4.1.1
This Chapter presents an assessment
of noise impacts associated with the construction and operation of the proposed
Project.
4.1.2
Noise generated during the
construction phase by works activities and powered mechanical equipment would
pose potential impact to the surrounding Noise Sensitive Receivers (NSRs).
Appropriate mitigation measures are recommended where necessary to mitigate
such impacts.
4.1.3
The proposed access road along the
northern channel bank will be open to public use. In addition, a viewing point
and carpark will be constructed at the channel outfall. The introduction of
road traffic along the maintenance access road may pose potential traffic noise
impact to nearby noise sensitive receivers during operation. Operational
phase of the channel would only involve small scale routine maintenance and is
not expected to generate any excessive noise.
Construction Noise
4.2.1
There are currently no statutory
criteria for noise generated from construction work other than percussive
piling during the daytime hours of
4.2.2
The noise standards for general
construction works during normal working hours (i.e. 0700 to 1900 hours on any
day not being a Sunday or public holiday) stipulated in
Table 1B of Annex 5 of the
EIAO-TM are given
in Table
4.1.
EIAO-TM Daytime
Construction Noise Standards
Uses |
Daytime Construction Noise Standards, Leq (30
minutes) dB(A) |
Domestic Premises |
75 |
Educational
institutions (normal periods) |
70 |
Educational
institutions (during examination periods) |
65 |
Notes:
These standards assume the use of
open windows for ventilation. They are the maximum permissible noise levels
assessed at 1 m from the receiver’s external façade.
4.2.3
The principal legislation on the
control of construction noise during restricted hours is the Noise Control
Ordinance (NCO) (Cap.400) and its associated Technical Memoranda (TM). The NCO
provides statutory controls on general construction works during the restricted
hours (i.e. 1900 to 0700 hours Monday to Saturday and at any time on Sundays
and public holidays). The Contractor shall comply with the NCO and all relevant
regulations under this Ordinance, including restrictions placed on noise from
construction work and the requirements to seek Construction Noise Permit (CNP).
At present, construction works during restricted hours are not expected.
However, should works have to be carried out during restricted hours, a CNP
must be obtained from the relevant Noise Control Authority (i.e. EPD) before
the works are allowed to take place. Percussive piling works are also subjected
to CNP licensing under the NCO. The Contractor is also required to display
these permits appropriately.
4.2.4
Despite the description or
assessment made in the subsequent sections, there is no guarantee that a CNP
will be issued for the project construction. The Noise Control Authority will
consider a well-justified CNP application, once filed, for construction works
within restricted hours as guided by the by the relevant Technical Memorandum
(Memoranda) issued under the NCO. The Noise Control Authority will take into
account of contemporary situations/conditions of adjoining land uses and any
previous complaints against construction activities at the site before making
his decision in granting a CNP. Nothing in this Report shall bind the Noise
Control Authority in making his decision. If a CNP is to be issued, the Noise
Control Authority shall include in it any conditions that are considered
appropriate and such conditions are to be followed while the works covered by
the permit are being carried out. Failure to comply with any such conditions
will lead to cancellation of the CNP and prosecution action under the NCO.
Road Traffic Noise
4.2.5
Road traffic noise criteria are
listed in Table 1A of Annex 5 of the EIAO-TM and listed in Table 4.2 below.
Road Traffic
Noise Criteria
Noise Sensitive Uses |
Peak Hour Traffic, L10(1 hour),
dB(A) |
All domestic premises, hotels,
offices and temporary housing accommodation |
70 |
Educational institutions including
kindergartens, nurseries and all others where unaided voice communication is
required, places of public worship and courts of law |
65 |
Hospitals, clinics, convalescences
and home for the aged, diagnostic rooms, wards |
55 |
Notes:
The above standards apply
to uses which rely on opened windows for ventilation.
The above standards should
be viewed as the maximum permissible noise levels assessed at 1 m from the
external façade.
4.2.6
According to EIAO Guidance Note No. 12/2005 – “Road Traffic
Noise Impact Assessment Under the EIAO”, for road traffic noise, in cases where
practicable direct mitigation measures would not be wholly adequate in
mitigating noise impacts, indirect mitigation measures in the form of window
insulation and air-conditioning is often the “last resort” in an attempt to
ameliorate the residual impact.
4.2.7
On the eligibility testing criteria for indirect noise
mitigation measures, reference is made to the relevant procedures stipulated in
Calculation of Road Traffic Noise (CRTN) (paragraph 6 on Requirements for use
with the Noise Insulation Regulations) which is used for the assessment of road
traffic noise as per Section 5.1, Annex 13 of the EIAO-TM. The testing criteria
are set out as below:
(i)
the
predicted overall noise level from the the road project together with other
traffic noise in the vicinity must be above a specified noise level (e.g. 70
dB(A) for domestic premises and 65 dB(A) for education institutions, all in L10(1hr));
(ii)
the
predicted overall noise level is at least 1.0 dB(A) more than the prevailing
traffic noise level, i.e. the total traffic noise level existing before the
works to construct the road were commenced; and
(iii)
the
contribution to the increase in the predicted overall noise level from the road
project must be at least 1.0 dB(A).
4.2.8
For the purpose of this EIA Study, all roads are described as
either:
·
‘existing’ which are the existing roads that are unchanged by
the Project; or
·
‘new’ which is the proposed access road.
