4.1
Waste
management issues associated with the Project will be related to the demolition
of existing crematorium as well as the construction and operation of the new crematorium.
This section identifies the possible waste arisings from the Project, evaluates
the potential environmental impacts associated with the handling, collection,
treatment, transportation and disposal of waste and recommends appropriate
mitigation measures and good site practice to minimize the identified environmental
impacts.
Environmental
Legislation, Policies, Plans, Standards and Criteria
Environmental Legislation
4.2
Annexes
7 and 15 of the Technical Memorandum on Environmental Impact Assessment Process
correspondingly sets out the Criteria and Guidelines for evaluating and
assessing the Waste Management Implications arising from the Project.
4.3
The
following legislations cover the handling, treatment and disposal of waste in
the Hong Kong Special Administration Region (HKSAR), and have been considered
in the assessment.
·
Waste
Disposal Ordinance (Cap. 354) and subsidiary Regulations;
·
Land
(Miscellaneous Provisions) Ordinance (Cap. 28); and
·
Public
Health and Municipal Services Ordinance (Cap.132)
Environmental
Guideline
4.4 Other guideline documents that detail how the contractor should comply with the regulations are as follows:
·
A
Guide to the Registration of Chemical Waste Producers, Environmental Protection
Department,
·
A
Guide to the Chemical Waste Control Scheme, Environmental Protection Department,
·
Ch9
Environment (2007), Hong Kong Planning and Standards Guidelines,
·
Code
of Practice on Packaging, Labelling and Storage of Chemical Wastes (1992),
Environmental Protection Department;
·
Code
of Practice on the Handling, Transportation and Disposal of Asbestos Waste
(1993) Environmental Protection Department;
·
Code
of Practice on Asbestos Control: Asbestos Work Using Full Containment or Mini
Containment Method (1997) Environmental Protection Department;
·
Code
of Practice on Asbestos Control: Asbestos Work Using Glove Bag Method;
·
Code
of Practice on Asbestos Control: Safe Handling of Low Risk Asbestos Containing
Materials (1997) Environmental Protection Department;
·
Code
of Practice on Asbestos Control: Preparation of Asbestos Investigation Report,
Asbestos Management Plan and Asbestos Abatement Plan (1997) Environmental
Protection Department;
·
ProPECC
PN2/97 Handling of Asbestos Containing Materials in Buildings;
·
Guidance
Note for Contaminated Land Assessment and Remediation (2007) Environmental
Protection Department;
·
Works
Branch Technical Circular 32/92, The Use of Tropical Hard Wood on Construction
Sites; Works Branch,
·
Works
Branch Technical Circular No. 2/93, Public Dumps;
·
Works
Branch Technical Circular No. 2/93B, Public Filling Facilities
·
Works
Branch Technical Circular No.16/96, Wet Soil in Public Dumps;
·
Works
Bureau Technical Circular No.4/98 & 4/98A, Use of Public Fill in
Reclamation and Earth Filling Projects;
·
Works
Branch Technical Circular No. 19/2001, Metallic Site Hoardings and Signboards;
·
Works
Bureau Technical Circular No.33/2002, Management of Construction / Demolition
Materials including Rock;
·
Works
Bureau Technical Circular No.31/2004, Trip-ticket System for Disposal of
Construction and Demolition Materials; and
·
Works
Bureau Technical Circular No.19/2005, Environmental Management on Construction
Sites.
4.5 The project site is the site of the existing Cape Collinson Crematorium which consists of twelve cremators with four service halls. According to current available information, it was first put to use in 1962 with several alterations and development hereafter.
4.6
Cape
Collinson Crematorium is located at
4.7 The new crematorium will be constructed in two phases. Site formation work will be carried out at the beginning of Phase 1. After the site formation has been completed, a new crematorium with 4 cremators and 2 service halls will be constructed to the north of the existing crematorium. During this period, all the 12 cremators in the existing crematorium will remain in operation until the satisfactory commissioning of the new cremators under Phase 1 by 2012.
4.8 After the satisfactory commissioning of the new cremators under Phase 1, demolition of the existing crematorium as well as the construction of another 6 cremators and 1 service hall will then be carried out in Phase 2. The total installed capacity of 4 cremators in Phase 1 and 6 cremators in Phase 2 will be approximately 583 kg/hour and 943 kg/hour, respectively.
4.9
The
assessment of waste management impacts arising from this Project during
construction phase and operation phase is made in accordance with the EIA Study
Brief and criteria given in Annexes 7 and 15 of the EIA Technical Memorandum.
4.10
Waste
generation reduction methods have been assessed based upon the following:
·
Avoiding
or minimizing waste generation through out the design stage;
·
Segregation
of waste materials would be promoted and consider as better management
practices;
·
Reuse
and recycling; and
·
Waste
diversion to public fill or other construction site
4.11
Types
and quantities of waste have been estimated and disposal options have been identified.
Estimation of existing and future capacities of waste disposal facilities and
the environmental implication on handling, collection and disposal of waste
materials have also been taken into
account.
4.12
The
assessment includes:
·
Construction
and Demolition phase waste generation analysis
-
Excavated
materials and Construction & Demolition (C&D) materials from site formation
-
Contaminated
materials
-
Chemical
waste from plants and equipment maintenance
-
General
waste from daily activities
·
Operation
phase waste generation analysis
-
Waste
generation from cremation process
-
Waste
generation from maintenance of plant and equipment
-
General
waste from daily activities
·
Proposals
on waste management during construction and operation phases for respective
sources of waste in terms of:
-
Reduction,
reuse and recycling
-
Disposal
options
-
Impacts
and mitigation measures
-
·
Impacts
caused by handling, collection and disposal of waste, in terms of
-
Potential
hazards
-
Air
and odour emissions
-
Noise
-
Wastewater
discharge
-
Public
transport
Identification of Environmental Impacts
Activities and Waste Generation for
Construction and Demolition Phase
4.13
Based
on the tentative construction and demolition programme, construction site activities
will be divided into two phases: Phase 1 – July 2010 to March 2012 and Phase 2
– March 2012 to December 2014. Due to high demand for cremation service, all
the twelve cremators in the existing crematorium will remain in operation
during the construction of Phase 1 until full operation of four new cremators
with total capacity of 583 kg/hour and other main facilities to be provided
under Phase 1 of the Project.
