Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance
Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Impact Assessment Report
Contents
7............ NOISE
Impact. 7-1
7.1 Introduction. 7-1
7.2 Environmental Legislation, Policies, Plans, Standards
and Criteria. 7-1
7.3 Description of the Environment 7-1
7.4 Noise Sensitive Receivers. 7-1
7.5 Assessment Methodology. 7-1
7.6 Identification of Environmental Impacts. 7-1
7.7 Prediction and Evaluation of Environmental
Impacts. 7-1
7.8 Mitigation of Environmental Impacts. 7-1
7.9 Evaluation of Residual Impacts. 7-1
7.10 Environmental Monitoring and Audit 7-1
7.11 Summary. 7-1
Lists of Tables
Table
7.1
Construction Noise Criteria for Activity other than
Percussive Piling
Table
7.2
Acceptable Noise Levels for Percussive Piling
Table
7.3
Permitted Hours of Operation for Percussive Piling
Table
7.4
Operational Noise Criteria for Fixed Noise Sources
Table
7.5
Summary of Area Sensitive Rating for NSRs for Fixed Plant
Noise Assessment
Table
7.6
Representative Noise Sensitive Receivers for Noise Impact
Assessment
Table
7.7
Measured SWLs for Kai Tak Tunnel Ventilation Shaft
Table
7.8
A Comparison of Typhoon Shelters in Relation to NSRs in
Hong Kong
Table
7.9
Summary of Cumulative Unmitigated Construction Noise Levels
at Representative NSRs During Normal Daytime Working Hours
Table
7.10
Summary of Traffic Noise Impact for Other Sites within KTD
area
Table
7.11
Predicted Maximum Allowable Sound Power Levels for ESS
Table
7.12
Summary of Predicted Operational Noise Levels
Table
7.13
Predicted Maximum Allowable Sound Power Levels for Ventilation
Shafts
Table
7.14
Summary of Predicted Operational Noise Levels
Table
7.15
Predicted Maximum Allowable Sound Power Levels for SCL
Ventilation Shafts
Table
7.16
Summary of Predicted Operational Noise Levels
Table
7.17
Predicted Maximum Allowable Sound Power Levels for Cruise
Terminal Ventilation
Table
7.18
Summary of Predicted Operational Noise Levels
Table
7.19
Predicted Maximum Allowable Sound Power Levels for EFTS
Depot
Table
7.20
Summary of Predicted Operational Noise Levels
Table
7.21
Predicted Maximum Allowable Sound Power Levels for PTI
Ventilation System
Table
7.22
Summary of Predicted Operational Noise Levels
Table
7.23
Summary of Predicted Operational Noise Levels
Table
7.24
Predicted Maximum Allowable Sound Power Levels for DCSP
Table
7.25
Summary of Predicted Operational Noise Levels
Table
7.26
Predicted Potential Noise Impact from the Main Stadium on
the Nearest NSRs
Table
7.27
Summary of Helicopter Noise Emission Data
Table
7.28
Summary of Cumulative Mitigated Construction Noise Levels
at Representative NSRs During Normal Daytime Working Hours
Table
7.29
Construction Noise Residual Impacts
7
NOISE Impact
7.1
Introduction
7.1.1
This section presents noise impact assessment
for the construction and operational phases of the Kai Tak Development.
Existing and planned noise sensitive receivers in the vicinity of the study
area are determined. Potential noise quality impacts associated with the
Project have been identified together with the proposed methodology for the
respective impact assessments.
7.2
Environmental Legislation,
Policies, Plans, Standards and Criteria
General
7.2.1
Noise impacts were
assessed in accordance with the criteria and methodology given in the Technical
Memoranda (TMs) under the Noise Control Ordinance (NCO), and the Technical Memorandum
on Environmental Impact Assessment Process (EIAO-TM).
7.2.2
The NCO and EIAO
provide the statutory framework for noise control. Assessment procedures
and standards are set out in the five TMs listed below:
l
TM on Environmental
Impact Assessment Process (EIAO-TM)
l
TM on Noise from
Construction Work other than Percussive Piling (GW-TM)
l
TM on Noise from
Percussive Piling (PP-TM)
l
TM on Noise from
Construction Work in Designated Areas (DA-TM)
l
TM on Noise from Places
other than Domestic Premises, Public Places or Construction Sites (IND-TM)
Construction Noise – General Construction
7.2.3
The NCO provides the statutory
framework for noise control of construction work, other than percussive piling,
using powered mechanical equipment (PME) between the hours of 1900 and 0700
hours or at any time on Sundays and general holiday (that is, restricted
hours). Noise control on construction activities taking place at other
times is subject to the Criteria for Evaluating Noise Impact stated in
Table 1B of Annex 5 in the EIAO-TM. The noise limit is Leq (30
minutes) 75 dB(A) at the façades of dwellings
and 70 dB(A) at the façade of schools (65 dB(A) during examinations).
7.2.4
Between 1900 and 0700
hours and all day on Sundays and public holidays, activities involving the use
of PME for the purpose of carrying out construction work is prohibited unless a
construction noise permit (CNP) has been obtained. A CNP may be granted
provided that the Acceptable Noise Level (ANL) for the NSRs can be complied
with. ANLs are assigned depending upon the area sensitive rating
(ASR). The corresponding basic noise levels (BNLs) for evening and night
time periods are given in Table 7.1.
Table
7.1
Construction Noise Criteria for Activity other than Percussive Piling
|
Basic Noise Level (BNLs)
|
|
ASR B
|
ASR C
|
Evening (1900 to 2300 hours) (1)
|
60
|
65
|
70
|
|
45
|
50
|
55
|
Notes: (1) Includes Sundays and Public Holidays during daytime and
evening
7.2.5
Despite any description
or assessment made in this EIA on construction noise aspects, there is no
guarantee that a Construction Noise Permit (CNP) will be issued for the project
construction. The Noise Control Authority will consider a well-justified
CNP application, once filed, for construction works within restricted hours as
guided by the relevant Technical Memoranda issued under the Noise Control
Ordinance. The Noise Control Authority will take into account of
contemporary conditions / situations of adjoining land uses and any previous
complaints against construction activities at the site before making his
decision in granting a CNP. Nothing in this EIA shall bind the Noise
Control Authority in making his decision. If a CNP is to be issued, the
Noise Control Authority shall include in it any condition he thinks fit.
Failure to comply with any such conditions will lead to cancellation of the CNP
and prosecution action under the NCO.
7.2.6
Percussive piling is
prohibited between 1900 and 0700 hours on any weekday not being a general
holiday and at any time on Sunday or general holiday. A CNP is required
for the carrying out of percussive piling between 0700 and 1900 hours on any
day not being a general holiday. PP-TM sets out the requirements for working
and determination of the permitted hours of operations. ANLs for
percussive piling for different types of NSRs are shown in Table 7.2.
Table
7.2
Acceptable Noise Levels for Percussive Piling
|
|
|
100
|
NSR
with central air conditioning system
|
90
|
NSR
with windows or other openings but without central air conditioning system
|
85
|
Note:
10 dB(A) shall be subtracted from the ANLs shown above for NSRs which
are hospitals, medical clinics, educational institutes, courts and law or other
NSRs which are considered by the Authority to be particularly sensitive to
noise.
7.2.7
In accordance with
PP-TM, the permitted hours of operation for carrying out of percussive piling
work, subject to the issuance of a CNP, are listed in Table 7.3.
Table
7.3
Permitted Hours of Operation for Percussive Piling
Amount by which Corrected Noise
Level (CNL) exceeds Acceptable Noise Level (ANL), CNL-ANL
|
Permitted hours of operation on
any day not being a general holiday
|
|
|
|
|
Operational Road Traffic Noise
7.2.8
For road traffic noise,
Annex 5, Table 1A “A Summary of Noise Criteria” of the EIAO-TM defines the
criteria L10(1 hour) for the road traffic noise at various noise
sensitive receivers (NSRs):
· 70dB(A) at the façades of residential
dwellings, hotels, offices;
· 65dB(A) at the façades of schools, places of
public worship, courts of law, places where unaided voice communication is
required; and
· 55dB(A) at the façades of hospital or clinics.
7.2.9
If any façades of NSRs
are still exposed to predicted noise levels exceeding the relevant noise
criteria after the implementation of all direct mitigation measures, provision
of indirect technical remedies in the form of acoustic insulation and air
conditioning should be considered under the EIAO-TM and the ExCo Directive
“Equitable Redress for Persons Exposed to Increased Noise Resulting from the
Use of New Roads”. The eligibility for indirect technical remedies shall
be tested against the following three criteria:
·
the predicted overall
noise level from the new road, together with other traffic noise in the
vicinity must be above a specified noise level (for example, 70 dB(A) for
domestic premises and 65 dB(A) for educational institutions, all in L10 (1
hour)); and
·
the predicted overall
noise level is at least 1.0 dB(A) more than the prevailing traffic noise level,
that is, the total traffic noise level existing before the works to construct
the road commence; and
·
the contribution to the
increase in the predicted overall noise level from the new road must be at
least 1.0 dB(A).
7.2.10 For the purpose of the traffic noise
assessment in this Report, the roads within 300m from the proposed project alignment
were included in the assessment. All roads are described as one of the
following:
·
‘Existing’ Roads:
includes Prince Edward Road East, Kwun Tong Bypass and other existing roads
around KTD.
·
‘New’ Roads: includes
all new roads created and roads substantially altered in KTD.
7.2.11 The noise contribution from “New”
roads should be less than 70 dB(A) at any dwellings (less than 65 dB(A) for
educational institutions and places of public worship), so as to satisfy the
relevant noise criteria, and there should not be any increase in traffic noise
impact. In the case of an NSR where existing noise levels already
exceeded the relevant criteria, any increase in noise level contributed by the
“new” roads should be less than 1.0 dB(A). The extent of ‘New’ roads
under this Project has been depicted in Appendix 3.18.
Operational Phase Fixed Plant Noise
7.2.12 Fixed plant noise sources, such as cruise
terminal operation, sewage pumping stations, tunnel ventilation shafts,
ventilating systems for public transport interchange and electric substation,
are controlled by the NCO and IND-TM with a noise criteria of 5 dB(A) below the
appropriate Acceptable Noise Levels (ANL) shown in Table 3 of the TM on Noise
from Places other than Domestic Premises, Public Places or Construction Sites
or the prevailing background noise levels (for quiet areas with level 5dB(A)
below the ANL). The ANLs for different Area Sensitivity Ratings are
summarised in Table 7.4 below.
Table 7.4
Operational Noise Criteria for Fixed Noise Sources
Time Period
|
ANL, dB(A)
|
Criteria (ANL-5), dB(A)
|
ASR A
|
ASR B
|
ASR C
|
ASR A
|
ASR B
|
ASR C
|
Day (0700 to 1900 hours)
|
60
|
65
|
70
|
55
|
60
|
65
|
Evening (1900 to 2300 hours)
|
60
|
65
|
70
|
55
|
60
|
65
|
Night (2300 to 0700 hours)
|
50
|
55
|
60
|
45
|
50
|
55
|
7.2.13 The Project areas are located in the
proximity to well developed urban areas and the prevailing background noise
level measurements at selected representative NSRs have been conducted and it
is demonstrated that the prevailing background noise level are higher than
ANL-5 (Appendix 7.1).
Thus, ANL-5 has been adopted for the fixed plant noise impact assessment.
The Area Sensitive Rating (ASR) of the type of area within which the NSR is
located was determined for assessment. Determination of ASR was
considered the below item.
· The type of area within the concerned NSR is
located;
· The Influencing Factor (IF) identified;
· The Degree to which the NSR is affected by IF;
and
· If applicable, nearby OZP “Industrial” or
“Industrial Estates” zone
7.2.14 A summary of the Area Sensitive
Rating (ASR) for the NSRs for the fixed plant noise assessment is given in Table
7.5.
Table 7.5
Summary of Area Sensitive Rating for NSRs for Fixed Plant Noise Assessment
NSRs
|
District (1)
|
Location
|
Existing /
Planned Land Use
|
ASR (2)
|
Remarks
|
N1
|
KT
|
Cha Kwo Ling Tsuen
|
Residential
|
B
|
|
N2
|
KT
|
Cha Kwo Ling
|
Residential
|
B
|
|
N3
|
KT
|
Laguna City IV
|
Residential
|
C
|
(3) (a)
|
N4
|
KB
|
Buddhist Chi King Primary School
|
Educational
|
C
|
(3) (a)
|
N5
|
KB
|
S.K.H Kowloon Bay Kei Lok Primary School
|
Educational
|
C
|
(3) (a)
|
N6
|
KB
|
Richland Gardens
|
Residential
|
C
|
(3) (a)
|
N7
|
NCW
|
Luk Ching House, Choi Hung Estate
|
Residential
|
C
|
(3) (a)
|
N8
|
NCW
|
Kam Pik House, Choi Hung Estate
|
Residential
|
C
|
(3) (a)
|
N9
|
NCW
|
Pik Hoi House, Choi Hung Estate
|
Residential
|
C
|
(3) (a)
|
N10A
|
SPK
|
Rhythm Garden (Block 7)
|
Residential
|
C
|
(3) (b)
|
N10B
|
SPK
|
Rhythm Garden (Block 9)
|
Residential
|
C
|
(3) (b)
|
N11
|
SPK
|
Cognitio College
|
Educational
|
C
|
(3) (b)
|
N12
|
SPK
|
Sir Robert Black Health Centre
|
Clinic
|
C
|
(3) (b)
|
N13
|
SPK
|
Lee Kau Yan Memorial School
|
Educational
|
C
|
(3) (b)
|
N14
|
SPK
|
South Mansion
|
Residential
|
C
|
(3) (b)
|
N15
|
SPK
|
Jenford Building
|
Residential
|
C
|
(3) (b)
|
N16
|
KC
|
Parc 22
|
Residential
|
C
|
(3) (c)
|
N17
|
KC
|
Sky Tower
|
Residential
|
C
|
(3) (c)
|
N18
|
KC
|
HK Society for Blind hostel
|
Residential
|
B
|
|
N19
|
TKW
|
Mok Cheong Street Residential District
|
Residential
|
B
|
|
N20A
|
TKW
|
Grand Waterfront
|
Residential
|
B
|
|
N20B
|
TKW
|
Grand Waterfront
|
Residential
|
B
|
|
N21
|
TKW
|
Hang Chien Court
|
Residential
|
B
|
|
N22
|
TKW
|
Wei Chien Court
|
Residential
|
B
|
|
N23
|
TKW
|
Holly Carpenter Primary School
|
Educational
|
B
|
|
N24
|
TKW
|
Oblate Father’s Primary School
|
Educational
|
B
|
|
N25
|
TKW
|
Sunrise Villa
|
Residential
|
B
|
|
N26
|
TKW
|
Wing Kwong Street Residential District
|
Residential
|
B
|
|
N27
|
TKW
|
CCC Kei To Secondary School
|
Educational
|
B
|
|
N28
|
TKW
|
Po Leung Kuk Ngan Po Ling College
|
Educational
|
B
|
|
N29
|
TKW
|
Sunrise Plaza
|
Residential
|
B
|
|
N30
|
TKW
|
Ming Lung Street
|
Residential
|
B
|
|
N31
|
SPK
|
Canossa Primary School (San Po Kong)
|
Educational
|
B
|
|
N32
|
TKW
|
Holy Trinity Church
|
Place of Public Worship
|
C
|
(3) (c)
|
PN1
|
SPK
|
Rhine
Harbour (Planned)
|
Residential
|
C
|
(3) (b)
|
PN2
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN3
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN4
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN5
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN6A
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN6B
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN7A
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN7B
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN8
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN9
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN10
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN11
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN12
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN13
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN14
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN15
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN16
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN17
|
KTD
|
Site 1A1
(Planned)
|
Residential
|
B
|
|
PN18
|
KTD
|
Site 1A2
(Planned)
|
Educational
|
B
|
|
PN19
|
KTD
|
Site 1A3
(Planned)
|
Educational
|
B
|
|
PN20
|
KTD
|
Site 1A4 (Planned)
|
Educational
|
B
|
|
PN21
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN22
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN23A
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN23B
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN23C
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN24
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN25
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN26
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN27
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN28
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN29
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN30A
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN30B
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN31A
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN31B
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN32
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN33
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN34
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN35
|
KTD
|
Site 1B1
(Planned)
|
Residential
|
B
|
|
PN36
|
KTD
|
Site 1B2
(Planned)
|
Educational
|
B
|
|
PN37
|
KTD
|
Site 1B3
(Planned)
|
Educational
|
B
|
|
PN38
|
