Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Impact Assessment Report
Contents
5............ EIA on Decommissioning of the remaining parts (Ex-GFS Building and Radar Station) of the former Kai Tak Airport
5.5 Waste Management Implications
5.7 Landscape and Visual Impact
5.8 Environmental Monitoring and Audit Requirement
5.9 Implementation Schedule of the Proposed Mitigation Measures
List of Tables
Table 5.1 Summary of Environmental Impacts
Table 5.2 Hong Kong Air Quality Objectives
Table 5.4 Summary of Representative Air Sensitive Receivers
Table 5.5 Construction Noise Criteria for Activity other than Percussive Piling
Table 5.6 Summary of Water Quality Objectives for the Victoria Harbour WCZ
Table 5.7 WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes
Table 5.8 Summary Statistics of Marine Water Quality in the Victoria Harbour WCZ in 2006
Table 5.10 Pollution Levels Measured at KTAC in October 2005
Table 5.11 Pollution Levels Measured at KTAC in January 2006
Table 5.12 Summary of Estimated C&D Material
Table 5.13 Summary of findings in the relevant EIA reviewed
Table 5.14 Summary of Soil Samples Exceeding the Dutch B/C Levels
Table 5.15 Summary of Groundwater Samples Exceeding the Dutch B/C Values
Table 5.16 Evaluation of Significance of Risk Due to Groundwater Contamination
Table 5.18 Location, Depth and Estimated Quantity of Contaminated Soil
Table 5.19 Estimated Quantity of Different Type of Contaminated Soil
Table 5.20 Treatment Technologies for Contaminated Soil with Metals / TPH /SVOCs
Table 5.21 List of Soil Remediation Technologies for Metals / TPH / SVOCs Contaminated Soil
Table 5.22 Summary of Proposed Remediation Methods for Metals / TPH / SVOCs Contaminated Soil
Table 5.23 Universal Treatment Standards (UTS) for the Concerned Heavy Metals
Table 5.25 Landscape Resources / Landscape Character Areas and Their Sensitivity to Change
Table 5.26
VSRs and Their Sensitivity to Change
Table 5.27 Significance of Landscape Impacts in Construction Phase
Table 5.29 Implementation Schedule for Air Quality Measures
Table 5.30 Implementation Schedule for Noise Measures
Table 5.31 Implementation Schedule for Water Quality Measures
Table 5.32 Implementation Schedule for Waste Management Measures
Table 5.33 Implementation Schedule for Land Contamination Measures
Table 5.1 Summary of Environmental Impacts
|
Decommissioning Phase |
Operational Phase |
Air |
|
û |
Noise |
|
û |
Water Quality |
|
û |
Waste Management |
|
û |
Land Contamination |
|
û |
Hazard to Life |
û |
û |
Cultural Heritage |
û |
û |
Landscape and Visual Impact |
|
û |
Ecological Impact |
û |
û |
Fisheries Impact |
û |
û |
Table 5.2
Pollutant |
Maximum Concentration (µg m-3) (1) |
|||
Averaging Time |
||||
1 hour (2) |
8 hour (3) |
24 hour (3) |
Annual (4) |
|
Total Suspended Particulates (TSP) |
- |
- |
260 |
80 |
Respirable Suspended Particulates (RSP) (5) |
- |
- |
180 |
55 |
|
800 |
- |
350 |
80 |
Nitrogen Dioxide (NO2) |
300 |
- |
150 |
80 |
Carbon Monoxide (CO) |
30,000 |
10,000 |
- |
- |
Photochemical Oxidants (as Ozone, O3) (6) |
240 |
- |
- |
- |
Notes:
(1) Measured at 298 K and 101.325 kPa.
(2) Not to be exceeded more than three times per year.
(3) Not to be exceeded more than once per year.
(4) Arithmetic mean.
(5) Suspended particulates in air with a nominal aerodynamic diameter of 10 mm or smaller.
(6) Photochemical oxidants are determined by measurement of ozone only.
Table 5.3 Annual Average Concentrations of Pollutants in Year 2006 at EPD’s Sham Shui Po and Kwun Tong Air Quality Monitoring Stations
Pollutant |
Annual Average AQO (mg m-3) |
Year 2006 Annual Average Concentration (mg m-3) |
|
Sham Shui Po station |
Kwun Tong station |
||
TSP |
80 |
79 |
75 |
RSP |
55 |
55 |
55 |
NO2 |
80 |
67 |
61 |
SO2 |
80 |
24 |
19 |
Table 5.4 Summary of Representative Air Sensitive Receivers
ASRs |
District (1) |
Location |
Existing / Planned Land Use |
Max. Building Height, m (2) |
Distance to DP3a Boundary, m |
A7 |
KT |
CAC Tower |
Commercial |
57 |
1044 |
A8 |
KT |
Bite Industrial Building |
Industrial |
30 |
799 |
A9 |
KT |
Wharf T&T Square |
Commercial |
45 |
543 |
A10 |
KT |
Hoi Bun Road Park |
Recreation |
1.5 |
449 |
A11 |
NTK |
Kowloon Bay Factory Estate |
Industrial |
24 |
242 |
A12 |
NTK |
Kowloon Bay Motor Vehicle Exam Centre |
Industrial |
6 |
219 |
A13 |
NTK |
New Kowloon Bay Motor Vehicle Exam Centre |
Industrial |
3 |
166 |
A14 |
NTK |
Kai Fok Industrial Centre |
Industrial |
24 |
566 |
A15 |
KB |
Sing Tao Building |
Commercial |
30 |
662 |
Note: (1) KT – Kwun Tong; NTK – Ngau Tau Kok; KB – Kowloon Bay
(2) The maximum height for Planned ASR was made reference to the RODP.
Identify the potentially fugitive dust emission during decommissioning phase; and
Assess the significance of construction dust emissions from decommissioning activities.
· Cruise Terminal Development and related advance works
· Infrastructure works at North Apron, Phase 1 - Housing Sites and Government Offices
· Kai Tak Nullah modification works
· Infrastructure works at runway and Metro Park
· Infrastructure works at North Apron, Phase 2
· Trunk Road T2 and infrastructure works at South Apron
· SCL Construction
· CKR Construction
· Anderson Road Project, etc.
The excavation area should be limited to as small in size as possible and backfilled with clean and/or treated soil shortly after excavation work.
The exposed excavated area should be covered by the tarpaulin during night time.
The top layer soils should be sprayed with fine misting of water immediately before the excavation.
Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust and other air pollutants emission.
Misting for the dusty material should be carried out before being loaded into the vehicle.
Any vehicle with an open load carrying area should have properly fitted side and tail boards.
Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin.
The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation.
The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials.
Vehicle washing facilities should be provided at every vehicle exit point.
The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.
Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet.
Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides.
Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.
Solidification
The solidification pit/area should be provided with dust suppression measures.
Handling and mixing of cement shall follow Air Pollution Control (Construction Dust) Regulation to limit cement emission.
The bin should be covered during residence period after mixing process.
Biopiling
During the course of biopile formation, the stockpiled soils at the biopiles should be covered by tarpaulin or low permeable sheet to avoid fugitive emissions of dust or any air pollutants from the biopiles affecting the surrounding environment and to minimise runoff from the stockpiled soils. Biopile(s) should be covered by impermeable sheeting (such that no longer than 5m of a biopile should be exposed to open air) to avoid fugitive emissions of dust or any pollutants from the biopile(s).
Upon formation of a biopile, the biopile should be covered by low permeable geotextiles to prevent dust emission and runoff.
During the operation of biopile, the biopiles should be fully covered to control the extraction of VOCs.
The vented air from the biopile(s) should be connected to blower and carbon adsorption system with 99% control efficiency for treatment before release to the atmosphere. Exhaust air from the blower and carbon adsorption system should be monitored for TVOC bi-weekly to check the performance of the carbon filter. The frequency of monitoring might be adjusted subject to review on site. The location of the exhaust of the carbon filter should be sited as far away as possible from the nearby ASRs.
Spent activated carbon of the carbon adsorption system should be replaced at appropriate intervals such that the TVOC emission concentration from the system is acceptable (i.e. the measured TVOC concentration is below 20ppm).
· TM on Environmental Impact Assessment Process (EIAO-TM)
· TM on Noise from Construction Work other than Percussive Piling (GW-TM)
· TM on Noise from Construction Work in Designated Areas (DA-TM)
· TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM)
Table 5.5 Construction Noise Criteria for Activity other than Percussive Piling
Time Period |
Basic Noise Level (BNLs) |
||
ASR A |
ASR B |
ASR C |
|
Evening (1900 to 2300 hours) (1) |
60 |
65 |
70 |
Night (2300 to 0700 hours) |
45 |
50 |
55 |
Notes: (1) Includes Sundays and Public Holidays during daytime and evening
· Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program.
· Mobile plant, if any, should be sited as far away from NSRs as possible.
· Machines and plant (such as trucks) that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.
· Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.
· Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.
l Annex 6 – Criteria for Evaluating Water Pollution
l Annex 14 – Guidelines for Assessment of Water Pollution.
Table 5.6 Summary of Water Quality Objectives for the Victoria Harbour WCZ
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
Dissolved oxygen (DO) within 2m of the seabed |
Not less than 2.0mg/l for 90% of samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0mg/l for 90% of samples |
Marine waters |
pH |
To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2 |
Marine waters |
Salinity |
Change due to human activity not to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not to exceed 2 oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by 30% caused by human activity |
Marine waters |
Unionised ammonia (UIA) |
Annual mean not to exceed 0.021mg/l as unionised form |
Whole zone |
Nutrients |
Shall not cause excessive algal growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic nitrogen not to exceed 0.4mg/l |
Marine waters |
Toxic substances |
Should not attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms. |
Whole zone |
Human activity should not cause a risk to any beneficial use of the aquatic environment. |
Whole zone |
Source: Statement of Water Quality Objectives (Victoria Harbour (Phases One, Two and Three) Water Control Zone).
