9.                            LANDSCAPE AND VISUAL IMPACT ASSESSMENT

 

9.1                        Introduction

 

9.1.1                 The objective of this Landscape and Visual Impact Assessment (LVIA) report is to identify the existing and proposed landscape elements and the visual quality within the limits of the primary visual envelope of the study area (Figure 9.1) and provide an evaluation of the impact on the landscape and visual aspects due to the proposed improvement works with engineered drainage channel and other associated works (the Project). Alternative alignment options of the Project are discussed in detail in Section 2.4.  The assessment will cover the landscape and visual impact on the surrounding with stage of the life cycle through out the Project.

 

9.1.2                 It will address the main concerns from the visual and landscape point of view to derive mitigation measure to minimize the landscape and visual impact due to the Project.

 

9.2                        Legislation

 

9.2.1                 The assessment of the landscape and visual impact due to the proposed Project has been carried out all in accordance with the criteria and methodology in Annexes 10 and 18 of the Technical Memorandum on EIA Process (EIAO-TM) issued under the EIAO (Cap.499).

 

9.2.2                 The HKPSG (Chapter 10 – Landscape and Conservation) outlines the criteria, which should be considered when planning in the rural environment; the Government Circular regarding tree preservation ETWB TC(W) No. 3/2006 – Tree Preservation is also applied to this assessment.

 

9.2.3                 In addition, the following guidelines and technical circulars have been considered in the landscape and visual assessment:

 

(i)                     EIAO Guidance Note No. 8/2002 – Preparation of Landscape and Visual Impact Assessment under the EIAO;

(ii)                   WBTC No. 17/2000 – Improvement to the Appearance of Slopes;

(iii)                  ETWB TC(W) No. 2/2004 – Maintenance of Vegetation and Hard Landscape Features;

(iv)                 ETWB TC(W) No. 29/2004 – Registration of Old and Valuable Trees, and Guidelines for their Preservation;

(v)                   Technical Guidelines on Landscape Treatment and Bio-Engineering of Man-made Slope and Retaining Walls (GEO Publication No. 1/2000); and

(vi)                 Use of Vegetation as Surface Protection on Slope (GEO 1999).

 

9.3                        Assessment Methodology

 

9.3.1                 The methodology adopted for the proposed Project conforms to the requirements of the EIAO. A robust methodology will be derived for the LVIA to meet the requirements of the EIA Study Brief and the EIAO-TM. It consists of:

 

·                  A definition of the scope and contents of the proposed works;

·                  Review of Planning Development Control Framework;

·                  A comprehensive description of the baseline landscape and visual character;

·                  Identification of the potential landscape and visual impacts and prediction of its magnitude and extent of impact;

·                  Recommendations on mitigation measures; and

·                  Assessment of residual impact and conclusion.

 

Scope and Contents

 

9.3.2                 In setting the scope of the landscape and visual impact assessment for proposed development, the following aspects will be considered:

 

·                  Site description;

·                  Proposed development;

·                  Level of details required for baseline studies;

·                  Key viewpoints to be covered;

·                  System to be used for judging significance of impact;

·                  Other development if cumulative impacts are to be assessed;

·                  Impact assessment; and

·                  Recommended mitigation measures.

 

Key Issues to be Addressed

 

9.3.3                  The assessment identifies the impacts of the proposed Project, upon the character of that landscape and upon the visual amenity of that area.  The surrounding area has its distinctive character and its own landscape value.  The alteration of the existing landscape elements, such as tree belt would be vulnerable to the existing landscape character. The study area is exposed to view thus lead to the loss of visual quality on the surrounding. Mitigation measure should be addressed to compensate on the loss of visual quality due to the proposed Project.

 

 

 

9.3.4                  Key issues relating to landscape impact of the Project will include:

 

·                  Impacts upon the landscape character within the study area; and

·                  Impacts upon the proposed landscaping in the study area from the surrounding area.

 

9.3.5                  Key issues relating to the visual impact of the Project will include:

 

·                  Impact upon sensitive receivers due to the proposed improvement works during the construction stage and operation stage; and

·                  Interference of views due to the proposed improvement works.

 

Baseline Study

 

9.3.6                  The baseline study will present an appraisal of the landscape and visual resources of the study area. It will focus on the sensitivity of the landscape and visual impact on the visual receiver and its ability to accommodate change.  Under the EIA Study Brief, the study area defines for the Landscape Impact Assessment is approximately 500 meters from the proposed works site boundary. A visual envelop defines the area for the Visual Impact Assessment.  This is generally the view shed formed by natural/manmade feature such as tree line and building block.

 

9.3.7                  Landscape resources considered include topography, woodland, and other vegetation, built form, settlement pattern, land use, scenic spots and details of local streetscapes.  The baseline study described the landscape resource by identifying broadly homogenous Landscape Character Units (LCUs) of a similar character, they are rated on the quality of element, their sensitivity to change and its importance at various geographical level.

 

9.3.8                  Visual resources considered are typical viewpoints located and direct towards the Project. A visual envelop will establish which define the extent of visual influence of the Project and the potential visual impacts.  Definition of the extent of the view shed formed by natural / man-made feature, such as ridgeline or building blocks, will be based on desktop study and site investigation. As the topography of the site area is situated within a lower ground level, the zone of visual influence is expected to be limited within the immediate surrounding area. Sensitive Visual Receivers (SVRs) identified in this assessment are representative in that individual or groups that have a similar sensitivity to changes in the visual and landscape environment.

 


Review of the Planning and Development Control Framework

 

9.3.9                  A review of the planning and development control framework has been undertaken to provide an insight to the future outlook of the area affected and the way the proposed development would fit into its wider context. This will also give further insight into possible future sensitive receiver that might be affected by the proposed improvement works.

 

Principle View Point

 

9.3.10              Viewpoint from area surrounding the study area will be established and examined. They are representation of the specific type of SVRs subject to the impact covered by proposed improvement works.

 

Methodology for Assessment of Landscape and Visual Impact

 

Landscape Impact

 

9.3.11              Landscape impacts can be positive or negative.  They are assessed at two levels:

 

·                  Impacts upon individual landscape features and resources; and

·                  Impacts upon landscape character.

 

9.3.12             Landscape impacts are assessed as a function of the magnitude of change and the sensitivity of the landscape resource or landscape character.  Landscape sensitivity is assessed as high, medium and low, and magnitude of change is assessed as large, intermediate, small and negligible.  Landscape impacts are assessed subsequent to the implementation of prescribed mitigation measures at both construction and operational stages.

 

·                  Landscape sensitivity is the ability of the landscape resource or character to accommodate change without prejudice to the quality of that resource.

·                  Magnitude of change is the degree of degradation or intrusion on the landscape element on which it may be possible to affect through landscape or environment enhancement.

 

9.3.13             Impacts are assessed as substantial, moderate and slight (positive or negative).  Insignificant impacts are termed negligible. A matrix is used to assess landscape impacts and is shown in the Table below:

 


Landscape Impact Characteristic (Positive or Negative)

 

Magnitude of Change

Sensitivity of Landscape Resource / Character

High

Medium

Low

Large

Substantial

Substantial / Moderate

Moderate

Intermediate

Substantial / Moderate

Moderate

Moderate / Slight

Small

Moderate

Moderate / Slight

Slight

Negligible

Negligible

Negligible

Negligible

 

Substantial  -       Adverse / Beneficial impact where the proposed project would cause significant degradation or improvement in existing landscape baseline conditions.

 

Moderate     -       Adverse / Beneficial impact where the proposed project would cause noticeable degradation or improvement in existing landscape baseline conditions.

