Table of Contents
The
Need and Justification for the Project
Consideration
of Alternative Options
Construction
and Demolition Programme
3 Key Findings of
Environmental Impact assessment
Environmental Monitoring and Audit
List of Figures
1.1
The
existing Cape Collinson Crematorium has started operation since 1962. Cremator
Nos. 1-10 were replaced in 1995 and Nos. 11-12 were commissioned in 2001.
1.2
The
existing cremators are approaching the end of serviceable life and further restoration
work is considered not cost-effective or sustainable. In
order to cope with an increasing demand for cremation service, Food and
Environmental Hygiene Department (FEHD) proposes to demolish the existing
crematorium as well as to construct and operate a new crematorium in-situ as a
replacement (hereinafter referred to as the Project). The Project will be developed in two phases.
The Need and Justification for the Project
2.1
The
number of cremation sessions has been rising steadily in the past three decades
and the existing cremators in the territory are operating at almost their full
capacities. In 2008, out of the total number of deaths of 41,530 in
2.2
The
old cremators at Cape Collinson Crematorium should be replaced in the public
interest and the capacity of the crematorium facilities should be expanded to
meet the increasing demand.
2.3
The
current
2.4
If
the existing cremators are not replaced and upgraded in time, or if sufficient
numbers of cremators are not provided for commissioning by 2012 (Phase 1) and
2014 (Phase 2), a considerable number of applications for cremation sessions
will unlikely be met within the present pledge of 15 days. Extended waiting
time for the bereaved family will not be acceptable to the community. In
addition, it is envisaged that the air quality in the vicinity of
Consideration of Alternative Options
2.5
Apart from the redevelopment of the existing Cape
Collinson Crematorium, the following alternative options have been considered
for the new crematorium: new sites in more remote areas; alternative site in
Tuen Mun Area 46; alternative extension at other existing crematorium sites;
expansion of the existing Cape Collinson Crematorium; and alternative in-situ
extension arrangements.
2.6
Taking into account the environmental benefits and dis-benefits
of different possible options, the preferred scenario is redevelopment of the existing Cape Collinson
Crematorium site by adjustment into its adjoining area so that the overall site
area can accommodate 10 cremators and other ancillary facilities by 2014. It is
selected for the following reasons:
l
It is
the most suitable option for early implementation to meet the rising demand for
cremation service as soon as possible;
l
Human
disturbance already exist in the current site and its vicinity, therefore the
environmental impact of the Project on the local environment is marginal
compared with a new development on a
l
In-situ
redevelopment in the existing site has a much less significant environmental
impact with regard to introducing a new source of air emission and visual
impact of a new crematorium facility to a new site;
l
The
existing cremators can be upgraded using the latest cremation technology as
soon as possible, thereby addressing the local concern and achieving the
environmental benefit of improving the air quality.
2.7
The
project site is the site of the existing Cape Collinson Crematorium at
Construction and Demolition Programme
2.8
The
Project will be carried out in two phases as outlined below:
Phase
1 (July 2010 to March 2012)
2.9
Four
new cremators, together with two multi-purpose service halls and other
necessary ancillary facilities, will be provided at the adjoining site to the
north of the existing crematorium. The total installed capacity of four new
cremators under Phase 1 will be about 583 kg/hour.
2.10
As
advised by FEHD, the existing crematorium will still be operating to serve the public
during the testing and commissioning (T&C) of the four new cremators under
Phase 1. However, special arrangement will be made to ensure that there will be
no more than ten of both existing and new cremators in operation at any time
(i.e. two new cremators and eight existing cremators) during T&C period to
avoid additional loading of chimney emissions to the environment.
Phase
2 (March 2012 to December 2014)
2.11
After
the satisfactory commissioning of the new cremators under Phase 1, the existing
crematorium as well as the existing underground fuel tank will be demolished
and removed. There will be no overlapping of construction/demolition works
between Phase 1 and Phase 2. Six new cremators, together with one multi-purpose
service hall and other necessary ancillary facilities, will be provided under
Phase 2. The total installed capacity of six new cremators under Phase 2 will
be about 943 kg/hour.
2.12 The proposed Project will have the following key environmental and social benefits:
l
The
Project will be able to address the increasing cremation demand without
construction of additional cremators as the efficiency of the new cremators is
much improved;
l
The
existing cremators can be upgraded within the shortest possible time to address
local concern on air emissions;
l
Installation
of new cremators of improved design and air pollution control technologies will
improve the air quality in the vicinity of the
l
Instead
of ultra low sulphur diesel, Towngas has been selected as burning fuel for the
new cremators to further reduce emissions of air pollutants from fuel
combustion, thereby to be more environmentally-friendly;
l
The
Project will be able to address the increasing cremation demand efficiently by avoiding
the long lead time required to get a piece of vacant and earmarked land for
adding a new crematorium in the relevant statutory plan;
l
Food,
Environment and Hygiene Committee (FEHC) under the Eastern District Council at
its meeting in 2008 supported the reprovisioning plan by emphasizing the need
for timely replacement of the crematorium to improve air emission quality.
3 Key Findings of Environmental Impact assessment
3.1
The
potential air quality impacts from the construction of the Project would mainly
be related to construction dust from site clearance,
ground excavation, cut and fill operations and construction of the new
cremators and other ancillary facilities. The potential dust
impact arising from the demolition and construction of the Project was
assessed. Results showed that the
predicted air quality at the air sensitive receivers (ASRs) would comply with
and far below the respective criteria with the implementation of dust
suppression measures as stipulated in the Air Pollution Control (Construction
Dust) Regulation. The predicted highest hourly and daily TSP concentrations
during Phase 1 construction are
3.2
During
the operation of the Cape Collinson Crematorium, the potential sources of air
quality impacts would be the air emissions from the stacks of incineration
process. The assessment results indicated that the
predicted air pollutant concentrations at all representative ASRs would comply
with the respective criteria. The highest hourly NO2 concentrations
of 179 mg/m3 would occur at the staff quarters of Cape Collinson Crematorium,
which is the nearest ASR to the emission source, would still comply with the
relevant Air Quality Objective of 300 mg/m3.
