5 Land contamination
Introduction
5.1
Contaminated
land refers to the land which has been polluted by hazardous substances as a
result of industrial operations carried out on the site over a number of
years. These contaminants if present,
may pose hazardous risks or cause adverse effects to the land users and the
nearby environment. The implications of
land contamination associated with the Phased Reprovisioning of Cape Collinson
Crematorium (hereinafter known as
“Project”) and its works area (hereinafter called “Study Area”) have been
assessed in accordance with the EIA Study Brief (No. ESB-177/2008) in this
Section.
Environmental Legislation, Policies, Plans
Standards and Criteria
5.2
”Guidance Note for
5.3
Further
consideration of contamination issues is provided in Section 3 (Potential
Contaminated Land Issues) of Annex 19 “Guidelines for Assessment of Impact on
Sites of Cultural Heritage and Other Impacts” of the Technical Memorandum on
Environmental Impact Assessment Process (EIAO-TM).
Risk-based Remediation Goals (RBRGs)
5.4
The
Guidance Note 2 refers the Risk-based Remediation Goals (RBRGs) as the criteria
for land contamination assessment. The “Guidance Manual for Use of Risk–Based
Remediation Goals for Contaminated Land Management” (Guidance Manual) which
promulgated by EPD on 15 August 2007, presents guidance for interpretating soil
and groundwater data in respect to the RBRGs levels developed for post-restoration
land use scenarios.
5.5 The Guidance Manual has referred four different post-restoration land use scenarios, 1) Urban residential, 2) Rural residential, 3) Industrial and 4) Public parks. In accordance with the Guidance Manual Section 3, post-restoration land uses for public utilities shall refer to the RGRBs Industrial land use. Receptors for this land use are those at sites where part of the operation is carried out directly on land and the workers are more likely to be exposed to soil.
Assessment Methodology
5.6
In
accordance with the above guidance notes, desktop study of historical and
current land uses and site appraisal have been conducted to identify any
potential land contamination hotspots in the Study Area. According to the
findings of site appraisal, a Contamination Assessment Plan (CAP) (Appendix 5.1) was prepared and endorsed by EPD on 2 April 2008. A site investigation was carried out subsequently
in accordance with the approved CAP. The
results, findings and recommended remedial works were presented in the
Contamination Assessment Report & Remediation Action Plan (CAR & RAP)
as attached in Appendix 5.2 which has been submitted to EPD for
approval on 23 April 2008.
5.7
Possible
sources of contamination in the new crematorium and precautionary measures for
prevention of future land contamination due to the new operation will also be
identified under this Chapter.
Description of the
Environment
5.8
The
Study Area is located at
5.9
The
Existing Crematorium is bounded to west and south by six columbarium blocks and
Hong Kong Electric substation. Cemeteries and Fung Wah Estate are at the east
and north of the Existing Crematorium respectively.
Site Geology and
Hydrogeology
5.10
According
to the Hong Kong Geological Survey Map (Series: HGM20) – Sheet No. 11 (1:20,000
scale) on the solid and superficial geology of the Study Area, the Study Area
is mainly underlain by Shing Mun Formation, undivided sedimentary and volcanic
rock consisting of tuffite of Upper Jurassic Period of Mesozoic Era.
5.11
A
review of previous ground investigation (GI) reports undertaken at or in
vicinity of the Study Area was conducted at the Civil Engineering and
Development Department’s (CEDD) Geotechnical Information Library to obtain
information about the geological and hydrogeological conditions of the Study Area.
Details of the reviewed GI reports are listed below:
·
Agreement No. CE 9/95 Feature No.
