3.1.1
Noise
will be one of the key environmental issues in this Project. It is anticipated
that noise from the use of powered mechanical equipment (PME) on site and the
haulage of construction materials during the construction of the Project will
cause a nuisance to the nearby noise sensitive receivers. During operation
phase, road traffic noise would have significant noise impacts on the adjacent
noise sensitive receivers if unmitigated.
3.1.2
This
section presents a detailed noise assessment for the construction and operation
phases of the Project. The representative noise assessment points to be
affected by the Project are identified. The relevant noise legislation,
assessment methodology, potential noise impacts together with an evaluation of
noise mitigation measures aimed to alleviate the impacts are presented in this
section.
General
3.2.1
Noise
impacts have been assessed in accordance with the criteria and methodology given
in the Technical Memoranda (TMs) under the Noise Control Ordinance (NCO), and
the Technical Memorandum on Environmental Impact Assessment Process (EIA-TM).
3.2.2
The
Noise Control Ordinance (Cap 400) (NCO) and the Environmental Impact Assessment
Ordinance (Cap 499) (EIAO) provide the statutory framework for noise
control. Guidelines concerning the
assessment methodology and relevant criteria are provided in the supporting
Technical Memoranda (TMs).
3.2.3
The
following TMs are applicable to the control of noise from construction
activities:-
l
TM on Environmental Impact
Assessment Process (EIA-TM)
l
TM on Noise from Construction Work
other than Percussive Piling (GW-TM)
l
TM on Noise from Percussive Piling
(PP-TM)
l
TM on Noise from Construction Work in
Designated Areas (DA-TM)
Construction Noise –
Percussive Piling
3.2.4
Percussive
piling is prohibited at any time on Sundays and public holidays and during the
weekday evening and night-time hours (i.e. 1900 to 0700 hours, Monday through
Saturday). A Construction Noise Permit (CNP) is required for such works during
the weekday daytime hours (i.e. 0700 to 1900 hours, Monday through Saturday).
3.2.5
When
assessing a CNP application for carrying out percussive piling, the Noise
Control Authority is guided by the PP-TM. The Noise Control Authority will pay
particular concern on the difference between the Acceptable Noise Levels
(ANLs), as promulgated in the PP-TM and the Corrected Noise Levels (CNLs) that
are associated with the proposed piling activities. Depending on the level of
noise impact on nearby Noise Sensitive Receivers (NSRs), the Noise Control
Authority would determine the time periods for percussive piling operation. The
time periods are indicated in Table 3.1.
Table 3.1 Permitted Hours of
Operation for Percussive Piling (not involving the use of diesel, pneumatic
and/or steam hammers)
Amount by which CNL
excceds ANL
|
Permitted hours of
operation on any day not being a holiday
|
10 dB(A) <
CNL-ANL
|
0800 – 0900 and 1230 –
1330 and 1700 - 1800
|
0 dB(A) <
CNL-ANL £ 10 dB(A)
|
0800 – 0930 and 1200 –
1400 and 1630 - 1800
|
CNL-ANL £ 0 dB(A)
|
0700
– 1900
|
3.2.6
The
Government is committed to phase out the use of diesel, pneumatic and steam hammer
pile drivers which are particularly noisy. There are more stringent
requirements for the use of diesel, pneumatic and steam hammer after 1 October
1999.
3.2.7
In
this Project, percussive piling may be employed. The Contractor will apply for the Construction
Noise Permit (CNP) if necessary.
The Noise Control Authority will judge these at the time of CNP
application.
Construction Noise –
General Construction
3.2.8
Noise
generated by general construction works during normal working hours (i.e. 0700
to 1900 hours on any day not being a Sunday or public holiday) fall within the
scope of the EIA-TM. The recommended noise standards are presented in Table
3.2.
Table 3.2 EIA-TM Daytime
Construction Noise Limit
Uses
|
Noise Standard
(Leq 30min dB(A))
|
Domestic Premises
|
75
|
Educational Institutions (normal periods)
|
70
|
Educational Institutions (during examination periods)
|
65
|
The above standards apply to uses
which rely on opened windows for ventilation.
Construction Noise –
During Restricted Hours
3.2.9
The
NCO provides statutory controls on general construction works during the
restricted hours (i.e. 1900 to 0700 hours Monday to Saturday and at any time on
Sundays and public holidays). The use of PME for the carrying out of
construction works during the restricted hours would require a CNP. The Noise
Control Authority is guided by the GW-TM when assessing such an application.
3.2.10
When
assessing a CNP application for the use of PME, the Noise Control Authority
will compare the ANLs as promulgated in the GW-TM, and the CNLs (after
accounting for factors such as barrier effects and reflections) associated with
the agreed PME operations. The CNP may be issued if the CNL is equal to or less
than the ANL. The ANLs are related to the noise sensitivity of the area in
question and the Noise Control Authority will judge these at the time of the
CNP application. As conditions may vary between the time of the EIA for a
project and the time of a CNP application, the assignment of any Area
Sensitivity Ratings in the EIA is not binding upon the Noise Control Authority.
The relevant ANLs are shown in Table 3.3.
Table 3.3 Acceptable Noise
levels (ANL, Leq 5min dB(A))
Time Period
|
Basic Noise Levels
|
ASR A
|
ASR B
|
ASR C
|
All days during the evening (1900-2300) and general
holidays (including Sundays) during the day and evening (0700-2300)
|
60
|
65
|
70
|
All days during the night-time (2300-0700)
|
45
|
50
|
55
|
3.2.11
In
addition to the general controls on the use of PME during the restricted hours,
the Noise Control Authority has implemented a more stringent scheme via the DA-TM.
The DA-TM regulates the use of five types of Specified Powered Mechanical
Equipment (SPME) and three types of Prescribed Construction Work (PCW) which
are non-PME activities, in primarily densely populated neighborhoods called
Designated Areas (DAs) during restricted hours. The SPME and PCW are shown in
Table 3.4.