KTD
|
Site 1B4 (Planned)
|
Educational
|
B
|
|
PN39
|
KTD
|
Site 1I1
(Planned)
|
Residential
|
B
|
|
PN40
|
KTD
|
Site 1I1
(Planned)
|
Residential
|
B
|
|
PN41
|
KTD
|
Site 1I2
(Planned)
|
Residential
|
B
|
|
PN42
|
KTD
|
Site 1I2
(Planned)
|
Residential
|
B
|
|
PN43
|
KTD
|
Site 1I3
(Planned)
|
Residential
|
B
|
|
PN44
|
KTD
|
Site 1I3
(Planned)
|
Residential
|
B
|
|
PN45
|
KTD
|
Site 1K1
(Planned)
|
Residential
|
B
|
|
PN46
|
KTD
|
Site 1H2
(Planned)
|
Residential
|
B
|
|
PN47
|
KTD
|
Site 1L2
(Planned)
|
Residential
|
B
|
|
PN48
|
KTD
|
Site 1K3
(Planned)
|
Residential
|
B
|
|
PN49
|
KTD
|
Site 1K2
(Planned)
|
Residential
|
B
|
|
PN50
|
KTD
|
Site 1L2
(Planned)
|
Residential
|
B
|
|
PN51
|
KTD
|
Site 1L3
(Planned)
|
Residential
|
B
|
|
PN52
|
KTD
|
Site 1L3
(Planned)
|
Residential
|
B
|
|
PN53
|
KTD
|
Site 1L3
(Planned)
|
Residential
|
B
|
|
PN54
|
KTD
|
Site 1L1
(Planned)
|
Residential
|
B
|
|
PN55
|
KTD
|
Site 2B1
(Planned)
|
Residential
|
B
|
|
PN56
|
KTD
|
Site 2B1
(Planned)
|
Residential
|
B
|
|
PN57
|
KTD
|
Site 2B2
(Planned)
|
Residential
|
B
|
|
PN58
|
KTD
|
Site 2B3
(Planned)
|
Residential
|
B
|
|
PN59
|
KTD
|
Site 2B4
(Planned)
|
Residential
|
B
|
|
PN60
|
KTD
|
Site 2B5
(Planned)
|
Residential
|
B
|
|
PN61
|
KTD
|
Site 2B6
(Planned)
|
Residential
|
B
|
|
PN62
|
KTD
|
Site 2B6
(Planned)
|
Residential
|
B
|
|
PN63
|
KTD
|
Site 4A1
(Planned)
|
Residential
|
B
|
|
PN64
|
KTD
|
Site 4B5
(Planned)
|
Residential
|
B
|
|
PN65
|
KTD
|
Site 5A4
(Planned)
|
Residential
|
B
|
|
PN66
|
KTD
|
Site 5A4
(Planned)
|
Residential
|
B
|
|
PN67
|
KTD
|
Site 5C5
(Planned)
|
Educational
|
B
|
|
PN68
|
KTD
|
Site 5C6
(Planned)
|
Educational
|
B
|
|
PN69
|
KTD
|
Site 1D3 (Planned)
|
Community Use with hostel
|
C
|
(3) (b)
|
PN70
|
KTD
|
Site 1D3
(Planned)
|
Community Use with hostel
|
B
|
|
PN71
|
KTD
|
Site 1E1
(Planned)
|
Mixed Use
|
C
|
(3) (b)
|
PN72
|
KTD
|
Site 1E1
(Planned)
|
Mixed Use
|
C
|
(3) (b)
|
PN73
|
KTD
|
Site 1F1
(Planned)
|
Mixed Use
|
B
|
|
PN74
|
KTD
|
Site 1M1
(Planned)
|
CDA
|
B
|
|
PN75
|
KTD
|
Site 1M2
(Planned)
|
CDA
|
B
|
|
PN76
|
KTD
|
Site 3B1
(Planned)
|
Undesignated
|
C
|
(3) (a)
|
PN77
|
KTD
|
Site 3B2
(Planned)
|
Undesignated
|
C
|
(3) (a)
|
PN78
|
KTD
|
Site 3B3
(Planned)
|
Undesignated
|
C
|
(3) (a)
|
PN79
|
KTD
|
Site 3B4
(Planned)
|
Undesignated
|
C
|
(3) (a)
|
PN80
|
KTD
|
Site 3C1
(Planned)
|
Hospital / Clinic
|
C
|
(3) (a)
|
PN81
|
KTD
|
Site 3C1
(Planned)
|
Hospital / Clinic
|
C
|
(3) (a)
|
PN82
|
KTD
|
Site 3C1
(Planned)
|
Hospital / Clinic
|
C
|
(3) (a)
|
PN83
|
KTD
|
Site 3C1
(Planned)
|
Hospital / Clinic
|
C
|
(3) (a)
|
PN84
|
KTD
|
Site 3C1
(Planned)
|
Hospital / Clinic
|
C
|
(3) (a)
|
PN85
|
KTD
|
Site 3C1
(Planned)
|
Hospital / Clinic
|
C
|
(3) (a)
|
PN86
|
KTD
|
Site 3C1
(Planned)
|
Hospital / Clinic
|
B
|
|
PN87A
|
KTD
|
Site 3E1
(Planned)
|
Commercial
|
B
|
|
PN87B
|
KTD
|
Site 3E1
(Planned)
|
Commercial
|
B
|
|
PN88
|
KTD
|
Site 3D2 (Planned)
|
Commercial
|
C
|
(3) (a)
|
PN89
|
KTD
|
Site 3D2
(Planned)
|
Commercial
|
C
|
(3) (a)
|
PN90
|
KTD
|
Site 3D3
(Planned)
|
Commercial
|
C
|
(3) (a)
|
PN91A
|
KTD
|
Site 3D4
(Planned)
|
Commercial
|
C
|
(3) (a)
|
PN91B
|
KTD
|
Site 3D4 (Planned)
|
Commercial
|
C
|
(3) (a)
|
PN92
|
KTD
|
Site 3D4
(Planned)
|
Commercial
|
C
|
(3) (a)
|
PN92A
|
KTD
|
Site 3D4
(Planned) facing the existing public cargo working area
|
Commercial
|
C
|
(3) (a)
|
PN93
|
TKW
|
Sung Wong
Toi Road CDA site
|
CDA
|
B
|
|
PN94
|
TKW
|
Sung Wong
Toi Road CDA site
|
CDA
|
B
|
|
PN95
|
TKW
|
Sung Wong
Toi Road CDA site
|
CDA
|
B
|
|
PN96
|
KTD
|
Site 2A1
(Planned)
|
Commercial
|
C
|
(3) (b)
|
PN97
|
KTD
|
Site 2A2
(Planned)
|
Commercial
|
C
|
(3) (b)
|
PN98
|
KTD
|
Site 2A3
(Planned)
|
Commercial
|
C
|
(3) (b)
|
PN99
|
KTD
|
Site 2A4
(Planned)
|
Commercial
|
C
|
(3) (b)
|
PN100
|
KTD
|
Site 2A5
(Planned)
|
Commercial
|
C
|
(3) (b)
|
PN101
|
KTD
|
Site 2A6
(Planned)
|
Commercial
|
C
|
(3) (b)
|
PN102
|
KTD
|
Site 4A2
(Planned)
|
Commercial
|
B
|
|
PN103
|
KTD
|
Site 4C1
(Planned)
|
Commercial
|
B
|
|
PN104
|
KTD
|
Site 4C2
(Planned)
|
Commercial
|
B
|
|
PN105
|
KTD
|
Site 4C3
(Planned)
|
Commercial
|
B
|
|
PN106
|
KTD
|
Site 4C4
(Planned)
|
Commercial
|
B
|
|
PN107
|
KTD
|
Site 4C5
(Planned)
|
Commercial
|
B
|
|
PN108
|
KTD
|
Site 4A3
(Planned)
|
Commercial
|
B
|
|
PN109
|
SPK
|
Choi Hung
Road CDA Site (Planned)
|
CDA
|
B
|
|
PN110
|
SPK
|
Ex-San Po Kong Flatted Factory
|
Residential
|
B
|
|
PN111
|
SPK
|
Ex-San Po Kong Flatted Factory
|
Residential
|
B
|
|
PN112
|
SPK
|
Ex-San Po Kong Flatted Factory
|
Residential
|
B
|
|
Note:
(1) KT – Kwun Tong; NTK – Ngau Tau Kok; KB – Kowloon
Bay; NCW – Ngau Chi Wah; SPK – San Po Kong; KC – Kowloon City, TKW – To Kwa
Wan; HH – Hung Hom; KTD – Kai Tak Development.
(2) All NSRs are located in Urban
Area.
(3) NSR affected by “major road”
that has heavy and generally continuous flow of vehicular traffic and, in
normal circumstances, means a road with an annual average daily traffic flow in
excess of 30,000.
(a) affected by Kwun Tong Bypass
(b) affected by Prince Edward Road East
(c) affected by Ma Tau Chung Road
Noise from Open Air Entertainment Activities
7.2.15 For the operation of the proposed Stadium
Complex in KTD, the Noise Control Guidelines for Holding Open Air Entertainment
Activities stipulated by EPD has to be followed. Noise level from the
activity (including set up, rehearsal, main event and stage dismantling etc.)
should not be more than 5 dB(A) above the background noise level, as measured
at one metre from the exterior building facade of the most affected noise
sensitive receivers, during day time and evening period, i.e. 0700 – 2300
hours. For the night time, i.e. 2300 – 0700 hours, noise should not be
audible within nearby noise sensitive receivers.
Heliport Noise
7.2.16 Potential noise impact would be
arisen from the operation of the heliport proposed at the tip of the former
runway. According to Table 1A of Annex 5 “A Summary of Noise Criteria” in
the EIAO-TM, the criteria for helicopter noise is Lmax 90dB(A) for offices and
Lmax 85dB(A) for domestic premises, hotels, hostels, education institutes,
places of worship, hospital and clinics during 0700-1900 hours. The standards
apply to uses that rely on openable windows for ventilation and the standards
should be viewed as the maximum permissible noise levels assessed at 1m from
the external façade.
Rail Noise
7.2.17 Railway noise is controlled under
the Noise Control Ordinance (NCO), IND-TM and EIAO-TM. The ANLs for
different Area Sensitivity Ratings are summarised in Table 7.4
above. According to Table 1A of Annex 5 “A Summary of Noise Criteria” in
the EIAO-TM, the criteria for rail noise is Lmax 85dB(A) for all sensitive
receiver during 2300-0700 hours and the appropriate ANL shown in Table 2 of the
TM on Noise from Places other than Domestic Premises, Public Places or
Construction Sites. The standards apply to uses that rely on openable
windows for ventilation and the standards should be viewed as the maximum
permissible noise levels assessed at 1m from the external façade.
Marine Traffic Noise (include noise from
typhoon shelters)
7.2.18 Marine traffic noise sources, such
as marine traffic noise from operation activities on the moored vessels in
typhoon shelters and manoeuvring of vessels including cruise vessels during
operational phase of the proposed development. It is
similar to noise from public place which vessels are free to move around and
implementation control measures are not possible. It is not even possible
to quantify accurately or compare to existing standard. No objective
noise standard for marine traffic noise (include noise from typhoon shelters)
in this EIA.
7.3
Description of the Environment
7.3.1
The Study Area is
located in the southeastern part of Kowloon Peninsula and comprises the north
apron and runway areas of the former Kai Tak Airport, existing waterfront areas
at To Kwa Wan, Ma Tau Kok, Kowloon Bay, Kwun Tong and Cha Kwo Ling. It
has an area of 328 ha, including 48 ha of existing built-up area adjacent to
the former airport site. It also covers the Kowloon Bay, To Kwa Wan
Typhoon Shelter and Kwun Tong Typhoon Shelter.
7.3.2
The existing land uses
in adjoining areas are commercial, industrial, residential and recreational
uses. Prince Edward Road East, Kwun Tong Bypass and other distributor
networks are dominant noise sources in the area.
7.4
Noise Sensitive Receivers
7.4.1
In order to evaluate
the construction and operational noise impacts from the Project, representative
Noise Sensitive Receivers (NSRs) within the Study Area are identified for
assessment. Only the first layer of NSRs has been identified for
assessment because it would provide acoustic shielding to those receivers at
further distance behind. As centrally air-conditioned buildings do not
rely on opened windows for ventilation, the noise standard as stipulated in Table
1 Annex 5 of EIAO-TM would not be applicable, and hence these buildings are not
selected for noise impact assessment. For example, Fire Station with
quarter at Site 2A8, the quarter will most likely be centrally air-conditioned
with window insulation. Therefore, Fire Station with quarter is not
classified as a NSR. For the NSRs at housing sites (Site 1A and 1B), the
latest site layout plan is obtained from the Hong Kong Housing Authority
(HKHA). The population of intake would be around later 2012 for these two
sites. Table 7.6 and Figure 3.2 shows the
representative NSRs selected for this noise impact assessment. The
photographs of the representative NSRs are shown in Appendix 3.19.
Table 7.6
Representative Noise Sensitive Receivers for Noise Impact Assessment
NSRs
|
District(1)
|
Location
|
Existing / Planned Land Use
|
Max.
Building Height, m
|
Construction
Phase
|
Operational
Phase
|
N1
|
KT
|
Cha Kwo Ling Tsuen
|
Residential
|
5
|
|
|
N2
|
KT
|
Cha Kwo Ling
|
Residential
|
15
|
|
|
N3
|
KT
|
Laguna City IV
|
Residential
|
81
|
|
|
N4
|
KB
|
Buddhist Chi King Primary School
|
Educational
|
24
|
|
|
N5
|
KB
|
S.K.H Kowloon Bay Kei Lok Primary School
|
Educational
|
27
|
|
|
N6
|
NCW
|
Richland Gardens
|
Residential
|
99
|
|
|
N7
|
NCW
|
Luk Ching House, Choi Hung Estate
|
Residential
|
60
|
|
|
N8
|
NCW
|
Kam Pik House, Choi Hung Estate
|
Residential
|
21
|
|
|
N9
|
NCW
|
Pik Hoi House, Choi Hung Estate
|
Residential
|
60
|
|
|
N10A
|
SPK
|
Rhythm Garden
(Block 7)
|
Residential
|
87
|
|
|
N10B
|
SPK
|
Rhythm Garden
(Block 9)
|
Residential
|
87
|
|
|
N11
|
SPK
|
Cognitio College
|
Educational
|
18
|
|
|
N12
|
SPK
|
Sir Robert Black Health Centre
|
Clinic
|
9
|
|
|
N13
|
SPK
|
Lee Kau Yan Memorial School
|
Educational
|
10
|
|
|
N14
|
SPK
|
South Mansion
|
Residential
|
15
|
|
|
N15
|
SPK
|
Jenford Building
|
Residential
|
12
|
|
|
N16
|
KC
|
Parc 22
|
Residential
|
33
|
|
|
N17
|
KC
|
Sky Tower
|
Residential
|
141
|
|
|
N18
|
KC
|
HK Society for Blind hostel
|
Residential
|
9
|
|
|
N19
|
TKW
|
Mok Cheong Street Residential District
|
Residential
|
18
|
|
|
N20A
|
TKW
|
Grand Waterfront
|
Residential
|
153
|
|
|
N20B
|
TKW
|
Grand Water Front
|
Residential
|
153
|
|
|
N21
|
TKW
|
Hang Chien Court
|
Residential
|
39
|
|
|
N22
|
TKW
|
Wei Chien Court
|
Residential
|
39
|
|
|
N23
|
TKW
|
Holly Carpenter Primary School
|
Educational
|
18
|
|
|
N24
|
TKW
|
Oblate Father’s Primary School
|
Educational
|
21
|
|
|
N25
|
TKW
|
Sunrise Villa
|
Residential
|
90
|
|
|
N26
|
TKW
|
Wing Kwong Street Residential District
|
Residential
|
21
|
|
|
N27
|
TKW
|
CCC Kei To Secondary School
|
Educational
|
24
|
|
|
N28
|
TKW
|
Po Leung Kuk Ngan Po Ling College
|
Educational
|
27
|
|
|
N29
|
TKW
|
Sunrise Plaza
|
Residential
|
39
|
|
|
N30A
|
TKW
|
No. 91 Ma Tau Kok
Road
|
Residential
|
7
|
|
|
N30B
|
TKW
|
No. 3 Hing Yan Street
|
Residential
|
8
|
|
|
N31
|
SPK
|
Canossa Primary School (San Po Kong)
|
Educational
|
3
|
|
|
N32
|
TKW
|
Holy Trinity Church
|
Place of Public
Worship
|
2
|
|
|
PN1
|
SPK
|
Rhine Harbour (Planned)
|
Residential
|
130
|
|
|
PN2
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN3
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN4
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN5
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN6A
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN6B
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN7A
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN7B
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN8
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN9
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN10
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN11
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN12
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN13
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN14
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN15
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN16
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN17
|
KTD
|
Site 1A1 (Planned)
|
Residential
|
115
|
|
|
PN18
|
KTD
|
Site 1A2 (Planned)
|
Educational
|
40
|
|
|
PN19
|
KTD
|
Site 1A3 (Planned)
|
Educational
|
40
|
|
|
PN20
|
KTD
|
Site 1A4 (Planned)
|
Educational
|
40
|
|
|
PN21
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN22
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN23A
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN23B
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN23C
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN24
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN25
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN26
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN27
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN28
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN29
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN30A
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN30B
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN31A
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN31B
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN32
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN33
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN34
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN35
|
KTD
|
Site 1B1 (Planned)
|
Residential
|
115
|
|
|
PN36
|
KTD
|
Site 1B2 (Planned)
|
Educational
|
40
|
|
|
PN37
|
KTD
|
Site 1B3 (Planned)
|
Educational
|
40
|
|
|
PN38
|
KTD
|
Site 1B4 (Planned)
|
Educational
|
40
|
|
|
PN39
|
KTD
|
Site 1I1 (Planned)
|
Residential
|
95
|
|
|
PN40
|
KTD
|
Site 1I1 (Planned)
|
Residential
|
95
|
|
|
PN41
|
KTD
|
Site 1I2 (Planned)
|
Residential
|
95
|
|
|
PN42
|
KTD
|
Site 1I2 (Planned)
|
Residential
|
95
|
|
|
PN43
|
KTD
|
Site 1I3 (Planned)
|
Residential
|
95
|
|
|
PN44
|
KTD
|
Site 1I3 (Planned)
|
Residential
|
95
|
|
|
PN45
|
KTD
|
Site 1K1 (Planned)
|
Residential
|
105
|
|
|
PN46
|
KTD
|
Site 1H2 (Planned)
|
Residential
|
105
|
|
|
PN47
|
KTD
|
Site 1L2 (Planned)
|
Residential
|
95
|
|
|
PN48
|
KTD
|
Site 1K3 (Planned)
|
Residential
|
95
|
|
|
PN49
|
KTD
|
Site 1K2 (Planned)
|
Residential
|
105
|
|
|
PN50
|
KTD
|
Site 1L2 (Planned)
|
Residential
|
95
|
|
|
PN51
|
KTD
|
Site 1L3 (Planned)
|
Residential
|
45
|
|
|
PN52
|
KTD
|
Site 1L3 (Planned)
|
Residential
|
45
|
|
|
PN53
|
KTD
|
Site 1L3 (Planned)
|
Residential
|
95
|
|
|
PN54
|
KTD
|
Site 1L1 (Planned)
|
Residential
|
95
|
|
|
PN55
|
KTD
|
Site 2B1 (Planned)
|
Residential
|
105
|
|
|
PN56
|
KTD
|
Site 2B1 (Planned)
|
Residential
|
105
|
|
|
PN57
|
KTD
|
Site 2B2 (Planned)
|
Residential
|
95
|
|
|
PN58
|
KTD
|
Site 2B3 (Planned)
|
Residential
|
80
|
|
|
PN59
|
KTD
|
Site 2B4 (Planned)
|
Residential
|
80
|
|
|
PN60
|
KTD
|
Site 2B5 (Planned)
|
Residential
|
80
|
|
|
PN61
|
KTD
|
Site 2B6 (Planned)
|
Residential
|
80
|
|
|
PN62
|
KTD
|
Site 2B6 (Planned)
|
Residential
|
80
|
|
|
PN63
|
KTD
|
Site 4A1 (Planned)
|
Residential
|
60
|
|
|
PN64
|
KTD
|
Site 4B5 (Planned)
|
Residential
|
40
|
|
|
PN65
|
KTD
|
Site 5A4 (Planned)
|
Residential
|
60
|
|
|
PN66
|
KTD
|
Site 5A4 (Planned)
|
Residential
|
105
|
|
|
PN67
|
KTD
|
Site 5C5 (Planned)
|
Educational
|
40
|
|
|
PN68
|
KTD
|
Site 5C6 (Planned)
|
Educational
|
40
|
|
|
PN69
|
KTD
|
Site 1D3 (Planned)
|
Community Use
with hostel
|
55
|
|
|
PN70
|
KTD
|
Site 1D3 (Planned)
|
Community Use
with hostel
|
55
|
|
|
PN71
|
KTD
|
Site 1E1 (Planned)
|
Mixed Use
|
95
|
|
|
PN72
|
KTD
|
Site 1E1 (Planned)
|
Mixed Use
|
95
|
|
|
PN73
|
KTD
|
Site 1F1 (Planned)
|
Mixed Use
|
95
|
|
|
PN74
|
KTD
|
Site 1M1
|
CDA
|
35
|
|
|
PN75
|
KTD
|
Site 1M2
|
CDA
|
170
|
|
|
PN76
|
KTD
|
Site 3B1 (Planned)
|
Undesignated
|
40
|
|
|
PN77
|
KTD
|
Site 3B2 (Planned)
|
Undesignated
|
40
|
|
|
PN78
|
KTD
|
Site 3B3 (Planned)
|
Undesignated
|
40
|
|
|
PN79
|
KTD
|
Site 3B4 (Planned)
|
Undesignated
