4.                   WATER QUALITY

Introduction

4.1               The EIA Report predicted that the discharge of treated effluent from the normal operation of the Project would not have adverse impact on the marine water quality. A post project monitoring (PPM) programme will be implemented to confirm the water quality impacts predicted under normal operation of the Project.    It should be noted that effluent quality, including the levels of E. coli, suspended solids, 5-day biochemical oxygen demand and total residual chlorine (TRC), from the SCISTW will also be governed by the discharge licence conditions after the Project is commissioned. 

4.2               Marine water quality monitoring is also recommended during and after the following situations:

l             Emergency discharge as a result of equipment / power failure at SCISTW during the operational phase;

l             Temporary sewage bypass (required for the construction of the interconnection between the two main pumping stations at SCISTW and other modification works) during the construction phase or early commissioning of the Project; and

l             Emergency discharge of undisinfected effluent from SCISTW in the event of chlorination / dechlorination plant failure during the operational phase. 

4.3               A framework of the responses has been formulated in this EM&A Manual to minimize the impacts from the temporary sewage bypass and emergency discharge.  Detailed contingency plan and operational procedures for the Project will be developed separately at the detailed design stage.

4.4               In this section, the requirements, methodology, equipment, monitoring locations, criteria and protocols for the monitoring and audit of water quality impacts during the construction and operation phase of the Project are presented.

Post Project Monitoring under Normal Operation of the Project

4.5               A post project monitoring (PPM) programme will be implemented to confirm the water quality impacts predicted under normal operation of the Project.  The PPM would consist of one-year baseline monitoring before commissioning and at least one-year impact monitoring after commissioning of the Project. The extent of PPM programme is subject to the prevailing environmental conditions at the time before commissioning of the Project.  The PPM after the first year of operation of the Project will be subject to the first year review.  The PPM shall comprise (i) effluent quality monitoring, (ii) marine water quality monitoring, (iii) ecotoxicological assessment, (iv) sediment quality monitoring, (v) benthic survey assessment and (iv) water quality and plume dispersion modelling and assessment. Details of the PPM requirements shall be agreed with the Director of Environmental Protection prior to the commissioning of the Project.  Based on the PPM results, recommendation shall be made with respect to the need for improvement to the operation of the Project as well as the requirements for, and methodologies to be employed in the course of, future monitoring programme or supplementary investigations to quantitatively assess and predict future performance of the Project and its impact on the environment.  A Post Project Monitoring and Audit Manual shall be prepared for long term monitoring of the performance or the outfall to ensure acceptability of the impacts of the effluent discharges on the receiving environment.

Effluent and Marine Water Quality Monitoring

Effluent Monitoring

4.6               The effluent monitoring data (TRC, chlorination by-products (CBPs), arsenic, chromium, copper, mercury, nickel, zinc, sulphide, surfactants, phenol, cyanide and ammonia nitrogen (NH3-N), E.coli, suspended solids (SS), 5-day biochemical oxygen demand (BOD5), total kjeldahl nitrogen (TKN), total phosphorus (TP), ortho-phosphate (PO4) and other contaminant of concern (COC) to be agreed with EPD) shall be used to provide information to investigate the observations in the marine water quality monitoring and whole effluent toxicity test (WETT).  

Effluent Sample Collection

4.7               Effluent from SCISTW shall be collected at a suitable location.  The sampling location should be agreed with the Environmental Consultant, approved by DSD and EPD, and should fulfil the following requirements:

l             Effluent collected at the sampling location is representative to the effluent discharged at the effluent diffuser

l             Sampling works at the sampling location would not interfere with the SCISTW operation

l             Sampling works at the sampling location would not induce safety hazard (e.g. staff sampling effluent drops into the culvert)

4.8               The effluent should be collected in a full 24-hour period.  Twenty four-hour flow-weighted composite effluent sample for subsequent chemical analysis and testing[1] should be prepared by the following procedures:

l             Collect effluent sub-sample at bi-hourly interval over a 24 hour period

l             Obtain flow record of SCISTW for the 24-hour sampling period

l             Calculate the volume of each sub-sample for preparation of flow-weighted composite sample

l             Transfer the appropriate volume of sub-samples to a clean container and mix thoroughly

4.9               The effluent sampling should be planned carefully to ensure appropriate volume of effluent sub-samples is collected to prepare sufficient amount of flow-weighted composite effluent sample for carrying out subsequent chemical analysis and testing.

Effluent Monitoring Schedule

4.10           The effluent monitoring shall be performed over one year before commissioning of the Project and the first year of Project operation and shall be coincide with the marine water sampling schedule as detailed in Sections 4.25 and 4.26.  The effluent monitoring shall be ceased in the events of any emergency discharges.  

4.11           Besides, a close to real time on-line operation phase monitoring on TRC in treated effluent shall be performed daily over the first year of Project operation after the commissioning period of the Project.   

Effluent Monitoring Parameters

4.12           The effluent concentrations for nine CBPs (bromoform, bromodichloromethane, chloroform, dibromochloromethane, bromoacetic acid, chloroacetic acid, dibromoacetic acid, dibromoacetic acid, dibromoacetic acid), arsenic, chromium, copper, mercury, nickel, zinc, sulphide, surfactants, phenol, cyanide, TRC, E.coli, SS, BOD5, TKN, NH3-N, TP and PO4 shall be determined by laboratory.  The suggested analysis method and detection limit are presented in Table 4.6.

4.13           Nine CBPs species are selected for monitoring because:

l             they are known to be the most important and abundant CBPs, relatively more toxic and of greater concern, and therefore serve as good indicators for CBPs; 

l             international drinking water standards for these 9 CBPs are made available for protection of public health;

l             they were classified as contaminants of concern (COCs) in the HATS ADF EIA, and found to be of concentrations higher than other halogenated organics in the chlorinated/dechlorinated (C/D) HATS effluent; 

l             for other 25 halogenated organics grouped as “potential CBPs” and studied in the ADF EIA, they are not considered in setting the discharge limits because almost none of them were found in the C/D HATS effluent.  Moreover, most of these compounds are not directly related to the disinfection process, but they were included in the EIA study merely for conservative assessment as some of them are regulated by US for controlling industrial discharges.

Recommended Discharge Limits

4.14           The TRC discharge standards for the effluent are recommended based on the water quality modelling results.  Besides, CBPs discharge limit is set with reference to the Toxicity Reference Value (TRVs) used in the ecological risk assessment under the EIA.  The TRVs for the CBPs species are either the most stringent international water quality criteria (for such species), or values specifically derived from relevant ecotoxicity of the highest toxicity using the USEPA procedures.  Effluent reaching the zone of initial dilution (ZID) is assumed to have diluted to 38 times which is the minimum dilution predicted for the Stage 2A.  The limits are set such that all proposed TRVs should be met at the edge of ZID.