4.14
The
following types of waste will be generated from the construction and / or
demolition works during Phase 1 and Phase 2:
· Phase 1
-
Excavated
materials;
-
Construction
and demolition (C&D) waste materials;
-
Chemical
waste; and
-
General
refuse
· Phase 2
-
Excavated
materials;
-
Construction
and demolition (C&D) waste materials;
-
Contaminated
materials including ash waste, building structure and contaminated soil;
-
Chemical
waste; and
-
General
refuse
4.15
Waste
from construction and demolition phase may cause environmental impact and
nuisance if handling and disposal methods are not properly managed. The
potential impacts and the mitigation measures have been discussed and proposed
in Sections 4.18 to 4.47 and Sections 4.58 to 4.85, respectively.
Activities and Waste Generation for Operation
Phase
4.16
During
the operation phase of the new crematorium, major types of waste to be
generated are as follows
·
Bone Ash and non-combustible residues
generated by cremators during the combustion process of the cremators;
·
Chemical waste generated from plant,
equipment and machinery maintenance and servicing;
·
Fly ash generated from the air pollution
system; and
·
General refuse generated by the visitors and
staff during daily operation.
4.17
Potential
impacts and mitigation measures have been discussed and proposed in Sections 4.48
to 4.57 and Sections 4.86 to 4.103, respectively.
Prediction and Evaluation of Environmental
Impacts for Construction and Demolition Phase
Excavated Materials from Phases 1
and 2
4.18
For
construction works during two phases, excavated materials will be generated from
site formation and foundation works for new crematorium. As advised by ArchSD, approximately
14,300m3 and 27,000m3 of excavated materials will be
generated from Phase 1 and Phase 2, respectively. The excavated materials to be reused on site are
estimated to be 720m3 and 1,350m3
for Phase 1 and Phase 2 respectively.
4.19
With
careful planning for reusing excavated materials on site, secondary
environmental impacts and potential impacts on waste handling is expected to be
minimal.
Construction and Demolition
(C&D) Materials from Phases 1 and 2
4.20
C&D
materials can be divided into two portions, namely inert materials portion such
as rock, concrete which can be used as fill materials and also non-inert
materials portion including timber, glass, steel and plastic is termed C&D
waste. Some C&D waste can be reused or recycled prior to disposal at
landfill site.
4.21
During
Phases 1 and 2, the following C&D materials will be generated:
·
Timber
from formwork and falsework;
·
Existing
crematorium structure from Phase 2 such as concrete, rock, steel, bricks,
glass, wood and plastic;
·
Materials
and equipment wrappings;
·
Unusable
/ surplus concrete or grouting mixes
4.22
According
to the information provided by ArchSD, approximately 15,830m3 and 42,440m3
of C&D materials will be generated from Phase 1 and Phase 2, respectively. A more detailed account of C&D material
generation will be provided in the Waste Management Plan to be prepared by the
Contractor.
4.23
As
advised by ArchSD, the quantities of C&D materials to be reused, delivered
to public fill and disposed of at landfill have been estimated as shown in Table 4.1.
Table 4.1 Estimated Quantity of C&D materials to be Generated, Reused and Disposed Of
|
Estimated Quantity of C&D Materials (m3) |
|
|
Phase 1 |
Phase 2 |
C&D Materials Generated |
1,530 |
15,440 |
Reuse on Site |
0 |
580 |
Deliver to Public Fill |
720 |
12,850 |
Dispose of at Landfill |
810 |
2,010 |
4.24
The
project proponent would obtain an advance agreement from the Public Fill
Committee to ensure the availability and capacity of public fill facility for
disposal of the anticipated amount of C&D materials.
4.25
Provided
that waste management practices as detailed in Sections 4.58 to 4.66 are
properly implemented, the secondary environmental impacts arising from on-site
handling of the C&D materials would be minimal.
Contaminated Materials from Phase 2
4.26
According
to the construction schedule, all twelve cremators in the existing crematorium
would remain in operation and no demolition works will be carried out during Phase
1.
4.27
Also,
based on the findings from Asbestos Investigation Report (April 2008) and
Contaminated Assessment Plan (March 2008), all identified asbestos containing
materials are located in the existing crematorium building and no heavy metals
and dioxin containing surface soil was found in Phase 1 works area. Under this
consideration, no contaminated materials is anticipated during the Phase 1 construction.
4.28
Contaminated
materials are expected to be generated during Phase 2 construction and
demolition works. The key types of contaminated materials will include:
·
Asbestos
containing materials (ACM) – likely from existing building structure;
·
Dioxin
containing materials (DCM) – likely from ash waste and contaminated subsurface
soil;
·
Potential
Contaminated Soil.[1]
4.29
All
the above contaminated materials are classified as chemical waste under the
Waste Disposal (Chemical Waste)(General) Regulation. Asbestos is classified as
a special waste.
4.30
The
contaminated materials are expected to be accumulated around cremators, flues
and chimneys. Since the existing crematorium is in operation and these areas
are not accessible, thus no sampling is carried out at this stage.
Asbestos Containing Materials (ACM) from
Phase 2
4.31
According
to the Asbestos Investigation Report (see Appendix 3.3), asbestos
investigation has been carried out at assessable areas of the existing
crematorium by a registered asbestos consultant. The asbestos survey revealed
the presence of ACM. Asbestos gasket (woven) and insulation sheet were
identified during the survey. ACM has not been found in the six columbarium
blocks and car park area.
4.32
External
structure of the crematorium main building and cremator at Hindu Service Hall
were inspected by the survey team. However, all the pipelines concealed inside the
wall were not available for this inspection. Moreover, flange connection was
covered by a metal cover, which was also inaccessible for inspection.
4.33
Re-inspection
of the inaccessible area will be undertaken prior to demolition works. Due to
low friability nature and good condition of ACM, potential hazard is relatively
low which subsequently will not impose health hazard to occupier.
4.34
Environmental
impacts associated with ACM are anticipated to be minimal, provided that the
mitigation measures are implemented.
Dioxin Containing Materials (DCM) from
Demolition of Existing Crematorium during Phase 2
4.35
Since
the cremators are still in operation, it is not possible to carry out site
investigation inside the cremation rooms at this stage. Further site inspection
is recommended to be carried out after decommissioning and prior to the
demolition of the existing crematorium. A
DCM Assessment Plan shall be prepared for EPD endorsement to present detailed
sampling and testing plan. Findings of site investigation and appropriate
remediation methods will be presented in DCM Assessment Report for EPD
endorsement prior to the commencement of any earthworks.
