Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Impact Assessment Report
Contents
17.......... Environmental
Monitoring and Audit Requirements. 17-1
17.1 Introduction. 17-1
17.2 Air Quality Impact 17-1
17.3 Noise Impact 17-2
17.4 Water Quality Impact 17-2
17.5 Waste Management Implications. 17-2
17.6 Land Contamination Impact 17-2
17.7 Impact on Culture Heritage. 17-2
17.8 Landscape and Visual Impact 17-2
17.9 Ecological Impact 17-2
17.10 Fisheries
Impact 17-2
17
Environmental
Monitoring and Audit Requirements
17.1
Introduction
17.1.1 This section elaborates the
requirements of EM&A for the Project, based on the assessment results of
various environmental issues.
17.1.2 The objectives of carrying out
EM&A for the Project include the following:
· to provide a database against which any environmental
impacts of the Project can be determined;
·
to provide an early
indication should any of the environmental control measures or practices fail
to achieve the acceptable standards;
·
to monitor the
performance of the Project and the effectiveness of mitigation measures;
·
to verify the
environmental impacts predicted in this EIA;
·
to determine project
compliance with regulatory requirements, standards and government policies;
·
to take remedial action
if unexpected problems or unacceptable impacts arise; and
· to provide data to enable an environmental
audit.
17.1.3 The EM&A reporting shall be
carried out in paper based plus electronic submission upon agreeing the format
with the ER and EPD. All the monitoring data (baseline and impact) shall
also be submitted in electronic format.
17.1.4 The following sections summarise the
recommended EM&A requirements. Details of EM&A are provided in
the EM&A Manual.
17.2
Air Quality Impact
17.2.1
The construction work will inevitably lead to
dust (TSP) emissions, mainly from excavation, filling activities, truck haulage
and material handling. No exceedance of hourly and daily TSP criteria are
predicted at air sensitive receivers (ASRs) in the vicinity of work sites with
eight times daily watering on active work areas. With implementation of
the proposed mitigation measures, dust suppression measures stipulated in the Air
Pollution Control (Construction Dust) Regulation, good site practices and
comprehensive dust monitoring and audit, the dust impact would be further
diminished. Dust monitoring is recommended in the EM&A Manual to
ensure the efficacy of the control measures.
17.2.2 With the implementation of suggested
mitigation measures, the predicted air quality in the study area complies with
the AQOs during operational phase. No environmental monitoring and audit
is proposed for vehicular emissions, cruise ship emissions from the proposed
cruise terminal at Kai Tak, chimney emissions from the San Po Kong and Kwun
Tong industrial areas and emission from the Planned Hospital
in Kai Tak.
17.2.3 Monthly (from July to September)
monitoring of odour impacts from KTAC and KTTS, for a period of 2 years, is proposed
during the operational phase of the Project to ascertain the effectiveness of
the proposed mitigation measures over time, and to monitor any on-going odour
impacts at the ASRs. If residual odour impact is still found at the end
of the odour monitoring programme, further investigation would be carried out
to review the odour problem and to identify the parties responsible for further
remedial action.
17.2.4 In order to determine the
effectiveness of the bioremediation monitoring of treated sediment is
proposed. Annual sediment sampling for a period of 2 years should be
conducted during the operational phase after completion of the odour
remediation works conducted at KTAC and KTTS including the full-scale in-situ
bioremediation, localized maintenance dredging and the 600m gap opening.
17.3
Noise Impact
17.3.1
Construction noise impacts from this Project,
in addition to the concurrent construction tasks of other projects could be
expected at the NSRs identified in this EIA. Appropriate mitigation
measures are required in order to alleviate the impacts to meet the EIAO-TM
criteria. Noise monitoring during construction phase will need to be
carried out to ensure that such mitigation measures are implemented properly.
17.3.2 The Contractors are requested to
implement and operate a continuous noise monitoring mechanism throughout the
entire construction period of the Project. This mechanism will include a
system to report the real time monitoring results on the Project Proponent’s
website within a period of time, to be agreed by EPD, after the relevant noise
monitoring data are collected. In cases where exceedances are found, the
Contractor and ET should take immediate actions to implement remediation measures
following the procedures specified in the EM&A Manual.
