5.
WATER
QUALITY IMPACT ASSESSMENT
5.1.1
This Chapter details the current condition of the water
bodies within the Study Area, and describes the potential impacts
on water quality during the construction and operation phases of the Project. Mitigation
measures are proposed and the residual impacts after implementation of these
measures are evaluated.
5.2
Environmental Legislation, Policies, Standards and
Criteria
5.2.1
The Water Pollution Control
Ordinance (WPCO) (Cap.358) enacted in 1980 is the principal legislation controlling water
quality in Hong Kong along with Annexes 6 and 14 of the Technical Memorandum on
EIA Process (EIAO-TM). Under the WPCO,
5.2.2 The other relevant guideline is the Practice Note for Professional Persons (ProPECC Note) PN 1/94 – “Construction Site Drainage” which provide guidelines for the handling and disposal of construction discharges. This ProPECC Note is generally applicable for control of site runoff and wastewater generated during the construction phase of the Project.
5.2.3
The Technical Memorandum on Standards for Effluents Discharged into Drainage
and Sewerage Systems, Inland and Coastal Waters under the WPCO defines
acceptable discharge limits to different types of receiving water in
5.3.1
According to the EIA Study Brief, the Study Area for the
water quality impact assessment should include all areas within 300 m from the
Project site boundary, including but not limited to Hang Hau Tsuen stream
catchment area and
5.4
Baseline Water Quality Conditions of the Study Area
Desktop
Review and Field Observations
5.4.1
Site visits took place over a
number of days between December 2007, January, May and September 2008. General
descriptions and field observations of the water bodies in the Study Area (Figure
5.2) are provided below and in Table 5.1.
San Hing Tsuen Channel
5.4.2
San Hing Tsuen Channel is a
rectangular concrete channel originating from the under road box culvert at
Fung Kong Tsuen Channel
5.4.3
Fung Kong Tsuen Channel is a
rectangular channel originating near Fong Kong Tsuen which collects drainage flow
from Fong Kong Tsuen and nearby villages. This drainage channel traverses
across a number of open storage sites / container yards and collects effluents
from these industrial premises in additional to village runoff and domestic
wastewater from nearby unsewered villages. It drains into Hang Hau Tsuen stream
after joining with San Hing Tsuen Channel.
Hang Hau Tsuen Stream
5.4.4
Hang Hau Tsuen stream is a semi-natural
tidal stream of about 435 m in length. It collects drainage flow from the San
Hing Tsuen Channel and Fung Kong Tsuen Channel and discharges into
5.4.5
Prior to 1997, a large number of
squatter houses were built on the stream which affected water flow. The
squatter houses were subsequently demolished in 1997.
5.4.6
The stream is covered with grasses
along the section above tidal influence and partly lined with mangroves below
the high tide level.
Fishponds
5.4.7
A total of four fishponds can be
found within the Study Area. All appeared to be abandoned. Grassy and weedy
vegetation were recorded in the pond bunds. The conditions of the water inside
the ponds are fairly turbid. Rubbish and construction waste can be found at the
edge of the ponds.
5.4.8
Hang Hau Tsuen stream directly
discharges into
5.4.9
Field Observations of the Inland
Water Bodies in the Study Area
Stream / Channel |
Description |
Water Quality Observations |
San Hing Tsuen Channel |
Concrete rectangular
drainage channel flowing across open storage sites and container yards. Water
is almost stagnant during dry season. |
Water is grossly
polluted with visible floating scum, oil stains and rubbish. Water is black
in colour and very turbid. The lower reaches of the channel bed along |
Fung Kong Tsuen Channel |
Concrete rectangular
drainage channel flowing across open storage sites and container yards. Low
water flow during dry season. |
Water is grossly
polluted with visible oil stains and floating rubbish. Water is black in
colour and very turbid. |
Hang Hau Tsuen Stream (upstream section) |
The upstream portion is
a natural stream with rocky bottom and is overgrown with grasses. It receives
flows from San Hing Tsuen Channel and Fung Kong Tsuen Channel via a box
culvert underneath |
Blackish turbid water,
with rubbish trapped within the grasses along the stream bed. |
Hang Hau Tsuen Stream (mid-stream section) |
Natural stream with dark
colour muddy bottom and is partly overgrown with grasses and mangroves. The
stream is narrower in the upstream portion with faster water flow. Extensive
grasses occupy the stream bank. The stream widens in the middle portion where
mangroves and shrubs can be found. Stream bank is partly occupied by
footpaths and village houses. A sub-standard wooden bridge provides access
across the stream. |
Blackish turbid water,
presence of rubbish along the stream bed. Water quality appears to
slightly improve during the start of the wet season of 2008, probably due to
the continuous heavy rain during the period. |
Hang Hau Tsuen Stream (downstream section) |
Natural stream section
affected by tidal action with a slightly lighter colour muddy bottom. Smaller
patches of mangroves. Stream bank is occupied by footpaths and village
houses. Presence of broken stilt structures. A sub-standard wooden bridge
provides access across the stream. |
Blackish turbid water. Water quality appears to
slightly improve due to the continuous heavy rain during the start of 2008
wet season, but still turbid probably due to the tidal action of Deep Bay. |
Hang Hau Tsuen Stream (outfall section & towards |
Natural stream section
affected by tidal action with extensive intertidal mudflats along the coast.