4.36
With
reference to the approved EIA Study for Provision of Cremators at Wo Hop Shek
Crematorium, it is not anticipated that large amount
of contaminated materials will be present, as these materials will only be
found with the residual ash waste inside the cremators, flue and chimneys. Through appropriate handling,
treatment and disposal of contaminated ash waste, the associated environmental
impact is expected to be minimal.
Dioxin Containing Materials (DCM) / Total
Petroleum Hydrocarbon Containing Materials (TPHCM) from Subsurface Soil at Phase
2 Project Site
4.37
The
Contamination Assessment Plan and Contamination Assessment Report / Remediation
Action Plan have been presented in Appendix 5.1 and Appendix 5.2,
respectively.
4.38
Ten
soil samples were collected from four boreholes for contamination assessment
around the underground fuel tank system, while five surface soil samples were
collected for laboratory analysis for surface deposition contamination
assessment. The results indicated that no detectable VOCs or TPHs was reported
and only 1 soil sample (BH-1, 1.5 –
4.39
Further
site investigation underneath the pipeline (TP-1) will be carried out before the
Phase 2 demolition works of the exiting cremators. A supplementary
Contamination Assessment Report will be prepared to present the findings of
further site investigation for EPD’s approval. If contamination is found,
supplementary Remediation Action Plan will be submitted to EPD and all
contaminated soils will be treated prior to the commencement of any
construction works.
4.40
With
appropriate handling, treatment and disposal of contaminated subsurface soil
around existing building structure, the associated environmental impact is
expected to be minimal.
Chemical Waste from Phases 1 and 2
4.41
During
the construction and demolition works, construction plant and equipment will
require regular maintenance and servicing, which will generate chemical waste
such as cleaning fluids, solvents and lubrication oil.
4.42
Chemical
waste is likely to pose serious environmental, health and safety hazards if it
is not properly managed in accordance with the Waste Disposal (Chemical Waste)
(General) Regulation and the Code of Practice on Packaging, Labelling and
Storage of Chemical Waste. These hazards may include:
·
Toxic
effects to workers;
·
Adverse
effects on water quality from spill; and
·
Fire
hazards
4.43
The
majority of chemical waste generated from the construction and demolition works
of the Project is anticipated during Phases 1 and 2. Should any chemical waste
be generated, the Contractor must register with EPD as a chemical waste
producer. These types of waste will be readily accepted for disposal at the
Chemical Waste Treatment Centre (CWTC) at Tsing Yi. A detailed account of
chemical waste generation should be provided by the Contractor during
preparation of the site Waste Management Plan.
4.44
The
potential environmental impacts associated with the storage, handling and
disposal of the chemical waste will be minimal provided that the relevant
mitigation measures in Sections 4.81 to 4.83 are implemented.
General Refuse from Phases 1 and 2
4.45
Generation
of general refuse is anticipated by resident site staff during construction and
demolition phases. General refuse include food waste, plastic bottles,
aluminium cans and waste paper. Storage of general refuse on site will generate
adverse environmental impacts. These include water quality (if waste enters
nearby water bodies) contamination; odour nuisance and visual impact if waste
is stored on site without frequent collection for disposal. The site may also
attract pests and vermin if waste storage areas are not well maintained and
cleaned up regularly. The amount of general refuse generated by the site staffs
during construction and demolition activities is expected to be insignificant.
4.46
The
potential environmental impacts will be insignificant provided that the mitigation
measures and good site practices in Sections 4.84 to 4.85 are implemented.
4.47
Table 4.2
provides a summary of the various waste types likely to be generated from construction
and demolition works during Phase 1 and Phase 2 for the Project, together with
the recommended disposal methods.
Table 4.2 (1) Summary of Recommended Disposal Routes from C&D Works During Phase 1 and Phase 2
|
Waste Material Type |
Generated from works item |
Total Quantity Generated |
Quantity to be disposed of |
Recommended Disposal Outlets |
Phase 1 |
Excavated materials |
Formation and foundation works |
14,300m3 |
720m3 |
Reuse on site as far as practicable |
|
|
|
13,580m3 |
Public fill reception facility |
|
C&D materials |
|
1,530m3 |
720m3 |
Reuse and recycle as much as possible before
disposal at public fill reception facility |
|
810m3 |
Reuse and recycle as much as possible before
disposal at landfill |
||||
Chemical waste |
Cleaning fluids, solvents and lubrication oil |
Small |
Small |
Recycle by licensed facility or disposal at
CWTC |
|
General refuse |
Resident site staff (food waste, plastic
bottles, aluminium cans and waste paper) |
Insignificant |
Insignificant |
Reuse or recycle as much as possible before
disposal at landfill |
|
Phase 2 |
Excavated materials |
Formation and foundation works |
27,000m3 |
1,350m3 |
Reuse on site as far as practicable |
|
|
|
25,650m3 |
Public fill reception facility |
|
C&D materials |
|
15,440m3 |
12,850m3 |
Reuse and recycle as much as possible before
disposal at public fill reception facility |
|
2,010m3 |
Reuse and recycle as much as possible before
disposal at landfill |
||||
580m3 |
Reuse on site as far as practicable |
||||
ACM2 |
Demolition |
- |
- |
Follow the code of Practice on the Handling,
Transportation and Disposal of Asbestos to dispose of at landfill |
|
DCM (2) (Low contaminated) |
Demolition |
- |
- |
Disposal at landfill |
|
DCM (2) (Moderately contaminated) |
Demolition |
- |
- |
Disposal at landfill with CWTC as fallback
option |
|
DCM (2) (Severely contaminated) |
Demolition |
- |
- |
Disposal at CWTC where it will be incinerated
and the residue will be disposed of at landfill |
|
DCM/TPHCM containing subsurface soil (2) |
Demolition |
- |
- |
Disposal at landfill with CWTC as fallback
option |
|
Chemical waste |
Cleaning fluids, solvents and lubrication oil |
Small |
Small |
Recycle by licensed facility or disposal at
CWTC |
|
General refuse
|
Resident site staff (food waste, plastic
bottles, aluminium cans and waste paper) |
Insignificant |
Insignificant |
Reuse or recycle as much as possible before
disposal at landfill |
Note 1: Prior to the wastes
(shown in Table 4.2) can be properly disposed of in future, Project Proponent
or their representatives are still required to demonstrate all their proposed
disposal outlets can fulfill the specific requirements to be given by the
relevant reception authorities e.g CWTC or Landfill Authority, etc.