|
40
|
|
|
PN80
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN80A
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN81
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN82
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN83
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN84
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN84A
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN85
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN86
|
KTD
|
Site 3C1 (Planned)
|
Hospital / Clinic
|
55
|
|
|
PN87A
|
KTD
|
Site 3E1 (Planned)
|
Commercial
|
95
|
|
|
PN87B
|
KTD
|
Site 3E1 (Planned)
|
Commercial
|
95
|
|
|
PN88
|
KTD
|
Site 3D2 (Planned)
|
Commercial
|
95
|
|
|
PN89
|
KTD
|
Site 3D2 (Planned)
|
Commercial
|
95
|
|
|
PN90
|
KTD
|
Site 3D3 (Planned)
|
Commercial
|
95
|
|
|
PN91A
|
KTD
|
Site 3D4 (Planned)
|
Commercial
|
95
|
|
|
PN91B
|
KTD
|
Site 3D4 (Planned)
|
Commercial
|
95
|
|
|
PN92
|
KTD
|
Site 3D4 (Planned)
|
Commercial
|
95
|
|
|
PN92A
|
KTD
|
Site 3D4 (Planned) facing the existing public cargo working area
|
Commercial
|
95
|
|
|
PN93
|
TKW
|
Sung Wong Toi Road CDA site
|
CDA
|
95
|
|
|
PN94
|
TKW
|
Sung Wong Toi Road CDA site
|
CDA
|
95
|
|
|
PN95
|
TKW
|
Sung Wong Toi Road CDA site
|
CDA
|
95
|
|
|
PN96
|
KTD
|
Site 2A1 (Planned)
|
Commercial
|
65
|
|
|
PN97
|
KTD
|
Site 2A2 (Planned)
|
Commercial
|
65
|
|
|
PN98
|
KTD
|
Site 2A3 (Planned)
|
Commercial
|
65
|
|
|
PN99
|
KTD
|
Site 2A4 (Planned)
|
Commercial
|
55
|
|
|
PN100
|
KTD
|
Site 2A5 (Planned)
|
Commercial
|
55
|
|
|
PN101
|
KTD
|
Site 2A6 (Planned)
|
Commercial
|
55
|
|
|
PN102
|
KTD
|
Site 4A2 (Planned)
|
Commercial
|
40
|
|
|
PN103
|
KTD
|
Site 4C1 (Planned)
|
Commercial
|
40
|
|
|
PN104
|
KTD
|
Site 4C2 (Planned)
|
Commercial
|
40
|
|
|
PN105
|
KTD
|
Site 4C3 (Planned)
|
Commercial
|
40
|
|
|
PN106
|
KTD
|
Site 4C4 (Planned)
|
Commercial
|
40
|
|
|
PN107
|
KTD
|
Site 4C5 (Planned)
|
Commercial
|
40
|
|
|
PN108
|
KTD
|
Site 4A3 (Planned)
|
Commercial
|
40
|
|
|
PN109
|
SPK
|
Choi Hung Road CDA Site (Planned)
|
CDA
|
Unknown
|
|
|
PN110
|
SPK
|
Ex-San Po Kong Flatted Factory
|
Residential
|
100
|
|
|
PN111
|
SPK
|
Ex-San Po Kong Flatted Factory
|
Residential
|
100
|
|
|
PN112
|
SPK
|
Ex-San Po Kong Flatted Factory
|
Residential
|
100
|
|
|
Note:
(1) KT – Kwun Tong; NTK – Ngau Tau Kok; KB – Kowloon
Bay; NCW – Ngau Chi Wah; SPK – San Po Kong; KC – Kowloon City, TKW – To Kwa
Wan; HH – Hung Hom; KTD – Kai Tak Development
7.5
Assessment Methodology
Construction Noise during
Unrestricted Hours
7.5.1
The construction
activities of the Project taking place concurrently within 300 m of a given NSR
are considered to contribute to the cumulative impact at that NSR. Noise
sources from the areas greater than this distance were excluded from the
assessment.
7.5.2
The methodology
outlined in the GW-TM was used for the assessment of construction noise
(excluding percussive piling). Sound Power Levels (SWLs) of the equipment
were taken from Table 3 of this TM. Where no SWL is provided in the
GW-TM, reference was made to BS 5228 or other previous similar studies or from
measurements taken at other sites in Hong Kong.
7.5.3
Referring to the
construction programme of the KTD Project and other projects within the study
area, it is noted that construction period of following projects in the
vicinity of KTD might overlap:
·
Construction of and
Distributor Road;
·
Sewage pumping stations;
·
Decommissioning of
Remaining Parts of the Former Kai Tak Airport;
·
Decommissioning of the
Former Kai Tak Airport Other than the North Apron;
·
Construction of Local
Roads;
·
600m Runway Opening;
·
Public landing steps
cum fireboat berth;
·
Dredging work for
proposed cruise terminal at Kai Tak;
·
Kwun Tong
Transportation Link;
·
Trunk Road T2;
·
Central Kowloon Route;
·
Shatin Centre Link;
·
Barging point for the development
project at Anderson Road and etc.
7.5.4
The above concurrent
construction activities are considered to contribute to the cumulative impact
at the noise assessment points and were included in the cumulative assessment
if any of these construction activities are undertaken within 300m of a given
noise assessment point. Locations of notional sources and distance for
NSRs are given in Appendix
3.20.
7.5.5
A positive 3 dB(A)
façade correction was added to the predicted noise levels in order to account
for the facade effect at each noise assessment point.
Ground-borne
Noise
7.5.6
A part of the proposed
Shatin to Central Link (SCL) within KTD site boundary would be constructed by
Tunnel Boring Machine (TBM). A qualitative
assessment was conducted with reference to the approved EIA reports in the EIAO Register regarding
potential ground-borne noise impacts from TBM, including the Kowloon Southern
Link (KSL) EIA (Register No.: AEIAR-083/2005) & Sheung Shui to Lok Ma Chau
Spur Line (Register No.: AEIAR-052/2002).
Operational Road Traffic Noise
7.5.7
Traffic noise was
predicted using the methodology provided in the UK Department of Transport
Calculation of Road Traffic Noise (CRTN) 1988. The assessment was based
on the projected peak hour flows for the worst year within 15 years after
opening of the roads. Road traffic noise levels is presented in terms of
noise levels exceeded for 10% of the one-hour period during the peak traffic
flow, i.e. L10,1hr dB(A). The projected 2031 morning peak hour
traffic flows and vehicle compositions are attached in Appendix 3.21.
Those roads with traffic flow below 50 veh/hr were not
considered in this assessment. For the Kwun Tong Transportation Link
(KTTL), the capacity traffic flow was assumed for conservative assessment.
7.5.8
Only roads within 300m (perpendicular
distance) from each NSR were considered in the assessment for that NSR.
7.5.9
The existing noise
screening structures and mitigation measures listed below for Prince Edward
Road East and Kwun Tong Bypass were taken into account in the assessment:
·
Low noise surfacing on
the existing Prince Edward Road East and Kwun Tong Bypass;
·
4m high barrier along
N/B of Kwun Tong Bypass and its slip road; and
·
Semi-enclosures along
Kwun Tong Bypass near Richland Garden and Choi Hung Estate.
7.5.10 The building layout plan with
mitigation measures (1.5m vertical fins) for Site 1A1 and 1B1 are provided by
the Housing Department and was adopted in this assessment under the unmitigated
scenario.
Operational Phase Fixed Plant Noise
7.5.11 Fixed plant noise source is
controlled by the NCO and IND-TM with a criteria of 5dB(A) below the
appropriate Acceptable Noise Levels (ANL) shown in Table 3 of the TM on Noise
from Place other than Domestic Premises, Public Places or Construction Sites or
the prevailing background noise levels. The following procedures were
applied to the operational phase fixed plant noise assessment.
l
Identify fixed plant
noise;
l
Calculate the correction
factors based on the distance between the NSRs and the noise source positions;
l
Apply acoustics
correction factors for façade, distance, barrier attenuation, acoustic
reflection where applicable;
l
Calculate the maximum
allowable Sound Power Level (SWL) as the compliance criteria for each fixed
noise sources; and
l
Quantify the level of
impact at the NSRs in accordance with IND-TM.
Noise from Open Air Entertainment
Activities
7.5.12 Open air entertainment noise
assessment was conducted in accordance with the following procedures:
l
Establish the open air
entertainment noise level from previous relevant noise measurement data;
l
Determine in accordance
with standard acoustic principle and practices the representative sound power
level;
l
Determine the
separation distance at the NSRs from the noise source;
l
Apply corrections for
façade, distance, barrier attenuation and acoustic reflection where applicable;
and
l
Quantify the level of
impact at the NSRs in accordance with guidelines.
Heliport Noise
7.5.13 Potential noise impact would be arisen
from the operation of the heliport proposed at the tip of the former runway.
According to Table 1A of Annex 5 “A Summary of Noise Criteria” in the
EIAO-TM, the criteria for helicopter noise is Lmax 90dB(A) for offices and Lmax
85dB(A) for domestic premises, hotels, hostels, education institutes, places of
worship, hospital and clinics during 0700-1900 hours. The standards apply
to uses that rely on openable windows for ventilation and the standards should
be viewed as the maximum permissible noise levels assessed at 1m from the
external façade.
7.5.14 Reference was made to other relevant
approved EIA Report in the EIAO Register regarding potential noise impacts from
heliport operation in urban area, including the Comprehensive Feasibility Study
for The Revised Scheme of South East Kowloon Development (SEKDCFS) EIA and
the EIA on Expansion of Heliport Facilities at Macau Ferry Terminal.
Assessment was based on basic acoustic principle with reference to the
EIAO-TM.
Rail Noise
7.5.15 Rail noise assessment was conducted
in accordance with the following procedures:
l
Identify noise source;
l
Assess its noise impact
to sensitive receiver
Marine Traffic Noise (include noise from
typhoon shelters)
7.5.16 Marine traffic noise assessment was
conducted in accordance with the following procedures:
l
Identify noise source;
l
Assess its noise impact
to sensitive receiver
7.6
Identification of Environmental Impacts
Construction Phase
7.6.1
The potential
construction impact arising from this Project includes construction of road
network, land formation and other related works. These construction
activities will involve the use of Powered Mechanical Equipment (PME) including
breakers, excavators, lorries, mobile cranes, concrete truck mixers, pokers,
rollers, etc. The construction noise impact assessment was carried out
based on the best available construction plant inventory. The preliminary
plant inventory for SCL was obtained from SCL engineer for this assessment.
Mitigation measures, where required, would be formulated and the residual
construction noise impact assessed. The use of PMEs adopted for the
assessment is detailed in Appendix
3.22.
7.6.2
The construction
activities of the Project will coincide with the barging point facilities for
the Anderson Road Project. The barging point project is to be implemented
by CEDD/Special Duties (Works) from Jan 2008 through Dec 2014. The
barging point facilities are located at middle Runway for transporting the
surplus C&D materials from the development area to receptor sites.
Given the shortest notional source distance to NSR is more than 1 km, the
related cumulative construction noise impact arising from these barging
facilities was not assessed.
Ground-borne Noise
7.6.3
A part of the proposed
Shatin to Central Link (SCL) within KTD site boundary would be constructed by
TBM. The construction method of SCL is illustrated in Figure 7.1.
Reference was made to the approved EIA reports in the EIAO Register regarding
potential ground-borne noise impacts from TBM, including the Kowloon Southern
Link (KSL) EIA (Register No.: AEIAR-083/2005), Sheung Shui to Lok Ma Chau Spur
Line (Register No.: AEIAR-052/2002).
7.6.4
Figure 7.1 is illustrated that two sections of
SCL alignment within KTD will be constructed by TBM. The TBM will be at
least 25m and 60m away from the nearest sensitive receiver at Site 1A (PN6A)
and Site 2B1 (PN56). The geology at the concerned area comprises mainly
alluvial material and granite which is considered similar to the geology for
throughout the KSL alignment. With reference to the KSL EIA report, the
ground borne noise level for the sensitive receiver is 43dB(A) at 5m away from
the TBM. In addition, with reference to the Spur Line EIA, there was no
noticeable effect from the Kwai Tsing tunnel which was constructed by TBM and
it passed within 20m of Kwai Tsing Theatre. Given the larger separation
distance in this case between the SCL TBM sections of the nearby NSRs in KTD,
adverse ground borne noise impact arising from the SCL TBM is not
anticipated.
7.6.5
As discussed in Section
1.5 of this report, the proposed SCL is a Schedule 2 designated project
under the EIAO. The proposed SCL will be designed, constructed and
operated by the others. The associated environmental impacts will be
adequately addressed in a further detailed EIA study to be prepared and
submitted under the EIAO by the respective project proponent.
Operational Phase
7.6.6
Operational phase
impacts will arise from the following operations:
l
Road traffic noise
l
Operational phase fixed
plant noise (including marine traffic noise)
l
Noise from open air
entertainment activities
l
Helicopter noise
l
Rail noise
l
Marine traffic noise
(include noise from typhoon shelters)
Road Traffic Noise
7.6.7
The proposed road
network in Kai Tak Development comprises of district distributors and local
distributors. Together with the existing heavily trafficked roads
surrounding the development site such as Prince Edward Road East and Kwun Tong
Bypass, potential impact by road traffic noise would affect the planned NSRs
within the development site.
Operational Phase Fixed Plant Noise
7.6.8
Sewage Pumping
Stations (SPS):
Seven sites are planned for the construction of sewage pumping stations to
serve the KTD and the hinterland. The major noise sources come from the
pumps and ventilation system. Some of these sites are located close to
nearby NSRs. However, all pumps will be installed underground and
enclosed with a building structure according to typical design adopted by the
Drainage Services Department. The design of the SPS should also avoid
creating noise nuisance to the surrounding NSRs. By locating the opening
of the exhaust of the ventilation system away from any NSRs and installing
acoustic louvers at the exhaust could effectively attenuate the noise generated
during operation of the SPS. Insurmountable noise impact to the NSRs from
the operation of the SPS is therefore not expected.
7.6.9
Electrical Substations (ESS): Total six sites are reserved for electric substations to support the
KTD. The capacities of each ESS are stated below. The major noise
sources come from the transformer and ventilation system. Some of them
are located close to nearby NSRs. For these ESS, the equipment which
would generate noise should be enclosed in a building structure. By
locating the opening of the exhaust of the ventilation system away from any
NSRs and installing acoustic louvers at the exhaust could effectively attenuate
the noise generated during operation of the ESS. The location of the
ventilation system’s opening or chillers should be located away from the NSRs
as far as possible. Insurmountable noise impact to the NSRs from the
operation of the ESS is therefore not expected.
ESS
|
Capacities
|
Site 1A5
|
132kV
|
Site 1D1
|
132kV
|
Site 1P4
|
132kV
|
Site 2A7
|
400kV
|
Site 5A2
|
132kV
|
Site 4D5
|
132kV
|
7.6.10 Tunnel Ventilation Shafts: There are five proposed tunnel ventilation
shafts and one existing ventilation shaft in the vicinity of KTD. The
major noise source comes from the ventilation fan inside the shaft. The
locations of the ventilation shafts and the maximum sound power levels (SWLs)
of the ventilation fan that are required to meet the relevant noise criteria
were determined. For the ventilation shaft of Kai Tak Tunnel, a survey
has been conducted to collect the SWL. The measured results are shown in
Table 7.7 below. In order to present the worst case scenario, SWL
93dB(A) was used for the calculation.
Table
7.7
Measured SWLs for Kai Tak Tunnel Ventilation Shaft
Kai Tak Airport Ventilation Shaft
|
Measured SWL, dB(A)
|
South
façade
|
93
|
West
façade
|
87
|
North
façade
|
88
|
7.6.11 Apart from the restriction on the
SWLs, the openings of the proposed ventilation shafts should be oriented such
that they would be faced away from any nearby NSRs and adopt any necessary
further mitigation measures like acoustic louvers and silencers. The
potential noise impact at the NSRs due to the operation of the ventilation
shafts is expected to be minimal with proper mitigation measures adopted.
7.6.12 Cruise Terminal Operation: A two-berth cruise terminal
is proposed at the southern tip of the former Kai Tak Airport runway. The
major noise sources from the ventilation system of cruise terminal and noise
emissions from cruise would be expected during cruise mooring. Other
noise sources emitted from machinery intake/uptake or ventilation inlet/outlet
would also be expected during cruise hotelling.
7.6.13 Public Transport Interchange (PTI): There are total of four PTIs
located within the Kai Tak Development site. They are located in Site 1F2,
4D2, 6A4 and 5B2. Sites 6A4 and 5B2 are existing PTIs located next to the
Kwun Tong Ferry Pier and Kowloon City Ferry Pier.
