Table of Contents
7.3 Potential Hazards
Associated with Landfill Gas
7.5 Description and History of
Gin Drinkers Bay Landfill
7.6 Landfill Gas Risk
Assessment
7.7 Proposed Protection and
Precautionary Measures
7.8 Environmental Monitoring
& Audit
List
of Tables
Table
7‑1 Qualitative
Risk Assessment Category
Table
7‑2 Methane
Concentrations at Gin Drinkers Bay Landfill
Table
7‑3 Carbon
Dioxide Concentrations at Gin Drinkers Bay Landfill
Table
7‑4 Qualitative
Risk Assessment
Table
7‑5 Summary
of Required Actions in the Event of Gas Detected
List of Figures
Figure 7-1 Location
of Tsuen Wan Road Relative To Gin Drinkers Bay Landfill
Figure 7-2 Consultation
Zone of Gin Drinkers Bay Landfill and Locations of Landfill Gas Monitoring
Points
Figure 7-3 Diverted
Utility Routes to be Designated as “Special Routes”
Figure 7-4 Details
of Possible Cut-Off Barriers for New Utilities Crossing Consultation Zone
7.1.1
Under Annexes 7 and 19 of the Technical Memorandum of the
Environmental Impact Assessment Ordinance (EIAO-TM), landfill gas (LFG)
hazard assessment is required for any development or re-development within the
Consultation Zone, i.e. the area surrounding the landfill boundary as defined
by a line running parallel to and 250m away from the edge of the waste. The
Project falls within the Consultation Zone (CZ) of Gin Drinker Bay Landfill
(GDBL). Therefore, LFG hazard assessment is required in this EIA Study.
7.1.2
EPD has issued the Landfill Gas Hazard Assessment Guidance Note
(EPD/TR8/97) (the Guidance Note), which provides a risk assessment
framework for developments proposed close to landfill sites. Generally, a
qualitative landfill risk assessment is required to ensure that appropriate
levels of safety design features are incorporated within the development.
7.2.1
This assessment has been undertaken with close reference to the
Guidance Note and in line with Annexes 7 and 19 of the EIAO-TM. The following
tasks have been undertaken:
·
review of background information relating
to the GDBL;
·
identification of the sources, nature and
likely quantities/concentrations of LFG emissions with the potential to affect
the TWR Upgrading works;
·
identification of likely viable pathways
through the ground, underground cavities, utilities or groundwater via which
LFG may reach the TWR Upgrading works;
·
the identification of TWR Upgrading works
that would be sensitive to the effects of the LFG emissions;
·
a qualitative assessment of the degree of
risk that the LFG emissions may pose to the TWR Upgrading works for the
identified source-pathway-target combination; and
·
the proposal of appropriate measures to
minimise landfill gas hazard during construction and operation.
7.2.2
The location of TWR relative to GDBL is indicated in Figure 7-1.
7.3.1
LFG is a flammable, toxic and asphyxiating mixture of methane and
carbon dioxide, often with a trace of volatile compounds. It is a product of
the anaerobic decomposition of solid wastes.
7.3.2
Methane (CH3) is one of the major components of LFG. When
methane is mixed with air within the lower and upper explosive limits (LEL and
UEL, 5 to 15% by volume) in confined spaces and given a source of ignition such
as an electrical spark, an explosion can result. Methane is also asphyxiant,
odourless and colourless and its presence (or absence) can only be confirmed by
using appropriately calibrated detectors.
7.3.3
Carbon dioxide (CO2) is the other major component of LFG.
It is asphyxiating and causes adverse health effects at relatively low
concentrations. The long-term Occupational Exposure Limit (OEL) is 0.5% by
volume. Like methane, in the pure form, it is odourless and colourless and its
presence (or absence) can only be confirmed by using appropriately calibrated
detectors.
7.3.4
The LFG mixture has a density similar to air, although this varies
according to its exact composition. Upward movement of LFG is usually a result
of excess pressure over the ambient rather than buoyancy. Also, bulk gas
movements may be caused by the pumping effect of a rising water table, whereas
subsurface lateral diffusion through semi-porous strata and cracks may occur
due to a concentration gradient.
7.3.5
LFG is capable of migrating away from its source along permeable
pathways such as cracks and fissures in the surrounding rock and other
preferential pathways such as utility routes. It has been known to travel along
these pathways more than 200m away from the source.
7.4.1
The methodology set out in the Guidance Note was adopted in this
assessment. For ease of reference, key points of the Guidance Note are
reproduced in the following sections.
7.4.2
The risk due to LFG may be evaluated based upon the following three
components:
·
Source – the location, nature and likely
quantities/concentrations of LFG generated by GDBL;
·
Pathway - the nature and length of
potential pathways through which LFG could migrate (such as geological
features, utility services and leachate flow); and
·
Target - the level of vulnerability of
the development.
