2.1
In this section, the requirements, methodology,
equipment, monitoring locations, criteria and protocols for the monitoring and
audit of air quality impacts during the construction phase of all construction
works are presented. As the
construction dust is the prime concern, total suspended particulates (TSP)
levels shall be monitored to evaluate the dust impact during the construction
phase.
2.2
The findings of the EIA also indicated that the
existing odour sources at PTWs & SCISTW would have potential odour impact
on the selected air sensitive receiver (ASR) during operational phase of the
Project. Odour monitoring would be
required to determine the effectiveness of mitigation measures and monitor the
odour impact on the selected ASRs.
2.3
Monitoring and audit of the TSP levels shall be
carried out by the ET to ensure that any deteriorating air quality could be
readily detected and timely action taken to rectify the situation.
2.4
One-hour and 24-hour TSP levels should be measured to
indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. Upon approval of the ER, 1-hour TSP
levels can be measured by direct reading methods which are capable of producing
comparable results as that by the high volume sampling method, to indicate
short event impacts.
2.5
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail. A sample
data sheet is shown in Appendix B1.
2.6
The locations of ASRs within and adjacent to the
Project work site are shown in Figure 2.1 (a to i).
Operational Phase
2.7
Odour patrol should be conducted by independent trained
personnel / competent persons patrolling and sniffing at the identified ASRs to
indicate the operational odour impacts.
Besides, odour measurements should be conducted at the exhaust stacks of
the deodorization system at SCISTW.
Construction Phase
2.8
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
a) 0.6
- 1.7 m3 per minute adjustable flow range;
b) equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
c) installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
d) capable
of providing a minimum exposed area of 406 cm2;
e) flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
f)
equipped with a shelter to protect
the filter and sampler;
g) incorporated
with an electronic mass flow rate controller or other equivalent devices;
h) equipped
with a flow recorder for continuous monitoring;
i)
provided with a peaked roof inlet;
j)
incorporated with a manometer;
k) able
to hold and seal the filter paper to the sampler housing at horizontal
position;
l)
easily changeable filter; and
m) capable
of operating continuously for a 24-hour period.
2.9
The ET is responsible for provision of the monitoring
equipment. They shall ensure that
sufficient number of HVSs with an appropriate calibration kit are available for
carrying out the baseline monitoring, regular impact monitoring and ad hoc
monitoring. The HVSs shall be equipped
with an electronic mass flow controller and be calibrated against a traceable
standard at regular intervals. All
the equipment, calibration kit, filter papers, etc., shall be clearly labelled.
2.10
Initial calibration of dust monitoring equipment shall
be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable
to the internationally recognised primary standard and be calibrated
annually. The concern parties such
as IEC shall properly document the calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
2.11
The flow-rate of the sampler before and after the
sampling exercise with the filter in position shall be verified to be constant
and be recorded in the data sheet as mentioned in Appendix B1.
2.12
If the ET proposes to use a direct reading dust meter
to measure 1-hour TSP levels, he shall submit sufficient information to the IEC
to prove that the instrument is capable of achieving a comparable result to the
HVS. The instrument should also be
calibrated regularly, and the 1-hour sampling shall be determined periodically
by the HVS to check the validity and accuracy of the results measured by direct
reading method.
2.13
Wind data monitoring equipment shall also be provided
and set up for logging wind speed and wind direction near the dust monitoring
locations. The equipment
installation location shall be proposed by the ET and agreed with the IEC. For installation and operation of wind
data monitoring equipment, the following points shall be observed:
a) The
wind sensors should be installed 10 m above ground so that they are clear of
obstructions or turbulence caused by buildings.
b) The
wind data should be captured by a data logger. The data shall be downloaded for
analysis at least once a month.
c) The
wind data monitoring equipment should be re-calibrated at least once every six
months.
d) Wind
direction should be divided into 16 sectors of 22.5 degrees each.
2.14
In exceptional situations, the ET may propose
alternative methods to obtain representative wind data upon approval from the
ER and agreement from the IEC.
2.15
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS
accredited.
