12.1
An impact
assessment of air
quality impacts associated with the construction phase of the Project is presented in this section. Representative Air Sensitive Receivers (ASRs) in the vicinity
of the Project site are identified. Potential air quality impacts arising from construction work
sites, concrete
batching plant, temporary magazine sites, stockpiles and barging facilities have been assessed
and appropriate mitigation measures are recommended.
12.2
The XRL is an electric railway,
therefore, no air pollutants emissions generated within the rail system is expected. However, it may have diesel locomotives to be
operated at Shek Kong Stabling Sidings (SSS). The air quality implication in connection
with the operation of these diesel locomotives is presented in this
section. A public transport interchange (PTI) will be
provided at the ground floor of Ventilation Building Complex (next to West
Kowloon Terminus) during the operation phase. The air quality inside the PTI is also addressed.
Environmental
Legislation, Standards and Guidelines
12.3
The criteria for evaluating air quality
impacts and the guidelines for air quality assessment are laid out in Annex 4
and Annex 12 of the EIAO-TM as well as the requirements set out under Clause
Air Quality Objective & EIAO-TM
12.4
The Air Pollution Control Ordinance (APCO)
provides the statutory authority for controlling air pollutants from a variety
of sources. The Hong Kong Air Quality Objectives (AQOs), which stipulate the
maximum allowable concentrations over specific periods for typical pollutants,
should be met. The relevant AQOs are listed in Table 12.1.
Table 12.1
Maximum Concentration (µg m-3)
(1) |
||||
Pollutant |
Averaging Time |
|||
1 hour (2) |
8 hour (3) |
24 hour (3) |
Annual (4) |
|
- |
- |
260 |
80 |
|
Respirable Suspended Particulates (RSP) (5) |
- |
- |
180 |
55 |
|
800 |
- |
350 |
80 |
Nitrogen
Dioxide (NO2) |
300 |
- |
150 |
80 |
Carbon
Monoxide (CO) |
30,000 |
10,000 |
- |
- |
Photochemical
Oxidants (as
Ozone, O3) (6) |
240 |
- |
- |
- |
Note:
(1)
Measured at 298 K and 101.325 kPa.
(2)
Not to be exceeded more than three times per
year.
(3)
Not to be exceeded more than once per year.
(4)
Arithmetic mean.
(5)
Suspended particulates in air with a nominal
aerodynamic diameter of 10 mm or smaller.
(6)
Photochemical oxidants are determined by
measurement of ozone only.
12.5
The EIAO-TM stipulates that the hourly TSP
level should not exceed 500 mgm-3
(measured at 25oC and one atmosphere) for construction dust impact
assessment. Mitigation measures for construction
sites have been specified in the Air Pollution Control (Construction Dust)
Regulation.
Air Pollution Control (Construction Dust) Regulation
12.6
Notifiable and regulatory works are under the control
of Air Pollution Control (Construction Dust) Regulation. Notifiable works
are site formation, reclamation, demolition, foundation and superstructure
construction for buildings and road construction. Regulatory works are building renovation,
road opening and resurfacing, slope stabilisation, and other activities
including stockpiling, dusty material handling, excavation, concrete
production, etc. This Project is expected
to include notifiable works (foundation and
superstructure construction) and regulatory works (temporary stockpile, dusty
material handling, excavation and concrete production). Contractors and site agents are required to
inform EPD and adopt dust reduction measures to minimize dust emission, while
carrying out construction works, to the acceptable level.
Air Pollution Control Ordinance - Control of Emissions from
Specified Processes
12.7
The operation of the following facility is
classified as Specified Processes (SP) under the APCO and is subject to a more stringent emission
control.
·
Operation of Cement Works in which the total
silo capacity exceeds 50 tonnes and in which cement is handled or in which
argillaceous and calcareous materials are used in the production of cement
clinker, and works in which cement clinker is ground.
12.8
A licence is required for the operation of
the Cement Work (Concrete Batching Plant) under Part IV of the ordinance. Application for licence should be made to
EPD. EPD may either grant or refuse to
grant a licence subject to whether the applicant can fulfil the environmental
standards to avoid causing air pollution.
If EPD decides to grant the licence, a set of conditions will be imposed
to prevent adverse impact from the
discharge of air pollutant emissions.
PTI Air Quality Guideline
12.9
The air quality guideline of PTI is
stipulated in EPD’s ProPECC PN1/98 Control of Air
Pollution in Semi-confined Public Transport Interchanges, which recommend the
maximum allowable concentration of pollutants in a semi-confined PTI. The PTI Air Quality Guideline is shown in Table 12.2 below.
Table 12.2 PTI Air Quality Guideline
Pollutant |
Maximum Concentration not be exceed
(µg m-3) (1) |
|
|
1 hour
average (mg/m3) |
5-minute
average (mg/m3) |
Carbon
Monoxide (CO) |
30,000 |
115,000 |
|
800 |
1,000 |
Nitrogen
Dioxide (NO2) |
300 |
1,800 |
Note:
(1)
Expressed at the reference condition of 25°C and 101.325 kPa.
Description of the Environment
12.10
The Project alignment runs from Huanggang (Mainland) beneath Mai Po, Ngau
Tam Mei, Kam Tin, Tai Mo Shan and Kwai
Chung, Lai Chi Kok, Nam Cheong
and Tai Kok Tsui to the
West Kowloon Terminus (WKT). The main
land uses of Mai Po, Ngau Tam Mei, Kam Tin, Tai Mo Shan are rural area; and villages / low
density developments. The areas in Kwai Chung, Lai Chi Kok, Nam Cheong, Tai Kok Tsu and West Kowloon Terminus are urban areas and the main
land uses are
residential, commercial and educational institutes.
12.11
A total of eight
ventilation buildings will be located in the
12.12
Stabling Sidings and maintenance facility
will be located at Shek Kong to provide stabling and
maintenance and cleaning activities. An
emergency rescue station (ERS) will be located next to Shek
Kong Stabling Sidings (SSS) for evacuation of passengers and access by
emergency personnel to deal with incidents.
12.13
Site visits were conducted from August to
September 2008 to investigate the baseline environment in the vicinity of the
WKT, ventilation buildings and SSS. A
summary of description of baseline environment and identified dominant air emission sources at the surveyed areas during the site inspection
are presented in Table 12.3.
Table 12.3 Baseline
Environmental Condition
Area |
Baseline
Environment |
Mai
Po |
Low
density residential area and the surrounding land uses mainly comprise a mixture
of open storage, temporary carpark and residential
uses. Dominant air emission sources
were identified as the traffic emissions from |
Ngau Tam Mei |
Village
area with scattered 1- to 2-storey houses.
|
Tai
Kong Po |
Village
area with the surrounding land uses mainly comprise a mixture of poultry and
residential uses. |
Shek Kong/Tse |
Shek Kong PLA Barracks
is located next to the SSS and a scattering of residential houses are located
in the vicinity. |
Pat
Heung |
Low
density residential area. The surrounding land uses mainly comprise a mixture
of residential and agricultural uses. |
Shek Yam |
Well
developed urban area. The surrounding
major land uses are residential use. Dominant
air emission sources are traffic emissions from |
Shing Mun |
Well
developed urban area. The surrounding land uses are residential use. Dominant air emission source was the
traffic emissions from |
Kwai Chung |
Well
developed urban area. The surrounding land uses are industrial use. Air
emission sources were the traffic emissions from |
|
Well developed urban area. The surrounding land uses are educational
institutes, residential and recreational uses. Traffic emissions from |
|
Well
developed urban area. The surrounding land uses mainly comprise a mixture of
schools and residential uses. Dominant
air emission sources were identified as the traffic emissions from |
Mong Kok West |
Well
developed urban area. The surrounding land uses mainly comprise a mixture of
commercial, GIC and residential uses. Dominant air emission sources were
identified as the traffic emissions from |
|
Well
developed urban area. The surrounding land uses mainly comprise a mixture of
commercial, GIC and residential uses. Dominant air emission sources were
identified as the traffic emissions from |
12.14
There are six
barging points to be proposed for this Project.
They would be located at
12.15
Two magazine
sites would be proposed to be located at So Kwun Wat and
12.16
There are currently four Environmental
Protection Department (EPD) fixed air quality monitoring stations located
within the study area. These monitoring
stations are located at Yuen Long, Tsuen Wan, Kwai Chung and Sham Shui Po. The annual averages of pollutants in mg m-3 monitored
at these stations for the Year 2007 are summarized in Table 12.4.