7.4.3
These components and their evaluation criteria are discussed in the
following paragraphs.
7.4.4
The source of LFG (i.e. GDBL) should be evaluated with respect to the
classifications as follows:
·
Minor – Landfill sites at which gas controls have been installed and proven
to be effective by comprehensive monitoring that has demonstrated that no
migration of gas beyond the landfill boundary (or any specific control
measures). The landfill must have measures to control gas that do not rely
solely on an active gas extraction system or any other single control measure
which is vulnerable to failure; or old landfill sites where the maximum
concentration of methane within the waste, as measured at several location
across the landfill and on at least four occasions over a period of at least
six months, is less than 5% by volume (v/v).
·
Medium – Landfill sites at which some forms of gas control have been
installed (e.g. a lined site or one where vents or barriers have been
retrospectively installed), but where there are only limited monitoring data to
demonstrate prevention of off-site gas; or landfill sites where comprehensive
monitoring has demonstrated that there is no migration of gas beyond the
landfill boundary but where the control of gas relies solely on an active gas
extraction system or any other single control system that is vulnerable to
failure.
·
Major – Recently filled landfill sites at which there is little or no
control to prevent migration of gas or at which the efficacy of the gas control
measures has not been assessed; or any landfills site at which monitoring has
demonstrated that there is significant migration of gas beyond the site
boundary.
7.4.5
The broad classification of the pathway is as follows:
·
Very Short/Direct
– Path length of less than 50m for unsaturated permeable strata and fissured
rock or less than 100 m for anthropogenic conduits.
·
Moderately Short/Direct
– Path length of 50 to 100m for unsaturated permeable soil or fissured rock or
100 to 250m for anthropogenic conduits.
·
Long/Indirect
– Path length of 100 to 250m for unsaturated permeable soils and fissured rock.
7.4.6
Target may be classified according to the following evaluation
criteria:
·
High Sensitivity
– Buildings and structures with ground level or below ground rooms/voids or
into which services enter directly from the ground and to which members of the
general public have unrestricted access or that contain sources of ignition.
This would include developments where there is a possibility of additional
structures being erected directly on the ground on an ad hoc basis and without
regard to the potential risks.
·
Medium Sensitivity
– Other buildings, structures or service voids where there is access only by
authorised, well trained personnel, such as the staff of utility companies, who
have been briefed on the potential hazards relating to LFG and the specific
safety procedures to be followed; and deep excavations.
·
Low Sensitivity
– Buildings/structures that are less prone to gas ingress by virtue of their
design (such as those with a raised floor slab), shallow excavations or
developments that involve essentially outdoor activities but where evolution of
gas could pose potential problems.
7.4.7
Once the status of each of the source, pathway and target have been
evaluated against the above criteria, a qualitative assessment of the overall
risk may be made with reference to Table
7-1.
Table 7‑1 Qualitative
Risk Assessment Category
Source |
Pathway |
Target Sensitivity |
Risk Category |
Major |
Very Short / Direct |
High |
Very High |
Medium |
High |
||
Low |
Medium |
||
Moderately Short / Direct |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Long / Indirect |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Medium |
Very Short / Direct |
High |
High |
Medium |
Medium |
||
Low |
Low |
||
Moderately Short / Direct |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Long / Indirect |
High |
Medium |
|
Medium |
Low |
||
Low |
Very Low |
||
Minor |
Very Short / Direct |
High |
High |
Medium |
Medium |
||
Low |
Low |
||
Moderately Short / Direct |
High |
Medium |
|
Medium |
Low |
||
Low |
Very Low |
||
Long / Indirect |
High |
Medium |
|
Medium |
Low |
||
Low |
Very Low |
7.5.1
Landfilling commenced in 1960 with waste being tipped into the open
waters of Gin Drinkers Bay from the northern shoreline (now the north-east
corner of GDBL) and the site became a “controlled tip” in 1973 before closing
in February 1979. The 29ha landfill received approximately 11.4Mm3
of waste. The thickness of the waste increases from the perimeter towards the
centre platform at about +45mPD. Under the platform, the base of the waste is
approximately -10mPD, giving a maximum waste depth of approximately 55m.
7.5.2
GDBL was capped using 1 to 2 m completely decomposed granite (CDG).
Passive LFG vents were installed around the perimeter but there were no
provisions for the collection of leachate, which seeped out of the base of the
landfill and into the adjacent Rambler Channel. When leachate levels were
elevated, leachate often overflowed onto low-lying parts of the roads and
footpaths surrounding the site.
