This Section elaborates the EM&A requirements for the construction and operation of the
Biodiesel Plant, based on the assessment results for the various environmental
issues considered.
The objectives of undertaking EM&A for
the Project are as follows:
·
to
provide a database against which the environmental impacts of the Project can be determined;
·
to
provide an early indication should any of the environmental control measures or
practices fail to achieve the acceptable standards;
·
to monitor the performance of the Project and the
effectiveness of mitigation measures;
·
to
verify the environmental impacts predicted in this EIA;
·
to
determine project compliance with regulatory requirements, standards and
government policies;
·
to
take remedial action if unexpected problems or unacceptable impacts arise; and
·
to provide data to enable an environmental audit.
With respect to the findings and
recommendations of the EIA study, the following sections describe the EM&A
requirements during construction and operational phases of the Project.
The Implementation Schedule, containing the recommended mitigation
measures, monitoring and audit requirements, and implementation agent of the
mitigation measures for the Project, is presented in Annex D.
As no adverse dust impact is anticipated, no
dust monitoring (in terms of TSP) is required.
However, monthly site audits will be conducted to ensure the implementation of suitable
dust control measures and good site practices recommended in Section 4.7.1.
Monitoring of the emissions of the boiler stack, biogas flare (if in
operation) and process building, and odour concentrations at the final scrubber stack will be carried
out. Odour patrols along the Project Site boundary will also be conducted. The purpose of the monitoring is to ensure
the emissions from the boiler, biogas flare, process building and final
scrubber are operated under its design conditions and emission limits.
The operating
conditions (ie exhaust gas temperature and velocity)
of the boiler, biogas flare (if in operation), and process building stacks will
be monitored at monthly intervals for a period of 12 months after the
commissioning of the biodiesel plant. If the monitoring results of the first year
monitoring meet the limit level, the monitoring will be reduced to half-yearly
intervals for the whole operational stage.
For odour monitoring at
the final air scrubber, the monitoring will be conducted for the first two
operational years of the biodiesel plant. Table 9.2a summarizes the monitoring
parameters, locations and frequency of the emissions from these stacks.
Table 9.2a Monitoring Parameters, Locations and Frequency of the Stacks (a)
Stacks |
Monitoring Frequency |
Parameters |
Boiler |
· Monthly for the
first 12 months of operation. If the monitoring results of the first year
monitoring meet the limit level, the monitoring will be reduced to
half-yearly intervals for the whole operational stage |
Laboratory
analysis for: · NOx · CO · NMOC · SO2 During
measurement: · Exhaust gas
temperature · Exhaust gas
velocity (m s-1) |
Biogas Flare
(if in operation) |
· Monthly for the
first 12 months of operation. If the monitoring results of the first year monitoring
meet the limit level, the monitoring will be reduced to half-yearly intervals
for the whole operational stage |
Laboratory
analysis for: · NOx · CO · NMOC · SO2 During
measurement: · Exhaust gas
temperature · Exhaust gas
velocity (m s-1) |
|
· Monthly for the
first 12 months of operation. If the monitoring results of the first year
monitoring meet the limit level, the monitoring will be reduced to
half-yearly intervals for the whole operational stage |
Laboratory
analysis for: · Acetyldehyde · Methanol During
measurement: · Exhaust gas
temperature · Exhaust gas
velocity (m s-1) |
Final Air
Scrubber |
· Monthly for the
first 2 years of operation |
Laboratory
analysis for: · Odour
concentration (OU s-1) During
measurement: · Exhaust gas temperature · Exhaust gas
velocity (m s-1) |
Note: (a)
Monitoring will not be carried out during raining
days. |
Table 9.2b summarises the monitoring methodologies for
Table 9.2b Monitoring
Methodology
Stacks |
Parameter |
Recommended Method (a) |
Boiler |
· NOx · CO · SO2 · NMOCs · Exhaust gas temperature · Exhaust gas
velocity / flow rate |
· USEPA Method 7 · USEPA Method
10B · USEPA Method 3 · USEPA Method
TO-14 · USEPA 40 CFR
Part 60 · USEPA Method 2D |
Biogas Flare
(if in operation) |
· NOx · CO · SO2 · NMOCs · Exhaust gas
temperature · Exhaust gas velocity
