Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Impact Assessment Report
Contents
16.......... SEwerage
and Sewage treatment implications. 16-1
16.1 Introduction. 16-1
16.2 Population and Employment Data. 16-1
16.3 Sewerage Catchments. 16-1
16.4 Hydraulic Assessment Methodology for
Sewerage System.. 16-1
16.5 Sewage Flow Projections. 16-1
16.6 Assessment of Impact to Existing and
Planned Sewerage System.. 16-1
16.7 Proposed Sewerage System inside KTD. 16-1
16.8 Summary. 16-1
16.9 Reference. 16-1
List of
Tables
Table
16.1 Population and Employment Data for Kai Tak
Development to KTPTW
Table 16.2 Population and
Employment Data for Kai Tak Development to TKWPTW
Table 16.3 Planning Data
adopted for Design Scenarios
Table 16.4 Passengers and
Crewmembers of Cruise Vessels
Table 16.5 Sewerage Catchments
of KTPTW and TKWPTW by PVS Zones Excluding KTD Catchment
Table 16.6 Unit Flow Factors
Adopted for KTD
Table 16.7 Unit Flow Factors
for Cruise Vessels
Table 16.8 Pipe Roughness
Coefficient used inside KTD
Table 16.9 Pipe Roughness
Coefficient used inside KTD
Table 16.10 Unit Flow Factors
adopted for KTPTW and TKWPTW Catchments Excluding KTD
Table 16.11 Peaking Factor for
Existing Trunk Sewer
Table 16.12 Estimated Average Dry
Weather Flow of KTD to KTIPS and KTPTW
Table 16.13 Estimated Average Dry
Weather Flow for KTD to TKWPTW
Table 16.14 Estimated Average Dry
Weather Flows for KTIPS, KTPTW and TKWPTW Catchments Excluding KTD
Table 16.15 Estimated Average Dry
Weather Flows for KTIPS, KTPTW and TKWPTW Catchments, Excluding KTD
Table 16.16 Estimated Sewage Flows
for Cruise Vessel Discharge
Table 16.17 Average Dry Weather
Flows for Year 2016, Year 2030 and Ultimate Scenarios
Table 16.18 Peaking Factors for
KTIPS, KTPTW and TKWPTW
Table 16.19 Projected Peak Flows
for Year 2016 and Year 2030 Scenarios
Table 16.20 Dimensions of the
Trunk Sewers along Hoi Bun Road
Table 16.21 Existing Facilities of
KTIPS
Table 16.22 Projected Flows of
KTIPS
Table 16.23 Existing Facilities of
KTPTW
Table 16.24 Projected Flows of
KTPTW under RCESMP (2003)
Table 16.25 Projected Flows of
KTPTW under TR4E (2006)
Table 16.26 Projected Flows of
KTPTW
Table 16.27 Existing Facilities of
TKWPTW
Table 16.28 Projected Flows to
TKWPTW under RCESMP (2003)
Table 16.29 Projected Flows to
TKWPTW under TR4E (2006)
Table 16.30 Projected Flows for
TKWPTW
Table 16.31 Design Capacities of
the Conveyance Tunnels
Table 16.32 PWWFs at Ultimate
Stage for the Design of Conveyance Tunnels
Table 16.33 Projected Peak Wet
Weather Flows to KTPTW and TKWPTW
Table 16.34 Comparison of
Estimated Overflow
Table 16.35 Estimated ADWF for Kai
Tak Development
Table 16.36 Estimated ADWF for
KTIPS, KTPTW and TKWPTW Catchments Excluding KTD
Table 16.37 Estimated Sewage Flows
for Cruise Vessel Discharge
Table 16.38 Projected ADWF for
KTIPS, KTPTW and TKWPTW
Table 16.39 Projected PWWF
for KTIPS, KTPTW and TKWPTW
Table 16.40 Design Capacities and
Projected PWWF of KTIPS and KTPTW
16
SEwerage and Sewage
treatment implications
16.1
Introduction
16.1.1
This Section describes
the assessment of the impacts on the existing sewerage system in the vicinity
of the study area resulting from the planned development, and recommends
appropriate mitigation measures where adverse impacts are identified. The
new sewerage network within the study area arising from the proposed
development is also presented. The criteria and guidelines for evaluating
and assessing the sewerage impact of the Project on the public sewerage and
sewage treatment and disposal facilities as given in Section 6.5 in Annex 14 of
the EIAO-TM are considered in the assessment.
16.1.2
The coverage of this
Section includes:
·
Present the population
and employment data based on the latest KTD development schedule as well as the
population figures from the Planning Department
·
Present the sewerage
catchments of the Kai Tak Development, Kwun Tong Preliminary Treatments Works
(KTPTW), and To Kwa Wan Preliminary Treatments Works (TKWPTW)
·
Present the hydraulic
assessment methodology for sewerage system adopted for the Project
·
Present the flow
projections for the catchments of the Project
·
Assess the impacts to
the existing and planned sewerage system, sewage treatment and disposal
facilities
·
Describe the proposed
sewerage system inside KTD
·
Summarize the findings
and conclusions
16.1.3
The Study has taken
note and agreed with EPD on the relevant development arising from Action Plan
for Tackling Water-Related Pollution problems at the Kai Tak Approach Channel
by relevant departments (sewerage infrastructure related). The Action
Plan includes the following elements:
Project Title
|
Brief Scope of Works
|
Responsible Department
|
Target Completion Date
|
4344DS “Upgrading of Central
& East Kowloon
Sewerage - Packages 1 to 4”
|
Upgrading and construction of
about 21km long sewers and associated sewerage works in Kwun Tong, Ngau Tau Kok,
Yau Tong, Kowloon Bay, Choi Hung, Wong Tai Sin, San Po Kong, Kowloon City, To
Kwa Wan, Ma Tau Kok, Hung Hom and Tsim Sha Tsui and upgrading of some
existing dry weather flow interceptors in Central and East Kowloon.
|
DSD
|
2014 (2012 for relevant upstream
sewers of KTAC)
|
Sewerage Interception in Kowloon City
|
Divert the flows from Kowloon City and San Po Kong area to the To
Kwa Wan Wan PTW.
|
DSD
|
2012
|
Kai Tak Development
|
Plan and Provide for adequate
sewerage infrastructure to serve the planned facilities in KTD.
|
CEDD
|
2016
|
Kai Tak Approach Channel –
Expedient Connection Survey
|
Undertake surveys for
identification of expedient connections in public drains/sewers and domestic buildings
in Kowloon City, Ngau Tau Kok, Kowloon Bay, Wong Tai Sin and Choi Hung.
|
EPD
|
2009
|
Control of Water Pollution at
Jordan Valley Box Culvert
|
Install interception facility
at JVBC to divert polluted water into public sewerage system.
|
DSD
|
2012
|
16.2
Population and
Employment Data
Kai Tak Development
16.2.1
The delineation of the
sewerage catchments and population within Kai Tak Development (KTD) are based on
the latest development schedule of Recommended Outline Development Plan
(May08). The intake years of development sites in KTD are presented in Figure 16.3.
16.2.2
The development schedule
showing the latest population and employment data and the development schedule
is presented in Appendix
16.1. The categorization of residential population and employment
followed DSD’s Sewerage Manual Part 1 (1995).
16.2.3
The population
projections for Year 2016 and Year 2021 (commissioning of the whole KTD)
contributed to the sewerage catchments of KTPTW and TKWPTW are summarized in Table
16.1 and 16.2 respectively.
Table 16.1 Population and Employment
Data for Kai Tak Development to KTPTW
Category
|
Population
|
Year
2016
|
Year
2021
|
Domestic
|
|
|
Public Rental House (RS)
|
35,000
|
35,000
|
R1
|
0
|
0
|
R2
|
10,812
|
10,812
|
R3
|
0
|
4,873
|
Mix Use
|
0
|
1,819
|
Sub-Total
|
45,812
|
52,504
|
Commercial
|
|
|
Employees
|
20,634
|
48,496
|
Hotel
|
3,179
|
9,238
|
Hospital
|
0
|
800
|
Sub-Total
|
23,813
|
58,535
|
School
|
|
|
Student
|
8,420
|
8,420
|
Total
|
78,045
|
119,459
|
Table
16.2 Population and Employment Data for Kai Tak Development to TKWPTW
Category
|
Population
|
Year
2016
|
Year
2021
|
Domestic
|
|
|
Public Rental House (RS)
|
0
|
0
|
R1
|
4,740
|
4,740
|
R2
|
0
|
25,891
|
R3
|
0
|
0
|
Mix Use
|
2,312
|
2,312
|
Sub-Total
|
7,052
|
32,944
|
Commercial
|
|
|
Employees
|
19,477
|
34,361
|
Hotel
|
0
|
2,832
|
Hospital
|
0
|
0
|
Sub-Total
|
19,477
|
37,193
|
School
|
|
|
Student
|
4,210
|
5,480
|
Total
|
30,739
|
75,616
|
16.2.4
As advised by LCSD in August 2007, the number of
visitors and workers at Runway Park is estimated to be 11,250 persons per day.
Since population figures for Metro Park in KTD are not available at this stage,
assumption on 11,250 persons per day (visitors and workers) is also applied.
Developments within KTPTW and TKWPTW Sewerage
Catchments, Excluding KTD
16.2.5
For the sewerage catchments outside Kai Tak
Development, the planning data provided by Planning Department (PlanD) would be
adopted for the following design scenarios (Table 16.3).
Table
16.3 Planning Data adopted for Design Scenarios
Scenario
|
Planning Data
|
2016
|
Territorial Population and Employment Data Matrix (TPEDM)
2003-based Estimate – Scenario II
|
2030
|
Hong Kong 2030: Planning Vision and Strategy (HK2030
Study)
|
Ultimate
|
HK2030 Study + 5%
|
Note: An extra 10% contingency is added to the calculated
ADWFs and peak flows.
Para. 16.8.3 refers.
Cruise Vessel
16.2.6
The sewage to be
collected from the cruise vessel is based on the number of passengers and crewmembers
for different types of vessel to be berthed in the planned Cruise Terminal.
16.2.7
Based on the design of the Marine Works at Kai Tak, a
cruise terminal is proposed at the southeast tip of the former Kai Tak runway.
The terminal is planned to accommodate two berthing scenarios: (1) one super
post-Panamax (SPP) vessel (360m-length) and one post-Panamax (PP) vessel (max
length 345m); or (2) two post-Panamax vessels.
16.2.8
For the estimation of passengers and crewmembers of
vessels, reference is made to the passengers and crewmembers of the existing
and being built vessels. Table 16.4 shows the passengers and
crewmembers of different cruise vessels for sewage flow estimate.
Table
16.4 Passengers and Crewmembers of Cruise
Vessels
|
Vessel
Type
|
Super
Post-Panamax
|
Post-Panamax
|
Passengers
|
5,400
|
4,000
|
Crewmembers
|
2,000
|
1,500
|
TOTAL
|
7,400
|
5,500
|
Notes:
The crewmember to passenger ratio is 37%.
|
16.3
Sewerage Catchments
16.3.1
The sewerage catchments
in KTD have been divided into twelve catchments (A to L). The sewage from
seven catchments (E, F, G, H, I, J and L) would be conveyed to Kwun Tong
Preliminary Treatment Works (KTPTW) and the sewage from the remaining
catchments would be conveyed to To Kwu Wan Preliminary Treatment Works
(TKWPTW). The sewerage catchments in the KTD are shown in Figure 16.1.
The site references of the sub-planning areas are shown in Figure 16.2.
16.3.2
The sewerage catchments
by Planning Vision and Strategy (PVS) Zones of KTPTW and TKWPTW are shown in Figure 16.4.
The sewage flows to KTPTW and TKWPTW excluding KTD are based on the EPD’s
Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning
(2005). The following table (Table 16.5) shows the sewerage
catchments by PVS Zones of KTPTW and TKWPTW excluding KTD catchment.