7.5.3
Following completion of the filling and placement of the cover soils,
several thousand trees were planted on the site and preliminary works for
development of the site as a community park (Kwai Chung Park) were undertaken
by Regional Services Department. These works were suspended in the early 1990s
as plans were finalised for the construction of a MTRC viaduct that cut through
part of the site.
7.5.4
In common with the other closed landfill sites in Hong Kong,
restoration works were deemed necessary to reduce the potential health and
environmental risks associated with LFG and landfill leachate, and to allow
beneficial afteruse of the site. The restoration works for GDBL were carried
out as part of a Design-Build-Operate (DBO) contract led by Government, under
the management of EPD. Restoration works commenced in February 1999 and were
completed in September 2000. The Restoration Contractor installed an active LFG
collection system, including gas headers, gas extraction wells, a flare and an
electricity generator. A new leachate collection system was installed, as
controlling leachate levels was considered to be of paramount importance
because of its detrimental effects on the MTRC viaduct. A Leachate Treatment
Plant (LTP) was constructed on a platform below the MTRC viaduct to treat
leachate from the landfill. A new geosynthetic capping system was installed on
top of the platforms, with the heavily vegetated side slopes left uncapped.
Prior to landscaping, a number of groundwater, LFG and leachate monitoring
wells were installed. The landfill site is developed as a green zone currently.
7.5.5
The deposited waste is underlain by marine deposits and alluvial /
colluvial sediments, that are in turn underlain by varying thicknesses of
moderately or completely decomposed granite bedrock.
7.5.6
The works to be carried out as part of the TWR Upgrading within the CZ
are as follows:
·
construction of retaining walls alongside
TWR;
·
demolition and reprovision of footbridge
from the east of TWR leading to GDBL; and
·
paving works alongside TWR, adjacent to
GDBL.
7.6.1
GDBL contains a substantial volume of waste and is a major source of
gas. When initially constructed the landfill site contained few measures to
control either LFG or leachate, although some measures were retrospectively
installed.
7.6.2
Restoration works were carried out between Year 1999 and Year 2000 with
the aim of minimizing the risks associated with off-site migration of LFG and
leachate. As part of the Aftercare Provision of the Restoration Contract,
monitoring of LFG is being carried out since completion of the restoration
works. The monitoring results are summarized in Tables 7-2 and 7-3 and
the locations of monitoring points are shown in Figure 7-2.
Table 7‑2 Methane
Concentrations at Gin Drinkers Bay Landfill
|
Methane Concentrations at Different
Monitoring Points at GDBL (% by volume) |
||||||||
GDB5 |
GDB6 |
GDB7 |
GDB10 |
GDBGW7 |
G1 |
SV23B |
SV24B |
||
Compliance
Limit |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
1 |
|
Oct-01 |
<0.1 |
0.8 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Nov-01 |
<0.1 |
0.9 |
<0.1 |
0.3 |
<0.1 |
<0.1 |
<0.1 |
--- |
|
Dec-01 |
<0.1 |
<0.1 |
0.4 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jan-02 |
<0.1 |
0.4 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Feb-02 |
<0.1 |
0.5 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Mar-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Apr-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
May-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jun-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jul-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Aug-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Sep-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Oct-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Nov-02 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Dec-02 |
<0.1 |
0.8 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jan-03 |
<0.1 |
0.6 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Feb-03 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Mar-03 |
<0.1 |
<0.1 |
<0.1 |
0.6 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Apr-03 |
<0.1 |
0.9 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
May-03 |
<0.1 |
3.2 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
|
Jun-03 |
<0.1 |