 

Slight            -       Adverse / Beneficial impact where the proposed project would cause a barely noticeable degradation or improvement in existing landscape conditions or where the changes brought about by the project would not be apparent in visual terms.

 

Negligible    -       The proposed project does not perceptibly affect the existing landscape baseline conditions.

 

Visual Impact

 

9.3.14             Visual impacts can be positive or negative and are defined as a function of the sensitivity of a receiver and the magnitude of the change to that receiver’s existing view.

 

9.3.15              The assessment of visual impacts is structured by receiver sensitivity. Sensitive Visual Receivers (SVRs) are identified through the definition of the structure’s Zone of Visual Influence or ZVI  (i.e. the area within which views of the study area are possible).  For the purpose of this study, receivers have been grouped into the following categories:

 

Residential  -      Those people who would view the proposal from their home.

 

Occupational -   Those people who would view the proposal from their workplace.

 

Travelers -         Those people who would view the proposal from their vehicles or on foot.

 

Recreational -    Those people who would view the proposal whilst engaging in recreational activities.

 

 

9.3.16              The sensitivity of receivers to visual impacts is influenced by the immediate context of the viewer, the activity in which they are engaged and the value that they attach to this location in particular. Receivers are categorized as being of high, medium or low sensitivity to visual impacts.

 

9.3.17              Those who view the proposal from their homes are considered to be highly sensitive to any visual intrusion.  This is because the attractiveness, or otherwise, of the view would have a notable effect on a resident’s general quality of life and acceptability of their home environment.

 

9.3.18              Those people who view the scheme from their workplace are considered relatively less sensitive to visual intrusion.  This is because they are employed in activities where visual outlook plays a less important role in the perception of the quality of the working environment.  They are classified as a low sensitivity group.

 

9.3.19              For those who view the scheme whilst engaging in outdoor leisure pursuits, visual sensitivity varies depending on the type of recreational activity.  Those taking a stroll in a park, for example, would be classified as a high sensitivity group compared to football players who would have a low sensitivity rating.

 

9.3.20              For those people who view the scheme from public thoroughfares, the degree of visual intrusion experienced depends on the speed of travel and whether views are continuous or only occasional.  Generally, the slower the speed of travel and the more continuous the viewing experience, then the greater the degree of sensitivity.

 

9.3.21              The criteria used to determine the sensitivity of SVRs are given below:

 

·                  Value and quality of existing views;

·                  Type of view;

·                  Availability and amenity of alternative views;

·                  The number of visual receivers;

·                  The category or type of visual receivers as discussed above;

·                  The particular visual backdrop from specific viewpoints;

·                  The frequency (length and duration of time) the proposed development is in view; and

·                  Distance to the project.

 


9.3.22              The criteria used to determine the magnitude of change to a view are given below:

 

·                  Proximity of receivers;

·                  Degree of change of views;

·                  The particular visual backdrop to the development from specific important view points;

·                  The landscape context of the proposed development;

·                  The nature of the proposed development and its compatibility with the surrounding landscape;

·                  Scale of development;

·                  Reversibility of change;

·                  Potential blockage of view; and

·                  Duration of impacts under construction and operation phase.

 

9.3.23              Impacts are assessed as substantial, moderate and slight.  Insubstantial impacts are termed negligible.  A matrix is used to assess visual impacts and is shown in Table below:

 

Visual Impact Characteristic (Positive or Negative)

 

Magnitude of Change

Sensitivity of Receiver Group

High

Medium

Low

Large

Substantial

Substantial  / Moderate

Moderate

Intermediate

Substantial / Moderate

Moderate

Moderate / Slight

Small

Moderate

Moderate / Slight

Slight

Negligible

Negligible

Negligible

Negligible

 

Substantial  -       Adverse / Beneficial impact where the proposed project would cause significant degradation or improvement in existing visual baseline conditions.

 

Moderate     -       Adverse / Beneficial impact where the proposed project would cause noticeable degradation or improvement in existing visual baseline conditions.

 

Slight            -       Adverse / Beneficial impact where the proposed project would cause a barely noticeable degradation or improvement in existing visual conditions or where the changes brought about by the project would not be apparent in visual terms.

 

Negligible    -       The proposed project does not perceptibly affect the existing visual baseline conditions

 


Recommendation for Mitigation Measure

 

9.3.24              Alternative alignment, design and construction method that would avoid or reduce the identified impacts on landscape, or that would make the project visually more compatible with the surrounding setting will be examined. The identification of the landscape and visual impact will highlight those sources of conflict requiring design solutions or modification to reduce impacts and absorb the improvement and associated activities into the surrounding landscape. These mitigation efforts will consider factors as listed below and will derive landscape mitigation proposals to alleviate the identified landscape and visual impact.

 

·                  Woodland, tree and shrub planting to new or disturbed slopes, amenity strips, highway reservations and adjacent to any proposed structures;

·                  Contouring of new slopes to blend with existing topography in a natural manner;

·                  Earth mounding and screening;

·                  Highlighting unacceptable impacts and considering alternative proposals;

·                  Hard landscape elements including design and appearance of proposed facility; and

·                  Significant landscape elements.

 

Residual Landscape and Visual Impact

 

9.3.25              Residual impact is defined as the impact remaining after all practical methods of mitigation have been implemented. The final stage of the LVIA study is to assess the significance of the residual impacts. The impacts will be classified according to their level of significance as summarized below:

 

·                  Beneficial - the project will complement the landscape and visual character of its setting, will follow the relevant planning objectives and will improvement the landscape and visual quality of the study area.

·                  Acceptable - the assessment indicates that there will be no significant effects on the landscape, no significant visual effects caused by the appearance of the project, or no interference with key views.

·                  Acceptable with mitigation measure - there will be some adverse effects; these can be eliminated, reduced or offset to a large extent by specific measures.

·                  Unacceptable - the adverse effects are considered too excessive and are unable to mitigate practically.

·                  Undetermined - significant adverse effects are likely, but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question.

 

9.4                        Existing Site Condition

 

9.4.1                  The Project is located at the south of Lau Fau Shan, partially running within the heart of Hung Hau Tsuen between the shore of Deep Bay and Deep Bay Road. The aerial photograph of the subject site is shown in Figure 9.2. To the south is Yuen Tau Shan, Tin Shui Wai Town Centre is located to the east with Deep Bay to the northwest of site. The site for the proposed improvement works will sits on a natural muddy-bottomed stream course and portion of squatter huts constructed on stilts.

 

Landscape and Visual Context in the Study Area

 

9.4.2                  The landscape elements and visual context in the immediate vicinity has been characterized by a number of contrasting features as illustrated in Figure 9.3.

 

9.4.3                  The subject site is situated along the watercourse of Hang Hau Tsuen stream, bounded by the shore of Deep Bay to the west and Deep Bay Road to the east. Orientated in east to west direction, abandoned farmland, fishponds and scattered buildings occupy the area around the east portion of the site. Towards the west portion of the site, squatter huts largely occupy immediate areas along the banks of the stream. Further towards the mouth of the stream entering to Deep Bay, large mangrove cover is found along the mudflats of the stream. Apart from the extensive backdrop of large open storage of containers to the distance east of the site, the visual context is mainly man-made rural character in a natural setting, which consists of concrete channel stream among the building area to natural stream bed toward the Deep Bay area; and extensive container storage to the east to huts constructed on stilts along the banks.     

 

Woodland / Vegetated Area

 

9.4.4                  A wooded hill slope is located at the south of the site. It is mature woodland that forms a green pleasant backdrop on views to the south. Other vegetated area are found mainly along roadsides, in villages and in amenity area surrounding the study area with vegetated mangrove characterize the mouth of Hang Hau Tsuen stream entering Deep Bay.