Table 12.4 EPD
Air Quality Monitoring Data in 2007
Pollutant |
Annual
Average Concentration (μg/m3) |
|||
Yuen Long |
Tsuen Wan |
Kwai Chung |
Sham Shui Po |
|
SO2 |
24 |
24 |
31 |
20 |
NO2 |
55 |
64 |
61 |
69 |
Ozone |
36 |
29 |
28 |
27 |
TSP |
97 |
79 |
85 |
79 |
RSP |
64 |
59 |
60 |
57 |
12.17 In accordance with Annex 12 of the EIAO-TM, any domestic premises,
hotel, hostel, hospital, clinic, nursery, temporary housing accommodation,
school, educational institution, office, factory, shop, shopping centre, place
of public worship, library, court of law, sports stadium or performing arts
centre are considered as air sensitive receivers (ASRs). Any other premises or place with
which, in terms of duration or number of people affected, has a similar
sensitivity to the air pollutants as the aforelisted
premises and places is also considered to be a sensitive receiver. As stated
in the EIA Study Brief, the boundary of the assessment area for air quality
assessment should be
Table 12.5 Representative
Air Sensitive Receivers
Works Area |
Area ID |
ASR |
Description |
Land Use |
Distance between ASR and closest work
boundary(m) |
No. of
storey |
Mai Po
(Figure No. NOL/ERL/300/C/XRL/ENS/M60/002) |
||||||
MPV |
A |
MPA1 |
House 5 Phase A Royal Palms |
Residential (Existing) |
57 |
3 |
A |
MPA2 |
|
Residential (Existing) |
5 |
2 |
|
A |
MPA3 |
No. 166 |
Residential (Existing) |
57 |
3 |
|
A |
MPA4 |
Proposed Comprehensive Development at Wo Shang |
Residential (Planned) |
Planned |
N/A |
|
Ngau Tam Mei (Figure No. NOL/ERL/300/C/XRL/ENS/M60/003
& 004) |
||||||
NTV |
B |
NTA1 |
Yau Tam Mei Village House |
Residential |
18 |
2 |
B |
NTA2 |
Yau Tam Mei Village House |
Residential |
9 |
2 |
|
B |
NTA3 |
Yau Tam Mei Village House |
Residential |
9 |
2 |
|
Tai Kong
Po (Figure No. NOL/ERL/300/C/XRL/ENS/M60/005,
006 & 007) |
||||||
TPV |
C |
TPA1 |
|
Residential |
8 |
2 |
C
(Access Road) |
TPA2 |
|
Residential |
1 |
1 |
|
C
(Access Road) |
TPA3 |
|
Residential |
1 |
2 |
|
C
(Access Road) |
TPA4 |
Kam Hing |
Residential |
5 |
3 |
|
C |
TPA5 |
|
Residential |
5 |
3 |
|
C
(Access Road) |
TPA6 |
Oakwood, Seasons Monarch |
Residential |
11 |
3 |
|
Shek Kong (Figure No.
NOL/ERL/300/C/XRL/ENS/M60/008 & 009) |
||||||
SSS |
D |
SSA1 |
630 Sheung Tsuen |
Residential |
9 |
2 |
D |
SSA |
|
Residential |
18 |
3 |
|
D |
SSA1b |
|
Residential |
18 |
1 |
|
D |
SSA2 |
Building 201, Shek
Kong Barrack |
N/A |
16 |
N/A |
|
D |
SSA3 |
Leung |
Residential |
6 |
2 |
|
D |
SSA4 |
Leung |
Residential |
6 |
2 |
|
D (Access Road) |
SSA5 |
Block 16, Seasons Villas |
Residential |
1 |
2 |
|
D |
SSA7 |
|
Residential |
20 |
1 |
|
D |
SSA8 |
Leung |
Residential |
51 |
2 |
|
D |
SSA9 |
DD110 |
Residential |
3 |
1 |
|
D |
SSA10 |
No. 265, |
Residential |
9 |
2 |
|
D |
SSA11 |
Leung |
Residential |
1 |
2 |
|
D |
SSA12 |
Abandoned
village house in Shek Kong |
Residential |
2 |
3 |
|
Pat Heung
(Figure No. NOL/ERL/300/C/XRL/ENS/M60/010) |
||||||
PHV |
F |
PHA1 |
DD 114 |
Residential |
2 |
2 |
F |
PHA2 |
No.
305, Sheung Tsuen San Tsuen Village House |
Residential |
6 |
4 |
|
Tse Uk Tsuen (Figure No. NOL/ERL/300/C/XRL/ENS/M60/010) |
||||||
TUW |
E |
TUA1 |
Tse |
Residential |
6 |
1 |
E |
TUA2 |
No. 489H Tse Uk Tsuen |
Residential |
12 |
3 |
|
Shek Yam (Figure No.
NOL/ERL/300/C/XRL/ENS/M60/013) |
||||||
SYW |
H |
SYA1 |
No. 168, Yau Ma Hom Resite
Village |
Residential |
3 |
3 |
H |
SYA2 |
Sun Fung Centre |
Commercial |
14 |
N/A |
|
Shing Mun (Figure No.
NOL/ERL/300/C/XRL/ENS/M60/013) |
||||||
SMV |
G |
SMA1 |
Sau Shan House, Cheung Shan Estate |
Residential |
21 |
25 |
G |
SMA2 |
Cheung Shan Estate Market |
G/IC |
33 |
N/A |
|
Kwai Chung (Figure No.
NOL/ERL/300/C/XRL/ENS/M60/014) |
||||||
KCV |
J |
KCA1 |
|
Industrial |
5 |
N/A |
J |
KCA2 |
Central Kwai
Chung Park |
Park |
6 |
N/A |
|
K |
KCA3 |
Drainage Department Maintenance Depot |
Industrial |
24 |
N/A |
|
K |
KCA4 |
Kwai Chung Depot |
Industrial |
21 |
N/A |
|
Rambler
Channel Barging Point (NOL/ERL/300/C/XRL/ENS/M60/015) |
||||||
RCB |
Z |
RBPA1 |
Kwai Chung Preliminary Treatment Works |
Industrial |
9 |
N/A |
|
||||||
MLW |
L |
MLA |
Po Leung Kuk Tong Nai
Kan College |
School |
2 |
7 |
|
||||||
NCV |
S |
NCA1 |
|
Residential |
6 |
38 |
S & T |
NCA2 |
Tower 6, Harbour Green |
Residential |
6 |
45 |
|
S & T |
NCA3 |
|
Recreational |
7 |
N/A |
|
R |
NCA4 |
Cheong |
Residential |
38 |
15 |
|
O |
NCA5 |
Fu Hoi House, Fu Cheong Estate |
Residential |
12 |
19 |
|
P |
NCA6 |
Tack Ching Girls'
Secondary School |
School |
9 |
8 |
|
P |
NCA7 |
St. Margaret's Co-educational English
Secondary & Primary School |
School |
42 |
8 |
|
Y (Barging Point) |
NCA8 |
|
Industrial |
6 |
1 |
|
M |
NCA9 |
Workshop next to |
Industrial |
27 |
N/A |
|
M |
NCA10 |
|
Industrial |
87 |
N/A |
|
S |
NCA11 |
Tower 1, |
Residential |
24 |
45 |
|
Mong Kok West (Figure
No. NOL/ERL/300/C/XRL/ENS/M60/019) |
||||||
MKV |
U & V |
MKA1 |
|
School |
27 |
8 |
U & V |
MKA2 |
|
School |
36 |
16 |
|
|
||||||
WKT |
V |
WKA1 |
FSD |
Institutional |
16 |
N/A |
|
V |
WKA2 |
Planned Residential Development at |
Residential (Planned) |
Planned |
N/A |
|
V |
WKA3 |
|
Residential |
5 |
52 |
|
W |
WKA5 |
Tsim Sha Tsui Fire Station |
G/IC |
8 |
N/A |
|
W |
WKA6 |
The |
Residential |
9 |
54 |
|
W |
WKA7 |
The |
Residential |
6 |
53 |
|
W |
WKA8 |
The Waterfront, Tower 3 |
Residential |
5 |
38 |
|
V |
WKA9 |
46-48 |
Residential |
10 |
19 |
Siu Lam Barging Point (Figure No. NOL/ERL/300/C/XRL/ENS/M60/022) |
||||||
SLB |
AA |
SLBA1 |
Lok On Pai Siu Lam Flea Market |
Commercial |
21 |
N/A |
AA |
SLBA2 |
Aqua Blue Block 3 |
Residential |
99 |
6 |
|
Magazine
Site next to |
||||||
TSW |
AE |
TSA1 |
Village House next to |
Residential |
54 |
1 |
Magazine
Site at So Kwun
Wat (Figure No. NOL/ERL/300/C/XRL/ENS/M60/024) |
||||||
SKW |
AC |
SKW |
|
Residential |
27 |
2 |
Tsing Chau Tsai Barging
Point (Figure
No. NOL/ERL/300/C/XRL/ENS/M60/026) |
||||||
TCB |
AG |
TCA1 |
|
Commercial |
273 |
2 |
AG |
TCA2 |
Shipyard at Tsing
Chau Tsai |
Industrial |
82 |
N/A |
|
Siu Lang Shui Storage and
Plant Nursery Area (Figure No. NOL/ERL/300/C/XRL/ENS/M60/027) |
||||||
SLSW |
AB |
TMA1 |
Planned Sensitive Use at the Former Siu Lang Shui Landfill |
Camp Site/Education Use |
57 |
N/A |
Lung Kwu Sheung Tan Barging Point (Figure No. NOL/ERL/300/C/XRL/ENS/M60/028) |
||||||
LKB |
AF |
LKA1 |
Office of Concrete Plant |
Industrial |
23 |
1 |
Construction Phase
12.18
The Hong Kong section of the XRL is
approximately
12.19
Major construction works/activities that
would contribute to construction dust impacts would include surface works for
the construction of the superstructures
including the eight
ventilation buildings and West Kowloon Terminus, TPP, SSS, ERS,
a PTI and a substation nearby WKT, the Project alignment by cut-and-cover technique, operation of a concrete batching plant and barging
points. The standard
working hours will be from 0700 to 1900 hours from Monday to Saturday excluding
public holidays. Locations of the cut
and cover work sites, ventilation buildings, ERS, SSS, temporary stockpiles,
temporary magazine sites, concrete batching plant and barging points are
illustrated in Figure Nos. NOL/ERL/300/C/XRL/ENS/M60/001 - 010, 013
– 024, 026 - 028. The details
of construction activities and potential emission sources are described as
follows.