Noise
Assessment Study Area
4.3.1
For the purpose of noise assessment,
the Study Area covers essentially 300 m from the boundary of each of the work
sites of the Project. This Study Area can be reduced if the first layer of the
noise sensitive receivers, closer than 300 m from the boundary, provides
acoustic shielding to those receivers at further distance behind.
Description
of the Existing
Noise Environment
4.3.2
The major landuse in the vicinity
of the Project area is village
environs. Some industrial establishments, such as open storage
sites and container yards, can be
found along
4.3.3
The existing noise environment near
the upstream portion of Hang Hau Tsuen stream is dominated by the road traffic
on
4.3.4
Noise generated by the commercial
activities at Lau Fau Shan is considered to be insignificant.
4.4
Representative
Noise Sensitive Receivers
4.4.1
The Representative Noise Sensitive
Receivers (NSRs) chosen for noise assessment are shown in Figure 4.1. Photographs
showing these NSRs are shown in Figure 1 of Appendix 4.1. These Representative NSRs are selected in
accordance with the criteria in Annex 13 of the EIAO-TM. Reference has been
made to the landuses annotated under the following latest Outline Zoning Plans
(OZPs): S/YL-HT/9 and S/YL-LFS/7. Based on the available information at the
time of assessment, there is an approved residential development to the north
of the Project (TPB Application No. A/YL-LFS/156). However, no development
layout or programme is available at the time of the EIA Study. A description of the Representative NSRs is
tabulated in Table 4.3.
Representative Noise Sensitive Receivers (NSRs)
Representative NSR |
General Description |
No. of Floors |
Approximate Horizontal Distance from Construction
Activities (Notional Point Source) |
Shortest Horizontal Distance to Road Kerb |
NSR 1 |
Wing
Jan Kindergarten |
1 |
42
m |
82 m to New Road |
NSR 2 |
Wing
Jan Camp |
1 |
17
m |
32 m to New Road |
NSR 3* |
Village
house at No. 84 Hang Hau Tsuen |
2 |
15
m |
10 m to New Road 154 m to |
NSR 4* |
Village
house at No. 57 Hang Hau Tsuen |
1 |
15
m |
16 m to New Road |
NSR 5* |
Village
house at No. 26 Hang Hau Tsuen |
2 |
16
m |
15 m to New Road |
NSR 6* |
Village
house at No. 88 Hang Hau Tsuen |
2 |
14
m |
30 m to New Road |
NSR 7 |
House
at Deep Bay Grove |
3 |
165
m |
175 m to New Road |
NSR 8 |
Village
house at No. 30 Lau Fau Shan |
2 |
255
m |
245 m to New Road |
NSR 9 |
Planned
residential development |
2 -
3 |
55
m |
50 m to New Road |
NSR 10* |
Village
house at No. 45A Hang Hau Tsuen |
2 |
12
m |
4 m to New Road |
Note:
The location of the NSRs is
shown in Figure 4.1.
* Tin-sheeted house, height
not more than 5m.
4.5
Construction
Noise Impact Assessment
Potential
Sources of Impacts
4.5.1
The main construction activities for the proposed drainage
channel include site clearance, excavation of channel to formation level, construction of channel linings,
footbridges, concreting works, road surfacing works and landscaping works.
4.5.2
Dedicated
haul road is not anticipated for the Project as access to the site is readily available
from
4.5.3
Construction of the channel will
generally be carried out starting from the downstream end to the upstream to
facilitate simple draining of the works site. However, the Contractor may start
at isolated sections to suit his allocation of resources and to maintain access
across the channel banks.
4.5.4
Majority of the potential
construction noise impact may occur during the site clearance and excavation
works, when soil and stream bed sediments are excavated and transported out of
the site. The construction of the Project includes construction of the channel,
concreting works, road resurfacing works and landscaping works. Since the
available works area is limited, the number of construction equipment will also
be limited. Portion of the channel involves retaining sections of the stream
bed and mangroves in-situ, as such construction activities is expected to be substantially
scaled down. Similarly, the construction of maintenance access road and foot
bridges will involve few mechanical equipment.
Construction
Equipment
4.5.5
The type and quantity of Powered
Mechanical Equipment (
4.5.6
The equipment used in the noise
calculation was based on site experience and was reviewed by the design
engineers. It was considered reasonable in terms of the types and numbers to be
used by the Contractor for satisfactory completion of the Project based on the
tentative construction programme, though there may be variation in the actual
construction stage. A copy of CEDD’s memo acknowledging the proposed
construction equipment is attached in Appendix 4.1.
Construction Schedule and Programme
4.5.7
The
construction duration for this Project is expected to last for about 36 months
within the tentative construction timeframe of end 2009 to end 2012.
Currently, construction work during
restricted hours is not anticipated.
Assessment Methodology and Assumptions
4.5.8
The construction noise assessment
has been conducted based on standard acoustic principles. The methodology has
made reference to the following:
§
Sections 5.3 & 5.4 of
Annex 13 of the EIAO-TM;
§
Technical Memorandum on Noise from
Construction Work other than Percussive Piling (TM-GW);
§
BS 5228: Part 1: 1997 – Noise and
Vibration Control on Construction and Open Sites, Part 1: Code of Practice for
Basic Information and Procedures for Noise and Vibration Control (BS5228); and
§
EIAO Guidance Note No. 9/2004 – “Preparation
of Construction Noise Impact Assessment under
the Environmental Impact Assessment Ordinance”.
