Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Impact Assessment Report
Contents
3............ EIA on New distributor roads serving the planned KTD
3.5 Waste Management Implications
3.7 Impact on Cultural Heritage
3.8 Landscape and Visual Impact
3.9 Environmental Monitoring and Audit Requirement
3.10 Implementation Schedule of the Proposed Mitigation Measures
List of Tables
Table 3.1 Summary of Environmental Impacts
Table 3.2 Hong Kong Air Quality Objectives
Table 3.3 Tunnel Air Quality Guidelines (TAQG)
Table 3.5 Summary of Representative Air Sensitive Receivers
Table 3.6 Emission Factors for Construction Activities
Table 3.7 Major Dust Generating Activities in the Worst Case Scenarios during Construction Phase
Table 3.9 Vehicle Classes in EMFAC-HK Model
Table 3.12 Portal and Ventilation Building Emissions
Table 3.13 Predicted Cumulative Maximum 1-hour Average TSP Concentrations at 1.5m above ground
Table 3.14 Summary of Predicted Results
Table 3.15 Predicted NO2 Concentration Inside the Tunnel / Landscape Deck
Table 3.16 Construction Noise Criteria for Activity other than Percussive Piling
Table 3.17 Representative Noise Sensitive Receivers for Noise Impact Assessment
Table 3.19 Summary of Traffic Noise Impact for Other Sites within KTD area
Table 3.21 Construction Noise Residual Impacts
Table 3.22 Summary of Water Quality Objectives for the Victoria Harbour WCZ
Table 3.23 WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes
Table 3.24 Summary Statistics of Marine Water Quality in the Victoria Harbour WCZ in 2006
Table 3.26 Summary Statistics of 2006 River Water Quality for Kai Tak Nullah
Table 3.27 Pollution Levels Measured at KTAC in October 2005
Table 3.28 Pollution Levels Measured at KTAC in January 2006
Table 3.29 Summary of Locations of the New Distributor Roads
Table 3.30 Summary of findings in the relevant EIA reviewed
Table 3.31 Summary of Soil Samples Exceeding the Dutch B/C Levels
Table 3.32 Summary of Groundwater Samples Exceeding the Dutch B/C Values
Table 3.33 Evaluation of Significance of Risk Due to Groundwater Contamination
Table 3.35 Location, Depth and Estimated Quantity of Contaminated Soil
Table 3.36 Estimated Quantity of Different Type of Contaminated Soil
Table 3.37 Summary of Reviewed Information on Potential Contaminative Land Uses
Table 3.39 Landscape Resources / Landscape Character Areas and
Their Sensitivity to Change
Table 3.40 Visual Sensitive Receivers (VSRs) and Their Sensitivity to Change
Table 3.41 Significant Landscape Impacts of the Proposed Works during Construction Phase
Table 3.44 Landscape and Visual Mitigation Measures during Construction Phase
Table 3.45 Landscape and Visual Mitigation Measure during
Operation Phase
Table 3.46 Implementation Schedule for Air Quality Measures
Table 3.47 Implementation Schedule for Noise Measures
Table 3.48 Implementation Schedule for Water Quality Measures
Table 3.49 Implementation Schedule for Waste Management Measures
Table 3.50 Implementation Schedule for Land Contamination Measures
Table 3.51 Implementation Schedule for Landscape and Visual Impacts
Table 3.1 Summary of Environmental Impacts
|
Construction Phase |
Operational Phase |
Air |
|
|
Noise |
|
|
Water Quality |
|
|
Waste Management |
|
|
Land Contamination |
|
û |
Hazard to Life |
û |
û |
Cultural Heritage |
|
û |
Landscape and Visual Impact |
|
|
Ecological Impact |
û |
û |
Fisheries Impact |
û |
û |
Table 3.2
Pollutant |
Maximum
Concentration (µg m-3) (1) |
|||
Averaging
Time |
||||
1
hour (2) |
8
hour (3) |
24
hour (3) |
Annual
(4) |
|
Total Suspended Particulates (TSP) |
- |
- |
260 |
80 |
Respirable Suspended Particulates (RSP) (5) |
- |
- |
180 |
55 |
|
800 |
- |
350 |
80 |
Nitrogen Dioxide (NO2) |
300 |
- |
150 |
80 |
Carbon Monoxide (CO) |
30,000 |
10,000 |
- |
- |
Photochemical Oxidants (as Ozone, O3) (6) |
240 |
- |
- |
- |
Notes:
(1) Measured at 298 K and 101.325 kPa.
(2) Not to be exceeded more than three times per year.
(3) Not to be exceeded more than once per year.
(4) Arithmetic mean.
(5) Suspended particulates in air with a nominal aerodynamic diameter of 10 mm or smaller.
(6) Photochemical oxidants are determined by measurement of ozone only.
Table 3.3 Tunnel Air Quality Guidelines (TAQG)
Air Pollutant |
Averaging Time |
Maximum Concentration |
|
(mg/m3) (1) |
ppm |
||
Carbon Monoxide (CO) |
5 minutes |
115,000 |
100 |
Nitrogen Dioxide (NO2) |
5 minutes |
1,800 |
1 |
Sulphur Dioxide (SO2) |
5 minutes |
1,000 |
0.4 |
Note: (1) Expressed at reference conditions of 298K and 101.325kPa.
Table 3.4 Annual Average Concentrations of Pollutants in Year 2006 at EPD’s Sham Shui Po and Kwun Tong Air Quality Monitoring Stations
Pollutant |
Annual Average AQO (mg m-3) |
Year 2006 Annual Average Concentration (mg m-3) |
|
Sham Shui Po station |
Kwun Tong station |
||
TSP |
80 |
79 |
75 |
RSP |
55 |
55 |
55 |
NO2 |
80 |
67 |
61 |
SO2 |
80 |
24 |
19 |
Table 3.5 Summary of Representative Air Sensitive Receivers
ASRs |
District (1) |
Location |
Existing / Planned Land Use |
Max. Building Height, m (2) |
Distance to this DP, m |
Distributor Road |
A1 |
KT |
Cha Kwo Ling Tusen |
Residential |
5 |
1695 |
D3 |
A2 |
KT |
Cha Kwo Ling |
Residential |
15 |
1637 |
D3 |
A3 |
KT |
Laguna City IV |
Residential |
81 |
1370 |
D3 |
A4 |
KT |
Laguna Park |
Recreation |
1.5 |
1336 |
D3 |
A5 |
KT |
Hoi Bun Industrial Centre |
Industrial |
42 |
1050 |
D3 |
A6 |
KT |
Seapower Industrial Centre |
Industrial |
33 |
868 |
D3 |
A7 |
KT |
CAC Tower |
Commercial |
57 |
728 |
D3 |
A8 |
KT |
Bite Industrial Building |
Industrial |
30 |
667 |
D3 |
A9 |
KT |
Wharf T&T Square |
Commercial |
45 |
519 |
D4 |
A10 |
KT |
Hoi Bun Road Park |
Recreation |
1.5 |
405 |
D4 |
A11 |
NTK |
Kowloon Bay Factory Estate |
Industrial |
24 |
145 |
D4 |
A12 |
NTK |
Kowloon Bay Motor Vehicle Exam Centre |
Industrial |
6 |
103 |
D4 |
A13 |
NTK |
New Kowloon Bay Motor Vehicle Exam Centre |
Industrial |
3 |
84 |
D4 |
A14 |
NTK |
Kai Fok Industrial Centre |
Industrial |
24 |
522 |
D3 |
A15 |
KB |
Sing Tao Building |
Commercial |
30 |
537 |
D3 |
A16 |
KB |
WSD Kowloon Bay Pipe Yard |
Industrial |
1.5 |
445 |
D3 |
A17 |
KB |
Hong Kong International Trade & Exhibition Centre |
Commercial |
54 |
234 |
D2 |
A18 |
KB |
Hong Kong Bank New Treasury Building |
Commercial |
12 |
266 |
D2 |
A19 |
KB |
Electrical & Mechanical Services Department Headquarters |
G/IC |
21 |
90 |
D2 |
A20 |
KB |
Sino Industrial Plaza |
Industrial |
30 |
207 |
D2 |
A21 |
KB |
Skyline Tower |
Commercial |
117 |
154 |
D2 |
A22 |
KB |
Football field |
Recreation |
1.5 |
231 |
D2 |
A23 |
KB |
Kowloon Health Centre |
G/IC |
30 |
274 |
D2 |
A24 |
KB |
Bicycle Track Near Richland Garden |
Recreation |
1.5 |
245 |
D2 |
A25 |
NCW |
Richland Gardens Shopping Centre |
Shopping Center |
30 |
323 |
D2 |
A26 |
NCW |
Richland Gardens |
Residential |
99 |
432 |
D2 |
A27 |
NCW |
Kam Bik House, Choi Hung Estate |
Residential |
60 |
567 |
D1 |
A28 |
NCW |
Pik Hoi House, Choi Hung Estate |
Residential |
60 |
525 |
D1 |
A29 |
NCW |
Rhythm Garden |
Residential |
87 |
333 |
D1 |
A30 |
SPK |
Cognitio College |
Educational |
18 |
164 |
D1 |
A31 |
SPK |
Sir Robert Black Health Centre |
Clinic |
9 |
141 |
D1 |
A32 |
SPK |
Lee Kau Yan Memorial School |
Educational |
10 |
126 |
D1 |
A33 |
SPK |
Shek Ku Lung Road Playground |
Recreation |
1.5 |
64 |
D1 |
A34 |
SPK |
Regal Oriental Hotel |
Hotel |
42 |
78 |
D1 |
A35 |
SPK |
South Mansion |
Residential |
15 |
78 |
D1 |
A36 |
SPK |
Jenford Building |
Residential |
12 |
72 |
D1 |
A37 |
KC |
Sung Wong Toi Playground |
Recreation |
1.5 |
20 |
D1 |
A38 |
KC |
Sung Wong Toi Garden |
Recreation |
1.5 |
220 |
D1 |
A39 |
TKW |
Parc 22 |
Residential |
33 |
303 |
D1 |
A40 |
TKW |
Sky Tower |
Residential |
141 |
338 |
D1 |
A41 |
TKW |
Freder Centre |
Industrial |
153 |
305 |
D2 |
A42 |
TKW |
K K Industrial Building |
Industrial |
12 |
236 |
D2 |
A43 |
TKW |
HK Society for Blind hostel |
Hostel |
9 |
121 |
D2 |
A44 |
TKW |
Mok Cheong Street Residential District |
Residential |
18 |
192 |
D2 |
A45 |
TKW |
China Gas Company |
Commercial |
15 |
347 |
D2 |
A46 |
TKW |
Ming Lun Street Residential District |
Residential |
21 |
332 |
D2 |
A47 |
TKW |
Grand Waterfront |
Residential |
153 |
335 |
D2 |
A48 |
TKW |
Merit Industrial Center |
Industrial |
36 |
464 |
D2 |
A49 |
TKW |
Wei Chien Court |
Residential |
39 |
441 |
D2 |
A51 |
TKW |
United Daily |
Industrial |
48 |
581 |
D2 |
A52 |
TKW |
Holly Carpenter Primary School |
Educational |
18 |
588 |
D2 |
A53 |
TKW |
Oblate Father’s Primary School |
Educational |
21 |
664 |
D2 |
A54 |
TKW |
Sui Ying Industrial Building |
Industrial |
33 |
773 |
D2 |
A55 |
TKW |
Fook Shing Industrial Building |
Industrial |
36 |
865 |
D2 |
A56 |
TKW |
Sunrise Villa |
Residential |
90 |
932 |
D2 |
A57 |
TKW |
Wing Kwong Street Residential District |
Residential |
21 |
1226 |
D2 |
A58 |
TKW |
CCC Kei To Secondary School |
Educational |
24 |
1244 |
D2 |
A59 |
TKW |
Po Leung Kuk Ngan Po Ling College |
Educational |
27 |
1330 |
D2 |
A60 |
HH |
Sunrise Plaza |
Residential |
39 |
1398 |
D2 |
A61 |
HH |
Peninsula Square |
Commercial |
69 |
1374 |
D2 |
A62 |
HH |
A.P.B Centre |
Industrial |
1.5 |
1284 |
D2 |
A63 |
HH |
DSD To Kwan Wan PTW Workshop |
G/IC |
27 |
1189 |
D2 |
PA1 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
276 |
D1 |
PA2 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
323 |
D1 |
PA3 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
335 |
D1 |
PA4 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
350 |
D1 |
PA5 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
327 |
D1 |
PA6 |
KTD |
Site 1A2 (Planned) |
Educational |
40 |
385 |
D1 |
PA7 |
KTD |
Site 1A3 (Planned) |
Educational |
40 |
398 |
D1 |
PA8 |
KTD |
Site 1A4 (Planned) |
Educational |
40 |
504 |
D1 |
PA9 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
381 |
D1 |
PA10 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
407 |
D2 |
PA11 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
291 |
D2 |
PA12 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
290 |
D2 |
PA13 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
202 |
D2 |
PA14 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
149 |
D2 |
PA15 |
KTD |
Site 1B4 (Planned) |
Educational |
40 |
63 |
D2 |
PA16 |
KTD |
Site 1C1 (Planned) |
G/IC |
85 |
51 |
D1 |
PA17 |
KTD |
Site 1D2 (Planned) |
Commercial |
95 |
93 |
D1 |
PA18 |
KTD |
Site 1D3 (Planned) |
G/IC |
55 |
86 |
D1 |
PA19 |
KTD |
Site 1D4 (Planned) |
G/IC |
95 |
34 |
D1 |
PA20 |
KTD |
Site 1E1 (Planned) |
G/IC |
95 |
72 |
D1 |
PA21 |
KTD |
Site 1E1 (Planned) |
G/IC |
95 |
256 |
D1 |
PA22 |
KTD |
Site 1F1 (Planned) |
Commercial |
145 |
34 |
D1 |
PA23 |
KTD |
Site 1F2 (Planned) |
Commercial |
170 |
60 |
D1 |
PA24 |
KTD |
Site 1G2 (Planned) |
G/IC |
75 |
71 |
D1 |
PA25 |
KTD |
Site 1H1 (Planned) |
Residential |
105 |
320 |
D1 |
PA26 |
KTD |
Site 1H2 (Planned) |
Residential |
105 |
338 |
D1 |
PA27 |
KTD |
Site 1H3 (Planned) |
Residential |
105 |
347 |
D2 |
PA28 |
KTD |
Site 1I1 (Planned) |
Residential |
95 |
143 |
D2 |
PA29 |
KTD |
Site 1I2 (Planned) |
Residential |
95 |
127 |
D2 |
PA30 |
KTD |
Site 1I3 (Planned) |
Residential |
95 |
122 |
D2 |
PA31 |
KTD |
Site 1J1 (Planned) |
G/IC |
55 |
49 |
D2 |
PA32 |
KTD |
Site 1J3 (Planned) |
G/IC |
25 |
91 |
D2 |
PA33 |
KTD |
Site 1K1 (Planned) |
Residential |
105 |
403 |
D2 |
PA34 |
KTD |
Site 1K2 (Planned) |
Residential |
105 |
417 |
D2 |
PA35 |
KTD |
Site 1K3 (Planned) |
Residential |
95 |
439 |
D2 |
PA36 |
KTD |
Site 1L1 (Planned) |
Residential |
95 |
105 |
D2 |
PA37 |
KTD |
Site 1L2 (Planned) |
Residential |
95 |
67 |
D2 |
PA38 |
KTD |
Site 1L3 (Planned) |
Residential |
95 |
44 |
D2 |
PA39 |
KTD |
Site 1L4 (Planned) |
Residential |
25 |
30 |
D2 |
PA40 |
KTD |
Site 1M1 (Planned) |
Commercial |
35 |
334 |
D1 |
PA41 |
KTD |
Site 1M1 (Planned) |
Commercial |
35 |
81 |
D1 |
PA42 |
KTD |
Site 1M2 (Planned) |
Commercial |
35 |
83 |
D1 |
PA43 |
KTD |
Site 2A1 (Planned) |
G/IC |
65 |
83 |
D1 |
PA44 |
KTD |
Site 2A2 (Planned) |
G/IC |
65 |
39 |
D1 |
PA45 |
KTD |
Site 2A3 (Planned) |
G/IC |
65 |
31 |
D1 |
PA46 |
KTD |
Site 2A4 (Planned) |
G/IC |
65 |
159 |
D1 |
PA47 |
KTD |
Site 2A5 (Planned) |
G/IC |
65 |
62 |
D1 |
PA48 |
KTD |
Site 2A6 (Planned) |
G/IC |
40 |
45 |
D1 |
PA49 |
KTD |
Site 2B1 (Planned) |
Residential |
105 |
162 |
D1 |
PA50 |
KTD |
Site 2B1 (Planned) |
Residential |
105 |
165 |
D1 |
PA51 |
KTD |
Site 2B2 (Planned) |
Residential |
95 |
160 |
D1 |
PA52 |
KTD |
Site 2B3 (Planned) |
Residential |
80 |
165 |
D1 |
PA53 |
KTD |
Site 2B4 (Planned) |
Residential |
80 |
177 |
D1 |
PA54 |
KTD |
Site 2B5 (Planned) |
Residential |
80 |
178 |
D1 |
PA55 |
KTD |
Site 2B6 (Planned) |
Residential |
80 |
207 |
D1 |
PA56 |
KTD |
Site 2D1 (Planned) |
Recreation |
40 |
143 |
D2 |
PA57 |
KTD |
Site 2D1 (Planned) |
Recreation |
40 |
146 |
D2 |
PA58 |
KTD |
Site 3C1 (Planned) |
Hospital |
55 |
31 |
D4 |
PA59 |
KTD |
Site 3C1 (Planned) |
Hospital |
55 |
75 |
D4 |
PA60 |
KTD |
Site 3C1 (Planned) |
G/IC |
55 |
72 |
D4 |
PA61 |
KTD |
Site 3C1 (Planned) |
Hospital |
55 |
95 |
D4 |
PA62 |
KTD |
Site 3D1 (Planned) |
Commercial |
95 |
60 |
D4 |
PA63 |
KTD |
Site 3D2 (Planned) |
Commercial |
95 |
265 |
D4 |
PA64 |
KTD |
Site 3D3 (Existing)/ Site 3D3 (Planned) |
Industrial / Commercial |
168 / 95 |
136 |
D4 |
PA65 |
KTD |
Site 3D4 (Planned) |
Commercial |
95 |
138 |
D4 |
PA66 |
KTD |
Site 3D4 (Planned) |
Commercial |
95 |
298 |
D4 |
PA67 |
KTD |
Site 4A1 (Planned) |
Residential |
60 |
64 |
D3 |
PA68 |
KTD |
Site 4A1 (Planned) |
Residential |
60 |
58 |
D3 |
PA69 |
KTD |
Site 4A2 (Planned) |
Commercial |
40 |
170 |
D3 |
PA70 |
KTD |
Site 4A3 (Planned) |
Commercial |
75 |
47 |
D3 |
PA71 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
90 |
D3 |
PA72 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
198 |
D3 |
PA73 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
53 |
D3 |
PA74 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
195 |
D3 |
PA75 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
64 |
D3 |
PA76 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
219 |
D3 |
PA77 |
KTD |
Site 4B1 (Planned) |
Residential |
50 |
55 |
D3 |
PA78 |
KTD |
Site 4B1 (Planned) |
Residential |
50 |
62 |
D3 |
PA79 |
KTD |
Site 4B2 (Planned) |
Residential |
50 |
51 |
D3 |
PA80 |
KTD |
Site 4B2 (Planned) |
Residential |
50 |
66 |
D3 |
PA81 |
KTD |
Site 4B3 (Planned) |
Residential |
60 |
62 |
D3 |
PA82 |
KTD |
Site 4B3 (Planned) |
Residential |
60 |
62 |
D3 |
PA83 |
KTD |
Site 4B4 (Planned) |
Residential |
50 |
153 |
D3 |
PA84 |
KTD |
Site 4B4 (Planned) |
Residential |
50 |
58 |
D3 |
PA85 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
64 |
D3 |
PA86 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
56 |
D3 |
PA87 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
56 |
D3 |
PA88 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
61 |
D3 |
PA89 |
KTD |
Site 4C1 (Planned) |
Commercial |
40 |
172 |
D3 |
PA90 |
KTD |
Site 4C2 (Planned) |
Commercial |
50 |
158 |
D3 |
PA91 |
KTD |
Site 4C3 (Planned) |
Commercial |
40 |
150 |
D3 |
PA92 |
KTD |
Site 4C4 (Planned) |
Commercial |
40 |
153 |
D3 |
PA93 |
KTD |
Site 4C5 (Planned) |
Commercial |
40 |
159 |
D3 |
PA94 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
463 |
D3 |
PA95 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
408 |
D3 |
PA96 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
656 |
D3 |
PA97 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
658 |
D3 |
PA98 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
228 |
D3 |
PA99 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
255 |
D3 |
PA100 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
451 |
D3 |
PA101 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
569 |
D3 |
PA102 |
KTD |
Site 5A4 (Planned) |
Residential |
60 |
241 |
D2 |
PA103 |
KTD |
Site 5A4 (Planned) |
Residential |
105 |
303 |
D2 |
PA104 |
KTD |
Site 3B1 (Planned) |
Undesignated |
40 |
293 |
D3 |
PA105 |
KTD |
Site 3B2 (Planned) |
Undesignated |
40 |
288 |
D3 |
PA106 |
KTD |
Site 3B3 (Planned) |
Undesignated |
40 |
306 |
D3 |
PA107 |
KTD |
Site 3B4 (Planned) |
Undesignated |
40 |
310 |
D3 |
PA108 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
136 |
D3 |
PA109 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
203 |
D3 |
PA110 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
355 |
D3 |
PA111 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
328 |
D3 |
PA112 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
248 |
D3 |
PA113 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
49 |
D3 |
Note: (1) KT – Kwun Tong; NTK – Ngau Tau Kok; KB – Kowloon Bay; NCW – Ngau Chi Wah; SPK – San Po Kong; KC – Kowloon City, TKW – To Kwa Wan; HH – Hung Hom; KTD – Kai Tak Development
(2) The maximum heights for Planned ASRs were made reference to the RODP.