 

Residential / Settlement Area

 

9.4.5                  Settlement area are located at the distance east, north and south of the study area in Hang Hau Tsuen, village houses of 1 to 3 stories high are located on both sides of the stream which stretch and collects to Lau Fau Shan, Deep Bay Grove and Sha Kong Tsuen located along the shore of Deep Bay. San Hing Tsuen is located of the distance east of site bounded by Lau Fau Shan Road. Due to the topography of the area is generally flat, with the site located at a lower ground level, distance open view to the site from the surrounding area is limited.

 

Open Container Storage Area

 

9.4.6                  The open container storage areas are located at the east to south of the study area. The landscape context of this area is in great contrast with the natural setting of the surrounding landscape. The extent and bulkiness of the containers have a substantial visual intrusion on the surrounding.

 

Fish Pond

    

9.4.7                  Fishponds are found at the immediate north and south of the site. The ponds vary in size and shape. All of the ponds have been abandoned and not maintained. Nevertheless, the overgrown vegetation on the bunds of the ponds forms a pleasant view to the receptors.  

 

Coastal Area

 

9.4.8                  Deep Bay is located to the west of the study area. The coastal land along this area is generally taken up by shellfish farming. The estuary along Deep Bay area is colonized by mangrove.   

 

Agricultural Land

 

9.4.9                  Agricultural land is mainly composed of croplands and orchards. Most of the croplands were abandoned and dominated by grasses and weeds, while a few pockets were actively farmed and mainly grown with vegetables.

 

9.5                        Description of the Proposed Development

 

9.5.1                  The Project is intended to alleviate the flooding problem in the area by converting the existing Hang Hau Tsuen stream between Deep Bay and Deep Bay Road into an engineered channel. The proposed project works comprise:

 

(i)               training of Hang Hau Tsuen stream including construction of a drainage channel of 370 m in length connecting the downstream ends of Fung Kong Tsuen Channel and San Hing Tsuen Channel to Deep Bay;

 

(ii)             construction of a 25 m long triple-cell box culvert of 5.5 m (W) x 3 m (H) beneath the Deep Bay Road and 4 nos. of footbridges across the channel;

 

(iii)            provision of an access road of 3.5 m in width with passing bays along the northern bank of the channel, a 3.5 m in width maintenance access along the southern bank of the channel and footpaths of 2 m in width on both sides of the channel and ancillary works such as retaining walls, drainage and water works as well as associated landscaping works; and

 

(iv)           a viewing point and car park at the downstream end of the channel.

 

Life Cycle of the Proposed Development

 

9.5.2                  The life cycle of this work can be divided into the construction stage and operational stage.

 

9.6                        Baseline Study

 

Background

 

9.6.1                  The baseline study will present an appraisal of the landscape and visual resources of the assessment area.  It will focus on the sensitivity of the landscape and visual impact on the visual receiver and its ability to accommodate change.

 

Baseline Landscape Resources

 

9.6.2                  In accordance with the EIA Study Brief, Landscape Character Units (LCUs) and Landscape Elements (LEs) have been identified within 500 m from the site boundary. Their results are described in Table 9.1 for Landscape Elements and Table 9.2 for Landscape Character Units. These to include the followings:

 

LEs

·      LE1 - Woodland (Approx. 12 ha)

-      Existing wooded area comprises the predominantly wooded hillsides around the site.

·      LE2 - Existing Vehicle Corridor (Approx. 1.25 ha)

-      Existing linear structure for vehicle of Deep Bay Road, Lau Fau Shan Road and other minor roads.

·      LE3 - Residential/Settlement area (Approx. 16 ha)

-      Existing residential areas and village settlement at Hang Hau Tsuen, Lau Fau Shan, Sha Kong Tsuen and Deep Bay Grove, as well as market stores, shops, small temple and school within Lau Fau Shan.

·      LE4 - Open Storage (Approx. 27.2 ha)

-      Existing large open storage area and workshop buildings within Lau Fau Shan.

·      LE5 - Stream course (Approx. 0.78 ha)

-      Man-made and natural stream course within the study area.

·      LE6 - Fish Pond (Approx. 1 ha)

-  Existing abandoned fishpond around the subject site.

·      LE7 - Open Water (Approx. 37 ha)

-  Deep Bay at the west of the subject site

·      LE8 - Agricultural Land (Approx. 7.6 ha)

-  Existing abandoned and a few active agricultural field and orchards within the study area.

·      LE9 - Scrubland/Grassland and Roadside Planting (Approx. 9 ha)

-  Existing green area comprises the predominantly roadside planting, scrubland and grassland within the study area.

 

LCUs

·         LCU1 - Upland and Hillside

-      Existing green area comprises the predominantly of hillside plantation area, woodland, roadside planting, scrubland and fresh water body.

·         LCU2 - Transport Corridor

-      Existing linear structure for vehicle of Deep Bay Road, Lau Fau Shan Road and other minor roads.

·         LCU3 - Village and Settlement

-      Existing residential and settlement area at Hang Hau Tsuen, Lau Fau Shan, San Hing Tsuen, Sha Kong Tsuen and residential development of Deep Bay Grove.

·         LCU4 - Industrial / Utility

-      Existing large open container storage area, warehouse and workshop building within Lau Fau Shan area.

·         LCU5 - Coastal Area

-   Mudflats of mangrove and shellfish farming along the shoreline of Deep Bay.

 


Table 9.1

Landscape Elements (LEs)

 

Landscape Elements

LE

Type

Description

Sensitivity to Change

LE1

Woodland

Quantity: Medium

Existing wooded area comprise the predominantly wooded hillsides around the site

Medium

LE2

Vehicle Corridor

Quantity: Low

Existing linear structure for vehicle of Deep Bay Road, Lau Fau Shan Road and other minor roads

Low

LE3

Residential/Settlement area

Quantity: Medium

Existing residential areas and villages settlement at Hang Hau Tsuen, Lau Fau Shan, Sha Kong Tsuen and Deep Bay Grove, as well as market stores, shops, small temple and school within Lau Fau Shan

Low

LE4

Open Storage

Quantity: Large

Existing large open storage area and workshop buildings within Lau Fau Shan.

Low

LE5

Stream Course

Quantity: Low

Man-made and natural stream course within the study area

Medium

LE6

Fish Pond

Quantity: Low

Existing abandon fish pond around the subject site

Medium

LE7

Open Water (Deep Bay)

Quantity: Large

Deep Bay at the west of the subject site

High

LE8

Agricultural Land

Quantity: Medium

Existing abandoned and a few active agricultural land within the study area

 

Low

LE9

Scrubland/Grassland and Roadside Planting

Quantity: Medium

Existing green area comprises the predominantly roadside planting, scrubland and grassland within the study area.

Medium

 

 


Table 9.2

Landscape Character Units (LCUs)

 

Landscape Character Units

LCU

Name

Description

Quality / Sensitivity to Change

LCU1

Upland and Hillside

Existing green area comprises the predominantly of hillside plantation area, woodland, roadside planting, scrubland and fresh water body

Medium/Medium

LCU2

Transport Corridor

Existing linear structure for vehicle of Deep Bay Road, Lau Fau Shan Road and other minor roads

Medium/Low

LCU3

Village and Settlement

Existing residential and settlement area houses at Hang Hau Tsuen, Lau Fau Shan, San Hing Tsuen, Sha Kong Tsuen and residential development of Deep Bay Grove

Medium/Low

LCU4

Industrial / Utility

Existing large open container storage area, warehouse and workshop building within Lau Fau Shan area

Low/Low

LCU5

Coastal Area

Mudflats of mangrove and shell fish farming along the shoreline of Deep Bay

High/High

 


9.6.3                  A tree survey has been carried out and the extent of existing trees in conflict with the improvement works was assessed in the Tree Survey Report. The location of trees surveyed is shown on Figure 9.16. Information from the Tree Survey Report is summarized below:

 

(i)               There are in total 14 tree species found at the location within the site boundary of the proposed improvement works. The most abundant tree species are Celtis sinensis (16 nos.) and Macaranga tanarius (16 nos.), they are common native woodland trees of height from 4 m to 12 m, trunk diameter from 0.12 m to 0.85 m and a spread from 4 m to 12 m.

