TABLE OF
CONTENTS
1.1. Project Description1
1.2. Need of an EM&A Programme
1.3. Purpose of the Manual
1.4. Project Organisation
2.1. Introduction
2.2. Methodology and Criteria
2.3. Monitoring Equipment
2.4. Laboratory Measurement / Analysis
2.5. Monitoring Locations
2.6. Baseline Monitoring
2.7. Impact Monitoring
2.8. Event and Action Plan
2.9. Mitigation Measures
3.1. Introduction
3.2. Construction Noise Parameters
3.3. Construction Monitoring Equipment
3.4. Construction Noise Monitoring Locations
3.5. Construction Noise Baseline Monitoring
3.6. Construction Noise Impact Monitoring
3.7. Event and Action Plan for Construction Noise
3.8. Construction Noise Mitigation Measures
3.9. Operation Ventilation Noise
4.1. Introduction
4.2. Site Inspection1
4.3. Mitigation Measures
5. waste management implications
5.1. Introduction
5.2. Mitigation Measures
6.1. Introduction
6.2. Monitoring Details
6.3. Mitigation Measures
7.1. Introduction
7.2. Precaution Measures / Monitoring
8.1. Site Inspections
8.2. Compliance with Legal and Contractual Requirements
8.3. Environmental Complaints
9.1. General
9.2. Electronic Reporting of EM&A Information1
9.3. Baseline Monitoring Report1
9.4. Monthly EM&A Reports
9.5. First Monthly EM&A Report
9.6. Subsequent Monthly EM&A Reports
9.7. Final EM&A Review Report
9.8. Data Keeping
9.9. Interim Notifications of Environmental Quality Limit Exceedances
List of Tables
Table 1.1 Preliminary Construction Programme
Table 2.1 Proposed Dust
Monitoring Stations
Table 2.2 Action and Limit
Levels for Air Quality (Dust)
Table 2.3 Event / Action
Plan for Air Quality (Dust)
Table 3.1 Noise Monitoring
Stations during Construction Phase
Table 3.2 Action and Limit
Levels for Construction Noise
Table 3.3 Event and Action
Plan for Construction Noise
Table 3.4 Summary of Max SWL
for Ventilation Shafts
List of Figures
Figure 1.2 Project
Organisation and Line of Communication
Figure 2.1 Locations
of Dust / Construction Noise Monitoring
Stations
Figure 6.1 Proposed Landscape Mitigation
Measure
Figure 8.1 Environmental
Complaint Flow Diagram
List of
Appendices
Appendix A Preliminary
Construction Programme
Appendix
B Implementation Schedule of
Mitigation Measures
Appendix C Sample
Data Sheets for Dust and Construction Noise Monitoring
Project Background
Project Location and Description
Project Scope and Programme
·
A subway (Subway TST) from the
north end of TST Station, running approx
·
A satellite concourse (the
Satellite Concourse) approx 45m underneath
·
A subway (Subway MSC) from the
north end of the Satellite Concourse, running approx
·
An Emergency Exit situated in
the east footpath and planter of
· Ventilation shafts for the proposed subway and satellite concourse. The ventilation shafts will be integrated with the Tung Ying Redevelopment and Miramar Hotel; and
· A new plant basement near existing Entrance A1 to house the station equipment relocated from the north end of TST Station for accommodating the TNS connection. The Entrance A1 will be reconstructed on the same site.