Stream is slightly narrower at the outfall due to presence of large concrete
platform. Oyster shell hash can be found at various locations. A small
concrete / metal footbridge with landing step cases provide access across the
stream. No mangroves exist to the east of the footbridge due to the platform.
To the west of the footbridge, there is a large patch of mangroves at one
side and mooring areas with concrete landing places for small boats on the
other side. |
Blackish turbid water.
Presence of mudskipper, intertidal crabs and other invertebrates on the
mudflats. Water quality appears to
slightly improve due to the continuous heavy rain during the start of 2008
wet season, but still turbid probably due to the tidal action of Deep Bay. |
Baseline
Conditions
Stream Water Quality
5.4.10 There
is no EPD river water quality monitoring station near the Study Area. Water
quality sampling was conducted in January 2008 to characterise the water
quality of Hang Hau Tsuen stream.
5.4.11 The
sampling locations are shown in Figure 5.1. The results are
summarized in Table 5.2 and presented in Appendix 5. The results verified the
poor water quality observed from field survey. The major pollution sources are
mainly attributed to wastewater discharges from unsewered villages (Hang Hau
Tsuen and other villages upstream) and industrial effluent from upstream
sources.
5.4.12 Levels
of E. coli were relatively high
compared to levels found in
Results of Water Quality Sampling
at Hang Hau Tsuen Stream
Parameters |
Unit |
Sample Location |
|
W1 (upstream) |
W2 (downstream) |
||
Temperature |
oC |
15.1 |
15.7 |
pH |
- |
7.32 |
7.02 |
Salinity |
ppt |
0.2 |
2.2 |
Turbidity |
NTU |
134 |
56.2 |
Dissolved Oxygen |
mg/L |
5.48 |
3.52 |
Dissolved Oxygen (DO) |
% |
54.7 |
36 |
Suspended
Solids (SS) |
mg/L |
70 |
34 |
Ammonia Nitrogen
(NH3-N) |
mg/L |
2.97 |
1.38 |
Reactive
Phosphorus (PO4) |
mg/L |
0.34 |
0.03 |
Total Kjeldahl
Nitrogen (TKN) |
mg/L |
5.1 |
3.6 |
Total Phosphorus
(P) |
mg/L |
0.8 |
0.4 |
Nitrate
Nitrogen (NO3-N) |
mg/L |
1.46 |
0.97 |
Nitrite
Nitrogen (NO2-N) |
mg/L |
0.2 |
0.16 |
Arsenic (As) |
µg/L |
<10 |
<10 |
Cadmium (Cd) |
µg/L |
0.5 |
0.3 |
Chromium (Cr) |
µg/L |
5 |
3 |
Copper (Cu) |
µg/L |
96 |
47 |
Lead (Pb) |
µg/L |
235 |
115 |
Mercury (Hg) |
µg/L |
<0.5 |
<0.5 |
Nickel (Ni) |
µg/L |
7 |
8 |
Silver (Ag) |
µg/L |
<1 |
<1 |
Zinc (Zn) |
µg/L |
308 |
217 |
E. coli |
cfu/100mL |
66,000 |
26,000 |
Biochemical
Oxygen Demand (BOD) |
mg/L |
10 |
8 |
Chemical Oxygen
Demand (COD) |
mg/L |
122 |
122 |
Oil &
Grease |
mg/L |
8 |
<5 |
Total Organic
Carbon (TOC) |
mg/L |
20 |
16 |
Notes:
The sampling locations are shown in
Figure 5.1.
Marine Water Quality
5.4.13 Water
and sediment quality in
5.4.14 A
summary of EPD water quality data from 2005 to 2007 for the monitoring station closest
to the Project (DM3) is shown in Table 5.3.
