Construction of Cycle
Tracks and the
Associated Supporting
Facilities
From Sha Po Tsuen to
Environmental Impact
Assessment
Environmental Monitoring
& Audit (EM&A) Manual
Final
December 2008
In association with
Oikos Consulting Limited
Hong Kong Institute of Archaeology
Civil Engineering and Development Department |
Contract No. (if any): |
|
Agreement No.:
|
||
Project Title: |
Construction of Cycle Tracks and the Associated Supporting Facilities
from Sha Po Tsuen to |
Project No.: 4082 |
Document No.: |
4082-OR036-02 |
Controlled Copy No.: |
Document Title: |
Final Environmental Monitoring &
Audit (EM&A) Manual |
|
Covering Letter/Transmittal
Ref. No.: |
Date of Issue: |
|
4082/OG091/Elt17552/SB/ww |
24 December 2008 |
Revision, Review and Approval Records
|
|
/ |
/ |
/ |
|
|
/ |
/ |
/ |
|
|
/ |
/ |
/ |
02 |
Final EM&A Manual |
Various / 24 December 2008 |
Wing Wong / 24 December 2008 |
Susana Bezy / 24 December 2008 |
Revision |
Description |
Prepared by / date |
Reviewed by / date |
Approved by / date |
Distribution (if insufficient space, please
use separate paper)
Controlled Copy No. |
Issued to |
01-13 |
EPD |
14-18 |
CEDD |
19 |
SWL |
20 |
ACL |
Table of Contents
2.1 Key Parties and Organisation Chart
2.2 Civil Engineering & Development Department
2.3 Environmental Protection Department
2.5 Independent Environmental Checker
3.2 EM&A Requirements During Construction Phase
3.3 EM&A
Requirements During Operational Phase
4.2 EM&A Requirements During Construction Phase
4.3 EM&A Requirements During Operational
Phase
5.2 EM&A Requirements During Construction
Phase
5.3 EM&A Requirements during Operational
Phase
6.2 EM&A Requirements during Construction Phase
6.3 EM&A
Requirements During Operational Phase
7.2 Land Contamination Assessment
7.3 Safety Precautionary Measures
8.2 EM&A Requirements During Construction Phase
8.3 EM&A Requirements During Operational Phase
11.2 Compliance with Legal and Contractual Requirements
12.3 First Monthly EM&A Report
12.4 Subsequent Monthly EM&A Reports
12.5 Quarterly EM&A Summary Reports
12.6 Final EM&A Summary Report
12.7 Typical Forms to be Adopted
12.9 Interim Notifications of Environmental Quality Limit Exceedances
List of Tables
Table
4‑1 Selected Construction Noise Monitoring Stations
Table
4‑2 Action and Limit Levels for Construction Noise Monitoring
Table
4‑3 Event and Action Plan for Construction Noise Monitoring
Table 10‑1 Construction Phase Mitigation Measures
Table 10‑2 Operational Phase Mitigation Measures
List of Figures
Figure 1-1 Proposed
Cycle Track Alignment & Supporting Facilities
Figure 4-1 Noise
Monitoring Stations
Figure 4-2 Noise
Monitoring Stations
Figure 4-3 Noise
Monitoring Stations
Figure 7-1 Land
Contamination Investigation Locations
Figure 7-2 Land
Contamination Investigation Locations
Figure 8-1 Ecological
Mitigation Measures
Figure 10-1 Design
Concept Drawings and Recommended Landscape Mitigation Measures
Figure 10-2 Design
Concept Drawings and Recommended Landscape Mitigation Measures
Figure 10-3 Design
Concept Drawings and Recommended Landscape Mitigation Measures
Figure 10-4 Design
Concept Drawings and Recommended Landscape Mitigation Measures
Figure 10-5 Design
Concept Drawings and Recommended Landscape Mitigation Measures
Figure 10-6 Design
Concept Drawings and Recommended Landscape Mitigation Measures
List of Appendices
Appendix 1 Implementation
Schedule
Appendix 2 Proforma
for EM&A
1.
Construction of a new cycle
track (with footpath) linking up local cycle track networks in
2.
Construction of the associated
support facilities which includes 5 Resting Stations (formerly named “places of
rest” in the EIA Study Brief) - R5, R6, R7, R8, and R9, and
3. The associated streetscape, landscape, utilities diversions, traffic aids installation, street lighting, water, sewerage and drainage works;
4. Provision of environmental mitigation measures.
· Duties of the Contractor, Engineer’s Representative (ER), the Environmental Team (ET) and the Independent Environmental Checker (IEC) with and their respective responsibilities with regards to the EM&A requirements during construction;
· Information on project organisation, work schedule and activities;
· Requirements with respect to the work schedule and the necessary EM&A programme to detect the various possible environmental impacts;
· Definition of Action/ Limit Levels and the establishment of Event/ Action Plans;
· Requirements for reviewing potential sources of pollution and assessing working procedures in the event of non-compliance with the environmental criteria;
· Requirements for the presentation of EM&A data and appropriate reporting procedures; and
· Proposed field data forms to be adopted during the various phases of the works.
