This Section presents the assessment of
potential land contamination impact associated with the demolition of the CCPP
at the GICP. The assessment identifies
the potential source of land contamination, summarises
the intrusive site assessment findings and recommends mitigation
measures, monitoring and audit programme to minimise potential environmental implications from
demolition of the CCPP, and assesses potential residue impacts after the
implementation of the mitigation measures.
A site appraisal
of CCPP was carried out to identify potential sources
of land contamination within the Project area and a Contamination Assessment
Plan (CAP) was prepared outlining a programme for the intrusive site investigation at
the CCPP to determine presence and extent (if any) of contamination at the
Project area. References are made to
potential land contamination that may be present due to the historical and
current land uses of the Project area and the surroundings during the proposed
demolition works and the proposed future uses of the Project area. The CAP was approved by the EPD in January
2008.
Land contamination site investigation was
carried out in accordance with the CAP in February, 2008. Upon completion of the site investigation, a
Contamination Assessment Report (CAR) was prepared detailing the investigation
programme, on-site observations and the results of the soil sampling and
testing. The CAR was endorsed by the EPD
in May 2008.
This land contamination assessment has
been undertaken in accordance with the requirements of Section 3.4.2 of the EIA Study Brief and makes reference
to the CAP, dated 7 January 2008 (a copy of which is included in Annex A1) and the CAR, dated 11 April 2008
(a copy of which is included in Annex A2).
4.2
Legislative
Requirements and Evaluation Criteria
As described in Section 1, the
decommissioning of the CCPP is classified as a designated project under Item 3
of Part II Schedule 2 of the Environmental
Impact Assessment Ordinance (EIAO)
and hence it requires an EP prior to the decommissioning works.
Section 3.2.1 (ii) of the EIA Study Brief requires the EIA study
to address likely issues associated with the land contamination due to past
uses at the site. The brief requires the
contamination impact to be evaluated and assessed as stipulated in Section 3 of
Annex 19 of the Technical Memorandum on
the Environmental Impact Process (EIAO-TM),
issued under Section 16 of the EIAO. Annex
19 of the EIAO-TM: Guidelines for Assessment of Impact on Sites
of Cultural Heritage and Other Impacts provides guidance on contamination
assessment of potential contaminated land.
The assessment of land contamination
sources and the potential impacts to particular development projects are guided
by the EPD’s Guidance
Manual for Use of Risk-based Remediation Goals (RBRGs)
for Contaminated Land Management (the RBRG Guidance Manual), the associated
Guidance Note for Contaminated Land
Assessment and Remediation, and the EPD’s Guidance Notes for Investigation and
Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and
Car Repair/Dismantling Workshop. The
RBRGs were developed for four different
post-restoration land-use scenarios. The
Project Site is classified as an Industrial Site under the RBRGs.
Of particular relevance to the land
contamination assessment for this Project is the concept of preparing a
conceptual site model (CSM) for the site, which is referred to in The Guidance Manual for Use of Risk-based
Remediation Goals for
In addition, reference has been made to
the following documents published by the EPD.
·
Waste
Disposal Ordinance (Cap
354);
·
Waste
Disposal (Chemical Waste) (General) Regulation (Cap 354C);
·
Code
of Practice on the Packaging, Labelling and Storage of Chemical Wastes, EPD (1992); and
·
Waste
Disposal (Charges for Disposal of Construction Waste) Regulation (Cap 354N)
The following sections describe the
Project Site, its environmental setting and the CSM.
The following information is contained in
the CAP in Annex A1 and referenced as
deemed necessary.
4.3.1
Site Environmental Setting
The Project Site is surrounded by the
following land uses.
·
North: a lawn beyond which is situated a LPG store (to the
northwest), and a container office (to the northeast);
·
South: an internal road, beyond which is the Pulverised
Fly Ash (PFA) Grinding and Classification system;
·
East: the operating cement kiln; and
·
West: an internal road, beyond which is situated a Pack
House and cement silos (to the northwest) and to the southwest, underground
fuel storage tanks.
The overall setting of the Green Island
Cement Plant (GICP) within which the CCPP is situated is as follows.