Table 16.5 Sewerage
Catchments of KTPTW and TKWPTW by PVS Zones
Excluding KTD Catchment
Kwun
Tong Preliminary Treatment Works
|
To
Kwa Wan Preliminary Treatment Works
|
PVS
Zone No.
|
Proportion
of Sewage Flow of PVS
|
PVS
Zone No.
|
Proportion
of Sewage Flow of PVS
|
101
|
1.0
|
054-057
|
1.0
|
102
|
0.1
|
058
|
0.05
|
103
|
0.4
|
059
|
0.05
|
104
|
0.0
|
062
|
1.0
|
105-109
|
1.0
|
068-072
|
1.0
|
111-129
|
1.0
|
073
|
0.25
|
219
|
0.1
|
075-077
|
1.0
|
304
|
0.3
|
078
|
0.5
|
305
|
0.4
|
097
|
0.15
|
307-309
|
1.0
|
098-100
|
1.0
|
-
|
-
|
102
|
0.9
|
-
|
-
|
103
|
0.6
|
-
|
-
|
104
|
1.0
|
-
|
-
|
275
|
1.0
|
-
|
-
|
300-302
|
1.0
|
-
|
-
|
304
|
0.7
|
-
|
-
|
305
|
0.6
|
Notes: (1) PVS marked with
SEKD, i.e. PVS 253, 254, 336 and 337 of KTPTW and PVS 110, 254, 260, 278, 306 and
335 of TKWPTW, would not be included for flow projection under KTPTW or TKWPTW
catchments. The flow projection of these PVS zones would be discussed
under Kai Tak Development.
(2) Source: Guidelines for Estimating Sewage Flows for Sewage Infrastructure
Planning Version 1.0, by EPD.
16.3.3
In addition to the sewage flows generated from KTPTW
sewerage catchments, sewage discharges from cruise vessels will be included in
the assessment. Cruise ships would be berthed in the planned Cruise
Terminal in the ex-runway area and the sewage from cruise vessels would be
discharged to the planned sewerage system at Cruise Terminal and then conveyed
to Kwun Tong Intermediate Pumping Station (KTIPS) and eventually to KTPTW via
the existing trunk sewers along Hoi Bun Road.
16.4
Hydraulic Assessment Methodology for Sewerage
System
16.4.1
InfoWorks CS version 7.51 developed by Wallingford
Software would be used as a tool in the hydraulic assessment. InfoWorks has the capability of modelling urban sewerage systems and is
capable of determining the capacity of culverts, pipes, channels and hydraulics
structures.
16.4.2
The hydraulic assessment methodology is critical to the
result of the assessment. Also, the model simulation result would greatly vary
depending on different simulation run parameters used. Different methodology in
modeling also yields different results. Hence, in this Section, the basis of
the background information together with the adoption of different parameters
would be elaborated. In addition, the methodology of modelling would be
presented in this Section as well.
16.4.3
The hydraulic
assessment methodology is composed of two portions:-
·
Hydraulic Assessment Methodology for the New Sewers
inside KTD
· Hydraulic Assessment Methodology for the Existing Trunk Sewer
Hydraulic
Assessment Methodology for the New Sewers inside KTD
16.4.4
In the proposed sewerage scheme of Kai Tak Development (KTD),
sewage generated from the new developments would be conveyed to the existing
sewerage system.
16.4.5
For designing the size of the proposed sewers for KTD,
the capacity of the new sewer would be assessed by hydraulic modeling.
Sewage Flows
16.4.6
The dry weather sewage flows of the Kai Tak Development
(KTD) sewerage catchments are calculated based on the latest development
schedule of KTD with unit flow factors given in the Sewerage Manual Part
1. The unit flow factors adopted in the assessment for KTD are shown as
follows (Table 16.6):
Table
16.6 Unit Flow Factors Adopted for KTD
Category
|
Unit
(per)
|
Unit
Flow Factors
(m3/d)
|
Domestic
|
|
|
·
Public Rental House (RS)
|
person
|
0.175
|
·
R1
|
person
|
0.240
|
·
R2
|
person
|
0.300
|
·
R3
|
person
|
0.370
|
·
Mixed Use
|
person
|
0.370
|
Commercial
|
|
|
·
Employment
|
employee
|
0.350
|
·
Hotel(1)
|
person
|
0.240
|
·
Hospital(1)
|
person
|
0.370
|
School
|
person
|
0.025
|
Note: (1) The unit flow factors for “Hotel’
and “Hospital” are based on the agreed values presented in the Technical Report
No. TR4E under the Agreement No. CE4/2004(TP) – Kai Tak Planning
Review.
16.4.7
For the parks inside KTD, the projected sewage flows
are based on the total no. of visitors and workers with the unit flow factor of
0.010 m3/d/person and 0.025 m3/d/person
respectively. With reference to other local projects containing large
scale theme park, the visitors to KTD’s recreation parks are assumed to be
mobile and will not stay in the park for long period and hence the unit flow
factor for visitors and the generated sewage shall be smaller as compared to
the theme parks. For the unit flow factor for workers in the park,
the same unit flow factor for school is adopted.
16.4.8
For the cruise vessel, the sewage from cruise vessels
mainly comprises blackwater and greywater. Blackwater is the toilet water
and medical facility water while greywater is the wastewater generated from
showers, sinks, food liquid, laundry, etc. Reference has been made to
Alaska Cruise Ship Initiative 2000 for the unit flow factors to be adopted in
estimating sewage flows from cruise vessels. (Table 16.7)
Table
16.7 Unit Flow Factors for Cruise Vessels
|
Unit
(per)
|
Unit
Flow Factors
(m3/d)
|
Blackwater
- Passenger / crewmember
|
Person
|
0.019
|
Greywater
- Passenger / crewmember
|
Person
|
0.209
|
Source: Alaska Cruise Ship Initiative 2000.
Pipe
Roughness
16.4.9
The pipe roughness is specified as an equivalent sand
roughness (ks) used by the Colebrook-White equation. For the hydraulic assessment
of the new sewers inside KTD, the roughness coefficient to be used would follow
the values proposed in the Design Memorandum (DM) of this study as listed
below:- (Table 16.8)
Table 16.8 Pipe Roughness Coefficient used
inside KTD
Pipe Size
|
Pipe Material
|
ks
|
<600mm
|
Vitrified Clay Pipe
|
0.6mm
|
>=600mm to 2400mm
|
Precast Concrete Pipes with PVC
lining
|
1.5mm
|
Global
Peaking Factors
16.4.10
The unit flow factor (UFF) and population together with
appropriate global peaking factors would be inputted to the hydraulic model for
capacity assessment.
16.4.11
The global peaking factor is based on the cumulative
contributing population. As the cumulative contributing population
increases, the global peaking factor and the peak flow will decrease.
Although separate sewerage system and stormwater system will be designed from
KTD, as a conservative approach, the global peaking factors including
stormwater allowance would be used for assessing the peak flow condition.
The global peaking factor is selected in accordance with the following table: (Table
16.9)
Table 16.9 Peaking Factor for Sewers in KTD
Population Range
|
Global Peaking Factor (including stormwater allowance) for sewers
|
<
1,000
|
8
|
1,000
– 5,000
|
6
|
5,000
– 10,000
|
5
|
10,000
– 50,000
|
4
|
>
50,000
|
7.3/N0.165
|
Note: N is
the contributing population in thousands
16.4.12
(Not used)
Peaking Factor Scenarios and Model Runs
16.4.13
Hydraulic analysis of different peaking factor
scenarios would be undertaken for assessment of different sections of sewers in
the following:-
·
Different Global Factor Scenarios for different
sections of sewers
·
Performance Scenario (a flat DWF profile of 3 times
ADWF for simulation runs with duration not less than 3 hours; and a flat DWF
profile of 4 times ADWF with duration of 2 hours for sewer size smaller or
equal to 375mm diameter)
16.4.14
The Performance
Scenario using for hydraulic analysis is made reference to Chapter 11 of the
EPD Guidelines for Sewer Network Hydraulic Model Build and Verification for the
new sewers inside KTD since the field data for the new catchments inside KTD
are not available.
16.4.15
The modelling approach
is based on the EPD Guidelines for Sewer Network Hydraulic Model Build and
Verification for the hydraulic modelling assessment for the new sewers inside
KTD.
Hydraulic
Assessment Methodology for the Existing Trunk Sewer
16.4.16
In the proposed sewerage scheme of Kai Tak Development
Area (KTD), sewage generated from the new developments would be conveyed to
existing trunk sewer and then onward transfer to existing sewage treatment
plant for further treatment. Assessment of the capacity of the existing trunk
sewer subjected to the additional sewage flow from KTD is necessary in order to
justify the feasibility of the proposed sewerage scheme.
Sewage Flows
16.4.17
The sewage flows for the sewerage sub-catchments of the
existing trunk sewer outside KTD are projected based on the latest planning
data from PlanD and the unit flow factors given in the Guidelines for
Estimating Sewage Flows for Sewage Infrastructure Planning (GESF) (2005) from
EPD. The unit flow factors adopted in the assessment for KTPTW and TKWPTW
are shown as follows (Table 16.10):
Table 16.10 Unit Flow Factors adopted for KTPTW and TKWPTW
Catchments
Excluding KTD
Category
|
Unit
(per)
|
Unit
Flow Factor
(m3/day)
|
KTPTW
|
TKWPTW
|
Domestic
|
|
|
|
·
Permanent Housing
|
person
|
0.190
|
0.190
|
·
Other Housing
|
person
|
0.175
|
0.175
|
·
Mobile Residents
|
person
|
0.190
|
0.190
|
Commercial(1)
|
|
|
|
·
J2 Electricity Gas & Water
|
employee
|
0.330
|
0.330
|
·
J3 Transport, Storage & Communication
|
employee
|
0.180
|
0.180
|
·
J4 Wholesale & Retail Trades
|
employee
|
0.280
|
0.280
|
·
J5 Import & Export Trades
|
employee
|
0.080
|
0.080
|
·
J6 Finance, Insurance, Real Estate & Business
Service
|
employee
|
0.080
|
0.080
|
·
J7 Agriculture & Fishing
|
employee
|
0.080
|
0.080
|
·
J8 Mining & Quarrying
|
employee
|
0.080
|
0.080
|
·
J9 Construction
|
employee
|
0.230
|
0.230
|
·
J10 Restaurants & Hotels
|
employee
|
1.580
|
1.580
|
·
J11 Community, Social & Personal Service
|
employee
|
0.280
|
0.280
|
·
J12 Public Administration
|
employee
|
0.080
|
0.080
|
School
·
School student
|
person
|
0.040
|
0.040
|
Industrial
·
J1 Manufacturing
|
employee
|
0.530
|
0.630
|
Notes: (1) The unit flow factor for
commercial shown is the sum of the unit flow factor of employee (0.080m3/day)
and the unit flow factor of commercial activities of a particular trade under
consideration.
16.4.18
Catchment-inflow-factors (PCIF) are
extracted from the EPD’s guideline to assess broadly the extent of the overall
net excessive inflow situation of every catchment. Net inflow to the
sewerage system is the combined effect of two principal effects:
·
Undesirable inflow to the sewerage system occurs when
stormwater or groundwater enters the sewerage system through cracks in the
sewers or when stormwater pipes are incorrectly connected to sewers.
·
On the other hand, flow to the sewerage system is
reduced when sewage is discharged illegally or inadvertently into stormwater
system. These expedient connections tend to occur mostly in the older
catchments. Eradication of expedient connections will increase sewage
flow to the PTWs.
16.4.19
As described in the Final Report on Flow & Load Projections,
issued in Mar 2008 under the HATS project (Agreement
No. CE8/2006), the Catchment-inflow-factors were adjusted with more updated
flow data. Hence, the PCIF for KTPTW and TKWPTW catchments are
1.14 and 1.00, respectively.
