3.1 In this section, the requirements, methodology, equipment, monitoring locations, criteria and protocols for the monitoring and audit of noise impacts during the construction phase of the Project are presented. Noise levels shall be monitored to evaluate the construction noise impact during the construction phase. The EIA findings confirmed that proper designs of TM54SPS would control the potential noise impacts at noise sensitive receivers within acceptable levels, thus operational phase noise monitoring will not be required.
3.2 The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria.
3.3 Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference. A sample data record sheet based on the one presented in the EM&A Guidelines for Development Projects in Hong Kong, is shown in Appendix B. The ET Leader may modify the data record sheet for this EM&A programme, of which the format should be agreed by the ER and the IEC.
3.4 As referred to in the Technical Memorandum (TM) issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement, the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements shall be accepted as valid only if the calibration levels before and after the noise measurement agree to within 1.0 dB.
3.5 Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m s-1 or wind with gusts exceeding 10 m s-1. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m s-1.
3.6 The ET is responsible for providing sufficient and suitable noise measuring equipment and associated instrumentation for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. All the equipment and associated instrumentation shall be clearly labelled.
3.7
The EIA Report indicated that unmitigated
construction activities would cause noise exceedance at
Table 3.1 Noise
Monitoring Stations during Construction Phase
Identification No. |
Noise Monitoring Location |
N1 |
|
N2 |
Kei
Lun Wei |
3.8 When alternative monitoring locations are proposed, the monitoring locations shall be chosen based on the following criteria:
·
Monitoring at sensitive receivers close to the major site activities
which are likely to have noise impacts;
·
Monitoring at the noise sensitive receivers as defined in
the Technical Memorandum; and
·
Assurance of minimal disturbance to the occupants during
monitoring.
3.9
The monitoring station shall
normally be at a point
3.10 The ET shall carry out baseline noise monitoring prior to the commencement of the construction works. The baseline monitoring shall be carried out daily for a period of at least two weeks. Before commencing the baseline monitoring, the ET shall develop and submit to the IEC the baseline monitoring programme such that the IEC can conduct on-site audit to ensure accuracy of the baseline monitoring results.
3.11 In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall liaise with the ER, EPD and IEC to agree on an appropriate set of data to be used as a baseline reference and submit to the ER and IEC for agreement and EPD for approval.
3.12 Noise monitoring shall be carried out at the designated monitoring station. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency on a weekly basis when noise generating activities are underway:
·
one set of measurement between 0700 and 1900
hours on normal weekdays.
3.13 If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.
3.14 In case of non-compliance with the construction noise criteria, more frequent monitoring, as specified in the Action Plan in Table 3.3, shall be carried out. This additional monitoring shall be continued until the recorded noise levels are rectified or demonstrated to be unrelated to the construction activities.
3.15 The Action and Limit levels for construction noise are defined in Table 3.2. Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan in Table 3.3 shall be implemented.
Table 3.2 Action
and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900 hours on normal weekdays |
When one documented complaint is
received |
75 dB(A) |
3.16 The EIA report indicated that construction activities at TM54SPS would cause noise exceedance at some existing NSRs in the vicinity of the site . Therefore, appropriate mitigation measures and good site practices are recommended to be properly implemented. The mitigation measures recommended in the EIA report are summarised below:
·
Adoption of quiet plant for following construction
activities/scenarios:
- Site clearance;
- Bulk excavation for sub-structure and site
formation;
- Steel fixing concreting of sub-structure;
- Steel fixing and concreting of roof and columns
- Brick Works & Finishing, M&E
Installation & Pipeworks, Landscape Works & Roadworks;
·
Implementation of the following good site practices:
- only well-maintained plant shall be
operated on-site and plant shall be serviced regularly during the construction
program;
- silencers or mufflers on construction
equipment shall be utilised and shall be properly maintained during the
construction program;
- mobile plant, if any, shall be sited as far
away from NSRs as possible;
- machines and plant (such as trucks) that
may be in intermittent use shall be shut down between work periods or throttled
down to a minimum;
- plant known to emit noise strongly in one
direction shall, wherever possible, be orientated so that the noise is directed
away from the nearby NSRs; and
- material stockpiles and other structures shall
be effectively utilised, wherever practicable, in screening noise from on-site
construction activities.
3.17 The implementation schedule for the recommended mitigation measures is presented in Appendix A.
3.18
Based on the design information,
the transformer will be housed in enclosed
3.19 The implementation schedule for the recommended mitigation measures is presented in Appendix A.
Table
3.3 Event/Action
Plan for Construction Noise
EVENT |
ACTION |
|||
|
ET |
IEC |
ER |
CONTRACTOR |
Action Level being
exceeded |
1.
Notify ER, IEC and Contractor; 2.
Carry out investigation; 3.
Report the results of investigation to the IEC, ER and
Contractor; 4.
Discuss with the IEC and Contractor on remedial measures
required; 5.
Increase monitoring frequency to check mitigation
effectiveness. |
1. Review
the investigation results submitted by the ET; 2.
Review the proposed remedial measures by the Contractor
and advise the ER accordingly; 3.
Advise the ER on the effectiveness of the proposed
remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. In
consolidation with the IEC, agree with the Contractor on the remedial
measures to be implemented; 4. Supervise
the implementation of remedial measures. |
1. Submit noise mitigation proposals to ET and
ER; 2. Implement noise mitigation proposals. |
Limit Level being
exceeded |
1.
Inform IEC, ER, Contractor and EPD; 2.
Repeat measurements to confirm findings; 3.
Increase monitoring frequency; 4.
Identify source and investigate the cause of exceedance; 5.
Carry out analysis of Contractor’s working procedures; 6.
Discuss with the IEC, Contractor and ER on remedial
measures required; 7.
Assess effectiveness of Contractor’s remedial actions and
keep IEC, EPD and ER informed of the results; 8.
If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET, and Contractor on the potential
remedial actions; 2.
Review Contractor’s remedial actions whenever necessary to
assure their effectiveness and advise the ER accordingly. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. In
consolidation with the IEC, agree with the Contractor on the remedial
measures to be implemented; 4. Supervise
the implementation of remedial measures; 5. If
exceedance continues, consider stopping the Contractor to continue working on
that portion of work which causes the exceedance until the exceedance is
abated. |
1.
Take immediate action to avoid further exceedance; 2.
Submit proposals for remedial actions to ET and ER within
3 working days of notification; 3.
Implement the agreed proposals; 4.
Submit further proposal if problem still not under
control; 5.
Stop the relevant portion of works as instructed by the ER
until the exceedance is abated. |