Table 3.6 Emission Factors for Construction Activities
Construction Activities |
Emission Rate (g/m2/s) |
Remark |
All construction work |
E = 1.49684E-05 |
- 50% of works area with active dust emitting construction activities - 87.5% reduction by water suppression (watering eight times a day) - USEPA AP-42 5th ed., S.13.2.3.3 |
Barging point serving the Development at Anderson Road Project |
E = 2.04236E-05 |
- USEPA AP-42 5th ED., S. 13.2.4 - Information for emission rate calculation was provided by Anderson Road Project Engineer - 75% reduction by water suppression for each unloading |
Wind erosion for all construction work (including barging point) |
E = 1.34767E-06
|
- 50% of works area with active construction activities - AP-42 5th ed., S.11.9 Table 11.9.4 |
Table 3.7 Major Dust Generating Activities in the Worst Case Scenarios during Construction Phase
Activities |
Period |
|
Mid 2009 to Mid 2013 |
Mid 2013 to Late 2016 |
|
Scenario 1 |
Scenario 2 |
|
Package A - Cruise Terminal Development (Phase 1 Berth), related advance works and Runway Park |
||
Phase 1 Berth |
|
|
Road TD3, TD4, L14 and minor road works in Kowloon Bay |
|
|
Modification off Taxiway Bridge |
|
|
Pumping Station PS6 |
|
|
Fireboat Berth |
|
|
Runway Park |
|
|
Package B - Infrastructure works at North Apron, Phase 1 - Housing Sites and Government Offices |
||
Construction of Road D1 (part) |
|
|
Local Roads L2, L3, L15 and associated footpaths at North Apron |
|
|
Local Roads L4 & L5 |
|
|
Construction of Box Culvert (2.5m x 2.5m) |
|
|
Construction of Box Culvert (3m x 2.8m) |
|
|
Construction of Pumping Station PS1A |
|
|
Construction of Road D1 |
|
|
Construction of Road D2 (part) |
|
|
Construction of Road L1 |
|
|
Construction of Road L2 & L11 (part) |
|
|
Construction of Road L4 (Part) & L5 |
|
|
Construction of Slip Road S7 & S8 of CKR/T2 Interchange |
|
|
Construction of Box Culvert (5m x 2.5m) |
|
|
Upgrading of Pumping Station PS1 |
|
|
Package D - Kai Tak Nullah modification works |
||
Rebuild Kai Tak Nullah |
|
|
Construction of DSD's Desilting Compounds at Kai Tak Nullah |
|
|
Package E - Infrastructure works at runway and Metro Park |
||
600m Wide Opening in Runway |
|
|
Construction of Road D3 (near at Metro Park) |
|
|
Construction of Road L12 & L13 |
|
|
Conversion of TD3 into D3 with Street Lighting/ Landscaping Works(include Road L14) |
|
|
Conversion of TD4 into D4 |
|
|
Elevated Landscape Deck above Road D3 |
|
|
Package F - Infrastructure works at North Apron, Phase 2 |
||
Construction of Road D1, L7, L8, L9 & L16 |
|
|
Construction of Drainage Culvert (2.5x2.5m) |
|
|
Construction of Drainage Culvert (4x3m) |
|
|
Construction of Drainage Culvert (5x4m) |
|
|
Construction of Road D2, D3, L6, L17 & L19 |
|
|
Pumping Station PS2 |
|
|
Pumping Station NPS |
|
|
Upgrading of Pumping Station PS3 |
|
|
Stadium Complex |
|
|
Package G - Trunk Road T2 and infrastructure works at South Apron |
||
Construction of Trunk Road T2, Local Roads L10, L18 and associated footpaths at South Apron |
|
|
Cut and Cover Section of T2 |
|
|
Kwun Tong Transportation Link |
|
|
Other concurrent projects |
||
SCL Construction |
|
|
CKR Construction |
|
|
Anderson Road Project |
|
|
Background pollutant concentrations based on five years averaged monitoring data from EPD monitoring stations at Sham Shui Po and Kwun Tong;
Vehicle emissions from open sections of existing and proposed road networks within 500m from the project site boundary;
Portal emissions from Road T2 Tunnel, proposed Road L1 tunnel, decked Road D2, tunnel section of Tseung Kwan O – Lam Tin Tunnel (near TKO/T2 interface), existing Kai Tak Tunnel and existing Eastern Harbour Crossing Tunnel (EHC) portal;
Emissions from idling traffic at the toll plaza section of EHC near Yau Tong;
Ventilation building emissions from Road T2 Tunnel, planned Central Kowloon Route (CKR), existing Kai Tak Tunnel and existing EHC;
All industrial chimneys within 500m from the study boundary;
Emission from the proposed hospital within KTD;
Cruise ship emissions from the proposed cruise terminal at Kai Tak;
Emission from the existing Typhoon Shelters
Emission from Sai Tso Wan Landfill; and
Planned heliport emission at the end of runway.
Table 3.8 Annual Average Concentrations of Pollutants in Latest Five Years at Sham Shui Po and Kwun Tong Air Quality Monitoring Stations
Pollutant |
Annual Average Concentration in Latest Five Years (2002-2006) (mg m-3) |
|
Sham Shui Po station |
Kwun Tong station |
|
RSP |
55 |
57 |
NO2 |
67 |
63 |
SO2 |
24 |
19 |
new roads in the Kai Tak Development
the existing roads
Vehicle Classes
3.2.23 EMFAC-HK model was adopted to estimate the vehicle emission rates and inventories of exhaust, carbon monoxide, oxides of nitrogen and particulate matter.
3.2.24 The “vehicle fleet” refers to all motor vehicles operating on roads within this Study Area. The modelled fleet was broken down into 16 vehicle classes based on the information as shown on Table 4.4 (Registration and Licensing of Vehicle by Fuel Type) of the Transport Monthly Digest (Sep 2007) and vehicle population provided by EPD. The vehicle group classification was based on the definition in The Annual Traffic Census 2006 – Appendix F Vehicle Classification System.
Table 3.9 Vehicle Classes in EMFAC-HK Model
Vehicle Class |
Description |
Fuel Type |
Gross Vehicle Weight |
MC1 |
Petrol Private Cars (PC) & Light Goods Vehicles (LGV) |
Petrol |
all |
MC3 |
Diesel Private Cars & Light Goods Vehicles<2.5t |
Diesel |
<=2.5t |
MC4 |
Diesel Private Cars & Light Goods Vehicles 2.5-3.5t |
Diesel |
>2.5-3.5t |
MC5 |
Public Light Buses |
LPG, Diesel |
all |
MC6 |
Light Goods Vehicles >3.5t |
Diesel |
>3.5-5.5t |
MC7 |
Medium & Heavy Goods Vehicles with GVW 5.5-15t |
Diesel |
>5.5-15t |
MC8 |
Medium & Heavy Goods Vehicles with GVW >=15t |
Diesel |
>15t |
MC10 |
Double Deck Franchised Buses |
Diesel |
all |
MC11 |
Motor Cycles |
Petrol |
all |
Taxi3 |
Taxi |
LPG |
all |
Taxi4 |
Private Light Buses <3.5t |
LPG, Diesel |
<=3.5t |
Taxi5 |
Private Light Buses >3.5t |
LPG, Diesel |
>3.5t |
Taxi6 |
Non- franchised Buses <6.4t |
Diesel |
<=6.4t |
Taxi7 |
Non- franchised Buses 6.4-15t |
Diesel |
>6.4-15t |
Taxi8 |
Non- franchised Buses >15t |
Diesel |
>15t |
Taxi10 |
Single Deck Franchised Buses |
Diesel |
all |
3.2.26 With reference to the road design, the design speed limits of all road links within the Study Area included 50kph, 70kph and 80kph. Hence, three sets of emission factors for the three road types were calculated.
3.2.30 Each vehicle class had diverse technological factors in different years. According to the underlying assumption in EMFAC-HK, each vehicle class could be modelled by the individual behaviour of unique technology groups. Each technology group represented the same vehicle class had distinct emission control technologies, similar in-use deterioration rates and responded the same to repair. It means that the vehicles from the same class had the same emission standards or specific equipment installed on them (e.g. multi-port fuel injection, three-way catalyst, adaptive fuel controls, etc) which made them had the same performance.
3.2.31 The Up to Date Vehicle Licensed Number by Age and Technology Group Fractions provided in EPD’s website was adopted in this assessment. Since the provided exhaust technology fractions were only up to Year 2003, for those after Year 2003 were projected in accordance with EPD Guideline on Modelling Vehicle Emissions Appendix II “The Implementation Schedule of Vehicle Emission Standards in Hong Kong (Updated as at 17 August 2005)” and Appendix III “The Technology Group Indexes”.
3.2.32 According to the EPD Guideline on Modelling Vehicle Emissions, it mentioned that the existing vehicle emission control programmes were included in the EMFAC-HK. No other vehicle emission control measures were assumed in the assessment, thus the projected breakdown (%) in Years 2004 – 2031 of private cars & light goods vehicles and breakdown (%) of diesel & LPG private light bus >3.5t were made reference to the default data.
3.2.35 As recommended in the EPD Guideline on Modelling Vehicle Emissions, the latest vehicle age distribution data provided in the EPD’s website, that is, the Vehicle Population in Year 2003, was used except the population of private car and taxi.
3.2.36 After the implementation of stringent emission standard in 1998, there was no new certification of diesel private car registration in Hong Kong. Thus, the number of diesel private car was extracted and grouped into the “petrol private car”. Since diesel Taxi started to switch to LPG from Year 2001 and only one fuel type of Taxi was available in EMFAC-HK Model, 100% LPG taxi was therefore be assumed in this assessment.
3.2.37 The then Environment, Transport and Works Bureau (ETWB) implemented an incentive scheme to encourage the early replacement of diesel light buses with LPG or electric ones since 2002. In view of the environmental report established by EPD, nearly 80% of new public light buses in 2004 operating on LPG. As a conservative approach, the incentive scheme for light buses would not be considered in this assessment.
3.2.40 The diurnal variation of daily trips was used to estimate the start emissions of petrol vehicles, thus the trips of other vehicles would be zero. The number of trips per day of petrol vehicle was equal to the number of cold starts per day. The diurnal variation of daily trips could be estimated based on the ratio of trip/VMT in the entire territory and the Study Area. The number of vehicle trips was calculated by the following equation:
3.2.41 Vehicle-mile-travelled (VMT) represents the total distance travelled on a weekday. The VMT was calculated by multiplying the number of vehicle which based on the forecast hourly traffic flow in Year 2031, which is the maximum traffic projects within 15 years upon the commissioning year of the DP1 Project, and the length of road travelled in the Study Area. The input in the model was by vehicle/fuel/hour.
3.2.42 The hourly profile of traffic flow was made reference to the Annual Traffic Census 2006. The major core station along Prince Edward Road East Road (No. 3003) was selected for representing the hourly profile of all roads within the Study Area. However, the same traffic breakdown in % would be applied to all hours.
3.2.45 The speed limits of each road were made reference to the Traffic AIDs from Transport Department. It was assumed that all vehicle classes had the same speed profile in the model.
3.2.46 In accordance with the Road Traffic Ordinance, for any road with design speed limit of 70kph or above, the maximum speed limit for medium goods vehicles, heavy goods vehicles, buses and buses shall be limited to 70kph. Thus, the speeds of medium goods vehicles, heavy goods vehicles and buses from the flow speed of 70kph, whichever is lower, are adopted.
3.2.47 To simulate the effect of different road speed during the rush and non-rush hour, sensitivity test has been done. The design road speed limits are assumed for representing the situation during non-rush hour, while the vehicle speed of peak hour flow (8:00a.m.-9:00a.m.) in Year 2031 which having the lowest traffic speed will be representing the situation during rush-hour.
3.2.48 The flow speeds were calculated based on the peak traffic flow in Year 2031 and volume/capacity ratio of different road type. For obtaining the speed fractions of each vehicle type, the vehicle speeds of each road link were first calculated and weighing by VMT. If the road links are in two-way direction, the vehicle speeds were calculated by weighing vehicle speeds of each direction. The calculated peak flow speed fractions are summarized in Appendix 3.7.
3.2.49 In the model, same road speeds are applied to all hours to demonstrate the effect of using peak flow speed and design speed. Based on the comparison of the total daily emission rate, the worst road speed fraction is applied for predicting the vehicle emissions. Model year of 2031 is adopted in the sensitivity test.
3.2.50 From the results of the sensitivity test, it indicates that higher total daily NOX and RSP emissions will be obtained at lower road speed under road groups with design speed of 50kph, 70kph and 80kph except the total daily NOX emission factors for vehicle types other than petrol private cars and taxi under road group with design speed of 80kph. Although the total daily NOX emissions under scenario using design speed for vehicle types other than petrol private cars and taxi are less than 5% higher than that under scenario using peak flow speed, major vehicle types travel within the study area are petrol private cars and taxi (about 63% of the total number of vehicles). Thus, the peak hour flow speed in Year 2031 is applied to all hours for predicting the total hourly emissions in this assessment as a conservative approach. This sensitivity test results are presented in Appendix 3.8.
3.2.51 The fleet average emission factor under congestion traffic condition for calculating the emissions inside tunnel/full enclosure is also considered in the study. The travel speed is assumed as 10kph at all hours under congestion traffic condition.
3.2.52 According to the construction programme, the completion of the Project would be in Year 2016. The air quality impact prediction would be based on the maximum traffic projections within 15 years upon operation of the Project. For the purpose of finding the worst emission year, 15 sets of vehicle emissions based on the emission control schemes from Year 2016 to 2031 by using the same VMT in 2031 were produced. The emission standards of each vehicle class were the major factor influencing the vehicle exhaust emission. According to the implementation schedule of emission standards, the latest program was up to Year 2006 or 2009. Better emission controlled vehicles (Euro IV and V) would replace the old pre-Euro diesel/petrol vehicles. The vehicle exhaust emissions of Year 2016 to Year 2031 were calculated. Sensitivity tests were undertaken to calculate the vehicle exhaust emissions in different year by using the VMT of each road category and the flow speed fractions in Year 2031. By using the peak hour flow speed in Year 2031 at all hours, the total daily NOX an RSP emissions by 16 vehicle classes in different vehicle exhaust emission year from 2016 to 2031 are summarized in Appendix 3.9.
3.2.53 Comparing the total daily NOX and RSP emissions under different vehicle exhaust emission years from Year 2016 to 2031, the highest vehicle emissions were found in Year 2016 using emission control scenario and were decreased from Year 2016 to 2031. Therefore, as a conservative approach, the emissions using emission control scenario in Year 2016 were adopted for this assessment.
3.2.54 As a conservative approach, the hourly emissions in Year 2016 were first divided by the number of vehicles and the distance travelled to obtain the emission factors in gram per miles per vehicle. The calculated maximum vehicle emission factors were then selected for incorporation into the air dispersion model. These conservative vehicle emission factors together with the forecasted Year 2031 peak traffic flow were adopted in this air quality impact assessment. The calculation of fleet vehicle emission for this assessment is presented in Appendix 3.10. The forecast traffic flow and speed fraction for year 2031 with 16 vehicle classes have been submitted to the Transport Department (TD) on 19 March 2008 and received no objection from TD on 15 April 2008 for using the forecasted traffic flow for the EIA. The response letter from TD is attached in Appendix 3.11 for reference.
Table 3.10 Emission Factors for Year 2016 for Different Vehicle Classes (EMFAC-HK) under Normal Traffic Condition)
Vehicle Class |
Description |
Emission Factors for 2016, g/mile-veh |
|||||
Road Type 1 (with design speed limit of 50kph) |
Road Type 2 (with design speed limit of 70kph) |
Road Type 3 (with design speed limit of 80kph) |
|||||
NOX |
RSP |
NOX |
RSP |
NOX |
RSP |
||
MC1 |
Petrol Private Cars (PC) & Light Goods Vehicles (LGV) |
0.1577 |
0.0072 |
0.1502 |
0.0064 |
0.1363 |
0.0040 |
MC3 |
Diesel Private Cars & Light Goods Vehicles<2.5t |
0.4284 |
0.1682 |
0.4053 |
0.1351 |
0.3898 |
0.1063 |
MC4 |
Diesel Private Cars & Light Goods Vehicles 2.5-3.5t |
0.2898 |
0.0992 |
0.2760 |
0.0798 |
0.2674 |
0.0601 |
MC5 |
Public Light Buses |
0.3121 |
0.2344 |
0.3143 |
0.2118 |
0.3258 |
0.1552 |
MC6 |
Light Goods Vehicles >3.5t |
2.3674 |
0.2024 |
2.2447 |
0.1627 |
2.1809 |
0.1217 |
MC7 |
Medium & Heavy Goods Vehicles with GVW 5.5-15t |
4.7748 |
0.3267 |
4.5221 |
0.2216 |
- |
- |
MC8 |
Medium & Heavy Goods Vehicles with GVW >=15t |
6.0139 |
0.3124 |
5.5571 |
0.1940 |
- |
- |
MC10 |
Double Deck Franchised Buses |
3.0364 |
0.1055 |
2.9914 |
0.0878 |
- |
- |
MC11 |
Motor Cycles |
1.1568 |
0.0634 |
1.2549 |
0.0617 |
- |
- |
Taxi3 |
Taxi |
0.2682 |
0.0289 |
0.2508 |
0.0244 |
0.2266 |
0.0159 |
Taxi4 |
Private Light Buses <3.5t |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
Taxi5 |
Private Light Buses >3.5t |
0.3522 |
0.2604 |
0.3530 |
0.2263 |
0.3394 |
0.1673 |
Taxi6 |
Non- franchised Buses <6.4t |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
- |
- |
Taxi7 |
Non- franchised Buses 6.4-15t |
3.9808 |
0.1882 |
3.8591 |
0.1374 |
- |
- |
Taxi8 |
Non- franchised Buses >15t |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
- |
- |
Taxi10 |
Single Deck Franchised Buses |
3.1628 |
0.2100 |
3.2206 |
0.2135 |
- |
- |
Note:
# Since there is no private light buses<3.5t, non-franchised buses <6.4t, non-franchised buses >15t travelled within the study area, the calculated emission factors for these vehicle classes are zero.
Table 3.11 Emission Factors for Year 2016 for Different Vehicle Classes (EMFAC-HK) under Congestion Traffic Condition
Vehicle Class |
Description |
Emission Factors for 2016, g/mile-veh |
|||||
Road Type 1 (with design speed limit of 50kph) |
Road Type 2 (with design speed limit of 70kph) |
Road Type 3 (with design speed limit of 80kph) |
|||||
NOX |
RSP |
NOX |
RSP |
NOX |
RSP |
||
MC1 |
Petrol Private Cars (PC) & Light Goods Vehicles (LGV) |
0.2131 |
0.0201 |
0.2132 |
0.0201 |
0.2132 |
0.0202 |
MC3 |
Diesel Private Cars & Light Goods Vehicles<2.5t |
0.6021 |
0.2956 |
0.6005 |
0.3002 |
0.6024 |
0.2984 |
MC4 |
Diesel Private Cars & Light Goods Vehicles 2.5-3.5t |
0.4191 |
0.1824 |
0.4191 |
0.1836 |
0.4190 |
0.1826 |
MC5 |
Public Light Buses |
0.4743 |
0.4807 |
0.4763 |
0.4807 |
0.4749 |
0.4901 |
MC6 |
Light Goods Vehicles >3.5t |
3.4179 |
0.3719 |
3.4178 |
0.3727 |
3.4180 |
0.3723 |
MC7 |
Medium & Heavy Goods Vehicles with GVW 5.5-15t |
7.0419 |
0.6268 |
7.0420 |
0.6269 |
- |
- |
MC8 |
Medium & Heavy Goods Vehicles with GVW >=15t |
8.6842 |
0.5648 |
8.6836 |
0.5610 |
- |
- |
MC10 |
Double Deck Franchised Buses |
5.5264 |
0.2559 |
5.5260 |
0.2563 |
- |
- |
MC11 |
Motor Cycles |
1.0151 |
0.0898 |
1.0148 |
0.0915 |
- |
- |
Taxi3 |
Taxi |
0.3833 |
0.0875 |
0.3834 |
0.0875 |
0.3834 |
0.0877 |
Taxi4 |
Private Light Buses <3.5t |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
Taxi5 |
Private Light Buses >3.5t |
0.5270 |
0.5153 |
0.5267 |
0.5159 |
0.5264 |
0.5158 |
Taxi6 |
Non- franchised Buses <6.4t |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
- |
- |
Taxi7 |
Non- franchised Buses 6.4-15t |
5.9660 |
0.3743 |
5.9657 |
0.3736 |
- |
- |
Taxi8 |
Non- franchised Buses >15t |
0.0000# |
0.0000# |
0.0000# |
0.0000# |
- |
- |
Taxi10 |
Single Deck Franchised Buses |
5.8447 |
0.5219 |
5.8422 |
0.5337 |
- |
- |
Note:
# Since there is no private light buses<3.5t, non-franchised buses <6.4t, non-franchised buses >15t travelled within the study area, the calculated emission factors for these vehicle classes are zero.
Model Assumptions for Open Road Vehicle Emission
Wind speed : 1 m/s
Wind direction : 360 wind directions
Resolution : 1°
Wind variability : 24°
Stability class : D
Surface roughness : 1 m
Mixing height : 500 m
Portal emissions from the proposed Road L1 Tunnel, Road D2 Landscape Deck, Trunk Road T2 Tunnel and tunnel section of Tseung Kwan O – Lam Tin Tunnel (near TKO/T2 interface);
Portal emissions from the existing Kai Tak Tunnel and EHC Tunnel;
Ventilation buildings for the proposed CKR and Road T2; and
Ventilation buildings for the existing Kai Tak Tunnel and EHC Tunnel.
