9.
LANDSCAPE AND
VISUAL IMPACT ASSESSMENT
9.1.1
The objective of this Landscape
and Visual Impact Assessment (LVIA) report is to identify the existing and
proposed landscape elements and the visual quality within the limits of the
primary visual envelope of the study area (Figure 9.1) and provide an
evaluation of the impact on the landscape and visual aspects due to the
proposed improvement works with engineered drainage channel and other
associated works (the Project). Alternative alignment options of the Project
are discussed in detail in Section 2.4. The assessment will cover the landscape
and visual impact on the surrounding with stage of the life cycle through out
the Project.
9.1.2
It will address the main
concerns from the visual and landscape point of view to derive mitigation
measure to minimize the landscape and visual impact due to the Project.
9.2.1
The assessment of the landscape
and visual impact due to the proposed Project has been carried out all in
accordance with the criteria and methodology in Annexes 10 and 18 of the
Technical Memorandum on EIA Process (EIAO-TM) issued under the EIAO (Cap.499).
9.2.2
The HKPSG (Chapter 10 –
Landscape and Conservation) outlines the criteria, which should be considered
when planning in the rural environment; the Government Circular regarding tree
preservation ETWB TC(W) No. 3/2006 – Tree Preservation is also applied to this assessment.
9.2.3
In
addition, the following guidelines and technical circulars have been considered
in the landscape and visual assessment:
(i)
EIAO
Guidance Note No. 8/2002 – Preparation of Landscape and Visual Impact
Assessment under the EIAO;
(ii)
WBTC No.
17/2000 – Improvement to the Appearance of Slopes;
(iii)
ETWB TC(W)
No. 2/2004 – Maintenance of Vegetation and Hard Landscape Features;
(iv)
ETWB TC(W)
No. 29/2004 – Registration of Old and Valuable Trees, and Guidelines for their
Preservation;
(v) Technical Guidelines on Landscape Treatment and Bio-Engineering of Man-made Slope and Retaining Walls (GEO Publication No. 1/2000); and
(vi) Use of Vegetation as Surface Protection on Slope (GEO 1999).
9.3.1
The methodology adopted for the
proposed Project conforms to the requirements of the EIAO. A robust methodology
will be derived for the LVIA to meet the requirements of the EIA Study Brief
and the EIAO-TM. It consists of:
·
A definition
of the scope and contents of the proposed works;
·
Review of
Planning Development Control Framework;
·
A
comprehensive description of the baseline landscape and visual character;
·
Identification
of the potential landscape and visual impacts and prediction of its magnitude
and extent of impact;
·
Recommendations
on mitigation measures; and
·
Assessment
of residual impact and conclusion.
Scope and Contents
9.3.2
In setting the scope of the landscape
and visual impact assessment for proposed development, the following aspects
will be considered:
·
Site
description;
·
Proposed
development;
·
Level of
details required for baseline studies;
·
Key
viewpoints to be covered;
·
System to
be used for judging significance of impact;
·
Other
development if cumulative impacts are to be assessed;
·
Impact assessment;
and
·
Recommended
mitigation measures.
Key Issues to be Addressed
9.3.3
The assessment identifies the
impacts of the proposed Project, upon the character of that landscape and upon
the visual amenity of that area.
The surrounding area has its distinctive character and its own landscape
value. The alteration of the
existing landscape elements, such as tree belt would be vulnerable to the
existing landscape character. The study area is exposed to view thus lead to the loss of visual quality on the
surrounding. Mitigation measure should be addressed to compensate on the loss
of visual quality due to the proposed Project.
9.3.4
Key issues relating to
landscape impact of the Project will include:
·
Impacts upon the landscape character within the
study area; and
· Impacts upon the proposed landscaping in the study area from the surrounding area.
9.3.5
Key issues relating to the
visual impact of the Project will include:
·
Impact upon sensitive receivers due to the proposed improvement
works during the construction stage and
operation stage; and
· Interference of views due to the proposed improvement works.
Baseline Study
9.3.6
The baseline study will present
an appraisal of the landscape and visual resources of the study area. It will
focus on the sensitivity of the landscape and visual impact on the visual
receiver and its ability to accommodate change. Under the EIA Study Brief, the study
area defines for the Landscape Impact Assessment is approximately 500 meters
from the proposed works site boundary. A visual envelop defines the area for the
Visual Impact Assessment. This is generally the view shed formed by natural/manmade feature
such as tree line and building block.
9.3.7
Landscape resources considered
include topography, woodland, and other vegetation, built form, settlement
pattern, land use, scenic spots and details of local streetscapes. The baseline study described the
landscape resource by identifying broadly homogenous Landscape Character Units
(LCUs) of a similar character, they are rated on the quality of element, their
sensitivity to change and its importance at various geographical level.
9.3.8
Visual resources considered are
typical viewpoints located and direct towards the Project. A visual envelop
will establish which define the extent of visual influence of the Project and
the potential visual impacts. Definition
of the extent of the view shed formed by natural / man-made feature, such as
ridgeline or building blocks, will be based on desktop study and site investigation.
As the topography of the site area is situated within a lower ground level, the
zone of visual influence is expected to be limited within the immediate
surrounding area. Sensitive Visual Receivers (SVRs) identified in this
assessment are representative in that individual or groups that have a similar
sensitivity to changes in the visual and landscape environment.
Review of the Planning and Development
Control Framework
9.3.9
A review of the planning and
development control framework has been undertaken to provide an insight to the
future outlook of the area affected and the way the proposed development would
fit into its wider context. This will also give further insight into possible
future sensitive receiver that might be affected by the proposed improvement
works.
Principle
View Point
9.3.10
Viewpoint from area surrounding
the study area will be established and examined. They are representation of the
specific type of SVRs subject to the impact covered by proposed improvement works.
Methodology for Assessment of Landscape and
Visual Impact
Landscape Impact
9.3.11
Landscape impacts can be
positive or negative. They are
assessed at two levels:
· Impacts upon individual landscape features and resources; and
·
Impacts
upon landscape character.
9.3.12
Landscape impacts are assessed
as a function of the magnitude of change and the sensitivity of the landscape
resource or landscape character.
Landscape sensitivity is assessed as high, medium and low, and magnitude
of change is assessed as large, intermediate, small and negligible. Landscape impacts are
assessed subsequent to the implementation of prescribed mitigation measures at
both construction and operational stages.
· Landscape sensitivity is the ability of the landscape resource or character to accommodate change without prejudice to the quality of that resource.
· Magnitude of change is the degree of degradation or intrusion on the landscape element on which it may be possible to affect through landscape or environment enhancement.
9.3.13
Impacts are assessed as
substantial, moderate and slight (positive or negative). Insignificant impacts are termed
negligible. A matrix is used to assess landscape impacts and is shown in the Table
below:
Landscape
Impact Characteristic (Positive or Negative)
Magnitude of
Change |
Sensitivity of Landscape Resource / Character |
||
High |
Medium |
Low |
|
Large |
Substantial |
Substantial
/ Moderate |
Moderate |
Intermediate |
Substantial
/ Moderate |
Moderate |
Moderate /
Slight |
Small |
Moderate |
Moderate /
Slight |
Slight |
Negligible |
Negligible |
Negligible |
Negligible |
Substantial - Adverse
/ Beneficial impact where the proposed project would cause significant
degradation or improvement in existing landscape baseline conditions.