4.5.9
In general
terms, the methodology used involves the following steps:
(i)
identification
of the most likely worst case scenario from the construction programme;
(ii)
identification
of the nearest representative NSRs to the work site;
(iii)
calculation
of the total Sound Power Level (SWL) of equipment to be used;
(iv)
calculation
of distance attenuation to NSRs from work site notional noise source point; and
(v)
comparison of
the Predicted Noise Levels (PNLs) with the relevant noise standards.
4.5.10
The assessment has been undertaken
on the basis of the assumption that all construction equipment will be located
on a notional noise source point (in accordance with the TM-GW) and is
operating at the same time. The various construction activities are not
expected to be carried out concurrently. Shielding effect from existing
building structures, and/or topographic features have not been considered to
simulate worst-case effect. A façade correction of +3 dB(A) is added to account
for the sound reflection from the building’s surface of a NSR.
Assessment Results
4.5.11
The unmitigated PNL at the Representative NSRs are
summarised below in Table 4.4. Detailed calculations are presented in Appendix
4.1.
Predicted
Noise Level during Construction of Hang Hau Tsuen Channel - Unmitigated
NSR |
Unmitigated Construction Noise Level, dB(A) |
|||||
Site Clearance |
Excavation to Formation
Level |
Construction of Channel
Lining, Crossings and other Works |
Concreting Works |
Road Surfacing Works |
Landscaping and
Finishing Works |
|
NSR 1* |
77 |
77 |
78 |
77 |
77 |
77 |
NSR 2 |
89 |
89 |
90 |
88 |
88 |
89 |
NSR 3 |
90 |
90 |
91 |
90 |
90 |
90 |
NSR 4 |
90 |
90 |
91 |
90 |
90 |
90 |
NSR 5 |
89 |
89 |
90 |
89 |
89 |
89 |
NSR 6 |
90 |
90 |
92 |
90 |
90 |
90 |
NSR 7 |
69 |
69 |
70 |
69 |
69 |
69 |
NSR 8 |
65 |
65 |
66 |
65 |
65 |
65 |
NSR 9 |
78 |
78 |
80 |
78 |
78 |
78 |
NSR 10 |
92 |
92 |
93 |
91 |
91 |
92 |
Notes:
Numbers in BOLD denote exceedance of daytime noise
standard: 75 dB(A) for residential premises, 70 dB(A)
for educational institution.
*
Wing Jan Kindergarten (noise standard during examination not applicable)
4.5.12 Table 4.4 shows that unmitigated construction noise levels would exceed the daytime noise standards at most of the Representative NSRs at Hang Hau Tsuen. The predicted exceedance is due to the close proximity of the construction works to the NSRs. However, the likely overall exceedance with respect to each receiver is expected to be intermittent and not severe, as some part of the works would be carried out within the channel where the noise would be partially shielded. Moreover, as the available works area for the channel, pipes or box culvert are limited, the use of heavy construction machinery will be limited. Nonetheless, adequate mitigation measures will be required. The recommended mitigation measures for the construction works are discussed in the subsequent section.
4.6
Operational
Noise Impact Assessment
Introduction
4.6.1 Potential noise impacts during operational phase of the Project are identified as follow:
·
Road traffic
noise from the proposed access road along the northern channel bank (which will
be open for public use); and
·
Noise from mechanical
equipment during the routine maintenance of the proposed channel.
Road Traffic Noise
4.6.2 The aim of this assessment is to quantify by computer modelling the traffic noise impact from the existing surrounding roads and the proposed access road (Road A) along the northern channel bank on the representative NSRs within a 15 years period upon the commencement of the operation of the Project. The location of the proposed access road (Road A) is shown in Figure 4.1.
Assessment
Criteria
4.6.3 Road traffic noise criteria used in this assessment are in accordance with the standards listed in Table 1A of Annex 5 of the EIAO-TM. The peak noise level from road traffic, measured in terms of L10 (1‑hr) is 70 dB(A) at domestic premises and 65 dB(A) at educational institutions. The peak noise level criterion of 55 dB(A) in L10 (1‑hr) is considered not applicable to the current assessment as no NSRs of the related uses were identified in the vicinity of the Project area.
4.6.4 Putting these criteria into the current assessment, the maximum predicted noise levels due to traffic on surrounding roads in terms of hourly L10 should not exceed 70 dB(A) for NSR 2 to NSR 10, and should not exceed 65 dB(A) for NSR 1.
Assessment
Methodology
4.6.5 An in-house developed computer model based on the U.K. Department of Transport's procedure "Calculation of Road Traffic Noise" (CRTN) was used to predict the hourly L10 levels at typical facades of NSRs near the subject site. Peak hour traffic forecast on the existing nearby roads and the proposed access road (Road A) for the year 2027 were used for the study (Appendix 4.2).
4.6.6 In order to assess the additional operational traffic noise impact brought by the proposed access road (Road A) on the nearby noise sensitive receivers, the same computer model was employed to assess the traffic noise impact in the year 2027 without the Project. Peak hour traffic data on the existing nearby roads for the year 2027 without the Project were used for this purpose (Appendix 4.2).
