Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
EIA Executive Summary
Contents
1.2 Objectives of the Environmental Impact Assessment 1
1.3 The Need of Project and Scenario without the Project
2............ PROJECT DESCRIPTION
2.1 Site Location and Study Area
2.2 Nature, Scope and Benefits of the Project
3............ CONSIDERATION OF ALTERNATIVES
5............ KEY FINDINGS OF THE ENVIRONMENTAL IMPACT ASSESSMENT
5.4 Waste Management Implications
5.8 Landscape and Visual Impact
5.11 Sewerage and Sewage Treatment Implications
5.12 Environmental Monitoring and Audit
Lists of Tables
Table 5.1 Summary of Environmental Impacts Associated with the Project
Lists of Figures
Figure 1.1a Recommended Outline Development Plan (dated May 2008)
(i) The overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project and associated works, and their related stage implementation;
(ii) The conditions and requirements for mitigating environmental nuisances associated with introducing the Project as a new urban development in the existing environs close to an embayed area with known pollution problems;
(iii) The conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
(iv) The acceptability of residual impacts after the staged as well as the full implementation of the Project, the associated works and the related proposed mitigation measures.
Terrestrial Ecology
Marine Ecology
Table 5.1 Summary of Environmental Impacts Associated with the Project
Sensitive Receivers / Assessment Points |
Impact Prediction Results |
Relevant Standards / Criteria |
Extents of Exceedances |
Impact Avoidance Measures / Mitigation Measures |
Residual Impacts (After Implementation of Mitigation Measures) |
|
Air Quality Impact |
|
|
|
|
||
Construction Phase |
||||||
85 assessment points |
Cumulative 1-hour Average TSP Conc.: 152-481 mg/m3 Cumulative 24-hour Average TSP Conc.: 100-220mg/m3 |
EIAO-TM and Air Quality Objective
1-hour Average TSP Conc.: 500 mg/m3 24-hour Average TSP Conc.: 260mg/m3 |
Nil |
Eight times daily watering with complete coverage of active dust emitting area(s) or other alternative equivalent effective dust suppression measures. Requirements of the Air Pollution Control (Construction Dust) Regulation The following mitigation measures, good site practices and a comprehensive dust monitoring and audit programme are recommended to minimise cumulative dust impacts. · Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission. · Misting for the dusty material should be carried out before being loaded into the vehicle. · Any vehicle with an open load carrying area should have properly fitted side and tail boards. · Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin. · The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation. · The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials.
· Vehicle washing facilities should be provided at every vehicle exit point. · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores. · Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet. · Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides. · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites. |
Nil |
|
Construction Phase (Decommissioning works) |
||||||
9 assessment points |
No adverse construction dust impacts arising from demolition works, excavation works, transportation, loading and unloading of contaminated soils, and mixing process in solidification expected at the representative ASRs |
EIAO-TM and Air Quality Objective
1-hour Average TSP Conc.: 500 mg/m3 24-hour Average TSP Conc.: 260mg/m3 |
Not Applicable |
Eight times daily watering with complete coverage of active dust emitting area(s) or other alternative equivalent effective dust suppression measures. Requirements of the Air Pollution Control (Construction Dust) Regulation The following mitigation measures, good site practices and a comprehensive dust monitoring and audit programme are recommended to minimise cumulative dust impacts. · Stockpiling site(s) should be lined with impermeable sheeting and bunded. Stockpiles should be fully covered by impermeable sheeting to reduce dust emission. · Misting for the dusty material should be carried out before being loaded into the vehicle. · Any vehicle with an open load carrying area should have properly fitted side and tail boards.