Moderate - Adverse
/ Beneficial impact where the proposed project would cause noticeable degradation
or improvement in existing landscape baseline conditions.
Slight - Adverse /
Beneficial impact where the proposed project would cause a barely noticeable
degradation or improvement in existing landscape conditions or where the
changes brought about by the project would not be apparent in visual terms.
Negligible - The proposed project does not
perceptibly affect the existing landscape baseline conditions.
Visual Impact
9.3.14
Visual impacts can be positive
or negative and are defined as a function of the sensitivity of a receiver and
the magnitude of the change to that receiver’s existing view.
9.3.15
The assessment of visual
impacts is structured by receiver sensitivity. Sensitive Visual Receivers
(SVRs) are identified through the definition of the structure’s Zone of Visual Influence
or ZVI (i.e. the area within which
views of the study area are possible).
For the purpose of this study, receivers have been grouped into the
following categories:
Residential - Those people who would view the proposal from their home.
Occupational - Those people who would view the proposal from their workplace.
Travelers - Those people who would view the proposal from their vehicles or on foot.
Recreational - Those people who would view the proposal whilst engaging in recreational activities.
9.3.16
The sensitivity of receivers to
visual impacts is influenced by the immediate context of the viewer, the
activity in which they are engaged and the value that they attach to this
location in particular. Receivers are categorized as being of high, medium or
low sensitivity to visual impacts.
9.3.17
Those who view the proposal
from their homes are considered to be highly sensitive to any visual
intrusion. This is because the
attractiveness, or otherwise, of the view would have a notable effect on a
resident’s general quality of life and acceptability of their home environment.
9.3.18
Those people who view the
scheme from their workplace are considered relatively less sensitive to visual
intrusion. This is because they are
employed in activities where visual outlook plays a less important role in the
perception of the quality of the working environment. They are classified as a low sensitivity
group.
9.3.19
For those who view the scheme
whilst engaging in outdoor leisure pursuits, visual sensitivity varies
depending on the type of recreational activity. Those taking a stroll in a park, for
example, would be classified as a high sensitivity group compared to football
players who would have a low sensitivity rating.
9.3.20
For those people who view the
scheme from public thoroughfares, the degree of visual intrusion experienced
depends on the speed of travel and whether views are continuous or only
occasional. Generally, the slower
the speed of travel and the more continuous the viewing experience, then the
greater the degree of sensitivity.
9.3.21
The criteria used to determine
the sensitivity of SVRs are given below:
·
Value and
quality of existing views;
·
Type of
view;
·
Availability
and amenity of alternative views;
·
The number
of visual receivers;
·
The
category or type of visual receivers as discussed above;
·
The
particular visual backdrop from specific viewpoints;
·
The frequency
(length and duration of time) the proposed development is in view; and
· Distance to the project.
9.3.22
The criteria used to determine
the magnitude of change to a view are given below:
·
Proximity
of receivers;
·
Degree of
change of views;
·
The
particular visual backdrop to the development from specific important view
points;
·
The
landscape context of the proposed development;
·
The nature
of the proposed development and its compatibility with the surrounding
landscape;
·
Scale of
development;
·
Reversibility
of change;
·
Potential
blockage of view; and
·
Duration of impacts under
construction and operation phase.
9.3.23
Impacts are assessed as
substantial, moderate and slight.
Insubstantial impacts are termed negligible. A matrix is used to assess visual
impacts and is shown in Table below:
Visual Impact Characteristic (Positive or Negative)
Magnitude of Change |
Sensitivity of Receiver
Group |
||
High |
Medium |
Low |
|
Large |
Substantial |
Substantial / Moderate |
Moderate |
Intermediate |
Substantial
/ Moderate |
Moderate |
Moderate /
Slight |
Small |
Moderate |
Moderate /
Slight |
Slight |
Negligible |
Negligible |
Negligible |
Negligible |
Substantial - Adverse
/ Beneficial impact where the proposed project would cause significant
degradation or improvement in existing visual baseline conditions.
Moderate - Adverse
/ Beneficial impact where the proposed project would cause noticeable
degradation or improvement in existing visual baseline conditions.
Slight - Adverse /
Beneficial impact where the proposed project would cause a barely noticeable
degradation or improvement in existing visual conditions or where the changes
brought about by the project would not be apparent in visual terms.
Negligible - The proposed project does not
perceptibly affect the existing visual baseline conditions
Recommendation for Mitigation Measure
9.3.24
Alternative alignment, design
and construction method that would avoid or reduce the identified impacts on
landscape, or that would make the project visually more compatible with the
surrounding setting will be examined. The identification of the landscape and
visual impact will highlight those sources of conflict requiring design solutions
or modification to reduce impacts and absorb the improvement and associated
activities into the surrounding landscape. These mitigation efforts will
consider factors as listed below and will derive landscape mitigation proposals
to alleviate the identified landscape and visual impact.
·
· Contouring of new slopes to blend with existing topography in a natural manner;
· Earth mounding and screening;
· Highlighting unacceptable impacts and considering alternative proposals;
· Hard landscape elements including design and appearance of proposed facility; and
· Significant landscape elements.
Residual Landscape and Visual
Impact
9.3.25
Residual impact is defined as
the impact remaining after all practical methods of mitigation have been
implemented. The final stage of the LVIA study is to assess the significance of
the residual impacts. The impacts will be classified according to their level
of significance as summarized below:
· Beneficial - the project will complement the landscape and visual character of its setting, will follow the relevant planning objectives and will improvement the landscape and visual quality of the study area.
· Acceptable - the assessment indicates that there will be no significant effects on the landscape, no significant visual effects caused by the appearance of the project, or no interference with key views.
· Acceptable with mitigation measure - there will be some adverse effects; these can be eliminated, reduced or offset to a large extent by specific measures.
· Unacceptable - the adverse effects are considered too excessive and are unable to mitigate practically.
· Undetermined - significant adverse effects are likely, but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question.
9.4.1
The Project is located at the
south of Lau Fau Shan, partially running within the heart of Hung Hau Tsuen
between the
Landscape and Visual Context in the Study Area
9.4.2
The landscape elements and
visual context in the immediate vicinity has been characterized by a number of
contrasting features as illustrated in Figure 9.3.
9.4.3
The subject site is situated along
the watercourse of Hang Hau Tsuen stream, bounded by the
9.4.4
A wooded hill slope is located
at the south of the site. It is mature woodland that forms a green pleasant
backdrop on views to the south. Other vegetated area are found mainly along
roadsides, in villages and in amenity area surrounding the study area with
vegetated mangrove characterize the mouth of Hang Hau Tsuen stream entering
Deep Bay.
Residential / Settlement
Area
9.4.5
Settlement area are located at
the distance east, north and south of the study area in Hang Hau Tsuen, village
houses of 1 to 3 stories high are located on both sides of the stream which stretch
and collects to Lau Fau Shan, Deep Bay Grove and Sha Kong Tsuen located along
the shore of Deep Bay. San Hing Tsuen is located of the distance east of site
bounded by
Open Container Storage Area
9.4.6
The open container storage areas
are located at the east to south of the study area. The landscape context of this
area is in great contrast with the natural setting of the surrounding
landscape. The extent and bulkiness of the containers have a substantial visual
intrusion on the surrounding.
Fish Pond
9.4.7
Fishponds are found at the
immediate north and south of the site. The ponds vary in size and shape. All of
the ponds have been abandoned and not maintained. Nevertheless, the overgrown
vegetation on the bunds of the ponds forms a pleasant view to the
receptors.