Noise
Sensitive Receivers
4.6.7 The representative noise sensitive receivers are identified in Table 4.3 above. Each of the NSRs has at least one assessment point located on the facade that is most affected by the traffic noise from the nearby roads. Subject to the orientation of the NSRs and their distances to the nearby roads, some of the NSRs have two or more assessment points on different facades. For NSR 1 and NSR 2, three assessment points were placed while for NSR 3, NSRs 5 to 8 and NSR 10, two assessment points were selected for each of them. For the planned NSR 9, four assessment points were placed. Location of the assessment points are shown in Appendix 4.2.
4.6.8 Some of the NSRs such as NSR 3, NSRs 5 to 10 are of multi-storeys. All assessment points were taken at 1.2 m above floor slabs and at 1 m away from the external facade of the building of the sensitive receivers. The mPD levels of each floor of the NSRs are tabulated below.
Floor Levels of the NSRs
Floor Levels |
NSRs |
|||||||||
NSR1 |
NSR2 |
NSR3 |
NSR4 |
NSR5 |
NSR6 |
NSR7 |
NSR8 |
NSR9 |
NSR10 |
|
1/F |
13.4 |
4.0 |
3.0 |
2.8 |
2.8 |
2.8 |
5.3 |
4.2 |
5.5 |
2.8 |
2/F |
-- |
-- |
5.5 |
-- |
5.3 |
5.6 |
8.3 |
6.7 |
8.5 |
5.3 |
3/F |
-- |
-- |
-- |
-- |
-- |
-- |
11.3 |
-- |
11.5 |
-- |
Road
Characteristics
4.6.9 The road sections that are within a distance of 300 m from the representative NSRs are considered in the model of this assessment. To simulate the worst case scenario, all the road sections in the model are assumed to be impervious with speed limit of 50 km/hr.
4.6.10 The proposed access road, Road A, will be connected to a viewing point with 8-9 numbers of parking spaces. It was assumed that the parking period for each vehicle at the parking space is half an hour at peak hour. As Road A is proposed to be a single two-ways road, it was therefore predicted that the peak traffic flow of Road A is 50 vehicles per hour. Vehicles longer than 7 m will be restricted from using the access road, hence a minimal 10% heavy vehicles are expected.
4.6.11 The traffic forecast in 2027 with and without the Project for the roads identified for this assessment are tabulated in Table 4.6 and Table 4.7 below. The location of the road network is shown in Appendix 4.2. A copy of Transport Department (TD) memo expressing no comments on the forecast traffic flow is included in Appendix 4.2.
Traffic Forecast in 2027
with the Project
Road Name |
Traffic Volume (veh/hr) |
% of Passenger Vehicle |
% of Heavy Vehicles |
Speed (km/hr) |
Road Surface |
Proposed access road (Road A) |
50 |
90 |
10 |
50 |
Impervious |
|
255 |
49 |
51 |
50 |
Impervious |
|
129 |
41 |
59 |
50 |
Impervious |
|
454 |
45 |
55 |
50 |
Impervious |
Access road to Lau Fau Shan Police Station (N4/S4) |
41 |
39 |
61 |
50 |
Impervious |
Notes:
* Vehicles longer than 7m will be restricted from using the
proposed access road.
Traffic Flow Data in 2027
without the Project
Road Name |
Traffic Volume (veh/hr) |
% of Passenger Vehicle |
% of Heavy Vehicles |
Speed (km/hr) |
Road Surface |
|
205 |
39 |
61 |
50 |
Impervious |
|
129 |
41 |
59 |
50 |
Impervious |
|
404 |
39 |
61 |
50 |
Impervious |
Access road to Lau Fau Shan Police Station (N4/S4) |
41 |
39 |
61 |
50 |
Impervious |
Assessment
Results
4.6.12 The predicted hourly L10 (1hour) dB(A) at the assessment points of the representative NSRs are tabulated in Table 4.8 to Table 4.10 below.
