2                                  Project Description

2.1                            Operation of the CCPP

The pilot plant, combining thermal treatment of municipal solid waste (MSW) with cement production, was developed by GIC in collaboration with the Chemical Engineering Department of the Hong Kong University of Science and Technology (HKUST).  The pilot demonstration was funded by the Innovation and Technology Fund under the University-Industry Collaboration Programme.  The CCPP consists of a MRRF at the front-end followed by a patented thermal process for integrated treatment of the MSW.   

Before the plant was built, the GIC submitted its Specified Process (SP) licence application to the EPD under the Section 14 of the Air Pollution Control Ordinance.  The first licence was granted on 25 November 2003 and was renewed in 2005.  According to the licence’s conditions, the CCPP could only be in operation for a cumulative duration of 16 weeks (maximum) over the licensing period.  

The CCPP was installed within the GICP at Tap Shek Kok by February 2005 and commissioning trials were undertaken in April and July/August 2005 in order to demonstrate its performance to EPD according to the licensing conditions.  Continuous operation of the plant was started in early October 2005 and completed in December 2005 (for a cumulative period of 11 weeks).  No more than 24 tonnes of MSW were treated per day during the pilot demonstration of the CCPP.  Figure 2.1a shows the layout of the GICP and the location of CCPP.  Figure 2.1b shows the detailed layout of the CCPP.

During the operation of pilot plant, the GIC and HKUST obtained satisfactory results and sufficient design and operational data on the Co-Combustion technology.  All MSW delivered to the site was treated and no MSW is currently stored on-site.  All the Co-Combustion residues (including bottom ash and fly ash) were securely packed in labelled sealed bags and stored in the covered waste reception hall of the MRRF building.

An air quality monitoring programme was commenced in December 2004 and continued throughout the pilot demonstration of the CCPP until one month after the completion of the trials.  The Hong Kong Productivity Council was employed as the independent consultant for monitoring of flue gas emissions and ambient air quality at the site. 

Monitoring equipment was installed in the stack of the CCPP for the continuous monitoring of Total Organic Carbon (TOC), Hydrogen Chloride (HCl), Hydrogen Fluoride (HF), Sulphur Dioxide (SO2), Nitrogen Oxides (NOx), Carbon Monoxide (CO) and opacity in the flue gas emissions during the operation of the CCPP. 

Two off-site air quality monitoring stations were established in Butterfly Estate and Lung Kwu Tan Village to monitor the potential air quality impacts to these Air Sensitive Receivers (ASRs).  Ambient air quality was monitored at these stations before (to establish the baseline conditions) and during the operation (impact monitoring) of the CCPP.  The parameters monitored included Total Suspended Particulates (TSP), Respirable Suspended Particulates (RSP), Nitrogen Dioxide (NO2), Sulphur Dioxide (SO2), dioxins and heavy metals.   

Monitoring results show that the operation of the CCPP did not cause adverse air quality impact to the identified ASRs.  The results (including the flue gas emission and ambient air quality measured at the off-site monitoring stations) can be found on the GIC’s web page at http://www.gii.com.hk/eng/coco_main.htm.

2.2                            Demolition of CCPP

2.2.1                      The Need of the Project

The CCPP was designed as a pilot demonstration process and had the following objectives:

·           to demonstrate that the Co-Combustion plant could meet EPD’s Best Practical Means for Incinerators (Municipal Waste Incineration) (BPM 12/1 (08)); and

·           to obtain engineering data to refine the design of the Co-Combustion Process. 

The pilot demonstration has fulfilled its objectives and the CCPP was closed down on 17 December 2005.  It is necessary to demolish the whole pilot plant so that the Project Site could be released for the operation and future development of the GICP.  The residues attached to the wall of the process equipment and units will be removed prior to reuse/disposal.  It facilitates better materials recovery and recycling as the equipment and steel structure can be reused overseas or recycled locally.

Without this Project, the equipment, plant and buildings will be left on site and have to be regularly maintained by GIC to ensure their structural integrity.  The residues of the CCPP will continue be stored on site.  In the long-term, there is a potential of release of the residues due to degradation of the storage bags/containers.  Most of the plant and equipment for the materials recovery facilities are still in good serviceable conditions and can be reused for other waste management facilities.  If the CCPP is not demolished, the conditions of the equipment will be deteriorated and hence reduce the reuse opportunity of the equipment.   This Project will not only enable the reuse of the materials recovery equipment, and minimise the long-term environmental risk of storage of residues on site but also will release the Project Site for operation and future development of the GICP.