3.3
Air pollution control and stack
monitoring system will be installed for the Cape Collinson Crematorium to
ensure that the emissions from the cremator stacks will meet the target
emission limits equivalent to those stipulated in
3.4
With the implementation of
practicable air pollution control, the Cape Collinson Crematorium will not
cause adverse air quality impact at all representative ASRs during operation
phase.
3.5
Waste likely to be generated
during the construction phase of the Project includes excavated material,
construction and demolition materials, contaminated materials, chemical waste
and general refuse. Ash and
non-combustible residues, chemical waste and general refuse are expected to be
the major types of waste arising from the operation of the new crematorium.
3.6 With effective implementation of the good practices and mitigation measures, it is anticipated that the impacts on the environment and the potential impacts on the capacity of waste collection, transfer and disposal facilities will be insignificant during both construction and operation phase.
3.7
Prior to the demolition phase of the existing
crematorium, further contamination investigation will be carried out to confirm
quality and quantity of contaminated materials (including those contaminated by
asbestos and dioxins).
3.8
A land contamination assessment
was undertaken and lead contamination in soil was found at the borehole BH-1 near the
existing underground fuel tank at the depth of
3.9
Further
site investigation in areas that are currently in use and cannot be accessed
will be undertaken after decommissioning and prior to the demolition of the
existing crematorium. These areas
include the trial pit for soil sampling underneath the pipeline and two
cremation rooms.
3.10 As Towngas will be used as burning fuel instead of ultra low sulphur diesel in the new crematorium, leakage or spillage from the underground fuel tank and the pipeline system is eliminated. With the new design of cremators, aerial deposition of contaminants will be insignificant. Land contamination due to the operation of the new crematorium is unlikely.
3.11
Visual impact on R1 (
3.12
The
architectural appearance of proposed crematorium will be aesthetically designed
to be compatible with adjacent landscape setting to enhance the overall outlook
to minimise visual impact during operation phase. Roof greening will be
adopted for the provision of landscape amenity and character of remembrance. Landscape roof garden will enhance
and embrace the amenity space with the existing
3.13
Overall, the residual visual
impacts of the proposed development are acceptable with mitigation measures
during construction and operation phase.
3.14
The construction noise impacts of the Project during
normal daytime working was assessed. The predicted unmitigated noise levels at
representative NSRs would range from 60 to 79 dB(A)
for Phase 1 and 61 to 81 dB(A) for Phase 2. With
the use of quiet powered mechanical equipment for excavator/loader, soil
nailing drilling machine, rock dowel drilling machine, bulldozer, dump truck and crawler mounted rock drill, the noise levels at all
representative NSRs would comply with the construction noise limit of 75 dB(A).
3.15
The
noise impact associated with the operation of the Project was assessed. The predicted unmitigated noise levels at all representative NSRs
would exceed the night-time planning noise criteria by 1 to 6 dB(A). The potential noise impact at the
NSRs will be mainly from the operation of the radiators on the roof of the
crematorium building. To mitigate the noise impact at
the affected NSRs, 2.5m high noise barriers have been proposed to surround the
radiators. Besides, the noise barrier will be lined with sound absorbing
material at the surface of the barrier facing the noise source to further
enhance the noise reduction effectiveness. With such noise barriers in place,
the predicted noise levels at all representative NSRs ranging from 43 to 49
dB(A) will comply with both the daytime and night-time planning noise
criteria.
3.16
For the concurrent operation of
existing fixed plant and new fixed plant during T&C stage of Phase 1, the
predicted cumulative noise levels at all representative NSRs will comply with
the relevant daytime/evening Acceptable Noise Level of 65 dB(A) with the 2.5m
high noise barriers for the radiators in place.
3.17
Water
quality impacts from the land-based construction and demolition works can be
controlled to acceptable levels by implementing the recommended mitigation
measures. No unacceptable water quality
impacts will be expected from the land-based construction and demolition
activities. Site inspections should be undertaken routinely to inspect the
works areas in order to ensure the recommended mitigation measures are properly
implemented.
3.18
No effluent will be discharged
from the Air Pollution Control equipment in the new crematorium as “dry” process
will be adopted. Sewage generated by visitors and workers, as well as
wastewater from cleaning activities will be connected to the sewerage
system. Sewerage impact assessment has
been conducted for the Project. Assessment results indicated that the
additional wastewater / sewage generated from the Project would not cause any
adverse impacts to the existing sewerage systems. Hence, adverse water quality
impact during operation phase is not expected.
Environmental Monitoring and Audit
3.19
Environmental
monitoring and audit (EM&A) requirement for the Project have been specified
in an EM&A Manual. The EM&A
Manual contains details of proposed baseline and compliance monitoring
programme, implementation schedule of the environmental mitigation measures,
EM&A reporting procedures and complaint handling procedures.
4.1
The
findings of this EIA have provided information on the nature and extent of
environmental impacts arising from the construction and operation of the
Project. The EIA has, where appropriate, identified mitigation measures to
reduce the environmental impacts to acceptable levels.
4.2
In
general, the environmental impacts arising from the Project are either
considered minimal or can be mitigated to an extent where the impacts on the
sensitive receivers are acceptable. No unacceptable residual impacts
are anticipated, provided that the recommended mitigation measures are properly
implemented. Monitoring and audit requirements have been specified in a
stand-alone EM&A Manual to ensure proper implementation of the recommended
mitigation measures.