16.4.20 There are inherent uncertainties in the flow estimates due to a
number of as-yet unquantified factors (e.g. unit flow factors, catchment-inflow
factors, transient population and portions of different types of residential
populations). It is proposed to add an extra 10% contingency to the
calculated ADWFs and peak flows. It is assumed that the 10% contingency for the
uncertainties will be materialised linearly from year 2006 until 2030 (i.e.
+2% on Year 2010; +6% on Year 2020 and 10% on Year 2030/Ultimate). This approach is based on the report of “Technical Note
Flow and Load Projections” under Agreement No. CE 45/2005(EP) – HATS Stage 2A
Environmental Impact Assessment Study – Investigation.
Model
Networks and Catchment
16.4.21
The sewerage network model built in 2001 with projected
population scenarios for the Central and East Kowloon
sewerage catchments was obtained from EPD in March 2007. Recently, the
latest sewerage network model for the existing East Kowloon sewerage catchment
was available from EPD. However, the latest sewerage network model for
the Central Kowloon sewerage catchment is still under preparation by EPD and
not yet available. The latest model only covers the flow condition of the
existing population scenario without future population scenarios. The existing
trunk sewer of the latest model was slightly modified by EPD according to the
as-built records in comparison with the model built in 2001. Since the
aim of the hydraulic assessment is to check the capacity of the existing trunk
sewer, the latest sewerage network model was used and trimmed to a simplified model
which contains the network of the concerned trunk sewer only for hydraulic
assessment.
Pipe
Roughness
16.4.22
The pipe roughness is specified as an equivalent sand
roughness (ks) used by the Colebrook-White equation. In this hydraulic
assessment, the roughness coefficient to be used for the existing sewer would
follow the values (Ks=3mm) adopted in the previous Review of Central and East
Kowloon Sewerage Master Plans (RCEKSMP).
Sediments
16.4.23
The presence of sediments inside the trunk sewer will
reduce the capacity of the sewer due to the reduction in cross sectional
area. Based on the field data from the flow survey conducted under this
Project so far, the depth of sediments at various part of the trunk sewer (i.e.
box culvert to KTPTW) varies from 0 to 200mm,
about 0 to 8.7% of the height of the culvert. The sediment depth used in the
model will be referenced to the measured silt depth from the survey data. (The
measured silt levels in the trunk sewer conducted by the flow surveys in May
2007 were presented in Appendix B of the report of “Hydraulic Assessment on
Trunk Sewer and Treatment Facilities based on the Flow Survey Data” under
Agreement No. CE 35/2006(CE) project.) The average value of the silt depths is
hence assigned to the whole trunk sewer of the sewerage network models.
Peaking
Factors
16.4.24
The peak flow for the corresponding section of trunk
sewer is used in the hydraulic assessment to examine the sewerage impact.
The peak flow is calculated from multiplying the average dry weather flow
(ADWF) by the peaking factor.
16.4.25
The peaking factor is based on the cumulative
contributing population. As the cumulative contributing population
increases, the peaking factor and the peak flow will decrease. The
peaking factor including stormwater allowance is used for the calculation of
the peak flow. The peaking factor for the trunk sewer is selected in
accordance with the following table (Table 16.11):
Table
16.11 Peaking Factor for Existing Trunk Sewer
Population Range
|
Peaking Factor (including stormwater allowance) for facility with
existing upstream sewerage
|
<
1,000
|
8
|
1,000
– 5,000
|
6
|
5,000
– 10,000
|
5
|
10,000
– 50,000
|
4
|
>
50,000
|
Max[7.3/N0.15,
2.4]
|
Note: N is
the contributing population in thousands
16.4.26
The contributing population is equal to the calculated
total average flow divided by a factor of 0.27. The factor is taken as an
average unit flow factor described in Paragraph 12 of the Guidelines for
Estimating Sewage Flows for Sewage Infrastructure Planning (GESF) (2005) from
EPD.
Design
Scenarios and Model Runs
16.4.27
Hydraulic analysis of different design scenarios would
be undertaken for the following:
·
2016 Design Scenario;
·
2030 Design Scenario; and
·
Ultimate Scenario (2030 Design Scenario + 5%)
16.4.28
According to Para 16.4.20, uncertainty allowances
are added to the calculated ADWFs and peak flows.
Modelling
Approach
16.4.29
The following approach is applied for the hydraulic
modelling assessment without availability of calibrated flows data for the
existing trunk sewer:
·
Identify the discharge points from the existing
sewerage catchments and the Kai Tak Development sewerage catchments for
assessment.
·
Calculate the average dry weather flows (ADWF) of the
sewerage catchments.
·
Determine the peaking factors based on the cumulative
contributing population at different sections of the trunk sewer for different
scenarios.
·
Calculate the peak flows for different sections of the
trunk sewer at different design scenarios.
·
Enter inflow hydrographs with the peak flows to the
model for different design scenarios at different sections of the trunk sewer
for model runs.
· Conduct model runs for different design scenarios.
16.4.30
When the flow survey data is available, the verification
and calibration adjustments will be made to the sewerage model network to
achieve a good fit between observed and predicted flows. Afterward a
simulation for the total peak flows including a calibrated dry weather diurnal
flow and a synthetic storm event (1 in 5 year return period as referenced to
“Guidelines for Sewer Network Hydraulic Model Build and Verification” issued by
EPD) will be applied to the calibrated sewerage model network to replace the
methodology of peaking factors at different sections of the trunk sewer adopted
in the above, if the peak flows based on surveyed data is higher than the
calculated peak flow described in Para 16.4.24.
Model
Calibration by Flow Survey Data
1.
Dry Weather Flow
16.4.31 The predicted velocity will be adjusted by changing the pipe
roughness of the sewer in the model to fit the measured velocity.
If the section of the sewer between flow monitors is the same, the average
value of pipe roughness will be applied to this section. The pipe roughness
of the whole trunk sewer in the model will be adjusted accordingly.
16.4.32
With the flow Survey data from the selected dry weather
events, the values of measured flow, water depth and velocity were obtained at
flow monitor locations. Plots for the measured flow, water depth and
velocity are required to show for a 24 hour daily period.
16.4.33
Dry weather diurnal profile will be obtained from the
measured flow data of the most downstream of the flow monitor of the respective
sub-catchment. Modifications to the average unit flow factor will be made
to each sewerage sub-catchment in order to fit the predicted dry weather flow
to the measured dry weather flow.
16.4.34
The predicted water depth will be adjusted by changing the
sediment depth of the sewer in the model to fit the measured water depth.
The sediment depth used in the model will be based on the measured silt depth
from the survey data. The average value of the silt depths amongst the
flow monitor location will be applied to the trunk sewer section within the
respective sub-catchment. Hence, the sediment depth of the whole trunk sewer in
the model is determined.
2.
Wet Weather Flow
16.4.35 A suitable storm event from the flow survey data will be selected
for storm verification process. Similar to the dry weather event, plots
for the measured flow, water depth and velocity are required to show for a 24
hour daily period.
16.4.36 Rainfall data will be obtained from the field raingauge monitoring
locations. The rainfall data would be used for a model run to
determine the percentage of the surface runoff entered into the sewerage
network for each sub-catchment. This percentage represents the
infiltration of the storm flows into the sewerage model network for different
storm event scenarios.
16.5
Sewage Flow Projections
Kai Tak Development
16.5.1
Based on the population and the unit flow factors, the
average dry weather flows of Kai Tak Development (excluding sewage flow from
cruise vessels) for Year 2016 and Year 2021 contributed to KTPTW and TKWPTW are
estimated as shown in Table 16.12 and Table 16.13 respectively.
Table
16.12 Estimated Average Dry Weather Flow of KTD to KTIPS and KTPTW
Category
|
ADWF
(m3/d)
|
Year
2016
|
Year
2021
|
Domestic
|
|
|
·
Public Rental House (RS)
|
6,125
|
6,125
|
·
R1
|
0
|
0
|
·
R2
|
3,244
|
3,244
|
·
R3
|
0
|
1,803
|
·
Mixed Use
|
0
|
673
|
Sub-Total
|
9,369
|
11,845
|
Commercial
|
|
|
·
Employment
|
7,222
|
16,974
|
·
Hotel
|
763
|
2,217
|
·
Hospital
|
0
|
296
|
Sub-Total
|
7,985
|
19,487
|
School
|
211
|
211
|
TOTAL
|
17,565
|
31,543
|
Notes: (1) The breakdown of flow projection of KTD (ADWF)
excluding cruise vessels to KTPTW
is
presented in Appendix
16.2A-1.
Table
16.13 Estimated Average Dry Weather Flow for KTD to TKWPTW
Category
|
ADWF
(m3/d)
|
Year
2016
|
Year
2021
|
Domestic
|
|
|
·
Public Rental House (RS)
|
0
|
0
|
·
R1
|
1,138
|
1,138
|
·
R2
|
0
|
7,767
|
·
R3
|
0
|
0
|
·
Mixed Use
|
856
|
856
|
Sub-Total
|
1,994
|
9,761
|
Commercial
|
|
|
·
Employment
|
6,817
|
12,026
|
·
Hotel
|
0
|
680
|
·
Hospital
|
0
|
0
|
Sub-Total
|
6,817
|
12,706
|
School
|
105
|
137
|
Others(1)
|
|
|
·
Handwashing at Toilets in Stadium
|
950
|
950
|
·
Showering in Stadium
|
173
|
173
|
·
Toilet Flushing in Stadium
|
4,604
|
4,604
|
Sub-Total
|
5,727
|
5,727
|
TOTAL
|
14,642
|
28,330
|
Notes:
(1) Estimated ADWF in Stadium is quoted from Appendix C - Site No. 2D-1 Stadium
Fresh and Salt Water Demand Estimate of Technical Report No. TR4F:
Preliminary Water and Utility Assessments (Final)
(2) Projected flow is rounded to the nearest
integer.
16.5.2
The breakdown of the flow projections inside KTD for
Sewerage Catchments A-L (KTPTW and TKWPTW catchments) is presented in the Appendix 16.2A-2.
Developments within KTPTW and TKWPTW Catchments,
Excluding KTD
16.5.3
Based on the population and the unit flow factors, the
average dry weather flows of KTIPS, KTPTW and TKWPTW catchments excluding KTD
for Year 2016, Year 2030 and Ultimate Scenarios are estimated as shown in Tables
16.14 and 16.15.