11SE-D/F19 Chai Wan Ground Investigation Factual Fieldwork Report by Bachy Soletanche Group in 1995. (CEDD’s Geotechnical Information
Unit Report No. 21583)
·
Slope No. 11SE-D/R2 Regional Council
Crematorium, Tai Tam Road, H.K. Ground Investigation Factual Fieldwork Report by Bachy Soletanche Group in 1999. (CEDD’s Geotechnical Information
Unit Report No. 30513)
·
Agreement No. CE 10/2004 (GE) 10-Year
Extended LPM Project, Phase 5, Package D – Hong Kong Island Landslip Preventive
Works on Government Slopes and Related Studies – Investigation, Design and
Construction Feature No. 11SE-D/C71 Location: Cape Collinson Crematorium Final
Factual Fieldwork Report by Fugro Geotechnical Services Ltd.
in 2006. (CEDD’s Geotechnical Information Unit Report No. 42859)
5.12
With
reference to the above GI reports, the area close to the Study Area is
generally covered by a layer of fill materials/colluvium (~0.5m to 1.5m in
thickness) composed of sandy SILT and clayey sandy SILT with occasional fine to
medium gravel. It is then followed by a layer (~1.15m to 10.1m in thickness) of
saprolitic soil (in the majority of fine ash vitric TUFF and sandy SILT) before
reaching the lower variable decomposed rock (rock of grade IV with thickness of
~0.4m to 6m). In terms of the likelihood of migration of contaminants, fill
materials (i.e. top soil layer) generally have higher permeability and therefore,
ability of potential contaminant migration through this horizon is higher than
downward migration.
5.13
According
to the general topography of the Study Area and groundwater levels recorded in
some of the reviewed GI reports, elevation of the groundwater level varies from
+153mPD to +110mPD from hillside south to hillside north of the Existing
Crematorium. The general groundwater pattern likely flows from south to north,
i.e. from
Site History
5.14 A review of historical aerial photographs (as shown in Table 5.1) available in the Survey and Mapping Office of Lands Department was undertaken. The aim of this review is to identify the landuses associated with potential contamination implication within or near the Study Area.
Table 5.1 Reviewed Historical Aerial Photographs
Year |
Height (Ft.) |
Photograph Reference No. |
1945 |
20000 |
4062 |
1949 |
8600 |
6063 |
1961 |
30000 |
120 |
1963 |
2700 |
6979 |
1967 |
6250 |
5631 |
1972 |
13000 |
2289 |
1974 |
12500 |
9697 |
1976 |
4000 |
12673 |
1978 |
4000 |
23782 |
1980 |
4000 |
29864 |
1982 |
4000 |
40872 |
1984 |
4000 |
53720 |
1986 |
4000 |
A06043 |
1987 |
4000 |
A10339 |
1989 |
4000 |
A17812 |
1992 |
4000 |
A32626 |
1994 |
4000 |
CN6926 |
1996 |
4000 |
CN14150 |
1998 |
4000 |
CN21101 |
2000 |
4000 |
CN28278 |
2002 |
3500 |
CW39611 |
2004 |
4000 |
CW55553 |
2006 |
4000 |
CW72455 |
2007 |
3000 |
CW77143 |
5.15
As
concluded from the review of aerial photographs, the location of the Existing
Crematorium was an open area until 1962 and residential houses were found in
the location of current Fung Wah Estate. Six columbarium blocks were built
successively from 1970s to 1990s. Tai Tam Gap Correctional Institution at the
southeast of the Existing Crematorium was also built in 1972. Residential
houses were demolished and Fung Wah Estate was built in 1980s. No major land
uses changes of the Study Area and surrounding areas were observed since then.
Identification of Sensitive Receivers
5.16
Construction
workers and crematorium staffs are the most likely group to be exposed to any
potential contaminated material during the construction and operation phases
respectively. During the construction
phase, workers may be exposed to potential contaminated soil when carrying out excavation
and preparation of foundation works.
Depending on the nature of the contaminants, hazard during subsurface
services may be of concern. The
principal exposure routes for workers include:
·
Direct
ingestion of contaminated soils through eating or drinking/smoking on site; and
·
Dermal
contact with contaminated soils.
5.17
Given
that the contaminated soil would have been remediated in the construction
phase, it will unlikely present a residual hazard to the crematorium staffs
during their routine operation & maintenance works.
