8.
LANDSCAPE AND VISUAL
8.1.1
The
EIA has recommended landscape and visual mitigation measures to be undertaken
during construction and operation phases of the Project. This section defines
the EM&A requirements to ensure the proposed landscape and visual impact
mitigation measures are effectively implemented.
8.1.2
The
construction phase EM&A of the landscape and visual environment and
mitigation works shall be carried out as part of the site audit programme. Specific
EM&A during operation phase of the Project is not required as long as the
proposed mitigation measures in the EIA and as depicted in the Landscape Plan
are fully implemented.
8.2.1
Baseline
changes with respect to the landscape and visual environments should be carried
out in reference to the recorded baseline conditions of the site as described
in the EIA. The monitoring should in particular record changes of each
landscape resource, landscape character area and the view conditions of each
visually sensitive receiver. Parameters used to describe changes in each of the
above should be the same as in the EIA.
8.2.2
The
baseline monitoring should be conducted as a one-off site survey prior to
commencement of any construction works.
8.3.1
Monitoring
and audit should be undertaken during the construction phase of the Project to
ensure and check that the implementation and maintenance of landscape and
visual mitigation measures are being properly carried out. Site inspections
should be undertaken at least once every two weeks through the construction
period.
8.3.2
A landscape
auditor (as a member of the ET) shall be employed to review Contractor’s
submission and proposals and to monitor and audit the Contractor’s landscape
works in particular to ensure the existing trees retained on-site are being
well preserved, tree transplanting and felling operations are being undertaken
in accordance with the requirements, procedures and specifications as
stipulated in the contract and the approvals granted by concerned authorities,
and all the newly planted vegetations are being maintained properly during the
establishment period.
8.3.3
In
particular, the extent of the agreed works areas should be regularly checked
during the construction phase. Any trespass by the Contractor outside the limit
of the works, including any damage to existing trees, woodland and vegetation
should be noted.
8.3.4
The
landscape auditor should also audit the proposed operation phase mitigation
measures in the EIA to ensure they are fully implemented by the Contractor within
the Project design and construction.
8.4.1
Should non-compliance of the
landscape and visual impacts occur, actions in accordance with the action plan
stated in Table 8.1 should be carried out.
Event and
Action Plan for Landscape and Visual Impact - Construction Phase
Action
Level |
Environmental
Team (ET) Leader |
Independent
Environmental Checker (IEC) |
Engineer’s Representative
(ER) |
Contractor |
Non-conformity on one occasion |
1. Identify
source 2. Inform
the IEC and the ER 3. Discuss
remedial actions with the IEC, the ER and the Contractor 4. Monitor
remedial actions until rectification has been completed |
1. Check
report 2. Check
the Contractor’s working method 3. Discuss
with the ER and the Contractor on possible remedial measures 4. Advise
the ER on effectiveness of proposed remedial measures |
1. Notify
the Contractor 2. Ensure
remedial measures are properly implemented |
1. Amend
working methods 2. Rectify
damage and undertake remedial measures or any necessary replacement |
Repeated Non-conformity |
1.
Identify source 2.
Inform the IEC, the ER and EPD 3.
Increase monitoring (site audit)
frequency 4.
Discuss remedial actions with the
IEC, the ER and the Contractor 5.
Monitor remedial actions until
rectification has been completed 6.
If exceedance stops, cease
additional monitoring (site audit) |
1. Check
report 2. Check
the Contractor’s working method 3. Discuss
with the ER and the Contractor on possible remedial measures 4. Advise
the ER on effectiveness of proposed remedial measures 5. Supervise
implementation of remedial measures |
1.
Notify the Contractor 2.
Ensure remedial measures are
properly implemented |
1. Amend
working methods 2. Rectify
damage and undertake remedial measures or any necessary replacement |
8.5
Landscape and Visual Impact Mitigation Measures
8.5.1
A comprehensive
range of landscape mitigation measures (LMM) and landscape framework have been
developed in conjunction with the site planning and phasing of the site works
as shown in Table 8.2 will illustrate the mitigation measure for each SVR.
The landscape framework includes the following enhancement and mitigation
measures.
8.5.2
Recommended landscape
mitigation measures at construction stage are:
· LMM1 Advance tree transplanting
· LMM2 Sensitive design site hoarding
· LMM3 Preservation of existing tree to be retained
· LMM4 Demarcation of tree protection zone
· LMM5 Minimize of construction works in stream
· LMM6 Soil conservation
· LMM7 Operational time restriction
8.5.3
To minimize the impact on
landscape and visual features, proper provision of mitigation measures during
the design stage would result in a visually more compatible design when viewed
at adjacent environment. Subject to
the detailed design, possible mitigation measures to be considered during
design stage should include:
· LMM8 Selection of fast growing native tree and shrub mixes
· LMM9 Preservation of stream and pond not affected
· LMM10 Sensitive treatment and design to the external finish of channels walls
· LMM11 Maintenance of planting works
· LMM12 Compensation planting of mangrove
8.5.4
To mitigate the loss of 16 trees, 114 nos.
of new trees in heavy standard size will be planted within the site. The
proposed trees consisting mostly of native species will include Celtis sinensis, Cinnamomum parthenoxylon, Ficus
microcarpa, Hibiscus tiliaceus
and Cassia siamea. The total
aggregated girth size of compensatory trees of 8.55 m is more than the felled 3.59
m. Therefore, loss of tree will be
compensated with a ratio of more than 1:1 in terms of numbers and aggregated
girth size.
