the CEPT process is typically around 60%
and 80% respectively. Implementation of Stage 2A can therefore reduce
the overall BOD and SS loads discharged to the marine water. The model predicted that implementation of Stage 2A would improve the BOD levels in the western
6.244 Full compliance with the WSD criteria for BOD (≤ 10 mg/l) was predicted at all the flushing water intakes (Appendix 6.3). However, non-compliance with the WSD criteria for SS (≤ 10 mg/l) was predicted for some flushing water intakes. These non-compliances were not caused by the Stage 2A implementation as similar degree of non-compliances was also predicted under the baseline (without Stage 2A) scenarios. These non-compliances were caused by the background pollution loading from local storm outfalls assumed in the modelling. Full compliance with the WQO for SS (i.e. elevation of less than 30% of ambient baseline level) would be achieved under both Stage 2A and Stage 2B scenarios in the whole Study Area including all the coral sites. There is no WQC and WQO available for BOD.
6.245
The model predicted that
implementation of Stage 2A would slightly reduce the sedimentation rate in
areas close to the SCISTW outfall including the western Victoria Harbour,
Western Buffer and Northern Western WCZ. There was no observable difference in the extent of sedimentation rates
between different assessment scenarios in the eastern
6.246 Far field water quality modelling was conducted for TRC and 34 CBP compounds as listed in Table 6.11. The model results had taken into account other concurrent discharges such as Pillar Point STW, Sha Tin STW and Tai Po STW where chlorination and dechlorination were assumed to be their disinfection method for worst-case assessment. Possible discharges of TRC and CBP from spent cooling water were also included in the model for cumulative assessment. The initial CBP levels assumed in the effluent discharges and other concurrent discharges were based on the laboratory CBP testing in the C/D effluent samples as previously discussed. The effluent TRC level was assumed to be 0.2 mg/l at 95th percentile standard.
6.247 The contour plots for TRC are shown in Figure 6.43 which represent the maximum values predicted over the whole model simulation period. The model results showed that the predicted maximum values at and near the SCISTW outfall complied well with the assessment criterion of 0.008 mg/l. The contour plots indicated some localized TRC exceedances along the coastlines. These localized exceedances were contributed from the background sources and were not related to the HATS discharges.
6.248 The predicted maximum values for all the identified CBP compounds complied well with their corresponding ambient water objectives as shown in Table 6.11. The predicted maximum levels of dichloroacetic acid and trichloroacetic acid were higher than the measured ambient levels near the outfall location under Stage 2A. The predicted maximum levels for bromoform were higher than the measured ambient levels near the outfall location during Stage 2B. The predicted maximum values for all the remaining CBP compounds were within the measured ambient levels. The model results are presented as contour plots for dichloroacidic acid, trichloroacetic acid and bromoform in Figure 6.44 to Figure 6.46 respectively.
6.249 Overall, there was no difference in the key findings from the assessment of TRC and CBP impacts between the EIA study for ADF and this EIA. All the TRC and CBP levels predicted at the SCISTW outfall complied well with the assessment criteria. However, it was observed that the plume size of conservative tracer (dichloroacetic acid and trichloroacetic acid) predicted under Stage 2A for this EIA was slightly larger than that presented in the EIA report for ADF but the plumes were still considered localized and confined in area close to the SCISTW outfall. This was in contrast to the assumption that the effluent flow rates used under the ADF study were more conservative than that used under this EIA.
6.250 The effluent plume would be moving around the SCISTW outfall as driven by the changing water current. As the model results for TRC and CBP were presented as the maximum values predicted over the entire simulation period, the TRC and CBP plumes shown in the contour plots did not represent the actual maximum plume size. They were considered as the areas which enveloped the moving plumes over the entire simulation period. The maximum instantaneous coverage of the effluent plume should be much smaller. The movement of the effluent plume would be affected by tides and water current. The modelling performed under this EIA covered a series of annual simulations which took into account more tidal condition and the corresponding envelop could be larger than that predicted under the EIA study for ADF which was based on a series of 30-day simulations only. TRC would be subject to decay once it is discharged to the sea and is therefore less susceptible to such hydrodynamic effect. The effect was also not noticeable for conservative tracer (bromoform) predicted for Stage 2B, because the flow rate adopted in the ADF study for Stage 2B (2.8M m3/d) was much larger than that used under this EIA (2.45M m3/d) which may neutralize the hydrodynamic effect. The flow difference under Stage 2A between the ADF study (2.34M m3/d) and this EIA (2.17M m3/d) was much smaller.
6.251 The TRC and CBP results in Figure 6.43 to Figure 6.46 indicated a sizable mixing zone for a number of background cooling water discharges. The TRC and CBP results for these background sources were based on some very conservative assumptions. The peak discharge flow rates of the cooling water systems were applied to the model continuously (that is, 24 hours daily). For cooling water where no information on the residual chlorine level was available, the maximum chlorine dose rates were directly applied to calculate the TRC loading for model input which, again, represented a very adverse scenario. In reality, the peak flow rates would occur during a short period of time within a day and the chlorine would be decayed within the cooling water systems. Therefore, the actual chlorine contents in the cooling water discharges should be smaller than that assumed in the model. The background cooling water discharges were included in the model only for the purpose of addressing the possible worst-case cumulative impact with the HATS effluent. The model results indicated that the C/D HATS effluent would not cause any cumulative TRC and CBP impact with all other concurrent discharges assumed in the model.
6.252 The model predicted that implementation of Stage 2A would improve the water quality in the receiving water (including the area close to the SCISTW outfall) for all the selected water quality parameters as compared to the baseline (without Stage 2A) condition. However, exceedances of the assessment criteria were still predicted at the SCISTW outfall area for two parameters (TIN and UIA respectively) at Stage 2A and one parameter (TIN) at Stage 2B. Table 6.45 shows the approximate dimensions of the mixing zones at the SCISTW outfall. The approximate location of the maximum mixing zone predicted for TIN and UIA at the late phase of Stage 2A with respect to the SCISTW outfall diffuser is shown in Figure 6.47.
Table 6.45 Approximate
Dimensions of Mixing Zones at the SCISTW Outfall - Base Case
Scenarios
Parameter |
Approximate Dimension of Mixing Zone (km2) |
Figure Reference |
2014 – Stage 1 without Stage 2A
– HATS Flow Rate of 1.55 M m3/d (Scenario 1a) |
||
Total Inorganic Nitrogen (Annual Mean) |
12.5 |
|
Unionized Ammonia (Annual Mean) |
2.7 |
|
Unionized Ammonia (4-day Average) |
3.9 |
|
2014 – Early Phase of Stage 2A
– HATS Flow Rate of 2.06 M m3/d (Scenario 1b) |
||
Total Inorganic Nitrogen (Annual Mean) |
5.5 |
|
Unionized Ammonia (Annual Mean) |
1.4 |
|
Unionized Ammonia (4-day
Average) |
1.9 |
|
2021 – Late Phase of Stage 2A – HATS Flow Rate of 2.17 M m3/d (Scenario 2b) |
||
Total Inorganic Nitrogen
(Annual Mean) |
9.4 |
|
Unionized Ammonia (Annual Mean) |
3.5 |
|
Unionized Ammonia (4-day
Average) |
4.9 |
|
Ultimate – Stage 2B (Scenario 3b) |
||
Total Inorganic Nitrogen |
30.3 |
6.253 A sensitivity test, namely Scenario 2c (refer to Table 6.30) was conducted to examine the water quality effect as a result of assuming a less conservative storm loading under the Stage 2A scenario in 2021. The model predicted that the change of storm loading input would not cause any obvious reduction in the degree of TIN and UIA exceedances from the base case scenario (Scenario 2b) as illustrated in Figure 6.29, Figure 6.30, Figure 6.32 and Figure 6.33.
6.254
Another sensitivity test, namely Scenario 2d, was conducted using a less
conservative HATS flow rate of about 1.9M m3/d (refer to Table 6.30) under Stage 2A in 2021. It was found that the
area of modelled exceedances predicted near the SCISTW outfall area for TIN and
UIA would be slightly reduced as compared to the base case scenario (Scenario
2b - with a HATS flow rate of about 2.2M m3/d). The sensitivity analysis indicated that
the background storm pollution loading would contribute only very minor
cumulative impact with the HATS effluent discharge for TIN and UIA. The exceedances for UIA and TIN
predicted near the SCISTW outfall area should mainly be contributed from the
HATS effluent.
6.255 It was assumed under the base case modelling scenarios that Stage 2B would be implemented by 2021. A sensitivity test, namely Scenario 2e, was conducted to investigate the change in water quality impacts as a result of the possible change of Stage 2B implementation schedule (refer to Table 6.30). Under this sensitivity test the effluent flow from HATS Stage 2A was assumed to be reaching its design flow rate of 2.45M m3/day to examine the water quality impacts of the CEPT effluent without Stage 2B. As illustrated in Figure 6.29 to Figure 6.33, increasing the CEPT effluent flow to 2.45M m3/day would increase the area of modelled exceedances for both TIN and UIA. The increased CEPT effluent flow would also contribute a new mixing zone for PO4 at the SCISTW outfall area but the extent of the mixing zone would be small and limited. Table 6.46 shows the approximate dimensions of the mixing zones predicted under Scenario 2e.
Table
6.46 Approximate
Dimension of Mixing Zones at the SCISTW Outfall - Sensitivity Test
Parameter |
Approximate Dimension of Mixing Zone (km2) |
Figure Reference |
Sensitivity Test – Use of Design HATS Flow Rate of 2.45 M m3/d for Stage 2A at Ultimate Year (Scenario 2e) |
||
Ortho-phosphate (Annual Mean) |
0.06 |
|
Total Inorganic Nitrogen |
14.5 |
|
Unionized Ammonia (Annual Mean) |
5.7 |
|
Unionized Ammonia (4-day
Average) |
6.2 |
6.256
The whole effluent toxicity
tests (WETT), which reflected the cumulative effects of all toxic contaminants
(including UIA) that were present in the CEPT effluent, were conducted to determine
whether the CEPT effluent would induce any adverse effects on aquatic life and
the results were used to supplement the water quality model results. Based on
the minimum dilution at the edge of mixing zone for UIA as shown in Table 6.45 and Table 6.46, the chronic toxicity unit (TUc) ([23]) at the edge of the mixing zone for UIA was calculated for the CEPT
effluent and the results are summarized in Table
6.47.
Table
6.47 Summary of Chronic
Toxicity Unit (TUc) at Edge of Mixing Zone
Scenario |
Minimum Dilution Factor
1 |
NOEC Detected for
Diatom in the WETT 2 |
TUc at Effluent 3 |
Predicted TUc at Edge
of Mixing Zone 4 |
Criterion (mg/l) 5 |
% of Criterion |
2014 – Early Phase of
Stage 2A (Scenario 1b) |
46 |
27.2% |
3.68 |
0.08 |
1 |
8% |
2021 – Late Phase of Stage 2A (Scenario 2b) |
49 |
0.08 |
8% |
|||
Sensitivity Test - Use of Design Flow for Stage 2A
(Scenario 2e) |
56 |
0.07 |
7% |
Notes:
1.
Based on minimum dilution rate
predicted at the edge of mixing zone.
2.
NOEC of 27.2% was detected in C/D
CEPT effluent for diatom (see Table
6.34)
3.
TUc = 100/NOEC
4.
TUc at edge of mixing zone = TUc
at effluent / minimum dilution
5.