Tunnel, Adits
& Shafts, Ventilation Buildings/EAP
12.20
The construction for tunnel would involve cut
and cover, drill and blast, and soft ground TBMs. The drill and blast and TBM would be
performed entirely underground, therefore, potential dust impacts could be expected from the section of alignment using the cut and
cover technique. Dusty construction activities would include excavation,
material handlings and transportation of spoils on the paved haul road within
the site.
12.21
The tunnel
sections using cut and cover technique would be at Shek
Kong works area (location of ERS and ramp structure), Nam Cheong works area and
Table 12.6 Tunnel
Construction using Cut and Cover Method
Area ID |
Chainage * |
|
Length |
Type |
|
From |
To |
(m) |
|
D |
123+540 |
124+315 |
775 |
ERS Cut & Cover |
D |
124+315 |
124+912 |
597 |
Cut & Cover ramp structure |
Q |
140+380 |
140+540 |
160 |
|
U |
140+570 |
140+800 |
230 |
Mong Kok West Cut &
Cover |
W & V |
140+800 |
141+684 |
884 |
|
Note: * Chainage
refer to Figure No. NOL/ERL/300/C/XRL/ENS/M53/207 to /208 and /221 to /228.
12.22
There are adits and
shafts to be built along the Project alignment for the operational tunnel
ventilation and are also used during construction phase. These provide access for tunnelling
equipment, permanent material and the removal of spoil (for sections of Project
alignment using TBM and drill and blast method). A
summary of the construction shafts and adits is
presented in Table 12.7.
Table 12.7 Locations
of Construction Shafts and Adits
Location |
Area ID |
Principle
Activity |
Future
Use |
Length
(m) |
Width
(m) |
Mai Po Shaft |
A |
Launching and retrieval of TBM |
|
204 |
57 |
Ngau Tam Mei Shaft |
B |
Retrieval of TBM & drive drill and blast
tunnel |
|
130 |
25 |
Tai Kong Po Shaft |
C |
Retrieval of TBM & drive drill and blast
tunnel |
Tai Kong Po
Emergency Access Point |
60 |
55 |
ERS - North
Access |
D |
Launching of TBM, ERS construction |
- |
840 |
27 |
ERS Ramp |
D |
Launching of TBM |
- |
595 |
27 |
Tse |
E |
Retrieval of TBM |
- |
12 |
30 |
Pat Heung Adit |
F |
Drive drill and blast tunnel south |
|
20 |
12 |
Shing Mun Shaft |
G |
Shaft construction |
|
16 |
16 |
Shek Yam Adit |
H |
Drive drill and blast tunnel north & south |
- |
10 |
16 |
Kwai Chung Adit |
J |
Drive drill and blast tunnel north & south |
|
25 |
12 |
|
L |
Drive dill and blast tunnel north & retrieval
of TBM |
- |
18 |
18 |
|
P |
Launching of TBMs north and south |
|
214 |
30 |
|
V |
Retrieval of TBM |
- |
30 |
18 |
Mong Kok West Shaft |
V |
- |
|
35 |
22 |
12.23
The size of the construction area for each adit/shaft would be limited. After site clearance and open-cut excavation
at the surface area, the sheet piles/diaphragm wall would be installed. Generally, the
tracked crane would be used for mucking out. The mucking areas would not be
fully enclosed. However, during
excavation and unloading of spoils, water spraying would be provided to
alleviate potential dust emissions. All
the trucks loaded with spoil would be well covered by impervious cover before
leaving the mucking-out areas. Therefore, adverse dust impact from the
transportation of spoil would not be anticipated.
12.24
Regarding the Mei Lai Road Shaft, an overhead
gantry crane would be constructed. An
enclosed spoil removal hoist (with bucket hopper) would be provided for mucking
out as the ASRs just located next to the shaft.
The excavation work would be carried out in enclosed area and the
excavation level would be from ground level to underground level. The spoil removal process would also be
conducted inside the enclosed structure. There is a dust extraction system equipped with the filters serving this enclosed structure. As same as other adits/shafts,
all the trucks
loaded with spoil must be well covered by impervious cover
before leaving the mucking-out area. No
adverse dust impact from the transportation of spoil would be anticipated.
12.25
Wheel watering facilities would be provided at every
designated vehicle exit point of construction areas. Since all vehicles would be washed at exit
points and all trucks loaded with the dusty materials would be covered entirely
before leaving the construction sites, the dust nuisance from construction vehicle
movement outside the work site is unlikely to be significant. The access roads to the adits/shafts at rural areas are normally existing local roads. As the width of some local roads may be not
enough for the trucks travelling, minor widening of local roads would be
carried out before the mucking out activities.
In view of minor road improvement works and implementation of the dust
suppression measures, adverse dust impact would not be anticipated during
widening of local access roads.
12.26
A
temporary stockpile area would be located adjacent to each shaft/adit and the area would be about 30m x 20m (enough for 24
hours only). All excavated spoil would
be transported from the mucking-out area to the barging point per day. If the operation of the barging point is ceased, the spoil materials would be stored in the
temporary stockpile. Impervious sheeting
would be well covered on it and water
spraying system would also
be installed to
minimize dust emissions. Adverse dust
impacts are not anticipated.
12.27
A building for EAP and a total of eight ventilation buildings along the Project alignment will be provided. The
buildings will all sit on top of a shaft or adjacent to an adit
which will be in use to support the tunnel construction. The buildings are simple reinforced concrete
structures with rooms to house the ventilation fans and support systems. Minor improvement works on the access roads
to the ventilation buildings would also be undertaken under the Project. Adverse dust impacts arsing
from construction of these buildings
and minor road improvement works are not anticipated with the implementation of
dust suppression measures stipulated in Air Pollution Control (Construction
Dust) Regulation.
12.28
The construction activities for West Kowloon
Terminus (WKT)
would include site clearance, excavation, foundation works and superstructure
construction. A stockpile would be
located next to the WKT site for temporary storage of the excavated
spoils. The active area of this
stockpile would be limited to 15% of the total area. Since the West Kowloon Terminus would be constructed concurrently with the construction of Project alignment, operation of concrete
batching plant and barging points, cumulative dust impacts would be expected.