 

(ii)             Bauhinia purpurea (5 nos.) usually planted for amenity purpose, another amenity trees Cassia surattensis (1 nos.) are exotic species of height from 5 m to 8 m, trunk diameter from 0.15 m to 0.3 m and spread from 5 m to 8 m.

 

(iii)            Delonix regia (2 nos.) and Albizia lebbek (1 no.) are exotic ornamental tree species of height from 6m to 10m, trunk diameter from 0.27 m to 1.0 m and spread from 6 m to 15 m.

 

(iv)           Many native woodland trees are found of height from 3 m to 10 m, trunk diameter from 0.12 m to 1.0 m and spread from 3 m to 7 m, they are Melia azedarach (3 nos.), Ficus microparpa (2 nos.), Morus alba (2 nos.), Bridelia tomentosa (1 no.) and Sapium sebiferum (1 no.).

 

(v)             Several common fruit tree species of height from 4 m to 6 m, trunk diameter from 0.1 m to 0.15 m and spread from 3 m to 4 m are found in residential area, Dimocarpus longan (1 no.), Mangifera indica (1 no.) and Clausena lansium (1 no.).

 

(vi)           Trees surveyed have good to poor tree form and health with medium to low amenity value and survival rate after transplanting.

 

(vii)          No trees in the Study Area are registered as Old and Valuable Trees (OVTs) under ETWB TC(W) No. 29/2004 or are considered potentially registrable as OVTs.

 

(viii)        Based on the layout of the development, the proposed treatment to the existing trees are as follows:

 

·                     Existing trees survey on site                53 nos.

·                     No. of trees proposed for retention               27 nos.

·                     No. of trees proposed for transplant               10 nos.

·                     No. of trees proposed for felling                     16 nos.

 

 

 

(ix)           26 existing trees within the works area will be affected by the proposed improvement works. Of which 10 nos. of trees will be transplanted as they have relatively higher survival rate after transplanting and better tree form and health. Transplant trees include Celtis sinensis (5 nos.), Bauhinia purpurea (3 nos.), Albizia lebbek (1 no.) and Ficus microparpa (1 no.).

 

(x)             The remaining trees, Macaranga tanarius (5 nos.), Celtis sinensis (2 nos.), Melia azedarach (3 nos.), Morus alba (1 no.), Sapium sebiferum (1 no.), Bauhinia purpurea (1 no.), Bridelia tomentosa (1 no.), Cassia surattensis (1 no.) and Delonix regia (1 no.), have low survival rate after transplanting, poor tree form and health and/or are in conflict with the proposed Project design, these trees are proposed to be felled with compensatory tree planting.

 

Baseline Visual Resources

 

9.6.4                  In accordance with the study methodology, Sensitive Visual Receivers (SVRs) within the visual envelope were identified and grouped into types as shown in Table 9.3. The visual resources closely relate to the landscape character units. These units vary from traffic corridor, residential development to woodland.

 

9.6.5                  A visual envelope has been mapped to determine SVRs. Key views from and towards the proposed Project are shown in Figure 9.5 and described as below.

 

Key Views toward the Proposed Development

 

- Figure 9.6

View South from Hang Hau Tsuen

- Figure 9.7

View South from Hang Hau Tsuen

- Figure 9.8

View Southeast from Hang Hau Tsuen

- Figure 9.9

View North from Hang Hau Tsuen

- Figure 9.10

View Southwest from Deep Bay Grove

- Figure 9.11

View North from Deep Bay Road

- Figure 9.12

View Northwest from Wing Jan Kindergarten

- Figure 9.13

View Northwest from Hang Hau Tsuen Sitting-Out Area

 

9.6.6                  Details of the SVRs are listed in Table 9.3.


Table 9.3

Sensitive Visual Receivers (SVRs)

 

SVR

Location and Quantity of Viewer Group

Viewer Group

Max. Staying Time

Distance to the Project

Frequency and Duration of View and Sources of Impact Type of View

Sensitivity to Change and Visual Intrusion

SVR 1

- VPT1.1  (Figures 9.6 9.9)

- Hang Hau Tsuen

Residents

24hr Depends on SVRs

Approx.  0 – 100m

-  Open to Obstructed View towards the site. Degree of View Varies depends on location of SVRs.

-  High frequency.

-  View during day and night. Duration of view is varies depends on the activity of SVRs.

Medium

- VPT1.2  (Figure 9.10)

- Deep Bay Grove

Residents

24hr Depends on SVRs

Approx. 150m

-  Obstructed view towards the site.

-  High frequency.

-  View during day and night. Duration of view is varies depends on the activity of SVRs.

Medium

SVR 2

-  VPT2.1  (Figure 9.11)

-  Deep Bay Road

Passengers & Pedestrian

Approx. 2min

Approx.  0 – 100m

-  Open view towards the site.

-  Low frequency.

Low

SVR 3

-  VPT3.1  (Figure 9.12)

-  Wing Jan Kindergarten

Teachers & Students

Approx. 8 hrs Depends on SVRs

0 – 80m

 

-  Open view towards the site.

-  Medium frequency.

Medium

SVR 4

-  VPT4.1  (Figure 9.13)

-  Hang Hau Tsuen Sitting-Out Area

Visitors

Approx. 2 – 30 mins Depends on SVRs

30m

-  Open view towards the site.

-  Low frequency.

Medium

 


9.7                        Review of Planning and Development Control Framework

 

9.7.1                  The broad statutory planning framework of the proposed site area is currently covered by the approved Lau Fau Shan & Tsim Bei Tsui Outline Zoning Plan (OZP) No. S/YL-LFS/7 and the approved Ha Tsuen OZP No. S/YL-HT/9. The proposed channel is partly zoned “Residential (Group D)” (R(D)) on OZP No. S/YL-LFS/7, and partly zoned “Coastal Protection Area” (CPA) and “Comprehensive Development Area” (CDA) on OZP No. S/YL-HT/9. As the proposed stream improvement works is a public works project implemented by the Government, it is always permitted under the covering Notes of the above OZPs. Planning permission from Town Planning Board is therefore not required.

 

9.8                        Landscape and Visual Impact Assessment

 

Landscape & Visual Impact Assessment during Construction Stage

 

Background

 

9.8.1                  The proposed improvement works is located on the streambed of Hang Hau Tsuen stream and the adjacent vegetated riverbanks. Potential construction impact will be the removal of existing vegetation, building material delivery, site formation, construction of the drainage channel and associated works. The area of potential landscape impact on the Landscape Character Units (Figure 9.4) and Landscape Elements (Figure 9.3) are shown in Table 9.4 and Table 9.5 respectively. The level of potential landscape impact is shown in Tables 9.6 - 9.7.