2.16
If a site laboratory is set up or a non-HOKLAS
accredited laboratory is hired for carrying out the laboratory analysis, the
laboratory equipment shall be approved by the ER and the measurement procedures
shall be witnessed by the IEC. Any
measurement performed by the laboratory shall be demonstrated to the
satisfaction of the ER and IEC. IEC
shall regularly audit to the measurement performed by the laboratory to ensure
the accuracy of measurement results.
The ET Leader shall provide the ER with one copy of the Title 40 of the
Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.
2.17
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall
be a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
2.18
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned
to the laboratory for reconditioning in the humidity-controlled chamber
followed by accurate weighing by an electronic balance with readout down to 0.1
mg. The balance shall be regularly
calibrated against a traceable standard.
2.19
All the collected samples shall be kept in a good
condition for 6 months before disposal.
2.20
Based on the EIA report, a number of worst affected
locations are designated for construction dust monitoring as listed in Table 2.1 and illustrated in Figure
2.2 (a to g). The status
and locations of dust sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall
propose updated monitoring locations and seek approval from ER and agreement
from the IEC.
Table 2.1 Construction Dust Monitoring Locations
ASR ID in EIA Report |
Monitoring ID |
Location |
NP5 |
CM_NP1 |
K. Wah Centre |
NP6 |
CM_NP2 |
Hong Kong & Islands Regional Office, WSD |
NP7 |
CM_NP3 |
Tin Shui Street Children’s Playground |
WC3 |
CM_WC1 |
Society for the Prevention of Cruelty to Animals |
C1 |
CM_C1 |
Sheung Wan Fire Station |
FM2 |
CM_FM1 |
Western Wholesale Food Market |
CB1 |
CM_CB1 |
Cyber Centre |
CB2 |
CM_CB2 |
Le Meridien Cyberport |
WF2 |
CM_WF1 |
Wah Ming House, Wah Fu Estate |
AB4 |
CM_AB1 |
Dairy Farm Ice and Cold Storage |
SCI1 |
CM_SCI1 |
Government Dockyard Offices |
SCI3 |
CM_SCI2 |
COSCO Hit Terminal |
SCI6 |
CM_SCI3 |
Club House |
SCI7 |
CM_SCI4 |
Works site boundary (near Ngong Shuen Chau Barracks Group 2) |
2.21
When alternative monitoring locations are proposed,
the proposed site should, as far as practicable:
a)
be at the site boundary or such
locations close to the major dust emission source;
b)
be close to the sensitive receptors;
and
c) take
into account the prevailing meteorological conditions.
2.22
The ET shall agree with the ER in consultation with
the IEC on the position of the HVS for the installation of the monitoring
equipment. When positioning the
samplers, the following points shall be noted:
a)
a horizontal platform with
appropriate support to secure the samplers against gusty wind should be
provided;
b)
no two samplers should be placed
less than 2 meters apart;
c)
the distance between the sampler and
an obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
d)
a minimum of 2 meters of separation
from walls, parapets and penthouses is required for rooftop samplers;
e)
a minimum of 2 meters separation
from any supporting structure, measured horizontally is required;
f)
no furnace or incinerator flue is
nearby;
g)
airflow around the sampler is
unrestricted;
h)
the sampler is more than 20 meters
from the dripline;
i)
any wire fence and gate, to protect
the sampler, should not cause any obstruction during monitoring;
j)
permission must be obtained to set
up the samplers and to obtain access to the monitoring stations; and
k) a
secured supply of electricity is needed to operate the samplers.