ERS at Shek Kong and Shek
Kong Stabling Sidings
12.29
The ERS and associated ramp would be
constructed using cut and cover technique.
The construction methods would be a temporary diaphragm wall around the
permanent insitu box structure. Potential dust impacts from the construction
of the ERS would be anticipated. The
stabling sidings will be located at grade on the west of the ERS box. As it would involve minor excavation works,
adverse dust impacts would not
be expected with the implementation of dust suppression measures stipulated in
Air Pollution Control (Construction Dust) Regulation.
Barging Points
12.30
There are six new barging points to be provided for this
Project. They would be located at
12.31
The haul roads within the barging sites would be all paved and water spraying would be
provided on the haul roads to keep wet condition. Vehicles would be required to pass through
designated wheel washing facilities before leaving the barging facilities. To
alleviate the potential dust impacts, the dusty materials on the trucks would
be well covered. The tipping halls would be three sides
enclosure with a top cover, water spraying and dust curtain would be
provided at the loading points (from barging point to the barges).
12.32
The details of each barging point and
potential impact are described as follows.
12.33
The barging facilities would include two
loading ramps (at the approximate locations of KSL barging points) and three
no. additional new ramps at the west (See Figure No.
NOL/ERL/300/C/XRL/ENS/M50/008). The transportation of excavated spoils would
be carried out by trucks from the work face (or stockpiling area) to the
barging points. The maximum number of
trucks per day is estimated to be 900. There
are other dusty activities such as materials handling at the stockpiles,
operations of concrete batching plant and construction of West Kowloon Terminus would be conducted concurrently adjacent to
this barging point, cumulative dust impact would be expected at the nearby
ASRs.
12.34
The barging facilities would have three ramps
(See Figure No. NOL/ERL/300/C/
XRL/ENS/M50/007). The
barging point at Nam Cheong is approximately
Rambler
Channel Barging Point
12.35
The barging facilities would include two
ramps (see Figure No. NOL/ERL/300/C/XRL/
ENS/M50/009). The
construction activities within this works area would be limited to material
handling at the
temporary stockpiles and unloading spoils to the barges.
There is only one identified ASR (office of Kwai
Chung Preliminary Treatment Works) within the study area (see Figure No.
NOL/ERL/300/C/XRL/ENS/M60/015). No other
dusty activities would be undertaken
within the study
area concurrently.
With the implementation of measures as mentioned in Sections 12.30 and 12.31, no adverse dust impact arising from the
operation of this barging point is anticipated.
Siu Lam
Barging Point
12.36
The barging facilities would include two
ramps (see Figure No. NOL/ERL/300/C/XRL/
ENS/M50/010). The
construction activities within this works area would be limited to material
handling at the
temporary stockpiles and unloading spoils to the barges.
Other dusty activities would not be undertaken concurrently within the study area. With the implementation of measures as
mentioned in Sections 12.30 and 12.31, no adverse dust impact arising from the
operation of this barging point is expected.
Lung Kwu Sheung Tan Barging Point and Tsing Chau Tsai
Barging Point
12.37
Each of these two barging points would
include two ramps (see Figure No. NOL/ERL/300/C/XRL/
ENS/M50/014 and NOL/ERL/300/C/XRL/ENS/M50/015). The construction activities within these
works areas would be limited to material handling at the temporary stockpiles and unloading
spoils to the
barges. Other construction activities
would not be undertaken concurrently within the study areas. With the implementation of measures as
mentioned in Sections 12.30 and 12.31, dust impact arising from the operation of
these two barging points are not expected.
Concrete Batching Plant
12.38
A concrete batching plant would be located at
12.39
The aggregate would be transported through
both marine and land access by barge and tipper trucks, respectively. The aggregates would be unloaded onto the
receiving hopper (for both land and marine access) provided with enclosures on three sides in addition to top cover and equipped
with water spraying system. The conveyor belt underneath the receiving
hopper would transfer the aggregates to the proper compartment of the overhead
storage bins of the batching plant.
12.40
The cement would also be transported through
both marine and land access by barge and cement tankers respectively. The cement by barge would be unloaded onto
the receiving hopper and then transfer to the two large capacity cement silos
via air slide. On the land access,
cement tanker and PFA tanker would be towed by tractors to the plant site. The tractors would be equipped with a blower
for blowing cement or PFA via flexible duct directly from the tanker into the
nine small cement/PFA silos (3 cement silos and 6 PFA silos) of the concrete
batching plant. Each silo would have a
level sensor to monitor and control the refilling level of cement/PFA. Once the material has reached the designated
level, the alarming system, with ringing sound and flashing light, would be activated to draw the attention of
responsible operator to stop the pumping process manually.
12.41
The size of aggregates bins and cement silo
are sufficient to ensure concrete production, therefore, there is no storage
area within the site. The aggregate and
cement conveying systems are fully enclosed.
12.42
Aggregates would be transferred to the
weighting hopper via a chute from their overhead storage bins. Cement/PFA would be loaded into the weighting
hopper via a crew conveyor from their respective silo. Admixture and water would be supplied to
their respective weighting hopper via pipes linking the supply sources and the
weighing hoppers. Each batch of raw
materials would be weighed on the weighing hoppers of the batching plant before
discharging into the mixer for thorough mixing.
The whole process of weighing and mixing is performed in a totally
enclosed environment (i.e. Mixing Tower 1, 2 and 3). After completion of the mixing process, the
concrete would be discharged from the mixer into the transit mixer of a truck.
12.43
The maximum consumption rate of raw materials
per day would be 1,200 tonnes of cement, 450 tonne of PFA and 6,000 tonnes of
aggregate. One dust collector is assumed to serve for each silo/mixer, therefore,
fourteen dust collectors in total would be employed in the concrete batching
plant. The filter
capacity of dust collectors for large capacity cement silo and small silo/mixer
would be 3,528 m3/hour
and 1,780 m3/hour, respectively. The design emission
concentrations of the dust collectors for large capacity cement silo, mixer and
small silos for cement/PFA would be limited to not more than 50mg/m3;
40mg/m3 and 30mg/m3. The area within the plant would be paved and
water spraying would be provided on the haul roads to keep wet condition. Vehicle washing facility would be provided at
the gate for wheel washing before leaving the plant.
12.44
The potential dust emissions sources of the
concrete batching plant would be unloading of aggregate on the receiving
hoppers, haul road within
the plant and dust collectors on the top of large capacity
cement silos, cement/PFA silos and mixers.
Temporary Magazine Sites
12.45
The construction of the Project would involve
substantial amount of rock excavation of which majority could be carried out by
drill and blast method. Two temporary magazine sites are proposed to be
constructed at the areas in the vicinity of
Cumulative Dust Impacts from Other Concurrent Projects
12.46
The construction works would commence in
December 2009 and the overall project completion is anticipated to be in
2015. As discussed in Section 2, the
Project is likely interactions with the some projects (excluding
Table 12.8 Interfacing
Project
Interfacing Project |
Construction
Period |
Nearby Work Site |
Possible cumulative adverse dust impacts |
Road Works at |
2012 to 2014 |
|
The maximum operation rate of all
construction activities and the largest size of the construction work sites
for XRL would occur in 2010. In the 3rd quarter of 2011, the area of
the cut and cover work site at |
Construction of Cycle Tracks and the
associated Supporting Facilities from Sha Po Tsuen to |
Mid 2009 to Early 2012 |
Mai Po Shaft |
No.
Insignificant dust impact from construction of cycle tracks and
associated supporting facilities is expected as mentioned in the approved EIA
Report. |
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long |
2008 to 2012 |
Mai Po Shaft |
No. As mentioned in respective approved EIA Report, the potential
air quality impact is anticipated to be short-term and can be controlled at
acceptable levels through appropriate design and good site practice
stipulated in the Air Pollution Control (Construction Dust) Regulation. |
Upgrading of Remaining Sections of |
2010 to 2014 |
Shek Kong Stabling Sidings |
No. Localized dust impact from upgrading
works of |
Yuen Long & Kam
Tin Sewerage and Sewage Disposal |
2009 to 2013 |
Mai Po Shaft and Shek
Kong Stabling Sidings |
No. Dust
impact would be localized. |
Operation Phase
12.47 During operation of the Project, no air pollutants emissions would be
generated from the electrical railway.