Table 5.7 WSD’s Water Quality Criteria for Flushing Water at Sea Water Intakes
Parameter (in mg/l unless otherwise stated) |
Target Limit |
Colour (HU) |
< 20 |
Turbidity (NTU) |
< 10 |
Threshold Odour Number (odour unit) |
< 100 |
Ammoniacal Nitrogen |
< 1 |
Suspended Solids |
< 10 |
Dissolved Oxygen |
> 2 |
Biochemical Oxygen Demand |
< 10 |
Synthetic Detergents |
< 5 |
E. coli (no. per 100ml) |
< 20,000 |
Table 5.8 Summary Statistics of Marine Water Quality in the Victoria Harbour WCZ in 2006
Parameter |
Victoria Harbour East |
Victoria Harbour Central |
WPCO WQO (in marine waters) |
|
VM2 |
VM4 |
|||
Temperature (oC) |
23.5 |
23.6 |
Not more than 2 oC in daily temperature range |
|
Salinity |
31.7 |
31.6 |
Not to cause more than 10% change |
|
Dissolved Oxygen (DO) (% Saturation) |
Depth average |
81 |
80 |
Not available |
Bottom |
81 |
79 |
Not available |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
5.8 |
5.7 |
Not less than 4 mg/l for 90% of the samples |
Bottom |
5.8 |
5.6 |
Not less than 2 mg/l for 90% of the samples |
|
pH |
7.9 |
7.9 |
6.5 - 8.5 (± 0.2 from natural range) |
|
Secchi disc Depth (m) |
2.0 |
2.0 |
Not available |
|
Turbidity (NTU) |
11.2 |
12.1 |
Not available |
|
Suspended Solids (SS) (mg/l) |
4.2 |
4.9 |
Not more than 30% increase |
|
5-day Biochemical Oxygen Demand (BOD5) (mg/l) |
0.6 |
0.7 |
Not available |
|
Nitrite Nitrogen (NO2-N) (mgN/l) |
0.024 |
0.024 |
Not available |
|
Nitrate Nitrogen (NO3-N) (mgN/l) |
0.10 |
0.11 |
Not available |
|
Ammonia Nitrogen (NH3-N) (mgN/l)
|
0.11 |
0.13 |
Not available |
|
Unionised Ammonia (UIA) (mgN/l) |
0.004 |
0.004 (0.002 – 0.007) |
Not more than 0.021 mg/l for annual mean |
|
Total Inorganic Nitrogen (TIN) (mgN/l) |
0.23 |
0.26 (0.08 – 0.44) |
Not more than 0.4 mg/l for annual mean |
|
Total Nitrogen (TN) (mgN/l)
|
0.42 (0.20 – 0.64) |
0.47 |
Not available |
|
Orthophosphate Phosphorus (PO4) (mgP/l) |
0.03 |
0.03 |
Not available |
|
Total Phosphorus (TP) (mgP/l) |
0.05 |
0.05 |
Not available |
|
Chlorophyll-a (µg/L) |
3.0 |
2.9 (1.0 – 9.2) |
Not available |
|
E coli (cfu/100 ml) |
1100 |
2600 |
Not available |
|
Faecal Coliforms (cfu/100 ml) |
2600 |
6500 |
Not available |
Notes:
1. Data source: EPD’s publication: “Marine Water Quality Monitoring in Hong Kong 2006”
2. Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: Surface, mid-depth, bottom.
3. Data presented are annual arithmetic means of depth-averaged results except for E. coli and faecal coliforms that are annual geometric means.
4. Data in brackets indicate the ranges.
Table 5.9 Summary Statistics of Marine Water Quality in the Kwun Tong and To Kwa Wan Typhoon Shelters in 2006
Parameter |
WPCO WQO (in marine waters) |
|||
Temperature (oC) |
23.9 (17.5 – 28.8) |
23.5 (17.2 – 28.6) |
Not more than 2 oC in daily temperature range |
|
Salinity (ppt) |
29.3 (23.2 – 31.4)
|
30.5 (21.8 – 32.7) |
Not to cause more than 10% change |
|
Dissolved Oxygen (DO) (% saturation) |
Depth average |
68 (29 – 112) |
83 (56 – 115) |
Not available |
Bottom |
66 (26 – 110) |
84 (54 – 117) |
Not available |
|
Dissolved Oxygen (DO) (mg/l) |
Depth average |
4.9 (2.0 – 7.6) |
6.0 (3.9 – 7.9) |
Not less than 4 mg/L for 90% of the samples |
Bottom |
4.7 (1.8 – 7.4) |
6.0 (3.7 – 8.0) |
Not less than 2 mg/L for 90% of the samples |
|
pH value |
7.7 (7.4 – 8.1) |
8.0 (7.7 – 8.3) |
6.5 - 8.5 (± 0.2 from natural range) |
|
Secchi disc (m) |
1.4 (1.0 – 2.0) |
1.7 (0.9 – 2.5) |
Not available |
|
Turbidity (NTU) |
12.7 (4.1 – 30.1) |
14.8 (9.0 – 22.1) |
Not available |
|
Suspended Solids (SS) (mg/l) |
2.6 (1.2 – 3.5) |
6.7 (2.4 – 20.6) |
Not more than 30% increase |
|
Silica (as SiO2) (mg/l) |
1.0 (0.4 – 1.8) |
0.7 (0.2 – 1.6) |
Not available |
|
5-day Biochemical Oxygen Demand (BOD5) (mg/l) |
2.2 (1.1 – 3.5) |
1.0 (0.6 – 1.6) |
Not available |
|
Nitrite Nitrogen (NO2-N) (mg/l) |
0.157 (0.082 – 0.227) |
0.029 (0.012 – 0.059) |
Not available |
|
Nitrate Nitrogen (NO3-N) (mg/l) |
0.34 (0.22 – 0.64) |
0.16 (0.05 – 0.42) |
Not available |
|
Ammoniacal Nitrogen (NH3-N) (mg/l) |
0.48 (0.29 – 0.65) |
0.12 (0.06 – 0.21) |
Not available |
|
Unionised Ammonia (UIA) (mg/l) |
0.011 (0.005 – 0.016) |
0.004 (0.002 – 0.006) |
Not more than 0.021 mg/L for annual mean |
|
Total Inorganic Nitrogen (TIN) (mg/l) |
0.97 (0.71 – 1.42) |
0.31 (0.13 – 0.54) |
Not more than 0.4 mg/L for annual mean |
|
Total Nitrogen (TN) (mg/l) |
1.33 (1.02 – 1.82) |
0.53 (0.39 – 0.80) |
Not available |
|
Ortho-Phosphate (PO4) (mg/l) |
0.214 (0.153 – 0.295) |
0.028 (0.007 – 0.050) |
Not available |
|
Total Phosphorus (TP) (mg/l) |
0.26 (0.20 – 0.36) |
0.05 (0.04 – 0.06) |
Not available |
|
Chlorophyll-a (µg L-1) |
18.2 (1.0 – 35.0) |
7.9 (1.0 – 20.5) |
Not available |
|
E. coli (cfu per 100 mL) |
9,200 (2,800 – 29,000) |
1,100 (340 – 4,400) |
Not available |
|
Faecal Coliforms (cfu per 100 mL) |
22,000 (4,400 – 78,000) |
2,600 (860 – 8,300) |
Not available |
Notes:
1. Data source: EPD’s publication: “Marine Water Quality Monitoring in Hong Kong 2006”
2. Except as specified, data presented are depth-averaged data.
3. Data presented are annual arithmetic means except for E.coli and faecal coliforms that are geometric means.
4. Data enclosed in brackets indicate ranges.
Table 5.10 Pollution Levels Measured at KTAC in October 2005
WQO: |
Depth-averaged Suspended Solids |
Depth-averaged Ammonia Nitrogen |
Depth-averaged E.coli |
Depth-averaged Total Inorganic Nitrogen |
Depth-averaged BOD5 |
10th Percentile Bottom DO |
10th Percentile Depth-averaged DO |
Mg/L |
mg/L |
cfu/100mL |
mg/L |
mg/L |
mg/L |
mg/L |
|
NA |
NA |
NA |
0.4 |
NA |
2 |
4 |
|
25 |
0.9 |
115519 |
3.11 |
11 |
0.99 |
1.48 |
|
28 |
1.0 |
17960 |
3.21 |
10 |
0.74 |
1.18 |
|
19 |
0.9 |
60517 |
3.53 |
9 |
1.14 |
1.47 |
|
20 |
1.2 |
37857 |
3.15 |
10 |
0.93 |
1.33 |
|
21 |
1.2 |
28832 |
3.28 |
8 |
1.19 |
1.54 |
|
26 |
1.4 |
34375 |
2.76 |
9 |
0.86 |
1.41 |
|
27 |
0.8 |
15863 |
2.60 |
7 |
2.06 |
2.20 |
Bolded and shaded – Exceedance of WQO
NA – WQO is not available
Table 5.11 Pollution Levels Measured at KTAC in January 2006
WQO: |
Depth-averaged Suspended Solids |
Depth-averaged Ammonia Nitrogen |
Depth-averaged E.coli |
Depth-averaged Total Inorganic Nitrogen |
Depth-averaged BOD5 |
10th Percentile Bottom DO |
10th Percentile Depth-averaged DO |
Mg/L |
mg/L |
cfu/100mL |
mg/L |
mg/L |
mg/L |
mg/L |
|
NA |
NA |
NA |
0.4 |
NA |
2 |
4 |
|
Bolded and shaded – Exceedance of WQO
NA – WQO is not available
· Waste Disposal Ordinance (Cap. 354)
· Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354)
· Land (Miscellaneous Provisions) Ordinance (Cap. 28)
· Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation
· Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)
· Estimation of the types and quantities of the wastes generated.
· Assessment of potential impacts from the management of solid waste with respect to potential hazards, air and odour emissions, noise, wastewater discharge and transport.
· Assessment of impacts on the capacity of waste collection, transfer and disposal facilities.
· C&D material
· Chemical waste
· General refuse
Table 5.12 Summary of Estimated C&D Material
Projects
|
Disposal Site (Landfill or Public Fill)
|
Estimated Quantity
|
Decommissioning of the remaining parts (ex-GFS Building and Radar Station) of the former Kai Tak Airport |
Landfill / public fill
|
· 9500 m3 for demolition of ex-GFS Building
· 5,000 m3 for demolition of ASDE radar
tower
· 28,750 m3 for decommissioning and decontamination of
the south apron
|
· Toxic effects to workers
· Adverse impacts on water quality from spills
· Fire hazards
· Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.
· Training of site personnel in proper waste management and chemical waste handling procedures.
· Provision of sufficient waste disposal points and regular collection for disposal.
· Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.
· A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites).
· Sort C&D waste from demolition of the remaining structures to recover recyclable portions such as metals.
· Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.
· Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force.
· Any unused chemicals or those with remaining functional capacity shall be recycled.
· Proper storage and site practices to minimise the potential for damage or contamination of construction materials.
· Where it is unavoidable to have transient stockpiles of C&D material within the work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible.
· Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric.
· Skip hoist for material transport should be totally enclosed by impervious sheeting.
· Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site.
· The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores.
· The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle.
· All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.
· The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading.
Table 5.13 Summary of findings in the relevant EIA reviewed
EIA reviewed |
Site Investigation Findings |
Date of Approval |
SEKDCFS EIA |
||
SEKDCFS EIA
|
l Reviewed SEKDFS EIA and NAKTA Decommissioning EIA. l Suggested land contamination assessment on potential land contaminated sites which were not accessible during the site investigation for the NAKTA Decommissioning EIA. l Identified potential contamination hotspots within former Kai Tak Airport and the vicinity. |
September 2001 EIAO Register: AEIAR-044/2001 |
l Direct ingestion of contaminated soils through eating or drinking/smoking on site; and
l Dermal contact with contaminated soils.
Table 5.14 Summary of Soil Samples Exceeding the Dutch B/C Levels
Sample I.D. |
Depth (m BBC) |
Contaminant |
Dutch Level (mg/kg) |
Concentration (mg/kg) |
Dutch Level Exceeded |
|
B |
C |
|||||
GFSA-17 |
3.25-3.7 |
Lead |
150 |
600 |
200 |
>B |
GFSA-18 |
1 |
Phenanthrene |
10 |
100 |
14 |
>B |
Benzo(a)pyrene |
1 |
10 |
11 |
>C |
||
Fluoranthene |
10 |
100 |
19 |
>B |
||
Pyrene |
10 |
100 |
17 |
>B |
||
GFSA-20 |
1 |
Zinc |
500 |
3000 |
2000 |
>B |
GFSA-22 |
3.25-3.7 |
Copper |
100 |
500 |
150 |
>B |
GFSB-01 |
1.65 |
TPH |
1000 |
5000 |
2875 |
>B |
GFSD-03 |
1 |
Cadmium |
5 |
20 |
6 |
>B |
Lead |
150 |
600 |
480 |
>B |
||
Zinc |
500 |
3000 |
2300 |
>B |
||
3.3-3.75 |
Cadmium |
5 |
20 |
510 |
>C |
|
Nickel |
100 |
500 |
410 |
>B |
||
Cobalt |
50 |
300 |
1200 |
>C |
||
GFSD-04 |
2.2-2.65 |
Cadmium |
5 |
20 |
15 |
>B |
Lead |
150 |
600 |
430 |
>B |
||
3.2-3.65 |
Lead |
150 |
600 |
300 |
>B |
Table 5.15 Summary of Groundwater Samples Exceeding the Dutch B/C Values
Sample I.D. |
GW depth (m below ground) |
Contaminant |
Dutch Level |
Concentration (μg/L) |
Dutch Level Exceeded |
|
B |
C |
|||||
Radar Station |
||||||
RSB-01
|
2.24
|
Cadmium |
2.5 |
10 |
3.2 |
>B |
Copper |
50 |
200 |
76 |
>B |
||
Lead |
50 |
200 |
1600 |
>C |
||
Zinc |
200 |
800 |
700 |
>B |
||
Barium |
100 |
500 |
390 |
>B |
||
TPH |
200 |
600 |
2871 |
>C |
||
RSB-01A
|
2.20
|
Cadmium |
2.5 |
10 |
3.8 |
>B |
Copper |
50 |
200 |
92 |
>B |
||
Lead |
50 |
200 |
1300 |
>C |
||
Zinc |
200 |
800 |
670 |
>B |
||
Barium |
100 |
500 |
250 |
>B |
||
TPH |
200 |
600 |
259 |
>B |
||
RSB-02 |
2.18 |
Lead |
50 |
200 |
410 |
>C |
Zinc |
200 |
800 |
310 |
>B |
||
Barium |
100 |
500 |
170 |
>B |
||
TPH |
200 |
600 |
435 |
>B |
||
RSB-07 |
2.24 |
Lead |
50 |
200 |
210 |
>C |
Zinc |
200 |
800 |
210 |
>B |
||
RSB-08 |
2.28 |
Lead |
50 |
200 |
450 |
>C |
Zinc |
200 |
800 |
510 |
>B |
||
Barium |
100 |
500 |
640 |
>C |
||
TPH |
200 |
600 |
250 |
>B |
||
Phenanthrene |
2 |
10 |
2.3 |
>B |
||
Ex-GFS Building |
||||||
GFSA-17 |
2.62 |
Mercury |
0.5 |
2 |
1.2 |
>B |
Molybdenum |
20 |
100 |
31 |
>B |
||
TPH |
200 |
600 |
231 |
>B |
||
GFSA-18 |
2.58 |
Lead |
50 |
200 |
77 |
>B |
Zinc |
200 |
800 |
250 |
>B |
||
Molybdenum |
20 |
100 |
21 |
>B |
||
Barium |
100 |
500 |
150 |
>B |
||
TPH |
200 |
600 |
327 |
>B |
||
GFSA-19 |
2.54 |
Lead |
50 |
200 |
72 |
>B |
Molybdenum |
20 |
100 |
39 |
>B |
||
Barium |
100 |
500 |
120 |
>B |
||
GFSA-20 |
2.73 |
Barium |
100 |
500 |
110 |
>B |
GFSA-21 |
2.53 |
Chromium |
50 |
200 |
64 |
>B |
Lead |
50 |
200 |
590 |
>C |
||
Zinc |
200 |
800 |
420 |
>B |
||
Barium |
100 |
500 |
610 |
>C |
||
GFSA-22 |
2.68 |
Chromium |
50 |
200 |
57 |
>B |
Lead |
50 |
200 |
130 |
>B |
||
Zinc |
200 |
800 |
250 |
>B |
||
Barium |
100 |
500 |
220 |
>B |
||
GFSD-01 |
2.69 |
Copper |
50 |
200 |
55 |
>B |
Lead |
50 |
200 |
550 |
>C |
||
Zinc |
200 |
800 |
480 |
>B |
||
Barium |
100 |
500 |
340 |
>B |
||
TPH |
200 |
600 |
365 |
>B |
||
GFSD-02 |
2.83 |
Cadmium |
2.5 |
10 |
2.7 |
>B |
Copper |
50 |
200 |
59 |
>B |
||
Lead |
50 |
200 |
2100 |
>C |
||
Zinc |
200 |
800 |
1000 |
>C |
||
Barium |
100 |
500 |
680 |
>C |
||
GFSD-03 |
2.63 |
Cadmium |
2.5 |
10 |
27 |
>C |
Lead |
50 |
200 |
240 |
>C |
||
Zinc |
200 |
800 |
470 |
>B |
||
Cobalt |
50 |
200 |
200 |
>B |
||
Barium |
100 |
500 |
650 |
>C |
||
TPH |
200 |
600 |
740 |
>C |
||
GFSD-04 |
2.31 |
Cadmium |
2.5 |
10 |
3 |
>B |
Lead |
50 |
200 |
320 |
>C |
||
Zinc |
200 |
800 |
290 |
>B |
||
Barium |
100 |
500 |
160 |
>B |
||
TPH |
200 |
600 |
369 |
>B |
Table 5.16 Evaluation of Significance of Risk Due to Groundwater Contamination
Receptor |
Significance of Risk due to Groundwater Contamination |
Rationale |
Construction workers for decommissioning / decontamination works (by ingestion) |
Significant |
Existence of potential risk. |
Construction workers for decommissioning / decontamination works (by inhalation) |
Insignificant |
Decommissioning and decontamination works would be located in the outdoor area. Also, it is recommended that personal protective equipment (PPE) should be used by site workers as a mitigation measures. |
Construction workers for decommissioning / decontamination works (by dermal contact) |
Uncertain |
Toxicity and / or chemical specific data do not exist for the COCs for risk assessment to be undertaken. As such, it is recommended that personal protective equipment (PPE) be used by site workers as a mitigation measure. |
Future land users |
Insignificant |
As most of the contamination in the site would be removed after the decontamination works, the soil quality would be within Dutch B level and the groundwater contamination would be much reduced. In addition, the site will be covered by filling materials / concrete. Groundwater at the site will not be used as potable water or used for recreation / irrigation purposes. |
Future construction workers |
Insignificant |
Contaminated soil is considered as the major contributor for elevated COCs in the groundwater. As most of the contamination in the site would be removed after the decontamination works, the soil quality would be within Dutch B level and the contaminants in groundwater would be much reduced. |
Table 5.17 Maximum Source Concentrations and Non-carcinogenic Oral Reference Doses / Carcinogenic Oral Slope Factors of Chemicals of Concern
Parameter |
Source Concentration |
Sample I.D. |
Noncarcinogenic Oral Reference Dosea (RfDo) |
Minimum Noncarcinogenic Oral Reference Dosea (RfDo) |
Carcinogenic Oral Slope Factorb (CSFo) |
[mg/L] |
[mg/kg-day] |
[mg/kg-day] |
1/[mg/kg-day] |
||
TPHs |
2.871 |
RSB-01 |
0.03 to 5.00 |
0.03 |
Not applicable |
Barium |
0.68 |
GFSD-02 |
0.07 |
Not applicable |
Not applicable |
Cadmium |
0.027 |
GFSD-03 |
0.0005 |
Not applicable |
Not applicable |
Chromium* |
0.064 |
GFSA-21 |
0.003 |
Not applicable |
Not applicable |
Cobalt |
0.2 |
GFSD-03 |
0.02 |
Not applicable |
Not applicable |
Copper |
0.092 |
RSB-01A |
0.04 |
Not applicable |
Not applicable |
Lead |
2.1 |
GFSD-02 |
0.0036 |
Not applicable |
Not applicable |
Phenanthrene |
0.0023 |
RSB-08 |
0.04 |
Not applicable |
Not applicable |
Mercury |
0.0012 |
GFSA-17 |
0.0003 |
Not applicable |
Not applicable |
Molybdenum |
0.039 |
GFSA-19 |
0.005 |
Not applicable |
Not applicable |
Xylenes |
0.03 |
All** |
0.2 |
Not applicable |
Not applicable |
Zinc |
1 |
GFSD-02 |
0.3 |
Not applicable |
Not applicable |
Remarks:
a Source for TPHs : TPH Criteria Working Group, 1999. Total Petroleum Hydrocarbons Criteria Working Group Series Volume 5 – Human Health Risk-Based Evaluation of Petroleum Release Sites: Implementing the Working Group Approach. Massachusetts, U.S.A., Amherst Scientific Publishers.