Operational
Phase
2.23
A number of existing ASR and one planned ASR (namely
SCI5) are identified for odour monitoring as shown in Table 2.2 and illustrated in Figure 2.3 (a to i). The odour monitoring shall be conducted at
a height of
Table 2.2 Operation Odour Monitoring Locations
ASR ID in EIA Report |
Monitoring ID |
Location |
NP3 |
OM_NP1 |
King’s Road
Playground & Skating Area |
NP4 |
OM_NP2 |
Customs HQ
Tower (planned) |
NP5 |
OM_NP3 |
K. Wah
Centre |
WC3 |
OM_WC1 |
Society for
the Prevention of Cruelty to Animals |
WC4 |
OM_WC2 |
|
C1 |
OM_C1 |
Sheung Wan
Fire Station |
C2 |
OM_C2 |
Water Front
Divisional Police Station |
C3 |
OM_C3 |
Sheung Wan
Gala Point |
FM2 |
OM_FM1 |
Western
Wholesale Food Market |
SB1 |
OM_SB1 |
|
SB2 |
OM_SB2 |
Home for
the Elderly |
SB3 |
OM_SB3 |
Maclehose
Medical Rehabilitation Centre |
SB4 |
OM_SB4 |
The Duchess
of Kent Children’s Hospital |
CB1 |
OM_CB1 |
Cyber
Centre |
CB2 |
OM_CB2 |
Le Meridien
Cyberport |
WF2 |
OM_WF1 |
Wah Ming
House, Wah Fu Estate |
AB4 |
OM_AB1 |
Dairy Farm
Ice and Cold Storage |
ALC3 |
OM_ALC1 |
Shell Ap
Lei Chau Depot |
SCI1 |
OM_SCI1 |
Government Dockyard
Offices |
SCI3 |
OM_SCI2 |
COSCO Hit Terminal |
SCI4 |
OM_SCI3 |
KMB Depot Office |
SCI5 |
OM_SCI4 |
Planned FSD
Diving Rescue and Diving Training Centre |
SCI6 |
OM_SCI5 |
Club House |
2.24
Baseline monitoring shall be carried out at all of the
designated monitoring locations for at least 14 consecutive days prior to the
commissioning of the construction works to obtain daily 24-hour TSP
samples. The selected baseline
monitoring stations should reflect baseline conditions at the impact
stations. One-hour sampling should
also be done at least 3 times per day while the highest dust impact is
expected.
2.25
During the baseline monitoring, there should not be
any construction or dust generation activities in the vicinity of the
monitoring stations. Before
commencing baseline monitoring, the ET shall inform the IEC of the baseline
monitoring programme such that the ER can conduct on-site audit to ensure
accuracy of the baseline monitoring results.
2.26
In case the baseline monitoring cannot be carried out
at the designated monitoring locations during the baseline monitoring period,
the ET Leader shall carry out the monitoring at alternative locations that can
effectively represent the baseline conditions at the impact monitoring
locations. The alternative baseline
monitoring locations shall be approved by the ER and agreed with the IEC.
2.27
In exceptional cases, when insufficient baseline
monitoring data or questionable results are obtained, the ET shall liaise with
the IEC and EPD to agree on an appropriate set of data to be used as a baseline
reference and submit to ER for approval.
2.28
Ambient conditions may vary seasonally and shall be
reviewed once every three months.
When the ambient conditions have changed and a repeat of the baseline
monitoring is required to be carried out for obtaining the updated baseline
levels, the monitoring should be at times when the Contractor's activities are
not generating dust, at least in the proximity of the monitoring stations. Should change in ambient conditions be
determined, the baseline levels and, in turn, the air quality criteria, should
be revised. The revised baseline
levels and air quality criteria should be agreed with the IEC and EPD.
2.29
One year prior to the commissioning of the Project, a
programme to monitor odour patrol at the identified monitoring locations shall
be undertaken.
2.30
The measured results at ASRs will serve as the
baseline data set prior to the commissioning of the Project. These will be compared with the results
obtained during the impact monitoring stage.
2.31
In addition, the following information shall be
obtained:
·
Meteorological conditions from the nearest Hong Kong
Observatory’s Weather Station (including temperature, wind speed, relative
humidity) during the monitoring;
·
Whether any abnormal operations were being carried out at
the monitoring site during the monitoring.
2.32
The baseline monitoring events shall be carried out
every three months at the same locations within the year before the Project
commissioned.
Construction Phase
2.33
The ET shall carry out impact monitoring during the
course of the Works. For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at all the monitoring stations for 24-hour TSP
monitoring. For 1-hour TSP
monitoring, the sampling frequency of at least three times in every six-days
should be undertaken when the highest dust impact occurs. Before commencing baseline monitoring,
the ET shall inform the IEC of the impact monitoring programme such that the IEC
can conduct on-site audit to ensure accuracy of the impact monitoring results.