5.4.15 The
water quality of
Summary of
Parameters |
Unit |
DM3 |
||
2005 |
2006 |
2007 |
||
DO |
mg/L |
5.3 |
5.8 |
6.4 |
DO |
% |
72 |
80 |
86 |
Turbidity |
NTU |
38.0 |
21.2 |
19.3 |
SS |
mg/L |
40.7 |
16.9 |
13.4 |
NH3-N |
mg/L |
0.75 |
0.69 |
0.84 |
NO2-N |
mg/L |
0.25 |
0.19 |
0.21 |
NO3-N |
mg/L |
0.73 |
0.63 |
0.54 |
TKN |
mg/L |
1.19 |
0.95 |
1.28 |
PO4 |
mg/L |
0.13 |
0.11 |
0.14 |
TP |
mg/L |
0.21 |
0.16 |
0.20 |
E. coli |
cfu/100mL |
150 |
120 |
38 |
BOD |
mg/L |
1.7 |
1.6 |
2.3 |
Sources:
EPD (2006) Marine Water Quality Monitoring in
EPD (2007) Marine Water Quality Monitoring in
5.4.16 An
updated baseline water quality should
be established before the commencement of the construction phase of the Project
to allow appropriate action and limit levels to be determined for impact
monitoring and audit.
Sediment Quality
5.4.17 A
Sediment Quality Report (SQR) has been undertaken to ascertain the volume and
degree of contamination of the stream sediment that needs to be excavated such
that appropriate marine disposal sites can be allocated by the relevant
authorities. Details are presented in Chapter 6 – Waste Management.
5.5.1
The Water Sensitive Receivers (WSRs) likely to be impacted by the Project include
the Hang Hau Tsuen stream itself, the nearby abandoned fishponds, the mudflats along
the Deep Bay coast, the mangroves near the mid and downstream section of the stream,
the oyster bed and the waters of Deep Bay into which the proposed channel discharges.
Inner Deep Bay SSSI is located over 3 km to the north of the channel discharge
point. Adverse impact from the Project on
5.6
Potential
Impacts During Construction Phase
Site Preparation
/ Clearance
5.6.1
Preparation of the land for
construction of the drainage channel will involve removal of surface vegetation
and excavations, removal and import of construction materials. Construction of
some temporary infrastructure may also be necessary such as drainage, bunds and
access roads.
5.6.2
The permeability characteristics of
the site may change, reducing infiltration into surface layer. This may lead to
increased site surface runoff with high suspended solids loadings during the
wet season. Erosion of soil enriched in organic matter may also release
nutrients into the nearby water bodies.
De-Watering
/ Excavation of Streams / Pond and Removal of Sediment
5.6.3
During
excavation, the water in the stream will be temporarily diverted
to provide a dry working stream
bed prior to the channel works. This may lead to disturbance of organic rich
bottom sediments which will release nutrients and suspended solids into the
water.
5.6.4
Sediment
characterisation surveys were conducted in January 2008 and November 2008 to
determine whether there are any contaminants in the sediments. The results
indicated that some of the sediments are “uncontaminated” (Category L) and some
are “contaminated” (Category M and H). Details of the sediment testing and its
recommended disposal route can be found in Chapter 6 – Waste Management.
5.6.5
Excavation of the stream sediments
will be required for channel formation at the upstream portion of the stream.
The stream sediment at the downstream section will largely be left in-situ. Excavated
sediments, whether clean or contaminated, may have to be stored on-site before
being sorted, reused or transported to disposal sites. If stored as open air
stockpiles and left uncovered during rainfall, there is a potential risk of the
excavated sediments being washed away, back into the stream water or the nearby
waterbodies including the abandoned fishponds, thereby causing sudden increase
of oxygen demand, turbidity and heavy metals (from contaminated sediments) during
rainy condition.
Concreting Work
5.6.6
Concreting work will be required
for part of the channel formation and other ancillary infrastructure. If
concrete spillage, washdown or concrete curing water is inadvertently
introduced into the water course, the pH level will be raised and may result in
contamination of the water or creation of toxic conditions for the aquatic
life. Turbidity and suspended solids levels will also increase if contaminated by
runoff containing waste concrete. Other possible sources of concrete enriched
waste water include water from wheel wash facilities, and washout from concrete
lorries / pumps.
5.6.7
With the
use of natural substrates such as mud and rip-rap as well as retention of the
existing natural stream bed in parts of the proposed channel, the use of
concrete will be substantially reduced.
Site
Workshop or Depot
5.6.8
Works areas and site offices will
be provided for site staff and contractors, which may include workshop or depot
to provide maintenance and repair services for the equipment on site. The
workshop may store engine oil, lubricants, chemicals and waste oil/materials which may create impacts if accidental spillage
occurs. Waste oil may infiltrate the surface topsoil and contaminate the
ground. Stormwater runoff from the site may wash the oil spillage into adjacent
water bodies.