Predicted Hourly Traffic
Noise Level L10 at the Assessment Points of Representative NSRs in
2027 with the Project
NSR |
Assessment Point |
Predicted Hourly Traffic Noise
Level (L10 (1 hour), dB(A)) |
||
G/F |
1/F |
2/F |
||
NSR
1* |
N1A |
64 |
- |
- |
N1B |
67 |
- |
- |
|
N1C |
58 |
- |
- |
|
NSR
2 |
N2A |
67 |
- |
- |
N2B |
67 |
- |
- |
|
N2C |
64 |
- |
- |
|
NSR
3 |
N3A |
63 |
63 |
- |
N3B |
63 |
63 |
- |
|
NSR
4 |
N4 |
62 |
- |
- |
NSR
5 |
N5A |
57 |
57 |
- |
N5B |
58 |
58 |
- |
|
NSR
6 |
N6A |
59 |
59 |
- |
N6B |
57 |
57 |
- |
|
NSR
7 |
N7A |
68 |
68 |
68 |
N7B |
67 |
67 |
67 |
|
NSR
8 |
N8A |
70 |
70 |
- |
N8B |
71 |
71 |
- |
|
NSR
9 |
N9A |
68 |
68 |
68 |
N9B |
64 |
64 |
64 |
|
N9C |
60 |
60 |
60 |
|
N9D |
60 |
60 |
61 |
|
NSR
10 |
N10A |
61 |
61 |
- |
N10B |
62 |
62 |
- |
* Wing Jan Kindergarten
Predicted Hourly Traffic
Noise Level L10 at the Assessment Points of Representative NSRs in
2027 without the Project
NSR |
Assessment Point |
Predicted Hourly Traffic Noise
Level (L10 (1 hour), dB(A)) |
||
G/F |
1/F |
2/F |
||
NSR
1* |
N1A |
64 |
- |
- |
N1B |
67 |
- |
- |
|
N1C |
58 |
- |
- |
|
NSR
2 |
N2A |
67 |
- |
- |
N2B |
67 |
- |
- |
|
N2C |
63 |
- |
- |
|
NSR
3 |
N3A |
62 |
62 |
- |
N3B |
61 |
61 |
- |
|
NSR
4 |
N4 |
59 |
- |
- |
NSR
5 |
N5A |
54 |
54 |
- |
N5B |
55 |
55 |
- |
|
NSR
6 |
N6A |
58 |
58 |
- |
N6B |
53 |
53 |
- |
|
NSR
7 |
N7A |
67 |
67 |
67 |
N7B |
67 |
67 |
67 |
|
NSR
8 |
N8A |
70 |
70 |
- |
N8B |
71 |
71 |
- |
|
NSR
9 |
N9A |
67 |
67 |
67 |
N9B |
63 |
63 |
63 |
|
N9C |
58 |
58 |
59 |
|
N9D |
60 |
60 |
60 |
|
NSR
10 |
N10A |
57 |
57 |
- |
N10B |
57 |
57 |
- |
* Wing Jan Kindergarten
Maximum Predicted Hourly
Traffic Noise Level L10 at the Representative NSRs in 2027
NSR |
Floor |
Maximum |
||
With Project |
Without Project |
Difference |
||
NSR 1* |
G/F |
67 |
67 |
0 |
NSR 2 |
G/F |
67 |
67 |
0 |
NSR 3 |
G/F |
63 |
62 |
1 |
1/F |
63 |
62 |
1 |
|
NSR 4 |
G/F |
62 |
59 |
3 |
NSR 5 |
G/F |
58 |
55 |
3 |
1/F |
58 |
55 |
3 |
|
NSR 6 |
G/F |
59 |
58 |
1 |
1/F |
59 |
58 |
1 |
|
NSR 7 |
G/F |
68 |
67 |
1 |
1/F |
68 |
67 |
1 |
|
2/F |
68 |
67 |
1 |
|
NSR 8 |
G/F |
71 |
71 |
0 |
1/F |
71 |
71 |
0 |
|
NSR 9 |
G/F |
68 |
67 |
1 |
1/F |
68 |
67 |
1 |
|
2/F |
68 |
67 |
1 |
|
NSR 10 |
G/F |
62 |
57 |
5 |
1/F |
62 |
57 |
5 |
* Wing Jan Kindergarten
4.6.13 According to the predicted traffic noise level as tabulated in Table 4.8 and Table 4.10, the maximum predicted noise level in the year 2027 with the Project at the majority of the noise sensitivity receiver is within the traffic noise criterion of 70 dB(A) for residential and 65 dB(A) for school while the predicted noise level at the NSR 8B exceed the residential criterion by 1 dB(A) and that at the NSR 1B exceed the school criterion by 2 dB(A). However, as shown in Table 4.9 and Table 4.10, there will be no increase of the predicted traffic noise at these two NSRs with and without the Project. This shows that these two NSRs will not experience any significant additional noise after the operation of the proposed access road (Road A).
4.6.14 By comparing the predicted traffic noise levels upon the other representative NSRs in the year 2027 with and without the Project (Tables 4.8 to 4.10), some of the representative NSRs would experience an increase in traffic noise level by more than 1 dB(A). This additional traffic noise impact due to the operation of the proposed access road (Road A) would be mostly on the representative NSRs along Road A, namely NSR 3, NSR 4, NSR 5, NSR 6 and NSR 10. Nevertheless, the predicted traffic noise levels on these NSRs were still well within the criterion of 70 dB(A).
4.6.15 Therefore, for most of the NSRs, the predicted maximum traffic noise levels in 2027 with and without the Project will be the same or with the differences not more than 1 dB(A) and will still be within the relevant traffic noise criteria (except NSRs N8B and N1B which has been explained in Section 4.6.13 above). In conclusion, no adverse traffic noise impact would be brought by the operation of the Project to the nearby NSRs.
Maintenance of the Channel
4.6.16
Maintenance would be necessary for the proposed channel to
remove excessive silts, vegetation, debris and obstructions in order to
maintain its hydraulic performance and structural integrity. Siltation will
generally be allowed to accumulate and removal of excess silt would be carried
out at locations where it would impede water flow. Such small scale maintenance
would require only light mechanical equipment such as a small loader and/or a
small crane truck. Hand-held equipment will be used for vegetation removal.
Little or no maintenance will be necessary for the natural stream bed section
of the proposed channel. Therefore the operational phase of this Project (in
terms of maintenance of the channel) would unlikely cause any adverse noise
impact.
Construction Phase
4.7.1 The predicted noise levels showed that construction works would give rise to daytime noise impacts to most of the Representative NSRs. The following types of mitigation measures are recommended.
