8.
FISHERIES IMPACT ASSESSMENT
8.1.1 The Fisheries Impact Assessment comprises three major parts: establishment of baseline conditions, evaluation and assessment of fisheries impact following the criteria and guidelines of Annexes 9 and 17 of the EIAO-TM, and recommendations of mitigation measures where necessary.
8.1.2
Key issues of the Fisheries
Impact Assessment, as stipulated in Section
·
Pond culture
·
Oyster farming
8.1.3 The assessment covers potential impacts on both capture and culture fisheries during the construction and operation of the Project.
8.1.4 The Fisheries Impact Assessment includes the following:
·
description of the physical environmental background;
·
description and quantification of existing fisheries activities (e.g.
pond culture and oyster farming);
·
description and quantification of the existing fisheries resources;
·
identification of parameters (e.g. water quality parameters) and areas
(e.g. breeding/spawning grounds and nursery grounds) that are important to
fisheries aspect;
·
identification and quantification of any direct, indirect, on-site and off-site
impacts to fisheries during the construction and operation phases (e.g. loss of
fish ponds/oyster beds and temporary occupied areas);
·
evaluation of impacts and proposals for any practical alternatives or
mitigation measures to prevent or minimize adverse impacts on fisheries; and
·
determination of any need for fisheries monitoring and, if necessary, recommendations
of a monitoring and audit programme.
8.2.1 HKSAR Ordinances and Regulations which are relevant to this study include the following:
· The Environmental Impact Assessment Ordinance (Cap. 499) and the associated TM;
· Fisheries Protection Ordinance (Cap. 171) and its subsidiary legislation, the Fisheries Protection Regulations;
· Marine Fish Culture Ordinance (Cap. 353) and associated subsidiary legislation; and
· Water Pollution Control Ordinance (Cap. 358) and its supporting regulations and statements.
8.3.1 In accordance with the EIA Study Brief, the assessment area includes 500 m from the limit of the Project site boundary and any areas likely to be impacted by the Project.
8.4
Methodology for Baseline Establishment and Assessment
8.4.1 Baseline information on the assessment area was reviewed. A review of Government and private sector reports, independent Government published literature and academic studies was undertaken to determine the existing conditions of fisheries in the assessment area, and to identify practices, areas and species of potential fisheries importance which may be affected by the Project. This review included but was not limited to the following:
· Port Survey 2006;
·
Agriculture, Fisheries and Conservation Department (AFCD) annual reports
and website; and
·
Other relevant reports from private sectors or Government.
8.4.2
Port Survey
is the most comprehensive fisheries study conduced by AFCD every few
years. Different from the approach
adopted in previous Port Surveys in which Hong Kong waters were divided into
“Fishing Areas” of various sizes, a uniform grid was overlaid on
8.4.3
AFCD’s
annual reports and website provide the most
updated information on the development and trend in
8.4.4 The validity of the information compiled during the literature review has been assessed before it is adopted into the present EIA study.
8.4.5
Impacts are
assessed in the absence of mitigation.
The construction and operational phase impacts on capture fisheries and
mariculture have been assessed individually, then cumulatively, in combination
with other existing, committed and proposed developments.
Sites of Fisheries Importance
8.5.1
Besides the fishing grounds in
Capture Fisheries
8.5.2
The Port Survey consisted of an
interview programme. About 36% of
the local fishing fleet which accounted for all homeports (i.e. places at which
local fishing vessels are based) and vessel types was interviewed. During the interviews, particulars (e.g.
vessel length, type and its homeport) of the fishing vessels were recorded and
information about their fishing operations and fisheries production in
8.5.3
Recent detailed data on HKSAR
capture fisheries in the fisheries assessment area were taken from the latest
Port Survey 2006. In this report a uniform grid of
8.5.4
As reported
in the Port Survey 2006 (see AFCD website), the catches from Grid Cells inside Deep Bay were all ranked
very low in Hong Kong (<
Mariculture
8.5.5
The
predominant type of mariculture in
8.5.6
Oyster
farming is another type of mariculture in
8.5.7 Though they have no direct relation with the settlement and growth of oysters, the mudflats provide a substrate for the deployment of oyster cultches. Cultches on mudflats are rearranged 2 to 3 times a year to maintain the angle favouring oyster growth. The average diameter of each oyster cultch with oysters is about 0.2 m. The spacing between rows of cultch in oyster beds is about 1 m, and the spacing between two oyster cultches is about 0.3 m. Normally it takes about three years for the oysters to mature to a marketable size (ARUP 2002).