Toxicity criterion for far field
modelling (see Table
6.11)
6.257 As shown in Table 6.47, the predicted maximum TUc at the edge of mixing zone for Stage 2A would be 0.08 which fully complied with the established criterion of 1. There was a great safety margin of over 90% between the predicted chronic toxicity unit and the criteria value at the edge of the mixing zone. It should be noted that compliance with the chronic toxic criterion would be achieved with a dilution of 5 times only, which would be equivalent to a location at the immediate vicinity of the SCISTW outfall diffuser. Therefore, the extent of the chronic toxicity impact of the CEPT effluent would be limited. As predicted by the model, the WQC and WQO for UIA would be fully complied at all the identified water and marine ecological sensitive receivers. The non-compliance with the numeric WQO/WQC for UIA predicted near the SCISTW outfall area is considered acceptable due to the following:
6.258 As discussed before, the key water quality issue in relation to the high nutrient (N and P) level in marine water would be the potential enhancement of algal bloom. The non-compliance with the numeric WQO/WQC for N & P is considered acceptable due to the following:
6.259
However, if Stage 2B is not
implemented for HATS as scheduled, the nutrient contents (both P and N) in the
marine water would ultimately increase to exceed the baseline Stage 1 level
when the HATS flow is reaching its design capacity of 2.45M m3/day. The increased areas of
modelled exceedance for PO4 was only observed in areas very close to the SCISTW outfall diffuser as shown in Figure 6.31. There was no further
increase in the predicted P contents in the
6.260 It should be noted that the mixing zone for TIN predicted for Stage 2B was large with an area of about 30 km2 as indicated in Table 6.45 and the area of exceedance would encroach on the nearby water sensitive receivers (e.g. Ma Wan Fish Culture Zone). This is due to the elevated oxidized nitrogen assumed for the proposed nitrification process at Stage 2B as well as the increased HATS effluent flow assumed for Stage 2B. It is recommended that these water quality issues should be further investigated / assessed under the future EIA for Stage 2B. Further mitigation measures / alternative treatment designs should also be considered under the future EIA for Stage 2B to mitigate / minimize the potential TIN exceedances.
6.261 Based on the nutrient ratios recorded at the EPD’s routine water quality monitoring stations as illustrated in Figure 6.21 and Figure 6.22, the Study Area (including the North Western, Southern, Western Buffer, Victoria Harbour, Junk Bay and Eastern Buffer WCZ) was under a P-limiting condition (i.e. the water was rich in N relative to P) in consistent with the EEFS findings. All phytoplankton species require both N & P for growth. Under a P-limiting condition and provided with favourable flow & atmospheric condition, algal growth may in theory respond to addition of P. By contract, further addition of N may not cause further effect on algal growth given the abundant N with limited P in the water.
6.262 It was however concluded that nutrient (both N & P) was not a critical limiting factor for algal bloom in the open water environment within the western waters including the Victoria Harbour, North Western and Western Buffer WCZ (where the SCISTW outfall is located), based on the fact that over 90% of past red tides in Hong Kong occurred in eastern & southern waters with comparatively low nutrient levels. Red tides rarely occurred in the western waters where the nutrient levels were much higher. Based on past research studies, algal blooms were mostly observed in weakly flushed coastal waters under calm wind condition and with adequate light penetration. In the open water environment within the Victoria Harbour, North Western and Western Buffer WCZ, the effect of tidal flushing was high.As these western waters were frequently diluted by horizontal advection or vertical mixing, the accumulation of algal biomass and hence the chance of algal bloom would be more effectively minimized.
6.263 As such, a more stringent WQC for P & N was established under EEFS for the poorly flushed semi-enclosed bays (Figure 6.3) to minimize occurrence of red tides. The WQC for N & P is 0.1 mg/l & 0.01 mg/l respectively for semi-enclosed bays. The WQC are less stringent for other open waters such as the Western Buffer WCZ (where the SCISTW outfall is located) with a limit of 0.4 mg/l & 0.04 mg/l for N & P respectively.
6.264 Based on the model results and past monitoring records, the WQO/WQC for N was exceeded in the Study Area under the existing Stage 1 condition (including the SCISTW outfall location, the Southern water, the North Western water and all the semi-enclosed bays). On the other hand, the WQC for P was exceeded at the semi-enclosed bays only. Full compliance with the WQC for P was achieved in all other open waters including the Western Buffer WCZ under the existing Stage 1 condition.
6.265 The HATS 2A implementation would reduce the nutrients (both N & P) in the whole Study Area (including the Western Buffer and all the semi-enclosed bays) as compared to the Stage 1 condition. Hence, HATS 2A would not increase the risk of red tide. However exceedance for N & P was still predicted after the HATS 2A implementation but the level of exceedance was smaller than that under the existing Stage 1 condition.
6.266 Stage 2B would cause a further reduction of P level in the receiving water as compared to the Stage 2A condition. Further increase in N caused by the nitrification process of Stage 2B would not increase the risk of algal bloom because their growth would be limited by the reduced P in the water.
6.267
Nutrient removal has been
considered for HATS Stage 2A to minimize the nutrient levels in the receiving
water. As the background source (
6.268
To
verify the occurrence of P exceedances at the semi-enclosed bays as predicted
by the model, the relevant model predictions for HATS Stage 1 condition are
compared with the EPD routine monitoring data collected in 2006 at or near the
four semi-enclosed bays in the Southern waters as shown in Table 6.48. These four semi-enclosed bays were predicted to be
under the greatest influence from the Stage 2A effluent. The comparison showed
that the model predictions are reasonable and in line with the actual measurements.
The locations of EPD monitoring stations are shown in Figure 6.1 and the semi-enclosed bays are indicated in Figure 6.3.
Table 6.48 Comparison between
the Model Prediction and the EPD Monitoring Data
ID (Figure
6.3) |
Semi-enclosed
Bays (EPD
Monitoring Station) |
Annual
Mean P Level under Stage 1 Condition, in mg/l |
|
Model
Prediction |
EPD
Monitoring Data |
||
WQC
: |
0.01 |
||
1 |
|
0.014 |
0.02 |
2 |
|
0.014 |
0.02
|
3 |
|
0.012 |
0.01 |
4 |
|
0.010 |
0.01 |
6.269 A sensitivity test, namely Scenario 2f, was conducted to investigate the effect of enhancing the P removal rate at the SCISTW to around 80% under Stage 2A in 2021. The P removal rate from the current CEPT process at SCISTW was around 40% to 50% (equivalent to an effluent PO4 concentration of about 2 mg/l). With an 80% enhanced P removal rate, the PO4 concentration in the HATS effluent could be reduced to 0.6 mg/l (based on Table 2.16 of the EEFS Final Report). Based on the sensitivity test results as shown in Figure 6.48, the enhanced P removal would further reduce the areas of modelled exceedances at the semi-enclosed bays located in the Southern waters as compared to the baseline Stage 1 condition and the Stage 2A condition.
6.270
However,
the enhanced P removal from the Stage 2A effluent of up to 80% would not
completely eliminate the PO4 exceedances (only the area of the
modelled exceedances would be reduced). Table
6.49 to Table 6.51 tabulate the
mean P level predicted at the four semi-enclosed bays. The values shown in the
tables represent the P level predicted at the centre of each semi-enclosed bay.
Table 6.49 Predicted Depth-averaged Ortho-Phosphate Levels at
Semi-enclosed Bays (Annual Mean)
Semi-enclosed |
(1) |
(2) |
(3) |
(4) |
(5) |
HATS + Background source (mg/l) |
% difference |
||||
2021 without HATS 2A (under Stage 1
Condition) |
2021 Late Phase of HATS 2A |
2021 Late Phase of HATS 2A + Enhanced
P-removal of 80% |
Reduction Due to HATS 2A
Implementation (2) - (1) |
Further Reduction Due to
Enhanced P Removal for HATS 2A (3) - (2) |
|
|
0.0152 |
0.0142 |
0.0110 |
-6.9% |
-22.3% |
|
0.0146 |
0.0136 |
0.0109 |
-6.5% |
-20.1% |
|
0.0125 |
0.0121 |
0.0109 |
-3.3% |
-9.8% |
|
0.0104 |
0.0100 |
0.0092 |
-3.5% |
-8.8% |
Note: Bolded and shaded
value indicate exceedance of WQC
Table 6.50 Predicted Depth-averaged Ortho-Phosphate Levels at
Semi-enclosed Bays (Dry Season)
Semi-enclosed |
(1) |
(2) |
(3) |
(4) |
(5) |
HATS + Background source (mg/l) |
% difference |
||||
2021 without HATS 2A (under Stage 1
Condition) |
2021 Late Phase of HATS 2A |
2021 Late Phase of HATS 2A + Enhanced
P-removal of 80% |
Reduction Due to HATS 2A
Implementation (2) - (1) |
Further Reduction Due to
Enhanced P Removal for HATS 2A (3) - (2) |
|
|
0.0170 |
0.0158 |
0.0119 |
-6.9% |
-24.6% |
|
0.0157 |
0.0147 |
0.0111 |
-6.7% |
-24.2% |
|
0.0114 |
0.0110 |
0.0092 |
-4.3% |
-15.6% |
|
0.0096 |
0.0093 |
0.0083 |
-3.9% |
-10.4% |
Note: Bolded and
shaded value indicate exceedance of WQC
Table 6.51 Predicted Depth-averaged Ortho-Phosphate Levels at
Semi-enclosed Bays (Wet Season)
Semi-enclosed |
(1) |
(2) |
(3) |
(4) |
(5) |
HATS + Background source (mg/l) |
% difference |
||||
2021 without HATS 2A (under Stage 1
Condition) |
2021 Late Phase of HATS 2A |
2021 Late Phase of HATS 2A + Enhanced
P-removal of 80% |
Reduction Due to HATS 2A
Implementation (2) - (1) |
Further Reduction Due to
Enhanced P Removal for HATS 2A (3) - (2) |
|
|
0.0159 |
0.0158 |
0.0137 |
-1.2% |
-13.2% |
|
0.0173 |
0.0172 |
0.0157 |
-1.0% |
-8.6% |
|
0.0189 |
0.0188 |
0.0185 |
-0.2% |
-1.8% |
|
0.0145 |
0.0143 |
0.0134 |
-1.3% |
-6.6% |
Note: Bolded and shaded
value indicate exceedance of WQC
6.271
Based
on the mean values shown in tables above, the enhanced P removal for HATS would
eliminate the P exceedance at only 1 semi-enclosed bay in dry season. In
wet season, the WQC for P would still be exceeded at all the bays even with the
adoption of enhanced P removal of up to 80%. Further modelling works were
conducted to distinguish the impacts due to the HATS effluent discharge and
those due to other background pollution sources; and to analyze the modelled data
to detect the spatial and seasonal trends. A total of four sensitivity
scenarios were tested for the late phase of Stage 2A in 2021 to isolate the
impact of HATS as listed below:
Scenario 1 - With HATS effluent only (without other background pollution source), no
enhanced P removal is assumed for HATS
Scenario 2 - With HATS
effluent only (without other background pollution source), enhanced P removal
(80%) is assumed for HATS
Scenario 3 - With HATS
effluent plus other background pollution sources, no enhanced P removal is
assumed for HATS
Scenario 4 - With HATS
effluent plus other background pollution sources, enhanced P removal (80%) is
assumed for HATS
6.272
The
time series plots to show the seasonal trends of P levels predicted at the
semi-enclosed bays under the four sensitivity scenarios are given below.