Identification of Environmental
Impacts
5.18 There were four service halls for carrying out ceremonies, two cremation rooms with twelve cremators and a number of smaller structures such as offices. The New Cape Collinson Garden of Remembrance opened in December 2007, was situated at the west of the Existing Crematorium.
5.19
A capacity of
5.20 Twelve cremators were located in two cremation rooms at the ground floor of the Existing Crematorium. Floors of both cremation rooms were covered by intact ceramic tiles while the cremators were set up on concrete foundation. Diesel fuel was fed to the cremators from the AST via vertical pipelines that ran outside along the wall. The oil pipes ended behind the cremators where their connections were clad in metal plates. Given the limited space and burn hazard from the operating cremator for close inspection, it was unable to access to the pipe joint or coupling where their conditions or any signs of leakage were uncertain. The site PIC from Electrical & Mechanical Services Department (EMSD) expressed that small-scale leakage of fuel from the pipes possibly happened occasionally inside the cremation room. There was no storage of chemicals or dangerous goods were observed and as told by the manager of the Crematorium during site inspection.
5.21 Six chimneys connected to the twelve cremators were located at the top roof of the Existing Crematorium. Some areas around the Existing Crematorium were landscaped with trees and shrubs while other areas were paved with intact concrete. No stain or odour were observed during site inspection. The structural layout is shown in Figure 5.1.
5.22
Site
investigations were conducted at the locations near underground storage tank
system and around chimneys to evaluate any impact to environment. A
contamination assessment report & remediation action plans (CAR & RAP)
have been prepared as attached in Appendix 5.2 to discuss the site investigation
findings including the fieldworks and laboratory analytical results and
recommend appropriate remediation plans for the identified contaminated areas.
5.23
The site investigation (SI)
works were carried out from 15 March to 20 March 2008. Four boreholes and five soil surface sampling locations were proposed at
the hotspots within the Study Area in accordance with the approved CAP. The locations of the sampling points are
shown in Figure 5.2. Results summary of laboratory testing are summarized in Table 5.2. Results exceeded to the relevant RBRGs are
highlighted in bold font.
Table 5.2 Laboratory
Results Summary
Criteria |
VOCs mg/kg |
TPH, mg/kg |
Heavy Metal, mg/kg |
Dioxin, ng/kg |
|||||||||||||||||||||||
Benzene |
Toluene |
Ethylbenzene |
Xylenes (Total) |
C6-C8 |
C9-C16 |
C17-C35 |
Antimony |
Arsenic |
Barium |
Cadmium |
Chromium III |
Chromium VI |
Cobalt |
Copper |
Lead |
Manganese |
Mercury |
Molybdenum |
Nickel |
Tin |
Zinc |
Dioxins (I-TEQ) |
|||||
Industrial |
9.21 |
10000 |
8240 |
1230 |
10000 |
10000 |
10000 |
261 |
196 |
10000 |
653 |
10000 |
1960 |
10000 |
10000 |
2290 |
10000 |
38.4 |
3260 |
10000 |
10000 |
10000 |
5000 |
||||
Soil Saturation Limit
(Csat) |
336 |
235 |
138 |
150 |
1000 |
3000 |
5000 |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
_ |
||||
Location |
Depth (m) |
Sampling Date |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||
From |
To |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
S1 |
0.10 |
NA |
14/03/2008 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
<0.50 |
6.1 |
26 |
0.10 |
6.6 |
<1.0 |
1.7 |
9.2 |
57 |
170 |
<0.05 |
2.3 |
3.6 |
13 |
54 |
8.32 |
|
S2 |
0.50 |
NA |
14/03/2008 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
<0.50 |
2.0 |
72 |
<0.10 |
1.8 |
<1.0 |
2.9 |
2.4 |
91 |
830 |
<0.05 |
<1.0 |
1.0 |
3.5 |
25 |
3.92 |
|
S3 |
0.10 |
NA |
14/03/2008 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
<0.50 |
4.7 |
17 |
<0.10 |
6.4 |
<1.0 |
1.0 |
5.8 |
67 |
140 |
<0.05 |
2.4 |
2.7 |
8.2 |
36 |
2.24 |
|
S4 |
0.10 |
NA |
14/03/2008 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
<0.50 |
4.1 |
19 |
<0.10 |
1.7 |
<1.0 |
6.2 |
1.9 |
150 |
520 |
<0.05 |
1.2 |