4.15           The discharge limits derived according to the above approach are shown below:

 

Table 4.1          Discharge Limits for TRC and CBPs

Determinant

Toxicity Reference Values (mg/L)

Discharge Limit (measured in HATS effluent) (mg/L)

Total residual chlorine

0.013 (edge of ZID)

0.008 (edge of mixing zone)

0.2 (95 %tile)

0.4 (Max.)

Bromoform

Tri-

halomethanes (THMs)

0.36

13

Bromodichloromethane

0.022

0.8

Chloroform

0.012

0.45

Dibromochloromethane

0.034

1.2

Bromoacetic acid

Halo-acetic Acids (HAAs)

1.6

60

Chloroacetic acid

32

1200

Dibromoacetic acid

0.69

26

Dichloroacetic acid

0.23

8

Trichloroacetic acid

93

3500

l             The suggested detection limit was in light of the concentration of interest (COI) for human health and/or ecological resources, which was based on local/international authority approved standard.   Determinant at concentration below COI is not expected to induce concern to human health and ecological resources. 

 

4.16           The discharge license of the existing SCISTW, E coli level and quality of other relevant parameter of the effluent discharge into the inlet of the submarine outfall are listed below:

l             E coli (no. per 100 ml): 20,000 (Geometric Mean), 300,000 (95 Percentile)

l             pH: 6-10

l             Suspended Solids: 55 mg/L (Percentile Standards)

l             Biochemical Oxygen Demand (5 days, 20oC): 75 mg/L (Percentile Standards)

Chlorination/Dechlorination Dosage Record

4.17            The Environmental Consultant shall collect from SCISTW the chemical dosage record of the chlorination/dechlorination process under the Project for the first year operation after the commissioning period of the Project for data analysis.  The Environmental Consultant shall compare the actual dosages with those predicted under the EIA Study to see whether there is any significant difference which causes deviations of the monitoring results from the model prediction under the EIA Study. The close to real time on-line monitoring (on dosage of sodium hypochlorite and sodium bisulphite) record and review shall be submitted to DSD and EPD.

Marine Water Quality Monitoring and Locations

Water Quality Monitoring in Area Close to the Outfall Diffuser

4.18            The marine water quality monitoring (for CBPs, TRC, unionized ammonia (UIA), arsenic, chromium, copper, mercury, nickel, zinc, sulphide, surfactants, phenol, cyanide, E.coli, SS, BOD5, ammonia nitrogen (NH3-N), nitrite nitrogen (NO2), nitrate nitrogen (NO3), TP, PO4 and other COC to be agreed with EPD) is recommended in order to achieve the following objectives:

l             To check whether the Project would cause an increase in concentrations of these contaminants in marine water close to the SCISTW outfall diffuser.

l             To verify the predictions of the Human Health Risk Assessment, details on the use of monitoring data for this objective are presented in Section 5 of the EM&A Manual.

l             To verify the predictions of the Ecological Risk Assessment, details on the use of monitoring data for this objective are presented in Section 6 of the EM&A Manual.

4.19           It is recommended to set up 6 near field monitoring stations with their locations and co-ordinates as shown in Figure 4.1, which also shows the boundary of the ZID and the boundary of mixing zone. The ZID was determined by the near field water quality modelling.  The mixing zone provided in Figure 4.1 was based on the far field water quality model results predicted for UIA at the early phase of Stage 2A in 2014.  As shown in Figure 4.1, 4 stations would be located at the edge of ZID (stations 2 and 3) and the edge of mixing zone (stations 1 and 4), forming a transect line perpendicular to the effluent diffuser.  Stations SM6 and SM12 would be located in areas that would unlikely be affected by the Project and will therefore serve as control stations.  The coordinates of the proposed monitoring stations are listed in Table 4.2.

Table 4.2  Proposed Marine Water Quality Monitoring Stations Close to SCISTW Outfall

Station

Description

Easting

Northing

1

Edge of Mixing Zone (northwest of effluent diffuser)

829762.00

819604.47

2

Edge of ZID (northwest of effluent diffuser)

830117.99

819251.93

3

Edge of ZID (southeast of effluent diffuser)

830186.21

819184.37

4

Edge of Mixing Zone (southeast of effluent diffuser)

830525.00

818848.87

SM6

Control Station

826179.81

805902.89

SM12

Control Station

819524.19

808420.40

 

Water Quality Monitoring in the Far Field Area

4.20           The Environmental Consultant shall review and analyze the concentrations for E.coli, SS, BOD5, NH3-N, UIA, NO2, NO3, PO4, TP, arsenic, chromium, copper, mercury, nickel, zinc, sulphide, surfactants, phenol, cyanide and other COC to be agreed with EPD in the Western Buffer, Victoria Harbour and Southern waters (including the semi-enclosed bays as identified in the EIA) during the one year before the commissioning of the Project and the first year of Project operation.

4.21           The Environmental Consultant shall also review and analyze the E.coli concentrations collected at the beaches in Tsuen Wan District during the one year before the commissioning of the Project and the first year of Project operation.

4.22           It is recommended to set up 21 far field monitoring stations as shown in Figure 4.2.  These stations represent the areas which would potentially have water quality improvement due to the Project implementation as predicted by the water quality model. 

4.23           The coordinates of the proposed monitoring stations are listed in Table 4.3.

Table 4.3          Proposed Marine Water Quality Monitoring Stations in the Far Field Area

Station

Description

Easting

Northing

Parameters

B7

Anglers’ Beach

823836.36

825044.52

E.coli

B8

Gemini Beach

825215.29

824933.71

B9

Ho Mei Wan Beach

825388.98

825067.17

B10

Casam Beach

825731.46

825330.90

B11

Lido Beach

825917.78

825385.83

B12

Ting Kau Beach

826277.40

825519.01

B13

Approach Beach

827237.94

825301.02

B14

Ma Wan Beach

824431.47

823415.85

WM2

Western Buffer

827881.70

816189.04

E.coli, SS, BOD5, NH3-N, UIA, NO2, NO3,  PO4, a suite of heavy metals, sulphide, surfactants, phenol, cyanide and other COC to be agreed with EPD

WM3

Western Buffer

828048.67

820118.17

WM4

Western Buffer

825354.99

823325.61

VM5

Central Victoria Harbour

836091.75

816541.13

VM7

Western Victora Harbour

832495.44

817473.60

NM1

North Western

820255.99

823213.76

SM3

East Lamma Channel

833462.67

809640.82

SM9

West Lamma Channel

824950.63

814983.89

SM6

West Lamma Channel

826179.81

805902.89

SM4

Semi-enclosed Bay – Northern Lamma

832319.64

808221.84

SM10

Semi-enclosed Bay – Eastern Lantau

821337.85

818133.63

SM11

Semi-enclosed Bay – Southeast Lantau

819888.34

813185.26

SM13

Semi-enclosed Bay – South Lantau

814119.93

808604.29

Sampling Method

4.24           During each beach monitoring event, beach water samples shall be collected where the water depth is between thigh to waist depth i.e. about 1 metre depth for analysis of E. coli bacteria and physical measurements of pH, salinity and turbidity.