· Civil Engineering & Development Department (CEDD) - Project Proponent
·
Environmental Protection
Department (
· Engineer’s Representative (ER) - Scott Wilson Ltd. employed under Agreement No. CE 22/2006 (HY) by CEDD
· The Independent Checker (Environment) (IEC) – to be employed by CEDD
· The Environmental Team (ET) – to be employed preferably by CEDD or the Contractor
· The Contractor
· Review and audit in an independent, objective and professional manner in all aspects of the EM&A programme;
· Validate and confirm the accuracy of monitoring results, appropriateness of monitoring equipment, monitoring locations with reference to the locations of the nearby sensitive receivers, and monitoring procedures;
· Carry out random sample check and audit on monitoring data and sampling procedures, etc;
· Conduct random site inspection (at least once a month);
· Audit the EIA recommendations and EP requirements against the status of implementation of environmental protection measures on site;
· Review the effectiveness of environmental mitigation measures and Project environmental performance;
· On an as needed basis, verify and certify the environmental acceptability of the construction methodology (both temporary and permanent works), relevant design plans and submissions under the environmental permit. Where necessary, the IEC shall agree in consultation with the ET Leader and the Contractor the least impact alternative;
· Verify investigation results of complaint cases and the effectiveness of corrective measures;
· Verify EM&A reports submitted and certified by the ET Leader; and
· Feedback audit results to ER/ ET by signing according to the Event/ Action Plans specified in this Manual.
· Sampling, analysis and statistical evaluation of monitoring parameters with reference to the EIA study recommendations and requirements;
· Environmental site surveillance;
· Inspection and audit of compliance with environmental protection, and pollution prevention and control regulations;
· Inspection and audit of compliance with procedures established to enable an effective response to environmental incidents, exceedances or non-compliance;
· Assess the effectiveness of the environmental mitigation measures implemented;
· Monitor the implementation of environmental mitigation measures;
· Monitor compliance with the environmental protection clauses/specifications in the Contract;
· Review the construction schedule and provide comments as necessary;
· Review work methodologies which may affect the extent of environmental impact during the construction phase and comment as necessary;
· Complaint investigation, evaluation and identification of corrective measures;
· Liaison with the IEC on all environmental performance matters, and timely submission of all relevant EM&A proforma for IEC’s approval;
· Advice to the Contractor on environmental improvement, awareness, enhancement matters, etc. and;
·
Timely submission of the
EM&A reports to the Project Proponent and the
Mitigation Measures
· The works area for site clearance shall be sprayed with water before, during and after the operation so as to maintain the entire surface wet;
· Restricting heights from which materials are to be dropped, as far as practicable, to minimise the fugitive dust arising from unloading/ loading;
· Immediately before leaving a construction site, all vehicles shall be washed to remove any dusty materials from the bodies and wheels. However, all spraying of materials and surfaces should avoid excessive water usage;
· Where a vehicle leaving a construction site is carrying a load of dusty materials, the load shall be covered entirely by clean impervious sheeting to ensure that the dusty materials will not leak from the vehicle;
· Travelling speeds should be controlled to reduce traffic induced dust dispersion and re-suspension within the site from the operating haul trucks;
· Erection of hoarding of not less than 2.4 m high from ground level along the site boundary, where appropriate;
· Any stockpile of dusty materials shall be covered entirely by impervious sheeting; and/or placed in an area sheltered on the top and 4 sides;
· All dusty materials shall be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.
Noise Parameters
Proposed Noise Monitoring Stations
Table
4‑1 Selected Construction Noise Monitoring
Stations
Noise Monitoring Station |
Description |
N1 |
|
N2 |
|
N3 |
No.
159 Mai Po San Tsuen |
N4 |
No.
1C Mai Po Lo Wai |
N5 |
Block
2, |
N6 |
Home
of Loving Faithfulness |
· At location(s) close to the major site activities which is/are likely to have noise impacts;
· Close to the NSRs (as defined by the EIAO TM); and
· For monitoring locations located in the vicinity of the sensitive receivers, care shall be taken to cause minimal disturbance to occupants during monitoring.