· Material having the potential to create dust should not be loaded from a level higher than the side and tail boards and should be dampened and covered by a clean tarpaulin. · The tarpaulin should be properly secured and should extent at least 300 mm over the edges of the sides and tailboards. The material should also be dampened if necessary before transportation. · The vehicles should be restricted to maximum speed of 10 km per hour and confined haulage and delivery vehicle to designated roadways insider the site. On-site unpaved roads should be compacted and kept free of lose materials. · Vehicle washing facilities should be provided at every vehicle exit point. · The area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores. · Every main haul road should be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet. · Every stock of more than 20 bags of cement should be covered entirely by impervious sheeting placed in an area sheltered on the top and the three sides. · Every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites. Solidification · The solidification pit/area should be provided with dust suppression measures. · Handling and mixing of cement shall follow Air Pollution Control (Construction Dust) Regulation to limit cement emission. · The bin should be covered during residence period after mixing process. Biopiling · During the course of biopile formation, the stockpiled soils at the biopiles should be covered by tarpaulin or low permeable sheet to avoid fugitive emissions of dust or any air pollutants from the biopiles affecting the surrounding environment and to minimise runoff from the stockpiled soils. Biopile(s) should be covered by impermeable sheeting (such that no longer than 5m of a biopile should be exposed to open air) to avoid fugitive emissions of dust or any pollutants from the biopile(s). · Upon formation of a biopile, the biopile should be covered by low permeable geotextiles to prevent dust emission and runoff. · During the operation of biopile, the biopiles should be fully covered to control the extraction of VOCs. · The vented air from the biopile(s) should be connected to blower and carbon adsorption system with 99% control efficiency for treatment before release to the atmosphere. Exhaust air from the blower and carbon adsorption system should be monitored for TVOC bi-weekly to check the performance of the carbon filter. The frequency of monitoring might be adjusted subject to review on site. The location of the exhaust of the carbon filter should be sited as far away as possible from the nearby ASRs. · Spent activated carbon of the carbon adsorption system should be replaced at appropriate intervals such that the TVOC emission concentration from the system is acceptable (i.e. the measured TVOC concentration is below 20ppm). |
Nil |
|
Operational Phase (Vehicular Emission) |
||||||
175 assessment points |
1-hour Average NO2 Conc.: 72 - 190 mg/m3
24-hour Average NO2 Conc.: 68 -106mg/m3
24-hour Average RSP Conc.: 57-70mg/m3 |
Air Quality Objective
1-hour Average NO2 Conc.: 300 mg/m3 24-hour Average NO2 Conc.: 150mg/m3 24-hour Average RSP Conc.: 180mg/m3
|
Nil |
Not Applicable |
Nil |
|
Air quality inside deckover for planned landscape deck for Road D2 and Road L1 tunnel. |
Achieve EPD recommended standard of 1 ppm NO2 concentration |
EPD Tunnel Air Quality Guidelines 1 ppm NO2 concentration |
Nil |
Not Applicable |
Nil |
|
Operational Phase (Sewage Pumping Stations) |
||||||
139 assessment points |
No adverse odour impacts arising sewage pumping stations |
EIAO-TM Meet 5 odour units based on an averaging time of 5 seconds for odour prediction assessment. |
Nil |
Provision of deodorization system and odour sources being enclosed. |
Nil |
|
Operational Phase (Cumulative) |
||||||
175 assessment points |
Cumulative 1-hour Average NO2 Conc.: 114-835 mg/m3 Cumulative 24-hour Average NO2 Conc.: 77 -384mg/m3 Cumulative 1-hour Average SO2 Conc.: 125-4075mg/m3 Cumulative 24-hour Average SO2 Conc.: 52-1698mg/m3 Cumulative 24-hour Average RSP Conc.: 61-229mg/m3 |
Air Quality Objective 1-hour Average NO2 Conc.: 300 mg/m3 24-hour Average NO2 Conc.: 150mg/m3 1-hour Average SO2 Conc.: 800mg/m3 24-hour Average SO2 Conc.: 350mg/m3 24-hour Average RSP Conc.: 180mg/m3 |
Exceed 1-hour Average NO2 Conc. by up to 535 mg/m3 Exceed 24-hour Average NO2 Conc. by up to 234mg/m3 Exceed 1-hour Average SO2 Conc. by up to 3274mg/m3 Exceed 24-hour Average SO2 Conc. by up to 1348mg/m3 Exceed 24-hour Average RSP Conc by up to 49mg/m3 |
The only affected planned ASR is the proposed
Tourism Node and would be provided with central air conditioning, no adverse
air quality impact would be expected with the provision of appropriate fresh air
intake locations for this ASR. |
Nil |
|
42 assessment points |
The predicted odour concentrations range from 1.9 to 32.2 ou/m3 over averaging time of 5 seconds under worst case condition.