Source for Ba, Cd, Cr, Co, Cu, Hg, Mo, Zn, Phenanthrene and Xylene:USEPA Region IX Risk-based Concentration Table (revised on Oct 04), USEPA Region IX.
Source for Pb: The value is referenced to the tolerable daily intake (TDI) from the National Institute of Public Health and the Environment (RIVM), The Netherlands, 2001.
b Source for TPHs, Ba, Cd, Cr, Co, Cu, Hg, Mo, Zn, Phenanthrene and Xylene: USEPA Region IX Risk-based Concentration Table (revised on Oct 04), USEPA Region IX.
** All sampling locations showed the same concentrations for Xylenes (i.e. 30ug/L as the Dutch B level).
* Chromium is assumed to be Cr(VI) as conservative assessment.
Soil Contamination
Estimation of Soil Contamination Extent
Table 5.18 Location, Depth and Estimated Quantity of Contaminated Soil
Zone I.D. |
Sample I.D. |
Depth (m BBC) |
Contaminant |
Concentration |
Estimated Contamination Extent |
||||
Vertical |
Horizontal |
Estimated Volume (m3) |
|||||||
Exceedances found in the soil samples collected below 0m to 1m BBC |
|||||||||
A |
GFSA-18 |
1 |
Phenanthrene |
14 |
0.5-1.5 |
36 |
36 |
||
Benzo(a)pyrene |
11 |
||||||||
Fluoranthene |
19 |
||||||||
Pyrene |
17 |
||||||||
B |
GFSA-20 |
1 |
Zinc |
2000 |
0.5-1.5 |
36 |
36 |
||
C |
GFSD-03 |
1 |
Cadmium |
6 |
0.5-1.5 |
36 |
36 |
||
Lead |
480 |
||||||||
Zinc |
2300 |
||||||||
Exceedances found in the soil samples collected below 1m to 6m BBC |
|||||||||
D |
GFSB-01 |
1.65 |
TPH |
2875 |
1.15-2.15 |
36* |
36 |
|
|
E |
GFSD-04 |
2.2-2.65 |
Cadmium |
15 |
1.7-4.15 |
36 |
88.2 |
|
|
Lead |
430 |
|
|||||||
3.2-3.65 |
Lead |
300 |
|
||||||
F |
GFSA-17 |
3.25-3.7 |
Lead |
200 |
2.75-4.2 |
36 |
52.2 |
|
|
G |
GFSA-22 |
3.25-3.7 |
Copper |
150 |
2.75-4.2 |
36 |
52.2 |
|
|
H |
GFSD-03 |
3.3-3.75 |
Cadmium |
510 |
2.8-4.25 |
36 |
52.2 |
|
|
Nickel |
410 |
|
|||||||
Cobalt |
1200 |
|
|||||||
Total Volume of Estimated Contaminated Soil=388.8m3 |
|||||||||
|
|
|
|
|
|
|
|
|
|
Remarks:
BBC= Below Base of Existing Concrete Pavement
* Due to space constraint within the D.G. Store, 6m X 6m square centered at GFSB-01 may not be feasible. The frame for excavation would have to be adjusted on site based on the actual site condition.
Table 5.19 Estimated Quantity of Different Type of Contaminated Soil
Land |
Contaminants |
|
Metals Only |
TPH/SVOCs |
|
Ex-GFS building |
316.8 m3 |
72 m3 |
Radar Station |
Nil |
Nil |
Total |
316.8 m3 |
72 m3 |
Note: The actual volume may be different and is subject to confirmatory sampling and testing to be conducted during the course of proposed remediation processes.
Consideration of Remediation Methods for Contaminated Soil
l Technical and cost effectiveness;
l Technology development status;
l Environmental benefits and dis-benefits;
l Commercial availability;
l Experience; and
l Expertise requirement.
Table 5.20 Treatment Technologies for Contaminated Soil with Metals / TPH /SVOCs
Technology |
In-situ Treatment |
Ex-situ Treatment |
|
|
|||
Biological Treatment |
Natural Attenuation Soil Venting |
Biopiling Landfarming |
|
Physical / Chemical Treatment |
Electrokinetic Separation |
Solidification/Stabilization Soil washing |
|
Removal |
NA |
Excavation and Landfill disposal |
|
Table 5.21 List of Soil Remediation Technologies for Metals / TPH / SVOCs Contaminated Soil
Remediation Option |
Descriptions |
Applicability / Environmental Benefits |
Limitations / Environmental Dis-benefits |
Biopiling |
Ex-situ bioremediation method where bacteria grow in the piled contaminated soil and degrade the waste into harmless products.
|
l Effective to TPH and other wide range of organic contaminants with some successful local case studies, e.g. decontamination works at the Cheoy Lee Shipyard at Penny’s Bay, reclamation works at North Tsing Yi Shipyard site. l Most cost-effective for large volumes of contaminated soil l All materials and equipments are commercially available. l Can be designed to be a closed system; vapour emissions can be controlled. |
l Labour-intensive; require considerable maintenance l Time-consuming (~1 year required) and not cost-effective for treating small volume of soil. l Space required for biopile construction |
Soil Venting |
In situ bioremediation method that uses indigenous bacteria to degrade contaminants. Activity of the bacteria is enhanced by inducing air flow (using extraction or injection wells) and, if necessary, by adding nutrients. |
l Very effective to TPH. l Suitable for remediation in built up areas because wells can be placed between or below buildings. l Applicable to large sites with widespread contamination. l Uses readily available equipment; easy to install. l Vapour emissions can be controlled but not to the extent of biopiling due to underground soil in-situ properties. |
l Effectiveness is limited by underground soil features e.g. soil moisture content, permeability, etc. l May induce possible air emission to the sensitive receivers l Require large space for the system development |
Landfarming |
Ex-situ bioremediation method that mixes the soil with bacteria involving the spread and exposure of contaminated soil to atmosphere. |
l Very effective in treating TPH. l Simple to design and implement.
|
l May induce possible dust and vapour emission to the sensitive receivers (surrounding factories and buildings) and relatively difficult to control l Require large flat space for the system development l Slow bioremediation rate and require long operation period (as long as 2years) which may affect future development schedule |
Solidification /Stabilization |
Ex-situ immobilization technique treats contaminated soil by mixing soil with binding agents, e.g. cement so that the contaminants become physically bound within stable mass. |
l Applicable to clean-up inorganic contaminants such as heavy metals. l Solidification/stabilization has been used on certain contaminated sites in Hong Kong and demonstrated as a successful treatment method for inorganic contaminated soil, e.g. decontamination works at the Cheoy Lee Shipyard at Penny’s Bay, reclamation works at North Tsing Yi Shipyard site and few isolated sites identified in the Deep Bay Link project. |
l The effectiveness reduces with the presence of organic contaminants l Large boulders may hinder the mixing process. Soil sorting is necessary before the treatment taken place. |
Soil Washing |
Ex-situ soil separation processes mostly based on mineral processing techniques. It is a water-based process for scrubbing soils ex-situ to remove contaminants. |
l Applicable to clean inorganic contaminants such as heavy metals from coarse-grained soils. |
l The effectiveness of the treatment depends on soil particle size. Fine soil particles may require the addition of a polymer to remove them from the washing fluid. l Complex waste mixtures make formulating washing fluid difficult. l Require further treatment and disposal for residuals. |
Electrokinetic Separation |
In-situ remediation uses electrochemical and electrokinetic processes to desorb and remove metals and polar organics from soil. Low intensity direct current is applied to the soil to mobilize the charged species. |
l Applicable to treat low permeability soil contaminated with heavy metals. |
l The effectiveness depends on moisture content of soil. It decreases with moisture content less than 10%. l Require further treatment to remove the desorbed contaminants and thus increase the cost of remediation. l Presence of anomalies such as large gravels and insulating material in soil can induce variability of electrical conductivity in soil. This may reduce the effectiveness. |
Excavation and Landfill Disposal |
Ex-situ method whereby contaminants are removed by excavation of the contaminated soil and direct disposal to landfill. |
l Most simple and quickest way to dispose of large volume of contaminated soil. l Contamination is removed definitely. l Higher certainty of success. l Wide experience in Hong Kong. l Applicable to all waste or mixture that meet land disposal restriction treatment standards. l Common practice for shallow, highly-contaminated soils. |
l Pre-treatment may be required for contaminated soil to meet landfill disposal criteria l Landfill space limited and valuable. l Indirect costs to the landfill management on monitoring and maintenance. l Potential long-term liabilities to landfill l Need large volume of clean backfill materials l No access to the working site until completion of backfilling l Least desirable management option. |
l Degree and extent of the contamination;
l Anticipated future use of the site;
l Nature of the contaminants;
l Soil characteristics;
l Time available for remediation; and
l Availability of local expertise and facilities for undertaking the treatment or disposal of the contaminated wastes.
Remediation Methods for Soil Contaminated with Metals
Remediation Methods for Soil Contaminated with TPH / SVOCs
Summary of Proposed Remediation Methods for Soil Contamination
Table 5.22 Summary of Proposed Remediation Methods for Metals / TPH / SVOCs Contaminated Soil
Soil Contaminant(s) |
Estimated Volume of Contaminated Soil (m3) |
Remediation Method |
Justification |
Metals |
316.8 |
Solidification/ Stabilization |
l Well developed technology with operation experience in Hong Kong ; l Higher certainty of success; l Simple operation; l Cost effective; and l Treated soil is acceptable to be reused as backfill. |
TPH/ SVOCs |
72 |
Biopiling |
Overall Remediation Arrangement
(i) Temporary stockpiling areas;
(ii) Solidification / stabilization unit;
(iii) Biopiling unit; and
(iv) Site management office.