Table 3.4 Specified Powered
Mechanical Equipment and Prescribed Construction Work Controlled under DA-TM
Specified Powered Mechanical Equipment
(SPME)
|
Prescribed Construction Work (PCW)
|
l
Hand-held Breaker
l
Bulldozer
l
Concrete Lorry Mixer
l
Dump Truck
l
Hand-held Vibratory
Poker
|
l
Erection or Dismantling
of Formwork or Scaffoldings
l
Loading, Unloading or Handling
of Rubble, Wooden Boards, Steel Bars, Wood or Scaffolding Material
l Hammering
|
3.2.12
In
the interest of offering additional protection to the population, PCW is
generally banned inside a DA during restricted hours. As for the use of SPME, it
would be necessary to comply with DA-TM noise level requirements that are 15
dB(A) less than those listed in the GW-TM before a CNP may be issued.
3.2.13
Factors
such as the assigning of Area Sensitivity Rating, ANLs etc could affect the
assessment results of a CNP application. The Noise Control Authority would
decide these at the time of assessment of such an application based on the
contemporary situations/conditions. It should be noted that the
situations/conditions around the sites may change from time to time.
3.2.14
Despite any description or assessment made in this EIA
Report on construction noise
aspects, there is no guarantee that a CNP will be issued for the project
construction. The Noise Control Authority will consider a well-justified CNP
application, once filed, for construction works within restricted hours as
guided by the relevant Technical Memoranda issued under the Noise Control
Ordinance. The Noise Control Authority will take into account contemporary
conditions/ situations of adjoining land uses and any previous complaints
against construction activities at the site before deciding whether to grant a
CNP. Nothing in this EIA Report
should bind the Noise Control Authority in making its decision. If a CNP is to be issued, the Noise
Control Authority should include in the permit any condition it thinks
fit. Failure to comply with any
such conditions will lead to cancellation of the CNP and prosecution under the
NCO.
3.2.15
In
case that the CNL exceeds the ANL, a CNP may be granted if it can be
demonstrated to the satisfaction of the Authority that carrying out the
construction work during restricted hours would cause less public annoyance or
inconvenience than would be caused by carrying out the work during
non-restricted hours.
Operational Noise – Traffic
Noise
3.2.16
The
EIA-TM provides guidance on acceptable road traffic noise levels at openable
windows of various types of noise sensitive buildings. The relevant criteria
are shown in Table 3.5.
Table 3.5 EIA-TM Road Traffic
Noise Planning Criteria
Uses
|
Road Traffic Noise
L10, (1hr) dB(A)
|
Domestic Premises
|
70
|
Hotel and Hostels
|
70
|
Offices
|
70
|
Educational Institutions
|
65
|
Places of Public Worship and Courts of Law
|
65
|
Hospital, Clinics
and Homes for the aged
|
55
|
Note: The criteria presented in the
above apply to noise sensitive uses which rely on opened window for
ventilation
|
3.3.1
The
existing noise environment in the vicinity of the Project area is dominated by
the road traffic on the existing Tuen
Mun Road, Pui To Road, Tuen Hing Road, Wong Chu Road
and Castle Peak Road.
3.3.2
The
existing land uses in the vicinity of the Project site are mainly for
residential and recreational uses. Besides, there are some educational and GIC
land uses scattered along the concerned roads.
3.4.1
Existing
NSRs including residential uses, places of worship, etc relying on opened
windows for ventilation and educational institutions within 300m of study area were identified in
accordance with Section 3 of Annex 13 of the EIA-TM.
3.4.2
There
is an open storage area adjacent to the CSBS (Mrs. Aw Boon Haw Secondary
School). The land use is zoned as GIC area under the Tuen Mun Outline Zoning
Plan S/TM/24 and no planning application for change of land use was found on
the website (http://www.ozp.tpb.gov.hk/default.aspx)
for e-Planning Archives of Planning Department in July 2008. A site office for
this Project will be located at this open storage area.
3.4.3
By
considering the acoustic shielding of the front layer receivers, the existing
representative NSRs were identified for noise assessment with reference to
topographic maps and field surveys. For the purpose of the noise assessment, a
number of representative NSRs which were considered to be potentially
worst-affected were selected and has been agreed with EPD (The relevant
correspondence letter is attached in Appendix 3.1). Photographs of all the identified
existing NSRs are provided in Appendix 3.2. The representative NSRs for
construction and traffic noise assessments are summarised in Tables 3.6
below. Their locations are illustrated in Figures 3.1A to 3.1C.
Table 3.6 Representative NSRs
for Noise Assessments
NSR
|
Description
|
Use
|
Traffic Noise
Criteria
dB(A)
|
No. of Storey
|
TMC
|
Tuen Mun
Church
|
Place of worship
|
65
|
6
|
PAC
|
Parkview Court
|
Residential
|
70
|
28
|
ELC
|
ELCHK Tuen
Mun Lutheran
Church Dzwen Sheng Tang
Kindergarten
|
School
|
65
|
3
|
YLB 1
|
Yik Lee
Building
|
Residential
|
70
|
5
|
YLB 2
|
Yik Lee
Building
|
Residential
|
70
|
2
|
PEN
|
PEN Church of Hong Kong
Sheltered Workshops and Hostel
|
GIC
|
70
|
3
|
KHB
|
Kam Hing
Building
|
Residential
|
70
|
25
|
EC1
|
Eldo Court
|
Residential
|
70
|
24
|
EC2
|
Eldo Court
|
Residential
|
70
|
24
|
RDG
|
Rose Dale Garden
|
Residential
|
70
|
25
|
FEC *
|
Far East Consortium
Tuen Mun
Central Building
|
Residential
|
70
|
10
|
HFB
|
Hing Fat
Building
|
Residential
|
70
|
15
|
OC
|
Orchid Court
|
Residential
|
70
|
16
|
FM *
|
Forward Mansion
|
Residential
|
70
|
11
|
HTB *
|
Hing Tai
Building
|
Residential
|
70
|
8
|
FHB
|
Fu Hang Building
|
Residential
|
70
|
5
|
MSB
|
Man Shing
Building
|
Residential
|
70
|
14
|
SC
|
Sun Court
|
Residential
|
70
|
14
|
TMTP1 *
|
Tuen Mun
Town Plaza
|
Residential
|
70
|
27
|
TMTP2
|
Tuen Mun
Town Plaza
|
Residential
|
70
|
27
|
TMTP3
|
Tuen Mun
Town Plaza
|
Residential
|
70
|
27
|
TMTP4
|
Tuen Mun
Town Plaza
|
Residential
|
70
|
29
|
TMTP5
|
Tuen Mun
Town Plaza
|
Residential
|
70
|
27
|
TMTP6
|
Tuen Mun
Town Plaza
|
Residential