<1.0 |
1.3 |
22 |
2.71 |
|
S5 |
0.10 |
NA |
18/03/2008 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
<0.50 |
3.2 |
18 |
<0.10 |
2.5 |
<1.0 |
1.7 |
5.4 |
68 |
210 |
<0.05 |
1.5 |
1.6 |
3.0 |
34 |
8.58 |
|
BH-1 |
0.50 |
NA |
17/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
59 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-1 |
1.50 |
1.95 |
17/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
180000 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-1 |
5.50 |
5.95 |
17/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
260 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-2 |
0.50 |
NA |
17/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
37 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-2 |
2.00 |
2.45 |
18/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
72 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-2 |
5.80 |
6.25 |
18/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
48 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-3 |
0.50 |
NA |
15/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
Na |
NA |
NA |
NA |
NA |
NA |
57 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-3 |
1.50 |
2.00 |
15/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
64 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-3 |
5.50 |
6.00 |
15/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
21 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
|
BH-4 |
0.50 |
NA |
17/03/2008 |
<0.20 |
<0.20 |
<0.20 |
<0.60 |
<5.0 |
<200 |
<500 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
64 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA: denotes not applicable
5.24
For the fuel tank system, ten
soil samples were collected from four boreholes for laboratory analysis. Among
these samples analyzed, only one soil sample from BH-1 at
5.25 In accordance with the CAP, one trial pit (TP-1) was proposed underneath the pipeline of the underground fuel tank system. According to the drawing provided by EMSD (presented in the CAR), the existing pipeline is running parallel to the drive at the southwest side of the Study Area, which was possessed by Civil Engineering and Development Department (CEDD) for 10-Year Extended Landslip Preventive Measures (LPM) Project, Phase 5, Package D – Landslip Preventive Works or Slopes in Hong Kong Island project at the time of conducting SI. Access to the proposed trial pit location for sampling could not be obtained during SI. Replies from CEDD and ArchSD are presented in the CAR.
5.26
Hard strata were encountered
from
5.27
For
the surface soil samples, ten soil samples were
collected at
5.28 No groundwater was encountered for all the sampling location during the course of SI. No groundwater sample was collected for laboratory analysis.
5.29 Since the cremators are still in operation and the proposed trial pit location (TP-1) is possessed by CEDD, it is not possible to carry out site investigation inside the cremation rooms and at TP-1 at this stage. Further site inspection of TP-1 and two cremation rooms will be carried out after decommissioning and prior to the demolition of the existing crematorium. A supplementary CAP will be prepared for EPD endorsement to present detailed sampling and testing plan for two cremation rooms. Further SI of TP-1 will be conducted in accordance with the approved CAP. Findings of site investigation and appropriate remediation methods will be presented in supplementary CAR and RAP for EPD endorsement prior to the commencement of any earthworks. The extent of contamination, if any, should be estimated based on the depth where contaminants found, the hydrogeological condition and the contaminants levels. The actual extent will be determined by confirmatory sampling and testing.
Prediction
and Evaluation of Environmental Impacts
Construction Phase
Phase 1 - Construction of New Crematorium
5.30
No
surface soil sample has found exceeded the relevant RBRGs Industrial levels for
the heavy metals or dioxins. Therefore, no potential environmental impacts due
to aerial deposition of contaminants are anticipated during the construction
phase.