Level 1 Mitigation - Use of Quiet Plant
4.7.2
The use of quiet plant (also
referred as silenced equipment) can provide significant reduction in noise
level. Quiet plant is defined as PME whose actual sound power level is less
than the value specified in the TM-GW for the same piece of equipment. The
common source of these information is from international standard /
certification, e.g. BS 5228. To allow the Contractor some flexibility to select
equipment to suit actual needs, it is considered too restrictive to specify
which specified silenced equipment to be used for the construction works. Hence, it
is preferable and practical to specify the noise performance specification of the
plant on site in terms of the sound power level so that the Contractor is
allowed some flexibility. It should be noted that various types of silenced
equipment can be found in
4.7.3 The use of quiet plant is considered to be the most effective ways of alleviating construction noise impact. The Contractor should use quiet plant with sound power level lower than that stipulated in the TM-GW as the Level 1 mitigation for construction noise.
4.7.4 The use of mini or lower power rating equipment (e.g. mini excavator) should also be considered where practical. This technique would be feasible and practical at some locations given the limited space available for using large size construction equipment and the small scale works involved.
4.7.5 The Contractor should take note of ETWB TCW No. 19/2005 – “Environmental Management on Construction Sites” which sets out the policy and procedures requiring contractors to, among others, adopt Quality Powered Mechanical Equipment (QPME)[1].
4.7.6 A list of quiet powered mechanical equipment (PME) recommended for use during construction phase is tabulated below in Table 4.11.
Quiet Powered Mechanical
Equipment Recommended for Use during Construction Phase
Powered Mechanical Equipment |
Power Rating / Size, Weight |
Reference |
SWL, dB(A) |
Excavator, loader |
52
kW |
BS5228
C.3-97 |
105 |
Dump truck |
450
kW, 50 t |
BS5228
C.9-39 |
103 |
Crane |
62
kW |
BS5228
C.7-114 |
101 |
Vibratory roller |
9
kW |
BS5228
C.3-115 |
102 |
Concrete lorry mixer |
22
kW, 6 m3 |
BS5228
C.6-23 |
100 |
Vibratory poker |
2
kW |
BS5228
C.6-32 |
100 |
Asphalt paver / spreader |
90
kW, 13 t |
BS5228
C.8-24 |
101 |
Road roller |
10
t |
BS5228
C.8-25 |
96 |
4.7.7 With the use of quiet plant, most of the Representative NSRs still exceed the noise standard and will still require further mitigation measures.
Level 2 Mitigation - Use of Temporary Noise Barriers
4.7.8 Since most of the NSRs within the Project area are typically low-rise tin-sheeted village houses of not more than 2 storeys (all are less than 5 m tall), it would be effective to have noise screening structures or temporary noise barriers purposely-built along the site boundary to provide additional protection to NSRs close to the construction site boundary. This could be in the form of purposely-built site hoarding constructed from appropriate materials with a minimum superficial density of 7 kg/m2. Noise barrier should be provided for noisy construction activities that would be undertaken close (about 30 m or less) to NSRs. The noise barrier should have a vertical height of at least 3 m or (depending on the height of the NSRs to be protected) a height ensuring that the operating equipment can be shielded from the view of the NSRs. The temporary noise barrier should have no gaps or opening at joints. The Contractor should regularly inspect and maintain the noise barrier to ensure its effectiveness.
4.7.9 For the construction works which have the potential to exceed the noise standards on nearby NSR and whose line of sight cannot be effectively blocked by the temporary noise barrier, movable (mobile) barriers should be provided. This may also be applicable in situation where construction of a temporary noise barrier may not be possible due to site / space constraints, for example blocking village or emergency vehicle access. Movable barriers of at least 2.5 m height with a small cantilevered upper portion and skid footing can be located within a few meters of stationary plant (e.g. generator) and within about 5 m or more of a mobile equipment (e.g. excavator), such that the line of sight to the NSR is blocked by the barriers.
4.7.10 With the shielding effect provided by the proposed temporary noise barriers and/or mobile barriers, noise reduction of 10 dB(A) and 5 dB(A) is expected for stationary equipment and mobile equipment respectively.
4.7.11 The proposed noise barrier for the affected Representative NSRs is shown in Figure 4.2. A typical cross section view of the barrier showing line of sight could be shielded by the proposed barrier is included in Appendix 4.1.
Good Site Practices
4.7.12 In general, potential construction noise impact can be minimised or avoided by imposing a combination of the following good site practices as mitigation measures:
(a)
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction period.
(b) Construction plant should be sited away from NSRs.
(c) Machines and plant that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum.
(d) Equipment known to emit sound strongly in one direction should be orientated such that the noise is directed away from nearby NSRs.
(e) Material stockpiles and other structures (such as site offices) should be effectively utilised to shield on-site construction activities.
(f) Stationary equipment should be located within the channel when weather conditions permit (e.g. dry season).
(g) The Contractor shall devise, arrange methods of working and carrying out the works in such manner as to minimise noise impacts on the surrounding environment, and shall provide experienced personnel with suitable training to ensure that these measures are implemented properly.
(h) In the event that new schools are built near the works area, the Contractor should minimise construction noise exposure to the schools (especially during examination periods). The Contractor should liaise with the school and the Examination Authority to ascertain the exact dates and times of all examination periods during the course of the contract and to avoid noisy activities during these periods.
4.7.13 The implementation of the above good site practices could be readily applied to construction sites and can, in theory, provide additional reduction in construction noise levels. However, such noise reduction is difficult to quantify and is therefore not considered in the calculations.