2.2.2                      Structures to be Demolished

The CCPP will be demolished and all structures, plant and equipment, foundations and footing will be dismantled and removed from the site.  The site area will be restored into an open area for operations and development. 

The structures to be demolished including their sizes and heights are shown in Figures 2.2a to 2.2c.

2.2.3                      Consideration of Alternative Demolition & Cleaning Methods

All equipments and buildings of the CCPP are asbestos-free.  Reusable equipments, such as materials sorting equipments, will be sold to second hand equipment vendors for reuse in other similar plants.  The decommissioning works will begin by dismantling the process equipment into segments and disconnecting/removal of main process components.  All equipment segments and pipes will then be cleaned ([1]) in a designated area within the MRRF building prior to removal from the site for recycle or disposal.  

Various dismantling/demolition methods have been considered and were compared in terms of engineering feasibility, potential environmental impacts and cost implication with reference to the Buildings Department’s Code of Practice for Demolition of Buildings (2004) and other overseas projects ([2]) ([3]).  The assessment of alternative demolition methods are presented in Table 2.2a.  

After the process equipments and structures been dismantled and demolished, a cleaning process will be carried out to allow recycling of the scrap metals and to minimise the potential environmental impacts associated with the disposal of the non-recyclable waste at landfills.  Various cleaning methods (1) have been considered and are summarised in Table 2.2b.


Table 2.2a  Comparison of Potential Dismantling/ Demolition Methods for the CCPP

Method No.

Description

Principles/ Procedures

Engineering Feasibility

Potential Environmental Impacts

Cost Implication

1

Loosing the flanges, cutting & lifting

Dismantling the steel structures by loosing the nuts and bolts and flanges, or cutting the structure using mechanical, thermal or laser saw and then lift from top to the ground

 

It is the most common method for dismantling steel structures.  Simple equipment will be required (eg electrical or hydraulically powered hand held tools).  The structures can be dismantled with care and hence minimise the potential release of the Co-Combustion residues to the environment.  Both ends of the structures will be sealed immediately after dismantling to contain the residues inside the structure. 

 

Electrical or hydraulically powered hand held tools will be used and the potential for air and noise impacts will be minimal.  As the structures can be dismantled with care and hence minimise the potential release of the Co-Combustion residues to the environment.  

Low

2

Top down methods

Breaking away the structure by jack hammer, percussive or pneumatic hammer

This method is mostly used for concrete structures.  

 

Potential release of Co-Combustion residues that remain in the process lines of the CCPP to the environment, which may cause adverse environmental impacts.   

 

Low

3

Hydraulic crusher with long boom

Breaking the structure using a machine mounted hydraulic crusher with long arm extension

 

The hydraulic crusher can be operated from the ground outside the building or adjacent to the structures.

 

Potential release of Co-Combustion residues that remain in the process lines of the CCPP to the environment, which may cause adverse environmental impacts.

Medium

4

Wrecking ball

Destruction by impact of steel ball suspended from a crane

Suitable for dilapidated buildings, silos and other industrial facilities; requires substantial clear space and demands high level skill operators and well-maintained equipment.  As the dismantled plant and equipment will be deformed, it will be difficult to decontaminate the equipment.  It is therefore considered that this method is not appropriate.

 

Potential release of Co-Combustion residues that remain in the process lines of the CCPP to the environment, which may cause adverse environmental impacts.

Medium

5

Implosion

Use of explosives

Applicable for concrete structure but not suitable for incinerator/process equipments. 

Potential of dispersion of building debris into adjoining land during blasting and could cause significant dust, noise and vibration problems.  Potential release of Co-Combustion residues that remain in the process lines of the CCPP to the environment, which may cause adverse environmental impacts. 

 

High

6

Drilling

Coring, drilling and cutting by stitch drilling

This is suitable for concrete structures but not for thermal treatment facilities or process equipment.  With respect to the nature of the structures (ie steel structures and processing equipment) of the CCPP, this method is not suitable.  

Potential release of Co-Combustion residues that remain in the process lines of the CCPP to the environment, which may cause adverse environmental impacts. 

 

Medium 

7

Non explosive demolition agent (NEDA)

Use of static demolition agent to generate an expansive pressure to crack and break concrete and stone

 

Not applicable to slabs and walls.

Low vibration, noise and dust impacts.

