3.1
Waste
likely to be generated during the construction phase of the Project include
excavated material, construction and demolition materials, contaminated materials
including ash waste and building structure, chemical waste and general refuse.
3.2
During
the operation phase of the new crematorium, the major types of waste to be
generated are ash and non-combustible residues generated from combustion
process, chemical waste generated from air pollution control system and
machinery maintenance and servicing, and general refuse generated by visitors
and staffs during daily operation.
3.4
If good site practices are strictly followed,
it is expected that adverse environmental impacts due to waste generation will
not arise. Good management and control can prevent the generation of
significant amounts of waste. In
addition, specific mitigation measures are recommended to minimise
environmental impacts during handling, transportation and disposal of wastes
generated from the Project. The
environmental mitigation measures for waste management during the construction
phase as well as during the operation phase are summarised in the following
sections.
3.5
Site
audit has been recommended during the construction phase. The EIA Study has
determined that with effective implementation of the appropriate mitigation measures,
there will be no significant impact from these wastes.
Implementation schedule for recommended waste management mitigation
measures is presented in Appendix A.
Mitigation
Measures for Construction Phase
General – Good Site Practice and Waste Reduction
Measures
3.6
Adverse
environmental impacts due to waste generation are not expected. The following
recommendations should be implemented during the construction activities:
·
Obtain
relevant waste disposal permits from the appropriate authorities, in accordance
with the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Chemical
Waste)(General) Regulation (Cap. 354), Waste Disposal (Charges for Disposal of
Construction Waste) Regulation (Cap 345) and the Land (Miscellaneous Provision)
Ordinance (Cap.28)
·
Prepare
a Waste Management Plan approved by the Engineer / Supervising Officer of the
Project based on current best practice on Construction Sites
·
Waste
licensed collector to collect waste
·
Implementation
of trip ticket system with reference to ETWB(W) No.31/2004 Trip Ticket System
for Disposal of Construction & Demolition Materials.
·
Provide
staff training for proper waste management and chemical waste handling
procedures
·
Separation
of chemical waste for special handling and dispose to licensed facility for
treatment
·
Sufficient
waste disposal points and regular collection programme setup
·
Recording
system for waste generation, recycle and disposal
3.7
The
ETWB TCW No.19/2005 “Environmental Management on Construction” includes
procedures on waste management requiring contractors to reduce the C&D
material to be disposed of during the course of construction. Under this ETWB
TCW No.19/2005, the Contractor is required to prepare and implement an
Environmental Management Plan (EMP) and the Waste Management Plan (WMP) becomes
part of the EMP.
3.8
Waste
reduction should be considered in planning and design stage, the following
practice should be implemented.
·
Prior
to disposal of C&D waste, wood, steel and other materials should be
separated for reuse, recycling to minimize the quality of waste to be disposed
of at landfill.
·
Minimize
use of wood and reuse non-timber formwork to reduce C&D waste
·
As
far as practicable, segregate and store different types of waste in different
containers, skips or stockpiles to enhance reuse or recycling of materials and
their proper disposal.
·
Encourage
collection of aluminum cans, plastic bottles and packaging material and office
paper
Excavated Materials
3.9
Rock
and soil generated from excavation should be reused during site formation and
landscaping as far as practicable to reduce total amount to be disposed of
off-site.
3.10
Trip-ticket
system should be implemented for surplus excavated materials disposal in
accordance with ETWB TC(W) No.31/2004 and the Construction Waste Disposal
Charging Scheme. Waste should be delivered to a public fill reception facility.
Copies or counterfoils of trip tickets will be kept for record purpose.
Construction and Demolition Materials
3.11
Well-planned
design and good site management can minimize over-loading and generation of
waste materials such as concrete and cement grouts. Wooden frame should be
replaced by metals. Plastic fencing and reusable site office structure can
reduce C&D waste generation.
3.12
The
Contractor should recycle as much C&D materials as possible. Proper
segregation of waste types on site to enhance reuse and recycling of materials.
Designated areas for different materials storage should be assigned for
segregation.
3.13
Under
the Construction Waste Disposal Charging Scheme, construction waste producers
such as construction and renovation contractors and premises owners, prior
using government waste disposal facilities, need to prepare a billing account
with EPD and pay for construction waste disposal.