Public
Relation Strategy
4.7.14 Having a good public relation with the local communities during the construction phase is indispensable for a smooth implementation of the Project. Prior to commencement of the construction, visits to the affected villages, local communities and property owners should be carried out. The purpose of the visits is to advise the public the following information in relation to the Project:
· the implementation programme of the works;
· the planned construction activities that will be involved;
· the possible impacts arising from the works;
· the measures to avoid or mitigate any adverse impacts;
· the monitoring programme to check the efficiency of the measures; and
· the communication channels between the local communities and the project office.
4.7.15 To maintain an effective communication channel with the public, a 24-hour hotline system should be established by the project office for the Contractor to receive any enquiry and complaint lodged by the public in respect of the Project. Upon receipt of enquiry / complaint, the Contractor (or its Environmental Team) should investigate the causes of the incident and take the appropriate action to rectify the situation. Periodic newsletters, information leaflets, notices or other means of communication should be provided to the affected villages, communities, and residents advising them the current progress, the schedule of works in future, the potential environmental impacts arising from the works and the corresponding mitigation measures. It is considered that such a close relation between the local communities and the project site office could ensure speedy resolution of any environmental non-compliance and maintain an environmental standard acceptable to the local communities during construction.
4.7.16 Table 4.12 shows the predicted noise levels with the implementation of the proposed Level 1 mitigation measure (use of quiet plant).
Predicted
Noise Level during Construction of Hang Hau Tsuen
Channel - Mitigated
(Level 1 mitigation : use of quiet plant)
NSR |
Mitigated Construction Noise Level, dB(A) |
|||||
Site Clearance |
Excavation to Formation
Level |
Construction of Channel
Lining, Crossings and other Works |
Concreting Works |
Road Surfacing Works |
Landscaping and
Finishing Works |
|
NSR 1* |
66 |
66 |
68 |
65 |
64 |
66 |
NSR 2 |
77 |
78 |
80 |
77 |
76 |
77 |
NSR 3 |
79 |
79 |
81 |
78 |
77 |
79 |
NSR 4 |
79 |
79 |
81 |
78 |
77 |
79 |
NSR 5 |
78 |
78 |
80 |
77 |
77 |
78 |
NSR 6 |
79 |
80 |
81 |
79 |
78 |
79 |
NSR 7 |
58 |
58 |
60 |
57 |
56 |
58 |
NSR 8 |
54 |
54 |
56 |
53 |
52 |
54 |
NSR 9 |
67 |
68 |
69 |
67 |
66 |
67 |
NSR 10 |
80 |
81 |
83 |
80 |
79 |
80 |
Notes:
Numbers in BOLD denote exceedance of daytime noise
standard: 75 dB(A) for residential premises, 70 dB(A)
for educational institution.
*
Wing Jan Kindergarten (noise standard during examination not applicable)
4.7.17 Table 4.13 shows the predicted noise levels with the implementation of the proposed Level 2 mitigation measures (use of quiet plant + temporary noise barrier) for the affected Representative NSRs (NSRs 2, 3, 4, 5, 6 & 10).
Predicted Noise Level during Construction of Hang Hau
Tsuen Channel - Mitigated
(Level 2
mitigation : use of quiet plant + use of noise barriers)
NSR |
Mitigated Construction Noise Level, dB(A) |
|||||
Site Clearance |
Excavation to Formation
Level |
Construction of Channel
Lining, Crossings and other Works |
Concreting Works |
Road Surfacing Works |
Landscaping and
Finishing Works |
|
NSR 2 |
72 |
73 |
74 |
72 |
71 |
72 |
NSR 3 |
74 |
74 |
76 |
73 |
72 |
74 |
NSR 4 |
74 |
74 |
76 |
73 |
72 |
74 |
NSR 5 |
73 |
73 |
75 |
72 |
72 |
73 |
NSR 6 |
74 |
74 |
76 |
73 |
73 |
74 |
NSR 10 |
75 |
76 |
77 |
75 |
74 |
75 |
Notes:
Numbers in BOLD denote exceedance of daytime noise
standard: 75 dB(A) for residential premises, 70 dB(A)
for educational institution.
4.7.18 Although the proposed temporary noise barrier and mobile barrier can shield the view of NSRs 3, 4, 6 & 10 to the construction site (see Figure 1 of Appendix 4.1), there would be slight marginal exceedance of about 1-2 dB(A) as shown in Table 4.13 due to the close proximity of these NSRs to the works. Further mitigation is recommended for NSRs 3, 4, 6 & 10 by restricting concurrent usage of several equipment at the same time during excavation and construction of the channel lining, crossings. As demonstrated in Appendix 4.1, with the restriction of current usage of equipment, noise level will be within the daytime construction noise standard. Such restriction is considered feasible and would not hinder the overall progress of the construction works. It should be noted that similar noise reduction can be expected with the implementation of good site practices. It is also recommended that at least one of these NSRs be included in the EM&A programme during construction period to monitor the noise level and effectiveness of the mitigation measures.