Table
16.14 Estimated Average Dry Weather Flows for KTIPS, KTPTW and TKWPTW
Catchments, Excluding KTD
Category
|
Year 2016 ADWF
|
KTIPS
(m3/d)
|
KTPTW
(m3/d)
|
TKWPTW
(m3/d)
|
Domestic
|
·
Permanent Housing
|
120,285
|
194,309
|
96,844
|
·
Other Housing
|
1,366
|
2,002
|
2,295
|
·
Mobile Residents
|
4,222
|
6,567
|
3,565
|
Sub-Total
|
125,873
|
202,878
|
102,704
|
Commercial
|
·
J2 Electricity Gas &
Water
|
299
|
334
|
227
|
·
J3 Transport, Storage &
Communication
|
8,547
|
9,824
|
5,035
|
·
J4 Wholesale & Retail
Trades
|
17,733
|
19,610
|
11,287
|
·
J5 Import & Export Trades
|
10,700
|
11,090
|
5,835
|
·
J6 Finance, Insurance, Real
Estate & Business Service
|
7,731
|
8,129
|
3,508
|
·
J7 Agriculture & Fishing
|
18
|
34
|
15
|
·
J8 Mining & Quarrying
|
0
|
0
|
0
|
·
J9 Construction
|
7,177
|
8,482
|
3,703
|
·
J10 Restaurants & Hotels
|
35,330
|
40,939
|
60,776
|
·
J11 Community, Social &
Personal Service
|
20,180
|
29,465
|
21,952
|
·
J12 Public Administration
|
329
|
489
|
737
|
Sub-Total
|
108,044
|
128,396
|
113,075
|
School
·
School student
|
4,241
|
6,233
|
4,236
|
Industrial
·
J1 Manufacturing
|
4,009
|
4,858
|
3,563
|
Total
|
242,167
|
342,365
|
223,578
|
Table
16.15 Estimated Average Dry Weather Flows for KTIPS, KTPTW and TKWPTW
Catchments, Excluding KTD
Category
|
Year 2030 ADWF
|
Ultimate ADWF
|
KTIPS
(m3/d)
|
KTPTW
(m3/d)
|
TKWPTW
(m3/d)
|
KTIPS
(m3/d)
|
KTPTW
(m3/d)
|
TKWPTW
(m3/d)
|
Domestic
|
·
Permanent Housing
|
132,208
|
219,017
|
113,188
|
138,818
|
229,970
|
118,849
|
·
Other Housing
|
1,080
|
1,527
|
1,393
|
1,134
|
1,603
|
1,462
|
·
Mobile Residents
|
5,496
|
8,795
|
5,013
|
5,770
|
9,234
|
5,263
|
Sub-Total
|
138,784
|
229,339
|
119,594
|
145,722
|
240,807
|
125,574
|
Commercial
|
·
J2 Electricity Gas &
Water
|
240
|
267
|
183
|
252
|
281
|
192
|
·
J3 Transport, Storage &
Communication
|
8,721
|
10,186
|
6,507
|
9,157
|
10,695
|
6,832
|
·
J4 Wholesale & Retail
Trades
|
10,428
|
12,480
|
11,072
|
10,949
|
13,103
|
11,625
|
·
J5 Import & Export Trades
|
9,655
|
10,040
|
5,986
|
10,137
|
10,542
|
6,286
|
·
J6 Finance, Insurance, Real
Estate & Business Service
|
5,101
|
5,565
|
4,495
|
5,356
|
5,843
|
4,719
|
·
J7 Agriculture & Fishing
|
14
|
26
|
12
|
15
|
28
|
13
|
·
J8 Mining & Quarrying
|
0
|
0
|
0
|
0
|
0
|
0
|
·
J9 Construction
|
8,315
|
10,017
|
4,552
|
8,731
|
10,517
|
4,779
|
·
J10 Restaurants & Hotels
|
37,586
|
44,294
|
62,257
|
39,465
|
46,508
|
65,370
|
·
J11 Community, Social &
Personal Service
|
22,894
|
34,528
|
26,592
|
24,039
|
36,254
|
27,922
|
·
J12 Public Administration
|
362
|
491
|
574
|
380
|
515
|
603
|
Sub-Total
|
103,316
|
127,894
|
122,230
|
108,481
|
134,286
|
128,341
|
School
·
School student
|
4,480
|
6,620
|
4,519
|
4,704
|
6,951
|
4,745
|
Industrial
·
J1 Manufacturing
|
5,601
|
5,734
|
1,335
|
5,881
|
6,021
|
1,402
|
Total
|
252,181
|
369,587
|
247,678
|
264,788
|
388,065
|
260,062
|
Notes:
(1) The breakdowns of the flow projections for the sewage catchments of KTIPS,
KTPTW and
TWKPTW,
excluding KTD, are presented in Appendix 16.2B-1.
Cruise Terminal
16.5.4
Table 16.16 shows the
estimated sewage flows for two cruise vessel berthing scenarios and the sewage
discharge rates to the Kai Tak sewerage system. It is understood that
cruise vessels would normally stop in HK for a minimum of 8 hours. For
the worst berthing scenarios (Super Post-Panamax + Post-Panamax and two
Post-Panamax), it is assumed the sewage quantity would be pumped to the Kai Tak
sewerage system in a shortest duration of 8 hours in order to avoid overly
design the Kai Tak sewerage system.
Table
16.16 Estimated Sewage Flows for Cruise Vessel Discharge
|
Cruise Vessel Berthing Scenarios
|
Parameters
|
Super Post-Panamax + Post-Panamax
|
Two Post-Panamax
|
|
Super
Post-Panamax
|
Post-Panamax
|
Total
|
Post-Panamax 1
|
Post-Panamax 2
|
Total
|
Sewage Generation
|
|
|
|
|
|
|
- Blackwater (m3/day)
|
141
|
105
|
245
|
105
|
105
|
209
|
- Greywater (m3/day)
|
1,547
|
1,150
|
2,696
|
1,150
|
1,150
|
2,299
|
- Total (m3/day)
|
1,687
|
1,254
|
2,941
|
1,254
|
1,254
|
2,508
|
Discharge to KT Sewerage System
|
|
|
|
|
|
|
- One day
quantity (m3)
|
1,687
|
1,254
|
2,941
|
1,254
|
1,254
|
2,508
|
- Discharge
rate in 8 hours (l/s)
|
59
|
44
|
103
|
44
|
44
|
88
|
16.5.5
It should be noted that the phase 1 berth will be
commissioned in year 2012 and the phase 2 berth will be scheduled for
commissioning after 2015. For the worst case scenario, daily sewage flow
discharged from cruise vessels is estimated to be 2,941m3/day for
Year 2016 and beyond.
16.5.6
Additional sewage flow generated from one cruise vessel
passengers in the cruise terminal buildings after berthing is assumed to be 30%
of the sewage flow generated from the cruise terminal buildings. Average
flow generated from two cruise vessel passengers at the cruise terminal
buildings is estimated to be 2,016m3/day for Year 2016 and
beyond. According to Appendix 16.2A-3
showing the projected flows for sub-planning area, the cruise terminal
buildings belong to Area 4D and the daily sewage flows (ADWF) is
2,607.9+735+17.5 m3/d (i.e. 3,360.4 m3/d). Hence,
the sewage flows of the landed passengers at cruise terminal buildings for
vessel 1 and 2 are 2 x 3,360 x 30% = 2,016 m3/d.
Jordan Valley Box Culvert
16.5.7
A sewage pumping station was proposed by EPD under “IP
07-001 Study on the Control of Water pollution at Jordan Valley Box Culvert” at
Jordan Valley Box Culvert (JVBC) to alleviate the pollution problem at the Kai
Tak Approach Channel. The proposed works will be constructed under the
DSD project of “Control of Water Pollution at Jordan Valley Box Culvert –
Investigation, Design and Construction” in KTD area. The polluted dry
weather flow from JVBC will be intercepted to the sewage pumping station at
JVBC and then discharged to the existing sewer box culvert at Kai Fuk
Road. A preliminary analysis conducted in the feasibility study of “Control
of Water Pollution at Jordan Valley Box Culvert” reviewed that the capacity
of the existing downstream sewerage system would be adequate to deal with the
intercepted flow.
16.5.8
The discharge rate of the pumping station at JVBC is
0.5m3/s. For the projection of the peak flows at KTIPS and
KTPTW, an extra 0.5m3/s is suggested to be added to the estimated
PWWFs from KTD, Kwun Tong catchments, cruise ships and the terminal buildings.
Summary of Flow Projections
16.5.9
Tables 16.17, 16.18 and 16.19 show the average dry weather flows, peaking factors and peak flows
respectively for KTIPS, KTPTW and TKWPTW for Year 2016, Year 2030 and Ultimate
Scenarios. The breakdown of the flow projections is presented in Appendices
16.2A-2 and 16.2B-1.
Table 16.17 Average Dry Weather Flows for Year 2016, Year 2030 and
Ultimate Scenarios
Facilities
|
Projected ADWF (m3/day)
|
Year 2016
|
Year 2030
|
Ultimate
|
Kwun Tong Intermediate Pumping Station
|
Kai Tak Development
|
17,565
|
31,543
|
31,543
|
Kwun Tong Catchments
|
242,167
|
252,181
|
264,788
|
Cruise Passenger at
Terminal Buildings(1)
|
2,016
|
2,016
|
2,016
|
Cruise Vessel
Discharge
|
2,941
|
2,941
|
2,941
|
TOTAL
|
264,689
|
288,681
|
301,288
|
Kwun Tong Preliminary Treatment Works
|
Kai Tak Development
|
17,565
|
31,543
|
31,543
|
Kwun Tong Catchments
|
342,365
|
369,587
|
388,065
|
Cruise Passenger at Terminal Buildings(1)
|
2,016
|
2,016
|
2,016
|
Cruise Vessel Discharge
|
2,941
|
2,941
|
2,941
|
TOTAL
|
364,887
|
406,087
|
424,565
|
To Kwa Wan Preliminary Treatment Works
|
Kai Tak Development
|
14,642
|
28,330
|
28,330
|
To Kwa Wan Catchments
|
223,578
|
247,678
|
260,062
|
TOTAL
|
238,220
|
276,008
|
288,392
|
Notes: (1) Sewage
flows generated from cruise passengers at terminal buildings are assumed to be
30% flow of Cruise Terminal Buildings for one berthing.
(2) The above
projected ADWF estimated for Kwun Tong Preliminary Treatment Works and Kwun
Tong Intermediate under all scenarios exclude the ADWF intercepted from JVBC
since the exact quantity of the intercepted flows will be subject to the design
under Agreement No.
CE13/2008(DS).
Table 16.18 Peaking Factors for KTIPS, KTPTW and TKWPTW
|
Peaking Factors
|
Year 2016
|
Year 2030
|
Ultimate
|
KTIPS
|
2.49
|
2.48
|
2.47
|
KTPTW
|
2.44
|
2.42
|
2.42
|
TKWPTW
|
2.51
|
2.49
|
2.48
|
Notes: (1)
Peaking factors (PF) are calculated from EPD’s guideline for
population>50,000:
Max (3.9/N0.065, 2.4),
where
N is the contributing population in thousands
Contributing population = Calculated total average flow/0.27
Table
16.19 Projected Peak Flows for Year 2016 and Year 2030 Scenarios
Facilities
|
Projected
PWWF (m3/s)
|
Year
2016
|
Year
2030
|
Ultimate
|
Kwun
Tong Intermediate Pumping Station
|
Kai Tak Development
|
0.51
|
0.91
|
0.91
|
Kwun Tong Catchments
|
6.99
|
7.23
|
7.57
|
Cruise Passenger at Terminal
Buildings(1)
|
0.06
|
0.06
|
0.06
|
Cruise Vessel Discharge(2)
|
0.10
|
0.10
|
0.10
|
DWFI
from JVBC
|
0.50
|
0.50
|
0.50
|
TOTAL
|
8.15
|
8.80
|
9.14
|
Kwun
Tong Preliminary Treatment Works
|
Kai Tak
Development
|
0.50
|
0.89
|
0.89
|
Kwun
Tong Catchments
|
9.67
|
10.37
|
10.86
|
Cruise
Passenger at Terminal Buildings(1)
|
0.06
|
0.06
|
0.06
|
Cruise
Vessel Discharge(2)
|
0.10
|
0.10
|
0.10
|
DWFI
from JVBC
|
0.50
|
0.50
|
0.50
|
TOTAL
|
10.83
|
11.91
|
12.40
|
To
Kwa Wan Preliminary Treatment Works
|
Kai Tak
Development
|
0.43
|
0.82
|
0.81
|
To Kwa Wan Catchments
|
6.49
|
7.13
|
7.46
|
TOTAL
|
6.92
|
7.95
|
8.27
|
Notes: (1) Sewage flows generated from
cruise passengers at terminal buildings are assumed to be 30% flow of Cruise
Terminal Buildings for one berthing.
(2) Cruise vessels discharge to the Kai Tak
sewerage system is assumed to be pumped in a period of 8hours (Qvessel
(m3/s) = 2941/60/60/8)
(3) Projected peak flows are rounded to 2
decimal places.