8.5.5
The following native shrub species are recommended to be
planted on the hydroseeded slope of the embankments: Calliandra haematocephala, Codiaeum
variegatum, Duranta repen and Lxora stricta. Drooping plants such as Jasminum mesnyi, Russelia equisetiformis and Asparagus
sprengeri are recommended to be planted to soften and provide greenery to
the channel walls.
Landscape Plan
8.5.6
As details of the proposed
planting cannot be ascertain at the EIA stage, the preliminary design stage of
the Project, it is recommended that a detailed Landscape Plan be submitted
before commencement of planting or landscape works of the Project. The
Landscape Plan should include the locations, size, number and species of
plantings, design details, implementation programme, maintenance
and management schedules, and drawings in scale of 1:1000 showing the landscape
and visual mitigation measures. The Landscape Plan should be certified by the
ET Leader and verified by the Independent Environmental Checker (IEC) as
conforming to the information, requirements and recommendations set out in the
approved EIA Report before submission to the relevant authorities.
8.5.7
The
implementation schedule for the recommended mitigation measures is presented in
Appendix
A.
8.5.8
If
the above measures are not sufficient to restore the impacts to acceptable
levels upon the advice of ET Leader, the Contractor shall liaise with the ET
Leader on some other mitigation measures, endorsed by IEC and propose to ER for
approval, and implement the mitigation measures.
Summary of Landscape and Visual Mitigation Measures
Programming Management
LMM |
Recommended Landscape and
Visual Mitigation Measures |
Objectives of the
Recommended Measures & Main Concerns |
Location / Timing |
What requirements or
standards for the measure to achieve |
Funding/ Implementation
Agent |
Management and
Maintenance Agent |
LMM1 |
Advance tree transplanting of existing trees affected
by the proposed development. |
Preservation of existing
trees |
Project area / Commencement of construction |
Require advance tree surgery preparation Comply to ETWB TCW No. 3/2006 |
Project Proponent / Contractor |
LCSD* |
LMM2 |
Sensitively designed site hoarding in both color and
form to screen view to the construction works. |
Visual enhancement |
Project area / Commencement of construction |
N/A |
Project Proponent / Contractor |
Project Proponent / Contractor |
LMM3 |
Preservation of existing tree to be retain
on area not affected by the proposed development. |
Conservation of existing
trees; Visual screen |
Project area not affected
with tree surgery works /
Commencement of construction |
Comply to ETWB TCW No. 3/2006 |
Project Proponent / Contractor |
LCSD* |
LMM4 |
Demarcation of the tree protection zone for retain trees |
Preservation of existing trees |
Project area / Commencement of construction and throughout construction
period |
Comply to ETWB TCW No. 3/2006 |
Project Proponent / Contractor |
Project Proponent
/ Contractor |
LMM5 |
Minimization of the construction works in the existing stream |
Preservation of existing landscape resources and landscape character |
Project area / Commencement of construction and throughout construction
period |
Comply to ETWB TCW No. 5/2005 |
Project Proponent / Contractor |
Project Proponent / Contractor |
LMM6 |
Soil conservation – conservation of
existing and imported soil resources.
|
Conservation of existing
topsoil |
Project area not affected for
stockpile / Commencement of
construction and throughout construction period. |
Existing soil resources on site will be conserved in
stockpiles with a maximum height of 2 m.
All material stockpiles should be covered with an impermeable material
and sandbagging diversions should also be placed around exposed soil. Material stockpiled should be in area
with the least obstruction to pedestrian. |
Project Proponent / Contractor |
Project Proponent / Contractor |
LMM7 |
Operational time restrictions to limit after dark
welding and lighting. |
Limit night time glare |
Project area / Throughout the construction period |
N/A |
Project Proponent / Contractor |
Project Proponent / Contractor |
LMM8 |
Selection of fast growing native trees and shrubs mix
in compensation for the removal / disturbance area. Planting will be planted along the
channel bunds as landscape treatment to screen the built element and mitigate
the landscape and visual impact.
The combination of natives trees and shrubs mix will provide a more
diverse edge effect and break up the overall visual dominance. |
Visual screen; Landscape
compensation |
Project area / Construction
period |
Selection and agree on the
specified plant species |
Project Proponent / Contractor |
LCSD* |
LMM9 |
Preservation of existing stream and pond not affected by the
development. |
Preservation of Landscape resources and character |
Section of existing stream and pond not affected
by the project / Throughout the construction period and operation period |
Comply to ETWB TCW No. 5/2005 |
Project Proponent / Contractor |
DSD (for area within DSD Boundary)* |
LMM10 |
Provide sensitive treatment and design to the external finish of the
channel walls such as adopting the use of natural materials and planting to
soften surface of built structures |
Visual enhancement |
Commencement of construction and throughout the construction period |
N/A |
Project Proponent / Contractor |
DSD* |
LMM11 |
Maintenance of
planting works upon completion. |
Landscape compensation |
Operation period |
Agree on the maintenance
requirement and programme Comply to ETWB TCW No.2/2004 |
Project Proponent / Contractor |
Contractor (for the establishment period after
construction); DSD and LCSD* |
LMM12 |
Compensation planting of mangrove to stream bed |
Landscape compensation |
Operation period |
Agree on the maintenance requirement and programme Comply to ETWB TCW No.2/2004 |
Project Proponent / Contractor |
Contractor (for the establishment period) No long term maintenance necessary |
* The project proponent (CEDD) will
assume to be responsible for the mitigation measures until an agreement is
reached between CEDD and relevant parties on the management and maintenance of
the mitigation measures.