1                     INTRODUCTION

Background of the Project

 

1.1               According to the Territorial Development Strategy Review in 1996, the housing supply capacity of approved plans and programmes would not be adequate to meet the estimated housing demand after 2001. In response to the estimated shortfall in flat supply, the Government identified a list of areas, including Tuen Mun Area 54, having potential for housing development.

 

1.2               The New Territories West Development Office (NTWDevO) of Territory Development Department (TDD) completed the “Planning and Development Study of Potential Housing Site in Area 54, Tuen Mun” (the Study) in 1999 under Agreement No. CE21/97. The Study put forward proposals on housing types, development parameters and planning layouts and assessed the development impacts on transport network, infrastructural capacities and environmental quality.

 

1.3               In order to convey the sewage collected from Tuen Mun Area 54 to the existing sewers at Ming Kum Road, a new sewage pumping station, close to Tsz Tin Road, will be constructed and operated, with a capacity of about 90,000 m3 per day.  The design average dry weather flow is about 0.32 m3/s.

 

1.4               The proposed sewage pumping station is classified as a Designated Project under Schedule 2, Part I, F3(b) of the Environmental Impact Assessment Ordinance (EIAO), i.e. a sewage pumping station with an installed capacity of more than 2000 m3 per day and a boundary of which is less than 150 m from an existing or planned residential area. An Environmental Impact Assessment (EIA) study is thus required for the proposed Tuen Mun Area 54 sewage pumping station (hereafter referred to as “the Project”).

 

The Assignment

 

1.5               Maunsell Consultants Asia Limited (MCAL) was commissioned by the Government of the Hong Kong Special Administrative Region, represented by the Director of Civil Engineering and Development (DCED), on 19 December 2006 to undertake the “Environmental Impact Assessment for the Tuen Mun Area 54 Sewage Pumping Station” under Additional Services No. 2 of Agreement No. CE21/2005(CE) (hereafter referred to as “the Assignment”).

 

1.6               Under this Assignment, MCAL will carry out the Environmental Impact Assessment for the Tuen Mun Area 54 Sewage Pumping Station so as to establish the environmental constraints of the proposed works and to identify appropriate measures to overcome the constraints.  The location of the proposed sewage pumping station is shown in Figure 1.1.

 

Objectives of the Assignment

 

1.7               The main objective of the Assignment is to satisfactorily complete the EIA Study for the Project as required by the Brief in accordance with the EIAO.  The EIA Report will be prepared so as to:

 

(i)             to describe the Project and associated works together with the requirements for carrying out the Project;

 

(ii)           to identify and describe the elements of the community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including both the natural and man-made environment;

 

(iii)          to present the considerations of alternatives to avoid and minimise the potential adverse environmental impacts on the sensitive uses; to compare the environmental benefits and dis-benefits of the options; to provide reasons for selecting the preferred option(s) and to describe the part of environmental factors played in the selection;

 

(iv)          to identify and quantify emission sources, to determine the significance of impacts on sensitive receivers and potential affected uses and to propose measures to mitigate these impacts;

 

(v)            to identify and quantify any potential impacts from point and non-point pollution sources on the identified water systems and sensitive receivers and to propose measures to mitigate these impacts;

 

(vi)          to identify any potential landscape and visual impacts and to propose measures to mitigate these impacts;

 

(vii)         to identify any potential impacts on any archaeological resources and to propose measures to mitigate these impacts;

 

(viii)       to propose the provision of mitigation measures to minimise pollution, environmental disturbance and nuisance during construction and operation of the Project;

 

(ix)         to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;

 

(x)           to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;

 

(xi)         to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;

 

(xii)        to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification; and

 

(xiii)      to design and specify the environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.

 

Assessment Area

 

1.8               The Assessment Area for the EIA Study, as specified in the EIA Study Brief (Ref. No. ESB-157/2006) issued by EPD on 21 November 2006, is presented below:

 

(i)             Air quality impact assessment – area within a distance of 500m from the boundary of the Project site.

 

(ii)           Noise impact assessment – areas within 300m from the Project boundary.   Subject to EPD agreement, the assessment area would be reduced accordingly if the first layer of noise sensitive receivers provides acoustic shielding to those receivers located further away.

 

(iii)          Water quality impact assessment – cover an area within 300m of the Project site boundary and all relevant water sensitive receivers downstream of emergency sewage discharge location at the Tuen Mun River Channel and Castle Peak Bay, including the typhoon shelter and bathing beaches. 

 

(iv)          Waste management implications – cover an area within the Project site boundary.

 

(v)            Landscape and visual impact assessment – the assessment area for landscape impact assessment will include areas within a 500m distance from the site boundary of the work areas while the assessment area for the visual impact assessment will be defined by the visual envelope of the Project.

(vi)          Cultural heritage assessment – cover an area within the Project site boundary.

 

Structure of the Report

 

1.9               The structure of the EIA Report is set out below:

 

              Section 2 provides a description of the Project and its need.

              Section 3 identifies and assesses the potential air quality impacts associated with the construction and operation of the Project.

              Section 4 identifies and assesses the potential noise impacts associated with the construction and operation of the Project.

              Section 5 identifies and assesses the potential water quality impacts associated with the construction and operation of the Project.

              Section 6 identifies and assesses the potential waste management implications associated with the construction and operation of the Project.

              Section 7 presents the landscape and visual impact assessment of the construction and operation of the Project.

              Section 8 presents the potential impact on any archaeological site during construction of the Project.

              Section 9 outlines the environmental monitoring and audit (EM&A) requirements for the Project.  The scope and methodology are presented in detail in a stand-alone EM&A Manual.

              Section 10 summarises and concludes the findings of the EIA Study.

              Section 11 presents the Implementation Schedules for mitigation of the various environmental issues addressed in the EIA Study.