Excavation of Contaminated Soil
l Excavate the contaminated soil and properly packed until no contaminants are found (confirmed by field and laboratory tests);
l Soils contaminated with different types of contaminants shall not be mixed to avoid the increase the volume of soil that would require treatment by different remediation methods;
l Transport the excavated soil by roll-off trucks for on-site treatment;
l Any free product encountered during excavation will be recovered and drummed properly and collected by licensed chemical waste collector for proper treatment; and
l Finally, backfill the excavation with clean soils.
l The soil / fill material from around the tank / pipeline shall be removed adequately, except for the identified contaminated material which shall be separately stockpiled on site for further decontamination treatment to be agreed by the Engineer and the Land Decontamination Specialist;
l Appropriate heavy equipment shall be used for the underground fuel tank / pipeline removal / lifting. Relevant safety precautions should be formulated in the method statement to be prepared by the Contractor;
l The excavated tank should be transferred to a secure area on site. The excavated tank / pipeline should be examined for structural integrity and signs of leakage, if any. Contamination on the exterior surface of excavated tank, if any, should be properly washed and/or treated; and
l The excavated tank / pipeline should then be sent for off-site disposal as general construction and demolition (C&D) waste.
l The gas freeing, abandoning, removing and disposal of all tanks / pipelines should be in accordance with the guidelines contained in Chapter 15 of the “Guidance for the Design, Construction, Modification, Maintenance and Decommissioning of Filling Stations”, jointly published by the Association for Petroleum and Explosives Administration (APEA) and Energy Institute;
l Precautionary guidelines for hot works (as provided in Appendix 5.4) are to be followed at all times throughout the demolition process; and
l A competent person should be assigned in writing to supervise all hot works and method statement should be submitted to FSD for scrutinizing before the commencement of the demolition works.
l Temporary fencing or warning ribbons shall be provided to the boundary of excavation, slope crest and temporarily stockpiled areas. Where necessary, the exposed areas shall be temporarily covered with impermeable sheeting during heavy rainstorm.
l There shall be a clear separation and management of “contaminated” area and “uncontaminated” area for both excavation and stockpiling. There shall also be facilities for decontamination of workers and equipment.
l Workers are required to wear appropriate protective clothing and safety equipment.
l Smoking, eating, drinking and hotworks are strictly prohibited.
l Monitoring for Lower Explosive Limit (LEL) in the work zone, and total VOCs (with a Photo-ionisation Detector (PID)) in the breathing zone shall be undertaken. If the PID reading in the breathing zone is greater than 100ppm, monitoring for benzene in the breathing zone shall also be undertaken.
l Relevant occupational health and safety regulations and guidelines during excavation shall be observed.
Biopiling
Biopile Formation
Biopile Operation
Biopile Cleanup Progress Monitoring
Biopile Closure Assessment
Solidification / Stabilization
Toxicity Characteristics Leaching Procedure Test
Table 5.23 Universal Treatment Standards (UTS) for the Concerned Heavy Metals
Parameter |
Universal Treatment Standard* |
|
|
||
Lead |
0.75 mg/L as TCLP |
|
Copper |
7.8** mg/L as TCLP |
|
Zinc |
4.3 mg/L as TCLP |
|
Cadmium |
0.11 mg/L as TCLP |
|
Nickel |
11 mg/L as TCLP |
|
Cobalt |
Not Available** |
|
Remarks:
* Reference to Universal Treatment Standards (UTS) of U.S. Resource Conservation and Recovery Act (RCRA) in Title 40 of the Code of Federal Regulations (CFR) Parts 268.
**It should be noted that the UTS standard for copper and cobalt are unavailable. To determine the UTS for copper, a comparison has been made between Drinking Water Standards for the USEPA and the USEPA Federal Register. It was found that the 2 sets of standards differ by a factor of ~6 (for Chromium) to ~2950 (for Cyanide). Using a more conservative approach, the factor of 6 is taken. Therefore, the UTS for copper is taken to be the Drinking Water Standard value of 1.3mg/L times a factor of 6, giving a value of 7.8mg/L. For cobalt, it should be noted that there is no UTS or USEPA Drinking Water Standard for Cobalt. Therefore, a cleanup standard is not established for Cobalt. However, it is expected that the solidification process will likely isolate the Cobalt in the same manner as the other COC present.
Excavation and Transportation
· Excavation profiles must be properly designed and executed.
· Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission. If this is not practicable due to frequent usage, regular watering should be applied. However, watering should be avoided on stockpiles of contaminated soil to minimise contaminated runoff.
· Stockpiles of contaminated soil should be properly covered by impermeable sheeting to minimize contaminated runoff from the stockpiles.
· Excavation and stockpiling should be carried out during dry season as far as possible to minimise contaminated runoff from contaminated soils.
· Supply of suitable clean backfill material is needed after excavation.
· Vehicles containing any excavated materials should be suitably covered to limit potential dust emissions or contaminated wastewater run-off, and truck bodies and tailgates should be sealed to prevent any discharge during transport or during wet conditions.
· Speed control for the trucks carrying contaminated materials should be enforced.
· Vehicle wheel and body washing facilities at the site’s exist points should be established and used.
Biopiling
l To avoid fugitive emissions of dust or any air pollutants from the biopile(s) and to minimise runoff from the stockpiled soils, the stockpiled soils at the biopiles should be covered by impermeable sheeting such that not longer than 5m of the biopile is exposed to open air.
l Upon formation of a biopile, the biopile should be fully covered by impermeable sheeting to prevent dust emission and runoff.
l Impermeable sheeting should be placed at the bottom of the biopiles and leachate collection sump should be constructed along the perimeter of the biopiles to prevent leachate from contaminating the underlying soil/groundwater. The collected leachate should be discharged following the requirements of Water Pollution Control Ordinance (WPCO).
l The vented air from the biopile(s) should be connected to blower and carbon adsorption system with 99% control efficiency for treatment before release to the atmosphere. Exhaust air from the blower and carbon adsorption system should be monitored for TVOC biweekly to check the performance of the carbon filter. The frequency of monitoring might be adjusted subject to review on site.
l The biopiles should be fully covered by impermeable sheeting to control the extraction of TVOC.
l Spent activated carbon of the carbon adsorption system should be replaced at appropriate intervals such that the VOC emission concentration from the system is acceptable. (i.e. the measured TVOC concentration is below 20 ppm).
l Silencers should be installed at the biopile blowers to minimise noise impact.
l Contaminated runoff from biopile(s) should be prevented by constructing concrete bunds along the perimeter of the biopiles.
Solidification / Stabilization
l The loading, unloading, handling, transferring and storage of cement should be carried out in an enclosed system.
l Mixing process and other associated material handling activities should be properly scheduled to minimise potential noise impact.
l Mixing of contaminated soils and cement / water / other additive(s) should be undertaken at a solidification plant to minimise the potential for leaching.
l Runoff from the solidification / stabilization area should be prevented by constructing concrete bunds along the perimeter.
· Set up a list of safety measures for site workers;
· Provide written information and training on safety for site workers;
· Keep a log-book and plan showing the contaminated zones and clean zones;
· Maintain a hygienic working environment;
· Avoid dust generation;
· Provide face and respiratory protection gear to site workers;
· Provide personal protective clothing (e.g. chemical resistant jackboot, liquid tight gloves) to site workers; and
· Provide first aid training and materials to site workers.
· Environmental Impact Assessment Ordinance (Cap.499.S.16) and the Technical Memorandum on EIA Process (EIAO-TM), particularly Annexes 10 and 18;
· Town Planning Ordinance (Cap 131);
· EIAO Guidance Note 8/2002;
· ETWB TCW No. 2/2004 - Maintenance of Vegetation and Hard Landscape Features, and Tree Preservation;
· ETWB TCW No. 3/2006 - Tree Preservation;
· ETWB TCW No. 36/2004 - Advisory Committee on the Appearance of Bridges and Associated Structures (ACABAS);
· Hong Kong Planning Standards and Guidelines;
· Land Administration Office Instruction (LAOI) Section D-12 - Tree Preservation;
· Study on Landscape Value Mapping of Hong Kong;
· WBTC No. 25/92 - Allocation of Space for Urban Street Trees; and
· WBTC No. 7/2002 - Tree Planting in Public Works.
· Comprehensive Feasibility Study for the Revised Scheme of South East Kowloon Development; and
· Kai Tak Planning Review.
· Approved Kai Tak (KPA22) Outline Zoning Plan no. S/K22/2 (6.11.2007);
·
Approved Ngau Tau Kok and
· Draft Kwun Tong (South) (KPA 14 Pt.) Outline Zoning Plan No. S/K14S/15 (5.10.2007).
High:
|
Important
landscape or landscape resource of particularly distinctive character or high
importance, sensitive to relatively small changes.
|
Medium:
|
Landscape
or landscape resource of moderately valued landscape characteristics
reasonably tolerant to change.
|
Low:
|
Landscape
or landscape resource, the nature of which is largely tolerant to change.
|
Large:
|
The
landscape or landscape resource would suffer a major change.
|
Intermediate:
|
The
landscape or landscape resource would suffer a moderate change.
|
Small:
|
The
landscape or landscape resource would suffer slight or barely perceptible
changes.
|
Negligible:
|
The
landscape or landscape resource would suffer no discernible change.
|
Table 5.24 Relationship between Receptor Sensitivity and Impact Magnitude in Defining Impact Significance
Magnitude of Impact (Both adverse and beneficial impact are assessed.) |
Large |
Slight / Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight / Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial / Slight |
Slight / Moderate |
Slight / Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
|
Receptor Sensitivity (of Landscape Resource, Landscape Character Area or VSRs) |
Note: All impacts are Adverse unless otherwise noted with Beneficial.
