3.                       Air Quality IMPACT Assessment

 

3.1                    Introduction

 

3.1.1              This Chapter presents an assessment of air quality impact associated with the construction and operation of the Hang Hau Tsuen Channel at Lau Fau Shan (the Project).

 

3.1.2              Potential construction phase air quality impact consists of increased fugitive dust from excavation and other construction works affecting the nearby air quality sensitive receivers.

 

3.1.3              The proposed access road along the northern channel bank will be open to public use. In addition, a viewing point and carpark will be constructed at the channel outfall. The potential operation phase air quality impact will be the vehicular emission arising from the increase traffic. In addition, annual maintenance cutting of vegetation and sediment removal may be necessary during operation of the drainage channel. The above activities, however, are not expected to have any significant air quality impacts.

 

3.2                    Air Quality Assessment Criteria

 

3.2.1              The criteria for evaluating air quality impacts and the guidelines for air quality assessment are laid out in Annex 4 and Annex 12 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

 

3.2.2              The principal legislation regulating air emissions in Hong Kong is the Air Pollution Control Ordinance (APCO) (Cap.311) of 1983 and its subsidiary regulations. The whole of the HKSAR has been covered by Air Control Zones. The Hong Kong Air Quality Objectives (AQOs) stipulate maximum acceptable concentration of air pollutants. The AQOs for 1 hour, 24 hour and annual concentrations of four major pollutants are shown in Table 3.1.

 


Table 3.1

Hong Kong Air Quality Objectives (AQOs)

 

Pollutants

Concentration in

Micrograms per Cubic Meters (µg/m3)

Averaging Time

1 hourA

8 hoursB

24 hoursB

1 yearC

Carbon Monoxide (CO)

30,000

10,000

--

--

Nitrogen Dioxide (NO2)

300

--

150

80

Sulphur Dioxide (SO2)

800

--

350

80

Total Suspended Particulates (TSP)

500E

--

260

80

Respirable Suspended Particulates (RSP)D

--

--

180

55

 

Notes:

Concentrations measured at 298K (25°C) and 101.325 kPa (one atmosphere).

A              Not to be exceeded more than 3 times per year.

B              Not to be exceeded more than once per year.

C              Arithmetic means.

D              Respirable suspended particulates means suspended particulates in air with a nominal aerodynamic diameter of 10 micrometer (µm) or smaller

E              This control limit has no statutory basis but is used as a target level for limiting fugitive dust emissions generated by construction activities.

 

3.2.3              The EIAO-TM also stipulates that the odour level at a sensitive receiver should not exceed 5 odour units based on an averaging time of 5 seconds for odour prediction assessment.

 

3.3                    Study Area

 

3.3.1              The Study Area for air quality impact assessment is defined by a distance of 500 m from the boundary of the Project works site.

 


3.4                    Air Sensitive Receivers

 

3.4.1              The representative air sensitive receivers (ASRs) that may potentially be impacted by the Project are listed in Table 3.2 and shown in Figure 3.1.

 

Table 3.2

Representative Air Sensitive Receiver (ASR)

 

Representative ASR

General Description

No. of Floors

Approximate Distance to Works Site Boundary

Shortest Horizontal Distance to Road Kerb

ASR 1

Wing Jan Kindergarten

1

22 m

82 m to New Road

18 m to Deep Bay Road

ASR 2

Wing Jan Camp

1

4 m

32 m to New Road

45 m to Deep Bay Road

ASR 3

Village house at No. 84 Hang Hau Tsuen

2

1 m

 10 m to New Road

154 m to Deep Bay Road

ASR 4

Village house at No. 57 Hang Hau Tsuen

1

1 m

 16 m to New Road

267 m to Deep Bay Road

ASR 5

Village house at No. 26 Hang Hau Tsuen

2

1 m

 15 m to New Road

ASR 6

Village house at No. 88 Hang Hau Tsuen

2

1 m

30 m to New Road

ASR 7

House at Deep Bay Grove

3

150 m

175 m to New Road

48 m to Deep Bay Road

ASR 8

Village house at No. 30 Lau Fau Shan

2

210 m

245 m to New Road

24 m to Deep Bay Road

ASR 9

Planned residential development (TPB application no. A/YL-LFS/156)

2-3

40 m

50 m to New Road

5 m to Deep Bay road

ASR 10

Village house at No. 45A Hang Hau Tsuen

2

1 m

4 m to New Road

 

Note:

The location of the ASRs is shown in Figure 3.1.

