2                     Project Description

2.1               Site Location

2.1.1          The Project involves widening the following sections of TMR from dual-two carriageway to dual-three carriageway:-

          Wong Chu Road Section, (from Wong Chu Road Interchange to Tuen Hing Road); and

          Tuen Mun Town Plaza Section, (from Tuen Hing Road to Yan Oi Town Square).

2.2               EIA Study Area

2.2.1          Tuen Mun Road Town Centre section is a primary distributor with high capacity junction. The study area is generally a populated area dominated by high-rise buildings.

2.2.2          As stated in the EIA Study Brief, the boundary of the assessment area for this EIA should be 500m from either side of and along the full stretch of the proposed road alignment, except that, for noise and water quality impact assessments, the study area should be defined by a distance of 300m from the proposed road alignment.  As for LVIA, according to EIA Study Brief No. ESB-161/2006, the study area for the landscape impact assessment shall include all areas within 100m extended from the boundary of the scope of the EIA study.

2.2.3          For noise impact assessment, the study area could be reduced accordingly if the first layer of the noise sensitive receivers (NSRs) is closer than 300m from the road and provide acoustic shielding to those receivers at further distance behind subject to agreement of the Director of Environmental Protection. 

2.2.4          With regard to the visual impact assessment, all sensitive receivers should be assessed within the visual envelope outlining the area of land.  The assessment should include the view on any part of the proposed road and the associated structures.

2.3               Need of the Project, Scope and Benefits

2.3.1          TMRTCS is currently operating close to its capacity. In the morning peak period (7a.m. – 9a.m.), the volume/capacity (v/c) ratios of the southbound two-lane carriageways are in the range of 0.89 – 0.99.  In other words, TMRTCS at these two-lane sections is operating close to its design capacity and there is little spare capacity to cater for future traffic growth.

2.3.2          The objective of the Assignment is to propose improvement measures to resolve the traffic congestion problem of TMRTCS.  The traffic improvement option developed under the Feasibility Stage were compared and evaluated and bring forward in this Assignment for the detailed design and construction.

2.3.3          Without the Project, TMRTCS roads will operate to its design capacity and will be severely affected as it becomes a bottleneck due to increased traffic from HK-SWC and growth in the territory.  Congestions and queues would be resulted along this section of the road and it would finally adverse the HK-SWC traffic as well as Tuen Mun residents.


2.3.4          The scope of the Project comprises:

a)           Widening of the Tuen Mun Road Town Centre Section between Yan Oi Town Square to Wong Chu Road with one additional traffic lane for both Kowloon bound and Yuen Long bound carriageways;

b)           Construction of a one-lane flyover to connect Tsing Hoi Circuit and Tuen Mun Road Kowloon bound carriageway;

c)           Improvement of existing traffic light signal-controlled junctions along Castle Peak Road;

d)           Re-provision of four numbers of existing footbridges;

e)           Installation of cantilever/vertical noise barriers and noise enclosures; and

f)             Associated works including slope, drainage, landscaping, water and utility works; installation of traffic control & surveillance systems; and modification of directional signs.

2.4               Considerations of Alternative Schemes for Tuen Mun Road Town Centre Section (TMRTCS) Traffic Improvement

2.4.1          For the Feasibility Study under the HyD Agreement No. CE 38/2005(HY), four options have been considered for traffic improvement of Tuen Mun Road Town Centre Section.  The four options include:

Ÿ             Option 1 – Sam Shing Hui Slip Road Option: This option suggested a new interchange constructed at Sam Shing Hui

Ÿ             Option 2 – Tunnel Option: This scheme was initiated by TMDC members during consultations

Ÿ             Option 3 – Dual 3-lane Widening Option which is currently adopted

Ÿ             Option 4 – Dual 3-lane Widening combined with modified slip road option

2.4.2          An Option Assessment Report was completed under Agreement No. CE 38/2005 (HY) and the recommendations were brought forward to this Investigation, Design and Construction Assignment.  The above four traffic improvement options were compared and evaluated against the criteria including traffic benefits, social benefits, engineering feasibility, environmental impacts, land requirements, programme and costs.

2.4.3          Having assessed and evaluated each of these options, the D3 Option was selected as the preferred option of the Project. The recommended option was presented to the Tuen Mun District Council (TMDC) on 10 November 2006. The TMDC had no objection to the implementation of the recommended option and reiterated the urgency of the Project.

