Table 11.1 Summary
of Key Environmental Outcomes/ Benefits
Issue |
Environmental
Outcomes/Benefits |
The Project |
Requirements: ·
Widening the following sections of Tuen Mun Road
Town Centre Section (TMRTCS) from dual 2-lane carriageway to dual 3-lane
carriageway Ø
Ø
Benefits ·
The Project can relieve the traffic congestion at
the TMRTCS between Potential
Sequences without the Project ·
Without the Project, there would be traffic
capacity concern for TMRTCS. This
road section may become a bottleneck due to the natural traffic growth of TMR
and the increased traffic bring about by HK-SWC and the Deep Bay Link. ·
Due to the possible severe traffic congestion at
TMRTCS, there would be a consequential adverse air quality impacts to the
nearby ASRs as the vehicles are in idling condition during traffic congestion.
|
Development
Alternatives |
·
Comparing with the “Tunnel” option, the “Dual
3-lane widening from ·
In view of environmental
aspects, widening of existing road section would pose relatively less
environmental impacts to the surrounding environment. The Dual 3-lane widening option would involve less excavation quantities, no portal exhaust as
required by tunnel, less construction traffic and smaller construction area. |
Construction
Noise |
Impact/Problem ·
Unmitigated cumulative construction noise levels:
66 dB(A) to 91 dB(A). Key
environmental problem avoided: ·
Recommended mitigation measures: adopting quiet
construction plant, movable noise
barriers, scheduling
of construction activities and implementing good site practices. Environmental
benefits of environmental protection measures recommended & Environmentally sensitive areas protected: ·
Under mitigated scenario, all representative NSRs
would be protected to comply with the daytime construction noise standard as
set out in the EIAO-TM, except 5 NSRs of educational institutions, namely CMA, LWF,
LCKP, LCK and CSBS would exceed the noise criteria during examination periods. The contractor would be
suggested to liaise with all relevant schools to check out their examination
periods and activities in the beginning of the works programme. The noise impacts would be alleviated
by good planning and arrangement of works and providing sufficient mitigation
plans from the contractor. |
Road Traffic
Noise |
Impact/Problem ·
Unmitigated noise levels: 61 dB(A) to 85 dB(A). Key environmental problem avoided: ·
Recommended mitigation measures as shown in Figures
3.3A to 3.3C. Environmental
benefits of environmental protection measures recommended & Environmentally sensitive areas protected: ·
Mitigated noise levels of NSRs along widened Tuen
Mun Road Town Centre Section: 52 dB(A) to 76 dB(A). The ‘New’ road noise
contributions to the overall noise levels at all representative NSRs (except
TFH, CLFY2, CLFY5, CLFY6, HKG, TTP, KFG1A and KFG1B) would be below the relevant noise
criteria, though the overall noise levels at some of the NSRs would still
exceed the relevant noise criteria. Such exceedances are due to the existing
roads.
·
Due to site constraint, noise enclosure is technically
infeasible to be built to further alleviate the noise impacts at TFH, CLFY2, CLFY3, CLFY5, CLFY6, HKG, TTP, JCP, HG, KFG |
Construction
Air Quality |
Impact/Problem ·
Potential air quality impacts are dust nuisance. Key
environmental problem avoided: ·
Mitigation measures: implement the Air Pollution Control
(Construction Dust) Regulation and good site practices. Environmental
benefits of environmental protection measures recommended: ·
No adverse air quality impacts are
anticipated. |
Operational
Air Quality |
Impact/Problem ·
No adverse traffic emission impacts are anticipated
at the existing and future ASRs. |
Construction
Water Quality |
Impact/Problem ·
General construction activities associated with the
construction of the Project could lead to site runoff. Key environmental problem avoided: ·
All of the recommended mitigation measures are
implemented and all construction site / work area discharges comply with the
TM-DSS standards. Environmental benefits of environmental protection
measures recommended: ·
No unacceptable residual water quality impacts are
expected during the construction of the proposed infrastructure |
Operational
Water Quality |
Impact/Problem Adverse water quality
impacts associated with the operation of the Project are not expected at the water
sensitive receivers within the study area. Thus, there will be no residual impact
associated with the operation of the Project. |
Waste
Management |
Impact/Problem ·
Wastes generated by construction activities: general
refuse from the workforce, chemical waste from plant and equipment
maintenance, and C&D material from excavation works and the demolition of
existing structures. Environmentally friendly designs recommended: ·
5,850 m3 of inert C&D material
(public fill) to be disposed to public fill reception facilities for other
beneficial uses. ·
3,000 m3 of inert C&D material to be
reused on-site.