/ flow rate |
· USEPA Method 7 · USEPA Method
10B · USEPA Method 3 · USEPA Method
TO-14 · USEPA 40 CFR
Part 60 · USEPA Method 2D |
|
· Acetyldehyde · Methanol · Exhaust gas
temperature · Exhaust gas
velocity / flow rate |
· USEPA Method
TO-14 · USEPA Method
TO-14 · USEPA 40 CFR
Part 60 · USEPA Method 2D |
Final Scrubber |
· Odour · Exhaust gas
temperature · Exhaust gas
velocity / flow rate |
Air sampling · Grab sampling
by using Teflon bag Laboratory
analysis · Forced-choice
Dynamic Olfactometer according to Eurpean Standard Method (EN13725) |
Note: (a)
Reference to
http://www.epa.gov/ttn/emc/promgate.html |
The limit levels
for
Table 9.2c Limit
Levels for Various Parameters of the Stacks
Stack |
Parameters |
Limit
Level |
Boiler |
NOx |
0.66 g s-1 (based on volume of
oil consumed) |
|
CO |
0.17 g s-1 (based on volume of
oil consumed) |
|
SO2 |
0.24 g s-1 (based on volume of
oil consumed) |
|
NMOC |
1.13 x 10-2 g s-1 (if biogas
is burnt) at 0oC, 1 atm |
|
Exhaust gas pressure |
1 atm |
|
Exhaust gas temperature |
100°C (minimum) |
|
Exhaust gas velocity |
7 m s-1 (minimum) |
Biogas Flare |
NOx |
0.015 g s-1 |
(if in operation) |
CO |
0.005 g s-1 |
|
SO2 |
1.07x10-3 g s-1 |
|
NMOC |
4.9x10-4 g s-1 |
|
Exhaust gas pressure |
1 atm |
|
Exhaust gas temperature |
815°C (minimum) |
|
Exhaust gas velocity |
0.54 m s-1 (minimum) |
|
Acetyldehyde |
0.028 g s-1 |
|
Methanol |
0.028 g s-1 |
|
Exhaust gas temperature |
35°C (minimum) |
|
Exhaust gas velocity |
0.79 m s-1 (minimum) |
Final Scrubber |
Odour |
200.3 OU s-1 |
|
Exhaust gas temperature |
ambient |
|
Exhaust gas velocity |
0.7 m s-1 (minimum) |
Odour patrol will be carried out along the Project
Site boundary on monthly
basis during the first year of the operation of the biodiesel
plant. If there is no exceedance of action limit or there is no substantiated
odour compliant during the first year of operation, the monitoring frequency
will be reduced to quarterly intervals in the second year of the operation.
During the second year of operation, if the action level is triggered,
the frequency will be resumed to monthly until compliance with the action level
for three consecutive months is obtained and the frequency will be reduced to
quarterly interval thereafter. If the
action level is not triggered for four consecutive quarterly monitoring, the
monitoring can be terminated.
The patrol will be conducted a trained
personnel/competent person who should have a specific sensitivity to a
reference odour (i.e. on reference materials n-butanol with the concentration of 50ppm in nitrogen (v/v)).
The parameter, location and frequency of
odour patrol are summarized in Table
9.2d.
Table 9.2d Parameter,
Location and Frequency for Odour Patrol
Patrol Location |
Patrol Frequency |
Parameters |
Patrol
along Biodiesel Plant Site Boundary |
Two times
a day, one in the morning
and one in the afternoon
|
Odour
Intensity (see Table 9.2e) |
The odour intensity detected during the patrol will be categorised as in Table 9.2e.
Table 9.2e Odour
Intensity Level
Class |
Odour Intensity |
Description |
0 |
Not
Detected |
No odour perceived
or an odour so weak that it cannot be easily characterised or described |
1 |
Slight |
Identified
odour, slight |
2 |
Moderate |
Identified
odour, moderate |
3 |
Strong |
Identified
odour, strong |
4 |
Extreme |
Severe
odour |
Odour patrol will be conducted by a
trained personnel/competent person patrolling and sniffing along the Project Site boundary to detect any odour. The trained personnel/competent person shall:
·
Have
their individual odour threshold of n-butanol in
nitrogen gas in the range of 20 to 80 ppb/v required by the Europoean
Standard Method (EN 13725);
·
Be
free from any respiratory diseases;
·
Not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 minutes
before and during the odour patrol; and
·
Take
great care not to cause any interference with their own perception or that of
others by lack of personal hygiene or the use of perfumes, deodorants, body
lotions or cosmetics.
The trained personnel/competent person
shall use their noise (olfactory sensors) to sniff odours along the patrol
route. The main odour emission sources
and the areas to be affected by the odour nuisance shall be identified.
Table
9.2f shows the action and
limit levels to be used for odour patrol.
When the action and limit levels are triggered, investigation will be
carried out to identify the cause of exceedance and
actions in accordance with the Event and
Action Plan will be taken.