General
Construction Works
5.6.9
The channel construction works are
scheduled to start in end 2009 for completion in end 2012. General construction
works will be continuous throughout both wet and dry seasons. During the wet season, silty runoff from the
sites will be generated from areas cleared of vegetation. Spillage, hydraulic
leakage and runoff from the surface of standby construction equipment during
rainy conditions may release oil and lubricants to the surrounding environment.
If the site runoff is not adequately managed, it may enter the water bodies and
increase the suspended solids, turbidity and oil & grease levels of these
water bodies.
Presence
of Additional Population (Workers)
5.6.10 The presence of site staff and
construction workers will generate sewage and domestic refuse. Impacts include
waste and wastewater generated from eating areas, toilets and waste disposal
areas. Sewage arising from on-site construction workforce would have the
potential to cause water pollution if it is discharged directly into adjacent
water bodies without any appropriate treatment.
5.7
Mitigation
Measures for Construction Phase
5.7.1
The main potential impacts from the
construction phase of the Project include an increase in suspended solids, pH
value, oil & grease and general site effluent entering adjacent water
bodies. The following sections discuss the proposed mitigation measures for the
potential water quality impacts identified above.
General
5.7.2
The Contractor shall observe and
comply with the Water Pollution Control Ordinance (WPCO) and its subsidiary
regulations. The Contractor shall carry out the works in such a manner as to
minimise adverse impacts on the water quality during execution of the works. In
particular the Contractor shall arrange his method of working to minimise the
effects on the water quality within and outside the site and on the transport
routes.
5.7.3
The Contractor shall follow the practices, and be
responsible for the design, construction, operation and maintenance of all the
mitigation measures below and as specified in ProPECC PN 1/94 – “Construction
Site Drainage”. The design of the mitigation measures shall be submitted by the
Contractor to the Engineer for approval.
Site
Preparation / Clearance
5.7.4
Proper construction site drainage
management measures should be implemented to control site
runoff and drainage, and thereby prevent high sediment loadings from reaching
5.7.5
Turbid water from construction
sites must be treated to minimise the solids content before being discharged. Advice
on the handling and disposal of site discharge is given in the ProPECC Note PN
1/94 – “Construction Site Drainage”.
5.7.6
In general, surface run-off from
construction sites should be discharged into water bodies via adequately designed
silt removal facilities such as sand traps, silt traps and sediment basins.
Channels or earth bunds or sand bag barriers should be provided on site to
properly direct stormwater to such silt removal facilities. Perimeter channels
at site boundaries should be provided to intercept storm run-off from outside
the site so that it will not wash across the site (or into the proposed channel
works area). Catchpits and perimeter channels should be constructed in advance
of earthworks.
5.7.7
Silt removal facilities and
diversion channels should be maintained and the deposited silt and grit should
be removed regularly, especially at the onset of and after each rainstorm to
ensure proper functioning of these facilities at all times.
5.7.8
Measures should be taken to prevent
the washing away of construction materials, soil, silt or debris into the
nearby water bodies. Open stockpiles susceptible to erosion should be covered with
tarpaulin or similar fabric and provided with containment such as bunds, sand
bag barriers or equivalent measures,
especially during the wet season (April
– September) or when heavy rainstorm is predicted. Runoff to
watercourses should be reduced by minimising flat exposed areas of permeable
soil, and by forming pits or diversion channels into which runoff can flow to
suitable treatment facilities before discharge.
De-watering
/ Excavation of Stream / Pond and Removal of Sediment
5.7.9
Excavation works within the
existing stream section and pond should
be programmed to be carried
out during dry season from 1st October to 31st March as
far as practicable to minimise impacts on downstream water quality and nearby sensitive
receivers.
5.7.10 The
use of containment structure such as sheet
pile barriers, earth bunds, sand bag barriers wrapped with geotextile fabric or
similar material, diversion channels or other similar techniques should
be installed surrounding the excavation area to facilitate a dry or at least
confined excavation within the stream. Schematic
diagram of typical drainage measures during excavation of the stream is shown
in Figure
5.3. The Contractor should submit details of the temporary drainage
measures along with the proposed measures to ameliorate the potential water
quality impacts to the Environmental Team (ET) for verification and to the Engineer
for approval before commencement of the construction works.
5.7.11 The
excavation area should be limited to section of half width of the stream in
order to maintain continuous water flow within the stream during the
construction phase.
5.7.12 After
dewatering of the stream and pond, the sediments should be allowed to dry
before excavation (yet still maintain a moist state to avoid dust nuisance).
This will facilitate excavation of the sediments and also minimise the risk of drained water flowing
back into watercourses as the sediment
is handled. Where time or weather constraints require handling of wet sediment, care should be taken in
the removal of sediment
and the storage area should be bunded to prevent silty runoff entering water bodies.