2.34
The specific time to start and stop the 24-hour TSP
monitoring shall be clearly defined for each location and be strictly followed
by the operator.
2.35
In case of non-compliance with the air quality
criteria, more frequent monitoring, as specified in the Action Plan in the
following section, shall be conducted within 24 hours after the result is
obtained. This additional monitoring
shall be continued until the excessive dust emission or the deterioration in
air quality is rectified.
Operational Phase
Odour Measurement at Exhaust Stacks of Deodorization System of SCISTW
2.36
Odour measurement for all the
exhaust stacks of the deodorization system at SCISTW should be conducted with
an aim to determine the total odour emission rates from the deodorization
system. The measured total odour emission
rate should be used to compare with the estimated total mitigated odour emission
rate as presented in the EIA Report.
2.37
Odour gaseous sample should be collected by using an
odour sampling system, which includes a battery-operated air pump, a sampling
vessel, and an odour bag. The odour
emission rate should be determined by forced-choice dynamic olfactometer
(Olfactomat-n2) in accordance with the European Standard Method (EN13725). The ET shall propose the detailed measurement method for approval by the ER
and agreement by the IEC.
2.38
The odour measurement shall be
conducted in the first five years upon commissioning of the expanded SCISTW. Odour measurement shall be conducted
every three months for the first year of operation for the expanded
SCISTW. The first odour measurement shall be conducted within one month after operation
of the expanded SCISTW. Subsequent
odour measurement shall be conducted
at the 4th, 7th and 10th month. For
the 2nd to 5th year, if the measurement results indicate
that the measured total odour emission rate is lower than 90% of the estimated total mitigated odour emission rate stated in the EIA Report, the frequency
of the impact measurement could be
reduced to once every 6 months subject to EPD’s approval.
Odour Patrol
2.39
Odour monitoring in the form of odour patrol shall be
conducted by the ET. The monitoring
shall not be conducted on rainy days. Hourly meteorological conditions
(temperature, wind speed & direction, humidity) shall be recorded
throughout the monitoring period.
2.40
Odour patrol shall be conducted by independent trained
personnel / competent persons patrolling and sniffing around the Air Sensitive
Receiver to detect any odour at the concerned hours.
2.41
The odour impact monitoring programme shall be
conducted in the first five years upon commissioning of each upgraded PTWs and expended
SCISTW. Odour impact monitoring
shall be conducted every three months for the first year of operation for all upgraded
PTWs and expended SCISTW. The first
odour monitoring shall be conducted within one month, after the operation of
the upgraded PTWs and expended SCISTW.
Subsequent odour monitoring shall be conducted at the 4th, 7th and 10th
month. For the 2nd to 5th year, if
the monitoring results are below the action levels, the frequency of the impact
monitoring could be reduced to once every 6 months subject to EPD’s
approval.
2.42
The independent trained personnel / competent persons
shall :
·
have their individual odour threshold of n-butanol in
nitrogen gas in the range of 20 to 80 ppb/v required by the European Standard
Method (EN 13725).
·
be at least 16 years of age and willing and able to follow
instructions.
·
be free from any respiratory illnesses.
·
be engaged for a sufficient period to build up and
monitor/detect at several monitoring location;
·
not be allowed to smoke, eat, drink (except water) or use
chewing gum or sweets 30 min before and during odour intensity analysis;
·
take great care not to cause any interference with their own
perception or that of others by lack of personal hygiene or the use of
perfumes, deodorants, body lotions or cosmetics;
·
not communicate with each other about the results of their choices.
2.43
At least three independent trained personnel /
competent persons shall be selected to form an odour panellist to conduct the
odour patrol, who should participate in a set of screening tests.
2.44
Subject to the prevailing weather forecast condition, odour
intensity analysis shall be conducted by independent trained personnel /
competent persons at the downwind locations. During the analysis, the sequence
should start from less odorous locations to stronger odorous locations.
2.45
The perceived odour intensity is to be divided into 5
levels which are ranked in the descending order as follows:
0 - Not detected. No odour perceived or an odour so weak that it can not
be easily characterised or described;
1 - Slight identifiable odour, and slight chance to have odour nuisance;
2 - Moderate identifiable odour, and moderate chance to have odour
nuisance;
3 - Strong identifiable, likely to have odour nuisance;
4 - Extreme severe odour, and unacceptable odour level.