Phase 2 - Demolition of the Existing Crematorium and Construction of New
Crematorium
5.31
Based
on the analytical results of soil presented above, soil sample at location BH-1
at the depth of
5.32
Defining the extent of localised
contaminated soils with the consideration of no-contamination results of the
adjacent boreholes, a
5.33
The
proposed vertical extent of excavation is
5.34
Based
on the above approach, the vertical excavation depth was estimated to be
Table 5.3 Estimated Quantity of Contaminated Soil
Area |
Contaminant |
Estimated
Contamination Extent |
||
Vertical
m bcl |
Horizontal
(m2) |
Quantity
of contaminated soil (m3) |
||
BH1 |
Lead |
1.5 - 1.95m bcl (1.0 -2.45m bcl) |
25 |
37 |
Operation Phase
5.35
Since
Towngas will be used as burning fuel instead of diesel, there will be no
underground storage tank in the Study Area in the future, therefore, possible
leakage or spillage from the underground fuel tank is eliminated.
5.36
The
new cremators are designed to be capable of meeting the newly revised
requirements described in “A Guidance Note on the Best Practicable Means for
Incinerators (Crematoria)” BPM12/2(06), the quantities of metals and dioxins
emission will be limited. As no exceedance in dioxin or heavy metals for
surface deposition has been found in this Study, and quantities of heavy metals
and dioxin emission will be limited with the future cremator design, surface
soil contaminated with heavy metal or dioxin by surface deposition is therefore
not anticipated.
Mitigation
of Adverse Environmental impacts
Construction Phase
5.37
The
mitigation measures for the soil contamination are detailed in the CAR/RAP. Soil remediation options applicable to the
subject sites were addressed based on the following criteria:
l Technical and cost effectiveness
l Technology development status
l Commercial availability
l Experience
l Expertise requirement
5.38
The
applicability/ environmental benefits and limitations/ environmental
dis-benefits of the above remediation techniques for lead (heavy metal)
contamination soil are detailed in Table
5.4.
Table 5.4 Potential Soil Remediation Technologies
Remediation
Measures |
Descriptions |
Applicability |
Limitations |
Cement Solidification/ Stabilization |
Ex situ immobilization technique treats contaminated soil by mixing soil with
binding agents, e.g. cement so that the contaminants become physically bound
within stable mass. |
l Applicable to
clean-up inorganic contaminants, including heavy metals. l Solidification/stabilization
has been used on certain contaminated sites in |
l The effectiveness
reduces with the presence of organic contaminants (N.B. No organic
contaminants were found in the heavy metal contaminated soil in this Study). l Large boulders
may hinder the mixing process. Soil sorting is necessary before the treatment
taken place. l The process may
result in volume increase. l Pilot test is
required to set the appropriate ratio of cement to soil for complete
immobilization. |
Electronkinetic Separation |
In situ
remediation uses electrochemical and electrokinetic processes to desorb and
remove metals and polar organics from soil. Low intensity direct current is
applied to the soil to mobilize the charged species. |
l Applicable to
treat low permeability soil contaminated with heavy metals. |
l The
effectiveness depends on moisture content of soil. It decreases with moisture
content less than 10%. l Require further
treatment to remove the desorbed contaminants and thus increase the cost of
remediation. l Presence of
anomalies such as large gravels and insulating material in soil can induce
variability of electrical conductivity in soil. This may reduce the
effectiveness. |
Excavation and Landfill
Disposal |
Ex-situ method whereby
contaminants are removed by excavation of the contaminated soil and direct
disposal to landfill |
l
Most simple and quickest
way to dispose of small volume of contaminated
soil l
Contamination is removed
definitely l
Higher certainty of
success l
Wide experience in
Applicable to all waste
or mixture that meet land disposal restriction treatment standards.
