Agreement No. CE 35/2006(CE)
Kai Tak Development
Engineering Study
cum Design and Construction of Advance
Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Impact Assessment Report
Contents
9............ WASTE
MANAGEMENT Implications. 9-1
9.1 Introduction. 9-1
9.2 Environmental Legislation, Policies, Plans,
Standards and Criteria. 9-1
9.3 Assessment Methodology. 9-2
9.4 Identification of Key Environmental Impacts. 9-2
9.5 Mitigation of Environmental Impacts. 9-2
9.6 Evaluation of Residual Environmental Impacts. 9-2
9.7 Environmental Monitoring and Audit 9-2
9.8 Summary. 9-2
Lists of Tables
Table
9.1(a)
Summary of Estimated Dredged Marine Sediment 9-2
Table
9.1(b)
Summary of Estimated Maintenance Dredging Project 9-2
Table
9.2a
Summary of Estimated C&D Material
9-2
Table
9.2a
Summary of Estimated C&D Material (Con’t) 9-2
Table
9.2b
Schedule of Quantities of C&D Materials Generated
9
WASTE MANAGEMENT
Implications
9.1
Introduction
9.1.1
This section identifies
the types of solid wastes that are likely to be generated during the
construction and operational phases of the Project and evaluates the potential
environmental impacts that may result from these wastes. During
construction phase, the main solid waste issues would be related to dredged
marine sediment and construction and demolition (C&D) material generated
from dredging operations, demolition of the remaining structures, and various
civil works for the construction of buildings and infrastructure within the
Project boundary. During operational phase of the Project, the major
solid wastes are municipal wastes generated from different land uses within the
development.
9.2
Environmental Legislation, Policies, Plans,
Standards and Criteria
9.2.1
The criteria and
guidelines for assessing waste management implications are set out in Annex 7
and Annex 15 of the Technical Memorandum on Environmental Impact Assessment
Ordinance (EIAO-TM), respectively.
9.2.2
The following
legislation relates to the handling, treatment and disposal of wastes in the
Hong Kong SAR and has been used in assessing potential impacts:
·
Waste Disposal
Ordinance (Cap. 354)
·
Waste Disposal
(Chemical Waste) (General) Regulation (Cap. 354)
·
Land (Miscellaneous
Provisions) Ordinance (Cap. 28)
·
Public Health and
Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of
Nuisances Regulation
·
Waste Disposal (Charges
for Disposal of Construction Waste) Regulation (Cap. 354N)
·
Dumping at Sea
Ordinance (Cap. 466)
Waste Management
9.2.3
The Waste Disposal
Ordinance (WDO) prohibits the unauthorised disposal of wastes. Construction
waste is defined as any substance, matter or thing that is generated from
construction work and abandoned, whether or not it has been processed or
stockpiled before being abandoned, but does not include any sludge, screenings
or matter removed in or generated from any desludging,
desilting or dredging works. Under the WDO,
wastes can be disposed of only at designated waste disposal facilities.
9.2.4
Under the WDO, the
Chemical Waste (General) Regulation (1992) provides regulations for chemical
waste control, and administers the possession, storage, collection, transport
and disposal of chemical wastes. The Environmental Protection Department
(EPD) has also issued a guideline document, the Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes (1992), which details
how the Contractor should comply with the regulations on chemical wastes.
9.2.5
The Public Cleansing
and Prevention of Nuisances Regulation provides control on illegal tipping of
wastes on unauthorised (unlicensed) sites.
Dredged Marine Sediment
9.2.6
The ETWB TCW No.
34/2002 sets out the procedure for seeking approval to dredge / excavate
sediment and the management framework for marine disposal of dredged / excavated
sediment. This Technical Circular outlines the requirements to be
followed in assessing and classifying the sediment and explains the marine
disposal arrangement for the classified material.
9.2.7
Dumping permits from
EPD are required in accordance with the Dumping at Sea Ordinance for marine
disposal of dredged materials.
Chemical Waste
9.2.8
Under the Waste
Disposal (Chemical Waste) (General) Regulations, all producers of chemical
waste must register with EPD and treat their wastes, either utilising on-site
plant licensed by EPD, or arranging for a licensed collector to transport the
wastes to a licensed facility. The regulation also prescribes the storage
facilities to be provided on site, including labelling and warning signs, and
requires the preparation of written procedures and training to deal with
emergencies such as spillages, leakages or accidents arising from the storage
of chemical wastes.
Construction and Demolition (C&D) Materials
9.2.9
The current policy
related to the disposal of C&D material is documented in the Works Branch
Technical Circular No. 2/93, ‘Public Dumps’. Construction and demolition
materials that are wholly inert, namely public fill, should not be disposed of
to landfill, but taken to public filling areas, which usually form part of
reclamation schemes. The Land (Miscellaneous Provisions) Ordinance
requires that dumping licences be obtained by individuals or companies who
deliver public fill to public filling areas. The Civil Engineering and
Development Department (CEDD) issues the licences under delegated powers from
the Director of Lands.
