9.2 Yau
Kom Tau Water Treatment
Works Location and Operations
9.3 Tsuen
Wan Road Upgrading Project
9.4 Meteorological
Conditions and Population
Data
9.7 Rationalisation
of Chlorine Release scenarios And estimation of Scenario Frequencies
9.8 Quantitative
Risk Assessment
9.9 Conclusions
and Recommendations
List of Tables
Table 9-1 Plant
Operating Data for Yau Kom Tau WTW
Table 9-2 Meteorological
Data Used in the Study
Table 9-3 Population
Data Assumed for Different Scenarios
Table 9-4 Physiological
Effects of Chlorine (IChemE, 1989)
Table 9-5 Summary
of Chlorine Release Quantities
Table 9-7 Summary
of Fatalities
Table 9-8 Injuries
to Fatality Ratio
Table 9-9 Location
of Incidents
Table 9-10 Primary
Causes of Incidents
Table 9-11 Hazards
Identified during HAZOP Study for Yau Kom Tau WTW
Table 9-12 Failure
Modes of Contain and Absorb System Identified at HAZOP Study
Table 9-13 Characterisation
of Chlorine Release Scenarios
Table 9-14 Chlorine
Toxicity Relationship
Table 9-15 Effective
Outdoors Probability of Fatality
Table 9-16 Summary of
Source Term Modelling Results for Yau Kom Tau WTW
Table 9-17 Summary of
Wind Tunnel Tests Results for Yau Kom Tau WTW
Table 9-18 Summary of
CFD Modelling Results
Table 9-19 Summary of
DRIFT Modelling Results
Table 9-20 Chlorine
Cloud Heights
Table 9-21 Rationalisation
of Chlorine Release Scenarios
Table 9-22 Release
Scenarios Included in YKT WTW QRA
Table 9-23 Release
Scenarios Categorised by Leak Quantity
Table 9-24 Base
Failure Rate Data
Table 9-25 Event Frequencies
- Base Case of WTW QRA
Table 9-26 Frequencies
(times per year) of Chlorine Release Events used in the Present Study
Table 9-27 Breakdown
of the Case 4 FN Data by Release
Scenario
Table 9-29 Breakdown
of Case 4 and Case 5 PLL by Population Area
Table 9-1 Plant Operating Data for Yau Kom Tau WTW
Table
9-2 Meteorological Data Used
in the Study
Table
9-3 Population Data
Assumed for Different Scenarios
Table
9-4 Physiological
Effects of Chlorine (IChemE, 1989)
Table
9-5 Summary of Chlorine
Release Quantities
Table
9-6 Summary of Injuries
Table
9-7 Summary of
Fatalities
Table
9-8 Injuries to Fatality
Ratio
Table
9-10 Primary Causes of
Incidents
Table
9-11 Hazards Identified
during HAZOP Study for Yau Kom Tau WTW
Table
9-12 Failure Modes of
Contain and Absorb System Identified at HAZOP Study
Table
9-13 Characterisation of
Chlorine Release Scenarios
Table
9-14 Chlorine Toxicity
Relationship
Table
9-15 Effective Outdoors
Probability of Fatality
Table
9-16 Summary of Source
Term Modelling Results for Yau Kom Tau WTW
Table
9-17 Summary of Wind
Tunnel Tests Results for Yau Kom Tau WTW
Table
9-18 Summary of CFD
Modelling Results
Table
9-19 Summary of DRIFT
Modelling Results
Table
9-20 Chlorine Cloud
Heights
Table
9-21 Rationalisation of
Chlorine Release Scenarios
Table
9-22 Release Scenarios
Included in YKT WTW QRA
Table
9-23 Release Scenarios
Categorised by Leak Quantity
Table
9-24 Base Failure Rate
Data
Table
9-25 Event Frequencies –
Base Case of WTW QRA
Table 9-26 Frequencies (time per year) of Chlorine Release Events Used in
the Present Study
Table 9-27 Breakdown of the Case 4 FN Data by Release Scenario
Table 9-28 Total PPL Values
Table
9-29 Breakdown of Case 4 and Case 5
PLL by Population Area
List of Figures
Figure 9-1 Site Layout of Yau Kom Tau Water Treatment Works
Figure 9-2 Site Location of Yau Kom Tau WTW
Figure 9-3 Tsuen
Wan Road Upgrading Project and theeh
Developments Planned in its Vicinity
Figure 9-4 Population Map
Figure 9-5 Scheme of Traffic Lanes included in the Traffic Impact Assessment for the Project
Figure 9-6 FN Curves for Background General Population
Figure 9-7 FN Curves for Updated General Population
Figure 9-8 Individual
Risk Levels
List of Appendices
Appendix 9-A DRIFT
Flat Terrain Dispersion Modelling
Appendix 9-B Wind Tunnel Test Results
Appendix 9-C CFD Modelling Results for Sha Tin WTW and Tai Po Tau WTW
Appendix 9-D Application of Dispersion Modelling Results in QRA
Appendix 9-E Chlorine Cloud Height Predictions
Appendix 9-F Modelling of Escape from Chlorine Cloud
Appendix 9-G Seismic Hazard Assessment
Appendix 9-H Aircraft Crash Frequency Assessment
Appendix 9-I Frequency Estimation
Appendix 9-J Traffic Projections from the Project Traffic Impact Assessment
Appendix
9-K Probability
of Fatality for the Indoor Population
9.1.1
Hazard to life assessment has been conducted, in association with
Environmental Resources Management (ERM), during the construction and
operational phases of the Project following the criteria for evaluating hazard
to life as stated in Annexes 4 and 22 of the TM (Hong Kong Risk
Guidelines).
9.1.2
As
stipulated in Section 3.4.7.1 of the EIA Study Brief No. ESB-141/2006, the
hazard assessment will include the following:
(i) Identification of all credible and applicable hazardous scenarios requiring Quantitative Risk Assessment (QRA) associated with the chlorine storage and on-site transport in the Yau Kom Tau Water Treatment Works (YKTWTW);
(ii)
Execution of a QRA expressing population risks in both
individual and societal terms;
(iii)
Comparison of individual and societal risks with Hong Kong
Risk Guidelines (Annex 4 of TM); and
(iv)
Identification and assessment of practicable and
cost-effective risk mitigation measures.
9.1.3
Hazard assessment that is consistent with the previous QRA for YKTWTW
(ERM, 2001) has been adopted. As
suggested in the EIA Study Brief, the similar methodology of the earlier QRA
for Route 8 (formerly Route 16) which also crosses Consultation Zones of Water
Treatment Works is also taken into account. This Report outlines our methodology and presents the
results of the Hazard to Life Assessment.
9.1.4
The hazard assessment for Yau Kom Tau Water Treatment Works (ERM, 2001)
was conducted on behalf of the Water Supplies Department as part of a larger
project: “Reassessment of Chlorine Hazard for Eight Existing Water Treatment
Works” (ERM, 1997a).
9.1.5
The
study included detailed Hazard Identification, Consequence Analysis (which involved physical modelling of the
dispersion of chlorine clouds in a wind tunnel as well as numerical modelling
using CFD and dispersion models), Event Frequency Estimation and Quantitative Risk Assessment exercises. The results of the QRA were expressed in
terms of individual and societal risk and compared with the Hong Kong Risk
Guidelines as expressed in TM (EPD, 1997). A GIS-based software application GISRisk,
custom-built for the study is described in Section 8.1.
9.1.6
EIA
for that route was conducted by Scott Wilson (Hong Kong) Ltd and Parsons
Brinckerhoff (Asia) Ltd in joint venture, in association with ERM Hong Kong
(responsible for the Hazard to Life Assessment) and MVA Asia.
9.1.7
Two separate road alignments were considered (Scott Wilson, 1998a,b),
both passing in close vicinity of a number of Water Treatment Works (WTWs)
which were considered the principal source of hazard for both the construction
and operational phase of Route 16.
Approach to the risk assessment related to potential chlorine spills at
WTWs was very similar to the detailed studies of eight WTWs for the Water
Supplies Department (ERM, 1997a).
9.1.8 This study is based on the results of QRA for the Yau Kom Tau WTW study (ERM, 2001) and is similar in scope. However the previous input data to the risk modelling have been updated and the modelling repeated in order to take into account the proposed road works under the project as well as the latest traffic and population projections for the area. The study is concerned only with the hazards posed by the storage, handling and on-site transport of chlorine at the YKTWTW.
9.1.9
The
geographical scope includes all the
areas that, based on the results of the previous study could be adversely
affected by a potential chlorine spill at YKTWTW (refer to Figure
9-2). It
should be noted that while such areas may extend beyond the 1 km WTW
Consultation Zone, they do not cover the whole site of the Tsuen Wan Road
Upgrading Project, of which only the western part is included in this
assessment.
9.1.10
The approach to the study follows that of the WTW QRA (ERM, 1997ab,
2001) but takes into account the details of the Tsuen Wan Road upgrading and
the latest traffic and population projections for the area. The resulting societal and individual
risk levels are evaluated for both the construction and operational phases of
the Tsuen Wan Rd upgrading project. The background scenario, assuming that no
Tsuen Wan Rd upgrading is performed is also evaluated. The societal risk is
expressed in terms of PLL (potential loss of life) values and FN curves,
showing a cumulative frequency (F) of various levels of fatalities (N). They
can be directly compared with Hong Kong Risk Guidelines (Annex 4 of TM) as well
as the Government regulations concerning Potentially Hazardous Installation
(PHIs). The individual risk levels express a risk for a hypothetical individual
spending 100% of their time outdoors at a specific location.
9.1.11
Four
separate scenarios are assessed in this study:
·
Case
1: 2006 background conditions;
·
Case
2: 2030 background conditions (no Tsuen Wan Road upgrading project);
·
Case
3: Construction Phase of the project; and
·
Case
4: Operational Phase, 2030 projections of traffic and population.
·
Societal risk results for the Tsuen Wan Rd population
only, for the construction and operational phases of the project are also presented.
9.1.12
The
remaining part of the report is divided into the following sections:
·
Section 9.2 provides a description of Yau Kom
Tau WTW operations;
·
Section 9.3 describes the proposed Tsuen Wan Rd
Upgrading Project;
·
Section 9.4 describes the meteorological and
population data used in the assessment;
·
Section 9.5 deals with hazard identification;
·
Section 9.6 presents the results of the
consequence analysis;
·
Section 9.7 concerns the chlorine release
scenarios and their frequencies
·
Section 9.8 describes the results of the QRA in
terms of the societal and individual risk levels;
·
Section 9.9 presents the conclusions and
recommendations of the study;
·
Section 9.10 includes a list of references; and
·
Appendices 9-A to 9-K include supporting
information related to different parts of this report.
9.2.1
Yau
Kom Tau WTW is situated about 1 km west of Tsuen Wan. The WTW is located on a level platform cut into the hillside
immediately above the Tuen Mun Road.
To the east and south-west of the WTW lie the high rise residential
developments such as Greenview Terrace, Greenview Court, Bayview Garden ,
Belvedere Garden, Hanley Villa and Sunny Villa. Access to the site is via Castle Peak Road leading up to Yau
Kom Tau village. The Tsuen Wan Bypass, Widening of Tsuen Wan Road between Tsuen Tsing
Interchange and Kwai Tsing Interchange and Associated Junction Improvement
Works project
site is located to the east and
south-east of YKT WTW site, with
its western boundary about 1 km to the east from the WTW.
9.2.2
The
site location and the site layout plan are shown in Figures 9-1 and 9-2.
9.2.3
Chlorine
is delivered to Yau Kom Tau WTW in batches of up to 6 x 1 tonne drums. Unloading takes place inside the
chlorine store with the doors closed in a designated truck unloading bay. The movement of drums within the
storage area and unloading bay is carried out using one of two hoist/monorail
systems with purpose-built lifting beams.
Each system covers two of the four rows of drums within the chlorine
store. Prior to usage, the drums
are stored on cradles within the chlorine storage area.
9.2.4
Table 9-1 provides the basic plant operating data for Yau Kom Tau WTW according
to the latest information received from WSD. It can be seen that the average chlorine stock level,
chlorine dosage and estimated chlorine usage are now significantly lower than
those reported in ERM (2001). Nevertheless, since due to increased demand the
chlorine usage at WTW can increase in the future, the value of 1187 tonnes per
year, based on the maximum plant capacity is used in the modelling.
Table 9-1 Plant
Operating Data for Yau Kom Tau WTW
Items |
Units |
1996 |
2007 |
Assumed in
modelling |
Type
of container in use |
- |
1
tonne |
1
tonne |
1
tonne |
Design
capacity of plant |
Mld |
250 |
250 |
- |
Plant
throughput (average) |
Mld |
120 |
120 |
- |
Chlorine
stock level (average) |
tonnes |
45 |
32 |
64 |
Chlorine
dosage (average) |
mg/l |
13 |
2 |
|
Estimated
chlorine usage |
tonnes
per year |
350 |
100 |
1187 |
Chlorine
storage capacity (including duty and standby containers) |
tonnes |
64 |
64 |
64 |
Number
of draw-off units |
- |
2 |
2 |
2 |
Chlorine
container lifting device |
- |
Hoist/Monorail |
Hoist/Monorail |
Hoist/Monorail |
Scrubber
capacity |
tonnes
chlorine |
1 |
1 |
1 |
Distance
travelled by chlorine truck along site access road |
km |
0.2 |
0.2 |
0.2 |
9.2.5
The
draw-off units comprise pairs of drums, one drum on duty, the other serving as
standby. The number of drums on
line is subject to the raw water quality.
Changeover panels automatically change the draw-off from duty to standby
when the draw-off pressure falls below a preset level. The changeover is achieved by
electrically actuated isolating valves provided for each drum.
9.2.6
Liquid
chlorine is drawn from the 1 tonne drums and is passed to the evaporators for
conversion into the gaseous state.
The gaseous chlorine passes through the chlorinators and dissolves in
water at ejectors to form a chlorinated water solution for feeding into the
bulk water stream during the treatment process.
9.2.7
The chlorinators are of vacuum venturi type and thus the section of
line between the regulator and the chlorinator is at negative pressure. Double non return valves are provided
within the chlorinator units.
9.2.8
The chlorine drum storage/evaporator area and chlorinator rooms are
normally ventilated via a supply of fresh air at high level and extracted at
low level. On detection of
chlorine levels above 3 ppm there are visual and audible alarms and the
ventilation extract fans stop.
9.2.9
An
emergency chlorine scrubbing system is installed to remove any leaked chlorine
in the chlorine handling and storage areas. The system is a packed tower utilising sodium hydroxide as
the neutralising agent. The plant
and equipment are installed in a separate scrubber room.
9.2.10
On
detection of a chlorine concentration of 3 ppm or above in the chlorine
handling or storage areas, the scrubbing system will activate
automatically. The air/chlorine
mixture in the affected areas is drawn into the scrubber by the scrubber fan
via ducting connected to the normal ventilation system.
9.2.11
The
scrubber system is normally set at auto control mode to recycle air back to the
drum storage area. However, the
treated air may be discharged to atmosphere at roof level when the chlorine
concentration is below 3 ppm. The
control for recycling or discharging air to atmosphere is effected by means of
a pair of electrically operated change-over dampers which can also be manually
controlled from the local control panel.
A continuous chlorine monitor is installed at a point downstream of the
packed tower and upstream of the vent/recycle changeover dampers. It has a high level alarm which sounds
at both the local control panel and in the main control room when the chlorine
concentration exceeds a pre-set level.
9.2.12
The
sodium hydroxide solution is of 10-12% concentration and is held in a solution
tank beneath the packed tower.
When the system is in operation, the sodium hydroxide is recirculated by
a pump to the distributor at the top of the packed tower to provide adequate
irrigation to the packing.
Sufficient solution is provided to absorb 1 tonne of chlorine. A mist eliminator is provided at the
top of the packed tower to prevent entrainment of liquid into the treated air.
9.2.13
The
scrubber is provided with the following additional features: a sampling point,
a top entry mixer (for in-situ preparation of the sodium hydroxide solution), a
direct reading transparent level gauge, an inspection window and level
indication with high and low level alarms, and a temperature measurement device
for monitoring the temperature of caustic solution during the preparation
process.
9.2.14
According to Fire Services Department's fire safety requirements, a set
of emergency repair/stoppage kit for chlorine spillage/leakage is provided and maintained in good
working condition at all times for use by the trained persons and stowed
adjacent to but outside the store/plant room. Regular drills are conducted to train personnel on the
proper use of the breathing apparatus and protective clothing.
9.2.15
Yau Kom Tau WTW is situated on a hillside at about 80 m above Principal
Datum (PD). To the
north of the site is a steep hill rising to above 400m PD. To the south, the slope falls towards
Rambler Channel. High rise
developments lie to both the east and southwest of the site. Both the topography and nearby high
rise buildings have been taken into account in the chlorine dispersion
modelling.
9.3.1
The existing TWR is generally a dual-three lane carriageway, dropping
to 2 lanes through both Tai Chung Road and Tsuen Tsing Interchanges with single
lane up and down ramps at Kwai Tsing Road, Texaco Road and Tai Chung Road. It
is an elevated structure between Tuen Mun Road and Tsuen Tsing Interchange.