Coastal Area
9.4.8
Agricultural Land
9.4.9
Agricultural land is mainly composed
of croplands and orchards. Most of the croplands were abandoned and dominated
by grasses and weeds, while a few pockets were actively farmed and mainly grown
with vegetables.
9.5
Description of
the Proposed Development
9.5.1
The Project is intended to
alleviate the flooding problem in the area by converting the existing Hang Hau
Tsuen stream between
(i)
training
of Hang Hau Tsuen stream including construction of a drainage channel of 370 m
in length connecting the downstream ends of Fung Kong Tsuen Channel and San
Hing Tsuen Channel to
(ii)
construction
of a 25 m long triple-cell box culvert of 5.5 m (W) x 3 m (H) beneath the Deep
Bay Road and 4 nos. of footbridges across the channel;
(iii)
provision
of an access road of 3.5 m in width with passing bays along the northern bank
of the channel, a 3.5 m in width maintenance access
along the southern bank of the channel and footpaths of 2 m in width on both sides
of the channel and ancillary works such as retaining walls, drainage and water
works as well as associated landscaping works; and
(iv)
a
viewing point and car park at the downstream end of the channel.
Life Cycle of the Proposed Development
9.5.2 The life cycle of this work can be divided into the construction stage and operational stage.
Background
9.6.1
The baseline study will present an appraisal of the landscape and visual resources of the assessment
area. It will focus on the
sensitivity of the landscape and visual impact on the visual receiver and its
ability to accommodate change.
Baseline Landscape Resources
9.6.2
In accordance with the EIA Study
Brief, Landscape Character Units (LCUs) and Landscape Elements (LEs) have been
identified within 500 m from the site boundary. Their results are described in Table
9.1 for Landscape Elements and Table 9.2 for Landscape Character Units. These
to include the followings:
LEs
·
LE1 -
-
Existing wooded area comprises the predominantly wooded hillsides around the
site.
·
LE2 - Existing
Vehicle Corridor (Approx. 1.25 ha)
-
Existing linear structure for vehicle of
·
LE3 - Residential/Settlement
area (Approx. 16 ha)
- Existing residential areas and village settlement at Hang Hau Tsuen, Lau Fau Shan, Sha Kong Tsuen and Deep Bay Grove, as well as market stores, shops, small temple and school within Lau Fau Shan.
· LE4 - Open Storage (Approx. 27.2 ha)
-
Existing large open storage
area and workshop buildings within Lau Fau Shan.
· LE5 - Stream course (Approx. 0.78 ha)
-
Man-made
and natural stream course within the study area.
· LE6 - Fish Pond (Approx. 1 ha)
- Existing abandoned fishpond around the subject site.
· LE7 - Open Water (Approx. 37 ha)
-
· LE8 - Agricultural Land (Approx. 7.6 ha)
- Existing abandoned and a few active agricultural field and orchards within the study area.
· LE9 - Scrubland/Grassland and Roadside Planting
(Approx. 9 ha)
- Existing green area comprises the predominantly roadside planting, scrubland and grassland within the study area.
LCUs
·
LCU1 -
-
Existing green area comprises
the predominantly of hillside plantation area, woodland, roadside planting,
scrubland and fresh water body.
· LCU2 - Transport Corridor
-
Existing linear structure for
vehicle of
· LCU3 - Village and Settlement
- Existing residential and settlement area at Hang Hau Tsuen, Lau Fau Shan, San Hing Tsuen, Sha Kong Tsuen and residential development of Deep Bay Grove.
· LCU4 - Industrial / Utility
- Existing large open container storage area, warehouse and workshop building within Lau Fau Shan area.
· LCU5 - Coastal Area
- Mudflats of mangrove
and shellfish farming along the shoreline of
Landscape Elements (LEs)
Landscape Elements |
|||
LE |
Type |
Description |
Sensitivity to Change |
LE1 |
Quantity: Medium |
Existing wooded
area comprise the predominantly wooded hillsides around the site |
Medium |
LE2 |
Vehicle Corridor Quantity: Low |
Existing linear structure for
vehicle of |
Low |
LE3 |
Residential/Settlement area Quantity: Medium |
Existing residential areas and villages settlement
at Hang Hau Tsuen, Lau Fau Shan, Sha Kong Tsuen and Deep Bay Grove, as well
as market stores, shops, small temple and school within Lau Fau Shan |
Low |
LE4 |
Open Storage Quantity: Large |
Existing large open storage area and
workshop buildings within Lau Fau Shan. |
Low |
LE5 |
Stream Course Quantity: Low |
Man-made and natural stream course
within the study area |
Medium |
LE6 |
Fish Pond Quantity: Low |
Existing abandon fish pond around the subject site |
Medium |
LE7 |
Open Water ( Quantity: Large |
|
High |
LE8 |
Agricultural
Land Quantity:
Medium |
Existing
abandoned and a few active agricultural land within the study area |
Low |
LE9 |
Scrubland/Grassland
and Roadside Planting Quantity:
Medium |
Existing
green area comprises the predominantly roadside planting, scrubland and
grassland within the study area. |
Medium |
Landscape Character Units (LCUs)
Landscape Character Units |
|||
LCU |
Name |
Description |
Quality / Sensitivity to Change |
LCU1 |
|
Existing green area comprises
the predominantly of hillside plantation area, woodland, roadside planting,
scrubland and fresh water body |
Medium/Medium |
LCU2 |
Transport Corridor |
Existing linear structure for vehicle of |
Medium/Low |
LCU3 |
Village and Settlement |
Existing residential and settlement area houses at Hang
Hau Tsuen, Lau Fau Shan, San Hing Tsuen, Sha Kong Tsuen and residential
development of Deep Bay Grove |
Medium/Low |
LCU4 |
Industrial
/ Utility |
Existing large open container storage area, warehouse and workshop building within Lau
Fau Shan area |
Low/Low |
LCU5 |
Coastal Area |
Mudflats of mangrove and shell fish farming along
the shoreline of |
High/High |
9.6.3
A tree survey has been carried
out and the extent of existing trees in conflict with the improvement works was
assessed in the Tree Survey Report. The location of trees surveyed is shown on Figure
9.16. Information from the Tree Survey Report is summarized below:
(i) There are in total 14 tree species found at the location within the site boundary of the proposed improvement works. The most abundant tree species are Celtis sinensis (16 nos.) and Macaranga tanarius (16 nos.), they are common native woodland trees of height from 4 m to 12 m, trunk diameter from 0.12 m to 0.85 m and a spread from 4 m to 12 m.
(ii) Bauhinia purpurea (5 nos.) usually planted for amenity purpose, another amenity trees Cassia surattensis (1 nos.) are exotic species of height from 5 m to 8 m, trunk diameter from 0.15 m to 0.3 m and spread from 5 m to 8 m.
(iii) Delonix regia (2 nos.) and Albizia lebbek (1 no.) are exotic ornamental tree species of height from 6m to 10m, trunk diameter from 0.27 m to 1.0 m and spread from 6 m to 15 m.
(iv) Many native woodland trees are found of height from 3 m to 10 m, trunk diameter from 0.12 m to 1.0 m and spread from 3 m to 7 m, they are Melia azedarach (3 nos.), Ficus microparpa (2 nos.), Morus alba (2 nos.), Bridelia tomentosa (1 no.) and Sapium sebiferum (1 no.).