|
70
|
27
|
WG1
|
Waldorf Garden
|
Residential
|
70
|
26
|
WG2 *
|
Waldorf Garden
|
Residential
|
70
|
26
|
NTM1
|
New Town Mansion
|
Residential
|
70
|
22
|
NTM2
|
New Town Mansion
|
Residential
|
70
|
22
|
CMA *
|
CMA Choi Cheung Kok
Secondary School
|
School
|
65
|
6
|
LWF *
|
Yan Oi Tong Madam
Lau Wong
Fat Primary
School
|
School
|
65
|
7
|
THC1
|
Ting Hoi Court
|
Residential
|
70
|
17
|
THC2
|
Ting Hoi Court
|
Residential
|
70
|
17
|
TMF *
|
Tuen Mun Fa Yuen
|
Residential
|
70
|
17
|
LCK *
|
Lui Cheung
Kwong Lutheran
College
|
School
|
65
|
6
|
LPB
|
Lee Bo Building
|
Residential
|
70
|
28
|
LBB
|
Lai Bo Building
|
Residential
|
70
|
27
|
CLFY1 *
|
Chi Lok Fa Yuen
|
Residential
|
70
|
16
|
CLFY2
|
Chi Lok Fa Yuen
|
Residential
|
70
|
15
|
CLFY3
|
Chi Lok Fa Yuen
|
Residential
|
70
|
16
|
CLFY4
|
Chi Lok Fa Yuen
|
Residential
|
70
|
15
|
CLFY5
|
Chi Lok Fa Yuen
|
Residential
|
70
|
15
|
CLFY6
|
Chi Lok Fa Yuen
|
Residential
|
70
|
15
|
TFH *
|
On Ting Estate (
Ting Fuk House)
|
Residential
|
70
|
27
|
LCKP *
|
Lui Cheung
Kwong Lutheran
Primary School
|
School
|
65
|
7
|
RG
|
Rainbow Garden
|
Residential
|
70
|
18
|
HKG
|
Hong King
Garden
|
Residential
|
70
|
18
|
TTP *
|
Tung Wah Group of Hospitals Tai Tung Pui Social
Service Building
|
GIC
|
55 / 70 #
|
11
|
JCP
|
JC Place
|
Residential
|
70
|
18
|
CSBS *
|
CSBS Mrs. Aw Boon Haw
Secondary School
|
School
|
65
|
6
|
HG
|
Harvest Garden
|
Residential
|
70
|
17
|
HFDG
|
Hanford Garden
|
Residential
|
70
|
26
|
SSE
|
Sam Shing Estate
|
Residential
|
70
|
27
|
SST
|
Sam Shing
Temple
|
Temple
|
65
|
1
|
KFG1A
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG1B
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG2A
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG2B
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG2C
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG2D
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG3A
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG3B
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG3C
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG3D *
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG4A
|
Kam Fai Garden
|
Residential
|
70
|
15
|
KFG4B
|
Kam Fai Garden
|
Residential
|
70
|
15
|
SHT
|
Tuen Mun Sin Hing
Tong
|
Temple
|
65
|
2
|
SLC1
|
Po Lun House, Siu Lun Court
|
Residential
|
70
|
35
|
SLC4
|
Sui Lun House, Siu Lun Court
|
Residential
|
70
|
35
|
Remark:
* NSRs
with asterisk are representative NSRs assessed for both traffic noise impact
and construction noise impact; others are assessed for traffic noise impact
only.
# The
noise criteria of TTP for 1F to 4F is 55 dB(A).
Construction Noise
3.5.1
Construction
noise impact was assessed by adopting the standards acoustic principles and the
methodologies relevant to technical memoranda issue under the Noise Control
Ordinance, primarily the GW-TM.
3.5.2
During
daytime from 0700 to 1900 hours on weekdays other than general holidays, the
assessment of construction noise was carried out in accordance with the
methodology stipulated in paragraphs 5.3 and 5.4 of Annex 13 and the criteria
in Table 1B of Annex 5 of the EIA-TM.
3.5.3
Sound
Power Levels (SWLs) of the equipment were taken from Table 3 of the GW-TM. The
assessment also made reference to the British Standards BS 5228: Part 1:1984
Noise Control on Construction and Open Sites, Part1: Code of Practice for Basic
Information and Procedures for Noise Control. Sound power levels of equipment
will be made reference to these TMs and the BS5228, where applicable, and the
emission levels in previous projects in Hong Kong
would also be referred.
3.5.4
Schedules
of powered mechanical equipment (PME) for different construction tasks of the
Project and other concurrent construction activities of other projects during
normal daytime working hours are presented in Appendix 3.3. The Project
Proponent has confirmed that the plant inventory is valid for the Project
works.
3.5.5
It
was assumed that all PME items required for a particular construction activity
would be located at the notional or probable source position of the segment
where such activity is to be performed.
The assessment was based on the cumulative SWL of PME likely to be used
for each location, taking into account the construction period in the vicinity
of the receiver location. To
predict the noise level, PME was divided into groups required for each discrete
construction task. The objective was to identify the worst case scenario
representing those items of PME that would be in use concurrently at any given
time. The sound pressure level of each construction task was calculated,
depending on the number of plant and distance from receivers. The noise levels
at NSRs were then predicted by adding up the SWLs of all concurrent
construction tasks.
3.5.6
A
positive 3 dB(A) façade correction was added to the predicted noise levels in
order to account for the facade effect at each NSR.
3.5.7
Accordingly
the unmitigated construction noise impacts at the identified NSRs were
predicted. Practicable direct mitigation measures including use of quieter
equipment, movable barriers, enclosures and quieter alternative methods were
recommended if exceedance of relevant criteria was predicted. In case where the
mitigated noise levels still exceeded the relevant criteria, the duration of
the noise exceedance would be estimated.
3.5.8
The construction of the Project
is originally to be commenced in late 2008 and completed by 2010. Due to a
number of factors and various design developments, the commencement of the
Project is postponed and the completion date will be delayed to 2012. Details of construction tasks are as
follows:
l
Site clearance, fencing &
hoarding;
l
Construction of a flyover and
modification to existing flyover;
l
Demolition of 4 existing footbridges
and construction of 4 new footbridges;
l
At grade road widening, i.e.
demolition of existing verges, kerbs, central reserves, excavation works, minor
slopeworks, realign the kerb, etc;
l
Road paving and road marking;
l
Construction of noise barrier and
noise enclosures;
l
Landscape works; and
l
Tree transplantation and
compensation works.