5.7.13 Tightly
sealed closed grab excavators should be employed to minimize leakage and loss
of sediments during excavation works within the stream.
5.7.14 Excavated
sediment material from stream should be stored in covered impermeable skips and
disposed within 2 days, to avoid inadvertent release of silty runoff and contaminants
to nearby water bodies. If sediment material is identified to be suitable for
reuse as stream bed material, it should be properly stockpiled, adequately
covered and provided with containment to prevent runoff during wet season.
5.7.15 Regular
monitoring of suspended solids and turbidity
should be conducted during excavation works. Any exceedance of water quality in
the nearby water bodies caused by inadvertent release of site runoff should be
rectified in accordance with EM&A programme for this Project.
Concreting
Work
5.7.16 Runoff
should be carefully channelled to prevent concrete-contaminated water from
entering watercourses. Adjustment of pH can be achieved by adding a suitable
neutralising reagent to wastewater prior to discharge. Reuse of the supernatant
from the sediment pits for washing out of concrete lorries should be practised.
5.7.17 Any
exceedance of acceptable range of pH levels in the nearby water bodies caused
by inadvertent release of site runoff containing concrete should be monitored
and rectified under the EM&A programme for this Project.
Site
Workshop or Depot
General
Construction Works
5.7.18 Any
Contractor generating waste oil or other chemicals as a result of his
activities should register as a chemical waste producer and provide a safe designated storage
area for chemicals on site. The storage site should be located away from existing water courses.
5.7.19 All compounds in works areas should be located on
areas of hard standing surface with provision of diversion channels and
settlement ponds where necessary to allow interception and controlled release
of settled / treated water. Hard standing compounds should
drain via an oil interceptor. The oil
interceptor should
be regularly inspected and cleaned to avoid wash-out of oil during storm
conditions. A bypass should be provided to avoid overload of the interceptor's
capacity. To prevent spillage of fuels or other chemicals to water courses, all
fuel tanks and storage areas should be sited on sealed areas within a bund of a
capacity equal to 110% of the storage capacity of the largest tank. Where temporary storage of chemicals or fuel drums
outside the storage area is necessary, drip tray should be provided. Disposal
of the waste oil should be carried out by a licensed collector. Good
housekeeping practices should
be implemented to minimise careless spillage and to keep the storage and the work space
in a tidy and clean condition. Appropriate training including safety codes and
relevant manuals should be given to the personnel who regularly handle the
chemicals on site.
Emergency Contingency Plan
5.7.20 The Contractor should prepare an emergency
contingency plan (spill response plan) for the Project to contain and remove
accidental spillage of chemicals and all hazardous materials on-site including
fuels at short notice and to prevent or to minimize the quantities of
contaminants from entering the stream water or nearby water bodies and
affecting the sensitive habitats. The Contractor should submit the emergency
contingency plan to the ET for review & comment and the Engineer for
approval. The Plan should include, but not limited to, the following:
(i)
potential
emergency situations
(ii)
chemicals
or hazardous materials used on-site (and their location)
(iii)
emergency
response team
(iv)
emergency
action plans and procedures
(v)
list of emergency
telephone hotlines
(vi)
locations
and types of emergency response equipment
(vii)
training
plan and emergency drill
(viii)
schedules
for review and audit.
General Guidance for Handling of Spillage / Leakage
5.7.21 In the event that accidental spillage or leakage of
hazardous substances / chemical wastes takes place, the response procedures as
listed below should be followed. It should be noted that the procedures below
are not exhaustive. The Contractor should propose other response procedures in
the emergency contingency plan based on actual site conditions as well as the
particular types and quantities of chemicals or hazardous substances used,
handled and stored on-site.
·
Contact person in charge or
nominated person immediately and initiate action plans based on the emergency
contingency plan.
·
Oil
leakage or spillage should be contained and cleaned up immediately. Waste oil
should be collected and stored for recycling or disposal in accordance with the
Waste Disposal Ordinance.
·
Instruct
untrained personnel to keep at a safe distance well away from the spillage
area.
·
If the
spillage / leakage involves high toxic, volatile or hazardous waste, initiate emergency
evacuation and call the emergency service.
·
Only
trained persons equipped with suitable protective clothing and equipment should
be allowed to enter and clean up the waste spillage / leakage area.
·
Where
the spillage / leakage is contained in the enclosed storage area, the waste can
be transferred back into suitable containers by suitable handheld equipment,
such as hand operated pumps, scoops or shovels. If the spillage / leakage
quantity is small, it can be covered and mixed with suitable absorbing
materials such as tissue paper, dry soft sand or vermiculite. The resultant
slurry should be treated as chemical waste and transferred to suitable
containers for disposal.