(v) Several common fruit tree species of height from 4 m to 6 m, trunk diameter from 0.1 m to 0.15 m and spread from 3 m to 4 m are found in residential area, Dimocarpus longan (1 no.), Mangifera indica (1 no.) and Clausena lansium (1 no.).
(vi) Trees surveyed have good to poor tree form and health with medium to low amenity value and survival rate after transplanting.
(vii) No trees in the Study Area are registered as Old and Valuable Trees (OVTs) under ETWB TC(W) No. 29/2004 or are considered potentially registrable as OVTs.
(viii)
Based on the layout of the development, the
proposed treatment to the existing trees are as follows:
·
Existing trees survey on site 53 nos.
·
No. of trees proposed for retention 27 nos.
·
No. of trees proposed for transplant 10
nos.
·
No. of trees proposed for felling 16 nos.
(ix)
26 existing trees within the
works area will be affected by the proposed improvement works. Of which 10 nos.
of trees will be transplanted as they have relatively higher survival rate
after transplanting and better tree form and health. Transplant trees include Celtis sinensis (5 nos.), Bauhinia purpurea (3 nos.), Albizia lebbek (1 no.) and Ficus microparpa (1 no.).
(x)
The remaining trees, Macaranga tanarius (5 nos.), Celtis sinensis (2 nos.), Melia azedarach (3 nos.), Morus alba (1 no.), Sapium sebiferum (1 no.), Bauhinia
purpurea (1 no.), Bridelia tomentosa
(1 no.), Cassia surattensis (1 no.)
and Delonix regia (1 no.), have low
survival rate after transplanting, poor tree form and health and/or are in
conflict with the proposed Project design, these trees are proposed to be
felled with compensatory tree planting.
Baseline Visual Resources
9.6.4
In accordance with the study
methodology, Sensitive Visual Receivers (SVRs) within the visual envelope were
identified and grouped into types as shown in Table 9.3. The visual
resources closely relate to the landscape character units. These units vary
from traffic corridor, residential development to woodland.
9.6.5
A visual envelope has been
mapped to determine SVRs. Key views from and towards the proposed Project are
shown in Figure 9.5 and described as below.
Key Views toward the Proposed
Development
- Figure 9.6 |
View South from Hang Hau Tsuen |
- Figure 9.7 |
View South from Hang Hau Tsuen |
- Figure 9.8 |
View Southeast from Hang Hau Tsuen |
- Figure 9.9 |
View North from Hang Hau Tsuen |
- Figure 9.10 |
View Southwest from Deep Bay Grove |
- Figure 9.11 |
View North from |
- Figure 9.12 |
View Northwest from Wing Jan Kindergarten |
- Figure 9.13 |
View Northwest from Hang Hau Tsuen Sitting-Out Area |
9.6.6
Details of the SVRs are listed
in Table
9.3.
Sensitive Visual Receivers (SVRs)
SVR |
Location and Quantity of
Viewer Group |
Viewer Group |
Max. Staying Time |
Distance to the Project |
Frequency and Duration of
View and Sources of Impact Type of View |
Sensitivity to Change and
Visual Intrusion |
SVR
1 |
- VPT1.1 (Figures 9.6 – 9.9) - Hang Hau Tsuen |
Residents |
24hr Depends on SVRs |
Approx. 0 – 100m |
- Open to Obstructed View towards the site.
Degree of View Varies depends on location of SVRs. - High frequency. - View during day and night. Duration of
view is varies depends on the activity of SVRs. |
Medium |
- VPT1.2 (Figure 9.10) - Deep Bay Grove |
Residents |
24hr Depends on SVRs |
Approx. 150m |
- Obstructed view towards the site. - High frequency. - View during day and night. Duration of
view is varies depends on the activity of SVRs. |
Medium |
|
SVR
2 |
- VPT2.1 (Figure 9.11) - |
Passengers & Pedestrian |
Approx. 2min |
Approx. 0 – 100m |
- Open view towards the site. - Low frequency. |
Low |
SVR
3 |
- VPT3.1 (Figure 9.12) - Wing Jan Kindergarten |
Teachers & Students |
Approx. 8 hrs Depends on SVRs |
0 – 80m |
- Open view towards the site. - Medium frequency. |
Medium |
SVR
4 |
- VPT4.1 (Figure 9.13) - Hang Hau Tsuen Sitting-Out Area |
Visitors |
Approx. 2 – 30 mins Depends on
SVRs |
30m |
- Open view towards the site. - Low frequency. |
Medium |
9.7
Review of Planning and Development Control
Framework
9.7.1
The broad statutory planning
framework of the proposed site area is currently covered by the approved Lau
Fau Shan & Tsim Bei Tsui Outline Zoning Plan (OZP) No. S/YL-LFS/7 and the
approved Ha Tsuen OZP No. S/YL-HT/9. The proposed channel is partly zoned
“Residential (Group D)” (R(D)) on OZP No. S/YL-LFS/7, and partly zoned “Coastal
Protection Area” (CPA) and “Comprehensive Development Area” (CDA) on OZP No.
S/YL-HT/9. As the proposed stream improvement works is a public works project
implemented by the Government, it is always permitted under the covering Notes
of the above OZPs. Planning permission from Town Planning Board is therefore
not required.
9.8
Landscape and Visual Impact Assessment
Landscape & Visual Impact Assessment during Construction Stage
Background
9.8.1
The proposed improvement works is
located on the streambed of Hang Hau Tsuen stream and the adjacent vegetated riverbanks.
Potential construction impact will be the removal of existing vegetation,
building material delivery, site formation, construction of the drainage channel
and associated works. The area of potential landscape impact on
the Landscape Character Units (Figure 9.4) and Landscape Elements (Figure
9.3) are shown in Table
9.4 and Table 9.5 respectively. The level of
potential landscape impact is shown in Tables 9.6 - 9.7.
Summary of Disturbance to Landscape
Character Units
Landscape
Character Units |
Description |
Disturbance |
LCU 1 |
|
1.58 ha |
LCU 2 |
Transport Corridor |
Nil |
LCU 3 |
Village and Settlement |
0.19 ha |
LCU 4 |
Industrial /
Utility |
Nil |
LCU 5 |
Coastal Area |
Nil |
Summary of Disturbance to Landscape Elements
Landscape Elements |
Type of Landscape Element |
Total Area within the Study Area |
Area in Interaction with the Development |
LE 1 |
|
Approx. 12 ha |
Nil |
LE 2 |
Existing Vehicle Corridor |
Approx.1.25 ha |
Nil |
LE 3 |
Residential/Settlement area |
Approx. 16 ha |
Approx. 0.19 ha |
LE 4 |
Open Storage |
Approx. 27.2 ha |
Nil |
LE 5 |
Stream Course |
Approx. 0.78 ha |
Approx.
0.32 ha |
LE 6 |
Fish Pond |
Approx. 1 ha |
Approx.