4.25           For all other marine water monitoring stations, sampling shall be taken at three water depths, namely, 1m below water surface, mid-depth and 1m above sea bed, except where the water depth is less than 6m, in which case the mid-depth station may be omitted.  Shall the water depth be less than 3m, only the mid-depth station will be monitored.   At each monitoring station, six replicate samples shall be collected at each water depth, which is a reasonable number of replicates for environmental monitoring data to be analyzed by common statistical analysis method (Townend, 2002).  The Environmental Consultant shall review the number of replicates by statistical power analysis after the first set of baseline marine water quality monitoring. Sufficient volume of each water sample shall be collected for analysis to achieve the required detection limit.   In-situ measurements at DO, pH, salinity, temperature and turbidity shall be taken at 0.5m depth intervals at all the marine water quality monitoring stations.

Monitoring Schedule

4.26           The marine water quality monitoring shall be performed over one year before commissioning of the Project and the first year of Project operation. For baseline monitoring, marine water sampling shall coincide with the baseline effluent sampling. At least 4 survey events shall be undertaken over one year to give adequate coverage of different tidal states during both wet and dry seasons. During each survey event, sampling shall be taken at 2 slack tide conditions (low-water and high-water). The purpose of the baseline monitoring is to establish ambient conditions without the Project.  The baseline monitoring shall be ceased in the events of any emergency discharges.

4.27           Similarly, the marine water sampling for operation phase monitoring shall coincide with the effluent sampling for operation phase monitoring. At least 4 operational phase survey events shall be undertaken over one year to give adequate coverage of different tidal states during both wet and dry seasons. During each survey event, sampling shall be taken at 2 slack tide conditions (low-water and high-water). The operation phase monitoring shall be ceased in the events of any emergency discharges and the monitoring programme after the first year of operation of the Project will be subject to the first year review.

4.28           Besides, a close to real time on-line operation phase monitoring on TRC in marine water shall be performed daily over the first year of Project operation after the commissioning period of the Project.  Monitoring programme after the first year of operation of the Project will also be subject to the first year review.

Laboratory Measurement / Analysis

4.29           The suggested analysis method and detection limit are presented in Table 4.6.

Statistical Analysis of Monitoring Data

4.30           After the data of the first set of baseline marine water quality monitoring has been obtained, a statistical power analysis shall be conducted to verify and review the number of replicates required for subsequent baseline and operation phase monitoring sessions. 

4.31           The monitoring data should be analyzed using analysis of variance techniques to test for differences between sampling locations.  Once a time series of data (sequential sampling events) has been gathered, difference should be tested between the stations and between the different sampling events to examine any temporal trends in pollutant concentrations in marine water.  The statistical analysis of monitoring data would provide information to identify any difference of pollutant level in marine water in spatial and temporal terms.

4.32           One key objective of the proposed monitoring programme is to check whether the Project would cause an increase in contaminant concentrations in marine water close to the SCISTW outfall (such as for CBPs, TRC, UIA, arsenic, chromium, copper, mercury, nickel, zinc, sulphide, surfactants, phenol, cyanide).  Therefore, once the operation phase monitoring programme for the year is complete, the operation phase monitoring data obtained for the year should be compared with the baseline monitoring data using statistical analysis technique to determine whether there is increase of contaminant concentrations in marine water after implementation of the Project.  Should the statistical analysis reveal that contaminant concentrations in marine water increase after implementation of the Project, the monitoring data collected in effluent quality monitoring shall be used to provide information to investigate whether such increase is due to the effluent discharged by the Project.  

4.33           If any of the near field water quality criteria as indicated in Table 4.3a are exceeded, the follow-up actions as listed below shall be taken:

l             Check the accuracy of the measurements and the correctness of the analytical results

l             Increase the monitoring frequency to check if exceedance persists

l             In case of persistent CBP exceedances:

Ø       monitor the CBPs levels in the influent, and in the effluent stream before and after chlorination / dechlorination

Ø       review the chemical dosages and TRC levels in the effluent

Ø       Consider measures (e.g. adjusting chemical dosages) to reduce TRC and CBPs levels in the effluent.  Such measures should not cause significant deterioration in the required disinfection power or targeted bacteria reduction level

l             Conduct human health risk assessment and ecological risk assessment using the operation phase monitoring data obtained for the year to verify that the human health risk/impact and ecological risk due to potential contaminants discharged from SCISTW effluent is acceptable.  The details of the human health risk assessment and ecological risk assessment are presented in Section 5 and Section 6 of the EM&A Manual respectively.

 

Table 4.3a        Near Field Water Quality Criteria

Parameter

Value

Type / Period

Applicable Zones / Uses

Unionized ammonia (UIA)

≤ 0.021 mg/l (as N) (2)

Annual average

At edge of ZID (1)

≤ 0.035 mg/l (as NH3) (3)

4-day average

At edge of ZID (1)

≤ 0.233 mg/l (as NH3) (3)

1-hour average

At edge of ZID (1)

pH

6.5 – 8.5,

and change ≤ 0.2

90% of occasions

At edge of ZID (1)

Temperature

change ≤ 2 oC

90% of occasions

At edge of ZID (1)

Sulphide

≤ 0.02 mg/l

90% of occasions

At edge of ZID (1)

Cyanide

≤ 0.005 mg/l

90% of occasions

At edge of ZID (1)

Total residual chlorine (TRC)

≤ 0.013 mg/l

Daily Maximum

At edge of ZID (1)

Surfactants

≤ 0.03 mg/l

90% of occasions

At edge of ZID (1)

Copper

≤ 0.005 mg/l

90% of occasions

At edge of ZID (1)

Nickel

≤ 0.005 mg/l

90% of occasions

At edge of ZID (1)

Total chromium

≤ 0.05 mg/l

90% of occasions

At edge of ZID (1)

Zinc

≤ 0.02 mg/l

90% of occasions

At edge of ZID (1)

Mercury

≤ 0.00021 mg/l

90% of occasions

At edge of ZID (1)

Arsenic

≤ 0.02 mg/l

90% of occasions

At edge of ZID (1)

Phenol

≤ 0.005 mg/l

90% of occasions

At edge of ZID (1)

Acute Toxicity

0.3 acute toxicity units (TUa) (derived from LC50 values based on whole effluent toxicity tests) (4)

One hour average condition not to exceed this value

At edge of ZID (1)

(Source: EEFS Report on Community Consultation for the Proposed Water Quality Criteria)

(1) For a surface plume, initial dilution is defined as the dilution obtained at the centre line of the plume when the sewage reaches the surface.  For a trapped plume, initial dilution is defined as the dilution obtained at the center line of the plume where the plume reaches the maximum rise height when the vertical momentum / buoyancy of the plume becomes zero.