High

8

Thermal lance

Use of intense heat by fusion of metal

 

Involves very high temperature up to 2,000 to 4,000°C and therefore requires special precautionary measures and care.

Low vibration, noise and dust impacts.

High

9

Water jet

Jetting of water at high pressure

Requires protection of person and properties from high pressure water.  With respect to the nature of the structures (ie steel structures and processing equipment) of the CCPP, this method is not suitable.

Large amount of wastewater with slurry of concrete debris and aggregate will be generated. 

Medium

 


Table 2.2b Comparison of Potential Cleaning Methods for Process Equipments and Structures

Method No.

Description

Principles/ Procedures  

Advantage

Disadvantage

A

Manual wet wiping and scrubbing

Manual wiping and scrubbing by workers

·      Suitable for small scale decontaminations

·      Suitable for low-hazard potential buildings and equipments

·      Low cost

 

·      Labour intensive

·      Requires protection of person and properties from potential contaminated environment

B

Vacuum cleaning

Make use of vacuum cleaner

·      Require simple skills and equipments

 

·      Not suitable for fastened materials

C

Abrasive blasting

High speed impingement of particles on an object with the purpose of abrading away surface materials

 

·      High decontamination capability

·      Containment of abrasive media and debris generated

D

Vibratory Decontamination Unit

A vibrating tub of metal beads that act to abrade particle, rust, debris etc. from the surfaces; a liquid flushing system is used to wash debris off of the decontaminated item prior to exit chute. Materials has to be cut into small pieces (< 30cm in diameter)

·      Sectioned materials will occupy less volume

·      Sectional materials will has higher packaging efficiency

·      Materials have to be cut into small pieces

·      Equipment may not be available locally and it required large area for the decontamination activities 

·      Resulted in a liquid waste for disposal

·      High cost and not common locally

 

E

Chemical flushing

Dissolve away surface contamination from materials

·      A variety of chemicals are available for decontamination

·      Resulted in large volume of liquid waste requiring disposal

 

F

Electro-polishing  

Similar to chemical flushing except that an electrical charge is applied to the items being decontaminated to create an accelerated corrosion reaction.

·      Removal of surface materials from metallic items along with the contaminants on their surface

·      Required corrosive liquid as the electro-polishing medium

·      Resulted in large volume of liquid waste for disposal

·      Only applicable for metallic items

·      Expensive

 

G

Ultrasonic

Transmitting high-frequency impulses though a liquid medium on the surface of a contaminated object.

·      Safe operation

·      Materials have to be cut to fit into an ultrasonic cleaning tank.

·      Resulted in liquid waste requiring disposal

 

H

High pressure water lance

 

High-pressure water spray

·      Require simple equipments

·      Resulted in large volume of contaminated wastewater requiring treatment prior to disposal

 

I

High-temperature water spray system 

Provide cleaning spray and a vacuum collection system

·      Suitable for removing loose contamination on concrete and brick surfaces

·      Not applicable for hard or smooth surface


2.2.4                      Selection of Preferred Demolition and Cleaning Methods

The selection of preferred demolition/dismantling methods has made reference to the common demolition methods in Hong Kong and the characteristics of the Project such as size of the CCPP, building materials, degree of potential contamination, demolition/dismantling duration, etc to avoid prolonged adverse environmental impacts.  

The main system and MRRF building of the CCPP are mainly made of steel while the fire service water tank and pump house are made of concrete.  In view of small size of the CCPP, the best option for dismantling the steel structures (e.g. the MRRF Building) and process equipment (e.g. the Co-Combustion unit) will be the loosing the flanges /cutting and lifting method (ie Method 1 in Table 2.2a).  Mechanical cutting and thermal cutting are most common and will not cause significant environmental impacts.  Other cutting methods (e.g. laser cutting/saw) which have a better cutting ability, are not considered with respect to the plate thickness of the CCPP and MRRF building.  The sequence of the demolition works will be from the top to the bottom of the structures.   

For the small concrete structures of the fire service water tank and pump house, breaking away the structure by jack hammer, pneumatic or hydraulic breaker (i.e. Method 2 – top down method in Table 2.2a) will be used. 

Noise and dust impacts could easily be controlled by practical mitigation measures, such as low noise equipment, temporary noise barriers and water spraying at the work area, which are commonly used in Hong Kong.   