Table 9.2f Action
and Limit Levels for Odour
Parameter |
Action Level |
Limit Level |
Perceived
odour intensity and odour complaint |
·
Odour intensity ≥ Class 2
received; or ·
One substantiated complaint
received |
·
Odour intensity ≥ Class 3
recorded on 2 consecutive patrols (a) (b) |
Notes: (a)
Either Class 3-strong or Class
4-extreme odour intensity. (b)
The exceedances
of the odour intensity do not need to be recorded at the same location. |
The Project Proponent
and the Contractor will take the actions in accordance with the Event and
Action Plan in Table 9.2g when the action or limit levels are
exceeded.
Table 9.2g Event
and Action Plan for Air Quality Monitoring During Operational Phase
Event |
Action |
Exceedance of Limit Level
of stack emission |
·
Repeat measurement to confirm findings ·
Identify source(s) and investigate the cause(s) of exceedance ·
Rectify any unacceptable performance ·
Propose and implement remedial measures or amend
design as required |
Exceedance of Action Level
for odour |
·
Identify source/reason of exceedance
or complaint ·
Rectify any unacceptable practice ·
Amend working methods as required ·
Implement amended working methods, if necessary |
Exceedance of Limit Level
for Odour |
·
Identify source/reason of exceedance
or complaint ·
Rectify any unacceptable practice ·
Propose and implement remedial measures or amend
design as required |
The EIA study predicted that the noise
levels at the identified representative NSRs due to
the construction activities of the Project were well below the respective noise
criteria and no NSRs would be adversely affected by
the construction noise, given a large separation distance (more than 700m) between
the NSRs and the Project Site. Noise monitoring during construction phase is
considered not necessary. However,
monthly site inspections will be carried out during construction to audit the
compliance of the Contractor with regard to noise control and to recommend
further mitigation measures if found to be necessary.
No adverse noise
impacts were predicted at the identified representative NSRs during the operational phase and hence no
operational phase monitoring is required.
The impact assessment (see Section 6.5) has evaluated that there
would be no adverse water quality impacts arising from the construction
activities on the Water Sensitive Receivers (WSRs) within the Study Area. As a result,
it is considered that environmental monitoring of water quality is not
required. Nevertheless, monthly site
inspections will be undertaken to ensure that the recommended mitigation
measures are properly implemented during construction. The site audit frequency
will be increased to weekly intervals during the piling works.
The impact assessment (see Section 6.6) indicates that adverse
water quality impacts on the WSRs within the Study
Area are not expected from the operational activities. However, to ensure
that the stormwater or effluent discharged from the
Project Site will comply with the discharge standards, the quality of the stormwater/effluent will be monitored at the terminal
manholes of the stormwater and foul water drainage
systems on a monthly basis. Parameters
to be monitored will include:
·
Stormwater discharge from the site: Oil and
grease and suspended solids;
·
Treated
effluent from the WWTP: Parameters listed in Table 1 of the Technical
Memorandum on Standards for Effluents Discharged to Drainage and Sewerage
Systems, Inland and Coastal Water or those specified in the WPCO licence.
If the
monitoring results indicate exceedance of relevant
effluent standards (stormwater or treated effluent)
to be agreed with the Authority, the actions stipulated in Table 9.4a should
be taken.
Table 9.4a Event and Action Plan for Water Quality
Monitoring During Operational Phase
Event |
Action |
Exceedance of relevant effluent standards (stormwater
or treated effluent) |
·
Repeat measurement to confirm findings ·
Identify source(s) and investigate the cause(s) of exceedance ·
Rectify any unacceptable performance ·
Propose and implement remedial measures or amend
design as required |
No dredging of
marine sediment will be required for the marine works. Potential
impacts to marine ecological resources arising from the construction works will
be associated mainly with the construction of the jetty by piling. The jetty will be constructed in the form of a
piled deck. Bore piles will be driven
through the existing rubble mound seawall.
There will be a direct
loss of a small stretch of low ecological value intertidal and subtidal hard-substrata habitats associated with the
artificial seawall. However, the pile
surfaces can serve as artificial habitats for settlement and re-colonisation of
marine assemblages. Residual
impacts are expected to be low.
Other potential impacts to marine
ecological resources, which may be caused by changes in water quality and
hydrodynamic regime, and accidental spillage of raw materials and biodiesel
during the construction and operation of the biodiesel plant, will be negligible and minimal with the implementation of the recommended mitigation measures and good
site practices.
No environmental monitoring is thus
considered necessary during the construction and operation phases of the
Project. Monthly site inspections
will be carried out during construction phase.