3.5.9
As
the road widening works are to be undertaking on existing Tuen Mun Road, working space for the
works is limited. It is anticipated that the works will be conducted in batches
progressively with maximum of 170m works front at a time. The above
construction activities would not be taken place concurrently.
3.5.10
The
programme of the Project may overlap with the project of “Widening of Tuen Mun
Road at Tsing Tin Interchange” which commenced in June 2008 and would be
completed in 2010. However, the
separation distance between both projects boundary would be more than 300m,
cumulative noise impacts are therefore not expected.
3.5.11
The
portion of project site of “Reconstruction and Improvement of Tuen Mun Road -
Sam Shing Hui Section, Contract No.HY/2008/11” near Kam Fai Garden is planned to
be commenced in mid 2009 and completed by end 2010. The Tuen Mun Town Centre Project is
planned to be commenced in end 2009.
Upon the completion of the works, this portion of the site would be
handover to the Tuen Mun Town Centre Project for construction works. The works for Tuen Mun Town Centre
Project from end 2009 to end 2010 would be mainly tree transplantation and
felling works. It is anticipated
that there would be no overlapping of major construction activities of both
projects.
3.5.12
Noise
sources from the areas greater than 300m
of a given NSR are excluded from the assessment.
Operation Noise
3.5.13
Traffic
noise was predicted using the methodology provided in the UK Department of
Transport Calculation of Road Traffic Noise (CRTN) 1988. All noise levels were expressed in terms
of L10(1-hour) dB(A). The value of L10 (1-hour) dB(A) is
the noise level exceeded for just 10% of the time over a period of one hour.
For comparison with the specified noise level or the EIA-TM standards, the
relevant noise level from traffic was to be rounded to the nearest whole number
(0.5 being rounded up).
3.5.14
Considering
the scope of this Project, road sections were classified as the following
categories for purpose of road traffic noise assessment:-
l
‘New’ Roads - roads within the
meaning of Item A.1, Part I, Schedule 2 of the EIAO) that are completely new or
major modification to an existing road sections resulting in 25% increase in
lanes or substantial changes in alignment or characters of the road due to the
proposed Project. In this Project, whole section of
the Tuen Mun Road
within the Project boundary is identified as new road with the exception of the
realigned sections of Tsing Hoi Circuit and a small portion near the northern
end. Sensitivity tests for aforesaid sections have been carried out and the
results demonstrating that there is no adverse traffic noise impact to the
nearby NSRs in accordance with the EIA-TM. Results of the sensitivity test are
given in Appendix 3.9.
l
‘Existing’ Roads - that is, roads
that are unchanged or subject to minor changes (i.e. less than 1.0 dB(A) noise
contribution from the improved road to the overall noise level) by the Project
except for possibly taking additional traffic.
3.5.15
The
‘New’ roads defined for the assessment are shown in Figures 3.2A to 3.2C.
3.5.16 As
mentioned in Section 2.6.2, the Project is originally to be completed in 2010 but now is postponed
to 2012. As a result from the
change of completion date to 2012, a review on the traffic figures adopted in
this assessment has been carried out. The 2025 traffic forecast endorsed by TD
for use in this assessment was derived from the 2003-based TPEDM SI planning
data. However, this set of planning data is now superseded by the 2006-based
TPEDM SI planning data which was released by PlanD in mid 2008. Comparing the
2027 population and employment data in NWNT from the 2006-based TPEDM SI
against the assumed 2025 population and employment data adopted in the 2025
traffic forecast, the 2027 figures obtained from the 2006-based TPEDM SI
planning data are even smaller than the assumed 2025 figures adopted in the
2025 traffic forecast which were developed with reference to the 2003-based
TPEDM SI planning data. There are some reductions in population and employment
assumptions in the 2006-based TPEDM SI planning data. Since the traffic flows
on TMRTCS are in proportion to the population and employment of NWNT (i.e. Tuen
Mun/Tin Shui Wai/Yuen Long areas),
the endorsed 2025 traffic forecast for the EIA are derived from a set of
relatively higher population and employment assumptions. Hence even the
assessment year of the EIA is postponed to 2027 and the traffic forecast for
the EIA is to be updated with the latest set of 2006-based TPEDM SI planning
data, the 2027 traffic forecast so produced would still be anticipated to be
less than the endorsed 2025 traffic forecast. Therefore, adoption of endorsed
2025 traffic figure in the assessment is on a conservative side.
3.5.17
Apart
from the traffic noise after completion of the road improvement works,
prevailing traffic noise level (based on the traffic data at 2008 before
project commencement) have also been assessed for eligibility test for noise
insulation works. The projected 2025 peak hour traffic flows and 2008
prevailing traffic flow data are presented in Appendix 3.4. The agreement letter from Transport
Department on the use of the projected traffic data for this Study is attached
in Appendix 3.4.
3.5.18
The
unmitigated traffic noise levels at the selected NSRs were predicted. If an
exceedance of noise limit at any NSR occurred, noise mitigation measures would
be considered to alleviate the traffic noise impact.
3.5.19
Direct
mitigation measures would be proposed for ‘New’ roads (i.e. within the meaning
of Item A.1 of Schedule 2 of EIAO-TM) if there would be an adverse
environmental impact. If the NSRs are affected by noise from other existing
roads, direct mitigation measures are required to reduce the noise from the
‘New’ roads to a level that it:-
l
is not higher than the noise
standard; and
l
has no significant contribution to the overall noise from other existing
roads, if the cumulative noise level (i.e. noise from the new road together
with other existing roads) exceeds the noise standard.