The only source of carbon dioxide (CO2) would be from the
breathing of the passengers and staff working in the station. The ventilation system is designed for an air
exchange rate of 5 litre/person/second in accordance with MTRC Design
Manual. As a result, all CO2
exhaled by passengers/staff would be sufficiently diluted by the fresh air
intake before being discharged through the normal air exchange. Similar to
other electrified rail projects with substantial sections underground (e.g.
Kowloon Southern Link), air quality impact from the operations of vent shafts
would not be considered a key environmental issue.
12.48 The vent shaft is also designed to be sited at more than 5m from any
opening at the adjacent building, in accordance with the Fire Services
Department’s requirement. According to
the preliminary design of Project, the distance between the vent shafts and
openings of the adjacent building would be over 8m away, and at this distance,
there should be no noticeable temperature effect as a result of emissions from
vent shafts. The vent shafts would
therefore not expect to lead to adverse air quality impacts to the
neighbourhood. It is noted that the
separation distance between the
12.49
In accordance with
the preliminary design, maximum of six diesel or electrical locomotives will be
provided at SSS. Potential air
pollutants emitted from the diesel locomotive would include nitrogen dioxide,
sulphur dioxide and particulates.
However, the potential air quality is expected to be insignificant as it
is in occasional operation and only one diesel locomotive to be operated at one
time.
12.50
The potential air quality impact on PTI at the Ventilation Building Complex (next to
West Kowloon Terminus) would
be traffic emissions from travelling and idling vehicles. To alleviate the adverse air quality impacts,
mechanical air ventilation would be provided to the PTI. The design of the ventilation system would
fulfil the air quality guideline of PTI stipulated in EPD’s ProPECC
PN1/98 Control of Air Pollution in Semi-confined Public Transport
Interchanges. No adverse air quality in
the PTI would be anticipated.
Construction Phase
12.51
Referring to Sections 12.11 – 12.46, potential adverse dust impact would be
expected from open-cut excavation for some sections of Project alignment at
12.52
Regarding construction of adits/shafts/ventilation
buildings/EAP at other areas, loading and unloading of spoils at the adits/shafts and nearby stockpiles, minor excavation for
SSS and operation of magazine sites, no adverse dust impact at nearby sensitive
receivers would be expected due to limited dusty construction activities and minor excavation works. With the implementation of dust suppression
measures as stipulated in Air Pollution Control (Construction Dust) Regulation,
no adverse dust impacts would be expected from these construction activities.
Therefore, the potential dust impacts arising from these works areas are
addressed qualitatively in the study, except that the stockpiles at Pat Heung Adit and Tse Uk
Tsuen Shaft which would be located within
12.53
Limited dust impact from unloading of spoils
at the barging points would be expected as the tipping hall is
provided with enclosures on three sides and top cover. In addition, the mitigation measures such as
water spraying system and dust curtain provided at the loading point, well covered the
inactive temporary stockpiles areas, and water spraying on the active
stockpiles area and haul roads would also be applied. However, the barging points at
Emission Inventory
12.54
Predicted dust emissions are based on emission factors from USEPA
Compilation of Air Pollution Emission Factors (AP-42), 5th Edition. The scenario under the peak rate of all
construction activities and the largest size of works sites are considered in
the assessment. The major dusty
construction activities for the Project to be considered in the modelling
assessment include:
(A)
(i) Barging Point (5 ramps)
-
Transportation of
the spoils to the enclosed tipping hall of Barging Point by trucks on the paved
haul road
-
Unloading point to
the barge
(ii) Tunnel Cut & Cover areas and West Kowloon Terminus
-
Heavy construction
activities including excavation and material handlings within the construction
site
-
Wind erosion of
open active site
-
Materials handling
and wind erosion at the active stockpile
-
(iii) Concrete Batching Plant
-
Unloading of
aggregates to the receiving hopper
-
Emissions from
dust collectors on the top of large capacity cement silos, cement/PFA silos and
mixers
-
Transporting of
raw materials/products by trucks on the paved haul road within the plant
(B)
(i) Barging Point (3 ramps)
-
Transportation of
the spoils to the enclosed tipping hall of Barging Point (2 ramps) by trucks on
the paved haul road
-
Unloading point to
the barge
-
Materials handling
and wind erosion at the active temporary stockpile (emergency use)
(ii) Tunnel Cut & Cover areas and vent shaft
-
Heavy construction
activities including excavation and material handlings within the construction
site
-
Wind erosion of
open active site
-
Materials handling
and wind erosion at the active stockpile
(C) Shek Kong Works Area
(i) Tunnel Cut & Cover areas and vent
shaft
-
Heavy construction
activities including excavation and material handlings within the construction
site
-
Wind erosion of
open active site
(ii) ERS site
-
Heavy construction
activities including excavation, stockpile handling works and slope works
within the construction site
-
Emissions from
trucks travelling on paved haul roads
-
Wind erosion of
open active site
12.55
According to the preliminary engineering
design information, the maximum production capacity of the concrete batching
plant would be 3,000 m3 per day.
The total capacity of silo exceeds 50 tonnes and in which cement is
handled. The operation of the concrete
batching plant is therefore classified as Specified Process (SP). The Contractor should apply the SP license
under APCO. The requirements and
mitigation measures stipulated in the Guidance
Note on the Best Practicable Means for Cement Works (Concrete Batching Plant)
BPM 3/2(93) should be followed and implemented. The dust control measures have been
incorporated into the design of the concrete batching plant, barging facilities
and stockpile areas, as presented in Tables
12.9, 12.10
and 12.11, respectively. The schematic diagrams for the barging points with the dust emission
control measures are presented in Appendix
12-1. These dust control measures
have also been taking into account in the assessment.
Table 12.9 Concrete Batching
Plant – Dust Emission Design Control Measures
Process |
Description |
Dust
Emission Design Control Measures |
Unloading of raw materials |
Unloading
of aggregates from the tipper trucks to receiving hopper. |
The
aggregates would be unloaded from the tipper trucks to the receiving hopper
equipped with enclosures on 3 sides and top cover, and water spraying
system. As a worst case scenario, minimal
dust emission would be generated during unloading the raw materials. |
Unloading
of cement and PFA from tankers into the silo. |
The
cement and PFA would be directly loaded into the silo via a flexible
duct. Dust collectors would be
installed at cement/PFA silos, therefore, no dust emission would be expected. |
|
Transfer
of raw materials |
Storage
of aggregates in overhead storage bins. |
The
aggregates would be stored in fully enclosed overhead storage bins. The top of overhead storage bins would be
covered with cladding. Water spraying
system would be installed at the top of storage bins for watering the
aggregates, and aggregate storage bins would be fully enclosed. Thus, no dust emission would be expected. |
Batching
of raw materials |
Weighing
and Batching of cementitious materials |
The
whole process of weighing and mixing would be performed in a fully enclosed
environment. The mixers would all
equip with dust collectors, no dust emission would be expected. |
Truck
loading |
Loading
of concrete from mixer into transit
mixer of a truck |
The
concrete would be directly loaded from the mixer into the transit mixer of a
truck in “wet” form, no dust would be generated in this process. |
Trucks |
Tipper
trucks and cement tankers within the site. |
Haul
road within the site is paved. Wheel
washing pit would be installed at the gate of the concrete batching
plant. Insignificant dust emission
generated from the paved haul road would be expected. Water spraying system would be installed
along the haul road. |
Table 12.10 Cut & Cover Area
and Stockpiles – Dust Emission Design Control Measures
Process |
Description |
Dust
Emission Design Control Measures |
Cut & Cover Areas and Stockpiles in the vicinity