9.2.10 Under the Waste Disposal (Charges
for Disposal of Construction Waste) Regulation, enacted in January 2006,
construction waste delivered to a landfill for disposal must not contain more
than 50% by weight of inert material. Construction waste delivered to a
sorting facility for disposal must contain more than 50% by weight of inert
material, and construction waste delivered to a public fill reception facility
for disposal must consist entirely of inert material. In accordance with
the Environment, Transport and Works Bureau (ETWB) TCW No. 31/2004 “Trip Ticket
System for Disposal of Construction and Demolition Materials”, for all
contracts that are expected to generate inert C&D materials (e.g. soil,
broken rock, broken concrete and building debris etc.) requiring disposal from
the site, the project office shall write to the Public Fill Committee (PFC)
through the Secretary of the PFC to request a designated disposal ground for
incorporation into the tender documents. For contracts where the
estimated amount of non-inert C&D materials requiring disposal at landfill
facilities equal or exceed 50m3, the project office shall seek
confirmation from the Director of Environmental Protection (DEP) as to whether
landfill facilities will be available for disposal of such materials. The
DEP will designate landfill facilities, if available, for the contract.
Where the estimated amount of non-inert C&D materials to be generated from
the contract is less than 50m3, the project office is not required
to apply to DEP for designated landfill facilities. However, the project
office should still specify in the tender documents appropriate landfill
facilities (e.g. Outlying Islands Transfer Facilities managed by the EPD, SENT
Landfill at Tseung Kwan O, NENT Landfill at Ta Kwu Ling and WENT Landfill at Nim
Wan).
9.2.11 Measures have been introduced under
ETWB TCW No. 33/2002, “Management of Construction and Demolition Material
Including Rock” to enhance the management of construction and demolition
material, and to minimize its generation at source. The enhancement measures
include: (i) drawing up a Construction and Demolition
Material Management Plan (C&DMMP) at the feasibility study or preliminary
design stage to minimize C&D material generation and encourage proper
management of such material; (ii) vetting of the C&DMMP prior to upgrading
of the project to Category A in the Public Works Programme; and (iii) providing
the contractor with information from the C&DMMP in order to facilitate him
in the preparation of the Waste Management Plan (WMP) and to minimize C&D
material generation during construction. Projects generating C&D material
less than 50,000m3 or importing fill material less than 50,000m3
are exempt from the C&DMMP. The new ETWB TCW No. 19/2005
“Environmental Management on Construction Sites” includes procedures on waste
management requiring contractors to reduce the C&D material to be disposed
of during the course of construction. Under ETWB TCW No. 19/2005, the
contractor is required to prepare and implement an Environmental Management
Plan (EMP) and the WMP becomes part of the EMP. Besides, ETWB TCW
No.31/2004 “Trip Ticket System for Disposal of Construction and Demolition
Materials” promulgates the latest trip ticket system for public works contracts
including capital works contracts, term contracts and design and build
contracts, where C&D materials including waste generated on site require
disposal.
9.3
Assessment Methodology
Construction Phase
9.3.1
The criteria for
assessing waste management implications are outlined in Annex 7 of the
EIAO-TM. The methods for assessing potential waste management impacts
during the construction phase of the Project follow those presented in Annex 15
of the EIAO-TM and include the following:
·
Estimation of the types
and quantities of the wastes generated.
·
Assessment of potential
impacts from the management of solid waste with respect to potential hazards,
air and odour emissions, noise, wastewater discharge
and transport.
·
Assessment of impacts
on the capacity of waste collection, transfer and disposal facilities.
Operational Phase
9.3.2
The quantity of
domestic waste generation during the operational phase was estimated from the
population, land uses and the program of the proposed development. A
capita disposal rate of domestic waste was adopted for estimate waste
generation. According to “Monitoring of Solid Waste in Hong
Kong 1999 prepared by EPD”, the per capita disposal rate of
domestic waste in 2016 is 1.48 kg/person /day.
9.3.3
The commercial and industrial (C&I) waste
generated from the passengers at the proposed Cruise Terminal and employee from
the commercial activities are the other sources of waste generation. The
quantity of waste arising was estimated using the latest available information
on the planned employment population at the time of reporting. A
projected generation rate of C&I waste of 0.58 kg/person/day was adopted
for the assessment, as forecasted in the Monitoring of Solid Waste in Hong Kong
1999 prepared by EPD.
9.4
Identification of Key Environmental Impacts
Construction Phase
9.4.1
The construction phase
activities to be carried out for the proposed Project would generate a variety
of wastes that can be divided into distinct categories based on their composition
and ultimate method of disposal. The identified waste types
include:
·
Dredged marine sediment
·
C&D material
·
Chemical waste
·
General refuse
9.4.2
Each type of waste arising
is described below, together with an evaluation of the potential environmental
impacts associated with the generation, handling, storage and transport of the
waste.
Dredged Marine Sediment
Cruise Terminal
9.4.3
Dredged marine sediment
would be generated from the dredging of the seabed to provide the manoeuvring
basin for the cruise terminal. Environmental impacts of dredged marine
sediment have been addressed in the approved EIA Report on Dredging Works for
Proposed Cruise Terminal at Kai Tak (EIAO Register
No. AEIAR-115/2007) (CT Dredging EIA) and are extracted below.
9.4.4
The total volume of
dredged sediment generated from the dredging of the seabed to provide the
manoeuvring basin for the cruise terminal is estimated to be approximately 1.38
Mm3 during construction phase. Based on the results of the
chemical and biological screening, approximately 430,000 m3 was
classified as contaminated dredged sediment (Category M and H) requiring Type 1
– Open Sea Disposal (Dedicated Sites) or Type 2 - Confined Marine Disposal, and
approximately 950,000 m3 was classified as Category L sediment
suitable for Type 1 - Open Sea Disposal in accordance with ETWB TCW No.
34/2002.