Table 4‑2 Action and Limit Levels for Construction
Noise Monitoring
Noise Sensitive Uses |
0700 to 1900 hours on any day not being a Sunday
or general holiday, Leq(30 min), dB(A) |
|
Action |
Limit |
|
Dwelling |
When
one documented complaint is received |
75 |
School |
70
(65 during examination) |
Table 4‑3 Event and Action Plan for Construction
Noise Monitoring
Event |
Action |
|||
ET Leader |
IEC |
ER |
Contractor |
|
Action Level is reached |
1.
Notify IC(E) and Contractor 2.
Carry out investigation 3.
Report the results of investigation to the IC(E) and Contractor 4.
Discuss with the Contractor and formulate remedial measures 5. Increase monitoring frequency to check mitigation effectiveness |
1.
Review the analysed results submitted by the ET 2.
Review the proposed remedial measures by the Contractor and advise
the ER accordingly 4. Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in writing 2.
Notify Contractor 3.
Require Contractor to propose remedial measures for the analysed noise
problem 4.
Ensure remedial measures are properly implemented |
1.
Submit noise mitigation proposals to IC(E) 2. Implement noise mitigation proposals |
Limit Level is reached |
1.
Notify IC(E), ER, EPD and Contractor 2.
Identify source 3.
Repeat measurement to confirm findings 4.
Increase monitoring frequency 5.
Carry out analysis of Contractor's working procedures to determine possible
mitigation to be implemented 6.
Inform IC(E), ER and EPD the causes & actions taken for the exceedances 7.
Assess effectiveness of Contractor's remedial actions and keep IC(E), EPD and
ER informed of the results 8. If exceedance stops, cease additional monitoring |
1.
Discuss amongst ER, ET, and Contractor
on the potential remedial actions 2.
Review Contractor's remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly 3. Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in writing 2.
Notify Contractor 3.
Require Contractor to propose remedial measures for the analysed noise
problem 4.
Ensure remedial measures are properly implemented 5. If exceedance continues, consider what portion of the work is
responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated |
1. Take
immediate action to avoid further exceedance 2.
Submit proposals for remedial actions to IC(E) within 3 working days of
notification 3.
Implement the agreed proposals 4.
Resubmit proposals if problem still not under control 5. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated |
Noise Mitigation Measures
· In order to prevent potential cumulative
construction noise impacts to NSRs at Mai Po San Tsuen and Palm Springs, the
works at the cycle track section (near CH-MP5+100m) are recommended to be
scheduled to avoid works at the areas near Castle Peak Road of the Proposed
Comprehensive Development at Wo Shang Wai (CDWSW) project if the works site of
the CDWSW project is less than 300 m away from Castle Peak Road;
·
The contractor shall liaise with the Yuen Long and Kam Tin Sewerage
and Sewage Disposal Stage 2 (YLKTSSD2) works Salt Water Supply for
·
Use of temporary
noise barrier in the form of site hoarding;
·
Use of
noise enclosure;
·
The
barrier / enclosure material’s surface mass shall be in excess of 7 kg/m2;
·
Use of
alternative quieter plant such as excavator mounted road ripper instead of
handheld breaker during levelling/excavation works.
·
The Contractor
should adopt the following good working practices in order to minimise
construction noise as far as possible:
§
The
Constractor shall adopt the Code of Practice on Good Management Practice to
Prevent Violation of the Noise Control Ordinance (Cap. 400) (for Construction
Industry) published by
§ The Contractor shall observe and comply with the statutory and non-statutory requirements and guidelines;
§ Before commencing any work, the Contractor shall submit to the ER for approval the method of working, equipment and noise mitigation measures intended to be used at the site;
§ The Contractor shall devise and execute working methods to minimise the noise impact on the surrounding sensitive uses, and provide experienced personnel with suitable training to ensure that those methods are implemented;
§ Noisy equipment and noisy activities should be located as far away from the NSRs as is practical.;
§
Unused equipment
should be turned off. Powered mechanical
equipment should be kept to a minimum and the parallel use of noisy equipment /
machinery should be avoided;
§
Regular
maintenance of all plant and equipment;
§
Material
stockpiles and other structures should be effectively utilised as noise
barriers, where practicable; and
§
The
Contractor shall liaise with the schools that are located near the works sites
regarding their examination period and schedule the noisy works to avoid the
examination period as far as possible.
· Inspection of the effectiveness of silt removal facilities and erosion and sediment control structures to ensure proper and efficient operation at all times and particularly during rainstorms;
· Inspection of the effectiveness of control measures to prevent soil erosion and sediment laden run-off from stockpiles;
· Inspection of the effectiveness of collection, handling, storage and disposal of materials to ensure they do not enter the nearby stormwater drainage system; and
· Review of the Contractor’s compliance with discharge license requirements.
Mitigation Measures
1.
