1                     introduction

1.1               Background of the Project

1.1.1          Highways Department of Hong Kong SAR Government commissioned Maunsell Consultants Asia Ltd. to undertake Agreement No. CE 38/2005 (HY) “Traffic Improvement to Tuen Mun Road Town Centre Section – Feasibility Study” (hereafter referred to as “the Assignment”).

1.1.2          This Assignment comprises traffic improvement works to Tuen Mun Road – Town Centre Section (TMRTCS) between Yan Oi Tong in the north and Wong Chu Road in the south. This road section is about 1.8km long and is basically a road widening works from the existing dual two-lane highway to dual three-lane highway.

1.1.3          In the morning peak period (7a.m. – 9a.m.), the volume/capacity (v/c) ratios of the southbound two-lane carriageways are in the range of 0.89- 0.99, the most critical being the Wong Chu Road section.  In other words, TMRTCS at these two-lane sections is operating close to its design capacity and there is little spare capacity to cater for any substantial increase in traffic.

1.1.4          TMRTCS is currently operating close to its capacity and there is virtually no spare capacity to cater for any substantial increase in traffic.  In particular, there would be potential congestion of TMRTCS after opening of the Hong Kong – Shenzhen Western Corridor (HK-SWC) and the Deep Bay Link (DBL) in late 2006/ early 2007.  It is anticipated that HK-SWC will bring additional traffic through TMRTCS.  To alleviate the problem, a medium term measure to improve the traffic condition of TMRTCS should be investigated to meet the medium term traffic demand till 2016.

1.1.5          The objective of the Assignment is to propose improvement measures to resolve the traffic congestion problem of TMRTCS.  The traffic improvement options under the Assignment were compared and evaluated against the criteria including traffic benefits, social benefits, engineering feasibility, land requirement, programme and cost.  The “Dual 3-land widening from Yan Oi Town Square to Wong Chi Road” option is selected as the preferred option of the Project. 

1.1.6          Maunsell Consultants Asia Limited (MCAL) was commissioned by the Highways Department to undertake the investigation, design and construction of the traffic improvement measures proposed for TMRTCS.  The proposed traffic improvement measures mainly comprised of duel three-lane road widening works along TMRTCS from Yan Oi Town Square to Wong Chu Road (hereafter referred to as “the Project”).  Further studies including Geotechnical Assessment Study, Traffic Impact Assessment Study and Environmental Impact Assessment (EIA) Study were also carried out.

1.1.7          Under Section A.1 of Schedule 2, Part 1 of the Environmental Impact Assessment Ordinance (Cap. 499), the Project is a designated project and therefore will require an environmental permit. 

 

 

 

 

`

1.2               Project Location and Programme

1.2.1          The Project involves widening the following sections of TMR from dual-two carriageway to dual-three carriageway:

Ø           Wong Chu Road Section, (from Wong Chu Road Interchange to Tuen Hing Road);

Ø           Tuen Mun Town Plaza Section, (from Yan Oi Town Square to Tuen Hing Road).

1.2.2          The proposed Tuen Mun Road – Town Centre is located between Lam Tei Interchange and Wong Chu Road, a heavy-trafficked strategic road. The area, in the vicinity of the construction works, is generally a populated area dominated by high-rise buildings. The Project location is shown on Figure 1.1.

1.2.3          The construction works of the Project are anticipated to commence in 2009 and be completed by 2012.

1.3               Project Scope

1.3.1          The scope of work of the Project comprises:

(a)                 Widening of the TMRTCS from dual 2-lane carriageway to dual 3-lane carriageway from Yan Oi Town Square to Wong Chu Road for both southbound and northbound;

(b)                 Construction of a one-lane flyover extending from Tuen Hing Road, running along Tsing Hoi Circuit and merging with TMR Kowloon bound;

(c)                 Implementation of local road re-alignment and widening and modification to existing traffic light signal-controlled junctions along CPR and Tsing Hoi Circuit;

(d)                 Reconstruction of approximately 80m long of the existing Wong Chu Road slip road to facilitate proper merging with the new flyover described in (b);

(e)                 Demolition and reconstruction of 4 existing footbridges spanning across TMRTCS which could interfere with the execution of the Project;

(f)                   Implementation of traffic management measures such as local road re-alignment and widening and modifications to existing traffic light signal-controlled junctions along CPR;

(g)                 Construction of associated noise barriers and noise enclosures, earth retaining structure, slope works, geotechnical works including hazard mitigation measures, and works on environmental mitigation, landscaping, drainages, road lightings, and watermains; and

(h)                 Provision of traffic control & surveillance system (TCSS) including lane control signals, variable speed limit signs, automatic incident detectors, closed-circuit television (CCTV) cameras, etc. at Tuen Mun Town Centre and variable message signs (VMS) between Yuen Long and Tuen Mun and on TMR, including their integration with the central control systems at the TD’s Traffic Control Centre in Wanchai or other TCSS as appropriate.

 

 

1.4               Purpose of the Manual

1.4.1          The purpose of this Environmental Monitoring and Audit (EM&A) Manual is to guide the set up of an EM&A programme to ensure compliance with the EIA study recommendations, to assess the effectiveness of the recommended mitigation measures and to identify any further need for additional mitigation measures or remedial action.  This Manual outlines the monitoring and audit programme for the construction and operational phases of the Project.  It aims to provide systematic procedures for monitoring, auditing and minimising environmental impacts associated with construction works and operational activities.