9.3.2
Under
the project, two single lane viaducts with connection to Tuen Mun Road will be
provided on the two sides of the existing elevated section of TWR. The proposed
viaducts will be separate from the existing structure. Near Hoi Kok Street,
these two single lane viaducts will link with the up and down ramps from/to Hoi
On Road and become two 2-lane viaducts. The proposed 2-lane viaducts will also
be separate from the existing structure and located on the two sides of the
existing elevated section of TWR. A down ramp branching off from the Kowloon
bound 2-lane viaduct would be provided near Tsuen Tsing Interchange for the
traffic to Texaco Road. The proposed 2-lane viaducts will end after joining the
at-grade TWR near Tsuen Tsing Interchange, where the existing at-grade TWR
would be widened from dual-3 to dual-5 until the Project limit near Kwai Tsing
Interchange.
9.3.3
The
EIA study area covers the existing urban area of Tsuen Wan West and Kwai Chung.
This dense urban area includes a variety of landuse such as
industrial/commercial buildings, high rise residential towers, schools, open
spaces and recreation facilities. In addition, several West
Rail property developments are planned in the immediate neighbourhood of the
Project. The location of the project, new roadways to be constructed and the
planned MTR developments are shown in Figure 9-3.
9.3.4
Construction works are tentatively planned to commence
in 2011 for completion in Year 2015. A maximum of 840 construction workers are
expected to work on-site with additional 110 in the office to be located in the
western part of the project site.
Operational Phase
9.3.5
Completion
of the project will result in improving driving conditions on the Tsuen Wan
Road and an overall increase of the traffic volumes. Increased traffic volumes
are also expected on Tuen Mun Road. The details of the traffic volumes
predicted at various locations are given in Appendix 9-J.
Meteorological Conditions
9.4.1
For
the sake of consistency with the previous assessment, the meteorological data
to be used in this study is the data recorded at the Shell Tsing Yi weather
station in the year 1996 by the Hong Kong Observatory which was also used in
the hazard assessment for Yau Kom Tau Water Treatment Works (ERM, 2001). The weather data have been rationalised
into different combinations of wind direction, speed and atmospheric stability
class. The probabilities of
occurrence of each combination during day and night are presented in Table 9-2. The Pasquill-Gifford stability classes range from A through
F. Class A represents extremely
unstable conditions which typically occur under conditions of strong daytime
insolation. Class F on the other
hand represents moderately stable conditions which typically arise on clear
nights with little wind. Turbulent
mixing, which will affect the dispersion of a chlorine cloud, increases through
the stability class range from F to A.
Table 9-2 Meteorological
Data Used in the Study
|
Probability |
||||||||
Wind Speed (m/s): |
Day |
Night |
Total |
||||||
2.5 |
2.5 |
5 |
2 |
2.5 |
5 |
2 |
|||
Atmospheric Stability: |
B |
D |
D |
F |
D |
D |
F |
||
Direction |
|
|
|
|
|
|
|
|
|
N |
|
0.0018 |
0.0078 |
0.0019 |
0.0070 |
0.0068 |
0.0043 |
0.0315 |
0.0611 |
NE |
|
0.0011 |
0.0043 |
0.0001 |
0.0051 |
0.0000 |
0.0001 |
0.0348 |
0.0455 |
E |
|
0.0134 |
0.0335 |
0.0497 |
0.0166 |
0.0387 |
0.0442 |
0.1198 |
0.3159 |
SE |
|
0.0398 |
0.0452 |
0.0528 |
0.0088 |
0.0106 |
0.0173 |
0.0777 |
0.2522 |
S |
|
0.0487 |
0.0252 |
0.0147 |
0.0046 |
0.0036 |
0.0038 |
0.0161 |
0.1167 |
SW |
|
0.0143 |
0.0039 |
0.0009 |
0.0009 |
0.0010 |
0.0001 |
0.0035 |
0.0246 |
W |
|
0.0181 |
0.0080 |
0.0036 |
0.0009 |
0.0030 |
0.0010 |
0.0057 |
0.0403 |
NW |
|
0.0137 |
0.0329 |
0.0216 |
0.0085 |
0.0206 |
0.0058 |
0.0403 |
0.1434 |
Total |
|
0.1509 |
0.1608 |
0.1453 |
0.0524 |
0.0843 |
0.0766 |
0.3294 |
1 |
Population in the Areas Surrounding YKT WTW
9.4.2
Since
the present assessment is based on the previous QRA Study for YKT WTW (ERM,
2001) we start with a description of the population assumptions of that study
and then will describe their modifications introduced for the present
assessment to make the population information up to date.
9.4.3
The population data for the area
surrounding Yau Kom Tau WTW have been gathered from a variety of sources:
·
Planning Department;
·
Social Welfare Department;
·
Education Department;
·
Transport Department; and
·
surveys undertaken by the Consultants.
9.4.4
Detailed information has been gathered for the area up to 2 km from the
chlorine store at Yau Kom Tau WTW.
9.4.5
The population data which was included in the Hazard Assessment is all
population within the Consultation Zone (CZ), in addition to population outside
the CZ which can be affected by the LD03 contour (refer to Section 9.6),
up to a maximum of 2 km from the WTW.
9.4.6
The population data is presented in five time periods: night, working
day, weekend day, peak hour and 'jammed peak', the last time period
representing conditions under which traffic on some roads is at a standstill,
'bumper-to-bumper'. The definition
of the time periods is given in Appendix 9-I.
9.4.7
For the purposes of risk modelling (refer to Section 9.8) the population was grouped in a number of
separate point, line and polygon GIS themes shown in Figure 9-4. The corresponding population numbers assumed for
these areas are presented in Table
9-3. Note that except for major roads (33 to 39), the population
units with a letter reference lie within the 1 km Consultation Zone, while the
numbered units are located further away from YKTWTW. Population units labelled
V, W and 40 have been added for the purposes of this assessment.
9.4.8
While two separate population datasets reflecting the 1996 situation
and 2006 population projection were used in ERM (2001) only the latter case is
relevant in this study. The detailed population data of the 2006 case of the
previous assessment are listed in column “Case 1” of Table 9-3.
9.4.9
Sensitive populations such as homes for the elderly, kindergartens and
hospitals (vulnerable population factor 3.3) are separately identified from
other populations (vulnerable population factor 1). The definition of the vulnerable population factor and its
use in the QRA are explained in Section 9.6.
9.4.10
The modelling of the impact of chlorine releases on road populations
follows the approach in HSE (1998) and is explained further in Section 9.6
General Population Assumptions for the Present Assessment
9.4.11
Five
separate population scenarios are considered in this study:
·
Case
1 is a scenario using the 2006 population estimates of the
previous assessment (ERM, 2001). It is included here as a background case, for
comparison with other scenarios;
·
Case
2 uses the same general population data as Case 1, but the road
populations reflect the traffic projections for 2030, after the completion of
the project;
·
Case
3 is similar to Case 2 but the road populations reflect the
2015 construction phase of the project;
·
Case
4 uses the updated general population data and the
2030 projection for the road populations; and
·
Case
5 involves the updated general population data,
but concerns the 2015 construction phase of the project.
9.4.12
As
can be seen our five scenarios include different combinations of two general
population data sets: the 2006 projection of ERM (2001) and the updated
population data as well as three road populations: the 2006 projection of ERM
(2001), the 2015 construction phase, and 2030 operational phase of the project.
9.4.13
The following paragraphs discuss updating of
population assumptions for various population units listed in Table
9-3. Note that only the population totals, where
necessary, are subject to change. The assumptions regarding the population
presence during different time periods, vulnerability factors etc remain
unchanged. The road populations are separately discussed in Sections
9.4.28 to 9.4.53.
9.4.14
Note that the same “updated” general population
estimates are applicable to Case 4 reflecting the 2015 situation and to Case 5
which concerns year 2030. The reason is that reliable population forecasts for
the area are not available beyond 2011 (PlanD, 2006). Thus, where applicable
(ie principally for the village populations only), the 2011 data have been
assumed for both 2015 and 2030. This is considered a conservative assumption,
since in general the population in this area is declining over the years. Note
that the PlanD 2003-based TPEDM population projections up to 2021 by “PVS-338
Zones” have also been consulted, but those projections are older, applicable to
strategic studies only and their PVS-338 Zones appear less adequate to the
specific areas considered in this study than the Tertiary Planning Units (TPUs)
used in PlanD (2006). Thus, the PlanD 2011 of PlanD (2006) projections will
form the basis for our village population estimates. It should however be noted
that also according to the TPEDM projections for areas relevant to this project
their 2021 population estimates do not exceed the 2006 levels.
9.4.15
36
residents were assumed for 2006 to live in the YKT WTW Staff Quarters (Table
9-3 Ref A).
However, according to the recent information provided by WSD, there are
currently only 10 people living there and that number is not expected to
increase in the future. Thus, the population of 10 is assumed for cases 4 and 5
of the present study.
9.4.16
A
residential development Golden Villa is located on the north side of Castle
Peak Road, just to the south of Blocks 5, 6 and 7 of Hanley Villa. Golden Villa was not specifically
mentioned in the previous assessment. The age of the buildings is not known, so
it is not certain if its population was included in the total for the Sunny and Hanley Villas and Keymount Lodge (Table
9-3 Ref F)
or was simply not taken into account, since it was non-existent at the time. It
is a two-block, 30 storey development with two flats on each floor. Additionally, a new residential
development is being constructed just to the east of Golden Villa. We were
advised by Paul Y Builders, Ltd who is the construction contractor that this
will be a one-block, 33 storey development also with 2 flats at each floor.
9.4.17
To
accommodate the population of these two developments in the risk assessment, a
new separate population unit V has been created. Its population is estimated
assuming 2.5 people per flat ie a number slightly greater than that used for
the Sunny and Hanley villas estimates in the previous assessment as 2.5 x 2 x 2
x 30 + 2.5 x 2 x 1 x 33 = 465 and this estimate is used for Cases 4 and 5 of
the present study.
9.4.18
Another
new residential development, close to YKT WTW has been recently constructed on Po
Fung Road, south of Tuen Mun Rd. It is about 25 storeys high with three flats
per floor, while at present the building is not yet in use, its future
population could be estimated at 25 x 3 x 2 5 = 188. This development will be represented by a new population
unit W.
9.4.19
Under
the previous assessment, over 25,000 people were assumed to live in 2006 in the
Tsuen Wan Bay Further Reclamation area (TWBFR). However, no reclamation works have been undertaken to date
and according to the latest Tsuen Wan Zoning Plan No S/TW/24, the project has
been cancelled. Thus, the possible
future population of TWBFR is not taken into account in Cases 4 and 5 of the
present assessment.
9.4.20
Since
the specific village population projections for the area are not available, it
has been decided to apply a general Planning Department population forecast for
separate Tertiary Planning Units (TPUs).
9.4.21
Thus,
the future village populations (refer to Table 9-3 Ref 11, 12, 22, 24-29, B)
all located within the PlanD TPU 3.2.3 are estimated based by applying a factor
of 0.975 to their 2006 population levels assumed in the previous assessment.
The factor is based on the general population for 2006-2011 projection for TPU
3.2.3 (see Table 15, PlanD, 2006).
Similarly, for the village population unit 31, located within TPU 3.5.1
a factor of 0.974 will be applied
9.4.22
Note
that the assumed decline of the village populations may seem contradictory to
the general HK population trends[1]. However, in our opinion, even if the general HK population will follow the
high growth scenario, the population growth will be concentrated in the newly
developed areas, while the population of the already developed areas such as
Tsuen Wan, and in particular the village population in such areas would remain
steady or decline, as shown in PlanD (2006).
9.4.23
Note
that PlanD projections are not available beyond 2011 so we conservatively
assume that after 2011 no further population decline will occur in the area.
9.4.24
Due
to its proximity to YKT WTW and low protection provided by squatter dwellings,
Yau Kom Tau Squatter population estimated at 676 during the previous
assessment, is of particular interest. On a site visit on 12 September 2007 the
number of squatter dwelling in the area, some of which seemed abandoned, was
estimated as not more than 20. While, according to the information obtained
from Lands Department there are no specific clearance plans for the area, it is
reasonable to expect that in the future that population will further decline.
Nevertheless, for the Cases 4 and 5 of this assessment, the squatter population E is
conservatively assumed at 100.
9.4.25
Population
of the schools, hospitals, kindergartens and similar institutions (refer to Table
9-3 Ref 2,
3, 4, 5, 6, 7, 14, 15, 16, 17, N, O, P, Q, R, S, T, U) are assumed at their 2006,
Case 1 levels. Note that in the previous assessments it
was also assumed that their population does not change, and the 2006
projections were equal to actual 1996 numbers.
9.4.26
Specific
residential and hotel developments that were included in the previous
assessments (refer to Table 9-3 Ref 1, 8, 9, 10, 19, 23, C, D, F, G, H, I,
K, L,) are also assumed to retain populations at their 2006 levels. Note that
this is a conservative assumption, since in the previous assessment (ERM, 2001)
for this category of buildings the population was assumed to decline, and the
projected 2006 numbers were markedly lower than those for 1996.
9.4.27
Similarly,
for the following other units the populations are assumed at their 2006, Case 1
levels: 13 (Discovery Shopping Mall), 18 (Factories and Godown), 20 (Fire
Station), 21 (Hing Shing Temporary Housing Area), 30 (Cement Plant), 32 (Tsing
Yi Jetties and Shipyards), and J (Bus Terminal). It should be noted that for
the unit 18 with a particularly high population number at 12,000, this is a
conservative assumption, since the HK manufacturing activities tend to decline
over the years.
9.4.28
Since
the current assessment concerns the Tsuen Wan Road Upgrading project and the
Tuen Mun Road population contributed over 30% of the total PLL under the
previous assessment (see Table 7.3b of ERM, 2001) projections of the road
population require a special attention.
9.4.29
The
methodology of the road population estimation does in general follow that of
the previous assessment, however the estimates are now based on the traffic
information from the Traffic Impact Assessment (TIA) for the Tsuen Wan Rd
Upgrading Project (refer to Appendix 9-J) that has been endorsed by
Transport Department and other relevant parties, or, where unavailable, from
the latest traffic census. Note that the former case applies to all the major
roads in the vicinity of YKT WTW, ie not only Tsuen Wan Rd, but also Tuen Mun
Rd, eastern sections of Castle Peak Rd and Hoi On Rd, so the 2006 traffic
census information is only used for more remote roads such as Ting Kau Bridge
or the western part of Castle Peak Rd. The following paragraphs describe
population assumptions for all roads that are included in the assessment for Case 4
- the 2030 operational phase of the project. The methodology for the Case 5,
is similar, only the data from different TIA tables are used, so the
computations are not repeated here and only their results are listed in Table
9-3. The Case 5 population of Tsuen Wan Rd
is additionally discussed in Section 9.4).
9.4.30
Generally,
the peak hour populations for free flowing roads are estimated from the
relevant traffic data assuming vehicle speed of 35 km/h and 3.3 persons per
vehicle on the average. It should be noted that the latter assumption, used
both in ERM (2001) and in the present assessment is significantly higher than
2.3 persons per vehicle assumed in the previous Route 16 assessments (Scott
Wilson, 1998a,b).
9.4.31
The
pertinent data from the Traffic Impact Assessment for the Tsuen Wan Rd
Upgrading Project are for the reader’s reference included in Appendix
9-J to this report.
9.4.32
The
1996 estimate of 2593 people present on the 3.158 km stretch of Tuen Mun Rd
(refer to Figure 9-4) during the peak hour used in the previous
assessment was obtained from the AADT value of 99180 from the 1996 Traffic
Census multiplied by a factor of 0.00943 and the length of the road (3.158).
9.4.33
The
factor 0.00943 is equal to 0.10 x 3.3 / 35 where 0.1 is the assumed fraction of
AADT during the peak hour, 3.3 the average number of people per vehicle and 35
the assumed peak hour traffic speed in km/h.
9.4.34
Note
that even during the “jammed peak” period the traffic is assumed free-flowing,
with above estimate valid for both the “peak” and “jammed peak” periods.
9.4.35
Similar
approach is adopted for the present assessment, however the peak hour traffic
volumes are now taken from the Traffic Impact Assessment undertaken for the
Tsuen Wan Rd Upgrading Project.
9.4.36
For
the case “with TWR upgrading”, the TIA 2030 estimate of the Tuen Mun Rd two-way
traffic (Sections E+D, see Figure 4.2 and Annex J) the morning peak hour traffic volume is 7650.
9.4.37
Thus,
applying the same assumption as in ERM (2001) we obtain 7650 x 3.158 x 3.3 / 35
= 2278. Note that while this value is lower than 2354 used for 2006 in the
previous assessment, it should not be surprising, since according to the 2005
Traffic Census the traffic volumes on Tuen Mun Rd (Core Station 5035)
significantly declined between 2002-2005 and in 2006 the AADT value at 68530
was again lower than in 2005, so it can be assumed that this trend would
continue. If the factor 0.00943 x 3.146 was applied to the actual 2006 AADT,
the population estimate would stand at 2040, significantly lower than the 2006
projection made for the previous assessment.
9.4.38
Following
ERM (2001) the time distribution of the Tuen Mun Rd, as well as all the other
free-flowing roads is assumed as the percentage of the peak as follows:
·
night: 5%
·
jammed
peak: 100%
·
peak
hour: 100%
·
weekend
day: 50%
·
working
day: 55%
9.4.39
Since
the Ting Kau Bridge is not covered by the TIA, the traffic estimates are based
on the latest Traffic Census.
Since the bridge lies on the periphery of the study area, this approach
is considered adequate for the purposes of the study. According to the 2006
Traffic Census the AADT on Ting Kau Bridge was 76300 in 2005 and 75380 in 2006.