Table 3.12 Portal and Ventilation Building Emissions
Location |
Type |
Tunnel Length |
Exhaust Height |
Ventilation Building Exhaust Velocity |
Total Emission |
|
NO2 (g/s) |
RSP (g/s) |
|||||
Road L1 (N/B & S/B) |
Portal |
243 |
- |
- |
7.308E-03 |
2.853E-03 |
Road D2 Landscape Deck (E/B & W/B) |
Portal |
214 |
- |
- |
6.668E-03 |
2.443E-03 |
Road T2 (N/B) |
Portal |
2640 |
- |
- |
7.640E-02 |
2.125E-02 |
Road T2 (S/B) |
Portal |
2640 |
- |
- |
8.848E-02 |
2.471E-02 |
Kai Tak Tunnel (E/B) |
Portal |
900 |
- |
- |
2.576E-02 |
8.910E-03 |
Kai Tak Tunnel (W/B) |
Portal |
900 |
- |
- |
3.242E-02 |
1.067E-02 |
EHC (E/B) |
Portal |
1800 |
|
|
4.516E-02 |
1.263E-02 |
TKO-LLT (E/B) |
Portal |
140 |
|
|
9.547E-03 |
2.621E-03 |
TKO-LLT (W/B) |
Portal |
140 |
|
|
1.030E-02 |
2.814E-03 |
CKR* |
Vent. Building |
1260 |
33 |
10 |
2.017E-01 |
9.072E-02 |
Road T2 Ventilation Building inside KTD site |
Vent. Building |
2640 |
24 |
10 |
1.146E-01
|
3.188E-02
|
Road T2 Ventilation Building (Kwun Tong) |
Vent. Building |
2640 |
6 |
10 |
8.848E-02 |
2.471E-02 |
Kai Tak Tunnel |
Vent. Building |
900 |
20 |
10 |
5.818E-02 |
1.958E-02 |
EHC Ventilation Building |
Vent. Building |
1800 |
17 |
2.12 |
1.054E-01 |
2.948E-02 |
Note: * The total length of tunnel section of CKR is about 3.9km long, it is assumed air emission within about 1.26km long of tunnel section would be emitted from the Ventilation Building in KTD.
the CALINE4 model was used to predict the open road emissions from the existing and planned road networks; and
the ISCST3 model was used to predict all the portal emissions and ventilation shaft emissions, chimney emissions, emission from hospital, cruise ship, proposed heliport and typhoon shelters.
Planned Landscape Deck at Road D2
Road L1 Tunnel
ASRs |
Scenario 1 (Mid 2009 to Mid 2013) |
Scenario 2 (Mid 2013 to Late 2016) |
||
Predicted 1-hr TSP conc.[1] |
Predicted 24-hr TSP conc.[2] |
Predicted 1-hr TSP conc.[1] |
Predicted 24-hr TSP conc.[2] |
|
A1 |
228 |
131 |
250 |
133 |
A2 |
163 |
117 |
165 |
116 |
A3 |
161 |
114 |
183 |
112 |
A4 |
163 |
115 |
189 |
114 |
A5 |
187 |
117 |
174 |
114 |
A6 |
170 |
111 |
188 |
118 |
A7 |
170 |
114 |
196 |
124 |
A8 |
191 |
118 |
208 |
130 |
A9 |
203 |
124 |
211 |
137 |
A10 |
218 |
125 |
224 |
139 |
A11 |
234 |
128 |
240 |
144 |
A12 |
210 |
123 |
219 |
140 |
A13 |
238 |
140 |
247 |
159 |
A14 |
267 |
161 |
280 |
169 |
A15 |
251 |
152 |
304 |
170 |
A16 |
250 |
149 |
325 |
173 |
A17 |
304 |
168 |
384 |
220 |
A18 |
212 |
133 |
267 |
166 |
A19 |
235 |
161 |
315 |
191 |
A20 |
194 |
132 |
253 |
156 |
A21 |
200 |
144 |
248 |
161 |
A22 |
174 |
128 |
218 |
144 |
A23 |
160 |
115 |
196 |
126 |
A24 |
191 |
131 |
212 |
132 |
A25 |
237 |
124 |
217 |
122 |
A26 |
234 |
139 |
211 |
117 |
A27 |
210 |
118 |
177 |
110 |
A28 |
254 |
128 |
178 |
113 |
A29 |
192 |
121 |
298 |
156 |
A30 |
219 |
114 |
308 |
134 |
A31 |
376 |
183 |
410 |
192 |
A32 |
290 |
145 |
312 |
169 |
A33 |
191 |
119 |
303 |
182 |
A34 |
190 |
118 |
326 |
170 |
A35 |
208 |
117 |
350 |
176 |
A36 |
206 |
117 |
360 |
183 |
A37 |
209 |
107 |
289 |
154 |
A38 |
193 |
104 |
245 |
139 |
A39 |
206 |
103 |
230 |
133 |
A40 |
217 |
106 |
247 |
138 |
A41 |
229 |
110 |
274 |
149 |
A42 |
236 |
113 |
291 |
156 |
A43 |
283 |
123 |
409 |
195 |
A44 |
251 |
130 |
358 |
182 |
A45 |
222 |
129 |
239 |
138 |
A46 |
222 |
121 |
245 |
143 |
A47 |
246 |
143 |
258 |
152 |
A48 |
477 |
207 |
481 |
212 |
A49 |
217 |
128 |
301 |
153 |
A50 |
212 |
115 |
245 |
135 |
A51 |
197 |
110 |
236 |
128 |
A52 |
194 |
111 |
265 |
154 |
A53 |
188 |
108 |
231 |
124 |
A54 |
182 |
107 |
204 |
114 |
A55 |
174 |
106 |
197 |
124 |
A56 |
165 |
106 |
271 |
151 |
A57 |
162 |
106 |
223 |
131 |
A58 |
163 |
106 |
220 |
127 |
A59 |
159 |
103 |
221 |
128 |
A60 |
154 |
101 |
201 |
117 |
A61 |
152 |
100 |
258 |
117 |
A62 |
157 |
101 |
202 |
126 |
A63 |
160 |
102 |
169 |
117 |
PA1(4) |
N/A |
N/A |
207 |
123 |
PA2(4) |
N/A |
N/A |
216 |
121 |
PA3(4) |
N/A |
N/A |
225 |
124 |
PA4(4) |
N/A |
N/A |
239 |
128 |
PA5(4) |
N/A |
N/A |
242 |
131 |
PA6(4) |
N/A |
N/A |
198 |
117 |
PA7(4) |
N/A |
N/A |
196 |
119 |
PA8(4) |
N/A |
N/A |
210 |
121 |
PA9(4) |
N/A |
N/A |
257 |
137 |
PA10(4) |
N/A |
N/A |
235 |
131 |
PA11(4) |
N/A |
N/A |
227 |
126 |
PA12(4) |
N/A |
N/A |
254 |
131 |
PA13(4) |
N/A |
N/A |
253 |
141 |
PA14(4) |
N/A |
N/A |
292 |
155 |
PA15(4) |
N/A |
N/A |
363 |
193 |
PA16(4) |
N/A |
N/A |
366 |
180 |
PA19(4) |
N/A |
N/A |
274 |
158 |
PA31(4) |
N/A |
N/A |
372 |
199 |
PA98(4) |
N/A |
N/A |
260 |
148 |
N/A |
N/A |
246 |
142 |
|
PA100(4) |
N/A |
N/A |
231 |
133 |
PA101(4) |
N/A |
N/A |
228 |
134 |
Table 3.14
Summary of Predicted Results
Emission Sources |
Predicted Concentration, mg/m3 |
||||
NO2 |
SO2 |
RSP |
|||
1-hr average |
24-hr average |
1-hr average |
24-hr average |
24-hr average |
|
EM1 |
72 – 190 |
68
– 106 |
N/A |
N/A |
57
– 70 |
EM |
67 – 75 |
67
– 70 |
N/A |
N/A |
57–
58 |
EM2 |
67 – 82 |
67 – 70 |
24 – 348 |
24 – 121 |
57 – 59 |
EM3 |
69 – 118 |
67 – 76 |
118 – 927
at A7, 45 – 343 at other ASRs |
27
– 177 |
57
– 61 |
EM4 |
92 – 826
at PA108-113, 86 – 253 at other ASRs |
72 – 380
at PA108-113, 72 – 109 at other ASRs |
145 – 4075
at PA108-113, 681 – 1016
at PA64*, 341 – 410 at PA64**, 110 – 674 at other ASRs |
52 – 1698
at PA108-113, 48 – 247 at other ASRs |
60 – 228
at PA108-113, 60 – 80 at other ASRs |
EM5 |
71 –169 |
68 – 84 |
27 – 105 |
24 – 38 |
57 – 66 |
EM6 |
67 – 145 |
67 – 87 |
24 – 88 |
24 – 40 |
57 – 86 |
C.I. |
114 – 835 at
PA108-113, 118 – 256 at other ASRs |
84 – 384
at PA108-113, 77
– 116 at other ASRs |
125 – 927 at A7, 145 – 4075 at
PA108-113, 681 – 1016
at PA64*, 341 – 410 at PA64**, 126 – 674 at other ASRs |
52 – 1698
at PA108-113, 53
– 247 at other ASRs |
64 – 229
at PA108-113, 61 – 91 at other ASRs |
Note:
EM1: Predicted worst-case concentration due to vehicular emissions (include open road, portals & ventilation buildings) alone
EM1a: Predicted worst-case concentration due to vehicular emissions (through Road L3) alone
EM2: Predicted worst-case concentration due to emission from the proposed hospital at Kai Tak alone
EM3: Predicted worst-case concentration due to chimney emissions from San Po Kong and Kwun Tong industrial areas alone
EM4: Predicted worst-case concentration due to cruise emissions from the proposed cruise terminal at Kai Tak alone
EM5: Predicted worst-case concentration due to typhoon shelters emissions alone
EM6: Predicted worst-case concentration due to heliport emission alone
C.I.: Predicted worst-case concentration due to cumulative Impacts from all the above emission sources
Bolded and underlined value exceeds the AQO criteria
* Predicted results for the outdoor air quality at PA64 at assessment
heights from 100m to 170m above ground.
**Predicted results for the indoor air quality at PA64 at assessment
heights from 100m to 170m above ground (see S.3.2.93 for details).
Table 3.15 Predicted NO2 Concentration Inside the Tunnel / Landscape Deck
Location |
NO2 Concentration (mg/m3) |
|
Normal traffic |
Congested traffic |
|
Road L1 tunnel (S/B & N/B) |
181 |
543 |
Road D2 (E/B & W/B) |
72 |
87 |
Tunnel Air Quality Objective |
1,800 |
1,800 |
Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission.
Misting for the dusty material should be carried out before being loaded into the vehicle.
Any vehicle with an open load carrying area should have properly fitted side and tail boards.
Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin.
The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation.
The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials.
Vehicle washing facilities should be provided at every vehicle exit point.
The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.
Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet.
Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides.
Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.
· TM on Environmental Impact Assessment Process (EIAO-TM)
· TM on Noise from Construction Work other than Percussive Piling (GW-TM)
· TM on Noise from Percussive Piling (PP-TM)
· TM on Noise from Construction Work in Designated Areas (DA-TM)
· TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM)
Table 3.16 Construction Noise Criteria for Activity other than Percussive Piling
Time Period |
Basic Noise Level (BNLs) |
||
ASR A |
ASR B |
ASR C |
|
Evening (1900 to 2300 hours) (1) |
60 |
65 |
70 |
Night (2300 to 0700 hours) |
45 |
50 |
55 |
Notes: (1) Includes Sundays and Public Holidays during daytime and evening
· 70dB(A) at the façades of residential dwellings, hotels, offices;
· 65dB(A) at the façades of schools, places of public worship, courts of law, places where unaided voice communication is required; and
· 55dB(A) at the façades of hospital or clinics.
· the predicted overall noise level from the new road, together with other traffic noise in the vicinity must be above a specified noise level (for example, 70 dB(A) for domestic premises and 65 dB(A) for educational institutions, all in L10 (1 hour)); and
· the predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level, that is, the total traffic noise level existing before the works to construct the road commence; and
· the contribution to the increase in the predicted overall noise level from the new road must be at least 1.0 dB(A).
· ‘Existing’ Roads: includes Prince Edward Road East, Kwun Tong Bypass and other existing roads around KTD.
· ‘New’ Roads: includes all new roads created and roads substantially altered in KTD.
Table 3.17 Representative Noise Sensitive Receivers for Noise Impact Assessment
NSRs |
District(1) |
Location |
Existing / Planned Land Use |
Max. Building Height, m |
Construction Phase |
Operational Phase |
N1 |
KT |
Cha Kwo Ling Tsuen |
Residential |
5 |
|
|
N2 |
KT |
Cha Kwo Ling |
Residential |
15 |
|
|
N3 |
KT |
Laguna City IV |
Residential |
81 |
|
|
N4 |
KB |
Buddhist Chi King Primary School |
Educational |
24 |
|
|
N5 |
KB |
S.K.H Kowloon Bay Kei Lok Primary School |
Educational |
27 |
|
|
N6 |
NCW |
Richland Gardens |
Residential |
99 |
|
|
N7 |
NCW |
Luk Ching House, Choi Hung Estate |
Residential |
60 |
|
|
N8 |
NCW |
Kam Pik House, Choi Hung Estate |
Residential |
21 |
|
|
N9 |
NCW |
Pik Hoi House, Choi Hung Estate |
Residential |
60 |
|
|
N10A |
SPK |
Rhythm Garden (Block 7) |
Residential |
87 |
|
|
N10B |
SPK |
Rhythm Garden (Block 9) |
Residential |
87 |
|
|
N11 |
SPK |
Cognitio College |
Educational |
18 |
|
|
N12 |
SPK |
Sir Robert Black Health Centre |
Clinic |
9 |
|
|
N13 |
SPK |
Lee Kau Yan Memorial School |
Educational |
10 |
|
|
N14 |
SPK |
South Mansion |
Residential |
15 |
|
|
N15 |
SPK |
Jenford Building |
Residential |
12 |
|
|
N16 |
KC |
Parc 22 |
Residential |
33 |
|
|
N17 |
KC |
Sky Tower |
Residential |
141 |
|
|
N18 |
KC |
HK Society for Blind hostel |
Residential |
9 |
|
|
N19 |
TKW |
Mok Cheong Street Residential District |
Residential |
18 |
|
|
N20A |
TKW |
Grand Waterfront |
Residential |
153 |
|
|
N20B |
TKW |
Grand Water Front |
Residential |
153 |
|
|
N21 |
TKW |
Hang Chien Court |
Residential |
39 |
|
|
N22 |
TKW |
Wei Chien Court |
Residential |
39 |
|
|
N23 |
TKW |
Holly Carpenter Primary School |
Educational |
18 |
|
|
N24 |
TKW |
Oblate Father’s Primary School |
Educational |
21 |
|
|
N25 |
TKW |
Sunrise Villa |
Residential |
90 |
|
|
N26 |
TKW |
Wing Kwong Street Residential District |
Residential |
21 |
|
|
N27 |
TKW |
CCC Kei To Secondary School |
Educational |
24 |
|
|
N28 |
TKW |
Po Leung Kuk Ngan Po Ling College |
Educational |
27 |
|
|
N29 |
TKW |
Sunrise Plaza |
Residential |
39 |
|
|
N30 |
TKW |
Ming Lung Street |
Residential |
7 |
|
|
N31 |
SPK |
Canossa Primary School (San Po Kong) |
Educational |
3 |
|
|
N32 |
TKW |
Holy Trinity Church |
Place of Public Worship |
3 |
|
|
PN1 |
SPK |
Rhine Harbour (Planned) |
Residential |
130 |
|
|
PN2 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN3 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN4 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN5 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN6A |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN6B |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN7A |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN7B |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN8 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN9 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN10 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN11 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN12 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN13 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN14 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN15 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN16 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN17 |
KTD |
Site 1A1 (Planned) |
Residential |
115 |
|
|
PN18 |
KTD |
Site 1A2 (Planned) |
Educational |
40 |
|
|
PN19 |
KTD |
Site 1A3 (Planned) |
Educational |
40 |
|
|
PN20 |
KTD |
Site 1A4 (Planned) |
Educational |
40 |
|
|
PN21 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN22 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN23A |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN23B |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN23C |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN24 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN25 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN26 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN27 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN28 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN29 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN30A |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN30B |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN31A |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN31B |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN32 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN33 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN34 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN35 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
|
|
PN36 |
KTD |
Site 1B2 (Planned) |
Educational |
40 |
|
|
PN37 |
KTD |
Site 1B3 (Planned) |
Educational |
40 |
|
|
PN38 |
KTD |
Site 1B4 (Planned) |
Educational |
40 |
|
|
PN39 |
KTD |
Site 1I1 (Planned) |
Residential |
95 |
|
|
PN40 |
KTD |
Site 1I1 (Planned) |
Residential |
95 |
|
|
PN41 |
KTD |
Site 1I2 (Planned) |
Residential |
95 |
|
|
PN42 |
KTD |
Site 1I2 (Planned) |
Residential |
95 |
|
|
PN43 |
KTD |
Site 1I3 (Planned) |
Residential |
95 |
|
|
PN44 |
KTD |
Site 1I3 (Planned) |
Residential |
95 |
|
|
PN45 |
KTD |
Site 1K1 (Planned) |
Residential |
105 |
|
|
PN46 |
KTD |
Site 1H2 (Planned) |
Residential |
105 |
|
|
PN47 |
KTD |
Site 1L2 (Planned) |
Residential |
95 |
|
|
PN48 |
KTD |
Site 1K3 (Planned) |
Residential |
95 |
|
|
PN49 |
KTD |
Site 1K2 (Planned) |
Residential |
105 |
|
|
PN50 |
KTD |
Site 1L2 (Planned) |
Residential |
95 |
|
|
PN51 |
KTD |
Site 1L3 (Planned) |
Residential |
45 |
|
|
PN52 |
KTD |
Site 1L3 (Planned) |
Residential |
45 |
|
|
PN53 |
KTD |
Site 1L3 (Planned) |
Residential |
95 |
|
|
PN54 |
KTD |
Site 1L1 (Planned) |
Residential |
95 |
|
|
PN55 |
KTD |
Site 2B1 (Planned) |
Residential |
105 |
|
|
PN56 |
KTD |
Site 2B1 (Planned) |
Residential |
105 |
|
|
PN57 |
KTD |
Site 2B2 (Planned) |
Residential |
95 |
|
|
PN58 |
KTD |
Site 2B3 (Planned) |
Residential |
80 |
|
|
PN59 |
KTD |
Site 2B4 (Planned) |
Residential |
80 |
|
|
PN60 |
KTD |
Site 2B5 (Planned) |
Residential |
80 |
|
|
PN61 |
KTD |
Site 2B6 (Planned) |
Residential |
80 |
|
|
PN62 |
KTD |
Site 2B6 (Planned) |
Residential |
80 |
|
|
PN63 |
KTD |
Site 4A1 (Planned) |
Residential |
60 |
|
|
PN64 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
|
|
PN65 |
KTD |
Site 5A4 (Planned) |
Residential |
60 |
|
|
PN66 |
KTD |
Site 5A4 (Planned) |
Residential |
105 |
|
|
PN67 |
KTD |
Site 5C5 (Planned) |
Educational |
40 |
|
|
PN68 |
KTD |
Site 5C6 (Planned) |
Educational |
40 |
|
|
PN69 |
KTD |
Site 1D3 (Planned) |
Community Use with hostel |
55 |
|
|
PN70 |
KTD |
Site 1D3 (Planned) |
Community Use with hostel |
55 |
|
|
PN71 |
KTD |
Site 1E1 (Planned) |
Mixed Use |
95 |
|
|
PN72 |
KTD |
Site 1E1 (Planned) |
Mixed Use |
95 |
|
|
PN73 |
KTD |
Site 1F1 (Planned) |
Mixed Use |
95 |
|
|
PN74 |
KTD |
Site 1M1 |
CDA |
35 |
|
|
PN75 |
KTD |
Site 1M2 |
CDA |
170 |
|
|
PN76 |
KTD |
Site 3B1 (Planned) |
Undesignated |
40 |
|
|
PN77 |
KTD |
Site 3B2 (Planned) |
Undesignated |
40 |
|
|
PN78 |
KTD |
Site 3B3 (Planned) |
Undesignated |
40 |
|
|
PN79 |
KTD |
Site 3B4 (Planned) |
Undesignated |
40 |
|
|
PN80 |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN80A |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN81 |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN82 |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN83 |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN84 |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN84A |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN85 |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN86 |
KTD |
Site 3C1 (Planned) |
Hospital / Clinic |
55 |
|
|
PN87A |
KTD |
Site 3E1 (Planned) |
Commercial |
95 |
|
|
PN87B |
KTD |
Site 3E1 (Planned) |
Commercial |
95 |
|
|
PN88 |
KTD |
Site 3D2 (Planned) |
Commercial |
95 |
|
|
PN89 |
KTD |
Site 3D2 (Planned) |
Commercial |
95 |
|
|
PN90 |
KTD |
Site 3D3 (Planned) |
Commercial |
95 |
|
|
PN91A |
KTD |
Site 3D4 (Planned) |
Commercial |
95 |
|
|
PN91B |
KTD |
Site 3D4 (Planned) |
Commercial |
95 |
|
|
PN92 |
KTD |
Site 3D4 (Planned) |
Commercial |
95 |
|
|
PN92A |
KTD |
Site 3D4 (Planned) facing the existing public cargo working area |
Commercial |
95 |
|
|
PN93 |
TKW |
Sung Wong Toi Road CDA site |
CDA |
95 |
|
|
PN94 |
TKW |
Sung Wong Toi Road CDA site |
CDA |
95 |
|
|
PN95 |
TKW |
Sung Wong Toi Road CDA site |
CDA |
95 |
|
|
PN96 |
KTD |
Site 2A1 (Planned) |
Commercial |
65 |
|
|
PN97 |
KTD |
Site 2A2 (Planned) |
Commercial |
65 |
|
|
PN98 |
KTD |
Site 2A3 (Planned) |
Commercial |
65 |
|
|
PN99 |
KTD |
Site 2A4 (Planned) |
Commercial |
55 |
|
|
PN100 |
KTD |
Site 2A5 (Planned) |
Commercial |
55 |
|
|
PN101 |
KTD |
Site 2A6 (Planned) |
Commercial |
55 |
|
|
PN102 |
KTD |
Site 4A2 (Planned) |
Commercial |
40 |
|
|
PN103 |
KTD |
Site 4C1 (Planned) |
Commercial |
40 |
|
|
PN104 |
KTD |
Site 4C2 (Planned) |
Commercial |
40 |
|
|
PN105 |
KTD |
Site 4C3 (Planned) |
Commercial |
40 |
|
|
PN106 |
KTD |
Site 4C4 (Planned) |
Commercial |
40 |
|
|
PN107 |
KTD |
Site 4C5 (Planned) |
Commercial |
40 |
|
|
PN108 |
KTD |
Site 4A3 (Planned) |
Commercial |
40 |
|
|
PN109 |
SPK |
Choi Hung Road CDA Site (Planned) |
CDA |
Unknown |
|
|
PN110 |
SPK |
Ex-San Po Kong Flatted Factory |
Residential |
100 |
|
|
PN111 |
SPK |
Ex-San Po Kong Flatted Factory |
Residential |
100 |
|
|
PN112 |
SPK |
Ex-San Po Kong Flatted Factory |
Residential |
100 |
|
|
Note: (1) KT – Kwun Tong; NTK – Ngau Tau Kok; KB – Kowloon Bay; NCW – Ngau Chi Wah; SPK – San Po Kong; KC – Kowloon City, TKW – To Kwa Wan; HH – Hung Hom; KTD – Kai Tak Development
· Cruise Terminal Development and related advance works
· Infrastructure works at North Apron, Phase 1 - Housing Sites and Government Offices
· Kai Tak Nullah modification works
· Infrastructure works at runway and Metro Park
· Infrastructure works at North Apron, Phase 2
· Trunk Road T2 and infrastructure works at South Apron
· SCL Construction
· CKR Construction
· Anderson Road Project, etc.