Common practice for shallow,
highly-contaminated soils. |
l
Pre-treatment may be
required for contaminated soil to meet landfill disposal criteria l
Landfill space limited
and valuable. l
Indirect costs to the
landfill management on monitoring and maintenance. l
Potential long-term liabilities
to landfill l
Need large volume of
clean backfill materials
No access to the working
site until completion of backfilling
Least desirable
management option. |
Remediation Methods for Soil Contaminated with Metals
5.39
Among
the remediation methods listed in Table
5.4, soil washing is considered not applicable as extra treatment steps may
be required to address hazardous levels of washing solvent remaining in the
treated residuals which may increase the cost of remediation. While the
electrokinetics method suitable for low permeability soil, the contaminated
soil at the Study Area belonged to the high permeable fill type materials, making
such method not suitable. In addition, the lack of experience in
5.40
For
the solidification / stabilization, the solid monolithic block adopted in this
solidification / stabilization technique is extremely resistant to the leaching
of inorganic contaminants. Additives can
be added to assist in chemically binding the contaminants in a matrix that
typically shows unconfined compressive strengths similar to a soil-cement
mix. In addition, solidification /
stabilization has been used on certain contaminated sites in Hong Kong and as a
successful treatment method for inorganic contaminated soil, e.g.
decontamination works at the Cheoy Lee Shipyard at Penny’s Bay, reclamation
works at North Tsing Yi Shipyard site and few isolated sites identified in the
Deep Bay Link project. Based on the
above discussion, solidification / stabilization technique is considered as the
most practical and cost-effective method to treat the metals contaminated soil
on site.
Outline Procedures and Operation of
Remediation
Excavation of
Contaminated Soil
5.41
The
excavation plans for the identified contaminated areas at the Study Area are
shown in Figure 5.3.
Factors such as excavation areas and depths, engineering properties and
stability of the soils shall be considered for safe working conditions. The excavations will be designed in
accordance with the geotechnical properties of the soils and appropriate safety
factors as determined by the Engineer.
All excavated areas will be set out by an appropriate qualified and
licensed land surveyor based upon the excavation plans shown in Figure 5.3.
5.42
The
excavation sequence would be as follows:
l Excavate the contaminated soil and properly packed until no contaminants are found (confirmed by field and laboratory tests);
l Transport the excavated soil by roll-off trucks for on-site treatment;
l Finally, backfill the excavation with clean soils.
Closure Assessment
5.43 Confirmatory soil sampling for closure assessment should be carried out to confirm the clean-up of the contaminated soil. In general, at least one sample from the base of the excavation pit and four samples from the sidewall should be collected for confirmatory testing. Figure 5.4 presents the proposed confirmatory sampling locations.
5.44
If the analytical results of
the confirmatory samples are below the relevant RBRGs lead content, removal of
contaminated soil shall be considered complete. If the analytical results exceed the relevant
level, excavation shall be extended further (with
Cement Solidification /
Stabilisation (CS/S)
5.45 The amount of heavy metal contaminated soil proposed for CS/S treatment in this Study is ~37m3. A treatment area should be confined for carrying out the CS/S mixing and temporary soil stockpile. Prior to solidification, lead contaminated soil should be screened to segregate soil from debris, rock fragment, and other materials and to break soil clumps into sizes to allow effective mixing with solidifying agents.
5.46 During the CS/S process, cement, water and/or other additive(s) should be added to the contaminated soils to form a solid matrix. After setting, the samples of the blocks should be collected for testing to confirm if contaminated materials meet the i) Toxicity Characteristics Leaching Procedure (TCLP) and ii) unconfined compressive strength (UCS) tests i.e. achievement of the stabilization targets.
Toxicity Characteristics Leaching Procedure
Test
5.47
TCLP tests should be conducted
in accordance with USEPA Method 1311 and USEPA Method 6020 for the concerned
metals in this Study. The TCLP test of the CS/S treated soil should comply with
the “Universal Treatment Standards” (UTS), as shown in Table 5.5, before using the soil on-site.
Table 5.5 Universal
Treatment Standards (UTS) for the Concerned Heavy Metals
Parameters |
Universal
Treatment Standard |
Lead |
0.75 mg/L as TCLP |
Unconfined compressive strength (UCS)
5.48 The treated material should be allowed to set to achieve the unconfined compressive strength (UCS) of not less than 1 MPa with reference to the USEPA guidelines (1986) – handbook for Stabilisation/Solidification of Hazardous Wastes, EPA/540/2-86-00. The test procedure of UCS test shall be based on BS 1377.