0.08 ha |
LE 7 |
Open Water ( |
Approx. 37 ha |
Nil |
LE 8 |
Agricultural
Land |
Approx. 7.6ha |
Nil |
LE 9 |
Scrubland/Grassland
and Roadside Planting |
Approx. 9 ha |
Approx. 1.18ha |
Summary of Landscape Impact on Landscape
Character Units (Without Mitigation Measures)
Landscape Impact (Without Mitigation Measures) |
|||||||
Landscape Character Units |
Disturbed Area |
Quality / Sensitivity of Change |
Construction Stage |
Operational Stage |
|||
Magnitude of Change and Source of Landscape Impact |
Significance Threshold of Residual Landscape Impact |
Magnitude of Change |
Significance Threshold of Residual Landscape Impact |
||||
LCU 1 |
|
1.58 ha |
Medium/Medium |
Intermediate (Site formation +
Construction of Drainage Channel) |
Moderate adverse |
Small |
Slight adverse |
LCU 2 |
Transport Corridor |
Nil |
Medium/Low |
Negligible |
Negligible |
Negligible |
Negligible |
LCU 3 |
Village and Settlement |
0.19
ha |
Medium/Low |
Small (Site formation +
Construction of Drainage Channel) |
Slight adverse |
Negligible |
Negligible |
LCU 4 |
Industrial /
Utility |
Nil |
Low/ Low |
Negligible |
Negligible |
Negligible |
Negligible |
LCU 5 |
Coastal Area |
Nil |
High/High |
Negligible |
Negligible |
Negligible |
Negligible |
Summary of Landscape Impact on Landscape Elements
(Without Mitigation Measures)
Landscape Impact (Without Mitigation Measures) |
|||||||
Landscape Elements |
Disturbed Area |
Quantity / Sensitivity of Change |
Construction Stage |
Operational Stage |
|||
Magnitude of change and Source of Landscape Impact |
Significance Threshold of Residual Landscape Impact |
Magnitude of Change |
Significance Threshold of Residual Landscape Impact |
||||
LE 1 |
|
Nil |
Medium/High |
Negligible |
Negligible |
Negligible |
Negligible |
LE 2 |
Existing Vehicle Corridor |
Nil |
Low/Low |
Negligible |
Negligible |
Negligible |
Negligible |
LE 3 |
Residential/Settlement Area |
Approx. 0.19 ha |
Medium/Low |
Small (Demolition of existing residential settlement) |
Slight adverse |
Small |
Slight adverse |
LE 4 |
Open Storage |
Nil |
Large/Low |
Negligible |
Negligible |
Negligible |
Negligible |
LE 5 |
Stream Course |
Approx. 0.32 ha |
Low/Medium |
Intermediate (Site formation +
Construction of Drainage Channel) |
Moderate adverse |
Small |
Slight adverse |
LE 6 |
Fish Pond |
Approx. 0.08 ha |
Low/Medium |
Small (Filling of the existing
fish pond) |
Moderate adverse |
Small |
Moderate adverse |
LE 7 |
Open Water ( |
Nil |
Large/High |
Negligible |
Negligible |
Negligible |
Negligible |
LE 8 |
Agricultural
Land |
Nil |
Medium/Low |
Negligible |
Negligible |
Negligible |
Negligible |
LE 9 |
Scrubland/Grassland
and Roadside Planting |
Approx. |
Medium/Medium |
Intermediate (Removal of the existing vegetation and
tree) |
Moderate adverse |
Small |
Slight adverse |
Source of Landscape Impact
9.8.2
The source of construction
landscape impact will include:
· The removal of existing vegetation;
· The construction works of principle site formation works for the drainage channel and associated works;
· Designation of temporary site area for storage, plant cabins and associated site equipment; and
· Temporary construction arrangement that affect access to adjacent area.
Prediction and Evaluation
of Landscape Impact during Construction
9.8.3
A landscape impact is a
physical change to an existing landscape resource. Any loss or alteration can be assessed
and re-provisioned or compensated by landscape mitigation measures. The
landscape impact in the construction stage will have a moderate to slight negative
impact upon the landscape character units and landscape element of the study
area by the construction of the drainage channel. A summary of the disturbance
to the LCUs is shown in Table 9.4 and to the LEs in Table
9.5. The potential landscape impact is quantified in Tables
9.4 and 9.5. The levels of
the landscape impact on individual LCUs and LEs at construction stage have been
stated in Tables 9.6 and 9.7 respectively.
LCU1 –
9.8.4 The site formation and construction of the proposed channel will affect the hillside plantation, scrubland and water stream / pond character of the upland area. As the proposed channel will largely sit on the existing Hang Hau Tsuen stream, the magnitude of change would be Intermediate during construction and the impact would be Moderate adverse.
LCU2 – Transport Corridor
9.8.5
No work is carried out within
this LCU, therefore the magnitude of change is Negligible and the impact is
also Negligible.
LCU3 – Village and Settlement
9.8.6
The construction of the proposed
channel will affect a few of the village houses, inducing small magnitude of
change. However, since the sensitivity is Low, the impact would be Slight
adverse during construction.
LCU4 – Industrial / Utility
9.8.7
No work is carried out within
this LCU, therefore the magnitude of change is Negligible and the impact is
also Negligible.
LCU5 –
Coastal Area
9.8.8 No work is carried out within this LCU, therefore the magnitude of change is Negligible and the impact is also Negligible.
LE1 -
9.8.9
No work is carried out within
the LE, therefore the magnitude of change is Negligible and the impact is also
Negligible.
LE2 – Existing Vehicle Corridor
9.8.10 No work is carried out within the LE, therefore the magnitude of change is Negligible and the impact is also Negligible.
LE3 – Residential / Settlement Area
9.8.11 The site formation works of the proposed channel will affect a few of the village structures near the edge of the stream, causing a disturbance of approximately 0.19 ha. The magnitude of change is Small inducing a Slight adverse during construction.
LE4 – Open Storage
9.8.12
No work is carried out within
the LE, therefore the magnitude of change is Negligible and the impact is also
Negligible.
LE5 – Stream Course
9.8.13
The proposed channel will
largely sit on the existing course affecting approximately 0.32 ha. The
magnitude of change during construction would be Intermediate inducing a
Moderate adverse impact.
LE6 – Fish Pond
9.8.14 The site formation works of the proposed channel will affect approximately 0.08 ha of the fishpond edge. For the formation of the approximately 5 m high flood bank, the affected pond edge will be filled with soil to form the eventual vegetated embankment. Therefore, the magnitude of change would be Small inducing a Moderate adverse impact during construction.
LE7 – Open Water (
9.8.15
No work is carried out within
the LE, therefore the magnitude of change is Negligible and the impact is also
Negligible.
LE8 – Agricultural Land
9.8.16
No work is carried out within
the LE, therefore the magnitude of change is Negligible and the impact is also
Negligible.
LE9 – Scrubland/Grassland and Roadside
Planting
9.8.17 The proposed works will affect approximately 1.18 ha of vegetated stream banks area and some mangrove area. This will involve the removal the existing tree and shrub vegetations for the site formation work and construction of the channel and associated improvement works. The magnitude of change during construction would be Intermediate, inducing a Moderate adverse impact.
Source of Visual Impact
9.8.18
The elements of the proposed
development would create varying levels of visual impact on the visual amenity
of the surrounding area during construction stage. Potential impact would
result from the followings:
· Removal of existing vegetation within the site;
· Storage of existing topsoil and reinstatement works;
· Possible glares generated from the area flood light at night;
· Material stockpiling;
· Construction equipment and plants; and
· Temporary parking area on site, accommodation and working areas.
Prediction and Evaluation
of Visual Impacts during Construction
9.8.19
It is considered that SVRs
located close to the construction works will receive a substantial to moderate
negative visual impact. On this
basis, SVRs in the following location as illustrated in Table 9.8 would be worst
affected during the construction stage.
