7                     landscape and visual impacts assessment

Introduction

7.1               The EIA has recommended landscape and visual mitigation measures to be undertaken during construction and operation phases of the Project.  This Section defines the EM&A requirements to ensure the proposed landscape and visual impact mitigation measures are effectively implemented.

Baseline Monitoring

7.2               A register landscape architect (RLA) (as a member of the ET) shall be responsible for conducting the baseline review and monitoring the implementation of landscape and visual mitigation measures during construction phase in accordance with the EIA Report.

 

7.3               Baseline changes with respect to the landscape and visual environmental should be carried out in reference to the recorded baseline conditions of the site as described in Section 7 of the EIA.  The monitoring should in particular record changes of each landscape resource, landscape character area and the view conditions of each visually sensitive receiver.  Parameters used to describe changes in each of the above should be the same as in Section 7 of the EIA.

 

7.4               The baseline monitoring should be conducted as a one-off site survey prior to commencement of any construction works in the project boundary.

 

Construction Phase

 

Baseline Review

 

7.5               A baseline review shall be undertaken at the commencement of the construction contracts.  The purpose of the review is:

·         to check the status of the landscape resources within, and immediately adjacent to, the construction sites and works areas;

·         to determine whether any change has occurred to the status of the landscape resources since the EIA;

·         to determine whether amendments in the design of the landscape and visual mitigation measures are required for those changes; and

·         to recommend any necessary amendments to the design of the landscape and visual mitigation measures.

            Design of Landscape and Visual Mitigation Measures

 

7.6               The landscape and visual mitigation measures shall be incorporated to ensure the mitigation effect and achieve the intended aims as described in Tables 7.2 and 7.3. Any changes to the mitigation measures that may be recommended as a result of the Baseline Review or ongoing Monitoring of the Design, Construction and Establishment Works shall be taken into account.

 

            Landscape and Visual Monitoring

 

7.7               All landscape and visual monitoring should carry out on site audit with register landscape architect (RLA) for supervision. The design, implementation and maintenance of landscape and visual mitigation measures shall be checked monthly to ensure that they are fully required. Any potential conflicts between the proposed landscape measures and any other project works or operational requirements shall also be recorded for the Contractor to resolve in early stage, without compromising the intention of the mitigation measures. All sensitive landscape resources is shown in Figure 7.2.1 to 7.2.2 and Figure 7.3.1 to 7.3.2 of the EIA Report, sensitive visual receivers is defined in Figure 7.4.1 to 7.4.4 of the EIA Report

 

Operational Phase

 

            Landscape and Visual Monitoring

 

7.8               All landscape and visual mitigation measures shall be monitored monthly on site during the first year of the Operational Phase to ensure that the effectiveness of the mitigations. All sensitive landscape resources is shown in Figure 7.3.1 and 7.3.2 of the EIA Report and sensitive visual receivers is defined in Figure 7.4.1 to 7.4.4 of the EIA Report

Event and Action Plan

7.9               Should non-compliance of the landscape and visual impacts occur, actions in accordance with the action plan stated in Table 7.1 shall be carried out.

Table 7.1     Event and Action Plan for Landscape and Visual Impact - Construction Phase

Action Level

Environmental Team Leader (ETL)

Independent Environmental Checker (IEC)

Engineer’s Representative (ER) 

Contractor

Non-conformity on one occasion

1.  Identify source

2.  Inform the IEC and the ER

3.  Discuss remedial actions with the IEC, the ER and the Contractor

4.  Monitor remedial action until rectification has been completed

1.    Check report

2.    Check the Contractor’s working method

3.    Discuss with the ER and the Contractor on possible remedial measures

4.    Advise the ER on effectiveness of proposed remedial measures

 

1.    Notify the Contractor

2.    Ensure remedial measures are properly implemented

 

1.   Amend working methods

2.   Rectify damage and undertake remedial measures or any necessary replacement

Repeated Non-conformity

 

 

 

 

 

 

 

 

1.  Identify source

2.  Inform the IEC and the ER

3.  Increase monitoring (site audit) frequency

4.  Discuss remedial actions with the IEC, the ER and the Contractor

5.  Monitor remedial actions until rectification has been completed

6.  If exceedance stops, cease additional monitoring (site audit)

1.   Check report

2.   Check the Contractor’s working method

3.   Discuss with the ER and the Contractor on possible remedial measures

4.   Advise the ER on effectiveness of proposed remedial measures

5.   Supervise implementation of remedial measures

1.   Notify the Contractor

2.   Ensure remedial measures are properly implemented

1.   Amend working methods

2.   Rectify damage and undertake remedial measures or any necessary replacement

Mitigation Measures

7.10            Landscape and visual mitigation measures in the construction and operation, together with an indication of Funding, Implementation and Maintenance Agencies are listed in Tables 7.2 and Table 7.3. Approval-in-principle to the implementation, management and maintenance of the proposed mitigation measures sought from the appropriate authorities in accordance with the ETWB TCW No. 3/2006 are also indicated in Table 7.2 and Table 7.3..

