10                 CONCLUSION

Introduction

10.1            This EIA study has provided an assessment of the potential environmental impacts associated with the construction and operation phases of the proposed TM54SPS.  The environmental issues below have been assessed in the EIA Study, in accordance with the EIA Study Brief (No. ESB-157/2006) registered under the EIAO for the Project:

 

           Air Quality Impact

           Noise Impact

           Water Quality Impact

           Waste Management Implications

           Landscape and Visual Impact

           Cultural Heritage Impact

 

10.2            Specific mitigation measures necessary for avoiding or reducing impacts from the Project to acceptable levels, as well as environmental monitoring and auditing procedures to ensure full implementation of all mitigation measures and compliance with relevant standards and guidelines, have been developed during the detailed assessments.  The Implementation Schedules listing the recommended mitigation measures are presented in Section 11.  The environmental outcomes and principal findings of this EIA Report are summarized below.   

 

Environmental Outcomes

10.3            The major sensitive areas within the study area include residential buildings and educational institutions.  With the implementation of the proposed mitigation measures, no adverse environmental impacts would be expected at the air, noise and water quality sensitive receivers within the study area during both construction and operational phases.  A summary of the key environmental outcomes arising from the EIA study and benefits of the environmental protection measures recommended are presented in Table 10.1 below.

 

Table 10.1    Summary of Key Environmental Outcomes/Benefits

 

Issue

Environmental Outcomes/Benefits

 

The Project

Requirements:

·       Construction of a new sewage pumping station at Site 4A of the Tuen Mun Area 54, with a capacity of about 90,000m3/day.

 

Benefits:   

·       TM54SPS is to convey sewage from the proposed development in Area 54, the four recognized villages within Area 54 namely Tsz Tin Tsuen, Po Tong Ha, Kei Lun Wai and Siu Hang Tsuen and the proposed Tuen Mun North Sewage Pumping Station in Area 52 to the existing trunk sewer at Ming Kum Road.

 

Alternatives

The sewage pumping station was moved to Site 4A which was a relatively low point within the sewerage basin area.  This enables the connection of gravity feed sewers from the proposed development in Tuen Mun Area 54 and the existing villages.  During the public consultation, three alternative locations are aligned adjacent to the future Road L54B.  All the 3 locations are feasible and acceptable for accommodating the TM54SPS in view of engineering aspects.  However, the preferred location is more favorable when summing up the grave public concern.

 

In view of environmental aspects, all 3 locations are considered to be similar in environmental impacts associated with the construction and operation of the TM54SPS.

 

Construction Air Quality Impact

Impact/Problem

·       Potential air quality impacts are dust nuisance.

Environmental benefits of environmental protection measures recommended & Environmentally sensitive areas protected :

·       Mitigation measures: implement the Air Pollution Control (Construction Dust) Regulation and good site practices.

·       No adverse air quality impacts are anticipated at nearby existing ASRs at Unicorn Garden, Kei Lun Wai and Siu Hang Tsuen.

 

Operational Air Quality Impact

Impact/Problem

·       Potential odour impacts from wet wells and screen chambers of TM54SPS are anticipated at the existing and future ASRs.

Environmental benefits of environmental protection measures recommended & Environmentally sensitive areas protected :

·       Mitigation measures: installation of a deodourization unit with 90% odour removal efficiency. 

·       No adverse odour impacts are anticipated at the nearby existing ASRs (Unicorn Garden, Kei Lun Wai and Siu Hang Tsuen) and future ASRs (planned educational institutions at Site 4A).  The estimated population of existing residents within 500 m of the study area to be benefited from proposed mitigation measures would be about 54,000.

 

Construction Noise Impact

Impact/Problem

·       Unmitigated construction noise levels due to the Project: 63 dB(A) to 80 dB(A).

·       Mitigated construction noise levels due to the Project: 56 dB(A) to 69 dB(A).

·       Taking into account of concurrent project, cumulative construction noise levels would be 67 dB(A) to 70 dB(A). 

Environmental benefits of environmental protection measures recommended & Environmentally sensitive areas protected :

·       Recommended mitigation measures: adopting quiet construction plant and implementing good site practices for the Project.

·       With the implementation of mitigation measures for the Project, the nearest existing NSRs at Unicorn Garden, Kei Lun Wai and Siu Hang Tsuen would be protected to comply with the daytime construction noise standard as set out in the EIAO-TM. 

Operational Noise Impact

Impact/Problem/Environmental benefit of proper design

·       No adverse operational noise impacts are expected at the existing and future NSRs with the installation of acoustic silencers at the exhaust fan of deodorizing unit and louvers of the pump house, enclosed reinforced concrete structure design for transformer, pump sets and mechanically raked screens.  The estimated population of existing residents within 300m of the study area to be benefited from proper design of SPS would be about 23,000.