The percentage (%) of time in compliance with the WQC for different sensitivity
scenarios under different seasons are shown in Table 6.52 to Table 6.54.
Table 6.52 Percentage of Time in Compliance with the WQC for
P (within a 1-year period)
Sensitivity
Scenario |
Description (Late
Phase of Stage 2A with HATS flow of 2.17M m3/day) |
|
|
|
|
1 |
HATS
Stage 2A only (without Enhanced P Removal) |
100% |
100% |
100% |
100% |
2 |
HATS
Stage 2A only (with Enhanced P Removal) |
100% |
100% |
100% |
100% |
3 |
HATS
Stage 2A + Other Background Pollution Sources (without Enhanced P Removal) |
55% |
68% |
52% |
56% |
4 |
HATS
Stage 2A + Other Background Pollution Sources (with Enhanced P Removal) |
85% |
84% |
72% |
75% |
Table 6.53 Percentage of Time in Compliance with the WQC for
P (in Dry Season)
Sensitivity
Scenario |
Description (Late Phase of Stage 2A with HATS
flow of 2.17M m3/day) |
|
|
|
|
1 |
HATS
Stage 2A only (without Enhanced P Removal) |
100% |
100% |
100% |
100% |
2 |
HATS
Stage 2A only (with Enhanced P Removal) |
100% |
100% |
100% |
100% |
3 |
HATS
Stage 2A + Other Background Pollution Sources (without Enhanced P Removal) |
14% |
36% |
34% |
64% |
4 |
HATS
Stage 2A + Other Background Pollution Sources (with Enhanced P Removal) |
93% |
100% |
100% |
96% |
Table 6.54 Percentage of Time in Compliance with the WQC for
P (in Wet Season)
Sensitivity
Scenario |
Description (Late Phase of Stage 2A with HATS
flow of 2.17M m3/day) |
|
|
|
|
1 |
HATS
Stage 2A only (without Enhanced P Removal) |
100% |
100% |
100% |
100% |
2 |
HATS
Stage 2A only (with Enhanced P Removal) |
100% |
100% |
100% |
100% |
3 |
HATS
Stage 2A + Other Background Pollution Sources (without Enhanced P Removal) |
11% |
3% |
0% |
0% |
4 |
HATS
Stage 2A + Other Background Pollution Sources (with Enhanced P Removal) |
29% |
8% |
0% |
3% |
6.273
With
the HATS effluent discharge alone, all the P levels predicted at the
semi-enclosed bays were well below the WQC with no significant variation between
dry and wet seasons. With the addition of other background sources, the P
level exceeded the WQC at all the semi-enclosed bays with an obvious trend of
increasing P in the wet season. It was also predicted that the WQC exceedance
for P occurred more frequently in the wet season. Appendix 6.6 summarizes the relative P contributions from
individual pollution sources including the HATS discharge, the
6.274
Based
on the model results, reduction of local pollution load would be a more
effective means to reduce the P exceedance at the semi-enclosed bays. It
should be noted that the local pollution load assumed in the model was derived
from theoretical calculation. Following the common approach normally adopted in
other approved EIAs, it was assumed in this EIA that 10% of the total load
generated in the catchment would be discharged to the marine water under all
the future assessment scenarios which is a conservative assumption. In fact, to tackle the local pollution problems, the government has
been implementing the following local sewerage works to serve the unsewered
villages in the outlying islands:
·
·
Outlying Island Sewerage Stage 2
Lamma Village Sewerage Phase II (scheduled to commence construction in 2010 for
completion in 2013)
·
Outlying Island Sewerage Stage 1
Phase I Part II and Phase I Yung Shue Wan and Sok Kwu
Wan Sewerage, Sewage Treatment and Disposal (scheduled to commence construction
in 2008 for completion in 2010)
·
Upgrading of Mui Wo Village Sewerage
Phase 2 and Mui Wo Sewage Treatment Works Investigation, Design and
Construction (scheduled to commence construction in 2009 for completion in
2012)
6.275
With
the continuous effort to implement sewerage improvement and pollution
control measures to reduce the local pollution sources by the Government, there will be a further load reduction for the local pollution
sources at the time when the Stage 2A is implemented by 2014.
6.276
The modelling assessment indicated that the risk of red tide occurrence would
already be reduced as a result of the Stage 2A implementation alone. The model
predicted that the Stage 2A implementation alone would improve the water
quality (in terms of both N & P) in the receiving waters including the
semi-enclosed bays in the
6.277
The upper limits of the
operational range for sodium bisulphite dosage of 11 mg/l, 4 mg/l and 2 mg/l
for ADF, Stage
6.278
The average and maximum levels
of oxygen depletion predicted at the Project discharge point are given in Table 6.55. Based on the EPD routine monitoring
data, the mean ambient oxygen levels measured near the Project discharge point
were 5.7 and 5.8 mg/l at stations WM3 and VM8 respectively in 2005. It should be noted that the oxygen
depletion as shown in Table 6.55 was
based on the values extracted from the grid cell in which the SCISTW outfall
was located. The size of the grid cells at or near the SCISTW outfall was
approximately
Table
6.55 Predicted Oxygen
Depletion at the SCISTW Outfall Location
TScenario |
Average |
Maximum |
||
Value (mg/l) |
% Decrease |
Value (mg/l) |
% Decrease |
|
2014
– Late Phase of ADF Stage |
0.024 |
0.43% |
0.074 |
1.29% |
2021
– Late Phase of Stage |
0.012 |
0.21% |
0.034 |
0.60% |
Ultimate
Year – Stage 2B |
0.007 |
0.12% |
0.019 |
0.33% |
Note: The
% decrease was calculated using the mean ambient oxygen levels measured near
the SCISTW outfall at EPD station WM
6.279 The oxygen depletions shown in Table 6.55 represented a very conservative condition as the maximum chemical dosage was assumed to be the sodium bisulphite concentration in the effluent. In reality, the chemical would react with chlorine and be consumed within the dechlorination facilities and the diffuser systems. The actual concentration of the dechlorination chemical in the effluent should be much smaller. Thus, oxygen depletion caused by the Project would be negligible.
6.280 The modelling results for the worst-case sewage overflow at all the PTWs within the HATS catchment due to heavy rain for a period of 8 hours under normal operation of the Project (namely Scenario A) are tabulated for all the water and marine ecological sensitive receivers identified within the Study Area in Appendix 6.3 to Appendix 6.5. Appendix 6.3 presents the peak concentrations for E.coli, NH3-N, SS and BOD5 as well as the minimum concentrations for DO predicted at the WSD flushing water intakes for comparison with the WSD water quality standards. Appendix 6.4 gives the annual geometric means for E.coli and annual averages for UIA, PO4, TIN and UIA predicted at all the beaches for comparison with the WQO/WQC. Appendix 6.5 also gives the annual geometric means for E.coli and annual averages for UIA, PO4, TIN and UIA as well as the maximum sedimentation rates predicted at all the marine ecological sensitive receivers (including fish culture zones and coral sites) for comparison with the assessment criteria. It should be noted that, under Scenario A, several model runs were conducted to cover different discharge start times. However, the results provided in Appendix 6.3 to Appendix 6.5 are not presented for all the model runs. For the sake of simplicity, only the model run with greater water quality impact is selected and presented in these appendices.
6.281 Some of the model results presented in Appendix 6.4 and Appendix 6.5 for beaches and marine ecological sensitive receivers are mean values over the entire simulation period which cannot reflect the short term impacts of the temporary overflow over 8 hours. The elevation / trend of pollution levels during and after the sewage bypass period (as compared to the normal condition during late phase of HATS Stage 2A) is illustrated by means of time series plots. The time series plots for selected indicator points (beaches, fish culture zones and flushing water intakes) covering the periods before, during and after the temporary discharges are shown in Figure 6.49 to Figure 6.56. The results provided in the time series plots for the beaches and fish culture zones are depth-average values whereas those for the WSD flushing water intakes represent the middle water layer. As this scenario aims to address the water quality effects due to heavy rain, only wet season results are presented and assessed.
6.282 The water quality impact on secondary contact recreation subzones, beaches and fish culture zones (FCZ) is assessed in terms of E.coli, which is used to measure the suitability of water recreation, bathing and marine cultural activities. Water quality objectives have been established for beaches at 180 no. per 100 ml, which is a geometric mean value for bathing season (March to October). Water quality objectives have also been established for secondary contact recreation subzones and FCZ at 610 no. per 100 ml, which is an annual geometric mean value. The model predicted that the worst-case overflow event would cause the following water quality effects:
·
Short-term and very minor elevation of E.coli level at two beaches (B24, B26), refer to Figure 6.1 for their locations.
The short-term sewage overflows did not cause the E.coli level predicted at these 2
beaches to exceed the criteria value of 180 no. per 100 ml. Only very minor or
negligible increase of E.coli level
was predicted at all the remaining beaches within the Study Area.
·
Short-term and very minor elevation of E.coli level at the eastern part of the secondary contact
recreation subzone in
·
Short-term elevation of E.coli
level at two FCZ (F1, F4), refer to Figure 6.1 for their locations.
All the peak E.coli values
predicted at F4 during the overflow period were below the criteria value of 610
no. per 100 ml under all the discharge scenarios. However, the E.coli levels predicted at F1 would reach a peak value of about 700
no. per 100 mL under the spring-ebb tide condition which marginally exceeded
the criteria value.
6.283 The time series plots for selected beaches (B9, B14, B24, B26, B27, B28) and FCZ (F1, F4, F5) are presented for E.coli in Figure 6.49 and Figure 6.50 for reference. Figure 6.1 shows these indicator points. It was found that all elevations of E.coli levels caused by the temporary overflow were minor and transient. The normal water quality conditions (i.e. the conditions under normal operation of Stage 2A) were predicted to recover quickly (within 1 day) after the end of the temporary overflow period.
6.284
The
pollution levels for other parameters such as nutrients and DO were not predicted to be adversely affected
by the sewage overflows. Figure 6.51 and Figure 6.52 presents the time series plots for DO (which is an important parameter
for maintaining a healthy ecosystem) which indicated that the short-term
overflows would only cause minor or negligible effect on the DO level predicted
at all the beaches and FCZ.
6.285
As
shown in Appendix 6.5, the maximum
values for sedimentation rates predicted at all the coral sites complied well with
the assessment criterion of 100g/m2/day under the overflow
scenario. The SS levels predicted
at all the ecological sensitive receivers would also fully comply with the WQO
of no more than 30% increase from the ambient level.
6.286 The time series plots for WSD flushing water intakes are presented for E.coli in Figure 6.53 and Figure 6.54. The target E.coli limit specified by WSD at the flushing water intake points is 20,000 no. per 100 ml, expressed as a maximum value. The model predicted that the worst-case sewage overflows would cause short-term elevations of E.coli at 12 flushing water intakes (WSD9, WSD10, WSD11, WSD 12, WSD13, WSD15, WSD17, WSD18, WSD19, WSD20, WSD22, WSD21). Figure 6.1 shows these indicator points. However all the peak values predicted during the overflow periods complied well with the WSD criterion of 20,000 no. per 100mL except at only one flushing water intake (WSD10) where the peak E.coli level exceeded the criteria value. The peak value predicted at WSD10 was about 145,960 no. per 100 mL under the spring-ebb condition. For the discharge under the neap tide condition, the peak E.coli level predicted at WSD10 was much lower (about 30,000 no. per 100 mL) which only marginally exceeded the criteria value. It was found that all elevations of E.coli levels caused by the temporary overflows were transient. The normal water quality conditions (i.e. the conditions under normal operation of the Stage 2A) were predicted to recover quickly (within 1 day) after the end of the temporary overflow period.