 


3.5                    Baseline Air Quality

 

3.5.1              The Study Area is located in the north-western part of Hong Kong and to the north is Shenzhen. This area falls within the Deep Bay Airshed and is topographically confined. The area generally exhibits a limited dispersive capacity because of the occurrence of inversion layers in the morning and evening[1].

 

3.5.2              The wind rose from the Lau Fau Shan Station indicates that the dominant wind direction is mainly easterly with occasional north-easterly and south-easterly wind.

 

Existing Air Conditions

 

3.5.3              As there is no monitoring station at the Study Area, EPD's Air Quality Monitoring Station at Yuen Long was used to establish ambient air quality over the Study Area. Background concentration for NO2 and RSP are estimated based on 5-year averages of the most recent monitored air quality data obtained by EPD (i.e. 2003-2007) at the Yuen Long station. Background concentration for CO is estimated based on 4-year averages (2004-2007) of data obtained by EPD at the Yuen Long station. The background data of the air pollutants concentrations at EPD’s Yuen Long Station are listed in Table 3.3.

 

Table 3.3

Average Background Air Pollutants Concentrations at EPD’s Yuen Long Station

 

Pollutants

Annual Average Concentration (μg/m3)

AQOs (μg/m3)

CO

941

--

NO2

60

80

RSP

64

55

TSP

103

80

 

3.5.4              The table indicates that the averaged concentration of RSP and TSP at Yuen Long exceed the stipulated AQOs.

 

3.5.5              The high RSP and TSP levels recorded at EPD's Yuen Long Station were probably attributable to various construction activities in the vicinity of the Station and the heavy industrial activities near Shenzhen as well as vehicular emission from the nearby highways.


3.6                    Construction Phase Impact Assessment

 

               Dust

 

3.6.1              The principal potential source of air quality impact arising from the construction of the Project will be fugitive dust. The temporary dust nuisance, measurable as TSP (Total Suspended Particulates) and RSP (Respirable Suspended Particulates) will be generated as a result of construction activities, especially from site clearance / excavation works where dusty and silty material movement may be involved. The nuisance from emission of construction vehicles and plant will be relatively small for the area involved, as the number of construction vehicles and plant is expected to be limited and small. Moreover, the dust impact is expected to be relatively insignificant as the excavated material of the area will be mainly from the stream which have high moisture content. The major items of the works are:

 

Ÿ                 site clearance;

Ÿ                 excavation works to formation level;

Ÿ                 construction of channel structures / linings, box culverts, drainage pipes, and ancillary drainage facilities;

Ÿ                 construction of footbridges, maintenance access road and associated road fixtures; and

Ÿ                 planting and landscaping works.

 

3.6.2              The construction duration is expected to last for about 3 years within the tentative construction programme timeframe of end 2009 to end 2012.

 

3.6.3              The most affected air sensitive receivers will be those village houses near and around the works areas. Only minor impacts will be expected due to off-site transportation of spoil materials because the volume of spoil materials requiring disposal is expected to be relatively small. It is expected that the approximate amount of C&D materials to be handled per day is about 30 m3 which equates to approximately 6 trucks per day.

 

3.6.4              Due to the limited scale of construction works required, no concrete batching plants will be required for this Project. Construction tenders / contracts will stipulate that on-site concrete batching shall not be practised.

 

3.6.5              Parts of the proposed channel sites are natural stream. Portion of the natural stream bed will be retained to avoid impacting on the established mangrove stands. Hence, the amount of spoil and construction activities is expected to be relatively small.

 

 

3.6.6              As the construction works will likely be constructed section by section, construction dust nuisance is not expected to cause any significant dust impacts to the nearby sensitive receivers. The quantity of the spoil materials from site clearance and excavation is unlikely to be large enough to cause a significant dust nuisance. It is anticipated that excavated material will only be stockpiled on each local works area and the duration of the stockpiling will be as short as possible. The feasibility of reusing some of the excavated materials as backfilling materials will be rigorously examined during the detailed design stage. As some materials may be used back in the construction processes, the quantity of material need to be disposed of can be reduced. Hence construction dust nuisance at nearby representative sensitive receivers will expect to be insignificant. Provided that proper construction dust mitigation measures are in place as required by the Air Pollution Control (Construction Dust) Regulation, adverse dust impact during is not expected.