9.4.5
The total volume of
dredged sediment generated from maintenance dredging during operational phase
is estimated to be approximately 350,000 m3 every 5 to 10
years. Prior to any maintenance dredging, sediment sampling and testing
will be carried out in accordance with the ETWB TCW No. 34/2002 to determine
the contamination level of the dredged sediment. The most appropriate
open sea or confined marine disposal site will be allocated for proper disposal
of the dredged sediment on the basis of the chemical and biological test
results in accordance with the ETWB TCW No. 34/2002.
9.4.6
The dredging rationale
for the dredging works for the proposed cruise terminal has been submitted and
accepted by the Secretary of Marine Fill Committee (see Appendix 9.1) prior to
the approval of the CT Dredging EIA. As stated in the approved CT
Dredging EIA, it will be the responsibility of the contractor to satisfy the
appropriate authorities that the contamination levels of the marine sediment to
be dredged have been analysed and recorded. According to the ETWB TCW No.
34/2002, this will involve the submission of a formal Sediment Quality Report
to DEP, prior to the dredging contract being tendered. The project
proponent and his contractor for the dredging works shall apply for allocation
of marine disposal sites and all necessary permits from relevant authorities
for the disposal of dredged sediment.
Runway Opening
9.4.7
Opening a 600m wide gap
at the northern end of the former Kai
Tak Airport runway was considered under the
KTPR as a potential mitigation measure to improve the water circulation and
water quality in Kai Tak Approach Channel. The
opening would be covered by a piled deck. Demolition of existing runway
will involve excavation of bulk fill and dredging to about -6.5mPD. The
proposed construction method adopts an approach where the existing seawall at
the runway will not be removed until completion of all excavation and dredging
works for demolition of the runway. Thus, excavation of bulk fill
material will be carried out behind the existing seawall and the estimated
C&D materials from land-based excavation are presented in Section 9.4.24
below. Dredging will be required to remove the built up sediment along
the existing seawalls at the gap opening location prior to the removal of the
seawall facing the To Kwa Wan Typhoon Shelter
(TKWTS). The dredging volume involved is estimated to be about 3,200 m3.
9.4.8
In accordance with the
ETWB TCW No. 34/2002, Management of Dredged / Excavated Sediment, sediments are
classified into Category L, M and H according to the concentration of the
contaminants. With reference to the approved EIA Report of the
Comprehensive Feasibility Study for the Revised Scheme of South East Kowloon
Development (SEKDCFS EIA) (EIAO Register No. AEIAR-044/2001), sediment sampling
and analysis had been carried out in the vicinity of the To Kwa
Wan Typhoon Shelter (TKWTS), Kwun Tong Typhoon
Shelter (KTTS), and Kai Tak Approach Channel (KTAC).
9.4.9
From the results of the
SEKDCFS EIA, the sediment samples collected from the 2 locations near the
seawall of proposed gap opening facing TKWTS (sampling locations KB6 and KB7)
were all classified as Category H material. In view of the proximity of
the proposed dredging areas to these 2 sampling locations, it is likely that
the dredged sediments from the proposed dredging areas along the seawalls would
also be highly contaminated. These sediments must be dredged and transported
with great care in accordance with ETWB TCW No. 34/2002.
9.4.10 The dredging rationale together with
the estimated dredged sediment quantity for the dredging works for the proposed
runway opening was approved by the Marine Fill Committee in August 2008 (see Appendix 9.2).
The dredged contaminated sediment must be effectively isolated from the
environment upon final disposal and shall be disposed of at the disposal
site(s) to be allocated by MFC.
9.4.11 It will be the responsibility of the
dredging contractor to satisfy the appropriate authorities that the
contamination levels of the marine sediment to be dredged have been analysed
and recorded. According to the ETWB TCW No. 34/2002, this will involve
the submission of a formal Sediment Quality Report (SQR) by the project
proponent to the DEP, prior to the dredging contract being tendered. The
project proponent and his contractor for the dredging works shall apply for
allocation of marine disposal sites and all necessary permits from relevant
authorities for the disposal of dredged sediment.
Localized Maintenance Dredging of KTAC
9.4.12 As part of the odour mitigation measures
for KTAC, it is proposed to carry out localized maintenance dredging around the
discharge locations of KTN and JVC, and along the seawall of the runway facing
KTAC. The purpose of the localized maintenance dredging to remove the
most odorous sediment deposited around the KTN and JVC discharge
locations. The dredging will also provide at least 3.5m water depth over
the entire KTAC so that the odour emissions from the sediment could be
suppressed by the water column above. The dredging volume involved is
estimated to be about 120,000 m3.
9.4.13 From the results of the SEKDCFS EIA,
the sediment samples collected from all the 7 locations at KTAC (sampling
locations AC1 to AC7) were all classified as Category H material. In view
of the proximity of the proposed localised dredging areas to these sampling
locations, it is likely that the dredged sediments from the proposed dredging
areas in KTAC would also be highly contaminated. These sediments must be
dredged and transported with great care in accordance with ETWB TCW No.
34/2002.
9.4.14 The dredging rationale together with
the estimated dredged sediment quantity for the localised maintenance dredging
at KTAC was approved by the Marine Fill Committee in August 2008 (see Appendix 9.2).
The dredged contaminated sediment must be effectively isolated from the
environment upon final disposal and shall be disposed of at the disposal
site(s) to be allocated by MFC.
9.4.15 It will be the responsibility of the
dredging contractor to satisfy the appropriate authorities that the
contamination levels of the marine sediment to be dredged have been analysed
and recorded. According to the ETWB TCW No. 34/2002, this will involve the
submission of a formal SQR by the project proponent to the DEP, prior to the
dredging contract being tendered. The project proponent and his
contractor for the dredging works shall apply for allocation of marine disposal
sites and all necessary permits from relevant authorities for the disposal of
dredged sediment.