of adits/shafts |
||
Heavy construction activities at Cut &
Cover Areas, Storage of materials at
Stockpiles |
Active areas for heavy construction
activities, loading & unloading
materials at stockpiles |
The specified requirements for cut & cover
areas and stockpiles at (i) Shek Kong works area – active area minimized to 15% of
total area, watering with complete coverage of active area ten times a day. (ii) Nam Cheong works area – active area
minimized to 30% of total area, watering with complete coverage of active
stockpile area four times a day. (iii) West Kowloon works area – active area
minimized to 15% of total area, watering with complete coverage of active
area eight times a day. For other sites, the active area would be
minimized to 30% of the total area, water spraying system would be applied on
the active area and watering with complete coverage of active area four times
a day would be required. The remaining inactive area would be well
covered with impervious sheeting at all work sites. |
Trucks |
Transportation of materials |
Wheel wash facilities provided at the site
exit. The vehicles would be washed before leaving the stockpiles. The spoils would also be well covered
before leaving the site in order to minimise generation of dusty materials. The haul roads within the site would be all
paved and water spraying would be provided to keep the wet condition. For the Shek Kong
works area, watering paved haul roads once per hour would be provided. |
Temporary stockpiles in the vicinity of
barging points |
||
Loading point |
Loading of spoils from trucks onto stockpile |
Water spraying would be provided at the loading
points to suppress the dust impact. |
Storage of materials |
Active area for loading & unloading
materials |
Water spraying system would be applied on the
active area and watering with complete coverage of active area four times a day
would be required. |
Table 12.11 Barging Facilities –
Dust Emission Design Control Measures
Process |
Description |
Dust
Emission Design Control Measures |
Haul road within barging facilities |
Transportation of spoils to the Barging Point |
All road surfaces within the barging
facilities would be paved and water spraying would be provided to keep the
wet condition. For haul roads at |
Unloading of materials |
Unloading of spoil materials to the barge |
The unloading process would be undertaken
within enclosed tipping hall. Water
spraying and dust curtain would be provided at the discharge point for dust
suppression. |
Trucks |
Vehicles leaving the barging facility |
Vehicle wheel washing facilities provided at
site exit. |
Transportation of spoils (only for one of Nam
Cheong Barging Point) |
Transportation of spoils to Nam Cheong
Barging Point |
Fully enclosed conveyor system would be
adopted for transportation of spoils from shaft to the barging point. |
12.56
The excavation rate, material handling rate,
moisture content, silt content, number of trucks and truck speed are based on
the preliminary engineering design. The
emission rate of identified pollutant sources in the
Table 12.12 Emission Factors
for Dusty Construction Activities at
Emission Source |
Activity |
Emission
Rate |
Remarks |
Concrete Batching Plant |
Unloading of aggregates to the
receiving hopper of concrete batching plant |
E
= = 2.43056 x 10- |
AP42
Section 11.12, (aggregate transfer)
Max. loading rate of aggregate = 500 tons/hr
95%
reduction for the unloading in the tipping hall with enclosures on three
sides in addition to top cover, and equipped with water spraying system |
Dust collector for
each small Cement Silo |
E
=30mg/m3 =1.48333 x 10 |
Design
emission concentration of 30 mg/m3
Exhaust
Rate for dust collector:
Number
of small Cement Silos: 3 |
|
Dust collector
for each Large Capacity Cement Silo |
E
=50mg/m3 =4.90000x 10 |
EPD
BPM for Cement Works (Concrete Batching Plant) emission limits: 50mg/m3
Exhaust
Rate for dust collector: 3528m3/hr
Number
of Large Capacity Cement Silos: 2 |
|
|
Dust
collector for each PFA Silo |
E
=30mg/m3 =1.48333 x 10 |
Design
emission concentration of 30 mg/m3
Exhaust
Rate for dust collector:
Number
of PFA Silos: 6 |
|
Dust
collector for each Mixer |
E
=40mg/m3 =1.97778x 10 |
Design
emission concentration of 40 mg/m3
Exhaust
Rate for dust collector:
Number
of Mixer: 3 |
|
Paved |
E = =6.92456 x 10-4 g/m/s |
E=k´(sL/2)^0.65´(W/3)^1.5
Particle
size multiplier:
Silt
content:
Averaged
truck weight: 21 tons
No. of
truck trips: 420 truck trips/day,
95%
reduction by water spraying to keep wet condition on paved haul road and
wheel washing pit installed at the gate of the concrete batching plant.
AP42,
Section |
Cut
and Cover Locations and stockpile area at West Kowloon Works Area |
Cut and Cover Area and Stockpile |
E=2.69 Mg/hectare /month
of activity =3.89178 x 10-6 g/m2/s |
15%
area actively operating
87.5%
reduction by complete watering coverage of active construction area eight
times a day
AP42,
Section |
|
Wind Erosion (night time) |
E=0.85Mg/hectare /year =4.043 x 10 |
15%
active site
AP42,
Table |
Barging Point at |
Unloading of spoils to barge at West Kowloon Terminus Works Area |
E=3.54 x
10 =
4.26664 x 10-3 g/s |
E= k x
(0.0016) x [(U/2.2)^1.3 / (M/2)^1.4]
AP-42,
S
Material
Moisture Content (M) : 5%
Max.
handling capacity for each barging point: 434Mg/hr
Number
of barging points at West Kowloon Works Area: 5
Unloading
within the tipping hall with enclosures on three sides in addition to a top
cover, water spray and flexible dust curtain will be provided at discharging
point. 90% reduction of dust emission
assumed. |
Paved haul road -Transport the spoil from the stockpile to the Barging
Point (The paved haul road served for 5 ramps, therefore, number of trucks on
each section of the haul road would be different. Details refer to Appendix 12.1) |
E = =1.97363 x 10 =3.94727
x 10-4 g/m/s (for 720 truck
trips) =4.93408
x 10-4 g/m/s (for 900 truck trips) =5.92090
x 10-4 g/m/s (for 1080 truck trips) =7.89453 x 10-4 g/m/s (for 1440 truck trips) =9.86817
x 10-4 g/m/s (for 1800 truck trips) |
E=k´(sL/2)^0.65´(W/3)^1.5
Particle
size multiplier: 24g/VKT
Silt
content:
Averaged
truck weight: 16 tons
No. of
truck trips: 360 to 1800 truck trips/day
97.5%
reduction by watering haul road once per hour and keeping paved haul roads in
wet condition.
AP42,
Section 13.2.1. |
Table 12.13 Emission Factors
for Dusty Construction Activities at
Emission Source |
Activity |
Emission Rate |
Remarks |
Construction
Site for cut-cover section of Project Alignment and ventilation building |
Heavy Construction Activities and Stockpile Areas |
E=2.69 Mg/hectare /month of activity =1.55671 x 10 |
30%
area actively operating
75%
reduction by complete watering coverage of active construction area four
times a day AP42, Section 13.2.3 |
Wind
Erosion (night time) |
E=0.85Mg/hectare /year =8.08600 x 10-7 g/m2/s |
30%
active site
AP42,
Table 11.9.4 |
|
|
Paved
|
E = =6.31563 x 10 |
E=k´(sL/2)^0.65´(W/3)^1.5
Particle
size multiplier: 24g/VKT
Silt
content:
Averaged
truck weight: 16 tons
No. of
truck trips: 288 truck trips/day
90%
reduction by water spraying to keep wet condition on paved haul roads
AP42,
Section |
Barging point at Nam Cheong Works Area |
Unloading of spoils from conveyor /
trucks to barge for Nam Cheong Works Area |
E =1.28x10 = 1.67442 X 10-2 g/s |
E= k x
(0.0016) x [(U/2.2)^1.3 / (M/2)^1.4]
AP-42,
S
Material
Moisture Content (M) : 2%
Max.
handling capacity for each barging point: 473Mg/hr
Number
of barging points for Nam Cheong Works Area: 2
Unloading
within the tipping hall with enclosures on three sides in addition to a top
cover, water spray and flexible dust curtain will be provided at discharging
point. 90% reduction of dust emission
assumed. |
|
Unloading of spoils by trucks to
barge for West Kowloon Terminus Works Area |
E =3.54x10 = 4.26664 X 10- |
E= k x
(0.0016) x [(U/2.2)^1.3 / (M/2)^1.4]
AP-42,
S
Material
Moisture Content (M) : 5%
Max.
handling capacity for each barging point: 434Mg/hr
Number
of barging points for West Kowloon Terminus at Nam Cheong Works Area: 1
Unloading
within the tipping hall with enclosures on three sides in addition to a top
cover, water spray and flexible dust curtain will be provided at discharging
point. 90% reduction of dust emission
assumed. |
|
Paved haul road -Transport the spoil to the
Barging Point (The paved haul road served for 2 ramps, therefore, number of
trucks on each section of the haul road would be different.) |
E = =1.97363 x 10 =3.94727 x 10-4 g/m/s (for 720 truck trips) |
E=k´(sL/2)^0.65´(W/3)^1.5
Particle
size multiplier:
Silt
content:
Averaged
truck weight: 16 tons
No. of
truck trips: 360 to 720 truck trips/day
97.5%
reduction by watering haul road once per hour and keeping paved haul roads in
wet condition.