·
With the implementation of the recommended mitigation
measures and practices for the handling, transportation and disposal of the
identified waste arisings, no adverse environmental impacts are expected. |
Ecology |
Impact/Problem & Environmentally friendly
designs recommended ·
The proposed construction works would only be
conducted in the developed area.
No direct impact on ecological important habitats, such as woodland
habitat, would be resulted from the proposed works. ·
The removal of roadside plantation of common species
within the proposed site area would be compensated by compensatory planting. ·
Disturbance impacts to habitats and associated
communities adjacent to the proposed site area would be resulted due to the
construction works. Wildlife within the proposed site area and the adjacent
woodland also adapted to high levels of human disturbance, heavy traffic flow
and traffic noise, thus the disturbance impact is considered low. ·
Impacts resulting from improper dumping of
construction materials/wastes and deposition of dust on vegetation adjacent
to site areas would be resulted in the construction phase. The potential
impacts can be avoided and minimized to acceptable levels through the
implementation of standard good site practice. ·
Sediment and runoff if uncontrolled, would carry
pollutants into Tuen Mun River Channel. With the implementation of adequate
construction site drainage and provision of sediment removal facilities, it
is anticipated that unacceptable water quality impacts on the River Channel
would not be arisen. ·
With the implementation of effective mitigation
measures, construction phase noise disturbance would be minimised. In the
worse-case scenario, alternative similar foraging habitat for Little Egret is
relatively common along Tuen Mun River Channel. With the implementation of
adequate construction site drainage and provision of sediment removal
facilities, unacceptable water quality impacts on the River Channel would not
be arisen. Overall, the potential impact to Little Egret is considered low. Environmentally friendly designs recommended: ·
Noise barrier with transparent panels implemented
in the operation phase would cause potential bird mortality. As the
transparent panels would appear invisible to birds or mirrors the facing
landscape, birds are unable to recognize them as physical barriers. With
bird-friendly design of noise barriers, such as using non-glaring and tinted
materials, putting falcon stickers on the transparent panels, bird collision
due to the noise barrier would be minimized. Environmental benefits of environmental protection
measures recommended: ·
the bird collision due to the noise barrier would
be minimized. |
Landscape and
Visual |
Impact/Problem ·
Approximate
860 trees (out of approximately 1000 existing trees) will be affected by the
construction of traffic improvement works to ·
A
number of open space and planting areas in Tsing Sin Playground, Yan Oi Tong Circuit, On Tin Estate and Tsing Hoi
Playground will be alienated by the temporary works during the construction phase.
Many of the affected areas during the construction will be reinstated after
the construction work.
Approximate 350sqm of open space area (12%) will be permanently lost
in Tsing Hoi Playground and approximate 700sqm of open space area (14%) will
be permanently lost in Tsing Sin Playground due to the road works. ·
There will be visual impact due to the provision of
noise barriers and enclosures. Environmentally
friendly designs recommended ·
Heavy
standard and standard trees will be planted at 1:1 ratio in terms of quantity
to compensate for the felled trees.
·
Vertical greening panels with design theme in area
with adequate sunlight and maintenance access to reflect the local context is
proposed. The green roof for the
noise enclosure have been fully explored and proposed where space for
maintenance access is allowed. Environmental
benefits of environmental protection measures recommended: ·
With the implementation of the mitigation measures
such as the provision of approximate 11,000sqm vertical greening with
thematic treatment along the noise barriers and enclosures facade and
approximate 20,000sqm of green roof proposed on the enclosure, and the
implementation of the Tuen Mun District Planting Scheme, it is believed that
the landscape and visual impact will be brought down to a marginally
acceptable level after 10 years. |
Land
Contamination |
Impact/Problem ·
No potential land contamination concern was
identified within the Project boundary. However indirect concern was identified
at the existing petrol filling station located outside the assessment area
approximately 2m from the boundary. Key environmental problem avoided: ·
Preliminary land contamination survey was proposed
to better understand the baseline condition of the underground media which
might have impacted by the operation at the off-site petrol filling station. Environmental benefits of environmental protection
measures recommended: ·
No adverse land contamination impacts are
anticipated if the proposed protection measures and necessary remediation
actions are carried out. |
Construction Phase
Operation Phase
Construction Phase
Operation Phase
Construction Phase
Operation Phase