Public Landing Steps cum Fireboat Berth
9.4.16 A section of about 100m of the
existing seawall at the former Kai
Tak Airport runway will need to be
re-constructed for the proposed public landing steps cum fireboat berth under
KTD. Seawall reconstruction would involve excavation and dredging at and
near the existing seawall of the runway. The estimated volume of dredged
sediment generated from this activity would be approximately 600m3
9.4.17 In accordance with the ETWB TCW No.
34/2002, Management of Dredged / Excavated Sediment, sediments are classified
into Category L, M and H according to the concentration of the
contaminants. A Sediment Sampling and Testing Plan (SSTP) for two
sampling locations in the vicinity of the proposed public landing steps cum
fireboat berth (namely sampling locations VC1 and VC2) has been prepared and
accepted by EPD as per EIA Study Brief No. ESB 152/2006 S.3.4.7.6(k) and
S.3.4.9.2(iii) (Annex 18.4). Marine site investigation was then
carried out in accordance with the accepted SSTP in April and May 2007.
The chemical testing laboratory results (Appendix 9.3) indicates
that the sediments samples collected at the two sampling locations were
classified as Category L material. That is, all sediment samples are with
all contaminant levels not exceeding the Lower Chemical Exceedance
Level (LCEL). The materials must be dredged, transported and disposed of
in a manner, which minimizes the loss of contaminants either into solution or
by resuspension.
9.4.18 The dredging rationale together with
the estimated dredged sediment quantity for the public landing steps sum
fireboat berth was approved by the Marine Fill Committee in August 2008 (see Appendix 9.2). It
will be the responsibility of the dredging contractor to satisfy the appropriate
authorities that the contamination levels of the marine sediment to be dredged
have been analysed and recorded. According to the ETWB TCW No. 34/2002,
this will involve the submission of a formal SQR by the project proponent to
the DEP, prior to the dredging contract being tendered. The project
proponent and his contractor for the dredging works shall apply for allocation
of marine disposal sites and all necessary permits from relevant authorities
for the disposal of dredged sediment.
Immersed Tunnel Sections of Road T2 and CKR
9.4.19 The CKR and Road T2 will join up to
provide an east-west road link across Kowloon,
from Tseung Kwan O in the east to West
Kowloon in the west. Road T2 includes an immersed tube
section from Cha Kwo Ling to the South Apron area of
the former airport. The road is then at-grade connecting to CKR near the
north end of the former runway. The CKR then enters a short section of
immersed tube in inner Kowloon
Bay before entering a
tunnel beneath To Kwa Wan. Both the immersed
tube sections of Road T2 and CKR will require dredging. The estimated volume of
dredged sediment generated from these two activities would be approximately
2,620,000 m3 in total (2,260,000 m3 for T2 and 360,000 m3
for CKR) which are subject to the actual construction methods to be adopted.
9.4.20 From the results of the SEKDCFS EIA,
the sediment samples collected from the 4 locations near the proposed alignment
of the T2 tunnel (sampling locations KT1, KT2, KT3 and KT4) and the 2 locations
near the proposed alignment of the CKR tunnel (sampling locations KB3 and KB6)
were all classified as Category H material. In view of the proximity of
the proposed dredging areas to these 6 sampling locations, it is likely that
the dredged sediments from the proposed dredging areas along the proposed
alignment of the immersed tunnels would also be highly contaminated.
These sediments must be dredged and transported with great care in accordance
with ETWB TCW No. 34/2002.
9.4.21 The dredging rationale together with
the estimated dredged sediment quantity for the immersed tunnel sections of
Road T2 and CKR was approved by the Marine Fill Committee in August 2008. The
dredged contaminated sediment must be effectively isolated from the environment
upon final disposal and shall be disposed of at the disposal site(s) to be
allocated by MFC.
9.4.22 It will be the responsibility of the
dredging contractor to satisfy the appropriate authorities that the
contamination levels of the marine sediment to be dredged have been analysed
and recorded. According to the ETWB TCW No. 34/2002, this will involve
the submission of a formal SQR by the project proponent to the DEP, prior to
the dredging contract being tendered. The project proponent and his contractor
for the dredging works shall apply for allocation of marine disposal sites and
all necessary permits from relevant authorities for the disposal of dredged
sediment.
Relocation of the Hong Kong China Gas (HKCG)
Submarine Gas Main
9.4.23 An existing twin 400mm diameter
submarine gas mains is located to the west of the former Kai
Tak Airport runway which serves as a strategic gas supply
to Hong Kong Island. Since a section of the submarine gas
mains would fall within the manoeuvring area of the proposed second berth of
the Cruise Terminal, according to the HKCG diversion schedule, gas mains will
be carried out between 2010 to 2012 in order to cater
for the dredging works for the Cruise Terminal. The tentative
alignment of the new submarine gas main is indicated in Figure 9.1, which is
in a preliminary stage and subject to further investigation and studies to
confirm its feasibility and exact location. The estimated volume of dredged sediment
generated from the dredging works for the new submarine gas main in would be
approximately 442,000 m3.
9.4.24 From the results of the SEKDCFS EIA,
the sediment samples collected from the 3 locations near the proposed alignment
of the new HKCG submarine gas mains (sampling locations KB3, KB4 and KB5) were
all classified as Category H material. In view of the proximity of the
proposed dredging area to these 3 sampling locations, it is likely that the
dredged sediments from the proposed dredging area for the new HKCG submarine
gas mains would also be highly contaminated. These sediments must be
dredged and transported with great care in accordance with PNAP 252.