6.287
The
temporary overflows would not cause any exceedance at the flushing water intakes
for DO, SS, NH3-N and BOD5 (refer to Appendix 6.3). Figure 6.55 and Figure 6.56 illustrate the trend of SS levels predicted at the WSD flushing water
intakes, which indicated that the SS elevations caused by the temporary
discharge were minor and acceptable.
6.288 The maximum increase in E.coli at secondary contact recreation subzones, beaches and FCZ attributable to the overflows would be small. The impact of the overflow dissipated rapidly, due to the combination of natural die off of the bacteria in seawater and through dilution. By one day after the end of the discharge the effect would be completely gone. The temporary overflow would not cause any non-compliance with the assessment criteria at all the secondary contact recreation subzones, beaches and FCZ. Although the peak E.coli level predicted at Tung Lung Chau FCZ (F1) marginally breached the criteria value during the overflow period, the impact would be short term (for a few hours). Non-compliance with the WQO/WQC (which is an annual geometric mean) was not predicted.
6.289 The E.coli impact of the overflows on flushing water intakes was predicted to be more dramatic, mostly because the overflows were assumed to be discharged via seawall bypass locations which are often close to the flushing water intakes (also located along the seawall). However, it was predicted that E.coli exceedance would occur at only one intake at Cha Kwo Ling (WSD10) under the wet season scenario.
6.290 It should be highlighted that the adverse assumption of using the peak overflow value for continuous discharge of 8 hours was adopted for modelling. In reality, the peak flow rates would occur during a short period of time within the overflow period. It is also assumed that the peak overflow discharge would occur at all the PTWs at the same time. This is also extremely conservative due to the fact that not all the catchments will peak at the same time. From historical records for the Stage 1 PTWs, emergency sewage overflow due to storm events mostly occurred at NWKPS which will be modified under this Project to minimize the overflow discharge. For the rest of the catchment, sewage overflow as a result of heavy rain only occurred twice since 2005 at Chai Wan PTW and Kwun Tong PTW respectively. The recorded annual sewage overflow volume (6,028 m3 associated with heavy rainfall from the Chai Wan PTW and Kwun Tong PTW) is insignificant (as compared to the total overflow volume of 358,848 m3 assumed in this modelling exercise). Therefore, the model results presented in this EIA represent an extremely worst scenario for conservative assessment. The real situation that would happen would be much better than that simulated under this modelling exercise.
6.291 The water quality impact from the overflow discharge is considered minor and acceptable in view of the following:
·
The temporary overflow would not cause any adverse effect on
public health and health of biota or risk to life (the temporary discharge
would not cause any WQO/WQC non-compliance at all the identified secondary
contact recreation subzones, beaches and FCZ based on model predictions);
·
The magnitude of the adverse water quality impact would be
small and the potential water quality impact would be short-term (less than 1
day) and reversible (the normal water quality would resume quickly after the
discharges);
·
The frequency of the potential water quality impact would be
low (less than 1 per year based on historical records);
·
The water quality impact would not occur in areas or regions
that are ecologically fragile or sensitive (the impact zone would be mainly
confined in Victoria Harbour and the adjacent waters and would not encroach on
any ecological sensitive receiver of great importance);
·
The temporary bypass would not cause any disruption to the
seabed and therefore no disruption to any site of cultural heritage;
·
The potential impact area is not of international and
regional importance (the area is currently subject to the pollution discharge
from the urbanized areas in
6.292 The modelling results for emergency discharge from HATS due to equipment / power failure (namely Scenario B and Scenario C) are tabulated for all the water and marine ecological sensitive receivers identified within the Study Area in Appendix 6.3 to Appendix 6.5. Appendix 6.3 presents the peak concentrations for E.coli, NH3-N, SS and BOD5 as well as the minimum concentrations for DO predicted at the WSD flushing water intakes for comparison with the WSD water quality standards. Appendix 6.4 gives the annual geometric means for E.coli and annual averages for UIA, PO4, TIN and UIA predicted at all the beaches for comparison with the WQO/WQC. Appendix 6.5 also gives the annual geometric means for E.coli and annual averages for UIA, PO4, TIN and UIA as well as the maximum sedimentation rates predicted at all the marine ecological sensitive receivers (including fish culture zones and coral sites) for comparison with the assessment criteria. It should be noted that, under Scenario B (i.e. total power / equipment breakdown at SCISTW), several model runs were conducted to cover different discharge start times. Under Scenario C (i.e. power / equipment failure at the Stage 2 PTWs), separate model runs were performed to simulate the impact for each of the 8 individual PTWs and for different discharge start times. However, the results provided in Appendix 6.3 to Appendix 6.5 are not presented for all the model runs. Only the model run with greater water quality impact is selected and presented in these appendices.
6.293 Some of the model results presented in Appendix 6.4 and Appendix 6.5 for beaches and marine ecological sensitive receivers are mean values over the entire simulation period which cannot reflect the short term impacts of the temporary overflow over 6 hours. The elevation / trend of pollution levels during and after the sewage bypass period (as compared to the normal condition during late phase of Stage 2A) is illustrated by means of time series plots. The time series plots for selected indicator points (beaches, FCZ and flushing water intakes) covering the periods before, during and after the temporary discharges are shown in Figure 6.57 to Figure 6.72. The results provided in the time series plots for the beaches and fish culture zones are depth-average values whereas those for the WSD flushing water intakes represent the middle water layer.
6.294 The water quality impact on secondary contact recreation subzones, beaches and fish culture zones (FCZ) is assessed in terms of E.coli, which is used to measure the suitability of secondary contact recreation subzones, bathing and marine cultural activities. Water quality objectives have been established for beaches at 180 no. per 100 ml, which is a geometric mean value for bathing season (March to October). Water quality objectives have also been established for secondary contact recreation subzones and FCZ at 610 no. per 100 ml, which is an annual geometric mean value. The model predicted that the worst-case emergency discharge would cause the following water quality effects:
·
Short-term elevation of E.coli
level at four beaches (B7, B8, B9, B14, 24) in dry season and seven beaches
(B7, B8, B9, B14, B24, B26, B31) in wet season (refer to Figure 6.1 for their locations). The short-term emergency discharge
would cause the E.coli level
predicted at these beaches to occasionally exceed the criteria value of 180 no.
per 100 ml. The E.coli elevations
were relatively minor or negligible for all the remaining beaches identified in
the Study Area.
·
Short-term and very minor elevation of E.coli level at the secondary contact recreation subzones in Tsuen
Wan and Southern Districts. All the peak E.coli
values predicted at the secondary contact recreation subzones during the
overflow period were below the criteria value of 610 no. per 100 ml under all
the discharge scenarios.
·
Short-term elevation of E.coli
level at three FCZ (F1, F4, F5) (refer to Figure 6.1 for their locations).
However, the peak E.coli values
predicted at all the three FCZ during the emergency period were below the
criteria value of 610 no. per 100 ml under all the discharge scenarios, except
at Tung Lung Chau FCZ (F1) where the E.coli
levels would reach a peak value of 738 no. per 100 mL under the spring-ebb
tide condition which marginally exceeded the criteria value.
6.295 The time series plots for selected beaches and FCZ are presented for E.coli in Figure 6.57 to Figure 6.60. Figure 6.1 shows these indicator points. The time series plot of E.coli for an indicator point located at the boundary of the secondary contact recreation subzone in Tsuen Wan District is given in Figure 6.60a. Elevations of E.coli levels were predicted immediately after the start of temporary discharge. The normal water quality conditions (i.e. the conditions under normal operation of the HATS Stage 2A) were predicted to recover within 1 days after the end of the emergency discharge.
6.296
The
pollution levels for other parameters such as nutrients and DO were not predicted to be significantly
affected by the emergency discharge. Figure 6.61 to Figure 6.64 present the time series plots for DO (which is an important parameter
for maintaining a healthy ecosystem) which indicated that the short-term
emergency discharge would only cause minor or negligible effect on the DO level
predicted at all the beaches and FCZ.
6.297
As
shown in Appendix 6.5, the maximum
values for sedimentation rates predicted at all the coral sites complied well with
the assessment criterion of 100g/m2/day under the emergency
scenario. The SS levels predicted at all the ecological sensitive receivers
would also fully comply with the WQO of no more than 30% increase from the
ambient level.
6.298 The time series plots for WSD flushing water intakes are presented for E.coli in Figure 6.65 to Figure 6.68. The target E.coli limit specified by WSD at the flushing water intake points is 20,000 no. per 100 ml, expressed as a maximum value. The model predicted that the worst-case emergency discharge would cause E.coli exceedances at 10 flushing water intakes (WSD5, WSD9, WSD10, WSD11, WSD12, WSD13, WSD17, WSD18, WSD19, WSD22) in dry season and 8 flushing water intakes (WSD5, WSD9, WSD10, WSD11, WSD12, WSD13, WSD18, WSD19) in wet season. Figure 6.1 shows the intake locations. The exceedance values predicted at these intakes ranged from 24,880 to 126,100 no. per 100 mL as compared to the WSD criterion of 20,000 no. per 100mL. Elevations of E.coli levels were predicted immediately after the start of temporary discharge. The normal water quality conditions (i.e. the conditions under normal operation of the HATS Stage 2A) were predicted to recover within 1 day after the end of the emergency discharge.
6.299
The
emergency discharge would not cause any exceedance at the flushing water
intakes for DO, SS, NH3-N and BOD5 (refer to Appendix 6.3). Figure 6.69 to Figure 6.72 illustrate the trend of SS levels predicted at the WSD flushing water
intakes, which indicated that the SS elevations caused by the temporary
discharge were minor and acceptable.
6.300
Precautionary
measures e.g. standby equipment and dual (back-up) power supply would be
provided at the SCISTW to control emergency discharge. From historical records,
no emergency discharge has happened at SCISTW before since its commissioning.
Under the extremely remote case that it did happen, the bacterial level in the
6.301 Under the emergency discharge event, water quality at the beaches in Tsuen Wan and Southern Districts would be potentially affected. The Leisure and Cultural Services Department (LCSD) is currently the “beach management authority”, responsible for determining the opening and closing of gazetted beaches. The decision is made with reference to the advice provided by EPD on the suitability of beach water quality for bathing purposes and the consideration of all other factors. Generally, a beach will be closed if it is ranked "Very Poor" repeatedly. Beaches having geometric mean E.coli densities greater than 610 per 100mL are ranked "Very Poor". As indicated in the in Figure 6.57 to Figure 6.60, all the peak E.coli values predicted at the beaches during and after the emergency discharge period are considered acceptable and well below 610 per 100 mL. As the potential elevation of E.coli level occurred only for a very short period (less than 1 day), non-compliance with the WQO/WQC (which is a geometric mean for bathing season, March to October) was not predicted. No unacceptable public health effect would be expected due to the temporary discharge. In case of the extremely remote event of total equipment or power failure at SCISTW, it is recommended that relevant government departments including EPD and LCSD should be informed by DSD as soon as possible of any emergency discharge. Water quality monitoring should be carried out at such a time to quantify the water quality impacts and to determine when the baseline water quality conditions are restored.