7.6.14 The PTI at Site 5B2 may be upgraded
and modified after construction of CKR. In case of upgrade and modify, some
general considerations should be taken during the planning stages including (i)
avoid locating open-form PTI in proximity to noise sensitive uses; (ii)
consider adopting a complete podium decking over the PTI; (iii) take into
account the potential locations of ingress/egress and consequent noise
disturbances due to traffic routings, particularly during sensitive hours; and
(iv) give consideration to adopting administrative controls to avoid the noise
impact from PTI.
7.6.15
The nearest NSR to the
PTI at Site 1F2 and Site 4D2 are located with a distance of about 47 m at Site
1F1 and 130 m at Site 4B5. For Site 1F1, as stated in OZP No. S/K22/2, a
special design requirement is incorporated for this site facing the Station
Square such that the residential element should commensurate with the
commercial element in form. The layout of the affected NSRs at Site 1F1
could be designed to avoid the noise sensitive uses facing the PTI or providing
the noise sensitive uses with window insulation and air conditioning. The
top of the PTI is proposed to develop with a commercial building which could
provide noise screening to the nearby NSRs. Furthermore, general
considerations during the planning stages including (i) avoid locating
open-form PTI in proximity to noise sensitive uses; (ii) consider adopting a
complete podium decking over the PTI; (iii) take into account the potential
locations of ingress/egress and consequent noise disturbances due to traffic
routings, particularly during sensitive hours; and (iv) give consideration to
adopting administrative controls to avoid the noise impact from PTI should be
considered. Therefore, adverse noise impact due to PTI at the NSRs is not
expected.
7.6.16
The other noise source
comes from the ventilation system of the PTI. The locations of the
ventilation system and the maximum sound power levels (SWLs) of the ventilation
fan that are required to meet the relevant noise criteria were
determined. Apart from the restriction on the SWLs, the openings of the
proposed ventilation shafts should be oriented such that they would be faced
away from any nearby NSRs and adopt any necessary further mitigation measures
like acoustic louvers and silencers. The potential noise impact at the
NSRs due to the operation of the ventilation shafts is expected to be minimal
with proper mitigation measures adopted.
7.6.17
Fixed Plant Noise
from Railway and Railway Station: The proposed Shatin to Central Link (SCL) and its stations would be at
Site 1F (Kai Tak Station) and Site 2D (To Kwan Wan Station). Two
ventilation buildings are proposed at the both To Kwan Wan Station and Kai Tak
Station and identified as fixed plant noise sources. The locations of the
ventilation shafts and the maximum sound power levels (SWLs) of the ventilation
fan that are required to meet the relevant noise criteria were
determined. Apart from the restriction on the SWLs, the openings of the
proposed ventilation shafts should be oriented such that they would be faced
away from any nearby NSRs and adopt any necessary further mitigation measures
like acoustic louvers and silencers. The potential noise impact at the
NSRs due to the operation of the ventilation shafts is expected to be minimal
with proper mitigation measures adopted.
7.6.18
Fixed Plant Noise
from Environmental Friendly Transportation System (EFTS) Depot: The proposed EFTS is located at
the Metro Park. The depot of EFTS would be in the form of an enclosed
building structure. The potential noise impact at the NSRs due to the
operation of the EFTS depot is expected to be minimal with proper mitigation
measures adopted.
7.6.19
As discussed in Section
1.5 of this report, the proposed EFTS Depot is a Schedule 2 designated
project under the EIAO. The proposed EFTS will be designed, constructed
and operated by the others. The associated environmental impacts will be
adequately addressed in a further detailed EIA study to be prepared and
submitted under the EIAO by the respective project proponent.
7.6.20
Fire Station and
Ambulance Depot (FSAD): The proposed locations of the fire station and ambulance deport are
located at Site 2A8 and Site 3C2. The distance to the nearest NSRs to
FSAD at Site 2A8 namely N15 and PN60 are 103m and 107m, respectively. For
the FSAD located at Site 3C2, the distance to the nearest NSRs (PN86) is about
30m.
7.6.21
Noise sources
associated with these stations would be related to the emergency response of
the stations and would include the station loudspeakers, siren and the vehicle
sirens. Noise from fire stations may sometimes be disturbing particularly
during emergency duties. Yet such occurrences are of short duration and
infrequent, and could not be avoided when emergencies occur. The sirens
are intended to warn surrounding emergency, so that priority may be given to
them. Emergency vehicles could also be assisted in their response by
installation of “hurry call” or other signalisations at intersection along the
route.
7.6.22 The noise impact at NSR PN60 can be
screened by the building structure at Site 2A6. Adverse noise impact is
therefore not anticipated.
7.6.23 For NSR PN86, it is confirmed with
Food and Health Bureau that the proposed hospital site will provide with window
insulation and air conditioning, adverse noise impacts due to FSAD at this NSR
is not expected. The documentation of confirmation from the Food and
Health Bureau is included in Appendix 18.1.
7.6.24 The “C” area sensitivity rating was
identified for N15 and considering that it is already affected by the existing
high traffic noise level along Prince Edward Road East. In addition, the
noise event from FSAD would be short term. The time-averaged noise level
for Leq, 30 min would be low. Administrative measures would be adopted by
the Director of Fire Services to minimize the noise impact to nearby NSRs.
Adverse noise impact due to FSAD is not expected.
7.6.25 Noise from Sports Activity at
Stadium: Site 2D is
reserved for the development of a Stadium Complex. The location of the
Stadium Complex has been planned with considerations of protection of view
corridor, accessibility by public transport and provision of sufficient buffer
distance to the nearby NSRs. Noise from stadiums for sporting activities
may include both the crowd noise and public address broadcast (PA).
7.6.26 District Cooling System Plant
(DCSP): Total
two sites (Site 1N2 and Site 4C1) are reserved for DCSP. The major noise
sources come from the pump system. The DCSP at Site 4C1 would be
installed below ground. Adverse noise impact at the nearby NSRs is not
expected. For the DCSP at Site 1N2, the nearest NSRs are PN34 & PN38.
For this DCSP, the equipment which would generate noise should be enclosed in a
building structure. By locating the opening of the exhaust of the
ventilation system away from any NSRs and installing acoustic louvers at the
exhaust could effectively attenuate the noise generated during operation of the
DCSP. The location of the ventilation system’s opening should be located
away from the NSRs as far as possible. Insurmountable noise impact to the
NSRs from the operation of the DCSP is therefore not expected.
7.6.27 Public Cargo Working Area (PCWA): Existing Kwun Tong Cargo Working
Area is located at Hoi Bun Road, Kwun Tong. The major noise sources would
be loading and unloading of containers and goods handling. For
those nearest planned NSRs at Site 3D4, the commercial development will most
likely be centrally air-conditioned, and it could also be designed to avoid
sensitive façade facing to the noise sources or incorporate hotel-like service
apartment with the provision of central air conditioning. Adverse noise
impacts at this site due to the operation of PCWA are not expected.
7.6.28 Other Fixed Noise Sources: With reference to the RODP dated
May 2008, no Concrete Batching Plants, Construction Material Handling
Facilities, Open Car/Lorry Park and Refuse Transfer Station are located within
the Kai Tak Development.
Noise from Open Air Entertainment Activities
7.6.29 Site 2D is reserved for the
development of a Stadium Complex. The location of the Stadium Complex has
been planned with considerations of protection of view corridor, accessibility
by public transport and provision of sufficient buffer distance to the nearby
NSRs.
7.6.30 The major noise sources associated
with the Stadium Complex include the use of loudspeakers and the crowd.
With reference to the findings of SEKDCFS EIA report, there will be no
significant noise impact on NSRs if the main stadium incorporated the
retractable roof design. The retractable roof of the main stadium could
provide screening effect on noise impact, nearby NSRs without direct
line-of-sight of the spectator area of the main stadium could be benefited from
this.
7.6.31
As discussed in Section
1.5 of this report, the outdoor sporting facility of the proposed Stadium
Complex is a Schedule 2 designated project under the EIAO. The proposed
Stadium Complex will be designed, constructed and operated by the others.
The associated environmental impacts will be adequately addressed in a further
detailed EIA study to be prepared and submitted under the EIAO by the
respective project proponent.
Heliport Noise
7.6.32
A heliport is proposed
at the tip of the former Kai Tak Airport runway. The closest NSR to the
heliport is located at a distance of more than 700 m in Site 4B5. With
reference to the CFS for the Revised Scheme of SEKD (2001), a 300 m
setback of the heliport from the NSR is required. Hence the current
buffer distance of 700 m allowed in the RODP should be sufficient to attenuate
the noise impact generated by the operation of the heliport to meet the HKPSG
noise criteria of Lmax 85 dB(A). The flight path should be so designated
to reduce noise impacts. However, as the proposed heliport is located
adjacent to the proposed Runway Park, some forms of barrier could be considered
to minimise the potential noise impacts of heliport operation on the
pedestrians / visitors at the Runway Park despite the Runway Park is not
considered as a NSR.
7.6.33
For the helicopter
landing/take-off at Hong Kong Aviation Club (HKAC), according to the latest
development schedule of KTD, the helipad should cease operation prior to
occupation of the residential site (i.e. on or before 2012). Therefore,
no helicopter noise impact arising from HKAC during operational phase of the
Project.
Rail Noise
7.6.34
The proposed Shatin to
Central Link (SCL) and its stations would be at Site 1F (Kai Tak Station) and
Site 2D (To Kwan Wan Station). The SCL line would be underground and
hence operational railway noise impact is not expected.
7.6.35
EFTS is proposed to be
introduced to operate as a major internal mode of transport within Kai Tak
Development. It is proposed to provide feeder services between SCL Kai
Tak Station, SCL To Kwa Wan Station and the Tourism Node. As discussed in
Section 2, two options of alignment of EFTS were studied. The alignment of EFTS for both options are shown in Figure 7.2.
7.6.36
Several modes of EFTS,
including light rail transit (LRT), trolley bus, automatic people mover (APM),
monorails, and electric / LPG bus, were investigated during feasibility
study. For conservative noise assessment, the rail based EFTS was assumed
for rail noise assessment. The tentative train operation mode is listed
below.
·
Operation Hour: 6am to 12mid-night
·
Train frequency: 14 train/hr for peak hour and 4
train/hr for non-peak hour for each direction
7.6.37
As discussed in Section
1.5 of this report, the proposed ETFS is a Schedule 2 designated project
under the EIAO if the selected system is rail type. The proposed ETFS
will be designed, constructed and operated by the others. The associated
environmental impacts will be adequately addressed in a further detailed EIA
study to be prepared and submitted under the EIAO by the respective project
proponent.
Marine Traffic Noise (include noise
from typhoon shelters)
7.6.38
Noise impacts arising
from operation activities on the moored vessels in typhoon shelters and
manoeuvring of vessels at the proposed cruise terminal from the typhoon
shelters may vary with the composition and type of the vessels. The
potential noise impact is likely come from the engine noise and operation activities
of individual vessel in operation. It is similar
to noise from public place which vessels are free to move around and
implementation control measures are not possible.
7.6.39 Noise from Marine Traffic: With reference to approved
SEKDCFS EIA Report, the measured daytime noise level of marine traffic at Hung
Hom waterfront was about 59.9 dB(A) in Leq (30min). The measured noise
level was associated with several kinds of vessel manoeuvring, such as speed
boats, cargo ships, ferries, tug boats, etc. Given measured noise level
was low and the marine traffic during night-time would likely be much
lower. Therefore, adverse noise impact from marine traffic is not
anticipated.
7.6.40 Noise from Typhoon Shelters: A comparison of typhoon
shelters of different typhoon shelters is presented in below Table 7.8.
The locations of the typhoon shelters are shown in Figure 7.3.
Table 7.8
A Comparison of Typhoon Shelters in Relation to NSRs in Hong Kong
Typhoon
Shelters (TS)
|
Distance to the nearest NSRs, m
|
Boundary of TS
|
Centre of TS
|
Yau Ma Tei TS
|
140
|
860
|
Sam Ka Tsuen TS
|
200
|
320
|
Shek Tong Mei TS
|
100
|
170
|
Causeway Bay TS
|
140
|
500
|
Aberdeen TS
|
150
|
250
|
Kwun Tong TS
|
110 (Site 3D4 – PN92 Commercial)
250 (Site 4B5 – PN64 Residential)
|
280 (Site 3D4 – PN92 Commercial)
450(Site 4B5 – PN64 Residential)
|
To Kwa Wan TS
|
280 (N23 - Education)
380 (N22 – Residential)
|
540 (N23 Education)
700 (N22 – Residential)
|
Note: PN92 is for commercial use with no domestic plot ratio.
Kwun Tong Typhoon Shelter
7.6.41 The existing Kwun Tong Typhoon
Shelter is located to the southeast of Site 3D4 with about 110m separation
distance between the nearest NSR and the boundary of the typhoon shelter.
With reference to the SEKDCFS EIA Report, the measured noise level of existing
typhoon shelter at Kwun Tong is about 68.8 dB(A) in Leq (30min). Taking
into account the distance attenuation effect associated with a buffer distance
of about 110m between the Kwun Tong Typhoon Shelter and the nearest NSR, the
noise level at the nearest NSR would be minimal. Given no domestic plot
ratio on Site 3D4, the land use of NSR would be commercial with sensitive uses
and all affected NSRs are commercial NSRs which will most likely be centrally
air-conditioned. Other measures such as the layout of the affected NSRs
could be designed to avoid the noise sensitive uses facing the major noise
sources or providing the noise sensitive uses, like hotel, with window
insulation and air conditioning. Adverse noise impact at the site is not
expected.
To Kwa Wan Typhoon Shelter
7.6.42 The existing To Kwa Wan Typhoon
Shelter is located to the southeast of Site 5C with about 280m separation
distance between the nearest NSR (Holy Carpenter Primary School) and the
boundary of the typhoon shelter. As the nature of this typhoon shelter is
similar to the Kwun Tong Typhoon Shelter, the same noise level of 68.8 dB(A) in
Leq (30min) was adopted for the assessment. Taking into account the
distance attenuation effect associated with a buffer distance of about 280m between
the To Kwa Wan Typhoon Shelter and the nearest NSR, the noise level at the
nearest NSR would be minimal.
7.7
Prediction and
Evaluation of Environmental Impacts
Construction Phase
7.7.1
For normal daytime
working hours, exceedances of the construction noise criteria (Leq (30-min) 75 dB(A) for
residential uses and 70 dB(A) for educational institutions (65 dB(A) during
examinations)) are predicted at representative NSRs in the absence of
mitigation measures. Details of construction noise calculations and
results are presented in Appendix
3.23. The assessment results show that the predicted cumulative
noise levels related to the concurrent construction works of the Project are in
the range of 45 to 92 dB(A) Leq (30-min). A
summary of the unmitigated construction noise levels of the representative NSRs
during normal daytime working hours within the construction period of the
Project is listed in Table 7.9. Noise mitigation measures would
therefore be required to reduce noise levels at the NSRs for compliance with
the noise standard.
Table
7.9
Summary of Cumulative Unmitigated Construction Noise Levels at
Representative NSRs During Normal Daytime
Working Hours
NSR
|
Noise Criteria, dB(A)
|
Predicted Unmitigated Construction Noise Levels during Normal Daytime
Working Hour (Leq (30-min), dB(A))
|
Exceedance, dB(A)
|
N1
|
75
|
54 - 81
|
6
|
N2
|
75
|
54 - 77
|
2
|
N3
|
75
|
56 - 73
|
0
|
N4
|
65/70*
|
64 - 76
|
11/6
|
N5
|
65/70*
|
63 - 78
|
13/8
|
N6
|
75
|
61 - 81
|
6
|
N7
|
75
|
59 - 87
|
12
|
N8
|
75
|
58 - 81
|
6
|
N9
|
75
|
58 - 79
|
4
|
N10
|
75
|
58 - 84
|
9
|
N11
|
65/70*
|
59 - 84
|
19/14
|
N12
|
75
|
60 - 84
|
9
|
N13
|
65/70*
|
60 - 82
|
17/12
|
N14
|
75
|
60 - 89
|
14
|
N15
|
75
|
60 - 86
|
11
|
N16
|
75
|
59 - 78
|
3
|
N17
|
75
|
60 - 82
|
7
|
N18
|
75
|
63 - 83
|
8
|
N19
|
75
|
62 - 82
|
7
|
N20A
|
75
|
61 - 76
|
1
|
N20B
|
75
|
61 - 82
|
7
|
N21
|
75
|
61 - 82
|
7
|
N22
|
75
|
60 - 80
|
5
|
N23
|
65/70*
|
60 - 91
|
26/21
|
N24
|
65/70*
|
59 - 70
|
5/0
|
N25
|
75
|
58 - 78
|
3
|
N26
|
75
|
57 - 74
|
0
|
N27
|
65/70*
|
57 - 74
|
9/4
|
N28
|
65/70*
|
57 - 76
|
11/6
|
N29
|
75
|
57 - 72
|
0
|
N30
|
75
|
62 - 80
|
5
|
N31
|
65/70*
|
45 - 58
|
0
|
N32
|
75
|
59 - 79
|
4
|
PN1
|
75
|
60 - 84
|
9
|
PN2
|
75
|
66 - 92
|
17
|
PN35
|
75
|
69 - 81
|
10
|
Note:
*For normal daytime working hours, the noise criteria are 70 dB(A) and 65 dB(A)
for normal teaching periods and examination periods, respectively.
Operational Phase
7.7.2
Operational phase
impacts will arise from the following operations:
l
Road traffic noise
l
Operational phase fixed
plant noise
l
Noise from open air
entertainment activities
l
Helicopter noise
l
Rail noise
l
Marine traffic noise
(include noise from typhoon shelters)
Road Traffic Noise
7.7.3
The proposed road
network in Kai Tak Development comprises of district distributors and local
distributors. Together with the existing heavily trafficked roads
surrounding the development site such as Prince Edward Road East and Kwun Tong
Bypass, potential impact by road traffic noise would affect the planned NSRs
within the development site.
7.7.4
Traffic noise levels
have been predicted at representative noise assessment points including
existing residential, institutional uses, and future uses on planned
receivers. Appendix
3.24 gives the breakdown of the noise contributions from the new roads
and existing roads at all representative existing and planned NSRs for the RODP
as well as for the Through Road L3 alternative option. Sample output
files for 10 representative assessment points are included in Appendix 3.25.