2.4.4          The text below summarizes the key findings of each option.      

Option 1 (Sam Shing Hui Slip Road Option)

2.4.5          This option involves building an additional interchange consisting of two new slip roads to connect Tuen Mun Road and Castle Peak Road (CPR) near Sam Shing Estate to alleviate the traffic problem of TMRTCS. The layout is shown in Figure 2.1. The scheme is to attract traffic used to travel along TMRTCS to use CPR. The traffic diversion would inevitably increase the traffic flows along CPR and the performance of the junctions along CPR would be adversely affected.  As such, it is necessary to implement the junction modification to mitigate the effect on CPR junctions. The scheme would bring benefits to relieve the TMR traffic. However, the actual performance of the scheme is subject the actual driver behaviour or decisions on choosing CPR instead of TMR.

2.4.6          The Tuen Mun District Council (TMDC) Traffic and Transport Committee (T&TC) were consulted on the Additional Interchange Scheme on 13 May 2005 and 29 June 2005.  However, the DC Members and local residents strongly objected to this option.  They alleged that the proposed additional interchange could not possibly solve the traffic problems in the TMRTCS.  More importantly, they claimed that the additional interchange would adversely affect their environment and might probably degrade the value of their properties nearby.

2.4.7          The option incurred the lowest capital cost and recurrent cost. The traffic benefit is comparable to the recommended option (Option 3 – D3 Widening Option). However, due to the strong objection from the public, this option is not recommended.

Option 2: (Tunnel Option)

2.4.8          The tunnel option was initiated by Tuen Mun DC members.  An optimal scheme for the tunnel option as shown in Figure 2.2 & 2.3.  The tunnel running between Tsing Yung Terrace and Tsing Tin Interchange would need to be constructed by cut and cover method in view of the topographic condition and the shallow depth requirements to allow connection to the existing highway. This option was considered not feasible as the tunnel excavation and construction works will require closure of existing traffic lanes at TMRTCS.  TMR is a sensitive “Red” route on which lane closure is prohibited during peak hours under normal circumstance. Construction of the proposed tunnel would take several years. It is necessary to implement substantial temporary traffic measure to divert traffic to the adjacent local road networks at the town centre.  However, traffic diversion is not practicable in view of capacity of local road and the junctions. Therefore, this option is considered not feasible and not recommended.      

Option 3: (Dual 3-lane Widening Option which is currently adopted)

2.4.9          Under this option, the existing dual 2-lane carriageway of TMRTCS will be widened to a dual 3-lane highway. The traffic directly benefits from the road widening without the traffic diversion as required in Option 1. It is noted the traffic performance of the tunnel option would be better than this option as the tunnel option which provides an extra 2 lanes on each direction. However, the construction of tunnel would require closure of Tuen Mun Road Town Centre Section for years while this option would be able to maintain the existing traffic. This is of paramount importance to keep Tuen Mun Road live since it serves as one of the key linkages to the North West New Territories.

2.4.10      As the works under this option involves substantial widening of existing distributor road, the Project will be classified as a Designated Project and require full compliance to various regulations as stipulated in EIA Ordinance.  As a result, the road widening works will be associated with a very extensive noise barrier and noise enclosure along TMRTCS.  The construction of noise enclosure would impose substantial persisting visual impact to the adjacent VSRs. However, on the other hand, it is an opportunity to address the public request for mitigating the noise nuisance created by TMRTCS traffic.  This is in fact one of the key concerns within the Tuen Mun District.

Option 4: (Dual 3-lane Widening combined with modified slip road option)

2.4.11      It is a combined scheme of Option 1 and Option 3. It involves upgrading of existing dual 2-lane carriageway of TMRTCS to dual 3-lane carriageway and construction of additional interchange near Sam Shing Estate. Although the layout of the new slip roads is different from Option 1 as shown in Figure 2.4, it is expected strong objection will be received from the public with the reasons similar to that for Option 1.  Hence, Option 4 was not selected.

Recent Consultations and Recent Developments

2.4.12      The D3 option was presented to the TMDC T&TC on 10 November 2006 and was well-received by TMDC. A number of consultations to TMDC and site meetings with District Facilities Management Committee (DFMC) members of TMDC have also been carried out on various aspects of the Project, including roadworks, trees, noise barriers/enclosures, greening designs of noise barriers/enclosures. The following table summarises the consultation meetings.

Date

Subject

14/9/2007

TMDC T&TC meeting on road widening works and noise barriers

21/9/2007

TMDC EHDDC meeting on road widening works and noise barriers

19/2/2008

TMDC DFMC Meeting on Tree Treatment

14/3/2008

TMDC T&TC meeting on road widening works and noise barriers

29/4/2008

Task Group Meeting of DFMC on Tree Treatment

15/5/2008

Site meeting with Task Group members of DFMC on tree planting areas and species

28/5/2008

Site meeting with Task Group members of DFMC on tree planting areas and species

21/11/2008

TMDC EHDDC meeting on Noise Barrier and Noise Enclosure Greening Designs

 

2.4.13      Recently, the Final Report for the Tuen Mun - Chek Lap Kok Link and Tuen Mun Western Bypass – Feasibility Study under CE 28/2005 (HY) indicates that even with both the Tuen Mun Western Bypass and TMRTCS widening works in place in 2021, the critical section of TMRTCS is also predicted to operate over its design capacity with v/c ratio = 1.02 during the critical AM peak hour. Thus the widening works along TMRTCS is necessary to relieve the traffic congestions.