(2) The WQC for annual averaged UIA was derived with reference to the WQO under WPCO which is expressed as N.

(3) The WQC for 1-hour and 4-day averaged UIA was derived with reference to the USEPA which is expressed as NH3.

(4) USEPA Technical Support Document for Water Quality-Based Toxics Control (March 1991), from which one acute Toxicity Unit (TUa) is defined as TUa = 100/LC50, where LC50 = % of effluent which gives 50% survival of the most sensitive of the range of species tested.

4.34           Based on the review and analysis of the monitoring data, the Environmental Consultant shall also review the effectiveness of the Project for improving the water quality in the marine water (in terms of E.coli, SS, BOD5, TIN, UIA and PO4 etc.) in the Western Buffer, Victoria Harbour and Southern waters.  Also, the Environmental Consultant shall review the need for upgrading or improvements to the Project operation and provide recommendation on the SCISTW effluent quality (in terms of E.coli, SS, BOD5, NH3-N and PO4 etc.).

Ecotoxicological Assessment (Indicative)

4.35           A programme of ecotoxicological assessment shall be proposed, with full scientific justification, for the approval of the EPD to determine the toxicity of the treated effluent and the toxicity of the receiving marine water.  All ecotoxicological samples shall be fully characterized physically and chemically. The list of determinants shall include ammonia, sulphide, a suit of heavy metal, selected species of CBPs, TRC and other COC to be agreed with EPD. The test organisms used for the toxicity tests shall include representative species of the local environment, preferably including common species of fish cultured locally. Drainage Services Department (DSD) is required to undertake routine sampling and testing for characterization of the treated effluent under the Water Pollution Control Ordinance discharge licence for SCISTW. The Environmental Consultant shall coordinate the works required under effluent monitoring and liaise with DSD properly in order to minimize duplication of effort and expenditure for sampling and testing related to this Assignment. The requirements of ecotoxicological assessment are detailed in Section  6 of this EM&A Manual.

Sediment Quality Monitoring (Indicative)

4.36           Sediment sampling shall be performed four times over the field work period of one year to give adequate coverage of both wet and dry seasons. The sampling locations shall cover selected stations in both near-field and far-field and analysis of sediment samples to be conducted shall be agreed with the Director of Environmental Protection. Analysis shall include determinands such as percentage of silt/ clay, pH, acid volatile sulphides, total volatile solids, total organic carbon, ammonia, total nitrogen, total phosphorous, a suite of metals and other contaminants of concern identified in the treated effluent, if any.

Benthic Survey (Indicative)

4.37           Benthic sampling shall be conducted four times over the field work period of one year, in parallel with the sediment sampling described in Section 4.34 above, using the same monitoring stations. The benthos collected shall be identified to the lowest taxonomic level and the benthic community structure determined.

Water Quality and Plume Dispersion Modelling and Assessment (Indicative)

Modelling Software

4.38           The modellinging software shall be capable of accurately simulating stratification and salinity transport in three dimensions within the model area.

4.39           The modelling software shall contain hydrodynamic, water quality and particle dispersion modules. The hydrodynamic and water quality modules shall have proven successful applications locally and overseas.

4.40           The hydrodynamic and water quality modules shall strictly conserve mass at all levels.

Model Details – Calibration and Validation

4.41           No field data collection is required for the purposes of model calibration for this study. However, before commencement of this study, the models shall have been properly calibrated and validated with the field data collected from studies which may include, inter alia:

           

·         Hydraulic and Water Quality Studies in Victoria Harbour (1987)

·         Port and Airport Development Strategy - Enhancement of WAHMO Mathematical Models (1990)

·         Strategic Sewage Disposal Scheme Stage II - Oceanic Outfall, Oceanographic Surveys and Modelling (1992)

·         Update on Cumulative Water Quality and Hydrological Effect of Coastal Developments and Upgrading of Assessment Tool (1998)

·         Environmental and Engineering Feasibility Assessment Studies in relation to the Way Forward of the Harbour Area Treatment Scheme (2004)

·         EPD’s routine monitoring data

·         Tidal data from HK Observatory, Macau and relevant Mainland Authorities

4.42           Tidal elevation data shall be calibrated and validated in both frequency and time domain manner.

4.43           For the purposes of calibration and validation, the model shall simulate not less than 15 days of real tide sequence (excluding model spin up) in both dry and wet seasons with due consideration for the time required to establish initial conditions.

4.44           In general, the hydrodynamic models must be calibrated to the following criteria:

Criteria

Level of fitness

                                    with field data

Ø                   tidal elevation (root mean square)                                                        < 8 %

Ø                   maximum phase error at High Water and Low Water                             <20 minutes

Ø                   maximum current speed deviation                                                       < 35 %

Ø                   maximum phase error at peak speed                                                   < 20 minutes

Ø                   maximum direction error at peak speed                                               < 15 degrees

Ø                   maximum salinity deviation                                                                 < 2.5 ppt

 

Model Details – Simulation

4.45           Model runs shall be undertaken to simulate the actual conditions to help ascertain and predict the impact of the discharge on the receiving waters. The water quality modelling results shall be qualitatively explainable, and any identifiable trend and variations in water quality shall be reproduced by the model.  The water quality model shall simulate and take account of the interaction of dissolved oxygen, phytoplankton, organic and inorganic nitrogen, phosphorus, silicate, biochemical oxygen demand, temperature, suspended solids, air-water exchange processes. It shall also simulate salinity transport and E.coli dispersion. Salinity results simulated by hydrodynamic models and water quality models shall be demonstrated to be consistent.

4.46           The hydrodynamic and water quality models shall be carefully designed such that its boundary is remote enough and would not be affected by the Project with a fine grid commensurate with the detail of assessment.  In general, the model grid size shall be less than 400m in open waters and less than 75m around sensitive receivers and outfall diffusers.  A fine grid model can be used for detailed assessment but shall either be dynamically linked to or form part of the far field model, which cover the Pearl Estuary and the Dangan (Lema) Channel to incorporate the effects of oceanic and Pearl River discharge processes, through nesting or gradual refinement techniques. The model coverage and grid schematisation shall be agreed with the Director of Environmental Protection.

Modelling Assessment

4.47           Hydrodynamic and water quality models shall be run to simulate 15 days (excluding model spin up) of real tide sequence.

4.48           The models shall be used to help ensure cost effective design of the field monitoring programme and to help establish the extent of and influences on the zone of influence.

4.49           The models shall be used to facilitate the assessment of the impact of the treated effluent discharge on the receiving environment in order to ensure that the study objectives are fully satisfied.

4.50           Dye Tracer Surveys, if necessary shall be conducted during wet and dry seasons in post-commissioning period, both on a flood tide and an ebb tide, to assess the behaviour of the effluent plume from the discharge points and to quantify the actual dilution under both stratified and non-stratified water columns.