·
For
spillage / leakage in other areas, immediate action is required to contain the
spillage / leakage. Suitable liquid absorbing materials such as tissue paper,
dry soft sand or vermiculite should be used to cover the spill. The resultant
slurry should be treated as chemical waste and transferred to suitable
containers for disposal.
·
Areas
that have been contaminated by chemical waste spillage / leakage should be cleaned.
While water is a soluble solvent for aqueous chemical wastes and water soluble
organic waste, kerosene or turpentine should be used for organic chemical
wastes that are not soluble in water. The waste from the cleanup operation
should be treated and disposed of as chemical waste.
·
In
incidents where the spillage / leakage may result in significant contamination
of an area or risk of pollution, the Environmental Protection Department should
be informed immediately.
Presence
of Additional Population (Workers)
5.7.22 Sewage
arising from construction workers on site should be collected in a suitable
storage facility, such as portable
chemical toilets. An
adequate number of portable toilets should be provided for the construction
workforce. The portable toilets should be maintained in a state that will not
deter the workers from using them. Wastewater collected should be discharged
into foul sewers and collected by licensed collectors.
5.7.23 The
collected wastewater from sewage facilities and also from eating areas or
washing facilities of site offices should be disposed to foul sewer. If there
is no foul sewer in the vicinity, a septic tank and soakaway system or for
larger flow, a sewage treatment plant should be provided. All domestic sewage
discharges (except into foul sewer) are controlled under the WPCO. The
Contractor must apply for a discharge licence from EPD and must comply with the
terms and conditions of a valid WPCO licence.
5.8
Potential Impacts During Operational Phase
Introduction
5.8.1
Potential
water quality impacts during operational phase of the Project include:
•
pollution
loads entering the proposed channel (from polluted upstream water, runoff from
adjacent land / villages and flood waters);
•
pattern of
sediment deposition due to change in flow regime;
•
increase in
suspended solids during maintenance of the proposed channel; and
•
road surface
runoff from the proposed access road, viewing point and carpark.
5.8.2
It should be
noted that the operation of the proposed channel does not in itself generate
any new pollution loading to
Pollution Loads entering the Channel
5.8.3
Long term
reduction of pollution load into the channel is required to improve the water
quality in the channel and the receiving waters of
5.8.4
Vegetation
removes dissolved and particulate pollution through absorptive, filtration and
biological mechanisms. As concrete drainage environment will not provide such
functions, parts of the existing natural stream bed will be retained. In
addition, some sections of the channel will be lined with original stream bed
materials. Vegetations will be allowed to re-establish along the channel
naturally.
5.8.5
Standard drainage design of
catchpits with sand traps can effectively reduce the amount of sands, grits and
refuse contained in surface runoff of Hang Hau Tsuen from entering the proposed
channel.
Pattern of Sediment Deposition due to Change in Flow
Regime
5.8.6
The proposed channel will need to
effectively collect and convey storm water to alleviate the risk of flooding in
Hang Hau Tsuen. The increase in flowrate in the channel as a result of better
conveyance will likely increase the amount and rate of sediment discharge from
the channel which will affect the pattern of sediment deposition especially at
the outfall of the channel. This would be exacerbated by the use of concrete
lining in the channel. Such changes in sediment deposition would have an adverse
effect in particular to the established mangrove stands and intertidal fauna at
the mudflats located near the channel outfall.
5.8.7
With the proposed design of using rip-rap
and original stream bed materials lining which mimics the current stream condition,
sediment will be allowed to accumulate on the channel bed which will reduce
sudden discharge of sediment downstream during storm flow. By raising the bank
level and widening of the stream, water flowrate will not increase
significantly. Furthermore, the retained mangroves and stream bed at the
downstream section would have similar effect in retaining the sediment as in
the current condition. The proposed channel will therefore have negligible
effect on sediment deposition pattern. The sediment deposition pattern will remain
the same as in current situation which is predominantly controlled by the tidal
action of
Maintenance of the Channel
5.8.8
Maintenance would be necessary for the proposed channel to
remove excessive sediment, vegetation, rubbish, debris and obstructions in
order to maintain its hydraulic performance and structural integrity. Siltation
will generally be allowed to accumulate and removal of excess silt would be
carried out at locations where it would impede water flow. Little or no
maintenance will be necessary for the natural stream bed section of the channel.
A maintenance access will be provided along the southern downstream portion of
the channel to allow access by maintenance personnel to access and maintain the
channel bank and box culvert (footbridge). The alignment of the maintenance
access has been selected to minimize disturbance to the existing mangroves
lying along the north bank. The potential temporary impacts include an
increase of suspended solids during removal of the accumulated sediments and
disturbance to the aquatic communities from workers and equipment. The impacts
associated with the maintenance works are not expected to create adverse water
quality impacts.