 

3.6.7              As the Project is close to existing road, purpose-built haul road is not expected for the transportation of excavated material and filling material.

 

Odour

 

3.6.8              Odour is not expected from the excavated stream material. In the unlikely event that potential odourous materials are encountered during construction, excavation works should be conducted in the shortest time span possible. Programming of the works should be carried out to ensure that the time for such works can be minimised. If necessary, the Contractors should also liaise with local resident to inform them of the duration of potential odour nuisance, and that efforts are made to minimise and mitigate such nuisance. Excavated material, if found to be odorous, should be placed as far away from air sensitive receivers as possible. Temporary stockpiles of odorous excavated material should be removed off-site as soon as practically possible within 2 days to avoid odour nuisance arising.

 


3.7                    Operational Phase Impact Assessment

 

Introduction

 

3.7.1              Potential air quality impacts during operational phase of the Project are identified as follow:

 

§                     Traffic emission from the proposed access road (which will be open for public use) and the associated carpark near the viewing point; and

 

§                     Dust and odour from the routine maintenance of the proposed channel.

 

3.7.2              Apart from maintenance, there are no other potential odour impacts at the ASRs during normal operation of the Hang Hau Tsuen Channel.

 

Traffic Emission Impact

 

3.7.3              The proposed access road will be open to public use. According to the HKPSG, a minimum buffer distance of 5 m to ASRs is recommended for local distributor road. As shown in Table 3.2, majority of the ASRs would have adequate buffer distance to the proposed access road, except ASR 10 (at 4 m). However, it should be noted that the HKPSG recommendation is relevant to local distributor road with continuous free flowing through traffic. As there is no through traffic for the access road and only a very few parking spaces (8-9 nos.) will be provided, the worst case forecast peak traffic flow in 2027 is expected to be 50 vehicles with 10% heavy vehicles per hour only. With such very limited traffic flow on the access road, the expected vehicular emission at the ASR 10 would still be acceptable.  In addition, traffic management will be implemented to restrict vehicles longer than 7 m from using the access road. With the very low traffic flow and buffer distance, adverse traffic emission impact from the proposed access road to the nearby ASR is therefore not expected.

 

Maintenance Impact

 

3.7.4              Maintenance would be necessary for the constructed channel to remove excessive silts, vegetation, debris and obstructions in order to maintain its hydraulic performance and structural integrity. Siltation will generally be allowed to accumulate and removal of excess silt would be carried out at locations where specific flooding or safety issue is identified. The excavated sediment will be properly stored and disposed of to minmise dust and odour nuisance. Little or no maintenance will be necessary for the natural stream bed sections of the channel. Therefore, maintenance of the channel during the operational phase is unlikely to cause any adverse air quality impacts in terms of dust and odour.

 

3.8                    Mitigation Measures

 

Construction Phase

 

Construction Dust

 

3.8.1              In order to comply with Air Pollution Control Ordinance (APCO), the Contractor should undertake at all times measures to prevent dust nuisance as a results of his activities. The Contractor should follow all the requirements for dust control stipulated in the Air Pollution Control (Construction Dust) Regulation. Dust suppression measures should be installed as part of good construction practice, and they should be incorporated in the Contract Specification and implemented to minimize dust nuisance to within acceptable levels arising from the works. The followings are examples of the dust suppression measures.

 

(i)                  The area in which excavation takes place shall be sprayed with water immediately prior to, during and immediately after the excavation to minimise dust generation.

 

(ii)                The Contractor shall frequently clean and water the site to minimize fugitive dust emissions.

 

(iii)               Effective water sprays shall be used during the delivery and handling of aggregate, and other similar materials, when dust is likely to be created and to dampen all stored materials during dry and windy weather.

 

(iv)              Watering of exposed surfaces shall be conducted at least 2 times per day especially during dry and windy weather.

 

(v)                Areas within the site where there is a regular movement of vehicles must be regularly watered as often as necessary for effective suppression of dust or as often as directed by the Engineer.

 

(vi)              Where dusty material are being discharged to vehicle from a conveying system at a fixed transfer point, a three-sided roofed enclosure with a flexible curtain across the entry shall be provided. Exhaust fans shall be provided for this enclosure and vented to a suitable fabric filter system.

 

(vii)             The Contractor shall restrict all motorised vehicles within the site, excluding those on public roads, to a maximum speed of 15 km per hour and confine haulage and delivery vehicles to designated roadways inside the site.