8.5.8
In the
subtidal zone, rafts are used for oyster cultivation. Most oyster rafts measure
about 80 -
8.5.9 As observed on site between November 2007 to May 2008 (a supplementary visit was conducted in July 2008 as well) and by reviewing government aerial photos between 2003 to 2007, there was no oyster rafts within 500 m distance from the project boundary, while some oyster beds (about 9.1 ha) were located on the mudflat, about 300 m from the project boundary for the nearest one.
Pond Fish Culture
8.5.10 The pond fish culture industry (either freshwater or brackish) is centred in the north-west
8.5.11 The Project site is
located near the coastal area of
8.6
Impact Identification and Evaluation
Construction Phase - Direct Impacts
8.6.1
The Project would not encroach any intertidal or subtidal areas and thus
would not directly impact capture fisheries and oyster farming. To facilitate the alignment of the new
channel, however, the construction of the Project would cause a permanent loss of
8.6.2
When compared with the
Construction Phase - Indirect Impacts
8.6.3 The construction of the Project might potentially pose indirect impacts on fisheries in several ways, with water quality impact being the commonest one. The major potential sources that could cause water quality impacts during the construction phase of the Project include:
·
Construction site runoff; and
·
Wastewater from construction activities.
8.6.4
Deterioration of marine water quality would potentially affect the fishing
ground and oyster farming in Lau Fau Shan and
8.6.5 Construction site runoff and wastewater might cause water quality impacts on the surrounding fishponds as well. Although the four fishponds are currently abandoned, the pond operators/owners may opt to redevelop the fishponds for aquaculture in the future. Site runoff and wastewater shall not be allowed to discharge into the fishponds irrespective of the status of the fishponds.
8.6.6
For some fishponds in
8.6.7 The access to the four fishponds (including the affected fishpond) would not be blocked or occupied during the construction phase. The Contractor would be required under the Contract to maintain or re-provide all existing roads/accesses throughout the construction period. The construction works would be limited within the Project boundary. The majority of the existing accesses or roads around the four fishponds would not be affected, with only a small foot path on the north side of the affected fishpond would fall within the Project boundary. Vehicle access to the affected fishpond (at its eastern side) would not be affected. Though the four fishponds were currently abandoned, access to these fishponds would not be blocked during the construction if fish farming operation is to be resumed.
8.6.8
The impacted fishpond will only suffer a partial
loss of 0.13 ha at
its northern boundary. Water tight
containment measures such as temporary sheet piling will be established along
the site boundary within the direct loss area before onset of the channel
construction works, so as to separate the remaining part of the fishpond from
the direct loss area. The sheetpile
will be sealed and water in the pond within the site boundary will be pumped
out to provide a relatively dry site condition for the construction of the
river channel bank. There should be no disturbance on the remaining part of the
fishpond from the construction works.
Though the remaining part of the fishpond would not be directly
disturbed and the water quality as well as the access would be protected, thus the
pond operators/owners might opt to redevelop aquaculture within the remaining
part during the construction phase, this part of fishpond is however subject to
a higher risk from environmental incidents (e.g. accidental leakage of silty
water) during the construction phase.
To take a more conservative approach, this remaining part of the
fishpond (0.21 ha in size) would be considered as a temporary fishpond loss
during the construction phase. Given the
fact that the affected fishpond is abandoned and small
in size, the potential impacts on pond fish production in
Operational Phase - Indirect Impacts
8.6.9
As the Project would not alter the catchment area of Hang Hau Tsuen
stream and the connecting drainage channel, the discharge volume from the
future modified channel should not be changed. Marine water quality parameters such as
salinity in the vicinity should not be changed, and therefore no impacts on capture
fisheries and oyster farming are anticipated.
8.6.10
Given the nature of the Project, no disturbance on the fishpond culture
operation or deterioration of the fishpond water quality during the operation
phase of the channel are anticipated. After the formation of the channel and
pond bund, the temporary sheetpile will be extracted by plant on the proposed
channel bank top. The pond operators/owners may opt to redevelop aquaculture in
the currently abandoned fishponds, including the remaining part of the
fishpond, during the operation phase.