6.302
The E.coli impact was predicted at the flushing water intakes in
6.303
It was predicted that the E.coli level would exceed the criteria
value of 610 no. per 100 mL at Tung Lung Chau FCZ due to the emergency
discharge. However, the predicted peak level was 738 no. per 100 mL which only
marginally exceeded the criteria value. As the exceedance occurred only for a
very short period (about three hours), non-compliance with the WQO/WQC (which
is an annual geometric mean value) was not predicted. No insurmountable water
quality impact would be expected on the FCZ due to the emergency discharge.
6.304 The water quality impact from the emergency discharge is considered minor and acceptable in view of the following:
·
The emergency discharge would not cause any adverse effect
on public health and health of biota or risk to life (the emergency discharge
would not cause any non-compliance with the WQO/WQC at all the identified
secondary contact recreation subzones, beaches and FCZ based on model
predictions);
·
The magnitude of the adverse water quality impact would be
small and the potential water quality impact would be short-term (less than 1
day) and reversible (the normal water quality would resume quickly after the
discharges);
·
The frequency of the potential water quality impact would be
extremely remote as dual power supply and standby facilities would be provided
at the SCISTW to minimize the occurrence of emergency discharge (no emergency
discharge has happened at SCISTW since its commissioning);
·
The water quality impact would not occur in areas or regions
that are ecologically fragile or sensitive (the impact zone would be mainly
confined in Victoria Harbour and the adjacent waters and would not encroach on
any ecological sensitive receiver of great importance);
·
The emergency discharge would not cause any disruption to
the seabed and therefore no disruption to any site of cultural heritage;
·
The potential impact area is not of international and
regional importance (the area is currently subject to the pollution discharge
from the urbanized areas in
6.305
Precautionary
measures e.g. standby equipment and dual (back-up) power supply would be
provided at the PTWs to control emergency discharge.This
scenario represents the worst-case impact from seawall bypass of raw sewage at
individual PTW within the Stage 2 catchment due to power or equipment
failure. Model simulation was
performed for only one PTW at a time to evaluate the extent of impact due to
the sewage bypass at one individual PTW alone. Model runs were performed for
all the eight Stage 2 PTWs.
6.306
The model predicted that the
emergency discharge from individual Stage 2 PTW would cause the following
short-tem E.coli exceedances:
Scenario See Note 1 |
Location of exceedances (refer to Figure
6.1) |
Season |
Peak E.coli
level predicted over the emergency discharge period (no./100 mL) |
Maximum duration of exceedance (hours) |
Total power / equipment failure at Wan
Chai East PTW See Note 2 |
WSD17 |
Dry Season |
33,813 |
2 |
WSD22 |
Dry Season |
99,389 |
7 |
|
Total power / equipment failure at North
Point PTW See Note 3 |
WSD17 |
Dry Season |
33,595 |
2 |
Total power / equipment failure at Central
PTW See Note 4 |
WSD18 |
Dry Season |
76,561 |
7 |
Wet Season |
41,580 |
2 |
||
WSD19 |
Dry Season |
41,010 |
2 |
|
Wet Season |
22,970 |
2 |
||
Total power / equipment failure at Sandy
Bay PTW See Note 5 |
B31 |
Wet Season |
425 |
6 |
Total
power / equipment failure at Cyberport PTW See Note 6 |
B31 |
Wet
Season |
421 |
6 |
Total
power / equipment failure at Ap Lei Chau PTW See Note 7 |
B31 |
Wet
Season |
358 |
6 |
Notes:
1.
Power failure
at individual PTW may involve failure of sewage transfer pumping stations
causing sewage bypass at more than one PTWs (see Notes 2 to 7 below). No
exceedance was predicted for power failure at
2.
Power
failure at Wan Chai East PTW may cause sewage bypass from North Point and Wan
Chai East PTWs
3.
Power
failure at North Point PTW may cause sewage bypass from North Point PTW only
4.
Power
failure at Central PTW may cause sewage bypass from
5.
Power
failure at Sandy Bay PTW may cause sewage bypass from
6.
Power
failure at Cyberport PTW may cause sewage bypass from Cyberport, Wah Fu,
7.
Power
failure at Ap Lei Chau PTW may cause sewage bypass from Ap Lei Chau PTWs only.
6.307
The modelling results for
Scenario C are tabulated for all the water and marine ecological sensitive
receivers identified within the Study Area in Appendix 6.3 to Appendix
6.5. The time series plots for
Scenario C are not presented as they are similar to those presented for
Scenario A and Scenario B showing transient elevations of pollution levels at
sensitive receivers.
6.308
A total of 32 separate model
runs were performed to cover the emergency discharges from all the eight Stage
2 PTWs under various discharge start times. Only transient E.coli exceedances would occur at isolated sensitive receivers
under 10 out of 32 discharge scenarios and the water quality would return to
normal condition within 1 day after the end of emergency discharge period. No
exceedance was predicted under all the remaining 22 discharge scenarios. Precautionary measures e.g. standby equipment and dual (back-up) power
supply would be provided at the PTWs to control emergency discharge.
6.309 Temporary elevation of E.coli level was predicted at Chung Hom Kok beach (B31). The Leisure and Cultural Services Department (LCSD) is currently the “beach management authority”, responsible for determining the opening and closing of gazetted beaches. The decision is made with reference to the advice provided by EPD on the suitability of beach water quality for bathing purposes and the consideration of all other factors. Generally, a beach will be closed if it is ranked "Very Poor" repeatedly. Beaches having geometric mean E.coli densities greater than 610 per 100mL are ranked "Very Poor". As indicated in the in table above, all the peak E.coli values predicted at B31 during and after the emergency discharge period are considered acceptable and well below 610 per 100 mL. As the potential exceedance of the E.coli criterion of 180 no. per 100 mL occurred only for a very short period (maximum 6 hours), non-compliance with the WQO/WQC (which is a geometric mean value for bathing season, March to October) was not predicted. Potential elevation of E.coli levels were also predicted at the secondary contact recreation subzones in Southern Districts. Similarly, as the potential elevation would be short-term non-compliance with the WQO/WQC (which is an annual geometric mean value) was not predicted at the secondary contact recreation subzones. No unacceptable public health effect would be expected due to the temporary discharge.
6.310
The E.coli impact was predicted at the flushing water intakes in
6.311 The water quality impact from the emergency discharge is considered minor and acceptable in view of the following:
·
The emergency discharge would not cause any adverse effect
on public health and health of biota or risk to life (the emergency discharge
would not cause any WQO/WQC non-compliance at all the identified secondary
contact recreation subzones, beaches and FCZ based on model predictions);
·
The magnitude of the adverse water quality impact would be
small and the potential water quality impact would be short-term (less than 1
day) and reversible (the normal water quality would resume quickly after the
discharges);
·
Standby unit(s) will be provided at all the Stage 2 PTWs to
minimize the risk of emergency discharge. The frequency of the potential water
quality impact would be remote. Emergency discharge occurred only once at Kwun
Tong PTW (due to equipment failure) for 2 hours since 2005 based on the review
of historical emergency discharge records for all the Stage 1 PTWs;
·
The water quality impact would not occur in areas or regions
that are ecologically fragile or sensitive (the impact zone would be localized
and would not encroach on any ecological sensitive receiver of great
importance);
·
The emergency discharge would not cause any disruption to
the seabed and therefore no disruption to any site of cultural heritage;
· The potential impact area is not of international and regional importance (the area is currently subject to the pollution discharge from the urbanized areas in HK Island; Implementation of this Project would reduce the pollution discharge to the concerned area).
6.312
Water
quality impacts in relation to the temporary failure of chlorination plant have
been fully assessed under the separate EIA for “HATS Provision of Disinfection
Facilities at SCISTW (ADF)” and are therefore not re-modelled under this EIA
(also see Section 6.18).
6.313 The model results provided in the EIA report for ADF indicated that the bacteria levels at the gazetted beaches and the secondary contact recreation subzones in Tsuen Wan coastal waters would be significantly elevated due to the emergency release of undisinfected effluent at the SCISTW outfall during ADF stage and Stage 2A. The peak E.coli values predicted at the Tsuen Wan beaches would exceed the WQO of 180 no. per 100 mL but impacts are expected to be short-term. The water quality would return to normal conditions within 2 days after the end of the emergency discharge periods. In the event of emergency discharge of undisinfected effluent, all the beaches in the Tsuen Wan District should be closed. The Plant operators of SCISTW should inform EPD and LCSD as soon as possible so that appropriate actions can be taken. Water quality monitoring should be carried out to quantify the water quality impacts and to determine when the normal water quality conditions are recovered. In view of the temporary nature of the emergency discharge, no insurmountable water quality impact is expected. Detailed model results for the temporary discharge of undisinfected CEPT effluent from SCISTW can be referred to the approved EIA report for ADF.
6.314 The discharge of chlorinated effluent (without dechlorination) under the event of dechlorination plant failure has been modelled under the EIA study for ADF for various discharge durations and scenarios, refer to Table 6.31b. It is considered that the chlorination process could be practically stopped within 30 minutes upon the occurrence of any dechlorination plant failure. The model results provided under the ADF EIA indicated that, during the emergency discharge periods, the TRC levels near the SCISTW outfall would be elevated and the TRC levels would exceed the assessment criterion in the near field during the emergency discharge period. Since the impact zones for the emergency TRC discharge were predicted to be localized (close to the SCISTW outfall) and temporary (within a few hours), the associated water quality and ecological impacts should be limited. The model results indicated that the maximum TRC levels predicted at all the identified water and ecological sensitive receivers would comply well with the assessment criterion of 0.008 mg/l under the emergency situations. Detailed modelling results for the temporary discharge of undisinfected CEPT effluent from SCISTW can be referred to the approved EIA report for ADF.
6.315 The Project would involve the following major construction activities:
·
Site formation & site establishment
·
Piling (pre-bored H pile)
·
Excavation and backfilling
·
Tunnel construction works
·
Erection of formwork and reinforcement
·
Concreting
·
Fabrication of steelwork & installation of E&M
equipment
6.316
The land-based construction works would have the potential to
cause water pollution. Various
types of construction activities may generate wastewater. These include general
cleaning and polishing, wheel washing, dust suppression and utility
installation. These types of
wastewater would contain high concentrations of suspended solids. Impacts could also result from the
accumulation of solid and liquid waste such as packaging and construction
materials, and sewage effluent from the construction work force involved with
the construction.
6.317 However, the effects on water quality from general construction activities are likely to be minimal, provided that site drainage would be well maintained and good construction practices would be observed such that litter, fuels, and solvents are managed, stored and handled properly.
6.318 Based on the Sewerage Manual, Part I, 1995 of the Drainage Services Department (DSD), the sewage production rate for construction workers was estimated to be 0.35 m3 per worker per day. For every 50 construction workers working simultaneously at the construction site, about 17.5 m3 of sewage would be generated per day. The sewage should not be allowed to discharge directly into the surrounding water body without treatment. Sufficient chemical toilets should be provided for workers.
6.319
During a rainstorm, site runoff
would wash away the soil particles. The runoff is generally characterised by
high concentrations of suspended solids.
Release of uncontrolled site runoff would increase the SS levels and
turbidity in the nearby water environment.
6.320 Wind blown dust would be generated from exposed soil surfaces in the works areas. It is possible that wind blown dust would fall directly onto the nearby water bodies when a strong wind occurs. Dispersion of dust within the works areas may increase the SS levels in surface runoff causing a potential impact to the nearby sensitive receivers.
6.321 Construction run-off and drainage may cause local water quality impacts. Increase in SS arising from the construction site could block the drainage channels and may result in local flooding when heavy rainfall occurs. High concentrations of suspended degradable organic material in marine water could lead to a reduction in DO levels in the water column.