16.6
Assessment of Impact to Existing and Planned
Sewerage System
16.6.1
The sewage generated from KTD will be diverted to the
existing To Kwa Wan and Kwun Tong Preliminary Treatment Works (PTW). The
proposed sewerage system for KTD is sub- divided into two parts. The
south-western part of KTD will be diverted to To Kwa Wan PTW while the
north-eastern part of KTD will be diverted to Kwun Tong PTW via the existing
trunk sewers along Prince Edward Road East, Wang Kwong Road, Kai Fuk Road and
Hoi Bun Road. The proposed schematic sewerage network of KTD is shown in Figure 16.5.
16.6.2
For assessment of the impacts on the existing and
planned sewerage system, sewage treatment and disposal facilities, three flow
scenarios (namely Year 2016, Year 2030 and Ultimate Scenarios) were evaluated
taken into consideration of the available planning data from Planning
Department. The Year 2016 Scenario is used to assess the potential impacts
arising from the Cruise Terminal on the existing and planned sewerage system,
sewage treatment and disposal facilities. The Year 2030 Scenario and the
Ultimate Scenario (Year 2030+5%) are used to assess the long-term impacts
arising from the whole KTD on the existing and planned sewerage system, sewage
treatment and disposal facilities.
16.6.3
The key components of the sewerage system in the study
area as listed below were assessed:-
·
Trunk sewers along Hoi Bun Road
·
Kwun Tong Intermediate Pumping Station (KTIPS)
·
Kwun Tong Preliminary Treatment Works (KTPTW)
·
To Kwa Wan Preliminary Treatment Works (TKWPTW)
·
Conveyance tunnels from KTPTW to Stonecutters Island
STW
Trunk
Sewers along Hoi Bun Road
Existing
Condition
16.6.4
The sewerage along Wang Kwong Road and Hoi Bun Road are
the trunk sewers of Kwun Tong Preliminary Treatment Works (KTPTW) catchment,
which convey the sewage flows from upstream catchment to Kwun Tong Intermediate
Pumping Station (KTIPS) then to KTPTW.
16.6.5
The sewage generated from the developments and the
Cruise Terminal will be conveyed to the existing trunk sewers along Wang Kwong
Road and Hoi Bun Road.
16.6.6
The location of this existing trunk sewers is indicated
in Figure 16.10.
The dimensions of the trunk sewers are listed in the following table (Table
16.20).
Table
16.20 Dimensions of the Trunk Sewers along Hoi
Bun Road
Section
|
Dimensions (mm)
|
A-B
|
1800 – 2500 x 2300 BC
|
B-C
|
2500 x 2300 BC
|
C-D
|
2500 x 2300 BC
|
D-E
|
3000 x 2300 BC – 3000 x 2300 + 2000 x
2300 BC
|
Planned
Upgrading
16.6.7
There is no further upgrading works currently proposed for
the existing trunk sewers.
Future Flows
16.6.8
The projected sewage flows for Year 2016 and Ultimate
Scenarios will be used to access the capacity of the trunk sewers.
16.6.9
The sewage generated from three catchments inside KTD
would be conveyed to the trunk sewers at three points. The sewage from
five existing sewage catchments of KTPTW would be conveyed to the trunk
sewer. The breakdown of the flow projections is presented in Appendix 16.2A-1 and Appendix 16.2B-2.
16.6.10 The connection points to the trunk sewers and their corresponding
sewage flows to be discharged are shown in Figure 16.6 and
Figure 16.7.
Sewage Flow
Survey
16.6.11 In order to verify the projected sewage flows on the trunk sewer and
conduct the calibration of the sewage hydraulic model, a flow survey on
sewerage system was carried out between June and August 2007 for about 90 days
during wet season.
16.6.12 Based on the survey data, the average dry weather flows were revised
to fit the measured dry weather flows.
16.6.13 The ADWF with surveyed flow data for Year 2016 and Ultimate
Scenarios are presented in Figure 16.8 and Figure 16.9.
In general, the value of the measured ADWF was less than the predicted
ADWF. As a conservative approach, the predicted sewage flows projected
under Para 16.5 with calibrated hydraulic model would be used for
hydraulic analysis.
Capacity Evaluation
16.6.14 The InfoWorks model obtained from EPD was used for the hydraulic
analysis exercise. Since the hydraulic analysis will only focus on the trunk
sewer along Hoi Bun Road instead of the whole sewerage networks in KTPTW catchments,
we have simplified the hydraulic model obtained from EPD by inputting the
sewage flows into 8 discharge points along the trunk sewer. The peak
sewage flows were calculated based on the latest planning data from Planning
Department and the latest development schedule of KTD. The hydraulic
model for the trunk sewer was run to assess the hydraulic performance of the
trunk sewer under the Year 2016 and Ultimate flow conditions. It is
considered that this approach is sufficient for the assessment of the trunk
sewer. The assessment results for Year 2016 and Ultimate Scenarios are
indicated in Figure
16.10 and Figure
16.11.
16.6.15
The hydraulic modeling networks and results of the
simplified models for assessment of the hydraulic performance of the trunk
sewers along Hoi Bun road are provided in the Appendix 16.3.
Summary
16.6.16 Based on the latest flow projections with implementation of the flow
survey data for model calibration, the capacity of the existing trunk sewer
along Hoi Bun Road will be sufficient to cater for the projected flows in Year
2016 and Ultimate scenarios.
Kwun Tong
Intermediate Sewage Pumping Station
Existing
Facilities and Flows
16.6.17
Kung Tong Intermediate Pumping Station (KTIPS) is
located at Wai Yi Street, northwest to the existing KTPTW. It is required
to lift the flow from Kwun Tung and Kai Tak catchments and deliver it to the
KTPTW. The design capacity of the KTIPS is of 9.2m3/s.
Its existing facilities comprise five screw-type inlet lifting pumps, four duty
and one standby (see Table 16.21).
Table 16.21 Existing Facilities of KTIPS
Key Equipments
|
No.
of Units
|
Capacity
of Duty Units (m3/s)
|
Duty
|
Standby
|
Screw Inlet Pumps
|
4
|
1
|
9.2
|
Planned
Upgrading
16.6.18 There is no further upgrading works currently proposed for the
KTIPS.
Future Flows
16.6.19
With reference to the latest projected flows in Para.
16.5.9, the projected peak wet weather flow of KTIPS including flows from
DWFI at JVBC will be of 8.15m3/s, 8.80m3/s and 9.14m3/s
for Year 2016, Year 2030 and Ultimate Scenarios respectively. (See Table
16.22).
Table 16.22 Projected Flows of KTIPS
Sewage
Flows
|
Year
2016
|
Year
2030
|
Ultimate
|
PWWF (m3/s)
|
8.15
|
8.80
|
9.14
|
ADWF (m3/day)
|
264,689
|
288,681
|
301,288
|
Capacity Evaluation
16.6.20 Based on the assessment results, it was found that the existing
capacity of KTIPS should be able to handle the additional flows from KTD under
Year 2016, Year 2030 and Ultimate Scenarios. The capacity assessment of
existing sewage treatment and disposal facilities for Year 2016 Scenario, Year
2030 Scenario and Ultimate Scenario is shown in Figure 16.12, Figure 16.13 and Figure 16.14.
Summary
16.6.21 Based on the latest flow projection, the existing capacity of KTIPS
will be sufficient to handle the increased flow for Year 2016, Year 2030 and
Ultimate Scenarios. No plant upgrade is required.
Kwun Tong
Preliminary Treatment Works
Existing
Facilities and Flow Capacity
16.6.22 Kwun Tong Preliminary Treatment Works (KTPTW) is located at Wai Yip
Road, south east to the existing KTIPS. The designed capacity of KTPTW is
10.93 m3/s.
16.6.23 The existing facilities of the KTPTW comprise four 150mm spacing
hand raked coarse screen, six screw-type inlet pumps, four mechanically raked
fine screens with 6mm screen spacing and four detritors. The capacities
of existing treatment units of KTPTW are shown in Table 16.23.
Table 16.23 Existing Facilities of KTPTW
Key
Equipments
|
No.
of Units
|
Capacity
of Duty Units (m3/s)
|
Duty
|
Standby
|
Hand raked coarse screen
(150mm spacing)
|
3
|
1
|
11.8
|
Screw inlet pump
|
5
|
1
|
11.8
|
Mechanical raked fine screen
(6mm spacing)
|
3
|
1
|
11.8
|
Detritor
|
4
|
0
|
10.93
|
Planned
Upgrading
16.6.24 Hydraulic adequacy of the existing KTPTW was reviewed in the Review
of Central and East Kowloon Sewerage Master Plans (RCEKSMP) and the Kai Tak
Planning Review (TR4E) in 2003 and 2006, respectively.
16.6.25 Based on the RCEKSMP, the current treatment capacity of KTPTW
(10.93m3/s) would be adequate for the expected 2006 and 2011 flows,
but not for flows from the 2016 scenario and beyond (see Table 16.24).
Table
16.24 Projected Flows of KTPTW under
RCESMP (2003)
Scenario
|
Design
Capacity
|
Year
|
2006
|
2011
|
2016
|
Ultimate
|
PWWF (m3/s)
Excess Flow to PTW (m3/s)
|
10.93
--
|
9.94
N/A
|
10.82
N/A
|
11.86
0.93
|
13.10
2.17
|
Notes: (1) PTW peak flows are based on the peaking factors
from the DSD Sewerage Manual.
16.6.26 With reference to the prediction from the RCEKSMP, the estimated
sewage flows were further reviewed in the TR4E. The projected flows under
the ultimate flow scenario with and without development of Kai Tak Development
(KTD) are shown in Table 16.25. Capacity shortfall in KTPTW was
still found under the TR4E based on the proposed population of 86,000 under the
revised PODP.
Table
16.25 Projected Flows of KTPTW under TR4E
(2006)
Scenario
|
Design Capcacity
|
Ult. Sewage Flow w/o Dev. in KTD
|
Ult. Sewage Flow w Dev. in KTD
|
PWWF (m3/s)
|
10.93
|
11.94
|
12.66
|
16.6.27
The following mitigation measures were proposed in the
RCEKSMP and the TR4E:
· Balancing
tanks at KTPTW or the upstream pumping stations of KTD; and
·
Telemetry system and variable speed drives in the
upstream pumping stations of KTD to control the pumped flow to the KTPTW.
16.6.28 Under the OZP, an area of approximately 15,000m2 (1.5ha)
to the south-east of the existing KTPTW, on the southern side of Kwun Tong
Nullah, has been allocated for the expansion of KTPTW.
16.6.29 EPD will study the need, scopes and programme for upgrading the
existing KTPTW. The upgrading plan of the KTPTW would subject to EPD’s
future study findings.
Future Flows
16.6.30 With reference to the latest flow projection conducted under this
Study (see Para. 16.5.9), the projected flows for KTPTW will be of
10.83m3/s, 11.91m3/s and 12.40m3/s for Year
2016, Year 2030 and Ultimate Scenarios. (See Table 16.26)
Table 16.26 Projected Flows of KTPTW
Sewage
Flows
|
Year
2016
|
Year
2030
|
Ultimate
|
PWWF (m3/s)
|
10.83
|
11.91
|
12.40
|
ADWF (m3/day)
|
346,887
|
406,087
|
424,565
|
Capacity
Evaluation
16.6.31
The existing capacity of KTPTW is 10.93m3/s,
which should be sufficient to handle the flows for Year 2016 (10.83m3/s)
Scenario. For the
long-term impact, Year 2030 and Ultimate Scenarios are used and the assessment
results show that the capacity of KTPTW would be exceeded only because of the
potential population increase in KTPTW catchments in 2030 and beyond. It
is understood that the project of investigation for the upgrading of KTPTW as
mentioned in Para. 16.6.29 will commence in June/July 2008 and will last
for about 17 months. The planned upgrading plant of KTPTW would consider
the long term projected flows for KTD such as Year 2030 and Ultimate Scenarios.