 

Table 9.4

Summary of Disturbance to Landscape Character Units

 

Landscape Character Units

Description

Disturbance

LCU 1

Upland and Hillside

1.58 ha

LCU 2

Transport Corridor

Nil

LCU 3

Village and Settlement

0.19 ha

LCU 4

Industrial / Utility

Nil

LCU 5

Coastal Area

Nil

 

 


Table 9.5

Summary of Disturbance to Landscape Elements

 

 

Landscape Elements

Type of Landscape Element

Total Area within the Study Area

Area in Interaction with the Development

LE 1

Woodland

Approx. 12 ha

Nil

LE 2

Existing Vehicle Corridor

Approx.1.25 ha

Nil

LE 3

Residential/Settlement area

Approx. 16 ha

Approx. 0.19 ha

LE 4

Open Storage

Approx. 27.2 ha

Nil

LE 5

Stream Course

Approx. 0.78 ha

Approx. 0.32 ha

LE 6

Fish Pond

Approx. 1 ha

Approx. 0.08 ha

LE 7

Open Water (Deep Bay)

Approx. 37 ha

Nil

LE 8

Agricultural Land

Approx. 7.6ha

Nil

LE 9

Scrubland/Grassland and Roadside Planting

Approx. 9 ha

Approx. 1.18ha


Table 9.6

Summary of Landscape Impact on Landscape Character Units (Without Mitigation Measures)

 

Landscape Impact (Without Mitigation Measures)

Landscape Character Units

Disturbed Area

Quality / Sensitivity of Change

Construction Stage

Operational Stage

Magnitude of Change and Source of Landscape Impact

Significance Threshold of Residual Landscape Impact

Magnitude of Change

Significance Threshold of Residual Landscape Impact

LCU 1

Upland and Hillside

1.58 ha

 

Medium/Medium

Intermediate (Site formation + Construction of Drainage Channel)

Moderate adverse

Small

 

Slight adverse

LCU 2

Transport Corridor

Nil

Medium/Low

Negligible

Negligible

Negligible

Negligible

LCU 3

Village and Settlement

0.19 ha

Medium/Low

Small (Site formation + Construction of Drainage Channel)

Slight adverse

Negligible

Negligible

LCU 4

Industrial / Utility

Nil

Low/ Low

Negligible

Negligible

Negligible

Negligible

LCU 5

Coastal Area

Nil

High/High

Negligible

Negligible

Negligible

Negligible

 

 

 


Table 9.7

Summary of Landscape Impact on Landscape Elements (Without Mitigation Measures)

 

Landscape Impact (Without Mitigation Measures)

Landscape Elements

Disturbed Area

Quantity / Sensitivity of Change

Construction Stage

Operational Stage

Magnitude of change and Source of Landscape Impact

Significance Threshold of Residual Landscape Impact

Magnitude of Change

Significance Threshold of Residual Landscape Impact

LE 1

Woodland

Nil

Medium/High

Negligible

Negligible

Negligible

Negligible

LE 2

Existing Vehicle Corridor

Nil

Low/Low

Negligible

Negligible

Negligible

Negligible

LE 3

 

Residential/Settlement Area

Approx. 0.19 ha

Medium/Low

Small (Demolition of existing residential settlement)

Slight adverse

Small

 

Slight adverse

LE 4

Open Storage

Nil

Large/Low

Negligible

Negligible

Negligible

Negligible

LE 5

Stream Course

Approx. 0.32 ha

Low/Medium

Intermediate (Site formation + Construction of Drainage Channel)

Moderate adverse

Small

Slight adverse

LE 6

Fish Pond

Approx. 0.08 ha

Low/Medium

Small (Filling of the existing fish pond)

Moderate adverse

Small

Moderate adverse

LE 7

Open Water (Deep Bay)

Nil

Large/High

Negligible

Negligible

Negligible

Negligible

LE 8

Agricultural Land

Nil

Medium/Low

Negligible

Negligible

Negligible

Negligible

LE 9

Scrubland/Grassland and Roadside Planting

Approx.
1.18 ha

Medium/Medium

Intermediate (Removal of the existing vegetation and tree)

Moderate adverse

Small

Slight adverse

 

 

 


Source of Landscape Impact

 

9.8.2                  The source of construction landscape impact will include:

 

·                  The removal of existing vegetation;

·                  The construction works of principle site formation works for the drainage channel and associated works;

·                  Designation of temporary site area for storage, plant cabins and associated site equipment; and

·                  Temporary construction arrangement that affect access to adjacent area.

 

Prediction and Evaluation of Landscape Impact during Construction

 

9.8.3                 A landscape impact is a physical change to an existing landscape resource.  Any loss or alteration can be assessed and re-provisioned or compensated by landscape mitigation measures. The landscape impact in the construction stage will have a moderate to slight negative impact upon the landscape character units and landscape element of the study area by the construction of the drainage channel. A summary of the disturbance to the LCUs is shown in Table 9.4 and to the LEs in Table 9.5. The potential landscape impact is quantified in Tables 9.4 and 9.5.  The levels of the landscape impact on individual LCUs and LEs at construction stage have been stated in Tables 9.6 and 9.7 respectively.

 

LCU1 – Upland and Hillside

 

9.8.4                 The site formation and construction of the proposed channel will affect the hillside plantation, scrubland and water stream / pond character of the upland area. As the proposed channel will largely sit on the existing Hang Hau Tsuen stream, the magnitude of change would be Intermediate during construction and the impact would be Moderate adverse.

 

LCU2 – Transport Corridor

 

9.8.5                 No work is carried out within this LCU, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LCU3 – Village and Settlement

 

9.8.6                 The construction of the proposed channel will affect a few of the village houses, inducing small magnitude of change. However, since the sensitivity is Low, the impact would be Slight adverse during construction.

 


LCU4 – Industrial / Utility

 

9.8.7                 No work is carried out within this LCU, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LCU5 – Coastal Area

 

9.8.8                 No work is carried out within this LCU, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LE1 - Woodland

 

9.8.9                 No work is carried out within the LE, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LE2 – Existing Vehicle Corridor

 

9.8.10             No work is carried out within the LE, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LE3 – Residential / Settlement Area

 

9.8.11             The site formation works of the proposed channel will affect a few of the village structures near the edge of the stream, causing a disturbance of approximately 0.19 ha. The magnitude of change is Small inducing a Slight adverse during construction.

 

LE4 – Open Storage

 

9.8.12             No work is carried out within the LE, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LE5 – Stream Course

 

9.8.13             The proposed channel will largely sit on the existing course affecting approximately 0.32 ha. The magnitude of change during construction would be Intermediate inducing a Moderate adverse impact.

 

LE6 – Fish Pond

 

9.8.14             The site formation works of the proposed channel will affect approximately 0.08 ha of the fishpond edge.  For the formation of the approximately 5 m high flood bank, the affected pond edge will be filled with soil to form the eventual vegetated embankment. Therefore, the magnitude of change would be Small inducing a Moderate adverse impact during construction.

 

 

LE7 – Open Water (Deep Bay)

 

9.8.15             No work is carried out within the LE, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LE8 – Agricultural Land

 

9.8.16             No work is carried out within the LE, therefore the magnitude of change is Negligible and the impact is also Negligible.

 

LE9 – Scrubland/Grassland and Roadside Planting

 

9.8.17             The proposed works will affect approximately 1.18 ha of vegetated stream banks area and some mangrove area.  This will involve the removal the existing tree and shrub vegetations for the site formation work and construction of the channel and associated improvement works.  The magnitude of change during construction would be Intermediate, inducing a Moderate adverse impact.

 

Source of Visual Impact

 

9.8.18             The elements of the proposed development would create varying levels of visual impact on the visual amenity of the surrounding area during construction stage. Potential impact would result from the followings:

 

·                  Removal of existing vegetation within the site;

·                  Storage of existing topsoil and reinstatement works;

·                  Possible glares generated from the area flood light at night;

·                  Material stockpiling;

·                  Construction equipment and plants; and

·                  Temporary parking area on site, accommodation and working areas.