Road-plots of the traffic noise model, the existing low noise surfacing and
noise barrier are shown in Appendix 3.25.
7.7.5
Without the noise
mitigation measures in place, the predicted noise levels at the identified NSRs
would range from 42 to 87 dB(A) L10 (1-hour). The following
paragraphs discuss the potential noise impacts at difference area of NSRs under
this study.
7.7.6
Existing NSRs (N1
to N32) and Planned (NSR PN1, PN93 – PN95 & PN109): The predicted noise levels at all
existing NSRs (except N21 to N23) and planned NSR PN1, PN93 to PN95 &
PN109 exceeded the noise criterion of 70 dB(A) or 65 dB(A) for schools or
55dB(A) for clinics. However, the noise exceedances are caused by the
existing roads. The ‘New’ road noise contribution to the overall noise
level would be less than 1.0 dB(A) and the ‘New’ road noise levels at these
NSRs would all be below 70 dB(A).
7.7.7
For the existing school
and clinic, the on-site survey has revealed that all of these NSRs have already
been noise insulated with air-conditioners. With the provision of
air-conditioners, it is considered that the traffic noise impact would be minimised by keeping the
windows closed. Therefore, traffic noise impact at these NSRs would be
insignificant. Hence, direct mitigation measures on ‘New’ roads are not
required as they would not be effective in improving the noise environment at
the sensitive receivers.
7.7.8
Site 1A: The predicted noise levels at
PN6A, PN6B, PN7A, PN18, PN19, PN20 & PN20A exceeded the noise criterion of
70 dB(A) or 65 dB(A) for schools. However, the noise exceedances are
caused by the existing roads. The ‘New’ road noise contribution to the
overall noise level would be less than 1.0 dB(A) and the ‘New’ road noise
levels at these NSRs would all be below 70 dB(A). In addition, the piling
work has already been completed at Site 1A1, alternative land use arrangement
for this site is considered not feasible. The low-rise nature of schools
will make any noise mitigation measures such as cantilever barriers more
effective than for the case of high-rise domestic development. There is
not enough non-sensitive uses e.g. carpark, commercial uses as noise
screen. Hence, direct mitigation measures on ‘New’ roads are not required
as they would not be effective in improving the noise environment at the
sensitive receivers.
7.7.9
Under the Through Road
L3 alternative option, the predicted noise levels at Site 1A are similar to the
basic option without through road except PN19A & PN20A. The predicted
noise level at PN19A & PN 20A exceeded the noise criterion of 65dB(A) and
increased by up to 8 dB(A) when compared with the basic option.
Mitigation measures should be considered for Through Road L3 to minimise the
associated noise impact, alternatively, the layout of the affected schools
could be designed to avoid sensitive façade facing the major traffic noise
sources or provided with window insulation and air conditioning.
7.7.10
Site 1B1: The predicted noise levels at PN23A
to PN23C, PN26, PN29, PN30A to PN31B & PN33 exceeded noise criterion of 70
dB(A). It is identified that the ‘New’ road noise contribution to the
overall noise level would be more than 1.0 dB(A). The major noise source
is Road L2 and Kwun Tong Bypass that contributed significant traffic noise
impact to these NSRs. Hence, direct mitigation measures on ‘New’ road
(Road L2) are required to reduce the traffic noise impact.
7.7.11
Site 1B2 to 1B4: The predicted overall noise levels
at PN36, PN37 & PN38 exceeded the noise criterion of 65 dB(A). The
‘New’ roads noise contribution to the overall noise levels would be more than
1.0 dB(A). The major noise sources are Road L2 and Road L4. Hence,
direct mitigation measures at Road L2 and Road L4 are required for the affected
NSRs.
7.7.12
Site 1I1: The predicted overall noise levels
at PN39 & PN40 exceeded the noise criterion of 70 dB(A). The ‘New’
road noise contributions to the overall noise levels would be more than 1.0
dB(A) and the ‘New’ road noise levels at these NSRs would be above 70 dB(A) for
residential dwellings. Hence, direct mitigation measures at Road L4 would
be required to reduce the noise impact from ‘New’ roads for PN39 & PN40.
7.7.13
Site 1L2 and 1L3: The predicted overall noise levels
at PN50, PN51 & PN52 exceeded the noise criterion of 70 dB(A). The
‘New’ road (Road D2) noise contributions to the overall noise levels would be
more than 1.0 dB(A) and the ‘New’ road noise levels at these NSRs would be
above 70 dB(A) for residential dwellings. Hence, direct mitigation
measures at Road D2 would be required to reduce the noise impact from ‘New’
roads for PN50, PN51 & PN52.
7.7.14
Site 2B6: The predicted noise levels at
planned NSRs for PN61 & PN62 exceeded the noise criterion of 70
dB(A). However, the noise exceedances are caused by the existing
roads. The ‘New’ road noise contribution to the overall noise level would
be less than 1.0 dB(A) and the ‘New’ road noise levels at these NSRs would all
be below 70 dB(A). Hence, direct mitigation measures on ‘New’ roads are
not required as they would not be effective in improving the noise environment
at the sensitive receivers.
7.7.15
Site 5A4: The predicted noise levels at
planned NSRs for PN65 and PN66 exceeded the noise criterion of 70 dB(A).
However, the noise exceedances are caused by the existing roads. The
‘New’ road noise contribution to the overall noise level would be less than 1.0
dB(A) and the ‘New’ road noise levels at these NSRs would all be below 70
dB(A). Hence, direct mitigation measures on ‘New’ roads are not required
as they would not be effective in improving the noise environment at the
sensitive receivers.
7.7.16
Site 3C (Hospital
/ Clinic): The
predicted noise levels at planned NSRs for PN80 to PN86 exceeded the noise
criterion of 55 dB(A). However, the noise exceedances are caused by both
existing road, the planned Road T2 and local road.
7.7.17
Other Sites within KTD area: The predicted traffic noise impacts for other
planned NSRs PN69 – PN108 (except PN93-95) within KTD area are summarized in Table
7.10. The noise exceedances are caused by both existing road and
“New” roads. All the affected NSRs are either commercial uses, mixed uses
or community uses and allowed some noise sensitive uses. For PN71-73 and
PN87-92, the land use allows domestic uses which will require planning
permission from the Town Planning Board. These planning applications
should include assessments on the traffic noise impact to demonstrate that the
proposed development would not result in adverse impact for the development.
Table 7.10
Summary of Traffic Noise Impact for Other Sites within KTD area
NSR
|
Location
|
Planned Land Use
|
Major Noise Sources
|
Noise Level Above criterion,
dB(A)
|
70
|
65
|
55
|
PN69
|
Site 1D3
|
Community Use with
hostel
|
Prince Edward
Road East
|
|
|
|
PN70
|
Site 1D3
|
Community Use
with hostel
|
Road D1
|
|
|
|
PN71
|
Site 1E1
|
Mixed Use
|
Prince Edward
Road East & Road D1
|
|
|
|
PN72
|
Site 1E1
|
Mixed Use
|
Prince Edward
Road East
|
|
|
|
PN73
|
Site 1F1
|
Mixed Use
|
Road D1
|
|
|
|
PN74
|
Site 1M1
|
CDA
|
Prince Edward
Road East
|
|
|
|
PN75
|
Site 1M2
|
CDA
|
Prince Edward
Road East
|
|
|
|
PN76
|
Site 3B1
|
Undesignated
|
Kwun Tong Bypass
&
Road T2
|
|
|
|
PN77
|
Site 3B2
|
Undesignated
|
Kwun Tong Bypass
&
Road T2
|
|
|
|
PN78
|
Site 3B3
|
Undesignated
|
Kwun Tong Bypass
&
Road T2
|
|
|
|
PN79
|
Site 3B4
|
Undesignated
|
Kwun Tong Bypass
&
Road T2
|
|
|
|
PN87A
|
Site 3E1
|
Commercial with
sensitive uses
|
Lam Chak Street
|
|
|
|
PN87B
|
Site 3E1
|
Commercial
with sensitive uses
|
Road D3 & D4
|
|
|
|
PN88
|
Site 3D2
|
Commercial with
sensitive uses
|
Cheung Yip Street
|
|
|
|
PN89
|
Site 3D2
|
Commercial with
sensitive uses
|
Kwun Tong Bypass
|
|
|
|
PN90
|
Site 3D3
|
Commercial with
sensitive uses
|
Cheung Yip Street
|
|
|
|
PN91A
|
Site 3D4
|
Commercial with
sensitive uses
|
Kai Hing Road
&
Kwun Tong Bypass
|
|
|
|
PN91B
|
Site 3D4
|
Commercial
with sensitive uses
|
Kai Hing Road
&
Kwun Tong Bypass
|
|
|
|
PN92
|
Site 3D4
|
Commercial with
sensitive uses
|
Kai Hing Road
|
|
|
|
PN96
|
Site 2A1
|
Commercial with
sensitive uses
|
Prince Edward
Road East & Road D1
|
|
|
|
PN97
|
Site 2A2
|
Commercial with
sensitive uses
|
Prince Edward
Road East & Road D1
|
|
|
|
PN98
|
Site 2A3
|
Commercial with
sensitive uses
|
Prince Edward
Road East & Road D1
|
|
|
|
PN99
|
Site 2A4
|
Commercial with sensitive
uses
|
Prince Edward
Road East & Road D1
|
|
|
|
PN100
|
Site 2A5
|
Commercial with
sensitive uses
|
Prince Edward
Road East & Road D1
|
|
|
|
PN101
|
Site 2A6
|
Commercial with
sensitive uses
|
Prince Edward
Road East & Road D1
|
|
|
|
PN102
|
Site 4A2
|
Commercial with
sensitive uses
|
Road L12
Road L13
|
|
|
|
PN103
|
Site 4C1
|
Commercial with
sensitive uses
|
Road L13
|
|
|
|
PN104
|
Site 4C2
|
Commercial with
sensitive uses
|
Road L13
|
|
|
|
PN105
|
Site 4C3
|
Commercial with
sensitive uses
|
Road L13
|
|
|
|
PN106
|
Site 4C4
|
Commercial with
sensitive uses
|
Road L13
|
|
|
|
PN107
|
Site 4C5
|
Commercial with
sensitive uses
|
Road L13
|
|
|
|
PN108
|
Site 4A3
|
Commercial with sensitive
uses
|
Road L12
|
|
|
|
7.7.18 Ex-San Po Kong Flatted Factory: The predicted overall noise levels
at PN111 & PN112 exceeded the noise criterion of 70 dB(A). The ‘New’ road
(slip road from Prince Edward Road East to San Po Kong) noise contributions to
the overall noise levels would be more than 1.0 dB(A) and the ‘New’ road noise
levels at these NSRs would be above 70 dB(A) for residential dwellings.
Hence, mitigation measure would be required to reduce the noise impact from
‘New’ roads for PN111 & PN112.
Operational Phase Fixed Plant Noise
7.7.19 Sewage Pumping Stations (SPS): Section 4.3 of this report
assessed the operational noise impacts from the proposed SPSs. The
locations of the ventilation fans and the maximum sound power levels (SWLs)
required to meet the relevant noise criteria were determined. The
operation noise impacts from SPSs ventilation fans can be effectively mitigated
by implementing noise control treatment at source during the design stage and
residual operation noise impacts are not anticipated.
7.7.20 Electrical Substations (ESS): The major noise source comes from
the transformer and ventilation system inside and enclosed in the ESSs building
structure. The locations of the exhaust fans and the maximum sound power
levels (SWLs) required to meet the relevant noise criteria were
determined. Table 7.11 shows the proposed locations of the ESS and
the required sound power level for the nearest affected NSRs to achieve noise
compliance. The detailed calculation is shown in Appendix 7.2. The
400kV substation and transmission line are a Schedule 2 DP and its
environmental impact will be fully addressed in separate EIA study.
Table 7.11
Predicted Maximum Allowable Sound Power Levels for ESS
ESS
|
Likely affected NSRs
|
ASRs
|
Approx Distance to NSR, m
|
Sound Power Level (SWL, dB(A)) required at source
in order to meet the criteria
|
Daytime
|
Nighttime
|
Site 1A5
|
PN18
|
B
|
15
|
86
|
-
|
Site 1D1
|
PN2
|
B
|
209
|
108
|
98
|
Site 1P4
|
PN52
|
B
|
83
|
80
|
80
|
Site 2A7
|
PN61
|
B
|
49
|
76
|
76
|
Site 4D5
|
PN64
|
B
|
404
|
94
|
89
|
Site 5A2
|
N18
|
B
|
50
|
75
|
75
|
Site 5A2
|
N19
|
B
|
44
|
75
|
75
|
Site 5C2
|
N24
|
B
|
5
|
76
|
-
|
7.7.21 The above SWL criteria should be
implemented and refined during the detailed design stage of the respective ESS
by the contractor(s). Any new NSRs should also be identified and
incorporated into the design as necessary. The contractor(s) shall
install sound attenuators, noise barriers and acoustic enclosures as
appropriate to ensure that the specified maximum SWLs in the above Table
7.11 are achieved. The performance of the sound attenuators shall be
obtained by comparing the total SWL of noise emanating from the facade and the
specified maximum SWL specified in the above Table 7.11. The
predicted noise levels at NSRs due to cumulative fixed plant operations are
presented in Table 7.12.
Table 7.12
Summary of Predicted Operational Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
N18
|
HK
Society for Blind hostel
|
B
|
60 / 60
|
49 / 50
|
N19
|
Mok
Cheong Street Residential District
|
B
|
60 / 60
|
50 / 50
|
N24
|
Oblate
Father’s Primary School
|
B
|
60 / 60
|
-
|
PN18
|
Site 1A2
(Planned)
|
B
|
60 / 60
|
-
|
PN2
|
Site 1A1
(Planned)
|
B
|
60 / 60
|
50 / 50
|
PN52
|
Site 1L3
(Planned)
|
B
|
60 / 60
|
50 / 50
|
PN61
|
Site 2B6
(Planned)
|
B
|
60 / 60
|
50 / 50
|
PN64
|
Site 4B5
(Planned)
|
B
|
60 / 60
|
50 / 50
|
7.7.22 Vehicular Tunnel Ventilation Shafts: Tunnel Ventilation shafts are
normally required at each end of the underground tunnels. Potential noise
sources are associated with the fan systems. Analysis has been conducted
to quantify the preliminary near-field SWL criteria (Appendix 7.2). A
summary of the SWL criteria which is recommended for incorporation into the
contract specification is given in Table 7.13.
Table 7.13
Predicted Maximum Allowable Sound Power Levels for Ventilation Shafts
Ventilation
Shafts
|
Likely
affected NSRs
|
ASRs
|
Approx
Distance to NSR, m
|
Sound Power Level (SWL, dB(A))
required at source in order to meet the criteria
|
Daytime
|
Nighttime
|
Road T2 (South façade)
|
PN63
|
B
|
445
|
106
|
96
|
Road T2 (South façade)
|
PN80
|
C
|
90
|
106
|
96
|
CKR at Site 5B1 (North façade)
|
N20B
|
B
|
51
|
93
|
83
|
CKR at Site 5B1 (South façade)
|
N21
|
B
|
22
|
86
|
76
|
CKR at Site 1P3
|
PN52
|
B
|
215
|
103
|
89
|
7.7.23 The above SWL criteria should be
implemented and refined during the detailed design by the respective project
proponent. Any new NSRs should also be identified and incorporated into
the design as necessary. The project proponent shall install sound
attenuators, noise barriers and acoustic enclosures as appropriate to ensure
that the specified maximum SWLs in the above Table 7.13 could be
achieved. The performance of the sound attenuators shall be obtained by
comparing the total SWL of noise emanating from the facade and the specified
maximum SWL specified in the above Table 7.13. The predicted noise
levels at NSRs due to cumulative fixed plant operations (include ESSs and SPSs)
are presented in Table 7.14.
Table
7.14
Summary of Predicted Operational
Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
N20B
|
Grand Waterfront
|
B
|
60
/ 60
|
50
/ 50
|
N21
|
Hang Chien Court
|
B
|
60
/ 60
|
50
/ 50
|
PN52
|
Site 1L3 (Planned)
|
B
|
60
/ 60
|
50
/ 50
|
PN63
|
Site 4A1 (Planned)
|
B
|
51
/ 60
|
41
/ 50
|
PN80
|
Site 3C (Planned)
|
C
|
65
/ 65
|
55
/ 55
|
7.7.24 Ventilation Shafts of SCL: The locations of the ventilation
fans and the maximum sound power levels (SWLs) required to meet the relevant
noise criteria were determined. Table 7.15 shows the assumed
locations of the ventilation shafts of SCL and the required sound power level
for the nearest affected NSRs to achieve noise compliance. The detailed
calculation is shown in Appendix
7.2.
Table 7.15
Predicted Maximum Allowable Sound Power Levels for SCL Ventilation Shafts
Ventilation
Shafts
|
Likely
affected NSRs
|
ASRs
|
Approx
Distance to NSR, m
|
Sound
Power Level (SWL, dB(A)) required at source in order to meet the criteria
|
Daytime
|
Nighttime
|
South Vent. Shaft at Kai Tak Station
|
PN45
|
B
|
77
|
96
|
86
|
North Vent. Shaft at Kai Tak Station
|
PN46
|
B
|
74
|
95
|
85
|
South Vent. Shaft at To Kwa Wan Station
(South)
|
PN94, PN62
|
B
|
35,
209
|
93
|
83
|
North Vent. Shaft at To Kwa Wan Station
(North)
|
PN62
|
B
|
232
|
108
|
98
|
Ventilation shaft at Site 5B6
|
N20B
|
B
|
51
|
93
|
83
|
Ventilation shaft at Site 5B6
|
N21
|
B
|
22
|
86
|
76
|
7.7.25 The above SWL criteria should be
implemented and refined during the detailed design stage of SCL. Any new
NSRs should also be identified and incorporated into the design as
necessary. The project proponent of SCL shall install sound attenuators,
noise barriers and acoustic enclosures as appropriate to ensure that the
specified maximum SWLs in the above Table 7.15 would be achieved.
The performance of the sound attenuators shall be obtained by comparing the
total SWL of noise emanating from the facade and the specified maximum SWL
specified in the above Table 7.15. The predicted mitigated noise
levels at those NSRs likely to be affected by the fixed plant noise of the SCL
ventilation shafts are presented in Table 7.16.