SVR1 (VPT 1.1)
9.8.20
This group of visual receptors
is the residents from the Hang Hau Tsuen, which is located mainly on the north
bank of the stream with a few residents located at the southwest side of the
stream. The village houses are generally packed in tight cluster facing each
other, with most of the building found to be derelict. The residents located
along the stream banks just outside the subject site area will have an open or
partially open view to the subject site. Due to the limited number of visual
receptor and would consider that exterior view plays an important part of their
normal life, thus the visual impact caused during construction stage is
considered as substantial adverse.
SVR2 (VPT 2.1)
9.8.21
This group of visual receptors is the passengers and pedestrians traveling
along
SVR3 (VPT 3.1)
9.8.22
This group of visual receptors is the teachers and pupil of Wing Jan Kindergarten
to the southeast of site. Located on a higher ground level not screened by immediate
vegetation, this group of visual receptors has open view of the site. The
visual impact is considered as moderate adverse during the construction stage.
SVR4 (VPT 4.1)
9.8.23
This group of visual receptors is the visitors to the Hang Hau Tsuen
Sitting-Out Area to the southeast of the subject site. Apart from a few immediate
screen trees, these visual receptors have an open view of the site. Due to the
sitting-out area is very small with limited visitors and expected short staying
time, the visual impact caused is considered as moderate adverse during the
construction stage.
9.8.24
Slight to negligible visual impact will be felt by SVRs located in the
distance of the subject site.
SVR1 (VPT 1.2)
9.8.25
This group of visual receptors is the residents from Deep Bay Grove to
the north of the site. The view towards the site is largely screened by the
existing tree and vegetation between the subject site and Deep Bay Grove. This group
of visual receptors have no view of the proposed works. Thus, the visual impact is considered
as negligible during construction stage.
Landscape and Visual Impact Assessment during Operational Stage
Background
9.8.26
The proposed improvement works
is to alleviate the flooding problem in the area by converting the existing
stream into an engineered channel. The new drainage channel, footbridges and
footpaths will intrude into the local landscape context. Once the improvement
work is put into operation, it will not result in any further perceptible
change to the existing landscape and visual character.
Prediction and Evaluation of Landscape Impact during Operation
9.8.27
During operational stage, it is
anticipated that the magnitude of change from the baseline condition will be small.
Apart from LCU1, LE3, LE5, LE6 and LE9 will experience a moderate to slight
adverse landscape impact due to the lost of existing tree and vegetation,
residential area and disturbance to the stream and fish pond, no change is
predicted to the other LCUs and LEs. A summary of landscape impact during
operation is given in Tables 9.6 and 9.7.
Prediction and Evaluation of Visual Impact during Operation
9.8.28
On completion of construction
and during operation of proposed development, no perceptible change to views
from SVRs in the baseline condition is predicted other than the cumulative
impact to the VPT1.1, VPT2.1, VPT3.1 and VPT4.1. A summary of visual impact during
operation is given in Table 9.8.
SVR 1 (VPT 1.1)
9.8.29
A few residents at Hang Hau
Tsuen will have direct view of the site and the completed drainage channel.
With the completion of the construction works, there will not be a critical
change to the view. With the implementation of mitigation measure, the upgraded
channel and associated footpaths will be a more pleasant environment with
amenity planting along both sides. Compare to the somewhat unhygienic state of
the existing stream view, the residual visual impact caused by the proposed development
on this group of visual receptors is considered as moderately beneficial. Photomontages of views from north of Hang Hau Tsuen
towards the proposed Project are shown in Figures 9.20 to 9.22.
SVR 2 (VPT 2.1)
9.8.30
This group of passengers and pedestrian along
SVR 3 (VPT 3.1)
9.8.31
This
group of teachers and pupil will have view of the upgraded channel. With the incorporation
of proposed mitigation measure of landscape treatments the visual impact caused
to this group of visual receptors during operation stage is considered slightly
beneficial. Photomontages of views from Wing Jan Kindergarten towards the proposed
Project are shown in Figures 9.17 to 9.19.
SVR 4 (VPT 4.1)
9.8.32
The visitors to the Hang Hau
Tsuen Sitting-Out area will have view of the upgraded channel. The visual
impact caused during the operation stage is considered moderate to slight
adverse. With the incorporation of proposed mitigation measures and landscaping,
the residual visual impact is considered moderately beneficial.
Nighttime Glare Assessment
9.8.33
Nighttime glare is potentially
a significant visual impact. Yet, permanent lighting of the proposed improvement
works is required to meet the safety and security requirement.
9.8.34
The impact of the nighttime
glare for the proposed improvement works will be similar to the existing
lighting provision along the footpaths.
9.8.35
No visual impact from nighttime
glare is expected during the operational stage.
9.8.36
It is predicted that the
magnitude of change will be negligible resulting in negligible impact.
Summary of Visual Impact (Without
Mitigation Measures)
Landscape Impact (Without Mitigation Measures) |
||||||
SVRs (Type) |
Name of (VPT) Location |
Sensitivity to Change and Visual Intrusion |
Construction Stage |
Operational Stage |
||
Magnitude of Change |
Significance Threshold of Potential Visual Impact |
Magnitude of Change |
Significance Threshold of Potential Visual Impact |
|||
SVR1 |
Residential
Settlement |
|
|
|
|
|
VPT1.1 Hang Hau
Tsuen |
Medium |
Large |
Substantial adverse |
Intermediate |
Moderate adverse |
|
VPT1.2 Deep Bay
Grove |
Medium |
Negligible |
Negligible |
Negligible |
Negligible |
|
SVR2 |
Traffic Corridor |
|
|
|
|
|
VPT2.1 |
Low |
Small |
Slight adverse |
Small |
Slight adverse |
|
SVR3 |
Institutional |
|
|
|
|
|
VPT3.1
Wing Jan Kindergarten |
Medium |
Intermediate |
Moderate adverse |
Small |
Slight adverse |
|
SVR4 |
Recreational |
|
|
|
|
|
VPT4.1 Hang Hau Tsuen Sitting-Out Area |
Medium |
Intermediate |
Moderate adverse |
Small |
Slight adverse |
9.9
Recommended Landscape Mitigation
Measures
Background
9.9.1
The assessment in the previous
section predicts that the visual impacts both during construction and initial
operations stage are predicted as slight to moderate adverse. The impact on landscape
character is predicted as substantial to moderate adverse due to the disturbance
to existing vegetation, fish pond and stream course. Impact on the visual
resources and SVRs are also predicted to be moderate to slight adverse primary
due to the project is relatively small in scale of height with visible view
only from up-close.
9.9.2
The key source landscape impact
arises from removal of existing vegetation, construction activity, such as site
formation, building material delivery and stockpiling. The key source of visual impact is
the permanent intrusion of the engineered channel.
9.9.3
A comprehensive
range of landscape mitigation measures (LMM) and landscape framework have been
developed in conjunction with the site planning and phasing of the site works
as shown in Table 9.9 will illustrate the mitigation measure for each SVR.
The landscape framework includes the following enhancement and mitigation
measures.
9.9.4
Recommended landscape
mitigation measures at construction stage are:
· LMM1 Advance tree transplanting
· LMM2 Sensitive design site hoarding
· LMM3 Preservation of existing tree to be retained
· LMM4 Demarcation of tree protection zone
· LMM5 Minimize of construction works in stream
· LMM6 Soil conservation
· LMM7 Operational time restriction
9.9.5
To minimize the impact on
landscape and visual features, proper provision of mitigation measures during
the design stage would result in a visually more compatible design when viewed
at adjacent environment. Subject to
the detailed design, possible mitigation measures to be considered during
design stage should include:
· LMM8 Selection of fast growing native tree and shrub mixes
· LMM9 Preservation of stream and pond not affected
· LMM10 Sensitive treatment and design to the external finish of channels walls.