The length of the road section included in the modelling is 1.147 km. Using the 2006 AADT and applying the
same 0.00943 factor (see above) we obtain the number of people on the bridge at
the peak hour as 75380 x 0.00934 x 1.147 = 808. The above
estimate, significantly higher than the 2006 projection used in the previous
assessment is assumed for the Cases 2 - 5 of the present study.
9.4.40
As
in the previous assessment, similar to Tuen Mun Rd, the Ting Kau Bridge traffic
even during the “jammed peak” period the traffic is assumed free-flowing, with
above estimate valid for both the peak and jammed peak periods.
9.4.41
Tsuen
Wan Rd was in the previous assessment modelled as a single line object. Despite
the addition of new lanes planned under the present project, since they run
parallel to the existing lanes, that approach is considered adequate for the
present assessment as well, especially that the road lies quite far from YKT
WTW.
9.4.42
Population
estimate for TWR on the 2030 traffic projections provided in the Traffic Impact
Assessment for the Project was referred in this assessment. The traffic estimate is based on the
western (closer to WTW) segment of the road with the heaviest traffic, ie the
sum of TIA sections BO, AK, AL, AG, J, G, F and B (refer Figure
9-4). The
morning peak hour traffic for the case “With TWR Upgrading” is projected for
these sections as 10400 vehicles (refer to Appendix 9-J). Applying the same
assumptions as in the case of Tuen Mun Rd, the number of people on the 1.570 km
segment of Tsuen Wan Road included in the modelling can be estimated as 10400 x
1.571 x 3.3 /35 = 1540.
9.4.43
As
in the previous assessment, similar to Tuen Mun Rd, the Tsuen Wan Rd traffic
even during the “jammed peak” period the traffic is assumed free-flowing, with
above estimate valid for both the peak and jammed peak periods.
9.4.44
The
2006 Traffic Census gives the AADT at station 6209, located on Castle Peak Road
to the east of Ting Kau Bridge as 6690, 1.5% lower than in 2005 and over 33%
lower than in 1996. Since suitable traffic projections for the future years on
this section of the Castle Peak Road are not available, this number will form a
basis for our population estimate. It is considered conservative, since similar
to other neighbouring roads, the traffic is has been declining over the recent years.
The length of this section is 2.616 km so the population estimate can be
obtained as 6690 x 0.00934 x 2.616 = 163, a number significantly lower than
used in the previous assessment.
9.4.45
As
in the previous assessment, similar to Tuen Mun Roadd, the Tsuen Wan Road
traffic even during the “jammed peak” period the traffic is assumed
free-flowing, with above estimate valid for both the peak and jammed peak
periods.
9.4.46
This Castle Peak Road section was the only road for which in the
previous assessment the traffic in one of the directions during the jammed peak
period was considered jammed, ie ‘bumper to bumper’. The same assumption will
be used in the present study, so the population estimation methodology is in
this case slightly different than for the other roads.
9.4.47
Similar to the previous assessment (ERM, 2001), the population of the
jammed lane is estimated assuming that each vehicle occupies on average 6 m of
the road. With the road length of 0.951 km and assuming as in the previous
cases 3.3 persons per car, the jammed lane population is 3.3 * 951/6 = 523.
9.4.48
The population of the other lane is computed as for other free-flowing
roads, based on the peak hour data from the project Traffic Impact Assessments.
The 2030 traffic volume on this section of Castle Peak Road is given in Appendix 9-J as 800 (Section BR –
see Figure 9-5) or 1050
(Section BD). For the one way traffic estimate we will use one half of the
average of these values, ie (800 + 1050)/4 = 463. Thus, assuming as for other roads the average speed of 35
km/h and 3.3 persons per vehicle, the population of this lane is 463 x 0.951 *
3.3 /35 = 42. The total jammed peak population of this road section is
therefore 523 + 42 = 565.
9.4.49
The road population for the peak hour, where both lanes are assumed
free-flowing is simply 84, the double of the free-flowing lane population
obtained for ‘jammed peak’. Note that this number constitutes 15% of the jammed
peak population.
9.4.50
For the other time periods we use the same fractions of the peak
periods that are used for other free flowing roads (see sub-section on Tuen Mun
Rd above). Thus, the corresponding percentages of the Cases 2 and 4
jammed peak population can be obtained as:
·
night: 5%
* 15% = 0.8%
·
jammed
peak: 100%
·
peak
hour: 15%
·
weekend
day: 50% * 15% =
7.5 %
·
working
day: 55% *
15% = 8%
9.4.51
Note that the corresponding jammed peak population of this section of
Castle Peak Rd
is for Cases 3 and 5
is 538
and the peak hour population is 29, so the night, peak, weekend day and working
day fractions can be similarly established at 0.3%, 5.4%, 2.7% and 3.0%.
9.4.52
For this part of Castle Peak Rd, which is also assumed as free-flowing,
the 2030 peak hour traffic volume is taken as the sum of TIA sections A + BH +
H (refer to Figure 9-5),
and according to Table J2 in Appendix 9-J amounts to 3600 vehicles. The length of this
road section assumed in the modelling is 1.040 km. Thus the peak hour population
is estimated as 3600 x 1.040 x 3.3 / 35 = 353.
9.4.53
Hoi On Rd traffic is assumed as an average of TIA sections BS and BE
(see Figure 4.2) which according to Table J2 in Appendix 9-J
is equal to 3700 vehicles. The length of the road assumed in modelling is 0.935
km. Thus Case 2 and
4 of 2030 peak hour
population can be estimated at 3700 x 0.935 x 3.3 /35 = 326.
9.4.54
For most population units the Case
3 and 5, ie Construction
Phase population is simply based on the appropriate population projections and
the 2015 TIA traffic forecast ‘without the project’. However the construction
workforce for the project needs also to be accounted for. According to the information provided
by CEDD, the maximum number of construction workers onsite will be 840 working
on the Tsuen Wan Rd plus 130 in temporary office located in the western part of
the project site.
9.4.55
For the office workers a separate population unit 40 is created. The
exact location of the office is not yet known, but it is understood that two
possible locations are considered. In order to account for the worst case, we
assume that it will be located at a site closer to the WTW, in the western part
of the Project site area (refer to Figure
9-4).
9.4.56
The remaining workforce is assumed to be evenly distributed along the
Tsuen Wan Rd, so this population component can simply be added to the
corresponding working day traffic population (Ref 35).
9.4.57
Similar to Cases 2 and 4 above, the jammed peak and peak
hour Case 3 and 5 traffic population of Tsuen Wan Rd, can be obtained as the sum of TIA sections BO,
AK, AL, AG, J, G, F and B multiplied by 1.571 x 3.3 /35, ie (see Table J1 of Appendix 9-J) 5850 x 1.571 x 3.3 /35 = 867. The working day
traffic population is assumed as 55% of the peak level, i.e. 477. Note that of the about 3.25 km of Tsuen
Wan Road within the Project site area, only its western 1.571 km is modelled in
this assessment, since the remaining part lies beyond the area of potential
risk associated with YKT WTW. So, only 840 x 1.571/3.25 = 406 construction
workers need to be added to the traffic population of that section of the road.
Thus, the working day population of Tsuen Wan Rd during the construction phase
can be estimated as 477 + 406 = 883. The peak and jammed peak population at 867
constitutes now 98% of this maximum, the night population is 5% x 98% = 5% and
the weekend day population 50% x 95% = 49%.
Table 9-3 Population Data Assumed
for Different Scenarios
Ref |
Description |
Case 1 Background 2006 (Previous Assessment) |
Case 2 Project Operation + Case 1 |
Case3 Project Construction +Case 1 |
Case 4 Project Operation + Revised Population |
Case 5 Project Construction + Revised Population |
Night |
Jammed Peak |
Peak Hour |
Weekend Day |
Working Day |
Portion Indoors |
Vulnerable Pop. Factor |
Storeys |
01 |
Allway
Gardens |
9753 |
9753 |
9753 |
9753 |
9753 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
27 |
02 |
Kei
Wai Primary School CCC HK Council |
840 |
840 |
840 |
840 |
840 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
03 |
YCH
Lim Por Yen Secondary School |
1080 |
1080 |
1080 |
1080 |
1080 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
04 |
PLK
Lee Shing Pik College |
1160 |
1160 |
1160 |
1160 |
1160 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
05 |
Chai
Wan Kok Catholic Primary School |
840 |
840 |
840 |
840 |
840 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
06 |
Textile
Int Acc Woo Hon Fai Prevocational School |
1000 |
1000 |
1000 |
1000 |
1000 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
07 |
Tsuen
Wan Adventist Hospital |
400 |
400 |
400 |
400 |
400 |
100% |
100% |
100% |
100% |
100% |
99% |
3.3 |
5 |
08 |
Sheeny
Terrace, Joyful Building, Kam Fung Garden |
2508 |
2508 |
2508 |
2508 |
2508 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
27 |
09 |
Proposed
Residential Development |
3456 |
3456 |
3456 |
3456 |
3456 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
35 |
10 |
Tsuen
King Garden, Tsuen Wan Centre |
21483 |
21483 |
21483 |
21483 |
21483 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
32 |
11 |
Squatters
and Villages |
31 |
31 |
31 |
30 |
30 |
100% |
50% |
50% |
70% |
50% |
0% |
1 |
1 |
12 |
Squatters
and Village Housing |
1838 |
1838 |
1838 |
1792 |
1792 |
100% |
50% |
50% |
70% |
50% |
0% |
1 |
1 |
13 |
Discovery
Park (Shopping Mall) |
1000 |
1000 |
1000 |
1000 |
1000 |
0% |
50% |
50% |
100% |
50% |
99% |
1 |
4 |
14 |
Allway
Kindergarten |
210 |
210 |
210 |
210 |
210 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
15 |
Annuciation
Catholic Kindergarten |
180 |
180 |
180 |
180 |
180 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
16 |
Sun
Island English Kindergarten |
294 |
294 |
294 |
294 |
294 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
17 |
Morning
Sun Kindergarten |
455 |
455 |
455 |
455 |
455 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
18 |
Factories
and Godown |
12000 |
12000 |
12000 |
12000 |
12000 |
10% |
50% |
50% |
20% |
100% |
99% |
1 |
20 |
19 |
Proposed
Hotel Development |
780 |
780 |
780 |
780 |
780 |
100% |
50% |
50% |
60% |
60% |
99% |
1 |
15 |
20 |
Fire
Station |
30 |
30 |
30 |
30 |
30 |
100% |
100% |
100% |
100% |
100% |
95% |
1 |
5 |
21 |
Hing
Shing Temporary Housing Area |
0 |
0 |
0 |
0 |
0 |
100% |
50% |
50% |
70% |
50% |
90% |
1 |
2 |
22 |
Village
Housing |
46 |
46 |
46 |
45 |
45 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
1 |
23 |
Proposed
Hotel Development |
780 |
780 |
780 |
780 |
780 |
100% |
50% |
50% |
60% |
60% |
99% |
1 |
14 |
24 |
Residential
Village Housing |
85 |
85 |
85 |
83 |
83 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
3 |
25 |
Ting
Kau Village |
174 |
174 |
174 |
170 |
170 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
3 |
26 |
Village
Housing |
11 |
11 |
11 |
11 |
11 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
1 |
27 |
Village
Housing |
319 |
319 |
319 |
311 |
311 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
3 |
28 |
Village
Housing |
6 |
6 |
6 |
6 |
6 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
1 |
29 |
Beach
Building, Village Housing |
5 |
5 |
5 |
5 |
5 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
2 |
30 |
Cement
Plant |
10 |
10 |
10 |
10 |
10 |
10% |
50% |
50% |
20% |
100% |
50% |
1 |
1 |
31 |
Village
|
120 |
120 |
120 |
117 |
117 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
3 |
32 |
Jetties
and Shipyards |
100 |
100 |
100 |
100 |
100 |
10% |
50% |
50% |
20% |
100% |
50% |
1 |
1 |
33 |
Tuen
Mun Road |
2354 |
2278 |
1772 |
2278 |
1772 |
5% |
100% |
100% |
50% |
55% |
50% |
1 |
0 |
34 |
Ting
Kau Bridge |
533 |
808 |
808 |
808 |
808 |
5% |
100% |
100% |
50% |
55% |
75% |
1 |
0 |
35 |
Tsuen
Wan Road |
1304 |
1540 |
883 |
1540 |
883 |
5%(1) |
100%(1) |
100%(1) |
50%(1) |
55%(1) |
75% |
1 |
0 |
36 |
Castle
Peak Road Section 1 (from Sham Tseng to Bayview Garden) |
275 |
163 |
163 |
163 |
163 |
5% |
100% |
100% |
50% |
55% |
75% |
1 |
0 |
37 |
Castle
Peak Road Section 2 (from Bayview Garden to Tuen Mun Road) |
752 |
565 |
538 |
565 |
538 |
1%(2) |
100% |
14%(2) |
7%(2) |
7%(2) |
75% |
1 |
0 |
38 |
Castle
Peak Road Section 3 (from Tuen Mun Road to Tai Chung Road) |
542 |
353 |
338 |
353 |
338 |
5% |
100% |
100% |
50% |
55% |
75% |
1 |
0 |
39 |
Hoi
On Road |
170 |
326 |
238 |
326 |
238 |
5% |
100% |
100% |
50% |
55% |
75% |
1 |
0 |
40 |
Temporary
Office for Tsuen Wan Rd Upgrading Project |
0 |
0 |
130 |
0 |
130 |
0% |
0% |
0% |
0% |
100% |
100% |
1 |
3 |
A |
YKT
WTW Staff Quarters |
36 |
36 |
36 |
10 |
10 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
2 |
B |
Yau
Kom Tau Village Extension |
476 |
476 |
476 |
464 |
464 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
3 |
C |
Greenview
Court and Belvedere Garden |
10394 |
10394 |
10394 |
10394 |
10394 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
33 |
D |
Gardenview
Terrace and Blossom Terrace |
587 |
587 |
587 |
587 |
587 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
3 |
E |
Yau
Kom Tau Squatters |
676 |
676 |
676 |
100 |
100 |
100% |
50% |
50% |
70% |
50% |
0% |
1 |
1 |
F |
Sunny
and Hanley Villa, Keymount Lodge |
1794 |
1794 |
1794 |
1794 |
1794 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
25 |
G |
Long
Beach Garden |
142 |
142 |
142 |
142 |
142 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
3 |
H |
The
Bay Bridge |
438 |
438 |
438 |
438 |
438 |
100% |
50% |
50% |
50% |
50% |
99% |
1 |
13 |
I |
Bayview
Garden |
3419 |
3419 |
3419 |
3419 |
3419 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
30 |
J |
Bus
Terminal |
150 |
150 |
150 |
150 |
150 |
10% |
100% |
100% |
30% |
30% |
0% |
1 |
1 |
K |
Belvedere
Garden, The Panorama |
9915 |
9915 |
9915 |
9915 |
9915 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
30 |
L |
Serenade
Cove |
2257 |
2257 |
2257 |
2257 |
2257 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
30 |
M |
Tsuen
Wan Bay Further Reclamation (Public and Private Housing) |
25757 |
25757 |
25757 |
0 |
0 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
39 |
N |
HK
Baptish Convention Primary School |
1050 |
1050 |
1050 |
1050 |
1050 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
O |
Future
Secondary School |
1080 |
1080 |
1080 |
1080 |
1080 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
P |
Future
Primary School |
840 |
840 |
840 |
840 |
840 |
0% |
50% |
50% |
0% |
100% |
95% |
1 |
5 |
Q |
Creative
KG |
185 |
185 |
185 |
185 |
185 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
R |
St.
Monica's Play School |
200 |
200 |
200 |
200 |
200 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
S |
Belvedere
Anglo-Chinese KG |
130 |
130 |
130 |
130 |
130 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
2 |
T |
Po
Leung Kuk Fong Tam Yuen Leung Nursery |
114 |
114 |
114 |
114 |
114 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
U |
Tsuen
Wan St. Andrew Anglo-Chinese Kindergarten |
115 |
115 |
115 |
115 |
115 |
0% |
50% |
50% |
0% |
100% |
95% |
3.3 |
1 |
V |
Golden
Villa and a new residential development nearby |
0 |
0 |
0 |
465 |
465 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
32 |
W |
New
residential development on Po Fung Rd |
0 |
0 |
0 |
188 |
188 |
100% |
50% |
50% |
70% |
50% |
99% |
1 |
25 |
Notes:
(1) Valid for
Cases 1, 2 and 4 only. For Cases 3 and 5 fractions see Section 9.4.
(2)
Valid for Case 1 only. For Cases 2-5 fractions see Section 9.4.
9.5.1
The following paragraphs summarise some of the key hazardous
characteristics of chlorine (ICI Chlorine Handbook, 1995):
·
Chlorine gas is heavier than air and as a result
will tend to accumulate in low places when released to the atmosphere and flow
downhill in still air. However,
slight breezes or thermal turbulence will cause it to move upward, so people
are not necessarily safe simply because they are above the point of release.
·
Chlorine gas has a greenish-yellow colour which
is only visible at concentrations (above approximately 500ppm) many times
higher than the danger level (see Table 5.1
below).
·
Chlorine gas is a respiratory irritant. Symptoms caused by inhalation of chlorine
include: headaches, pain, difficult breathing, burning sensation of the chest,
nausea and watering of the eyes.
The physiological effects of chlorine are summarised in Table 9-4.