17.3.3 No environmental monitoring and
audit for potential noise impact during the operational phase is considered
necessary.
17.4
Water Quality Impact
17.4.1 There would be potential impacts of
suspended solids upon the flushing water intakes due to the marine construction
works proposed under the KTD. Water quality monitoring and audit will
need to be carried out for the proposed dredging and filling works to ensure
that all the recommended mitigation measures are properly implemented.
17.4.2 Water quality monitoring and audit
is also recommended to be carried out during and after the sediment treatment
works proposed at KTAC and KTTS to ensure that the proposed treatment work
would not result in unacceptable impact.
17.4.3 A water quality monitoring and audit
programme will also be implemented before and after opening a 600 m gap at the
runway to ascertain the runway opening would not result in unacceptable impact
marine water quality as well as the WSD flushing water intakes and to confirm
the water quality impacts predicted under operational phase of the Project.
An algal bloom / red tide monitoring programme and action plan will also
be implemented to ascertain the runway opening and bioremediation for the
sediment at KTAC and KTTS would not result in unacceptable impact.
17.4.4 Details of the water quality
monitoring programme and the Event and Action Plan are provided in the EM&A
Manual.
17.5
Waste Management Implications
17.5.1 Waste management will be the
Contractor’s responsibility to ensure that all wastes produced during the
construction of the Project are handled, stored and disposed of in accordance
with the recommended good waste management practices and EPD’s regulations and
requirements. The waste management measures recommended in this EIA
Report should form the basis of the site Waste Management Plan to be developed
by the Contractor at the construction stage.
17.5.2 It is recommended that the waste
arisings generated during the construction activities should be audited
periodically to determine if wastes are being managed in accordance with
approved procedures and the site Waste Management Plan. The audits should
look at all aspects of waste management including waste generation, storage,
transport and disposal. An appropriate audit programme would be to
undertake a first audit near the commencement of the construction works, and
then to audit on a weekly basis thereafter. In addition, the routine site
inspections should check the implementation of the recommended good site
practices and other waste management mitigation measures.
17.6
Land Contamination Impact
17.6.1 The contaminated soil identified at
the ex-GFS building area should be excavated and treated on-site by biopiling or
solidification / stabilization. In order to gauge the effectiveness of
the remedial system and minimise the potentially adverse environmental impacts
arising from the handling of potentially contaminated materials, the
recommended environmental mitigation and safety measures, progress monitoring
and/or confirmation sampling / testing recommended during the course of
remedial works should be implemented during the decommissioning /
decontamination works of the Project. Detailed requirements are provided in
the EM&A Manual.
17.7
Impact on Culture Heritage
Marine Archaeology
17.7.1 The recent 2007 MAI concluded no
further MAI is necessary, yet it did not preclude the possibility that there
could be items buried within the Marine Deposit which may be exposed by the
dredging works. It is therefore recommended that the dredging contractor(s)
should monitor the dredged spoils from those marine works that caused
significant impact to the seabed. Guidelines for the Monitoring Brief have been
prepared in consultation with the AMO and are attached as Appendix 12.1.
Marine works in KTD that may cause significant impact to the seabed include the
dredging works for the immersed tunnel section of CKR at To Kwa Wan, dredging
works for the relocation of the Hong Kong China Gas (HKCG) submarine main,
dredging works for the proposed cruise terminal, and dredging works for the
immersed tunnel section of Road T2 (including the dredging required for the
associated reconstruction of a section of the existing Kwun Tong submarine
outfall). Details of the impacts and the recommended mitigation measures
for the dredging works for proposed cruise terminal are presented in the
corresponding approved EIA Report (EIAO Register No.: AEIAR-115/2007).
Whereas the impacts and mitigation measures required for CKR, HKCG submarine
main relocation, and Road T2 will be examined under the respective Schedule 2
EIA study.
Terrestrial Archaeology
17.7.2 Further archaeological investigation
and rescue excavation will be undertaken at Trench AA3. Whereas for Trench AA5,
preservation in situ of all identified sections of the Longjin Pier will
be required after the completion of further archaeological investigation.
The implementation of the works will be undertaken by the Hong Kong Government.
Built Heritage
17.7.3 No monitoring and audit programme
specific for built heritage would be required.