The process equipments and structures of the Co-Combustion unit will then be cleaned before recycling or disposal.  With respect to the small scale of the Project, wet wiping (i.e. Method A in Table 2.2b) and vacuum cleaning (Method B in Table 2.2b) are considered to be best suited and most cost effective for the Project.  The cleaning will be conducted using a combination of scraping and vacuum cleaning, followed by wet wiping.  Table 2.2c summarises the procedures.

 

Table 2.2c      Selected Cleaning Methods

 

Scraping/ Vacuum Cleaning

Wet Wiping

Procedures

Residues attached to the wall of the equipments will be removed by scraping and then collected by vacuum cleaner. 

Damping down the dust inside the ducts and equipment and then cleaned dust with wet cloths or other appropriate absorbents (eg paper towels). 

 

Applicable areas / instruments

Lining inside the rotary kiln, secondary combustion chambers, gas cooler, bag filter chambers and internal lining of pipes and ducts. 

 

Lining inside the rotary kiln, secondary combustion chambers, gas cooler, bag filter chambers and internal lining of pipes and ducts.

 

Secondary  pollution

Residual dust will be collected by the vacuum cleaner with HEPA filter so that no dust will be escape to the atmosphere.  Solid wastes will be stored in sealed bags/containers for reuse/disposal. 

 

Additional waste will be generated from the clothes or paper used for the cleaning which will be disposed at a designated landfill. 

 

Final Disposal / Treatment

The solid residues are intended to be reused as the raw materials for cement production. 

 

The solid residues will be reused as the raw materials for cement production.  The cleaning materials will be disposed of at a designated landfill.

 

Health and Safety of workers

Full body protection PPE will be provided to the workers.  Potential of disturbing the dust during the vacuum cleaning process as the dust may escape to the atmosphere if not properly contained. The effectiveness of the HEPA filter needs to be checked regularly to ensure no damage.

Full body protection PPE will be provided to the workers.  Dust generation is minimised by wetting the surface before wiping.

To prevent the unintentional spread of the residues and dust throughout the process area, the cleaning process will be conducted inside the enclosed cleaning workshop (i.e. the MRRF building after removal of all equipments, see Section 2.4 for further details) where forced ventilation will be provided and a slight negative pressured be maintained.  All dust and residues collected will be packed into labelled polyethylene (PE) bags and will be reused as the raw materials for cement production. 

2.3                            Demolition Methodology

The CCPP has been closed down awaiting decommissioning after the completion of the pilot demonstration.  All structures and the associated foundation, and plant and equipment will be dismantled, cleaned (where necessary) and removed from the Project Site for reuse, recycling or disposal.  The concrete slab of the Project Site will be demolished and the site will be backfilled with a layer of imported clean soil.  The Project Site area will be levelled and landscaped.  

Before the commencement of the demolition works, the Project Site area will be cordoned off and the access to the works area will be controlled ([4]) ([5]) .  The south-east side of the CCPP will be separated from the existing cement plant by hoarding.  Hoarding on the other sides are not considered necessary as the site is separated from the cement plant by existing road and drainage channel.  Safety is a prime consideration of the Project.  All required preparation works and general safety measures (including safety training, awareness programmes and provision of personnel protective equipments) will be in place before the commencement of the demolition works.  Only authorised persons who have attended the appropriate safety training would be allowed to work at the site.  Appropriate fire fighting equipment (eg fire extinguishers) will be provided at designated locations.

The overall sequence of demolition works is as follow:

·           Cordon off the site and erection of hoarding;

·           Disconnect the utilities (except for the power and water supplies to the fire services pump room and water tank);

·           Dismantling and removal of all plant and equipment inside the MRRF building;

·           Dismantling and removal of the Co-Combustion unit;

·           Cleaning of the Co-Combustion unit within the enclosed cleaning workshop inside the MRRF building;

·           Demolition of the steel structure of the MRRF building;

·           Demolition of the fires services pump room and water tank;

·           Demolition of the concrete slab and shallow footing foundation;

·           Backfilling the site with clean soil;

·           Provision of surface water drains at the site;

·           Landscaping the Project site area. 

The whole demolition process will be conducted in a safe manner for the protection of the workers and to minimise occupational health and safety hazards.  Detailed description of the demolition procedures and safety precautions are discussed in the following sections. 

2.3.1                      Site Preparation and Access Control

Before the demolition works, the Project Site will be cordoned off by hoarding or fencing.  Portable barricades will be used to separate different work zones within the Project Site where demolition works are in progress.  Suitable metal scaffolding working platform will be erected. 