The sensitivity of VSRs is classified as follows:
High:
|
The VSR is highly sensitive
to any change in their viewing experience.
|
Medium:
|
The VSR is moderately
sensitive to any change in their viewing experience.
|
Low:
|
The VSR is only slightly
sensitive to any change in their viewing experience.
|
The magnitude of visual impacts is classified as follows:
Large:
|
The VSRs
would suffer a major change in their viewing experience.
|
Intermediate:
|
The VSRs
would suffer a moderate change in their viewing experience.
|
Small:
|
The VSRs
would suffer a small change in their viewing experience.
|
Negligible:
|
The VSRs
would suffer no discernible change in their viewing experience.
|
The significance of visual impacts is categorized as follows:
Substantial:
|
Adverse
/ beneficial impact where the proposal would cause significant deterioration
or improvement in existing visual quality.
|
Moderate:
|
Adverse
/ beneficial impact where the proposal would cause a noticeable deterioration
or improvement in existing visual quality.
|
Slight:
|
Adverse
/ beneficial impact where the proposal would cause a barely perceptible
deterioration or improvement in existing visual quality.
|
Insubstantial:
|
No
discernible change in the existing visual quality.
|
Table 5.25 Landscape Resources / Landscape Character Areas and Their Sensitivity to Change
ID. No. |
Landscape Resources / Landscape Characters |
Sensitivity to Change (Low, Medium, High) |
Baseline Landscape Resources |
||
LR07 |
Trees in the Amenity Areas near Kai Fuk Road There are approximately 150 trees found in the Amenity Areas near Kwun Tong Road with height around 4-5 m, spread 2 m, trunk diameter 100-180 mm. The amenity value of these trees is considered as medium. Predominant species consist of Acacia confusa, Celtis sinensis, Casuarina equisetifolia, Ficus microcarpa, Hibiscus tiliaceus, Macaranga tanarius and Melaleuca quinquenervia. |
Medium |
LR21 |
Existing trees along the runway There are more than 80 trees along runway. All the trees are immature mostly with height around 2-7 m, spread 1-4 m, trunk diameter 100-250 mm.. The amenity value of these trees is considered as low. Species include Casuarina equisetifolia, Chrysalidocarpus lutescens, Eucalyptus citriodora, Ficus benjamina, Ficus microcarpa, Hibiscus tiliaceus and Macaranga tanarius. |
Low |
LR29 |
Hoi Bun Road Park This is an open space (~ 1.2ha) in the context of the surrounding industrial areas. Tree and shrub planting and sitting out area are provided. There are around 120 trees of common species with height around 3-11 m, spread 2-7 m, trunk diameter 200-350 mm. Predominant species include Acacia confusa, Aleurites moluccana, Bauhinia variegata, Caryota ochlandra, Delonix regia, Ficus microcarpa, Livistona chinensis and Melaleuca quinquenervia. A few of the trees are mature but most are of small to medium size. |
High
|
LR31B |
Victoria Harbour It is a recognised and distinctive feature of Hong Kong worldwide, both as a tourist attraction and working port. The Harbour forms a centrepiece of the Hong Kong setting, with the airport runway forming a unique coastline to it. |
High |
Baseline Landscape Character Areas |
||
LCA01 |
Former Kai Tak Airport Landscape Character Area This comprises the former Kai Tak Airport where the future development is to be located. This area is flat, open, primarily hard standing with a few existing buildings that relate to the use of the former airport at the north. The area is currently occupied by various parties for different temporary uses. This LCA can be further sub-divided to the north apron area which consists of a large concrete surface, the linear runway portion and the south apron corner including the Kwun Tong Waterfront with direct interfacing with adjacent Kowloon Bay and Kwun Tong area. |
Low |
LCA03 |
Kowloon Bay Late 20C / Early 21C Commercial / Residential Complex Landscape This is an area of primarily mixed residential / commercial use. This comprises a mix of low to high buildings for residential, commercial uses. The streetscape is utilitarian with no soft or little landscape treatment. |
Medium |
LCA05 |
Kwun Tong Industrial Urban Landscape This is an area of industrial use. This comprises medium to high rise industrial buildings. The streetscape is utilitarian with no soft landscape treatment. |
Low |
LCA08 |
Kwun Tong Typhoon Shelter Landscape This is an area for typhoon shelter use in Kwun Tong. It is substantially enclosed by coast and offshore breakwater. |
Low |
Table 5.26 VSRs and Their Sensitivity to Change
VSR Type & ID. |
Key VSR |
Number of Individuals (Many/ Medium/ Few/) |
Quality of Existing View (Good/ Fair/ Poor) |
Availability of Alternative Views (Yes/ No) |
Average Distance between VSRs and Impact Source (m) |
Degree of Visibility (Full/ Partial/ Glimpse) |
Duration of View (Long/ Medium/ Short) |
Frequency of View (Frequent/ Occasional/ Rare) |
Sensitivity to Change (Low, Medium, High) |
VSRs at Local Level |
|||||||||
Sunshine Kowloon Bay Cargo Centre |
Few |
Poor |
Yes |
400m |
Glimpse |
Medium |
Occasional |
Low |
|
Kowloon Bay Vehicle Inspection Centre, Vehicle Examination Centre, Water Supplies Department Kowloon East Regional Building, Kowloon Bay Transfer Station, Kowloon Bay Government Land Transport Agency Transport Pool |
Few |
Fair |
No |
20m |
Full |
Medium |
Occasional |
Medium |
|
GIC12 |
Kowloon Bay Vehicle Servicing Station, Public Works Central Laboratory Building (planned GIC use and open space under KTD) |
Medium |
Fair |
No |
10m |
Full |
Medium |
Occasional |
Medium |
GIC23 |
Kwun Tong Public Pier, Kwun Tong Ferry Pier Square and adjacent bus terminal (same planned use under KTD) |
Medium |
Fair |
No |
500m |
Glimpse |
Medium |
Occasional |
Low |
O14 |
Visitors at Hoi Bun Road Park |
Medium |
Fair |
Yes |
700m |
Partial |
Medium |
Occasional |
Medium |
I5 |
Industrial/Office Developments and Godowns at Cheung Yip Street (planned commercial use under KTD) |
Medium |
Fair |
Yes |
300m |
Full |
Medium |
Occasional |
Medium |
OU2 |
Business and Industrial Developments in Kowloon Bay (planned commercial use) |
Many |
Fair |
No |
20m |
Full |
Long |
Occasional |
Medium |
OU5 |
Business and Industrial Developments in Kwun Tong (planned commercial use) |
Many |
Fair |
No |
500m |
Full |
Long |
Occasional |
Medium |
T3 |
Motorists on Kwun Tong Bypass |
Many |
Fair |
Yes |
20m |
Full |
Short |
Occasional |
Low |
T4 |
Travelers of Harbour Traffic |
Many |
Fair |
Yes |
200m |
Full |
Medium |
Occasional |
Medium |
* C = Commercial, CDA = Comprehensive Development Area, GIC = Government/Institution/Community, I = Industrial, O = Open space, OU = Other use, T = Transport related.
Table 5.27 Significance of Landscape Impacts in Construction Phase
ID. No. |
Landscape Resources / Landscape Characters |
Sensitivity to Change (Low, Medium, High) |
Magnitude of Change (Negligible, Small, Intermediate, Large) |
Impact Significance Threshold BEFORE Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold AFTER Mitigation (Insubstantial, Slight, Moderate, Substantial) |
|||||||
Construction |
Operation |
||||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|
DAY 1 |
YEAR 10 |
|||||
Existing Landscape Resources During Construction and Operation Phase |
|||||||||||||
LR07 |
Trees in the Amenity Areas near Kai Fuk Road |
Medium |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
- |
||
LR21 |
Existing trees along the runway |
Low |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
-- |
||
LR29 |
Hoi Bun Road Park |
High |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
- |
||
LR31B |
Victoria Harbour |
High |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
- |
||
Landscape Character Areas During Construction and Operation Phase |
|||||||||||||
LCA01 |
Former Kai Tak Airport Landscape Character Area (KTD in Operation Phase) |
Low |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
- |
||
LCA03 |
Kowloon Bay Late 20C / Early 21C Commercial / Residential Complex Landscape |
Medium |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
- |
||
LCA05 |
Kwun Tong Industrial Urban Landscape |
Low |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
- |
||
LCA08 |
Kwun Tong Typhoon Shelter Landscape |
Low |
- |
Negligible |
- |
Insubstantial |
- |
Not required |
- |
- |
- |
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 5.28 Significance of Visual Impacts in the Construction Phase (Note: All impacts are adverse unless otherwise noted with Beneficial)
VSR Type & ID. |
Key Visually Sensitive Receiver (VSR) |
Main Source of Visual Impact |
Magnitude of Impact (Negligible, Small, Intermediate, Large) |
Receptor Sensitivity (Low, Medium, High) |
Impact Significance Threshold Before Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold After Mitigation (Insubstantial, Slight, Moderate, Substantial) |
||||||
Construction |
Operation |
||||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
DAY 1 |
YEAR 10 |
||||||
VSRs at Local Level |
|||||||||||||
C3 |
Sunshine Kowloon Bay Cargo Centre |
DP3a |
Negligible |
- |
Low |
- |
Insubstantial |
- |
Not Required |
- |
- |
- |
|
GIC9 |
Kowloon Bay Vehicle Inspection Centre, Vehicle Examination Centre, Water Supplies Department Kowloon East Regional Building, Kowloon Bay Transfer Station, Kowloon Bay Government Land Transport Agency Transport Pool |
DP3a |
Small |
- |
Medium |
- |
Slight |
- |
Not Required |
- |
- |
- |
|
GIC12 |
Kowloon Bay Vehicle Servicing Station, Public Works Central Laboratory Building (planned GIC use and open space under KTD) |
DP3a |
Large |
- |
Medium |
- |
Moderate |
- |
Not Required |
- |
- |
- |
|
GIC23 |
Kwun Tong Public Pier, Kwun Tong Ferry Pier Square and adjacent bus terminal (same planned use under KTD) |
DP3a |
Negligible |
- |
Low |
- |
Insubstantial |
- |
Not Required |
- |
- |
- |
|
O14 |
Visitors at Hoi Bun Road Park |
DP3a |
Negligible |
- |
Medium |
- |
Insubstantial |
- |
Not Required |
- |
- |
- |
|
I5 |
Industrial/Office Developments and Godowns at Cheung Yip Street (planned commercial use under KTD) |
DP3a |
Large |
- |
Medium |
- |
Slight |
- |
Not Required |
- |
- |
- |
|
OU2 |
Business and Industrial Developments in Kowloon Bay (planned commercial use) |
DP3a |
Negligible |
- |
Medium |
- |
Insubstantial |
- |
Not Required |
- |
- |
- |
|
OU5 |
Business and Industrial Developments in Kwun Tong (planned commercial use) |
DP3a |
Negligible |
- |
Medium |
- |
Insubstantial |
- |
Not Required |
- |
- |
- |
|
T3 |
Motorists on Kwun Tong Bypass |
DP3a |
Negligible |
- |
Low |
- |
Insubstantial |
- |
Not Required |
- |
- |
- |
|
T4 |
Travelers of Harbour Traffic |
DP3a |
Negligible |
- |
Medium |
- |
Insubstantial |
- |
Not Required |
- |
- |
- |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* C = Commercial, GIC = Government/Institution/Community, I = Industrial, O = Open space, OU = Other use, T = Transport related.