Road |
Speed limit |
Kwun Tong Bypass |
80kph |
Kwun Tong Bypass (near Richland Garden) |
70kph |
Prince Edward Road East |
70kph |
Kai Tak Airport Tunnel |
70kph |
Central Kowloon Route |
80kph |
Road T2 |
80kph |
Road D1, D2, D3 & D4 |
50kph |
Other Roads |
50kph |
· Low noise surfacing on the existing Prince Edward Road East and Kwun Tong Bypass;
· 4m high barrier along N/B of Kwun Tong Bypass and its slip road; and
· Semi-enclosures along Kwun Tong Bypass near Richland Gardens and Choi Hung Estate.
Table 3.18 Summary of Cumulative Unmitigated Construction Noise Levels at Representative NSRs During Normal Daytime Working Hours
NSR
|
Noise Criteria, dB(A)
|
Predicted Unmitigated Construction Noise Levels during Normal Daytime
Working Hour (Leq (30-min), dB(A))
|
Exceedance, dB(A)
|
N1 |
75 |
54 - 81 |
6 |
N2 |
75 |
54 - 77 |
2 |
N3 |
75 |
56 - 73 |
0 |
N4 |
65/70* |
64 - 76 |
11/6 |
N5 |
65/70* |
63 - 78 |
13/8 |
N6 |
75 |
61 - 81 |
6 |
N7 |
75 |
59 - 87 |
12 |
N8 |
75 |
58 - 81 |
6 |
N9 |
75 |
58 - 79 |
4 |
N10 |
75 |
58 - 84 |
9 |
N11 |
65/70* |
59 - 84 |
19/14 |
N12 |
75 |
60 - 84 |
9 |
N13 |
65/70* |
60 - 82 |
17/12 |
N14 |
75 |
60 - 89 |
14 |
N15 |
75 |
60 - 86 |
11 |
N16 |
75 |
59 - 78 |
3 |
N17 |
75 |
60 - 82 |
7 |
N18 |
75 |
63 - 83 |
8 |
N19 |
75 |
62 - 82 |
7 |
N20A |
75 |
61 - 76 |
1 |
N20B |
75 |
61 - 82 |
7 |
N21 |
75 |
61 - 82 |
7 |
N22 |
75 |
60 - 80 |
5 |
N23 |
65/70* |
60 - 91 |
26/21 |
N24 |
65/70* |
59 - 70 |
5/0 |
N25 |
75 |
58 - 78 |
3 |
N26 |
75 |
57 - 74 |
0 |
N27 |
65/70* |
57 - 74 |
9/4 |
N28 |
65/70* |
57 - 76 |
11/6 |
N29 |
75 |
57 - 72 |
0 |
N30 |
75 |
62 - 80 |
5 |
N31 |
65/70* |
45 - 58 |
0 |
N32 |
75 |
59 - 79 |
4 |
PN1 |
75 |
60 - 84 |
9 |
PN2 |
75 |
66 - 92 |
17 |
PN35 |
75 |
69 - 81 |
10 |
Table 3.19 Summary of Traffic Noise Impact for Other Sites within KTD area
NSR
|
Location
|
Planned Land Use
|
Major Noise Sources
|
Noise Level Above criterion,
dB(A)
|
||
70
|
65
|
55
|
||||
PN69 |
Site 1D3 |
Community Use with hostel |
Prince Edward Road East |
|
|
|
PN70 |
Site 1D3 |
Community Use with hostel |
Road D1 |
|
|
|
PN71 |
Site 1E1 |
Mixed Use |
Prince Edward Road East & Road D1 |
|
|
|
PN72 |
Site 1E1 |
Mixed Use |
Prince Edward Road East |
|
|
|
PN73 |
Site 1F1 |
Mixed Use |
Road D1 |
|
|
|
PN74 |
Site 1M1 |
CDA |
Prince Edward Road East |
|
|
|
PN75 |
Site 1M2 |
CDA |
Prince Edward Road East |
|
|
|
PN76 |
Site 3B1 |
Undesignated |
Kwun Tong Bypass & Road T2 |
|
|
|
PN77 |
Site 3B2 |
Undesignated |
Kwun Tong Bypass & Road T2 |
|
|
|
PN78 |
Site 3B3 |
Undesignated |
Kwun Tong Bypass & Road T2 |
|
|
|
PN79 |
Site 3B4 |
Undesignated |
Kwun Tong Bypass & Road T2 |
|
|
|
PN87A |
Site 3E1 |
Commercial with sensitive uses |
Lam Chak Street |
|
|
|
PN87B |
Site 3E1 |
Commercial with sensitive uses facing to Road D3 |
Road D3 & D4 |
|
|
|
PN88 |
Site 3D2 |
Commercial with sensitive uses |
Cheung Yip Street |
|
|
|
PN89 |
Site 3D2 |
Commercial with sensitive uses |
Kwun Tong Bypass |
|
|
|
PN90 |
Site 3D3 |
Commercial with sensitive uses |
Cheung Yip Street |
|
|
|
PN91A |
Site 3D4 |
Commercial with sensitive uses |
Kai Hing Road Kwun Tong Bypass |
|
|
|
PN91B |
Site 3D4 |
Commercial with sensitive uses |
Kwun Tong Bypass |
|
|
|
PN92 |
Site 3D4 |
Commercial with sensitive uses |
Kai Hing Road |
|
|
|
PN96 |
Site 2A1 |
Commercial with sensitive uses |
Prince Edward Road East & Road D1 |
|
|
|
PN97 |
Site 2A2 |
Commercial with sensitive uses |
Prince Edward Road East & Road D1 |
|
|
|
PN98 |
Site 2A3 |
Commercial with sensitive uses |
Prince Edward Road East & Road D1 |
|
|
|
PN99 |
Site 2A4 |
Commercial with sensitive uses |
Prince Edward Road East & Road D1 |
|
|
|
PN100 |
Site 2A5 |
Commercial with sensitive uses |
Prince Edward Road East & Road D1 |
|
|
|
PN101 |
Site 2A6 |
Commercial with sensitive uses |
Prince Edward Road East & Road D1 |
|
|
|
PN102 |
Site 4A2 |
Commercial with sensitive uses |
Road L12 & Road L13 |
|
|
|
PN103 |
Site 4C1 |
Commercial with sensitive uses |
Road L13 |
|
|
|
PN104 |
Site 4C2 |
Commercial with sensitive uses |
Road L13 |
|
|
|
PN105 |
Site 4C3 |
Commercial with sensitive uses |
Road L13 |
|
|
|
PN106 |
Site 4C4 |
Commercial with sensitive uses |
Road L13 |
|
|
|
PN107 |
Site 4C5 |
Commercial with sensitive uses |
Road L13 |
|
|
|
PN108 |
Site 4A3 |
Commercial with sensitive uses |
Road L12 |
|
|
|
Table 3.20 Summary of Cumulative Mitigated Construction Noise Levels at Representative NSRs During Normal Daytime Working Hours
NSR
|
Noise Criteria, dB(A)
|
Predicted Mitigated Construction
Noise Levels during Normal Daytime Working Hour (Leq (30-min)
dB(A))
|
Exceedance, dB(A)
|
Duration, Month
|
N1 |
75 |
41 - 71 |
0 |
0 |
N2 |
75 |
42 - 70 |
0 |
0 |
N3 |
75 |
43 - 67 |
0 |
0 |
N4 |
65/70* |
51 - 68 |
3/0 |
Examination Period |
N5 |
65/70* |
51 - 70 |
5/0 |
Examination Period |
N6 |
75 |
49 - 73 |
0 |
0 |
N7 |
75 |
46 - 75 |
0 |
0 |
N8 |
75 |
45 - 73 |
0 |
0 |
N9 |
75 |
45 - 71 |
0 |
0 |
N10 |
75 |
45 - 75 |
0 |
0 |
N11 |
65/70* |
47 - 75 |
10/5 |
66 include examination period |
N12 |
75 |
47 - 74 |
0 |
0 |
N13 |
65/70* |
47 - 74 |
9/4 |
66 include examination period |
N14 |
75 |
47 - 78 |
3 |
12 |
N15 |
75 |
47 - 75 |
0 |
0 |
N16 |
75 |
46 - 70 |
0 |
0 |
N17 |
75 |
47 - 75 |
0 |
0 |
N18 |
75 |
50 - 76 |
1 |
7 |
N19 |
75 |
50 - 75 |
0 |
0 |
N20A |
75 |
48 - 70 |
0 |
0 |
N20B |
75 |
48 - 78 |
3 |
60 |
N21 |
75 |
48 - 78 |
3 |
60 |
N22 |
75 |
48 - 75 |
0 |
0 |
N23 |
65/70* |
47 - 86 |
21/16 |
24 include examination period |
N24 |
65/70* |
47 - 64 |
0/0 |
0 |
N25 |
75 |
45 - 71 |
0 |
0 |
N26 |
75 |
45 - 68 |
0 |
0 |
N27 |
65/70* |
45 - 68 |
3/0 |
Examination Period |
N28 |
65/70* |
44 - 70 |
5/0 |
|
N29 |
75 |
44 - 66 |
0 |
0 |
N30 |
75 |
50 - 74 |
0 |
0 |
N31 |
60/70* |
32 - 51 |
0 |
0 |
N32 |
75 |
46 - 70 |
0 |
0 |
PN1 |
75 |
47 - 75 |
0 |
0 |
PN2 |
75 |
58 - 86 |
11 |
39 |
PN35 |
75 |
62 - 73 |
0 |
0 |
l is not higher than the noise standard; and
l has no significant contribution to the overall noise from other existing roads if the cumulative noise level (i.e. noise from the new road together with other existing roads) exceeds the noise standard.
Table 3.21 Construction Noise Residual Impacts
NSR |
Exceedance of the EIAO-TM Criterion |
Construction Activity Causing Exceedance |
Approximate duration of Exceedance |
|
65 dB(A) |
70 dB(A) |
|||
N4 |
3 (Jul 2010 to Dec 2015) |
0 |
l Local Roads L2, L3, L15 and associated footpaths at North Apron; l Local Roads L4; and SCL |
Examination Period |
N5 |
5 (Jul 2010 to Dec 2015) |
0 |
l Local Roads L2, L3, L15 and associated footpaths at North Apron; l Local Roads L4; and SCL |
Examination Period |
N11 |
10 (Sept 2009 to Apr 2010 and Jul 2010 to Dec 2015) |
5 (Jul 2010 to Dec 2015) |
l Construction of Road D1 l Local Roads L1, L2, L3, L11, L15 and associated footpaths at North Apron l Drainage, Sewerage & Watermain l Construction of Footbridge at Rhythm Garden (LW-04) l Rebuild Kai Tak Nullah l Construction of Landscape Walkway LW-02 l SCL |
66 month include examination period |
N13 |
9 (Sept 2009 to Apr 2010 and Jul 2010 to Dec 2015) |
4 (Jul 2010 to Dec 2015) |
l Construction of Road D1 l Local Roads L1, L2, L3, L11, L15 and associated footpaths at North Apron l Drainage, Sewerage & Watermain l Construction of Footbridge at Rhythm Garden (LW-04) l Construction of Landscape Walkway LW-03 l Underground Shopping Street (SB-01) l Upgrading of Pumping Station PS1 l Rebuild Kai Tak Nullah l Construction of Landscape Walkway LW-02 l SCL |
66 month include examination period |
N23 |
21 (Jan 2012 to Dec 2016) |
16 (Jan 2015 to Dec 2016) |
l Construction of Local Road L17 (Jan 2015 to Dec 2016) l CKR (Jan 2012 to Dec 2016) |
24 month include examination period |
N27 |
3 (Jan 2015 to Dec 2016) |
0 |
l Construction of local road L19 |
Examination Period |
N28 |
5 (Jan 2015 to Dec 2016) |
0 |
l Construction of local road L19 |
Examination Period |
NSR |
Exceedance of the EIAO-TM Criterion |
Construction Activity Causing Exceedance |
Approximate duration of Exceedance |
|
75 dB(A) |
||||
N14 |
2 (Jan 2015 to Dec 2015) |
l Construction of Road D1, L7, L8, L9 & L16 l Underground Shopping Street (SB-01) |
12 month |
|
N18 |
1 (Jan 2015 to July 2015) |
l SCL |
7 month |
|
N20B |
3 (Jan 2012 to Dec 2016) |
l CKR |
60 month |
|
N21 |
3 (Jan 2012 to Dec 2016) |
l CKR |
||
PN2 |
11 (Oct 2012 to Dec 2015) |
l SCL |
39 month |
· Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.
· Mobile plant, if any, should be sited as far away from NSRs as possible.
· Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.
· Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.
· Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.
l Annex 6 – Criteria for Evaluating Water Pollution
l Annex 14 – Guidelines for Assessment of Water Pollution.
Table 3.22 Summary of Water Quality Objectives for the Victoria Harbour WCZ
Parameters |
Objectives
|
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2m of the seabed |
Not less than 2.0mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0mg/l for 90% of samples |
Marine waters |
pH |
To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2 |
Marine waters |
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by human activity |
Marine waters |
Unionised ammonia (UIA) |
Annual mean not to exceed 0.021mg/l as unionised form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to exceed 0.4mg/l |
Marine waters |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
Human activity should not cause a risk to any beneficial use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality Objectives (Victoria Harbour (Phases One, Two and Three) Water Control Zone).
Table 3.23 WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes
Parameter (in mg/l unless otherwise stated) |
Target Limit |
Colour (HU) |
< 20 |
Turbidity (NTU) |
< 10 |
Threshold Odour Number (odour unit) |
< 100 |
Ammoniacal Nitrogen |
< 1 |
Suspended Solids |
< 10 |
Dissolved Oxygen |
> 2 |
Biochemical Oxygen Demand |
< 10 |
Synthetic Detergents |
< 5 |
E. coli (no. per 100ml) |
< 20,000 |
Table 3.24 Summary Statistics of Marine Water Quality in the Victoria Harbour WCZ in 2006
Parameter |
Victoria Harbour East |
Victoria Harbour Central |
WPCO WQO (in marine waters) |
|
VM2 |
VM4 |
|||
Temperature (oC) |
23.5 |
23.6 |
Not more than 2 oC in daily temperature range |
|
Salinity |
31.7 |
31.6 |
Not to cause more than 10% change |
|
Dissolved Oxygen (DO) (% Saturation) |
Depth average |
81 |
80 |
Not applicable |
Bottom |
81 |
79 |
Not applicable |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
5.8 |
5.7 |
Not less than 4 mg/l for 90% of the samples |
Bottom |
5.8 |
5.6 |
Not less than 2 mg/l for 90% of the samples |
|
pH |
7.9 |
7.9 |
6.5 - 8.5 (± 0.2 from natural range) |
|
Secchi disc Depth (m) |
2.0 |
2.0 |
Not applicable |
|
Turbidity (NTU) |
11.2 |
12.1 |
Not applicable |
|
Suspended Solids (SS) (mg/l) |
4.2 |
4.9 |
Not more than 30% increase |
|
5-day Biochemical Oxygen Demand (BOD3) (mg/l) |
0.6 |
0.7 |
Not applicable |
|
Nitrite Nitrogen (NO2-N) (mgN/l) |
0.024 |
0.024 |
Not applicable |
|
Nitrate Nitrogen (NO3-N) (mgN/l) |
0.10 |
0.11 |
Not applicable |
|
Ammonia Nitrogen (NH3-N) (mgN/l) |
0.11 |
0.13 |
Not applicable |
|
Unionised Ammonia (UIA) (mgN/l) |
0.004 |
0.004 (0.002 – 0.007) |
Not more than 0.021 mg/l for annual mean |
|
Total Inorganic Nitrogen (TIN) (mgN/l) |
0.23 |
0.26 (0.08 – 0.44) |
Not more than 0.4 mg/l for annual mean |
|
Total Nitrogen (TN) (mgN/l) |
0.42 (0.20 – 0.64) |
0.47 |
Not applicable |
|
Orthophosphate Phosphorus (PO4) (mgP/l) |
0.03 |
0.03 |
Not applicable |
|
Total Phosphorus (TP) (mgP/l) |
0.05 |
0.05 |
Not applicable |
|
Chlorophyll-a (µg/L) |
3.0 |
2.9 (1.0 – 9.2) |
Not applicable |
|
E coli (cfu/100 ml) |
1100 |
2600 |
Not applicable |
|
Faecal Coliforms (cfu/100 ml) |
2600 |
6500 |
Not applicable |
Notes:
1. Data source: EPD’s publication: “Marine Water Quality Monitoring in Hong Kong 2006”
2. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.
3. Data presented are annual arithmetic means of depth-averaged results except for E. coli and faecal coliforms that are annual geometric means.
4. Data in brackets indicate the ranges.
Table 3.25 Summary Statistics of Marine Water Quality in the Kwun Tong and To Kwa Wan Typhoon Shelters in 2006
Parameter |
WPCO WQO (in marine waters) |
|||
Temperature (oC) |
23.9 (17.5 – 28.8) |
23.5 (17.2 – 28.6) |
Not more than 2 oC in daily temperature range |
|
Salinity (ppt) |
29.3 (23.2 – 31.4)
|
30.5 (21.8 – 32.7) |
Not to cause more than 10% change |
|
Dissolved Oxygen (DO) (% saturation) |
Depth average |
68 (29 – 112) |
83 (56 – 115) |
Not applicable |
Bottom |
66 (26 – 110) |
84 (54 – 117) |
Not applicable |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
4.9 (2.0 – 7.6) |
6.0 (3.9 – 7.9) |
Not less than 4 mg/L for 90% of the samples |
Bottom |
4.7 (1.8 – 7.4) |
6.0 (3.7 – 8.0) |
Not less than 2 mg/L for 90% of the samples |
|
pH value |
7.7 (7.4 – 8.1) |
8.0 (7.7 – 8.3) |
6.5 - 8.5 (± 0.2 from natural range) |
|
Secchi disc (m) |
1.4 (1.0 – 2.0) |
1.7 (0.9 – 2.5) |
Not applicable |
|
Turbidity (NTU) |
12.7 (4.1 – 30.1) |
14.8 (9.0 – 22.1) |
Not applicable |
|
Suspended Solids (SS) (mg/l) |
2.6 (1.2 – 3.5) |
6.7 (2.4 – 20.6) |
Not more than 30% increase |
|
Silica (as SiO2) (mg/l) |
1.0 (0.4 – 1.8) |
0.7 (0.2 – 1.6) |
Not applicable |
|
5-day Biochemical Oxygen Demand (BOD3) (mg/l) |
2.2 (1.1 – 3.5) |
1.0 (0.6 – 1.6) |
Not applicable |
|
Nitrite Nitrogen (NO2-N) (mg/l) |
0.157 (0.082 – 0.227) |
0.029 (0.012 – 0.059) |
Not applicable |
|
Nitrate Nitrogen (NO3-N) (mg/l) |
0.34 (0.22 – 0.64) |
0.16 (0.05 – 0.42) |
Not applicable |
|
Ammoniacal Nitrogen (NH3-N) (mg/l) |
0.48 (0.29 – 0.65) |
0.12 (0.06 – 0.21) |
Not applicable |
|
Unionised Ammonia (UIA) (mg/l) |
0.011 (0.005 – 0.016) |
0.004 (0.002 – 0.006) |
Not more than 0.021 mg/L for annual mean |
|
Total Inorganic Nitrogen (TIN) (mg/l) |
0.97 (0.71 – 1.42) |
0.31 (0.13 – 0.54) |
Not more than 0.4 mg/L for annual mean |
|
Total Nitrogen (TN) (mg/l) |
1.33 (1.02 – 1.82) |
0.53 (0.39 – 0.80) |
Not applicable |
|
Ortho-Phosphate (PO4) (mg/l) |
0.214 (0.153 – 0.295) |
0.028 (0.007 – 0.050) |
Not applicable |
|
Total Phosphorus (TP) (mg/l) |
0.26 (0.20 – 0.36) |
0.05 (0.04 – 0.06) |
Not applicable |
|
Chlorophyll-a (µg L-1) |
18.2 (1.0 – 35.0) |
7.9 (1.0 – 20.5) |
Not applicable |
|
E. coli (cfu per 100 mL) |
9,200 (2,800 – 29,000) |
1,100 (340 – 4,400) |
Not applicable |
|
Faecal Coliforms (cfu per 100 mL) |
22,000 (4,400 – 78,000) |
2,600 (860 – 8,300) |
Not applicable |
Notes:
1. Data source: EPD’s publication: “Marine Water Quality Monitoring in Hong Kong 2006”
2. Except as specified, data presented are depth-averaged data.
3. Data presented are annual arithmetic means except for E.coli and faecal coliforms that are geometric means.
4. Data enclosed in brackets indicate ranges.
Table 3.26 Summary Statistics of 2006 River Water Quality for Kai Tak Nullah
Parameter |
EPD Monitoring Station |
|||||
KN1 (downstream) |
KN2 |
KN3 |
KN4 |
KN5 |
KN7 (upstream) |
|
DO (mg/L) |
5.9 |
6.8 |
7.6 |
8.0 |
7.9 |
7.4 |
pH |
7.1 |
7.2 |
7.4 (7.1 – 7.5) |
7.4 |
7.3 |
7.3 |
SS (mg/L) |
9 |
10 |
10 |
7 |
8 |
6 |
BOD3 (mg/L) |
7 |
3 |
2 |
3 |
3 |
3 |
COD (mg/L) |
40 |
23 |
28 |
34 |
34 |
26 |
Oil & grease (mg/L) |
0.5 |
0.5 |
0.5 |
0.5 |
0.5 |
0.5 |
Faecal coliforms (cfu/100mL) |
1,100,000 |
110,000 |
110,000 |
120,000 |
120,000 |
120,000 |
E.coli (cfu/100mL) |
580,000 |
53,000 |
39,000 |
51,000 |
47,000 |
48,000 |
NH3-N (mg/L) |
1.03 |
0.42 |
0.28 |
0.25 |
0.29 |
0.24 |
NO3-N (mg/L) |
4.7 |
5.45 |
5.90 |
5.40 |
5.40 |
5.35 |
TKN – soluble & particulate fractions (mg/L) |
2.20 |
1.45 |
1.30 |
1.20 |
1.20 |
1.30 |
Ortho-P (mg/L) |
1.75 |
1.90 |
1.95 |
1.80 |
1.75 |
1.75 |
TP – soluble & particulate fractions (mg/L) |
2.00 |
2.05 |
2.05 |
1.90 |
1.90 |
1.90 |
Sulphide – soluble and particulate fractions (mg/L) |
0.24 |
0.02 |
0.02 |
0.02 |
0.02 |
0.02 |
Aluminium (µg/L) |
50 |
50 |
50 |
50 |
50 |
50 |
Cadmium (µg/L) |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
Chromium (µg/L) |
1 (1 – 14) |
1 |
1 |
1 |
1 |
1 |
Copper (µg/L) |
9 |
7 |
8 |
7 |
7 |
9 |
Lead (µg/L) |
1 |
1 |
1 |
1 |
1 |
1 |
Zinc (µg/L) |
30 |
35 (30 – 60) |
30 |
30 |
25 |
30 |
Notes:
1. Data source: EPD’s publication: “River Water Quality Monitoring in Hong Kong 2006”
2. Data presented are annual arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
3. Data in brackets indicate the ranges.
4. Equal values for annual medians (or geometric means) and ranges indicate that all data are the same as or below laboratory reporting limits.