Note 2: Since the existing
crematorium is still under operation, the respective estimated volumes for ACM,,DCM
and DCM/TPHCM containing subsurface soil will be determined once the plant is
decommissioned.
Prediction
and Evaluation of Environmental Impacts for Operation Phase
Bone Ash and Non-combustible
Residues from Operation Phase
4.48
Remains
after cremation include bone ash and non-combustible residues. According to the
information provided by FEHD, the average weights of bone ash and
non-combustible residues after each cremation are about 1.6kg and 2.0kg, respectively.
Estimated quantities are provided in Table 4.3 and the maximum
generation of bone ash and non-combustible residues per day are 233.6kg and
292kg, respectively.
Table 4.3 Maximum Quantity of Bone Ash and Non-combustible Residues
Number of Cremators |
No. of Cremations per day |
Bone Ash, 1.6kg per
Cremation (kg/day) |
Non-combustible 2kg per Cremation (kg/day) |
10 |
14.6 |
233.6 |
292.0 |
4.49
Bone
ash is stored in covered container to be collected by the deceased’s relatives
within 2 months and non-combustible residues is collected in polyethylene bags
and disposed of at landfill. Therefore, only small quantity of waste will
require disposal.
4.50
The
associated environmental impacts will be minimal provided that the mitigation
measures in Sections 4.86 to 4.87 are implemented.
Chemical Waste from Operation Phase
4.51
A
small amount of chemical waste in the form of cleaning fluids, solvents,
lubrication oil and fuel would be generated during regular maintenance and
servicing of transformer, switch room and hydraulic lifts.
4.52
Chemical
waste is likely to pose a serious environmental, health and safety hazard if it
is not properly managed in accordance with the Waste Disposal (Chemical
Waste)(General) Regulation and the Code of Practice on Packaging, Labelling and
Storage of Chemical Wastes.
4.53
Should
any chemical waste be generated, the Operator must register with EPD as a
chemical waste producer. The chemical wastes will be readily accepted for disposal
at the Chemical Waste Treatment Centre (CWTC) at Tsing Yi. These chemical
wastes should be collected in drum-type containers by licensed chemical waste
collector periodically. With proper storage, handling and disposal of small
amount chemical waste, adverse environmental impacts are not anticipated.
Fly Ash from Operation Phase
4.54
Fly
ash consists of used activated carbon, un-reacted lime and collected
particulate matter, it solidifies while suspended in the exhaust gases and is
collected by electrostatic precipitators or filter bags, which form part of the
Air Pollution Control (APC) equipment.
4.55
According
to the information provided by FEHD, the estimated volume of particulate matter
is 76 kg per day and activated carbon / un-reacted lime is 18 kg per day.
General Refuse from Operation Phase
4.56
Quantity
of general refuse generated by visitors and staff during daily operation of the
new crematorium will not be substantial with the proper waste management
facilities. It is expected that the potential environmental impacts arising
from the handling and disposal of the general refuse will be negligible and
will not cause any major environmental concerns.
4.57
Table 4.4 provides
a summary of the various waste types likely to be generated during Operation
Phase for the Project, together with the recommended disposal methods.
Table 4.4 Summary of Recommended Disposal Routes During Operation Phase
Waste Material Type |
Generated from works item |
Total Quantity Generated |
Quantity to be disposed of |
Recommended Disposal Outlets |
Bone Ash |
During combustion process of
cremation |
233.6 kg/day |
|
Stored in covered container to be
collected by the deceased’s relatives |
Non-combustible
residues |
During combustion process of
cremation |
292.0 kg/day |
Small |
Collected in polyethylene bags and
disposal of at landfill |
Chemical
waste |
From plant, equipment and
machinery maintenance and servicing |
Small |
Small |
Recycle at licensed facility or
disposal at CWTC |
Fly ash |
During combustion process of
cremation |
76kg/day (Particulate matter); 18kg/day (Activated carbon/un-reacted lime) |
|
Store the fly ash in sealed drums
which are taken to CWTC for further treatment and the residue will be
disposed of at landfill |
General
refuse |
Visitors and staff |
Small |
Small |
Reuse and recycle as much as
possible before disposal at landfill |
Mitigation of Adverse Environmental Impacts for Construction and
Demolition Phase
General – Good Site Practice and Waste
Reduction Measures
4.58
Adverse
environmental impacts due to waste generation are not expected. The following
recommendations should be implemented during the construction activities:
·
Obtain
relevant waste disposal permits from the appropriate authorities, in accordance
with the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Chemical
Waste)(General) Regulation (Cap. 354), Waste Disposal (Charges for Disposal of
Construction Waste) Regulation (Cap 345) and the Land (Miscellaneous Provision)
Ordinance (Cap.28)
·
Prepare
a Waste Management Plan approved by the Engineer / Supervising Officer of the
Project based on current best practice on Construction Sites
·
Waste
licensed collector to collect waste
·
Implementation
of trip ticket system with reference to ETWB(W) No.31/2004 Trip Ticket System
for Disposal of Construction & Demolition Materials.
·
Provide
staff training for proper waste management and chemical waste handling
procedures
·
Separation
of chemical waste for special handling and dispose to licensed facility for
treatment
·
Sufficient
waste disposal points and regular collection programme setup
·
Recording
system for waste generation, recycle and disposal
4.59
The
ETWB TCW No.19/2005 “Environmental Management on Construction” includes
procedures on waste management requiring contractors to reduce the C&D material
to be disposed of during the course of construction. Under this ETWB TCW
No.19/2005, the Contractor is required to prepare and implement an
Environmental Management Plan (EMP) and the Waste Management Plan (WMP) becomes
part of the EMP.
4.60
Waste
reduction should be considered in planning and design stage, the following practice
should be implemented.
·
Prior
to disposal of C&D waste, wood, steel and other materials should be separated
for reuse, recycling to minimize the quality of waste to be disposed of at
landfill.
·
Minimize
use of wood and reuse non-timber formwork to reduce C&D waste
·
As
far as practicable, segregate and store different types of waste in different
containers, skips or stockpiles to enhance reuse or recycling of materials and
their proper disposal.
·
Encourage
collection of aluminum cans, plastic bottles and packaging material and office
paper.
Excavated Materials
4.61
Rock
and soil generated from excavation should be reused during site formation and
landscaping as far as practicable to reduce total amount to be disposed of off-site.