4.51           The monitoring programme shall maintain a degree of flexibility to allow the incorporation of the findings based on the monitoring results obtained as the study progresses. Therefore, the location and number of monitoring stations, number of samples and replicates, and types of tests and analyses will be subject to continual review by the Project Proponent and amendment as necessary. Accordingly, upon direction from the Director of Environmental Protection, resources for the monitoring programme may be redeployed, reduced or increased within the study area.

4.52           Field sampling and survey, if required, shall be proposed and arranged to characterize other major background pollution discharges in the Study Area.

4.53           The potential impacts of the treated effluent on marine ecology including commercial and aquaculture fisheries shall be assessed based on the water quality and ecotoxicological assessment and assessment of the available data in respect of the water quality.

4.54           Impacts arising as a consequence of the discharge of treated effluent from SCISTW shall be distinguished from those arising from other pollution sources and anthropogenic activities.

Water Quality Monitoring for Temporary Sewage Bypass / Emergency Discharge

Monitoring Locations and Schedule

4.55           Marine water quality monitoring for E.coli is recommended during and after the following situations:

Case 1 -  Emergency discharge as a result of equipment / power failure at SCISTW during the operational phase;

Case 2 - Temporary sewage bypass (required for the construction of the interconnection between the two main pumping stations at SCISTW and the modification works at the main pumping station at SCISTW) which will be conducted in the dry season during the construction phase or early commissioning of the Project;

Case 3-   Emergency discharge of undisinfected effluent from SCISTW in the event of chlorination / dechlorination plant failure during the operational phase; and

 Case 4- Temporary sewage bypass (required for the modification to the North West Kowloon Pumping Station) which will be conducted in the dry season during the construction phase or early commissioning of the Project;

4.56           It is recommended to set up 56 monitoring stations (for Case 1), 42 monitoring stations (for Case 2), 17 monitoring stations (for Case 3) and 13 monitoring stations (for Case 4) as shown in Table 4.4.  Locations of the monitoring stations are shown in Figure 4.2.  These stations represent the sensitive receivers which could potentially be affected by the temporary sewage bypass or emergency discharge from HATS.  These stations also cover some gradient stations to assist in the identification of the source of any impact at the sensitive receivers as well as the control station outside the influence zone of the temporary discharge as predicted by the water quality modelling.

4.57           The coordinates of the proposed monitoring stations are listed in Table 4.4.

Table 4.4          Proposed Marine Water Quality Monitoring Stations for Emergency Situations

Station

Description

Easting

Northing

Case 1 - Emergency Discharge of Screened Sewage via all the Stage 1 and Stage 2 PTWs