Table 9-4 Physiological
Effects of Chlorine (IChemE, 1989)
Concentration (ppm) |
Effects |
0.2-3.5 |
Threshold of odour perception in most
individuals |
3-5 |
Tolerated without undue ill effect for half to
one hour. |
5-8 |
Slight irritation of the mucous membranes of
the upper respiratory tract and of the eyes. |
15 |
Effects are immediate. Irritation of nose, throat and eyes
with cough and lachrymation. |
30 |
Immediate cough with a choking sensation,
retrosternal chest pain and a sense of constriction in the chest. |
40-60 |
Development of a chemical tracheo-bronchitis
and pulmonary oedema. |
1000 |
Concentration likely to be fatal after a few
deep breaths. |
9.5.2
A survey of worldwide incidents involving chlorine drums and cylinders
has been conducted and presented in Annex A of Methodology Report (ERM, 1997a). There have been a total of 86 incidents
in the previous 77 years.
9.5.3 The following reference data have been searched and consulted:
·
MHIDAS Database (MHIDAS is a Major Hazard
Incident Data Service developed by the Safety and Reliability Directorate of
the UK Atomic Energy Authority.
MHIDAS contains incidents from over 95 countries particularly the UK,
USA, Canada, Germany, France and India.
The database allows access to many other important sources of accident
data, such as the Loss Prevention Bulletin, and is continuously updated);
·
HSELine (The Library and Information
Services of the UK Health and Safety Executive has accumulated in a computer
database documents relevant to health and safety at work. HSELine contains citations to HSE and
Health and Safety Commission publications, together with documents, journal
articles, conference proceedings, etc.)
·
Lees (1996);
·
AQUALINE;
·
Chlorine Institute;
·
Chlorine Transport Risk Study, DNV
Technica (1997)
9.5.4
The search undertaken was for all incidents involving chlorine 'drums',
'cylinders' or 'containers' OR incidents occurring at treatment works.
9.5.5
The results are summarised in the following tables.
Table 9-5 Summary
of Chlorine Release Quantities
Release Quantity (in kg) |
Number of incidents |
Percentage |
0 - 9 |
4 |
4.7% |
10 - 99 |
8 |
9.3% |
100 - 499 |
4 |
4.7% |
500 -1000 |
9 |
10.5% |
1000+ |
2 |
2.3% |
Not specified |
59 |
68.6% |
TOTAL |
86 |
100.0% |
9.5.6
The above data shows a significant proportion of the incidents having a
release quantity of 500 kg or more.
A number of these incidents concerned faulty or damaged valves or
connecting pipework, illustrating the difficulty in being able to isolate even
relatively small leaks.
Number of Injuries |
Number of incidents |
Percentage |
0 - 9 |
23 |
26.7% |
10 - 49 |
10 |
11.6% |
50 - 100 |
6 |
7.0% |
100 - 499 |
8 |
9.3% |
500+ |
2 |
2.3% |
Not specified |
37 |
43.0% |
TOTAL |
86 |
100.0% |
Table
9-7 Summary
of Fatalities
Number of Fatalities |
Number of incidents |
Percentage |
0 |
29 |
33.7% |
1 |
7 |
8.1% |
2 |
5 |
5.8% |
3 |
2 |
2.3% |
4 - 9 |
3 |
3.5% |
10+ |
1 |
1.2% |
Not specified |
39 |
45.3% |
TOTAL |
86 |
100.0% |
9.5.7
Of the 86 recorded incidents, 8 specified both injuries and
fatalities. The overall injury to
fatality ratio is 48 to 1 as shown below in Table 9-8.
Table
9-8 Injuries
to Fatality Ratio
Date of Incident |
Injuries |
Fatalities |
10/1/47 |
104 |
1 |
8/5/69 |
33 |
2 |
27/12/74 |
85 |
2 |
14/8/76 |
1 |
2 |
12/6/85 |
100 |
5 |
24/5/91 |
600 |
5 |
4/7/95 |
19 |
3 |
6/7/95 |
73 |
1 |
TOTAL |
1015 |
21 |
Table 9-9 Location
of Incidents
Location |
Number of incidents |
Percentage |
Water Treatment Plant |
22 |
25.6% |
Sewage Treatment Plant |
7 |
8.1% |
Swimming Pool/Water Park |
2 |
2.3% |
Pumping Station |
2 |
2.3% |
Prechlorination House |
2 |
2.3% |
Road Transportation |
14 |
16.3% |
Rail Transportation |
2 |
2.3% |
Marine Transportation |
4 |
4.7% |
Loading/Unloading |
5 |
5.8% |
Elsewhere |
16 |
18.6% |
Not specified |
10 |
11.6% |
TOTAL |
86 |
100.0% |
9.5.8
The above table shows most incidents occurring either at water
treatment plant (25.6%) or during transportation (23.3%).
Table 9-10 Primary Causes of Incidents
Primary Cause |
Number of incidents |
Percentage |
Equipment Failure |
13 |
15.1% |
Human Error |
7 |
8.1% |
Corrosion |
4 |
4.7% |
Fire/Overheating |
1 |
1.2% |
Contamination |
5 |
5.8% |
Road accident |
5 |
5.8% |
Marine Accident |
5 |
5.8% |
Rail accident |
1 |
1.2% |
Loadshedding |
5 |
5.8% |
Unknown/not specified |
40 |
46.5% |
TOTAL |
86 |
100.0% |
9.5.9
The table shows that the primary cause of incidents was equipment
failure, eg faulty valves or pipework (15.1%). However, accidents during transportation of chlorine
containers are also significant (12.8%).
9.5.10
A Hazard and Operability (HAZOP) study was conducted for Yau Kom Tau
WTW to provide a full and systematic identification of the hazards associated
with delivery, storage and handling of chlorine (see ERM, 1997b, 2001).
The HAZOP technique provides a means of examining deviations from the
design intent, their causes, consequences and safeguards, in a structured
manner.
9.5.11
The primary focus of the HAZOP was on the hazards posed to people
off-site. 'Internal' as well as'
external' hazards were considered, ie those within the control of the operating
staff, such as the hazards arising during drum connection/disconnection, as well as those outside their control
such as an external fire. The
information provided for the HAZOP included the site layout plan, Process and
Instrumentation Diagram (P&ID), chlorine store layout plan, as well as the
Operations and Maintenance Manual.
9.5.12
The HAZOP sessions considered each of the following aspects of the
design and operation of the WTW:
·
transport of chlorine containers along the site
access road (including manoeuvring of the truck outside the entrance to the
truck unloading bay);
·
handling of containers within the store;
·
containers in storage;
·
connection and disconnection of containers;
·
chlorination system (including the liquid
chlorine pipework, evaporators, chlorinators and ejectors);
·
Contain and Absorb system.
9.5.13
The HAZOP considered the various operating modes of the plant
(auto/manual) as well as planned maintenance operations. Prior to the HAZOP study, previous
HAZOP studies of WTWs and chlorine leak incidents were reviewed to provide
additional input to the identification of the chlorine release scenarios.
9.5.14
In light of the recent judgement of the Court of Final Appeal (FACV
28/2005) the previous Hazard Identification Results have been carefully
reviewed for the purpose of the current assessment. In particular the latest
version of the world wide accident database MHIDAS (Major Hazard Incident Data
Service) has been independently reviewed in order to update the Hazard Identification
conclusions. However, only a few relevant chlorine incidents occurred worldwide
since the previous review, and after examination of their nature it has been
concluded that noonly minor
revisions of the previously identified hazard scenarios are necessary for this
study. They are incorporated in the
following sections where applicable.
9.5.15
Table 9-11 shows the hazards which were identified for Yam Kom
Tau WTW as a result of the review of past incident and the HAZOP studies.
9.5.16
In summary, the primary hazard arises from a loss of containment of
chlorine with subsequent acute exposure of people off-site leading to injuries
or fatalities. Releases may range
in size from a small leak (eg via a valve gland), through to dislodgement of a
fusible plug (¾" diameter) or catastrophic failure of the container
itself. The releases may be
isolatable (ie via closure of the changeover valves or drum valve) or
non-isolatable (ie a leak from the shell of the container).
9.5.17
The physical state of the release may be gas, liquid or two-phase
depending on the precise location, eg a small leak downstream of the evaporator
is likely to be gas, a leak from the 'pigtail' connection is likely to be
two-phase (due to flashing in the line), whereas a leak from the container
shell itself is likely to be liquid.
The release may arise from failure of the chlorine equipment itself or
failure induced by an external event such as an earthquake or landslide. The quantity of chlorine released may
vary from a few kilograms to several tonnes released instantaneously, eg in the
case of a severe external event such as an earthquake.
9.5.18
For releases occurring within the chlorine store a Contain and Absorb
system is provided to minimise the likelihood of the release escaping to
atmosphere. The principal failure
modes of the Contain and Absorb system, as identified at the HAZOP, are
summarised in Table 9-12.
Table
9-11 Hazards
Identified during HAZOP Study for Yau Kom Tau WTW
Hazard |
1. ACCESS
ROAD |
1.1 Fire on the truck
leading to melting of the fusible plugs on one or more containers |
1.2 Fire on the
roadside leading to melting of the fusible plugs on one or more containers |
1.3 Impact with
object during truck manoeuvring |
1.4 Lorry over-turns |
1.5 Collision with
another vehicle |
1.6 Loadshedding |
1.7 Spontaneous
container failure |
2. CONTAINER
HANDLING |
2.1 Dropped container |
2.2 Collision of
container with another object |
2.3 Accidental impact
of drum on pigtail during setdown at standby position |
2.4 Overextension
during use of truck crane (not normally used) 2.5 Section of
monorail track incorrectly aligned leading to a dropped drum |
3. CONTAINERS IN
STORAGE |
3.1 Leaking chlorine
containers |
3.2 Overfilled
containers leading to overpressurisation on thermal expansion |
3.3 Impurities in
chlorine containers, in particular nitrogen trichloride (leading to
explosion) or moisture (causing accelerated corrosion) |
3.4 Object falls onto
chlorine containers |
3.5 Fire (external or
internal) |
3.6 External
explosion |
3.7 Lightning strike |
3.8 Extreme wind |
3.9 Flooding |
3.10 Construction
activities |
3.11 Subsidence |
3.12 Landslide |
3.13 Earthquake |
3.14 Aircraft crash |
3.15 Sabotage |
3.16 Vehicle crash |
3.17 Electromagnetic
interference |
4. CONNECTION
AND DISCONNECTION OF CHLORINE CONTAINERS |
4.1 Human error or
equipment failure during connection/disconnection of containers |
5. CHLORINATION
SYSTEM |
5.1 Trapping of
liquid chlorine between closed valves and subsequent thermal expansion leading to overpressurisation of
pipework |
5.2 Pigtail failure |
5.3 Failure of fixed
chlorine pipework |
5.4 Open end on
pipework due to operator or maintenance error |
5.5 Corroded pipework |
5.6 Presence of
nitrogen trichloride in evaporator leading to explosion |
5.7 Presence of
moisture in evaporator leading to accelerated corrosion |
Table
9-12 Failure
Modes of Contain and Absorb System Identified at HAZOP Study
Hazard |
1. LEAK
DETECTION SYSTEM |
Chlorine leak detector 'cell' malfunction |
2. CONTAIN
SYSTEM |
Door left open |
Air inlet louvres fail to close on demand |
Normal ventilation system left in manual mode,
therefore does not shutdown on detection of chlorine leak |
Failure of chlorine absorption system (see
below) with dampers set to 'exhaust to atmosphere' position and failure to
detect chlorine breakthrough |
Failure of door seals |
Outage due to maintenance |
System disabled by operator |
3. CHLORINE
ABSORPTION SYSTEM |
Caustic pump failure |
Blockage in caustic pipework |
Overloading of scrubber |
Caustic valve inadvertently closed |
No caustic in tank |
Caustic pipe leakage |
Scrubber nozzles blocked |
Initial make-up of caustic incorrect |
Leakage of water into tank causing dilution of
caustic and reduced efficiency |
Degradation of caustic over a period of time |
Wrong chemical in tank |
Failure due to power failure |
Outage due to maintenance |
System disabled by operator |
9.5.19
Having
identified various possible mechanisms for a chlorine release (Table 9-11), the next step in the
Hazard Assessment is to characterise these release scenarios in terms of the
releasing inventory, hole size and phase of release (Table 9-13). This follows the approach outlined in ERM (1997a), however
the potential scenarios were re-examined and the table revised in light of the
recent CFA (FACV 28/2005) requirements with regards to Hazard Assessment.
9.5.20
Note
that, following the approach of (ERM, 2001) we conservatively assume that there
still can be “old” and “new” type chlorine canisters in use, the former having
six fusible plugs, instead of one and thus capable of releasing larger amount
of chlorine. According to the information received from WSD only the “new” type
is currently in use. However, as the number of fusible plugs is not specified
in the contract, the chlorine supplier is free to make future deliveries in
canisters with a larger number of plugs.
We therefore decided to keep the original approach.
Table
9-13 Characterisation
of Chlorine Release Scenarios
Chlorine release
scenario |
Outcome |
Releasing inventory
(tonnes) |
Hole size (diameter) |
Phase |
1.
ACCESS ROAD |
||||
1.1
Truck fire |
Considered
to result in melting of the fusible plugs on up to three drums. Three cases are considered according
to the number of 'old' and 'new' drums(1): Case
(i): 3 new drums, no old
drums Case
(ii): 2 new drums, 1 old drum Case
(iii): No new drums, 3 old drums |
3 3 3 |
3x6mm 2x6mm (new
drums) 6x6mm (old
drums) 18x6mm |
liquid liquid liquid |
1.2
Fire on the roadside |
Considered
to present a negligible off-site risk as truck does not park on site outside
the chlorine building |
- |
- |
- |
1.3
Manoeuvring accident |
Considered
to result in a single drum –small leak (eg valve gland failure) |
1 |
3mm |
liquid |
1.4
Rollover |
Single
drum - small leak (eg
valve gland failure) Single
drum - medium leak (eg
guillotine failure of drum valve) |
1 1 |
3mm 8mm |
liquid liquid |
|
Three
drums - medium leak (eg
guillotine failure of drum valves on three drums) |
3 |
3x8mm |
liquid |
|
Fire
(outcomes as item 1.1 above) |
|
|
|
1.5
Collision |
Single
drum - rupture Fire
(outcomes as item 1.1 above) |
1 |
- |
liquid |
1.6
Load-shedding |
Single
drum - small leak |
1 |
3mm |
liquid |
|
Single
drum - medium leak |
1 |
8mm |
liquid |
1.7
Spontaneous container failure |
Single
drum - medium leak |
1 |
8mm |
liquid |
|
Single
drum - large leak (eg
dislodgement of a fusible plug) |
1 |
20mm |
liquid |
|
Single
drum - rupture |
1(inst) |
- |
liquid |
2. DRUM
HANDLING |
|
|
||
2.1
Dropped drum |
Single
drum - medium leak |
1 |
8mm |
liquid |
|
Single
drum - large leak |
1 |
20mm |
liquid |
|
Single
drum - rupture |
1
(inst) |
- |
liquid |
2.2
Collision of drum with another object |
Single
drum – medium leak |
1 |
8
mm |
liquid |
2.3
Accidental impact of drum on pigtail during setdown at standby position |
Pigtail
- guillotine failure |
1 |
4.5mm |
two-phase |
2.4
Dropped drum due to incorrect alignment of monorail truck or overextension of
truck crane |
Single
drum –medium leak |
1 |
8mm |
liquid |
3.
CONTAINERS IN STORAGE |
||||
3.1
Leaking chlorine drums |
Single
drum - medium leak |
1 |
8mm |
liquid |
|
Single
drum - large leak |
1 |
20mm |
liquid |
|
Single
drum - rupture |
1
(inst) |
- |
liquid |
3.2
Overfilled drums leading to overpressurisa-tion on thermal expansion |
As
item 3.1 above |
|
|
|
3.3
Impurities in chlorine drum leading to explosion or leak |
As
item 3.1 above |
|
|
|
3.4
Object falls onto chlorine containers |
Single
drum – medium leak |
1 |
8
mm |
liquid |
3.5
Fire (external or internal) |
Since
chlorine stores are 2 hour fire-rated structures, the most significant internal source of fire is considered
to be the chlorine truck.
However, pessimistically, all truck fires are modelled as occurring
outdoors, thus this scenario is already included in Scenario 1.1. |
- |
- |
- |
3.6
External explosion |
Single
drum – medium leak |
1 |
8
mm |
liquid |
3.7
Lightning strike |
Single
drum – medium leak |
1 |
8
mm |
liquid |
3.8
Extreme wind |
Considered
to present no off-site risk as chlorine store is designed for typhoon loading |
- |
- |
- |
3.9
Flooding |
Considered
to pose no risk as flooding could only affect empty drums. |
- |
- |
- |
3.10
Construction activities |
Construction
activities could pose a significant risk to chlorine drums. However it is considered that this
'once-off' risk should be addressed through a HAZOP study prior to
commencement of construction. |
- |
- |
- |
3.11
Subsidence |
Single
drum – medium leak |
1 |
8
mm |
liquid |
3.12
Landslide |
Considered
to present no off-site risk - failure of cut slope (toe 10m from back of
chlorine store) would not cause sufficient damage to store to affect chlorine
containers (Ove Arup, 2000). |
- |
- |
- |
3.13
Earthquake(2) |
Roof
collapse: Multiple
drum-rupture |
11
(inst) |
- |
liquid |
3.14
Aircraft crash |
Roof
collapse: Multiple
drum-rupture similar to
earthquake) |
11
(inst) |
- |
liquid |
3.15
Sabotage |
Single
drum – medium leak |
1 |
8
mm |
liquid |
3.16
Vehicle crash |
Single
drum – medium leak |
1 |
8
mm |
liquid |
3.17
Electromagnetic interference |
Considered
to present no off-site risk as suitable precautions are adopted in the design
of the electrical systems. |
- |
- |
- |
|
||||
4. CONNECTION
AND DISCONNECTION OF CHLORINE CONTAINERS |
||||
4.1
Human error or equipment failure during connection or disconnection of drums |
Pigtail
- guillotine failure |
1 |
4.5mm |
two-phase |
5. CHLORINATION SYSTEM |
|
|
||
5.1
- 5.5 Failures associated with the chlorination system pipework |
Liquid
chlorine pipework - guillotine failure |
1.05(3) |
4.5mm(4) |
two-phase |
5.6
- 5.7 Failure of Evaporator |
Evaporator
- leak or rupture |
1.05 |
4.5mm |
two-phase |
Notes:
(1) 'New"
drums have a single fusible plug on each drum and make up about 85% of the
current drum stock.