3.14
It
is expected that trip-ticket system will be implemented for surplus C&D
materials disposal in accordance with ETWB TC(W) No.31/2004 and the Construction
Waste Disposal Charging Scheme. Waste should be delivered to a public fill
reception facility. Copies or counterfoils of trip tickets will be kept for
record purpose.
Contaminated Materials
3.15
Since
all twelve cremators in the existing crematorium will remain in operation
during Phase 1 and demolition works will be carried out during Phase 2,
contaminated material would only be generated during the Phase 2 construction
and demolition works.
Specific Plan for Contaminated Materials
arising from Demolition Works
3.16
Building
structure of cremators, flues and chimneys would likely to be contaminated by
DCM ash due to long term servicing. As the cremators are still in operation, it
is not possible to carry out site investigation in the areas of cremators,
flues and chimneys at this stage. To maintain uninterrupted cremation services,
further site investigation in cremation rooms and associated equipments are
proposed to undertake after decommissioning and prior to demolition of the
existing crematorium.
3.17
According
to the asbestos investigation report, asbestos gasket (woven) and insulation
sheet were identified with ACM. It is also not possible to inspect all
potential asbestos containing material locations due to on-going operation of
cremators, concealed pipeline inside wall and metal cover of flange connection.
Further inspection of the inaccessible locations will be undertaken after
decommissioning and prior to demolition of the existing crematorium.
3.18
Under this consideration, contaminated ash and ACM potential
contamination locations will be further identified. In view of close distance
between the contaminated ash and ACM, there is a concern on contaminated ash
wastes being embedded in ACM. Therefore, it is advisable to remove contaminated
ash waste prior to any asbestos containing material on building structures.
This is considered as the worst case scenario in this assessment.
3.19
Should contaminated ash is identified on the ACM, the contaminated ash
will be removed first prior to removal of ACM. If the procedures and
precautionary measures described in Section 3.23 to 3.26 are followed properly,
cross contamination could be minimized under normal
circumstances. These procedures and measures are considered as reasonable
approach to handle the cross contaminated wastes.
3.20
Asbestos
waste will be handled in accordance with the Code of practice on the Handling,
Transportation and Disposal of Asbestos Waste issued by the Environment Bureau.
3.21
Production,
collection and disposal of asbestos waste will follow the “trip-ticket” system.
The registered asbestos contractor will appoint a licensed asbestos waste
collector to collect the packaged asbestos waste and deliver to the designated
landfill for disposal. Notification has to be given to EPD for its disposal.
EPD will normally require ten working days notice of the intention to dispose
of any quantity of asbestos waste. After processing the notification, EPD will
issue specific instructions and directions for disposal of the waste. The waste
producer or his agent must strictly follow these directions.
3.22
Different
contamination classifications based on dioxin level in ash waste are proposed
in Table 3.1 and corresponding
mitigation measures are also described:
Table 3.1 Proposed Contamination Classifications for Ash Waste
Classification of Contamination |
Dioxin Level in Ash Waste |
Low
Contaminated DCM |
<1ppb
TEQ |
Moderately
Contaminated DCM |
>1
and <10 ppb TEQ |
Severely
Contaminated DCM |
>10ppb
TEQ |
3.23
Where
the ash waste contains low contamination levels of DCM, the Contractor should
avoid ash waste becoming airborne during demolition. General dust suppression
measures will be followed and ash waste will be directly disposed of at
landfill.
3.24
Where
the ash waste contains moderately contaminated DCM, the following steps should
be followed:
·
Site Preparation
- Except
the cremators / flue / chimney, all removable items should be removed as far as
practicable to avoid obstructing the decontamination activities;
- Preliminary
site decontamination of all debris should be carried out using High Efficiency
Particulate Air (HEPA) vacuum cleaner;
- Top
portion of the chimney should be enclosed by a 3-layer chamber of polyethene
sheets;
- At
the entrance to the cremators / flues / chimney, a 3-chamber decontamination
unit should be constructed for entry and exit from the work area. The 3-chamber
decontamination unit should comprise a dirty room, a shower room and a clean
room of at least 1m x 1m base with 3-layer of fire retardant polyethylene
sheet;
- Workers
should carry out decontamination procedure before leaving the work area;
- Workers
should wear full protective equipment, nitrile gloves, robber boots and
full-face positive pressure respirator; and
- Warning
signs in both Chinese and English should be displayed in conspicuous areas.
