Table
11.1 Implementation
Schedule for Waste Management
EIA Ref. |
Recommended Environmental Protection Measures / Mitigation Measures |
Timing of implementation? |
Who will implement? |
Location |
What requirements or standards for the measures to achieve? |
3.5.1.2 |
l The Waste Management Plan (WMP) shall prepared by the Contractor
to describe arrangements for waste avoidance, re-use and recycling, including
all handling, storage and transfer requirements. l The WMP should be refined and updated as more detailed information is generated on the volume of dredged marine mud. Similarly, it should be regularly reviewed and updated at least monthly throughout construction. |
1.
Before and during construction |
2.
Contractor |
3.
At all work sites |
4.
Waste Disposal Ordinance (Cap 354) 5.
ETWB 34/2002 6.
7.
Dumping at Sea Ordinance (Cap 466) |
3.5.2.1 |
l A marine disposal license shall be obtained from EPD. |
Prior to marine dredging |
Contractor |
|
ETWB 34/2002 Dumping at Sea Ordinance (Cap 466) |
3.5.2.2 |
l Bottom opening of barges shall be fitted with tight fitting seals
to prevent leakage of material. Excess
material shall be cleaned from the decks and exposed fittings of barges and
dredgers before the vessel is moved. l Monitoring of the barge loading shall be conducted to ensure that
loss of material does not take place during transportation. Transport barges or vessels shall be
equipped with automatic self-monitoring devices as specified by the EPD. l Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment-laden water during loading or transportation. |
During transportation and disposal of the dredged sediment |
Contractor |
At all construction work sites |
Waste Disposal Ordinance
(Cap 354) ETWB 34/2002 Dumping at Sea Ordinance (Cap 466) |
3.5.3 4.9.1.4 |
l The Contractor shall be required to register with the EPD as a
chemical waste producer. l The contractor shall follow the guidelines stated in the relevant CoP. |
During Construction and Operation |
Contractor / Operator |
At all work sites |
Waste Disposal (Chemical Waste)
(General) Regulation Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes |
3.5.5 |
l General refuse shall be stored in fully contained units separate
from chemical wastes. The general
refuse storage area shall be regularly maintained by a reputable waste
collector, with waste to be disposed at a designated refuse transfer station. l The Contractor shall be responsible for identifying which
materials can be recycled / reused, whether on site or off site. In the event
of the latter, the Contractor shall make arrangements for the collection of
the recyclable materials. Separate
labelled bins for their deposit shall be provided if feasible. l The Contractor is required to maintain a clean and hygienic site
throughout the Project. |
During Construction and Operation |
Contractors / Operator |
At all work sites |
ETWBTC (Works) No. 6/ |
11.2
Water Quality, Marine Ecology & Fisheries
Table
11.2 Implementation
Schedule for Water Quality, Marine Ecology & Fisheries Protection
EIA Ref. |
Recommended Environmental Protection Measures / Mitigation Measures |
Timing of implementation? |
Who will implement? |
Location |
What requirements or standards for the measures to achieve? |
3.5.4.1 4.9.1.3 4.9.2.3 |
l An adequate number of portable toilets, if necessary, should be provided for the construction and maintenance workforce if sufficient facilities are not provided at any onshore assembly area. l Portable toilets shall be maintained in a state that will not deter the workers from using them. Night soil shall be regularly collected by a licensed collector for disposal at a Sewage Treatment Works. |
During Construction and Operation |
Contractors / Operator |
At all work sites |
Water Pollution Control Ordinance (Cap. 358) WQOs |
4.9.1.1 5.10.1 |
l Working rate for dredging should not exceed 6,300 m3 / day for two dredgers. l Closed grab dredgers should be used for dredging. l The mechanical grabs should be properly maintained to minimise spillage of sediment. l Silt curtains should be provided closely surrounding the dredging point to minimise dispersion of sediment plumes. |
During marine dredging |
Contractor |
Junk Bay |
Water Pollution Control Ordinance (Cap. 358) WQOs |
4.9.1.1 5.10.2 |
l Jetting speed should not exceed 75 m/hr in the section between l Jetting speed should not exceed 150 m/hr for jetting operation carried out in the remaining sections of the transmission power cable and the array cable at the wind farm. |
During cable jetting |
Contractor |
At all cable locations |
Water Pollution Control
Ordinance (Cap. 358) WQOs |
4.9.1.1 |
l Pumping rate for seawater removal from suction caissons during foundation installation should not exceed 1,200 m3 / hr per foundation or 300 m3 / hr per pump. |
During foundation installation |
Contractor |
At all turbine foundation |
Water Pollution Control
Ordinance (Cap. 358) WQOs |
4.9.1.2 |
l Water Quality monitoring |
Before construction and
during Jetting operations. 8.