· LMM11 Maintenance of planting works
· LMM12 Compensation planting of mangrove
9.9.6
To mitigate the loss of 16 trees, 114
nos. of new trees in heavy standard size will be planted within the site. The
proposed trees consisting mostly of native species will include Celtis sinensis, Cinnamomum parthenoxylon, Ficus
microcarpa, Hibiscus tiliaceus
and Cassia siamea. The total
aggregated girth size of compensatory trees of 8.55 m is more than the felled
3.59 m. Therefore, loss of tree
will be compensated with a ratio of more than 1:1 in terms of numbers and
aggregated girth size.
9.9.7
The following native shrub species are recommended to be
planted on the hydroseeded slope of the embankments: Calliandra haematocephala, Codiaeum
variegatum, Duranta repen and Lxora stricta. Drooping plants such as Jasminum mesnyi, Russelia equisetiformis and Asparagus
sprengeri are recommended to be planted to soften and provide greenery to
the channel walls.
9.9.8
Figure 9.14 illustrates the preliminary landscape proposal layout plan of the
Project. Generally, the recommended mitigation measures seek to minimize
potential impacts of the channel structure, to soften and provide compensation
in the form of environmental improvements to offset the adverse effects of the proposed
Project. Figure 9.15 illustrates the typical section view with the
incorporation of the landscape proposal.
9.9.9
As details of the proposed
planting cannot be ascertain at the EIA stage, the preliminary design stage of
the Project, it is recommended that a detailed Landscape Plan be submitted
before commencement of planting or landscape works of the Project. The
Landscape Plan should include the locations, size, number and species of
plantings, design details, implementation programme, maintenance
and management schedules, and drawings in scale of 1:1000 showing the landscape
and visual mitigation measures. The Landscape Plan should be certified by the
ET Leader and verified by the Independent Environmental Checker (IEC) as
conforming to the information, requirements and recommendations set out in the
approved EIA Report before submission to the relevant authorities.
Summary of Landscape and
Visual Mitigation Measures Programming Management
LMM |
Recommended Landscape and
Visual Mitigation Measures |
Objectives of the
Recommended Measures & Main Concerns |
Location / Timing |
What requirements or
standards for the measure to achieve |
Funding/ Implementation
Agent |
Management and
Maintenance Agent |
LMM1 |
Advance tree transplanting of existing trees affected
by the proposed development. |
Preservation of existing
trees |
Project area / Commencement of construction |
Require
advance tree surgery preparation Comply to
ETWB TCW No. 3/2006 |
Project Proponent / Contractor |
LCSD* |
LMM2 |
Sensitively designed site hoarding in both color and
form to screen view to the construction works. |
Visual enhancement |
Project area / Commencement of construction |
N/A |
Project Proponent / Contractor |
Project Proponent / Contractor |
LMM3 |
Preservation of existing tree to be retain
on area not affected by the proposed development. |
Conservation of existing
trees; Visual screen |
Project area not affected
with tree surgery works / Commencement
of construction |
Comply to
ETWB TCW No. 3/2006 |
Project Proponent / Contractor |
LCSD* |
LMM4 |
Demarcation
of the tree protection zone for retain trees |
Preservation
of existing trees |
Project area
/ Commencement of construction and throughout construction period |
Comply to
ETWB TCW No. 3/2006 |
Project
Proponent / Contractor |
Project
Proponent / Contractor |
LMM5 |
Minimization
of the construction works in the existing stream |
Preservation
of existing landscape resources and landscape character |
Project area
/ Commencement of construction and throughout construction period |
Comply to ETWB TCW No. 5/2005 |
Project
Proponent / Contractor |
Project Proponent / Contractor |
LMM6 |
Soil conservation – conservation of
existing and imported soil resources.
|
Conservation of existing
topsoil |
Project area not affected for
stockpile / Commencement of
construction and throughout construction period. |
Existing soil resources on site will be conserved in
stockpiles with a maximum height of 2 m.
All material stockpiles should be covered with an impermeable material
and sandbagging diversions should also be placed around exposed soil. Material stockpiled should be in area
with the least obstruction to pedestrian. |
Project Proponent / Contractor |
Project Proponent / Contractor |
LMM7 |
Operational time restrictions to limit after dark
welding and lighting. |
Limit night time glare |
Project area / Throughout the construction period |
N/A |
Project Proponent / Contractor |
Project Proponent / Contractor |
LMM8 |
Selection of fast growing native trees and shrubs mix
in compensation for the removal / disturbance area. Planting will be planted along the
channel bunds as landscape treatment to screen the built element and mitigate
the landscape and visual impact.
The combination of natives trees and shrubs mix will provide a more
diverse edge effect and break up the overall visual dominance. |
Visual screen; Landscape
compensation |
Project area / Construction
period |
Selection and agree on the
specified plant species |
Project Proponent / Contractor |
LCSD* |
LMM9 |
Preservation
of existing stream and pond not affected by the development. |
Preservation
of Landscape resources and character |
Section of existing stream and pond not affected
by the project / Throughout the construction period and operation period |
Comply to ETWB TCW No. 5/2005 |
Project Proponent / Contractor |
DSD (for area within DSD Boundary)* |
LMM10 |
Provide
sensitive treatment and design to the external finish of the channel walls
such as adopting the use of natural materials and planting to soften surface
of built structures |
Visual
enhancement |
Commencement
of construction and throughout the construction period |
N/A |
Project
Proponent / Contractor |
DSD* |
LMM11 |
Maintenance of
planting works upon completion. |
Landscape
compensation |
Operation
period |
Agree on the maintenance
requirement and programme Comply to
ETWB TCW No.2/2004 |
Project Proponent / Contractor |
Contractor (for the establishment period after
construction); DSD and LCSD* |
LMM12 |
Compensation
planting of mangrove to stream bed |
Landscape
compensation |
Operation
period |
Agree on the
maintenance requirement and programme Comply to
ETWB TCW No.2/2004 |
Project
Proponent / Contractor |
Contractor
(for the establishment period) No long term
maintenance necessary |
* The project proponent (CEDD) will assume to be
responsible for the mitigation measures until an agreement is reached between
CEDD and relevant parties on the management and maintenance of the mitigation
measures.
9.10
Residual Impacts and Acceptability of the Proposed Improvement Works
Residual Landscape Impact
9.10.1
A Summary of Residual Landscape
Impact is shown in Table 9.10. In
general, the incorporation of mitigation measures into the proposed development
will be effective in reducing the ‘moderate adverse’ impact down to ‘slight
adverse’ impact at the construction stage and to ‘slight adverse’ and ‘moderately
beneficial’ at the operational stage.
9.10.2
With the incorporation of
mitigation measures the upgraded channel will be a more pleasant environment
with natural stone finish channel walls and lush surrounding tree and shrub
planting. Compare to the somewhat unhygienic state of the existing concrete stream
character, the residual landscape impact caused by the proposed development to
the landscape character of LCU1 and LCU3 is consider as Slight beneficial.
9.10.3
The quality of landscape
element LE9 will improve due to the proposed mitigation measures of soft
landscaping with proper management and maintenance. The residual landscape
impact caused by the proposed development to LE9 is considered as Moderate
beneficial.