3.5.20
If
any facades of existing NSRs are still exposed to predicted noise levels
exceeding the relevant noise criteria after implementation of all feasible
direct mitigation measures, provision of indirect technical remedies in the
form of acoustic insulation and air conditioning should be considered under the
EIAO GN 12-2005, “Road Traffic Noise Impact Assessment Under the Environmental Impact
Assessment Ordinance”. Eligibility for indirect technical remedies will be
tested against the following three criteria:-
l
The predicted overall noise level, L10(1-hour),
from the “New” road, together with other traffic noise in
the vicinity must be above 70 dB(A) for domestic premises and 65 dB(A) for
educational institutions;
l
The predicted overall noise level is
at least 1.0 dB(A) more than the prevailing traffic noise level; and
l
The contribution
to the increase in the predicted overall noise level from the “New” road must be at least 1.0 dB(A).
3.5.21
The
total number of existing dwellings, classrooms and other noise sensitive
elements that may be qualified for indirect technical remedies are then estimated.
Construction Phase
3.6.1
Potential
construction noise impacts may arise from the construction works outlined in
previous section.
Operation Phase
3.6.2
Road
traffic noise will arise from the new roads constructed or modified under the
Project and the adjacent existing roads.
Construction
Phase
3.7.1
As
illustrated in the preliminary construction programme attached in Appendix
3.5, some of the construction activities would be carried out concurrently.
In order to predict the noise level in the worst case scenario, the cumulative
effect arising from those concurrent and relative construction activities were
assessed at each representative NSRs.
The programme shown on Appendix 3.5 represents the worst case
scenario for the construction noise assessment. For other programme
arrangements, such as longer construction periods of different construction
activities, less cumulative noise impact is expected.
3.7.2
In
the absence of any mitigation measures, it was found that the predicted noise
levels at all representative NSRs were higher than the relevant construction
noise criteria. The calculated results are summarized in Table 3.7. Detailed
calculations of the unmitigated construction noise levels are presented in Appendix
3.6A.
3.7.3
In
order to alleviate the construction noise impacts at the affected NSRs,
mitigation measures such as adoption of quiet PME or use of movable noise
barriers are required.
Table 3.7 Unmitigated
Construction Noise Levels at Representative NSRs During Normal
Daytime Working Hours
NSR
|
Description
|
Unmitigated Construction Noise Levels*, dB(A)
|
FEC
|
Far East Consortium
Tuen Mun
Central Building
|
75 – 89
|
FM
|
Forward Mansion
|
82 – 89
|
HTB
|
Hing Tai
Building
|
80 – 90
|
TMTP1
|
Tuen Mun
Town Plaza
|
66 – 91
|
WG2
|
Waldorf Garden
|
71 – 87
|
CMA*
|
CMA Choi Cheung Kok
Secondary School
|
67 – 85
|
LWF*
|
Yan Oi Tong Madam
Lau Wong
Fat Primary
School
|
72 – 85
|
TMF
|
Tuen Mun Fa Yuen
|
68 – 91
|
LCK*
|
Lui Cheung
Kwong Lutheran
College
|
64 – 90
|
CLFY1
|
Chi Lok Fa Yuen
|
77 – 91
|
TFH
|
On Ting Estate (
Ting Fuk House)
|
73 – 90
|
LCKP*
|
Lui Cheung
Kwong Lutheran
Primary School
|
67 – 85
|
TTP
|
Tung Wah Group of Hospitals Tai Tung Pui Social
Service Building
|
84 – 91
|
CSBS*
|
CSBS Mrs. Aw Boon Haw
Secondary School
|
72 – 83
|
KFG3D
|
Kam Fai Garden
|
82 – 89
|
* Remark: Boldfaced
value presents the predicted noise level exceed the relevant noise limit. NSR
with asterisk means educational institution.
Operation Phase
3.7.4
Based
on the predicted peak hour traffic flows in 2008 and 2025, the prevailing
traffic noise levels prior to the commencement of the Project and the
unmitigated future traffic noise levels after completion of the Project at the
representative NSRs were calculated.
3.7.5
The
prevailing and unmitigated noise levels at the representative NSRs are provided
in Appendix 3.7A.
3.7.6
The
unmitigated noise levels in year 2025 for place of worship, residential and
schools developments are in the ranges of 67.6 to 81.4 dB(A), 61.0 to 84.7
dB(A) and 70.8 to 83.8 dB(A) respectively. Most of the identified NSRs would
expose to high noise levels exceeding the noise standards due to both the ‘New’
road and existing roads. The severe traffic noise impact is due to the high
traffic volume and percentage of heavy vehicles as well as the close proximity
of the nearby NSRs to the road alignments. Noise mitigation measures on ‘New’
roads are required to alleviate the adverse traffic noise impact.
Construction Noise
3.8.1
Good
site practice and management can significantly reduce the noise impact of
construction site activities on nearby NSRs. The following package of
measures should be followed throughout the construction period:
l
only well-maintained plant should be operated on-site and
plant should be serviced regularly during the construction works;
l
machines and plant that may be in intermittent use should be
shut down between work periods or should be throttled down to a minimum;
l
plant known to emit noise strongly in one direction should,
where possible, be orientated to direct noise away from the NSRs;
l
mobile plant should be sited as far away from NSRs as
possible; and
l
material stockpiles and other structures should be
effectively utilized, where practicable, to screen noise from on-site
construction activities.
3.8.2
The
following sections describe measures which may be considered to reduce noise to
the construction noise limits.
3.8.3
Mitigation
measures are proposed to be implemented in three levels, namely Level 1, which
involves adoption of quiet PME; Level 2, which involves provision of movable
noise barrier; and Level 3, which involves scheduling of construction
activities.
Level 1
Adoption of Quiet PME
Table 3.8 Listing
of Quiet PME Items
Quiet Powered Mechanical Equipment (PME)
|
Identification Code / BS5228
|
Maximum SWL, dB(A)
|
Excavator
|
C8/33
|
102
|
Crane
|
C7/114
|
101
|
Truck
|
C3/59
|
105
|
Concrete Truck
|
C6/35
|
100
|
Poker Vibrator
|
CNP 173
|
102
|
Asphalt Paver
|
C8/24
|
101
|
Roller, vibratory
|
C3/115
|
102
|
3.8.5
With
the use of quiet plant, the predicted noise levels at the NSRs in some months
would still exceed the noise criteria. Detailed calculations of the construction
noise levels at the NSRs with adoption of Level 1 mitigation measures are given
in Appendix 3.6B.
Level 2
Use of Movable Noise Barrier
3.8.6
After
adoption of Level 1 mitigation measures, the predicted construction noise at some
representative NSRs during construction period would still exceed the relevant
noise limits. Therefore, it is
proposed to enhance the noise mitigation by provision of movable noise barrier.