1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jul-03 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Aug-03 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Sept-03 |
--- |
<0.1 |
<0.1 |
<0.1 |
--- |
<0.1 |
--- |
--- |
|
Oct-03 |
--- |
<0.1 |
<0.1 |
<0.1 |
--- |
<0.1 |
--- |
--- |
|
Nov-03 |
--- |
<0.1 |
<0.1 |
<0.1 |
--- |
<0.1 |
--- |
--- |
|
Dec-03 |
--- |
0.3 |
<0.1 |
<0.1 |
--- |
<0.1 |
--- |
--- |
|
Jan-04 |
--- |
<0.1 |
<0.1 |
<0.1 |
--- |
<0.1 |
--- |
--- |
|
Feb-04 |
--- |
1.5 |
<0.1 |
<0.1 |
--- |
<0.1 |
--- |
--- |
|
Mar-04 |
--- |
0.7 |
0.5 |
0.2 |
--- |
<0.1 |
--- |
--- |
|
Apr-04 |
--- |
<0.1 |
0.3 |
0.2 |
--- |
<0.1 |
--- |
--- |
|
May-04 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jun-04 |
<0.1 |
0.5 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jul-04 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Aug-04 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Sept-04 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Oct-04 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Nov-04 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Dec-04 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jan-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Feb-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Mar-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Apr-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
May-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jun-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jul-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Aug-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Sept-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Oct-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Nov-05 |
<0.1 |
1.4 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Dec-05 |
<0.1 |
0.6 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jan-06 |
<0.1 |
0.3 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Feb-06 |
<0.1 |
0.3 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Mar-06 |
<0.1 |
5.9 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Apr-06 |
<0.1 |
7.6 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
May-06 |
<0.1 |
0.7 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jun-06 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jul-06 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Aug-06 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Sept-06 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Oct-06 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Nov-06 |
<0.1 |
1.2 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Dec-06 |
<0.1 |
3.7 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Jan-07 |
<0.1 |
4.6 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Feb-07 |
<0.1 |
9.7 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Mar-07 |
<0.1 |
8.6 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Apr-07 |
<0.1 |
9.4 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
|
Notes: ---: Data Not Available Bold: Value
exceeds compliance limit Source: Special Waste and Landfill Restoration Group,
Environmental Protection Department |
|
||||||||
Table 7‑3 Carbon
Dioxide Concentrations at Gin Drinkers Bay Landfill
|
Carbon Dioxide Concentrations at Different
Monitoring Points at GDBL (% by volume) |
|||||||
GDB5 |
GDB6 |
GDB7 |
GDB10 |
GDBGW7 |
G1 |
SV23B |
SV24B |
|
Compliance
Limit |
18.1 |
21.7 |
50.5 |
54.9 |
12.5 |
18.7 |
2 |
8.7 |
Oct-01 |
<0.1 |
0.9 |
16.2 |
18.5 |
<0.1 |
7.2 |
0.1 |
<0.1 |
Nov-01 |
<0.1 |
3.5 |
0.3 |
19.4 |
<0.1 |
8.8 |
<0.1 |
--- |
Dec-01 |
<0.1 |
<0.1 |
19.8 |
19.6 |
<0.1 |
8.5 |
<0.1 |
<0.1 |
Jan-02 |
<0.1 |
0.6 |
<0.1 |
0.1 |
0.8 |
8.1 |
<0.1 |
1.8 |
Feb-02 |
<0.1 |
1.1 |
<0.1 |
<0.1 |
<0.1 |
7.9 |
<0.1 |
<0.1 |
Mar-02 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
1 |
8.9 |
<0.1 |
<0.1 |
Apr-02 |
<0.1 |
<0.1 |
13.4 |
2.4 |
2.2 |
7.7 |
<0.1 |
<0.1 |
May-02 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
1.2 |
9.7 |
<0.1 |
<0.1 |
Jun-02 |
<0.1 |
4.2 |
12.5 |
1.2 |
2.4 |
9.6 |
<0.1 |
<0.1 |
Jul-02 |
0.3 |
6.1 |
<0.1 |
<0.1 |
3.7 |
8.1 |
<0.1 |
<0.1 |
Aug-02 |
<0.1 |
7.1 |
2.3 |
7.1 |
4.6 |
5.5 |
<0.1 |
<0.1 |
Sep-02 |
<0.1 |
8.6 |
7 |
<0.1 |
5.4 |
8 |
<0.1 |
<0.1 |
Oct-02 |
<0.1 |
7.4 |
<0.1 |
<0.1 |
0.5 |
8.9 |
<0.1 |
<0.1 |
Nov-02 |
<0.1 |
5.8 |
21.6 |
15.7 |
3.3 |
10.4 |
<0.1 |
<0.1 |
Dec-02 |
<0.1 |
4.2 |
14.9 |
17.6 |
<0.1 |
10.5 |
<0.1 |
<0.1 |
Jan-03 |
<0.1 |
3.4 |
15.3 |
4.8 |