4.62
Trip-ticket
system should be implemented for surplus excavated materials disposal in
accordance with ETWB TC(W) No.31/2004 and the Construction Waste Disposal
Charging Scheme. Waste should be delivered to a public fill reception facility.
Copies or counterfoils of trip tickets will be kept for record purpose.
Construction and Demolition Materials
4.63
Well-planned
design and good site management can minimize over-loading and generation of
waste materials such as concrete and cement grouts. Wooden frame should be
replaced by metals. Plastic fencing and reusable site office structure can
reduce C&D waste generation.
4.64
The
Contractor should recycle as much C&D materials as possible. Proper
segregation of waste types on site to enhance reuse and recycling of materials.
Designated areas for different materials storage should be assigned for
segregation.
4.65
Under
the Construction Waste Disposal Charging Scheme, construction waste producers
such as construction and renovation contractors and premises owners, prior using
government waste disposal facilities, need to prepare a billing account with
EPD and pay for construction waste disposal.
4.66
It
is expected that trip-ticket system will be implemented for surplus C&D materials
disposal in accordance with ETWB TC(W) No.31/2004 and the Construction Waste
Disposal Charging Scheme. Waste should be delivered to a public fill reception
facility. Copies or counterfoils of trip tickets will be kept for record
purpose.
Contaminated Materials
4.67
Since
all twelve cremators in the existing crematorium will remain in operation during
Phase 1 and demolition works will be carried out during Phase 2, contaminated
material will only be generated during the Phase 2 construction and demolition
works.
Specific Plan for Contaminated Materials arising
from Demolition Works
4.68
Building
structure of cremators, flues and chimneys would likely to be contaminated by
DCM ash due to long term servicing. As the cremators are still in operation, it
is not possible to carry out site investigation in the areas of cremators,
flues and chimneys at this stage. To maintain uninterrupted cremation services,
further site investigation in cremation rooms and associated equipments are
proposed to undertake after decommissioning and prior to demolition of the
existing crematorium.
4.69
According
to the asbestos investigation report, asbestos gasket (woven) and insulation
sheet were identified with ACM. It is also not possible to inspect all
potential asbestos containing material locations due to on-going operation of
cremators, concealed pipeline inside wall and metal cover of flange connection.
Further inspection of the inaccessible locations will be undertaken after
decommissioning and prior to demolition of the existing crematorium.
4.70
Under this consideration, contaminated ash and ACM potential
contamination locations will be further identified. In view of close distance
between the contaminated ash and ACM, there is a concern on contaminated ash
wastes being embedded in ACM. Therefore, it is advisable to remove contaminated
ash waste prior to any asbestos containing material on building structures.
This is considered as the worst case scenario in this assessment.
4.71
Should contaminated ash is identified on the ACM, the contaminated ash
will be removed first prior to removal of ACM. If the procedures and
precautionary measures described in Section 4.75 to 4.78 are followed properly,
cross contamination could be minimized under normal circumstances. These
procedures and measures are considered as reasonable approach to handle the
cross contaminated wastes.
4.72
Asbestos
waste will be handled in accordance with the Code of practice on the Handling,
Transportation and Disposal of Asbestos Waste issued by the Environment Bureau.
4.73
Production,
collection and disposal of asbestos waste will follow the “trip-ticket” system.
The registered asbestos contractor will appoint a licensed asbestos waste
collector to collect the packaged asbestos waste and deliver to the designated
landfill for disposal. Notification has to be given to EPD for its disposal. EPD
will normally require ten working days notice of the intention to dispose of any
quantity of asbestos waste. After processing the notification, EPD will issue
specific instructions and directions for disposal of the waste. The waste
producer or his agent must strictly follow these directions.
4.74
Different
contamination classifications based on the dioxin level in ash waste are
proposed in Table 4.5 and
corresponding mitigation measures are also described:
Table 4.5 Proposed Contamination Classifications for Ash Waste
Classification of Contamination |
Dioxin Level in Ash Waste |
Low
Contaminated DCM |
<1ppb
TEQ |
Moderately
Contaminated DCM |
>1
and <10 ppb TEQ |
Severely
Contaminated DCM |
>10ppb
TEQ |
4.75
Where
the ash waste contains low contamination levels of DCM, the Contractor should
avoid ash waste becoming airborne during demolition. General dust suppression
measures will be followed and ash waste will be directly disposed of at
landfill.
4.76
Where
the ash waste contains moderately contaminated DCM, the following steps should
be followed:
·
Site Preparation
- Except
the cremators / flue / chimney, all removable items should be removed as far as
practicable to avoid obstructing the decontamination activities;
- Preliminary
site decontamination of all debris should be carried out using High Efficiency
Particulate Air (HEPA) vacuum cleaner;
- Top
portion of the chimney should be enclosed by a 3-layer chamber of polyethene
sheets;
- At
the entrance to the cremators / flues / chimney, a 3-chamber decontamination
unit should be constructed for entry and exit from the work area. The 3-chamber
decontamination unit should comprise a dirty room, a shower room and a clean
room of at least 1m x 1m base with 3-layer of fire retardant polyethylene
sheet;
- Workers
should carry out decontamination procedure before leaving the work area;
- Workers
should wear full protective equipment, nitrile gloves, robber boots and
full-face positive pressure respirator; and
- Warning
signs in both Chinese and English should be displayed in conspicuous areas.
·
Demolition and Handling
- The
cremators / flue / chimney should be removed from top down. Any ash or residues
attached to the cremators / flue / chimney or any other building structure
should be removed by scrubbing and HEPA vacuuming;
- Waste
generated from the containment or decontamination unit including the protection
clothing of the workers should be disposed to landfill;
- After
removal, all surfaces should be decontaminated by HEPA vacuum cleaner; and
- The
storage area for ash waste should be properly enclosed throughout the
demolition works. The location of storage area for ash waste will be identified
in the Waste Management Plan to be prepared by the Contractor.
·
Treatment and Disposal
- Immobilise
ash waste by proper mixing with cement as determined by the pilot mixing and
Toxicity Characteristic Leaching Procedure (TCLP);
- Waste
material should be placed in polyethylene lined steel drums for disposal at
landfill, the drums should be 16 gauge steel or thicker and fitted with double
bung fixed ends adequately sealed and well labeled in new or good condition.
- Drums
should be clearly marked “DANGEROUS CHEMICAL WASTE” in English and Chinese.