Surface run-off from the
construction sites will be directed into storm drains via adequately designed
wastewater treatment facilities such as sand traps, silt traps and sediment
settling basins. This is particularly
important for works immediately adjacent to the
2. Channels, earth bunds or sand bag barriers will be provided on-site to properly direct stormwater to the above-mentioned facilities;
3.
Existing silt removal facilities, channels and manholes along roads and
pedestrian walkways will be maintained and the deposited silt and grit will be
removed regularly, at the onset of and after each rainstorm to ensure that
these facilities are functioning properly at all times;
4.
Other manholes (including any newly constructed ones) will be adequately
covered and temporarily sealed so as to prevent silt, construction materials or
debris from getting into the drainage system.
5.
Open stockpiles of materials on site will be avoided or where
unavoidable covered with tarpaulin or similar fabric during rainstorms. Measures will be taken to prevent the washing
away of construction materials, soil, silt or debris into any drainage system;
6.
Where possible, works entailing soil excavation will be minimized during
the rainy season (i.e. April to September).
7.
Where applicable, final earthworks surfaces/ slopes will be well
compacted and hydro-seeded following completion to prevent erosion.
8.
During construction works, chemical toilets will be provided for the use
of site staff. These will be provided by a licensed contractor, who will be
responsible for appropriate disposal and maintenance of the effluent.
9.
Works adjacent to the fishponds
near
10. Wastewater from site facilities (such as toilets) should be discharged to foul sewer, where available. Chemical toilets will be considered where there is no foul sewer connection. There is not expected to be a temporary canteen.
11.
All site discharges within
Water Control Zones must comply with the terms and conditions of a valid
discharge licence issued by
12. Vehicle wheel washing facilities should be provided, where applicable, at the site exit such that mud, debris, etc. deposited onto the vehicle wheels or body can be washed off before the vehicles are leaving the site area;
13. The section of the road between the wheel washing bay and the public road should be paved with backfill to reduce vehicle tracking of soil and to prevent site run-off from entering public road drains.
14. The project may occasionally involve the handling of fuel and generates chemical wastes. It must be ensured that all fuel tanks and chemical storage are sited on sealed areas and provided with locks.
15. The storage areas will be surrounded by bunds with a capacity equal to 110% of the storage capacity of the largest tank to prevent accidentally spilled oil, fuel or chemicals from reaching the receiving waters.
16. Oil and grease removal facilities will be provided where appropriate, for example, in area near plant workshop/ maintenance areas; and
17. Chemical waste arising from the site should be properly stored, handled, treated and disposed of in compliance with the requirements stipulated under the Waste Disposal (Chemical Waste) (General) Regulation.
Site Audit / Inspection
Waste Management Practices
Mitigation Measures
· To minimize the production of construction waste through careful design, planning, good site management, and control of ordering procedures, segregation and reuse of materials; To arrange for private contractors to collect used formwork materials for reuse;
·
To dispose of any chemical
wastes such as lubricating oil or solvent in strict accordance with the Waste
Disposal (Chemical Waste) (General) Regulation.
Only licensed chemical waste collectors shall be employed to collect any
chemical waste generated at site. The handling, storage, transportation and
disposal of chemical wastes shall be conducted in accordance with the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes and A Guide
to the Chemical Waste Control Scheme both published by
· All chemical toilets, if any, shall be regularly cleaned and the night-soil collected and transported by a licensed contractor to a Government Sewage Treatment Works facility for disposal;
· To assign a reliable waste collector to collect general refuse generated from the construction site on a daily basis to minimise the potential odour, pest and litter impacts; and
· To identify requirements on proper waste management for implementation during the operation of the project.
· Toolbox talks should be provided to workers about the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, reuse and recycling.
Good Site Practices
4. The Contractor shall be responsible for identifying what materials can be recycled/ reused, whether on-site or off-site. In the event of the latter, the Contractor shall make arrangements for the collection of the recyclable materials. Any remaining non-inert waste shall be collected and disposed of to the Public Filling Areas whilst any inert C&D materials shall be re-used on site as far as possible. Alternatively, if no use of the inert material can be found on-site, the materials can be delivered to a Public Fill Area or Public Fill Bank after obtaining the appropriate licence;
5. In order to monitor the disposal of C&D material and solid wastes at public filling facilities and landfills, and control fly-tipping, a trip-ticket system shall be implemented by the Contractor, in accordance with the contract and the requirements of WBTC 31/2004 “Trip Ticket System for Disposal of Construction and Demolition Material”.
6.