B7

Anglers’ Beach

823836.36

825044.52

B8

Gemini Beach

825215.29

824933.71

B9

Ho Mei Wan Beach

825388.98

825067.17

B10

Casam Beach

825731.46

825330.90

B11

Lido Beach

825917.78

825385.83

B12

Ting Kau Beach

826277.40

825519.01

B13

Approach Beach

827237.94

825301.02

B14

Ma Wan Beach

824431.47

823415.85

B24

Big Wave Bay Beach

843474.09

811730.33

B25

Rocky Bay Beach

844030.05

810286.64

B26

Shek O Beach

843891.17

809864.31

B30

St. Stephen’s Beach

839990.14

808461.60

B31

Chung Hom Kok Beach

838616.79

808752.43

B32

South Bay Beach

838104.70

809598.73

B33

Middle Bay Beach

838056.97

809993.31

B34

Repulse Bay Beach

838008.93

810827.28

B35

Deep Water Bay Beach

836785.60

811635.55

F1

Tung Lung Chau Fish Culture Zone

847571.26

813102.00

F4

Lo Tik Wan Fish Culture Zone

831366.51

809221.48

F5

Ma Wan Fish Culture Zone

823875.25

823699.48

WSD4

Tsuen Wan flushing water intake

828908.71

825681.26

WSD5

Tsing Yi flushing water intake

829862.33

823104.16

WSD6

Cheung Sha Wan flushing water intake

833991.16

820235.42

WSD7

Kowloon South flushing water intake

833968.78

818053.54

WSD9

Tai Wan flushing water intake

837955.17

818412.01

WSD10

Cha Kwo Ling flushing water intake

841379.00

817859.28

WSD11

Yau Tong flushing water intake

842149.61

816974.14

WSD12

Tsueng Kwan O flushing water intake

845512.14

817421.15

WSD13

Siu Sai Wan flushing water intake

843904.21

814469.38

WSD15

Sai Wan Ho flushing water intake

841215.41

816451.38

WSD17

Quarry Bay flushing water intake

839685.64

817081.46

WSD18

Central Water Front flushing water intake

833935.18

816624.15

WSD19

Sheung Wan flushing water intake

833383.13

816836.34

WSD20

Kennedy Town flushing water intake

830826.34

816244.46

WSD21

Ap Lei Chau flushing water intake

834105.49

810567.95

WSD22

Wan Chai flushing water intake

836246.19

816134.92

VM12

Gradient Station

830542.34

821139.51

VM14

Gradient Station

829254.66

825159.72

VM15

Gradient Station

832707.02

818964.77

VM8

Gradient Station

830363.95

817092.23

VM7

Gradient Station

832495.44

817473.60

VM5

Gradient Station

836091.75

816541.13

VM2

Gradient Station

839713.80

817641.47

VM4

Gradient Station

838056.49

817637.50

VM1

Gradient Station

841809.43

816567.96

JM3

Gradient Station

844931.70

816956.95

EM1

Gradient Station

844379.62

815140.61

EM2

Gradient Station

845472.92

813712.75

EM3

Gradient Station

845771.79

810953.82

WM1

Gradient Station

830685.17

812441.28

WM2

Gradient Station

827881.70

816189.04

WM4

Gradient Station

825354.99

823325.61

SM3

Gradient Station

833462.67

809640.82

SM2

Gradient Station

836402.69

809492.93

MM13

Control Station

864290.82

808693.11

SM17

Control Station

814115.31

801690.83

Case 2 – Temporary Bypass of Screened Sewage via the Stage 1 PTWs

B7

Anglers’ Beach

823836.36

825044.52

B8

Gemini Beach

825215.29

824933.71

B9

Ho Mei Wan Beach

825388.98

825067.17

B10

Casam Beach

825731.46

825330.90

B11

Lido Beach

825917.78

825385.83

B12

Ting Kau Beach

826277.40

825519.01

B13

Approach Beach

827237.94

825301.02

B14

Ma Wan Beach

824431.47

823415.85

B24

Big Wave Bay Beach

843474.09

811730.33

B25

Rocky Bay Beach

844030.05

810286.64

B26

Shek O Beach

843891.17

809864.31

F1

Tung Lung Chau Fish Culture Zone

847571.26

813102.00

F5

Ma Wan Fish Culture Zone

823875.25

823699.48

WSD5

Tsing Yi flushing water intake

829862.33

823104.16

WSD6

Cheung Sha Wan flushing water intake

833991.16

820235.42

WSD7

Kowloon South flushing water intake

833968.78

818053.54

WSD9

Tai Wan flushing water intake

837955.17

818412.01

WSD10

Cha Kwo Ling flushing water intake

841379.00

817859.28

WSD11

Yau Tong flushing water intake

842149.61

816974.14

WSD12

Tsueng Kwan O flushing water intake

845512.14

817421.15

WSD13

Siu Sai Wan flushing water intake

843904.21

814469.38

WSD15

Sai Wan Ho flushing water intake

841215.41

816451.38

WSD17

Quarry Bay flushing water intake

839685.64

817081.46

WSD18

Central Water Front flushing water intake

833935.18

816624.15

WSD19

Sheung Wan flushing water intake

833383.13

816836.34

WSD20

Kennedy Town flushing water intake

830826.34

816244.46

WSD22

Wan Chai flushing water intake

836246.19

816134.92

VM12

Gradient Station

830542.34

821139.51

VM14

Gradient Station

829254.66

825159.72

VM15

Gradient Station

832707.02

818964.77

VM8

Gradient Station

830363.95

817092.23

VM7

Gradient Station

832495.44

817473.60

VM5

Gradient Station

836091.75

816541.13

VM2

Gradient Station

839713.80

817641.47

VM4

Gradient Station

838056.49

817637.50

VM1

Gradient Station

841809.43

816567.96

JM3

Gradient Station

844931.70

816956.95

EM1

Gradient Station

844379.62

815140.61

EM2

Gradient Station

845472.92

813712.75

EM3

Gradient Station

845771.79

810953.82

MM13

Control Station

864290.82

808693.11

SM17

Control Station

814115.31

801690.83

Case 3 - Emergency Discharge of Undisinfected CEPT Effluent via the SCISTW Outfall

B7

Anglers’ Beach

809640.82

833462.67

B8

Gemini Beach

809492.93

836402.69

B9

Ho Mei Wan Beach

806868.38

851275.55

B10

Casam Beach

801678.43

826182.25

B11

Lido Beach

825917.78

825385.83

B12

Ting Kau Beach

826277.40

825519.01

B13

Approach Beach

827237.94

825301.02

B14

Ma Wan Beach

824431.47

823415.85

F5

Ma Wan Fish Culture Zone

823875.25

823699.48

WSD18

Central Water Front

833935.18

816624.15

WSD19

Sheung Wan

833383.13

816836.34

WSD20

Kennedy Town

830826.34

816244.46

WM4

Gradient Station

825354.99

823325.61

VM8

Gradient Station

830363.95

817092.23

VM7

Gradient Station

832495.44

817473.60

SM6

Control Station

826179.81

805902.89

SM12

Control Station

819524.17

808420.40

Case 4 - Bypass of Screened Sewage from NWKPTW at the Seawall of Stonecutters Island

B7

Anglers’ Beach

809640.82

833462.67

B8

Gemini Beach

809492.93

836402.69

B9

Ho Mei Wan Beach

806868.38

851275.55

B10

Casam Beach

801678.43

826182.25

B11

Lido Beach

825917.78

825385.83

B12

Ting Kau Beach

826277.40

825519.01

B13

Approach Beach

827237.94

825301.02

B14

Ma Wan Beach

824431.47

823415.85

F5

Ma Wan Fish Culture Zone

823875.25

823699.48

VM14

Gradient Station

829254.66

825159.72

WM4

Gradient Station

825354.99

823325.61

SM6

Control Station

826179.81

805902.89

SM12

Control Station

819524.17

808420.40

4.58           It should be noted that the temporary sewage bypass (Case 2 and Case 4) will be conducted under the dry season to minimize the water quality impacts. A three-month baseline monitoring programme covering the dry season is proposed at a frequency of once per month to establish the baseline water quality conditions at the designated stations before prior to the temporary sewage bypass during the construction phase or early commissioning of the Project.  A six-month baseline monitoring programme covering both dry and wet seasons is proposed at a frequency of once per month to establish the baseline water quality conditions at the 56 stations (for Case 1) and 17 stations (for Case 3) after commissioning of the Project.  During each monitoring event, water samples shall be collected at different tidal status (one for mid-flood tide and one for mid-ebb tide).  The purpose of the baseline monitoring is to establish ambient conditions when the HATS is operated normally.  The baseline monitoring shall be ceased in the events of any emergency discharges.

4.59           During each sampling occasion, measurements shall be taken at three water depths, namely, 1 m below water surface, mid-depth and 1 m above sea bed, except where the water depth is less than 6 m, in which case the mid-depth station may be omitted.  Shall the water depth be less than 3 m, only the mid-depth station will be monitored. 

4.60           In the event of temporary sewage bypass or emergency discharge, daily marine water monitoring shall be conducted at the designated monitoring stations as shown in Table 4.4 throughout the whole sewage discharge period until the baseline water quality resumes after the normal plant operation is restored.   During each monitoring event, water samples shall be collected at both mid-flood tide and mid-ebb tide (i.e. twice a day). 

4.61           The monitoring programme for Case 1 and Case 3 shall be conducted in the first 2 years after the completion of the baseline monitoring.  After the 2-year monitoring period, a review shall be conducted by the Environmental Consultant to determine whether such monitoring shall be continued.  The review results shall be submitted to DSD and EPD.  Termination or any amendment to the monitoring programme shall be agreed by DSD and EPD.

4.62           The status and locations of water sensitive receivers and the marine activities may change after issuing this Manual.  Necessary change in the monitoring locations shall be reviewed and approved by EPD, before the commencement of the monitoring.  It is recommended that DSD should monitor the quality (i.e. E.coli level, pH value, temperature) and quantity of sewage effluent discharged from the SCISTW during the marine water sampling for data interpretation.

4.63           It is recommended that relevant government departments including EPD, WSD and LCSD shall be informed of any emergency discharge events.  The Plant operators shall make reference to the response approach documented in the Beach Pollution Response Plan maintained by EPD and maintain good communications with various concerned parties.  A list of address, email address, phone and fax number of key persons in various departments responsible for action shall be made available to the Plant operators.  A framework of the emergency response is provided in Table 4.5.

Laboratory Measurement / Analysis

4.64           The suggested analysis method and detection limit are presented in Table 4.6.

Emergency Response

General Requirement

4.65           The Plant operator / DSD shall inform EPD, WSD and LCSD in case of any emergency discharge of undisinfected effluent due to power supply failure or equipment failure in SCISTW.  The Plant operator / DSD shall inform EPD, WSD and LCSD at least 4 weeks prior to the planned temporary sewage bypass during construction phase or early commissioning of the Project.  A list of address, email address, phone and fax number of key persons of concerned parties responsible for action should be made available to the Plant operators.    The Plant operator / DSD shall closely liaise with relevant parties so that the EPD, WSD and LCSD can be informed promptly of any cases of temporary sewage bypass or emergency discharge.  The event and action plan under temporary sewage bypass and emergency discharge are provided in Table 4.5.     