Possible Remediation Methods for Contaminated Soil underneath Pipeline
and at Cremation Rooms
5.49 As identified above, the major contamination source due to the pipeline and operation of cremation rooms is likely the leakage of fuel petroleum. Organic contaminants such as TPH and SVOCs are likely found exceeding the relevant RBRGs. If contaminated soil is found underneath the pipeline and at cremation rooms from the further SI, depending on the contamination extent, possible remediation methods for organic contaminants could be excavation and biopiling as well as in-situ soil venting. If the volume of contaminated is found to be small and the aforesaid remediation methods is infeasible and impracticable, excavation and landfill disposal could be considered as last resort. Closure assessment in accordance with paragraphs 5.43 to 5.44 will be carried out in order to confirm the clean-up of contaminated soil. The remediation method should be determined in the supplementary RAP according to the laboratory results and estimated quantity of contaminated soil.
Underground Storage Tank Removal
5.50
During
removal of the underground storage tank, appropriate precautions should be
taken to avoid contamination. All fuel
tank and associated pipelines should be emptied prior to any demolition work
being undertaken. Any remaining sludge
or sediment in the tanks or pipelines should be removed and disposed of as
chemical waste in accordance with the appropriate regulation for disposal of
such material. After removal of the underground storage
tank, confirmatory soil sample(s) underneath the tank should be collected and
tested for TPH, VOCs and Pb using the same approach as mentioned in Sections
5.43 and 5.44 above to ensure that no contamination due to fuel leakage.
Operation Phase
5.51 Provided that all contaminated soils identified are treated before construction of the new crematorium, land contamination impacts due to future operation of new crematorium are not anticipated. Therefore, mitigation measures are considered not necessary in operation phase.
Evaluation
of Residual Impacts
5.52
The
proposed remediation methods will completely remove contaminants from the Study
Area through excavation followed by immobilizing the contaminants by cement
solidification/ stabilization and backfilled on site subsequently. After completion of soil remediation, residual
impact in respect of land contamination on the future users should not be
expected.
5.53
Although
potential contamination from pipeline is uncertain, large scale land
contamination due to leakage or spillage from the pipeline is not
anticipated. Therefore, potential land
contamination arising from the pipeline will be localized and in a manageable
scale.
5.54
As
abovementioned, since possible leakage or spillage of diesel may occur at the
Cremation Rooms 1 and 2, further site investigation will be carried out for hydrocarbon
related contaminants.
5.55
If
in any case that soil is found contaminated with hydrocarbon related product at
Cremation Rooms 1 and 2, on-site soil treatment using bioremediation method
would possibly be one of the soil remediation option. With implementation of
proper remedial actions prior to the commencement of any earthworks, residual
land contamination impacts are not anticipated.
Recommended Health and Safety Measures and
Environmental Mitigation Measures
5.56
Mitigation
measures have been recommended in the RAP for handling of the contaminated
materials during the course of site remediation in order to minimise (1) the
potentially adverse effects on the health and safety of construction workers
and (2) the environmental impacts arising from the handling of contaminated
materials.
5.57 The following basic health and safety measures should be implemented as far as possible:
l Set up a list of safety measures for site workers;
l Provide written information and training on safety for site workers;
l Keep a log-book and plan showing the contaminated zones and clean zones;
l Maintain a hygienic working environment;
l Avoid dust generation;
l Provide face and respiratory protection gear to site workers;
l Provide personal protective clothing (e.g. chemical resistant jackboot, liquid tight gloves) to site workers; and
l Provide first aid training and materials to site workers.
5.58 The Contractor for the excavation works shall take note of the following points for excavation:
l Excavation profiles must be properly designed and executed;
l In case the soil to be excavated is situated beneath the groundwater table, it may be necessary to lower the groundwater table by installing well points or similar means. The discharge of groundwater, if any, should follow the requirements under the Water Pollution Control Ordinance (WPCO);
l Excavation zone should be fenced off;
l Quantities of soil to be excavated must be estimated;
l It may be necessary to split quantities of soil according to soil type, degree and nature of contamination;
l Temporary storage of soil at intermediate depot or on-site may be required. The storage site should include protection facilities for leaching into the ground e.g. a liner may be required;
l Supply of suitable clean backfill material is needed after excavation;
l Care must be taken of existing buildings and utilities; and
l Precautions must be taken to control of ground settlement.