Table 7.16
Summary of Predicted Operational Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
PN94
|
Sung
Wong Toi Road CDA site
|
B
|
60 / 60
|
50 / 50
|
N20B
|
Grand
Water Front
|
B
|
60 / 60
|
50 / 50
|
N21
|
Hang Chien Court
|
B
|
60 / 60
|
50 / 50
|
PN45
|
Site
1K1 (Planned)
|
B
|
57 / 60
|
47 / 50
|
PN46
|
Site
1H2 (Planned)
|
B
|
56 / 60
|
46 / 50
|
PN62
|
Site
2B6 (Planned)
|
B
|
59 / 60
|
49 / 50
|
7.7.26 The proposed Road T2 Tunnel, CKR and
SCL will be constructed by the other project proponent. The fixed noise source
will be adequately addressed in a separate EIA report to be prepared and
submitted under the EIAO by the other project proponent.
7.7.27 Cruise Terminal Operation: The proposed cruise terminal is
located at the southeast end of the previous Kai Tak Runway. The length
of the berthing structure is about 1 km. It is planned to accommodate two
cruise vessels. Fixed plant noise associated with the cruise terminal
operation include the fixed plant noise from the cruise ships operation and the
from the ventilation system of the cruise terminal. The nearest NSR to
the proposed cruise terminal is located in Site 4C5 (NSR PN107) for commercial
site with sensitive use and Site 4B5 (NSR PN64) for residential site. The
distance from the nearer cruise vessel (measured from the centre of the cruise
vessel) to the nearest NSR is about 150m. The distance from the further
cruise vessel is about 400 m. In addition, the commercial NSRs located at
Site 4C5 which will most likely be centrally air-conditioned. The layout
of the affected NSRs could be designed to avoid the noise sensitive uses facing
the major noise sources or providing the noise sensitive use, like hotel, with
window insulation and air conditioning. Adverse noise impact at this site
is not expected.
7.7.28 With regards to the fixed plant
noise from cruise ships operation, with reference to the Head Technical
Report, Airborne Noise, the noise level of a cruise is about 63 dB(A) in
Leq(30min) at 100m distance from operational cruise. The noise level of
63 dB(A) was representative for in-berth and idling activity and thus adopted
for predicting daytime noise levels. Furthermore, the nearest
residential NSR, Site 4B5 of 45mPD, will be partially screened from the cruise
vessels by the cruise terminal building of 35mPD.
7.7.29 With regards to the noise emission
associated with the ventilation system of the cruise terminal, the SWL criteria
stated in Table 7.17 below should be reviewed during the detailed design
stage of Cruise Terminal. Any new NSRs should also be identified and
incorporated into the design as necessary. It is anticipated that the
detailed design of the cruise terminal will incorporate the appropriate good
practices to minimise the nuisance of any fixed plant noise on the neighbouring
NSRs and fulfil the EIAO-TM and NCO criteria.
Table 7.17
Predicted Maximum Allowable Sound Power Levels for Cruise Terminal
Ventilation
Ventilation System
|
Likely affected NSRs
|
ASRs
|
Approx Distance to NSR, m
|
Sound Power Level (SWL, dB(A)) required at
source in order to meet the criteria
|
Daytime
|
Nighttime
|
Cruise Terminal
|
PN64
|
B
|
145
|
95
|
90
|
Cruise Terminal
|
PN107
|
B
|
160
|
95
|
-
|
7.7.30 The predicted mitigated noise levels
at those NSRs likely to be affected by the fixed plant noise from the cruise
terminal operation are presented in Table 7.18. The detailed
calculation is shown in Appendix
7.2.
Table
7.18
Summary of Predicted Operational
Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
PN64
|
Site 4B5 (Planned) Residential
|
B
|
60 / 60
|
50 / 50
|
PN107
|
Site 4C5
(Planned) Commercial with sensitive use
|
B
|
63 / 60
|
-
|
7.7.31 From Table 7.18, no adverse
fixed noise impact for PN64. However, exceedance was found at NSR PN107.
Given that this affect NSRs are commercial with sensitive use which will
most likely be centrally air-conditioned and not rely on opened windows for
ventilation, adverse fixed noise impact at these NSRs are not expected.
Alternatively, the layout of the site for NSR PN107 may be arranged in a way to
avoid the sensitive façade of the sensitive use facing the cruise terminal to
avoid unacceptable fixed noise impacts from the cruise terminal operation.
7.7.32 EFTS Depot: The location of the depot and the
maximum sound power levels (SWLs) required to meet the relevant noise criteria
were determined. Table 7.19 shows the assumed locations of the
depot and the required sound power level for the nearest affected NSRs to
achieve noise compliance. The detailed calculation is shown in Appendix 7.2.
Table 7.19
Predicted Maximum Allowable Sound Power Levels for EFTS Depot
Ventilation Shafts
|
Likely affected NSRs
|
ASRs
|
Approx Distance to NSR, m
|
Sound Power Level (SWL, dB(A)) required at
source in order to meet the criteria
|
Daytime
|
Nighttime
|
EFTS Depot
|
PN108
|
B
|
55
|
97
|
87
|
Note: This prediction is for indicative purpose only as Site 4A3
is planned for commercial use. Any noise sensitive uses like hotel at
this site will most likely be provided with central air-conditioning.
7.7.33 The above SWL criteria should be
implemented and refined during the detailed design stage of the depot.
Any new NSRs should also be identified and incorporated into the design as
necessary. The project proponent of the EFTS depot shall install sound
attenuators, noise barriers and acoustic enclosures as appropriate to ensure
that the specified maximum SWLs in the above Table 7.19 would be
achieved. The performance of the sound attenuators shall be obtained by
comparing the total SWL of noise emanating from the facade and the specified
maximum SWL specified in the above Table 7.19. The predicted
mitigated noise levels at those NSRs likely to be affected by the fixed plant
noise of the EFTS depot are presented in Table 7.20. The EFTS
depot is a Schedule 2 DP and its environmental impact will be fully addressed
in separate EIA study.
Table 7.20
Summary of Predicted Operational Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
PN108
|
Site 4A3 (Planned)
|
B
|
60 / 60
|
50 / 50
|
Note:
This prediction is for indicative purpose only as Site 4A3 is planned
for commercial use. Any noise sensitive uses like hotel at this site will
most likely be provided with central air-conditioning.
7.7.34 Public Transportation Interchange (PTI): The locations of the ventilation
fans and the maximum sound power levels (SWLs) required to meet the relevant
noise criteria were determined. Table 7.21 shows the assumed
locations of the ventilation system of PTIs and the required sound power level for
the nearest affected NSRs to achieve noise compliance. The detailed
calculation is shown in Appendix
7.2.
Table
7.21
Predicted Maximum Allowable Sound Power
Levels for PTI Ventilation System
Ventilation Shafts
|
Likely affected NSRs
|
ASRs
|
Approx Distance to NSR, m
|
Sound Power Level (SWL, dB(A))
required at source in order to meet the criteria
|
Daytime
|
Nighttime
|
PTI
at Site 1F2
|
PN73
|
B
|
47
|
88
|
78
|
PTI
at Site 4D2
|
PN64
|
B
|
130
|
95
|
90
|
PTI
at Site 4D2
|
PN107
|
B
|
160
|
95
|
-
|
Note:
This prediction for PN107 at Site 4A3 is for indicative purpose only as
Site 4C5 is planned for commercial use. Any noise sensitive uses like
hotel at this site will most likely be provided with central air-conditioning.
7.7.35 The above SWL criteria should be
implemented and refined during the detailed design stage of PTI. Any new
NSRs should also be identified and incorporated into the design as
necessary. The developer of PTI shall install sound attenuators, noise
barriers and acoustic enclosures as appropriate to ensure that the specified
maximum SWLs in the above Table 7.21 would be achieved. The performance
of the sound attenuators shall be obtained by comparing the total SWL of noise
emanating from the facade and the specified maximum SWL specified in the above Table
7.21. The predicted mitigated noise levels at those NSRs likely to be
affected by the fixed plant noise of the PTI ventilation system are presented
in Table 7.22.
Table 7.22
Summary of Predicted Operational Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
PN73
|
Site 1F1
(Planned)
|
B
|
56 / 60
|
46 / 50
|
PN64
|
Site 4B5
(Planned)
|
B
|
60 / 60
|
50 / 50
|
PN107
|
Site 4C5
(Planned)
|
B
|
63 / 60
|
-
|
Note:
This
prediction for PN107 at Site 4A3 is for indicative purpose only as Site 4C5 is
planned for commercial use. Any noise sensitive uses like hotel at this
site will most likely be provided with central air-conditioning.
7.7.36 From Table 7.22, no adverse
fixed noise impact for PN64. However the exceedance was found at NSR
PN107. Given that this affect NSRs are commercial with sensitive use which will
most likely be centrally air-conditioned and not rely on opened windows for
ventilation, adverse fixed noise impact at these NSRs are not expected.
Alternatively, the layout of the site for NSR PN107 may be arranged in a way to
avoid the sensitive façade of the sensitive use facing the PTI to avoid
unacceptable fixed noise impacts from the PTI.
7.7.37 Noise from Sports Activity at
Stadium: Site 2D is
reserved for the development of a Stadium Complex. The location of the
Stadium Complex has been planned with considerations of protection of view
corridor, accessibility by public transport and provision of sufficient buffer
distance to the nearby NSRs. Noise from stadiums for sporting activities
may include both the crowd noise and public address broadcast (PA).
7.7.38 Noise surveys for crowd noise and PA
system were carried out at the grandstand and adjacent areas during a
horseracing day and the measurement results are presented in the approved Main
Arena of the 2008 Olympic Equestrian Event EIA Report. The measured noise
level of crowd and PA noise is about 73 dB(A) at 1.2m above floor level.
It is considered that the potential noise generated from sports activities
would be similar or lower than that generated from horseracing event. For
the purpose of assessing the potential noise impacts from sports activity at
the Stadium Complex (including the main stadium and the secondary stadium), 73
dB(A) measured at horseracing event is therefore taken as a conservative
assumption. As mentioned above, the retractable roof of the main stadium
could provide screening effect to the noise impact and reduce noise levels at
nearby NSRs. The SEKDCFS EIA Report stated retractable roof can achieve
about 25 dB(A) reduction. As conservative approach, 10 dB(A) reduction
for retractable roof at main stadium was adopted for assessment.
7.7.39 The predicted noise levels at those
NSRs likely to be affected by the sports activity at the Stadium Complex
(including the main stadium and the secondary stadium) are presented in Table
7.23. The detailed calculation is shown in Appendix 7.3.
Table 7.23
Summary of Predicted Operational Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
PN48
|
Site 1K3
(Planned)
|
B
|
58 / 60
|
-
|
PN52
|
Site 1L3
(Planned)
|
B
|
60 / 60
|
-
|
PN65
|
Site 5A4
(Planned) façade facing to Stadium Complex
|
B
|
57 / 60
|
-
|
7.7.40 With the mitigation measures such as
retractable roof or other equivalent measures to be implemented for the main
stadium, noise impact due to the sports activity to be held in the stadium is
not likely to be significant and fulfil day time and evening period noise
criteria. However, due to the more stringent noise criteria during
night-time (after 11pm), the acceptability of the operation of the Stadium
Complex after 11pm should be demonstrated by noise impact assessment during its
detailed design stage.
7.7.41 District Cooling System Plant (DCSP): The major noise source comes from
the pump system inside and enclosed in the DCSP building structure. The
locations of the exhaust fans and the maximum sound power levels (SWLs)
required to meet the relevant noise criteria were determined. Table
7.24 shows the proposed locations of the DCSP and the required sound power
level for the nearest affected NSRs to achieve noise compliance. The
detailed calculation is shown in Appendix 7.2.
Table 7.24
Predicted Maximum Allowable Sound Power Levels for DCSP
DCSP
|
Likely affected NSRs
|
ASRs
|
Approx Distance to NSR, m
|
Sound Power Level (SWL, dB(A)) required at
source in order to meet the criteria
|
Daytime
|
Nighttime
|
Site 1N2
|
PN34
|
B
|
75
|
99
|
89
|
Site 1N2
|
PN38
|
B
|
70
|
99
|
89
|
Site 4C1
|
PN103
|
B
|
5
|
76
|
66
|
Note:
This
prediction for PN103 at Site 4C1 is for indicative purpose only as Site 4C1 is
planned for commercial use. Any noise sensitive uses like hotel at this
site will most likely be provided with central air-conditioning.
7.7.42 The above SWL criteria should be
implemented and refined during the detailed design stage of the respective DCSP
by the contractor(s). Any new NSRs should also be identified and
incorporated into the design as necessary. The contractor(s) shall
install sound attenuators, noise barriers and acoustic enclosures as
appropriate to ensure that the specified maximum SWLs in the above Table
7.24 are achieved. The performance of the sound attenuators shall be
obtained by comparing the total SWL of noise emanating from the facade and the
specified maximum SWL specified in the above Table 7.24. The
predicted noise levels at NSRs due to DCSP operations are presented in Table
7.25.
Table 7.25
Summary of Predicted Operational Noise Levels
NSR
|
NSR
Description
|
ASRs
|
Predicted Noise Level, dB(A)
/ ANL, dB(A)
|
Daytime
|
Nighttime
|
PN34
|
Site 1B1
|
B
|
59 / 60
|
49 / 50
|
PN38
|
Site 1B4
|
B
|
60 / 60
|
-
|
PN103
|
Site 4C1
|
B
|
60 / 60
|
50 / 50
|
Note:
This
prediction for PN103 at Site 4C1 is for indicative purpose only as Site 4C1 is
planned for commercial use. Any noise sensitive uses like hotel at this
site will most likely be provided with central air-conditioning.
Noise from Open Air Entertainment Activities
7.7.43 Site 2D is reserved for the
development of a Stadium Complex. The location of the Stadium Complex has
been planned with considerations of protection of view corridor, accessibility
by public transport and provision of sufficient buffer distance to the nearby
NSRs. For the secondary stadium, noise from secondary stadium for sporting
activities may include both the crowd noise and public address broadcast
(PA). The potential noise impacts associated with sporting activities was
assessed as fixed noise source and described above.
7.7.44 The major noise source come from the
main stadium includes the use of loudspeakers and the crowd. The buffer
distance between the main stadium and the NSRs varies from 200 to over 500 m
which could attenuate the noise impact significantly.
7.7.45 As the retractable roof of the main
stadium could provide screening effect to the noise impact and reduce noise
levels at nearby NSRs.
7.7.46 With reference to approved SEKDCFS
EIA Report, noise measurements from concerts in Hong Kong Stadium previously
showed that the typical noise levels in Leq(15mins) of about 170 m
away from Hong Kong Stadium was 73-75dB(A) or equal to SWL 125dB(A). It
is likely that noise from the proposed main stadium would affect nearby NSRs if
mitigation measures such as retractable roof or enclosure were not adopted.
The SEKDCFS EIA Report also proposed retractable roof to mitigate the impact
from noisy events and it can achieve about 25dB(A) reduction. For
conservative approach, 10dB(A) reduction was adopted for assessment.
7.7.47 With reference to the above, the
typical noise levels generated by open air entertainment activities at the NSRs
were assessed. The distance to the nearest NSRs surrounding the main
stadium and the potential noise impacts predicted with 10dB(A) reduction (with
a retractable roof) were summarised in Table 7.26. The detailed
calculation is shown in Appendix
7.4.
Table 7.26
Predicted Potential Noise Impact from the Main Stadium on the Nearest
NSRs
Likely affected NSRs
|
ASRs
|
Approx. Distance to NSR, m
|
Predicted Noise Impact,
Leq(15min), dB(A)
|
PN48
|
B
|
345
|
59
|
PN52
|
B
|
300
|
60
|
PN65 (façade facing to Stadium Complex)
|
B
|
215
|
63
|
7.7.48 The background noise level in urban
area is around 60 dB(A) or more in general. With the mitigation measures
such as retractable roof or other equivalent measures to be implemented for the
main stadium, noise impact due to the activities to be held in the main stadium
is not likely to be significant and fulfil day time and evening period noise
criteria (ie. noise level not more than 5 dB(A) above the background noise
level, as measured at one metre from the exterior building façade of the
affected NSRs). However, due to the more stringent noise criteria during
night-time (after 11pm), the acceptability of the operation of the Stadium
Complex after 11pm should be demonstrated by noise impact assessment during its
detailed design stage. The main stadium is a Schedule 2 DP and its
environmental impact will be fully addressed in separate EIA study.
Heliport Noise
7.7.49 With reference to a number of
approved EIA reports, the measured / predicted Lmax are shown in Table 7.27
below.
Table
7.27
Summary of Helicopter Noise Emission Data
Model
|
Lmax, dB(A)
|
Measurement distance, m
|
SWL, dB(A)
|
EC155B(1)
|
87.7
|
150
|
139
|
AS332 L2(1)
|
90.6
|
150
|
142
|
Sikorsky S76(2)
|
100
|
25
|
136
|
Black Hawk S70(2)
|
100
|
25
|
136
|
S76C+(3)
|
86
|
264
|
142
|
Note: (1) Data
extracted from Final EIA Study for Helipad at Yung Shue Wan, Lamma Island, 2006
(2) Data extracted from Agreement No. CE 32/99 SEKDCFS EIA Study
(3) EIA Study for the Expansion of Heliport Facilities at Macau Ferry Terminal,
2005
7.7.50
With reference to basic
acoustic principles and based on the noise level for a AS332 L2 and S76C+
helicopter, a setback distance of about 286 m to the nearest residential
premises is required in order to meet the EIAO-TM noise standard of 85 dB(A)
Lmax (domestic premises) for helicopter noise. From Table 7.27, it
is noted that for other helicopters, which is quieter than the AS332 L2 and
S76C+ helicopters, smaller set-back distances from the proposed helipads would
be required. The distance between the permanent helipad and the closest
residential NSR (PN64) is about 700 m with an estimated 80dB(A) Lmax at
PN64. Therefore, it is considered that the proposed helipad locations
would comply with the helicopter noise criteria at the nearest NSRs, adverse
helicopter noise impact would not be anticipated.