"Old" drums have six fusible plugs per drum and make up the
remaining 15% of the drum stock.
The fusible plugs have a 6mm fusible core (old and new drums)
(2)
For assessment of effects of
earthquakes on chlorine store refer to Appendix 9-G and Ove Arup (2000)
(3)
Inventory of drum (1 tonne)
and evaporator (50kg)
(4)
Diameter of liquid chlorine
pipework is 20mm but limiting orifice size is that of pigtail, ie 4.5mm.
9.6.1
The assessment of the consequences of a chlorine release essentially
involves three steps:
·
modelling the initial release of chlorine
(whether inside or outside the chlorine building);
·
modelling the dispersion of chlorine in
the atmosphere;
·
assessing the toxic impact to people
off-site (whether indoors or outdoors).
9.6.2 Methodology of this study follows that of the YKT WTW QRA as described in ERM (1997a, 2001). The most important points are summarised and discussed below.
9.6.3
The initial release of chlorine or 'source term' is modelled using
standard discharge rate formulae as detailed in ERM (1997a). Releases direct from the chlorine
container are the most significant and, in the case of chlorine drums, these
are modelled as liquid releases.
9.6.4
The rapid flashing of chlorine which occurs following a liquid leak
from a drum is conservatively assumed to result in 100% entrainment of the liquid
as aerosol with no rain-out. For
catastrophic (instantaneous) liquid releases the rapid boiling of the chlorine
on contact with the ground is assumed to result in entrainment of twice the
initial flash fraction as aerosol, following Lees (1996). The remainder of the liquid chlorine is
modelled as a spreading, evaporating pool.
9.6.5 For releases of chlorine within the chlorine building, a simple 'perfect mixing' model is used to account for the initial dilution of chlorine, based on Brighton (1989a, b) and Porter (1991). Instantaneous releases of 1 tonne of chlorine are assumed to result in pressurisation of the building to the extent that there could be a release of chlorine via weak points in the building structure, eg door seals. Continuous releases are assumed to be entirely contained, except in the event of failure of the Contain and Absorb system for which two modes of failure are considered: normal ventilation remains on or a door is left open.
9.6.6 Advanced techniques had been used for prediction of the dispersion of chlorine in the atmosphere. The effects of buildings and variable ground terrain on the dispersion of chlorine were modelled. The modelling involved three elements:
·
wind tunnel simulations;
·
Computational Fluid Dynamics (CFD); and
·
flat terrain dispersion modelling.
9.6.7 The wind tunnel and CFD studies represent the 'state of the art' in dense gas dispersion modelling and provide the only rigorous means of accounting for the effects of buildings and complex terrain. Wind tunnel testing has been used in this study to investigate a range of release scenarios, wind directions and wind speeds in near-neutral atmospheric conditions. CFD has been used to determine the influence of atmospheric stability on the dispersion of chlorine and provide a broad comparison against the wind tunnel results for neutral stability. Note, that while the wind tunnel tests were conducted specifically for YKT WTW, the results of CFD dispersion modelling from for two other sites representing the extremes of topography (Sha Tin WTW and Tai Po Tau WTW) were used to supplement the wind tunnel test results. Both the wind tunnel testing and CFD modelling besides the major topographical features have included off-site high rise buildings as well as on-site buildings, as these have a significant influence on the dispersion of the chlorine.
9.6.8 The role of the flat terrain dispersion modelling had been to provide the 'source term' for both the wind tunnel and CFD studies. The model used in the study was DRIFT (Webber et al, 1992), an integral dispersion model developed by AEA Technology under the sponsorship of the UK Health and Safety Executive. DRIFT contains the necessary thermodynamics and heat transfer sub-models to be able to simulate the dispersion of a cold, aerosol-laden cloud typical of the early stage of a chlorine release. As DRIFT runs were used to simulate the full range of chlorine release rates and weather conditions. In conjunction with the wind tunnel and CFD, this provided all the data needed for input to the QRA.
9.6.9 The following probit equation has been used to estimate the likelihood of fatality due to exposure to chlorine:
Pr
= -14.3 + lnC2.3t
where
Pr
= probit value
C
= chlorine concentration (mg/m3)
t
= exposure time (minutes)
9.6.10 This probit equation is recommended for use in QRA studies by the Dutch Government (TNO, 1992) and incorporates the findings of most recent investigations into chlorine toxicity.
9.6.11
Table 9-14 shows the relationship between the chlorine
concentration and the probability of fatality for the TNO probit, assuming 10
minute exposure duration.
Table 9-14 Chlorine
Toxicity Relationship
Chlorine concentration (ppm) |
Probit value for 10 min exposure |
Probability of Fatality (LD = Lethal Dose) |
251 |
3.17 |
0.03 (LD03) |
557 |
5.00 |
0.50 (LD50) |
971 |
6.28 |
0.90 (LD90) |
9.6.12
In risk assessments for toxic gas releases it is common practice to
take into account the possibility of escape of exposed persons. This is because at lower concentrations
of the gas people may be able to obtain protection by moving indoors or
directly out of the cloud.
9.6.13
Appendix 9-F provides details of the modelling of escape from a
chlorine cloud. The methodology
followed is similar to that developed by the UK Health and Safety Executive
(Lees and Ang, 1989). It assumes
that a person out of doors will have a probability of escape dependent on the
chlorine cloud concentration, with escape occurring either directly out of the
cloud or to a nearby building. The
methodology takes into account the dose received during escape as well as the
subsequent dose in the place of refuge.
Suitable conservative assumptions are made for the time of escape
bearing in mind the debilitating effect of the chlorine gas.
9.6.14
Incorporating all the above considerations it is possible to calculate
an 'effective' outdoors fatality probability, ie the fatality probability that
can be applied to the total outdoor population at any given location taking
into account the probability of escape.
9.6.15
The consequence analysis gives three fatality probability contours for
each release scenario, corresponding to 3%, 50% and 90% nominal outdoor
fatality probability. The effective outdoors fatality probabilities
corresponding to these levels of fatality are shown in Table 9-15.
Table 9-15 Effective
Outdoors Probability of Fatality
Nominal outdoor fatality probability (for a person remaining outdoors) |
% of population attempting escape |
Effective outdoor fatality probability (taking into account the probability of
escape) |
90% |
0% |
90% |
50% |
80% |
31% |
3% |
80% |
0.7% |
9.6.16
Based on a detailed analysis presented in Appendix 9-K, the
probability of fatality for a person indoors is assumed as 5% of that for a
person remaining out of doors, i.e. nominal outdoor fatality probability.
9.6.17
Protection is also considered for people on the upper floors of
high-rise buildings. This is based
on data on the typical height of a chlorine cloud provided by the dispersion
modelling.
9.6.18
Certain groups of people, ie the very young, the elderly and the infirm
will be more sensitive to the effects of chlorine than others. This is taken into account in the
QRA by increasing the fatality rate applied to certain sensitive receivers such
as nurseries, old people homes and hospitals. The fatality rate for these
groups of people is set a factor of 3.3 higher than for the average population
(refer to Table 9-3).
9.6.19
The approach adopted for assessing the risk to road populations
essentially follows that developed under research work undertaken on behalf of
the UK Health and Safety Executive (HSE, 1998).
9.6.20
All roads within the study area that carry significant quantities of
traffic are specifically modelled in the study. Data on traffic flows, obtained from the Project Traffic
Impact Assessment and the latest Annual Traffic Census are described in Section
9.4.
9.6.21
The analysis takes into account the variation in traffic flows by
modelling five separate time periods: night, working day, weekend day, peak
hour and ‘jammed peak’, the last period representing conditions under which
traffic is at a standstill, eg due to an accident, lane restriction etc.
9.6.22 One of the key factors in modelling the effects of chlorine on road vehicles is assessing the extent to which chlorine builds up inside the vehicle and whether this could impair driving ability. HSE (1998) shows that vehicles generally afford only limited protection from toxic gas ingress and that for a major highway located 100m from a chlorine storage facility, releases of the order of 10 kg/s could give rise to concentrations sufficient to cause vehicles to come to a standstill.
9.6.23 Thus, in this study the population associated with road vehicles is modelled as partially outdoors. To account for the worst case, the traffic is considered stationary, due to the presence of traffic lights, road junctions etc or the possibility that the chlorine itself may be of sufficient concentration to bring traffic to a halt. As for other outdoors populations, allowance is made for the possibility of escape of exposed persons either directly out of the cloud or to a nearby building, although with a minimum exposure duration of 5 minutes. Calculation of the indoor population factors for different roads is explained below.
9.6.24
Tuen Mun Road is located underneath the WTW and constitutes a
significant portion of risk in comparison to other roads. For the hazard
scenarios with some longest hazard range, such as those resulted from 8tonne
instantaneous release, LD90 contour is approximately 250m from the release
point. LD50 is 250m further away from LD90, and LD03 is 500m further away from
LD50 (see Annex B). Therefore the total distance of Tuen Mun Road affected by
LD90, LD50 and LD03 are 500m, 500m and 1000m respectively.
9.6.25 It is assumed that under LD90 chlorine concentration, vehicle passengers are exposed in equivalence to 0% indoor. Vehicle itself provides no protection under such a high chlorine concentration. For LD50 the assumption is slightly relaxed and passengers are assumed to be 50% indoor. For LD03, 75% indoor is assumed. At low concentration of LD03, vehicles can provide a reasonably good protection for passengers if they stay within. However, 25% outdoor is again assumed for some passengers attempting to escape out of cars.
9.6.26 Based on the discussion, the equivalent indoor proportion for Tuen Mun Road vehicle users is:
(500x0% + 500x50% + 1000x75%)/(500+500+1000) = 50%
9.6.27
All other roads which are further away from the WTW are assumed to be
affected by LD03 at most under the worst case scenarios and the assumption of
75% indoor is applied generically.
9.6.28
The results of the 'source term' modelling of chlorine releases is
summarised in Table 9-16 below according to ERM (2001).
Table 9-16 Summary of Source Term Modelling
Results for Yau Kom Tau WTW
Release
case |
Hole
size (mm) |
Phase |
Mode
of release to atmosphere (for internal release cases only) |
Release
rate to atmosphere or instantaneous release quantity |
Release
duration (Note
1) |
External
releases (1 tonne drum) |
|
|
|
||
Small
leak |
3 |
Liquid |
- |
0.2
kg/s |
83
min |
Medium
leak |
8 |
Liquid |
- |
1.4
kg/s |
12
min |
Multiple
medium leaks |
6
(x6) |
Liquid |
- |
4.8
kg/s |
3.5
min |
Large
leak |
20 |
Liquid |
- |
8.8
kg/s |
114
s |
Rupture |
- |
Liquid |
- |
1000
kg |
- |
Internal
releases (1 tonne drum or chlorine pipework) |
|
|
|||
Pigtail
- guillotine failure |
4.5 |
Two-phase |
Normal
ventilation remains on |
0.027
kg/s |
10
min (Note
2) |
|
|
|
Door
left open |
0.011
kg/s |
10
min |
Medium
leak from drum |
8 |
Liquid |
Normal
ventilation remains on |
0.30
kg/s |
10
min |
|
|
|
Door
left open |
0.13
kg/s |
10
min |
Large
leak from drum |
20 |
Liquid |
Normal
ventilation remains on |
0.56
kg/s |
10
min |
|
|
|
Door
left open |
0.29
kg/s |
10
min |
Rupture |
- |
Liquid |
Pressurisation
of chlorine store - release via weak points (Note 4) |
5.6
kg/s |
10 s (Note
3) |
Note
1: assumes
no intervention by operating staff
Note 2: upper
limit of 10 min set for duration of releases from chlorine building (by which
time action would be taken to shut-off ventilation, close doors etc.)
Note 3: assumed
release duration for catastrophic failure of a drum, eg a split along a weld
(QRA not sensitive to this assumption)
Note
4: 'Normal
ventilation remains on' and 'Door left open' are not included for this mode of
release since 'Pressurisation of chlorine store - release via weak points' will
be more dominant in the QRA.
9.6.29
It is apparent from Table 9-16 that releases from a drum due to
melting of the fusible plugs (4.8 kg/s) or dislodgement of a plug (8.8 kg/s)
occur sufficiently rapidly to cause emptying of the drum in a short period of
time (within a few minutes).
Therefore these release cases are treated as effectively instantaneous
releases.
9.6.30
It is also apparent that the chlorine building has a significant effect
in modifying the release of chlorine to the atmosphere, given failure of the
Contain and Absorb system. The
rate of chlorine release is reduced dramatically (eg for a medium leak the rate
of chlorine to atmosphere is reduced from 1.4kg/s to 0.30kg/s or 0.13kg/s) and
the chlorine becomes diluted in the building air. The failure mode of the Contain and Absorb system 'Normal
ventilation remains on' is a more severe case than 'Door left open' in terms of
the chlorine release rate to atmosphere.
This is because the normal ventilation (typically 2.6 air changes per
hour) provides a more rapid release of chlorine to the environment than if a
door is left open (normal ventilation shutdown, chlorine scrubber system in
operation).
9.6.31
The results of the wind tunnel testing for Yau Kom Tau WTW are
summarised below in Table 9-17 and Figures B.1 to B.13 in Appendix
9-B.
Table 9-17 Summary of Wind Tunnel Tests Results
for Yau Kom Tau WTW
Release case |
Release location |
Description |
Weather Class |
Wind directions (Note 1) |
Maximum extent of LD03 contour (m) (Note 2) |
50
kg (vapour) instantaneous |
Chlorine
store |
Chlorine
vapour release due to rupture of chlorine drum leading to pressurisation of
store and release via weak points. |
D2 |
S E N W |
195 No
LD03 contour off-site 169 273 |
1
tonne (aerosol) instantaneous |
Access
Road |
Catastrophic
failure of a chlorine conrtainer |
D2 |
S SE E NE N NW W SW |
435 468 520 663 390 468 585 696 |
1
tonne (aerosol) instantaneous |
Access
Road |
Catastrophic
failure of a chlorine container |
D5 |
W NE |
332 299 |
Note
1: Direction which wind
blows from
Note 2: Downwind distance to 3%
nominal outdoor fatality probability, ie not taking into account escape and assuming 10 min
exposure duration or cloud passage time (whichever is the shorter)
9.6.32
From the results in Table 9-3 above, Appendix 9-B and
RWDI (1998), the key findings of the wind tunnel testing may be
summarised. The downwind hazard
range is significant for both internal 1 tonne instantaneous releases (modelled
as 50kg (vapour) instantaneous releases) (169-273m) and external 1 tonne
instantaneous releases (390-696m).
Topography significantly influences the dispersion characteristics of
chlorine releases at Yau Kom Tau WTW, as manifested by:
·
flow reversal due to creation of a wake
zone at the site of the WTW for winds from the N (ie over the ridge) (Figures B2 and B8
in Annex B);
·
curtailment of dispersion up the slope on
which the WTW is situated leading to shorter, broader clouds (Figures B4
and B5 in Annex B);
·
channelling of chlorine releases along
Tuen Mun Road and around nearby high rise estates (Figures B6, B9 and
B10 in Annex B).
9.6.33
The wind tunnel testing for Yau Kom Tau WTW did not include the 1.4
kg/s continuous release case, as was done for Sha Tin, Pak Kong and Tai Po Tau
WTWs. The reason for this is that
an independent technical review of the wind tunnel testing (Webber, 1998)
highlighted the limitation of modelling this type of release in the wind tunnel
(1:500 scale) due to the difficulty of accurately simulating turbulence close
to the ground near the source of the release. The QRA for Yau Kom Tau WTW therefore makes use of the
results of the CFD modelling for this type of release, described below.
9.6.34
CFD modelling was performed for Sha Tin WTW and Tai Po Tau WTW. Details
can be found in ERM (2001), HSL (1998a) and HSL (1998b). The summary of these results is
provided in Table 9-18 and the LD contours are shown in Appendix 9-C.