1.4.2          Hong Kong environmental regulations and the Hong Kong Planning Standards and Guidelines have served as environmental standards and guidelines in the preparation of this Manual. In addition, the EM&A Manual has been prepared in accordance with the requirements stipulated in Annex 21 of the EIAO-TM.

1.4.3          This Manual contains the following information:

Ø           Responsibilities of the Contractor, the Engineer or Engineers Representative (ER), Environmental Team (ET) and Independent Checker (Environment) (IEC) with respect to the environmental monitoring and audit requirements during the course of the Project;

Ø           Project organization;

Ø           The basis for, and description of the broad approach underlying the EM&A programme;

Ø           Requirement with respect to the construction programme schedule and the necessary environmental monitoring and audit programme to track the varying environmental impact;

Ø           Details of the methodologies to be adopted, including all field laboratories and analytical procedures, and details on quality assurance and quality control programme;

Ø           The rationale on which the environmental monitoring data will be evaluated and interpreted;

Ø           Definition of Action and Limit levels;

Ø           Establishment of Event and Action plans;

Ø           Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints;

Ø           Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures;

Ø           Requirements for review of EIA predictions and the effectiveness of the mitigation measures / environmental management systems and the EM&A programme

1.4.4          For the purpose of this manual, the ET leader, who shall be responsible for and in charge of the ET, shall refer to the person delegated the role of executing the EM&A requirements.

 

 

1.5               Project Organization

1.5.1          The roles and responsibilities of the various parties involved in the EM&A process and the organizational structure of the organizations responsible for implementing the EM&A programme are outlined below.  The proposed Project organization and lines of communication with respect to environmental protection works are shown in Figure 1.2.

The Contractor

1.5.2          The Contractor shall report to the Engineer. The duties and responsibilities of the Contractor are:

Ø           Provide assistance to ET in carrying out monitoring and auditing;

Ø           Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event and Action Plans;

Ø           Implement measures to reduce impact where Action and Limit levels are exceeded;

Ø           Implement the corrective actions instructed by the Engineer;

Ø           Accompany joint site inspection undertaken by the ET; and

Ø           Adhere to the procedures for carrying out complaint investigation.

Environmental Team

1.5.3          The Environmental Team (ET) is employed by the Project Proponent to undertake monitoring, laboratory analysis and reporting of environmental monitoring and audit.

1.5.4          The ET Leader and the ET shall be employed to conduct the EM&A programme and ensure the Contractor’s compliance with the project’s environmental performance requirements during construction.  The ET Leader shall be an independent party from the Contractor and have relevant professional qualifications. The ET shall be led and managed by the ET leader.  The ET leader shall possess at least 7 years experience in EM&A.

1.5.5          The duties and responsibilities of the ET are:

Ø           Monitor various environmental parameters as required in this EM&A Manual;

Ø           Analyse the environmental monitoring and audit data and review the success of EM&A programme to cost-effectively confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions and to identify any adverse environmental impacts arising;

Ø           Carry out regular site inspection to investigate and audit the Contractors' site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and effect proactive action to pre-empt problems; carry out ad hoc site inspections if significant environmental problems are identified;

Ø           Audit and prepare monitoring and audit reports on the environmental monitoring data and site environmental conditions;

Ø           Report on the environmental monitoring and audit results to the IEC, Contractor, the ER and EPD or its delegated representative;

Ø           Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans; and

Ø           Adhere to the procedures for carrying out complaint investigation.

Engineer or Engineer’s Representative

1.5.6          The Engineer is responsible for overseeing the construction works and for ensuring that the works undertaken by the Contractor in accordance with the specification and contractual requirements. The duties and responsibilities of the Engineer with respect to EM&A may include:

Ø           Supervise the Contractors activities and ensure that the requirements in the EM&A Manual are fully complied with;

Ø           Inform the Contractor when action is required to reduce impacts in accordance with the Event and Action Plans;

Ø           Participate in joint site inspection undertaken by the ET; and

Ø           Adhere to the procedures for carrying out complaint investigation.

Independent Checker (Environment)

1.5.7          The Independent Checker (Environment) (IEC), employed by the Project Proponent, shall advise the Engineer’s Representative on environmental issues related to the Project. The IEC shall have project management experience in additional to the requirements of the ET Leader stated above.

1.5.8          The duties and responsibilities of the IEC are:

Ø           Review and audit the EM&A works performed by the ET (at least at monthly intervals);

Ø           Carry out random sample check and audit the monitoring activities and results (at least at monthly intervals);

Ø           Review the EM&A reports submitted by the ET;

Ø           Audit the results of the EM&A works carried out by the ET;

Ø           Review the effectiveness of environmental mitigation measures and project environmental performance;

Ø           Review the proposal on mitigation measures submitted by the Contractor in accordance with the Event and Action Plans; and

Ø           Adhere to the procedures for carrying out complaint investigation.

1.5.9          Sufficient and suitably qualified professional and technical staff shall be employed by the respective parties to ensure full compliance with their duties and responsibilities, as required under the EM&A programme for the duration of the Project.