2.46
The independent trained personnel / competent persons
shall record the findings including odour intensity, odour nature and possible
odour sources, and also the local wind speed and direction at each location. In addition, some relevant meteorological
data such as daily average temperature, daily average humidity, wind speed and
direction on that surveyed day shall be obtained from the Hong Kong Observatory
Station for reference.
2.47
If the monitoring results are below the action levels
at the last year of the monitoring programme, the impact monitoring would be
ceased. If exceedance of odour intensity
of 2 is recorded at the last year of monitoring programme, investigation shall
be conducted to determine the potential odour source and the corresponding
departments/parties for follow up monitoring (such as continue the monitoring
programme until the odour intensity of below 2 is measured) and rectification
of the odour problem. Monitoring
shall not be conducted on rainy days. Hourly meteorological conditions
(temperature, wind speed & direction, humidity) shall be recorded
throughout the monitoring period.
Odour Complaint Registration
2.48
In the event when an odour complaint is received at
the PTWs and SCISTW, operator shall liaise with the complainant and a Complaint
Registration Form shall be completed. The Complaint Registration Form is to
record detailed information regarding the odour complaint and hence,
facilitates efficient investigation work. The registration form shall contain, but
not be limited to the following information:
·
Location of where the odour nuisance occurred, including
whether the odour was experienced indoors or outdoors;
·
Date and time of the complaint and the nuisance event;
·
Description of the complaint, i.e. the type and
characteristics of the odour; and an indication of the odour strength (highly
offensive / offensive / slightly offensive / just continuously detectable
/intermittently detectable); and
·
Name and contact information of the complainant.
2.49
This information shall be obtained by the plant
engineer or his representative(s) of the PTWs and SCISTW when the complaint is
received. The Complaint
Registration Form is shown in Appendix B2
for reference.
2.50
In addition, the following information shall be
obtained:
·
Meteorological conditions from the nearest Hong Kong Observatory
Weather Station (including temperature, wind speed and direction, relative
humidity) at the time of the complaint; and
·
Whether any abnormal operations were being carried out at
the PTWs and SCISTW at the time the nuisance occurred.
2.51
The Odour Complaint Register shall be kept at the PTWs
and SCISTW.
2.52
The baseline monitoring results form the basis for
determining the air quality criteria for the impact monitoring. The ET shall compare the impact
monitoring results with air quality criteria set up for 24-hour TSP and 1-hour
TSP and odour criteria. Table 2.3 shows the air quality
criteria, namely Action and Limit levels to be used.
Table 2.3 Action / Limit Levels for Air Quality
Parameters |
Action |
Limit |
24-hour
TSP Level in mg
m-3 |
For
baseline level £
200mg
m-3, Action level = (baseline level * 1.3 + Limit level)/2; For
baseline level > 200mg m-3 Action level = Limit level |
260mg
m-3 |
1-hour TSP
Level in mg
m-3 |
For
baseline level £
384mg
m-3, Action level = (baseline level * 1.3 + Limit level)/2; For
baseline level > 384mg m-3, Action level = Limit level |
500mg
m-3 |
Odour
Nuisance |
·
When two documented complaint are
received; or ·
Odour Intensity of 2 is measured
from odour patrol; or ·
Measured
total odour emission rate from exhaust stacks of deodorization system at
SCSITW ≧
0.9 x Total mitigated odour emission rate
presented in EIA Report |
·
Five or more consecutive genuine
documented complaints within a week; or ·
Odour Intensity of 3 or above is
measured from odour patrol; or ·
Measured
total odour emission rate from exhaust stacks of deodorization system at
SCISTW ≧
Total mitigated odour emission rate
presented in EIA Report |
2.53
Should non-compliance of the air quality criteria
occur, actions in accordance with the Action Plan in Tables 2.4 and 2.5 shall be carried out.