Prior agreement of the disposal criteria must be obtained from EPD and the
landfill operator.
- As
a fall back option, if landfill disposal criteria cannot be met after
immobilization of the ash waste, disposal at the Chemical Waste Treatment
Center (CWTC) should be considered.
4.77
The
areas with severely contaminated DCM should be removed under containment as a
prudent approach to avoid the release of ash waste to the environment during the
demolition works of the existing building and the following should be addressed.
·
Site
Preparation
- Except
the cremators / flue / chimney, all identified removable items with severely
contaminated DCM should be removed as far as practicable to avoid obstructing
the decontamination activities;
- Preliminary
site decontamination of all debris should be carried out using High Efficiency
Particulate Air (HEPA) vacuum cleaner;
- The
walls, floor and ceiling of the cremator room where severely contaminated DCM
should be lined with 3-layer chamber of fire retardant polyethene sheets. Top
portion of the chimney above the roof should be enclosed by a 3-layer chamber
of polyethene sheets;
- At
the entrance to the cremators / flues / chimney, a 3-chamber decontamination
unit should be constructed for entry and exit from the work area. The 3-chamber
decontamination unit should comprise a dirty room, a shower room and a clean
room of at least 1m x 1m base with 3-layer of fire retardant polyethylene sheet
where all workers would carry out decontamination procedures before leaving the
work area;
- Air
movers should be installed at the cremator room, and at the bottom of the
chimney to exhaust air from work area. A stand-by air mover should be installed
with each of air movers. Sufficient air movement should be maintained to give a
minimum of 6 air changes per hour to the work area;
- New
pre-filters and HEPA filters should be used on the air movers.
- Before
commencement of the decommissioning work, a smoke test with non-toxic smoke
should be carried out to confirm the air tightness of the containment;
- Workers
should wear full protective equipment, disposable protective coverall (such as
Tyvek with shoe covers and hood), nitrile gloves, rubber boots and full-face
positive pressure respirator equipped with a combination cartridge that filters
particulate and removes organic vapour; and
- Warning
signs in both Chinese and English should be displayed in conspicuous areas.
·
Decontamination,
Demolition and Handling
- The
cremators / flue / chimney should be removed from top down. Any ash or residues
attached to the cremators / flue / chimney or any other building structure
should be removed by scrubbing and HEPA vacuuming;
- The
contaminated detached sections of the building structure with severely
contaminated DCM should be wrapped with 2 layers of fire retardant polyethene
sheets. The third layer should be wrapped and secured with duct tape.
Decontaminate the outer layer of the wrapped flue sections by wet wiping;
- After
completion of removal and decontamination, spray the innermost layer of the fire
retardant polyethene sheet with PVA. Upon drying, peel off and dispose of at landfill
site; and
- The
storage area for ash waste should be properly enclosed throughout the
demolition works. The location of storage area for ash waste will be identified
in the Waste Management Plan to be prepared by the Contractor.
·
Treatment and Disposal
- All
contaminated ash waste with severely contaminated DCM removed and the used HEPA
filters should be sent to Chemical Waste Treatment Center (CWTC) at Tsing Yi
accordingly to Chapters
2 & 3 Code of Practice on the Packaging, Labelling & Storage of Chemical
Wastes published under the Waste Disposal Ordinance (Cap 354), Section 35; and
- Other
waste including the building structures and its associated panels as well as
waste generated from this decommissioning works are also considered as
contaminated waste and should be disposed of at designated landfill. Waste
generated from this decommissioning works refer to the polyethene wrapping
sheets should be placed into appropriate containers for disposal. Waste
Disposal Permit has to be obtained from EPD. Disposal trip ticket is required
to be made available as record after disposal.
4.78
Further
investigation and confirmatory test for ash waste in cremator, chimney and flues
should be carried out on DCM prior to the demolition works of the existing
building. The sampling and analysis plan should be prepared and submitted to
EPD for approval.
4.79
The
principles as stated in Section 4.75 to 4.78 aim to address the detailed measures
of avoiding cross contamination of DCM and ACM and should form part of the DCM Assessment
Report which will be submitted to EPD for approval before the commencement of
the demolition of the existing crematorium.
4.80
Contaminated
Soil:
·
According to the Contamination Assessment
Report (CAR) and Remediation Action Plan (RAP) provide in Appendix 5.2, among five 0.1m samples analyzed, no surface soil
samples were found to have testing parameters exceeding the relevant Risk-Based
Remediation Goals (RBRGs).
·
In additional, further investigations and
confirmatory test should be carried out to determine if additional remediation
(in addition to the current RAP) is required.
Chemical Waste
4.81
All
the chemical waste should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes. The chemical waste should be stored and collected by a licensed
contractor for disposal at licensed facility in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation. Containers used for the storage of chemical waste should be:
·
Suitable
for substance holding, resistant to corrosion, maintained in good condition and
securely closed;
·
Capacity
of less than 450 liters unless the specifications have been approved by the EPD;
and
·
Display
a label in English and Chinese in accordance with instructions prescribed in
Schedule 2 of the Waste Disposal
(Chemical Waste) (General) Regulation.
4.82
The
storage area for chemical waste should:
·
Be
clearly labeled and used solely for the storage of chemical waste;
·
Be
enclosed on at least 3 sides;
·
Have
an impermeable floor and bunding, of capacity to accommodate 110% of the volume
of the largest container or 20% by volume of the chemical waste stored in that
area, whichever is the greatest;
·
Have
adequate ventilation;
·
Be
covered to prevent rainfall from entering (water collection within the bund
must be tested and disposal as chemical waste if necessary); and
·
Be
properly arranged so that incompatible materials are adequately separated.
4.83
The
chemical waste should be disposed of by:
·
A
licensed waste collector;
·
A
facility licensed to receive chemical waste, such as CWTC at Tsing Yi, which
offers chemical waste collection service and can supply the necessary storage
containers; and
·
A
waste recycling plant as approved by EPD.
General Refuse
4.84
General
refuse should be stored in enclosed bins or compaction units separated from
C&D and chemical wastes. Waste collector should be employed by the
Contractor to minimize odour, pest and litter impacts. Open burning of refuse
on construction site is prohibited by law.
4.85
The
Contractor should carry out an education programme for workers in avoiding,
reducing, reusing and recycling. This should include provision of three-colour
recycling bins and on site and posters and leaflets advising on the use of
recycling bins.