Rail Noise
7.7.51
The alignment of EFTS is shown in Figure 7.2. For
conservative noise assessment, the rail based EFTS was assumed for rail noise
assessment. Reference was made to the approved EIA reports in the EIAO
Register regarding potential noise impacts from railway operation in urban
area, including the SEKDCFS EIA, Light Rail Transit (LRT) Extension in Tin Shui
Wai Reserve Zone and Grade Separation of the LRT with Pui To Road and Tsing
Lung Road in Tuen Mun (Register No.: AEIAR-027/1999) and East Rail Extension –
Tai Wai to Ma On Shan (MOS) Rail (Register No.: AEIAR-028/1999).
7.7.52 With reference to the findings of
LRT EIA report, there will be no significant noise impacts on NSRs at
horizontal distance of 10m to 40m which is similar to the situation in
KTD. As shown in Figure 7.2, most of
the NSRs are not planned within 10m
buffer distance of the two proposed alignment options for EFTS. Given the maximum speed, train frequency
of the EFTS is slower and lower than LRT rail, adverse noise impact from ETFS
is not anticipated. For those NSRs
with horizontal separation distance from EFTS of less than 10m (the section
outside hotel sites Site 4A2 and Site 4C1 to 4C5 along ex-Runway and the
section along the public promenade outside commercial site Site 3D4 in Kowloon
Bay), the mitigation measures adopted in MOS Rail could be considered for the
EFTS to further reduce the noise impact, if required. The measures adopted in MOS rail include
multi-plenum system and vertical noise barrier at the all elevated sections of
the alignment on viaduct. The rail
based EFTS is a Schedule 2 DP and its environmental impact will be fully
addressed in separate EIA study if the selected system is rail type.
7.7.53
As to further reduce
the noise impact arising from the EFTS, the mitigation measures adopted in MOS
Rail could be considered for the EFTS, if required. The measures adopted
in MOS rail include multi-plenum system and vertical noise barrier at the all
elevated sections of the alignment on viaduct. The rail based EFTS is a
Schedule 2 DP and its environmental impact will be fully addressed in separate
EIA study if the selected system is rail type.
7.8
Mitigation of
Environmental Impacts
Construction Phase
7.8.1
In order to reduce the
excessive noise impacts at the affected NSRs during normal daytime working
hours, mitigation measures such as adopting quiet powered mechanical equipment,
movable noise barriers and temporary noise barriers are recommended. The
contractor(s) may be able to obtain particular models of plant that are quieter
than the PMEs given in GW-TM. It is considered too restrictive to specify
that a contractor has to use specific items of plant for the construction
operations. It is practical to specify the total SWL of all plant to be
used on site so that the contractor(s) is allowed some flexibility to select
plant to suit his needs.
7.8.2
The use of quiet plant
associated with the construction works is prescribed in British Standard “Noise
Control on Construction and Open Sites, BS5228: Part 1: 1997” which contains
the SWLs for specific quiet PME. The SWLs for quiet PMEs adopted for the
assessment are detailed in Appendix 3.26.
7.8.3
To alleviate the
construction noise impact on the affected NSRs, movable noise barrier for
Asphalt Paver, Breaker, Excavator and Hand-held breaker and full enclosure for
Air Compressor, Bar Bender, Concrete Pump, Generator and Water Pump are
proposed. Movable temporary noise barriers that can be located close to
noisy plant and be moved iteratively with the plant along a worksite can be
very effective for screening noise from NSRs. A typical design which has
been used locally is a wooden framed barrier with a small cantilevered upper
portion of superficial density no less than 14kg/m2 on a skid
footing with 25mm thick internal sound absorptive lining. This measure is
particularly effective for low level zone of NSRs. A cantilevered top cover
would be required to achieve screening benefits at upper floors of NSRs.
It is anticipated that suitably designed barriers could achieve at least 5 – 10
dB(A) reduction. For a conservative assessment, only a reduction of
5dB(A) is assumed. A sketch of typical temporary noise barrier and
enclosure are illustrated in Figure 3.13.
7.8.4
The use of full
enclosure has been considered in this assessment to shelter relatively static
plant including air compressor, bar bender, concrete pump, generator and water
pump. These enclosures can provide about 10 dB(A) noise reduction.
7.8.5
Noise reduction from
the use of mitigation measures including quiet plant, noise barrier and
enclosure for construction plants as described above has been applied in the
assessment. Detailed results of construction noise assessment for
“mitigated” scenario are given in Appendix 3.27. The
predicted cumulative noise levels and the exceedances over daytime construction
noise criteria are summarised in the following Table 7.28.
Table 7.28
Summary of Cumulative Mitigated Construction Noise Levels at
Representative NSRs During Normal Daytime
Working Hours
NSR
|
Noise Criteria, dB(A)
|
Predicted Mitigated Construction
Noise Levels during Normal Daytime Working Hour (Leq (30-min)
dB(A))
|
Exceedance, dB(A)
|
Duration, Month
|
N1
|
75
|
41 - 71
|
0
|
0
|
N2
|
75
|
42 - 70
|
0
|
0
|
N3
|
75
|
43 - 67
|
0
|
0
|
N4
|
65/70*
|
51 - 68
|
3/0
|
Examination Period
|
N5
|
65/70*
|
51 - 70
|
5/0
|
Examination Period
|
N6
|
75
|
49 - 73
|
0
|
0
|
N7
|
75
|
46 - 75
|
0
|
0
|
N8
|
75
|
45 - 73
|
0
|
0
|
N9
|
75
|
45 - 71
|
0
|
0
|
N10
|
75
|
45 - 75
|
0
|
0
|
N11
|
65/70*
|
47 - 75
|
10/5
|
66 include examination period
|
N12
|
75
|
47 - 74
|
0
|
0
|
N13
|
65/70*
|
47 - 74
|
9/4
|
66 include examination period
|
N14
|
75
|
47 - 78
|
3
|
12
|
N15
|
75
|
47 - 75
|
0
|
0
|
N16
|
75
|
46 - 70
|
0
|
0
|
N17
|
75
|
47 - 75
|
0
|
0
|
N18
|
75
|
50 - 76
|
1
|
7
|
N19
|
75
|
50 - 75
|
0
|
0
|
N20A
|
75
|
48 - 70
|
0
|
0
|
N20B
|
75
|
48 - 78
|
3
|
60
|
N21
|
75
|
48 - 78
|
3
|
60
|
N22
|
75
|
48 - 75
|
0
|
0
|
N23
|
65/70*
|
47 - 86
|
21/16
|
24 include examination period
|
N24
|
65/70*
|
47 - 64
|
0/0
|
0
|
N25
|
75
|
45 - 71
|
0
|
0
|
N26
|
75
|
45 - 68
|
0
|
0
|
N27
|
65/70*
|
45 - 68
|
3/0
|
Examination Period
|
N28
|
65/70*
|
44 - 70
|
5/0
|
N29
|
75
|
44 - 66
|
0
|
0
|
N30
|
75
|
50 - 74
|
0
|
0
|
N31
|
60/70*
|
32 - 51
|
0
|
0
|
N32
|
75
|
46 - 70
|
0
|
0
|
PN1
|
75
|
47 - 75
|
0
|
0
|
PN2
|
75
|
58 - 86
|
11
|
39
|
PN35
|
75
|
62 - 73
|
0
|
0
|
Note:
*For normal daytime working hours, the noise criteria are 70 dB(A) and 65 dB(A)
for normal teaching periods and examination periods, respectively.
7.8.6
With the exception of
NSRs N4, N5, N11, N13, N14, N18, N20B, N21, N23, N27, N28 & PN2, the predicted
mitigated construction noise levels arising from the Project at all other NSRs
selected for construction noise impact assessment would comply with the EIAO-TM
construction noise criteria.
Operational Phase
Road Traffic Noise
7.8.7
Direct mitigation
measures would be proposed for ‘New’ roads if there would be adverse
environmental impact. If the NSRs are affected by noise from other
existing roads, direct mitigation measures are required to reduce the noise
from the ‘New’ roads to a level that it
l
is not higher than the
noise standard; and
l
has no significant
contribution to the overall noise from other existing roads, if the cumulative
noise level (i.e. noise from the new road together with other existing roads)
exceeds the noise standard.
7.8.8
As discussed in above,
direct mitigation measures on some ‘New’ roads would be required to mitigate
the noise impact at Site 1A2 to 1A4 (Road L3 through Road), Site 1B (Road L2
& L4), Site 1I1 (Road L4), Site 1L2 (Road D2), Site 1L3 (Road D2) &
Site 2A6 (Road L9). A figure shown the direct noise mitigation measures
are presented in Figure
3.14. The detailed mitigation measures are discussed below:
7.8.9
Site 1A2 to 1A4
(School Site):
the predicted overall noise levels at PN19, PN20 & PN20A exceeded the noise
criterion of 65dB(A). In view of the site constraint, provision of noise
tolerant building is not feasible. The layout of these planned schools
may be arranged in a way to avoid the sensitive facades of the classrooms
facing Roads L2 and L3 or as the last resort all the classrooms should be noise
insulated with air-conditioners to avoid unacceptable traffic noise impacts
from the surrounding road network.
7.8.10 Under the Through Road L3
alternative option, the predicted overall noise levels at PN19A & PN20A
exceeded the noise criterion of 65 dB(A). Low noise surfacing is proposed
for a section of Road L3 to minimize the traffic noise impact. With the
proposed low noise surfacing, PN19A and PN20A facing the Through Road L3 would
comply with the noise criteria. Yet the layout of these planned schools
should still be arranged in a way to avoid the sensitive facades of the
classrooms facing Road L2 or as the last resort all the classrooms should be
noise insulated with air-conditioners to avoid unacceptable traffic noise
impacts from the surrounding road network.
7.8.11 Site 1B1: It is identified that the ‘New’
road noise contribution to the overall noise level is more than 1.0dB(A) for
PN23A to PN23C, PN26, PN29, PN30A to PN31B & PN33. The major noise
source is Road L2 and Kwun Tong Bypass that contributed significant traffic
noise impact on these NSRs even incorporated 1.5m vertical fins next to the
sensitive facades.
7.8.12 As to reduce the traffic noise
impact further, a number of mitigation measures have been reviewed. Owing
to the site constraint, setback of buildings to west direction is not
feasible. By rotating buildings orientation can reduce the view angle of
flats at one wing, but on the other hand also increase the view angle of some flats
on the other wings. It is therefore considered ineffective to reduce the
noise levels. Noise tolerant buildings as a noise barrier have already
been provided in front of those affected NSRs for screening the traffic noise
impact from Road L2. Therefore, provision of noise barrier along Road L2
is ineffective and a section of low noise surfacing on Road L2 is
proposed. In addition to the source treatment and low noise surfacing,
1.2m to 1.7m structural fins are also proposed at the location next to the
sensitive facades of the affected dwellings. The proposed extent of low
noise surfacing and structural fins locations are shown in Figure 3.14.
7.8.13 Site 1B2 to 1B4 (School Site): The predicted overall noise levels
at PN36, PN37 & PN38 exceeded the noise criterion of 65 dB(A). The
‘New’ roads noise contribution to the overall noise levels would be more than
1.0 dB(A). The major noise sources are Road L2 and Road L4. In view
of the site constraint, provision of noise tolerant building is not
feasible. The layout of these planned schools may be arranged in a way to
avoid the sensitive facades of the classrooms facing Roads L2 and L4 or as the
last resort all the classrooms should be noise insulated with air-conditioners
to avoid unacceptable traffic noise impacts from the surrounding road
network. In addition, a section of low noise surfacing on Roads L2 and L4
are proposed. The extent of low noise surfacing is shown in Figure 3.14.
7.8.14 Site 1I1: The predicted overall noise levels
at PN39 & PN40 exceeded the noise criterion of 70 dB(A). The ‘New’
road noise contributions to the overall noise levels would be more than 1.0
dB(A) and the ‘New’ road noise levels at these NSRs would be above 70 dB(A) for
residential dwellings.
7.8.15 In order to reduce the traffic noise
impact, a number of mitigation measures have been reviewed. Owing to the
site constraint, noise tolerant buildings are not feasible. By rotating
buildings orientation can reduce the view angle of flats, but on the other hand
also increase the view angle of some flats on the surrounding roads. It
is therefore considered ineffective to reduce the noise levels.
Therefore, low noise surfacing for a section of Road L4 and setback of the
building within the site by about 5m to the southwest direction are
proposed. The extent of low noise surfacing is shown in Figure 3.14.
For the other effective mitigation measures such as special building design
& architectural features / balcony, it would be subject to further
investigation by the future developer.
7.8.16 Site 1L2 and 1L3: The predicted overall noise levels
at PN50, PN51 & PN52 exceeded the noise criterion of 70 dB(A). The
‘New’ road noise contributions to the overall noise levels would be more than
1.0 dB(A) and the ‘New’ road noise levels at these NSRs would be above 70 dB(A)
for residential dwellings.
7.8.17 In order to reduce the traffic noise
impact, a number of direct mitigation measures have been reviewed. By
rotating building orientation can reduce the view angle of flats, but on the
other hand also increase the view angle of some flats on the surrounding
roads. Setback of the building by about 35m to the northwest direction at
Site 1L3 and 5m at Site 1L2 are proposed as mitigation measures for traffic
noise impact. For the other effective mitigation measures such as special
building design & architectural features / balcony, it would be subject to
further investigation by the future developer.
7.8.18 Site 2B6: The predicted noise levels at
planned NSRs for PN61 & PN62 exceeded the noise criterion of 70
dB(A). However, the noise exceedances are caused by the existing
roads. In the view of the ‘New’ road noise contribution to the overall
noise level would be less than 1.0 dB(A) and the ‘New’ road noise levels at
these NSRs would all be below 70 dB(A). Mitigation measures in the form
of special building design (include noise tolerant building & single aspect
building design) could be considered to reduce the traffic noise impact.
7.8.19 The proposed mitigation measures in
the form of special building design include: (i) avoid any sensitive façades
with openable window facing the existing Kowloon City Road network and (ii) for
the sensitive facades facing the To Kwa Wan direction, either setback the
facades by about 5m to the northeast direction or do not provide the facades
with openable window. The identified special building design have been
agreed with the Planning Department and the Lands Department. For the
other effective mitigation measures such as other special building design &
architectural features / balcony, it would be subject to further investigation
by the future developer. The traffic noise mitigation measures are
illustrated in Figure
3.15.
7.8.20 Site 5A4: The predicted noise levels at
planned NSRs for PN65 and PN66 exceeded the noise criterion of 70 dB(A).
However, the noise exceedances are caused by the existing roads. In the
view of the ‘New’ road noise contribution to the overall noise level would be
less than 1.0 dB(A) and the ‘New’ road noise levels at these NSRs would all be
below 70 dB(A). Mitigation measures such as special building design
(include noise tolerant building & single aspect building design) could be
considered to reduce the traffic noise impact. It should be noted that the
existing traffic noise impacts on the existing NSRs in Site 5A4 are not within
the scope of this EIA study.
7.8.21 The proposed mitigation measures in
the form of special building design include: (i) avoid any sensitive facades
with openable window facing the existing To Kwa Wan Road or (ii) provision of
17.5m high noise tolerant building fronting To Kwa Wan Road and restrict the
height of the residential block(s) located at less than 55m away from To Kwa
Wan Road to no more than 25m above ground. The identified special
building design have been agreed with the Planning Department and the Lands
Department. For the other effective mitigation measures such as other
special building design & architectural features / balcony, it would be
subject to further investigation by the future developer. The traffic
noise mitigation measures are illustrated in Figure 3.15.
7.8.22 Site 3C (Hospital / Clinic): The predicted noise levels at
planned NSRs for PN80 to PN86 exceeded the noise criterion of 55 dB(A).
As confirmed with Food and Health Bureau, the proposed hospital site will
provide with window insulation and air conditioning, adverse traffic noise
impacts at these NSRs are not expected. The documentation of confirmation
from Food and Health Bureau is shown in Appendix 18.1.
7.8.23 Other Sites within KTD area: The predicted noise levels at
planned NSRs for PN69 to PN108 (except PN93 – PN95) exceeded the noise
criterion of 55, 65 & 70 dB(A). The noise contribution is from
existing and “New” road. All the affected NSRs are either commercial uses
or the like, mixed uses or community uses and allowed some noise sensitive
uses. Given that most affected NSRs are commercial uses which will most
likely be centrally air-conditioned, the layout of the affected NSRs could be
designed to avoid the noise sensitive uses facing the major traffic noise
sources or providing the noise sensitive uses, like hotel, with window
insulation and air conditioning. Adverse traffic noise impacts at these
NSRs are not expected.
7.8.24 With reference to the OZP, a special
design requirement should be incorporated for Site 1F1 facing the Station
Square such that the residential element should commensurate with the
commercial element in form as stated in OZP. The residential development
could accommodate high quality hotel-like service apartment with its design and
appearance befitting the image of the Kai Tak Center and commensurate with
those premier commercial / office developments to its west and east.
Adverse traffic noise impacts at these NSRs are not expected.
7.8.25 For those planned NSRs at Site 1E1,
the residential development could be designed to avoid sensitive façade facing
to the noise sources or incorporate hotel-like service apartment with provision
of central air conditioning. Adverse traffic noise impacts at these NSRs
are not expected.
7.8.26 For those planned domestic NSRs at
Site 3D2 to 3D4 and Site 3E1, the residential development could be designed to
avoid sensitive façade facing to the noise sources or incorporate hotel-like
service apartment with provision of central air conditioning. Adverse
traffic noise impacts at these NSRs are not expected. Furthermore, the
planning applications should include assessments on the relevant technical and
environmental concerns and demonstrate that the proposed development would not
result in adverse traffic noise impact.
7.8.27 Ex-San Po Kong Flatted Factory: The predicted overall noise levels
at PN111 & PN112 exceeded the noise criterion of 70 dB(A). The ‘New’
road noise contributions to the overall noise levels would be more than 1.0
dB(A) and the ‘New’ road noise levels at these NSRs would be above 70 dB(A) for
residential dwellings.
7.8.28 In order to reduce the traffic noise
impact, a number of direct mitigation measures have
been reviewed. The proposed
mitigation measures in the form of special building design should avoid any
sensitive façades with openable window facing the slip road from Prince Edward Road East
to San Po Kong. The traffic noise
mitigation measures are illustrated in Figure 3.15. Since the proposed development is still
subject to detailed design and the layout is yet to be finalised, other
alternative effective mitigation measures including special building design for
the development and at-source mitigation measures for the surrounding new local
roads may also be considered respectively by the developer (namely the Housing
Department) and the implementation and maintenance agents of the surrounding
new local roads in the future.