AP42,
Section |
Temporary
Stockpile Area at |
Loading & unloading of materials |
E=2.69 Mg/hectare /month of activity =1.55671
x 10-5 g/m2/s |
30%
area actively operating
75%
reduction by complete watering coverage of active construction area four
times a day
AP42,
Section 13.2.3 |
|
Wind
Erosion (night time) |
E=0.85Mg/hectare /year =8.08600
x 10-7
g/m2/s |
30%
active site
AP42,
Table 11.9.4 |
Table 12.14 Emission Factors
for Dusty Construction Activities at Shek Kong Works Area
Emission Source |
Activity |
Emission
Rate |
Remarks |
Construction Site for cut-cover section of Project Alignment
and ventilation building |
Cut and Cover Areas and Stockpile Areas |
E=2.69 Mg/hectare /month
of activity =3.11343 x 10-6 g/m2/s |
15%
area actively operating
90%
reduction by complete watering coverage of active construction area ten times
a day
AP42,
Section |
Wind Erosion (night time) |
E=0.85Mg/hectare /year =4.04300 x 10- |
15%
active site
AP42,
Table |
|
|
Paved |
E = =4.01305 x 10-4 g/m/s (for 732 truck trips) =2.30257 x 10 |
E=k´(sL/2)^0.65´(W/3)^1.5
Particle
size multiplier: 24g/VKT
Silt
content:
Averaged
truck weight: 16 tons
No. of
truck trips: 420-732 truck trips/day
97.5%
reduction by watering the paved haul roads once per hour and keeping the haul
road in wet condition.
AP42,
Section |
|
Paved |
E = =1.57891 x 10- |
E=k´(sL/2)^0.65´(W/3)^1.5
Particle
size multiplier:
Silt
content:
Averaged
truck weight: 16 tons
No. of
truck trips: 72 truck trips/day
90%
reduction by water spraying to keep wet condition on paved haul roads
AP42,
Section |
|
Paved |
E = =3.15781 x 10 |
E=k´(sL/2)^0.65´(W/3)^1.5
Particle
size multiplier:
Silt
content:
Averaged
truck weight: 16 tons
No. of
truck trips: 288 truck trips/day
95%
reduction by water spraying to keep wet condition on paved haul roads and the
wheels of the trucks would be washed before entering the site.
AP42,
Section |
12.57
The design emission concentrations of the
dust collectors for cement/PFA silos and mixers of the concrete batching plant
would follow the recommendation in Table 12.12.
As advised by the Project Proponent, an active operation area of 15% is assumed for cut and cover areas at
Dispersion Modelling & Concentration Calculation
12.58
Fugitive Dust Model (FDM) (1993 version) is
adopted to assess potential dust impact from the construction works. The worst case meteorological condition is
used to predict the maximum 1-hour and 24-hour average TSP concentrations at
representative discrete ASRs in the vicinity of the construction sites. The height of 1.5m (the breathing level of
human), 5m, and 10m above ground are adopted
for the construction dust impact assessment.
For
·
Wind direction: 360 wind directions
·
Stability class: D (daytime) & F (night time)
·
Surface roughness: 1m
12.59
The background TSP level of 103
mg/m3,
based on the latest five years average monitoring data from EPD Yuen Long
monitoring station, is adopted as an
indication of the TSP background concentration at Shek
Kong works area during construction phase; while the background TSP level of 81
mg/m3,
based on the latest five years monitoring data from EPD Sham Shui Po monitoring station, is
adopted as indication of TSP background concentration at Nam Cheong and West
Kowloon works areas during the construction phase.
12.60
For the prediction of the annual TSP
concentrations due to the Project, Year 2005
meteorological data of King’s Park Weather Station are adopted for prediction
of the annual average TSP concentrations at the discrete ASRs in the vicinity
of
12.61
Actually, there are no construction
activities operated on Sundays and the public holidays. For the annual TSP concentration prediction,
the hours from 0700 to 1900 in the year excluding these days are adopted for
assessment of the daytime construction activities; while the hours from 1900 to
0700 in the year and the hours during Sunday and the public holidays are adopted
for impact assessment of wind erosion on the sites. For the temporary stockpile area at Nam
Cheong Barging Points, it would be for emergency use when the barging points
cannot be operated (e.g. Typhoon No.3 or above hoist). Therefore, this temporary stockpile is
considered to be operated for a month (in summer season) in the annual TSP
prediction. Regarding the Shek Kong works area, the bulk excavation period for ERS at
Shek Kong and Shek Kong
Stabling Sidings would be last for 8 months (from October 2011 to May 2012)
only and the construction activities in the remaining period would be
superstructure construction works which are not dusty construction activities.
This factor has taken into account in the annual prediction for the ASRs in the
vicinity of Shek Kong works area.
12.62
Maximum emission rates of dusty construction
activities are considered in all operation
hours in the modelling. However, the
emissions from dusty construction activities would not be always in the maximum
rate as confirmed from the engineer. Therefore, there is a reduction of 50% in the
annual concentrations prediction assuming that the normal emission rates of
dusty construction activities would be half of the peak dust emission rates.
Operation Phase
12.63
As there is no significant air quality impact
during operation of the Project and PTI, qualitative approach is adopted to
address the air quality implications.
Prediction and Evaluation of Impacts
Construction
Phase
12.64
The predicted cumulative maximum hourly and
daily average TSP concentrations at the representative ASRs due to construction
activities at
12.65
Based on the results indicated in Tables 12.15 and 12.16, the predicted maximum 1-hour
and 24-hour average TSP concentrations at all
representative ASRs would comply with the criteria in EIAO-TM and AQO. The contour plots at 1.5m, 10m and 20m above
ground level (AGL) are presented. The
contour plots of 1-hour and 24-hour average TSP concentrations at
Table 12.15 Predicted
Cumulative Maximum Hourly Average TSP Concentrations at Representative Air
Sensitive Receivers (
ASRs |
Cumulative
Maximum Hourly Average TSP Concentrations in mg/m3 |
||||||
1.5m AGL |
5m AGL |
10m AGL |
15m AGL |
20m AGL |
30m AGL |
40m AGL |
|
MKA1 |
96 |
97 |
97 |
96 |
96 |
94 |
92 |
MKA2 |
98 |
99 |
98 |
98 |
97 |
95 |
93 |
WKA1 |
113 |
114 |
112 |
110 |
107 |
102 |
96 |
WKA2 |
108 |
109 |
108 |
106 |
104 |
100 |
96 |
WKA3 |
-
|
- |
- |
126 |
117 |
104 |
96 |
WKA5 |
209 |
213 |
261 |
351 |
365 |
153 |
96 |
WKA6 |
-
|
- |
- |
125 |
118 |
105 |
96 |
WKA7 |
-
|
- |
- |
- |
- |
106 |
96 |
WKA8 |
- |
- |
- |
130 |
120 |
106 |
96 |
WKA9 |
138 |
138 |
130 |
122 |
114 |
102 |
95 |
Note: 1. The
background TSP level of 81 mg/m3 has been included in
the above results.
2. The
air sensitive uses at WKA3, WKA6 and WKA8 are
not less than 15m
AGL; air
sensitive uses at WKA7 are not less than 30m AGL.
Table 12.16 Predicted
Cumulative Maximum 24-Hour Average TSP Concentrations at Representative Air
Sensitive Receivers (
ASRs |
Cumulative
Maximum 24-Hour Average TSP Concentrations in mg/m3 |
||||||
1.5m AGL |
5m AGL |
10m AGL |
15m AGL |
20m AGL |
30m AGL |
40m AGL |
|
MKA1 |
90 |
90 |
90 |
90 |
89 |
88 |
87 |
MKA2 |
91 |
91 |
91 |
90 |
90 |
89 |
87 |
WKA1 |
99 |
100 |
99 |
97 |
95 |
92 |
89 |
WKA2 |
96 |
97 |
96 |
95 |
94 |
91 |
89 |
WKA3 |
-
|
- |
- |
105 |
99 |
92 |
88 |
WKA5 |
148 |
149 |
172 |
217 |
223 |
117 |
88 |
WKA6 |
-
|
- |
- |
104 |
100 |
93 |
88 |
WKA7 |
-
|
- |
- |
- |
- |
94 |
89 |
WKA8 |
- |
- |
- |
106 |
100 |
93 |
89 |
WKA9 |
114 |
113 |
108 |
103 |
98 |
92 |
88 |
Note: 1. The
background TSP level of 81 mg/m3 has been
included in the above results.