· to provide a database against which any environmental impacts of the DP3a Project can be determined;
· to provide an early indication should any of the environmental control measures or practices fail to achieve the acceptable standards;
· to monitor the performance of the DP3a Project and the effectiveness of mitigation measures;
· to verify the environmental impacts predicted in this EIA;
· to determine project compliance with regulatory requirements, standards and government policies;
· to take remedial action if unexpected problems or unacceptable impacts arise; and
· to provide data to enable an environmental audit.
Table 5.29 Implementation Schedule for Air Quality Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S5.2.19 |
Implementation of dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation. The following mitigation measures and good site practices are recommended to minimize cumulative dust impacts. · The excavation area should be limited to as small in size as possible and backfilled with clean and/or treated soil shortly after excavation work. · The exposed excavated area should be covered by the tarpaulin during night time. · The top layer soils should be sprayed with fine misting of water immediately before the excavation. · Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust and other air pollutants emission. · Misting for the dusty material should be carried out before being loaded into the vehicle. · Any vehicle with an open load carrying area should have properly fitted side and tail boards. · Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin. · The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation.
· The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials. · Vehicle washing facilities should be provided at every vehicle exit point. · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores. · Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet. · Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides. · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites.
|
Work sites / during decommissioning |
Contractor |
|
|
|
|
EIAO-TM & Air Quality Objective |
S5.2.20 |
Solidification · The solidification pit/area should be provided with dust suppression measures. · Handling and mixing of cement shall follow Air Pollution Control (Construction Dust) Regulation to limit cement emission. · The bin should be covered during residence period after mixing process.
Biopiling · During the course of biopile formation, the stockpiled soils at the biopiles should be covered by tarpaulin or low permeable sheet to avoid fugitive emissions of dust or any air pollutants from the biopiles affecting the surrounding environment and to minimise runoff from the stockpiled soils. Biopile(s) should be covered by impermeable sheeting (such that no longer than 5m of a biopile should be exposed to open air) to avoid fugitive emissions of dust or any pollutants from the biopile(s). · Upon formation of a biopile, the biopile should be covered by low permeable geotextiles to prevent dust emission and runoff. · During the operation of biopile, the biopiles should be fully covered to control the extraction of VOCs. · The vented air from the biopile(s) should be connected to blower and carbon adsorption system with 99% control efficiency for treatment before release to the atmosphere. Exhaust air from the blower and carbon adsorption system should be monitored for TVOC bi-weekly to check the performance of the carbon filter. The frequency of monitoring might be adjusted subject to review on site. The location of the exhaust of the carbon filter should be sited as far away as possible from the nearby ASRs. · Spent activated carbon of the carbon adsorption system should be replaced at appropriate intervals such that the TVOC emission concentration from the system is acceptable (i.e. the measured TVOC concentration is below 20ppm). |
Work sites / during solidification and biopiling process |
Contractor |
|
|
|
|
EIAO-TM & Air Quality Objective |
* Des - Design, C - Construction, O
– Operation, and Dec - Decommissioning
Table 5.30 Implementation Schedule for Noise Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S5.3.10 |
Good Site Practice: · Only well-maintained plant should be operated on-site and plant shall be serviced regularly during the decommissioning program. · Silencers or mufflers on construction equipment should be utilized and shall be properly maintained during the decommissioning program. · Mobile plant, if any, should be sited as far away from NSRs as possible. · Machines and plant (such as trucks) that may be in intermittent use shall be shut down between works periods or should be throttled down to a minimum. · Plant known to emit noise strongly in one direction shall, wherever possible, be orientated so that the noise is directed away from the nearby NSRs. · Material stockpiles and other structures should be effectively utilized, wherever practicable, in screening noise from on-site decommissioning activities.
|
Work sites / during decommissioning |
Contractor |
|
|
|
|
EIAO-TM, NCO |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 5.31 Implementation Schedule for Water Quality Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S5.4 |
Decontamination Processes Soil Excavation
· During excavation, all exposed pits shall be whenever possible backfilled immediately or covered. Where it is unavoidable to transiently pile up soils next to the excavation pit, the transient pile shall be bottom-lined, bunded and covered with impervious membrane during rain event in order to avoid generation of contaminated runoff. · Final surfaces after excavation shall be well compacted and the subsequent permanent work or surface protection shall be carried out as soon as practical after the final surfaces are formed to prevent erosion caused by rainstorms. Appropriate intercepting channels and partial shelters shall be provided where necessary to prevent rainwater from collecting within trenches or footing excavations. |
Work site / During excavation |
Contractor |
|
|
|
|
WPCO, TM-DSS |
S5.4 |
Decontaminated Water and
Wastewater from Wheel Washing
· During excavation, dump trucks or excavators shall be decontaminated before they leave the site to ensure that no contaminated earth, mud or debris is deposited by them on roads. A wheel washing bay shall be provided at every site exit that equipped with an adequately sized centralized wastewater treatment unit. The wastewater treatment unit shall deploy suitable treatment processes to settle out sands/ silts with contaminants cohered and remove other contaminants in wheel washes and decontamination water. The polluting parameters in effluent of the wastewater treatment unit shall be in compliance with the discharge standards stipulated in the TM-DSS before the effluent being discharged into the storm drains. The installation and operation of the wastewater treatment unit shall be licensed and subject to the effluent monitoring as required under the WPCO which is under the ambit of regional office (RO) of EPD. In any case, discharge of wheel wash water shall be minimized and recycled where possible. The selection of construction road between the wheel washing bay and the public road should be paved with backfill to reduce vehicle tracking of soil and to prevent surface runoff from entering public road drains.
|
Work site / During excavation |
Contractor |
|
|
Ö |
|
WPCO, TM-DSS |
S5.4 |
Operation of Solidification /
Stabilization Facility
· The solidification facility shall be sheltered and area of soil unloading / loading shall be provided with shed to avoid contaminated runoff. Excessive addition of water shall be avoided during the solidification process. · Any pit used for solidification area shall be shallower than the water table to minimize the leaching of the contaminated soils. An impermeable membrane / sheet shall be placed at the bottom of any solidification pit during the solidification process. · Any leachate generated from the solidification process shall be collected and treated in the centralized wastewater treatment unit before being discharged. The polluting parameters in effluent of the wastewater treatment unit shall be in compliance with the discharge standards stipulated in the TM-DSS before the effluent being discharged. The installation and operation of the wastewater treatment unit shall be licensed and subject to the effluent monitoring as required under the WPCO.
|
Decontamination works area / During soil treatment |
Contractor |
|
|
|
|
WPCO, TM-DSS |
S5.4 |
Operation of Biopiling · Iimpermeable liner shall be placed at the bottom of the biopiles and leachate collection sump shall be constructed along the perimeter of the biopiles to prevent leachate from contaminating the underlying soil/ groundwater. Concrete bund shall be constructed along the perimeter of biopiles to prevent the runoff coming out from the contaminated soil. Biopiles after formation and during rain shall be covered by anchored low permeability geotextiles to prevent contaminated runoff. It is proposed that the exposed biopile section at any time shall not be more than 5 m in length. · All leachate generated from the operation of biopiling shall be collected and recycled to the biopile to avoid effluent discharge.
|
Decontamination works area / During soil treatment |
Contractor |
|
|
|
|
WPCO, TM-DSS |
S5.4 |
Groundwater Cleanup · Floating oil/free product (of TPH) has only been found in the apron area of the Ex-GFS site. It is proposed that where free product is detected at the groundwater surface at excavated area, only the free product shall be skimmed off from the water surface. The skimmed free product shall be drummed properly and collected by a licensed chemical waste collector for disposal. |
Work site / During excavation |
Contractor |
|
|
|
|
WPCO, TM-DSS Waste Disposal (Chemical Waste) (General) Regulation |
S5.4 |
TPH Removal · Petrol interceptor should be adopted, where appropriate, as the first tier of treatment to removal TPH contaminant from contaminated runoff and effluent discharge from the decontamination works area.
|
Work site / During the decommissioning, excavation and soil treatment |
Contractor |
|
|
|
|
WPCO, TM-DSS
|
S5.4 |
Failure of Centralized Wastewater Treatment Unit · In the event of wastewater treatment unit failure, all decontamination activities should be ceased to avoid emergency discharge.