Under the Waste Disposal
(Chemical Waste) (General) Regulation, the Contractor shall register with
7. A sufficient number of covered bins shall be provided on site for the containment of general refuse to prevent visual impacts and nuisance to the sensitive surroundings. These bins shall be cleared daily and the collected waste disposed of to the refuse transfer station. Further to the issue of ETWB TCW No. 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness, the Contractor is required to maintain a clean and hygienic site throughout the project works;
8. All chemical toilets, if any, shall be regularly cleaned and the night-soil collected and transported by a licensed contractor to a Government Sewage Treatment Works facility for disposal;
10. The Contractor shall comply with all relevant statutory requirements and guidelines and their updated versions that may be issued during the course of project construction.
Waste Management
Practices
1. General site safety shall be enforced to include basic practices such as the use of safety boots, hard hats, coveralls, gloves and eye protection.
2. Though not expected to be a significant risk, it is important to avoid skin contact, ingestion and inhalation of excavated contaminated soils. Basic personal protective equipment should be used.
3. In addition to statutory occupational safety requirements, site staff and workers shall be given adequate training and instructions specific to the potential hazards associated with contaminated materials, their health and safety responsibilities and safe working practice including basic personal hygiene.
4. Measures shall be implemented to prevent non-workers from approaching the identified works areas in order to avoid exposure to contaminants.
Management of Contaminated Soils
1. Where appropriate, the use of bulk handling equipment should be maximised to reduce the potential contacts between excavated contaminated materials and associated workers.
2. The plants for excavation and transportation of the material shall be cleaned prior to leaving the Site.
3. All temporary stockpiles of the materials shall be completely covered with plastic/ tarpaulin sheets, particularly during heavy rainstorms. The stockpiling areas should be concrete-paved or lined with its perimeter constructed of a concrete bund where appropriate in order to avoid any leachate from migrating out of the area.
4. Any vehicles transporting the material shall be suitably covered to limit potential dust emissions.
5. Surface waters shall be diverted around any contaminated areas or stockpiles to minimize potential runoff into excavations, as runoff might increase the volume of contaminated water requiring disposal and suspended solids in the wastewater stream.
Site Audit / Inspection
Mitigation Measures
General Good Work Practices
Construction and Operational Audits
Mitigation Measures During Construction
Table 10‑1 Construction
Phase Mitigation Measures
Mitigation Code |
Mitigation Measure |
CP1 |
Preservation of
Existing Vegetation - The proposed
works should avoid disturbance to the existing trees as far as practicable
within the works areas. It is recommended that a full tree survey and felling
application will be undertaken and submitted for approval by the relevant
government departments in accordance with ETWB TCW No. 0 |
CP2 |
Preservation of
Existing Topsoil - Topsoil
disturbed during the construction phase will be tested using a standard soil
testing methodology and where it is found to be worthy of retention stored
for re-use. The soil will be stockpiled to a maximum height of 2 m and will
be either temporarily vegetated with hydroseeded grass during construction or
covered with a waterproof covering to prevent erosion. The stockpile should
be turned over on a regular basis to avoid acidification and the degradation
of the organic material, and reused after completion. Alternatively, if this
is not practicable, it should be considered for use elsewhere, including
other projects. |
CP |
Works Area and
Temporary Works Areas - The
landscape of these works areas should be restored to its original status or
new amenity area following the completion of the construction phase.
Construction site controls shall be enforced, where possible, to ensure that
the landscape and visual impacts arising from the construction phase
activities are minimised including the storage of materials, the location and
appearance of site accommodation and the careful design of site lighting to
prevent light spillage. Screen hoarding may not be practicable for this
project due to the close viewing distances involved and spatial constraints
of the works area. |
CP4 |
Mitigation
Planting - Replanting of
disturbed vegetation should be undertaken at the earliest possible stage of
the construction phase of the project and this should use predominantly
native and/or ornamental plant species. |
CP5 |
Transplantation of Existing Trees - Existing 792
trees recommended to be transplanted under the current proposal, final
recipient site should be, as far as space allows, adjacent to their current
locations alongside of the cycle track or within supporting facilities to
retain their contribution to the local landscape context, potential recipient
sites are shown in Figure 12-9I to 12-9P Conceptual Landscape Mater Plan of
the EIA Report. The implementation programme of the proposed works should
reserve enough time for advance tree transplanting preparation works to
enhance the survival of these transplant trees. Transplanting proposals will subject to the
findings of the detailed tree survey and felling application undertaken by
IDC consultants at the detailed design stage and upon to the approval by relevant
departments. |
CP6 |
Coordination with Concurrent Projects - Coordinated
implementation program with concurrent projects such as Kam Tin Trunk
Sewerage Improvement Works undertaken from DSD to minimise cumulative
landscape impact. This is evident through taking up the implementation of
proposed landscape areas under Kam Tin Trunk Sewerage Improvement Works by
cycle track proponent upon completion of cycle track. |
Mitigation Measures During Operation
Table 10‑2 Operational
Phase Mitigation Measures
Mitigation Code |
Mitigation Measure |
OP |
Design of Cycle Track and Associated Facilities - the cycle
track, Resting Station and Information Kiosk will incorporate design features
as part of design mitigation measures including: 1.