8.7.1 As all the direct and indirect impacts in both construction and operation phases are insignificant, no specific fisheries mitigation measures are required.
8.7.2 Standard site practices detailed in Chapter 5 would be implemented to avoid or minimise the impacts on water quality on site. Site runoff and wastewater shall not be allowed to discharge into the fishponds irrespective of the status of the fishponds. Adequate site drainage will be provided to ensure that site runoff and wastewater will be properly contained and treated prior to discharge into the surrounding water courses including Hang Hau Tsuen Stream.
8.8.1
The residual impacts from the Project would be loss of
8.9
Environmental Monitoring and Audit
8.9.1 Other than the water quality monitoring programme, no specific fisheries EM&A programme would be required during the construction and operation phases of the Project. In addition to the upstream and downstream water quality monitoring stations, impact monitoring stations near the oyster beds are recommended for water quality monitoring.
8.10.1 Literature review and field
visits have been conducted to establish the fisheries baseline condition of the
assessment area and assessment of potential impacts conducted in accordance
with the EIAO-TM requirements. The Project
would cause a loss of
AFCD 2008. AFCD Website. Retrieved 24 December 2008
<http://www.afcd.gov.hk/eindex.html>
AFCD 2006. Port Surveys 2006. Retrieved 24 December
2008 <http://www.afcd.gov.hk/english/fisheries/fish_cap/fish_cap_latest/fish_cap_latest_homeport.html>
AFCD 2007. AFCD
Departmental Annual Report 2006-2007. Retrieved 24 December 2008 <http://www.afcd.gov.hk/misc/download/annualreport2007/eng/fisheries.html>
ARUP 2002. Agreement No. CE 39/2001Shenzhen Western
Corridor - Investigation and Planning - Environmental Impact Assessment Report. Submitted to Highways Department.
Table 8.1 Construction and Operation Stage Impacts
Impact |
Source |
Receiver |
Nature of Impacts |
Severity |
Mitigation Required |
|||||
|
|
|
Nature of impact |
Size of affected area |
Loss of fisheries resources/ production |
Destruction and disturbance of nursery and spawning grounds |
Impact on fishing activities |
Impact on aquaculture activity |
|
|
Construction phase |
||||||||||
Fishpond loss |
Channelisation |
Abandoned fishpond immediately
to the south of the stream |
Permanent |
|
Yes |
No |
No |
The fishpond area will be loss. |
Insignificant |
No |
Fishpond loss |
Channelisation |
Abandoned fishpond immediately
to the south of the stream |
Temporary |
0.21 ha |
Yes |
No |
No |
The fishpond area might potentially
temporarily not available for pond culture. |
Insignificant |
No |
Marine water quality deterioration |
Site runoff and wastewater |
Oyster farming area and fishing
ground in |
Temporary |
In the vicinity |
No |
No |
No |
No |
Insignificant |
No specific fisheries mitigation required. Only standard site
practices |
Fishpond water
quality deterioration |
Site runoff and wastewater |
Four abandoned fishponds in 500m distance |
Temporary |
Four abandoned fishponds |
No |
No |
No |
Potentially affect the pond culture if aquaculture in the abandoned
ponds is resumed |
Insignificant |
No specific fisheries
mitigation required. Only standard site practices |
Stream water quality deterioration |
Site runoff and wastewater |
Streams / water courses as potential
water sources for pond culture (including Hang Hau Tsuen Stream). |
Temporary |
In the vicinity |
No |
No |
No |
Potentially affect the pond culture if the flow from the stream is
used as water source when aquaculture in the abandoned ponds is resumed |
Insignificant |
No specific fisheries
mitigation required. Only standard site practices |
Disturbance to pond culture
operation |
Blockage of road access |
Four abandoned fishponds in
500m distance |
Temporary |
Four abandoned fishponds |
No |
No |
No |
Access to the four fishponds would not be blocked or occupied. |
Insignificant |
No specific fisheries
mitigation required. The Contractor would be required under the Contract to maintain
or re-provide all existing roads / accesses throughout the construction period |
Operation phase |
||||||||||
Marine water quality
deterioration |
Surface runoff |
Oyster farming area and fishing
ground in |
Permanent |
In the vicinity |
No |
No |
No |
No |
Insignificant |
No |