Table 3.27 Pollution Levels Measured at KTAC in October 2005
WQO: |
Depth-averaged Suspended Solids |
Depth-averaged Ammonia Nitrogen |
Depth-averaged E.coli |
Depth-averaged Total Inorganic Nitrogen |
Depth-averaged BOD3 |
10th Percentile Bottom DO |
10th Percentile Depth-averaged DO |
mg/L |
mg/L |
cfu/100mL |
mg/L |
mg/L |
mg/L |
mg/L |
|
NA |
NA |
NA |
0.4 |
NA |
2 |
4 |
|
25 |
0.9 |
115519 |
3.11 |
11 |
0.99 |
1.48 |
|
28 |
1.0 |
17960 |
3.21 |
10 |
0.74 |
1.18 |
|
19 |
0.9 |
60517 |
3.53 |
9 |
1.14 |
1.47 |
|
20 |
1.2 |
37857 |
3.15 |
10 |
0.93 |
1.33 |
|
21 |
1.2 |
28832 |
3.28 |
8 |
1.19 |
1.54 |
|
26 |
1.4 |
34375 |
2.76 |
9 |
0.86 |
1.41 |
|
27 |
0.8 |
15863 |
2.60 |
7 |
2.06 |
2.20 |
Bolded and shaded – Exceedance of WQO
NA – WQO is not available
Table 3.28 Pollution Levels Measured at KTAC in January 2006
WQO: |
Depth-averaged Suspended Solids |
Depth-averaged Ammonia Nitrogen |
Depth-averaged E.coli |
Depth-averaged Total Inorganic Nitrogen |
Depth-averaged BOD3 |
10th Percentile Bottom DO |
10th Percentile Depth-averaged DO |
Mg/L |
mg/L |
cfu/100mL |
mg/L |
mg/L |
mg/L |
mg/L |
|
NA |
NA |
NA |
0.4 |
NA |
2 |
4 |
|
Bolded and shaded – Exceedance of WQO
NA – WQO is not available
· contaminated ground water from any dewatering activities as a result of excavation;
· release of any bentonite slurries and other grouting materials with construction run-off, storm water or ground water dewatering process;
· wash water from dust suppression sprays and wheel washing facilities; and
· fuel, oil and lubricants from maintenance of construction vehicles and equipment.
· use of sediment traps
· adequate maintenance of drainage systems to prevent flooding and overflow.
· Waste Disposal Ordinance (Cap. 354)
· Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354)
· Land (Miscellaneous Provisions) Ordinance (Cap. 28)
· Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation
· Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)
· Estimation of the types and quantities of the wastes generated.
· Assessment of potential impacts from the management of solid waste with respect to potential hazards, air and odour emissions, noise, wastewater discharge and transport.
· Assessment of impacts on the capacity of waste collection, transfer and disposal facilities.
· C&D material
· Chemical waste
· General refuse
· Toxic effects to workers
· Adverse impacts on water quality from spills
· Fire hazards
· Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.
· Training of site personnel in proper waste management and chemical waste handling procedures.
· Provision of sufficient waste disposal points and regular collection for disposal.
· Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.
· A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites).
· Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.
· Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force.
· Any unused chemicals or those with remaining functional capacity should be recycled.
· Proper storage and site practices to minimise the potential for damage or contamination of construction materials.
· Where it is unavoidable to have transient stockpiles of C&D material within the Project work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible.
· Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric.
· Skip hoist for material transport should be totally enclosed by impervious sheeting.
· Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site.
· The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.
· The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle.
· All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.
· The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading.
Table 3.29 Summary of Locations of the New Distributor Roads
Distributor Road Section |
Location |
D1 |
Within the North Apron of the Former Kai Tak Airport |
D2 |
Within the North Apron of the Former Kai Tak Airport |
D3 |
Within the North Apron and Runway of the Former Kai Tak Airport |
D4 |
Along Cheung Yip Street (Part of the alignment encroached on the area of ex-GFS building, Radar Station and EMSD Kowloon Bay Vehicle Repair & Maintenance Workshop situated on the South Apron of the Former Kai Tak Airport) |
Table 3.30 Summary of findings in the relevant EIA reviewed
EIA reviewed |
Site Investigation Findings |
Date of Approval |
NAKTA Decommissioning EIA |
||
NAKTA Decommissioning EIA
|
l 195 boreholes and 77 groundwater wells were installed for soil and groundwater contamination assessment. l
Land Contamination hotspots were identified.
Elevated levels of methane and anaerobic conditions were found in some areas.
l
The identified contaminated areas at the NAKTA had
been cleaned up during the period from 1998 to 2007 in accordance with the
Environmental Permit conditions.
|
September 1998 EIAO Register: AEIAR-002/1998 |
CAP, CAR/RAP for South East Kowloon Development Infrastructure at North Apron Area of Kai Tak Airport
|
l Accessed areas within NAKTA which were not covered in NAKTA decommissioning project due to accessibility issue. l 134 boreholes were constructed for the purpose of land contamination assessment. l Remediation were found to be necessary at 15 borehole locations with soil samples contaminated with metals, Benzo(a)pyrene and Total Petroleum Hydrocarbons (TPH) exceeding Dutch B/C levels. Findings from groundwater risk assessment indicated that the risk level associated with groundwater during construction was acceptable and no remediation for groundwater would be necessary. Free product, identified at one of the groundwater sampling wells, however, required remediation. l Solidification / stabilization and biopiling were recommended as the remediation method for metal contaminated soil and organic contaminated soil respectively whereas free product recovery was recommended for groundwater remediation. |
CAP: June 2003 CAR/RAP: October 2005 |
Remediation Report for South East Kowloon Development Infrastructure at North Apron Area of Kai Tak Airport
|
l The Remediation works were conducted according to the CAR/RAP of South East Kowloon Development Infrastructure at North Apron Area of Kai Tak Airport under Contract No. KL39/03 approved by Environmental Protection Department (EPD), HKSAR, in 2005 l Free product found in the groundwater monitoring well was manually skimmed off. For soil remediation, cement solidification/ stabilization (CSS) was implemented for heavy metal contaminated soil and biopiling was operated for organic contaminated soil as proposed in the approved CAR/RAP. The remediation works were conducted in the period from December 2005 to March 2007. |
August 2007 |
SEKDCFS EIA |
||
SEKDCFS EIA
|
l Reviewed SEKDFS EIA and NAKTA Decommissioning EIA. l Identified Potential contamination hotspots within former Kai Tak Airport and the vicinity. |
September 2001 EIAO Register: AEIAR-044/2001 |
KTA Decommissioning EIA |
||
KTA Decommissioning EIA
|
l Reviewed and assessed the implications of land contamination associated with the former Kai Tak Airport other than the North Apron. l A total of 77 boreholes and 18 trial pits were constructed to define the nature, scale and extent of possible land contamination resulted from past and current landuses on the former Kai Tak Airport other than the North Apron. |
December 2007 EIAO Register: AEIAR-114/2007 |
CAR/RAP for the Decommissioned Fuel Pipeline and Hydrant System at South Apron of Former Kai Tak Airport
|
l 2 site investigations (SI) have been conducted. For the first SI, a total of 16 boreholes and 20 trial pits were constructed with 70 soil samples and 33 water samples collected and analysed for metal, TPH, benzene, toluene, ethylbenzene and xylenes (BTEX), polycyclic aromatic hydrocarbons (PAHs), chlorinated hydrocarbons and heavy metals. l For the further SI, a total of 2 boreholes and 1 trial pit have been set up for soil and groundwater sampling. A total of 7 soil samples and 2 groundwater samples were collected for TPH and/or BTEX analyses. l 9 soil samples from the first SI were found with metals and TPH exceeding Dutch B/C levels while no exceedance was found in the further SI. l Biopiling was proposed to treat organic contaminated soil while Solidification/ Stabilization treatment was recommended for metal contaminated soil. For soil contaminated with TPH and metals, biopiling would be processed followed by cement solidification/ stabilization. |
CAP: January 2006
CAR/RAP: December 2007
|
CAP at Runway Area (including the Narrow Strip of North Apron CAR/RAP at Runway Area and the Narrow Strip of North Apron |
l A total of 39 boreholes were constructed and a total of 107 soil samples and 33 groundwater samples were collected and analysed for a range of metals, BTEX, TPH, PAHs and halogenated and non-halogenated hydrocarbons. l 1 soil samples was found with benzo(a)pyrene exceeding the Dutch B level. l Biopiling was proposed for the organic contamination found. |
CAP: January 2007
CAR/RAP: December 2007 |
Supplementary CAP at South Apron Area of Former Kai Tak Airport (ex-GFS Apron Area), CAP, CAR/RAP at South Apron Area of Former Kai Tak Airport (ex-GFS Apron Area) |
l 20 boreholes were constructed and a total of 65 soil samples and 20 groundwater samples were collected and analysed for a range of metals, BTEX, TPH, PAHs and halogenated and non-halogenated hydrocarbons. l 11 soil samples was contaminated with metals, TPH and VOCs (ethylbenzene and xylenes) exceeding Dutch B/C level. l Floating free products were observed in 3 groundwater wells. l Biopiling was proposed to treat organic contaminated soil while Solidification/ Stabilization treatment was recommended for metal contaminated soil. l Free products were proposed to be skimmed off from the water surface, drummed properly and stored in a designated storage area for the collection by a licensed chemical waste collector for proper disposal. |
CAP: June 2007
CAR/RAP: December 2007 |
l Direct ingestion of contaminated soils through eating or drinking / smoking on site; and
l Dermal contact with contaminated soils.
Table 3.31 Summary of Soil Samples Exceeding the Dutch B/C Levels
Sample I.D. |
Depth (m BBC) |
Contaminant |
Dutch Level (mg/kg) |
Concentration (mg/kg) |
Dutch Level Exceeded |
|
B |
C |
|||||
GFSA-17 |
3.25-3.7 |
Lead |
150 |
600 |
200 |
>B |
GFSA-18 |
1 |
Phenanthrene |
10 |
100 |
14 |
>B |
Benzo(a)pyrene |
1 |
10 |
11 |
>C |
||
Fluoranthene |
10 |
100 |
19 |
>B |
||
Pyrene |
10 |
100 |
17 |
>B |
||
GFSA-20 |
1 |
Zinc |
500 |
3000 |
2000 |
>B |
GFSA-22 |
3.25-3.7 |
Copper |
100 |
500 |
150 |
>B |
GFSB-01 |
1.65 |
TPH |
1000 |
5000 |
2875 |
>B |
GFSD-03 |
1 |
Cadmium |
5 |
20 |
6 |
>B |
Lead |
150 |
600 |
480 |
>B |
||
Zinc |
500 |
3000 |
2300 |
>B |
||
3.3-3.75 |
Cadmium |
5 |
20 |
510 |
>C |
|
Nickel |
100 |
500 |
410 |
>B |
||
Cobalt |
50 |
300 |
1200 |
>C |
||
GFSD-04 |
2.2-2.65 |
Cadmium |
5 |
20 |
15 |
>B |
Lead |
150 |
600 |
430 |
>B |
||
3.2-3.65 |
Lead |
150 |
600 |
300 |
>B |
Table 3.32 Summary of Groundwater Samples Exceeding the Dutch B/C Values
Sample I.D. |
GW depth (m below ground) |
Contaminant |
Dutch Level |
Concentration (μg/L) |
Dutch Level Exceeded |
|
B |
C |
|||||
Radar Station |
||||||
RSB-01
|
2.24
|
Cadmium |
2.5 |
10 |
3.2 |
>B |
Copper |
50 |
200 |
76 |
>B |
||
Lead |
50 |
200 |
1600 |
>C |
||
Zinc |
200 |
800 |
700 |
>B |
||
Barium |
100 |
500 |
390 |
>B |
||
TPH |
200 |
600 |
2871 |
>C |
||
RSB-01A
|
2.20
|
Cadmium |
2.5 |
10 |
3.8 |
>B |
Copper |
50 |
200 |
92 |
>B |
||
Lead |
50 |
200 |
1300 |
>C |
||
Zinc |
200 |
800 |
670 |
>B |
||
Barium |
100 |
500 |
250 |
>B |
||
TPH |
200 |
600 |
259 |
>B |
||
RSB-02 |
2.18 |
Lead |
50 |
200 |
410 |
>C |
Zinc |
200 |
800 |
310 |
>B |
||
Barium |
100 |
500 |
170 |
>B |
||
TPH |
200 |
600 |
435 |
>B |
||
RSB-07 |
2.24 |
Lead |
50 |
200 |
210 |
>C |
Zinc |
200 |
800 |
210 |
>B |
||
RSB-08 |
2.28 |
Lead |
50 |
200 |
450 |
>C |
Zinc |
200 |
800 |
510 |
>B |
||
Barium |
100 |
500 |
640 |
>C |
||
TPH |
200 |
600 |
250 |
>B |
||
Phenanthrene |
2 |
10 |
2.3 |
>B |
||
Ex-GFS Building |
||||||
GFSA-17 |
2.62 |
Mercury |
0.5 |
2 |
1.2 |
>B |
Molybdenum |
20 |
100 |
31 |
>B |
||
TPH |
200 |
600 |
231 |
>B |
||
GFSA-18 |
2.58 |
Lead |
50 |
200 |
77 |
>B |
Zinc |
200 |
800 |
250 |
>B |
||
Molybdenum |
20 |
100 |
21 |
>B |
||
Barium |
100 |
500 |
150 |
>B |
||
TPH |
200 |
600 |
327 |
>B |
||
GFSA-19 |
2.54 |
Lead |
50 |
200 |
72 |
>B |
Molybdenum |
20 |
100 |
39 |
>B |
||
Barium |
100 |
500 |
120 |
>B |
||
GFSA-20 |
2.73 |
Barium |
100 |
500 |
110 |
>B |
GFSA-21 |
2.53 |
Chromium |
50 |
200 |
64 |
>B |
Lead |
50 |
200 |
590 |
>C |
||
Zinc |
200 |
800 |
420 |
>B |
||
Barium |
100 |
500 |
610 |
>C |
||
GFSA-22 |
2.68 |
Chromium |
50 |
200 |
57 |
>B |
Lead |
50 |
200 |
130 |
>B |
||
Zinc |
200 |
800 |
250 |
>B |
||
Barium |
100 |
500 |
220 |
>B |
||
GFSD-01 |
2.69 |
Copper |
50 |
200 |
55 |
>B |
Lead |
50 |
200 |
550 |
>C |
||
Zinc |
200 |
800 |
480 |
>B |
||
Barium |
100 |
500 |
340 |
>B |
||
TPH |
200 |
600 |
365 |
>B |
||
GFSD-02 |
2.83 |
Cadmium |
2.5 |
10 |
2.7 |
>B |
Copper |
50 |
200 |
59 |
>B |
||
Lead |
50 |
200 |
2100 |
>C |
||
Zinc |
200 |
800 |
1000 |
>C |
||
Barium |
100 |
500 |
680 |
>C |
||
GFSD-03 |
2.63 |
Cadmium |
2.5 |
10 |
27 |
>C |
Lead |
50 |
200 |
240 |
>C |
||
Zinc |
200 |
800 |
470 |
>B |
||
Cobalt |
50 |
200 |
200 |
>B |
||
Barium |
100 |
500 |
650 |
>C |
||
TPH |
200 |
600 |
740 |
>C |
||
GFSD-04 |
2.31 |
Cadmium |
2.5 |
10 |
3 |
>B |
Lead |
50 |
200 |
320 |
>C |
||
Zinc |
200 |
800 |
290 |
>B |
||
Barium |
100 |
500 |
160 |
>B |
||
TPH |
200 |
600 |
369 |
>B |
Table 3.33 Evaluation of Significance of Risk Due to Groundwater Contamination
Receptor |
Significance of Risk due to Groundwater Contamination |
Rationale |
Construction workers for decommissioning / decontamination works (by ingestion) |
Significant |
Existence of potential risk. |
Construction workers for decommissioning / decontamination works (by inhalation) |
Insignificant |
Decommissioning and decontamination works would be located in the outdoor area. Also, it is recommended that personal protective equipment (PPE) should be used by site workers as a mitigation measures. |
Construction workers for decommissioning / decontamination works (by dermal contact) |
Uncertain |
Toxicity and / or chemical specific data do not exist for the COCs for risk assessment to be undertaken. As such, it is recommended that personal protective equipment (PPE) be used by site workers as a mitigation measure. |
Future land users |
Insignificant |
As most of the contamination in the site would be removed after the decontamination works, the soil quality would be within Dutch B level and the groundwater contamination would be much reduced. In addition, the site will be covered by filling materials / concrete. Groundwater at the site will not be used as potable water or used for recreation / irrigation purposes. |
Future construction workers |
Insignificant |
Contaminated soil is considered as the major contributor for elevated COCs in the groundwater. As most of the contamination in the site would be removed after the decontamination works, the soil quality would be within Dutch B level and the contaminants in groundwater would be much reduced. |
Table 3.34 Maximum Source Concentrations and Non-carcinogenic Oral Reference Doses / Carcinogenic Oral Slope Factors of Chemicals of Concern
Parameter |
Source Concentration |
Sample I.D. |
Noncarcinogenic Oral Reference Dosea (RfDo) |
Minimum Noncarcinogenic Oral Reference Dosea (RfDo) |
Carcinogenic Oral Slope Factorb (CSFo) |
[mg/L] |
[mg/kg-day] |
[mg/kg-day] |
1/[mg/kg-day] |
||
TPHs |
2.871 |
RSB-01 |
0.03 to 5.00 |
0.03 |
Not applicable |
Barium |
0.68 |
GFSD-02 |
0.07 |
Not applicable |
Not applicable |
Cadmium |
0.027 |
GFSD-03 |
0.0005 |
Not applicable |
Not applicable |
Chromium* |
0.064 |
GFSA-21 |
0.003 |
Not applicable |
Not applicable |
Cobalt |
0.2 |
GFSD-03 |
0.02 |
Not applicable |
Not applicable |
Copper |
0.092 |
RSB-01A |
0.04 |
Not applicable |
Not applicable |
Lead |
2.1 |
GFSD-02 |
0.0036 |
Not applicable |
Not applicable |
Phenanthrene |
0.0023 |
RSB-08 |
0.04 |
Not applicable |
Not applicable |
Mercury |
0.0012 |
GFSA-17 |
0.0003 |
Not applicable |
Not applicable |
Molybdenum |
0.039 |
GFSA-19 |
0.005 |
Not applicable |
Not applicable |
Xylenes |
0.03 |
All** |
0.2 |
Not applicable |
Not applicable |
Zinc |
1 |
GFSD-02 |
0.3 |
Not applicable |
Not applicable |
Remarks:
a Source for TPHs : TPH Criteria Working Group, 1999. Total Petroleum Hydrocarbons Criteria Working Group Series Volume 5 – Human Health Risk-Based Evaluation of Petroleum Release Sites: Implementing the Working Group Approach. Massachusetts, U.S.A., Amherst Scientific Publishers.
Source for Ba, Cd, Cr, Co, Cu, Hg, Mo, Zn, Phenanthrene and Xylene:USEPA Region IX Risk-based Concentration Table (revised on Oct 04), USEPA Region IX.
Source for Pb: The value is referenced to the tolerable daily intake (TDI) from the National Institute of Public Health and the Environment (RIVM), The Netherlands, 2001.
b Source for TPHs, Ba, Cd, Cr, Co, Cu, Hg, Mo, Zn, Phenanthrene and Xylene: USEPA Region IX Risk-based Concentration Table (revised on Oct 04), USEPA Region IX.
** All sampling locations showed the same concentrations for Xylenes (i.e. 30ug/L as the Dutch B level).
* Chromium is assumed to be Cr(VI) as conservative assessment.
Soil Contamination
Estimation of Soil Contamination Extent
Table 3.35 Location, Depth and Estimated Quantity of Contaminated Soil
Zone I.D. |
Sample I.D. |
Depth (m BBC) |
Contaminant |
Concentration |
Estimated Contamination Extent |
||||
Vertical |
Horizontal |
Estimated Volume (m3) |
|||||||
Exceedances found in the soil samples collected below 0m to 1m BBC |
|||||||||
A |
GFSA-18 |
1 |
Phenanthrene |
14 |
0.5-1.5 |
36 |
36 |
||
Benzo(a)pyrene |
11 |
||||||||
Fluoranthene |
19 |
||||||||
Pyrene |
17 |
||||||||
B |
GFSA-20 |
1 |
Zinc |
2000 |
0.5-1.5 |
36 |
36 |
||
C |
GFSD-03 |
1 |
Cadmium |
6 |
0.5-1.5 |
36 |
36 |
||
Lead |
480 |
||||||||
Zinc |
2300 |
||||||||
Exceedances found in the soil samples collected below 1m to 6m BBC |
|||||||||
D |
GFSB-01 |
1.65 |
TPH |
2875 |
1.15-2.15 |
36* |
36 |
|
|
E |
GFSD-04 |
2.2-2.65 |
Cadmium |
15 |
1.7-4.15 |
36 |
88.2 |
|
|
Lead |
430 |
|
|||||||
3.2-3.65 |
Lead |
300 |
|
||||||
F |
GFSA-17 |
3.25-3.7 |
Lead |
200 |
2.75-4.2 |
36 |
52.2 |
|
|
G |
GFSA-22 |
3.25-3.7 |
Copper |
150 |
2.75-4.2 |
36 |
52.2 |
|
|
H |
GFSD-03 |
3.3-3.75 |
Cadmium |
510 |
2.8-4.25 |
36 |
52.2 |
|
|
Nickel |
410 |
|
|||||||
Cobalt |
1200 |
|
|||||||
Total Volume of Estimated Contaminated Soil=388.8m3 |
|||||||||
|
|
|
|
|
|
|
|
|
|
BBC= Below Base of Existing Concrete Pavement
^The actual volume may be different and is subject to confirmatory sampling and testing to be conducted during the course of proposed remediation processes
* Due to space constraint within the D.G. Store, 6m X 6m square centred at GFSB-01 may not be feasible. The frame for excavation would have to be adjusted on site based on the actual site condition.