 

(viii)           Wheel washing facilities shall be installed and used by all vehicles leaving the site. No earth, mud, debris, dust and the like shall be deposited on public roads. Water in the wheel cleaning facility shall be changed at frequent intervals and sediments shall be removed regularly. The Contractor shall submit details of proposals for the wheel cleaning facility. Such wheel washing facilities shall be usable prior to any earthworks excavating activity on the site. The Contractor shall also provide a hard-surfaced road between any washing facility and the public road.

 

(ix)              All vehicle exhausts shall be directly vertically upwards or directed away from the ground.

 

(x)                Any materials dropped on paved roads shall be cleaned up immediately to prevent dust nuisance.

 

              Odour

 

3.8.2              In the event that excavated materials are found to be odourous, the following measures should be implemented by the Contractor.

 

(i)                  Place odorous excavated material as far away (say, at least 20m) from air sensitive receivers as possible.

 

(ii)                Temporary stockpiles of odorous excavated material should be properly covered with tarpaulin and should be removed off-site as soon as practically possible within 2 days to avoid any odour nuisance arising.

 


Operational Phase

 

3.8.3              No adverse air quality impact is identified during operational phase. In the event that sediment excavated during maintenance are found to be odourous, the following measures should be implemented by DSD (or DSD’s maintenance contractor).

 

(i)                  Place odorous excavated material as far away (say, at least 20m) from air sensitive receivers as possible.

 

(ii)                Odorous excavated material should be properly covered with tarpaulin or packed in plastic bags or stored in enclosed skips and should be removed off-site as soon as practically possible within 2 days to avoid any odour nuisance arising.

 

3.9                    Cumulative Impacts

 

3.9.1             There will likely be one concurrent project in the vicinity of the proposed Project (see Section 2.9). As the concurrent project is located about 150 m from the Project and given the small scale works of the concurrent project, cumulative air quality impact is not expected.

 

3.10                Monitoring and Audit Requirements

 

3.10.1          Dust impacts during the construction phase can be readily mitigated through implementation of standard mitigation measures and good housekeeping practices.

 

3.10.2          However, if the proposed construction dust mitigation measures are not fully implemented, it is likely that some nearest air sensitive receivers would suffer unacceptable impact. It is therefore recommended that an Environmental Monitoring & Audit (EM&A) programme in respect of dust issue be carried out at representative sensitive receivers to monitor the effectiveness and efficiency of the dust suppression measures.

 

3.10.3          It is recommended that at least the following representative ASRs (Table 3.4) should be selected for monitoring purpose during the construction phase. These representative sensitive receivers have been selected for monitoring because of their locations are close to the construction works areas, and/or are downwind from the sites under the most predominant meteorological conditions and hence, are the mostly likely being impacted if dust suppression measures are not properly implemented.

 

3.10.4          No monitoring is required during operational phase.

 

3.10.5          The monitoring requirement is broadly presented in Chapter 10 of this Report. Details of the monitoring and audit of construction dust will be presented in the separate EM&A Manual.

 

Table 3.4

Representative ASRs chosen for Air Quality Monitoring during Construction Phase

 

Air Quality Monitoring Station

ASR ID

General Description

A1

ASR 2

Wing Jan Camp

A2

ASR 4

Village house at No. 57 Hang Hau Tsuen

 

Notes:

Subject to the location of the construction works and to be proposed by the ET Leader.

 

3.11                Summary

 

3.11.1          The construction dust impact assessment has identified air sensitive receivers within the Study Area. Construction works that may cause potential construction dust nuisance is also identified. Mitigation measures, as required by Air Pollution Control (Construction Dust) Regulation, are also highlighted. Provided that the Contractor implements all the necessary mitigation, air quality at nearby air sensitive receivers during construction phase is expected to comply with the 1 hour TSP guideline and the daily TSP Air Quality Objectives.

 

3.11.2          Air quality monitoring is recommended at selected air sensitive receivers during the construction period to check for compliance with the permissible dust levels and effectiveness of the proposed mitigation measures.

 

3.11.3          During the operational phase of the Project, given the low volume of vehicles expected to use the access road, vehicular emission impact from the proposed access road upon the nearby air sensitive receivers is not expected. Maintenance of the channel is also unlikely to cause any adverse impact during operational phase.



    [1]            Royal Observatory Hong Kong (1984) Meteorological Assessment of Atmospheric Transport Condition in the Deep Bay Airshed.