The access to the Project Site will be controlled by security guards and no unauthorised persons will be allowed to enter the site.  Appropriate warning signboards will be posted around the perimeter of the Project Site.

2.3.2                      Demolition of the Fire Services Water Tank and Pump House

The pumps and control panels will be dismantled and sold to scrap metal recyclers.  All water in the water tank will be drained out.  The concrete wall of the water tank and the pump house will be demolished and removed by a pneumatic drill mounted backhoe.  The concrete structures will be damped down before and during the demolition works to control dust.  The steel reinforcement will be recovered as far as practicable for recycling.  The broken concrete will be disposed of at the public fill reception facilities.  The load will be properly covered with tarpaulin to minimise dust during transportation.

2.3.3                      Demolition/ Dismantling of the Co-Combustion Unit

The duct works of the Co-Combustion unit and the gas cooler will be dismantled by removal of the bolts or cutting at the joints.  The openings (both ends of ducts) will be immediately sealed with 2 layers of fire retardant polyethylene sheets to prevent escape of any dust within the duct.  The sheets will be secured with duct tapes.  The capped equipment sections/pieces will be lowered to ground level by crane.  Where necessary, the sections will be cut into smaller size to facilitate cleaning and transportation. 

The internal wall of the ducts will be properly cleaned with wet cloths or other suitable absorbents to remove the loose dust deposits.  The cleaning materials will be collected and placed in sealed bags and disposed of at a designated landfill. 

The refractory bricks of the rotary kiln will be removed before lifting the whole equipment down to the ground.  The refractory bricks will be placed in sealed bags and disposed of at a designated landfill.  The internal wall of the secondary combustion chambers will be damped down prior to dismantling.  The steel frame of the equipment will then be cut into manageable sections and sold to scrap metal recyclers. 

All filter bags from the dust collector will be removed and placed in sealed bags for disposal at a designated landfill.  The residual ash will be placed inside a sealed bag.  The metal casing of the dust collector will be properly cleaning using the same procedures for the duct works.  The cleaned dust collector will then be sold as scrap metal. 

2.3.4                      Dismantling of the MRRF Equipments

The main power supply to the Project Site will be cut off and all electrical cable and electrical equipment will be disconnected before the demolition works.

The materials recovery/recycling equipment (including shredder, conveyor belts, picking station, magnetic separator, eddy current separator, etc) in the MRRF building will be disassembled using powered mechanical hand tools and removed.  Most of the plant and equipment are still in good serviceable conditions and will be sold to other MRRF operators or second hand equipment vendors.   

2.3.5                      Demolition of Steel Structure of MRRF Building

After having dismantled and removed all machinery and equipments, and cleaning of the Co-Combustion unit, the steel frame structure of the MRRF building will be demolished in accordance with the Code of Practice for Demolition of Buildings and generally in the reverse order to that of their construction.  This building was used for reception sorting of MSW to recover recyclables.  There is no potential of concern of land contamination.  The structures will be demolished progressively from top to bottom.  The external non-loading bearing cladding or any non-structural elements will be removed first.  Crane and lifting gear will be used where possible to support the structural beams and columns whist they are being cut and lowered to the ground.  Air-powered wrenches, cutting torches, cranes and similar industrial equipment will be used.

The steel beams and column will be cut to manageable size to facilitate transportation.  This together with the metal claddings and scrap metals from the MRRF equipment will be sold to the scrap metal recyclers.

2.3.6                      Demolition of the Foundation and Concrete Pavement  

The foundation (including the reinforced concrete footing, plinths, with a maximum depth of 1.5m below ground) of the MRRF building, water tank and Co-Combustion unit will be demolished by hydraulic breakers and removed.   The concrete slab of the Project Site will then be demolished.  The demolition debris will be further broken down into manageable sizes (<250mm) and loaded on to dump trucks for transportation to public fill reception facilities.  Steel bars will be separated from concrete for recycling. 

The Project Site will then be backfilled using clean imported soil and landscaped.

2.4                            Cleaning of the Co-Combustion Unit

After all the machinery and equipment were removed, half of the MRRF building will be converted into a cleaning workshop for cleaning works.  At the entrance to the cleaning area, warning signs in both Chinese and English will be posted in a prominent location outside the cleaning workshop throughout the entire period of the decommissioning works.