·
North: the
·
South: the sea;
·
East: the Shiu Wing Steel works;
·
West: the
The GICP site is constructed on land
reclaimed from the sea and as such the underlying groundwater is not considered
to be a resource. Figures D1 and D2 of the
CAP (see Annex A1) illustrate the
fill materials underlying the GICP site, which appear to be natural hillside
stone.
The whole CCPP site area was paved with
concrete or asphalt during its operation.
Figure B1 of the CAP shows the layout plan of the CCPP.
4.3.2
Description of Existing Conditions
The operation of the CCPP commenced in
October 2005 and was stopped in December 2005.
No chemicals or hazardous substances were handled at the CCPP. Municipal Solid Waste (MSW) (eg paper, plastics, metals and putrescible
materials) was delivered to the Materials Recovery/Recycling Facility (MRRF) by
refuse collection vehicles. The waste was
unloaded onto an impermeable concrete ground surface and then loaded to the
MRRF to recover recyclable materials in the waste. The residual waste was shredded and fed to
the co-combustion unit to recover energy from the waste. The flue gas from the combustion process was
cleaned prior to discharge to the atmosphere.
The CCPP comprised the following key
components:
·
The
MRRF which consisted of a waste reception hall, trommel
screen, separators, shredder, belt conveyors and an underground wastewater
storage tank. The wastewater was fed to
the on-site wastewater treatment plant of the GICP for treatment and disposal;
·
The
Main Thermal Treatment System, which consisted of feed and combustion chambers,
rotary kiln, pre-calciner, cyclones with tipping
valves, bag house filter/dust collector, ash storage tank and heat exchanger
among other items; and
·
The
Lime Cooling System, which consisted of a lime storage bin, feed bin, lime
ejector, air blower and cyclone with tipping values.
The layout of the CCPP and location of
potential sources of land contamination within the Study Area are shown in Figure B2 of the CAP.
The possible land contamination sources are also shown in Figure B2 as the rotary kiln, secondary combustion
chamber, bag house filter/dust collector and heat exchanger. These are all above ground structures where
residues from the various activities may have collected. The wastewater storage tank could also
contain residues of wastewater from the MRRF.
As mentioned above, all activities
associated with the CCPP have ceased at the Project Site. During the short operation period (11 weeks)
of the CCPP no accidents, leakages, spillages or other problems likely to cause
land contamination were reported.
Historical Land Use and Activities
The Project Site is situated on an area of
reclamation and was developed using fill materials from the nearby hillsides,
see Figures D1 and D2 of the CAP.
Following start up of the cement plant in
1982, the Project Site was used for stockpiling of cement clinker until
1985. The Project Site was also used as
an emergency open stockpile of natural limestone between 1990 and 1994. A propane storage area was reportedly built
in the late 1980’s, but was never commissioned, and was removed in 1992.
Table
4.3a summarises the
historical development of the GICP and CCPP.
Further details of the historical land uses are provided in the Section 2.4 of the CAP.
Table 4.3a Site
Historical of the GICP and CCPP Site
Time |
GICP |
CCPP Site |
Late 1970s |
Site reclamation |
- |
Before 1982 |
Construction of the cement plant |
- |
1982 |
Operation of the GICP cement kiln began |
Reserved for propane storage and used as emergency
stockpile of cement clinker until 1985 |
1984-1990 |
Operation of the cement kiln suspended |
Reserved for propane storage and left vacant |
1990-1994 |
Operation of the cement kiln restarted |
Reserved for propane storage and used as emergency
storage of limestone imported from |
1992 |
Continuous operation of the GICP |
Propane storage was built but never commissioned. It
was removed in March 1992 |
After 1994 |
Continuous operation of the GICP |
Rehabilitated as a kiln lawn until the construction
of CCPP |
Dec 2001 |
Clinker production was suspended |
Rehabilitated as a kiln lawn until the construction
of CCPP |
Jun 2004 |
Clinker production was suspended |
Construction of the CCPP foundation |
Apr 2005 |
Clinker production was suspended |
First load commissioning test of the CCPP |
Jul 2005 |
Clinker production was suspended |
Second load commissioning test of the CCPP |
Oct 2005 |
Clinker production was suspended |
Continuous operation of the CCPP |
Dec 2005 |
Clinker production was suspended |
Operation ceased after all operation data has been
collected |
Jan 2006 |
Clinker production resumed |
- |
4.4
Potential Sources
of Land Contamination at the Site
Based on the historical uses of the
Project Site and the environmental setting described above, the following potential
existing on and off-site sources of contamination that could affect the Project
Site have been identified. They are
described in the following sections.