Integrated
design approach – the
alignment of cycle track should integrated, as far as technically feasible,
with existing built structures such as existing road, footpath and track and
embankment of river and drainage channel as part of design mitigation
measures to reduce the potential cumulative impact of the proposed works. The
location and orientation of the associated facilities should be away from
landscape and visually sensitive areas such wetland, fishpond and
agricultural field. 2.
Building
massing - the proposed
use of simple responsive design with a building height profile
,single-storey, lower than the adjacent village houses and avoids large built
structure for supporting facilities to reduce the intrusion of mass in the
rural area. 3.
Treatment of
built structures - the
architectural design should seek to reduce the apparent visual mass of the
facilities further through the use of natural materials such as wooden frame,
vertical greening or other sustainable materials such as recycle plastic. 4.
Responsive building finishes - In terms of
the building finishes natural tones should be considered for the colour
palette with non-reflective finishes are recommended on the outward facing
building facades to reduce glare effect. 5.
Responsive lighting design – Aesthetic
design of architectural and track lighting with following glare design
measures: § Directional and
full cut off lighting is recommended particularly for recreation and roadside
areas to minimise light spillage to the surrounding areas; § Minimise
geographical spread of lighting, only applied for safety at the key access
points and staircases; § Limited
lighting intensity to meet the minimum safety and operation requirement; and § High-pressure
sodium road lighting is recommended for more stringent light control reducing
spillage and thus visual impacts. |
OP2 |
Roadside and
Amenity Planting – These
planting will utilise large ornamental trees either with high canopy and thin
foliage to allow visual access in the views from the adjacent neighbourhoods
to the further roadside or rural landscape or dense foliage at selected
locations to provide shade environment for cyclist and give accent to the
existing roadside planting whilst native species will utilise on sloping or
wooded areas improving the ecological connectivity between existing woodland
habitats with the advantage of creating a more coherent landscape framework.
Large Feature Trees will utilise within the Resting Stations or along the
cycle track, where space allows, to create shaded environment and instant
greening effect species such as Aleurites moluccana, Bombax malabaricum,
Cinnamomum camphora, Ficus bengimina, Ficus microcarpa, Grevillea robusta,
are considered. The other ornamental or native species such as Delonix
regia, Bauhinia blakeana, Cassia siamea, Cassia surttensis, Celtis sinensis
and Microcos paniculata are considered in the planting proposal to create
a comprehensive planting framework that could enhance both ecological and
landscape value of the context. Vertical greening measures should also be
considered on engineering structures |
OP |
Compensatory Planting Proposals - Given the
works extent is largely limited along existing roadside and channel side
areas to minimise impact to existing village settlements and valuable
landscape resources such as wetland, streamcourse and existing trees, and
considered the importance of tree retention within the works area, new tree
planting will concentrate in the proposed amenity areas along the track
infilling between retained and transplanted trees. Even though proposed
planting areas will be largely reserved for receiving transplanted trees, the
preliminary planting proposals for the proposed works include some 919 new
trees utilised a combination of mature to light standard sized stock in
general roadside planting areas and semi-nature stock for feature trees at
selected locations. (i.e. approximate15% of mature trees, 25% of heavy
standard trees, 50% of standard trees, and 10% light standard trees).The
proposed planting will result in a compensatory planting ratio of 1.28:1 (new
planting: trees recommended for felling). This compares favourably with the
report's assertion that some 721 trees would be felled due to the proposed
works. Following the retention of existing trees through preserving them at
their current locations or transplanting locally to new planting areas along
the cycle track, the successful establishment of newly planted trees and the
transplantation of some of the existing trees, the project area will contain
approximately 1824 trees. Trees forming part of the roadside and slope
planting will provide amenity and shaded for the cyclists as well as neighbourhood
villagers and will utilise species native to Hong Kong or wide canopy
evergreen or with ornamental feature while the species selection for the
areas within the Resting Stations or information kiosk will required more
design accent utilised more flowering species and large feature trees. These
proposals will be subject to review at detailed design stage of the project. |
OP4 |
Treatment of Retaining Wall and Slopes- In accordance
with GEO Publication No. |
· The EIA recommendations and requirements in this Manual on environmental protection and pollution control mitigation measures;
· On-going results of the EM&A programme;
· Works progress and programme;
· Individual works methodology proposals (which shall include proposals on associated pollution control measures);
· The contract specifications on environmental protection and pollution prevention;
· The relevant environmental protection and pollution control laws, ProPECC Notes; and
· Previous site inspection results undertaken by the ET.