·
Demolition and Handling
- The
cremators / flue / chimney should be removed from top down. Any ash or residues
attached to the cremators / flue / chimney or any other building structure
should be removed by scrubbing and HEPA vacuuming;
- Waste
generated from the containment or decontamination unit including the protection
clothing of the workers should be disposed to landfill;
- After
removal, all surfaces should be decontaminated by HEPA vacuum cleaner; and
- The
storage area for ash waste should be properly enclosed throughout the
demolition works. The location of storage area for ash waste will be identified
in the Waste Management Plan to be prepared by the Contractor.
·
Treatment and Disposal
- Immobilise
ash waste by proper mixing with cement as determined by the pilot mixing and
Toxicity Characteristic Leaching Procedure (TCLP);
- Waste
material should be placed in polyethylene lined steel drums for disposal at
landfill, the drums should be 16 gauge steel or thicker and fitted with double
bung fixed ends adequately sealed and well labeled in new or good condition.
- Drums
should be clearly marked “DANGEROUS CHEMICAL WASTE” in English and Chinese.
Prior agreement of the disposal criteria must be obtained from EPD and the
landfill operator.
- As
a fall back option, if landfill disposal criteria cannot be met after
immobilization of the ash waste, disposal at the Chemical Waste Treatment
Center (CWTC) should be considered.
3.25
The
areas with severely contaminated DCM should be removed under containment as a
prudent approach to avoid the release of ash waste to the environment during
the demolition works of the existing building and the following should be
addressed.
·
Site
Preparation
- Except
the cremators / flue / chimney, all identified removable items with severely contaminated
DCM should be removed as far as practicable to avoid obstructing the
decontamination activities;
- Preliminary
site decontamination of all debris should be carried out using High Efficiency
Particulate Air (HEPA) vacuum cleaner;
- The
walls, floor and ceiling of the cremator room where severely contaminated DCM
should be lined with 3-layer chamber of fire retardant polyethene sheets. Top
portion of the chimney above the roof should be enclosed by a 3-layer chamber
of polyethene sheets;
- At
the entrance to the cremators / flues / chimney, a 3-chamber decontamination
unit should be constructed for entry and exit from the work area. The 3-chamber
decontamination unit should comprise a dirty room, a shower room and a clean
room of at least 1m x 1m base with 3-layer of fire retardant polyethylene sheet
where all workers would carry out decontamination procedures before leaving the
work area;
- Air
movers should be installed at the cremator room, and at the bottom of the
chimney to exhaust air from work area. A stand-by air mover should be installed
with each of air movers. Sufficient air movement should be maintained to give a
minimum of 6 air changes per hour to the work area;
- New
pre-filters and HEPA filters should be used on the air movers.
- Before
commencement of the decommissioning work, a smoke test with non-toxic smoke
should be carried out to confirm the air tightness of the containment;
- Workers
should wear full protective equipment, disposable protective coverall (such as
Tyvek with shoe covers and hood), nitrile gloves, rubber boots and full-face
positive pressure respirator equipped with a combination cartridge that filters
particulate and removes organic vapour; and
- Warning
signs in both Chinese and English should be displayed in conspicuous areas.
·
Decontamination,
Demolition and Handling
- The
cremators / flue / chimney should be removed from top down. Any ash or residues
attached to the cremators / flue / chimney or any other building structure
should be removed by scrubbing and HEPA vacuuming;
- The
contaminated detached sections of the building structure with severely
contaminated DCM should be wrapped with 2 layers of fire retardant polyethene
sheets. The third layer should be wrapped and secured with duct tape.
Decontaminate the outer layer of the wrapped flue sections by wet wiping;
- After
completion of removal and decontamination, spray the innermost layer of the
fire retardant polyethene sheet with PVA. Upon drying, peel off and dispose of
at landfill site; and
- The
storage area for ash waste should be properly enclosed throughout the
demolition works. The location of storage area for ash waste will be identified
in the Waste Management Plan to be prepared by the Contractor.