The details of the upgrading of KTPTW will be determined under this EPD’s
project. The capacity assessment of existing
sewage treatment and disposal facilities can be referred to Figure 16.12, Figure 16.13 and Figure 16.14.
16.6.32 In addition, capacities of individual facilities on a unit process
basis are assessed to identify if any inadequate areas would be encountered in
the KTPTW operation. The existing capacities of the coarse screening,
inlet pumping and fine screening systems are of 11.80m3/s, which is
adequate to handle the projected flows for Year 2016 scenario only. For
Year 2030 and Ultimate Scenarios, standby unit shall be utilized to handle the increased
flows but no standby unit is available to secure stable operation in case of
maintenance or breakdown. The need of an additional equipment of the
coarse screening, inlet pumping and fine screening systems should be reviewed
to secure operation reliability in the coming EPD’s Study.
16.6.33 The design capacity of detritor is of 10.93m3/s when all
four units are in operation. No standby unit is available during the peak
flow period. According to the latest flow projection in Para. 16.6.30, the
design capacity of the detritor system is insufficient to cater for the
projected peak flow for Year 2030 and Ultimate Scenarios of 11.91m3/s
and 12.40m3/s respectively. The upgrading details of detritor
system should be reviewed in the coming consultancy by EPD’s Study.
Summary
16.6.34
Based on the findings of RCEKSMP conducted in 2003 and
the TR4E conducted in 2006, the flow capacity of KTPTW was identified to be
insufficient to accommodate the additional sewage flows from KTD under the
ultimate development scenario. An area of approximately 15,000m2
(15ha) to the south-east of existing KTPTW has been allocated for future
expansion.
16.6.35 The flow projections have been reviewed under this Study based on
the latest planning data from Planning Department, and the latest development
schedule of KTD. The peak wet weather flow for ultimate scenario will be
reduced to 12.40m3/s. The existing capacity of KTPTW will be
adequate to handle the additional sewage from KTD for Scenario Year 2016 only.
For Year 2030 and Ultimate Scenarios, the sewage flows would exceed the
existing capacity of KTPTW. The planned upgrading plant of KTPTW would consider the long term
projected flows for KTD such as Year 2030 and Ultimate Scenarios. The details
of the upgrading of KTPTW will be determined under the project of “the
upgrading of Kwun Tong Sewage Preliminary Treatment Works” by EPD.
To Kwa Wan
Preliminary Treatment Works
Existing
Facilities and Flow Capacity
16.6.36
To Kwa Wan Preliminary Treatment Works (TKWPTW) is
located at Sung Ping Street. The design capacity of TKWPTW is 9.32m3/s.
16.6.37
The existing facilities of the TKWPTW comprise three
150mm spacing hand raked coarse screen, eight screw-type inlet pumps, five
mechanically raked fine screens with 6mm screen spacing and four
detritors. The capacities of existing treatment units of KTPTW are shown
in Table 16.27.
Table 16.27 Existing Facilities of TKWPTW
Key
Equipments
|
No.
of Units
|
Capacity
of Duty Units (m3/s)
|
Duty
|
Standby
|
Hand raked coarse screen
(150mm spacing)
|
2
|
1
|
9.32
|
Screw inlet pump
|
7
|
1
|
9.32
|
Mechanical raked fine screen
(6mm spacing)
|
4
|
1
|
9.32
|
Detritor
|
4
|
0
|
10.64
|
Planned Upgrading
16.6.38 Based on the RCEKSMP, the current treatment capacity of TKWPTW
(9.32m3/s) would have adequate capacity for the expected flows,
except in the ultimate development scenario (see Table 16.28). An
area of approximately 4,000m2 (0.4ha) adjacent to TKWPTW (to the
north) is allocated for extension of the PTW.
Table
16.28 Projected Flows to TKWPTW under RCESMP (2003)
Scenario
|
Design
Capacity
|
Year
|
2006
|
2011
|
2016
|
Ultimate
|
Peak Flow to PTW (m3/s)
Excess Flow to PTW (m3/s)
|
9.32
--
|
8.83
N/A
|
8.47
N/A
|
8.99
N/A
|
10.00
0.68
|
Notes: (1) PTW peak flows are
based on the peaking factors from the DSD Sewerage Manual.
16.6.39 Under the TR4E, the capacity of TKWPTW was further reviewed based on
the latest population data and revised PODP for KTD (see Table 16.29).
The TR4E concluded in 2006 that TKWPTW would have adequate treatment capacity
to handle the sewage flow from the study area.
Table
16.29 Projected Flows to TKWPTW under TR4E (2006)
Scenario
|
Design Capacity
|
Ult. Sewage Flow w/o Dev. in KTD
|
Ult. Sewage Flow w Dev. in KTD
|
Peak Flow (m3/s)
|
9.32
|
7.71
|
8.27
|
Future Flows
16.6.40 With reference to the latest flow projection conducted in Para
16.5.9, the projected flows of TKWPTW have further reduced and the peak wet
weather flow to TKWPTW will be of 6.92m3/s, 7.95m3/s and
8.27m3/s for year 2016, year 2030 and Ultimate Scenarios, respectively.
(See Table 16.30)
Table
16.30 Projected Flows for TKWPTW
Sewage
Flows
|
Year
2016
|
Year
2030
|
Ultimate
|
PWWF (m3/s)
|
6.92
|
7.95
|
8.27
|
ADWF (m3/day)
|
238,220
|
276,008
|
288,392
|
Capacity
Evaluation
16.6.41 The existing capacity of TKWPTW is 9.32m3/s, which should
be sufficient to handle the flows for Year 2016 (6.92m3/s), Year
2030 (7.95m3/s) and Ultimate (8.27m3/s) Scenarios.
The capacity assessment of existing sewage treatment and disposal facilities
can be referred to Figure
16.12, Figure 16.13
and Figure 16.14.
16.6.42 In addition, capacities of individual facilities on a unit process
basis are assessed to identify if any inadequate areas would be encountered in
the TKWPTW operation. The existing capacities of the coarse screening,
inlet pumping and fine screening systems are of 9.32m3/s, which is
adequate to handle the projected flows up to Year 2030 or Ultimate
Scenarios. Standby unit is also available to secure a stable operation in
case of maintenance or break-up.
16.6.43 The design capacity of detritor is of 10.64m3/s when all
four units are in operation. Although the design capacity of the detritor
unit is sufficient to cater for the projected peak flow for ultimate scenario
of 8.27m3/s, no standby unit is available during the peak
period. There is no standby unit in the original design but an
improvement option for provision of a standby unit would be beneficial to the
system for maintenance or emergency reason. The existing TKWPTW
should be able to handle the additional sewage flow from KTD.
Summary
16.6.44 Based on the RCEKSMP, the flow capacity of TKWPTW was identified to
be insufficient to accommodate the additional sewage flows from KTD under
ultimate development scenario. An area of approximately 4,000m2
(0.4ha) adjacent to the PTW was allocated for future extension. The
estimated flows were reviewed in the TR4E, the estimated flows were reduced
because of the smaller projected population in KTD under PODP, and the existing
capacity (9.32m3/s) of TKWPTW would be adequate for the peak flow
condition in ultimate scenario.
16.6.45
The flow projection is further reviewed under this
Study with the latest population data. The projected peak flows of
Ultimate Scenario is of 8.27m3/s, which is smaller than the current
capacity of TKWPTW. The existing TKWPTW should be able to handle the
additional sewage from KTD.
Conveyance
Tunnel
Existing
Facilities and Flows
16.6.46 Three sections of Conveyance Tunnels are assessed. The
schematic alignment is shown in the following Diagram 1.
Diagram 1 – Schematic Diagram of Conveyance System
16.6.47 Based on the design memorandum of Harbour Area Treatment Scheme
(HATS) Stage 1 (formerly Strategic Sewage Disposal Scheme (SSDS) Stage 1), the
deep tunnels were not designed to take into account of the unusual high, and
relatively infrequent, wet weather flows. Instead, a peaking factor was
selected to ensure that all normal dry weather diurnal variations applying to
average wet season flows (July – August) would be transferred into the tunnels.
A peaking factor of 2.0 for the large sewage catchments including KTPTW and
TKWPTW catchments was adopted for the design of the conveyance tunnels.
16.6.48 Table 16.31 shows the design capacity of
the conveyance tunnels.
Table
16.31 Design Capacities of the Conveyance Tunnels
Conveyance
Tunnel
|
Design
Capacity (m3/s)
|
1
|
KTPTW "
KTPTW Drop Shaft
|
7.70
|
2
|
KTPTW
Drop Shaft " TKWPTW Drop Shaft
|
14.81
|
3
|
TKWPTW "
TKWPTW Drop Shaft
|
6.99
|
4
|
TKWPTW
Drop Shaft " SCISTW
|
21.80
|
16.6.49 During the design stage of the tunnels, the estimated PWWF at
ultimate stage was larger than the design capacity of the tunnels. Hence, an
overflow situation was anticipated and allowed in the original design.
Relevant PWWFs are listed in Table 16.32 below.
Table
16.32 PWWFs at Ultimate Stage for the Design of Conveyance Tunnels
|
Conveyance
Tunnel
|
PWWF
(m3/s)
|
1
|
KTPTW " KTPTW Drop
Shaft
|
10.93
|
2
|
KTPTW Drop Shaft "
TKWPTW Drop Shaft
|
12.15
|
3
|
TKWPTW " TKWPTW Drop
Shaft
|
9.32
|
4
|
TKWPTW Drop Shaft "
SCISTW
|
17.64
|
Planned
Upgrading
16.6.50 Currently, there are no planned upgrading works for the existing
conveyance tunnels.
Future Flows
16.6.51 Table 16.33 shows the projected peak
flows of KTPTW and TKWPTW. The sewage flows from KTPTW and TKWPTW to the
conveyance tunnels would be limited by the tunnel capacities.
Table
16.33 Projected Peak Wet Weather Flows to KTPTW and TKWPTW
PTW
|
Year
2016 Scenario
(m3/s)
|
Year
2030
Scenario
(m3/s)
|
Ultimate
Scenario
(m3/s)
|
KTPTW
|
10.83
|
11.91
|
12.40
|
TKWPTW
|
6.92
|
7.95
|
8.27
|
Capacity
Evaluation
16.6.52 A Working Paper No. 5 – Flows, Loads and Stage 1 System Capacity
Constraints Analysis (Final) issued July 2005 under the project of “Environmental
and Engineering Feasibility Assessment Studies in Relation to the Way Forward
of the Harbour Area Treatment Scheme” (EEFS) evaluated the capacity
constraint, if any, in the existing HATS Stage I system. The Working
Paper No. 5 conducted the analysis of the overflows on the water quality
condition. The finding showed that the total volume of overflow was small
compared to the total annual volume of sewage and the overflow was
insignificant.
16.6.53 The Working Paper No. 5 concluded that there is no capacity
constraint with respect to the HATS Stage I system. Compared with the
population data using in the KTD project, the higher population set was adopted
in the Working Paper No. 5 under EEFS. Hence, based on EEFS’s argument,
it is concluded that the capacity of the HATS conveyance tunnels should be able
to handle the additional sewage flow from KTD.
16.6.54 The sewage flows from KTPTW and TKWPTW to the conveyance tunnels
would be limited by the tunnel capacities. The overflows from KTPTW and
TKWPTW are anticipated and unavoidable during wet peak wet weather flows.