Table 3.36 Estimated Quantity of Different Type of Contaminated Soil
Land |
Contaminants |
|
Metals Only |
TPH/SVOCs |
|
Ex-GFS building |
316.8 m3 |
72 m3 |
Radar Station |
Nil |
Nil |
Total |
316.8 m3 |
72 m3 |
Note: The actual volume may be different and is subject to confirmatory sampling and testing to be conducted during the course of proposed remediation processes.
Table 3.37 Summary of Reviewed Information on Potential Contaminative Land Uses
Potentially
Contaminative Uses
|
Location
|
Historical
Land Uses
|
Possible/Potential
Sources of Contamination
|
EMSD Kowloon Bay Vehicle
Maintenance Workshop
|
Cheung Yip Street
|
l 1959 Open Sea
l 1967: Vacant
l 1973: Warehouse
l 1975: Vacant
l 1982: Workshop identified
|
l Mineral oil, flammable liquid, solvent, paint, oily sludge, acidic
electrolyte and heavy metal compound have been used, stored or generated in
the workshop.
|
· Antiquities and Monuments Ordinance
· Environmental Impact Assessment Ordinance
· Hong Kong Planning Standards and Guidelines
· Technical Memorandum on Environmental Impact Assessment Process
· Criteria for Cultural Heritage Impact Assessment
· To excavate, carry on building works, plant or fell trees or deposit earth or refuse on or in a proposed monument or monument
· To demolish, remove, obstruct, deface or interfere with a proposed monument or monument
High:
|
Important
landscape or landscape resource of particularly distinctive character or high
importance, sensitive to relatively small changes.
|
Medium:
|
Landscape
or landscape resource of moderately valued landscape characteristics
reasonably tolerant to change.
|
Low:
|
Landscape
or landscape resource, the nature of which is largely tolerant to change.
|
Large:
|
The
landscape or landscape resource would suffer a major change.
|
Intermediate:
|
The
landscape or landscape resource would suffer a moderate change.
|
Small:
|
The
landscape or landscape resource would suffer slight or barely perceptible
changes.
|
Negligible:
|
The
landscape or landscape resource would suffer no discernible change.
|
Table 3.38 Relationship between Receptor Sensitivity and Impact Magnitude in Defining Impact Significance
Magnitude of Impact ((Both Adverse and Beneficial Impact are accessed.)) |
Large |
Slight / Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight / Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial / Slight |
Slight / Moderate |
Slight / Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
|
Receptor Sensitivity (of Landscape Resource, Landscape Character Area or VSRs) |
The sensitivity of VSRs is classified as follows:
High:
|
The VSR is
highly sensitive to any change in their viewing experience.
|
Medium:
|
The VSR is
moderately sensitive to any change in their viewing experience.
|
Low:
|
The VSR is only
slightly sensitive to any change in their viewing experience.
|
The magnitude of visual impacts is classified as follows:
Large:
|
The VSRs would
suffer a major change in their viewing experience.
|
Intermediate:
|
The VSRs would
suffer a moderate change in their viewing experience.
|
Small:
|
The VSRs would
suffer a small change in their viewing experience.
|
Negligible:
|
The VSRs would
suffer no discernible change in their viewing experience.
|
The significance of visual impacts is categorized as follows:
Substantial:
|
Adverse
/ beneficial impact where the proposal would cause significant deterioration
or improvement in existing visual quality.
|
Moderate:
|
Adverse
/ beneficial impact where the proposal would cause a noticeable deterioration
or improvement in existing visual quality.
|
Slight:
|
Adverse
/ beneficial impact where the proposal would cause a barely perceptible
deterioration or improvement in existing visual quality.
|
Insubstantial:
|
No
discernible change in the existing visual quality.
|
Table 3.39 Landscape Resources / Landscape Character Areas and Their Sensitivity to Change
ID. No. |
Landscape Resources / Landscape Characters |
Sensitivity to Change (Low, Medium, High) |
Existing Landscape Resources |
||
LR01 |
Olympic Garden This is a public local open space (~ 0.7ha) at the west end of the PERE and located under existing flyover network of Kowloon City, containing seating areas and planting beds. It is a popular resting and gathering place for local residents. Ornamental tree and shrub planting are provided throughout the open space. There are more than 100 trees with height around 4-13 m, spread 2-10 m, trunk diameter 120-500 mm. Species include Bauhinia blakeana, Callistemon viminalis, Chrysalidocarpus lutescens, Ficus microcarpa, Lagerstroemia speciosa and Roystonea regia. |
High |
LR02 |
Sung Wong Toi Garden This is a formal public open space (~ 0.4ha) where the Emperor’s Rock is kept comprising formal clipped hedgerows and screen tree planting along the periphery of the open space. There are approximately 30 mature trees with height around 4-8 m, spread 3-10 m, trunk diameter 150-700 mm. Species include Aleurites moluccana, Casuarina equisetifolia, Ficus microcarpa, Livistona chinensis and Macaranga tanarius. |
High |
LR03 |
Sung Wong Toi Playground This is a public open space (~ 0.9ha) comprising basketball courts, meandering footpaths, seating areas and ornamental tree and shrub planting. There are more than 100 trees with height around 4-13 m, spread 2-8 m, trunk diameter 120-450 mm. Species include Bauhinia blakeana, Bombax ceiba, Casuarina equisetifolia, Delonix regia and Ficus virens var. sublanceolata. |
High |
LR04A |
Rest Garden near Nga Tsin Wai Road The Rest Garden is a local open space (~ 0.2ha) with lush trees and shrub planting. It consists of children’s play equipment and seating areas under tree shade primarily for passive recreation. There are approximately 10 mature trees with height around 4-8 m, spread 2-10 m, trunk diameter 300-750 mm. Species include Aleurites moluccana and Ficus microcarpa. |
High |
LR04B |
Amenity area near Sha Po Road The amenity area consists of 26 trees of medium size and amenity value. The height of trees is around 5-6 m, spread 3 m, trunk diameter 150-200 mm. The species are mostly Bauhinia blakeana. |
Medium |
LR05 |
Shek Ku Lung Road Playground This is an open space (~1.4ha) with predominantly hard surface primarily for active recreation provision. Five-a-side football pitches and tennis courts are the main elements in the open space. Seating areas are also provided. There are more than 330 trees with height around 4-9 m, spread 3-8 m, trunk diameter 150-600mm. Species include Acacia confusa, Ailanthus fordii, Bauhinia blakeana, Bombax ceiba, Cassia surattensis, Delonix regia, Erythrina variegata, Ficus microcarpa, Macaranga tanarius, Melaleuca quinquenervia, Michelia x alba and Plumeria rubra. |
High |
LR06 |
Argyle Street Playground This is an open space (~ 0.8ha) with predominantly hard surface primarily for active recreation provision. Football pitches are the main elements in the open space. Seating areas are also provided at the northern side of the playground. There are approximately 20 trees with height around 4-7 m, spread 3-10 m, trunk diameter 180-400 mm. Species include Delonix regia and Lagerstroemia speciosa. |
High |
LR07 |
Trees in the Amenity Areas near Kai Fuk Road There are approximately 760 trees found in the Amenity Areas near Kwun Tong Road with height around 4-5 m, spread 2 m, trunk diameter 100-180 mm. The amenity value of these trees is considered as medium. Predominant species consist of Acacia confusa, Celtis sinensis, Casuarina equisetifolia, Ficus microcarpa, Hibiscus tiliaceus, Macaranga tanarius and Melaleuca quinquenervia. |
Medium |
LR08 |
Kai Tak East Playground This is an open space (~ 1.4ha) with an indoor playground and predominantly hard surface for active recreation provision. There is an indoor game hall at the southeast of the playground. Football pitches and basketball courts are the main elements in this open space. Seating areas are provided along both sides of these pitches. There are 40 trees primarily along the periphery of the open space. Some trees are mature. The height of trees is around 3-11 m, spread 2-9 m, trunk diameter 100-600 mm. Species include Acacia confusa, Ailanthus fordii, Aleurites moluccana, Bauhinia blakeana, Bombax ceiba, Delonix regia, Ficus microcarpa and Melaleuca quinquenervia. |
High |
LR09 |
To Kwa Wan Recreation Ground This is an open space (~ 2.8ha) with predominantly hard surface primarily for active recreation provision. There are approximately 150 trees in these amenity areas with height around 3-13 m, spread 2-7 m, trunk diameter 120-500 mm. Species include Aleurites moluccana, Araucaria heterophylla, Bauhinia blakeana, Chrysalidocarpus lutescens, Juniperus chinensis cv. Kaizuca, Macaranga tanarius, Michelia x alba and Roystonea regia. |
High |
LR11 |
Kowloon Walled City Park and Carpenter Road Park Kowloon Walled City Park is a one of the most historic sites in Kowloon. It is a regional open space (~ 3.3ha) in early Qing Dynasty style. The park consists of a mix of active and passive recreation in a tree and shrub landscape setting. It is a popular park for local residents and tourists. There are more than 350 trees of high amenity value with height around 4-10 m, spread 2-8 m, trunk diameter 200-700 mm. Species include Aleurites moluccana, Bauhinia blakeana, Bombax ceiba, Delonix regia, Ficus microcarpa, Juniperus chinensis cv. Kaizuca, Lagerstroemia speciosa, Macaranga tanarius, Melaleuca quinquenervia, Michelia x alba and Roystonea regia. Carpenter Road Park is a regional open space (~ 5.4 ha). The park provides active recreation with cycle track and passive recreation in a tree and shrub landscape setting. There are more than 150 trees of high amenity value with height around 4-8 m, spread 2-8 m, trunk diameter 200-500 mm. Predominate species include Aleurites moluccana, Ficus microcarpa, Juniperus chinensis cv. Kaizuca and Roystonea regia. |
High |
LR17 |
Trees near Aviation Club Buildings There are approximately 32 mature trees at the periphery of the development boundary along Song Wong Toi Road with height around 4-13 m, spread 3-7 m, trunk diameter 180-350 mm. The amenity value of these trees is considered as high. Predominant species consist of Aleurites moluccana, Casuarina equisetifolia, Delonix regia, Ficus microcarpa, Macaranga tanarius and Morus alba. |
High |
LR18 |
Trees at the periphery of existing lot boundary along Sung Wong Toi Road There are approximately 10 semi-mature/mature trees at the periphery of the existing lot boundary along Sung Wong Toi Road with height around 3-9 m, spread 3-10 m, trunk diameter 200-500 mm. The amenity value of these trees is considered as medium. Predominant species consist of Bauhinia blakeana, Delonix regia, Ficus microcarpa, Macaranga tanarius, Michelia x alba and Phoenix roebelenii. |
Medium |
LR19 |
Trees in the Amenity Areas along Sung Wong Toi Road There are approximately 19 trees found in the Amenity Areas near the Ventilation Building of the Airport Tunnel along Sung Wong Toi Road with height around 3-12 m, spread 2-8 m, trunk diameter 150-500 mm. Predominant species consist of Acacia confusa, Aleurites moluccana, Bauhinia blakeana, Ficus microcarpa and Phoenix roebelenii. |
Medium |
LR20 |
Trees in Amenity Areas of the interchange near Kwun Tong Road There are approximately 30 trees found in the Amenity Areas near Kwun Tong Road with height around 4-9 m, spread 3-5 m, trunk diameter 120-300 mm. The amenity value of these trees is considered as medium. Predominant species consist of Aleurites moluccana, Bauhinia blakeana, Bombax ceiba, Casuarina equisetifolia Ficus microcarpa, Leucaena leucocephala, Macaranga tanarius and Melaleuca quinquenervia. |
Medium |
LR21 |
Existing trees along the runway There are more than 830 trees along runway. All the trees are immature mostly with height around 2-7 m, spread 1-4 m, trunk diameter 100-250 mm. The amenity value of these trees is considered as low. Species include Casuarina equisetifolia, Chrysalidocarpus lutescens, Eucalyptus citriodora, Ficus benjamina, Ficus microcarpa, Hibiscus tiliaceus and Macaranga tanarius. |
Low |
LR22 |
Trees in Amenity Areas near the Interchange in Kowloon Bay There are more than 510 existing trees in the amenity areas near the interchange in Kowloon Bay with height around 4-13 m, spread 2-7 m, trunk diameter 150-350 mm. The amenity value of these trees is considered as medium. Predominant species are Aleurites moluccana, Bauhinia blakeana, Casuarina equisetifolia, Leucaena leucocephala and Melaleuca quinquenervia. |
Medium |
LR23 |
Trees in Amenity Areas of San Po Kong Interchange There are approximately 38 trees in the amenity areas of San Po Kong Interchange with height around 4-8 m, spread 2-5 m, trunk diameter 150-300 mm. The amenity value of these trees is considered as medium. Species include Ailanthus fordii, Callistemon viminalis, Cycas revoluta, Erythrina variegata, Lagerstroemia speciosa, Livistona chinensis and Phoenix roebelenii. |
Medium |
LR24 |
Trees in Amenity Area near Rhythm Garden There are approximately 30 trees in the amenity area adjacent to the internal road of Rhythm Garden with height around 4-8 m, spread 3-7 m, trunk diameter 150-400 mm. The amenity value of these trees is considered as medium. Predominant species include Acacia confusa, Aleurites moluccana, Bombax ceiba, Caryota ochlandra, Casuarina equisetifolia, Delonix regia, Eucalyptus robusta, Ficus altissima, Ficus elastica, Ficus microcarpa, Lagerstroemia speciosa and Melaleuca quinquenervia. |
Medium |
LR25 |
Trees near Grand Waterfront There are approximately 30 mature trees in the amenity areas near Grand Waterfront of height around 4-7 m, spread 3-7 m, trunk diameter 150-350 mm. The amenity value of these trees is considered as high. The species are mostly Bombax ceiba and Melaleuca quinquenervia. |
High |
LR26 |
Trees in Amenity Areas of Choi Hung Road PTI There are approximately 20 mature trees in the amenity planting beds and tree pits (~ 0.2ha) in the PTI. The height of trees is around 4-13 m, spread 3-10 m, trunk diameter 200-550 mm. The amenity value of these trees is considered as medium. Predominant species consist of Acacia confusa, Bombax ceiba, Callistemon viminalis, Casuarina equisetifolia, Delonix regia, Ficus microcarpa, Ficus virens and Macaranga tanarius. |
Medium |
LR27 |
Trees in planned open space near Rhythm Garden There are approximately 73 mature trees in the planned open space adjacent to Rhythm Garden with height around 4-10 m, spread 2-7 m, trunk diameter 150-450 mm. Some of the existing trees are found dead. In general, the amenity value of these trees is considered as medium. Predominant species consist of Bombax ceiba, Delonix regia, Cassia surattensis, Casuarina equisetifolia, Ficus elastica and Macaranga tanarius. |
Medium |
LR28 |
Trees in North Apron of Former Airport There are more than 500 trees in the amenity areas and on the podium near Kai Tak Government Building with height around 3-12 m, spread 2-6 m, trunk diameter 150-400 mm. The amenity value of these trees is considered as medium. Predominant species consist of Aleurites moluccana, Archontophoenix alexandrae, Bauhinia blakeana, Caryota ochlandra, Cassia siamea, Delonix regia, Ficus microcarpa, Livistona chinensis and Phoenix roebelenii. |
Medium |
LR29 |
Hoi Bun Road Park This is an open space (~ 1.2ha) in the context of the surrounding industrial areas. Tree and shrub planting and sitting out area are provided. There are around 120 trees of common species with height around 3-11 m, spread 2-7 m, trunk diameter 200-350 mm. Predominant species include Acacia confusa, Aleurites moluccana, Bauhinia variegata, Caryota ochlandra, Delonix regia, Ficus microcarpa, Livistona chinensis and Melaleuca quinquenervia. A few of the trees are mature but most are of small to medium size. |
High
|
LR31A |
Kai Tak Nullah An open drainage channel running through the centre of the site with littlie landscape value. |
Low
|
LR31B |
Victoria Harbour It is a recognised and distinctive feature of Hong Kong worldwide, both as a tourist attraction and working port. The Harbour forms a centrepiece of the Hong Kong setting, with the airport runway forming a unique coastline to it. |
High |
Planned Landscape Resources |
||
LR32 |
Planned Runway Park It is a planned regional open space with an aviation theme next to the Cruise Terminal at Tourism and Leisure Hub. |
High |
LR33 |
Planned Metro Park It is a planned regional open space at the heart of KTD which connects the Sports Hub and Runway Princint. |
High |
LR34 |
Planned Multi-purpose Stadium Complex Plaza It is a planned landscape plaza at the Multi-purpose Stadium Complex which connect the Kai Tak City Centre and the Metro Park. |
High |
LR35 |
Planned Sung Wong Toi Park It is a planned district open space with an Sung Dynasty Theme at the Sports Hubs close to the hinterland. |
High |
LR36 |
Planned Station Square It is a planned open plaza outside the Kai Tak Station which interacts the commencial and residential uses at the Kai Tak City Centre. |
High |
LR38 |
Planned Chinese Cultural Garden It is a planned open space along the waterfront at Ma Tau Kok forms part of waterfront promenade at KTD. |
High |
LR39 |
Planned Promenade It is a planned waterfront open space forms a promenade from Ma Tau Kok to Cha Kwo Ling. |
High |
Existing Landscape Character Areas |
||
LCA01 |
Former Kai Tak Airport Landscape Character Area This comprises the former Kai Tak Airport where the future development is to be located. This area is flat, open, primarily hard standing with a few existing buildings that relate to the use of the former airport at the north. The area is currently occupied by various parties for different temporary uses. |
Low |
LCA02 |
Kowloon City and To Kwa Wan Grid Mixed Urban Landscape This is an area of primarily mixed residential / commercial use. This comprises a mix of low to high buildings for residential and commercial uses. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
LCA03 |
Kowloon Bay Late 20C / Early 21C Commercial / Residential Complex Landscape This is an area of primarily mixed residential / commercial use. This comprises a mix of low to high buildings for residential, commercial uses. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
LCA04 |
San Po Kong Industrial Urban Landscape This is an area of industrial use. This comprises medium rise industrial buildings. Some of the low rise industrial buildings have been demolished for future development. The Planning Consultancy Study for San Po Kong Flatted Factory is under studied. The streetscape is utilitarian with no soft landscape treatment. |
Low |
LCA05 |
Kwun Tong Industrial Urban Landscape This is an area of industrial use. This comprises medium to high rise industrial buildings. The streetscape is utilitarian with no soft landscape treatment. |
Low |
LCA06 |
Kowloon City and Choi Hung Residential Urban Landscape This is an area of residential use. This comprises a mix of low to high rise buildings for residential uses. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
LCA08 |
Kwun Tong Typhoon Shelter Landscape This is an area for typhoon shelter use in Kwun Tong. It is substantially enclosed by coast and offshore breakwater. |
Low |
LCA09 |
To Kwa Wan Typhoon Shelter Landscape This is an area for typhoon shelter use in To Kwa Wan. It is substantially enclosed by coast and offshore breakwater. |
Low |
LCA11 |
Victoria Harbour Inshore Water Landscape This is an area of coastal water lying close to the shore and enclosed to a certain degree by landmasses or islands, which create a limited sense of enclosure or containment. Whilst the landscape is characterized predominantly by horizontality and muted hues of the coastal water, it also includes may marine activities of all kinds, including anchorages, commercial shipping lanes and ferry traffic. The result is a largely open, natural landscape which is punctuated by colours and noises of human features and activities. |
High |
LCA12 |
Kowloon City Medium / High-rise Commercial Urban Landscape This is an area predominantly of commercial, industrial and retail land uses. This comprises a mix of medium and high rise buildings. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
Planned Landscape Character Areas (Within KTD) |
||
LCA01A |