5.8.9
There would be no chemicals or
hazardous materials stored / used on-site during operation, as such the
likelihood of accidental spillage is not expected. Emergency contingency plan
for operation phase is therefore considered not necessary.
Road Surface Runoff from the Proposed Access Road, Viewing Point and
Carpark
5.8.10 Contaminants
from exhaust emissions, tyre wear and leakage of oil & grease from vehicles
deposited on the road surface and carpark have the potential to cause water
quality impacts to the receiving waters of
5.8.11 Given
the low numbers of vehicles (and visitors) expected to use the access road and
carpark, the amount of pollutants is expected to be very minimal. Moreover, the
standard highway drainage design consisting of gullies and silt / grit traps
can effectively trap such pollutants. Provided that the road drainage systems are properly
maintained, the proposed access road and viewing point and carpark are not
expected to create adverse water quality impacts.
5.9
Mitigation Measures for Operational Phase
Measures
to Reduce Pollution Loadings entering the Channel
5.9.1
Appropriate location along the toe
zone of the channel will be filled with about 200 mm thick original stream bed
materials. The upstream dry weather flow channel will also be filled with a
layer of about 100 mm thick original stream bed materials on top of the rip-rap
lining. The most important feature of such measure is the prospect of natural
re-colonization of benthic communities and re-establishment of vegetation along
the toe zone of the channel replicating riparian vegetation. The vegetation is
not expected to be detrimental in any way to the channel structure or to the
conveyance of flood flow. Specific planting is considered not necessary as
vegetation will recolonized and established itself naturally similar to current
condition. Non-woody species (such as sedges) is preferred for ease of
maintenance and pruning as they are easier to be pruned and will impede the
flow of water to lesser extent during large flow as the vegetation will just
collapse and spring back. However, seasonal cutting and clearance of
vegetation, particularly in advance of the wet season may be required. This
mitigation measure has additional benefits of aesthetic and ecological value.
5.9.2
In addition, the use of rock fill
base or original stream bed materials for the channel bed has the benefit of
providing uneven surfaces and cavities for sediment to accumulate. Ultimately a
sediment layer will build up on the channel bed, forming a natural layer for
development of the benthic community. Removal of the upper layer of this
sediment will only be necessary once the layer thickness has built up to around
300 mm thick, and sediment is likely to be washed downstream in heavy storms. A
minimum of 100 mm thick sediment should be allowed to accumulate at the channel
bed to permit recolonizing of benthic communities. Growth of vegetation will
inhibit washout of sediment and sediment removal can be carried out at the same
time as vegetation harvesting during the dry season when flows are minimal.
5.9.3
Catchpits with sand traps will be
provided in the drainage system to trap sands, grits and rubbish in the Hang
Hau Tsuen surface runoff prior to discharge to
Environmental
Considerations for Maintenance of the Proposed Channel
5.9.4
Maintenance may be necessary for
the proposed channel at regular intervals to remove excessive silts,
vegetation, rubbish, debris and obstruction. Little or
no maintenance will be necessary for the natural stream bed section of the
channel. Likewise, the retained and compensated mangroves within the mangrove
zone (Figure 2.7) will not require any long term maintenance. Good practice guides for
the planning and execution of desilting and maintenance works are
recommended in
the following sections.
5.9.5
The following considerations should be included in planning
for the maintenance works of the proposed channel:
(a)
Maintenance of the channel should be restricted to silt
removal when the accumulated silt will adversely affect the hydraulic capacity
of the channel (except during emergency situations where flooding risk is
imminent). Desilting should be carried out by hand or light machinery during
the dry season (October to March) when water flow is low.
(b)
The management of woody / emergent vegetation should be limited
to manual cutting, to be carried out during dry season and only when unchecked
growth of such vegetation is very likely to impede channel flow.
(c)
Mangroves within the mangrove zone should be retained if the
hydraulic capacity of the channel is adequate. Mangroves found outside the
mangrove zone but within the proposed channel should be remove as they will
affect the hydraulic capacity of the channel. Rip-rap that are used to
delineate the mangrove zone should be replaced if found damaged.
(d)
A minimum of 100 mm thick sediment should be allowed to
accumulate on the channel bed to permit recolonization of benthic communities.
(e)
Phasing of the works should be considered to better control
and minimize any impacts caused, and to provide refuges for aquatic organisms.
Where possible, works should be carried out along half width of the channel in
short sections. A free passage along the channel is necessary to avoid forming
stagnant water in any phase of the works and to maintain the integrity of
aquatic communities.
(f)
Containment structures (such as sand bags barrier or similar
method) should be provided for the active desilting works area to facilitate a
dry or at least confined working area within the channel.