 

Construction Water Quality Impact

Impact/Problem

·       General construction activities associated with the construction of the Project could lead to site runoff.

Environmental benefits of environmental protection measures recommended:

·       All of the recommended mitigation measures are implemented and all construction site / work area discharges comply with the TM-DSS standards.

·       No unacceptable residual water quality impacts are expected during the construction of TM54SPS.

 

Operational Water Quality Impact

Impact/Problem

·       Emergency sewage overflow due to the events of pump failure and power supply failure.

Environmental benefits of environmental protection measures recommended:

·       Mitigation measures: regular check and maintain plant equipment, provision of a stand-by pump and backup power supply.

·       With the incorporation of various precautionary measures, minimal residual operational water quality impact would be expected.

 

Waste Management Implications

Impact/Problem

·       Wastes generated by construction activities: general refuse from the workforce, chemical waste from plant and equipment maintenance, C&D material from excavation works, and screenings

Environmental benefits of environmental protection measures recommended:

·       Surplus material would require disposal to a public fill reception facility for other beneficial uses.

·       C&D material with suitable characteristics should be reused on-site as far as practicable.

·       With the implementation of the recommended mitigation measures and practices for the handling, transportation and disposal of the identified waste arisings, no adverse environmental impacts are expected.

 

Landscape and Visual Impact

Impact/Problem & Environmentally friendly designs recommended

·       After the implementation of mitigation measure both LR1 and LCA1 Landscape Impact will be lessen as sight as additional tree will be planted along the boundary of TM54SPS for screening and possible loss of greenery.

·       All residual adverse landscape impacts in the operational phase of Day 1 will be of insubstantial significance. After all landscape mitigation measures are implemented and have matured over 10 years, there would be no residual adverse landscape impacts of any significance in Year 10.

·       Residual impact on residents in existing villages of Union Garden and Kei Lun Wai (V1) will be still moderate after mitigation measure as the proposed buffer planting is still under constructional stage will be achieve potential screening effect.

·       Residents in existing high rise residential development of Siu Hong Court (R4) and Users in planned institutional development (3 nos. primary schools and 3 nos. Secondary schools) at Site 4A (GIC1) will have intermittent and distant views to the proposed SPS both residual impact is slight.

·       After the proposed mitigation measures have been implemented, the proposed tree planting would carry out ultimate screening, all residual adverse visual impacts in the operational phase will be of insubstantial significance.

 

Cultural Heritage Impact

Impact/Problem

·       Since the site of the proposed TM54SPS falls within Kei Lun Wai archaeological sites, construction of the proposed TM54SPS would likely have direct impacts on the archaeological resources within the archaeological site. It is recommended that Site 4A of Tuen Mun Area 54 be added to the programme of archaeological survey and rescue excavation to be undertaken by the Antiquities and Monuments Office (AMO) of LCSD for the proposed development at Tuen Mun Area 54 prior to the commencement of construction works.  As the archaeological survey cannot be conducted in this EIA stage due to land access constraint, the proposed works area for the TM54SPS which is located within Site 4A would be assessed in the future archaeological survey and rescue excavation.

·       Since there are no built heritage resources within the study area, impact on built heritage resources is not expected.

 

 

Air Quality Impact

10.4            With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation, dust nuisance at ASRs would not be expected. An EM&A programme is recommended for the construction phase to ensure that the dust criteria would be satisfied at the ASRs.

 

10.5            No potential odour impact would be expected at nearby ASRs during operation of TM54SPS with the installation of a deodourization unit.  Odour monitoring is proposed during the operational phase to ensure the compliance of odour criteria at the ASRs. 

 

Noise Impact

10.6            The potential noise impact arising from construction of TM54SPS on the nearest representative NSRs was assessed. Results indicated that noise exceedance was predicted at the NSRs N1 and N2 during some construction activities.  With the adoption of quiet PME during these construction activities, the predicted construction noise levels at NSRs N1 and N2 would all comply with the relevant noise criteria.  Good site practices were also proposed to further abate the impacts on the NSRs.  Two other projects (Site formation and infrastructural works for Site 2 under the project “Formation, Roads and Drains in Tuen Mun Area 54 – Phase 1 and 2, Private and Public Rental Housing Development in Tuen Mun Area 54”; and (ii) Village sewerage works under the project “Sewerage Upgrading Works in Tune Mun (Agreement No. CE 38/2006 (DS))” would be undertaken within 300 of the study area.  Referring to the programme, the village sewerage works at Kei Lun Wai and Unicorn Garden will be scheduled with the consideration of the construction of TM54 SPS to prevent overlapping with the construction of TM54SPS, therefore, it only considered the cumulative construction noise impacts from site formation and infrastructural works for Site 2 in the assessment.  Results indicated that all representative NSRs would still comply with construction noise criteria taking into account of the cumulative noise impacts from other concurrent project.  