 

Prediction and Evaluation of Visual Impacts during Construction

 

9.8.19             It is considered that SVRs located close to the construction works will receive a substantial to moderate negative visual impact.  On this basis, SVRs in the following location as illustrated in Table 9.8 would be worst affected during the construction stage.

 

SVR1 (VPT 1.1)

 

9.8.20             This group of visual receptors is the residents from the Hang Hau Tsuen, which is located mainly on the north bank of the stream with a few residents located at the southwest side of the stream. The village houses are generally packed in tight cluster facing each other, with most of the building found to be derelict. The residents located along the stream banks just outside the subject site area will have an open or partially open view to the subject site. Due to the limited number of visual receptor and would consider that exterior view plays an important part of their normal life, thus the visual impact caused during construction stage is considered as substantial adverse.

 

SVR2 (VPT 2.1)

 

9.8.21             This group of visual receptors is the passengers and pedestrians traveling along Deep Bay Road. At a few advantage locations along this relatively quiet road, the visual receptors have an open view to the site. This group of visual receptors is mainly transit in nature and the time to pass through this section of road is relatively short, thus the visual impact is considered as slight adverse during construction stage.

 

SVR3 (VPT 3.1)

 

9.8.22              This group of visual receptors is the teachers and pupil of Wing Jan Kindergarten to the southeast of site. Located on a higher ground level not screened by immediate vegetation, this group of visual receptors has open view of the site. The visual impact is considered as moderate adverse during the construction stage.

 

SVR4 (VPT 4.1)

 

9.8.23              This group of visual receptors is the visitors to the Hang Hau Tsuen Sitting-Out Area to the southeast of the subject site. Apart from a few immediate screen trees, these visual receptors have an open view of the site. Due to the sitting-out area is very small with limited visitors and expected short staying time, the visual impact caused is considered as moderate adverse during the construction stage.

 

9.8.24              Slight to negligible visual impact will be felt by SVRs located in the distance of the subject site.

 

SVR1 (VPT 1.2)

 

9.8.25              This group of visual receptors is the residents from Deep Bay Grove to the north of the site. The view towards the site is largely screened by the existing tree and vegetation between the subject site and Deep Bay Grove. This group of visual receptors have no view of the proposed works. Thus, the visual impact is considered as negligible during construction stage.

 


Landscape and Visual Impact Assessment during Operational Stage

 

Background

 

9.8.26              The proposed improvement works is to alleviate the flooding problem in the area by converting the existing stream into an engineered channel. The new drainage channel, footbridges and footpaths will intrude into the local landscape context. Once the improvement work is put into operation, it will not result in any further perceptible change to the existing landscape and visual character.

 

Prediction and Evaluation of Landscape Impact during Operation

 

9.8.27              During operational stage, it is anticipated that the magnitude of change from the baseline condition will be small. Apart from LCU1, LE3, LE5, LE6 and LE9 will experience a moderate to slight adverse landscape impact due to the lost of existing tree and vegetation, residential area and disturbance to the stream and fish pond, no change is predicted to the other LCUs and LEs. A summary of landscape impact during operation is given in Tables 9.6 and 9.7.

 

Prediction and Evaluation of Visual Impact during Operation

 

9.8.28              On completion of construction and during operation of proposed development, no perceptible change to views from SVRs in the baseline condition is predicted other than the cumulative impact to the VPT1.1, VPT2.1, VPT3.1 and VPT4.1. A summary of visual impact during operation is given in Table 9.8.

 

SVR 1 (VPT 1.1)

 

9.8.29              A few residents at Hang Hau Tsuen will have direct view of the site and the completed drainage channel. With the completion of the construction works, there will not be a critical change to the view. With the implementation of mitigation measure, the upgraded channel and associated footpaths will be a more pleasant environment with amenity planting along both sides. Compare to the somewhat unhygienic state of the existing stream view, the residual visual impact caused by the proposed development on this group of visual receptors is considered as moderately beneficial. Photomontages of views from north of Hang Hau Tsuen towards the proposed Project are shown in Figures 9.20 to 9.22.

 

SVR 2 (VPT 2.1)

 

9.8.30              This group of passengers and pedestrian along Deep Bay Road will have view of the upgrade channel. Due to the time to pass through this section of road is short, the visual impact caused during operation stage is considered slight adverse with the incorporation of the proposed mitigation measure of landscape treatment, the residual visual impact is considered slightly beneficial.

 

SVR 3 (VPT 3.1)

 

9.8.31              This group of teachers and pupil will have view of the upgraded channel. With the incorporation of proposed mitigation measure of landscape treatments the visual impact caused to this group of visual receptors during operation stage is considered slightly beneficial. Photomontages of views from Wing Jan Kindergarten towards the proposed Project are shown in Figures 9.17 to 9.19. 

 

SVR 4 (VPT 4.1)

 

9.8.32              The visitors to the Hang Hau Tsuen Sitting-Out area will have view of the upgraded channel. The visual impact caused during the operation stage is considered moderate to slight adverse. With the incorporation of proposed mitigation measures and landscaping, the residual visual impact is considered moderately beneficial.

 

Nighttime Glare Assessment

 

9.8.33              Nighttime glare is potentially a significant visual impact. Yet, permanent lighting of the proposed improvement works is required to meet the safety and security requirement.

 

9.8.34              The impact of the nighttime glare for the proposed improvement works will be similar to the existing lighting provision along the footpaths.

 

9.8.35              No visual impact from nighttime glare is expected during the operational stage.

 

9.8.36              It is predicted that the magnitude of change will be negligible resulting in negligible impact.

 


Table 9.8

Summary of Visual Impact (Without Mitigation Measures)

 

Landscape Impact (Without Mitigation Measures)

SVRs (Type)

Name of (VPT) Location

Sensitivity to Change and Visual Intrusion

Construction Stage

Operational Stage

Magnitude of Change

Significance Threshold of Potential Visual Impact

Magnitude of Change

Significance Threshold of Potential Visual Impact

SVR1

Residential Settlement

 

 

 

 

 

VPT1.1   Hang Hau Tsuen

Medium

Large

Substantial adverse

Intermediate

Moderate adverse

VPT1.2   Deep Bay Grove

Medium

Negligible

Negligible

Negligible

Negligible

SVR2

Traffic Corridor

 

 

 

 

 

VPT2.1   Deep Bay Road

Low

Small

Slight adverse

Small

Slight adverse

SVR3

Institutional

 

 

 

 

 

VPT3.1   Wing Jan Kindergarten

Medium

Intermediate

Moderate adverse

Small

 Slight adverse

SVR4

Recreational

 

 

 

 

 

VPT4.1   Hang Hau Tsuen Sitting-Out Area

Medium

Intermediate

Moderate adverse

Small

Slight adverse

 

 

 

 


9.9                        Recommended Landscape Mitigation Measures

 

Background

 

9.9.1                  The assessment in the previous section predicts that the visual impacts both during construction and initial operations stage are predicted as slight to moderate adverse. The impact on landscape character is predicted as substantial to moderate adverse due to the disturbance to existing vegetation, fish pond and stream course. Impact on the visual resources and SVRs are also predicted to be moderate to slight adverse primary due to the project is relatively small in scale of height with visible view only from up-close.

 

9.9.2                  The key source landscape impact arises from removal of existing vegetation, construction activity, such as site formation, building material delivery and stockpiling.   The key source of visual impact is the permanent intrusion of the engineered channel.