6.322 It is important that proper site practice and good site management be followed to prevent run-off with high level of SS from entering the surrounding waters. With the implementation of appropriate measures to control run-off and drainage from the construction site, disturbance of water bodies would be avoided and deterioration in water quality would be minimal.
6.323
A large variety of chemicals
may be used during construction activities. These may include surplus
adhesives, spent paints, petroleum products, spent lubrication oil, grease and
mineral oil, spent acid and alkaline solutions/solvent and other chemicals.
Accidental spillage of chemicals in the works areas may contaminate the surface
soils. The contaminated soil particles may be washed away by construction site
runoff or storm runoff causing water pollution. Provided that mitigation measures are properly implemented to minimize
and control accidental spillage, no adverse impact on the identified water
sensitive receivers is anticipated.
6.324 The proposed seawall re-construction at Aberdeen PTW would be conducted in close vicinity to the sea and may cause marine water quality impact due to potential release of construction wastes. Construction wastes are generally characterized by high concentration of SS and elevated pH. Adoption of good house keeping and mitigation measures would reduce the generation of construction wastes and potential water pollution. The implementation of measures to control runoff and drainage will be important for the construction works adjacent to the storm drains or marine water in order to prevent runoff and drainage water with high levels of SS from entering the water environment. With the implementation of adequate construction site drainage and the provision of mitigation measures, it is anticipated that unacceptable water quality impacts would not arise.
6.325 The modelling results for temporary sewage bypass during construction phase (namely Scenario D and Scenario E) are tabulated for all the water and marine ecological sensitive receivers identified within the Study Area in Appendix 6.3 to Appendix 6.5. Appendix 6.3 presents the peak concentrations for E.coli, NH3-N, SS and BOD5 as well as the minimum concentrations for DO predicted at the WSD flushing water intakes for comparison with the WSD water quality standards. Appendix 6.4 gives the annual geometric means for E.coli and annual averages for UIA, PO4, TIN and UIA predicted at all the beaches for comparison with the WQO/WQC. Appendix 6.5 also gives the annual geometric means for E.coli and annual averages for UIA, PO4, TIN and UIA as well as the maximum sedimentation rates predicted at all the marine ecological sensitive receivers (including fish culture zones and coral sites) for comparison with the assessment criteria.
6.326 Some of the model results presented in Appendix 6.4 and Appendix 6.5 for beaches and marine ecological sensitive receivers are mean values over the entire simulation period which cannot reflect the short term impacts of the temporary discharge for two weeks. The elevation / trend of pollution levels during and after the sewage bypass period (as compared to the normal condition during late phase of HATS Stage 1) is illustrated by means of time series plots. The time series plots for selected parameters covering the periods before, during and after the temporary discharges are shown in Figure 6.73 to Figure 6.76 for Scenario D and Figure 6.77 to Figure 6.84 for Scenario E. The predicted results for the normal operation scenarios are also included in these time series plots for comparison. The indicator points selected for presentation include ten beaches (namely B7, B8, B9, B10, B11, B12, B13, B14, B24 and B26), two fish culture zones (namely F1 and F5) and fourteen WSD flushing water intakes (namely WSD4, WSD5, WSD7, WSD9, WSD10, WSD11, WSD12, WSD13, WSD15, WSD17, WSD18, WSD19, WSD20 and WSD22) that may be potentially affected by the temporary bypass. The results provided in the time series plots for the beaches and fish culture zones are depth-average values whereas those for the WSD flushing water intakes represent the middle water layer. Figure 6.1 shows these indicator points.
6.327 Scenario D represents the worst-case temporary bypass of screened sewage at all the Stage 1 PTW submarine outfalls for a period of two weeks in the dry season at the late phase of HATS Stage 1 in 2014 due to the modification / interconnection works for the main pumping station at SCISTW.
6.328 The potential water quality impacts for secondary contact recreation subzones, beaches and fish culture zones (FCZ) are assessed in terms of E.coli, which is used to measure the suitability of secondary contact recreation subzones, bathing and marine cultural activities. The time series plots for selected beaches and FCZ are presented in Figure 6.73 for Scenario D. The time series plot of E.coli for an indicator point located at the boundary of the secondary contact recreation subzone in Tsuen Wan District is given in Figure 6.60a. Water quality objectives have been established for beaches at 180 no. per 100 ml, which is a geometric mean value for bathing season (March to October). Water quality objectives have also been established for secondary contact recreation subzones and FCZ at 610 no. per 100 ml, which is an annual geometric mean value. The model predicted that the 2-week temporary sewage bypass during dry season at the Stage 1 PTWs would cause the following water quality effects:
·
Short-term elevation of E.coli
level at nine beaches (B7, B8, B9, B10, B11, B12, B13, B14, B24). The model
predicted that the E.coli values at
these beaches would occasionally breach the criteria value of 180 no. per 100
ml during the temporary bypass period.
·
Short-term elevation of E.coli
level at the secondary contact recreation subzone in Tsuen Wan District where
the E.coli values would occasionally
breach the criteria value of 610 no. per 100 ml during the temporary bypass
period. The peak E.coli values
predicted at all other secondary contact recreation subzones (such as those in
the Southern District) were all below the criteria value of 610 no. per 100 ml.
·
Short-term elevation of E.coli
level at two FCZ (F1, F5). However,
all the peak E.coli values predicted
at the FCZ were below the criteria value of 610 no. per 100 ml.
6.329 Elevations of E.coli levels were predicted immediately after the start of temporary discharge. The trends of E.coli levels shown in Figure 6.73 indicated that the E.coli levels would sharply increase after the start of temporary sewage bypass. The normal water quality conditions (i.e. the conditions under normal operation of the HATS Stage 1) were predicted to recover within 2 days after the end of the temporary bypass period.
6.330
The
pollution levels for other parameters such as nutrients and DO were not
predicted to be significantly affected by the sewage bypass. Figure 6.74 presents the time series plots for DO (which is an important parameter
for maintaining a healthy ecosystem) which indicated that the temporary sewage
bypass would only cause minor or negligible effect on the DO level predicted at
all the beaches and FCZ.
6.331
As
shown in Appendix 6.5, the maximum
values for sedimentation rates predicted at all the coral sites complied well
with the assessment criterion of 100g/m2/day under the temporary bypass
scenario. The SS levels predicted at all the ecological sensitive receivers
would also fully comply with the WQO of no more than 30% increase from the
ambient level except for two isolated coral sites (C25 and CR28) in Junk Bay
where the SS increase was predicted to be 30.9% and 31.9% of the baseline
ambient values respectively which only marginally breached the WQO of 30%
increase. The SS exeedances at
these two coral sites would be very short-term (only last for 1 hour at CR25
and 4 hours at CR28), with a peak SS level of 5.2 mg/L only. These two coral sites are located in the eastern waters where the
baseline SS levels were low. In terms of the absolute values, the peak SS
levels predicted at these two coral sites were low and well below the value of
10 m/L. The SS value of 10 mg/L has been adopted as the SS criterion under many
other EIA studies in Hong Kong ([24]) for protection
of sensitive coral sites in the eastern and southern waters of
6.332 The time series plots for WSD flushing water intakes are presented for E.coli in Figure 6.75. The target E.coli limit specified by WSD at the flushing water intake points is 20,000 no. per 100 ml, expressed as a maximum value. The model predicted that the 2-week temporary sewage bypass would cause E.coli exceedances at only one flushing water intake (WSD5) with a peak value of 61,461 no. per 100 mL.
6.333
The
temporary bypass would not cause any exceedance at the flushing water intakes
for DO, SS, NH3-N and BOD5 (refer to Appendix 6.3). Figure 6.76 illustrates the trend of SS levels predicted at the WSD flushing water
intakes, which indicated that all the SS elevations caused by the temporary
discharge were minor and acceptable.
6.334 Scenario E represents the scenario of temporary bypass of screened sewage from NWK PTW at the seawall for a period of two weeks at the late phase of HATS Stage 1 in 2014 due to the modification to the existing NWKPS.
6.335 The potential water quality impacts for secondary contact recreation subzones, beaches and fish culture zones (FCZ) are assessed in terms of E.coli, which is used to measure the suitability of secondary contact recreation subzones, bathing and marine cultural activities. The time series plots for selected beaches and fish culture zones (FCZ) are presented for E.coli in Figure 6.77 and Figure 6.78 for Scenario E. Water quality objectives have been established for beaches at 180 no. per 100 ml, which is a geometric mean value for bathing season (March to October). Water quality objectives have also been established for secondary contact recreation subzones and FCZ at 610 no. per 100 ml, which is an annual geometric mean value. The model indicated that the 2-week temporary sewage bypass from the NWK PTW would cause only minor and short term E.coli elevations at four beaches (B7, B8, B9, B14) in dry season and two beaches (B7, 14) in wet season. The 2-week temporary sewage bypass from the NWK PTW would also cause minor and short term E.coli elevations at the secondary contact recreation subzone in Tsuen Wan District. The E.coli elevations were negligible for all the remaining secondary contact recreation subzones and beaches as well as all the FCZ identified in the Study Area. Non-compliance with the WQO/WQC was not predicted.
6.336
The
pollution levels for other parameters such as nutrients and DO were not
predicted to be significantly affected by the sewage bypass. Figure 6.79 and Figure 6.80 present the time series plots for DO (which is an important parameter
for maintaining a healthy ecosystem) which indicated that the temporary sewage
bypass would only cause minor or negligible effect on the DO level predicted at
all the beaches and FCZ.
6.337
As
shown in Appendix 6.5, the maximum
values for sedimentation rates predicted at all the coral sites complied well
with the assessment criterion of 100g/m2/day under the temporary
bypass scenario. The SS levels predicted at all the ecological sensitive
receivers would also fully comply with the WQO of no more than 30% increase
from the ambient level.
6.338 The temporary bypass from NWK PTW would not cause any exceedance at the flushing water intakes for all the parameters of concern including E.coli, DO, SS, NH3-N and BOD5 (refer to Appendix 6.3). Figure 6.81 to Figure 6.84 show the trend of pollution levels for selected parameters (E.coli and SS) predicted at the WSD flushing water intakes for reference.
6.339 The bacterial levels at 9 beaches (B7, B8, B9, B10, B11, B12, B13, B14, B24) and the secondary contact recreation subzone in the Tsuen Wan District were predicted to be potentially affected by the temporary sewage bypass under Scenario D. The geometric means of the E.coli levels predicted during the 2-week temporary sewage bypass period are shown in the table below and compared with the geometric mean values predicted under the normal HATS operation for the same period.