 

10.7            The noise impacts associated with the operation of the Project were also assessed. As the pump sets, mechanically raked screens and transformer would be housed in reinforced concrete structures with soundproof doors, and silencer would be provided for louvers of the pump house and exhaust fan of the deodorization unit, the operation noise levels at representative NSRs would comply with the daytime, evening time and night time noise criteria.  No mitigation measures were proposed.   

 

Water Quality Impact

10.8            The key issue in terms of water quality during the construction phase of the Project would be the potential for release of sediment-laden run-off from the works areas.  Minimisation of water quality deterioration could be achieved through implementing adequate mitigation measures such as control measures on site run-off and drainage from the works areas to minimise construction site run-off.  Proper site management and good housekeeping practices would also be required to ensure that construction wastes and other construction-related materials would not enter the Tsing Lun Nullah.  Sewage effluent arising from the construction workforce would also be handled through provision of portable toilets.  With the implementation of these recommended mitigation measures, the construction works for the Project would not be expected to result in unacceptable impacts on water quality.  Site inspections should be undertaken routinely to inspect the works areas in order to ensure the recommended mitigation measures are properly implemented.

 

10.9            In view of the potential adverse effect of emergency sewage bypass on the quality of the receiving waters, various precautionary measures are proposed to be incorporated in the design of TM54SPS to avoid emergency bypass of sewage to the maximum practicable extent. With the incorporation of these precautionary measures, the possibility of emergency sewage bypass would be extremely remote. 

 

Waste Management Implications

10.10        Waste types generated by the construction activities are likely to include C&D material from excavation works, general refuse from the workforce, and chemical waste from the maintenance of construction plant and equipment.  Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, adverse environmental impacts are not expected during the construction phase.

 

10.11        The only waste generated during operation of TM54SPS would be screenings removed from the mechanical screens in the inlet chamber.  The small quantity of screenings will require disposal to the designated landfill site.

 

Landscape and Visual Impact

10.12        There are no tree would be affected within the site boundary.

 

10.13        The landscape resources of LR1 and landscape character area of LCA2 will be moderate impact by the construction of an incongruous building mass, temporary works areas, additional construction traffic, storage of construction material and general loss of farmland plantation. After the implementation of mitigation measure both LR1 and LCA2 landscape Impact will be lessen as sight as additional tree will be planted along the boundary of the proposed pumping station for screening and possible loss of greenery.

 

10.14        Residents in existing villages of Union Garden and Kei Lun Wai (V1) will have moderate adverse residual impact during construction due to the close distant views to the proposed TM54SPS. The residual visual impact will be slight after implementation of mitigation measures during operation. The proposed TM54SPS will appear impact on the front row/ close distance/ high level building. As R1, R2, R3 building mass and T1 infrastructure will be dominated in entire area of operation stage. The landscape and visual mitigation measures will be implemented with screening on boundary and roof greening to mitigate both impacts on at grade or elevated level. Therefore the proposed Project is expected to be compatible with the rest of new development.

 

10.15        After the proposed mitigation measures have been implemented, the proposed heavy standard sized tree planting will carry out ultimate screening, all residual adverse landscape and visual impacts in operational phase will be of insubstantial significance. Except on VSRs V1, GIC1 and O1 will have slight adverse visual impact which will be lessen as insubstantial after 10 years of implementation of mitigation measures.

 

Cultural Heritage Impact

10.16        As the site of the proposed TM54SPS falls within the boundary of the Kei Lun Wai Archaeological Site, construction of the proposed TM54SPS would likely have direct impact on the archaeological resources within the archaeological site.  It is recommended that Site 4A of Tuen Mun Area 54 be added to the programme of archaeological survey and rescue excavation to be undertaken by the AMO of LCSD for the proposed development at Tuen Mun Area 54 prior to the commencement of construction works.  As the archaeological survey cannot be conducted in this EIA stage due to land access constraint, the proposed works area for TM54SPS which is located within Site 4A would therefore be assessed in the future archaeological survey and rescue excavation.

 

10.17        Since there are no built heritage resources within the study area, impact on built heritage resources is not expected.

 

Overall Conclusion

10.18        The findings of this EIA Study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation phases of the Project.  The EIA has, where appropriate, identified mitigation measures to ensure compliance with environmental legislation and standards.

 

10.19        Overall, the EIA Study for TM54SPS has predicted that the Project, with the implementation of the proposed mitigation measures for construction and operation phases, would comply with all applicable environmental standards and legislation.  This EIA has also demonstrated the acceptability of the residual impacts from the Project and the protection of the population and environmentally sensitive resources.  Environmental monitoring and audit mechanisms have been recommended, where necessary, to verify the accuracy of the EIA predictions and the effectiveness of recommended mitigation measures.