Mitigation
of Adverse Environmental Impacts for Operation Phase
Ash and Non-Combustible
Residues
4.86
The disposal of bone and non-combustible residues
should be properly collected and handled to avoid dust emissions. In line with
the current practices, the bone ash will be stored in covered containers for
collection by the deceased’s relatives within 2 months upon appointment while
the non-combustible residues will be collected in sealed heavy-duty polyethene
bags for disposal at landfill. Potential secondary environmental impacts will
be kept to a minimum.
4.87
Combustion gas temperature, residence time, air supply
and gas turbulence of the new cremators will be properly and adequately
controlled to optimize the effectiveness of combustion during cremation process,
therefore generation of Bone Ash will be expected in low amount.
Chemical Waste
4.88
Chemical
waste generated from the air pollution
system as well as from machinery maintenance and servicing should be managed in
accordance with the Code of Practice on
the Packaging, Labelling and storage of Chemical Wastes under the
provisions of the Waste Disposal (Chemical
Waste)(General) Regulation. The chemical waste should be collected by
drum-type containers and removed by licensed chemical waste contractor.
4.89
Plant
/ equipment maintenance schedules should be planned in order to minimize the
generation of chemical waste.
4.90
Non-recyclable
chemical wastes and lubricants should be disposed at an appropriate facility,
such as EPD Chemical Waste Treatment Centre at Tsing Yi. Copies or counterfoils
from collection receipts issued by the licensed waste collector should be kept
for record purpose.
4.91
Recyclable
chemical waste that is collected will be transported off-site for treatment by
a licensed collector. The Contractor will need to register with EPD as a
chemical waste producer. Where possible, chemical wastes (e.g. waste
lubricants) would be recycled at an appropriate facility, e.g. at Dunwell’s oil
re-refinery.
Fly Ash
4.92
During
the operation phase of the Project, combustion gas temperature, residence time,
air supply and gas turbulence of the new cremators will be properly and
adequately controlled to optimize the effectiveness of combustion during
cremation process, thereby minimizing the generation of fly ash.
4.93
Fly
ash is collected by the APC equipment. This is designed to maximize the
collection of fly ash.
4.94
Disposal
method of fly ash from the cremators should be stored in sealed drums and
placed in a designated area for collection by CWTC. Fully incinerated residues
should be disposed to landfill.
4.95
The
following methods have been considered and assessed for applicability in
treating the fly ash from cremators:
·
Bioremediation:
Using white-rot fungus (Ceriporia sp.)
to degrade dioxins in a trial study. Concerns relate to potential problem of
introducing a biohazard (the fungus) into the surrounding natural ecosystem. No
proven commercial application.
·
Detoxification:
Contacting the contaminated incineration ash with an aqueous solution of an
alkaline earth metal hydroxide at 100°C. A patented process but no proven
commercial application.
·
Thermal
Desorption: Considered feasible as the first stage in separating and
concentration the dioxin from the contaminated soil. However, the residue from
thermal desorption requires treatment. Thermal desorption was used in Hong Kong
to initially treat dioxin-contaminated soil from Penny’s Bay, but the residue
from the process still had to be treated at the CWTC.
·
Base
Catalytic Dechlorination and Gas Phase Chemical Reduction: Have been previously
examined for use in
·
Ultraviolet
Photolysis: This process volatilizes organic compounds from the soil matrix;
collects the desorbed organics in a solvent; and, destroys the contaminants with
high-intensity ultraviolet light. So far only a research project with no proven
commercial application.
·
Solidification:
Generally implies the physical encapsulation of APC residues with cement or
pozzolanic (cement-like) materials to reduce the leaching of constituents.
·
Stabilisation:
Generally defined as the addition of reagents to chemically transform soluble
contaminants into a less soluble form, making use of both the precipitation of
materials in new minerals as well as the binding of materials to minerals by
sorption.
·
Vitrification:
Involves the mixing of residues with glass precursor materials such as high
temperatures (1300 to 1500OC) to form a single-phase amorphous
glassy materials. This results in chemical bonding of inorganic species in the
residues with glass-forming materials and encapsulation of residue constituents
in a layer of glassy materials.
4.96
Of
the above methods, only solidification, stabilization and vitrification are
considered as potentially applicable for operation stage of this Project. The
other methods are either only at the pilot plant / demonstration stage or else
have no proven commercial application. The treatment method previously accepted
for use in
4.97
To
treat fly ash using solidification, stabilization or vitrification processes
will require the construction and operation of substantial infrastructure,
which would not only require the use of reagents and other chemicals (that
themselves can pose an environmental hazard in their use and storage) but which
would also occupy additional space with the Site. Furthermore, the on-site
treatment of fly ash would likely be considered as Designated Project itself,
under Item G.6 of Schedule 2 to the EIAO, and would thus require a separate
Environmental Permit.
4.98
In
conclusion, the use of alternative on-site treatment is not considered to be
feasible, either environmentally, economically and practically; and the
cremation and APC technologies adopted are considered optimal. Instead, it is
proposed that handling of fly ash from the cremators at Cape Collinson
Crematorium follows the established practice at other crematoria in Hong Kong,
i.e.:
·
Fly
ash is collected and stored in sealed drums provided by the CWTC.
·
Sealed
drums are stored in a designated area and are periodically collected by CWTC
(normally two to three weeks interval).
·
Drums
are taken to CWTC where they are incinerated and rendered harmless – this
includes the complete destruction of dioxins.
·
Residues
are then disposed of at landfill.
4.99
This
approach is considered to be environmentally sound, follows established
practice, uses appropriate existing Government waste treatment facilities and
minimizes the environmental impacts at the crematorium site during operational
stage. This approach allows for the safe treatment and disposal of fly ash,
irrespective of the concentration of dioxins or other contaminants in the fly
ash.
General Refuse
4.100
Waste generated in offices should be reduced through
segregation and collection of recyclable waste materials (such as paper). To
promote recycling of waste paper, aluminum cans and plastic bottles, it is
recommended to place clearly labeled recycling bins at designated locations. The
recyclable waste materials should be collected by licensed collectors.
4.101
General refuse, other than segregated recyclable
wastes, should be separated from any chemical waste and stored in covered skips.
FEHD should remove general refuse from the site on daily basis to minimize
odour, pest and litter impacts. Also, open burning of refuse must be strictly
prohibited.