|
EIAO-TM Meet 5 odour units based on an averaging time of 5 seconds for odour prediction assessment. |
Exceed the odour criterion up to 27 ou/m3
|
Odour nuisance associated with the KTAC and the KTN is an existing environmental problem. In order to improve the environment, this Project will take the opportunity to mitigate the potential sources of odour nuisance within the Project area so as to alleviate this existing environmental problem, as well as to provide an acceptable environment for the future land uses within the project area. Mitigation measures have been formulated to alleviate this existing odour problem. These include reconstruction or decking of KTN within the former apron area, full mitigation of the potential odour emissions from the headspace of KTN and JVBC near the existing discharge locations, localised maintenance dredging within KTAC, 600m gap opening at the northern section of the former runway to improve the water circulation in KTAC, and the implementation of in-situ bioremediation to treat the sediment accumulated at KTAC and KTTS. |
Residual odour impact is predicted at the planned ASRs. Nevertheless, the residual odour levels are predicted to be very low and no adverse health effect on human is expected. Hence, with the implementation of the proposed odour mitigation measures, adverse odour impact is not expected at the existing and planned ASRs in the vicinity of the Kai Tak Development. |
|
Noise Impact |
|
|
|
|
|
|
Construction Phase |
||||||
36 assessment points
|
Predicted noise levels would be in the range of 45 to 92 dB(A) |
Domestic premises: 75dB(A)
Educational institutions: 70 dB (A) during normal teaching periods
& 65 dB(A) during examinations
|
Domestic premises: Exceed the noise standard by up to 16dB(A). Educational institutions: Exceed the noise standard by 19 dB(A) during normal teaching period and up to 24dB(A) during examination period. |
Use of quiet equipment and movable/temporary noise barriers grouping to mininise construction noise impact
|
For N4 ( For N5 ( For N11 (Cognitio College), the predicted noise level would exceed the noise standard of 65 dB(A) by up to 10 dB(A) during examination periods from Sept 2009 to Apr 2010 and Jul 2010 to Dec 2015. The noise level also exceed the noise standard of 70dB(A) by up to 5 dB(A) during normal teaching period from Jul 2010 to Dec 2015. For N13 ( For N23 ( For N27 (CCC Kei To Secondary School), the predicted noise level would exceed the noise standard of 65 dB(A) by up to3 dB(A) during examination periods from Jan 2015 to Dec 2016. For N28 (Po Leung Kuk Ngan Po Ling College), the predicted noise level would exceed the noise standard of 65 dB(A) by up to 5 dB(A) during examination periods from Jan 2012 to Dec 2016. For N14 ( For N18 (HK Society for Blind hostel), the predicted noise level would exceed the noise standard of 75 dB(A) by up to 1 dB(A) from Jan 2015 to July 2015. For N20B (Grand Waterfront), the predicted noise level would exceed the noise standard of 75 dB(A) by up to 3 dB(A) from Jan 2012 to Dec 2016. For N21 ( For PN2 (Site 1A1 (Planned)), the predicted noise level would exceed the noise standard of 75 dB(A) by up to 11 dB(A) from Oct 2012 to Dec 2015. |
|
Operational Phase (Traffic Noise) |
||||||
158 assessment points |
L10: 42 to 87 dB(A) |
Domestic premises: 70 dB(A)
Educational institutions and all others where unaided voice
communication is required: 65dB(A)
|
Domestic premises: Exceed the noise standard by up to 17dB(A).