 

9.9.3                  A comprehensive range of landscape mitigation measures (LMM) and landscape framework have been developed in conjunction with the site planning and phasing of the site works as shown in Table 9.9 will illustrate the mitigation measure for each SVR. The landscape framework includes the following enhancement and mitigation measures.

 

9.9.4                  Recommended landscape mitigation measures at construction stage are:

 

·                  LMM1          Advance tree transplanting

·                  LMM2          Sensitive design site hoarding

·                  LMM3          Preservation of existing tree to be retained

·                  LMM4          Demarcation of tree protection zone

·                  LMM5          Minimize of construction works in stream

·                  LMM6          Soil conservation

·                  LMM7          Operational time restriction

 

9.9.5                  To minimize the impact on landscape and visual features, proper provision of mitigation measures during the design stage would result in a visually more compatible design when viewed at adjacent environment.  Subject to the detailed design, possible mitigation measures to be considered during design stage should include:

 

·                  LMM8          Selection of fast growing native tree and shrub mixes

·                  LMM9          Preservation of stream and pond not affected

·                  LMM10        Sensitive treatment and design to the external finish of channels walls.

·                  LMM11        Maintenance of planting works

·                  LMM12        Compensation planting of mangrove

 

9.9.6                  To mitigate the loss of 16 trees, 114 nos. of new trees in heavy standard size will be planted within the site. The proposed trees consisting mostly of native species will include Celtis sinensis, Cinnamomum parthenoxylon, Ficus microcarpa, Hibiscus tiliaceus and Cassia siamea. The total aggregated girth size of compensatory trees of 8.55 m is more than the felled 3.59 m.  Therefore, loss of tree will be compensated with a ratio of more than 1:1 in terms of numbers and aggregated girth size.

 

9.9.7                  The following native shrub species are recommended to be planted on the hydroseeded slope of the embankments: Calliandra haematocephala, Codiaeum variegatum, Duranta repen and Lxora stricta. Drooping plants such as Jasminum mesnyi, Russelia equisetiformis and Asparagus sprengeri are recommended to be planted to soften and provide greenery to the channel walls.

 

9.9.8                  Figure 9.14 illustrates the preliminary landscape proposal layout plan of the Project. Generally, the recommended mitigation measures seek to minimize potential impacts of the channel structure, to soften and provide compensation in the form of environmental improvements to offset the adverse effects of the proposed Project. Figure 9.15 illustrates the typical section view with the incorporation of the landscape proposal.

 

9.9.9                  As details of the proposed planting cannot be ascertain at the EIA stage, the preliminary design stage of the Project, it is recommended that a detailed Landscape Plan be submitted before commencement of planting or landscape works of the Project. The Landscape Plan should include the locations, size, number and species of plantings, design details, implementation programme, maintenance and management schedules, and drawings in scale of 1:1000 showing the landscape and visual mitigation measures. The Landscape Plan should be certified by the ET Leader and verified by the Independent Environmental Checker (IEC) as conforming to the information, requirements and recommendations set out in the approved EIA Report before submission to the relevant authorities.

 


Table 9.9

Summary of Landscape and Visual Mitigation Measures Programming Management

 

LMM

Recommended Landscape and Visual Mitigation Measures

Objectives of the Recommended Measures & Main Concerns

Location / Timing

What requirements or standards for the measure to achieve

Funding/ Implementation Agent

Management and Maintenance Agent

LMM1

Advance tree transplanting of existing trees affected by the proposed development.

Preservation of existing trees

Project area / Commencement of construction

Require advance tree surgery preparation

Comply to ETWB TCW No. 3/2006

Project Proponent / Contractor

LCSD*

LMM2

Sensitively designed site hoarding in both color and form to screen view to the construction works.

Visual enhancement

Project area / Commencement of construction

N/A

Project Proponent / Contractor

Project Proponent / Contractor

LMM3

Preservation of existing tree to be retain on area not affected by the proposed development.

Conservation of existing trees; Visual screen

Project area not affected with tree surgery works / Commencement of construction

Comply to ETWB TCW No. 3/2006

Project Proponent / Contractor

LCSD*

LMM4

Demarcation of the tree protection zone for retain trees

Preservation of existing trees

Project area / Commencement of construction and throughout construction period

Comply to ETWB TCW No. 3/2006

Project Proponent / Contractor

Project Proponent / Contractor

LMM5

Minimization of the construction works in the existing stream

Preservation of existing landscape resources and landscape character

Project area / Commencement of construction and throughout construction period

Comply to ETWB TCW No. 5/2005

Project Proponent / Contractor

Project Proponent / Contractor

LMM6

Soil conservation – conservation of existing and imported soil resources. 

Conservation of existing topsoil

Project area not affected for stockpile / Commencement of construction and throughout construction period.

Existing soil resources on site will be conserved in stockpiles with a maximum height of 2 m.  All material stockpiles should be covered with an impermeable material and sandbagging diversions should also be placed around exposed soil.  Material stockpiled should be in area with the least obstruction to pedestrian.

Project Proponent / Contractor

Project Proponent / Contractor

LMM7

Operational time restrictions to limit after dark welding and lighting.

Limit night time glare

Project area / Throughout the construction period

N/A

Project Proponent / Contractor

Project Proponent / Contractor

LMM8

Selection of fast growing native trees and shrubs mix in compensation for the removal / disturbance area.  Planting will be planted along the channel bunds as landscape treatment to screen the built element and mitigate the landscape and visual impact.  The combination of natives trees and shrubs mix will provide a more diverse edge effect and break up the overall visual dominance.

Visual screen; Landscape compensation

Project area / Construction period

Selection and agree on the specified plant species

Project Proponent / Contractor

LCSD*

LMM9

Preservation of existing stream and pond not affected by the development.

Preservation of Landscape resources and character

Section of existing stream and pond not affected by the project / Throughout the construction period and operation period

Comply to ETWB TCW No. 5/2005

Project Proponent / Contractor

DSD (for area within DSD Boundary)*

LMM10

Provide sensitive treatment and design to the external finish of the channel walls such as adopting the use of natural materials and planting to soften surface of built structures

 

Visual enhancement

Commencement of construction and throughout the construction period

N/A

Project Proponent / Contractor

DSD*

LMM11

Maintenance of planting works upon completion.

Landscape compensation

Operation period

Agree on the maintenance requirement and programme

Comply to ETWB TCW No.2/2004

Project Proponent / Contractor

Contractor (for the establishment period after construction); DSD and LCSD*

LMM12

Compensation planting of mangrove to stream bed

Landscape compensation

Operation period

Agree on the maintenance requirement and programme

Comply to ETWB TCW No.2/2004

Project Proponent / Contractor

Contractor (for the establishment period)

No long term maintenance necessary

 

* The project proponent (CEDD) will assume to be responsible for the mitigation measures until an agreement is reached between CEDD and relevant parties on the management and maintenance of the mitigation measures.


9.10                    Residual Impacts and Acceptability of the Proposed Improvement Works

 

Residual Landscape Impact

 

9.10.1              A Summary of Residual Landscape Impact is shown in Table 9.10.  In general, the incorporation of mitigation measures into the proposed development will be effective in reducing the ‘moderate adverse’ impact down to ‘slight adverse’ impact at the construction stage and to ‘slight adverse’ and ‘moderately beneficial’ at the operational stage.

 

9.10.2              With the incorporation of mitigation measures the upgraded channel will be a more pleasant environment with natural stone finish channel walls and lush surrounding tree and shrub planting. Compare to the somewhat unhygienic state of the existing concrete stream character, the residual landscape impact caused by the proposed development to the landscape character of LCU1 and LCU3 is consider as Slight beneficial.