·
Treatment and Disposal
- All
contaminated ash waste with severely contaminated DCM removed and the used HEPA
filters should be sent to Chemical Waste Treatment Center (CWTC) at Tsing Yi
accordingly to Chapters
2 & 3 Code of Practice on the Packaging, Labelling & Storage of Chemical
Wastes published under the Waste Disposal Ordinance (Cap 354), Section 35; and
- Other
waste including the building structures and its associated panels as well as
waste generated from this decommissioning works are also considered as
contaminated waste and should be disposed of at designated landfill. Waste
generated from this decommissioning works refer to the polyethene wrapping
sheets should be placed into appropriate containers for disposal. Waste
Disposal Permit has to be obtained from EPD. Disposal trip ticket is required
to be made available as record after disposal.
3.26
Further
investigation and confirmatory test for ash waste in cremator, chimney and
flues should be carried out on DCM prior to the demolition works of the
existing building. The sampling and analysis plan should be prepared and
submitted to EPD for approval.
3.27
The
principles as stated in Section 3.23 to 3.26 aim to address the detailed measures
of avoiding cross contamination of DCM and ACM and should form part of the DCM
Assessment Report which will be submitted to EPD for approval before the
commencement of the demolition of the existing crematorium.
3.28
Contaminated
Soil:
·
According
to the Contamination Assessment Report (CAR) and Remediation Action Plan (RAP)
provide in Appendix 5.2, among five 0.1m samples analyzed, no surface soil
samples were found to have testing parameters exceeding the relevant Risk-Based
Remediation Goals (RBRGs).
·
In
additional, further investigations and confirmatory test should be carried out
to determine if additional remediation (in addition to the current RAP) is
required.
Chemical Waste
3.29
All
the chemical waste should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes. The chemical waste should be stored and collected by a licensed
contractor for disposal at licensed facility in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation. Containers used for the storage of chemical waste should be:
·
Suitable
for substance holding, resistant to corrosion, maintained in good condition and
securely closed;
·
Capacity
of less than 450 liters unless the specifications have been approved by the
EPD; and
·
Display
a label in English and Chinese in accordance with instructions prescribed in
Schedule 2 of the Waste Disposal
(Chemical Waste)(General) Regulation.
3.30
The
storage area for chemical waste should:
·
Be
clearly labeled and used solely for the storage of chemical waste;
·
Be
enclosed on at least 3 sides;
·
Have
an impermeable floor and bunding, of capacity to accommodate 110% of the volume
of the largest container or 20% by volume of the chemical waste stored in that
area, whichever is the greatest;
·
Have
adequate ventilation;
·
Be
covered to prevent rainfall from entering (water collection within the bund must
be tested and disposal as chemical waste if necessary); and
·
Be
properly arranged so that incompatible materials are adequately separated.
3.31
The
chemical waste should be disposed of by:
·
A
licensed waste collector;
·
A
facility licensed to receive chemical waste, such as CWTC at Tsing Yi, which
offers chemical waste collection service and can supply the necessary storage
containers; and
·
A
waste recycling plant as approved by EPD.
General Refuse
3.32
General
refuse should be stored in enclosed bins or compaction units separated from
C&D and chemical wastes. Waste collector should be employed by the
Contractor to minimize odour, pest and litter impacts. Open burning of refuse
on construction site is prohibited by law.
3.33
The
Contractor should carry out an education programme for workers in avoiding,
reducing, reusing and recycling. This should include provision of three-colour
recycling bins and on site and posters and leaflets advising on the use of
recycling bins.
Mitigation
Measures for Operation Phase
General - Good
Site Practices and Waste Reduction Measures
3.34
It is recommended that the
following good operational practices should be adopted to minimise waste
management impacts:
§
Obtain the necessary waste disposal
permits from the appropriate authorities, in accordance with the Waste
Disposal Ordinance (Cap. 354), Waste Disposal (Chemical Waste) (General)
Regulation and the Land (Miscellaneous Provision) Ordinance (Cap. 28);
§
Nomination of an approved person
to be responsible for good site practice, arrangements for collection and
effective disposal to an appropriate facility of all wastes generated at the
site;
§
Use of a waste haulier
licensed to collect specific category of waste;
§
A trip-ticket system should
be included as one of the contractual requirements and implemented by the
Environmental Team to monitor the disposal of C&D and solid wastes at
public filling facilities and landfills, and to control fly tipping. Reference
should be made to ETWB TCW No. 31/2004.