4.4.1
Off-Site Sources
·
The
storage and transfer of fuel (diesel oil) at the fuel underground storage tanks
(UST) and dispensing station located approximately 20m to the southwest of the
Project Site. The USTs
were reportedly constructed of single-shell steel encased in concrete with a
minimum thickness of 150mm. In order to
minimise risk of accidental oil leakages, tank piping pressure tests/hydraulic
tests are conducted once every 5 years.
The fuel dispensing station was used for filling of around 20 vehicles
per day. The area was paved. The fuel UST and dispensing station will not
be included in the proposed decommissioning of CCPP.
·
Potential
leakage of fuel from overhead fuel pipelines connecting the fuel oil storage
tank (located approximately 100m to the southwest of the Project Site) with the
CCPP and the main cement kiln. No
evidence of leakage was observed during the site visit.
4.4.2
On-Site Sources
·
The
storage and handling of MSW used in the pilot tests. It is noted that prior to being fed into the
rotary kiln, all the wastes were received, stored and sorted in the MRRF, which
was an enclosed building with concrete floor.
All leachate and wastewater generated in the
building was collected in an enclosed drainage system leading to an UST and
then transferred to the wastewater treatment plant of the GICP for
treatment. The likelihood of the MSW or leachate / wastewater causing contamination below the
impermeable concrete floor is considered to be negligible.
·
Leakage
and/or spillage from the UST for leachate generated
from the MRRF. The UST is a steel tank
and its integrity has been checked to ensure no leakage prior to use. The tank was used for a short period of time
(11 weeks) during the operations of the CCPP and no evidence of leakage/damage
was observed. Therefore the likelihood
of the leachate / wastewater contaminating the soil
around the tank and groundwater is considered to be very low. Moreover, the waste handled at the MRRF was
MSW and the leachate generated from the operation of
the MRRF would be expected to have been organic in nature and not expected to
contain potential contaminants of concern such as heavy metals or persistent
organic compounds.
·
Leakage/spillage
of contaminants from the ash generated from the rotary kiln system during the
MSW incineration process. It is noted
that all ash generated from the CCPP was collected from the kiln directly into
bags and transferred for storage in the reception hall of the MRRF
building. After the completion of the
pilot test, the remaining ashes were vacuumed from the units and also collected
in bags. Therefore it is unlikely that
anything more than very limited fugitive ash was spilled on the paved floor of
the reception hall. The likelihood of
this ash then contaminating the soil or groundwater beneath the paved floor is
considered to be negligible.
·
Leakage/spillage
of contaminants from bottom ash quenching tank located at the bottom of the
rotary kiln. It is noted that the bottom
ash was quenched, collected in bags and transferred for storage in the
reception hall thus limiting the potential for the contamination of the underlying
soils and groundwater to negligible levels.
Locations and photos of these potential sources are
presented in the CAP (Annex A1).
The whole Project Site area was paved with
concrete and asphalt. The wastewater
from the MRRF was connected to a collection sump and was then transferred for
treatment at GICP. The stormwater run-off from the outdoor plant area was
collected within the GICP drainage system.
It was observed that the fuel oil transfer
pipelines used overhead pipes. No oil,
ash and wastewater spillage/leakage had reportedly occurred at the Project Site
during its short period of operation and none were observed during the site
visit.
Potential existing off-site sources of soil
and groundwater contamination are associated with the current operation of the
cement plant surrounding the Project Site.
Further off-site, the potential sources may include the power station
and a steel manufacturing plant which are also industrial use.
The Project Site’s future use remains
industrial (manufacture of cement and cement related products) and is
surrounded by remaining areas of the GICP.
After decommissioning, the concrete and asphalt slab and concrete
foundations and sub structures will be excavated, to a maximum depth of
1.5m. The whole Project Site will then
be levelled using clean imported materials.
The Project Site will remain as an open area for the operation and
future development of the GICP. It is currently
proposed that the surface of the clean imported materials will be rehabilitated
into a grass lawn.