7.1 |
10.3 |
<0.1 |
<0.1 |
Feb-03 |
<0.1 |
2.6 |
19.8 |
1.6 |
3 |
9.6 |
<0.1 |
<0.1 |
Mar-03 |
<0.1 |
3.7 |
5.6 |
14.8 |
0.3 |
10.4 |
<0.1 |
<0.1 |
Apr-03 |
<0.1 |
6.6 |
7.7 |
6.2 |
12.5 |
11 |
<0.1 |
<0.1 |
May-03 |
<0.1 |
6.1 |
0.1 |
0.3 |
4.4 |
9.3 |
<0.1 |
<0.1 |
Jun-03 |
<0.1 |
0.1 |
7.2 |
8.0 |
0.2 |
<0.1 |
<0.1 |
<0.1 |
Jul-03 |
<0.1 |
5.9 |
12.5 |
0.3 |
1.7 |
10.2 |
<0.1 |
<0.1 |
Aug-03 |
<0.1 |
8.2 |
4.2 |
1.7 |
3 |
11.8 |
<0.1 |
<0.1 |
Sept-03 |
--- |
0.6 |
3.2 |
12.8 |
--- |
8.7 |
--- |
--- |
Oct-03 |
--- |
5.1 |
0.4 |
<0.1 |
--- |
12.6 |
--- |
--- |
Nov-03 |
--- |
<0.1 |
1.1 |
4.6 |
--- |
13.5 |
--- |
--- |
Dec-03 |
--- |
4.8 |
6.5 |
2.8 |
--- |
11.5 |
--- |
--- |
Jan-04 |
--- |
<0.1 |
14.5 |
12.9 |
--- |
11.7 |
--- |
--- |
Feb-04 |
--- |
1.2 |
1.2 |
14.1 |
--- |
10.2 |
--- |
--- |
Mar-04 |
--- |
0.7 |
15.2 |
10.3 |
--- |
11.6 |
--- |
--- |
Apr-04 |
--- |
0.2 |
7.9 |
5.9 |
--- |
10.3 |
--- |
--- |
May-04 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
2.3 |
<0.1 |
<0.1 |
Jun-04 |
<0.1 |
9.6 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Jul-04 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Aug-04 |
<0.1 |
8.4 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
Sept-04 |
<0.1 |
8.7 |
<0.1 |
<0.1 |
<0.1 |
0.3 |
<0.1 |
<0.1 |
Oct-04 |
<0.1 |
3.4 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Nov-04 |
<0.1 |
8.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
0.8 |
Dec-04 |
<0.1 |
6.4 |
<0.1 |
<0.1 |
<0.1 |
0.9 |
<0.1 |
<0.1 |
Jan-05 |
<0.1 |
6.7 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
<0.1 |
0.2 |
Feb-05 |
<0.1 |
7 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Mar-05 |
<0.1 |
0.5 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Apr-05 |
<0.1 |
2.9 |
<0.1 |
3.9 |
<0.1 |
0.6 |
<0.1 |
<0.1 |
May-05 |
<0.1 |
0.3 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Jun-05 |
<0.1 |
<0.1 |
<0.1 |
4.7 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Jul-05 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Aug-05 |
<0.1 |
3.3 |
<0.1 |
6.9 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
Sept-05 |
<0.1 |
7 |
<0.1 |
7.1 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
Oct-05 |
<0.1 |
3.8 |
<0.1 |
13.8 |
<0.1 |
5.3 |
<0.1 |
<0.1 |
Nov-05 |
<0.1 |
5.9 |
<0.1 |
13.8 |
<0.1 |
14.1 |
<0.1 |
<0.1 |
Dec-05 |
<0.1 |
5.4 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Jan-06 |
<0.1 |
4.8 |
<0.1 |
7.4 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Feb-06 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
2.3 |
<0.1 |
<0.1 |
Mar-06 |
<0.1 |
9.6 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Apr-06 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
May-06 |
<0.1 |
8.4 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
<0.1 |
<0.1 |
Jun-06 |
<0.1 |
8.7 |
<0.1 |
<0.1 |
<0.1 |
0.3 |
<0.1 |
<0.1 |
Jul-06 |
<0.1 |
3.4 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Aug-06 |
<0.1 |
8.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
0.8 |
Sept-06 |
<0.1 |
6.4 |
<0.1 |
<0.1 |
<0.1 |
0.9 |
<0.1 |
<0.1 |
Oct-06 |
<0.1 |
6.7 |
<0.1 |
<0.1 |
<0.1 |
0.2 |
<0.1 |
0.2 |
Nov-06 |
<0.1 |
7 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Dec-06 |
<0.1 |
0.5 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Jan-07 |
<0.1 |
2.9 |
<0.1 |
3.9 |
<0.1 |
0.6 |
<0.1 |
<0.1 |
Feb-07 |
<0.1 |
0.3 |
<0.1 |
0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Mar-07 |
<0.1 |
<0.1 |
<0.1 |
4.7 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Apr-07 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Notes: ---: Data Not Available Bold: Value
exceeds compliance limit Source: Special Waste and Landfill Restoration Group,
Environmental Protection Department |
7.6.3
As part of the restoration works, an active gas extraction system was
put in place along the north-eastern boundary of the GDBL site (the western
side of TWR) to collect any LFG along this perimeter for venting via the stack
at the treatment plant at Kwai Hei Street. This is in addition to a number of
passive gas vents along the side of GDBL adjacent to TWR. Landfill gas control
is therefore provided by a mixture of active and passive systems.
7.6.4
The results indicate that there have been 11 exceedances of the
compliance criteria for methane, with concentrations ranging from 1.2% to 9.7% by
volume at monitoring point GDB6 in May 2003, February 2004, November 2005,
March to April 2006, and November 2006 to April 2007.