§
Training of site personnel
in proper waste management and chemical waste handling procedures;
§
Separation of chemical
wastes for special handling and appropriate treatment at a licensed facility;
§
Routine cleaning and
maintenance programme for drainage systems, sumps and oil interceptors;
§
Provision of sufficient
waste disposal points and regular collection for disposal;
§
Adoption of appropriate
measures to minimize windblown litter and dust during transportation of waste,
such as covering trucks or transporting wastes in enclosed containers;
§
Implementation of a
recording system for the amount of wastes generated, recycled and disposed of
(including the disposal sites).
3.35
Good management and control
can prevent the generation of significant amounts of waste. It is recommended
that the following good operational practices should be adopted to ensure waste
reduction:
§
Segregation and storage of
different types of waste in different containers, skips or stockpiles to enhance
reuse or recycling of materials and their proper disposal;
§
Encourage collection of
aluminium cans, plastic bottles and packaging material (e.g. carton boxes) and
office paper by individual collectors. Separate labelled bins should be
provided to help segregate this waste from other general refuse generated by
the work force;
§
Any unused chemicals or
those with remaining functional capacity should be reused as far as
practicable.
Ash and Non-Combustible
Residues
3.36
The disposal of bone and non-combustible residues
should be properly collected and handled to avoid dust emissions. In line with
the current practices, the bone ash will be stored in covered containers for
collection by the deceased’s relatives within 2 months upon appointment while
the non-combustible residues will be collected in sealed heavy-duty polyethene
bags for disposal at landfill. Potential secondary environmental impacts will
be kept to a minimum.
3.37
Combustion gas temperature, residence time, air supply
and gas turbulence of the new cremators will be properly and adequately
controlled to optimize the effectiveness of combustion during cremation
process, therefore generation of bottom ash will be expected in low amount.
Chemical Waste
3.38
Chemical
waste generated from the air pollution
system as well as from machinery maintenance and servicing should be managed in
accordance with the Code of Practice on
the Packaging, Labelling and storage of Chemical Wastes under the
provisions of the Waste Disposal
(Chemical Waste)(General) Regulation. The chemical waste should be
collected by drum-type containers and removed by licensed chemical waste
contractor.
3.39
Plant
/ equipment maintenance schedules should be planned in order to minimize the generation
of chemical waste.
3.40
Non-recyclable
chemical wastes and lubricants should be disposed at an appropriate facility,
such as EPD Chemical Waste Treatment Centre at Tsing Yi. Copies or counterfoils
from collection receipts issued by the licensed waste collector should be kept
for record purpose.
3.41
Recyclable
chemical waste that is collected will be transported off-site for treatment by
a licensed collector. The Contractor will need to register with EPD as a chemical
waste producer. Where possible, chemical wastes (e.g. waste lubricants) would
be recycled at an appropriate facility, e.g. at Dunwell’s oil re-refinery.
Fly Ash
3.42
During
the operation phase of the Project, combustion gas temperature, residence time,
air supply and gas turbulence of the new cremators will be properly and
adequately controlled to optimize the effectiveness of combustion during
cremation process, thereby minimizing the generation of fly ash.
3.43
Fly
ash is collected by the APC equipment. This is designed to maximize the
collection of fly ash.
3.44
Disposal
method of fly ash from the cremators should be stored in sealed drums and
placed in a designated area for collection by CWTC. Fully incinerated residues
should be disposed to landfill.
General Refuse
3.45
Waste generated in offices should be reduced through
segregation and collection of recyclable waste materials (such as paper). To
promote recycling of waste paper, aluminum cans and plastic bottles, it is recommended
to place clearly labeled recycling bins at designated locations. The recyclable
waste materials should be collected by licensed collectors.
3.46
General refuse, other than segregated recyclable
wastes, should be separated from any chemical waste and stored in covered
skips. FEHD should remove general refuse from the site on daily basis to
minimize odour, pest and litter impacts. Also, open burning of refuse must be
strictly prohibited.