All traces of MSW and the associated CCPP
will have been removed and there will not be a potential source of
contamination present at the Project Site.
4.5
Land Contamination Site Investigation Programme
An
intrusive contamination investigation was conducted at the Project Site,
details of which are presented in the CAR (see Annex A2). The site
investigation (SI) included:
·
Excavation of six trial pits down to a maximum of 1.5m
below ground level (m bgl), with
two trial pits (S1/S2 and S3/S4) located adjacent to the wastewater UST and
four trial pits (S5/S6, S7/S8, S9/S10 and S11/S12) located around the CCPP area
to determine any soil contamination;
·
Sampling
of two (2) soil samples were taken from each sampling location at just below
the concrete pavement and at between 1.0 to 1.5m bgl
for laboratory analysis of potential contaminants plus QA/QC samples;
·
Laboratory analysis of soil samples for heavy metals
(including Antimony (Sb), Arsenic (As), Barium (Ba), Cadmium (Cd), Chromium III
and VI (Cr III and Cr VI), Cobalt (Co), Nickel (Ni), Copper (Cu), Lead (Pb), Manganese (Mn), Mercury
(Hg), Molybdenum (Mo), Nickel (Ni), Tin (Sn), and
Zinc (Zn)); total petroleum hydrocarbons (TPH); and
benzene, toluene, ethyl benzene, and xylene (BTEX);
and
·
Laboratory analysis of three soil samples for
Polychlorinated biphenyls (PCBs) and Polychlorinated dibenzo-p-dioxins
and dibenzofurans (PCDD/Fs) (see Annex A3).
4.5.1
Soil Analytical Results
The
results of the laboratory analysis of the soil samples are presented in Tables 4.5a.
Levels of TPH analysed for all three
carbon ranges were below the reported detection limits for all samples. Concentrations of BTEX were also below the
reported detection limits at all locations.
Levels of all metals analysed in all samples were well below the RBRG
values. Levels of PCBs, dioxins and
furans analysed in all samples were well below the RBRG values for soil in
industrial area. Therefore, no concern
of dioxins/ PCBs contamination in the soil is expected.
The
detailed results of the laboratory analysis of the samples with the QA/QC
information are presented in the CAR (Annex
A2) and Annex A3 of this report.
Table 4.5a Soil
Analytical Results (all results in mg/kg dry weight)
Parameters |
LOR(a) |
S1 |
S2 |
S3 |
S4 |
S5 |
S6 |
S7 |
S8 |
S9 |
S10 |
S11 |
S12 |
S13(b) |
RBRG Industrial |
Csat (d) |
% Moisture Content |
0.1 |
15.3 |
8.1 |
10.6 |
9.8 |
10.3 |
9.8 |
9.4 |
10.6 |
7.4 |
7.5 |
9.5 |
10.6 |
7.6 |
- |
- |
TPH |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
·
C6-C8 Fraction |
5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
<5 |
1.00E+04 |
1.00E+03 |
·
C9-C16 Fraction |
200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
<200 |
1.00E+04 |
3.00E+03 |
·
C17-C35 Fraction |
500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
<500 |
1.00E+04 |
5.00E+03 |
Benzene |
0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
9.12E+00 |
3.36E+02 |
Toluene |
0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
1.00E+04 |
2.35E+02 |
Ethyl-benzene |
0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
8.24E+03 |
1.38E+02 |
m,p-Xylene |