7.6.5
Carbon dioxide concentrations have ranged from below detection limits
to 21.6% (in November 2002 at monitoring point GDB7) by volume. There has been
a single reading which reached the compliance limit (in April 2003 at
monitoring point GDBGW7). Other than this, the compliance limits for carbon
dioxide set out in the GDBL restoration contract have not been exceeded.
Background concentrations of carbon dioxide, before restoration works
commenced, are reported to be in the range of 0 to 49%.
7.6.6
Although elevated methane concentrations have been recorded at GDB6 (up
to 9.7%), the methane concentrations from the perimeter wells (GDB7, GDB10 and
GDB5, around the perimeter of GDBL) are in all cases less than 1% by volume.
The source of the elevated methane concentrations in GDB6 is believed to be due
to localized pockets of waste outside the boundary of GDBL which were deposited
during the operation of the landfill, and is unlikely to be a result of
migration from GDBL, as indicated by the low concentrations in the perimeter
wells, since any such migration would also be evident in the perimeter
monitoring points. It is considered necessary to mention explicitly in roadwork
contract that waste materials may be encountered during the excavation work and
proper handling and disposal of the waste will be needed.
7.6.7
Relatively elevated concentrations of carbon dioxide in certain off-site
monitoring points have been recorded on certain occasions. However, these
concentrations do not exceed the compliance targets for GDBL and are lower than
those measured before the restoration works. Carbon dioxide may be present in
soil gas as a result of the oxidation of many different types of organic matter
(including leakage of sewage pipes, organic sediments, fuel spillage, other
possible waste deposits outside the landfill boundary etc.), and its presence
is not necessarily indicative of the migration of landfill gas from GDBL. The
potential hazards associated with carbon dioxide include the risk of
asphyxiation to workers, especially those working in excavations or
semi-confined spaces.
7.6.8
In the TWR Upgrading works, only minor excavation at the slope toe
outside the boundary fence of the GDBL site will be carried out. It is
considered that no stored waste and landfill restoration facilities of GDBL
will be affected by this minor excavation. Furthermore, the slope toe will be designed in
accordance with the relevant standards in order to ensure the stability of the
landfill slope. Since the Project will encroach into a piece
of land allocated to EPD under Temporary Government Land Allocation No. TKT
1704, EPD considers that the narrow strip of land within the site boundary of the Project should be
reallocated from EPD to HyD. In this
respect, CEDD will circulate a land requirement plan to relevant parties,
including HyD, in order to address and solve the land allocation issue in the
coming stage.
7.6.9
GDBL is a restored landfill with comprehensive LFG control measures
consisting both active and passive LFG management systems and there is no
evidence indicating that there is significant migration of LFG beyond GDBL.
Also, no excavation will be conducted within the boundary fence of the landfill
site and it is considered that the stored waste as well as landfill restoration
facilities will not be affected. In view of these, the overall Source term is
classified as Medium.
7.6.10
Since the TWR Upgrading works are adjacent to GDBL and, in the case of
the footbridge, within the GDBL site boundary, and because of the existence of
localized pockets of waste outside the GDBL site boundary as mentioned in Section
7.6.6, the potential pathway for migration of gas from GDBL to the works is
classified as Very Short/ Direct.
7.6.11
The existing footbridge will be demolished and reconstructed, a new
section of pavement will be installed adjacent to the landfill, and a new
retaining wall will be constructed. Only minor excavation at the slope toe
outside the boundary fence of the landfill site will be carried and it is
considered that stored waste as well as the LFG management facilities will not
be affected. Detailed design of the foundations for these structures has not
been carried out, and hence the depth of excavations cannot be confirmed. The
Target is therefore classified as being of Medium Sensitivity during construction.
7.6.12
The operational phase will encompass users of the road and footbridge.
There are no below-ground voids or enclosed spaces where LFG may accumulate,
and the development can be classed as “essentially outdoor activities”. The
Target is therefore classified as being of Low Sensitivity during operation.
7.6.13
A qualitative assessment of LFG risk posed by GDBL to the TWR Upgrading
works is set out in Table 7-4.
Table 7‑4 Qualitative
Risk Assessment
Source |
Pathway |
Target |
Qualitative Risk |
Medium |
Adjacent to GDBL (Very Short/Direct) |
Construction Phase (Medium Sensitivity) |
Medium |
Operational Phase (Low Sensitivity) |
Low |
7.6.14
The Qualitative LFG Risk Assessment has indicated the risk associated
with LFG during TWR Upgrading (construction phase) is Medium and following completion of
the works (operation phase) is Low.
7.7.1
The level of risk from LFG is determined to be Medium during construction. Due to
the close proximity to the GDBL site, it is considered prudent to implement
precautionary measures during the construction phase, to further minimize any
risk to the site workforce. Particular precautions will be required with
respect to any trenching or excavation, and any creation of confined spaces at,
near to or below ground level.