Scenario |
B7- Anglers' |
B8 - Gemini |
B9 - Hoi Mei
Wan |
B10 - Casam |
B11 - |
B12- Ting Kau |
B13 -
Approach |
B14 - Ma Wan |
B24 - Big |
Geometric Mean
* (no. per 100 ml) for the 2-week Sewage Bypass Period |
|||||||||
Normal operation of HATS during late phase of
Stage 1 |
122 |
131 |
103 |
118 |
86 |
186 |
376 |
18 |
2 |
Temporary sewage bypass at Stage 1 PTWs
in dry season during late phase of Stage 1
|
238 |
279 |
232 |
166 |
135 |
236 |
514 |
57 |
20 |
6.340 The Leisure and Cultural Services Department (LCSD) is currently the “beach management authority”, responsible for determining the opening and closing of gazetted beaches. The decision is made with reference to the advice provided by EPD on the suitability of beach water quality for bathing purposes and the consideration of all other factors. Generally, a beach will be closed if it is ranked "Very Poor" repeatedly. Beaches having geometric mean E.coli densities greater than 610 per 100mL are ranked "Very Poor". As indicated in the table above, the geometric mean E.coli values predicted at the nine beaches are below 610 per 100 mL. Also, the temporary bypass will be scheduled to occur in the dry (or non-bathing) season (November to February) to minimize the potential impact. As the potential elevation of E.coli level occurred only for a very short period (about two weeks in dry season), non-compliance with the WQO/WQC (which is expressed as a geometric mean for bathing season, i.e. March to October) was not predicted at the beaches. In addition, the geometric mean E.coli levels predicted at the secondary contact recreation subzone in Tsuen Wan District were all below 610 no. per 100 ml. Non-compliance with the WQO/WQC was not predicted at the secondary contact recreation zone. No unacceptable effect on public health would be expected due to the temporary discharge. The potential elevation of E.coli level would be short term (about 2 weeks) and the water quality would return to the normal conditions quickly (within 2 days) after the temporary bypass. Relevant government departments including EPD and LCSD should be informed of the planned sewage bypass prior to any discharge. During the sewage bypass event, water quality monitoring should be carried out at such a time to quantify the water quality impacts at the beaches and to determine when the baseline water quality conditions are restored. No unacceptable impact would be expected with proper implementation of the recommended mitigation measures.
6.341 The E.coli impact was still predicted at the flushing water intake at Tsing Yi (WSD5) under the temporary bypass scenario. The peak E.coli level predicted at this intake was about 60,000 no. per 100 ml under the dry season scenario. E.coli should not be a critical parameter of concern for flushing water intake as it is understood that the seawater abstracted from all the WSD flushing water intakes would be treated by disinfection before it is distributed to the users for flushing purpose. Historical EPD monitoring data measured in 1998 at VM13 ([25]) (in close vicinity of WSD5) indicated that the E.coli level at this intake point could reach 130,000 no. per 100 mL during the pre-HATS period (much higher than the peak value predicted under the temporary bypass scenario). Given that the sewage bypass would be short-term (for 2 weeks) and the water quality would return to normal condition quickly after the end of sewage bypass period as demonstrated by the model predictions. No unacceptable water quality and public health effect would be expected.
6.342
The
SS impact was predicted at two isolated coral sites (C25 and CR28) in Junk Bay
where the SS increase was predicted to be 30.9% and 31.9% of the baseline
ambient values respectively which only marginally breached the WQO of 30%
increase. The SS exeedances at
these two coral sites would be very short-term (only last for 1 hour at CR25
and 4 hours at CR28), with a peak SS level of 5.2 mg/L only. These two coral sites are located in
the eastern waters where the baseline SS levels were low. In terms of the absolute
values, the peak SS levels predicted at these two coral sites were low and well
below the value of 10 m/L. The SS value of 10 mg/L has been adopted as the SS
criterion under many other EIA studies in Hong Kong (refer to Footnote no. 23
above) for protection of sensitive coral sites in the eastern and southern
waters of
·
The temporary sewage bypass would not cause any adverse
effect on public health and health of biota or risk to life (the temporary
discharge would not cause any WQO/WQC exceenance at all the identified
secondary contact recreation subzones, beaches and FCZ based on model
predictions);
·
The magnitude of the adverse water quality impact would be
small and the potential water quality impact would be short-term (about 2
weeks) and reversible (the normal water quality would resume quickly after the
discharges);
·
The water quality impact would not occur in areas or regions
that are ecologically fragile or sensitive (the impact zone would be mainly
confined in Victoria Harbour and the adjacent waters and would not encroach on
any ecological sensitive receiver of great importance);
·
The temporary bypass would not cause any disruption to the
seabed and therefore no disruption to any site of cultural heritage;
·
The potential impact area is not of international and
regional importance (the area is currently subject to the pollution discharge
from the urbanized areas in
6.343 No exceendance of the assessment criteria values was predicted at all the identified water and ecological sensitive receivers during the temporary sewage bypass from NWK PTW as demonstrated from the modelling assessment. As minor elevations of bacteria levels were predicted at some of the Tsuen Wan beaches, it is recommended that relevant government departments including EPD and LCSD should be informed of the planned sewage bypass prior to any discharge. During the sewage bypass event, water quality monitoring should be carried out at such a time to quantify the water quality impacts and to determine when the baseline water quality conditions are restored. No unacceptable residual impact would be expected with proper implementation of the recommended mitigation measures.
6.344 No adverse water quality impact associated with normal operation of the Project was predicted. Emergency discharges of screened sewage at the Stage 1 and Stage 2 PTWs would be the consequence of power or equipment failure at SCiSTW. Dual power supply would be provided at the SCISTW to minimize the occurrence of power failure. In addition, standby facilities for the main treatment units and standby equipment parts / accessories would also be provided at the SCISTW in order to minimize the chance of emergency discharge. To provide a mechanism to minimise the impact of emergency discharges and facilitate subsequent management of any emergency, an emergency contingency plan has been formulated to clearly state the response procedure in case of total power or equipment failure at SCISTW (details refer to the standalone EM&A Manual). The plant operators of SCISTW should closely communicate with relevant departments including EPD and LCSD during the emergency discharge. An event and action plan and a detailed water quality monitoring programme for the emergency discharge is given in a standalone EM&A Manual.
6.345 No unacceptable water quality impact was predicted associated with power or equipment failure at individual Stage 2 PTWs. Precautionary measures e.g. standby equipment and dual (back-up) power supply would be provided at all the Stage 2 PTWs to control emergency discharge.
6.346 In case of total power outage of the dechlorination plant, the uninterruptible power supply (UPS) system to be provided would switch the power supply of the sodium bisulphite dosing pump to a backup battery almost instantaneously, allowing continuous dosage of sodium bisulphite for at least half an hour so that sufficient time can be provided for shutting down the chlorination plant to avoid the possibility of discharge of chlorinated effluent. With proper implementation of these mitigation measures, the occurrence of discharge of non-dechlorinated effluent would be very remote. In case that the dechlorination process fails, the chlorination process could be practically stopped within 30 minutes to avoid discharge of TRC into the marine water. The E.coli impact due to no chlorination for a short period of time would be temporary and acceptable as supported by the water quality impact assessment conducted under the ADF study. A framework of the emergency response plan and water quality monitoring requirements for temporary failure of disinfection facilities are provided in the separate EM&A Manual.
6.347 The model predicted that if Stage 2B is not implemented for HATS in 2021 as scheduled, the nutrient contents (both P and N) in the marine water would ultimately increase to exceed the baseline Stage 1 level when the HATS flow is reaching its design capacity of 2.45M m3/day. It should be noted that the schedule of Stage 2B implementation would be subject to the review of flow build-ups and water quality conditions to be conducted in 2010/2011. It is recommended that the future review study for Stage 2B should review the validity of the model predictions provided in this EIA and confirm the need of enhanced nutrient removal for HATS after 2021.
6.348 It should be noted that the mixing zone for TIN predicted for Stage 2B was large with an area of about 30 km2 as indicated in Table 6.45 and the area of exceedance would encroach on the nearby water sensitive receivers (e.g. Ma Wan Fish Culture Zone). This is due to the elevated oxidized nitrogen assumed for the proposed nitrification process at Stage 2B as well as the increased HATS effluent flow assumed for Stage 2B. It is recommended that these water quality issues should be further investigated / assessed under the future EIA for Stage 2B. Further mitigation measures / alternative treatment designs should also be considered under the future EIA for Stage 2B to mitigate / minimize the potential TIN exceedances.
6.349
To minimize the potential water
quality impacts from construction site runoff and various construction
activities, the practices outlined in ProPECC PN 1/94 Construction Site
Drainage should be adopted.
6.350
Surface run-off from
construction sites should be discharged into storm drains via adequately
designed sand/silt removal facilities such as sand traps, silt traps and
sedimentation basins. Channels or
earth bunds or sand bag barriers should be provided on site to properly direct
stormwater to such silt removal facilities. Perimeter channels at site boundaries
should be provided where necessary to intercept storm run-off from outside the
site so that it will not wash across the site. Catchpits and perimeter channels should
be constructed in advance of site formation works and earthworks.
6.351 Silt removal facilities, channels and manholes should be maintained and the deposited silt and grit should be removed regularly, at the onset of and after each rainstorm. Any practical options for the diversion and re-alignment of drainage should comply with both engineering and environmental requirements in order to provide adequate hydraulic capacity of all drains. Minimum distances of 100 m should be maintained between the discharge points of construction site runoff and the existing saltwater intakes.
6.352 Construction works should be programmed to minimize soil excavation works in rainy seasons (April to September). If excavation in soil could not be avoided in these months or at any time of year when rainstorms are likely, for the purpose of preventing soil erosion, temporary exposed slope surfaces should be covered e.g. by tarpaulin, and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds. Intercepting channels should be provided (e.g. along the crest / edge of excavation) to prevent storm runoff from washing across exposed soil surfaces. Arrangements should always be in place in such a way that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm.
6.353 Earthworks final surfaces should be well compacted and the subsequent permanent work or surface protection should be carried out immediately after the final surfaces are formed to prevent erosion caused by rainstorms. Appropriate drainage like intercepting channels should be provided where necessary.
6.354 Measures should be taken to minimize the ingress of rainwater into trenches. If excavation of trenches in wet seasons is necessary, they should be dug and backfilled in short sections. Rainwater pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities.
6.355 Open stockpiles of construction materials (e.g. aggregates, sand and fill material) on sites should be covered with tarpaulin or similar fabric during rainstorms.
6.356 Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris from getting into the drainage system, and to prevent storm run-off from getting into foul sewers. Discharge of surface run-off into foul sewers must always be prevented in order not to unduly overload the foul sewerage system.
6.357 Good site practices should be adopted to remove rubbish and litter from construction sites so as to prevent the rubbish and litter from spreading from the site area. It is recommended to clean the construction sites on a regular basis.
6.358
Groundwater pumped out of
wells, etc. for the lowering of ground water level in basement or foundation
construction, and groundwater seepage pumped out of tunnels or caverns under
construction should be discharged into storm drains after the removal of silt
in silt removal facilities.
6.359
Water used in ground boring and
drilling for site investigation or rock / soil anchoring should as far as
practicable be recirculated after sedimentation. When there is a need for final disposal,
the wastewater should be discharged into storm drains via silt removal
facilities.
6.360
Wastewater generated from the
washing down of mixing trucks and drum mixers and similar equipment should
whenever practicable be used for other site activities. The discharge of wastewater should be kept
to a minimum and should be treated to meet the appropriate standard as
specified in the TM-DSS before discharging.
6.361 To prevent pollution from wastewater overflow, the pump sump of any wastewater system should be provided with an on-line standby pump of adequate capacity and with automatic alternating devices.
6.362 Under normal circumstances, surplus wastewater may be discharged into foul sewers after treatment in silt removal and pH adjustment facilities (to within the pH range of 6 to 10). Disposal of wastewater into storm drains will require more elaborate treatment.
6.363
All vehicles and plant should
be cleaned before they leave a construction site to minimize the deposition of
earth, mud, debris on roads. A
wheel washing bay should be provided at every site exit if practicable and
wash-water should have sand and silt settled out or removed before discharging
into storm drains. The section of
construction road between the wheel washing bay and the public road should be
paved with backfall to reduce vehicle tracking of soil and to prevent site
run-off from entering public road drains.