0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
<0.4 |
1.23E+03(c) |
1.50E+02(c) |
o-Xylene |
0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
<0.2 |
1.23E+03(c) |
1.50E+02(c) |
Priority Metal |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
·
Antimony (Sb)
|
1 |
7 |
<1 |
5 |
<1 |
2 |
<1 |
1 |
<1 |
<1 |
<1 |
2 |
1 |
<1 |
2.61E+02 |
- |
·
Arsenic (As) |
1 |
25 |
<1 |
25 |
<1 |
2 |
<1 |
1 |
<1 |
<1 |
<1 |
4 |
1 |
2 |
1.96E+02 |
- |
·
Barium (Ba) |
0.5 |
110 |
30.4 |
109 |
23.1 |
53.4 |
23.1 |
41.5 |
29.4 |
22.8 |
21.1 |
60.4 |
35.8 |
24.5 |
1.00E+04 |
- |
·
Cadmium (Cd) |
0.2 |
2.2 |
0.2 |
0.7 |
<0.2 |
0.6 |
<0.2 |
0.5 |
<0.2 |
<0.2 |
<0.2 |
0.6 |
0.7 |
<0.2 |
6.53E+02 |
- |
·
Chromium III (Cr III) |
0.5 |
35.3 |
8.8 |
28.2 |
2.3 |
14.2 |
3 |
12.1 |
4.2 |
8.5 |
3.2 |
15.7 |
21.5 |
24.5 |
1.00E+04 |
- |
·
Chromium VI (Cr VI) |
0.5 |
<0.5 |
<0.5 |
0.8 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
1.2 |
1.96E+03 |
- |
·
Cobalt (Co) |
0.5 |
11.5 |
3.2 |
14.6 |
2.7 |
3.9 |
3.4 |
5.2 |
2.6 |
2.3 |
1.4 |
4.3 |
3.7 |
3.5 |
1.00E+04 |
- |
·
Copper (Cu) |
1 |
226 |
22 |
103 |
2 |
35 |
2 |
20 |
3 |
17 |
2 |
57 |
32 |
30 |
1.00E+04 |
- |
·
Lead (Pb)
|
1 |
85 |
42 |
35 |
61 |
54 |
59 |
46 |
42 |
51 |
42 |
49 |
42 |
47 |
2.29E+03 |
- |
·
Manganese (Mn) |
0.5 |
152 |
452 |
447 |
296 |
279 |
265 |
339 |
254 |
364 |
316 |
298 |
221 |
344 |
1.00E+04 |
- |
·
Mercury (Hg) |
0.05 |
0.24 |
<0.05 |
0.08 |
<0.05 |
<0.05 |
<0.05 |
0.05 |
<0.05 |
<0.05 |
<0.05 |
0.05 |
<0.05 |
<0.05 |
3.84E+01 |
- |
·
Molybdenum (Mo) |
1 |
77 |
3 |
33 |
5 |
19 |
2 |
7 |
2 |
2 |
2 |
21 |
12 |
4 |
3.26E+03 |
- |
·
Nickel (Ni) |
1 |
21 |
3 |
22 |
1 |
<1 |
<1 |
3 |
<1 |
2 |
<1 |
2 |
<1 |
13 |
1.00E+04 |
- |
·
Tin (Sn) |
0.5 |
45.7 |
5.4 |
8.2 |
4.2 |
7.4 |
4.3 |
5.5 |
4 |
4.2 |
2.6 |
7.6 |
5.8 |
6.9 |
1.00E+04 |
- |
·
Zinc (Zn) |
1 |
523 |
72 |
387 |
31 |
116 |
31 |
114 |
34 |
92 |
32 |
142 |
162 |
228 |
1.00E+04 |
- |
Dioxins and Furans (e) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
·
PCDD/F |
Note
(f) |
1.2E-04 |
- |
- |
- |
6.3E-06 |
- |
8.9E-06 |
- |
- |
- |
- |
- |
- |
5.00E-03 |
- |
·
PCBs |
Note
(f) |
9.8E-06 |
- |
- |
- |
6.1E-07 |
- |
6.4E-07 |
- |
- |
- |
- |
- |
- |
7.48E-01 |
- |
Notes: (a)
LOR = Limit of reporting (b)
The duplicate sample taken from S7 (c)
The RBRG Industrial values for Total Xylenes (d)
The Csat
value/limit is the contaminant concentration in soil at which the absorptive
limits of the soil particles, the solubility limits of the soil pore water and
saturation of soil pore air have been reached (e)
Based on the locations and their potential of
PCDD/Fs and PCBs contamination, laboratory analysis for PCBs and PCDD/Fs were
conducted for three soil samples (S1, S5 & S7). (f)
The limits of detection for different PCDD/Fs and
PCBs compounds can be referred to the Annex
A3. |
4.6
Land
Contamination Impact Assessment
4.6.1
Conceptual Site Model at the CCPP Site
Based on the above sources identified and
the results of the investigation a conceptual site model has been constructed
for the Project Site as presented in Table 4.6a (see also Section 3 of the CAR).