Planned Kai Tak City Centre Urban Landscape It is a new Kai Tak urban centre with a mixture of residential and commercial uses. The existing Kai Tak Nullah will be turned into a ‘river’ which it brings a natural element into the new modern city; and with natural landscape and plaza zone, the railway station shall be intended to locate in a park-like area. |
Medium |
LCA01B |
Planned Kai Tak Sports Hub Urban Landscape The Main Stadium will be the new icon of South East Kowloon. It will provide great views out to the water for spectators seated in the stadium. Programming along the dedicated pedestrian walkways within the landscape deck connecting across Road D2 shall enhance connectivity between spaces. Large open areas around stadiums shall act as a plaza-like for gathering and holding difference functions. |
Medium |
LCA01C |
Planned Kai Tak Metro Park Urban Landscape It consists of a 27ha Metro Park at the centre of South East Kowloon – both geographically and psychologically. Anchored by the Multi-purpose Stadium Complex at the northern base of the runway, this new landscape character area will be the signature public open space of South East Kowloon. |
High |
LCA01D |
Planned Kai Tak Runway Precinct Urban Landscape It is a unique new ulinear harbourfront district with hotels and residential developments defined by the Runway Itself with water at the both sides. |
Medium |
LCA01E |
Planned Kai Tak South Apron Corner Urban Landscape It is a planned sub-district within KTD with GIC developments in an urban grid pattern. It is characterized by continuous linear waterfront promenade along the area. |
Medium |
LCA01F |
Planned Tourism and Leisure Hub Urban Landscape It is a planned Tourism and Leisure Hub with Cruise Terminal, Shopping and Entertainment Destination and Runway Park. The Tourism and Leisure Hub, with its landmark architectural design, will serve as a waterfront tourist destination with a variety of attractions for both local residents and visitors. |
Medium |
Table 3.40 Visual Sensitive Receivers (VSRs) and Their Sensitivity to Change
VSR Type & ID. |
Key Visually Sensitive Receiver (VSR) |
Number of Individuals (Many/ Medium/ Few/) |
Quality of Existing View (Good/ Fair/ Poor) |
Availability of Alternative Views (Yes/ No) |
Average Distance between VSRs and Impact Source (m) |
Degree of Visibility (Full/ Partial/ Glimpse) |
Duration of View (Long/ Medium/ Short) |
Frequency of View (Frequent/ Occasional/ Rare) |
Sensitivity to Change (Low, Medium, High) |
||
Existing VSRs at Local Level |
|||||||||||
Sky Tower and adjacent residential developments along Sung Wong Toi Road |
Medium |
Fair |
No |
20m |
Full |
Long |
Frequent |
High |
|||
R2 |
Medium-rise Residential Development along Ma Tau Chung Road |
Medium |
Fair |
No |
200m |
Full |
Long |
Frequent |
High |
||
R3 |
Regal Oriental Hotel and Low to Medium-rise Residential Development in Kowloon City |
Many |
Fair |
No |
100m |
Full |
Long |
Frequent |
High |
||
R5 |
Medium-rise Residential Development in San Po Kong |
Many |
Fair |
No |
100m |
Full |
Long |
Frequent |
High |
||
R6 |
Rhythm Garden |
Many |
Fair |
No |
40m |
Full |
Long |
Frequent |
High |
||
R7 |
Choi Hung Estate |
Many |
Fair |
No |
80m |
Full |
Long |
Frequent |
High |
||
R9 |
Richland Gardens |
Many |
Fair |
No |
60m |
Partial |
Long |
Frequent |
High |
||
R12 |
Residential Development in To Kwa Wan |
Many |
Fair |
yes |
200m |
Partial |
Long |
Frequent |
High |
||
R14 |
Laguna Verde and Whampoa Garden |
Many |
Fair |
Yes |
1200m |
Full |
Long |
Frequent |
Medium |
||
R16 |
Grand Waterfront (same planned use under KTD) |
Medium |
Fair |
Yes |
100m |
Full |
Long |
Frequent |
High |
||
R17 |
Wyler Gardens |
Many |
Fair |
Yes |
200m |
Partial |
Long |
Frequent |
High |
||
R18 |
Low-rise Residential Development adjacent to Grand Waterfront (same planned use under KTD) |
Medium |
Fair |
Yes |
100m |
Partial |
Long |
Frequent |
High |
||
R19 |
R(A) zone at King Fuk Street |
Medium |
Fair |
No |
100m |
Full |
Long |
Frequent |
High |
||
R20 |
R(A) zone to the southeast of Tung Tau Estate |
Medium |
Fair |
No |
150m |
Full |
Long |
Frequent |
High |
||
R21 |
Le Billionaire and adjacent R(A) Zone in Kowloon City |
Medium |
Fair |
No |
110m |
Full |
Long |
Frequent |
High |
||
R22 |
Low-Rise Residential Development along Mok Cheong Street (planned CDA in operation stage) |
Medium |
Fair |
No |
200m |
Full |
Long |
Frequent |
High |
||
R23 |
Harbourfront Landmark |
Medium |
Good |
Yes |
1500m |
Full |
Long |
Frequent |
Medium |
||
C2 |
Harbour Plaza and Harbourfront |
Many |
Good |
Yes |
1500m |
Full |
Medium |
Occasional |
Medium |
||
C4 |
Newport Centre (planned residential use under KTD) |
Medium |
Fair |
Yes |
100m |
Full |
Medium |
Frequent |
Medium – Construction Stage ( High- Operation Stage) |
||
Evangel Hospital, Christian Alliance P.C. Lau Memorial International School, Notre Dame College, Holy Trinity Primary School, HK Planning Association Centre |
Medium |
Fair |
Yes |
150m |
Partial |
Medium |
Occasional |
Medium |
|||
GIC2 |
Ng Wah College, Lee Kau Yan Memorial School, Sir Robert Black Health Centre, Petrol Station |
Medium |
Fair |
No |
40m |
Full |
Medium |
Occasional |
Medium |
||
GIC3 |
Cognitio College |
Medium |
Fair |
No |
40m |
Full |
Medium |
Occasional |
Medium |
||
GIC5 |
Kai Tak Operation Base and Existing Electricity Substation (same planned uses under KTD) |
Few |
Fair |
No |
20m |
Full |
Medium |
Occasional |
Medium (construction stage only) |
||
GIC6 |
EMSD Headquarter (same planned uses under KTD) |
Few |
Fair |
No |
20m |
Full |
Medium |
Occasional |
Medium (construction stage only) |
||
GIC9 |
Kowloon Bay Vehicle Inspection Centre, Vehicle Examination Centre, Water Supplies Department Kowloon East Regional Building, Kowloon Bay Transfer Station, Kowloon Bay Government Land Transport Agency Transport Pool |
Few |
Fair |
No |
20m |
Partial |
Medium |
Occasional |
Medium |
||
GIC10 |
Kei To Secondary School, Po Leung Kuk Ngan Po Ling College |
Medium |
Good |
No |
1000m |
Partial |
Medium |
Occasional |
Medium |
||
GIC12 |
Kowloon Bay Vehicle Servicing Station, Public Works Central Laboratory Building (planned GIC use and open space under KTD) |
Medium |
Fair |
No |
10m |
Partial |
Medium |
Occasional |
Medium (construction stage only) |
||
GIC13 |
To Kwa Wan Sewage Treatment Works |
Few |
Fair |
No |
1000m |
Partial |
Medium |
Occasional |
Low |
||
GIC14 |
Holy Carpenter Primary School and Oblate Father’s Primary School (same planned uses under KTD) |
Medium |
Fair |
No |
600m |
Partial |
Medium |
Occasional |
Medium |
||
GIC15 |
To Kwa Wan Motor Vehicle Inspection Centre and the adjacent cargo working area along Long Yuet Street (planned open space under KTD) |
Medium |
Fair |
No |
500m |
Partial |
Medium |
Occasional |
Medium |
||
GIC18 |
EMSD Workshops (planned sewage pumping station and open space under KTD) |
Medium |
Fair |
No |
50m |
Full |
Long |
Occasional |
High |
||
GIC20 |
Tai Wan Salt Water Pumping Station |
Few |
Good |
Yes |
1500m |
Partial |
Medium |
Occasional |
Low |
||
GIC21 |
Police Operational Facility at Dyer Avenue |
Few |
Fair |
Yes |
1500m |
Full |
Medium |
Occasional |
Low |
||
GIC22 |
Kowloon City Ferry Pier and bus terminal (planned ventilation shafts and waterfront promenade under KTD) |
Few |
Fair |
No |
1500m |
Full |
Short |
Occasional |
Low |
||
GIC23 |
Kwun Tong Public Pier, Kwun Tong Ferry Pier Square and adjacent bus terminal (same planned use under KTD) |
Medium |
Fair |
No |
700m |
Full |
Long |
Occasional |
Medium |
||
GIC25 |
Hong Kong Society for the Blind Factory (planned CDA in operation stage) |
Medium |
Fair |
No |
10m |
Full |
Long |
Frequent |
High |
||
O1 |
Visitors at Olympic Garden |
Medium |
Fair |
No |
100m |
Full |
Short |
Occasional |
Medium |
||
O2 |
Visitors at Sung Wong Toi Garden |
Medium |
Fair |
No |
100m |
Full |
Short |
Occasional |
High |
||
O3 |
Visitors at Sung Wong Toi Playground |
Medium |
Fair |
No |
100m |
Full |
Short |
Occasional |
High |
||
O4 |
Visitors at Rest Garden next to Nga Tsin Wai Road |
Medium |
Fair |
No |
100m |
Full |
Short |
Occasional |
High |
||
O5 |
Visitors at Shek Ku Lung Road Playground |
Medium |
Fair |
No |
60m |
Full |
Short |
Occasional |
High |
||
O6 |
Visitors at Argyle Street Playground |
Medium |
Fair |
No |
100m |
Partial |
Short |
Occasional |
High |
||
O7 |
Visitors at King Wan Street Playground (same planned use under KTD) |
Medium |
Fair |
No |
600m |
Partial |
Short |
Occasional |
Medium |
||
O13 |
Visitors at Hoi Sham Park (same planned use under KTD) |
Medium |
Fair |
No |
700m |
Partial |
Short |
Occasional |
Medium |
||
O14 |
Visitors at Hoi Bun Road Park |
Medium |
Fair |
Yes |
700m |
Glimpse |
Short |
Occasional |
Low |
||
O17 |
Visitors at Tai Wan Shan Park & Tai Wan Shan Swimming Pool |
Many |
Fair |
Yes |
1500m |
Partial |
Short |
Occasional |
Low |
||
I1 |
Industrial Buildings in San Po Kong (planned residential use in operation stage) |
Many |
Poor |
No |
40m |
Full |
Long |
Occasional |
Medium – Construction Stage High – Operation Stage |
||
I2 |
Industrial buildings along Yuk Yat Street (planned residential use in operation stage) |
Many |
Fair |
No |
500m |
Full |
Long |
Frequent |
Medium |
||
I4 |
Industrial Development along Mok Cheong Street (planned CDA in operation stage) |
Medium |
Poor |
No |
400m |
Full |
Long |
Occasional |
Low – Construction Stage High – Operation Stage |
||
I5 |
Industrial/Office Developments and Godowns at Cheung Yip Street (planned commercial use under KTD) |
Medium |
Fair |
Yes |
300m |
Partial |
Medium |
Occasional |
Medium |
||
OU1 |
Tunnel Administration Building (same planned use under KTD) |
Few |
Fair |
No |
10m |
Full |
Long |
Occasional |
Medium |
||
OU2 |
Business and Industrial Developments in Kowloon Bay (planned commercial use in operation stage) |
Many |
Fair |
No |
20m |
Full |
Long |
Occasional |
Medium |
||
OU3 |
Business and Industrial Developments in San Po Kong (planned commercial use in operation stage) |
Many |
Poor |
Yes |
40m |
Full |
Long |
Occasional |
Medium |
||
OU4 |
Business and Industrial Developments in Hung Hom (planned commercial use in operation stage) |
Medium |
Fair |
No |
1000m |
Full |
Long |
Occasional |
Medium |
||
OU5 |
Business and Industrial Developments in Kwun Tong (planned commercial use in operation stage) |
Many |
Fair |
No |
500m |
Full |
Long |
Occasional |
Medium |
||
OU6 |
Hong Kong International Trade and Exhibition Centre (same planned use under KTD) |
Many |
Good |
No |
0m |
Full |
Medium |
Occasional |
Medium |
||
T1 |
Motorists on Prince Edward Road East |
Many |
Fair |
Yes |
20m |
Full |
Short |
Occasional |
Low |
||
T2 |
Motorists on carriageway and Pedestrians on Footpaths along Sung Wong Toi Road |
Many |
Fair |
Yes |
20m |
Full |
Short |
Occasional |
Low |
||
T3 |
Motorists on Kwun Tong Bypass |
Many |
Fair |
Yes |
20m |
Full |
Short |
Occasional |
Low |
||
T4 |
Travelers of Harbour Traffic |
Many |
Fair |
Yes |
200m |
Full |
Medium |
Occasional |
Medium |
||
Planned VSRs at Local Level |
|||||||||||
R23P |
Planned Residential Developments at Site 1A and 1B |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Frequent |
High |
||
R24P |
Planned Residential Developments at Site 1H, II, 1J, IK, IL, and 2A |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Frequent |
High |
||
R25P |
Planned Residential Development at Site 4B |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Frequent |
High |
||
C7P |
Planned Commercial Developments at Site 2A |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
||
C8P |
Planned Commercial Developments at Site 4C |
Many |
Fair |
Yes |
50m |
Full |
Medium |
Occasional |
Medium |
||
C9P |
Planned Cruise Terminal and Tourism Related Uses at Site 2 and 3 |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
High |
||
GIC25P |
Planned GIC Developments at Site 3B, 3C |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
||
GIC26P |
Planned GIC Developments at Site 1C, 1D |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
||
GIC27P |
Planned GIC Developments at Site 2C |
Medium |
Fair |
Yes |
20m |
Partial |
Medium |
Occasional |
Medium |
||
GIC28P |
Planned GIC Developments at Site 2A |
Medium |
Fair |
Yes |
20m |
Partial |
Medium |
Occasional |
Medium |
||
GIC29P |
Planned GIC Developments at Site 1A |
Medium |
Fair |
Yes |
20m |
Partial |
Medium |
Occasional |
Medium |
||
GIC30P |
Planned GIC Developments at Site 1B |
Many |
Fair |
Yes |
10m |
Glimpse |
Medium |
Occasional |
Low |
||
GIC31P |
Planned GIC Developments at Site 1N |
Medium |
Fair |
Yes |
20m |
Partial |
Medium |
Occasional |
Medium |
||
CDA2P |
Planned CDA Developments at Kai Tak City Centre |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
||
O19P |
Planned Runway Park |
Many |
Fair |
Yes |
20m |
Full |
Medium |
Occasional |
High |
||
O20P |
Planned Metro Park |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
High |
||
O21P |
Planned Multi-purpose Stadium Complex |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
High |
||
O22P |
Planned Sung Wong Toi Park |
Many |
Fair |
Yes |
20m |
Partial |
Medium |
Occasional |
High |
||
O23P |
Planned Station Square |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
High |
||
O24P |
Planned Open Space at Site 3E |
Many |
Fair |
Yes |
200m |
Partial |
Medium |
Occasional |
High |
||
O25P |
Planned Promenade at Runway Precinct |
Many |
Fair |
Yes |
10m |
Partial |
Medium |
Occasional |
High |
||
OU6P |
Planned OU Development (Mixed Use) at Site 1E |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
High |
||
OU7P |
Planned OU Development at Site 1D |
Few |
Fair |
Yes |
10m |
Partial |
Medium |
Occasional |
Low |
||
|
|
|
|
|
|
|
|
|
|
|
|
C = Commercial, C/R = Commercial/Residential, GIC = Government/Institution/Community, I = Industrial, O = Open space, OU = Other use, R = Residential, T = Transport related.
Table 3.41 Significant Landscape Impacts of the Proposed Works during Construction Phase
Table 3.42 Significance of Landscape Impacts in Construction and Operation Phases (All impact are adverse unless otherwise stated beneficial.)
ID. No. |
Landscape Resources / Landscape Characters |
Sensitivity to Change (Low, Medium, High) |
Magnitude of Change (Negligible, Small, Intermediate, Large) |
Impact Significance Threshold BEFORE Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold AFTER Mitigation (Insubstantial, Slight, Moderate, Substantial) |
|||||||
Construction |
Operation |
||||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|
DAY 1 |
YEAR 10 |
|||||
Existing Landscape Resources |
|||||||||||||
LR01 |
Olympic Garden |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR02 |
Sung Wong Toi Garden |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR03 |
Sung Wong Toi Playground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR04A |
Rest Garden and amenity area near Nga Tsin Wai Road |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR04B |
Amenity area near Sha Po Road |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR05 |
Shek Ku Lung Road Playground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR06 |
Argyle Street Playground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR07 |
Trees in the Amenity Areas near Kai Fuk Road |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1, CM2, |
Slight |
Slight |
Slight |
||
LR08 |
Kai Tak East Playground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR09 |
To Kwa Wan Recreation Ground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR11 |
Kowloon Walled City Park and Carpenter Road Park |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR17 |
Trees near Aviation Club Buildings |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR18 |
Trees at the periphery of existing lot boundary along Sung Wong Toi Road |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR19 |
Trees in the Amenity Areas along Sung Wong Toi Road |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR20 |
Trees in Amenity Areas of the interchange near Kwun Tong Road |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR21 |
Existing trees along the runway |
Low |
Low |
Intermediate |
Intermediate |
Slight |
Slight |
CM1, CM2, |
Slight |
Slight |
Slight |
||
LR22 |
Trees in Amenity Areas near the Interchange in Kowloon Bay |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR23 |
Trees in Amenity Areas of San Po Kong Interchange |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR24 |
Trees in Amenity Area of Rhythm Garden |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR25 |
Trees near Grant Waterfront |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR26 |
Trees in Amenity Areas of Choi Hung Road PTI |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR27 |
Trees in planned open space near Rhythm Garden |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR28 |
Trees in North Apron of Former Airport |
Medium |
Medium |
Large |
Large |
Moderate |
Moderate |
CM1, CM2, |
Slight |
Slight |
Slight |
||
LR29 |
Hoi Bun Road Park |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR31A |
Kai Tak Nullah |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR31B |
Victoria Harbour |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
Planned Landscape Resources |
|||||||||||||
LR32 |
Planned Runway Park |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR33 |
Planned Metro Park |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR34 |
Planned Multi-purpose Stadium Complex |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR35 |
Planned Sung Wong Toi Park |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR36 |
Planned Station Square |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR38 |
Planned Chinese Cultural Garden |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR39 |
Planned Promenade |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
Landscape Character Areas During Construction and Operation Phase |
|||||||||||||
LCA01 |
Former Kai Tak Airport Landscape Character Area (KTD in Operation Phase) |
Low |
High |
Large |
Negligible |
Moderate |
Insubstantial |
CM1 to CM4, |
Slight |
Insubstantial |
Insubstantial |
||
LCA02 |
Kowloon City and To Kwa Wan Grid Mixed Urban Landscape |
Medium |
Medium |
Small |
Negligible |
Slight |
Insubstantial |
CM1 to CM4 |
Slight |
Insubstantial |
Insubstantial |
||
LCA03 |
Kowloon Bay Late 20C / Early 21C Commercial / Residential Complex Landscape |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1 to CM4 |
Slight |
Insubstantial |
Insubstantial |
||
LCA04 |
San Po Kong Industrial Urban Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1 to CM4 |
Slight |
Insubstantial |
Insubstantial |
||
LCA05 |
Kwun Tong Industrial Urban Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1 to CM4 |
Slight |
Insubstantial |
Insubstantial |
||
LCA06 |
Kowloon City and Choi Hung Residential Urban Landscape |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
CM1 to CM4 |
Slight |
Insubstantial |
Insubstantial |
||
LCA08 |
Kwun Tong Typhoon Shelter Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LCA09 |
To Kwa Wan Typhoon Shelter Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LCA11 |
Victoria Harbour Inshore Water Landscape |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LCA12 |
Kowloon City Medium / High-rise Commercial Urban Landscape |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
Planned LCA |
|||||||||||||
LCA01A |
Planned Kai Tak City Centre Urban Landscape |
High |
Medium |
Small |
Negligible |
Moderate |
Insubstantial |
CM1 to CM4, |
Slight |
Moderate (Beneficial) |
Substantial (Beneficial) |
||
LCA01B |
Planned Kai Tak Sports Hub Urban Landscape |
- |
Medium |
- |
- |
- |
- |
OM1 to OM5 |
- |
- |
Substantial (Beneficial) |
||
LCA01C |
Planned Kai Tak Metro Park Urban Landscape |
- |
High |
- |
- |
- |
- |
OM1 to OM5 |
- |
- |
Substantial (Beneficial) |
||
LCA01D |
Planned Kai Tak Runway Precinct Urban Landscape |
- |
Medium |
- |
- |
- |
- |
OM1 to OM5 |
- |
- |
Substantial (Beneficial) |
||
LCA01E |
Planned Kai Tak South Apron Corner Urban Landscape |
- |
Medium |
- |
- |
- |
- |
OM1 to OM5 |
- |
- |
Substantial (Beneficial) |
||
LCA01F |
Planned Tourism and Leisure Hub Urban Landscape |
High |
Medium |
Small |
Small |
Moderate |
Slight |
CM1 to CM4, |
Slight |
Moderate (Beneficial) |
Substantial (Beneficial) |
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: It is assumed that during the construction phase of DP1, part of the development in LCA01A and LCA01F will be completed. The impact on these areas due to DP1 during construction is assessed.