Residual Visual Impact
9.10.4
A summary of Residual Visual Impact
in Table
9.11 illustrates that the incorporation of mitigation measures in the
proposed development will effectively reduce construction and operational
visual impact from ‘moderate adverse’ (without mitigation measure) to ‘moderately
beneficial’ (with mitigation measure).
Acceptability of the Proposed Improved Works
9.10.5
The residual impacts are
evaluated as being acceptable with mitigation measures based on the following:
·
The
proposed development incorporates landscape and visual mitigation measures that
will reduce the overall adverse level of visual impact to an acceptable
beneficial level. The proposed landscape treatment along both sides of the
channel will enhance the local visual quality for the residents, visitors, and
traveller around the subject site.
The adverse impact on the woodland and streambed zone will be less
adverse due to the compensation-replanting scheme.
·
The proposed development has
been designed in consideration with the existing topography and in harmony with
the urban setting of the surrounding areas. The proposed development will provide
visual relief for the visual receptors and improve the current condition. The proposed development
is predicted to be acceptable with landscape and visual mitigation measure
implemented.
Table 9.10 Summary of Residual Landscape Impacts (With Landscape Mitigation
Measures)
Landscape Character Units
(LCUs) / Landscape Elements (LEs) |
Without Recommended
Mitigation Measures |
Recommended
Mitigation Measures |
With Recommended
Mitigation Measures |
||
Landscape Impact during Construction
Stage |
Landscape Impact during Operation Stage |
Threshold of Residual Landscape Impact
during Construction Stage |
Threshold of Residual Landscape Impact during
Operation Stage |
||
Landscape Character Units (LCUs) |
|||||
LCU 1 – |
Moderate adverse |
Slight adverse |
LMM1 to LMM5 and LMM7 to LMM12 |
Slight adverse |
Slight beneficial |
LCU 2 – Transport
Corridor |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
LCU 3 – Village and Settlement |
Slight adverse |
Negligible |
LMM2, LMM3, LMM7 and LMM8, LMM10 to LMM12 |
Slight
adverse |
Slight beneficial |
LCU 4 – Industrial
/ Utility |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
LCU 5 – Coastal Area |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
Landscape Elements (LEs) |
|||||
LE 1 – |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
LE 2 – Existing Vehicle Corridor |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
LE 3 – Residential /
Settlement Area |
Slight adverse |
Slight adverse |
LMM2, LMM3, LMM7 and LMM8,
LMM10 to LMM12 |
Slight adverse |
Slight adverse |
LE 4 – Open
Storage |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
LE 5 – Stream Course |
Moderate adverse |
Slight adverse |
LMM5, LMM9, LMM10, LMM12 |
Slight adverse |
Negligible |
LE 6 – Fish Pond |
Moderate adverse |
Moderate adverse |
LMM9 |
Slight adverse |
Slight adverse |
LE 7 – Open Water ( |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
LE8 –
Agricultural Land |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
LE9 –Scrubland/Grassland and
Roadside Planting |
Moderate adverse |
Slight adverse |
LMM1, LMM3, LMM4, LMM8, LMM10 to LMM12 |
Slight adverse |
Moderate beneficial |
Table 9.11 Summary of Residual Visual Impacts (With Landscape Mitigation
Measures)
SVR Number |
Without Recommended
Mitigation Measures |
Recommended
Mitigation Measures |
With Recommended
Mitigation Measures |
||
Visual Impact during Construction Stage |
Visual Impact during Operation Stage |
Significance Threshold of Residual
Visual Impact during Construction |
Significance Threshold of Residual
Visual Impact during Operation |
||
SVR1 |
|
|
|
|
|
VPT1.1 |
Substantial adverse |
Moderate adverse |
LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11 |
Moderate adverse |
Moderate beneficial |
VPT1.2 |
Negligible |
Negligible |
Nil |
Negligible |
Negligible |
SVR2 |
|
|
|
|
|
VPT2.1 |
Slight adverse |
Slight adverse |
LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11 |
Slight adverse |
Slight beneficial |
SVR3 |
|
|
|
|
|
VPT3.1 |
Moderate adverse |
Slight adverse |
LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11 |
Slight adverse |
Slight beneficial |
SVR4 |
|
|
|
|
|
VPT4.1 |
Moderate adverse |
Slight adverse |
LMM2, LMM3, LMM7, LMM8, LMM10 and LMM11 |
Slight adverse |
Moderate beneficial |
9.11
Environmental
Monitoring and Audit Requirements
9.11.1
Monitoring
and audit should be undertaken during the construction phase of the Project to
ensure and to check that the implementation and maintenance of landscape and
visual mitigation measures are being carried out properly.
9.11.2
A landscape
auditor (as a member of the Environmental Team (ET)) shall be employed to
review contractor’s submissions and proposals and to monitor and audit the
contractor’s landscape works in particular to ensure the existing trees
retained on-site are being well preserved, tree transplanting and felling
operations are being undertaken in accordance with the requirements, procedures
and specifications as stipulated in the contract and the approvals granted by
concerned authorities, and all the newly planted vegetations are being
maintained properly during the establishment period.
9.11.3
It is recommended that a
detailed Landscape Plan be submitted before commencement of planting or
landscape works of the Project. The Landscape Plan should include the
locations, size, number and species of plantings, design details,
implementation programme, maintenance and management schedules, and drawings in
scale of 1:1000 showing the landscape and visual mitigation measures. The
Landscape Plan should be certified by the ET Leader and verified by the
Independent Environmental Checker (IEC) as conforming to the information,
requirements and recommendations set out in the approved EIA Report before
submission to the relevant authorities.
9.11.4
The monitoring requirement is
broadly presented in Chapter 10 of this Report. Details
of the monitoring and audit of landscape and visual impact will be presented in
the separate EM&A Manual.
9.12.1
The
cumulative landscape and visual impact predicted by the LVIA are as follows:
·
The
project would result in the loss of 16 nos. of trees. Compensatory planting
will comprise about 114 nos.
of tree in attempt to restore the loss of greenery and to enhance the overall
landscape quality.
·
During the construction stage,
the predicted impact on LCU1, LE9, LE3, LE5 and LE6 are Slight adverse. Upon
completion of the improvement works with implementation of mitigation measures,
the impact on LE3 and LE6 will still be Slight adverse due to the small
affected portion of Fish Pond and Residential / Settlement Area. Where as, the
impact to LCU1, LCU3 and LE9 are predicted to be Moderate to Slight beneficial
due to the upgraded channel.
·
The
proposed development in general will have a beneficial visual
impact. Mitigation measures as
recommended in the previous sections will ease significantly the negative visual impact caused by proposed development.
9.12.2
The
landscape and visual impact assessment indicated that moderate to slight
adverse impact would occur during the construction stage and moderate to slight
beneficial impact during operational stage. The landscape mitigation measure will minimize
the adverse impact of the disturbance to existing trees from moderate adverse
to moderate beneficial in the long term. Adverse visual impact, which is in
a local context, will be minimized with the incorporation of mitigation
measures.
9.12.3
Apart
from the slight adverse impact on the elimination of small portion of
residential area and fishpond within the site area, it is predicted that the
proposed improvement works will have negligible adverse landscape impact and moderate
beneficial visual impacts during the operational stage. In conclusion, the
landscape and visual impacts in the construction and operational stage will be
“acceptable with of mitigation measures”.