Table 9-18 Summary of CFD
Modelling Results
Release case |
Weather class |
Maximum Extent of LD Cobtour (m) |
||
LD90 |
LD50 |
LD03 |
||
Sha Tin WTW |
|
|
|
|
1.4 kg/s continuous |
D2 |
110 |
140 |
205 |
|
F2 |
145 |
155 |
225 |
1 tonne instantaneous |
D2 |
170 |
200 |
255 |
|
F2 |
220 |
255 |
275 |
Tai Po Tau WTW |
|
|
|
|
1.4 kg/s continuous |
D2 |
135 |
165 |
265 |
|
F2 |
130 |
180 |
330 |
1 tonne instantaneous |
D2 |
200 |
215 |
255 |
|
F2 |
180 |
255 |
355 |
|
B2 |
75 |
95 |
105 |
9.6.35
The key findings of the CFD modelling may be summarised as follows:
·
atmospheric stability does not significantly
influence the hazard range of either a 1.4 kg/s continuous release of chlorine
or a 1 tonne instantaneous release of chlorine for the two weather conditions
of most interest in this study (ie D - neutral stability and F - stable
conditions). This is because, in
the presence of buildings and complex, heavily-vegetated terrain, atmospheric
stability has less of an influence on chlorine dispersion;
·
for B (unstable conditions) the CFD results for
Tai Po Tau WTW indicate that the chlorine hazard range is significantly reduced
compared to neutral conditions (ie a factor of 2.5 shorter for a 1 tonne
instantaneous release). It is
indicated that this is due to the unstable wind field which significantly
enhances vertical dispersion of the chlorine. However, as B conditions account for no more than 20% of the
weather in Hong Kong, this is not considered a significant factor for the QRA
(ie risks are not considered to be significantly overestimated by ignoring B
conditions); and
·
for F (stable conditions) the CFD results for
Tai Po Tau WTW indicate that, whilst the chlorine hazard range is not
significantly affected by atmospheric stability, the direction of travel of the
chlorine cloud may be affected. At
Tai Po Tau WTW, the chlorine releases in F conditions more closely followed the
topographic contours than the equivalent releases in D conditions, which
followed the direction of the wind.
9.6.36
The results of the flat terrain dispersion modelling using DRIFT are
summarised in Table 9-19 below.
Annex A contains the results of all the DRIFT runs undertaken.
Table 9-19 Summary of DRIFT
Modelling Results
Release case |
Weather class |
Downwind distance (m) |
||
LD90 |
LD50 |
LD03 |
||
0.2 kg/s continuous |
D2 |
86 |
119 |
182 |
1.4 kg/s continuous |
D2 |
268 |
362 |
550 |
1 tonne instantaneous |
D2 |
325 |
425 |
600 |
3 tonne instantaneous |
D2 |
586 |
735 |
1044 |
10 tonne instantaneous |
D2 |
1004 |
1286 |
1790 |
9.6.37
From the results in Table 9-18 it is possible to derive a
relationship between the chlorine release rate (or release quantity) and the
downwind hazard range. This is
shown graphically in Figures A1 and A2 in Appendix 9-A. This relationship is used in the QRA,
as described below.
9.6.38
Table 6.1shows the relationship between the chlorine concentration and
the probability of fatality for the TNO probit, assuming 10 minute exposure
duration.
·
the chlorine hazard range predicted by
the wind tunnel testing is generally shorter than that predicted by the DRIFT
flat terrain dispersion modelling.
This highlights the importance of modelling the effects of buildings and
complex terrain, which act to increase turbulence and cause greater mixing of
the chlorine. (It should also be
noted that there is an inherent limitation in models such as DRIFT, whereby the
surface roughness chosen must be small in relation to the cloud height. For dense gas release this limits the
scope of DRIFT-type simulations to relatively smooth terrain, which is not
applicable to Hong Kong conditions);
·
the hazard range predicted by the wind
tunnel for 1 tonne instantaneous releases are greater than those predicted by
the CFD modelling for Sha Tin WTW and Tai Po Tau WTW. The reason for this is not clear, however, as the wind
tunnel results err on the conservative side (whilst eliminating the pessimism
in the DRIFT-type predictions for these releases) they will be used in
preference in the QRA.
9.6.39
The
preceding sections have discussed the results arising from the various strands
of work on chlorine dispersion modelling.
The following paragraphs summarise how these results will be applied in
the QRA. More details are provided
in Appendix
9-D.
9.6.40
Wind
tunnel testing: the wind
direction-specific cloud shapes generated in the wind tunnel will used directly
in the QRA. This will achieved
through use of Graphical Information Systems (GIS) software which is described
in further detail below. Another
output of the wind tunnel testing was the influence of wind speed on the
chlorine hazard range. From the
wind tunnel test results for all eight WTWs a simple scale factor was derived
to modify the cloud contours for the 2m/s wind speed case to determine those
for the 5m/s case.
9.6.41
CFD
modelling: the CFD modelling results show no significant influence of
atmospheric stability on the chlorine hazard range (for D and F conditions),
therefore this parameter is not considered further in the QRA. However, the CFD results for the 1.4
kg/s continuous release case (D2 weather conditions), which are consistent for
Sha Tin WTW and Tai Po Tau WTW, are used in the QRA for YKT WTW.
9.6.42
DRIFT
modelling: the DRIFT flat terrain dispersion modelling results are not used
directly in the QRA. However the
relationships derived from the DRIFT modelling for the chlorine release
rate/quantity versus hazard range are used to scale the wind tunnel results for
the complete range of release scenarios which need to be considered in the
QRA. The method of simple, uniform
scaling provides a sufficiently accurate approach where the terrain surrounding
the WTW is relatively flat.
However, where there are significant topographic features, then the
uniform scaling approach provides only a crude approximation to the cloud
shape. In these situations, where
the uniform scaling approach does not provide sufficient accuracy, the
topographic features (e.g. hills) have been taken into account by allowing them
to modify the shape of the chlorine cloud, whilst preserving the cloud
area.
9.6.43
One
further aspect which needs to be considered in applying the results of the wind
tunnel testing in the QRA is the number of individual wind tunnel directions
which are considered. In the wind
tunnel testing up to eight wind directions were typically modelled for the most
important release scenarios (e.g. a 1 tonne instantaneous release). However, in a QRA, it is usually
necessary to consider a greater number of possible directions, in order to
eliminate any spurious, numerical error in the risk results. The process of interpolating between
the modelled wind directions is called 'wind smoothing' (achieved
mathematically in software such as RISKPLOT the Consultants' proprietary risk
integration tool).
9.6.44
The
application of wind smoothing in this study was considered in detail in
Technical Note 1 (ERM, 1998). It
was concluded that for sites with relatively flat surrounding terrain, wind
smoothing could be achieved by the simple method of cloud 'rotation' (ie
rotation of clouds to fill the directional 'gaps' left by the wind
tunnel). However for sites with
complex terrain and/or high rise buildings, such as Yau Kom Tau WTW, it would be necessary to demonstrate
that the important effects of the topography and buildings had been adequately
captured in the raw wind tunnel data.
However, in the case of Yau Kom Tau WTW sufficient number of wind
directions have been modelled in the wind tunnel to capture the important
topographic influences.
9.6.45
Information
on the height of a chlorine cloud has been obtained from the wind tunnel
simulations (Sha Tin WTW), CFD modelling (Sha Tin WTW and Tai Po Tau WTW) and
DRIFT flat terrain dispersion modelling. This is useful for determining the
degree of protection of people inside high rise buildings. The data, presented
in detail in Appendix
9-E, have
been rationalised for use in the QRA as shown in Table 9-19 below.
Table
9-1920 Chlorine Cloud
Heights
Release case |
Chlorine cloud height (m) (Note 1) |
Equivalent number of storeys (Note 2) |
1.4 kg/s continuous |
30 |
10 |
1 tonne instantaneous |
6 |
2 |
10 tonne instantaneous |
9 |
3 |
Note 1: Note
that this is not the full height of the chlorine cloud. It is the height up to which the ground
level chlorine concentration is assumed to apply for the purpose of calculating
numbers of fatalities in tall buildings.
Note 2: Assumes 3m per
storey
9.7.1
The
consequence analysis from wind tunnel testing and CFD modelling shows that only
certain, severe types of chlorine release which could produce fatal off-site
concentrations of chlorine (refer to Tables 9-17 and 9-18). The
release cases which fall into this category are external continuous releases of
1.4 kg/s or more (equivalent to guillotine failure of a drum valve) and
instantaneous releases of 1 tonne or more whether external or internal.
9.7.2
Appendix 9-F summarizes the results of modelling of escape from chlorine cloud.
9.7.3
These
results mean that some of the chlorine release scenarios identified in Section
5 (Table 9-8) can be eliminated from
further consideration in the QRA. Table 9-21 considers each release
scenario in turn and, based on the results of the consequence analysis,
determines whether the scenario poses an off-site hazard. Table 9-22 then summarises the results of the analysis in Table 9-21 by grouping the release
scenarios into 'events' having identical release characteristics (ie the same
release rate, duration and phase of release), eg
·
'truck fire - 3 new drums' (2.4 kg/s) is grouped
together with 'rollover - 3 drums medium leak' (4.2 kg/s) into RU1TMML (4.2
kg/s). This is a simplification
erring on the conservative side for the truck fire release;
·
the group RU1TSML (1.4 kg/s) has the following
release scenarios grouped together: 'rollover - single drum medium leak',
'loadshedding - single drum medium leak' and 'spontaneous container failure -
single drum medium leak'..
·
the group RU1TSRU (1 tonne) has the following
release scenarios grouped together: 'truck fire - 2 new drums/1 old drum' (1.6
kg/s plus 4.8 kg/s), 'collision - single drum rupture' (1 tonne), 'spontaneous
container failure - single drum large leak' (8.8 kg/s), and 'spontaneous
container failure - single drum rupture' (1 tonne). The truck fire scenario was
put in this group since the leak from the 'old' drum (4.8 kg/s) empties the
drum so quickly such that it can be considered to be an instantaneous release
from the drum. Similarly so for
'spontaneous container failure - single drum large leak' (8.8 kg/s).
9.7.4
Table 9-21 shows the events grouped according to the leak quantity. The
classification as a “significant off-site hazard” is based on the results of consequence
analysis (refer to Section 9.6).
Table 9-21 Rationalisation of Chlorine Release
Scenarios
Chlorine
release scenario |
Outcome |
Hole
size |
Phase |
Chlorine
release rate from primary source (kg/s) |
Chlorine
release quantity (tonnes) |
Chlorine
release rate (or quantity) to
atmosphere |
Significant off-site
hazard ? (Y/N) |
Event
Ref(2) |
1.
ACCESS ROAD |
|
|||||||
1.1
Truck fire |
Considered
to result in melting of the fusible plugs on up to three drums. Three cases are considered according
to the number of 'old' and 'new' drums: Case
(i): 3 new drums,
no old drums Case
(ii): 2 new drums,
1 old drum Case
(iii): No new
drums, 3 old
drums |
3x6mm 2x6mm (new
drums) 6x6mm (old
drums) 18x6mm |
liquid liquid liquid |
2.4 1.6 4.8 14.4 |
3 2 1 3 |
2.4
kg/s(3) 1.6
kg/s 4.8
kg/s(4) 14.4
kg/s(4) |
Y Y Y |
RU1TMML RU1TSRU RU1TMRU |
1.3
Manoeuvring accident |
Single
drum - small leak |
3mm |
liquid |
0.2
|
1 |
0.2
kg/s |
N |
- |
1.4
Rollover |
Single
drum - small leak Single
drum - medium leak |
3mm 8mm |
liquid liquid |
0.2
1.4 |
1 1 |
0.2
kg/s 1.4
kg/s |
N Y |
- RU1TSML |
|
Three
drums - medium
leak |
3x8mm |
liquid |
4.2 |
3 |
4.2
kg/s |
Y |
RU1TMML |
|
Fire
(outcomes as item 1.1 above) |
|
|
|
|
|
|
|
1.5
Collision |
Single
drum - rupture Fire
(outcomes as item 1.1 above) |
- |
liquid |
- |
1
(inst) |
1
tonne |
Y |
RU1TSRU |
1.6
Loadshedding |
Single
drum - small leak |
3mm |
liquid |
0.2 |
1 |
0.2
kg/s |
N |
- |
|
Single
drum - medium leak |
8mm |
liquid |
1.4 |
1 |
1.4
kg/s |
Y |
RU1TSML |
1.7
Spontaneous container failure |
Single
drum - medium leak |
8mm |
liquid |
1.4 |
1 |
1.4
kg/s |
Y |
RU1TSML |
|
Single
drum - large leak |
20mm |
liquid |
8.8 |
1 |
8.8
kg/s(4) |
Y |
RU1TSRU |
|
Single
drum - rupture |
- |
liquid |
- |
1(inst) |
1
tonne |
Y |
RU1TSRU |
2. DRUM
HANDLING |
|
|||||||
2.1
Dropped drum |
Single
drum - medium leak |
8mm |
liquid |
1.4 |
1 |
0.30
kg/s |
N |
- |
|
Single
drum - large leak |
20mm |
liquid |
8.8 |
1 |
0.56
kg/s |
N |
- |
|
Single
drum - rupture |
- |
liquid |
- |
1
(inst) |
57
kg |
Y |
IU1TSRU |
2.2
Collision of drum with another object |
Single
drum - medium leak |
8mm |
liquid |
1.4 |
1 |
0.30
kg/s |
N |
- |
2.3
Accidental impact of drum on pigtail during setdown at standby position |
Pigtail
- guillotine failure |
4.5mm |
two-phase |
0.12 |
1 |
0.027
kg/s |
N |
- |
2.4
Dropped drum due to incorrect alignment of monorail track or overextension of
truck crane |
As
item 2.1 above |
|
|
|
|
|
|
|
3.
CONTAINERS IN STORAGE |
|
|||||||
3.1
Leaking chlorine drums or Scenarios , 3.11, 3.15 of Table 5.5 which are
considered to result in a medium leak only) |
Single
drum - medium leak |
8mm |
liquid |
1.4 |
1 |
0.30
kg/s |
N |
- |
|
Single
drum - large leak |
20mm |
liquid |
8.8 |
1 |
0.56
kg/s |
N |
- |
|
Single
drum - rupture |
- |
liquid |
- |
1
(inst) |
56
kg |
Y |
IU1TSRU |
3.2
Overfilled drums leading to overpressurisation on thermal expansion |
As
item 3.1 above |
|
|
|
|
|
|
|
3.3
Impurities in chlorine drum leading to explosion or leak |
As
item 3.1 above |
|
|
|
|
|
|
|
3.4
Object falls onto chlorine containers |
Single
drum - medium leak |
8mm |
liquid |
1.4 |
1 |
0.30
kg/s |
N |
- |
3.6
External Explosion |
As
item 3.4 above |
|
|
|
|
|
|
|
3.7
Lightning Strike |
As
item 3.4 above |
|
|
|
|
|
|
|
3.11
Subsidence |
As
item 3.4 above |
|
|
|
|
|
|
|
3.12
Earthquake |
Roof
collapse: multiple
drum-rupture |
- |
liquid |
- |
11
(inst) |
7.7
tonnes(1) |
Y |
EU1TMRU EU1TMRUH |
3.12
Aircraft crash |
Roof
collapse: multiple
drum-rupture (similar to earthquake) |
- |
liquid |
- |
11
(inst) |
7.7
tonnes(1) |
Y |
AU1TMRU |
4. CONNECTION
AND DISCONNECTION OF CHLORINE CONTAINERS |
|
|||||||
4.1
Human error or equipment failure during connection/disconnection of drums |
Pigtail
- guillotine failure |
4.5mm |
two-phase |
0.12 |
1 |
0.027
kg/s |
N |
- |
5. CHLORINATION SYSTEM |
|
|||||||
5.1
- 5.5 Failures associated with the chlorination system pipework |
Liquid
chlorine pipework - guillotine failure |
4.5mm |
two-phase |
0.12 |
1.05 |
0.027
kg/s |
N |
- |
5.6
- 5.7 Failure of Evaporator |
Evaporator
- leak or rupture |
4.5mm |
two-phase |
0.12 |
1.05 |
0.027
kg/s |
N |
- |
Note (1): For large instantaneous
releases, 70% of the chlorine is estimated to be released instantaneously to
atmosphere as vapour and entrained aerosol. This comprises the initial vapour flash fraction (19%) plus
the entrained aerosol (2 x 19%) plus the contribution from the evaporating
chlorine pool over the first minute (around 10% depending on the pool size).
Note (2): Key
to event ref
E R
(Road) or E (Earthquake) or A (Aircraft crash) or I (internal)
U U
(Unisolated) or I (Isolated)
1T 1T
(1 tonne drums) or 50 (50 kg cylinders)
M S
(Single) or M (Multiple)
RU RU
(Rupture), LL (Large Leak), ML (Medium Leak) or SL (Small Leak)
H Earthquake
of higher ground acceleration
Note (3): This release (2.4 kg/s) treated as a multiple medium leak for
simplification (conservative assumption)
Note (4): These releases treated as effectively instantaneous releases
due to short release duration
Table 9-22 Release Scenarios Included in YKT WTW
QRA
Event Ref |
Component scenarios |
Release rate (or quantity)
to atmosphere |
Type of release |
Release location |
IU1TSRU |
Spontaneous
failure Dropped
drum |
56
kg |
Instantaneous |
Chlorine
store |
RU1TSML |
Rollover Loadshedding Spontaneous
failure |
1.4
kg/s |
Continuous |
Access
road |
RU1TMML |
Rollover Truck
fire |
4.2
kg/s |
Continuous |
Access
road |
RU1TSRU |
Truck
impact Truck
fire Spontaneous
failure |
1
tonne |
Instantaneous |
Access
road |
RU1TMRU |
Truck
fire |
3
tonnes |
Instantaneous |
Access
road |
EU1TMRU |
Earthquake:
roof collapse, ground acceleration 0.5g |
7.7
tonnes |
Instantaneous |
Chlorine
store |
EU1TMRH |
Earthquake:
roof collapse, ground acceleration 0.8g |
7.7
tonnes |
Instantaneous |
Chlorine
store |
AU1TMRU1G |
Aircraft
crash: roof collapse, |
7.7
tonnes |
Instantaneous |
Chlorine
store |
Table 9-23 Release Scenarios Categorised by Leak
Quantity
Leak Quantity (kg) |
Event Ref |
0-10 |
None |
10-100 |
IU1TSRU |
100-1000 |
RU1TSML, RU1TMML, RU1TSRU |
>1000 |
RU1TMRU, EU1TMRU, EU1TMRUH AU1TMRU |
9.7.5
Having
identified the chlorine release scenarios of interest (Section 9.5) the next step in the
Hazard Assessment is to determine their frequency of occurrence. This is based on the approach outlined
in the Consultants' Methodology Report (ERM, 1997a).
9.7.6
In
light of the recent judgement of the Court of Final Appeal (FACV 28/2005) that
methodology has been carefully reviewed for the purpose of the current
assessment. In particular the latest version of the world wide accident
database MHIDAS (Major Hazard Incident Data Service) has been independently
reviewed. However, only a few
relevant chlorine incidents occurred worldwide since the previous review, and
after examination of their nature it has been concluded that no significant
revisions of the previous event frequencies are necessary for this study.
9.7.7
It
should be noted that for the sake of consistency and to allow for a potential
increase in the future, the estimated frequencies of truck-related incidents
are still based on the 1187 tonnes per year chlorine use assumed in the
previous assessment, while according to the latest information the current
chlorine use at YKT WTW is only 100 tonnes per year (refer to Table 9-1). Similarly, as discussed
in Section
9.5, the
“old type” chlorine containers, that can release more chlorine in accidents are
still accounted for in the present assessment, even that they are currently not
in use.
9.7.8
Table 9-24 summarises the base data which has been used in the frequency
calculations. Appendix 9-I contains the details of how
this data has been used to determine the frequency of each of the events listed
in Table
9-22. Table 9-25 summarises the results of the frequency
calculations.
Table 9-24 Base Failure Rate Data
Data item |
Value |
Units |
Source |
1. Chlorine container |
|
|
|
1.1 (i) Spontaneous container failure
frequency (ii) Conditional probability of
catastrophic failure (iii) Conditional probability of medium
leak (iv) Conditional probability of large
leak |
1.5E-4 0.027 0.22 0.081 |
per year - - - |
Methodology Report
(based on review of worldwide failure data for chlorine containers and
generic pressure vessel failure data) |
1.2
(i) Probability of dropped
container (ii) Conditional probability
of
catastrophic failure |
7.7E-6 1.0E-4 |
per lift - |
Methodology Report
(based on Hong Kong data for number of lifts which have occurred without
incident) |
2. Chlorine delivery vehicle |
|
|
|
2.1 (i) Frequency of load shedding (ii) Conditional probability of a medium
leak |
1.1E-7 6.3E-2 |
per truck-km - |
Chlorine Transport Risk Study, DNV (1997) |
2.2 (i) Frequency of rollover (ii) Conditional probability of a
medium leak of a single drum (iii) Conditional probability of
medium leak of multiple
drums |
1.9E-7 1.5E-1 1.1E-2 |
per truck-km - - |
Chlorine Transport Risk Study, DNV (1997) |
2.3 (i) Frequency of vehicle impact (ii) Conditional probability of
drum rupture |
4.0E-7 1.7E-2 |
per truck-km - |
Chlorine Transport Risk Study, DNV (1997) |
2.4 (i) Frequency of spontaneous
truck fire (ii) Probability of having 2 or
3
'old' drums among the 3 ruptured drums (iii) Probability of having 1 'old'
drum among the 3 ruptured drums (iv)
Probability of having nil 'old'
drums among the 3 ruptured drums |
4.0E-9 0.061 0.33 0.61 |
per truck-km - - - |
Chlorine Transport Risk Study, DNV (1997) |
3. External events |
|
|
|
3.1 (i) Frequency of earthquake of
0.5g ground acceleration(1) (ii) Probability of roof collapse in an
earthquake of 0.5g ground
acceleration |
3.3E-6 0.1 |
per year - |
Cook et al (1993) Water Treatment Works Seismic Hazard
Assessment, Ove Arup (2000) |
3.2 (i) Frequency of earthquake of
0.8g ground acceleration(2) (ii) Probability of roof collapse in an
earthquake of 0.8g ground
acceleration |
1.4E-7 0.5 |
per year - |
Cook et al (1993) Water Treatment Works Seismic Hazard
Assessment, Ove Arup (2000) |
3.3 Frequency of aircraft crash |
1.2E-8 |
per landing |
Based on US National Transportation Safety
Board aircraft crash data (Appendix 9-H) |
Note
1: Approximately equivalent to MMX
Note
2: Approximately equivalent to
MMXI-XII
Note
3: Seismic Hazard Assessment is
attached in Appendix
9-G
Table 9-25 Event Frequencies - Base Case of WTW
QRA
Event Ref |
Component scenarios |
Frequencies (per year) |
Time periods during which event could occur |
IU1TSRU |
Dropped drum Spontaneous drum failure |
1.83E-6 2.60E-4 |
All except Night All |
|
Total |
2.62E-4 |
|
RU1TSML |
Rollover Loadshedding Spontaneous failure |
1.13E-6 2.75E-7 1.79E-7 |
All except Night All except Night All except Night |
|
Total |
1.58E-6 |
|
RU1TMML |
Rollover Truck fire |
8.29E-8 9.73E-8 |
All except Night All except Night |
|
Total |
1.80E-7 |
|
RU1TSRU |
Truck impact Truck fire Spontaneous drum failure Total |
2.69E-7 5.15E-8 8.78E-8 4.08E-7 |
All except Night All except Night All except Night |
RU1TMRU |
Truck fire |
9.63E-9 |
All except Night |
EU1TMRU |
Earthquake |
3.30E-7 |
All |
EU1TMRUH |
Earthquake |
7.00E-8 |
All |
AU1TMRU |
Aircraft crash |
1.36E-8 |
All |
9.7.9
Following
the QRA for the base case WTW operation, a number of possible mitigation
measures were discussed and three of them recommended for implementation in
order to reduce the societal risk As Low As Reasonably Practicable (see ERM,
2001).
9.7.10
These
mitigation measures included provision of a containment barrier at the S
boundary of the WTW site, improvements to the access road and improved
protection to the WTW staff quarters.
Since such measures had been since implemented, the present study is
based on the mitigated scenario of ERM (2001). Thus, in accordance with the mitigated scenario of the previous study, the event frequencies for
RU1TSRU and RU1TMML have been reduced by 33% and those for RU1TSML by 45% as
compared to those listed in Table 9-25 and Annex
9-I. The
frequencies for all other events remain unchanged.
9.7.11
The
event frequencies that are used in this study, ie basically those used for the mitigated case in of the previous assessment are listed in Table 9-26 for each of the time
periods considered in the study.
Table 9-26 Frequencies
(times per year) of Chlorine Release Events used in the Present Study
Event Ref |
Peak Hour |
Jammed Peak |
Night |
Working Day |
Weekend Day |
|
IU1TSRU |
3.52E-05 |
2.34E-06 |
1.30E-04 |
6.88E-05 |
2.50E-05 |
|
RU1TSML |
2.33E-07 |
1.55E-08 |
0.00E+00 |
4.56E-07 |
1.66E-07 |
|
RU1TMML |
3.23E-08 |
2.14E-09 |
0.00E+00 |
6.32E-08 |
2.30E-08 |
|
RU1TSRU |
7.34E-08 |
4.88E-09 |
0.00E+00 |
1.44E-07 |
5.22E-08 |
|
RU1TMRU |
2.58E-09 |
1.71E-10 |
0.00E+00 |
5.04E-09 |
1.83E-09 |
|
EU1TMRU |
4.42E-08 |
2.94E-09 |
1.65E-07 |
8.64E-08 |
3.14E-08 |
|
EU1TMRUH |
9.37E-09 |
6.23E-10 |
3.50E-08 |
1.83E-08 |
6.66E-09 |
|
AU1TMRU |
1.82E-09 |
1.21E-10 |
6.80E-09 |
3.56E-09 |
1.29E-09 |
|
9.8.1
The
QRA combines information on the consequences of chlorine releases with
information on the likelihood of releases to generate two measures of risk
-individual risk and societal risk.
Individual risk is the chance of death per year to a specified
individual at a specific location.
Societal risk is the risk to the population as a whole.
9.8.2
The
QRA will be undertaken using a GIS-based software application, GISRisk
developed specifically for the WTW project. The GIS component of the software enables the complex cloud
shapes generated by the wind tunnel to be input directly into the QRA. GISRisk is an application of
standard, well-validated, commercial software, ie ESRI's ARCVIEW GIS software,
Microsoft Access and Microsoft Excel.
9.8.3
Associated
with the GIS software is a database containing all the relevant information
relating to the WTW, the defined events, the meteorological data, the
population data and the chlorine cloud coordinates. The database contains the routines for the calculation of
individual and societal risk.
9.8.4
For
the purposes of the present study the database pertinent to the ERM-HK (2001)
case for the 2006 population and assuming implementation of the recommended
mitigation measures has been modified to include the latest population
estimates (refer to Section 9.4). The main outputs from the software are as follows:
·
Individual risk
in the form iso-risk contours overlaid on a base map of the area;
·
Societal risk
in the form of an FN curve,
which is a graphical representation of the cumulative frequency (F) of N or
more fatalities plotted against N on a log-log scale; and
·
Societal risk
in the form of a Potential Loss of Life (PLL)
value, which expresses the risk to the population as a whole and for each
scenario and its location.
The PLL is an
integrated measure of societal risk obtained by summing the product of each f-N
pair, as below:
PLL
= f1N1+f2N2+fnNn....
9.8.5
As
outlined in Section 4.2.2, the QRA is conducted in this Study for a number of
scenarios differing by their population assumptions. Five detailed population
data sets reflecting the 2006 projections of ERM (2001) and various estimates
for the present study have been discussed in Section 4.2 and listed in Table
4.2. Note that while the road
populations could be reliably estimated based on the detailed Traffic Impact
Assessment forecasts for the project, adequate general population projections
are not available so our estimates could only be based on publicly available
data such as Planning Department forecasts (PlanD, 2006) and the information
gathered during the site visits. Thus, while our population projections form a
basis for the principal scenarios, as a control exercise we also repeat the
model runs using the same general population data as in the previous study
(ERM, 2001).
9.8.6
Note
that all these cases differ only by their population assumptions. All other
assumptions of the study remain the same for all scenarios. The following
scenarios are being considered:
·
Case
1 is a scenario using the 2006 population estimates of the
previous assessment (ERM, 2001). It is included here as a background case, for
comparison with the other scenarios;
·
Case
2 uses the same general population data as Case 1, but the road
populations reflect the traffic projections for 2030, after the completion of
the project;
·
Case
3 is similar to Case 2 but the road populations reflect the
2015 construction phase of the project;
·
Case
4 uses the updated general population data and the
2030 projection for the road populations; and
·
Case
5 involves the updated general population data,
but concerns the 2015 construction phase of the project.
·
Societal risk results for the Tseun Wan Rd
population only, during the construction and operational phase of the Project
are also presented
9.8.7
The
Hong Kong Planning Standards and Guidelines (HKPSG), Chapter 12 require
that Potentially Hazardous Installations (PHIs) comply with Government Risk
Guidelines. The same risk guidelines are stipulated under EIAO in Annex 4 of Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). Acceptable risk
levels are defined as follows:
·
Individual Risk:
The maximum involuntary individual risk of death associated with accidents
arising at PHIs should not exceed 1 chance in 100,000 per year (10-5/yr).
·
Societal Risk:
The societal risk associated with a PHI should comply with the FN diagram (Fig
3 in HKPSG, Ch 11, also shown here in Figures 8.1 and 8.2). Three areas of risk are shown:
(i)
Acceptable where risks are so low that no action is
necessary;
(ii)
Unacceptable where risks are so high that they should
usually be reduced regardless of the cost or else the hazardous activity should
not proceed; and
(iii)
ALARP (As Low As Reasonably Practicable) where
the risks associated with each probable hazardous event at the PHI should be
reduced to a level ‘as low as reasonably practicable’, usually measured as a
trade off between the risk reduction afforded and the cost of that
reduction. Risk mitigation
measures may take the form of either engineered measures at the PHI or
development (ie population) controls in the vicinity of the PHI.
9.8.8
The
societal risk results for the areas surrounding YKT WTW (refer to Figure 9-5) are presented in Figure 9-6 and 9-7 in the form of FN
curves. Both the “background”
general population (Case 2 and Case 3, Figure 9-6) and the “updated” general population scenarios (Case
4 and Case 5, Figure
9-7) are
compared with the HKPSG Risk Guidelines and the Case 1 results, for the
“background” scenario of ERM (2001). The FN curves for the construction and
operation phases excluding the surrounding populations are also included in
Figure 9-6 and repeated in Figure 9-7. These include the Tsuen Wan Rd
population only, and for the construction phase also the temporary project
office (items 35 and 40 of Table 9-3)
9.8.9
As
can be seen, the shape of the FN curves is mostly influenced by the general
population projections – the cases differing only by the assumed road
populations (Cases 1-3 in Figure 9-6 and Cases 4 and 5 in Figure 9-7) have very similar FN curves, with the only
exception of F for N=1, which in both figures is significantly lower for the
construction phase scenarios. An analysis of the detailed results suggests that
the difference for N=1 is a result of the short-range IU1TSRU event and the
different road populations of Tuen Mun Road assumed for the construction and
operational phases. For other N values neither the constructional nor
operational phase of the project has a great influence on societal risk
results.
9.8.10
On
the other hand, the introduction of the “updated” general populations that
besides adding a few new residential development involved reduction of the
population of WTW Staff Quarters, Yau Kom Tau squatters and removing the
population of Tsuen Wan Bay Further Reclamation resulted in a significant
lowering of the F levels in the 100 to 800 N interval.
9.8.11
Nevertheless,
similar to the ERM (2001) results, for N greater than 20 and less than about
800 all of these FN curves exceed
are in the ALARP criterionregion,
and, but remain well below the
“Unacceptable” levels.
9.8.12
The
FN results for the Tsuen Wan Rd population only (that for the construction
phase includes both the project workforce, and the vehicular population) are
low, and well within the “Acceptable” zone.
9.8.13
The details of FN curve for the most relevant Case 4 (operational phase of the Project) are given in Table 9-27, which also shows the
breakdown of the F values between the different chlorine release scenarios
(refer to Table 9-22).
9.8.14
Table 9-27 Breakdown
of the Case 4 FN Data by Release
Scenario
N |
F
:Total |
EU1TMRU |
EU1TMRUH |
AU1 TMRU |
RU1 TMML |
RU1TSML |
RU1 TMRU |
RU1 TSRU |
IU1 TSRU |
1 |
3.14E-06 |
3.30E-07 |
6.98E-08 |
1.36E-08 |
5.96E-08 |
2.31E-07 |
9.53E-09 |
1.79E-07 |
2.25E-06 |
2 |
8.47E-07 |
3.30E-07 |
6.95E-08 |
1.36E-08 |
5.05E-08 |
1.98E-07 |
9.51E-09 |
1.76E-07 |
|
3 |
8.07E-07 |
3.28E-07 |
6.64E-08 |
1.36E-08 |
4.73E-08 |
1.81E-07 |
9.45E-09 |
1.61E-07 |
|
4 |
7.61E-07 |
3.24E-07 |
6.54E-08 |
1.34E-08 |
4.44E-08 |
1.56E-07 |
9.37E-09 |
1.49E-07 |
|
5 |
7.36E-07 |
3.21E-07 |
6.50E-08 |
1.33E-08 |
4.40E-08 |
1.42E-07 |
9.31E-09 |
1.41E-07 |
|
6 |
7.04E-07 |
3.07E-07 |
6.32E-08 |
1.31E-08 |
4.27E-08 |
1.35E-07 |
9.14E-09 |
1.34E-07 |
|
7 |
6.87E-07 |
3.07E-07 |
6.18E-08 |
1.31E-08 |
4.21E-08 |
1.31E-07 |
8.91E-09 |
1.24E-07 |
|
8 |
6.59E-07 |
3.02E-07 |
6.18E-08 |
1.27E-08 |
4.16E-08 |
1.13E-07 |
8.79E-09 |
1.19E-07 |
|
9 |
6.39E-07 |
2.92E-07 |
6.18E-08 |
1.26E-08 |
4.14E-08 |
1.08E-07 |
8.57E-09 |
1.15E-07 |
|
10 |
6.33E-07 |
2.92E-07 |
6.18E-08 |
1.24E-08 |
4.10E-08 |
1.05E-07 |
8.29E-09 |
1.13E-07 |
|
20 |
5.07E-07 |
2.67E-07 |
5.26E-08 |
1.16E-08 |
3.70E-08 |
3.13E-08 |
7.13E-09 |
1.01E-07 |
|
30 |
4.27E-07 |
2.45E-07 |
5.13E-08 |
1.05E-08 |
2.86E-08 |
3.95E-09 |
6.60E-09 |
8.16E-08 |
|
40 |
3.81E-07 |
2.32E-07 |
4.89E-08 |
9.97E-09 |
1.73E-08 |
|
5.77E-09 |
6.68E-08 |
|
50 |
3.60E-07 |
2.26E-07 |
4.65E-08 |
9.57E-09 |
1.01E-08 |
|
5.46E-09 |
6.23E-08 |
|
60 |
3.37E-07 |
2.20E-07 |
4.56E-08 |
9.27E-09 |
5.74E-09 |
|
4.90E-09 |
5.18E-08 |
|
70 |
3.21E-07 |
2.15E-07 |
4.44E-08 |
9.07E-09 |
1.67E-09 |
|
4.50E-09 |
4.62E-08 |
|
80 |
3.03E-07 |
2.09E-07 |
4.43E-08 |
8.88E-09 |
6.79E-10 |
|
4.24E-09 |
3.50E-08 |
|
90 |
2.88E-07 |
2.07E-07 |
4.27E-08 |
8.62E-09 |
4.57E-11 |
|
3.86E-09 |
2.50E-08 |
|
100 |
2.65E-07 |
2.01E-07 |
3.55E-08 |
8.34E-09 |
|
|
3.43E-09 |
1.61E-08 |
|
200 |
1.04E-07 |
8.57E-08 |
1.27E-08 |
4.30E-09 |
|
|
1.20E-09 |
|
|
300 |
4.90E-08 |
4.06E-08 |
6.00E-09 |
2.15E-09 |
|
|
2.72E-10 |
|
|
400 |
2.40E-08 |
1.99E-08 |
3.04E-09 |
1.10E-09 |
|
|
2.69E-12 |
|
|
500 |
1.27E-08 |
1.08E-08 |
1.29E-09 |
5.86E-10 |
|
|
|
|
|
600 |
4.65E-09 |
3.63E-09 |
6.37E-10 |
3.84E-10 |
|
|
|
|
|
700 |
2.16E-09 |
1.85E-09 |
1.68E-10 |
1.44E-10 |
|
|
|
|
|
800 |
1.00E-09 |
7.91E-10 |
1.17E-10 |
9.55E-11 |
|
|
|
|
|
900 |
8.90E-11 |
4.93E-11 |
7.07E-12 |
3.26E-11 |
|
|
|
|
|
1000 |
2.03E-12 |
|
|
2.03E-12 |
|
|
|
|
|
9.8.15 As can be seen, while the truck incident-related scenarios have some importance for the lower N values, practically only the two earthquake scenarios EU1TMRU and EU1TMRUH and aircraft crash AU1TMRU have a potential of causing 100 or more fatalities. The spontaneous failure or dropped drum event IU1TSRU is important for N=1 only.