9.4.25
The dredging rationale
together with the estimated dredged sediment quantity for the new submarine gas
mains was submitted to the Secretary of Marine Fill Committee in July 2007. The
dredged contaminated sediment must be effectively isolated from the environment
upon final disposal and shall be disposed of at the disposal site(s) to be
allocated by MFC.
9.4.26
It will be the
responsibility of the dredging contractor to satisfy the appropriate
authorities that the contamination levels of the marine sediment to be dredged
have been analysed and recorded. According to the ETWB TCW No. 34/2002,
this will involve the submission of a formal Sediment Quality Report (SQR) by
the project proponent to the DEP, prior to the dredging contract being
tendered. The project proponent and his contractor for the dredging works shall
apply for allocation of marine disposal sites and all necessary permits from
relevant authorities for the disposal of dredged sediment.
9.4.27
The estimated volume of
dredged marine sediment generated from the above dredging activities are
summarized in Table 9.1(a) & Table 9.1(b). The location /
extent of the proposed dredging works are shown in Figure 9.1.
Table
9.1(a)
Summary of Estimated Dredged Marine Sediment
Projects
|
Disposal Site
|
Estimated Quantity and Category
|
Cruise
terminal
(Manoeuvring
basin)
|
Type 1 – Open
Sea Disposal – gazetted
marine disposal ground allocated by MFC
|
· 950,000 m3 Category L
|
Type 1 – Open
Sea Disposal (Dedicated
Sites) or Type 2 – Confined Marine Disposal, to be allocated by MFC
|
· 430,000 m3 Category M and H
|
600m
runway opening
|
Subject to final allocation of the disposal sites by MFC
|
· 3,200 m3 Category H
|
Localized
maintenance dredging of KTAC
|
· 120,000 m3 Category H
|
Public
landing step cum fireboat berth
|
· 600 m3 Category L
|
Immersed
tunnel section of Road T2 (including the dredging required for the associated
reconstruction of a section of the existing Kwun
Tong Submarine Outfall)
|
· 2,260,000 m3 Category H
|
Immersed
tunnel section of CKR
|
· 360,000 m3 Category H
|
Relocation
of the Hong Kong China Gas
Submarine Main
|
·
442,000 m3 Category H
|
|
|
Total:
4,565,800 m3
|
Table
9.1(b)
Summary of Estimated Maintenance Dredging Project
Projects
|
Disposal Site
|
Estimated Quantity and Frequency
|
Cruise
terminal
(Maintenance
Dredging Project )
|
Subject to final allocation of the disposal sites by MFC
|
· 350,000 m3 every 5 to 10 years
|
Construction and
Demolition Materials
9.4.28
Construction and
demolition (C&D) material arising from construction activities such as site
clearance, excavation works, demolition of 600m runway opening, Trunk Road T2,
Kai Tak Nullah modification
works, site formation and various civil works for the construction of buildings
and infrastructure within the Project boundary. The inert materials would be
re-used on-site or in other projects as far as possible and delivered to the
public fill reception facilities or other designated sites as advised by the
Secretary of Public Fill Committee as the last resort. The estimated
quantity of C&D material generated and reused from major construction
activities are summarized in Table 9.2a. The schedule of quantities of
C&D material generated is shown in Table 9.2b.
Table 9.2a
Summary of Estimated C&D Material
Projects
|
Estimated Quantity
|
Reused Quantity
|
Disposal Site (Landfill or Public
Fill)
|
600m runway opening
|
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
130,000 m3
|
46,000 m3
|
Grade III or below rock
|
-
|
-
|
Insert soft C&D materials
|
1,860,000 m3
|
929,000 m3
|
Sub-total
|
1,990,000 m3
|
975,000 m3
|
Trunk Road T2
|
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
18,000 m3
|
18,000 m3
|
Grade III or below rock
|
-
|
-
|
Insert soft C&D materials
|
485,000 m3
|
185,000 m3
|
Sub-total
|
503,000 m3
|
203,000 m3
|
Kai Tak
Nullah modification works
|
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
-
|
-
|
Grade III or below rock
|
-
|
-
|
Insert soft C&D materials
|
600,000 m3
|
300,000 m3
|
Sub-total
|
600,000 m3
|
300,000 m3
|
Site Formation cum Marine
Works for Cruise Terminal
|
|
|
Inert C&D material to be
disposed off-site to the designated public fill reception facility, C&D
material should be reused as far as practicable
|
Grade II or above rock
|
58,000 m3
|
52,000 m3
|
Grade III or below rock
|
211,000 m3
|
148,000 m3
|
Insert soft C&D materials
|
689,000 m3
|
37,000 m3
|
Sub-total
|
958,000 m3
|
237,000 m3
|
Central Kowloon Route (depressed
road and tunnel sections in North Apron)
|
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
-
|
-
|
Grade III or below rock
|
-
|
-
|
Insert soft C&D materials
|
304,000 m3
|
66,000 m3
|
Sub-total
|
304,000 m3
|
66,000 m3
|
Shatin to Central Link
(To Kwa Wan Station and the Kai Tak
Station)
|
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
-
|
-
|
Grade III or below rock
|
-
|
-
|
Insert soft C&D materials
|
717,000 m3
|
282,000 m3
|
Sub-total
|
717,000 m3
|
282,000 m3
|
Table
9.2a
Summary of Estimated C&D Material (Con’t)
Public landing steps cum
fireboat berth
|
|
665,200 m3
|
Public fill / on-site reuse
|
Grade II or above rock
|