6.364
Bentonite slurries used in
diaphragm wall and bore-pile construction should be reconditioned and used
again wherever practicable. If the
disposal of a certain residual quantity cannot be avoided, the used slurry may
be disposed of at the marine spoil grounds subject to obtaining a marine
dumping licence from EPD on a case-by-case basis.
6.365 If the used bentonite slurry is intended to be disposed of through the public drainage system, it should be treated to the respective effluent standards applicable to foul sewer, storm drains or the receiving waters as set out in the TM-DSS (refer to Section 6.23).
6.366
Water used in water testing to
check leakage of structures and pipes should be used for other purposes as far
as practicable. Surplus unpolluted water could be discharged into storm drains.
6.367 Sterilization is commonly accomplished by chlorination. Specific advice from EPD should be sought during the design stage of the works with regard to the disposal of the sterilizing water. The sterilizing water should be used again wherever practicable.
6.368
Before commencing any
demolition works, all sewer and drainage connections should be sealed to
prevent building debris, soil, sand etc. from entering public sewers/drains.
6.369 Wastewater generated from building construction activities including concreting, plastering, internal decoration, cleaning of works and similar activities should not be discharged into the stormwater drainage system. If the wastewater is to be discharged into foul sewers, it should undergo the removal of settleable solids in a silt removal facility, and pH adjustment as necessary.
6.370
Acidic wastewater generated
from acid cleaning, etching, pickling and similar activities should be
neutralized to within the pH range of 6 to 10 before discharging into foul
sewers. If there is no public foul
sewer in the vicinity, the neutralized wastewater should be tinkered off site
for disposal into foul sewers or treated to a standard acceptable to storm drains
and the receiving waters.
6.371
Wastewater collected from
canteen kitchens, including that from basins, sinks and floor drains, should be
discharged into foul sewer via grease traps capable of providing at least 20
minutes retention during peak flow.
6.372 Drainage serving an open oil filling point should be connected to storm drains via a petrol interceptors with peak storm bypass.
6.373 Vehicle and plant servicing areas, vehicle wash bays and lubrication bays should as far as possible be located within roofed areas. The drainage in these covered areas should be connected to foul sewers via a petrol interceptor. Oil leakage or spillage should be contained and cleaned up immediately. Waste oil should be collected and stored for recycling or disposal in accordance with the Waste Disposal Ordinance.
6.374
The presence of construction
workers generates sewage. It is
recommended to provide sufficient chemical toilets in the works areas. The toilet facilities should be more
than 30 m from any watercourse. A
licensed waste collector should be deployed to clean the chemical toilets on a
regular basis.
6.375 Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment. Regular environmental audit on the construction site can provide an effective control of any malpractices and can encourage continual improvement of environmental performance on site. It is anticipated that sewage generation during the construction phase of the project would not cause water pollution problem after undertaking all required measures.
6.376 There is a need to apply to EPD for a discharge licence for discharge of effluent from the construction site under the WPCO. The discharge quality must meet the requirements specified in the discharge licence. All the runoff and wastewater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS. Minimum distances of 100 m should be maintained between the discharge points of construction site effluent and the existing saltwater intakes. The beneficial uses of the treated effluent for other on-site activities such as dust suppression, wheel washing and general cleaning etc., can minimise water consumption and reduce the effluent discharge volume. If monitoring of the treated effluent quality from the works areas is required during the construction phase of the Project, the monitoring should be carried out in accordance with the WPCO license which is under the ambit of regional office (RO) of EPD.
6.377
Contractor must register as a
chemical waste producer if chemical wastes would be produced from the
construction activities. The Waste Disposal Ordinance (Cap 354) and its
subsidiary regulations in particular the Waste Disposal (Chemical Waste)
(General) Regulation should be observed and complied with for control of
chemical wastes.
6.378 Any service shop and maintenance facilities should be located on hard standings within a bunded area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment involving activities with potential for leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.
6.379 Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:
·
Suitable containers should be used to hold the chemical
wastes to avoid leakage or spillage during storage, handling and transport.
·
Chemical waste containers should be suitably labelled, to
notify and warn the personnel who are handling the wastes, to avoid accidents.
·
Storage area should be selected at a safe location on site
and adequate space should be allocated to the storage area.
6.380 To minimize the potential water quality impacts from the construction works located at or near any watercourse, the practices outlined below should be adopted where applicable.
·
The use of less or smaller construction plants may be
specified to reduce the disturbance to the storm water courses or marine
environment.
·
Temporary storage of materials (e.g. equipment, filling
materials, chemicals and fuel) and temporary stockpile of construction
materials should be located well away from any water courses during carrying
out of the construction works.
·
Stockpiling of construction materials and dusty materials
should be covered and located away from any water courses.
·
Construction debris and spoil should be covered up and/or
disposed of as soon as possible to avoid being washed into the nearby water
receivers.
·
Construction activities, which generate large amount of
wastewater, should be carried out in a distance away from the waterfront, where
practicable.
·
Proper shoring may need to be erected in order to prevent
soil/mud from slipping into the storm culvert or sea.
6.381
It
is recommended that the temporary sewage bypass required for (i) the
modification to the existing pumping station at SCISTW and (ii) the
interconnection between the existing main pumping station and the new pumping station on
6.382
The construction phase water
quality impact would generally be temporary and localized during
construction. No unacceptable residual water quality impacts would be
expected during the construction phase of the Project, provided that all the
recommended mitigation measures are properly implemented.
6.383 The HATS Stage 2A implementation would improve the water quality in the receiving water as compared to the existing baseline condition. No adverse water quality impact associated with normal operation of the Project was predicted from the assessment. No unacceptable residual water quality impacts would be expected for the operation of the Project.
6.384 Monitoring of effluent quality is recommended for operational stage and under the perspective of the WPCO. A post project monitoring (PPM) programme will be implemented to confirm the water quality predictions made in the EIA report. The PPM would consist of one-year baseline monitoring before commissioning and at least one-year impact monitoring after commissioning of the Project. The extent of PPM programme is subject to the prevailing environmental conditions at the time before commissioning of the Project. A more detailed description of the PPM requirements is given in the standalone EM&A Manual.
6.385 Marine water quality monitoring is recommended during the emergency discharge (as a result of equipment / power failure at SCISTW) during operational phase and the temporary sewage bypass (required for the modification / interconnection works) during construction phase or early commissioning of the Project. A baseline monitoring programme is proposed to establish the baseline water quality conditions at selected monitoring points. In case of emergency discharge or temporary sewage bypass, daily marine water monitoring should be conducted throughout the whole discharge period until the normal water quality resumes. A more detailed description of the water quality requirements is given in the standalone EM&A Manual.
6.386 The general construction works for the Project would be land-based except seawall re-construction at the Aberdeen PTW. No dredging would be required for the Project. The fine content in the fill material during seawall re-construction at the Aberdeen PTW should be negligible. Key water quality issues associated with land-based construction would include the impacts from site run-off, sewage from workforce, accidental spillage and discharges of wastewater from various construction activities. With well maintained site drainage and the implementation of good site practices, impacts would be controlled to comply with the WPCO standards by implementing the recommended mitigation measures. No unacceptable water quality impact would therefore be expected.
6.387 Temporary bypass of sewage effluent via individual PTW would be required during the construction stage. The water quality impacts during the temporary sewage bypass were assessed using the Delft3D model. The predicted water quality impact associated with the temporary discharge would be short-term and the water quality would return to the normal condition quickly after the sewage bypass period. Water quality monitoring is recommended to be carried out during the temporary sewage bypass to quantify the water quality impacts and to determine when the baseline water quality conditions are restored. Also, a framework of the response procedures has been formulated to minimize the impact of temporary discharges. No insurmountable water quality impact would be expected.
6.388
The water quality impacts
during operation of the Project were assessed using the Delft3D model.
Impacts were assessed over a series of one-year simulation periods. The assessment area included the
6.389
The
water quality modelling results showed that the Project would not cause any
adverse impact on the marine water quality and on the identified sensitive receivers during normal
operations of the SCISTW. The total
residual chlorine from the chlorination/dechlorination disinfection process
would meet the criterion set for the edge of the zone of initial dilution, with
a large safety margin. Whole
effluent toxicity tests showed that the chlorination/dechlorination
disinfection process did not introduce additional toxic effects to the test
organisms. A Post Project Monitoring (PPM) programme was proposed to
confirm the model predictions made in this EIA.
6.390 Overflow at PTW may occasionally occur only during storm events and the extent of impact was predicted to be minor and acceptable. Mitigation measures, including dual power supply, standby pumps, treatment units and equipment, would be provided at SCISTW to minimize the occurrence of emergency discharge. Standby unit(s) and dual (backup) power supply would also be provided at all the Stage 2 PTWs to reduce the risk of equipment breakdown at the PTWs. The model suggested that the water quality impacts associated with power or equipment failure at SCISTW and the Stage 2 PTWs would be short term. The water quality would return to the normal condition quickly after the emergency sewage. In case of power outage of the dechlorination plant, the uninterruptible power supply (UPS) system to be provided would switch the power supply of the sodium bisulphite dosing pump to a backup battery almost instantaneously, allowing continuous dosage of sodium bisulphite for at least half an hour so that sufficient time can be provided for shutting down the chlorination plant to avoid the possibility of discharge of chlorinated effluent. An emergency contingency plan has been formulated to minimise the impact of emergency discharges and facilitate subsequent management of the emergency. An event and action plan and a detailed EM&A programme are recommended to collect water quality information and to mitigate the potential impact due to emergency discharge. The monitoring results shall be employed to identify areas for any further necessary mitigation measures to avoid, rectify and eliminate environmental damage associated with the Project.
Sai Kung Sewage
Treatment Works EIA Study;
Tai
The Proposed Submarine Gas Pipelines
from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai
Po Gas Production Plant, Hong Kong, EIA Report, The
Civil Engineering Department (1997)
Sand dredging and backfilling of Borrow Pits at the potential Eastern Waters
Marine Borrow Area EIA Report;
Civil Engineering Department (1998)
Environmental Impact Assessment of backfilling Marine Borrow Areas at East Tung
Lung Chau;
CLP Power (2001) Environmental
consultancy services for the proposed 11 kV cable circuits from Tsai Mong Tsai
to Kiu Tsui;
CLP Power (2002) Environmental
consultancy services for the proposed 132 kV cable circuits from A Kung Wan to
Sai Kung Pier;
The Hongkong Electric Co (2002) 132
kV submarine cable installation for Wong Chuk Hang – Chung Hom Kok 132 kV
circuits.
Sai Kung Sewage Treatment Works EIA
Study;
Tai
The Proposed Submarine Gas Pipelines
from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai
Po Gas Production Plant, Hong Kong, EIA Report, The
Civil Engineering Department (1997)
Sand dredging and backfilling of Borrow Pits at the potential Eastern Waters
Marine Borrow Area EIA Report;
Civil Engineering Department (1998)
Environmental Impact Assessment of backfilling Marine Borrow Areas at East Tung
Lung Chau;
CLP Power (2001) Environmental
consultancy services for the proposed 11 kV cable circuits from Tsai Mong Tsai
to Kiu Tsui;
CLP Power (2002) Environmental
consultancy services for the proposed 132 kV cable circuits from A Kung Wan to
Sai Kung Pier;
The Hongkong Electric Co (2002) 132
kV submarine cable installation for Wong Chuk Hang – Chung Hom Kok 132 kV
circuits.