4.66           Under temporary sewage bypass and emergency discharge, it is recommended that DSD should monitor daily quality (i.e. E.coli level, pH value, temperature) and quantity of sewage effluent discharged from the SCISTW during the whole water quality monitoring period for data interpretation. 

Table 4.5          Emergency Response Plan for Temporary Sewage Bypass and Emergency Discharge from HATS

Event

Action Plan

Case 1 - Total power / equipment failure at SCISTW during operational phase

1.      Plant operators / DSD to investigate the reason of plant failure and to implement appropriate remedial measures as stipulated in the contingency / operation plan for the HATS.

2.      If emergency discharge is required, Plant operators / DSD to inform EPD, WSD and LCSD within 1 hour after the discharge commence.

3.      Plant operators / DSD to instruct the Monitoring Team to commence water monitoring within 24 hours after the emergency discharge event occurs.

4.      Plant operators / DSD to record the effluent flow and effluent quality (i.e. E.coli level, pH value, temperature, salinity, turbidity and dissolved oxygen) during the water monitoring period.

5.      Plant operators / DSD to ensure appropriate remedial measures as stipulated in the contingency / operation plan are implemented.

6.      Monitoring Team to conduct daily marine water monitoring (as discussed in Section 3.2.15) until the baseline water quality levels are restored or 3 days after the emergency discharge is ceased, whichever is the shortest.

7.      The Environmental Consultant shall compare the impact monitoring data with the baseline data to identify the degree of impact caused by the emergency discharge (if any) and to determine when the normal water quality conditions are restored.  The findings shall be provided to EPD, WSD and LCSD.

Case 2/Case 4 - Temporary sewage bypass during construction phase

1.      If temporary sewage bypass is required, Plant operators / DSD to inform EPD, WSD and LCSD at least 4 weeks prior to the discharge.

2.      Environmental Team to conduct daily marine water monitoring (as discussed in Section 3.2.15) until the baseline water quality levels are restored or 3 days after the emergency discharge is ceased, whichever is the shortest.

3.      Plant operators / DSD to record the effluent flow and effluent quality (i.e. E.coli level, pH value, temperature, salinity, turbidity and dissolved oxygen) during the water monitoring period.

4.      The IEC shall compare the impact monitoring data with the baseline data to identify the degree of impact caused by the temporary sewage discharge (if any) and to determine when the normal water quality conditions are restored.  The findings shall be provided to EPD, WSD and LCSD.

Case 3 - Chlorination plant failure during operational phase

1.      Stop the dechlorination plant operation 15 minutes after the chlorination plant failure.

2.      If emergency discharge is required, Plant operators / DSD to inform EPD, WSD and LCSD within 1 hour after the discharge commence.

3.      Plant operators / DSD to investigate the reason of chlorination plant failure and to implement appropriate remedial measures as stipulated in the contingency / operation plan for the HATS.

4.      Plant operators / DSD to instruct the Monitoring Team to commence water monitoring within 24 hours after the emergency discharge event occurs.

5.      Plant operators / DSD to record the effluent flow and effluent quality (i.e. E.coli level, pH value and temperature) during the water monitoring period.

6.      Plant operators / DSD to implement appropriate remedial measures as stipulated in the contingency / operation plan and resume disinfection operation.

7.      Monitoring Team to conduct daily marine water monitoring (as discussed in Section 4.8) until the baseline water quality levels are restored or 3 days after the emergency discharge is ceased, whichever is the shortest.

8.      The Environmental Consultant shall compare the impact monitoring data with the baseline data to identify the degree of impact caused by the emergency discharge (if any) and to determine when the normal water quality conditions are restored.  The findings shall be provided to EPD, WSD and LCSD.

Case 3 - Dechlorination plant failure during operational phase

1.      Stop the chlorination plant operation immediately.

2.      Plant operator / DSD to inform the EPD, WSD and LCSD of the emergency discharge within 1 hour after the chlorination plant operation is stopped.

3.      Plant operators / DSD to investigate the reason of dechlorination plant failure and to implement appropriate remedial measures as stipulated in the contingency / operation plan for the HATS.

4.      Plant operators / DSD to instruct the Monitoring Team to commence water monitoring within 24 hours after the emergency discharge event occurs.

5.      Plant operators / DSD to record the effluent flow and effluent quality (i.e. E.coli level, pH value, and temperature) recorded during the water monitoring period.

6.      Plant operators / DSD to implement appropriate remedial measures as stipulated in the contingency / operation plan and resume disinfection operation.

7.      Monitoring Team to conduct daily marine water monitoring (as discussed in Section 4.8) until the baseline water quality levels are restored or 3 days after the emergency discharge is ceased, whichever is the shortest.

8.      The Environmental Consultant shall compare the impact monitoring data with the baseline data to identify the degree of impact caused by the emergency discharge (if any) and to determine when the normal water quality conditions are restored.  The findings shall be provided to EPD, WSD and LCSD.

4.67           The impact monitoring data shall be compared with the baseline data and relevant water quality objectives to identify the degree of impact caused by the temporary sewage bypass or emergency discharge.  For each emergency discharge event during operational phase, a Water Quality Monitoring Report shall be submitted by the Environmental Consultant to EPD within 10 days after the laboratory testing result for the last sample collected during the monitoring period is available.  Similarly, for the planned temporary sewage bypass event during construction phase, a Water Quality Monitoring Report shall be submitted by the IEC to EPD within 10 days after the laboratory testing result for the last sample collected during the monitoring period is available. The findings of the water quality monitoring results including data presentation, statistical analysis, discussion, conclusion and recommendation shall be provided in the Water Quality Monitoring Report.  The detailed reporting requirements shall be agreed with DSD and EPD.

Monitoring Equipment

Dissolved Oxygen and Temperature Measuring Equipment

4.68           The instrument shall be a portable and weatherproof DO measuring instrument complete with cable and sensor, and use a DC power source.  The equipment shall be capable of measuring:

·         a DO level in the range of 0 ‑ 20 mg L-1 and 0 ‑ 200% saturation; and

·         a temperature of 0 ‑ 45 degree Celsius.

4.69           It shall have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables shall be available for replacement where necessary. (For example, YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

4.70           Shall salinity compensation not be built-in to the DO equipment, in-situ salinity shall be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

4.71           Turbidity shall be measured in situ by the nephelometric method. The instrument shall be portable and weatherproof turbidity measuring instrument using a DC power source complete with cable, sensor and comprehensive operation manuals.  It shall have a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU. The cable shall not be less than 25m in length. The meter shall be calibrated in order to establish the relationship between NTU units and the levels of suspended solids.

Sampler

4.72           A water sampler is required.  It shall comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends.  The sampler shall have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).

Water Depth Detector

4.73           A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station.  This unit can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.