Table 3.43 Significance of Visual Impacts in the Construction and Operation Phases (Note: All impacts adverse unless otherwise noted
VSR Type & ID. |
Key Visually Sensitive Receiver (VSR) |
Main Source of Visual Impact |
Magnitude of Impact (Negligible, Small, Intermediate, Large) |
Receptor Sensitivity (Low, Medium, High) |
Impact Significance Threshold Before Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold After Mitigation (Insubstantial, Slight, Moderate, Substantial) |
|||||
Construction |
Operation |
|||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
DAY 1 |
YEAR 10 |
|||||
VSRs at Local Level |
||||||||||||
R1 |
Sky Tower and adjacent residential developments along Sung Wong Toi Road |
DP1 |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
R2 |
Medium-rise Residential Development along Ma Tau Chung Road |
DP1 |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
R3 |
Regal Oriental Hotel and Low to Medium-rise Residential Development in Kowloon City |
DP1 |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
R5 |
Medium-rise Residential Development in San Po Kong |
DP1 |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Insubstantial |
R6 |
Rhythm Garden |
DP1 |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Insubstantial |
R7 |
Choi Hung Estate |
DP1 |
Small |
- |
High |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
R9 |
Richland Gardens |
DP1 |
Small |
- |
High |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
R12 |
Residential Development in To Kwa Wan |
DP1 |
Small |
- |
High |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
R14 |
Laguna Verde and Whampoa Garden |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
R16 |
Grand Waterfront (same planned use under KTD) |
DP1 |
Small |
Small |
High |
High |
Moderate |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Insubstantial |
R17 |
Wyler Gardens |
DP1 |
Small |
- |
High |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
R18 |
Low-rise Residential Development adjacent to Grand Waterfront (same planned use under KTD) |
DP1 |
Small |
Small |
High |
High |
Moderate |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
R19 |
R(A) zone at King Fuk Street |
DP1 |
Small |
Intermediate |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight |
R20 |
R(A) zone to the southeast of Tung Tau Estate |
DP1 |
Small |
Small |
High |
High |
Moderate |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight |
R21 |
Le Billionaire and adjacent R(A) Zone in Kowloon City |
DP1 |
Small |
Small |
High |
High |
Moderate |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight |
R22 |
Low-Rise Residential Development along Mok Cheong Street (planned CDA in operation stage) |
DP1 |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight (Beneficial) |
R23 |
Harbourfront Landmark |
DP1 |
Small |
- |
High |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
C2 |
Harbour Plaza and Harbourfront |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
C4 |
Newport Centre (planned residential use under KTD) |
DP1 |
Small |
Small |
Medium |
High |
Slight |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight (Beneficial) |
GIC1 |
Evangel Hospital, Christian Alliance P.C. Lau Memorial International School, Notre Dame College, Holy Trinity Primary School, HK Planning Association Centre |
DP1 |
Small |
Negligible |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Insubstantial |
GIC2 |
Ng Wah College, Lee Kau Yan Memorial School, Sir Robert Black Health Centre, Petrol Station |
DP1 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight |
Cognitio College |
DP1 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight |
|
GIC5 |
Kai Tak Operation Base and Existing Electricity Substation (same planned uses under KTD) |
DP1 |
Intermediate |
- |
Medium |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
GIC6 |
EMSD Headquarter (same planned uses under KTD) |
DP1 |
Intermediate |
- |
Medium |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
GIC9 |
Kowloon Bay Vehicle Inspection Centre, Vehicle Examination Centre, Water Supplies Department Kowloon East Regional Building, Kowloon Bay Transfer Station, Kowloon Bay Government Land Transport Agency Transport Pool |
DP1 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
Kei To Secondary School, Po Leung Kuk Ngan Po Ling College |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
|
GIC12 |
Kowloon Bay Vehicle Servicing Station, Public Works Central Laboratory Building (planned GIC use and open space under KTD) |
DP1 |
Intermediate |
- |
Medium |
- |
Moderate |
- |
CM3, CM4 |
Slight |
- |
- |
GIC13 |
To Kwa Wan Sewage Treatment Works |
DP1 |
Small |
- |
Low |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
GIC14 |
Holy Carpenter Primary School and Oblate Father’s Primary School (same planned uses under KTD) |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
GIC15 |
To Kwa Wan Motor Vehicle Inspection Centre and the adjacent cargo working area along Long Yuet Street (planned open space under KTD) |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
GIC18 |
EMSD Workshops (planned sewage pumping station and open space under KTD) |
DP1 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight |
GIC20 |
Tai Wan Salt Water Pumping Station |
DP1 |
Small |
- |
Low |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
GIC21 |
Police Operational Facility at Dyer Avenue |
DP1 |
Small |
- |
Low |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
GIC22 |
Kowloon City Ferry Pier and bus terminal (planned ventilation shafts and waterfront promenade under KTD) |
DP1 |
Small |
- |
Low |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
GIC23 |
Kwun Tong Public Pier, Kwun Tong Ferry Pier Square and adjacent bus terminal (same planned use under KTD) |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
GIC25 |
Hong Kong Society for the Blind Factory (planned CDA in operation stage) |
DP1 |
Intermediate |
Large |
Medium |
Medium |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Moderate |
Slight |
Slight (Beneficial) |
O1 |
Visitors at Olympic Garden |
DP1 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
O2 |
Visitors at Sung Wong Toi Garden |
DP1 |
Large |
Intermediate |
High |
High |
Substantial |
Moderate |
CM3, CM4, OM1 to OM5 |
Moderate |
Slight |
Slight (Beneficial) |
O3 |
Visitors at Sung Wong Toi Playground |
DP1 |
Large |
Intermediate |
High |
High |
Substantial |
Moderate |
CM3, CM4, OM1 to OM5 |
Moderate |
Slight |
Slight (Beneficial) |
O4 |
Visitors at Rest Garden next to Nga Tsin Wai Road |
DP1 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Insubstantial |
O5 |
Visitors at Shek Ku Lung Road Playground |
DP1 |
Intermediate |
Intermediate |
High |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight (Beneficial) |
O6 |
Visitors at Argyle Street Playground |
DP1 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Insubstantial |
O7 |
Visitors at King Wan Street Playground (same planned use under KTD) |
DP1 |
Negligible |
- |
Medium |
- |
Insubstantial |
- |
CM3, CM4 |
Slight |
- |
- |
O13 |
Visitors at Hoi Sham Park (same planned use under KTD) |
DP1 |
Negligible |
- |
Medium |
- |
Insubstantial |
- |
CM3, CM4 |
Slight |
- |
- |
O14 |
Visitors at Hoi Bun Road Park |
DP1 |
Small |
- |
Low |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
O17 |
Visitors at Tai Wan Shan Park & Tai Wan Shan Swimming Pool |
DP1 |
Small |
- |
Low |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
I1 |
Industrial Buildings in San Po Kong (planned residential use in operation stage) |
DP1 |
Intermediate |
Intermediate |
Medium |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
I2 |
Industrial buildings along Yuk Yat Street (planned residential use in operation stage) |
DP1 |
Small |
- |
Low |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
I4 |
Industrial Development along Mok Cheong Street (planned CDA in operation stage) |
DP1 |
Substantial |
Intermediate |
Low |
High |
Moderate |
Moderate |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight (Beneficial) |
I5 |
Industrial/Office Developments and Godowns at Cheung Yip Street (planned commercial use under KTD) |
DP1 |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM3, CM4 |
Slight |
Slight |
Slight (Beneficial) |
OU1 |
Tunnel Administration Building (same planned use under KTD) |
DP1 |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM3, CM4 |
Slight |
Insubstantial |
Slight (Beneficial) |
OU2 |
Business and Industrial Developments in Kowloon Bay (planned commercial use in operation stage) |
DP1 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Insubstantial |
OU3 |
Business and Industrial Developments in San Po Kong (planned commercial use in operation stage) |
DP1 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Slight |
Slight |
OU4 |
Business and Industrial Developments in Hung Hom (planned commercial use in operation stage) |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4, OM1 to OM5 |
Slight |
- |
- |
OU5 |
Business and Industrial Developments in Kwun Tong (planned commercial use in operation stage) |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4, OM1 to OM5 |
Slight |
- |
- |
OU6 |
Hong Kong International Trade and Exhibition Centre (same planned use under KTD) |
DP1 |
Small |
Small |
Medium |
Medium- |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
T1 |
Motorists on Prince Edward Road East |
DP1 |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
T2 |
Motorists on carriageway and Pedestrians on Footpaths along Sung Wong Toi Road |
DP1 |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
T3 |
Motorists on Kwun Tong Bypass |
DP1 |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM3, CM4, OM1 to OM5 |
Slight |
Insubstantial |
Slight (Beneficial) |
T4 |
Travelers of Harbour Traffic |
DP1 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Slight |
- |
- |
Planned VSR |
||||||||||||
R23P |
Planned Residential Developments at Site 1A and 1B |
DP1 |
- |
Intermediate |
- |
High |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Insubstantial |
R24P |
Planned Residential Developments at Site 1H, II, 1J, IK, IL, and 2A |
DP1 |
- |
Intermediate |
- |
High |
- |
Moderate |
OM1 to OM5 |
- |
Slight |
Slight (Beneficial) |
R25P |
Planned Residential Development at Site 4B |
DP1 |
- |
Intermediate |
- |
High |
- |
Moderate |
OM1 to OM5 |
- |
Slight |
Slight (Beneficial) |
C7P |
Planned Commercial Developments at Site 2A |
DP1 |
- |
Intermediate |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
C8P |
Planned Commercial Developments at Site 4C |
DP1 |
- |
Intermediate |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Slight |
Slight (Beneficial) |
C9P |
Planned Cruise Terminal and Tourism Related Uses at Site 2 and 3 |
DP1 |
- |
Intermediate |
- |
High |
- |
Moderate |
OM1 to OM5 |
- |
Slight |
Slight |
GIC25P |
Planned GIC Developments at Site 3B, 3C |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
GIC26P |
Planned GIC Developments at Site 1C, 1D |
DP1 |
- |
Intermediate |
- |
Medium |
- |
Moderate |
OM1 to OM5 |
- |
Slight |
Slight (Beneficial) |
GIC27P |
Planned GIC Developments at Site 2C |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
GIC28P |
Planned GIC Developments at Site 2A |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
GIC29P |
Planned GIC Developments at Site 1A |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
GIC30P |
Planned GIC Developments at Site 1B |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
GIC31P |
Planned GIC Developments at Site 1N |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
CDA2P |
Planned CDA Developments at Kai Tak City Centre |
DP1 |
- |
Intermediate |
- |
Medium |
- |
Moderate |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
O19P |
Planned Runway Park |
DP1 |
- |
Small |
- |
High |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight |
O20P |
Planned Metro Park |
DP1 |
- |
Small |
- |
High |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight |
O21P |
Planned Multi-purpose Stadium Complex |
DP1 |
- |
Small |
- |
High |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight |
O22P |
Planned Sung Wong Toi Park |
DP1 |
- |
Small |
- |
High |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight |
O23P |
Planned Station Square |
DP1 |
- |
Small |
- |
High |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
O24P |
Planned Open Space at Site 3E |
DP1 |
- |
Intermediate |
- |
High |
- |
Moderate |
OM1 to OM5 |
- |
Slight |
Slight |
O25P |
Planned Promenade at Runway Precinct |
DP1 |
- |
Intermediate |
- |
Medium |
- |
Moderate |
OM1 to OM5 |
- |
Slight |
Slight (Beneficial) |
OU6P |
Planned OU Development (Mixed Use) at Site 1E |
DP1 |
- |
Small |
- |
High |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Slight (Beneficial) |
OU7P |
Planned OU Development at Site 1D |
DP1 |
- |
Small |
- |
Low |
- |
Slight |
OM1 to OM5 |
- |
Insubstantial |
Insubstantial |
C = Commercial, C/R = Commercial/Residential, GIC = Government/Institution/Community, I = Industrial, O = Open space, OU = Other use, R = Residential, T = Transport related.
Table 3.44 Landscape and Visual Mitigation Measures during Construction Phase
ID No. |
Landscape and Visual Mitigation Measure |
Funding Agency |
Implementation Agency |
CM11 |
All existing trees should be carefully protected during construction. |
CEDD |
CEDD |
CM21 |
Trees unavoidably affected by the works should be transplanted where practical. Detailed transplanting proposal will be submitted to relevant government departments for approval in accordance with ETWBC 2/2004 and 3/2006. Final locations of transplanted trees should be agreed prior to commencement of the work. |
CEDD |
CEDD |
CM31 |
Control of night-time lighting. |
CEDD |
CEDD |
CM41 |
Erection of decorative screen hoarding. |
CEDD |
CEDD |
Table 3.45 Landscape and Visual Mitigation Measure during Operation Phase
ID No. |
Landscape and Visual Mitigation Measure |
Funding Agency |
Implementation Agency |
Maintenance Agency |
OM1 |
Compensatory tree planting should be incorporated into the proposed projects where trees are affected. |
CEDD |
CEDD |
LCSD |
OM2 |
Tall buffer screen tree / shrub / climber planting should be incorporated to soften hard engineering structures and facilities. |
CEDD |
CEDD |
LCSD |
OM3 |
Sensitive streetscape design should be incorporated along all new roads to reflect the new urban development in Kai Tak. |
CEDD |
CEDD |
HyD/LCSD |
OM4 |
Structure, ornamental tree / shrub / climber planting should be provided along roadside amenity strips and central dividers to enhance the townscape quality, where space is available. |
CEDD |
CEDD |
LCSD |
OM5 |
Aesthetically pleasing design as regard to the form, material and finishes shall be incorporated to all buildings, engineering structures and associated infrastructure facilities. |
CEDD |
CEDD |
HyD/LCSD1 |
Residual Landscape Impacts in Construction Phase
Impact on Existing Trees
Residual Impact on Landscape Character Areas
Residual Visual Impact in Construction Phase
Residual Landscape Impacts in Operation Phase
Residual Impact on Existing Trees
Residual Impact on Landscape Character Areas
· to provide a database against which any environmental impacts of the DP1 Project can be determined;
· to provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;
· to monitor the performance of the Project and the effectiveness of mitigation measures;
· to verify the environmental impacts predicted in this EIA;
· to determine project compliance with regulatory requirements, standards and government policies;
· to take remedial action if unexpected problems or unacceptable impacts arise; and
· to provide data to enable an environmental audit.
Table 3.46 Implementation Schedule for Air Quality Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S3.2 |
8 times daily watering of the work site with active dust emitting activities.
|
Work site / during construction |
Contractor |
|
|
|
|
EIAO-TM |
S3.2 |
Implementation of dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation. The following mitigation measures, good site practices and a comprehensive dust monitoring and audit programme are recommended to minimize cumulative dust impacts. · Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission. · Misting for the dusty material should be carried out before being loaded into the vehicle. · Any vehicle with an open load carrying area should have properly fitted side and tail boards. · Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin. · The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation. · The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials. · Vehicle washing facilities should be provided at every vehicle exit point. · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores. · Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet. · Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides; and · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites. |
Work site / during construction |
Contractor |
|
|
|
|
EIAO-TM & Air Quality Objective |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 3.47 Implementation Schedule for Noise Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S3.3 |
Use of quiet PME, movable barriers barrier for Asphalt Paver, Breaker, Excavator and Hand-held breaker and full enclosure for Air Compressor, Bar Bender, Concrete Pump, Generator and Water Pump. |
Work Sites / Construction Period |
Contractor |
|
|
|
|
EIAO-TM, NCO |
S3.3 |
Good Site Practice: · Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program. · Silencers or mufflers on construction equipment should be utilized and should be properly maintained during the construction program. · Mobile plant, if any, should be sited as far away from NSRs as possible. · Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum. · Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs. · Material stockpiles and other structures should be effectively utilized, wherever practicable, in screening noise from on-site construction activities. |
Work Sites / Construction Period |
Contractor |
|
|
|
|
EIAO-TM, NCO |
S3.3 |
Scheduling of Construction Works during School Examination Period |
Construction site near to school / Examination Period |
Contractor |
|
|
|
|
|
* Des - Design, C - Construction, O
– Operation, and Dec – Decommissioning
Table 3.48 Implementation Schedule for Water Quality Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S3.4 |
Operational Phase
A surface water drainage system should be provided to collect road runoff. It is recommended that the road drainage should be provided with adequately designed silt trap and oil interceptors, as necessary. The design of the operational stage mitigation measures for the road works shall take into account the guidelines published in ProPECC PN 5/93 “Drainage Plans subject to Comment by the EPD” |
Project site / during design and operational stages |
CEDD |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 5/93 |
S3.4 |
Construction Phase
Construction
Runoff
Exposed soil areas should be minimised to reduce the potential for increased siltation, contamination of runoff, and erosion. Construction runoff related impacts associated with the above ground construction activities can be readily controlled through the use of appropriate mitigation measures which include: · use of sediment traps · adequate maintenance of drainage systems to prevent flooding and overflow |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Construction site should be provided with adequately designed perimeter channel and pre-treatment facilities and proper maintenance. The boundaries of critical areas of earthworks should be marked and surrounded by dykes or embankments for flood protection. Temporary ditches should be provided to facilitate runoff discharge into the appropriate watercourses, via a silt retention pond. Permanent drainage channels should incorporate sediment basins or traps and baffles to enhance deposition rates. The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Ideally, construction works should be programmed to minimise surface excavation works during the rainy season (April to September). All exposed earth areas should be completed as soon as possible after earthworks have been completed, or alternatively, within 14 days of the cessation of earthworks where practicable. If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed slope surfaces should be covered by tarpaulin or other means. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Sediment tanks of sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacity, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal. The system capacity is flexible and able to handle multiple inputs from a variety of sources and particularly suited to applications where the influent is pumped. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Open stockpiles of construction materials (for examples, aggregates, sand and fill material) of more than 50 m3 should be covered with tarpaulin or similar fabric during rainstorms. Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Precautions to be taken at any time of year when rainstorms are likely, actions to be taken when a rainstorm is imminent or forecast, and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Oil interceptors should be provided in the drainage system and regularly cleaned to prevent the release of oils and grease into the storm water drainage system after accidental spillages. The interceptor should have a bypass to prevent flushing during periods of heavy rain. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and located wheel washing bay should be provided at every site exit, and wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
Drainage It is recommended that on-site drainage system should be installed prior to the commencement of other construction activities. Sediment traps should be installed in order to minimise the sediment loading of the effluent prior to discharge into foul sewers. There should be no direct discharge of effluent from the site into the sea. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
All temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge should be adequately designed for the controlled release of storm flows. All sediment control measures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rain storms. The temporarily diverted drainage should be reinstated to its original condition when the construction work has finished or the temporary diversion is no longer required. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S3.4 |
All fuel tanks and storage areas should be provided with locks and be located on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank, to prevent spilled fuel oils from reaching the coastal waters of the Victoria Harbour WCZ. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94, WDO |
S3.4 |
Sewage Effluent Construction work force sewage discharges on site are expected to be connected to the existing trunk sewer or sewage treatment facilities. The construction sewage may need to be handled by portable chemical toilets prior to the commission of the on-site sewer system. Appropriate numbers of portable toilets should be provided by a licensed contractor to serve the large number of construction workers over the construction site. The Contractor should also be responsible for waste disposal and maintenance practices. |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO |
S3.4 |
Stormwater Discharges Minimum distances of 100 m should be maintained between the existing or planned stormwater discharges and the existing or planned seawater intakes |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, TM-DSS |
S3.4 |
Debris and Litter In order to maintain water quality in acceptable conditions with regard to aesthetic quality, contractors should be required, under conditions of contract, to ensure that site management is optimised and that disposal of any solid materials, litter or wastes to marine waters does not occur |
Work Sites / during construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, WDO |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 3.49 Implementation Schedule for Waste Management Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S3.5 |
Good Site Practices It is not anticipated that adverse waste management related impacts would arise, provided that good site practices are adhered to. Recommendations for good site practices during construction activities include: · Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site · Training of site personnel in proper waste management and chemical waste handling procedures · Provision of sufficient waste disposal points and regular collection for disposal · Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers · A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites) |
Work Sites / during construction |
Contractor |
|
Ö |
|
|
EIAO-TM, WDO |
S3.5 |
Waste Reduction Measures Good management and control can prevent the generation of a significant amount of waste. Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction include: · Sort C&D waste from demolition of the remaining structures to recover recyclable portions such as metals · Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal · Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force · Any unused chemicals or those with remaining functional capacity should be recycled · Proper storage and site practices to minimise the potential for damage or contamination of construction materials |
Work Sites / during construction |
Contractor |
|
Ö |
|
|
EIAO-TM, WDO |
|
Construction and Demolition
Materials
Mitigation
measures and good site practices should be incorporated in the contract
document to control potential environmental impact from handling and
transportation of C&D material. The mitigation measures include:
· Where it is unavoidable to have transient stockpiles of C&D material within the Project work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible. · Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric. · Skip hoist for material transport should be totally enclosed by impervious sheeting. · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site. · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores. · The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle. · All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet. |
Work sites / during construction |
Contractor and Independent Environmental Checker |
|
Ö |
|
|
ETWB TCW No. 33/2002, 31/2004, 19/2005 |
|
· The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading.
When delivering inert C&D material to public fill reception facilities, the material should consist entirely of inert construction waste and of size less than 250mm or other sizes as agreed with the Secretary of the Public Fill Committee. In order to monitor the disposal of the surplus C&D material at the designed public fill reception facility and to control fly tipping, a trip-ticket system as stipulated in the ETWB TCW No. 31/2004 “Trip Ticket System for Disposal of Construction and Demolition Materials” should be included as one of the contractual requirements and implemented by an Environmental Team undertaking the Environmental Monitoring and Audit work. An Independent Environmental Checker should be responsible for auditing the results of the system. |
Work sites / during construction |
Contractor and Independent Environmental Checker |
|
Ö |
|
|
ETWB TCW No. 33/2002, 31/2004, 19/2005 |
S3.5 |
Chemical Waste
After use, chemical wastes (for example, cleaning fluids, solvents, lubrication oil and fuel) should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Spent chemicals should be collected by a licensed collector for disposal at the CWTF or other licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation
|
Work Sites / during construction |
Contractor |
|
Ö |
|
|
Waste Disposal (Chemical Waste) (General) Regulation
Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes |
S3.5 |
General Refuse
General refuse should be stored in enclosed bins or compaction units separate from C&D material. A licensed waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material. Effective collection and storage methods (including enclosed and covered area) of site wastes would be required to prevent waste materials from being blown around by wind, wastewater discharge by flushing or leaching into the marine environment, or creating odour nuisance or pest and vermin problem |
Work Sites / during construction |
Contractor |
|
Ö |
|
|
Waste Disposal Ordinance
Water Pollution Control Ordinance |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 3.50 Implementation Schedule for Land Contamination Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S3.6.57 |
For any excavation works conducted at Radar Station
and ex-GFS building,
· As the risk due to dermal contact with groundwater by site workers is uncertain, it is recommended that personnel protective equipment (PPE) be used by site workers as a mitigation measure. |
Radar Station and ex-GFS building |
Contractor |
|
Ö |
|
|
|
S3.6.58 |
For EMSD Kowloon Bay Vehicle Maintenance Workshop · EMSD as the current occupant should conduct a land contamination assessment and complete the necessary remediation according to the relevant guidelines prior to future handing over the site to the Government for construction of the proposed Road D4. |
EMSD Kowloon Bay Vehicle Maintenance Workshop / Prior to construction of Road D4 |
EMSD
|
|
Ö |
|
|
l “Guidance Note for Contaminated Land Assessment and Remediation” l “Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management” l “Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair /Dismantling Workshop“. |
* Des - Design, C - Construction, O – Operation, and Dec -
Decommissioning
Table 3.51 Implementation Schedule for Landscape and Visual Impacts
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S3.8.12 |
Construction Phase · All existing trees should be carefully protected during construction. · Trees unavoidably affected by the works should be transplanted where practical. Detailed transplanting proposal will be submitted to relevant government departments for approval in accordance with ETWBC 2/2004 and 3/2006. Final locations of transplanted trees should be agreed prior to commencement of the work. · Control of night-time lighting. · Erection of decorative screen hoarding. |
Works area / During Construction Phase |
Contractor |
|
|
|
|
EIAO-TM |
S3.8.13 |
Operation Phase · Compensatory tree planting should be incorporated into the proposed projects where trees are affected. · Tall buffer screen tree / shrub / climber planting should be incorporated to soften hard engineering structures and facilities. · Sensitive streetscape design should be incorporated along all new roads to reflect the new urban development in Kai Tak. · Structure, ornamental tree / shrub / climber planting should be provided along roadside amenity strips and central dividers to enhance the townscape quality, where space is available. · Aesthetically pleasing design as regard to the form, material and finishes should be incorporated to all buildings, engineering structures and associated infrastructure facilities. |
Project area / During Design stage and Operation Phase |
CEDD |
|
|
|
|
EIAO-TM |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning