Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Impact Assessment Report
Contents
4........... EIA on New sewage pumping stations serving the planned KTD
4.5 Waste Management Implications
4.7 Impact on Cultural Heritage
4.8 Landscape and Visual Impact
4.9 Environmental Monitoring and Audit Requirement
4.10 Implementation Schedule of the
Proposed Mitigation Measures
List of Tables
Table 4.1 Summary of Environmental impacts
Table 4.2 Hong Kong Air Quality Objectives
Table 4.4 Summary of Representative Air Sensitive Receivers
Table 4.5 Construction Noise Criteria for Activity other than Percussive Piling
Table 4.6 Acceptable Noise Level for Fixed Plant Noise
Table 4.7 Summary of Area Sensitive Rating for NSR for Fixed Plant Noise Assessment
Table 4.8 Representative Noise Sensitive Receivers for Construction Noise Impact Assessment
Table 4.10 Predicted Maximum Allowable Sound Power Levels for SPSs
Table 4.11 Summary of Predicted Operational Noise Level
Table 4.13 Construction Noise Residual Impacts
Table 4.14 Summary of Water Quality Objectives for the Victoria Harbour WCZ
Table 4.15 WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes
Table 4.16 Summary Statistics of 2006 Marine Water Quality in the Victoria Harbour
Table 4.17 Design Information for Sewage Pumping Station
Table 4.18 Summary of Locations of the Sewage Pumping Stations
Table 4.19 Zoning for the Current Assessment with reference to the Coverage of the Previous Studies
Table 4.20 Summary of findings in the relevant EIA reviewed
Table 4.21 Identification of Potential Land Contamination Impacts
Table 4.22 Summary of Reviewed Information on Potential Contaminative Land Uses
Table 4.24 Landscape Resources / Landscape Character Areas and Their Sensitivity to Change
Table 4.25 Visual Sensitive Receivers (VSRs) and Their Sensitivity to Change
Table 4.26 Landscape Impacts of the Proposed Works during Construction Phase
Table 4.27 Significance of Landscape Impacts in Construction and
Operation Phases
Table 4.29 Landscape and Visual Mitigation Measures during
Construction Phase
Table 4.30 Landscape and Visual Mitigation Measures during
Operation Phase
Table 4.31 Implementation Schedule for Air Quality Measures
Table 4.32 Implementation Schedule for Noise Measures
Table 4.33 Implementation Schedule for Water Quality Measures
Table 4.34 Implementation Schedule for Waste Management Measures
Table 4.35 Implementation Schedule for Land Contamination
Table 4.36 Implementation Schedule for Landscape and Visual Impact
Table 4.1 Summary of Environmental impacts
|
Construction Phase |
Operational Phase |
Air |
|
|
Noise |
|
|
Water Quality |
|
|
Waste Management |
|
|
Land Contamination |
|
û |
Hazard to Life |
û |
û |
Cultural Heritage |
|
û |
Landscape and Visual Impact |
|
|
Ecological Impact |
û |
û |
Fisheries Impact |
û |
û |
Table 4.2
Pollutant |
Maximum
Concentration (µg m-3) (1) |
|||
Averaging
Time |
||||
1
hour (2) |
8
hour (3) |
24
hour (3) |
Annual
(4) |
|
Total Suspended Particulates (TSP) |
- |
- |
260 |
80 |
Respirable Suspended Particulates (RSP) (5) |
- |
- |
180 |
55 |
|
800 |
- |
350 |
80 |
Nitrogen Dioxide (NO2) |
300 |
- |
150 |
80 |
Carbon Monoxide (CO) |
30,000 |
10,000 |
- |
- |
Photochemical Oxidants (as Ozone, O3) (6) |
240 |
- |
- |
- |
Notes:
(1) Measured at 298 K and 101.325 kPa.
(2) Not to be exceeded more than three times per year.
(3) Not to be exceeded more than once per year.
(4) Arithmetic mean.
(5) Suspended particulates in air with a nominal aerodynamic diameter of 10 mm or smaller.
(6) Photochemical oxidants are determined by measurement of ozone only.
Table 4.3 Annual Average Concentrations of Pollutants in Year 2006 at EPD’s Sham Shui Po and Kwun Tong Air Quality Monitoring Stations
Pollutant |
Annual Average AQO (mg m-3) |
Year 2006 Annual Average Concentration (mg m-3) |
|
Sham Shui Po station |
Kwun Tong station |
||
TSP |
80 |
79 |
75 |
RSP |
55 |
55 |
55 |
NO2 |
80 |
67 |
61 |
SO2 |
80 |
24 |
19 |
Table 4.4 Summary of Representative Air Sensitive Receivers
ASRs |
District (1) |
Location |
Existing / Planned Land Use |
Max. Building Height, m (2) |
Distance to Project Boundary, m |
SPSs |
A17 |
KB |
|
Commercial |
54 |
326 |
PSIA |
A18 |
KB |
Hong Kong Bank New |
Commercial |
12 |
308 |
PSIA |
A19 |
KB |
Electrical & Mechanical Services Department Headquarters |
G/IC |
21 |
129 |
PSIA |
A20 |
KB |
|
Industrial |
30 |
247 |
PSIA |
A21 |
KB |
|
Commercial |
117 |
212 |
PSIA |
A22 |
KB |
Football field |
Recreation |
1.5 |
317 |
PSIA |
A23 |
KB |
|
G/IC |
30 |
440 |
PSIA |
A24 |
KB |
Bicycle Track Near |
Recreation |
1.5 |
332 |
PSIA |
A25 |
NCW |
|
Shopping Center |
30 |
394 |
PSIA |
A26 |
NCW |
|
Residential |
99 |
488 |
PSIA |
A27 |
NCW |
Kam Bik House, Choi Hung Estate |
Residential |
60 |
853 |
PSIA |
A28 |
NCW |
Pik Hoi House, Choi Hung Estate |
Residential |
60 |
920 |
PS1 |
A29 |
NCW |
|
Residential |
87 |
705 |
PS1 |
A30 |
SPK |
|
Educational |
18 |
244 |
|
A31 |
SPK |
Sir Robert Black Health Centre |
Clinic |
9 |
67 |
PS1 |
A32 |
SPK |
|
Educational |
10 |
95 |
PS1 |
A33 |
SPK |
|
Recreation |
1.5 |
152 |
PS1 |
A34 |
SPK |
Regal Oriental Hotel |
Hotel |
42 |
291 |
PS3 |
A35 |
SPK |
|
Residential |
15 |
228 |
PS3 |
A36 |
SPK |
|
Residential |
12 |
129 |
PS3 |
A37 |
KC |
Sung Wong Toi Playground |
Recreation |
1.5 |
128 |
PS3 |
A38 |
KC |
Sung |
Recreation |
1.5 |
217 |
PS3 |
A39 |
KC |
Parc 22 |
Residential |
33 |
288 |
PS3 |
A40 |
KC |
|
Residential |
141 |
303 |
PS3 |
A41 |
TKW |
Freder Centre |
Industrial |
153 |
331 |
NPS |
A42 |
TKW |
K K |
Industrial |
12 |
262 |
NPS |
A43 |
TKW |
HK Society for Blind hostel |
Hostel |
9 |
34 |
NPS |
A44 |
TKW |
|
Residential |
18 |
57 |
NPS |
A45 |
TKW |
China Gas Company |
Commercial |
15 |
211 |
NPS |
A46 |
TKW |
|
Residential |
21 |
231 |
NPS |
A47 |
TKW |
Grand Waterfront |
Residential |
153 |
185 |
NPS |
A48 |
TKW |
|
Industrial |
36 |
329 |
NPS |
A49 |
TKW |
|
Residential |
39 |
377 |
NPS |
A51 |
TKW |
United Daily |
Industrial |
48 |
423 |
NPS |
A52 |
TKW |
|
Educational |
18 |
535 |
NPS |
A53 |
TKW |
Oblate Father’s Primary School |
Educational |
21 |
598 |
NPS |
PA9 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
367 |
PSIA |
PA10 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
398 |
PSIA |
PA11 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
324 |
PSIA |
PA12 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
488 |
PSIA |
PA13 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
853 |
PSIA |
PA14 |
KTD |
Site 1B1 (Planned) |
Residential |
115 |
920 |
PS1 |
PA15 |
KTD |
Site 1B4 (Planned) |
Educational |
40 |
705 |
PS1 |
PA16 |
KTD |
Site 1C1 (Planned) |
G/IC |
85 |
244 |
|
PA17 |
KTD |
Site 1D2 (Planned) |
Commercial |
95 |
67 |
PS1 |
PA18 |
KTD |
Site 1D3 (Planned) |
G/IC |
55 |
95 |
PS1 |
PA19 |
KTD |
Site 1D4 (Planned) |
G/IC |
95 |
152 |
PS1 |
PA22 |
KTD |
Site 1F1 (Planned) |
Commercial |
145 |
291 |
PS3 |
PA23 |
KTD |
Site 1F2 (Planned) |
Commercial |
170 |
228 |
PS3 |
PA24 |
KTD |
Site 1G2 (Planned) |
G/IC |
75 |
129 |
PS3 |
PA25 |
KTD |
Site 1H1 (Planned) |
Residential |
105 |
128 |
PS3 |
PA26 |
KTD |
Site 1H2 (Planned) |
Residential |
105 |
217 |
PS3 |
PA27 |
KTD |
Site 1H3 (Planned) |
Residential |
105 |
288 |
PS3 |
PA28 |
KTD |
Site 1I1 (Planned) |
Residential |
95 |
303 |
PS3 |
PA29 |
KTD |
Site 1I2 (Planned) |
Residential |
95 |
331 |
NPS |
PA30 |
KTD |
Site 1I3 (Planned) |
Residential |
95 |
262 |
NPS |
PA31 |
KTD |
Site 1J1 (Planned) |
G/IC |
55 |
34 |
NPS |
PA32 |
KTD |
Site 1J3 (Planned) |
G/IC |
25 |
57 |
NPS |
PA33 |
KTD |
Site 1K1 (Planned) |
Residential |
105 |
324 |
PSIA |
PA34 |
KTD |
Site 1K2 (Planned) |
Residential |
105 |
243 |
PSIA |
PA35 |
KTD |
Site 1K3 (Planned) |
Residential |
95 |
187 |
PSIA |
PA36 |
KTD |
Site 1L1 (Planned) |
Residential |
95 |
110 |
PSIA |
PA37 |
KTD |
Site 1L2 (Planned) |
Residential |
95 |
437 |
PS1 |
PA38 |
KTD |
Site 1L3 (Planned) |
Residential |
95 |
306 |
PS1 |
PA39 |
KTD |
Site 1L4 (Planned) |
Residential |
25 |
130 |
PS1 |
PA40 |
KTD |
Site 1M1 (Planned) |
Commercial |
35 |
216 |
PS1 |
PA41 |
KTD |
Site 1M1 (Planned) |
Commercial |
35 |
219 |
PS1 |
PA42 |
KTD |
Site 1M2 (Planned) |
Commercial |
35 |
136 |
PS1 |
PA43 |
KTD |
Site 2A1 (Planned) |
G/IC |
65 |
405 |
PS1 |
PA44 |
KTD |
Site 2A2 (Planned) |
G/IC |
65 |
344 |
PSIA |
PA45 |
KTD |
Site 2A3 (Planned) |
G/IC |
65 |
348 |
PSIA |
PA46 |
KTD |
Site 2A4 (Planned) |
G/IC |
65 |
351 |
PSIA |
PA47 |
KTD |
Site 2A5 (Planned) |
G/IC |
65 |
59 |
PSIA |
PA48 |
KTD |
Site 2A6 (Planned) |
G/IC |
40 |
24 |
PS3 |
PA49 |
KTD |
Site 2B1 (Planned) |
Residential |
105 |
360 |
PS1 |
PA50 |
KTD |
Site 2B1 (Planned) |
Residential |
105 |
280 |
PS1 |
PA51 |
KTD |
Site 2B2 (Planned) |
Residential |
95 |
330 |
PS3 |
PA52 |
KTD |
Site 2B3 (Planned) |
Residential |
80 |
230 |
PS3 |
PA53 |
KTD |
Site 2B4 (Planned) |
Residential |
80 |
200 |
PS3 |
PA54 |
KTD |
Site 2B5 (Planned) |
Residential |
80 |
150 |
PS3 |
PA55 |
KTD |
Site 2B6 (Planned) |
Residential |
80 |
130 |
PS3 |
PA56 |
KTD |
Site 2D1 (Planned) |
Recreation |
40 |
278 |
PSIA |
PA57 |
KTD |
Site 2D1 (Planned) |
Recreation |
40 |
345 |
PSIA |
PA58 |
KTD |
Site 3C1 (Planned) |
Hospital |
55 |
274 |
PSIA |
PA59 |
KTD |
Site 3C1 (Planned) |
Hospital |
55 |
273 |
PS1 |
PA60 |
KTD |
Site 3C1 (Planned) |
G/IC |
55 |
79 |
PS1 |
PA61 |
KTD |
Site 3C1 (Planned) |
Hospital |
55 |
102 |
PS1 |
PA62 |
KTD |
Site 3D1 (Planned) |
Commercial |
95 |
84 |
PS1 |
PA63 |
KTD |
Site 3D2 (Planned) |
Commercial |
95 |
259 |
PS1 |
PA64 |
KTD |
Site 3D3 (Existing)/ Site 3D3 (Planned) |
Industrial / Commercial |
168/ 95 |
454 |
PS1 |
PA65 |
KTD |
Site 3D4 (Planned) |
Commercial |
95 |
337 |
PS1 |
PA66 |
KTD |
Site 3D4 (Planned) |
Commercial |
95 |
112 |
PS1 |
PA67 |
KTD |
Site 4A1 (Planned) |
Residential |
60 |
1316 |
NPS |
PA68 |
KTD |
Site 4A1 (Planned) |
Residential |
60 |
1259 |
NPS |
PA69 |
KTD |
Site 4A2 (Planned) |
Commercial |
40 |
1249 |
NPS |
PA70 |
KTD |
Site 4A3 (Planned) |
Commercial |
75 |
1177 |
NPS |
PA71 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
1050 |
NPS |
PA72 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
1121 |
NPS |
PA73 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
817 |
NPS |
PA74 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
800 |
NPS |
PA75 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
469 |
NPS |
PA76 |
KTD |
Site 4A (Planned) |
Recreation |
1.5 |
416 |
NPS |
PA77 |
KTD |
Site 4B1 (Planned) |
Residential |
50 |
1415 |
PS2 |
PA78 |
KTD |
Site 4B1 (Planned) |
Residential |
50 |
1251 |
PS2 |
PA79 |
KTD |
Site 4B2 (Planned) |
Residential |
50 |
1562 |
PS2 |
PA80 |
KTD |
Site 4B2 (Planned) |
Residential |
50 |
1485 |
PS2 |
PA81 |
KTD |
Site 4B3 (Planned) |
Residential |
60 |
1715 |
PS2 |
PA82 |
KTD |
Site 4B3 (Planned) |
Residential |
60 |
1621 |
PS2 |
PA83 |
KTD |
Site 4B4 (Planned) |
Residential |
50 |
1898 |
PS2 |
PA84 |
KTD |
Site 4B4 (Planned) |
Residential |
50 |
1823 |
PS2 |
PA85 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
2110 |
PS2 |
PA86 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
2103 |
PS2 |
PA87 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
2001 |
PS2 |
PA88 |
KTD |
Site 4B5 (Planned) |
Residential |
40 |
2001 |
PS2 |
PA89 |
KTD |
Site 4C1 (Planned) |
Commercial |
40 |
1436 |
PS2 |
PA90 |
KTD |
Site 4C2 (Planned) |
Commercial |
50 |
1588 |
PS2 |
PA91 |
KTD |
Site 4C3 (Planned) |
Commercial |
40 |
1727 |
PS2 |
PA92 |
KTD |
Site 4C4 (Planned) |
Commercial |
40 |
1883 |
PS2 |
PA93 |
KTD |
Site 4C5 (Planned) |
Commercial |
40 |
2117 |
PS2 |
PA94 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
2658 |
PS2 |
PA95 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
2658 |
PS2 |
PA96 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
2886 |
PS2 |
PA97 |
KTD |
Site 4D2 (Planned) |
G/IC |
1.5 |
2912 |
PS2 |
PA98 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
2298 |
PS2 |
PA99 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
2457 |
PS2 |
PA100 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
2681 |
PS2 |
PA101 |
KTD |
Site 4D3 (Planned) |
Commercial |
30 |
2809 |
PS2 |
PA102 |
KTD |
Site 5A4 (Planned) |
Residential |
60 |
89 |
PS2 |
PA103 |
KTD |
Site 5A4 (Planned) |
Residential |
105 |
155 |
PS2 |
PA104 |
KTD |
Site 3B1 (Planned) |
Undesignated |
40 |
485 |
PS2 |
PA105 |
KTD |
Site 3B2 (Planned) |
Undesignated |
40 |
644 |
PS2 |
PA106 |
KTD |
Site 3B3 (Planned) |
Undesignated |
40 |
782 |
PS2 |
PA107 |
KTD |
Site 3B4 (Planned) |
Undesignated |
40 |
860 |
PS2 |
PA108 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
2264 |
PS2 |
PA109 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
2434 |
PS2 |
PA110 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
2664 |
PS2 |
PA111 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
2620 |
PS2 |
PA112 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
2559 |
PS2 |
PA113 |
KTD |
Site 4D2 (Planned) Tourism node |
Other Specified Uses |
95 |
2339 |
PS2 |
Note: (1) KT – Kwun Tong; NTK – Ngau Tau Kok; KB – Kowloon Bay; NCW – Ngau Chi Wah; SPK – San Po Kong; KC – Kowloon City, TKW – To Kwa Wan; HH – Hung Hom; KTD – Kai Tak Development
(2) The maximum height for Planned ASR was made reference to the RODP.
Identify the potentially fugitive dust emission during construction phase; and
Assess the significance of construction dust emissions from construction phase.
Identify and locate the odour emission sources within the study area;
Identify and locate representative ASRs that may be affected by the odour sources; and
Assess the significance of odour impact.
Cruise Terminal Development and related advance works
Infrastructure works at North Apron, Phase 1 - Housing Sites and Government Offices
Kai Tak Nullah modification works
Infrastructure works at runway and
Infrastructure works at North Apron, Phase 2
Trunk Road T2 and infrastructure works at South Apron
SCL Construction
CKR Construction
Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission.
Misting for the dusty material should be carried out before being loaded into the vehicle.
Any vehicle with an open load carrying area should have properly fitted side and tail boards.
Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin.
The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation.
The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials.
Vehicle washing facilities should be provided at every vehicle exit point.
The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.
Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet.
Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides.
Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.
· TM on Environmental Impact Assessment Process (EIAO-TM)
· TM on Noise from Construction Work other than Percussive Piling (GW-TM)
· TM on Noise from Percussive Piling (PP-TM)
· TM on Noise from Construction Work in Designated Areas (DA-TM)
· TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM)
Table 4.5 Construction Noise Criteria for Activity other than Percussive Piling
Time Period |
Basic Noise Level (BNLs) |
||
ASR A |
ASR B |
ASR C |
|
Evening (1900 to 2300 hours) (1) |
60 |
65 |
70 |
Night (2300 to 0700 hours) |
45 |
50 |
55 |
Notes: (1) Includes Sundays and Public Holidays during daytime and evening
Table 4.6 Acceptable Noise Level for Fixed Plant Noise
Time Period |
NCO criteria |
EIAO-TM |
||
ASR ‘B’ |
ASR ‘C’ |
ASR ‘B’ |
ASR ‘C’ |
|
Daytime and Evening (0700-2300 hours) |
65 |
70 |
60 |
65 |
Night-time (2300-0700 hours) |
55 |
60 |
50 |
55 |
· The type of area within the concerned NSR is located;
· The Influencing Factor (IF) identified;
· The Degree to which the NSR is affected by IF; and
· If applicable, nearby OZP “Industrial” or “Industrial Estates” zone
Table 4.7 Summary of Area Sensitive Rating for NSR for Fixed Plant Noise Assessment
NSRs |
District (1) |
Location |
Existing / Planned Land Use |
ASR (2) |
Remarks |
N11 |
SPK |
|
Educational |
C |
(3) (a) |
N12 |
SPK |
Sir Robert Black Health Centre |
Clinic |
C |
(3) (a) |
N13 |
SPK |
|
Educational |
C |
(3) (a) |
N14 |
SPK |
|
Residential |
C |
(3) (a) |
N15 |
SPK |
|
Residential |
C |
(3) (a) |
N16 |
KC |
Parc 22 |
Residential |
C |
(3) (b) |
N17 |
KC |
|
Residential |
C |
(3) (b) |
N18 |
KC |
HK Society for Blind hostel |
Residential |
B |
|
N19 |
TKW |
|
Residential |
B |
|
PN41 |
KTD |
Site 1I2 (Planned) |
Residential |
B |
|
PN52 |
KTD |
Site 1L3 (Planned) |
Educational |
B |
|
PN61 |
KTD |
Site 2B6 (Planned) |
Educational |
B |
|
Note:
(1) SPK – San Po Kong; KC –
(2) All NSRs are located at the Urban Area
(3) NSR affected by the “major road” which has a heavy and generally continuous flow of vehicular traffic and, in normal circumstances, means a road with an annual average daily traffic flow in excess of 30,000.
(a) affected by
(b) affected by
Table 4.8 Representative Noise Sensitive Receivers for Construction Noise Impact Assessment
NSRs |
Location |
Existing / Planned Land Use |
Max. Building Height, m |
|
N11 |
SPK |
|
Educational |
18 |
N12 |
SPK |
Sir Robert Black Health Centre |
Clinic |
9 |
N13 |
SPK |
|
Educational |
10 |
N14 |
SPK |
|
Residential |
15 |
N15 |
SPK |
|
Residential |
12 |
N16 |
KC |
Parc 22 |
Residential |
33 |
N17 |
KC |
|
Residential |
141 |
N18 |
KC |
HK Society for Blind hostel |
Residential |
9 |
N19 |
TKW |
|
Residential |
18 |
PN41 |
KTD |
Site 1I2 (Planned) |
Residential |
95 |
PN52 |
KTD |
Site 1L3 (Planned) |
Residential |
45 |
PN61 |
KTD |
Site 2B6 (Planned) |
Residential |
80 |
Note:
(1) SPK – San Po Kong; KC –
· Cruise Terminal Development and related advance works
· Infrastructure works at North Apron, Phase 1 - Housing Sites and Government Offices
· Kai Tak Nullah modification works
·
Infrastructure works at
runway and
· Infrastructure works at North Apron, Phase 2
· Trunk Road T2 and infrastructure works at South Apron
· SCL Construction
· CKR Construction
·
l Identify fixed plant noise;
l Calculate the correction factors based on the distance between the NSRs and the noise source positions;
l Apply acoustics correction factors for façade, distance, barrier attenuation, acoustic reflection where applicable;
l Calculate the maximum allowable Sound Power Level (SWL) as the compliance criteria for each fixed noise sources; and
l Quantify the level of impact at the NSRs in accordance with IND-TM.
Table 4.9
Summary of Cumulative Unmitigated Construction Noise Levels at
Representative NSRs during Normal Daytime Working Hours.
NSR
|
Noise Criteria, dB(A)
|
Predicted Unmitigated Construction Noise Levels
during
|
Exceedance, dB(A)
|
N11 |
65/70* |
59 - 84 |
19/14 |
N12 |
75 |
60 - 84 |
9 |
N13 |
65/70* |
60 - 82 |
17/12 |
N14 |
75 |
60 - 89 |
14 |
N15 |
75 |
60 - 86 |
11 |
N16 |
75 |
59 - 78 |
3 |
N17 |
75 |
60 - 82 |
7 |
N18 |
75 |
63 - 83 |
8 |
N19 |
75 |
62 - 82 |
7 |
Table 4.10 Predicted Maximum Allowable Sound Power Levels for SPSs
SPSs |
Likely affected NSRs |
ASRs |
Approx Distance to NSR, m |
Sound Power Level (SWL, dB(A)) required at source in order to meet the criteria |
|
Daytime |
Nighttime |
||||
PS1A |
PN41 |
B |
25 |
90 |
80 |
PS1 |
N12 |
C |
111 |
108 |
98 |
PS2 |
PN52 |
B |
9 |
66 |
61 |
PS3 |
PN61 |
B |
135 |
105 |
94 |
PS-NPS |
N18 |
B |
49 |
96 |
84 |
Table 4.11 Summary of Predicted Operational Noise Level
NSR |
NSR Description |
Predicted Noise Level, dB(A) |
|
Daytime |
Nighttime |
||
N12 |
Sir Robert Black Health Centre |
65 |
55 |
N17 |
Sky Tower |
60 |
50 |
N18 |
HK Society for Blind hostel |
60 |
49 |
N19 |
Mok Cheong Street Residential District |
60 |
50 |
PN41 |
Site 1I2 (Planned) |
60 |
50 |
PN52 |
Site 1L3 (Planned) |
57 |
50 |
PN61 |
Site 2B6 (Planned) |
60 |
50 |
PN69 |
Site 1F2 (Planned) |
60 |
50 |
Table 4.12 Summary of Cumulative Mitigated Construction Noise Levels at Representative NSRs During Normal Daytime Working Hours
NSR
|
Noise Criteria, dB(A)
|
Predicted Mitigated Construction Noise
Levels during Normal Daytime Working Hour (Leq (30-min), dB(A))
|
Exceedance, dB(A)
|
Duration, Month
|
N11
|
65/70*
|
47 - 75
|
10/5
|
66 include examination period
|
N12
|
75
|
47 - 74
|
0
|
0
|
N13
|
65/70*
|
47 - 74
|
9/4
|
66 include examination period
|
N14
|
75
|
47 - 78
|
3
|
12
|
N15
|
75
|
47 - 75
|
0
|
0
|
N16
|
75
|
46 - 70
|
0
|
0
|
N17
|
75
|
47 - 75
|
0
|
0
|
N18
|
75
|
50 - 76
|
1
|
7
|
N19
|
75
|
50 – 75
|
0
|
0
|
· The exhaust of the ventilation system and any opening of the building should be located facing away from any NSRs;
· Louver or other acoustic treatment equipment could also be applied to the exhaust exit of the building; and
· Pumps and mechanical ventilation are either underground or enclosed within a structure or building.
Table 4.13 Construction Noise Residual Impacts
NSR |
Exceedance of the EIAO-TM Criterion |
Construction Activity Causing Exceedance |
Approximate duration of Exceedance |
|
65 dB(A) |
70 dB(A) |
|||
N11 |
10 (Sept 2009 to Apr 2010 and Jul 2010 to Dec 2015) |
5 (Jul 2010 to Dec 2015) |
l Construction of Road D1 l Local Roads L1, L2, L3, L11, L15 and associated footpaths at North Apron l Drainage, Sewerage & Watermain l Construction of Footbridge at Rhythm Garden (LW-04) l Rebuild Kai Tak Nullah l Construction of Landscape Walkway LW-02 l SCL |
66 month include examination period |
N13 |
9 (Sept 2009 to Apr 2010 and Jul 2010 to Dec 2015) |
4 (Jul 2010 to Dec 2015) |
l Construction of Road D1 l Local Roads L1, L2, L3, L11, L15 and associated footpaths at North Apron l Drainage, Sewerage & Watermain l Construction of Footbridge at Rhythm Garden (LW-04) l Construction of Landscape Walkway LW-03 l Underground Shopping Street (SB-01) l Upgrading of Pumping Station PS1 l Rebuild Kai Tak Nullah l Construction of Landscape Walkway LW-02 l SCL |
66 month include examination period |
NSR |
Exceedance of the EIAO-TM Criterion |
Construction Activity Causing Exceedance |
Approximate duration of Exceedance |
|
75 dB(A) |
||||
N14 |
2 (Jan 2015 to Dec 2015) |
l Construction of Road D1, L7, L8, L9 & L16 l Underground Shopping Street (SB-01) |
12 month |
|
N18 |
1 (Jan 2015 to July 2015) |
l SCL |
7 month |
· Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.
· Mobile plant, if any, should be sited as far away from NSRs as possible.
· Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.
· Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.
· Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.
l Annex 6 – Criteria for Evaluating Water Pollution
l Annex 14 – Guidelines for Assessment of Water Pollution.
Table 4.14 Summary of Water Quality Objectives for the Victoria Harbour WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2m of the seabed |
Not less than 2.0mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0mg/l for 90% of samples |
Marine waters |
pH |
To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2 |
Marine waters |
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone
|
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by human activity |
Marine waters |
Unionised ammonia (UIA) |
Annual mean not to exceed 0.021mg/l as unionised form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to exceed 0.4mg/l |
Marine waters |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
Human activity should not cause a risk to any beneficial use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality Objectives (Victoria Harbour (Phases One, Two and Three) Water Control Zone).
Table 4.15 WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes
Parameter (in mg/l unless otherwise stated) |
Target Limit |
Colour (HU) |
< 20 |
Turbidity (NTU) |
< 10 |
Threshold Odour Number (odour unit) |
< 100 |
Ammoniacal Nitrogen |
< 1 |
Suspended Solids |
< 10 |
Dissolved Oxygen |
> 2 |
Biochemical Oxygen Demand |
< 10 |
Synthetic Detergents |
< 5 |
E. coli (no. per 100ml) |
< 20,000 |
Table 4.16 Summary Statistics of 2006 Marine Water Quality in the Victoria Harbour
Parameter |
Victoria Harbour East |
Victoria Harbour Central |
Victoria Harbour West |
Stonecutters Island |
Rambler Channel |
WPCO WQO (in marine waters) |
||||||
VM1 |
VM2 |
VM4 |
VM5 |
VM6 |
VM7 |
VM8 |
VM15 |
VM12 |
VM14 |
|||
Temperature (oC) |
23.2 |
23.5 |
23.6 |
23.7 |
23.6 |
23.8 |
23.8 |
23.7 |
23.8 |
24.2 |
Not more than 2 oC in daily temperature range |
|
Salinity |
32.2 (29.5 – 33.4) |
31.7 |
31.6 |
31.4 |
31.5 |
30.8 |
20.7 |
31.1 |
30.8 |
28.7 |
Not to cause more than 10% change |
|
Dissolved Oxygen (DO) (% Saturation) |
Depth average |
82 |
81 |
80 |
77 |
78 |
80 |
85 |
80 |
77 |
84 |
Not available |
Bottom |
80 |
81 |
79 |
76 |
75 |
77 |
82 |
78 |
75 |
83 |
Not available |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
5.9 |
5.8 |
5.7 |
5.5 |
5.5 |
5.7 |
6.0 |
5.7 |
5.5 |
6.0 |
Not less than 4 mg/l for 90% of the samples |
Bottom |
5.7 |
5.8 |
5.6 |
5.4 |
5.4 |
5.5 |
5.8 |
5.5 |
5.3 |
5.9 |
Not less than 2 mg/l for 90% of the samples |
|
pH |
7.9 |
7.9 |
7.9 |
7.9 |
7.9 |
8.0 |
8.0 |
7.9 |
8.0 |
8.0 |
6.5 - 8.5 (± 0.2 from natural range) |
|
Secchi disc Depth (m) |
2.1 |
2.0 |
2.0 |
1.8 |
2.1 |
2.0 |
1.9 |
2.0 |
1.5 |
1.5 |
Not available |
|
Turbidity (NTU) |
12.6 |
11.2 |
12.1 |
11.6 |
11.1 |
11.5 |
11.9 |
12.4 |
15.6 |
12..6 |
Not available |
|
Suspended Solids (SS) (mg/l) |
5.5 |
4.2 |
4.9 |
4.6 |
4.5 |
5.5 |
5.9 |
6.1 |
11.0 |
5.9 |
Not more than 30% increase |
|
5-day Biochemical Oxygen Demand (BOD5) (mg/l) |
0.6 |
0.6 |
0.7 |
1.0 |
0.8 |
0.8 |
0.7 |
0.7 |
0.7 |
0.7 |
Not available |
|
Nitrite Nitrogen (NO2-N) (mgN/l) |
0.019 |
0.024 |
0.024 |
0.027 |
0.027 |
0.033 |
0.035 |
0.033 |
0.036 |
0.053 |
Not available |
|
Nitrate Nitrogen (NO3-N) (mgN/l) |
0.08 |
0.10 |
0.11 |
0.12 |
0.13 |
0.16 |
0.16 |
0.15 |
0.17 |
0.27 |
Not available |
|
Ammonia Nitrogen (NH3-N) (mgN/l) |
0.07 |
0.11 |
0.13 |
0.16 |
0.16 |
0.21 |
0.17 |
0.18 |
0.18 |
0.16 |
Not available |
|
Unionised Ammonia (UIA) (mgN/l) |
0.002 |
0.004 |
0.004 (0.002 – 0.007) |
0.005 |
0.005 (0.003 – 0.007) |
0.008 |
0.007 |
0.006 |
0.006 |
0.007 |
Not more than 0.021 mg/l for annual mean |
|
Total Inorganic Nitrogen (TIN) (mgN/l) |
0.18 |
0.23 |
0.26 (0.08 – 0.44) |
0.31 (0.14 – 0.50) |
0.32 |
0.40 |
0.37 |
0.36 |
0.39 |
0.48 |
Not more than 0.4 mg/l for annual mean |
|
Total Nitrogen (TN) (mgN/l)
|
0.34 |
0.42 (0.20 – 0.64) |
0.47 |
0.55 |
0.53 |
0.58 |
0.53 |
0.58 (0.35 – 0.86) |
0.57 |
0.64 |
Not available |
|
Orthophosphate Phosphorus (PO4) (mgP/l) |
0.02 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
0.03 |
Not available |
|
Total Phosphorus (TP) (mgP/l) |
0.04 |
0.05 |
0.05 |
0.06 |
0.06 |
0.05 |
0.04 |
0.06 |
0.05 |
0.04 |
Not available |
|
Chlorophyll-a (µg/L) |
2.6 |
3.0 |
2.9 (1.0 – 9.2) |
2.8 |
2.9 |
2.6 |
2.7 |
3.5 |
2.1 |
3.4 |
Not available |
|
E coli (cfu/100 ml) |
440 |
1100 |
2600 |
7700 |
5500 |
9400 |
6100 |
1800 |
3400 |
1300 |
Not available |
|
Faecal Coliforms (cfu/100 ml) |
940 |
2600 |
6500 |
19000 |
13000 |
23000 |
15000 |
4800 |
8100 (4200 – 14000) |
2800 (460 – 13000) |
Not available |
Notes: 1. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.
2. Data presented are annual arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
3. Data in brackets indicate the ranges.
· Occasional overflow of sewage effluent during storm event under normal operation
· Emergency sewage effluent discharge as the consequences of pump failure or interruption of the electrical power supply
Table 4.17 Design Information for Sewage Pumping Station
SPS ID (refer to Figure 1.3) |
Preliminary Design Peak Flow (m3/sec) |
Preliminary Design Average Flow (m3/day) |
Sewage Overflow or Emergency Discharge Route (refer to Figure 8.4) |
PS1 |
1.88 |
68,256 |
Discharge at storm outfall N via KTN |
PS1A |
0.41 |
11,753 |
|
PS2 |
0.40 |
11,627 |
|
PS3 |
2.02 |
72,576 |
Discharge at the inner corner
of |
Site 5A1 |
0.49 |
14,130 |
Stormwater Discharges
Construction Runoff and Drainage
· contaminated ground water from any dewatering activities as a result of excavation;
· release of any bentonite slurries and other grouting materials with construction run-off, storm water or ground water dewatering process;
· wash water from dust suppression sprays and wheel washing facilities;
· fuel, oil and lubricants from maintenance of construction vehicles and equipment.
General Construction Activities
· Dual power supply or emergency generator should be provided at all the SPSs to secure electrical power supply;
· Standby pumps should be provided at all SPSs to ensure smooth operation of the SPS during maintenance of the duty pumps;
· An alarm should be installed to signal emergency high water level in the wet well at all SPSs; and
· For all unmanned SPSs, a remote monitor system connecting SPSs with the control station through telemetry system should be provided so that swift actions could be taken in case of malfunction of unmanned facilities.
Construction site runoff and drainage
Sewage Effluent
Refuse and Debris
Stormwater Discharges
· Waste Disposal Ordinance (Cap. 354)
· Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354)
· Land (Miscellaneous Provisions) Ordinance (Cap. 28)
· Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation
· Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)
· Estimation of the types and quantities of the wastes generated.
· Assessment of potential impacts from the management of solid waste with respect to potential hazards, air and odour emissions, noise, wastewater discharge and transport.
· Assessment of impacts on the capacity of waste collection, transfer and disposal facilities.
· C&D material
· Chemical waste
· General refuse
· Toxic effects to workers
· Adverse impacts on water quality from spills
· Fire hazards
· Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.
· Training of site personnel in proper waste management and chemical waste handling procedures.
· Provision of sufficient waste disposal points and regular collection for disposal.
· Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.
· A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites).
· Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.
· Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force.
· Any unused chemicals or those with remaining functional capacity should be recycled.
· Proper storage and site practices to minimise the potential for damage or contamination of construction materials.
· Where it is unavoidable to have transient stockpiles of C&D material within the Project work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible.
· Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric.
· Skip hoist for material transport should be totally enclosed by impervious sheeting.
· Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site.
· The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.
· The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle.
· All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.
· The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading.
Table 4.18 Summary of Locations of the Sewage Pumping Stations
Sewage Pumping Station |
Location |
PS1 |
Inside North Apron of the former Kai Tak Airport |
PS2 |
Inside North Apron of the former Kai Tak Airport |
PS3 |
Inside North Apron of the former Kai Tak Airport |
PS1A |
Inside North Apron of the former Kai Tak Airport |
PS NPS |
Inside EMSD Sung Wong Toi Vehicle Repair & Maintenance Workshop (outside the boundary of the former Kai Tak Airport) |
Table 4.19 Zoning for the Current Assessment with reference to the Coverage of the Previous Studies
Sewage Pumping Station
|
Location
|
Previous Study
|
PS1 |
North Apron |
NAKTA
Decommissioning EIA
|
PS2 |
North Apron |
NAKTA Decommissioning EIA |
PS3 |
North Apron |
NAKTA
Decommissioning EIA
|
PS1A |
North Apron |
NAKTA
Decommissioning EIA
|
PS NPS |
EMSD Sung Wong Toi Vehicle Repair & Maintenance Workshop |
SEKDCFS
EIA
|
Table 4.20 Summary of findings in the relevant EIA reviewed
EIA reviewed |
Site Investigation Findings |
Date of Approval |
NAKTA Decommissioning EIA |
||
NAKTA Decommissioning EIA |
l 195 boreholes and 77 groundwater wells were installed for soil and groundwater contamination assessment. l
Land Contamination hotspots were identified.
Elevated levels of methane and anaerobic conditions were found in some areas.
l
The identified contaminated areas at the NAKTA had
been cleaned up during the period from 1998 to 2007 in accordance with the
Environmental Permit conditions.
|
September 1998 EIAO Register: AEIAR-002/1998 |
CAP, CAR/RAP for South East Kowloon Development Infrastructure at North Apron Area of Kai Tak Airport
|
l Accessed areas within NAKTA which were not covered in NAKTA decommissioning project due to accessibility issue. l 134 boreholes were constructed for the purpose of land contamination assessment. l Remediation were found to be necessary at 15 borehole locations with soil samples contaminated with metals, Benzo(a)pyrene and Total Petroleum Hydrocarbons (TPH) exceeding Dutch B/C levels. Findings from groundwater risk assessment indicated that the risk level associated with groundwater during construction was acceptable and no remediaton for groundwater would be necessary. Free product, identified at one of the groundwater sampling wells, however, required remediation. l Solidification / stabilization and biopiling were recommended as the remediation method for metal contaminated soil and organic contaminated soil respectively whereas free product recovery was recommended for groundwater remediation. |
CAP: June 2003 CAR/RAP: October 2005 |
Remediation Report for South East Kowloon Development Infrastructure at North Apron Area of Kai Tak Airport
|
l The Remediation works were conducted according to the CAR/RAP of South East Kowloon Development Infrastructure at North Apron Area of Kai Tak Airport under Contract No. KL39/03 approved by Environmental Protection Department (EPD), HKSAR, in 2005 Free product found in the groundwater monitoring well was manually skimmed off. For soil remediation, cement solidification/stabilization (CSS) was implemented for heavy metal contaminated soil and biopiling was operated for organic contaminated soil as proposed in the approved CAR/RAP. The remediation works were conducted in the period from December 2005 to March 2007.
|
August 2007 |
SEKDCFS EIA |
||
SEKDCFS EIA
|
l Reviewed SEKDFS EIA and NAKTA Decommissioning EIA l Identified Potential contamination hotspots within former Kai Tak Airport and the vicinity. |
September 2001 EIAO Register: AEIAR-044/2001 |
Table 4.21 Identification of Potential Land Contamination Impacts
Sewage Pumping
Station
|
Location in the
Kai Tak Development
|
Potential Land Contamination Impacts
|
PS1
|
North
Apron
|
û
|
PS2
|
North
Apron
|
û
|
PS3
|
North
Apron
|
û
|
PS1A
|
North
Apron
|
û
|
PS
NPS
|
EMSD
Sung Wong Toi Vehicle Repair & Maintenance Workshop
|
|
l Direct ingestion of contaminated soils through eating or drinking/smoking on site; and
l Dermal contact with contaminated soils.
Table 4.22 Summary of Reviewed Information on Potential Contaminative Land Uses
Potentially Contaminative Uses
|
Location
|
Historical Land Uses
|
Possible/Potential Sources of Contamination
|
EMSD Sung Wong Toi Vehicle Maintenance Workshop
|
Sung Wong Toi Road
|
l
1967: Workshop constructed with stockpiling at the
car park area of the main workshop
|
l Diesel storage tank of 1000 litres
l Battery cell, flammable liquid, oil sludge, acidic/alkaline
electrolytes, solvents, mineral/lube oil, refrigerants, paints, heavy metal
compounds, paints and scrap metal have been used, stored or generated
|
· Antiquities and Monuments Ordinance
· Environmental Impact Assessment Ordinance
· Hong Kong Planning Standards and Guidelines
· Technical Memorandum on Environmental Impact Assessment Process
· Criteria for Cultural Heritage Impact Assessment
· To excavate, carry on building works, plant or fell trees or deposit earth or refuse on or in a proposed monument or monument
· To demolish, remove, obstruct, deface or interfere with a proposed monument or monument
High:
|
Important
landscape or landscape resource of particularly distinctive character or high
importance, sensitive to relatively small changes.
|
Medium:
|
Landscape
or landscape resource of moderately valued landscape characteristics
reasonably tolerant to change.
|
Low:
|
Landscape
or landscape resource, the nature of which is largely tolerant to change.
|
Large:
|
The
landscape or landscape resource would suffer a major change.
|
Intermediate:
|
The
landscape or landscape resource would suffer a moderate change.
|
Small:
|
The
landscape or landscape resource would suffer slight or barely perceptible
changes.
|
Negligible:
|
The
landscape or landscape resource would suffer no discernible change.
|
Table 4.23 Relationship between Receptor Sensitivity and Impact Magnitude in Defining Impact Significance
Magnitude of Impact (Both Adverse and Beneficial Impact are assessed.) |
Large |
Slight / Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight / Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial / Slight |
Slight / Moderate |
Slight / Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
|
Receptor Sensitivity (of Landscape Resource, Landscape Character Area or VSRs) |
Note: All impacts are Adverse unless otherwise noted with Beneficial.
The sensitivity of VSRs is classified as follows:
High:
|
The VSR is highly sensitive
to any change in their viewing experience.
|
Medium:
|
The VSR is moderately
sensitive to any change in their viewing experience.
|
Low:
|
The VSR is only slightly
sensitive to any change in their viewing experience.
|
The magnitude of visual impacts is classified as follows:
Large:
|
The VSRs would suffer a
major change in their viewing experience.
|
Intermediate:
|
The VSRs would suffer a
moderate change in their viewing experience.
|
Small:
|
The VSRs would suffer a
small change in their viewing experience.
|
Negligible:
|
The VSRs would suffer no
discernible change in their viewing experience.
|
The significance of visual impacts is categorized as follows:
Substantial:
|
Adverse / beneficial impact where the proposal would cause
significant deterioration or improvement in existing visual quality.
|
Moderate:
|
Adverse / beneficial impact where the proposal would cause
a noticeable deterioration or improvement in existing visual quality.
|
Slight:
|
Adverse / beneficial impact where the proposal would cause
a barely perceptible deterioration or improvement in existing visual quality.
|
Insubstantial:
|
No discernible change in the existing visual quality.
|
Table 4.24 Landscape Resources / Landscape Character Areas and Their Sensitivity to Change
ID. No. |
Landscape Resources / Landscape Characters |
Sensitivity to Change (Low, Medium, High) |
Baseline Landscape Resources |
||
LR01 |
Olympic Garden This is a public local open space (~ 0.7ha) at the west end of the Prince Edward Road East and located under existing flyover network of Kowloon City, containing seating areas and planting beds. It is a popular resting and gathering place for local residents. Ornamental tree and shrub planting are provided throughout the open space. There are more than 100 trees with height around 4-13 m, spread 2-10 m, trunk diameter 120-500 mm. Species include Bauhinia blakeana, Callistemon viminalis, Chrysalidocarpus lutescens, Ficus microcarpa, Lagerstroemia speciosa and Roystonea regia. |
High |
LR02 |
Sung Wong Toi Garden This is a formal public open space (~ 0.4ha) where the Emperor’s Rock is kept comprising formal clipped hedgerows and screen tree planting along the periphery of the open space. There are approximately 30 mature trees with height around 4-8 m, spread 3-10 m, trunk diameter 150-700 mm. Species include Aleurites moluccana, Casuarina equisetifolia, Ficus microcarpa, Livistona chinensis and Macaranga tanarius. |
High |
LR03 |
Sung Wong Toi Playground This is a public open space (~ 0.9ha) comprising basketball courts, meandering footpaths, seating areas and ornamental tree and shrub planting. There are more than 100 trees with height around 4-13 m, spread 2-8 m, trunk diameter 120-450 mm. Species include Bauhinia blakeana, Bombax ceiba, Casuarina equisetifolia, Delonix regia and Ficus virens var. sublanceolata. |
High |
LR04A |
Rest Garden near Nga Tsin Wai Road The Rest Garden is a local open space (~ 0.2ha) with lush trees and shrub planting. It consists of children’s play equipment and seating areas under tree shade primarily for passive recreation. There are approximately 10 mature trees with height around 4-8 m, spread 2-10 m, trunk diameter 300-750 mm. Species include Aleurites moluccana and Ficus microcarpa. |
High |
LR04B |
Amenity area near Sha Po Road The amenity area consists of 26 trees of medium size and amenity value. The height of trees is around 5-6 m, spread 3 m, trunk diameter 150-200 mm. The species are mostly Bauhinia blakeana. |
Medium |
LR05 |
Shek Ku Lung Road Playground This is an open space (~1.4ha) with predominantly hard surface primarily for active recreation provision. Five-a-side football pitches and tennis courts are the main elements in the open space. Seating areas are also provided. There are more than 330 trees with height around 4-9 m, spread 3-8 m, trunk diameter 150-600mm. Species include Acacia confusa, Ailanthus fordii, Bauhinia blakeana, Bombax ceiba, Cassia surattensis, Delonix regia, Erythrina variegata, Ficus microcarpa, Macaranga tanarius, Melaleuca quinquenervia, Michelia x alba and Plumeria rubra. |
High |
LR06 |
Argyle Street Playground This is an open space (~ 0.8ha) with predominantly hard surface primarily for active recreation provision. Football pitches are the main elements in the open space. Seating areas are also provided at the northern side of the playground. There are approximately 20 trees with height around 4-7 m, spread 3-10 m, trunk diameter 180-400 mm. Species include Delonix regia and Lagerstroemia speciosa. |
High |
LR09 |
To Kwa Wan Recreation Ground This is an open space (~ 2.8ha) with predominantly hard surface primarily for active recreation provision. There are approximately 150 trees in these amenity areas with height around 3-13 m, spread 2-7 m, trunk diameter 120-500 mm. Species include Aleurites moluccana, Araucaria heterophylla, Bauhinia blakeana, Chrysalidocarpus lutescens, Juniperus chinensis cv. Kaizuca, Macaranga tanarius, Michelia x alba and Roystonea regia. |
High |
LR11 |
Kowloon Walled City Park and Carpenter Road Park Kowloon Walled City Park is a one of the most historic sites in Kowloon. It is a regional open space (~ 3.3ha) in early Qing Dynasty style. The park consists of a mix of active and passive recreation in a tree and shrub landscape setting. It is a popular park for local residents and tourists. There are more than 350 trees of high amenity value with height around 4-10 m, spread 2-8 m, trunk diameter 200-700 mm. Species include Aleurites moluccana, Bauhinia blakeana, Bombax ceiba, Delonix regia, Ficus microcarpa, Juniperus chinensis cv. Kaizuca, Lagerstroemia speciosa, Macaranga tanarius, Melaleuca quinquenervia, Michelia x alba and Roystonea regia. Carpenter Road Park is a regional open space (~ 5.4 ha). The park provides active recreation with cycle track and passive recreation in a tree and shrub landscape setting. There are more than 150 trees of high amenity value with height around 4-8 m, spread 2-8 m, trunk diameter 200-500 mm. Predominate species include Aleurites moluccana, Ficus microcarpa, Juniperus chinensis cv. Kaizuca and Roystonea regia. |
High |
LR17 |
Trees near Aviation Club Buildings There are approximately 32 mature trees at the periphery of the development boundary along Song Wong Toi Road with height around 4-13 m, spread 3-7 m, trunk diameter 180-350 mm. The amenity value of these trees is considered as high. Predominant species consist of Aleurites moluccana, Casuarina equisetifolia, Delonix regia, Ficus microcarpa, Macaranga tanarius and Morus alba. |
High |
LR18 |
Trees at the periphery of existing lot boundary along Sung Wong Toi Road There are approximately 10 semi-mature/mature trees at the periphery of the existing lot boundary along Sung Wong Toi Road with height around 3-9 m, spread 3-10 m, trunk diameter 200-500 mm. The amenity value of these trees is considered as medium. Predominant species consist of Bauhinia blakeana, Delonix regia, Ficus microcarpa, Macaranga tanarius, Michelia x alba and Phoenix roebelenii. |
Medium |
LR19 |
Trees in the Amenity Areas along Sung Wong Toi Road There are approximately 19 trees found in the Amenity Areas near the Ventilation Building of the Airport Tunnel along Sung Wong Toi Road with height around 3-12 m, spread 2-8 m, trunk diameter 150-500 mm. Predominant species consist of Acacia confusa, Aleurites moluccana, Bauhinia blakeana, Ficus microcarpa and Phoenix roebelenii. |
Medium |
LR22 |
Trees in Amenity Areas near the Interchange in Kowloon Bay There are more than 510 existing trees in the amenity areas near the interchange in Kowloon Bay with height around 4-13 m, spread 2-7 m, trunk diameter 150-350 mm. The amenity value of these trees is considered as medium. Predominant species are Aleurites moluccana, Bauhinia blakeana, Casuarina equisetifolia, Leucaena leucocephala and Melaleuca quinquenervia. |
Medium |
LR23 |
Trees in Amenity Areas of San Po Kong Interchange There are approximately 38 trees in the amenity areas of San Po Kong Interchange with height around 4-8 m, spread 2-5 m, trunk diameter 150-300 mm. The amenity value of these trees is considered as medium. Species include Ailanthus fordii, Callistemon viminalis, Cycas revoluta, Erythrina variegata, Lagerstroemia speciosa, Livistona chinensis and Phoenix roebelenii. |
Medium |
LR25 |
Trees near Grand Waterfront There are approximately 30 mature trees in the amenity areas near Grand Waterfront of height around 4-7 m, spread 3-7 m, trunk diameter 150-350 mm. The amenity value of these trees is considered as high. The species are mostly Bombax ceiba and Melaleuca quinquenervia. |
High |
LR28 |
Trees in North Apron of Former Airport There are more than 500 trees in the amenity areas and on the podium near Kai Tak Government Building with height around 3-12 m, spread 2-6 m, trunk diameter 150-400 mm. The amenity value of these trees is considered as medium. Predominant species consist of Aleurites moluccana, Archontophoenix alexandrae, Bauhinia blakeana, Caryota ochlandra, Cassia siamea, Delonix regia, Ficus microcarpa, Livistona chinensis and Phoenix roebelenii. |
Medium |
LR31A |
Kai Tak Nullah An open drainage channel running through the centre of the site with little landscape value. |
Low
|
LR31B |
Victoria Harbour It is a recognised and distinctive feature of Hong Kong worldwide, both as a tourist attraction and working port. The Harbour forms a centrepiece of the Hong Kong setting, with the airport runway forming a unique coastline to it. |
High |
Planned Landscape Resources |
||
LR34 |
Planned Multi-purpose Stadium Complex Plaza It is a planned landscape plaza at the Multi-purpose Stadium Complex which connects the Kai Tak City Centre and the Metro Park. |
High |
LR35 |
Planned Sung Wong Toi Park It is a planned district open space with a Sung Dynasty Theme at the Sports Hubs close to the hinterland. |
High |
LR36 |
Planned Station Square It is a planned open plaza outside the Kai Tak Station which interacts the commercial and residential uses at the Kai Tak City Centre. |
High |
LR38 |
Planned Chinese Cultural Garden It is a planned open space along the waterfront at Ma Tau Kok forms part of waterfront promenade at KTD. |
High |
LR31A |
Planned Kai Tak Nullah It will become either a decked open space or a new river channel with enhanced open space at the both sides of the river.
|
High |
Baseline Landscape Character Areas |
||
LCA01 |
Former Kai Tak Airport Landscape Character Area This comprises the former Kai Tak Airport where the future development is to be located. This area is flat, open, primarily hard standing with a few existing buildings that relate to the use of the former airport at the north. The area is currently occupied by various parties for different temporary uses. |
Low |
LCA02 |
Kowloon City and To Kwa Wan Grid Mixed Urban Landscape This is an area of primarily mixed residential / commercial use. This comprises a mix of low to high buildings for residential and commercial uses. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
LCA03 |
Kowloon Bay Late 20C / Early 21C Commercial / Residential Complex Landscape This is an area of primarily mixed residential / commercial use. This comprises a mix of low to high buildings for residential, commercial uses. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
LCA04 |
San Po Kong Industrial Urban Landscape This is an area of industrial use. This comprises medium rise industrial buildings. Some of the low rise industrial buildings have been demolished for future development. The Planning Consultancy Study for San Po Kong Flatted Factory is under studied. The streetscape is utilitarian with no soft landscape treatment. |
Low |
LCA05 |
Kwun Tong Industrial Urban Landscape This is an area of industrial use. This comprises medium to high rise industrial buildings. The streetscape is utilitarian with no soft landscape treatment. |
Low |
LCA09 |
To Kwa Wan Typhoon Shelter Landscape This is an area for typhoon shelter use in To Kwa Wan. It is substantially enclosed by coast and offshore breakwater. |
Low |
LCA12 |
Kowloon City Medium / High-rise Commercial Urban Landscape This is an area predominantly of commercial, industrial and retail land uses. This comprises a mix of medium and high rise buildings. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
Planned Landscape Character Areas |
||
LCA01A |
Planned Kai Tak City Centre Urban Landscape It is a new Kai Tak urban centre with a mixture of residential and commercial uses. The existing Kai Tak Nullah will be turned into a ‘river’ which it brings a natural element into the new modern city; and with natural landscape and plaza zone, the railway station shall be intended to locate in a park-like area. |
Medium |
LCA01B |
Planned Kai Tak Sports Hub Urban Landscape The Main Stadium will be the new icon of South East Kowloon. It will provide great views out to the water for spectators seated in the stadium. Programming along the dedicated pedestrian walkways within the landscape deck connecting across Road D2 shall enhance connectivity between spaces. Large open areas around stadiums shall act as a plaza-like for gathering and holding difference functions. |
Medium |
LCA01C |
Planned Kai Tak Metro Park Urban Landscape It consists of a 27ha Metro Park at the centre of South East Kowloon – both geographically and psychologically. Anchored by the Multi-purpose Stadium Complex at the northern base of the runway, this new landscape character area will be the signature public open space of South East Kowloon. |
High |
Table 4.25 Visual Sensitive Receivers (VSRs) and Their Sensitivity to Change
VSR Type & ID. |
Key Visually Sensitive Receiver (VSR) |
Number of Individuals (Many/ Medium/ Few/) |
Quality of Existing View (Good/ Fair/ Poor) |
Availability of Alternative Views (Yes/ No) |
Average Distance between VSRs and Impact Source (m) |
Degree of Visibility (Full/ Partial/ Glimpse) |
Duration of View (Long/ Medium/ Short) |
Frequency of View (Frequent/ Occasional/ Rare) |
Sensitivity to Change (Low, Medium, High) |
VSRs at Local Level |
|||||||||
R1 |
Sky Tower and adjacent residential developments along Sung Wong Toi Road |
Medium |
Fair |
No |
20m |
Full |
Long |
Frequent |
High |
R3 |
Regal Oriental Hotel and Low to Medium-rise Residential Development in Kowloon City |
Many |
Fair |
No |
100m |
Full |
Long |
Frequent |
High |
R6 |
Rhythm Garden |
Many |
Fair |
No |
40m |
Full |
Long |
Frequent |
High |
R7 |
Choi Hung Estate |
Many |
Fair |
No |
80m |
Full |
Long |
Frequent |
High |
R9 |
Richland Gardens |
Many |
Fair |
No |
60m |
Partial |
Long |
Frequent |
High |
R16 |
Grand Waterfront (same planned use under KTD) |
Many |
Fair |
Yes |
100m |
Full |
Long |
Frequent |
High |
R18 |
Low-rise Residential Development adjacent to Grand Waterfront (same planned use under KTD) |
Medium |
Fair |
Yes |
100m |
Partial |
Long |
Frequent |
High |
R19 |
R(A) zone at King Fuk Street |
Medium |
Fair |
No |
100m |
Full |
Long |
Frequent |
High |
R20 |
R(A) zone to the southeast of Tung Tau Estate |
Medium |
Fair |
No |
150m |
Full |
Long |
Frequent |
High |
R21 |
Le Billionaire and adjacent R(A) Zone in Kowloon City |
Medium |
Fair |
No |
110m |
Full |
Long |
Frequent |
High |
R22 |
Low-rise Residential Developments along Mok Cheong Street (planned CDA in operation stage) |
Medium |
Fair |
No |
200m |
Full |
Long |
Frequent |
High |
C4 |
Newport Centre (planned residential use under KTD) |
Medium |
Fair |
Yes |
100m |
Full |
Long |
Frequent |
Medium – Construction Stage High – Operation Stage |
GIC2 |
Ng Wah College, Lee Kau Yan Memorial School, Sir Robert Black Health Centre, Petrol Station |
Medium |
Fair |
No |
40m |
Full |
Medium |
Occasional |
Medium |
GIC3 |
Cognitio College |
Medium |
Fair |
No |
40m |
Full |
Medium |
Occasional |
Medium |
GIC5 |
Kai Tak Operation Base and Existing Electricity Substation (same planned uses under KTD) |
Few |
Fair |
No |
20m |
Full |
Medium |
Occasional |
Medium |
GIC6 |
EMSD Headquarters (same planned uses under KTD) |
Few |
Fair |
Yes |
20m |
Full |
Medium |
Occasional |
Medium (construction stage only) |
GIC18 |
EMSD Workshops (planned sewage pumping station and open space under KTD) |
Medium |
Fair |
No |
50m |
Full |
Long |
Occasional |
High (construction stage only) |
GIC25 |
Hong Kong Society for the Blind Factory (planned CDA in operation stage) |
Medium |
Fair |
No |
10m |
Full |
Long |
Frequent |
High |
O1 |
Visitors at Olympic Garden |
Medium |
Fair |
No |
100m |
Partial |
Short |
Occasional |
Medium |
O2 |
Visitors at Sung Wong Toi Garden |
Medium |
Fair |
No |
100m |
Partial |
Short |
Occasional |
High |
O3 |
Visitors at Sung Wong Toi Playground |
Medium |
Fair |
No |
80m |
Partial |
Short |
Occasional |
High |
O4 |
Visitors at Rest Garden next to Nga Tsin Wai Road |
Medium |
Fair |
No |
100m |
Partial |
Short |
Occasional |
High |
O5 |
Visitors at Shek Ku Lung Road Playground |
Medium |
Fair |
No |
60m |
Full |
Short |
Occasional |
High |
I1 |
Industrial Buildings in San Po Kong (planned residential use in operation stage) |
Many |
Poor |
No |
40m |
Full |
Long |
Occasional |
Medium |
I4 |
Industrial Development along Mok Cheong Street (planned CDA in operation stage) |
Medium |
Poor |
No |
400m |
Full |
Long |
Occasional |
Low – (Construction Stage) High – (Operation Stage) |
OU1 |
Tunnel Administration Building (same planned use under KTD) |
Few |
Fair |
No |
10m |
Full |
Long |
Occasional |
Medium |
OU3 |
Business and Industrial Developments in San Po Kong (Planned commercial use in operation stage) |
Many |
Fair |
No |
20m |
Full |
Long |
Occasional |
Medium |
T1 |
Motorists on Prince Edward Road East |
Many |
Fair |
Yes |
20m |
Full |
Short |
Occasional |
Low |
T2 |
Motorists on carriageway and Pedestrians on Footpaths along Sung Wong Toi Road |
Many |
Fair |
Yes |
20m |
Full |
Short |
Occasional |
Low |
T3 |
Motorists on Kwun Tong Bypass |
Many |
Fair |
Yes |
20m |
Full |
Short |
Occasional |
Low |
Planned VSR at KTD per se |
|||||||||
R23P |
Planned Residential Developments at Site 1A and 1B |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Frequent |
High |
R24P |
Planned Residential Developments at Site 1H, II, 1J, IK, IL, and 2A |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Frequent |
High |
C7P |
Planned Commercial Developments at Site 2A |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
GIC25P |
Planned GIC Developments at Site 3B, 3C |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
GIC26P |
Planned GIC Developments at Site 1C, 1D |
Medium |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
GIC27P |
Planned GIC Developments at Site 2C |
Medium |
Fair |
Yes |
20m |
Full |
Medium |
Occasional |
Medium |
GIC28P |
Planned GIC Developments at Site 2A |
Medium |
Fair |
Yes |
20m |
Full |
Medium |
Occasional |
Medium |
GIC29P |
Planned GIC Developments at Site 1A |
Medium |
Fair |
Yes |
550m |
Partial |
Medium |
Occasional |
Medium |
GIC30P |
Planned GIC Developments at Site 1B |
Many |
Fair |
Yes |
100m |
Full |
Medium |
Occasional |
Medium |
GIC31P |
Planned GIC Developments at Site 1N |
Medium |
Fair |
Yes |
100m |
Full |
Medium |
Occasional |
Medium |
CDA2P |
Planned CDA Developments at Kai Tak City Centre |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
Medium |
O21P |
Planned Multi-purpose Stadium Complex |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
High |
O22P |
Planned Sung Wong Toi Park |
Many |
Fair |
Yes |
20m |
Partial |
Medium |
Occasional |
High |
O23P |
Planned Station Square |
Many |
Fair |
Yes |
10m |
Full |
Medium |
Occasional |
High |
C = Commercial, GIC = Government/Institution/Community, O = Open space, OU = Other use, R = Residential, T = Transport related.
Table 4.26 Landscape Impacts of the Proposed Works during Construction Phase
ID No. |
Landscape Resources/ Landscape Character Areas |
Source of Impact |
Description of Impacts |
Magnitude of Impacts |
LR28 |
Trees in North Apron of Former Airport |
·
sewage
pumping stations (the DP2 Project) construction to be commenced in around mid 2009
|
· Approximately 3 trees will be affected by PS1 and 1 tree will be affected by PS2. The height of trees are around 4-6 m, spread 2-4 m, trunk diameter 200 mm. The amenity value of these trees is considered as medium. The species consist of Cassia siamea and Livistona chinensis. |
Small |
LCA01 |
Former Kai Tak Airport Landscape Character Area (KTD in Operation Phase) |
·
sewage
pumping stations (the DP2 Project) construction to be commenced in around mid 2009
|
· Impact due to construction works, excavation works, temporary works and associated impacts |
Small |
LCA02 |
Kowloon City and To Kwa Wan Grid Mixed Urban Landscape |
·
sewage
pumping stations (the DP2 Project) construction to be commenced in around mid 2009
|
· Impact due to construction works, excavation works, temporary works and associated impacts |
Negligible |
LCA04 |
San Po Kong Industrial Urban Landscape |
·
sewage
pumping stations (the DP2 Project) construction to be commenced in around mid 2009
|
· Impact due to construction works, excavation works, temporary works and associated impacts |
Negligible |
LCA05 |
Kwun Tong Industrial Urban Landscape |
·
sewage
pumping stations (the DP2 Project) construction to be commenced in around mid 2009
|
· Impact due to construction works, excavation works, temporary works and associated impacts |
Negligible |
LCA09 |
To Kwa Wan Typhoon Shelter Landscape |
·
sewage
pumping stations (the DP2 Project) construction to be commenced in around mid 2009
|
· Impact due to construction works, excavation works, temporary works and associated impacts |
Negligible |
LCA12 |
Kowloon City Medium / High-rise Commercial Urban Landscape |
·
sewage
pumping stations (the DP2 Project) construction to be commenced in around mid
2009
|
· Impact due to construction works, excavation works, temporary works and associated impacts |
Negligible |
Table 4.27 Significance of Landscape Impacts in Construction and Operation Phases
ID. No. |
Landscape Resources / Landscape Characters |
Sensitivity to Change (Low, Medium, High) |
Magnitude of Change (Negligible, Small, Intermediate, Large) |
Impact Significance Threshold BEFORE Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold AFTER Mitigation (Insubstantial, Slight, Moderate, Substantial) |
|||||||
Construction |
Operation |
||||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|
DAY 1 |
YEAR 10 |
|||||
Existing Landscape Resources |
|||||||||||||
LR01 |
Olympic Garden |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR02 |
Sung Wong Toi Garden |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR03 |
Sung Wong Toi Playground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR04A |
Rest Garden and amenity area near Nga Tsin Wai Road |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR04B |
Amenity area near Sha Po Road |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR05 |
Shek Ku Lung Road Playground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR06 |
Argyle Street Playground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR09 |
To Kwa Wan Recreation Ground |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR11 |
Kowloon Walled City Park and Carpenter Road Park |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR17 |
Trees near Aviation Club Buildings |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR18 |
Trees at the periphery of existing lot boundary along Sung Wong Toi Road |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR19 |
Trees in the Amenity Areas along Sung Wong Toi Road |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR22 |
Trees in Amenity Areas near the Interchange in Kowloon Bay |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR23 |
Trees in Amenity Areas of San Po Kong Interchange |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR25 |
Trees near Grant Waterfront |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR28 |
Trees in North Apron of Former Airport |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1, CM2 and OM1 |
Slight |
Insubstantial |
Insubstantial |
||
LR31A |
Kai Tak Nullah |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LR31B |
Victoria Harbour |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
Planned Landscape Resources |
|||||||||||||
LR34 |
Planned Multi-purpose Stadium Complex Plaza |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR35 |
Planned Sung Wong Toi Park |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR36 |
Planned Station Square |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
LR38 |
Planned Chinese Cultural Garden |
- |
High |
- |
Negligible |
- |
Insubstantial |
- |
- |
- |
Insubstantial |
||
Existing Landscape Character Areas |
|||||||||||||
LCA01 |
Former Kai Tak Airport Landscape Character Area (KTD in Operation Phase) |
Low |
- |
Small |
- |
Slight |
- |
CM1 to CM4 |
Slight |
- |
- |
||
LCA02 |
Kowloon City and To Kwa Wan Grid Mixed Urban Landscape |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
Insubstantial |
Insubstantial |
Insubstantial |
||
LCA04 |
San Po Kong Industrial Urban Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
Insubstantial |
Insubstantial |
Insubstantial |
||
LCA05 |
Kwun Tong Industrial Urban Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
Insubstantial |
Insubstantial |
Insubstantial |
||
LCA09 |
To Kwa Wan Typhoon Shelter Landscape |
Low |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
LCA12 |
Kowloon City Medium / High-rise Commercial Urban Landscape |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
||
Planned Landscape Character Areas |
|||||||||||||
LCA01A |
Planned Kai Tak City Centre Urban Landscape |
- |
Medium |
- |
Small |
- |
Slight |
OM1, OM2 and OM5 |
- |
Insubstantial |
Insubstantial |
||
LCA01B |
Planned Kai Tak Sports Hub Urban Landscape |
- |
Medium |
- |
Small |
- |
Slight |
OM1, OM2 and OM5 |
- |
Insubstantial |
Insubstantial |
||
LCA01C |
Planned Kai Tak Metro Park Urban Landscape |
- |
High |
- |
Negligible |
- |
Slight |
OM1, OM2 and OM5 |
- |
Insubstantial |
Insubstantial |
||
LCA01E |
Planned Kai Tak South Apron Corner Urban Landscape |
|
Medium |
- |
Negligible |
- |
Insubstantial |
- |
- |
Insubstantial |
Insubstantial |
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: It is assumed that during the construction phase of DP2, part of the development in LCA01A will be completed. The impact on these areas due to DP2 during construction is assessed.
Table 4.28 Significance of Visual Impacts in the Construction and Operation Phases (Note: All impacts adverse unless otherwise noted)
VSR Type & ID. |
Key Visually Sensitive Receiver (VSR) |
Main Source of Visual Impact |
Magnitude of Impact (Negligible, Small, Intermediate, Large) |
Receptor Sensitivity (Low, Medium, High) |
Impact Significance Threshold Before Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold After Mitigation (Insubstantial, Slight, Moderate, Substantial) |
|||||
Construction |
Operation |
|||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
DAY 1 |
YEAR 10 |
|||||
Existing VSR |
||||||||||||
R1 |
Sky Tower and adjacent residential developments along Sung Wong Toi Road |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R3 |
Regal Oriental Hotel and Low to Medium-rise Residential Development in Kowloon City |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R6 |
Rhythm Garden |
DP2 |
Small |
- |
High |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
R7 |
Choi Hung Estate |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R9 |
Richland Gardens |
DP2 |
Small |
- |
High |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
R16 |
Grand Waterfront (same planned use under KTD) |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R18 |
Low-rise Residential Development adjacent to Grand Waterfront (same planned use under KTD) |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R19 |
R(A) zone at King Fuk Street |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R20 |
R(A) zone to the southeast of Tung Tau Estate |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R21 |
Le Billionaire and adjacent R(A) Zone in Kowloon City |
DP2 |
Small |
Small |
High |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
R22 |
Low-rise Residential Developments along Mok Cheong Street (planned CDA in operation stage) |
DP2 |
Intermediate |
Intermediate |
High |
High |
Moderate |
Substantial |
CM3, CM4, |
Slight |
Slight |
Slight |
C4 |
Newport Centre (planned residential use under KTD) |
DP2 |
Intermediate |
Intermediate |
Medium |
High |
Moderate |
Substantial |
CM3, CM4, |
Slight |
Slight |
Slight |
GIC2 |
Ng Wah College, Lee Kau Yan Memorial School, Sir Robert Black Health Centre, Petrol Station |
DP2 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, |
Slight |
Slight |
Slight |
GIC3 |
Cognitio College |
DP2 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
GIC5 |
Kai Tak Operation Base and Existing Electricity Substation (same planned uses under KTD) |
DP2 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
GIC6 |
EMSD Headquarters (same planned uses under KTD) |
DP2 |
Large |
- |
Medium |
- |
Moderate |
- |
CM3, CM4, |
Slight |
- |
- |
GIC18 |
EMSD Workshops (planned sewage pumping station and open space under KTD) |
DP2 |
Intermediate |
Intermediate |
High |
High |
Moderate |
Moderate |
CM3, CM4, |
Slight |
Slight |
Slight |
GIC25 |
Hong Kong Society for the Blind Factory (planned CDA in operation stage) |
DP2 |
Large |
Intermediate |
Medium |
High |
Moderate |
Substantial |
CM3, CM4, |
Slight |
Moderate |
Slight |
O1 |
Visitors at Olympic Garden |
DP2 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4 |
Insubstantial |
Insubstantial |
Insubstantial |
O2 |
Visitors at Sung Wong Toi Garden |
DP2 |
Intermediate |
Intermediate |
High |
High |
Moderate |
Moderate |
CM3, CM4, |
Slight |
Slight |
Slight |
O3 |
Visitors at Sung Wong Toi Playground |
DP2 |
Large |
Intermediate |
High |
High |
Moderate |
Moderate |
CM3, CM4, |
Slight |
Slight |
Slight |
O4 |
Visitors at Rest Garden next to Nga Tsin Wai Road |
DP2 |
Small |
- |
High |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
O5 |
Visitors at Shek Ku Lung Road Playground |
DP2 |
Small |
- |
High |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
I1 |
Industrial Buildings in San Po Kong (planned residential use in operation stage) |
DP2 |
Small |
- |
Medium |
- |
Slight |
- |
CM3, CM4 |
Insubstantial |
- |
- |
I4 |
Industrial Development along Mok Cheong Street (planned CDA in operation stage) |
DP2 |
Small |
Small |
Low |
High |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
OU1 |
Tunnel Administration Building (same planned use under KTD) |
DP2 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
OU3 |
Business and Industrial Developments in San Po Kong (Planned commercial use in operation stage) |
DP2 |
Small |
Small |
Medium |
Medium |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
T1 |
Motorists on Prince Edward Road East |
DP2 |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
T2 |
Motorists on carriageway and Pedestrians on Footpaths along Sung Wong Toi Road |
DP2 |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
T3 |
Motorists on Kwun Tong Bypass |
DP2 |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM3, CM4, |
Insubstantial |
Insubstantial |
Insubstantial |
Planned VSR |
||||||||||||
R23P |
Planned Residential Developments at Site 1A and 1B |
DP2 |
- |
Small |
- |
High |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
R24P |
Planned Residential Developments at Site 1H, II, 1J, IK, IL, and 2A |
DP2 |
- |
Intermediate |
- |
High |
- |
Moderate |
OM1, OM2, OM5 |
- |
Slight |
Slight |
C7P |
Planned Commercial Developments at Site 2A |
DP2 |
- |
Small |
- |
Medium |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
GIC25P |
Planned GIC Developments at Site 3B, 3C |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
GIC26P |
Planned GIC Developments at Site 1C, 1D |
DP1 |
- |
Intermediate |
- |
Medium |
- |
Moderate |
OM1, OM2, OM5 |
- |
Slight |
Insubstantial |
GIC27P |
Planned GIC Developments at Site 2C |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
GIC28P |
Planned GIC Developments at Site 2A |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
GIC29P |
Planned GIC Developments at Site 1A |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
GIC30P |
Planned GIC Developments at Site 1B |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
GIC31P |
Planned GIC Developments at Site 1N |
DP1 |
- |
Small |
- |
Medium |
- |
Slight |
OM1, OM2, OM5 |
- |
Insubstantial |
Insubstantial |
CDA2P |
Planned CDA Developments at Kai Tak City Centre |
DP2 |
- |
Intermediate |
- |
Medium |
- |
Moderate |
OM1, OM2 OM5 |
- |
Slight |
Insubstantial |
O21P |
Planned Multi-purpose Stadium Complex |
DP2 |
- |
Small |
- |
High |
- |
Slight |
OM1, OM2 OM5 |
- |
Insubstantial |
Insubstantial |
O22P |
Planned Sung Wong Toi Park |
DP2 |
- |
Small |
- |
High |
- |
Slight |
OM1, OM2 OM5 |
- |
Insubstantial |
Insubstantial |
O23P |
Planned Station Square |
DP2 |
- |
Small |
- |
High |
- |
Slight |
OM1, OM2 OM5 |
- |
Insubstantial |
Insubstantial |
C = Commercial, GIC = Government/Institution/Community, O = Open space, OU = Other use, R = Residential, T = Transport related.