Education institution: Exceed the noise standard by up to 22dB(A)
|
Low noise surfacing at (i) Road L2 (ii) Road L3 (for through road option) (iii) Road L4
Building setback about 5m at site 1I1, 5m at 1L2 & 35m at 1L3.
Building setback at site 2B6
and no openable window facing to the Road L16 or section of existing roads in
For site 5A4, (i) avoid any sensitive facades with openable window facing the existing To Kwa Wan Road or (ii) provision of 17.5m high noise tolerant building fronting To Kwa Wan Road and restrict the height of the residential block(s) located at less than 55m away from To Kwa Wan Road to no more than 25m above ground. For ex-San |
With the proposed noise mitigation measures in place, the ‘New’ road noise contributions to the overall noise levels at all representative NSRs would be less than 1.0 dB(A) and the ‘New’ road noise levels would all be below the relevant noise criteria. No adverse noise impacts arising from the ‘New’ roads are predicted at representative NSRs. Noise exceedances at the representative NSRs, if any, would be due to the existing roads. |
|
Operational (Fixed Plant Noise ) |
||||||
23 assessment points |
All predicted Noise levels are within NCO criteria |
ASR B
Daytime & Evening: 60 dB(A)
Nighttime: 50dB(A)
ASR C:
Daytime & Evening: 65 dB(A)
Nighttime: 55dB(A)
|
Nil
|
l The exhaust of the ventilation system and any opening of the building should be located facing away from any NSRs; and
l Louver or other acoustic treatment equipment could also be applied to the exhaust exit of the building. |
Nil |
|
Noise impacts from Open Air Entertainment Activities |
||||||
1 assessment point |
The predicted Noise level is within criteria |
Noise Control Guidelines for Holding Open Air Entertainment Activities
|
Nil
|
l Installation of retractable roof or the main stadium could consider a fixed roof design. |
Nil |
|
Helipad Noise |
||||||
1 assessment point |
The predicted Noise level is within NCO criteria |
EIAO-TM
|
Nil
|
l Nil |
Nil |
|
Noise from EFTS |
||||||
1 assessment point |
All predicted Noise levels are within NCO criteria |
NCO
|
Nil
|
l Multi-plenum system and vertical noise barrier at the all elevated sections of the alignment on viaduct would be considered. |
Nil |
|
Marine traffic noise (include noise from typhoon shelters) |
||||||
2 assessment points |
Nil |
Nil
|
Nil
|
l Nil |
Nil |
|
Construction Phase Water Quality Impact |
|
|
|
|
||
Seawater intakes along the
waterfront of |
The model results indicate exceedances
of WSD water quality (SS) criterion at 6 flushing water intakes along the
water front of
|
1. WSD flushing water quality intake criterion for SS: < 10 mg/l 2. Target water quality objectives at coral sites for SS elevations: < 30 % of the background ambient levels 3. Sedimentation rate at corals: <100g/m2/day |
Full compliance would be achieved with implementation of all the recommended mitigation measures |
Use of closed grab dredger during dredging and filling operations. Deployment of silt curtains at appropriate dredging areas, and installation of silt screens at selected seawater intakes during dredging. Avoid maintenance dredging for cruise terminal in wet season (April to September). |
None |
|
Operational Phase Water Quality Impact |
||||||
Seawater
intakes along the waterfront of |
Operation
of KTD would not cause unacceptable impacts upon the water quality in |
Relevant WQO for marine water stipulated under the WPCO |
No WQO exceedance is induced by the Project |
Cleansing contractor will provide scavenging service (floating refuse) in the accessible water area surrounding the ex-Kai Tak Airport runway. Monitoring and audit programme will be implemented to ascertain the runway opening and bioremediation for the sediment at KTAC and KTTS would not result in unacceptable impact. |
None |
|
Waste Management Implications |
|
|
|
|
||
Water quality, air, and noise sensitive receivers at or near the Project site, the waste transportation routes and the waste disposal site. |
Main waste: dredged marine sediment with a total volume of
approximately 4.57 Mm3 from capital dredging and Of the sediment to be generated from capital dredging, approximately The total volume of dredged sediment generated from Other wastes: Chemical waste from plant and equipment maintenance during capital and
maintenance dredging; and Total volume of 5,946, |
l Waste Disposal Ordinance (Cap. 354) l Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354) l Land (Miscellaneous Provisions) Ordinance (Cap. 28) l Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation l Annexes 7 & 15 of EIAO TM |
Not applicable |
l Contaminated dredged sediment (Category M and H) would require either Type 1 =- Open Sea Disposal (Dedicated Sites) or Type 2 - Confined Marine Disposal at contaminated mud pit allocated by MFC. l Category L sediment is suitable for Type 1 - Open Sea Disposal at gazetted marine disposal ground allocated by MFC. l Mitigation measures and good site practices recommended in the EIA report on waste management should be incorporated into the contract document to control potential environmental impact from handling of the identified wastes arising from the Project |
None |
|
Land Contamination |
||||||
Construction workers during the construction and decommissioning stages.