Good Site
Practices and Waste Reduction Measures for Operation Phase
4.102
It is recommended that the
following good operational practices should be adopted to minimise waste
management impacts:
§
Obtain the necessary waste
disposal permits from the appropriate authorities, in accordance with the Waste
Disposal Ordinance (Cap. 354), Waste Disposal (Chemical Waste) (General)
Regulation and the Land (Miscellaneous Provision) Ordinance (Cap. 28);
§
Nomination of an approved
person to be responsible for good site practice, arrangements for collection
and effective disposal to an appropriate facility of all wastes generated at
the site;
§
Use of a waste haulier
licensed to collect specific category of waste;
§
A trip-ticket system should
be included as one of the contractual requirements and implemented by the
Environmental Team to monitor the disposal of C&D and solid wastes at
public filling facilities and landfills, and to control fly tipping. Reference
should be made to ETWB TCW No. 31/2004.
§
Training of site personnel
in proper waste management and chemical waste handling procedures;
§
Separation of chemical
wastes for special handling and appropriate treatment at a licensed facility;
§
Routine cleaning and
maintenance programme for drainage systems, sumps and oil interceptors;
§
Provision of sufficient
waste disposal points and regular collection for disposal;
§
Adoption of appropriate
measures to minimize windblown litter and dust during transportation of waste,
such as covering trucks or transporting wastes in enclosed containers;
§
Implementation of a
recording system for the amount of wastes generated, recycled and disposed of
(including the disposal sites).
4.103
Good management and control
can prevent the generation of significant amounts of waste. It is recommended
that the following good operational practices should be adopted to ensure waste
reduction:
§
Segregation and storage of
different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of materials and their proper disposal;
§
Encourage collection of
aluminium cans, plastic bottles and packaging material (e.g. carton boxes) and
office paper by individual collectors. Separate labelled bins should be
provided to help segregate this waste from other general refuse generated by
the work force;
§
Any unused chemicals or
those with remaining functional capacity should be reused as far as
practicable.
Impacts
Caused by Handling, Collection and Disposal of Waste
Potential Hazard –
Chemical Waste
4.104
Should any chemical waste be generated, the Contractor
must register with EPD as chemical waste producer. All chemical waste will be
handled according to the Code of Practice
on the Packaging, Labelling and Storage of Chemical Wastes. Chemical waste
will be stored and collected by an approved contractor for disposal at a
licensed facility in accordance with the
Waste Disposal (Chemical Waste) (General) Regulation.
4.105
For containers used for storage, requirements for
storage area and disposal method should refer to Sections 4.81 to 4.83 accordingly.
Potential Hazard – Asbestos
4.106
Air Pollution
Control Ordinance requires registered professionals to carry out the
abatement works, while the Waste Disposal
Ordinance provides control on the packaging, labeling, storage, collection
and disposal of asbestos waste. Asbestos waste should be handled in accordance
with the Code of Practice on the
Handling, Transportation and Disposal of Asbestos Waste issued by the Environment
and Food Bureau.
4.107
Asbestos waste is categorized as chemical waste under
the Waste Disposal (Chemical Waste) Regulation. The arrangement of production,
collection and disposal will follow the ‘trip-ticket’ system. The registered
asbestos contractor will appoint a licensed asbestos waste collector to collect
the packaged asbestos waste and deliver it to the designated landfill for disposal.
Potential Hazard – DCM
4.108
Contamination classifications, site preparation
procedures, demolition and handling procedures, treatment and disposal
procedures for different contamination levels of DCM from building structure
and soils have been presented in Sections 4.74 to 4.79.
Air and Odour Emissions
4.109
An air quality assessment for the Project has been presented
in Section 3. Air and odour emissions from the handling, collection and
disposal of waste during construction and demolition phase and operation phase
were discussed. A number of mitigation measures have been recommended. There
would be minimal impact from the handling, collection and disposal of waste in
terms of air and odour.
Noise
4.110
A noise assessment for the Project has been presented
in Section 7. During the construction, demolition and operation phases, no
significant noise impact would be expected from handling, collection and
disposal of waste.
Wastewater Discharge
4.111
Water quality assessment for the Project has been
presented in Section 8. Discharge of wastewater from the Project during the
construction and demolition phase was discussed and a number of mitigation
measures have been recommended. There will be minimal impact from the handling,
collection and disposal of waste.
4.112
During the operation phase of the Project, there will
be no significant wastewater impacts from the handling, collection and disposal
of waste as the proposed APC utilizes a “dry” process and all wastewater meets
WPCO standards for discharge to foul sewer.
Public Transport
4.113
The transportation of all waste material will, in the
immediate vicinity of the site, follow
4.114
According to information provided by ArchSD, the
number of vehicle trips for waste disposal at landfill is estimated to be about
5 trips per day.
4.115
For chemical wastes to be either recycled or disposal
of, the number of trips will depend on the quantity of chemical waste, but is
unlikely to exceed one vehicle trip per week, on average.
4.116
No significant impact on public transport would be
expected from the handling, collection and disposal of waste.
Evaluation
of Residual Impacts
4.117
With the implementation of the recommended mitigation
measures for the handling, transportation and disposal of the identified waste
arisings, no residual impact is expected to arise during the construction and
operation stages of the proposed Project.
Cumulative
Impacts due to Concurrent Projects
4.118
According to the currently available information, no
concurrent projects would be constructed and operated in the vicinity of the
Study Area of the Project.
4.119
Waste management implications of the demolition of existing
crematorium, construction and operation of the new crematorium have been
assessed.
4.120
With effective implementation of the mitigation
measures, it is anticipated that the impacts on the environment and the
potential impacts on the capacity of waste collection, transfer and disposal
facilities will be insignificant.
4.121
Prior to the demolition phase of the existing crematorium,
further contamination investigation should be carried out to confirm quality
and quantity of asbestos and DCM. Asbestos Investigation Report (AIR) should be
prepared by registered asbestos consultant. Samples testing should be carried
out by HOKLAS-accredited laboratory.
Asbestos Abatement Plan (AAP) should be prepared for asbestos
contaminated premises. Supplementary CAP/CAR/RAP should be carried out to
confirm quality and quantity of contaminated soil.
4.122
Ash sampling should be carried out at potential areas
of cremators, chimney and flues. Since the cremators are still in
operation, it is not possible to carry out site investigation at these areas at
this stage. The contaminated ash waste is recommended to be removed prior to any
asbestos containing material in building structures.
[1] Land
contamination issues would be addressed in Chapter 5 – Land Contamination
Assessment where appropriate