9.8.16
The total Potential Loss of Life values obtained for different
scenarios considered in this assessment are shown in Table 9-28.
Population Scenario |
PLL |
Case
1 |
1.24E-04 |
Case
2 |
1.23E-04 |
Case
3 |
1.14E-04 |
Case
4 |
8.43E-05 |
Case
5 |
7.56E-05 |
Operation
only |
4.45E-07 |
Construction
only |
3.37E-07 |
9.8.17
As can be seen, the Case 1 and Case 2 PLL values are practically
identical – with the same general population, the increase of the traffic
population on some roads was apparently compensated by the decrease on others.
On the other hand, the revision of the general population data resulted in a
marked decrease for the predicted risk levels, with Case 4 and Case 5 PLL
significantly lower than for Cases 2 and 3. Also, due to the lower road
population levels, PLL for the construction phase is slightly lower than for
the corresponding operational scenarios.
Table 9-29 Breakdown
of Case 4 and Case 5 PLL by Population Area
Ref |
Description |
Case 4 PLL |
Case 5 PLL |
||
per year |
% of total |
per year |
% of total |
||
33 |
Tuen Mun Rd |
3.678E-05 |
43.6% |
2.86E-05 |
37.8% |
C |
Greenview Court & Belvedere Garden |
1.008E-05 |
12.0% |
1.01E-05 |
13.3% |
B |
Yau Kom Tau Village Extension |
8.31E-06 |
9.9% |
8.31E-06 |
11.0% |
E |
Yau Kom Tau Squatters |
7.065E-06 |
8.4% |
7.07E-06 |
9.4% |
J |
Bus Terminal |
2.832E-06 |
3.4% |
2.83E-06 |
3.8% |
W |
New development at Po Fung Rd |
2.74E-06 |
3.3% |
2.74E-06 |
3.6% |
K |
Belvedere Garden, The Panorama |
2.04E-06 |
2.4% |
2.04E-06 |
2.7% |
D |
Gardenview & Blossom Terrace |
1.99E-06 |
2.4% |
1.99E-06 |
2.6% |
I |
Bayview Garden |
1.58E-06 |
1.9% |
1.58E-06 |
2.1% |
V |
Golden Villa + new development |
1.35E-06 |
1.6% |
1.35E-06 |
1.8% |
O |
Secondary Scool |
1.17E-06 |
1.4% |
1.17E-06 |
1.6% |
N |
HK Baptist Convention School |
8.34E-07 |
1.0% |
8.34E-07 |
1.1% |
|
-
- - - - |
- - - |
-
- - |
-
- - |
-
- - |
34 |
Ting Kau Bridge |
5.141E-09 |
0.0% |
5.14E-09 |
0.0% |
35 |
Tsuen Wan Rd |
4.45E-07 |
0.5% |
3.37E-07 |
0.5% |
36 |
Castle Peak Rd S 1 |
2.29E-07 |
0.3% |
2.29E-07 |
0.3% |
37 |
Castle Peak Rd S 2 |
3.39E-07 |
0.4% |
1.48E-07 |
0.2% |
38 |
Castle Peak Rd S 3 |
8.10E-08 |
0.1% |
7.75E-08 |
0.1% |
39 |
Hoi On Rd |
6.63E-07 |
0.8% |
4.84E-07 |
0.6% |
40 |
Construction Site Office |
0 |
0 |
9.71E-10 |
0.0% |
|
- - - - |
-
- - |
-
- - |
-
- - |
-
- - |
Other |
|
5.77E-06 |
7.3% |
5.71E-06 |
8.2% |
|
|
|
|
|
|
|
Total |
8.43E-05 |
|
7.56E-05 |
|
9.8.18
Table 9-29 shows that of the roads included in the assessment
only Tuen Mun Rd located close to YKT WTW significantly contributes to the
total PLL values. PLL values for other roads are significantly lower, in
particular the Tsuen Wan Rd which is the subject of the present project
contributes only about 0.5% to the total PLL, and that value includes not only
the traffic but (for Case 5) construction worker populations as well. PLL for
the Project Construction Site Office is even smaller, well below 0.001% of the
total.
9.8.19
EU1TMRU event contributes about 80% of the total Case 4 PLL at Tsuen
Wan Rd while over 19% is contributed to the other earthquake scenario EU1TMRUH
and the aircraft crash event AU1TMRU. The role of other scenarios considered in
the assessment is negligible. Similar proportions can be obtained for Cases 1,
3 and 5, and for the project site office for cases related to the construction
phase.
9.8.20
The individual risk levels for the areas surrounding Yau Kom Tau WTW
are presented in Figure 9-8 for all cases. The individual risk levels are
calculated for a hypothetical person spending 100% of their time outdoors, with
no provision for escape from the chlorine cloud. This is an upper-bound estimate of the risk to actual
individuals.
9.8.21
It should be noted that since the individual risk levels depend on the
assumed event frequencies and location only, but do not depend on the
population data, the risk level shown apply to all five cases considered in
this assessment.
9.8.22
As can be seen from the figure, the individual risk levels are well
below the HKPSG criterion of 10-5. In fact most of the Tsuen Wan Rd
Upgrading Project site lies outside the area of any significant individual risk,
with only its western part located within the 10-8 to 10-7 risk area.
9.8.23
Following the QRA assessment for YKTWTW (ERM, 2001) several mitigation
measures have been implemented at the WTW to reduce the risk As Low As
Reasonably Practicable. This study confirmed that those measures are adequate
even for the general and road populations projected up to 2030, ie the risk
levels remain well within the ALARP zone (refer to Figures 9-6 and 9-7).
On the other hand the Tsuen Wan Rd Upgrading Project itself has a very little
effect on the societal risk levels in the YKT WTW vicinity. It is therefore
concluded that no additional mitigation measures at YKT WTW are reasonably
practicable.
9.8.24
Similarly, the risk levels to the road and workforce population of
Tsuen Wan Rd are relatively low due to its significant distance to YKT WTW, and
since the risk to this population is dominated by an earthquake event affecting
both the YKT WTW and the Tsuen Wan Rd and subsequent chlorine release at WTW,
no mitigation measure that could significantly reduce such risk is considered
cost-effective or practicable.
9.8.25
This can be illustrated by the following simple cost-benefit analysis,
similar to that applied in Maunsell (2007).
9.8.26
The cost effectiveness mitigation measures may be
estimated by calculating the Implied Cost of Averting Fatality (ICAF) which may
then be compared with the statistical value of life to determine whether a
mitigation measure is reasonably practicable to implement. The value of life is
taken as HK$660M (including an ‘aversion factor’ of 20), same as used in the
approved Tuen Mun Rd EIA (Maunsell, 2007).
9.8.27
Assuming optimistically that a potential mitigation
measure could remove all risk to life to the Tsuen Wan Rd operational phase
population (PLL = 4.45 x 10-7per year, see Table 9-29) and assuming
that it will remain effective for a period of 50 years, in order to obtain ICAF
lower than $660M, the maximum cost of
a mitigation measure would have to be $660,000,000 x 4.45 x 10-7 x 50 = $14,685
9.8.28
It
is clear that no conceivable mitigation measure that could significantly reduce
the risk can be designed within the above cost. For example, Maunsell (2007) estimates the cost of a road
enclosure at HK150,000 per metre. No mitigation measures implemented at Tsuen
Wan Rd could therefore be considered cost-effective. Similar conclusion can
also be drawn for the operational phase population (PLL = 3.37
x 10-7 per year).
9.8.29
Nevertheless two measures previously recommended in the EIA for Route 8
(formerly Route 16) warrant consideration:
·
Introduce the ‘no stopping zones’ on the western
part of Tsuen Wan Rd and on all major roads within the area where the
individual risk levels exceed 1 x 10-9 (see Figure 8.39.8). This measure (if
not already implemented) would also be particularly effective on Tuen Mun Rd.
·
Provide traffic signals to stop in case of
emergency the traffic on western part of Tsuen Wan Rd and other major roads
within the area that could be affected by a chlorine spill at YKT WTW.
9.8.30
Similarly, implementation of the following measures for protection of
the Project construction workers should be considered:
·
The number of workers on site during
construction stage should not exceed the
levels assessed in this report.
·
The emergency procedures should specify
means of providing a rapid and direct warning (e.g. Siren and Flashing Light)
to construction workers in the event of chlorine gas release in the YKTWTW.
·
The construction site officer should
establish a communication channel with the YKTWTW operation personnel during
construction stage. In case of any hazardous incidents in the treatment works,
operation personnel of YKTWTW should advise the site officer to evacuate the
construction workers.
9.9.1
This QRA study re-assessed the hazard to life associated with a
potential chlorine spill at the Yau Kom Tau Water Treatment Works (YKT WTW) in
light of the increased road and workforce population associated with the
construction and operational phases of the Tsuen Wan Rd Upgrading Project. The
study methodology is based on the previous YKT WTW assessment (ERM, 2001)
however the updated newest
projections of the general population in the area have been taken into account.
Note that very similar methodologies have been adopted for the previous
chlorine spill hazard assessment (Scott Wilson, 1998a,b) for Route 8 (formerly
Route 16) and the recently approved EIA of Tuen Mun Rd widening (Maunsell,
2007). While the ERM (2001)
methodology has been carefully re-examined, based on the review of the recent
chlorine incidents worldwide, it proved robust and adequate for the present
assessment. Thus, most revisions introduced to the present methodology relate
to the population assumptions.
9.9.2
The QRA shows that the road population increases during the operational
phase of the Tsuen Wan Rd Upgrading Project as well as the workforce population
during the construction phase have little effect on the total societal risks in
the vicinity of YKTWTW, as expressed by the total PLL value and the FN
curves. While these risks, similar
to the ERM (2001) assessment, remain within the ALARP region of the HKPSG Risk
Guidelines, it should be noted that due to the updated population projections
introduced in this study, the general risk levels even for the 2030 project
operational phase are slightly lower than those predicted for 2006 in the ERM
(2001) assessment.
9.9.3
Since all the mitigation measures at YKT WTW suggested in ERM (2001) to
reduce the risk to As Low As Reasonably Practicable levels have already been
implemented, no new mitigation measures are recommended in this study.
Similarly, since the risk levels to the road and workforce population of Tsuen
Wan Rd are relatively low due to its significant distance to YKT WTW, and since
the risk to this population is dominated by an earthquake event affecting the
YKT WTW and the Tsuen Wan Rd and subsequent chlorine release at WTW, as shows a
simple quantitative cost-benefit analysis, no mitigation measure that could
significantly reduce such risk is considered cost-effective or
practicable. Nevertheless a number
of measures suggested in Section 9.8 such as introduction of no stopping
zones and emergency traffic signals on the relevant roads as well as
establishing adequate emergency procedures for the Project workforce are
recommended for the Project Proponent consideration.
(1)
Brighton, P W M. (1989a), "Pressures produced by
instantaneous chlorine releases inside buildings" UKAEA Report
SRD/HSE/R467.
(2)
Brighton, P W M. (1989b), "Continuous chlorine releases
inside buildings: concentrations on emission to atmosphere" UKAEA Report
SRD/HSE/R468.
(3)
Cook, I., N. J. Holloway, W. Nixon and D.W. Phillips (1993),
Consultancy on the Environmental Aspects of the Daya Bay Nuclear Power Station
for the Government of Hong Kong - Risk Assessment Report.
(4)
DNV(1997), Quantitative Risk Assessment of the Transport of
Chlorine in Hong Kong for Environmental Protection Department.
(5)
EIAO-TM, Technical Memorandum on Environmental Impact
Assessment Process, available at:
http://www.epd.gov.hk/eia/english/legis/index3.html .
(6)
ERM (1997a), Reassessment of Chlorine Hazard for Eight
Existing Water Treatment Works: Methodology Report, for Water Supplies
Department.
(7)
ERM (1997b), Reassessment of Chlorine Hazard for Eight
Existing Water Treatment Works: Hazard Identification Report, for Water
Supplies Department.
(8)
ERM (1998), Technical Note 1: Application of Wind Tunnel Test
Results in Hazard Assessments, Report for Water Supplies Department CE14/96
Reassessment of Chlorine Hazard for Eight Existing Water Treatment Works, for
Water Supplies Department.
(9)
ERM (2001) Reassessment of Chlorine Hazard for Eight Existing
Water Treatment Works: Hazard Assessment for Yau Kom Tau Water Treatment Works,
for Water Supplies Department.
(10)
HKPSG, Hong Kong Planning Standards and Guidelines, available
at: http://www.pland.gov.hk/tech_doc/hkpsg/english/index.htm
(11)
HSL (1998a), CFD Modelling of Chlorine Dispersion at Sha Tin
WTW, The Health and Safety Laboratory, March 1998.
(12)
HSL (1998b), CFD Modelling of Chlorine Dispersion at Tai Po
Tau WTW, The Health and Safety Laboratory, December 1998.
(13)
HSE (1998), The Implications of Major Hazard Sites in Close
Proximity to Major Transport Routes, Contract Research Report 163/1998 prepared
by WS Atkins Safety & Reliability.
(14)
IChemE (1989), "Chlorine Toxicity Monograph - Updated
Version", The Institution of Chemical Engineers.
(15)
ICI (1995), "Chlorine Handbook", ICI Australia.
(16)
Lees F P (1996), Loss prevention in the Process Industries,
Butterworth Heinemann.
(17)
Maunsell (2007) Widening of Tuen Mun Road at Tsing Tin
Interchange - Environmental Impact Assessment EIA 142/2007, approved under EIAO
on 23 January 2008
(18)
Ove Arup (2000), Water Treatment Works Seismic Hazard
Assessment - Seismic Assessment of Chlorine Storage Buildings and Chlorine
Containers.
(19)
PlanD(2006) http://www.pland.gov.hk/info_serv/statistics/tables/WGPD_Report_e.pdf
(20)
Porter (1991), Risk Mitigation in Land Use Planning: Indoor
Releases of Toxic Gases, International Conference on Modelling and Mitigating
the Consequences of Accidental Releases of Hazardous Materials, 1991.
(21)
RWDI (1998), Wind Tunnel Study - Reassessment of Chorine
Hazard for Yau Kom Tau WTW, Rowan Williams Davies and Irwin Inc., January 1998.
(22)
Scott Wilson (1998a) Agreement No CE 42/96, Route 16 from West
Kowloon to Sha Tin: EIA Study, Final Assessment Report, for Highways
Department.
(23)
Scott Wilson (1998b) Agreement No CE 42/96, Route 16
Alternative Alignment: EIA Study, Final Environmental Assessment Report, for
Highways Department.
(24)
TNO (1992), "Methods for the Determination of Possible
Damage to People and Objects Resulting from Releases of Hazardous
Materials", CPR 16E, Green Book, 1992.
(25)
Webber, D M, S J Jones, G A Tickle, and T Wren (1992), UKAEA
Report SRD/HSE R587 “ A model of dispersing gas cloud, and the computer
implementation DRIFT – II Steady Continuous Releases”
(26) Webber (1998), Brief Review of RWDI and DRIFT Results, 16 February 1998.
[1] PlanD: Hong Kong 2030: Planning
Vision and Strategy study, Working Paper No 42 (http://www.hk2030.gov.hk/eng/wpapers/pdf/wpaper42.pdf)