Summary of Construction Phase Mitigation
Measures
4.7.19 Table 4.14 summarises the mitigation measures proposed for the construction works. All these construction noise mitigation measures should be implemented by the Contractor during the construction phase of the works. The location of the temporary noise barriers and mobile noise barriers should be further reviewed by the Contractor during the construction stage based on the latest construction programme and contemporary conditions, including any changes with respect to NSRs. The Contractor should design, construct, operate and maintain the mitigation measures throughout the construction phase and as required by the Engineer. Before commencement of the works, the Contractor should submit to the Engineer for approval (as part of their method statement) details of the mitigation measures to be employed under the works. The Contractor’s proposed mitigation measures should also be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC) to ensure the intended noise reduction effectiveness can be achieved.
Summary of Proposed Construction Noise Mitigation Measures
Proposed Mitigation Measures |
Location |
Timing / Duration |
Implementation Agent |
Specific Requirements |
Use of quiet
equipment including QPME |
All construction
works / sites |
During the
construction period |
Contractor |
Some examples of
quiet plant and QPME are shown in Table 4.11. Contractor can propose
other suitable alternative equipment with similar or lower sound power level. |
Use of temporary
noise barrier (purpose-built site hoarding) and/or movable (mobile) noise
barrier |
The temporary
noise barrier shall be located as per Figure 4.2 or wherever noisy
construction works are being carried out close (30m or less) to NSRs |
During the
construction period |
Contractor |
Barriers should be
of at least 3 m high or able to shield construction equipment from
NSR’s view. These barriers should be constructed of appropriate material with
a minimum superficial density of 7 kg/m2, with no gaps or openings. Also, regular inspection
and maintenance should be carried out. Where barriers
cannot block line of sight, mobile barrier of 2.5 m high with a
cantilevered upper portion
should be provided. |
Good site
practices |
All construction
works / sites |
During the
construction period |
Contractor |
----- |
Public relation
strategy |
All construction
works / sites |
During the
construction period |
Project office
(Engineer) / Contractor |
Maintain a 24-hour
hotline for enquiry and complaint, periodic communication with affected
parties. |
Restrict
concurrent usage of several construction equipment at the same time |
For construction
works in close proximity to NSRs 3, 4, 6 &10 |
During the
construction period |
Contractor |
Contractor to
propose details or other suitable alternatives to the Engineer and ET Leader
for approval. |
Operational Phase
4.7.20 As no adverse noise impact is identified during operational phase, no specific mitigation measure is necessary.
4.8.1 With the implementation of proposed mitigation measures, adverse residual noise impact would not be expected from the construction works.
4.9.1 As indicated in Section 2.9, there is a potential concurrent project within the Study Area. Based on the best available information, this project involves the construction of a sewage pumping station near NSR7. Since no information regarding the concurrent project construction activities or noise assessment is available at the time of the EIA study, reference has been made to construction noise assessment for other similar sewage pumping station project approved under the EIAO.
4.9.2 The cumulative construction noise impact as a result of the proposed Project and the concurrent project on some of the likely worst affected NSRs is shown in Appendix 4.1. Given the distance separation between the concurrent project and the NSRs, no adverse cumulative noise impact is expected during construction.
4.10
Monitoring
and Audit Requirements
4.10.1 Further information regarding construction noise monitoring and audit are broadly described in Chapter 10 of this Report. Key points are summarized in the following sections. Details of the monitoring and audit of construction noise will be presented in the separate EM&A Manual.
4.10.2 Noise monitoring should be carried out at selected representative NSRs during the construction period to check for compliance with permissible noise standards, and to verify the effectiveness of the recommended mitigation measures. Ad-hoc monitoring and audit should also be carried out at other NSRs if complaints are received. Measures should be taken by the Contractor to ensure compliance with the noise standards.
4.10.3
It is recommended that at least
the following representative NSRs (Table 4.15) should be monitored
during the construction phase. The representative sensitive receivers have been
selected for monitoring to represent a particular area likely to be most
affected by the construction works of this Project.
4.10.4 As the predicted road traffic noise is within the EIAO-TM noise standard, no monitoring is required during operational phase.
Representative NSRs chosen for Noise Monitoring during Construction Phase
Noise Monitoring Station |
NSR ID |
General Description |
N1 |
NSR 1 |
Wing Jan Kindergarten |
N2 |
NSR 3 |
Village house at No. 84 Hang Hau Tsuen |
N3 |
NSR 6 |
Village house at No. 88 Hang Hau Tsuen |
Notes:
Subject to the location of the construction
works and to be proposed by the ET Leader.
4.11.1 The use of powered mechanical equipment during the construction phase of this drainage project is expected to create noise nuisance, due to the close proximity between the works areas and noise sensitive receivers. Assessment indicates that such noise impacts can be mitigated to acceptable levels by appropriate measures, such as the use of quiet plant, temporary noise barriers, restricting concurrent usage of equipment and the implementation of good site practices. The Contractor will be required to implement these measures when powered mechanical equipment is used during the construction phase. With these measures in place, residual noise impact would not be expected from the construction works and will comply with the EIAO-TM daytime construction noise standard.
4.11.2
Noise monitoring is recommended
at selected noise sensitive receivers during the construction period to check
for compliance with permissible noise levels and effectiveness of the proposed
mitigation measures.
4.11.3
The operation phase of the
Project, in terms of road traffic noise and during maintenance of the channel, is
not expected to pose any noise impact to the surrounding noise sensitive
receivers.
[1] QPME
are construction plant and equipment that are notably quieter, more
environmentally friendly and efficient. EPD has developed a system for the
registration of QPME that are used in