The cleaning workshop will be provided with forced ventilation and a slight negative pressure would be maintained within the cleaning workshop during the cleaning works.  The exhaust air from the cleaning workshop will be cleaned using a High Efficiency Particulate Air (HEPA) filter prior to discharge to the atmosphere. 

The characteristics of the residues were analysed.  The results show that the physical and chemical compositions of the both residues are similar to those of the typical clinker raw materials (including pulverised fly ash and bottom ash from coal fired power station, iron/copper slag).  The ingredients of both residues show the normal chemical substances associated with cement clinker raw feed materials (calcium carbonate/calcium oxide/calcium salts, alumina, and iron/copper slag).  The residues contain very low levels of heavy metals and extremely low levels of (in the order of part per trillion) dioxins (see Table 5.5c).  To minimise the exposure of residues, the workers will wear appropriate PPE (including face mask, protective gloves, overcoat, and safety boots).

It is expected that a small quantity of residues (e.g. fly ash, bottom ash) will remain inside the Co-Combustion unit since the operation of the CCPP was completed.  The materials that may still be present in the gas cooler and dust collector etc. are estimated to be less than 5 m3 in total.  The decommissioning process will start with removal of all residues remaining in the CCPP system by a vacuum cleaner with a HEPA filter.  Any residues attached within the equipments will be removed by a combined method of scraping and cleaning.  The internal surfaces of the equipments will be cleaned by wet wiping. 

The scraped lining material will be placed in sealed bags and disposed of at a designated landfill.  The filtered materials, and cloths used for wet wiping will be packed in sealed bags and disposal of at a designated landfill.  With proper precautionary measures and handling procedures in place, contamination of steel structure of the MRRF is not anticipated.

During the entire decommissioning process, strict industrial hygiene and safety control will be exercised to protect workers from contact with the residues.  The safety procedures to be used will include the use of personal protective gear such as chemical resistant clothing, gloves, boots and/or shoe covers, hard hats, full-face positive pressure respirators equipped with a cartridge that filter particulate, and other standard safety equipment. 

After completion of the cleaning process of the Co-Combustion equipment and removal of the equipment, the cleaning workshop will be vacuum cleaned and wet wiping.  The cleaning materials will be disposed of at designated landfill.

2.5                            Decommissioning Programme

All operation of the CCPP ceased on 17 December 2005 after it achieved the Project objectives as stated in Section 2.3.1.  Since that date the facility has been mothballed pending approval to decommission.  The tentative programme for the demolition, cleaning and disposal works is shown in Table 2.5a.

Table 2.5a      Tentative Programme for the Demolition, Cleaning and Disposal Works of CCPP

Tasks

Tentative Date

Issue of Environmental Permit by EPD

June 2009

Issue of Buildings Department Permit

July 2009

Demolition Works Tendering

June 2009

Site Preparation for Demolition Works

July 2009

Demolition and Cleaning

August to December 2009

Disposal of Scrap Materials

September to December 2009

Backfilling & Re-surfacing

December 2009

Completion of Demolition and Decommissioning

December 2009

 



([1])     The chemical analyses of the residues (including the fly ash, bottom ash and a small quantity of residues remaining in the plant and equipment of the thermal treatment unit) show that the residues contain very low level of heavy metals and extremely low concentrations of dioxins and furans (in term of part per trillion, see Section 5) . The physical and chemical compositions of the residues are similar to those of the typical clinker raw materials. The residues will be reused on-site for the production of cement.  The ground investigation shows that the soils to be distributed during the demolition works (ie for demolition of the shallow foundation of the CCPP) are not contaminated with reference to the RBRG standards (see Section 4).  The term cleaning method is therefore used in the description. 

([2])     Decontamination and Decommissioning Assessment for the Waste Incineration Facilities (Building 232-Z), United States Department of Energy, February 1994.

([3])     Development of Decommissioning Technology for Nuclear Power Plants in NUPEC. http://www.nupec.or.jp/database/paper/paper_12/p12_plant/R12-05-02.htm

([4])     It should be noted that the Project Site is located with the GICP site.  The access to the GICP (hence the Project Site) is controlled by the security guards on 24 hours basis.  No unauthorised access is allowed.  In addition, the Project Site will be cordoned off or segregated from the other parts of the GICP by hoarding and access to the Project Site will be controlled.

([5])     The Project Site boundary is not adjoining a public road, street, service land or other area accessible to the general public.  It is therefore considered that a site hoarding will not be required.  However, hoarding will be erected along the eastern boundary of the Project Site to separate the demolition works with the cement plant operation.