The estimated overflows based on the latest flow projections are shown in Table
16.34 below:
Table
16.34 Comparison of Estimated Overflow
Conveyance
Tunnel
|
Estimated
Overflow (m3/s)
|
|
2016
Scenario
|
1
|
KTPTW
to KTPTW Drop Shaft
|
3.13
|
2
|
TKWPTW
to TKWPTW Drop Shaft
|
0
|
|
2030
Scenario
|
1
|
KTPTW
to KTPTW Drop Shaft
|
4.21
|
2
|
TKWPTW
to TKWPTW Drop Shaft
|
0.96
|
|
Ultimate
Scenario
|
1
|
KTPTW
to KTPTW Drop Shaft
|
4.70
|
2
|
TKWPTW
to TKWPTW Drop Shaft
|
1.28
|
16.6.55 The results are also indicated in Figure 16.12, Figure 16.13 and Figure 16.14 for
Year 2016, Year 2030 and Ultimate Scenarios.
Summary
16.6.56 The sewage flows from KTPTW and TKWPTW to the conveyance tunnels
would be limited by the tunnel capacities. The deep tunnels were not
designed to take account of the unusual high, and relatively infrequent, wet
weather flows. A peaking factor of 2.0 for the large sewage catchments
including KTPTW and TKWPTW catchments was adopted for tunnel design.
Overflows from KTPTW and TKWPTW are anticipated during peak wet weather flows
for year 2016, 2030 and ultimate scenarios. However, the capacity of the
HATS conveyance tunnels should be able to handle the additional sewage flow
from KTD.
16.7
Proposed Sewerage
System inside KTD
16.7.1
Based on the population and employment data from the
development schedule of KTD, a new sewerage system is designed forming a
sewerage master layout plan for KTD.
16.7.2
To cope with the phasing development of KTD, the
proposed sewerage system will be implemented under 2 schemes, namely Interim
Scheme and Ultimate Scheme. The Interim Scheme is designed for the sewage flows
from the Cruise Terminal, Advance Works developments and the early developments
in North Apron areas including the Public Rental Housing (PRH) Sites and Kai
Tak Government Offices (KTGO) for intake by 2012, whereas the Ultimate Scheme
is designed to cater for all the developments in KTD at ultimate stage.
16.7.3 Figures 16.16 and 16.26
show the Interim Scheme and Ultimate Scheme of the proposed sewerage
network inside KTD respectively.
16.7.4
As stated in the previous sections, the sewage
generated in KTD will be diverted to KTPTW and TKWPTW. The flows
generated from sewerage catchments A, B, C, D and K will be conveyed to TKWPTW
whereas the flows generated from sewerage catchment E, F, G, H, I, J and L will
be conveyed to KTPTW.
Interim
Scheme
16.7.5
Interim Scheme is proposed for cruise terminal
developments near the tip of the ex-runway, and PRH and KTGO in North Apron.
The assessment of the sewerage impacts due to the above developments at early
phase was conducted in the previous section using the latest planning data from
the Planning Department and the latest development schedule of KTD under Year
2016 Scenario. No adverse impacts were identified.
16.7.6
The proposed sewerage systems for the Interim Scheme
are designed in accordance with the methodology stated in Para. 16.4 for
the new sewers inside KTD.
16.7.7
The proposed sewerage networks under the Interim Scheme
are presented in Figures 16.16 to
16.25.
Cruise
Terminal
16.7.8
Gravity sewer is proposed to be laid along Road L14 and
Road D3 to convey the flows from the residential development, commercial
development and the cruise terminal to Pumping Station PS6.
16.7.9
The PS6 lifts the sewage from a lower level to a higher
level at Cheung Yip Street. The proposed gravity sewer at Cheung Yip Street
would be connected to the existing trunk sewer at the junction of Hoi Bun Road
and Cheung Yip Street.
Public Rental
Housing
16.7.10 In view that the Pumping Station PS1A may not be able to commission
at the time of occupation of the PRH development in 2012, the sewage collected
from Site 1A (1A-1, 1A-2, 1A-3 and 1A-4) and Site 1B (1B-1 and 1B-4) is
proposed to be conveyed by gravity sewer directly to the existing manhole
immediately upstream of the existing inverted siphon at Eastern Road
temporarily before PS1A is in place where the sewage would be ultimately
conveyed to the existing trunk box culvert along Wang Kwong Road. The
internal sewer system of the two PRH sites would be gravitated towards the
Junction of Eastern Road/Road L2/Road L3 leading to the inverted siphon at
Eastern Road. The sizes of the sewers serving for Site 1A (1A-1, 1A-2, 1A-3 and
1A-4) and Site 1B (1B-1 and 1B-4) vary from 300mm to 675mm in diameter.
KTGO
16.7.11 As discussed with DSD/SP for the interfacing project “Agreement
No. CE 4/2007, Sewage Interception Scheme in Kowloon City – Investigation”,
the deletion of PS4 was concluded and only PS1 and PS3 are required to be
constructed. DSD/SP mentioned that the project (Agreement No. CE 4/2007) only
caters for sewage flows from the hinterland of Kowloon City. A short
section of sewer is proposed to be constructed along the realigned Concorde
Road on the southern side of KTGO to Pumping Station PS1 to be constructed by
DSD for commissioning in 2012, subject to the approval of CEDD’s Schedule 3 EIA
Study and their funding arrangement which could meet the project programme of
PWP Item No. 4357DS. The small amount of flow from the KTD catchment
(i.e. Sewage from Catchment A of KTD and the ADWF amount is about 0.089m3/s)
is allowed to discharge to PS1 and then to PS3, but it is envisaged that
structural upgrading pumping station of the pumping stations is not required.
In this case, no sewerage impact to the existing system will be induced
by KTGO.
16.7.12 In case the pumping stations PS1 and PS3 could not be completed by
2012, the fallback option will be to temporarily discharge the sewage generated
from the KTGO directly to the existing sewerage system. According to Appendix 16.2C, the
ADWF of the KTGO (Site 1D-4) is about 875 m3/d and the peak flow is
about 6x875m3/d=0.06 m3/s with peaking factor of
6. The capacity of the 900mm diameter existing sewer to be discharged is
about 1.45m3/s and the discharge flows occupy about 4.1% of existing
pipe capacity (Note: Pipe gradient= 1 in 150). The sewage discharge from KTGO
is insignificant compared to the capacity of the existing sewer for the
fallback option.
Ultimate
Scheme
16.7.13 The Ultimate Scheme is designed to serve the whole KTD. The
assessment of the impacts due to the whole KTD was conducted in the previous
section using the latest planning data from Planning Department and the latest
development schedule of KTD under Ultimate Scenario. No adverse impacts were
identified.
16.7.14 The proposed sewerage systems for the Ultimate Scheme are designed
in accordance with the methodology stated in Section. 16.4 for the new sewers
inside KTD.
16.7.15 The proposed sewerage networks in ultimate scenarios are presented
in Figures
16.26 to 16.39.
Sewerage
System for Flows generated from KTD Sewerage catchments to KTPTW
16.7.16 Further to the sewers constructed for PRH under Interim Scheme,
gravity sewer extension for catchment L and G are proposed for the north apron
area. The flows will be intercepted by Pumping Station PS1A and then
conveyed by rising mains to the existing trunk sewer as mentioned in Para
16.6.5.
16.7.17 The gravity sewer system for Catchment F proposed for ex-runway area
will be collected by Pumping Station PS6 and transferred to the gravity sewers
at Cheung Yip Street, which intercepts the gravity system for Catchment H and
eventually discharges to the existing box culvert at Hoi Bun Road.
16.7.18 For catchment E, an independent sewerage system is proposed to
convey the flows directly to the existing trunk sewer. For catchment I,
all are the existing developments and hence no sewerage impact was
identified. For catchment J, there is only 1 new tunnel administration
building at Site Area 6B-3 (ADWF=3.5m3/d and the peak flow is
about 8x3.5m3/d=0.324 L/s) and the generated sewage flows are
insignificant, and only 0.1% increase of the capacity of the existing 675mm
diameter sewer (Note: Pipe gradient = 1 in 900 and pipe capacity = 0.3m3/s).
16.7.19 A pumping station (JVBC-PS) proposed by DSD/CM at Jordan Valley Box
Culvert to intercept the dry weather flow and discharged to the existing trunk
sewer box culvert at Kai Fuk Road.
Sewerage
System for Flows generated from KTD Sewerage catchments to TKWPTW
16.7.20 The assessment of the sewerage impact to the existing TKWPTW due to
the sewage flows generated in KTD was conducted (i.e. the assessment for
TKWPTW) in previous section using the planning data from Planning Department
and the latest development schedule of KTD under ultimate Scenario. No
adverse impacts were identified.
16.7.21 Within the sewerage sub-catchments of KTWPTW, there are 2 pumping
stations (PS1 and PS3) which were recommended to be funded by EPD for
construction by DSD to cater for sewage flow from the hinterland as well as to
allow future expansion to cope with the flow generated within KTD. After review
of various possible options in consideration of the interface issues due to
cost and implementation programme, a proposed scheme (integrated with PS1 and
PS3) agreed with relevant offices of DSD and EPD was developed. The
proposed scheme would collect sewage from Catchment A of KTD into PS1 and then
to PS3 and the ADWF amount from Catchment A of KTD is about 0.089m3/s
for intake of year 2021 and beyond. The schematic arrangement of this
scheme is presented in Figure 16.15.
Based on the proposed scheme, there are two scenarios on the arrangement of PS1
and PS3 in below: Both scenarios will deal with the sewage from the
Catchment A of KTD and would not cause any sewerage impact.
·
Scenario 1 – construct the two pumping stations (PS1
and PS3) in one go under PWP Item No. 4357DS by DSD to cater for the sewage
flows from both hinterland (ADWF: 0.79m3/s to PS1) and Catchment A
of KTD (ADWF: 0.089m3/s) (i.e. the total flow is approximate 117% of
the hinterland flow). This is DSD/SP’s fallback option on EP application;
and
·
Scenario 2 – construct the two pumping stations (PS1 and
PS3) under PWP Item No. 4357DS by DSD to cater for the sewage flows from
hinterland only and then upgrade PS1 and PS3 by CEDD to cater for the sewage
flows from Catchment A of KTD (ADWF: ADWF: 0.089m3/s) (i.e. the
total flow is approximate 17% of the hinterland flow).
16.7.22 Under this scheme, a pumping station NPS is proposed to intercept
the sewage flows from pumping station PS2 intercepting the flows from
Catchments B and K, Catchment C and part of Catchment D as well as to serve as
a replacement DWFI at Sung Wang Toi Road.
Hydraulic
Modelling Networks and Results
16.7.23 The hydraulic modeling networks and results for the new sewerage
systems in KTD are provided in Appendix 16.4.
Flow Projection
16.8.1
Flow projection was conducted based on the latest
planning data from Planning Department and the latest implementation schedule
of KTD. Table 16.35 summarizes the projected average dry weather flows
(ADWF) for KTD. Table 16.36 summarizes the projected ADWF for Kwun
Tong Intermediate Pumping Station (KTIPS), Kwun Tong Preliminary Treatment
Works (KTPTW) and To Kwa Wan Preliminary Treatment Works (TKWPTW) catchments
excluding KTD. Table 16.37 summarizes the estimated sewage flow for
cruise vessels discharge.
Table 16.35 Estimated ADWF for Kai Tak Development
Category
|
Year
2016
(m3/day)
|
Year
2021
(m3/day)
|
Flow
to KTIPS and KTPTW
|
Flow
to TKWPTW
|
Flow
to KTIPS and KTPTW
|
Flow
to TKWPTW
|
Domestic
|
9,369
|
1,994
|
11,834
|
9,761
|
Commercial
|
7,985
|
6,817
|
19,487
|
12,706
|
School
|
211
|
105
|
211
|
137
|
Others (1)
|
-
|
5,727
|
-
|
5,727
|
TOTAL
|
17,565
|
14,642
|
31,543
|
28,330
|
Notes: (1) Included sewage flows for hand-washing at
toilets, showering and toilet flushing in Stadium. The sewage flows are
based on water demands and this approach has been agreed in the Kai Tak
Planning Review.