530 m3
|
Grade III or below rock
|
8,590 m3
|
Insert soft C&D materials
|
67,880 m3
|
Sub-total
|
77,000 m3
|
New sewage pumping stations
serving the planned Kai Tak Development (including
PS 6)
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
-
|
Grade III or below rock
|
-
|
Insert soft C&D materials
|
54,000 m3
|
Sub-total
|
54,000 m3
|
Decommissioning of the
remaining parts of the former Kai
Tak Airport and decommissioning of the
south apron area
|
|
Landfill / public fill
|
Grade II or above rock
|
-
|
Grade III or below rock
|
-
|
Insert soft C&D materials
|
43,250 m3
|
Sub-total
|
43,250 m3
(9,500 m3
for demolition of ex-GFS
Building
5,000 m3
for demolition of ASDE radar tower
28,750 m3
for decommissioning and decontamination of the south apron)
|
New Distributor Roads Serving
the Planned KTD
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
-
|
Grade III or below rock
|
-
|
Insert soft C&D materials
|
2,217 m3
|
Sub-total
|
2,217 m3
|
Other miscellaneous works
|
|
Public fill / on-site reuse
|
Grade II or above rock
|
4,470 m3
|
Grade III or below rock
|
4,410 m3
|
Insert soft C&D materials
|
688,653 m3
|
Sub-total
|
697,533 m3
|
Total
|
5,946,000 m3
|
2.728,200 m3
|
|
Table 9.2b
Schedule of Quantities of C&D Materials Generated
Year
|
Grade I/II rock(m3)
|
Grade III rock
(m3)
|
Soft material (m3)
|
Other material (m3)
|
2008
|
-
|
-
|
11,000 m3
|
-
|
2009
|
30,000 m3
|
105,000 m3
|
421,000 m3
|
-
|
2010
|
77,000 m3
|
119,000 m3
|
1,296,000 m3
|
-
|
2011
|
85,000 m3
|
-
|
1,504,000 m3
|
-
|
2012
|
18,000 m3
|
-
|
1,015,000 m3
|
-
|
2013
|
-
|
-
|
802,000 m3
|
-
|
2014
|
-
|
-
|
312,000 m3
|
-
|
2015
|
-
|
-
|
112,000 m3
|
-
|
2016
|
-
|
-
|
39,000 m3
|
-
|
2017
|
-
|
-
|
-
|
-
|
2018
|
-
|
-
|
-
|
-
|
Chemical Waste
9.4.29 The maintenance and servicing of
construction plant and equipment may generate some chemical wastes such as
cleaning fluids, solvents, lubrication oil and fuel. It is difficult to
quantify the amount of chemical waste that will arise from the construction
activities since it will be dependent on the contractor’s maintenance
requirements and the amount of plant utilised. However, it is anticipated
that the quantity of chemical waste, such as lubricating oil and solvent
produced from plant maintenance, would be small and in the order of a few cubic
metres per month for each works package. The amount of chemical waste to
be generated will be quantified in the site Waste Management Plan to be
prepared by the contractor(s) of the respective works package.
9.4.30 Chemical wastes arising during the
construction phase may pose environmental, health and safety hazards if not
stored and disposed of in an appropriate manner as stipulated in the Waste
Disposal (Chemical Waste) (General) Regulations. The potential hazards
include:
·
Toxic effects to
workers
·
Adverse impacts on
water quality from spills
·
Fire hazards
9.4.31 Materials classified as chemical wastes
will require special handling and storage arrangements before removal for
appropriate treatment at the Chemical Waste Treatment Facility (CWTF) or other
licensed facility. Wherever possible, opportunities should be taken to
reuse and recycle materials. Mitigation and control requirements for
chemical wastes are detailed in Section 9.5 below. Provided that
the handling, storage and disposal of chemical wastes are in accordance with
these requirements, adverse environmental impacts would not be expected to
result.
General Refuse
9.4.32
The construction
workforce would generate general refuse comprising food scraps, waste paper,
empty containers, etc. As the introduction of these wastes is likely to
have detrimental effects on water quality in the area, such refuse should be
properly managed so that intentional or accidental release to the surrounding
environment does not occur. Disposal of refuse at sites other than
approved waste transfer or disposal facilities shall be prohibited. Effective
collection of site wastes would be required to prevent waste materials being
blown around by wind, flushed or leached into the marine environment, or
creating an odour nuisance. The waste storage area should be well
maintained and cleaned regularly so as to prevent from attracting pests and
vermin to the work sites.
9.4.33 With the implementation of waste
management practices at the site (as recommended in Section 9.5 below), adverse
environmental impacts on potential hazard, air and odour emissions, noise,
wastewater discharge, and public transport would not be expected from the
storage, handling and transportation of refuse.
Operational Phase
9.4.34 With reference to the preliminary
development schedule of the Kai Tak Development (Appendix 2.1), the
residential, employment population and passenger from the proposed cruise
terminal has been estimated to about 85420, 83940 and 9400 respectively.
Based on the waste generation rates stated in “Monitoring of Solid Waste in
Hong Kong 1999”, the forecasted quantities of domestic waste and C&I waste
are 126 tonne/day (tpd) and 54 tpd,
respectively. It is estimated that the total waste (domestic and C&I
wastes) generated from the Project would be about 180 tpd.
