1                      introduction

Background of the Project

1.1               The existing Cape Collinson Crematorium has started operation since 1962. Cremator Nos. 1-10 were replaced in 1995 and Nos. 11-12 were commissioned in 2001. 

 

1.2               In order to cope with an increasing demand for cremation service, Food and Environmental Hygiene Department (FEHD) proposes to demolish the existing crematorium as well as to construct and operate a new crematorium in-situ as a replacement (hereinafter referred to as the Project). The Project will be developed in two phases. 

 

1.3               Architectural Services Department (ArchSD) is the works agent for the project management and implementation of the Project, while the FEHD is the Project Proponent and is responsible for the operation of the Project after completion of construction works.     

 

1.4               Based on the definitions laid down under Part I and Part II in Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) as well as the nature of the proposed Project, the proposed Project is classified as a Designated Project (DP) under Category N.4 - A crematorium, Part I in Schedule 2 of the EIAO.   

 

1.5               Pursuant to Section 5(7)(a) of the EIAO, the Director of Environmental Protection issued the EIA Study Brief No. ESB-177/2008 to the Project Proponent for carrying out an Environmental Impact Assessment (EIA) Study of the Project.

 

1.6               ENSR Asia (HK) Ltd. has been appointed by the ArchSD as the Consultant to undertake the EIA in accordance with the EIAO, Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) as well as the Study Brief. 


Project Scope and Programme

1.7               The project site is the site of the existing Cape Collinson Crematorium at Cape Collinson Road, Eastern District (see Figure 1.1). The new crematorium will be developed in two phases outlined below. Prior to Phase 1 construction works, tree transplanting will be carried out in advance from January 2010 to June 2010.

 

             Phase 1 (July 2010 to March 2012)

 

1.8               Site formation work will be carried out at the beginning of Phase 1 which involves extension of the existing car park area for the construction of an access road. After the site formation has been completed, a new crematorium with 4 cremators will be constructed to the north of the existing crematorium. During this period, all the 12 cremators in the existing crematorium will still remain in operation until the satisfactory commissioning of the new cremators under Phase 1 by 2012. The total installed capacity of 4 cremators in Phase 1 would be approximately 583 kg/hour.

 

             Phase 2 (March 2012 to December 2014)

 

1.9               After completion of the Phase 1 works, demolition of the existing crematorium, construction of another 6 cremators and 1 service hall will then be carried out in Phase 2. There will be no overlapping between Phase 1 and Phase 2. The total installed capacity of 6 cremators in Phase 2 would be approximately 943 kg/hour.


Purpose of the Manual

1.10            The purpose of this Environmental Monitoring and Audit (EM&A) Manual is to guide the set up of an EM&A programme to ensure compliance with the EIA study recommendations, to assess the effectiveness of the recommended mitigation measures and to identify any further need for additional mitigation measures or remedial action.  This Manual outlines the monitoring and audit programme for the proposed Project. It aims to provide systematic procedures for monitoring, auditing and minimising environmental impacts associated with Project activities.

 

1.11            Hong Kong environmental regulations and the Hong Kong Planning Standards and Guidelines (HKPSG) and recommendations in the EIA Report have served as environmental standards and guidelines in the preparation of this Manual. In addition, the EM&A Manual has been prepared in accordance with the requirements stipulated in Annex 21 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

 

1.12            This Manual contains the following information:


·         Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team (ET) and Independent Environmental Checker (IEC) with respect to the environmental monitoring and audit requirements during the course of the Project;

·         Project organisation for the Project;

·         The basis for, and description of the broad approach underlying the EM&A programme;

·         Requirements with respect to the construction programme schedule and the necessary environmental monitoring and audit programme to track the varying environmental impact;

·         Details of the methodologies to be adopted, including all field laboratories and analytical procedures, and details on quality assurance and quality control programme;

·         The rationale on which the environmental monitoring data will be evaluated and interpreted;

·         Definition of Action and Limit levels;

·         Establishment of Event and Action plans;

·         Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints;

·         Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures; and

·         Requirements for review of EIA predictions and the effectiveness of the mitigation measures / environmental management systems and the EM&A programme.