|
l Land contaminations impacts were identified by carrying out land contamination assessment/ comprehensive review of the historical/ current land uses of potential contaminative areas. Specific hotspots within the KTD study area were recognized. l Soil contamination identified was mainly organics (TPH, VOCs and SVOCs) and heavy metals (lead, copper, zinc, cadmium, nickel cobalt and arsenic) l Free product was observed in 3 groundwater monitoring wells at ex-GFS apron area. |
l EIAO TM; l Practice Note for Professional Persons ProPECC PN3/94 “Contaminated Land Assessment and Remediation”; l Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair /Dismantling Workshop; l Guidance Note for Contaminated Land Assessment and Remediation; and l Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management. |
l South Apron of the former l Ex-GFS apron area; l Localised spot near Kai Tak Tunnel; l Ex-GFS building |
l The contaminated soil identified should be excavated and treated on-site by biopiling and/or solidification / stabilization. l Free product should be treated by skimming as recommended in KTA Decommissioning EIA. l The recommended environmental mitigation and safety measures, progress monitoring and/or confirmation sampling / testing recommended during the course of remedial works should be implemented. |
None |
|
Hazard to Life |
||||||
Population near the hazardous installations |
l The risk levels of the examined hazardous installations at the assessment year of 2012, 2016 and 2021 to the future occupants of the Project are considered to be in compliance with the risk guidelines and no adverse impact is expected. |
l Annex 4 of EIAO TM |
Not applicable |
Not applicable |
Not applicable |
|
Cultural Heritage |
||||||
Built Heritage Resources |
A desk-based study and a
built heritage field survey have been conducted and revealed several heritage
resources associated with the former Kai Tak Airport, which include two wind
poles, the airport pier, Fire Station A, Fire Station B (and associated
pier), Fire Station C, seawall and the runway, the Old Far East Flying
Training School, Sung Wong Toi Inscription Rock, Fish Tail Rock, and Kowloon
Rock. The heritage significance of the |
l Criteria for Cultural Heritage Impact Assessment |
Not applicable |
Not applicable |
Not applicable |
|
Terrestrial Archaeological Resources |
The remains of the Longjin Pier and sherds from Sung Dynasty were recovered at two locations in the North Apron area. |
l Criteria for Cultural Heritage Impact Assessment l Guidelines for Handling of Archaeological Finds and Archives |
Not applicable |
l Further archaeological investigation and rescue excavation will be undertaken at location with sherds from Sung Dynasty. Whereas for Longjin Pier, preservation in situ of all identified sections of the Longjin Pier as part of the KTD is recommended after the completion of further archaeological investigation. |
Once
further archaeological investigation at location with sherds from Song
dynasty and subsequent rescue excavation have been completed, there will be
no residual impacts from terrestrial archaeology. Once further archaeological investigation for Longjin Pier has been completed and all identified sections of the Longjin Pier have been preserved in-situ there will be no residual impacts from terrestrial archaeology. |
|
Marine Archaeological Resources |
Destruction of marine archaeological resources by dredging |
l Guidelines for Marine Archaeological investigation |
Not applicable |
l Monitoring of dredged material |
None |
|
Landscape and Visual Impacts |
||||||
Landscape Resources, Landscape Character Areas, Visual Sensitive Receivers |