Table 2.4 Event / Action Plan for Construction Air Quality
Action |
||||
ET |
IEC |
ER |
Contractor |
|
ACTION
LEVEL |
||||
1. Exceedance
for one sample |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform
IEC and ER; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method. |
1. Notify
Contractor. |
1. Rectify any unacceptable
practice; 2. Amend working methods if
appropriate. |
2. Exceedance
for two or more consecutive samples |
1. Identify
source; 2. Inform
IEC and ER; 3. Advise
the ER on the effectiveness of the proposed remedial measures; 4. Repeat
measurements to confirm findings; 5. Increase
monitoring frequency to daily; 6.
Discuss with IEC and Contractor on
remedial actions required; 7. If
exceedance continues, arrange meeting with IEC and ER; 8. If
exceedance stops, cease additional monitoring. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss
with ET and Contractor on possible remedial measures; 4. Advise
the ET on the effectiveness of the proposed remedial measures; 5. Supervise
Implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. Ensure
remedial measures properly implemented. |
1. Submit proposals for
remedial to ER within 3 working days of notification; 2. Implement the agreed
proposals; 3. Amend proposal if
appropriate. |
LIMIT LEVEL |
||||
1. Exceedance for one sample |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform
ER, Contractor and EPD; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily; 5. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss
with ET and Contractor on possible remedial measures; 4. Advise
the ER on the effectiveness of the proposed remedial measures; 5. Supervise
implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. Ensure
remedial measures properly implemented. |
1.
Take immediate action to avoid
further exceedance; 2.
Submit proposals for remedial
actions to IEC within 3 working days of notification; 3.
Implement the agreed proposals; 4. Amend
proposal if appropriate. |
2. Exceedance
for two or more consecutive samples |
1. Notify
IEC, ER, Contractor and EPD; 2. Identify
source; 3. Repeat
measurement to confirm findings; 4. Increase
monitoring frequency to daily; 5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented; 6. Arrange
meeting with IEC and ER to discuss the remedial actions to be taken; 7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; 8. If
exceedance stops, cease additional monitoring. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss
amongst ER, ET, and Contractor on the potential remedial actions; 4. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; 5. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. In
consolidation with the IEC, agree with the Contractor on the remedial
measures to be implemented; 4. Ensure
remedial measures properly implemented; 5. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1. Take immediate action to
avoid further exceedance; 2. Submit proposals for
remedial actions to IEC within 3 working days of notification; 3. Implement the agreed
proposals; 4. Resubmit proposals if
problem still not under control; 5. Stop the relevant portion
of works as determined by the ER until the exceedance is abated. |
Table 2.5 Event/Action Plan for Operation Air Quality Monitoring
Event |
Action |
|
Person-in-charge
of Odour Monitoring |
DSD |
|
ACTION
LEVEL |
||
Exceedance
of action level |
1. Identify source/reason of exceedance; 2. Repeat odour patrol to confirm finding; 3. Repeat odour measurement at exhaust stacks of
deodorization system of SCISTW (if exceedance at SCISTW) to confirm finding |
1.
Carry out investigation to identify the source/reason of exceedance. Investigation shall be completed
within 2 week; 2.
Implement more mitigation measures if necessary. |
LIMIT LEVEL |
||
Exceedance
of Limit level |
1.
Identify source / reason of exceedance; 2.
Repeat odour patrol to confirm finding; 3.
Repeat odour measurement at exhaust stacks of deodorization system of SCISTW
(if exceedance at SCISTW) to confirm finding 4.
Increase monitoring frequency to monthly; 5.
If exceedance stops, cease additional monitoring. |
1.
Carry out investigation to identify the source/reason of exceedance.
Investigation shall be completed within 2 week; 2.
Rectify any unacceptable practice; 3.
Formulate remedial actions; 4.
