7                                  LANDSCAPE and VISUAL Impact

7.1                            Introduction

The EIA Report has recommended landscape and visual mitigation measures to be undertaken during construction and operation phases of the Project.  This Section defines the EM&A requirements to ensure the proposed landscape and visual impact mitigation measures are effectively implemented.

7.2                            Baseline Monitoring

The ET should carry out baseline landscape and visual monitoring prior to the commencement of any construction works.  The baseline monitoring should be conducted as a one-off site survey.

Before commencing the baseline monitoring, ET should inform the Contractor, IEC, ER and the EPD of the baseline monitoring schedule programme such that relevant parties could conduct on-site audit to ensure accuracy of the baseline monitoring results.

Any baseline changes with respect to the landscape and visual impact should be recorded in reference to the baseline conditions of the site as described in Section 8 of the EIA Report.  The baseline monitoring should in particular record changes of each landscape resource, landscape character area and the view conditions of each visual sensitive receiver.  Parameters used to describe changes in each of the above should be the same as in Section 8 of the EIA Report.

The purposes of the baseline monitoring are:

·           to check the status of the landscape resources within, and immediately adjacent to, the construction sites and works areas;

·           to determine whether any change has occurred to the status of the landscape resources since the EIA Study carried out;

·           to determine whether amendments in the design of the landscape and visual mitigation measures are required for those changes; and

·           to recommend any necessary amendments to the design of the landscape and visual mitigation measures.

A competent Landscape Architect should be employed to conduct the baseline landscape and visual environmental monitoring.

7.3                            Audit Requirements

In order to ensure landscape and visual impact is controlled and mitigated during both construction and operational phases of the Project, the ET should undertake regular site inspections to ensure those recommended mitigation measures were properly implemented.  Section 8 of this Manual sets out inspection requirements, and the inspection programme will verify the implementation status and evaluate the effectiveness and stability of the mitigation measures.

A competent Landscape Architect should be employed to conduct the regular landscape audit during both construction and operational stage.

For the operational phase, all landscape and visual mitigation measures should be monitored monthly during the first year of the operational phase to ensure that the effectiveness of the mitigations.

7.4                            Event and Action Plan

In cases where non-compliance of landscape and visual impacts occurs, actions should be carried out in accordance with the Action Plan shown in Table 7.1.


 

Table 7.1        Event and Action Plan for Landscape and Visual Impact

Event

Action

 

ET

IEC

ER

Contractor

Non-compliance on one occasion

1. Identify source;

2. Inform the IEC and the ER;

3. Discuss remedial actions with the IEC, the ER and the Contractor;

4. Monitor remedial action until rectification has been completed.

 

1. Check report;

2. Check the Contractor’s working method;

3. Discuss with the ER and the Contractor on possible remedial measures;

4. Advise the ER on effectiveness of proposed remedial measures.

 

1. Notify the Contractor;

2. Ensure remedial measures are properly implemented.

 

 

1. Amend working methods;

2. Rectify damage and undertake remedial measures or any necessary replacement.

 

Repeated Non-compliance

1. Identify source;

2. Inform the IEC and the ER;

3. Increase monitoring (site audit) frequency;

4. Discuss remedial actions with the IEC, the ER and the Contractor;

5. Monitor remedial actions until rectification has been completed;

6. If exceedance stops, cease additional monitoring (site audit).

 

1. Check report;

2. Check the Contractor’s working method;

3. Discuss with the ER and the Contractor on possible remedial measures;

4. Advise the ER on effectiveness of proposed remedial measures;

5. Supervise implementation of remedial measures.

 

1. Notify the Contractor;

2. Ensure remedial measures are properly implemented;

3. Inform EPD when necessary.

 

1. Amend working methods;

2. Rectify damage and undertake remedial measures or any necessary replacement.


7.5                            Mitigation Measures

The landscape and visual mitigation measures should be incorporated to ensure the mitigation effect and achieve the intended aims as described in Tables 7.2 and 7.3 below, together with an indication of Funding, Implementation and Maintenance Agencies.  Approval-in-principle to the implementation, management and maintenance of the proposed mitigation measures is sought from the appropriate authorities are indicated in Tables 7.2 and 7.3 below; according to the principles in Works Bureau Technical Circular WBTC 14/2002.  Any changes to the mitigation measures that may be recommended as a result of the baseline monitoring or ongoing monitoring of the design, construction and establishment works should be taken into account.

Table 7.2        Proposed Landscape and Visual Mitigation Measures during Construction Phase

Items

Landscape and Visual Mitigation Measures

Funding Agency

Implementation Agency

1

LMM 5 – Early Planting Works. Where technically feasible, new plantings are to be installed as early as possible during the construction works.

HyD

Contractor

2

LMM 6 – Site hoardings to be compatible with the surrounding environment. Where possible site hoardings to be coloured to complement the surrounding areas. Colours such as green and light brown are recommended.

HyD

Contractor

 

Table 7.3        Proposed Landscape and Visual Mitigation Measures during Operational Phase

Items

Landscape and Visual Mitigation Measures

Funding Agency

Implementation Agency

Maintenance/ Management Agency

 

1

Cultivation of areas compacted during construction.  Areas compacted during the construction phase that are not required during the operation phase, are to be cultivated to a depth of up to 300mm in accordance with the future Landscape Specification.

HyD

Contractor/HyD

LCSD/HyD

2

Soil stabilisation and planting. During the design phase, a soil stabilisation and embankment planting strategy will be developed to ensure that land affected by slope excavation can be replanted.  Soil preparation and the selection and provision of suitable growing medium is to be completed in accordance with the relevant best practice guidelines.

HyD

Contractor/HyD

LCSD/HyD

3

Tree and Shrub Planting.  All planting of trees and shrubs is to be carried out in accordance with the relevant best practice guidelines.  Plant densities are to be provided in future detailed design documents and are to be selected so as to achieve a finished landscape that matches the surrounding, undisturbed, equivalent landscape types. 

HyD

Contractor/HyD

LCSD/HyD

4

LMM 4 - Relocation. Landscape Resources of value to be re-located where practically feasible.

HyD

Contractor/HyD

LCSD

5

Design of Structures. Where possible, built structures will utilise appropriate designs to complement the surrounding landscape.  Materials and finishes will also be considered during detailed design.

HyD

Contractor/HyD

HyD

6

Design of noise barriers. The 2.5m high vertical noise barrier for the planned schools will be in the form of concrete structure installed with barrier panels to align with the existing provision in the vicinity and to integrate into the landscape. 

HyD

Contractor/HyD

HyD

7

Plantings in addition to the landscape mitigation plantings proposed, appropriate new plantings will be installed as appropriate to help integrate the new structures into the surrounding landscape.

HyD

Contractor/HyD

LCSD/HyD

Note: (1) LCSD means Leisure and Cultural Services Department;

             (2) HyD should be responsible for the maintenance and management for hard streetscape works and LCSD should be responsible for the maintenance and management of soft landscape works.

 

The design, implementation and maintenance of landscape and visual mitigation measures should be checked monthly to ensure that they are fully implemented.  Any potential conflicts between the proposed landscape measures and any other project works or operational requirements should also be recorded for the Contractor to resolve in early stage, without compromising the intention of the mitigation measures.

The landscape and visual mitigation measures recommended in the EIA Study are outlined in the Environmental Mitigation Implementation Schedule (EMIS) (Annex B).