Table 4.29 Landscape and Visual Mitigation Measures during Construction Phase
ID No. |
Landscape and Visual Mitigation Measure |
Funding Agency |
Implementation Agency |
CM11 |
All existing trees shall be carefully protected during construction. |
CEDD |
CEDD |
CM21 |
Trees unavoidably affected by the works shall be transplanted where practical. Detailed transplanting proposal will be submitted to relevant government departments for approval in accordance with ETWBC 2/2004 and 3/2006. Final locations of transplanted trees shall be agreed prior to commencement of the work. |
CEDD |
CEDD |
CM31 |
Control of night-time lighting. |
CEDD |
CEDD |
CM41 |
Erection of decorative screen hoarding. |
CEDD |
CEDD |
Note: (1) Mitigation measures refer to Good
Site Practices.
Table 4.30 Landscape and Visual Mitigation Measures during Operation Phase
ID No. |
Landscape and Visual Mitigation Measure |
Funding Agency |
Implementation Agency |
Maintenance Agency |
OM1 |
Compensatory tree planting should be incorporated into the proposed projects where trees are affected. |
CEDD |
CEDD |
DSD |
OM2 |
Tall buffer screen tree / shrub / climber planting, green roof and vertical green where appropriate should be incorporated to soften hard engineering structures and facilities. |
CEDD |
CEDD |
DSD |
OM3 |
Not used |
N/A |
N/A |
N/A |
OM4 |
Not used |
N/A |
N/A |
N/A |
OM5 |
Aesthetically pleasing design as regard to the form, material and finishes shall be incorporated to all buildings, engineering structures and associated infrastructure facilities. |
CEDD |
CEDD |
DSD |
Residual Landscape Impacts in Construction Phase
Residual Visual Impact in Construction Phase
Residual Visual Impact in Operation Phase
· to provide a database against which any environmental impacts of the DP2 Project can be determined;
· to provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;
· to monitor the performance of the Project and the effectiveness of mitigation measures;
· to verify the environmental impacts predicted in this EIA;
· to determine project compliance with regulatory requirements, standards and government policies;
· to take remedial action if unexpected problems or unacceptable impacts arise; and
· to provide data to enable an environmental audit.
Table 4.31 Implementation Schedule for Air Quality Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S4.2.17 |
Implementation of dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation. The following mitigation measures, good site practices and a comprehensive environmental audit programme are recommended to minimize cumulative dust impacts. · Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission. · Misting for the dusty material should be carried out before being loaded into the vehicle. · Any vehicle with an open load carrying area should have properly fitted side and tail boards. · Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin. · The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation. · The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials. · Vehicle washing facilities should be provided at every vehicle exit point. · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores. · Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet. · Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides. · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites. |
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM & Air Quality Objective |
S4.2.18 |
(i) Provision of deodorization system and odour sources being enclosed; and (ii) Commissioning tests for all deodorization system should be included in the Design and Construction Contract Document. |
PS1, PS |
DSD (for the initial phase of PS1 & PS3) CEDD
(for PS1A,
PS2, SPS at Site 5A1, PS6, and the ultimate phase of PS1 & PS3) |
|
|
|
|
EIAO-TM |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 4.32 Implementation Schedule for Noise Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S4.3 |
Use of quiet PME, movable barriers barrier for Asphalt Paver, Breaker, Excavator and Hand-held breaker and full enclosure for Air Compressor, Bar Bender, Concrete Pump, Generator and Water Pump. |
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM, NCO |
S4.3 |
Good Site Practice: · Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program. · Silencers or mufflers on construction equipment should be utilized and should be properly maintained during the construction program. · Mobile plant, if any, should be sited as far away from NSRs as possible. · Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum. · Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs. Material stockpiles and other structures should be effectively utilized, wherever practicable, in screening noise from on-site construction activities. · |
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM, NCO |
4.3 |
All the ventilation fans installed in sewage pumping stations should be provided with silencers or acoustics treatment. |
PS1, PS1A, PS2, PS3, SPS at Site 5A1 and PS6 |
DSD (for the initial phase of PS1 & PS3) CEDD
(for PS1A, PS2, SPS at Site 5A1, PS6, and the ultimate phase of PS1 & PS3) |
|
|
|
|
EIAO-TM |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 4.33 Implementation Schedule for Water Quality Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S4.4 |
Operational Phase
Dual power supply or
emergency generator should be provided at all the SPSs to secure electrical
power supply; Standby pumps should be
provided at all SPSs to ensure smooth operation of the SPS during maintenance
of the duty pumps; An alarm should be installed
to signal emergency high water level in the wet well at all SPSs; and For all unmanned SPSs, a
remote monitor system connecting SPSs with the control station through
telemetry system should be provided so that swift actions could be taken in
case of malfunction of unmanned facilities.
|
PS1, PS |
DSD (for the initial phase of PS1 & PS3) CEDD
(for PS1A,
PS2, SPS at Site 5A1, PS6, and the ultimate phase of PS1 & PS3) |
|
|
|
|
EIAO-TM, WPCO |
S4.4 |
Construction Phase
Construction site runoff and drainage
Construction site runoff and drainage should be prevented or minimised
in accordance with the guidelines stipulated in the EPD's Practice Note for
Professional Persons, Construction Site Drainage (ProPECC PN 1/94).
Good housekeeping and stormwater best management practices, as detailed in
below, should be implemented to ensure that all construction runoff complies
with WPCO standards and that no unacceptable impact on the WSRs arises due to
construction of the Project. All discharges from the construction site
should be controlled to comply with the standards for effluents discharged
into the Victoria Harbour WCZ under the TM-DSS.
|
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S4.4 |
Sewage Effluent
Construction work force sewage discharges on site are expected to be
connected to the existing trunk sewer or sewage treatment facilities.
The construction sewage may need to be handled by portable chemical toilets
prior to the commission of the on-site sewer system. Appropriate
numbers of portable toilets shall be provided by a licensed contractor to
serve the large number of construction workers over the construction
site. The Contractor shall also be responsible for waste disposal and
maintenance practices.
|
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO |
S4.4 |
Refuse and Debris
It is recommended that collection and removal of floating refuse should be performed at regular intervals on a daily basis. The contractor should be responsible for keeping the water within the site boundary and the neighbouring water free from rubbish during construction. |
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO |
S4.4 |
Stormwater Discharges
Minimum distances of 100 m shall be maintained between the existing or planned stormwater discharges and the existing or planned seawater intakes.
|
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM, WPCO |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 4.34 Implementation Schedule for Waste Management Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S4.5 |
Good Site Practices
It is not anticipated that adverse waste management related impacts
would arise, provided that good site practices are adhered to.
Recommendations for good site practices during the construction activities
include:
· Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site. · Training of site personnel in proper waste management and chemical waste handling procedures. · Provision of sufficient waste disposal points and regular collection for disposal. · Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers. · A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites). |
Work Sites / During Construction |
Contractor |
|
|
|
|
EIAO-TM, WDO |
S4.5
S4.5 |
Waste Reduction Measures
Good management and control can
prevent the generation of a significant amount of waste. Waste
reduction is best achieved at the planning and design stage, as well as by
ensuring the implementation of good site practices. Recommendations to
achieve waste reduction include:
· Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal. · Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force. · Any unused chemicals or those with remaining functional capacity shall be recycled. · Proper storage and site practices to minimise the potential for damage or contamination of construction materials.
Construction and Demolition Materials
Mitigation measures and good site
practices should be incorporated in the contract document to control
potential environmental impact from handling and transportation of C&D
material. The mitigation measures include:
· Where it is unavoidable to have transient stockpiles of C&D material within the Project work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible. |
Work sites / during construction
Work site / during construction |
Contractor
Contractor and Independent Environmental Checker
|
|
Ö
Ö |
|
|
EIAO-TM, WDO
ETWB TCW No. 33/2002, 31/2004, 19/2005 |
|
· Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric. · Skip hoist for material transport should be totally enclosed by impervious sheeting. · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site. · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores. · The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle. · All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet. · The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading. |
|
|
|
|
|
|
|
|
When delivering inert C&D material to public fill reception
facilities, the material should consist entirely of inert construction waste
and of size less than 250mm or other sizes as agreed with the Secretary of
the Public Fill Committee. In order to monitor the disposal of the
surplus C&D material at the designed public fill reception facility and
to control fly tipping, a trip-ticket system as stipulated in the ETWB TCW
No. 31/2004 “Trip Ticket System for Disposal of Construction and Demolition
Materials” should be included as one of the contractual requirements and
implemented by an Environmental Team undertaking the Environmental Monitoring
and Audit work. An Independent Environmental Checker should be
responsible for auditing the results of the system.
|
|
|
|
|
|
|
|
S4.5 |
Chemical Waste
After use, chemical wastes (for example, cleaning fluids, solvents,
lubrication oil and fuel) should be handled according to the Code of Practice
on the Packaging, Labelling and Storage of Chemical Wastes. Spent chemicals
should be collected by a licensed collector for disposal at the CWTF or other
licensed facility, in accordance with the Waste Disposal (Chemical Waste)
(General) Regulation.
|
Work Sites / during construction |
Contractor |
|
Ö |
|
|
Waste Disposal (Chemical Waste) (General) Regulation
Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes |
S4.5 |
General Refuse
General refuse should be stored in enclosed bins or compaction units
separate from C&D material. A licensed waste collector should be employed
by the contractor to remove general refuse from the site, separately from
C&D material. Effective collection and storage methods (including
enclosed and covered area) of site wastes would be required to prevent waste
materials from being blown around by wind, wastewater discharge by flushing
or leaching into the marine environment, or creating odour nuisance or pest
and vermin problem.
|
|
|
|
|
|
|
|
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 4.35 Implementation Schedule for Land Contamination
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S4.6.25 |
For EMSD Sung Wong Toi Vehicle Maintenance Workshop · EMSD as the current occupant of the EMSD Headquarters should conduct a land contamination assessment and complete the necessary remediation according to the relevant guidelines prior to handing over the site to the Government for redevelopment in the future. |
EMSD Sung Wong Toi Vehicel Maintenance Workshop / Prior to construction of PS NPS |
EMSD |
Ö |
|
|
Ö |
“Guidance Note for Contaminated Land Assessment and Remediation”
“Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management
“Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair /Dismantling Workshop“ |
Table 4.36 Implementation Schedule for Landscape and Visual Impact
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S4.8 |
Construction Phase · All existing trees shall be carefully protected during construction. · Trees unavoidably affected by the works should be transplanted where practical. Detailed transplanting proposal will be submitted to relevant government departments for approval in accordance with ETWBC 2/2004 and 3/2006. Final locations of transplanted trees should be agreed prior to commencement of the work. · Control of night-time lighting. · Erection of decorative screen hoarding.
|
Working site / During Construction Phase |
Contractor |
|
|
|
|
EIAO-TM |
S4.8 |
Operation Phase · Compensatory tree planting should be incorporated into the proposed projects where trees are affected. · Tall buffer screen tree / shrub / climber planting should be incorporated to soften hard engineering structures and facilities. · Aesthetically pleasing design as regard to the form, material and finishes shall be incorporated to all buildings, engineering structures and associated infrastructure facilities. |
Working site / During Design stage and Operation Phase |
DSD/CEDD |
|
|
|
|
EIAO-TM |
* Des - Design, C - Construction, O – Operation, and Dec – Decommissioning