Table 1.1 Preliminary Construction
Programme
Activity |
Time
period |
Site clearance and set up |
Jun 2009 to Jul 2009 |
Tree Protection |
Jun 2009 to Jan 2012 |
Plant Basement and Entrance A1
construction |
Jul 2009 to Dec 2010 and Nov
2010 to Nov 2011 |
Satellite Concourse and Entrances
Q1 and Q2 construction |
Nov 2009 to Jan 2012 |
Subway to TST Station |
Mar 2011 to Dec 2011 |
Subway to Miramar Shopping
Centre and Entrance Q3 construction |
Feb 2011 to Dec 2011 |
Emergency Exit at |
Jul 2009 to Aug 2009, Nov 2011
to Feb 2012 |
TST Connection Chamber |
Jul 2009 to Mar 2010 |
TST North End modification |
Jun 2011 to Mar 2012 |
Landscaping works |
Oct 2011 to Jan 2012 |
Site reinstatement works |
Jan 2012 to May 2012 |
Concurrent Projects
· Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team (ET) and Independent Environmental Checker (IEC) with respect to the EM&A requirements during the course of the Project;
· Project organisation;
· The basis for, and description of the broad approach underlying the EM&A programme;
· Requirements with respect to the construction programme schedule and the necessary EM&A programme to track the varying environmental impact;
· Details of the methodologies to be adopted, including all field laboratories and analytical procedures, and details on quality assurance and quality control programme;
· The rationale on which the environmental monitoring data will be evaluated and interpreted;
· Definition of Action and Limit Levels;
· Establishment of Event and Action Plans;
· Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints;
· Requirements for presentation of EM&A data and appropriate reporting procedures; and
· Requirements for review of EIA predictions and the effectiveness of the mitigation measures and the EM&A programme.
Engineer or Engineer’s Representative (ER)
· Supervising the Contractor’s activities and ensure the requirements in the EM&A Manual are fully complied with;
· Informing the Contractor when action is required to reduce impacts in accordance with the Event and Action Plans;
· Participating in joint site inspection undertaken by the ET and IEC; and
· Adhering to the procedures for carrying out complaint investigation.
The Contractor
· To provide assistance to ET in carrying out monitoring;
· To submit proposals on mitigation measures in case of exceedances of Action and Limit Levels in accordance with the Event and Action Plans;
· To implement measures to reduce impact where Action and Limit Levels are exceeded;
· To implement the corrective actions instructed by the Engineer;
· To accompany joint site inspection undertaken by the ET; and
· To adhere to the procedures for carrying out complaint investigation.
Environmental Team (ET)
· To monitor various environmental parameters as required in this EM&A Manual;
· To analyse the EM&A data and review the success of EM&A programme to cost-effectively confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions and to identify any adverse environmental impacts arising;
·
To carry out regular site
inspection to investigate and audit the Contractors
· To audit and prepare monitoring and audit reports on the environmental monitoring data and site environmental conditions;
· To recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit Levels in accordance with the Event and Action Plans; and
· To adhere to the procedures for carrying out complaint investigation.
Independent Environmental Checker (IEC)
· To provide proactive advice on EM&A matters related to the Project, independent from the management of construction works, but empowered to audit the environmental performance of construction;
· To audit in an independent, objective and professional manner in all aspects of the EM&A programme;
· To check, review, verify and validate the overall environmental performance of the project, including the implementation of environmental protection and mitigation measures, submissions relating to EM&A, and any other submissions required under the Environmental Permit (EP) for the project; and
· On a need basis, to verify and certify the environmental acceptability of the construction methodology, relevant design plans and submissions under the EP.
· To identify the extent of construction dust impacts on sensitive receivers;
· To determine the effectiveness of mitigation measures to control fugitive dust emission from activities during construction phase;
· To audit the compliance of the Contractor with regard to dust control, contract conditions and the relevant dust impact criteria;
· To recommend further mitigation measures if found to be necessary; and
· To comply with Action and Limit (A/L) Levels for air quality as defined in this Manual.
· The Hong Kong Air Quality Objectives (AQOs) for TSP, 24-hour TSP levels of 260mg m-3
·
The 1-hour TSP limit of
·
0.6 -
· Equipped with a timing / control device for 24 hours operation;
· Installed with elapsed-time meter for 24 hours operation;
·
Capable of providing a minimum
exposed area of
· Incorporated with an electronic mass flow rate controller or other equivalent devices;
· Equipped with a flow recorder for continuous monitoring;
· Provided with a peaked roof inlet;
· Incorporated with a manometer;
· Able to hold and seal the filter paper to the sampler housing at horizontal position;
· Easy to change the filter; and
· Capable of operating continuously for 24-hour period.
Table
2.1 Proposed Dust Monitoring Stations
Identification No. |
ASR ID in EIA Report |
Air Quality Monitoring Location |
M1 |
A2 |
|
· At the site boundary or such locations close to the major dust emission source;
· Close to the air sensitive receivers;
· Proper position/sitting and orientation of the monitoring equipment; and
· Take into account the prevailing meteorological conditions.
· A horizontal platform with appropriate support to secure the samplers against gusty wind shall be provided;
· No two samplers shall be placed less than 2m apart;
· The distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
· A minimum of 2m of separation from walls, parapets and penthouses is required for rooftops samplers;
· A minimum of 2m of separation from any supporting structure, measures horizontally is required;
· No furnace or incinerator flue is nearby;
· Airflow around the sampler is unrestricted;
· The sampler is more than 20m from the dripline;
· Any wire fence and gate to protect the sampler, shall not cause any obstruction during monitoring;
· Permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· A secured supply of electricity is needed to operate the samplers.
Table 2.2 Action and Limit Levels for Air Quality (Dust)
Parameter |
Action Level (1) |
Limit Level |
24-hour TSP |
·
BL £ ·
BL > |
|
1-hour TSP |
·
BL £ ·
BL > |
|
(1) BL = Baseline level,
Table 2.3 Event / Action Plan for Air Quality (Dust)
Event |
Action |
|||
ET |
Contractor |
ER |
IEC |
|
Action Level being exceeded |
1. Conduct additional measurement
to confirm finding. 2. Identify source and investigate
the causes of exceedance, if caused by MTRCL’s work. 3. Inform IEC, ER and Contractor. 4. Discuss with IEC, ER and
Contractor on remedial actions required. 5. If necessary, conduct
additional monitoring to assess the effectiveness of Contractor’s remedial
actions. 6. If exccedance continues, arrange
meeting with IEC and ER to review implementation and
identify further appropriate mitigation measures. 7. If excceedance stops, cease
additional monitoring. |
1. Discuss with ET on proper
remedial actions. 2. Submit proposals for remedial actions
to ER within 3 working days of notification. 3. Amend proposal if appropriate. 4. Implement the agreed proposals. 5. Liaise with ER to optimize the effectiveness of the agreed
mitigation. |
1. Confirm receipt of notification
of exceedance. 2. Notify Contractor. 3. Check Contractor’s working methods. 4. Agree with the Contractor on
the remedial measures to be implemented. 5. Ensure proper implementation of
remedial measures. 6. Assess the efficiency of remedial actions and keep the Contractor
informed. |
1. Check Contractor’s working
method. 2. Advise ET on the effectiveness
of the proposed remedial measures. |
Limit level being exceeded |
1. Conduct additional measurement
to confirm findings. 2. Identify source and investigate
the causes of exceedance; 3. Notify EPD, IEC, ER and
Contractor. 4. Check Contractor’s working
procedures. 5. Discuss with IEC, ER and
Contractor on remedial actions required. 6. If necessary, conduct
additional monitoring to assess effectiveness of Contractor’s remedial
actions. 7. Keep EPD, IEC and ER informed
of the monitoring results. 8. If exccedance continues,
arrange meeting with IEC and ER to review
implementation and identify further appropriate mitigation measures. 9. If exceedance stops, cease
additional monitoring. |
1. Take immediate action to avoid
further exceedance. 2. Discuss with ET and ER on
proper remedial actions. 3. Submit proposals for remedial
actions to ER within 3 working days of notification. 4. Implement the agreed proposals. 5. Liaise with ER to optimize the effectiveness of the agreed mitigation. |
1. Confirm receipt of notification
of exceedance. 2. Notify Contractor. 3. Check Contractor’s working methods. 4. Agree with the Contractor on
the remedial measures to be implemented. 5. Ensure proper implementation of
remedial measures. 6. Assess the efficiency of remedial actions and keep the Contractor
informed. |
1. Check Contractor’s working
method. 2. Review Contractor’s remedial
actions whenever necessary to assure their effectiveness and advise the ET
accordingly. |
· Watering of active construction works area twice a day.
· Skip hoist for material transport should be totally enclosed by impervious sheeting.
· Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site.
· The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.
·
Where a site boundary adjoins a
road, streets or other accessible to the public, hoarding of not less than
· Every stack of more than 20 bags of cement should be covered entirely by impervious sheeting places in an area sheltered on the top and the 3 sides.
· All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.
· The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading.
· Stockpile of excavated or dusty materials shall be covered entirely by clean impervious sheeting.
· The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle.
· Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.
Table 3.1 Noise
Monitoring Stations during Construction Phase
Identification No. |
NSR ID in EIA Report |
Noise Monitoring Location |
M1 |
N1 |
|
M2 |
N3 |
|
M3 |
N4 |
|
· Monitoring at sensitive receivers close to the major site activities which are likely to have noise impacts
· Monitoring at the noise sensitive receivers as defined in the TM
· Assurance of minimal disturbance to the occupants during monitoring
Table
3.2 Action and Limit Levels for
Construction Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900 hours on normal
weekdays |
When one documented complaint
is received |
75 dB(A)* |
* Reduced
to 70dB(A) for schools or institution and 65dB(A) during school examination
periods
Table 3.3 Event and Action Plan for Construction Noise
Event |
Action |
|||
ET |
Contractor |
ER |
IEC |
|
Action Level being exceeded |
1. Undertake measurement to establish validity of complaint. 2.
Identify source(s) of
complaint. 3. Notify IEC, ER and Contractor. 4.
Discuss with the IEC, ER and Contractor on remedial measures required. 5. Increase monitoring frequency
to check mitigation effectiveness. 6. If exccedance continues,
arrange meeting with IEC and ER to review
implementation and identify further appropriate mitigation measures. 7. If excceedance stops, cease
additional monitoring. |
1. Submit noise mitigation
proposals to ER within three
working days of notification. 2. Amend proposal if appropriate. 3. Implement noise mitigation
proposals. 4. Liaise with ER to optimize the effectiveness of the agreed
mitigation. |
1. Confirm receipt of notification
of complaint. 2. Notify Contractor. 3. Check Contractor’s working
methods. 4. Agree with the Contractor on
the remedial measures to be implemented. 5. Ensure proper implementation of
remedial measures. 6. Assess the efficiency of remedial actions and keep the Contractor informed. 7. Inform complainant of actions taken. |
1. Check Contractor’s working
methods. 2. Review the proposed remedial
measures by the Contractor and advise the ET accordingly. |
Limit Level being exceeded |
1. Repeat measurement to confirm
findings. 2. Identify source and investigate
the cause of exceedance. 3. Inform EPD, IEC, ER and
Contractor. 4. Check Contractor’s working
procedures. 5. Discuss with the IEC,
Contractor and ER on remedial measures required. 6. Increase monitoring frequency
to assess effectiveness of Contractor’s mitigation actions and keep EPD, IEC
and ER informed the results. 7. If exccedance continues,
arrange meeting with IEC and ER to review
implementation and identify further appropriate mitigation measures. 8. If exceedance stops, cease
additional monitoring. |
1. Take immediate action to avoid
further exceedance. 2. Submit proposals for remedial
actions to ER within 3 working days of notification. 3. Implement the agreed proposals. 4. Liaise with ER to optimize the effectiveness of the agreed
mitigation. |
1. Confirm receipt of notification
of exceedance. 2. Notify Contractor. 3. Check Contractor’s working
methods. 4. Agree with the Contractor on
the remedial measures to be implemented. 5. Ensure proper implementation of
remedial measures. 6. Assess the efficiency of remedial actions and keep the Contractor
informed. |
1. Check Contractor’s working
methods. 2. Review Contractor’s remedial
actions whenever necessary to assure their effectiveness and advise the ET
accordingly. |
· Use of silenced type of powered mechanical equipment, which should be in accordance with BS 5228: Part 1, 1997 during construction;
· Use of movable noise barrier;
· Use of noise enclosure / acoustic shed;
· Use of silencer;
· Use of noise insulating fabric;
· Decking over the excavation areas at the Entrance A1 and satellite concourse; and
· Implementation of the following good site practices:
Ø
Only well-maintained
plant shall be operated on-site and plant shall be serviced regularly during
the construction program.
Ø
Silencers
or mufflers on construction equipment shall be utilised and shall be properly
maintained during the construction program.
Ø
Mobile
plant, if any, shall be sited as far away from NSRs as possible.
Ø
Machines
and plant (such as trucks) that may be in intermittent use shall be shut down
between works periods or shall be throttled down to a minimum.
Ø
Plant
known to emit noise strongly in one direction shall, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs.
Ø
Material
stockpiles and other structures shall be effectively utilised, wherever
practicable, in screening noise from on-site construction activities.
Table
3.4 Summary of Max SWL for Ventilation
Shafts
*Source Location |
**Direction Facing |
Shortest horizontal distance to |
Maximum SWL at 0700-2300, dB(A) |
Maximum SWL at 2300-0700, dB(A) |
|
West ( |
17 |
92 |
85 |
South ( |
15 |
91 |
84 |
|
Hotel
Miramar |
West ( |
44 |
100 |
93 |
Note: (*) Only one of the sources would be in
operation as the exact locations for exhaust or smoke extraction are still
under design.
(**) The vent shaft would be located at one direction
only. The exact location of the shaft opening from
· Choose quieter plant such as those which have been effectively silenced.
· Include noise levels specification when ordering new plant (including chillier and E/M equipment).
· Locate fixed plant/louver away from any NSRs as far as practicable.
· Locate fixed plant in walled plant rooms or in specially designed enclosures.
· Locate noisy machines in a basement or a completely separate building.
· Install direct noise mitigation measures including silencers, acoustic louvers and acoustic enclosure where necessary.
· Develop and implement a regularly scheduled plant maintenance programme so that equipment is properly operated and serviced in order to maintain controlled level of noise. The programme should be implemented by properly trained personnel.
Construction Site Run-off and Drainage
· Provision of perimeter drains to intercept off-site water around the site with internal drainage works and erosion and sedimentation control facilities implemented. These shall be constructed in advance of site formation works and earthworks. Earth bunds or sand bag barriers should be provided on-site to direct storm water to silt removal facilities. The design of the temporary on-site drainage system will be undertaken by the Contractor prior to the commencement of construction.
· All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit should be regularly removed, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times.
· Exposed slope/soil surface should be covered by tarpaulin as soon as possible to reduce the potential of soil erosion. Arrangements should always be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm. Other measures that need to be implemented before, during and after rainstorms are summarized in ProPECC PN 1/94.
· Open stockpiles of construction materials (e.g. aggregates, sand and fill material) or construction wastes on-site of more than 50m3 should be covered with tarpaulin or similar fabric during rainstorms.
· Construction works should be programmed to minimise surface excavation works during the rainy seasons (April to September). All exposed earth areas should be completed and vegetated as soon as possible after earthworks have been completed, or alternatively, within 14 days of the cessation of earthworks where practicable. If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed surfaces should be covered by tarpaulin or other means.
· Manholes should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers.
· Precautions be taken at any time of year when rainstorms are likely, actions to be taken when a rainstorm is imminent or forecasted, and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.
· All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequate designed and sited wheel washing facilities should be provided at every construction site exit, where practicable. Wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.
· Oil interceptors should be provided in the drainage system downstream of any oil/fuel pollution sources. The oil interceptors should be emptied and cleaned regularly to prevent the release of oil and grease into the storm water drainage system after accidental spillage. A bypass should be provided for the oil interceptors to prevent flushing during heaving rain.
· Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly to avoid water quality impacts.
Underground Works
General Construction Site Activities
Good Site Practices
· Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.
· Training of site personnel in proper waste management and chemical waste handling procedures.