17.8
Landscape and Visual Impact
17.8.1 The EIA has recommended landscape
and visual mitigation measures to be undertaken during construction and
operation phases of the Project. The following paragraphs define the
EM&A requirements to ensure the proposed landscape and visual impact
mitigation measures are effectively implemented.
17.8.2 The construction phase EM&A of
the landscape and visual environment and mitigation works shall be carried out
as part of the site audit programme. Specific EM&A during operation
phase of the Project is not required as long as the proposed mitigation
measures in the EIA and as depicted in the Landscape Mitigation Plan are fully
implemented.
17.8.3 Baseline changes with respect to the
landscape and visual environments should be carried out in reference to the
recorded baseline conditions of the site as described in Section 13 of the
EIA. The monitoring should in particular record changes of each landscape
resource, landscape character area and the view conditions of each visually
sensitive receiver. Parameters used to describe changes in each of the above
should be the same as in Section 13 of the EIA.
17.8.4 The baseline monitoring should be
conducted as a one-off site survey prior to commencement of any construction
works.
17.8.5 All mitigation measures proposed in
the EIA and implemented by the Contractor should be audited by a landscape
auditor, as a member of the Environmental Team, on a regular basis to ensure
compliance with the intended aims of the measures. Site inspection should be
undertaken at least once every two weeks throughout the construction period.
17.8.6 In particular, the extent of the
agreed works areas should be regularly checked during the construction
phase. Any trespass by the contractor outside the limit of the works,
including any damage to the existing trees, woodland and vegetation should be
noted.
17.8.7 The landscape auditor should also
audit the proposed operation phase mitigation measures in the EIA to ensure
that they are fully implemented within the Project design and construction.
17.9
Ecological Impact
Terrestrial Ecology
17.9.1
As only minor impacts on terrestrial ecology are identified
in this assessment, no monitoring programme specific for terrestrial ecology is
required under this Project.
Marine Ecology
17.9.2
To avoid and minimise
potential loss of small and sparsely distributed coral colonies found in the Project
area, it is recommended to translocate the directly affected corals within the
Project area, as far as practicable, to the nearby suitable habitat such as Junk Bay
where similar hydrographic condition and healthy coral communities of the same
coral species were recorded. Coral translocation should be carried out
during the winter season (November-March) in order to avoid disturbance to the
transplanted colonies during the spawning period (i.e. July to October). A
detailed translocation plan (including pre-translocation coral survey,
translocation methodology and monitoring of transplanted corals) should be
prepared during the detailed design stage of the Project.
Pre-translocation survey on coral within the proposed dredging area(s) would be
focused on identifying and mapping of coral colonies that would be directly
impacted by the proposed dredging and investigating the translocation
feasibility of these coral colonies (e.g. health status of coral colony). The
detailed translocation plan (including pre-translocation coral survey,
translocation methodology and monitoring proposal) and ecologist involved in
coral translocation and monitoring should be approved by AFCD prior to
commencement of the translocation exercises. It is also important to ensure
that the proposed relocation of the coral colonies will not affect any private
/ public marine uses / rights at the recipient site.
17.9.3 It is recommended to implement
monitoring of the transplanted corals after translocation, every 3 months for
one year (this follows previous examples of
post-translocation monitoring methodology, proposed in the EM&A Manual for
Dredging Work for Proposed Cruise Terminal at Kai Tak). Information gathered during each post-translocation monitoring survey
should include observations on the presence, survival, health condition and
growth of the transplanted coral colonies. Oulastrea crispata is not
expected to grow significantly over the one year monitoring period but previous
study (Lam, 2000) has shown it to have a growth rate of 0.9-1.04 mm per month
and thus, growth should be detectable over the 12 month post-translocation
monitoring period. These parameters should then be compared with the baseline results collected
from the pre-translocation survey.
17.9.4 The mitigation measures for coral
colonies to be implemented for the dredging works for the proposed cruise
terminal are detailed in the approved EIA Report and Environmental Monitoring
and Audit (EM&A) Manual on Dredging Works for Proposed Cruise Terminal at
Kai Tak.
17.10
Fisheries Impact
17.10.1 No unacceptable fisheries impacts would be
anticipated during marine works associated with the project. Thus, no
fisheries specific monitoring programme would be required.