· Log complaint and date of receipt onto the complaint database and inform the IEC immediately;
· Investigate the complaint to determine its validity, and to assess whether the source of the problem is due to works activities;
· If a complaint is valid and due to works, identify mitigation measures in consultations with the IEC;
· If mitigation measures are required, advise the Contractor accordingly;
· Review the Contractor’s implementation of the identified mitigation measures, and the concurrent situation;
· If the complaint is transferred from EPD, submit interim report to EPD on status of the complaint investigation and follow-up action within the time frame assigned by EPD;
· Undertake additional monitoring and audit to verify the complaint if necessary, and ensure that any valid reason for complaint does not recur through proposed amendments to work methods, procedures, machines and/or equipment, etc;
· Report the investigation results and the subsequent actions to the source of complaint. (If the source of complaint is identified through EPD, the results should be reported within the time frame assigned by EPD); and
· Log a record on the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.
6. Executive Summary (1-2 pages);
- Breaches of Action/ Limit levels;
- Complaint Log;
- Notifications of any summons and successful prosecutions;
- Reporting Changes; and
- Future key issues.
7. Basic Project Information
- Project organisation including key personnel contact names and telephone numbers;
- Programme with fine tuning of activities showing the inter-relationship with environmental protection/mitigation measures for the month;
- Management structure; and
- Work undertaken during the month.
8. Environmental Status
- Works undertaken during the month with illustrations (such as location of works); and
- Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.
9. Summary of EM&A requirements including:
- All monitoring parameters;
- Environmental quality performance limits (Action/ Limit levels);
- Event/Action Plans;
- Environmental mitigation measures, as recommended in the project EIA study final report;
- Environmental requirements in contract documents;
1. Implementation Status
- Advice on the implementation status of environmental protection and pollution control/ mitigation measures as recommended in the project EIA report, summarised in the updated implementation schedule.
2. Monitoring Results (in both hard and soft copies) together with the following information
- Monitoring methodology;
- Name of laboratory and types of equipment used and calibration details;
- Parameters monitored;
- Monitoring locations;
- Monitoring date, time, frequency, and duration;
- Weather conditions during the period;
- Graphical plots of the monitored parameters in the month annotated against;
§ Major activities being carried out on site during the period;
§ Weather conditions that may affect the results; and
§ Any other factors which might affect the monitoring results;
- QA/QC results and detection limits;
- Waste generation and disposal records;
- All monitoring results should be tabulated with exceedances highlighted for ease of reference; and
- Compare/contrast and assess the EM&A data with the EIA predictions and provide discussion for any discrepancies.
3. Report on Non-compliance, Complaints, Notifications of Summons and Successful Prosecutions
- Compliance status with the EP under the EIAO and any EP submissions;
- Record of all non-compliance (exceedances) of the environmental quality performance limits (Action/ Limit levels);
- Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
- Record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/ pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, result and summary;
- Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and
- Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
4. Comments, Recommendations and Conclusions
- An account of the future key issues reviewed from the works programme and work method statements;
- Advice on the solid and liquid waste management status; and
- Submission of implementation status proforma, proactive environmental protection proforma, regulatory compliance proforma, site inspection proforma, data recovery schedule and complaint log summarising the EM&A of the period.
1. Executive Summary (1-2 pages)
- Breaches of Action/ Limit levels;
- Complaint log;
- Notifications of any summons and successful prosecutions;
- Reporting changes;
- Future key issues.
2. Environmental Status
- Programme with fine tuning of activities showing the inter-relationship with environmental protection/mitigation measures for the month;
- Work undertaken during the month with illustrations including key personnel contact names and telephone numbers; and
- Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.
3. Monitoring Results (in both hard and electronic copies) together with the following information.
- Monitoring methodology;
- Types of equipment used and calibration details;
- Parameters monitored;
- Monitoring locations;
- Monitoring date, time, frequency, and duration;
- Weather conditions during the period;
- Graphical plots of the monitored parameters in the month annotated against;
§ Major activities being carried out on site during the period;
§ Weather conditions that may affect the results; and
§ Any other factors which might affect the monitoring results;
- QA/QC results and detection limits;
- Waste generation and disposal records;
- All monitoring results should be tabulated with exceedances highlighted for ease of reference; and
- Compare/contrast and assess the EM&A data with the EIA predictions and provide discussion for any discrepancies.