Ensure amended working methods and remedial actions properly implemented; 5. If exceedance continues, consider what mitigation measures shall be
implemented. |
·
Skip hoist for material transport should be totally enclosed by
impervious sheeting;
·
Vehicle washing facilities should be provided at every vehicle exit
point;
·
The area where vehicle washing takes place and the section of the road
between the washing facilities and the exit point should be paved with
concrete, bituminous materials or hardcore;
·
Where a site boundary adjoins a road, streets or other areas accessible
to the public, hoarding of not less than 2.4 m high from ground level should be
provided along the entire length except for a site entrance or exit;
·
Regular watering, with complete coverage, to reduce dust emissions from
exposed site surfaces and unpaved roads, particularly during dry weather;
·
Side enclosure and covering of any aggregate or dusty material storage
piles to reduce emissions. Where
this is not practicable owing to frequent usage, watering should be applied to
aggregate fines;
·
Open stockpiles should be avoided or covered. Where possible, prevent placing dusty
material storage piles near ASRs;
·
Tarpaulin covering of all dusty vehicle loads transported to, from and
between site locations;
·
Control of vehicle speed on unpaved site roads. Ten kilometers per hour is the
recommended limit;
·
Every stock of more than 20 bags of cement should be covered entirely by
impervious sheeting placed in an area sheltered on the top and the 3 sides;
·
Every vehicle should be washed to remove any dusty materials from its
body and wheels before leaving the construction sites; and
·
Instigation of an environmental monitoring and auditing program to
monitor the construction process in order to enforce controls and modify method
of work if dusty conditions arise.
2.55
In order to achieve the air quality criteria, the
following watering measures for specific site would be required to control the
fugitive dust impacts:
·
Watering twice per day within the worksites at North Point PTW, Wan Chai
East PTW, Fung Mat Road Site, Sandy Bay PTW, Wah Fu PTW, Aberdeen PTW and SCS
worksite at Aberdeen;
·
Watering 4 times per day within worksites at the Central PTW;
·
The barging points should be continuous watering throughout the whole unloading
process; and
·
Watering 8 times per day within worksites at the SCS works area at Wan
Chai East and North Point, SCISTW and the Disinfection Facilities of SCISTW.
2.56
If the above measures are not sufficient to restore
the air quality to acceptable levels upon the advice of ET Leader, the
Contractor shall liaise with the ET Leader on some other mitigation measures,
propose to ER for approval, and implement the mitigation measures.
2.57
The fully covered design of the odour sources of the
upgraded PTWs & SCISTW and the installation of deodorization system at the
exhaust of ventilation system would adequately control potential odour impact. Adverse odour impact from the PTWs &
SCISTW is not anticipated.
2.58
In addition, good housekeeping practices for the
SCISTW and PTWs listed below should be followed to ameliorate any odour impact
from the plant and these standard practices should be included in the plant
operator manual.
·
Screens should be cleaned regularly to remove accumulated organic debris;
·
Grit and screening transfer systems should be flushed regularly with
water to remove organic debris and grit;
·
Grit and screened materials should be transferred to closed containers
to minimize odour escape;
·
Scum and grease collection wells and troughs should be emptied and
flushed regularly to prevent putrefaction of accumulated organics;
·
Skim and remove floating solids and grease from primary clarifiers
regularly;
·
Sludge should be frequently withdrawn from tanks to prevent the
production of gases;
·
Sludge cakes should be transferred to closed containers; and
·
Sludge containers should be flushed with water regularly.
2.59
Besides, in order to avoid excessive extraction of the
foul air from the drop shafts of the sedimentation tanks and also the effluent
flume structure of SCISTW to deodorization system, the extraction vent(s) of
the deodorization system should be located away from the top openings of the
drop shafts.
2.60
The odour impact from sludge transfer tanks could be
controlled by properly design and good cleaning practices of the sludge
transfer tanks. The loading opening
of sludge transfer tank is the potential odour source during the transportation
when there are gaps between the tank opening and its cover. DSD has issued a contract for the
refurbishment works of the sludge transfer tanks and works are scheduled to be
completed in early 2008. The first
few lots of refurbished sludge tanks should be deployed for transporting sludge
to the SENT Landfill since more sensitive receivers would be encountered during
the road transportation. The
air-tightness of the refurbished sludge tanks has been proved by DSD through
trial tests. With thorough cleaning
practice and regular condition test of the refurbished sludge tanks, odour
emission and leachate leakage during storage and transportation are not
anticipated. Further assessment and
performance tests on the sludge tanks with regards to potential odour emissions
would be conducted under the future EM&A programme for verification and
monitoring purposes.
2.61
The implementation schedule for the mitigation
measures during construction phase and operational phase is presented in Appendix A.