4.1
The landscape and visual mitigation measures should be
incorporated in the detailed design, so as to ensure the effectiveness of the
mitigation measures described in Table 5.4, Section 5 of EIA report. Any changes to the mitigation measures
that may be recommended to match the baseline review result or to match the
ongoing EM&A should also be incorporated in the detailed design.
4.2
The design, implementation and maintenance of mitigation
measures should be checked regularly to ensure that they are fully
realised. Any potential conflicts
among the proposed mitigation measures, the project works, and operational
requirements should also be identified and resolved early. The proposed mitigation measures should always
be given priority.
4.3
A landscape specialist with substantial site experience
should be responsible for supervising the landscape works during the
Construction Phase to ensure the mitigation measures are implemented according
to Table 5.4 Section 5 of EIA Report.
4.4
The implementation of landscape construction works and
maintenance operations during the subsequent 12 month Establishment Period must
be supervised by landscape specialist. The employment of a landscape specialist
for monitoring the tree protection measures is cited in the EIA as a mitigation
measure, and their involvement should be monitored.
4.5
Measures to mitigate landscape and visual impacts during
construction, should be checked regularly to ensure compliance with the
intended aims of the measures.
4.6
The extent of the agreed works areas should be regularly
checked during the construction phase.
Any trespass by the Contractor outside the limit of the works, including
any damage to existing trees shall be reported to the appropriate
authorities.
4.7 The progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the soft landscape works to be undertaken.
Table 4.1 Landscape and
Visual Mitigation Monitoring Programme
Area of
Works |
Items
to be Monitored |
Advance planting |
·
monitoring of implementation and
maintenance of planting, and against possible incursion, physical damage. |
Protection of §
all wall-cum-trees at §
all wall-cum-trees at §
all OVT within the project site
boundary §
all Champion trees within the
project site boundary. |
·
identification and demarcation
of all trees to be retained, erection of physical protection (e.g. fencing),
monitoring against possible incursion, physical damage, fire, pollution,
surface erosion, etc. ·
installation and implementation
of tree protection measures for all OVT within the works area, wall-cum-trees
at Forbes Street Temporary and ·
all Tree Protection Specification in Contract Specification are undertaken
and executed. |
Clearance of existing vegetation |
·
identification and demarcation
of trees / vegetation to be cleared, checking of extent of works to minimise
damage, monitoring of adjacent areas against possible incursion, physical
damage, fire, pollution, surface erosion, etc. ·
all retained trees are recorded photographically
before site clearance |
Transplanting of trees |
·
identification and demarcation
of trees / vegetation to be transplanted, ·
monitoring of extent of pruning
/ lifting works to minimize damage, timing of operations, implementation of
all stages of preparatory and translocation works, and maintenance of
transplanted vegetation, etc. ·
all tree transplanting
specification in Contract Specification are undertaken and executed |
Tree compensation |
·
monitoring of the tree
compensation ratio, and implementation of compensatory planting. |
Plant supply. |
·
monitoring of operations
relating to the supply of specialist plant material (including the
collecting, germination and growth of plants from seed) to ensure that plants
will be available in time to be used within the construction works. . |
Soiling, planting, etc. |
·
monitoring of implementation and
maintenance of soiling and planting works and against possible incursion,
physical damage, fire, pollution, surface erosion, etc. |
Establishment Works, etc. |
·
monitoring of implementation of
maintenance operations complied with the specification requirement during
Establishment Period. |
Re-provision of Public Open Space and facilities |
·
the compensation of the affected
LCSD public open space (Forbes
Street Playground, |
Decorative treatment of site hoarding |
·
implementation and maintenance,
to ensure compliance with agreed designs. |
Architectural treatment of entrance station and vent shaft. |
·
implementation and maintenance
of mitigation measures, to ensure compliance with agreed designs. |
Night time lighting |
·
implementation and maintenance
of screening measures, control of use and period of lighting to ensure
minimisation of night time glare |
4.8
Potential landscape and visual impacts have been carefully
considered during the development of the project design to (1) avoid impacts on
important landscape resources including the Forbes Street tree wall (LR1.2) and
KGV Park tree wall(LR1.6), as well as old and valuable trees in the LCSD
registry, as the first priority; and (2) locate, design and reduce physical
extent of the works as far as possible, as well as identify mitigation
measures, so as to minimize impacts on existing trees and open spaces, and to
minimize the degree of visual impact, as proposed below.