7.7.2
Construction contractors should be made aware that methane and carbon
dioxide are always likely to be present in the soil voids. They should also be
aware of the potential hazards and other properties of LFG. In addition, as
mentioned in Section 7.6.6, there exists outside the boundary of GDBL
localized pocketed of waste which were deposited during the operation of the
landfill. Therefore it is necessary to state in the roadwork contract that
waste materials may be encountered during the excavation work, and proper
handling as well as disposal of the waste may be needed.
7.7.3
In all construction work adjacent to GDBL, safety precautions should be
implemented to minimize the risks of:
·
Fires and explosions;
·
Asphyxiation of workers; and
·
Toxicity effects.
7.7.4
Precautions should be clearly laid down and rigidly adhered to with
respect to:
·
Trenching and excavation; and
·
Creation of confined spaces at, near to
or below ground level.
7.7.5
In addition to normal site safety procedures, gas detection equipment
and appropriate breathing apparatus should be available and used when entering
confined spaces or trenches deeper than 1m.
7.7.6
A Safety Officer, trained in the use of gas detection equipment and LFG
related hazards should be present on site throughout the groundwork phase. The
Safety Officer should be provided with an intrinsically safe portable
instrument (or instruments), appropriately calibrated and capable of measuring
the following gases in the ranges indicated:
·
Methane 0
to 100% LEL and 0 to 100% by volume
·
Carbon dioxide 0 to 100%; and
·
Oxygen
0 to 21%
7.7.7
The following safety measures should be implemented during the
construction phase of the Project:
a) All personnel who
work on site and all visitors to the site should be made aware of the
possibility of ignition of gas in the vicinity of the excavations. Safety
notices should be posted warning of the potential hazards.
b) Those staff who
work in, or have responsibility for “at risk” areas, including all excavation
workers, supervisors and engineers working within the CZ, should receive
appropriate training on working in areas susceptible to LFG, fire and explosion
hazards.
c) An excavation
procedure or code of practice to minimize LFG related risk should be devised
and carried out by the contractor.
d) No worker should
be allowed to work alone at any time in or near to any excavation. At least one
other worker should be available to assist with a rescue if needed.
e) Smoking, naked
flames and all other sources of ignition should be prohibited within 15m of any
excavation or ground-level confined space. “No Smoking” and No Naked Flame”
notices should be posted prominently on the construction site and, if
necessary, special areas designated for smoking.
f) Welding,
flame-cutting or other hot works should be confined to open areas at least 15m
from any trench or excavation.
g) Welding, flame
cutting or other hot works may only be carried out in trenches or confined
spaces when controlled by a “permit to work” procedure, properly authorised by
the Safety Officer or other appropriately qualified person.
h) The permit to
work procedure should set down clearly the requirements for continuous
monitoring for methane, carbon dioxide and oxygen throughout the period for
which the hot works are in progress. The procedure should also require the
presence of an appropriately qualified person in attendance outside the
“confined area” who shall be responsible for reviewing the gas measurements as
they are made, and who shall have executive responsibility for suspending the
work in the event of unacceptable or hazardous conditions. Only those workers
who are appropriately trained and fully aware of the potentially hazardous
conditions which may arise should be permitted to carry out hot works in
confined areas.
i)
Ground level construction plant should be fitted with vertical exhausts
at least 0.6m above ground level and with spark arrestors.
j)
Any electrical equipment, such as motors and extension cords, should be
intrinsically safe.
k) During piping
assembly or construction, all valves/seals should be closed immediately after
installation. As construction progresses, all valves/seals should be closed as
installed to prevent the migration of gases through the pipeline/conduit. All
piping/conducting should be capped at the end of each working day.
l)
Mobile offices, equipment stores, mess rooms etc should be located on
an areas which has been proven to be gas free (by survey with portable gas
detectors) and ongoing monitoring should be carried out to ensure that these
areas remain gas free. The use of permanent gas detectors may be appropriate in
some circumstances where there is a relatively high risk but for many
developments it will be sufficient to have regular monitoring undertaken
manually by the safety officer. The particular arrangements to be adopted at a
specific site will need to be determined during the risk assessment/design of
protection measures.
m) Alternatively,
such buildings should be raised clear of the ground. If buildings are raised
clear of the ground, a minimum clear separation distance (as measured from the
highest point on the ground surface to the underside of the lowest floor joist)
should be 500mm.
n) During
construction, adequate fire extinguishing equipment, fire-resistant clothing
and breathing apparatus (BA) sets should be made available on site.
o) The Contractor
should formulate a health and safety policy, standards and instructions for
site personnel to follow.