· Based on a very broad brush estimate, approximate 2,250 existing trees will be affected by Kai Tak Development, of which approximately 1,363 no. of trees will be felled and 887 no. of trees will be transplanted. Approximate 5,000 nos. of trees will be planted within new open spaces and approximate 1,000 nos. of trees will be planted for new distributor roads to compensate for the loss of existing trees. . · A total of approximately 89.5 ha of open space will be provided within the development to compensate loss of approximately 1.4ha within the adjacent districts. The overall residual impact on open space system is considered acceptable with mitigation measures. · The overall landscape character of the area will be dramatically changed from a flat open area with various temporary uses to a high-rise contemporary development with sports and entertainment nodes. The overall residual impact on LCAs within and adjacent to the KTD and is considered some beneficial in the long term with all soft landscape elements proposed in new parks, waterfront promenade and amenity areas become mature. ·
There will
unavoidably be moderate to substantial residual impact on the residential
VSRs at high rise buildings in To Kwa Wan, · Overall, the landscape and visual impacts due to the Kai Tak Development are considered to be acceptable with the implementation of the appropriate mitigation measures (including incorporation of all design measures in the layout plan) and in the long term be beneficial in respect of landscape and visual impacts. |
· Environmental Impact Assessment Ordinance (EIAO) (Cap. 499). · EIAO Technical Memorandum on EIA Process (EIAO-TM) Annex 10 and Annex 18 · ETWB 2/2004 · ETWB 3/2006 |
Not applicable |
Construction Phase · All existing trees shall be carefully protected during construction. · Trees unavoidably affected by the works shall be transplanted where practical. Detailed transplanting proposal will be submitted to relevant government departments for approval in accordance with ETWBC 2/2004 and 3/2006. Final locations of transplanted trees shall be agreed prior to commencement of the work. · Control of night-time lighting · Erection of decorative screen hoarding. Operation Phase · Compensatory tree planting should be incorporated into the proposed projects where trees are affected. · Tall buffer screen tree / shrub / climber planting, vertical green and roof greening where appropriate should be incorporated to soften hard engineering structures and facilities. · Sensitive streetscape design should be incorporated along all new roads to reflect the new urban development in Kai Tak. · Structure and ornamental tree planting should be provided along roadside amenity strips and central dividers to enhance the townscape quality, where space is available. · Aesthetically pleasing design as regard to the form, material and finishes shall be incorporated to all engineering structures and infrastructure facility buildings. · Control of Operation Night-time Glare |
None |
|
Ecological Impact |
||||||
Ecological resources at and near the Project area |
Terrestrial Ecology l Permanent loss of 202.7 ha of wasteland,
15.8 ha of plantation/grassland mosaic in the former l Permanent and temporary loss of 0.7 km and 1.6 km artificial coastline at the KTAC and part of the runway area. With provision of new artificial coastline after the construction phase, permanent loss of short length (~4%) of this habitat is not expected to cause significant adverse impact to the existing waterbird population under the Project. l Direct removal of about 2250 existing trees of common species within the Project area. l Indirect disturbance impact to nearby highly disturbed developed area and associated wildlife during construction and operation phases. l Potential secondary impact on waterbirds due to reduction of food available by deterioration of marine water quality during the construction works. Such impact is considered as minor and acceptable in view of its temporary nature and presence of similar alternative feeding area in the vicinity of Assessment Area. |
l Environmental Impact Assessment Ordinance (EIAO) (Cap. 499). l EIAO Technical Memorandum on EIA Process (EIAO-TM) l Annex 8 and Annex 16 l EIAO Guidance Note No. 3/2002 l EIAO Guidance Note No. 6/2002 l EIAO Guidance Note No. 11/2004 l Wild Animals Protection Ordinance (Cap. 170) l Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586) l Town Planning Ordinance (Cap.131) l The Marine Parks Ordinance (Cap.476) and Subsidiary Legislation l The Country Parks Ordinance (Cap. 208) l The Forests and Countryside Ordinance (Cap. 96) l The Marine Fish Culture Ordinance (Cap.353) |
Not applicable |