Table 4.6a Conceptual
Model at the CCPP Site
Source |
Pathway |
Receptor |
Risk |
Historical storage
of cement and limestone/ foundation construction |
Ingestion,
inhalation and skin contact |
Site workers
involved in the decommissioning and demolition work |
None – The concentrations
in the soil samples were well below the RBRGs. The demolition work will be limited to the
top 1.5 m and hence will not touch these materials. |
|
Soil pore
migration |
Ground and surface
waters |
None – The
concentrations in the soil samples were well below the RBRGs. The storage occurred over 10 years ago. |
MSW feedstock |
Ingestion,
inhalation and skin contact |
Humans (eg Site workers during decommissioning and demolition
works) |
None – The concentrations
in the soil samples were well below the RBRGs. No MSW remains on site at the time of the
site visit. |
Ash residue from
the thermal treatment trial |
Ingestion,
inhalation and skin contact |
Humans (eg Site workers during decommissioning and demolition
works) |
None –
The concentrations in the soil samples were well below the RBRGs. No ash
residues were left on the ground at the time of the site visit. The residues
currently properly stored within the MRRF building and will be properly
utilised or disposed of. |
Liquid runoff from
MSW/ash |
Ingestion,
inhalation and skin contacts |
Humans (eg Site workers during decommissioning and demolition
works) |
None – The
concentrations in the soil samples were well below the RBRGs. |
Liquid runoff from
MSW/ash |
Soil pore water |
Groundwater/
surface water |
None – The
concentrations in the soil samples were well below the RBRGs. Impermeable hardstanding
and enclosed drainage system. No leakage
of the wastewater collection UST reported. |
Off-site
contamination sources |
Migration on to
the CCPP site via soil pore water or air borne dust |
Humans - Site
workers during decommissioning Groundwater under
the Site |
None – The concentrations
in the soil samples were well below the RBRGs. There was no evidence to suggest any
spillages or leaks have occurred off-site to such an extent as to impact the
soils or groundwater underlying the Project Site. |
It is considered that the only potential
receptors at risk might be site workers involved in decommissioning and
demolition works, which was discussed in the CAP (see Annex A1).
As the contaminants analysed were either
not detected or with concentrations well below the RBRGs,
it is not considered that the activities of the CCPP pose risks to any
receptor.
No potential land contamination impact is
anticipated during the CCPP demolition or thereafter.
4.7
Land
Contamination Mitigation Measures
Based on the above investigation
results, no mitigation
measures are required during the demolition works.
4.8
Residual
Environmental Impacts
After completion of demolition works, the
Project Site will be backfilled with clean soil and landscaped. The area will be left as an open grassed area
whilst awaiting a future industrial use as part of the GICP operation.
There will not be any residual impacts at
the Project Site after completion of the demolition works.
4.9
Environmental
Monitoring and Audit
Based on the above investigation results, no further investigation is warranted.
As no potential
risks to receptors anticipated, no monitoring is deemed necessary.
The assessment of land contamination
sources and the potential impacts to potential receptors were investigated in
accordance with the RBRG Guidance. Site appraisal comprising a site visit, and a
review of background information and land history in relation to possible land
contamination was conducted. Potential
sources of contamination and associated impacts, risks or hazards are
identified in the CAP (see Annex A1). Land contamination assessment was carried out
and results presented in the CAR (see
Annex A2).
The results of the
site investigation works determined that:
·
TPH/BTEX were below the reported detection
limits in any of the soil samples collected;
·
Concentrations of priority pollutant metals
detected were well below the RBRG standards; and
·
Levels
of PCBs, dioxins and furans analysed in all samples were well below the RBRG
values.
Excavation works proposed for the
decommissioning and demolition works will be limited to the concrete
sub-structures and UST. No soil
excavation or groundwater extraction will be required for the Project and hence
no off-site disposal of soil and groundwater will be required.
The substructure areas of the Project Site
will be filled using clean imported fill materials and rehabilitated as green
lawn and open area. The potential for
human contact with any underlying contamination in the future is considered
low.
As
the result of the above, no potential impact from the contaminated soil is
anticipated.