2.5               Construction Methods and Engineering Requirements

2.5.1          The widening of the approximate 1.5km long at-grade road is a very complicated construction process that warrant careful planning on the construction sequences and activities.  For the purpose of this EIA Study, two alternative construction methods are derived and evaluated as following:

(a)         Widening and re-construction by partly closing existing lanes of Tuen Mun Road:

The advantage of this construction method is that a shorter construction period can be achieved thus resulting construction impacts of shorter term.  However, there are very significant drawbacks as described follows:

·                 Higher impacts on noise and air quality during construction period;

·                 Reduce existing carrying capacities of Tuen Mun Road;

·                 Result in frequent congestions; and

·                 Disturbance to existing road users and Tuen Mun residents;

(b)         Widening and re-construction of Tuen Mun Road in stages without affecting the current lane arrangements:

Under this option, the concerned section of Tuen Mun Road will be widened and re-constructed in stages involving multi-construction stages and temporary traffic arrangement (TTA).  Though the construction period will be longer, the following advantages can be achieved:

·                 Existing carrying capacities of Tuen Mun Road can be maintained;

·                 Less noise and air quality impacts during construction period thus more manageable; and

·                 Less disturbance to existing road users and Tuen Mun residents, in terms of traffic.

2.5.2          To conclude, as the current Tuen Mun Road is a major trunk road linking between Tune Mun and Kowloon/ Tsuen Wan, closing any part of existing lanes would result in reduction of the current carrying capacities of TMR thus having a huge adverse impact to both the traffic and the Tuen Mun residents. Despite the advantages that option (a) offered, maintaining the existing carrying capacities would be a prerequisite requirement of the Project and the drawbacks under option (b) are manageable and acceptable. Therefore, it is considered that option (b) should be adopted.  

2.6               Works Programme

2.6.1          The construction of the Project is originally planned to commence in late 2008 for completion by 2010. Due to a number of factors and various design developments, the commencement of the Project is postponed and the completion date will be delayed to 2012.

2.6.2          As a result from the change of completion date to 2012, a review on the traffic figures adopted in this assessment has been carried out. The 2025 traffic forecast endorsed by TD for use in this assessment was derived from the 2003-based TPEDM SI planning data. However, this set of planning data is now superseded by the 2006-based TPEDM SI planning data which was released by PlanD in mid 2008. Comparing the 2027 population and employment data in NWNT from the 2006-based TPEDM SI against the assumed 2025 population and employment data adopted in the 2025 traffic forecast, the 2027 figures obtained from the 2006-based TPEDM SI planning data are even smaller than the assumed 2025 figures adopted in the 2025 traffic forecast which were developed with reference to the 2003-based TPEDM SI planning data. There are some reductions in population and employment assumptions in the 2006-based TPEDM SI planning data. Since the traffic flows on TMRTCS are in proportion to the population and employment of NWNT (i.e. Tuen Mun/Tin Shui Wai/Yuen Long areas), the endorsed 2025 traffic forecast for the EIA are derived from a set of relatively higher population and employment assumptions. Hence even the assessment year of the EIA is postponed to 2027 and the traffic forecast for the EIA is to be updated with the latest set of 2006-based TPEDM SI planning data, the 2027 traffic forecast so produced would still be anticipated to be less than the endorsed 2025 traffic forecast. Therefore, the current traffic data adopted represents a critical situation.

2.6.3          The preliminary construction programme of the Project is shown on Appendix 3.5.

2.7               Related Projects

2.7.1          The Project would have interface with the following projects:

·             Widening of Tuen Mun Road at Tsing Tin Interchange under Contract No. HY/2007/14;

·             Reconstruction and Improvement of Tuen Mun Road – Sam Shing Hui Section under Contract No. HY/2008/11;

The site boundaries of the above projects are located within 500m study area of this Project and their construction periods would overlap with this Project. The construction for Contract No. HY/2007/14 commenced in June 2008 for completion in 2010 whereas Contract No. HY/2008/11 is scheduled to commence in mid 2009 for completion in mid 2014.  The location of concurrent projects within 500m of the study area is indicated in Figure 1.1.