7.8.29 Appendix 3.28 presents the breakdown of noise
contribution from the “New” roads and existing roads at all representative NSRs
when all the proposed mitigation measures are in place. With these
proposed measures in place, the predicted overall noise levels at all the
representative NSRs comply with the noise criterion.
Operational Phase Fixed Plant Noise
7.8.30 Sewage Pumping Stations (SPS): The main sources of noise for SPS are
pumps and ventilation system. The detailed design should incorporate the
following good practice in order to minimise the nuisance on the neighbouring
NSRs.
l
The exhaust of the
ventilation system and any opening of the building should be located facing
away from any NSRs;
l
Louver or other
acoustic treatment equipment could also be applied to the exhaust exit of the
building; and
l
Pumps and mechanical
ventilation are either underground or enclosed within a structure or building.
7.8.31 Electrical Substations (ESS): The major noise sources for ESS
are the transformer and ventilation system. The transformer should be
located inside and enclosed in the ESS building structure. The detailed
design should incorporate the following good practice in order to minimise the
nuisance on the neighbouring NSRs. The 400kV substation and transmission
line are a Schedule 2 DP and its environmental impact and mitigation measures,
if any, will be fully addressed in separate EIA study.
l
The exhaust of the
ventilation system and any opening of the building should be located facing
away from any NSRs; and
l
Louver or other
acoustic treatment equipment could also be applied to the exhaust exit of the
building.
7.8.32 Tunnel Ventilation Shafts: The main sources of noise are the
ventilation fans. The detailed design should incorporate the following
good practice in order to minimise the nuisance on the neighbouring NSRs.
l
The exhaust of the
ventilation system and any opening of the building should be located facing
away from any NSRs; and
l
Louver or other
acoustic treatment equipment could also be applied to the exhaust exit of the
building.
7.8.33 Cruise Terminal: The main sources are fixed plant
noise from ventilation system of cruise terminal and the cruise ships
operation. It is anticipated that the detailed design of the cruise
terminal will incorporate the appropriate good practices to minimise the
nuisance of any fixed plant noise on the neighbouring NSRs and fulfil the
EIAO-TM and NCO criteria.
7.8.34 For the exceedance at NSR PN107,
given that this affect NSRs are commercial with sensitive use which will most
likely be centrally air-conditioned and not rely on opened windows for
ventilation, adverse fixed noise impact at these NSRs are not expected.
Alternatively, the layout of the site for NSR PN107 may be arranged in a way to
avoid the sensitive façade of the sensitive use facing the cruise terminal to
avoid unacceptable fixed noise impacts from the cruise terminal operation.
7.8.35 EFTS Depot: The main sources of noise are the
maintenance and ventilation system. The detailed design should incorporate
the following good practice in order to minimise the nuisance on the
neighbouring NSRs. The EFTS depot is a Schedule 2 DP and its
environmental impact and mitigation measures, if any, will be fully addressed
in separate EIA study
l
The exhaust of the
ventilation system and any opening of the building should be located facing
away from any NSRs; and
l
Louver or other
acoustic treatment equipment could also be applied to the exhaust exit of the
building.
7.8.36 Noise from Sports Activity at
Stadium: Further
study has to be carried out in the detailed design stage of the Stadium Complex
to ensure the compliance to the relevant noise criteria with any necessary
mitigation measures. The mitigation measures such as retractable roof or
other equivalent measures would be considered for the main stadium. With
incorporation of proper mitigation measures such as retractable roof and
acoustics engineering for the sound system, adverse noise impact from the main
stadium on the neighbouring NSRs is not expected.
Noise from Open Air Entertainment
Activities
7.8.37 Further study has to be carried out
in the detailed design stage of the Stadium Complex to ensure the compliance to
the relevant noise criteria with any necessary mitigation measures. The
mitigation measures such as retractable roof or other equivalent measures would
be considered for the main stadium. With incorporation of proper
mitigation measures such as retractable roof, fixed roof and acoustics
engineering for the sound system, adverse noise impact from the main stadium on
the neighbouring NSRs is not expected. The main stadium is a Schedule 2
DP and its environmental impact and mitigation measures, if any, will be fully
addressed in separate EIA study
Heliport Noise
7.8.38 As mentioned in Sections 7.7,
adverse noise impact from the proposed helipad would not be expected at the
nearest NSR. Mitigation measures are not required.
Rail Noise (EFTS)
7.8.39
There will be no significant
noise impacts on NSRs arising from Environmental Friendly Transportation Link
(EFTS) at horizontal distance of 10 m away from rail line. As to further
reduce the noise impact arising from the EFTS, the mitigation measures adopted
in Ma On San (MOS) Rail could be considered for the EFTS, if required.
The measures adopted in MOS rail include the multi-plenum system and vertical
noise barrier at the all elevated sections of the alignment on viaduct.
The rail based EFTS is a Schedule 2 DP and its environmental impact and
mitigation measures, if any, will be fully addressed in separate EIA study if
the selected system is rail type.
7.9
Evaluation of Residual Impacts
Construction Phase
7.9.1
With the exception of
N4, N5, N11, N13, N14, N18, N20B, N21, N23, N27, N28 & PN2, the
construction noise levels at other NSRs selected for construction noise impact
assessment are predicted to comply with the noise standards stipulated in the
EIAO-TM with the implementation of the proposed mitigation measures.
Residual impacts at these affected NSRs are summarised in Table 7.29. It should be noted that the tabulated residual noise levels
are the predicted noise levels assuming the NSRs with opened windows.
7.9.2
The on-site survey has
revealed that N4, N5, N11, N13, N23, N27 and N28 have already been noise
insulated with air-conditioners. With the provision of air-conditioners,
it is considered that the noise impact would be minimized by keeping the
windows closed during the construction activities. Notwithstanding this,
due to more stringent noise criterion of 65 dB(A), it is recommended that
particularly noisy construction activities, especially those associated with
the construction of subway at Choi Hung Road, district distributor road (D1),
local roads (L1, L2, L3, L4, L7, L8, L9, L11, L15, L16, L17 and L19), rebuild
Kai Tak Nullah, landscape elevated walkway (LW-02, LW-03 & LW-04), SCL
& CKR, should be scheduled to avoid examination periods of these NSRs as far
as practicable. The Contractor should liaise with the school
representative(s) to obtain the examination schedule so as to avoid noisy
construction activities during school examination period.
Table 7.29
Construction Noise Residual Impacts
NSR
|
Exceedance of the EIAO-TM
Criterion
|
Construction Activity Causing
Exceedance
|
Approximate duration of
Exceedance
|
65 dB(A)
|
70 dB(A)
|
N4
|
3
(Jul 2010 to Dec 2015)
|
0
|
l Local Roads L2, L3, L15 and associated footpaths
at North Apron;
l Local Roads L4; and
l SCL
|
Examination Period
|
N5
|
5
(Jul 2010 to Dec 2015)
|
0
|
l Local Roads L2, L3, L15 and associated
footpaths at North Apron;
l Local Roads L4; and
l SCL
|
Examination Period
|
N11
|
10
(Sept 2009 to Apr 2010 and Jul
2010 to Dec 2015)
|
5
(Jul 2010 to Dec 2015)
|
l Construction of Road D1
l Local Roads L1, L2, L3, L11, L15 and
associated footpaths at North Apron
l Drainage, Sewerage & Watermain
l Construction of Footbridge at Rhythm Garden
(LW-04)
l Rebuild Kai Tak Nullah
l Construction of Landscape Walkway LW-02
l SCL
|
66 month include examination
period
|
N13
|
9
(Sept 2009 to Apr 2010 and Jul
2010 to Dec 2015)
|
4
(Jul 2010 to Dec 2015)
|
l Construction of Road D1
l Local Roads L1, L2, L3, L11, L15 and
associated footpaths at North Apron
l Drainage, Sewerage & Watermain
l Construction of Footbridge at Rhythm Garden
(LW-04)
l Construction of Landscape Walkway LW-03
l Underground Shopping Street (SB-01)
l Upgrading of Pumping Station PS1
l Rebuild Kai Tak Nullah
l Construction of Landscape Walkway LW-02
l SCL
|
66 month include examination
period
|
N23
|
21
(Jan 2012 to Dec 2016)
|
16
(Jan 2015 to Dec 2016)
|
l Construction of Local Road L17 (Jan 2015 to
Dec 2016)
l CKR (Jan 2012 to Dec 2016)
|
24 month include examination
period
|
N27
|
3
(Jan 2015 to Dec 2016)
|
0
|
l Construction of local road L19
|
Examination Period
|
N28
|
5
(Jan 2015 to Dec 2016)
|
0
|
l Construction of local road L19
|
Examination Period
|
|
NSR
|
Exceedance of the EIAO-TM
Criterion
|
Construction Activity Causing
Exceedance
|
Approximate duration of
Exceedance
|
75 dB(A)
|
N14
|
2
(Jan 2015 to Dec 2015)
|
l Construction of Road D1, L7, L8, L9 & L16
l Underground Shopping Street (SB-01)
|
12 month
|
N18
|
1
(Jan 2015 to July 2015)
|
l SCL
|
7 month
|
N20B
|
3
(Jan 2012 to Dec 2016)
|
l CKR
|
60 month
|
N21
|
3
(Jan 2012 to Dec 2016)
|
l CKR
|
PN2
|
11
(Oct 2012 to Dec 2015)
|
l SCL
|
39 month
|
7.9.3
For the N18, N20B, N21
& PN2, the exceedance is due to the CKR and SCL projects. In this
assessment, it has been assumed that all PME items are operating and gathered
within a worksite for a conservative assessment. There are uncertainties
on the prediction of construction noise impact from CRK and SCL since the
detailed construction method and arrangement of PME items are not available during
the course of this EIA study. Therefore, the detailed mitigation measures
and duration of residual impact would be subject to the detailed construction
programme and activities of the respective projects. Furthermore, both
the proposed CKR and SCL projects are Schedule 2 designated projects under the
EIAO. The associated environmental impacts will be adequately addressed
in further detailed EIA studies to be prepared and submitted under the EIAO by
the respective project proponents.
7.9.4
In addition to the
above-mentioned mitigation measures, the good site practices listed below shall
be adopted by all the contractors to further ameliorate the noise
impacts. Although the noise mitigating effects are not easily
quantifiable and the benefits may vary with the site conditions and operating
conditions, good site practices are easy to implement and do not impact upon
the works schedule.
·
Only well-maintained
plant should be operated on-site and plant should be serviced regularly during
the construction program.
·
Mobile plant, if any,
should be sited as far away from NSRs as possible.
·
Machines and plant
(such as trucks) that may be in intermittent use should be shut down between
works periods or should be throttled down to a minimum.
·
Plant known to emit
noise strongly in one direction should, wherever possible, be orientated so
that the noise is directed away from the nearby NSRs.
·
Material stockpiles and
other structures should be effectively utilised, wherever practicable, in
screening noise from on-site construction activities.
7.9.5
During school
examination periods, the daytime construction noise criterion is 65dB(A) which
is lower than the normal daytime school criterion of 70dB(A). Scheduling
of construction works outside school examination period to less intrusive
periods would definitely reduce the overall noise impacts at the NSRs and for
ensuring compliance with the construction noise criterion at some of the
NSRs. The Contractor shall liaise with the school representative(s) to
obtain the examination schedule and avoid noisy construction activities during
school examination period.
Operational Phase
7.9.6
With the proposed noise
mitigation measures in place, the ‘New’ road noise contributions to the overall
noise levels at all representative NSRs would be less than 1.0 dB(A) and the
‘New’ road noise levels would all be below the relevant noise criteria.
No adverse noise impacts arising from the ‘New’ roads would be predicted
at any of the representative NSRs. Noise exceedances at the
representative NSRs, if any, would be due to the existing roads. The
effectiveness of direct mitigation measures, in terms of the number of
residential dwellings and classrooms that will either be protected or benefited
(by at least 1 dB(A)), has been shown in Appendix 3.29.
7.9.7
Residual fixed plant
noise impacts are not anticipated. In order to ensure compliance of the operational
noise level with the stipulated noise standards in TM, noise commissioning
tests for all major fixed noise sources should be included in the Contract
Document.
7.9.8
No residual noise
impact from Open Air Entertainment Activities, proposed heliport and rail noise
would be expected.
7.10
Environmental Monitoring and Audit
Construction Phase
7.10.1 An EM&A programme is recommended
to be established according to the expected occurrence of noisy activities.
All the recommended mitigation measures for daytime normal working
activities should be incorporated into the EM&A programme for
implementation during construction. Details of the programme are provided
in the EM&A Manual.
Operational Phase
7.10.2 The assessment has indicated that
the noise from fixed plant noise would comply with the EIAO-TM standards.
As part of the design process, however, monitoring of operational noise
from the proposed fixed plants during the testing and commissioning stage would
be recommended to verify the maximum sound power levels as suggested in this
EIA.
7.10.3 No adverse noise impact from
operation of the Project is anticipated, therefore, no environmental monitoring
and audit is proposed.
7.11
Summary
7.11.1 This assessment has predicted the
construction noise impacts of the Project during normal daytime working hours,
taking into account other expected concurrent projects. The predicted
unmitigated noise levels would range from 42 to 92 dB(A) at the representative
NSRs. With the use of quiet PME, movable barriers and temporary barriers,
the noise levels at the NSRs selected for construction noise impact assessment
except NSRs N4, N5, N11, N13, N14, N18, N20B, N21, N23, N27, N28 & PN2
would comply with the construction noise standard.
7.11.2 Having exhausted practicable noise
mitigation measures, NSRs N4, N5, N11, N13, N14, N18, N20B, N21, N23, N27, N28
& PN2 would exceed the noise criteria. However, some of these affected
NSRs are schools (N4, N5, N11, N13, N23, N27 and N28) and they all have been
noise insulated with air conditioners. By keeping the windows closed
during construction activities, noise impacts at the indoor environment of
these NSRs can be avoided. Notwithstanding this, it is recommended that
the particularly noisy construction activities should be scheduled to avoid
examination periods of these NSRs as far as practicable.
7.11.3 This impact assessment does indicate
some noise exceedances for limited periods of time even with the consideration
of all practicable mitigation measures. During the actual construction
period, as much as practically possible should be done to reduce the
construction noise, and on-going liaison with all concerned parties and site
monitoring should also be conducted during the course of the construction
period.
7.11.4 A construction noise EM&A
programme is recommended to check the compliance of the noise criteria during
normal daytime working hours.
7.11.5
The potential road
traffic noise impacts have been assessed based on the worst case traffic flows
in 2031. Without any noise mitigation measures in place, the predicted
noise levels at the NSRs would range from 40 to 87 dB(A). Practicable traffic
noise mitigation measures are therefore formulated for the planned NSRs with
predicted noise levels exceeding the EIAO-TM traffic noise criteria.
7.11.6 Mitigation measures in the form of structural
fins, low noise surfacing, special building design and building setback are
proposed to mitigate the traffic noise impacts at Sites 1B1, 1I1, 1L2, 1L3, 2B6
& 5A4 and ex-San Po Kong Flatted Factory. The potential traffic noise
impact at these sites are contributed by both existing and ‘New’ roads.
With the proposed noise mitigation measures, the predicted overall noise levels
at these NSRs would comply with the noise criterion.
7.11.7 For those noise sensitive uses
located within the planned sites of commercial, mixed use, and hospital /
clinic, it is recommended that the noise sensitive uses should either be
located away from the traffic-noise affecting facades of the site or, as the
last resort, the sensitive uses should be noise insulated with air-conditioners
to avoid unacceptable traffic noise impacts from the surrounding road
network. For Site 1E1, 1F1, 3D2 to 3D4 and 3E1, the land use allows
domestic uses which will require planning permission from the Town Planning
Board. These planning applications should include assessments on the
traffic noise impact to demonstrate that the proposed development would not
result in adverse impact for the development.
7.11.8 For school sites 1A2, 1A3, 1A4, 1B2,
1B3 & 1B4, the layout of these planned schools should be arranged in a way
to avoid the sensitive facades of the classrooms facing Roads L2, L3 and L4, or
as the last resort all the classrooms should be noise insulated with
air-conditioners to avoid unacceptable traffic noise impacts from the
surrounding road network.
7.11.9 For those affected existing NSRs,
the ‘New’ road noise contributions to the overall noise levels would be less
than 1.0 dB(A) and the ‘New’ road noise levels would all be below the relevant
noise criteria, although the overall noise levels would still exceed the
relevant noise criteria. However, it should be noted that such noise
exceedances at the representative NSRs are due to the existing roads.
Hence, direct mitigation measures on ‘New’ roads are not required as they would
not be effective in improving the noise environment at the sensitive receivers.
7.11.10 Operational noise impacts from fixed plant
noise can be effectively mitigated by implementing noise control treatment at
source during the design stage and residual operational noise impacts are not
anticipated. The need for noise measurement during commissioning of fixed
noise sources should be included in the Contract Document.
7.11.11 Noise impacts from Open Air Entertainment
Activities, namely those from the proposed main stadium, can be effectively
mitigated by installation of retractable roof or the main stadium could
consider a fixed roof design. With proper design measures, the noise
impact due to the activities to be held in the main stadium is not likely to be
significant.
7.11.12 The distance between the proposed helipad and
the nearest planned residential NSR at Site 4B5 is about 700 m with an
estimated Lmax level of 80dB(A) at this NSR. Therefore, it is considered
that the proposed helipad locations would comply with the helicopter noise
criteria at the nearest NSRs and adverse helicopter noise impact would not be
anticipated.
7.11.13 With the implementation of practicable noise
mitigation measures and/or a buffer distance of not less than 10m between the
proposed Environmental Friendly Transportation Link (EFTS) (if decided to be a
railway form in the future) and the nearby NSRs, adverse rail noise impacts at
the NSRs would not be anticipated. Example of practicable noise
mitigation measures including those adopted in Ma On San (MOS) Rail namely the
use of multi-plenum system and vertical noise barrier at the all elevated
sections of the alignment on viaduct.
7.11.14 The operation activities of the marine traffic
noise (include noise from typhoon shelters) may vary with the composition and
type of the vessels. The potential noise impact is likely coming from the
engine noise and operation activities of individual vessel in operation.
It is similar to noise from public place which vessels are free to move around
and implementation control measures are not possible. Nevertheless, given
the large separation distance between the typhoon shelters and the nearby NSRs,
the noise level from the marine traffic noise (include noise from typhoon
shelters) at the NSRs would be minimal.