7.7.8
The following should be noted for LFG monitoring:
a) Periodically
during groundwork construction, the works area should be monitored for methane,
carbon dioxide and oxygen using appropriately calibrated portable gas detection
equipment.
b) The monitoring
frequency and areas to be monitored should be set down prior to commencement of
groundworks by either the Safety Officer or by an appropriately qualified
person.
c) Routine
monitoring should be carried out in all excavations, manholes and chambers and
any other confined spaces that may have been created by, for example, the
temporary storage of building materials on the site surface.
d) All measurements
in excavations should be made with the monitoring tube located not more than
10mm from the exposed ground surface,
e) Monitoring of
excavations should be undertaken as follows:
i)
For excavations deeper
than 1m, measurements should be made:
·
At the ground surface before excavation
commences;
·
Immediately before any workers enter the
excavation;
·
At the beginning of each working day for
the entire period the excavation remains open; and
·
Periodically through the working day
whilst workers are in the excavation.
ii)
For excavations
between 300mm and 1m deep, measurements
should be made:
·
Directly after the excavation has been
completed; and
·
Periodically whilst the excavations
remains open.
iii)
For excavations less
than 300mm deep, monitoring may be
omitted, at the discretion of the Safety Officer or other appropriately
qualified person.
7.7.9
Depending on the results of the measurements, actions required will
vary and should be set down by the Safety Officer or other appropriately
qualified person. As a minimum these actions should encompass those actions
specified in Table 7-5.
Table 7‑5 Summary
of Required Actions in the Event of Gas Detected
Parameter |
Measurement |
Required Action |
O2 |
< 19% |
Increase ventilation to restore O2
to >19% |
< 18% |
Stop work Evacuate Personnel Increase ventilation to restore O2
to >19% |
|
CH4 |
> 10% LEL |
Prohibit hot works Increase ventilation to restore CH4
to < 10% LEL |
> 20% LEL |
Stop work Evacuate Personnel Increase ventilation
to restore CH4 to < 10% LEL |
|
CO2 |
> 0.5% |
Increase ventilation to restore CO2
to < 0.5% |
> 1.5% |
Stop work Evacuate Personnel Increase ventilation to restore CO2
to < 0.5% |
7.7.10
If drilling of boreholes is carried out within the CZ, then the advice
given in Sections 8.29 to 8.49 of the Guidance Note should be followed, and in
particular the drilling contractor should provide a Method Statement detailing
the procedures to be followed, which should include:
a)
provision of an intrinsically safe
portable methane gas detector;
b)
no smoking to be allowed within 15m of a
borehole;
c)
capping of casing at the end of each
working day; and
d)
exhaust and air-intake stacks to be at
least 1.5m above ground level.
7.7.11
During the operation phase, no specific protection measures are
required with respect to the users of the road itself, since road users would
not have access to any enclosed spaces in which LFG could accumulate.
7.7.12
Realignment of or new utilities routes that are formed as part of the
road-widening works are identified within the CZ (see Figure 7-3). They should be designated as “special routes” and the
utility companies notified accordingly, such that the necessary precautions can
be implemented during maintenance or extension, in accordance with the
requirements of the Guidance Note. Any new utility routes passing through the
boundary of the CZ should have a protective impermeable barrier installed (as
illustrated in Figures 7.8 and 7.9 of the Guidance Note) at the boundary of the
CZ (refer to Figure 7-4).
7.8.1
To
ensure the safety of the Contractor’s personnel, landfill gas monitoring for
methane, carbon dioxide and oxygen shall be carried out to identify any
migration between the landfill and the site.
7.8.2
Monitoring
shall be carried out and reported in a similar manner to that for the
Restoration Contract to provide comparable data. The presentation format
for landfill gas monitoring shall be based on this format provided in Appendix
C3 in EM&A Manual and agreed with EPD.
7.9.1
The LFG Hazard Assessment has been undertaken with respect to the
current proposals for the TWR Upgrading works. The assessment has been
undertaken in accordance with the EIAO-TM and the Guidance Note issued by EPD.
7.9.2
The risks associated with LFG during the construction phase have been
classified as Medium. Since
construction works are to be carried out in close proximity to GDBL and within
the CZ, certain mitigation measures are recommended for implementation during
the construction phase. The LFG mitigation measures stated in Section 7.7
shall be incorporated into the contract documents and the project proponent
shall ensure that all the measures will be fully implemented during the
construction stage of the Project.
7.9.3
The risks associated with LFG during the operation phase have been
classified as Low, and as such any underground utilities formed as part
of the road-widening works should be designated as “special routes”, and the
necessary precautions outlined in the Guidance Note should be adopted for all
maintenance or extension works. Requirements will be incorporated into the
contract documents if appropriate.