3.8.7
Movable
barriers could be effective in screening noise of particular items of plant
such as poker vibrator and circular saw from reaching the NSRs. A noise
barrier located close to the noise generating component of a PME could produce
at least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant,
depending on the line of sight that could be blocked by the barriers when
viewed from the NSRs.
3.8.8
These
noise barriers should be free of gaps and made of materials having a surface
mass density of at least 15 kg/m2. To improve the effectiveness of noise reduction,
absorptive lining can be adhered on the inner surface of the barrier. The
barrier can be in the form of vertical or bend top barrier with an effective
height of 3m or above.
Its length should be long enough to cover the length of the PME being protected.
It is better to extend both ends of the barrier to exceed the size of the PME
by a distance equal to the separation between the barrier and the PME.
3.8.9
With
the implementation of the above mitigation measures, the mitigated construction
noise levels were predicted. Detailed calculations of the mitigated
construction noise levels are presented in Appendix 3.6C.
Table 3.9 Level 2 Mitigated
Construction Noise Levels at Representative NSRs During Normal
Daytime Working Hours
NSR
|
Description
|
Max Mitigated CNLs, dB(A)
|
FEC
|
Far East Consortium
Tuen Mun
Central Building
|
73
|
FM
|
Forward Mansion
|
73
|
HTB
|
Hing Tai
Building
|
74
|
TMTP1
|
Tuen Mun
Town Plaza
|
74
|
WG2
|
Waldorf Garden
|
71
|
CMA*
|
CMA Choi Cheung Kok
Secondary School
|
69
|
LWF*
|
Yan Oi Tong Madam
Lau Wong
Fat Primary
School
|
68
|
TMF
|
Tuen Mun Fa Yuen
|
75
|
LCK*
|
Lui Cheung
Kwong Lutheran
College
|
74
|
CLFY1
|
Chi Lok Fa Yuen
|
75
|
TFH
|
On Ting Estate (
Ting Fuk House)
|
74
|
LCKP*
|
Lui Cheung
Kwong Lutheran
Primary School
|
70
|
TTP
|
Tung Wah Group of Hospitals Tai Tung Pui Social
Service Building
|
75
|
CSBS*
|
CSBS Mrs. Aw Boon Haw
Secondary School
|
66
|
KFG3D
|
Kam Fai Garden
|
73
|
Remark:
NSR with asterisk means educational
institution.
Boldfaced value presents the predicted noise
level exceed the relevant noise limit.
Bold
and italic value presents the predicted noise level exceed the noise limit for
school during examination periods.
3.8.10
Based
on the results shown in Table 3.9, the predicted construction noise
levels at all residential NSRs would comply with the noise standard stipulated
in the EIA-TM. However, the
predicted construction noise level at education institute NSR LCK would exceed
the noise limit by 4 dB(A) during the normal teaching period.
3.8.11
The
predicted construction noise levels at five representative NSRs of educational
institutions, namely CMA, LWF, LCK, LCKP and CSBS would also exceed the noise
standard of 65 dB(A) by 1 to 9 dB(A) during examination periods.
Level 3
Scheduling of some Construction Activities
3.8.12
In
order to further diminish construction noise impacts at NSR LCK, it is proposed
that site clearance and the following activities at stage 2 (Ch. 28050 – 28200
of TMR) not to be undertaken in the vicinity of this NSR during normal teaching
hours. With the implementation of
these mitigation measures, the predicted noise levels at NSR LCK during normal
teaching period would comply with the noise criterion of 70 dB(A). Detailed calculations of the mitigated
construction noise levels are presented in Appendix 3.6D
·
Truck would not
operate concurrently with other PMEs during tree transplanting and noise barrier foundation work.
·
Tree Transplanting would not be undertaken concurrently with
Bulk Excavation and Utilities Diversion.
·
Construction of Storm Water Drain would not be undertaken
concurrently with Noise Barrier/Enclosure Foundation.
·
Construction of Sub-base and Road Base would not be
undertaken concurrently with Noise Barrier/Enclosure Installation.
·
Road Surfacing, Construction of Road kerbs, Central
Dividers, Parapets, and Installation of Crash Cushion and Sign Gantry would not
be undertaken concurrently.
·
Installation of Gantry and Directional Lighting, and Street
Lighting would not be undertaken concurrently.
3.8.13
In
order to avoid or reduce the construction noise problems at the schools (i.e.
NSR CMA, LWF, LCK, LCKP and CSBS) during examination periods, the Contractor of
the Project would be suggested to liaise with all the relevant schools to check
out their examination periods and activities for preparation of the works
programme. The noise calculations
as presented in Appendix 3.6D demonstrate that these educational
institutes would comply with the noise criterion during examination period with
the scheduling of noisy construction activities. These mitigation measures are as a
reference only, the Contractor can make good planning and arrangement of works
and provide sufficient mitigation plans to alleviate the noise impacts.
Operation Noise
3.8.14
As
mentioned in Section 3.5, direct mitigation measures should be considered or proposed
on road project under the subject DP such that the noise from the “New” road to
a level that it is not higher than the relevant standards and has no
significant contribution to the
overall noise from other existing roads. Based on this principle, mitigation
measures are proposed.
Mitigation Measures
3.8.15
Noise
mitigation measures in form of vertical barriers, cantilever barriers, partial
enclosure or full enclosures have been considered in order to reduce the
excessive noise impacts on the sensitive receivers arising from the Project.
The proposed noise screening structures are mainly reflective type with
transparent panels to reduce the visual intrusion and will be supported at
structural steel frames fixed on concrete parapets. These noise barriers will
have absorptive panels at the lower portion (about 1.5m). An enhanced low noise surfacing to
the standard low noise surfacing (i.e. 30mm thick with aggregate size of 10mm)
will be applied on the portion of carriageway as indicated on Figures 3.4A
and 3.4B. This enhanced low noise surfacing could either be (1) 30mm thick
low noise surfacing of smaller aggregate size (i.e. aggregate size < 10mm)
or (2) thicker low noise surfacing of similar aggregate size (thickness >
30mm).