 

9.10.3              The quality of landscape element LE9 will improve due to the proposed mitigation measures of soft landscaping with proper management and maintenance. The residual landscape impact caused by the proposed development to LE9 is considered as Moderate beneficial.

 

Residual Visual Impact

 

9.10.4              A summary of Residual Visual Impact in Table 9.11 illustrates that the incorporation of mitigation measures in the proposed development will effectively reduce construction and operational visual impact from ‘moderate adverse’ (without mitigation measure) to ‘moderately beneficial’ (with mitigation measure).

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


Acceptability of the Proposed Improved Works

 

9.10.5              The residual impacts are evaluated as being acceptable with mitigation measures based on the following:

 

·                  The proposed development incorporates landscape and visual mitigation measures that will reduce the overall adverse level of visual impact to an acceptable beneficial level. The proposed landscape treatment along both sides of the channel will enhance the local visual quality for the residents, visitors, and traveller around the subject site.  The adverse impact on the woodland and streambed zone will be less adverse due to the compensation-replanting scheme.

 

·                  The proposed development has been designed in consideration with the existing topography and in harmony with the urban setting of the surrounding areas.  The proposed development will provide visual relief for the visual receptors and improve the current condition. The proposed development is predicted to be acceptable with landscape and visual mitigation measure implemented.


Table 9.10                   Summary of Residual Landscape Impacts (With Landscape Mitigation Measures)

 

Landscape Character Units (LCUs) / Landscape Elements (LEs)

Without Recommended Mitigation Measures

Recommended Mitigation Measures

With Recommended Mitigation Measures

Landscape Impact during Construction Stage

Landscape Impact during Operation Stage

Threshold of Residual Landscape Impact during Construction Stage

Threshold of Residual Landscape Impact during Operation Stage

Landscape Character Units (LCUs)

LCU 1 – Upland and Hillside  

Moderate adverse

Slight adverse

LMM1 to LMM5 and

LMM7 to LMM12

Slight adverse

Slight beneficial

LCU 2Transport Corridor

Negligible

Negligible

Nil

Negligible

Negligible

LCU 3 – Village and Settlement

Slight adverse

Negligible

LMM2, LMM3, LMM7 and LMM8, LMM10 to LMM12

Slight adverse

Slight beneficial

LCU 4 – Industrial / Utility

Negligible

Negligible

Nil

Negligible

Negligible

LCU 5 – Coastal Area

Negligible

Negligible

Nil

Negligible

Negligible

Landscape Elements (LEs)

LE 1 Woodland

Negligible

Negligible

Nil

Negligible

Negligible

LE 2 – Existing Vehicle Corridor

Negligible

Negligible

Nil

Negligible

Negligible

LE 3 – Residential / Settlement Area

Slight adverse

Slight adverse

LMM2, LMM3, LMM7 and LMM8, LMM10 to LMM12

Slight adverse

Slight adverse

LE 4 Open Storage

Negligible

Negligible

Nil

Negligible

Negligible

LE 5 Stream Course

Moderate adverse

Slight adverse

LMM5, LMM9, LMM10, LMM12

Slight adverse

Negligible

LE 6 Fish Pond

Moderate adverse

Moderate adverse

LMM9

Slight adverse

Slight adverse

LE 7 Open Water (Deep Bay)

Negligible

Negligible

Nil

Negligible

Negligible

LE8 – Agricultural Land

Negligible

Negligible

Nil

Negligible

Negligible

LE9 –Scrubland/Grassland and Roadside Planting

Moderate adverse

Slight adverse

LMM1, LMM3, LMM4, LMM8, LMM10 to LMM12

Slight adverse

Moderate beneficial

 

 

 

Table 9.11                   Summary of Residual Visual Impacts (With Landscape Mitigation Measures)

 

SVR Number

Without Recommended Mitigation Measures

Recommended Mitigation Measures

With Recommended Mitigation Measures

Visual Impact during Construction Stage

Visual Impact during Operation Stage

Significance Threshold of Residual Visual Impact during Construction

Significance Threshold of Residual Visual Impact during Operation

SVR1

 

 

 

 

 

VPT1.1

Substantial adverse

Moderate adverse

LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11

Moderate adverse

Moderate beneficial

VPT1.2

Negligible

Negligible

Nil

Negligible

Negligible

SVR2

 

 

 

 

 

VPT2.1

Slight adverse

Slight adverse

LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11

Slight adverse

Slight beneficial

SVR3

 

 

 

 

 

VPT3.1

Moderate adverse

 Slight adverse

LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11

Slight adverse

Slight beneficial

SVR4

 

 

 

 

 

VPT4.1

Moderate adverse

Slight adverse

LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11

Slight adverse

Moderate beneficial

 

 

 


9.11                    Environmental Monitoring and Audit Requirements

 

9.11.1              Monitoring and audit should be undertaken during the construction phase of the Project to ensure and to check that the implementation and maintenance of landscape and visual mitigation measures are being carried out properly.

 

9.11.2              A landscape auditor (as a member of the Environmental Team (ET)) shall be employed to review contractor’s submissions and proposals and to monitor and audit the contractor’s landscape works in particular to ensure the existing trees retained on-site are being well preserved, tree transplanting and felling operations are being undertaken in accordance with the requirements, procedures and specifications as stipulated in the contract and the approvals granted by concerned authorities, and all the newly planted vegetations are being maintained properly during the establishment period.

 

9.11.3              It is recommended that a detailed Landscape Plan be submitted before commencement of planting or landscape works of the Project. The Landscape Plan should include the locations, size, number and species of plantings, design details, implementation programme, maintenance and management schedules, and drawings in scale of 1:1000 showing the landscape and visual mitigation measures. The Landscape Plan should be certified by the ET Leader and verified by the Independent Environmental Checker (IEC) as conforming to the information, requirements and recommendations set out in the approved EIA Report before submission to the relevant authorities.

 

9.11.4              The monitoring requirement is broadly presented in Chapter 10 of this Report. Details of the monitoring and audit of landscape and visual impact will be presented in the separate EM&A Manual.

 


9.12                    Summary

 

9.12.1              The cumulative landscape and visual impact predicted by the LVIA are as follows:

 

·                  The project would result in the loss of 16 nos. of trees. Compensatory planting will comprise about 114 nos. of tree in attempt to restore the loss of greenery and to enhance the overall landscape quality.

 

·                  During the construction stage, the predicted impact on LCU1, LE9, LE3, LE5 and LE6 are Slight adverse. Upon completion of the improvement works with implementation of mitigation measures, the impact on LE3 and LE6 will still be Slight adverse due to the small affected portion of Fish Pond and Residential / Settlement Area. Where as, the impact to LCU1, LCU3 and LE9 are predicted to be Moderate to Slight beneficial due to the upgraded channel. 

 

·                  The proposed development in general will have a beneficial visual impact.  Mitigation measures as recommended in the previous sections will ease significantly the negative visual impact caused by proposed development.

 

9.12.2              The landscape and visual impact assessment indicated that moderate to slight adverse impact would occur during the construction stage and moderate to slight beneficial impact during operational stage. The landscape mitigation measure will minimize the adverse impact of the disturbance to existing trees from moderate adverse to moderate beneficial in the long term. Adverse visual impact, which is in a local context, will be minimized with the incorporation of mitigation measures.

 

9.12.3              Apart from the slight adverse impact on the elimination of small portion of residential area and fishpond within the site area, it is predicted that the proposed improvement works will have negligible adverse landscape impact and moderate beneficial visual impacts during the operational stage. In conclusion, the landscape and visual impacts in the construction and operational stage will be “acceptable with of mitigation measures”.