4. Implementation Status
- Advice on the implementation status of environmental protection and pollution control/mitigation measures as recommended in the Project EIA report, summarised in the updated implementation schedule.
5. Report on Non-compliance, Complaints, Notifications of Summons and Successful Prosecutions
- Record of all non-compliance (exceedances) of the environmental quality performance limits (Action/ Limit levels);
- Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
- Record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, result and summary;
- Review of the reasons for and the implications of non-compliance, complaints, summons and prosecutions including review of pollution sources and working procedures; and
- A description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
6. Comments, Recommendations and Conclusions
- An account of the future key issues reviewed from the works programme and work method statements;
- Advice on the solid and liquid waste management status; and
- Submission of implementation status proforma, proactive environmental protection proforma, regulatory compliance proforma, site inspection proforma, data recovery schedule and complaint log summarising the EM&A of the period.
7. Appendix
- Action/ Limit Levels;
- Graphical plots of trends of monitored parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:
§ Major activities being carried out on Site during the periods;
§ Weather conditions during the period; and
- Any other factors which might affect the monitoring results
§ Monitoring schedule for the present and next reporting period;
§ Cumulative statistics on complaints, notifications of summons and successful prosecutions; and
§ Outstanding issues and deficiencies.
1. Up to half a page executive summary;
2. Basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of work undertaken during the quarter;
3. A brief summary of EM&A requirements including:
- Monitoring parameters;
- Environmental quality performance limits (Action/ Limit levels); and
- Environmental mitigation measures, as recommended in the project EIA report;
4. Advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation schedule, including waste generation and disposal records;
5. Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
6. Compliance status with the EP under the EIAO and any EP submissions;
7. Graphical plots of the trends of monitored parameters over the past 4 months (the last month of the previous quarter and the present quarter) for representative monitoring stations annotated against;
- The major activities being carried out on site during the period;
- Weather conditions during the period; and
- Any other factors that might affect the monitoring results.
8. Compare/contrast and assess the EM&A data with the EIA predictions and provide discussion for any discrepancies;
9. Advice on the solid and liquid waste management status;
Comments, Recommendations and Conclusions
10. A summary of non-compliance (exceedances) of the environmental quality performance limits (Action/ Limit levels);
11. A brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures;
12. A summary description of the action taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;
13. A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;
14. A summary record of all notifications of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislation, locations and nature of the breaches, investigation, follow-up actions taken and results;
15. Comments (e.g. effectiveness and efficiency of the mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions for the quarter; and
16. Proponent’s contacts and any hotline telephone number for the public to make enquiries.
1. An executive summary;
2. Basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of work undertaken during the entire construction phase of the works;
3. A brief summary of EM&A requirements including:
- Monitoring parameters;
- Environmental quality performance limits (Action/ Limit levels); and
- Environmental mitigation measures, as recommended in the project EIA study final report.
4. Advice on the implementation status of environmental protection and pollution control/ mitigation measures, as recommended in the project EIA study report, summarised in the updated implementation status proformas, including waste generation and disposal records;
5. Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
6. Compliance status with the EP under the EIAO and any EP submissions;
7. Graphical plots of the trends of monitored parameters over the period of construction (of the project) for representative monitoring stations annotated against;
- The major activities being carried out on site during the period;
- Weather conditions during the period;
- Any other factors which might affect the monitoring results; and
- The return of ambient environmental conditions.
8. Compare/contrast and assess the EM&A data with the EIA predictions and annotate with explanation for any discrepancies;
9. Provide clear-cut decisions on the environmental acceptability of the project with reference to the specific impact hypothesis;
10. Advice on the solid and liquid waste management status;
11. A summary of non-compliance (exceedances) of the environmental quality performance limits (Action/ Limit levels);
12. A brief review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures;
13. A summary description of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;
14. A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;
15. Review the monitoring methodology adopted and with the benefit of hindsight, comment on its effectiveness (including cost effectiveness);
16. A summary record of all notification of summons and successful prosecutions for breaches of the current environmental protection/pollution control legislation, locations and nature of the breaches, investigation, follow-up actions taken and results;
17. Review the practicality and effectiveness of the EIA process and EM&A programme (e.g. effectiveness and efficiency of the mitigation measures);
18. Recommend any improvement in the EM&A programme; and
19. A conclusion to state the return of ambient and/or the predicted scenario as per EIA findings.
1. Implementation Status Performa;
2. Data Recovery Schedule;
3. Site Inspection Corrective Action Proforma;
4. Proactive Environmental Protection Proforma;
5. Regulatory Compliance Proforma;
6. Complaint Log;
7. Sample Template for Interim Notifications of Environmental Quality Limits Exceedances; and
8. Noise Monitoring Field Record Sheet.