9.4.35 Domestic and C&I wastes will be
collected by licensed waste collector and delivered to the landfill sites in
Hong Kong by refuse collection vehicles for final disposal. Therefore, it
is anticipated that no adverse impact will be arising.
9.5
Mitigation of
Environmental Impacts
Good Site Practices
9.5.1
It is not anticipated that adverse waste
management related impacts would arise, provided that good site practices are
adhered to. Recommendations for good site practices during construction
activities include:
·
Nomination of an
approved person, such as a site manager, to be responsible for good site practices,
arrangements for collection and effective disposal to an appropriate facility,
of all wastes generated at the site.
·
Training of site
personnel in proper waste management and chemical waste handling procedures.
·
Provision of sufficient
waste disposal points and regular collection for disposal.
·
Appropriate measures to
minimise windblown litter and dust during transportation of waste by either
covering trucks or by transporting wastes in enclosed containers.
·
A recording system for
the amount of wastes generated, recycled and disposed of (including the
disposal sites).
Waste Reduction Measures
9.5.2
Good management and
control can prevent the generation of a significant amount of waste.
Waste reduction is best achieved at the planning and design stage, as well as
by ensuring the implementation of good site practices. Recommendations to
achieve waste reduction include:
·
Sort C&D waste from
demolition of the remaining structures to recover recyclable portions such as
metals.
·
Segregation and storage
of different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of materials and their proper disposal.
·
Encourage collection of
aluminium cans, PET bottles and paper by providing separate labelled bins to
enable these wastes to be segregated from other general refuse generated by the
work force.
·
Any unused chemicals or
those with remaining functional capacity shall be recycled.
·
Proper storage and site
practices to minimise the potential for damage or contamination of construction
materials.
Measures for Dredged Marine Sediment
9.5.3
The basic requirements
and procedures for dredged
sediment disposal are
specified under the ETWB TCW No. 34/2002. The management of the dredging,
use and disposal of marine mud is monitored by the MFC, while the licensing of
marine dumping is required under the Dumping at Sea Ordinance and is the
responsibility of the Director of Environmental Protection (DEP).
9.5.4 The dredged marine sediments would
be loaded onto barges and transported to the designated disposal sites
allocated by the MFC depending on their level of contamination. Sediment classified as Category L would
be suitable for Type 1 - Open Sea Disposal. Contaminated sediment would require
either Type 1 – Open Sea Disposal (Dedicated Sites), Type 2 - Confined Marine
Disposal or Type 3 – Special Treatment / Disposal and must be dredged and
transported with great care in accordance with ETWB TCW No. 34/2002. If any
sediment suitable for Type 3 disposal is identified, it is the responsibility
of the project proponent, in consultation with DEP, to identify and agree with
him/her, the most appropriate treatment and/or disposal arrangement.
9.5.5
It will be the
responsibility of the dredging contractor to satisfy the appropriate
authorities that the contamination levels of the marine sediment to be dredged
have been analysed and recorded. According to the ETWB TCW No. 34/2002,
this will involve the submission of a formal SQR to the DEP, prior to the
dredging contract being tendered. The contractor for the dredging works shall
apply for allocation of marine disposal sites and all necessary permits from
relevant authorities for the disposal of dredged sediment. During
transportation and disposal of the dredged marine sediments requiring Type 1,
Type 2, and Type 3 disposal, the following measures should be taken to minimise
potential impacts on water quality:
·
Bottom opening of
barges shall be fitted with tight fitting seals to prevent leakage of
material. Excess material shall be cleaned from the decks and exposed
fittings of barges and hopper dredgers before the vessel is moved.
·
Monitoring of the barge
loading shall be conducted to ensure that loss of material does not take place
during transportation. Transport barges or vessels shall be equipped with
automatic self-monitoring devices as required under the Dumping at Sea
Ordinance and as specified by the DEP.
·
Barges or hopper barges
shall not be filled to a level that would cause the overflow of materials or
sediment laden water during loading or transportation.
9.5.6
Negligible dust impacts
would be expected from dredging activities. In order to further ensure
compliance with the Air Quality Objectives at the air sensitive receivers,
requirements of the Air Pollution Control (Construction Dust) Regulation, where
relevant, shall be adhered to during dredging operations. The dredged
sediment placed on barge should be properly covered as far as practicable to
minimise the potential odour emissions during the dredging operation and
transportation of the dredged sediment.
Measures for Construction and Demolition
Materials
9.5.7
Mitigation measures and
good site practices should be incorporated into the contract document to
control potential environmental impact from handling and transportation of
C&D material. The mitigation measures include:
·
Where it is unavoidable
to have transient stockpiles of C&D material within the Project work site
pending collection for disposal, the transient stockpiles shall be located away
from waterfront or storm drains as far as possible.
·
Open stockpiles of
construction materials or construction wastes on-site should be covered with
tarpaulin or similar fabric.
·
Skip hoist for material
transport should be totally enclosed by impervious sheeting.
·
Every vehicle should be
washed to remove any dusty materials from its body and wheels before leaving a
construction site.
·
The area where vehicle
washing takes place and the section of the road between the washing facilities
and the exit point should be paved with concrete, bituminous materials or hardcores.
·
The load of dusty
materials carried by vehicle leaving a construction site should be covered entirely
by clean impervious sheeting to ensure dust materials do not leak from the
vehicle.
·
All dusty materials
should be sprayed with water prior to any loading, unloading or transfer
operation so as to maintain the dusty materials wet.