· Provision of sufficient waste disposal points and regular collection for disposal.
· Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.
· Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors.
· A Waste Management Plan should be prepared and submitted to the Engineer for approval. One may make reference to ETWB TCW No. 19/2005 for details.
· A recording system for the amount of wastes generated, recycled and disposed (including the disposal sites) should be proposed.
Waste Reduction Measures
· Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;
· Encourage collection of aluminium cans by providing separate labelled bins to enable this waste to be segregated from other general refuse generated by the workforce;
· Any unused chemicals or those with remaining functional capacity shall be recycled;
· Proper storage and site practices to minimise the potential for damage or contamination of construction materials; and
· Plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.
Construction and Demolition Material
· Covering stockpile of C&D material entirely by clean impervious sheet to reduce potential dust impact;
· Locating stockpiles to minimise potential visual impacts; and
· Minimizing land intake of stockpile areas as far as possible.
Design
Construction & Establishment Period
OVT Protection
· Measures stipulated in the ETWB TCW No. 29/ 2004 will be followed as appropriate.
· The area will be instituted to guard against intrusion into Cordon Zone (CZ).
· The CZ should not be allowed to become a resting place, eating or recreational space for workers.
· No construction crews, vehicles or equipment should be allowed for enter the CZ.
· Construction materials and equipment should not be stored inside the CZ.
· Construction wastewater or effluent should not flow into the CZ.
· Exhaust fames and hot air emanated by construction machines should not drift into the tree crown.
· The existing concrete paving and soil within CZ should be kept intact to avoid disturbing the soil and the enclosed roots.
· As far as practicable, construction equipment with a short rig or body should be employed to avoid conflicts with the tree crown.
·
Grouting will be carried out in
a controlled and effective manner for the protection of tree roots along
· A programme of close monitoring of tree condition before (baseline evaluation), during and for one year after completion of construction, shall be instituted at regular intervals.
· Induction seminar will be organized to coach construction workers and their supervisors of the need and the precautions to protect the tree.
· Precautionary measures, such as site inspection on tree condition, shall be conducted to protect the trees during the construction stage.
Construction Phase (Landscape)
· Existing trees including OVTs to be retained on site should be carefully protected and maintained during construction. Encroachment of any works close to the drip line of OVTs should be avoided. (CM1)
· Trees of high amenity and survival rate after transplanting which unavoidably affected by the works should be transplanted where practical. (CM2) Tree Transplanting/Replanting Works shall be implemented as early as practical.
Construction Phase (Visual)
· Control of night – time lighting. (CM3)
· Erection of decorative screen hoarding compatible with surrounding setting. (CM4)
Operation Phase (Landscape)
· Aesthetic design of Entrance A1 (Mimimisation of building bulk and adoption of transparent material) and Emergency Exit. (OM1)
·
Planting of 4 nos. of Delonix
regia or species as agreed with LCSD along
Operation Phase (Visual)
·
Reinstatement of
· The EIA and EM&A recommendations on environmental protection and pollution control mitigation measures;
· The Environmental Permit conditions;
· Ongoing results of the EM&A program;
· Works progress and programme;
· Individual works methodology proposals (which shall include proposal on associated pollution control measures);
· Contract specifications on environmental protection;
· Relevant environmental protection and pollution control laws; and
· Previous site inspection results undertaken by the ET and others.
(i) Brief project background information;
(ii) Drawings showing locations of the baseline monitoring stations;
(iii) An updated construction programme;
(iv) Monitoring results together with the following information:
· Monitoring methodology
· Types of equipment used and calibration details
· Parameters monitored
· Monitoring locations
· Monitoring date, time, frequency and duration
(v) Details of influencing factors, including:
· Major activities, if any, being carried out on the site during the period
· Weather conditions during the period
· Other factors which might affect results
(vi) Determination of the Action and Limit Levels for each monitoring parameter and statistical analysis of the baseline data; and
(vii) Comments, recommendations and conclusions.
(i) Executive summary:
· Breaches of Action and Limit levels;
· Complaint log;
· Notifications of any summons and successful prosecutions;
· Reporting changes; and
· Future key issues.