3.8.16
Layouts
of proposed noise mitigation measures are presented in Figures 3.3A to 3.3C and summarized as below. These noise barriers
should be designed and constructed to comply with the Guidelines on Design of Noise Barriers, March 2001, by
Environmental Protection Department and Highways Department.
3.8.17
With
the recommended noise mitigation measures, the mitigated traffic noise levels
were calculated. The mitigated noise levels at the affected NSRs are provided
in Appendix 3.7A.
3.8.18 With the proposed direct
mitigation measures in place, the predicted overall noise levels at some NSRs
would still exceed the relevant noise limits due to the noise contributions
from existing roads or noise contribution from the “New” road (i.e. the noise
levels from new roads at some NSRs still exceed the noise standards and/or the
‘New’ road noise contributions to the overall noise levels exceed 1.0
dB(A)). Taking into account of engineering, site and safety (e.g. fire services
requirements) constraints, the proposed noise barrier/enclosures cannot be
further extended, all direct noise mitigation measures are exhausted. The
engineering and site constraints in limiting the design of noise barriers are
given in Section 3.9.
3.8.19
The
affected residential NSRs with exceedance of noise standards contributed from
the “New” roads are summarized in Table 3.10.
Table 3.10 NSRs with Overall NLs
Exceeding Noise Criteria and Contribution
from ‘New’ Road NLs to Overall NLs Exceeding 1.0 dB(A)
NSR
|
Description
|
Contribution to Overall Noise Levels from
|
Mitigated Overall Noise Levels
dB(A)
|
Unmitigated New
Road Noise
|
Mitigated New Road
Noise
|
CLFY2
|
Chi Lok Fa Yuen
|
7.3 – 7.8
|
0.2 – 3.4
|
72.7 – 75.6
|
CLFY3
|
Chi Lok Fa Yuen
|
10.2 – 10.9
|
0.0 – 2.5
|
71.1 – 72.0
|
CLFY5
|
Chi Lok Fa Yuen
|
8.5 – 10.5
|
0.0 – 4.1
|
72.7 – 74.5
|
CLFY6
|
Chi Lok Fa Yuen
|
13.1 – 15.4
|
0.2 – 6.5
|
67.9 – 73.7
|
TFH
|
On Ting Estate
(Ting Fuk House)
|
8.5 – 13.8
|
2.0 –
3.9
|
63.4 – 74.3
|
HKG
|
Hong King Garden
|
4.7 – 9.7
|
1.0 – 1.8
|
67.7 – 75..8
|
TTP
|
Tung Wah Group of Hospitals Tai
Tung Pui
Social Service
Building
|
5.4 – 10.2
|
0.7 – 3.1
|
65.8 – 72.4
|
JCP
|
JC Place
|
5.3 – 6.8
|
0.5 – 1.5
|
70.0 – 72.3
|
HG
|
Harvest Garden
|
5.2 – 8.8
|
0.2 – 2.3
|
72.5 – 73.0
|
KFG1A
|
Kam Fai Garden
|
10.1 – 13.8
|
0.4 – 4.8
|
67.5 – 72.9
|
KFG1B
|
Kam Fai Garden
|
9.7 – 13.2
|
0.2 – 4.0
|
68.8 – 73.5
|
3.8.20
An
eligibility test for indirect technical remedies was conducted for these NSRs
to consider if provision of acoustic insulation and air conditioning is
required. The results of the eligibility test are given in Appendix 3.7B.
3.8.21
Results
of the eligibility test reveals that the NSRs are not eligible for provision of
indirect technical remedies.
3.9
Evaluation of Residual Impacts
Construction
Noise
3.9.1
With
the implementation of the recommended noise mitigation measures, the cumulative
construction noise impacts at all representative NSRs except some educational
institutes such as NSR CMA, LWF, LCK, LCKP and CSBS during examination periods
were predicted to be within the construction noise guidelines as stipulated in
the EIA-TM.
3.9.2
In
order to avoid or reduce the construction noise problems at the schools during
examination, the Contractor of the Project is suggested to liaison with all the
relevant schools to check out their examination periods and activities in the
beginning of the work programme.
Thus, the Contractor can make good planning and arrangement of works and
provide sufficient mitigation plans to alleviate the noise impacts.
Operation
Noise
3.9.3
With
the implementation of the proposed mitigation, the overall noise levels at NSR
FEC, OC, TMTP2, TMTP3, TMTP5, WG1, LCK, LPB, LBB, RG, SST, KFG2A, KFG2B, KFG2C, KFG2D, KFG3B, KFG3C, KFG3D and SLC1 are within the noise criteria. No
residual impact is expected at these NSRs.
3.9.4
The
overall noise levels at the residential premises including NSR PAC, YLB1, YLB2,
KHB, EC1, EC2, RDG, HFB, FM, HTB, FHB, MSB, SC, TMTP1, TMTP4, TMTP6, WG2, NTM1,
NTM2, THC1, THC2, TMF, CLFY1, CLFY4, HFDG, SSE, KFG3A, KFG4A, KFG4B and SLC4, schools including NSR ELC,
CMA, LWF, LCKP, CSBS and other uses such as NSR TMC, PEN and SHT would exceed
the relevant noise criteria. However, the ‘New’ road noise levels are within
the noise criteria and no adverse noise impact is arising from the ‘New’ roads.
Noise exceedances at these NSRs are mainly due to the existing roads.
3.9.5
The
overall noise levels at NSR CLFY3 (mid to high floors), JCP and HG would exceed
the traffic noise criterion. The ‘New’ road noise levels at these NSRs are all
within the noise criterion (70dB(A)) but the “New” road contribution to the
overall noise level would be greater than 1 dB(A).
3.9.6
For
the mid to high floors of NSR CLFY3, the noise exceedances would be dominantly
contributed from the elevated Tuen
Mun Road section. However, no further direct mitigation
measure on the “New” roads is allowed due to site constraint.
3.9.7
The
major noise sources at NSR JCP and HG comes from the existing road of Castle
Peak Road – Castle Peak Bay Section which is in front of the JC Place and
Harvest Garden and the bridge section of Tuen Mun Road which across the Hoi
Wing Road and Castle Peak Bay Section of Castle Peak Road. There is no upgrading work for this
bridge section of Tuen Mun Road
under this Project. Its existing
foundation cannot take into account of additional loadings of noise
barrier/enclosure. Therefore,
installing noise barriers or enclosure along this strip of land is considered
not feasible and remained as an open section.