·
The height from which
excavated materials are dropped should be controlled to a minimum practical
height to limit fugitive dust generation from unloading.
9.5.8
When delivering inert
C&D material to public fill reception facilities, the material shall
consist entirely of inert construction waste and of size less than 250mm or
other sizes as agreed with the Secretary of the Public Fill Committee. In
order to monitor the disposal of the surplus C&D material at the designed
public fill reception facility and to control fly tipping, a trip-ticket system
as stipulated in the ETWB TCW No. 31/2004 “Trip Ticket System for Disposal of
Construction and Demolition Materials” should be included as one of the
contractual requirements and implemented by an Environmental Team undertaking
the Environmental Monitoring and Audit work. An Independent Environmental
Checker should be responsible for auditing the results of the system.
Measures for Chemical Waste
9.5.9
After use, chemical
wastes (for example, cleaning fluids, solvents, lubrication oil and fuel)
should be handled according to the Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes. Spent chemicals should be collected by a
licensed collector for disposal at the CWTF or other licensed facility, in
accordance with the Waste Disposal (Chemical Waste) (General) Regulation.
Measures for General Refuse
9.5.10 General refuse should be stored in
enclosed bins or compaction units separate from C&D material. A
licensed waste collector should be employed by the contractor to remove general
refuse from the site, separately from C&D material. Effective
collection and storage methods (including enclosed and covered area) of site
wastes would be required to prevent waste materials from being blown around by
wind, wastewater discharge by flushing or leaching into the marine environment,
or creating odour nuisance or pest and vermin problem.
9.6
Evaluation of Residual
Environmental Impacts
9.6.1
With the implementation
of the recommended mitigation measures for the handling, transportation and
disposal of the identified waste arisings, no
residual impact is expected to arise during the construction of the proposed
Project.
9.7
Environmental Monitoring and Audit
9.7.1
Waste management will
be the contractor’s responsibility to ensure that all wastes produced during
the construction activities are handled and disposed of in accordance with the
recommended mitigation measures and EPD’s regulations
and requirements. The mitigation measures recommended in Section 9.5
above should form the basis of the Environmental Monitoring and Audit
requirements in the construction stage.
9.8
Summary
9.8.1
Wastes generated by the
Project are likely to include dredged marine sediment and construction and
demolition (C&D) material generated from 600m runway opening, site
formation and various civil works for the construction of buildings and
infrastructure within the Project boundary, as well as general refuse from the
workforce and chemical waste from the maintenance of construction plant and
equipment and from the soil remediation process. It is estimated that
approximately 4,565,800 m3 of dredged sediment and approximately
5,946,000 m3 of C&D material would be generated from the
Project. During operational phase of the Project, the major solid wastes are
municipal wastes generated from different land uses within the development.
9.8.2
The total volume of
dredged sediment generated from the dredging of the seabed to provide the
manoeuvring basin for the cruise terminal is estimated to be approximately 1.38
Mm3 during construction phase. Based on the results of the
chemical and biological screening, approximately 430,000 m3 was
classified as contaminated dredged sediment (Category M and H) requiring Type 1
– Open Sea Disposal (Dedicated Sites) or Type 2 - Confined Marine Disposal, and
approximately 950,000 m3 was classified as Category L sediment
suitable for Type 1 - Open Sea Disposal in accordance with ETWB TCW No.
34/2002.
9.8.3
The total volume of
dredged sediment generated from maintenance dredging for the cruise terminal is
estimated to be approximately 350,000 m3 every 5 to 10 years.
Prior to any maintenance dredging, sediment sampling and testing will be
carried out in accordance with the ETWB TCW No. 34/2002 to determine the
contamination level of the dredged sediment.
9.8.4
The total volume of
dredged sediment generated from 600m runway opening, localized maintenance
dredging at KTAC, and immersed tunnel sections of Road T2 & CKR are
estimated to be approximately 3,200 m3, 120,000 m3 and 2,620,000
m3 respectively. With reference to the
sediment sampling results presented in the SEKDCFS EIA for locations around the
proposed dredging areas, the dredged sediment is likely to be highly contaminated and would require confined
marine disposal.
9.8.5
The total volume of
dredged sediment generated from the existing seawall to be re-constructed for
the proposed public landing step cum fireboat berth is estimated to be
approximately 600m3. From the results of recent site
investigation around the proposed marine works area, the dredged sediment is
likely to be classified as Category L material. The materials must be dredged,
transported and disposed of in a manner, which minimizes the loss of
contaminants either into solution or by resuspension.
9.8.6
It will be the
responsibility of the dredging contractors of the respective dredging
operations to satisfy the appropriate authorities that the contamination levels
of the marine sediment to be dredged have been analysed and recorded.
According to the ETWB TCW No. 34/2002, this will involve the submission of a
formal SQR to the DEP, prior to the dredging contract being tendered. The
contractor for the dredging works shall apply for allocation of marine disposal
sites and all necessary permits from relevant authorities for the disposal of
dredged sediment.
9.8.7
The total volume of
C&D material generated from the major construction activities of the
Project are estimated to be approximately 5,946,000 m3 and 2,728,200m3 out of this total volume is estimated to be reused during construction
phase. Other wastes generated from the Project are likely to include
chemical waste from the maintenance of construction plant and equipment and
general refuse from the construction workforce.
9.8.8
Mitigation measures are
recommended in this EIA to minimise potential environmental impacts associated
with handling and disposal of different wastes arising from the Project.
Provided that the recommended mitigation measures are properly followed,
adverse environmental impacts would not be expected from the Project.