(g)
Where no maintenance access is available
for the channel, temporary access to the works site should be carefully planned and located
to minimize disturbance caused to the channel, adjacent vegetation (especially
mangroves) and nearby sensitive receivers by construction plants.
(h)
The use of lesser or smaller construction plants should be
considered to reduce disturbance to the channel bed. Quiet construction plants
should be used.
(i)
The locations for the disposal of the removed materials
should be identified and agreement sought with the relevant departments before
commencement of the maintenance works. Temporary stockpile of waste materials
should be located away from the channel and properly covered. These
waste materials should be disposed of in a timely and appropriate manner.
Mitigation
Measures for the Proposed Access Road, Viewing Point and Carpark
5.9.6
The following measures should be implemented to ensure no
adverse water quality impacts during the operation of the access road, viewing point
and carpark.
5.9.7
Highways Department (HyD) standard road drainage system
should be provided along the proposed access road and viewing point and carpark
to collect the road runoff. The road drainage design should incorporate gullies
and silt / grit traps to trap any pollutants in the road surface runoff prior
to discharge into
5.9.8
Regular cleansing of the access road and viewing point and
carpark following normal established practices should be carried out to remove
any accumulated silts, grits and litters. The gullies and silt / grit traps
should also be regularly cleaned and maintained in good working condition.
5.10
Residual
and Cumulative Impacts
5.10.1 With the effective implementation of mitigation measures
as described, residual impacts on water quality of the receiving water bodies
due to the implementation of this Project are expected to be negligible.
5.10.2 There
are no other concurrent projects in the vicinity of the Project that will give
rise to cumulative impacts.
5.11
Monitoring
and Audit Requirement
5.11.1 Potential water quality impacts during the construction of the
proposed channel can be mitigated by the implementation of the recommended site
practices and other measures to control runoff and to minimise water pollution.
5.11.2
A water quality monitoring and audit
programme is recommended to check for compliance with relevant water quality standards,
to ensure the proper implementation of the mitigation measures and to verify
the effectiveness of the recommended mitigation measures.
5.11.3
Monitoring of
pH value, dissolved oxygen, suspended solids and turbidity will need to be carried out
to ensure that any deteriorating water quality could be readily detected and timely
action taken to rectify the situation. Monitoring
should be provided at both downstream (as impact station) and upstream (as
control station) as shown in Table 5.4.
5.11.4
No monitoring is required during operational phase.
5.11.5
The monitoring requirement is broadly presented in Chapter
10 of this Report. Details of the monitoring and audit of water quality
will be presented in the separate EM&A Manual.
Water Quality Monitoring Stations during Construction Stage
Water Quality Monitoring Station |
Description |
Purpose
of Placing Sampling Station |
W1 |
Downstream of the works
immediately at the discharge point to |
Monitor and audit
potential impacts from the works, check water quality discharging to |
W2 |
Near the oyster bed in |
Monitor and audit
potential impacts from the works, check water quality discharging to |
W3 |
Near the oyster bed in |
Monitor and audit
potential impacts from the works, check water quality discharging to |
W4 |
Immediate downstream of any
specific works within Hang Hau Tsuen channel |
Temporary / mobile
station to monitor and audit potential impacts from any specific works, check
water quality discharging to Deep Bay, impact station |
W5 |
Upstream of the
works at the confluence of San Hing Tsuen Channel and Fung Kong Tsuen Channel |
Establish background water quality levels entering
Hang Hau Tsuen stream, control station |
W6 |
Waters of |
Establish background water quality levels in |
W7 |
Waters of |
Establish background water quality levels in |
Notes:
Subject to the location of the construction works and
to be proposed by the ET Leader.
5.12.1 The
current water quality of Hang Hau Tsuen stream and
5.12.2 The
construction of the channel could adversely impact the water bodies through
silt-laden site runoff, disturbance of stream sediment during excavation,
concreting works, runoff from workshops & depot and increased sewage and
wastewater resulting from the additional workforce on site. These impacts can
be readily mitigated through the construction of a suitable drainage system
with silt traps, good site management practices, careful working practices when
excavating sediments and proper sewage collection and disposal system.
5.12.3 The
Project will not generate any new pollution loading to
5.12.4
The provision of the access road and viewing point and
carpark would have minimal impact during operation with the incorporation of gullies
and silt / grit traps in the road drainage design.
5.12.5
With the implementation of the recommended mitigation
measures, no adverse residual water quality impact is expected during
construction and operation phases of the Project.
EPD (2006) Marine Water Quality Monitoring in
EPD (2007) Marine Water Quality Monitoring in
EPD (2008) Marine Water Quality Monitoring in