One week after completion of works |
9.
Contractor |
10.
Nine sites shown in Figure 4.2 of
EM&A Manual |
Water
Pollution Control Ordinance (Cap. 358) 11.
WQOs |
1.
5.12.1.5 |
l
Coral monitoring |
2.
Before construction, during Jetting
operations and until 2 weeks after completion of Jetting at impact sites |
3.
Contractor |
4.
Tung Lung Chau South, South Ninepins
and Victor Rock |
5.
Additional precaution agreed to by
project proponent. |
6.
6.8.1.1 |
l
Marine Mammal Exclusion zone |
7.
During installation of foundations
and turbine sub-structures |
8.
Contractor |
9.
250m around works barge |
10.
Additional precaution agreed to by
project proponent. |
11.
6.10.1.2 |
l
Marine Mammal Acoustic Monitoring |
12.
During operation |
13.
Contractor |
14.
Wind farm footprint |
15.
Additional measure agreed to by
project proponent. |
7.9.1.1 |
l
Avifauna
Field Monitoring |
·
Second
year of construction, during 1 year of operation |
·
Contractor |
·
Transect
route shown in Figure 7.11 of EIA |
·
Additional
measure agreed to by project proponent. |
11.3
Cultural Heritage
Table
11.3 Implementation
Schedule for Cultural Heritage Protection
EIA Ref. |
Recommended Environmental Protection Measures / Mitigation Measures |
Timing of implementation? |
Who will implement? |
Location |
What requirements or standards for the measures to achieve? |
9.10.1 |
l Align the array cable to avoid potential impacts upon Target A1. |
During Construction |
Contractor |
Near Target A1 within wind farm footprint |
|
9.10.2 |
l Implement a 150m-diameter buffer zone around each identified target to ensure potential impacts can be avoided. Within these buffer zones there shall be no permanent works or temporary anchoring of construction or maintenance vessels. The buffer separation shall be implemented with the use of on-board GIS systems for marine vessel manoeuvring. |
During Construction |
Contractor |
At all Targets |
Antiquities and Monuments Ordinance (Cap. 53) |
9.12.1.1 |
l To ensure the Project development does not result in any unforeseen impacts on objects of marine archaeological potential, further marine geophysical comprising seismic and magnetic surveys shall be conducted across the Study Area as the detailed engineering design advances, and before any marine construction works commence. |
Before Construction |
Contractors / Operator |
Across Study Area |
Antiquities and Monuments Ordinance (Cap. 53) |
11.4
Landscape & Visual
Table
11.4 Implementation
Schedule for Landscape & Visual Aspects
EIA Ref. |
Recommended Environmental Protection Measures / Mitigation Measures |
Timing of implementation? |
Who will implement? |
Location |
What requirements or standards for the measures to achieve? |
10.6.3.4 |
l Management of construction duration to the practical minimum. l Management of the number of pre-construction and construction vessels and vessel movements at the practical minimum. l Adopt a regular pattern of turbines to create a balanced, controlled appearance, as opposed to random or clustered groups. l The design of turbine tower, above the platform, should be slender and elegant |
Design and Construction |
Contractor |
At wind farm footprint |
EIAO (Cap 499) |
10.6.3.4 |
l Painting offshore in visually neutral / recessive colours where consistent with safety requirements. l Control night-time lighting and glare by hooding all lights, including safety lights where consistent with meeting safety requirements. l Ensure non-reflective materials used in construction of offshore structures. |
During Construction and Operation |
Contractor |
At wind farm footprint |
EIAO (Cap 499) |