5.59
Key
potential environmental impacts induced by CS/S processes include:
l Odour, run-off and dust emission from CS/S plant;
l Noise generated from CS/S process.
5.60
The
following mitigation measures are recommended to be implemented during CS/S
processes.
Air
Quality Impact
l The loading, unloading, handling, transfer or storage of cement should be carried out in an enclosed system.
l The loading, unloading, handling, transfer or storage of other materials which may generate airborne dust emissions such as untreated soil and oversize materials sorted out from the screening plant and stabilized soil stockpiled in the designated handling area, should be carried out in such a manner to prevent or minimise dust emissions. These materials should be adequately wetted prior to and during the loading, unloading and handling operations.
l All practicable measures should be taken to prevent or minimize the dust emission caused by vehicle movement.
Noise Impact
l The mixing area should be sited as far as practicable to nearby noise sensitive receivers.
l Simultaneous operation of mixing plants and other equipment should be avoided.
l Mixing process and other associated material handling activities should be properly scheduled to minimise potential cumulative noise impact on nearby noise sensitive receivers.
l Construction Noise Permit should be applied for the operation of powered mechanical equipment, if any, during restricted hours.
Water Quality Impact
l Stockpile of untreated soil should be covered as far as practicable to prevent the contaminated material from leaching out. The leachate should be discharged following the requirements of Water Pollution Control Ordinance.
Waste
l The oversize materials such as rocks and boulders should be screened out, cleaned the soil attached and used as filling material within the site. Contaminated materials (soil or rock fragments) of size smaller than 5 cm should be collected and transferred to the mixing area for decontamination treatment.
l Stabilized soils should be broken into suitable size for backfilling or reuse on site.
l A high standard of housekeeping should be maintained within the mixing area.
l There should be clear and separated areas for stockpiling of untreated and treated materials.
Conclusion
5.61
Site
investigation was undertaken for the fuel tank system and aerial
deposition from stack emission for land contamination assessment. The result
indicated that one soil sample (BH1, 1.5 –
5.62
Cement
solidification/stabilization (CS/S) treatment is proposed for the remediation
of ~37m3 soils contaminated with heavy metals in this Study. The
treated soils have to meet both the universal treatment standards in the TCLP
test and the unconfined compressive strength (UCS) test of not less than 1 MPa
before backfilling on site.
5.63
Further
site investigation in areas that are currently in use and cannot be accessed is
required. These areas include the trial
pit for soil sampling underneath the pipeline, Cremation Room 1 and Room
2. It is recommended that further site
investigation will be undertaken after decommissioning and prior to the
demolition of the existing crematorium.
5.64
A
supplementary CAP will be prepared for EPD endorsement to present detailed
sampling and testing plan for Cremation Rooms 1 and 2. For site investigation at pipeline, potential
contaminants have been identified in the approved CAP and SI shall be conducted
in accordance with the approved CAP.
5.65
Findings
of further site investigation will be presented in supplementary CAR and
supplementary RAP will be prepared, if required, for EPD endorsement prior to
the commencement of any earthworks.
5.66
Referring
to the site inspection presented in CAP, there is no record of large-scale
leakage or spillage at the Study Area. In
case of any contamination found related with hydrocarbon product during further
site investigation, on-site soil treatment using bio-remediation method could
be one of the remedial option.
5.67 As Towngas will be used as burning fuel instead of diesel in the new crematorium, possible leakage or spillage from the underground storage tank and the pipeline system is eliminated. With the new design of cremators which is capable of meeting the newly revised requirements described in “A Guidance Note on the Best Practicable Means for Incinerators (Crematoria)” BPM12/2(06), it is anticipated that aerial deposition would not give rise to significant land contamination.