Table 16.36 Estimated ADWF for KTIPS, KTPTW and TKWPTW Catchments
Excluding KTD
Category
|
Year
2016 (m3/day)
|
KTIPS
|
KTPTW
|
TKWPTW
|
Domestic
|
125,873
|
202,878
|
102,704
|
Commercial
|
108,044
|
128,396
|
113,075
|
School
|
4,241
|
6,233
|
4,236
|
Industrial
|
4,009
|
4,858
|
3,563
|
TOTAL
|
242,167
|
342,365
|
223,578
|
Category
|
Year
2030 (m3/day)
|
KTIPS
|
KTPTW
|
TKWPTW
|
Domestic
|
138,784
|
229,339
|
119,594
|
Commercial
|
103,316
|
127,894
|
122,230
|
School
|
4,480
|
6,620
|
4,519
|
Industrial
|
5,601
|
5,734
|
1,335
|
TOTAL
|
252,181
|
369,587
|
247,678
|
Category
|
Ultimate
(m3/day)
|
KTIPS
|
KTPTW
|
TKWPTW
|
Domestic
|
145,722
|
240,807
|
125,574
|
Commercial
|
108,481
|
134,286
|
128,341
|
School
|
4,704
|
6,951
|
4,745
|
Industrial
|
5,881
|
6,021
|
1,402
|
TOTAL
|
264,788
|
388,065
|
260,062
|
Notes: (1) Catchment Inflow Factors
(PCIF) are included.
(2) Projected flows for
ultimate scenario are assumed to be the estimated flows for Year 2030
scenario plus an additional 5%.
(3) Uncertainty allowance is
included.
Table 16.37 Estimated Sewage Flows for Cruise Vessel Discharge
Category
|
Cruise
Vessel Berthing in HK
|
Super
Post-Panamax
|
Post-Panamax
|
Total
|
Sewage Quantity (m3/day)
|
1,687
|
1,254
|
2,941
|
Discharge to KT Sewerage System in 8
Hours (l/s)
|
59
|
44
|
103
|
Notes:
(1) Sewage flows
generated from cruise passengers at the cruise terminal buildings (30%
flow of the sewage flows generated from cruise
terminal buildings) are excluded.
Capacity Assessment
16.8.2
For assessment of the impacts on the existing and
planned sewerage system, sewage treatment and disposal facilities, three flow
scenarios are selected taken into consideration the available planning data
from Planning Department, namely Year 2016, Year 2030 and ultimate (Year 2030 +
5%). The Year 2016 Scenario is used to access the potential impacts
arising from the Cruise Terminal and the early development on the existing and
planned sewerage system, sewage treatment and disposal facilities. The Year
2030 and Ultimate Scenarios are used to assess the long term impacts arising
from the whole KTD on the existing and planned sewerage system, sewage
treatment and disposal facilities.
16.8.3
There are inherent uncertainties in the flow estimates
due to a number of as-yet unquantified factors. It is proposed to add an
extra 10% contingency to the calculated ADWFs and peak flows. It is
assumed that the 10%
contingency for the uncertainties will be materialised linearly from year 2006
until 2030 (i.e. +2% on Year 2010; +6% on Year 2020 and 10%
on Year 2030/Ultimate).
16.8.4
The projected flows including the Average Dry Weather
Flow (ADWF) and the Peak Wet Weather Flow (PWWF) for KTPTW, KTIPS and TKWPTW
are summarized in the following tables (Table 16.38 and 16.39)
Table
16.38 Projected ADWF for KTIPS, KTPTW and TKWPTW
Facilities
|
Projected
ADWF (m3/day)
|
Year
2016
|
Year
2030
|
Ultimate
|
KTIPS
|
264,689
|
288,681
|
301,288
|
KTPTW
|
346,887
|
406,087
|
424,565
|
TKWPTW
|
238,220
|
276,008
|
288,392
|
Table
16.39 - Projected PWWF for KTIPS, KTPTW and TKWPTW
Facilities
|
Projected
Peak Flows (m3/s)
|
Year
2016
|
Year
2030
|
Ultimate
|
KTIPS
|
8.15
|
8.80
|
9.14
|
KTPTW
|
10.83
|
11.91
|
12.40
|
TKWPTW
|
6.92
|
7.95
|
8.27
|
16.8.5
The sewage generated from KTD will be diverted to the existing
To Kwa Wan Preliminary Treatment Works (TKWPTW) and Kwun Tong Preliminary
Treatment Works (KTPTW).
16.8.6
Capacity assessment was conducted to access the
hydraulic capacities of the trunk sewers along Hoi Bun Road, KTIPS, KTPTW,
TKWPTW and the conveyance tunnels from KTPTW to Stonecutters Island STW
(SCISTW). The assessment results reveal that the existing trunk sewers
along Hoi Bun Road, KTIPS and TKWPTW should be able to handle the additional
sewage flows from KTD for Year 2016, Year 2030 and Ultimate Scenarios.
For KTPTW, the assessment results indicate that the projected flows would
exceed its capacity in Year 2030 and Ultimate Scenarios. The planned upgrading plant of KTPTW
by EPD would consider the long term projected flows for KTD such as Year 2030
and Ultimate Scenarios. The details of the upgrading of KTPTW will be
determined under the EPD project.
16.8.7
The design capacities and the projected PWWF of KTIPS,
KTPTW and TKWPTW are shown in Table 16.40.
Table 16.40 Design Capacities and Projected
PWWF of KTIPS and KTPTW
Facilities
|
Design Capacity
(m3/s)
|
Projected PWWF (m3/s)
|
Year 2016
|
Year 2030
|
Ultimate
|
KTIPS
|
9.20
|
8.15
|
8.80
|
9.14
|
KTPTW
|
10.93
|
10.83
|
11.91
|
12.40
|
TKWPTW
|
9.32
|
6.92
|
7.95
|
8.27
|
16.8.8
The deep tunnels were not designed to take account of
the unusual high, and relatively infrequent, wet weather flows. A peaking
factor of 2.0 for the large sewerage catchments including KTPTW and TKWPTW
catchments was adopted for the tunnel design. Overflow from KTPTW and TKWPTW
are anticipated during peak wet weather flows.
16.8.9
The sewage flow from KTPTW and TKWPTW to the conveyance
tunnels would be limited by the tunnel capacity. EEFS concluded that there is
no capacity constraint with respect to the HATS Stage I system. Based on
EEFS’s argument, it is concluded that the capacity of the HATS conveyance
tunnels should be able to handle the additional sewage flow from KTD.
16.8.10 As the assessment results show that the existing trunk sewers along
Hoi Bun Road, KTIPS and TKWPTW should be able to handle the additional sewage
flows from KTD for Year 2016, Year 2030 and Ultimate Scenarios, and that KTPTW
should be able to handle the additional sewage flows from KTD for Year 2016
Scenario. The planned upgrading of KTPTW should consider the long term
projected flows such as Year 2030 and Ultimate Scenarios. In addition,
the capacity of the HATS conveyance tunnels should be able to handle the
additional sewage flow from KTD. There would be no adverse sewerage
impacts to the existing and planned facilities. No mitigation measures
are required.
Proposed
Sewerage System for KTD
16.8.11 Based on the population and employment data from the latest
development schedule of KTD, new sewers are designed and the sewerage master
layout plan is formed. Interim and Ultimate Schemes are developed for the
KTD.
16.8.12 The proposed sewerage networks under the Interim Scheme are
presented in Figure
16.16 to 16.25. The proposed sewerage networks under the Ultimate
Scheme are presented in Figure 16.26 to
16.39.
16.8.13 The proposed pumping stations scheme (PS1 and PS3) for the TKWPTW
Catchment agreed with relevant offices of DSD and EPD was developed.
16.9
Reference
16.9.1
The Report has made reference to the following reports,
manuals and design guidelines:
·
Agreement No. CE 25/98 – Review of Central and East
Kowloon Sewerage Master Plans, Final Report.
·
Agreement No. CE4/2004(TP) - South East Kowloon
Development Comprehensive Planning and Engineering Review Stage 1: Planning
Review, Technical Report No. TR4E – Preliminary Drainage and Sewerage
Assessment.
·
Agreement No. CE43/2005(EP) – Harbour Area Treatment
Scheme (HATS) Stage 2A Environmental Impact Assessment Study – Investigation, Technical
Note – Flow and Load Projections (Parts 1 and 2).
·
Agreement No. CE 8/2006/DS - HATS 2A Upgrading of Stonecutter’s Island Sewage treatment Works and Preliminary
Treatment Works, Final Report on Flow & Load Projections.
·
Agreement No. CE 42/2001 – Environmental and
Engineering Feasibility Assessment Studies in Relation to the Way Forward of
the Harbour Area Treatment Scheme, Working Paper No. 5 – Flows, Loads and Stage
1 System Capacity Constraints Analysis (Final).
·
Agreement No. CE 4/2007 – Sewage Interception Scheme in
Kowloon City – Investigation, Final Adoptive Review Report.
·
IP 07-001 – Study on the Control of Water Pollution at
Jordan Valley Box Culvert, Final Information Review Report.
·
IP 07-001 – Study on the Control of Water Pollution at
Jordan Valley Box Culvert, Final Working Paper on Options and Evaluation.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development
Engineering Study cum Design and Construction of Advance Works – Investigation,
Design and Construction, Hydraulic Assessment on Trunk Sewer and Treatment
Facilities based on the Flow Survey Data.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development Engineering
Study cum Design and Construction of Advance Works – Investigation, Design and
Construction, Working Paper on Assessment of Existing and Planned Sewerage,
Sewage Treatment and Disposal Facilities.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development
Engineering Study cum Design and Construction of Advance Works – Investigation,
Design and Construction, Discussion Paper on Options for Sewage Conveyance
Systems at North Apron without Sewage Pumping Station.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development
Engineering Study cum Design and Construction of Advance Works – Investigation,
Design and Construction, Final Review Report.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development
Engineering Study cum Design and Construction of Advance Works – Investigation,
Design and Construction, Essential Infrastructure Serving the Kai Tak
Government Office and Public Rental Housing in North Apron.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development
Engineering Study cum Design and Construction of Advance Works – Investigation,
Design and Construction, Preliminary Design Report - Essential
Infrastructure Serving the Kai Tak Government Office and Public Rental Housing
in North Apron.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development
Engineering Study cum Design and Construction of Advance Works – Investigation,
Design and Construction, Final Preliminary Design Report for Advance Works.
·
Agreement No. CE 35/2006(CE) - Kai Tak Development
Engineering Study cum Design and Construction of Advance Works – Investigation,
Design and Construction, Final Focus Assessment Report for Advance Works.
·
Agreement No. CE42/2000 – South East Kowloon
Development Infrastructure at North Apron Area of Kai Tak Airport – Design and
Construction
·
Agreement No. CE32/99 – Comprehensive Feasibility Study
for the Revised Scheme of South East Kowloon Development
·
IP 06-074 – Kai Tak Approach Channel Expedient
Connection Survey
·
Sewerage Manual (Volume 1), issued by Drainage Services
Department
·
Sewerage Manual (Volume 2), issued by Drainage Services
Department
·
Technical Paper Report No.: EPD/TP 1/05 – Guidelines
for Estimating Sewage Flows for Sewage Infrastructure Planning Version 1.0,
issued by Environmental Protection Department
·
Guidelines for Sewer Network hydraulic Model Build and
Verification, issued by Infrastructure Planning Group of Environmental
Protection Department
·
Code of Practice for the Hydraulic Modelling of Sewer
Systems Version 3.001, issued by Wastewater Planning Users Group (WaPUG)
·
Tables for the Hydraulic Design of Pipes and Sewers,
issued by Hydraulics Research, Wallingford