 

1.13            For the purpose of this manual, the ET leader, who shall be responsible for and in charge of the ET, shall refer to the person delegated the role of executing the EM&A requirements.

Project Organisation

1.14            The roles and responsibilities of the various parties involved in the EM&A process and the organisational structure of the organisations responsible for implementing the EM&A programme are outlined below.  The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 1.2.

 

The Contractor

 

1.15            The Contractor shall report to the Engineer. The duties and responsibilities of the Contractor are:

 

·         to employ an Environmental Team (ET) to undertake monitoring, laboratory analysis and reporting of environmental monitoring and audit;

·         to provide assistance to ET in carrying out monitoring and auditing;

·         to submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event and Action Plans;

·         to implement measures to reduce impact where Action and Limit levels are exceeded;

·         to implement the corrective actions instructed by the Engineer;

·         to accompany joint site inspection undertaken by the ET; and

·         to adhere to the procedures for carrying out complaint investigation.

 

Environmental Team

 

1.16            The ET shall report to the Contractor. The ET Leader and the ET shall be employed to conduct the EM&A programme and ensure the Contractor’s compliance with the project’s environmental performance requirements during construction and operation. The ET Leader shall be an independent party from the Contractor and have relevant professional qualifications, which shall include being an Accredited Monitoring Professional of the Hong Kong Institute of Environmental Impact Assessment (HKIEIA), subject to approval of the Engineer’s Representative (ER) and the Environmental Protection Department (EPD). The ET shall be led and managed by the ET leader.  The ET leader shall possess at least 7 years experience in EM&A and/or environmental management.

 

1.17            The duties and responsibilities of the ET are:

 

·         to monitor various environmental parameters as required in this EM&A Manual;

·         to analyse the environmental monitoring and audit data and review the success of EM&A programme to cost-effectively confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions and to identify any adverse environmental impacts arising;

·         to carry out regular site inspection to investigate and audit the Contractors' site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and effect proactive action to pre-empt problems; carry out ad hoc site inspections if significant environmental problems are identified;

·         to audit and prepare monitoring and audit reports on the environmental monitoring data and site environmental conditions;

·         to report on the environmental monitoring and audit results to the IEC, Contractor, the ER and EPD or its delegated representative;

·         to recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans; and

·         to adhere to the procedures for carrying out complaint investigation.

 

Engineer or Engineer’s Representative

 

1.18            The Engineer is responsible for overseeing the construction works and for ensuring that the works undertaken by the Contractor in accordance with the specification and contractual requirements. The duties and responsibilities of the Engineer with respect to EM&A may include:

 

·         to supervise the Contractor’s activities and ensure that the requirements in the EM&A Manual are fully complied with;

·         to inform the Contractor when action is required to reduce impacts in accordance with the Event and Action Plans;

·         to employ an IEC to audit the results of the EM&A works carried out by the ET;

·         to participate in joint site inspection undertaken by the ET; and

·         to adhere to the procedures for carrying out complaint investigation.

 

Independent Environmental Checker

 

1.19            The IEC shall advise the Engineer’s Representative on environmental issues related to the project. The IEC shall have project management experience in additional to the requirements of the ET Leader stated above.

 

1.20            The duties and responsibilities of the IEC are:

 

·         to review the EM&A works performed by the ET (at least at monthly intervals);

·         to audit the monitoring activities and results (at least at monthly intervals);

·         to review the EM&A reports submitted by the ET;

·         to review the effectiveness of environmental mitigation measures and project environmental performance;

·         to review the proposal on mitigation measures submitted by the Contractor in accordance with the Event and Action Plans; and

·         to adhere to the procedures for carrying out complaint investigation.

 

1.21            Sufficient and suitably qualified professional and technical staff shall be employed by the respective parties to ensure full compliance with their duties and responsibilities, as required under the EM&A programme for the duration of the Project.