(ii) Basic project information:
· Works undertaken during the month and upcoming months.
(iii) Environmental status:
· Drawings showing the project area and the locations of the monitoring stations; and
· Advice on status of statutory environmental compliance, the status of compliance with environmental permit (EP) conditions under the EIA Ordinance, submission status under the EP and implementation status of mitigation measures.
(iv) A brief summary of EM&A requirements including:
· All monitoring parameters; and
· Environmental quality performance limits (Action and Limit levels).
(v) Monitoring results together with the following information:
· Monitoring methodology;
· Types of equipment used and calibration details;
· Parameters monitored;
· Monitoring locations;
· Monitoring date, time, frequency, and duration;
· Graphical plots of the monitored parameters in the month; and
· Any other factors which might affect the monitoring results.
(vi) Report on non-compliance, complaints, and notifications of summons and successful prosecutions:
· Record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels);
· Record of all complaints received, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· Record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and
· Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
(vii) others
· An account of the future key issues as reviewed from the works programme;
· Advice on the solid and liquid waste management status during the month including waste generation and disposal records; and
· Comments including effectiveness of the mitigation measures, recommendations (for example, any improvement in the EM&A programme) and conclusions.
(i) Executive summary:
· Breaches of Action and Limit levels;
· Complaints log;
· Notifications of any summons and successful prosecutions;
· Reporting changes; and
· Future key issues.
(ii) Environmental status:
· Works undertaken during the month and next month;
· Drawing showing the locations of the monitoring stations; and
· Advice on status of statutory environmental compliance, the status of compliance with environmental Permit (EP) conditions under the EIA Ordinance, submission status under the EP and implementation status of mitigation measures.
(iii) Monitoring results together with the following information:
· Parameters monitored;
· Monitoring locations;
· Monitoring date, time, frequency, and duration;
· Graphical plots of the monitored parameters in the month; and
· Any other factors which might affect the monitoring results.
(iv) Report on non-compliance, complaints, and notifications of summons and successful prosecutions:
· Record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels);
· Record of all complaints received, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· Record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and
· Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
(v) others
· An account of the future key issues as reviewed from the works programme;
· Advice on the solid and liquid waste management status during the month including waste generation and disposal records; and
· Comments including effectiveness of the mitigation measures, recommendations (for example, any improvement in the EM&A programme) and conclusions.
(a) completion of construction activities and insignificant environmental impacts of the remaining outstanding construction works;
(b) trends analysis to demonstrate the narrow down of monitoring exceedances due to construction activities and the return of ambient environmental conditions in comparison with baseline data; and
(c) no environmental complaint and prosecution involved.
The proposed termination should be
implemented after it has been endorsed by the IEC, followed by approval from
the DEP.
(i) Executive summary;
(ii) Basic project information including a synopsis of work undertaken during the course of the Project or past twelve months;
(iii) A brief summary of EM&A requirements including:
· Monitoring parameters; and
· Environmental quality performance limits (Action and Limit levels).
(iv) Advice on the implementation status of environmental and pollution control/mitigation measures;
(v) Drawings showing the project area and the locations of the monitoring stations;
(vi) Graphical plots of the trends of monitored parameters over the course of the Project;
(vii) Provide clear-cut decisions on the
environmental acceptability of the project;
(viii) Advice on the solid and liquid waste management status including waste generation and disposal records;
(ix) A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit Levels);
(x) A brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures;
(xi) A summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;
(xii) A summary record of all complaints received, liaison and consultation undertaken, actions and follow-up procedures taken;
(xiii) Review the monitoring methodology adopted and with the benefit of hindsight, comment and its effectiveness (including cost effectiveness);
(xiv) A summary record of notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislations, locations and nature of the breaches, investigation, follow-up actions taken and results; and
(xv) Review the practicality and effectiveness of the EM&A programme (e.g. a review of the effectiveness and efficiency of the mitigation measures), recommendations (for example, any improvement in the EM&A programme).