Table 4.2 Landscape
and Visual Mitigation Measures during Construction Phase
ID No. |
Nature / Type |
Landscape and Visual Mitigation Measure |
Funding / Implementation |
Management/ Maintenance |
CM-01 |
Design / construction Planning |
Re-use of Existing Soil Existing topsoil shall be re-used where possible for new
planting areas within the project. The construction program shall consider
using the soil removed from one phase for backfilling another. Suitable
storage ground, gathering ground and mixing ground may be set up on-site as
necessary. |
MTRC |
N/A |
CM-02 |
Design / construction Planning |
No-intrusion Zone To maximize protection to existing trees, ground
vegetation and the associated understory habitats, construction contracts may
designate “No-intrusion Zone” to various areas within the site boundary with
rigid and durable fencing for each individual no-intrusion zone. The
contractor should close monitor and restrict the site working staff not to
enter the “no-intrusion zone”, even for non-direct construction activities
and storage of equipment. |
MTRC |
N/A |
CM-03 |
Design / construction Planning |
Decorative Hoarding Erection of decorative screen hoarding should be designed
to be compatible with the existing urban context. |
MTRC |
NA |
CM-04 |
Site Practice |
Minimize light pollution and control of night-time
glare All security floodlights for construction sites shall be
equipped with adjustable shield, frosted diffusers and reflective covers, and
be carefully controlled to minimize light pollution and night-time glare to
nearby residences and GIC users. The Contractor shall consider other security
measures which shall minimize the visual impacts. |
MTRC |
NA |
CM-05 |
Design / Construction Planning |
Aesthetic design of the conveyor belt system The removal of excavated material requires installation of
a conveyor and a barging point. The conveyor will be covered, except the
portion where it meets the barging point. The aim of covering or enclosing
the conveyor is to avoid noise and air quality issues; however, the conveyor
where above-ground should be adequately screened and /or constructed of
suitable materials and in colours/tones that minimize visual intrusion. |
MTRC |
NA |
CM-06 |
Site Supervision |
Protection of Retained Trees All retained trees should be recorded photographically at
the commencement of the Contract, and carefully protected during the
construction period. Detailed tree protection specification shall be allowed
and included in the Contract Specification, which specifying the tree
protection requirement, submission and approval system, and the tree
monitoring system. In addition, the Contractor shall be required to submit,
for approval, a detailed working method statement for the protection of trees
prior to undertaking any works adjacent to all retained trees, including
trees in contractor’s works areas. All implementation of tree protection works and tree
preservation measures shall be supervised by a landscape specialist on site. |
MTRC |
NA |
CM-07 |
Design/ Construction Planning |
Protection of
Registered Old and Valuable Trees
Detailed tree protection measures as stipulated in WBTC
No. 29/2004 – Registration of Old and Valuable Trees, and Guidelines for
their Preservation, shall be allowed and included in the Contract
Specification. All implementation of OVT protection measures shall be
supervised by a landscape specialist on site. |
MTRC |
LCSD |
CM-08 |
Design / Construction Planning |
Protection of Old Stone Wall-cum-trees Detailed tree protection specification shall be allowed
and included in the Contract Specification, which specifying the tree
protection requirement, submission and approval system, and the tree
monitoring system. All implementation of Old stone wall-cum-trees protection
measures shall be supervised by a landscape specialist on site. |
MTRC |
N/A |
Table 4.3 Landscape
and Visual Mitigation Measures during Operation Phase
ID No. |
Nature /
Type |
Landscape and Visual Mitigation Measure |
Funding /
Implementation |
Management/
Maintenance |
OM-01 |
Design / construction Planning |
Tree Transplanting Trees of high to medium survival rate after transplanting
to be affected by the works shall be transplanted where possible and practicable.
Tree transplanting proposal including
final location for transplanted trees will be submitted separately to seek
relevant government department’s approval, in accordance with ETWB TCB 3/2006.
|
MTRC |
N/A |
OM-02 |
Design / construction Planning |
Compensation Tree Planting Compensatory tree planting should be provided to
compensate for felled trees as far as practicable. Compensatory tree planting proposal
including location of compensation will be submitted separately to seek relevant
government department’s approval, in accordance with ETWB TCB 3/2006. |
MTRC |
LCSD |
OM-03 |
Design / construction Planning |
Aesthetic landscape and architectural treatment on
Station / Entrance / vent shaft All station entrances, vent shafts and all above ground
structures shall be sensitively designed to ensure the element with colour,
texture and tonal quality being compatible to the existing urban context,
which shall include tree planting where space permits, to minimize the
potential adverse landscape and visual impacts. For example, roof greening
and vertical greening would be applied where possible subject to technical
operational and maintenance constraints |
MTRC |
MTRC |
OM-04 |
Design / construction Planning |
Re-instatement of excavated Area All excavated area and disturbed area for utilities
diversion, temporary road diversion, and pipeline woks shall be reinstated to
former conditions or even better, to the satisfaction of the relevant
Government departments. |
MTRC |
N/A |
OM-05 |
Design / construction Planning |
Re-provision of public open spaces Every effort should be made to so that no public open
space would be unnecessarily affected by the Project and if affected, they should
be reprovided as far as possible and practicable. Sensitive design and reprovision of
the affected Public Open Space (Forbes Street Playground, Hill Road Rest
Garden, Ki Ling Lane Children’s Playground, Mui Fong Street Children Playground,
Sai Woo Lane Playground, Centre Street Market Sitting-out Area, King George V
Memorial Park) incorporating replacement facilities for those provided at
present, using materials of quality suitable for long term use and acceptable
to relevant Government authority.
Relevant government departments including LCSD and PlanD should be
consulted on the design of the reprovisioned public open spaces at the early
stage of the design process. |
MTRC |
LCSD / ArchSD (hard landscape works) |