 

Table 7.2     Proposed Landscape Mitigation Measures for Construction Phase 

ID No.

Nature / Type

Visual Mitigation Measure

Funding / Implementation 

Management/ Maintenance

CM1

Design / Construction Planning

No-intrusion Zone

To maximize protection to existing trees, woodland, plantation areas and ground vegetation, construction contracts may designate “No-intrusion Zone” to various areas within the site boundary with rigid and durable fencing for each individual no-intrusion zone.

The contractor should closely monitor and restrict the site working staff not to enter the “no-intrusion zone”, even for non-direct construction activities and storage of equipment. 

CEDD

CEDD

CM2

Design / Construction Planning

Hoarding

Hoarding or boundary fencing for construction shall be considered. It should be sensitively designed,  subtle, camouflaged and more ‘permeable’ so that they fit into the existing environment when looking from outside.

CEDD

CEDD

CM3

Site Practice

Minimize disturbance of construction workers

To ensure minimum disturbance to existing village, rustic dwellings and workshops users, construction works may only enter these areas with their helmets and safely vests properly stored or carried in non-transparent bags. They shall also properly and cleanly dress.

The construction contract should require the main contractor to issue guideline to the construction works to minimize disturbance to existing village, rustic dwellings and workshops.  

CEDD

CEDD

CM4

Site Practice

Dust and Erosion Control for Exposed Soil

Excavation works and demolition of existing squatters / workshops which will be highly visible form surrounding areas should be well planned and with precautions to suppress dust.

Exposed soil shall be covered or ‘camouflaged’ and watered often. Areas that are expected to be left with bare soil for a long period of time after excavation shall be properly covered with suitable protective fabric. Silt and erosion shall be controlled by ground barriers around the slope cutting area.

CEDD

CEDD

CM6

Site Practice

Construction Light

All security floodlights for construction sites shall be equipped with adjustable shield, frosted diffusers and reflective covers, and be carefully controlled to minimize light pollution and night-time glare to nearby village.

The Contractor shall consider other security measures which shall minimize the visual impacts.

CEDD

CEDD

CM7

Design / Construction

Re-use of Existing Soil

Existing topsoil shall be re-used where possible for new planting areas within the project.

The construction program shall consider using the soil removed from one phase for backfilling another. Suitable storage ground, gathering ground and mixing ground may be set up on-site as necessary.

CEDD

CEDD

CM8

Site Supervisions/ Establishment Period 

Establishment Period

12 month establishment period for the soft landscape works will be allowed in the main contract. Most construction contracts in Hong Kong require the Contractor to carry out routine horticultural operations, including watering, pruning, weeding, pest control, replacement of dead plants etc. to ensure healthy establishment of new planting during a 12 month establishment period.

This period also serves as a kind of warranty / guarantee on the quality of the plants supplied and installed by the Contractor.  

CEDD

CEDD

 

Table 7.3     Proposed Landscape Mitigation Measures for Operation Phase

ID No.

Nature / Type

Landscape Mitigation Measure

Funding / Implementation 

Management/ Maintenance

OM1

Design / Operation

Re-instatement of excavated Area

All excavated area and disturbed area for utilities diversion, temporary road diversion, and pipeline woks will be reinstated to former conditions, subject to applicable Government Standards.

DSD

DSD

OM2

Design / Operation

Architectural Treatment for the proposed structures

Compatible design, construction materials and surface finishes of the proposed Sewage Pumping Station should be harmony with proposed GIC development within Site 4A. (open space and 6 nos. schools development) so as to achieve visual uniformity.

Finishing materials shall have due consideration to form, basic color, color/tone variation, micro- and macro-texture, and reflectivity/light absorbance to avoid glare. 

CEDD

(Design) /

DSD

(Operation)

DSD

OM3

Design / Operation

Greening for the proposed Sewage Pumping Station

Permeable boundary wall with tree and shrub planting (with 1.2m topsoil depth planting strip) shall be used. The tree planting (21 nos. of trees) should be in heavy standard sized (the stem diameter is exceeding 75mm but not exceeding 150mm measure at a height of 1m from the root collar) to provide early screening effect. Trees with normal standard size (the stem diameter is exceeding 45mm but not exceeding 75mm measure at a height of 1m from the root collar) (14 nos. of trees) and shrub are proposed for buffer planting.  The trees would be one or more of following species: Bauhinia blakeana, Bischofia trifoliate, Cassia surattensis, Callistemon rigidus and Magnolia grandiflora.  The shrubs would be one or more of following species: Codiaeum variegatum, Hibiscus rosa-sinensis, Jasminum sambac, Osmanthus fragrans and Rhododendron pulchrum.  One or more of the following climbers: Bauhinia glauca, Bougainvillea spectabilis, Lonicera japonica, Parthenocissus himalayana, Pyrostegia venusta and Wisteria sinensis, flowers racks or other vertical greening should be installed to soften the monolithic effects of boundary wall.  Green roof with shrub and groundcovers is proposed. 

CEDD

(Design) /

DSD (Operation)

DSD