|
Work site / During the decommissioning, excavation and soil treatment |
Contractor |
|
|
|
|
WPCO, TM-DSS
|
S5.4 |
Building Demolition The site practices outlined in ProPECC PN 1/94 “Construction Site Drainage” should be followed as far as practicable in order to minimise surface runoff and the chance of erosion. |
Work sites / during decommissioning |
Contractor |
|
|
|
|
EIAO-TM, WPCO, ProPECC PN 1/94 |
S5.4 |
There is a need to apply to EPD for a discharge licence under the WPCO for discharging effluent from the construction site. The discharge quality is required to meet the requirements specified in the discharge licence. All the runoff, wastewater or extracted groundwater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS. It is anticipated that the wastewater generated from the works areas would be of small quantity. Monitoring of the treated effluent quality from the works areas should be carried out in accordance with the WPCO license which is under the ambit of regional office (RO) of EPD. |
Work sites / during decommissioning |
Contractor |
|
|
|
|
EIAO-TM, WPCO, TM-DSS |
S5.4 |
Sewage from Workforce Temporary sanitary facilities, such as portable chemical toilets, should be employed on-site where necessary to handle sewage from the workforce. A licensed contractor would be responsible for appropriate disposal of waste matter and maintenance of these facilities. |
Work sites / during decommissioning |
Contractor |
|
|
|
|
EIAO-TM, WPCO |
S5.4 |
Solid Waste and Accidental Spillage Debris and refuse generated on-site should be collected, handled and disposed of properly to avoid entering into the adjacent harbour waters. Stockpiles of cement and other construction materials should be kept covered when not being used. |
Work sites / during decommissioning |
Contractor |
|
|
|
|
EIAO-TM, WPCO, WDO |
S5.4 |
Oils and fuels should only be used and stored in designated areas which have pollution prevention facilities. To prevent spillage of fuels and solvents to the nearby harbour waters, all fuel tanks and storage areas should be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank. The bund should be drained of rainwater after a rain event. |
Work sites / during decommissioning |
Contractor |
|
|
|
|
EIAO-TM, WPCO, WDO |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 5.32 Implementation Schedule for Waste Management Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S5.5 |
Good Site Practices It is not anticipated that adverse waste management related impacts would arise, provided that good site practices are adhered to. Recommendations for good site practices during decommissioning activities include: · Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site · Training of site personnel in proper waste management and chemical waste handling procedures · Provision of sufficient waste disposal points and regular collection for disposal · Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers · A recording system for the amount of wastes generated, recycled and disposed of (including the disposal sites) |
Work sites / during decommissioning |
Contractor |
|
|
|
Ö |
EIAO-TM |
S5.5 |
Waste Reduction Measures Good management and control can prevent the generation of a significant amount of waste. Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction include: · Sort C&D waste from demolition of the remaining structures to recover recyclable portions such as metals · Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal · Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force · Any unused chemicals or those with remaining functional capacity should be recycled · Proper storage and site practices to minimise the potential for damage or contamination of construction materials |
Work sites / during decommissioning |
Contractor |
|
|
|
Ö |
EIAO-TM |
S5.5 |
Construction and Demolition Material Mitigation measures and good site practices should be incorporated into the contract document to control potential environmental impact from handling and transportation of C&D material. The mitigation measures include: · Where it is unavoidable to have transient stockpiles of C&D material within the work site pending collection for disposal, the transient stockpiles shall be located away from waterfront or storm drains as far as possible · Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric · Skip hoist for material transport should be totally enclosed by impervious sheeting · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving a construction site · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores · The load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure dust materials do not leak from the vehicle · All dusty materials should be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet · The height from which excavated materials are dropped should be controlled to a minimum practical height to limit fugitive dust generation from unloading |
Work sites / during decommissioning |
Contractor |
|
|
|
Ö |
ETWB TCW No. 33/2002, 31/2004, 19/2005 |
|
When delivering inert C&D material to public fill reception facilities, the material should consist entirely of inert construction waste and of size less than 250mm or other sizes as agreed with the Secretary of the Public Fill Committee. In order to monitor the disposal of the surplus C&D material at the designed public fill reception facility and to control fly tipping, a trip-ticket system as stipulated in the ETWB TCW No. 31/2004 “Trip Ticket System for Disposal of Construction and Demolition Materials” should be included as one of the contractual requirements and implemented by an Environmental Team undertaking the Environmental Monitoring and Audit work. An Independent Environmental Checker should be responsible for auditing the results of the system. |
Work site / during decommissioning |
Contractor and Independent Environmental Checker |
|
|
|
Ö |
ETWB TCW No. 31/2004 |
S5.5 |
Chemical Waste
After use, chemical wastes (for example, cleaning fluids, solvents, lubrication oil and fuel) should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Spent chemicals should be collected by a licensed collector for disposal at the CWTF or other licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation |
Work sites / during decommissioning |
Contractor |
|
|
|
Ö |
Waste Disposal (Chemical Waste) (General) Regulation
Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes |
S5.5 |
General Refuse
General refuse should be stored in enclosed bins or compaction units separate from C&D material. A licensed waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material. Effective collection and storage methods (including enclosed and covered area) of site wastes would be required to prevent waste materials from being blown around by wind, wastewater discharge by flushing or leaching into the marine environment, or creating odour nuisance or pest and vermin problem |
Work sites / during decommissioning |
Contractor |
|
|
|
Ö |
Waste Disposal Ordinance
Water Pollution Control Ordinance |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning
Table 5.33 Implementation Schedule for Land Contamination Measures
EIA Ref |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stages* |
Relevant Legislation and Guidelines |
|||
Des |
C |
O |
Dec |
|||||
S5.6.96 |
For any excavation works conducted at Radar Station and ex-GFS building, · As the risk due to dermal contact with groundwater by site workers is uncertain, it is recommended that personnel protective equipment (PPE) be used by site workers as a mitigation measure. |
Radar Station and ex-GFS building |
Contractor |
|
Ö |
|
|
|
S5.6.35, S5.6.51to S5.6.60
S5.6.94
S.5.6.94
S5.6.94
S5.6.95
|
For ex-GFS building, the following environmental mitigation measures are proposed during the course of the site remediation in order to minimise the potential adverse environmental impacts arising from the handling of potentially contaminated materials: Excavation and decontamination works · Personal protective equipment (PPE) should be used by site workers during soil excavation. · All contaminated soil within the ex-GFS building should be excavated and treated on-site at a centralized decontamination works area located at the northern part of the south apron · After excavation, confirmation sampling and testing should be conducted to ensure complete excavation of contaminated soils · Contaminated soil should be sorted and handled with respect of their contamination · Health and safety plan for excavation should be followed · The following remediation processes should be applied for different types of soil contamination - Biopiling for TPH/SVOCs contamination - Solidification / stabilization for metal contamination
Excavation and Transportation · Excavation profiles must be properly designed and executed. · Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission. If this is not practicable due to frequent usage, regular watering should be applied. However, watering should be avoided on stockpiles of contaminated soil to minimise contaminated runoff. · Stockpiles of contaminated soil should be properly covered by impermeable sheeting to minimise contaminated runoff from the stockpiles. · Excavation and stockpiling should be carried out during dry season as far as possible to minimise contaminated runoff from contaminated soils. · Supply of suitable clean backfill material is needed after excavation. · Vehicles containing any excavated materials should be suitably covered to limit potential dust emissions or contaminated wastewater run-off, and truck bodies and tailgates should be sealed to prevent any discharge during the transportation or during wet conditions. · Speed control for the trucks carrying contaminated materials should be enforced; · Vehicle wheel and body washing facilities at the site’s exist points should be established and used. Biopiling · To avoid fugitive emissions of dust or any air pollutants from the biopile(s) and to minimise runoff from the stockpiled soils, the stockpiled soils at the biopiles should be covered by impermeable sheeting such that not longer than 5m of the biopile is exposed to open air. · Upon formation of a biopile, the biopile should be fully covered by impermeable sheeting to prevent dust emission and runoff. · Impermeable sheeting should be placed at the bottom of the biopiles and leachate collection sump should be constructed along the perimeter of the biopiles to prevent leachate from contaminating the underlying soil/groundwater. The collected leachate should be discharged following the requirements of Water Pollution Control Ordinance (WPCO). · The vented air from the biopile(s) should be connected to blower and carbon adsorption system with at least 99% control efficiency for treatment before release to the atmosphere. Exhaust air from the blower and carbon adsorption system should be monitored for TVOCs biweekly to check the performance of the carbon filter. The frequency of monitoring might be adjusted, subject to review on site. · The biopiles should be fully covered by impermeable sheeting to control the extraction of VOCs. · Spent activated carbon of the carbon adsorption system should be replaced at appropriate intervals such that the TVOC emission concentration from the system is acceptable (i.e. the measured TVOC concentration is below 20 ppm). · Silencers should be installed at the biopile blowers to minimise noise impact. · Contaminated runoff from biopile(s) should be prevented by constructing concrete bunds along the perimeter of the biopiles. Solidification / Stabilization · The loading, unloading, handling, transfer and storage of cement should be carried out in an enclosed system. · Mixing process and other associated material handling activities should be properly scheduled to minimise potential noise impact. · Mixing of contaminated soils with cement / water / other additive(s) should be undertaken at a solidification plant to minimise the potential for leaching. · Runoff from the solidification / stabilization area should be prevented by constructing concrete bunds along the perimeter. In order to minimise the potential adverse effects on health and safety of construction workers during the course of site remediation, the Occupational Safety and Health Ordinance (OSHO) Chapter 509, and its subsidiary Regulations should be followed by all site personnel working on the site at all times. In addition, the following basic health and safety measures should be implemented as far as possible: · Set up a list of safety measures for site workers; · Provide written information and training on safety for site workers; · Keep a log-book and plan showing the contaminated zones and clean zones; · Maintain a hygienic working environment; · Avoid dust generation; · Provide face and respiratory protection gear to site workers; · Provide personal protective clothing (e.g. chemical resistant jackboot, liquid tight gloves) to site workers; and · Provide first aid training and materials to site workers.
|
Excavation zones/ During excavation
Excavation zones/ During excavation
Excavation zones/ During excavation
Excavation zones/ During excavation
Excavation zones/ During excavation
Decontamination works area/ During excavation
Excavation zones and decontamination works area/ During excavation and soil treatment
Excavation zones and decontamination works area/ During excavation and soil treatment
Excavation zones and decontamination works area/ During excavation and soil treatment
Excavation zones and decontamination works area/ During excavation and soil treatment
|
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
Contractor
|
Ö
Ö
Ö
Ö
Ö
Ö
Ö |
|
|
Ö
Ö
Ö
Ö
Ö
Ö
Ö
Ö
Ö
Ö |
Occupational Safety & Health Ordinance
l Waste Disposal Ordinance l Waste Disposal (Chemical Waste) (General) Regulation l Water Pollution Control Ordinance l Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes
Occupational Safety and Health Ordinance, Chapter 509 and its subsidiary Regulations.
|
S5.6.97 |
For the remaining areas with potential land contamination concerns in ex-GFS building and Radar Station, · A supplementary land contamination assessment shall be carried out upon the cessation of the operations and prior to the redevelopment, following the approved supplementary sampling plan in the respective CAR and/ or RAP of Radar Station and ex-GFS building in the EIA Report. · Supplementary CAR(s) and if necessary RAP(s) shall be prepared. If contamination is identified in the supplementary site investigation, remediation shall be performed according to the supplementary CAR/RAP upon EPD’s approval.
|
Ex-GFS building and Radar Station |
CEDD |
Ö |
|
|
Ö |
the Practice Note for Professional Persons ProPECC PN3/94
“Contaminated Land Assessment and Remediation” and “Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair /Dismantling Workshop“ |
* Des - Design, C - Construction, O – Operation, and Dec - Decommissioning