l As far as possible, implementation of compensatory planting of similar composition of native trees and vegetation within the Project area should be provided at a ratio not less than 1:1 in terms of quality and quantity after the construction works
l Coral translocation of directly affected colonies, as far as practicable, to avoid and minimize direct loss of this fauna of conservation interest l Water quality control measures such as installation of silt curtains around dredger(s) and use of closed grab dredger to minimise indirect impact on marine life due to change of water quality. l Re-construction of new seawalls to provide large area of hard substrate for re-colonization of existing intertidal and subtidal assemblages after the construction works. |
l Permanent loss of 202.7 ha wasteland, 15.8 ha plantation/grassland mosaic habitats of very low ecological values
l Permanent loss of 0.7km of artificial coastline / seawall habitat of low ecological value.
|
|
|
Marine Ecology l Direct impacts to the marine ecological resources would include temporary loss of approximately 74.4 hectares of soft bottom and subtidal habitat and about 1.6km of artificial intertidal habitat as well as permanent loss of about 0.7 km long of artificial intertidal habitat. All the marine habitats and associated marine life that would be directly lost are all of very low ecological values and taking into account of all the mitigation measures proposed including coral translocation and provision of newly constructed seawalls, such impact is considered as minor. l Indirect impacts on the marine ecology would be associated with changes of water quality due to dredging activities. l Considering that the benthic, intertidal and subtidal communities identified in the Project area are of generally very low ecological value and in view of the temporary nature of such impact, only minor indirect impact on marine resources is anticipated. |
l The Protection of the Harbour Ordinance (Cap.531) l The Water Pollution Control Ordinance (Cap.358) l International
l The PRC National Protection Lists of Important Wild Animals and Plants |
|
|
|
|
Fisheries Impact |
|
|
|
|
||
Fisheries resources at and near the Project area |
l The Project will result in the temporary loss of about 74.4 hectares of fishing area. In view of the small size of affected area, temporary and insignificant loss of fisheries production and low impact on fishing activities, fisheries impacts due to direct loss of fishing area within the dredging area is considered as minor and acceptable.
l Indirect impacts on fisheries resources would be associated with changes of water quality due to dredging activities. In view of the temporary and localised nature of such impact, only minor impact on capture fisheries resources is anticipated. No impact on culture fisheries resources is anticipated as the nearest FCZs Tung Lung Chau and Ma Wan are over 8km and 10km away from the project area respectively. l No operational phase impact on fisheries resources are expected to result from operation of the project as all construction works would take place within the existing land limits of the Kai Tak Development site and no structures would extend beyond these land limits. In addition, fishing activity will not be restricted in the sea area (turning area) off the cruise ship terminal and public landing steps cum fireboat berth during the operation of the project. |
l EIAO-TM Annex 9 and Annex 17 l Fisheries Protection Ordinance (Cap. 171) l Marine Fish Culture Ordinance (Cap. 353) l The Water Pollution Control Ordinance (Cap.358) |
Not Applicable |
No necessary fisheries-specific mitigation measures would be required. |
l Temporary loss of 74.4 hectares of fishing area.
|
|
Sewerage and Sewage Treatment Implications |
||||||
Existing and planned sewerage system, sewage treatment and disposal facilities. |
No adverse impact on the existing and planned sewerage system, sewage treatment and disposal facilities by the project are indentified. |
EIAO Technical Memorandum on EIA Process (EIAO-TM) Annex 14 |
Not Applicable |
No necessary mitigation measures would be required. |
None |
|
|
|
|
|
|
|
|