Salinity

4.74           A portable salinometer capable of measuring salinity in the range of 0 - 40 parts per thousand (ppt) shall be provided for measuring salinity of the water at each monitoring location.

pH

4.75           The instrument shall consist of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device. It shall be readable to 0.1pH in a range of 0 to 14. Standard buffer solutions of at least pH 7 and pH 10 shall be used for calibration of the instrument before and after use. Details of the method shall comply with APHA, 19th ed. 4500-HTB.

Monitoring Position Equipment

4.76           A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication or other equipment instrument of similar accuracy, shall be provided and used during marine water monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

Calibration of In-Situ Instruments

4.77           All in situ monitoring instruments shall be checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes shall be checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter shall be carried out before measurement.

4.78           Sufficient stocks of spare parts shall be maintained for replacements when necessary.  Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

Sample Containers and Storage

4.79           Water samples shall be stored and preserved in suitable containers according to the Standard Methods, APHA, and packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed within 24 hours after collection.  Sufficient volume of samples shall be collected to achieve the required detection limit.

Site Record

4.80           Other relevant data shall also be recorded, including monitoring location / position, time, water depth, pH value, salinity, temperature, turbidity, dissolved oxygen, tidal stages, weather conditions and any special phenomena or work underway nearby which may induce water quality impact on the sensitive receivers. A sample data record sheet based on the one presented in the EM&A Guidelines for Development Projects in Hong Kong, is shown in Appendix B.  The Monitoring Team Leader may modify the data record sheet for this EM&A programme, the format of which should be approved by the Environmental Consultant.

Laboratory Measurement / Analysis

Laboratory Measurement / Analysis

4.81           Analysis of marine water quality and effluent quality as listed in Table 4.6 shall be carried out in a HOKLAS or other international accredited laboratory.  The analysis shall commence within 24 hours after collection of the effluent samples.   Detailed testing methods, pre-treatment procedures, instrument use, Quality Assurance/Quality Control (QA/QC) details (such as blank, spike recovery, number of duplicate samples per batch, etc.), detection limits and accuracy shall be submitted to the Environmental Consultant for approval prior to the commencement of monitoring programme.  If in-house or non-standard methods are proposed, details of the method verification shall be required to submit to Environmental Consultant.  In any circumstance, the sample testing shall have comprehensive quality assurance and quality control programmes.  The laboratory shall prepare to demonstrate the programmes to Environmental Consultant or his representatives when requested.

 

Table 4.6          Suggested Analytical Methods and Detection Limit

Determinant

Suggested Method

Suggested Detection Limit

Total residual chlorine

APHA 4500CL: G

5 mg/L *

Bromoform

Tri-

halomethanes (THMs)

USEPA 8260 (Purge & Trap GCMS)

0.1 mg/L *

Bromodichloromethane

0.1 mg/L *

Chloroform

0.1 mg/L *

Dibromochloromethane

5 mg/L

Bromoacetic acid

Halo-acetic Acids (HAAs)

APHA 6251

2 mg/L

Chloroacetic acid

2 mg/L

Dibromoacetic acid

2 mg/L

Dichloroacetic acid

2 mg/L

Trichloroacetic acid

2 mg/L

Arsenic

USEPA 200.7

1 mg/L

Chromium III

USEPA 200.7

1 mg/L

Copper

USEPA 200.7

1 mg/L

Mercury

USEPA 200.7

0.1 mg/L *

Nickel

USEPA 200.7

1 mg/L

Zinc

USEPA 200.7

1 mg/L

Sulphide

APHA 20e 4500-S2-

10 mg/L

Total Surfactants

Surfactants – Anionic (MBAS)

APHA 5540 C

0.5 mg/L

Surfactants – Non-Ionic

APHA 5540 B & D

0.5 mg/L

Phenol

APHA 5530 B & D

0.2 mg/L

Cyanide

APHA 4500 CN-M

0.1 mg/L

Suspended Solids

APHA 17ed 2540D

1 mg/L

5-day Biochemical Oxygen Demand

APHA 19ed 5210B

1 mg/L

Ammonia Nitrogen

APHA 19ed 4500-NH3 F

0.02 mg/L

Unionized Ammonia

By calculation

0.001 mg/L

Total Kjeldahl Nitrogen

APHA 19ed 4500-Norg

0.01 mg/L

Nitrite-nitrogen

APHA 19ed 4500-NO2- B

0.01 mg/L

Nitrate-nitrogen

APHA 19ed 4500-NO3- E

0.02 mg/L

E. coli

EPD HKSAR, Wat. Sci. Tech. Vol.35, No. 11-12, pp 409-413

1 CFU per 100 ml

Orthophosphorus

APHA 19ed 4500- P.E

0.01 mg/L

Total Phosphorus

APHA 19ed 4500-P.B.E

0.01 mg/L

l             The suggested detection limit was in light of the concentration of interest (COI) for human health and/or ecological resources, which was based on local/international authority approved standard.   Determinant at concentration below COI is not expected to induce concern to human health and ecological resources. 

Construction Site Audits

4.82           Regular site audits shall be conducted to confirm that the recommended mitigation measures are properly undertaken during construction phase of the Project. It can also provide an effective control of any malpractices and therefore achieve continual improvement of environmental performance on site.

4.83           Site audits shall include site inspections and compliance audits.

Site Inspections

4.84           Site inspections shall be carried out by the ET on the mitigation measures recommended for water pollution control in the implementation schedule as attached in Appendix A. In the event that the recommended mitigation measures are not fully or properly implemented, deficiency shall be recorded and reported to the ER and IEC. Suitable follow up actions are to be carried out to:

·         Record the problems and investigate the causes;

·         Issue action notes to the Contractor who is responsible for the works;

·         Implement remedial and corrective actions immediately;

·         Re-inspect the site conditions upon completion of the remedial and corrective actions; and

·         Record the event and discuss with the Contractor for preventive actions.

Compliance Audits

4.85           Compliance audits are to be undertaken by ET in accordance with the discharge license issued by EPD prior to the discharge of effluent from the Project site. Monitoring of the treated effluent quality from the Works Areas is required during the construction phase of the Project, and should be carried out in accordance with the WPCO license which is under the ambit of regional office (RO) of EPD.  In case of non-compliance, suitable actions by the relevant parties should be undertaken to:

·         Notify the ER and IEC of the non-compliance;

·         Identify the sources of pollution;

·         Check the implementation status of the recommended mitigation measures;

·         Investigate the operating conditions of the on-site treatment systems;

·         Implement corrective and remedial actions to improve the effluent quality;

·         Increase monitoring frequency until the effluent quality is in compliance with the discharge licence requirements; and

·         Record the non-compliance and propose preventive measures.

Mitigation Measures

4.86           Mitigation measures for water quality control have been recommended in the EIA Report and are listed in the implementation schedule given in Appendix A.  

 



[1] Including Whole Effluent Toxicity Test (WETT) to be conducted during operation phase of the Project.