3.9.8
With
the proposed direct noise mitigation measures in place, noise exceedance would
still be predicted at NSR CLFY2, CLFY5, CLFY6, TFH, HKG, TTP, KFG1A and KFG1B.
The exceedance would be due to the traffic noise coming from the “New” road
sections that could not be screened by proposed direct mitigation measures due
to site constraint.
3.9.9
The
“New” road noise levels at NSR CLFY2, CLFY5, CLFY6, HKG and TTP would exceed
the 70dB(A) criterion. The majority of the noise impact comes from the
unscreened elevated road section running towards southern direction (between Ch28160
and Ch28200). This section of road belongs to the existing Tuen Mun Road and Wong Chu Road Upramp. The
elevated Wong Chu Road
structure was built in 1980s’ and has not been designed for any additional
future loadings for massive structures such as noise barriers or enclosure.
Based on preliminary assessment, the current Wong Chu Road Flyover is
already an optimal design and there is not enough spare capacity to support the
loading induced by installing new noise barriers or enclosure. Therefore, installing
noise barriers or enclosure on this structure is technically infeasible.
For narrow strip between the Wong Chu Road Upramp and the Tuen Mun Road, in order to provide
adequate horizontal clearance between the existing Tuen Mun Road and the existing Wong Chu Road Abutment,
there will be not enough room to install barriers along this narrow strip of
land while maintaining adequate clearance. Therefore, again, installing
noise barriers or enclosure along this strip of land is considered not
feasible. For this section, other than the portion of the roads between the
Wong Chu Road Flyover and TMR KLN/B, all practicable mitigation measures near Wong Chu Road
section have been explored. For the
section near Kam Fai Garden, please note that all practicable mitigation
measures near this section have been explored as well.
3.9.10
The
“New” road noise levels at NSR TFH would exceed the 70dB(A) criterion. The dominant noise contribution in the
“New” road noise levels would also come from the unscreened elevated road
section running towards southern direction (between Ch28160 and Ch28200). No
further noise mitigation measure is considered due to the site constraints as
mentioned in S3.9.9. The noise contribution
in the “New” road noise levels from partial open road section (Southbound of
TMR) in the vicinity of Lai
Po Building
is insignificant. The overall noise reduction is less than 1 dB(A) even though
covering this road section. In view of ineffective acoustic reduction, no
further noise mitigation measure could be proposed for this road section.
3.9.11
Exceedance
of “New” road noise levels at NSR KFG1A
and KFG1B is due to the noise emitted from the “New” road section in front of
Kam Fai Garden. Noise barriers have to be erected at Tuen Mun Road section above the Castle Peak Road or
otherwise the noise could not be screened. However, this section of the road is
an existing elevated structure (Sam
Shing Hui
Bridge) crossing Castle Peak Road.
The elevated structure has not been designed for any additional future loadings
for massive structures such as noise barriers or enclosure. Based on a
preliminary assessment, the current structure is already an optimal design and
there will be no enough spare capacity to support the loading induced by
installing new noise barriers or enclosure. Therefore, installing noise
barriers or enclosure on this structure is technically not feasible. For this section, other than the section
of the road on the existing Sam
Shing Hui
Bridge, all practicable
mitigation measures near this section have been explored.
3.9.12
The
eligibility test in Appendix 3.7B shows that none of the representative
NSRs is eligible for consideration for indirect technical remedies in the form
of acoustic insulation and air conditioning under the EIAO GN 12-2005, “Road
Traffic noise Impact Assessment under the Environmental Impact Assessment
Ordinance”.
3.9.13
The
number of dwellings or classrooms being protected or benefited from proposed
noise mitigation measures are estimated and summarized in Appendix 3.8.
3.10
Monitoring and Audit Requirements
Construction
Noise
3.10.1
An
EM&A programme is recommended to be established according to the predicted
occurrence of noisy activities. All the recommended mitigation measures for
daytime normal working activities should be incorporated into the EM&A
programme for implementation during construction. Details of the programme are provided in
the stand-alone EM&A Manual.
Operation Noise
3.10.2
Road
traffic noise levels should be monitored at representative NSRs, which are in
the vicinity of the recommended direct mitigation measures, during the first
year after road opening. Details of the programme are provided in the stand-alone
EM&A Manual.
Construction
Noise
3.11.1 This
assessment has predicted the construction noise impacts of the Project during
normal daytime working hours. With the use of quiet PME and movable barriers,
and scheduling of construction activities, the noise levels at all
representative NSRs would comply with the construction noise standard except
educational NSR CMA,
LWF, LCK, LCKP and CSBS during examination
period.
3.11.2 The Contractor of the Project is
suggested to liaison with these schools to check out their examination periods
and activities in the beginning of the work programme. Thus, the Contractor can make good
planning and arrangement of works and provide sufficient mitigation plans to avoid noisy construction activities undertaking
during examination period.
Operation Noise
3.11.3 The
potential road traffic noise impacts have been assessed based on the worst case
traffic flows in 2025. The noise levels at some NSRs are predicted to exceed
the EIA-TM traffic noise criteria due to both ‘New’ road and existing roads. As
a result, direct mitigation measures have been proposed to mitigate the noise
impacts at the NSRs where ‘New’ road noise contributions to the overall noise
levels would be more than 1.0 dB(A).
3.11.4 With the
proposed noise mitigation measures in place, the ‘New’ road noise contributions
to the overall noise levels at all representative NSRs, except those mentioned
in the following paragraphs, would be less than 1.0 dB(A) and the ‘New’ road
noise levels would all be below the relevant noise criteria, though the overall
noise levels at some of the NSRs would still exceed the relevant noise
criteria. However, it should be noted that such noise exceedances at the
representative NSRs are due to the existing roads.
3.11.5
Due
to site constraint, noise enclosures could not be built to further alleviate
the noise impacts at NSR TFH, CLFY2, CLFY3, CLFY5, CLFY6, HKG, TTP, JCP, HG,
KFG1A and KFG1B. Eligibility test
is conducted to assess the eligibility of these NSRs for provision of noise
insulation works (NIW). The test results show that the NSRs are not eligible
for provision of NIW.
3.11.6 Monitoring
of road traffic noise is recommended to verify the effectiveness of the
mitigation scheme during the first year after road opening.