2. The
air sensitive uses at WKA3, WKA6 and WKA8 are
not less than 15m
AGL; air
sensitive uses at WKA7 are not less than 30m AGL.
Table 12.17 Predicted
Contributions to Annual Average TSP Concentrations at Representative Air
Sensitive Receivers (
ASRs |
Annual Average TSP Concentrations in mg/m3 due to the
Project |
||||||
1.5m AGL |
5m AGL |
10m AGL |
15m AGL |
20m AGL |
30m AGL |
40m AGL |
|
MKA1 |
0.07 |
0.07 |
0.07 |
0.07 |
0.06 |
0.06 |
0.05 |
MKA2 |
0.08 |
0.09 |
0.08 |
0.08 |
0.08 |
0.07 |
0.06 |
WKA1 |
0.17 |
0.18 |
0.17 |
0.15 |
0.14 |
0.11 |
0.09 |
WKA2 |
0.17 |
0.17 |
0.16 |
0.15 |
0.14 |
0.11 |
0.09 |
WKA3 |
- |
- |
- |
0.74 |
0.53 |
0.32 |
0.22 |
WKA5 |
1.29 |
1.25 |
1.21 |
1.34 |
1.33 |
0.60 |
0.29 |
WKA6 |
- |
- |
- |
2.18 |
1.77 |
1.17 |
0.77 |
WKA7 |
- |
- |
- |
- |
- |
1.04 |
0.66 |
WKA8 |
- |
- |
- |
1.65 |
1.20 |
0.70 |
0.45 |
WKA9 |
0.52 |
0.52 |
0.44 |
0.37 |
0.32 |
0.23 |
0.17 |
Note: 1.
The background TSP level is 81 mg/m3.
2. The
air sensitive uses at WKA3, WKA6 and WKA8 are
not less than 15m
AGL; air
sensitive uses at WKA7 are not less than 30m AGL.
12.66
The annual average TSP concentrations at the
representative ASRs due to construction activities at
12.67
The predicted cumulative maximum hourly and
daily average TSP concentrations at the representative ASRs due to construction
activities at Nam Cheong works area are presented in Tables 12.18 and 12.19.
12.68
Based on the results indicated in Tables
12.18 and 12.19, the predicted maximum 1-hour and
24-hour average TSP concentrations at all
representative ASRs would comply with the criteria in EIAO-TM and AQO. It is noted that the worst levels would be at
Table 12.18 Predicted
Cumulative Maximum Hourly Average TSP Concentrations at Representative Air
Sensitive Receivers (
ASRs |
Cumulative
Maximum Hourly Average TSP Concentrations in mg/m3 |
||
1.5m AGL |
5m AGL |
10m AGL |
|
NCA4 |
96 |
97 |
96 |
NCA5 |
142 |
128 |
107 |
NCA6 |
128 |
127 |
118 |
NCA7 |
149 |
144 |
126 |
NCA8 |
126 |
- |
- |
Note: 1. The
background TSP level of 81 mg/m3 has been included in
the above results.
2. ASR NCA8 is
one-storey high.
Table
12.19 Predicted Cumulative Maximum
24-Hour Average TSP Concentrations at Representative Air Sensitive Receivers (
ASRs |
Cumulative
Maximum 24-Hour Average TSP Concentrations in mg/m3 |
||
|
|
|
|
NCA4 |
89 |
90 |
89 |
NCA5 |
114 |
106 |
95 |
NCA6 |
107 |
106 |
100 |
NCA7 |
116 |
113 |
104 |
NCA8 |
105
|
- |
- |
Note: 1. The
background TSP level of 81 mg/m3 has been
included in the above results.
2. ASR NCA8 is one-storey high.
Table 12.20 Predicted Contributions to Annual Average
TSP Concentrations at Representative Air Sensitive Receivers (
ASRs |
Annual Average TSP
Concentrations in mg/m3 due to the
Project |
||
|
|
|
|
NCA4 |
0.02 |
0.02 |
0.02 |
NCA5 |
1.44 |
1.07 |
0.61 |
NCA6 |
0.36 |
0.35 |
0.29 |
NCA7 |
1.19 |
1.06 |
0.78 |
NCA8 |
1.99 |
- |
- |
Note: 1. The
background TSP level is 81 mg/m3.
2. ASR NCA8 is one-storey high.
12.69
The annual average TSP concentrations at the
representative ASRs due to construction activities at Nam Cheong works area are
also predicted and presented in Table
12.20. The
predicted maximum contribution to the annual average TSP concentrations from the Project would be 1.99 mg/m3 (2.49% of
annual TSP AQO) occurring at ASR NCA8 at 1.5m AGL. The predicted contributions to the annual
average TSP concentrations at other
representative ASRs from the Project would be
increased by 0.02 – 1.44 mg/m3 (0.03% - 1.8% of
annual TSP AQO) only. The dust impacts arising from the Project to the ASRs are
considered insignificant. The contour
plots of annual TSP concentrations at
Shek Kong Works Area
12.70
The predicted cumulative maximum hourly and
daily average TSP concentrations at the representative ASRs due to construction
activities at Shek Kong works area are presented in Tables 12.21 and 12.22.
12.71
Based on the results indicated in Tables
12.21 and 12.22, the predicted 1-hour and 24-hour average TSP concentrations at all representative ASRs would comply with
the criteria in EIAO-TM and AQO. It is
noted that the worst levels would be at
Table 12.21 Predicted
Cumulative Maximum Hourly Average TSP Concentrations at Representative Air
Sensitive Receivers (Shek Kong Works Area)
ASRs |
Cumulative
Maximum Hourly Average TSP Concentrations in mg/m3 |
||
|
|
|
|
PHA1 |
129 |
129 |
124 |
PHA2 |
251 |
177 |
128 |
SSA1 |
162 |
150 |
139 |
SSA1a |
150 |
149 |
140 |
SSA1b |
172 |
162 |
144 |
SSA2 |
142 |
141 |
134 |
SSA3 |
146 |
146 |
139 |
SSA4 |
147 |
143 |
134 |
SSA5 |
125 |
126 |
125 |
SSA7 |
146 |
145 |
138 |
SSA8 |
129 |
128 |
124 |
SSA9 |
163 |
150 |
140 |
SSA10 |
173 |
167 |
151 |
SSA11 |
152 |
149 |
139 |
SSA12 |
146 |
140 |
133 |
TUA1 |
137 |
128 |
118 |
TUA2 |
171 |
136 |
118 |
Note: The
background TSP level of 103 mg/m3 has been
included in the above results.
Table 12.22 Predicted
Cumulative Maximum 24-Hour Average TSP Concentrations at Representative Air
Sensitive Receivers (Shek Kong Works Area)
ASRs |
Cumulative
Maximum 24-Hour Average TSP Concentrations in mg/m3 |
||
1.5m AGL |
5m AGL |
10m AGL |
|
PHA1 |
116 |
116 |
114 |
PHA2 |
178 |
140 |
116 |
SSA1 |
135 |
129 |
123 |
SSA1a |
130 |
129 |
123 |
SSA1b |
140 |
134 |
125 |
SSA2 |
123 |
123 |
119 |
SSA3 |
126 |
126 |
122 |
SSA4 |
128 |
125 |
120 |
SSA5 |
115 |
115 |
115 |
SSA7 |
126 |
125 |
121 |
SSA8 |
117 |
117 |
114 |
SSA9 |
139 |
130 |
123 |
SSA10 |
139 |
136 |
128 |
SSA11 |
128 |
127 |
121 |
SSA12 |
127 |
124 |
119 |
TUA1 |
122 |
117 |
111 |
TUA2 |
138 |
120 |
112 |
Note: The
background TSP level of 103 mg/m3 has been
included in the above results.
Table 12.23 Predicted
Contributions to Annual Average TSP Concentrations at Representative Air
Sensitive Receivers (Shek Kong Works Area) from the Project
ASRs |
Cumulative
Annual Average TSP Concentrations in mg/m3 due to the
Project |
||
1.5m AGL |
5m AGL |
10m AGL |
|
PHA1 |
0.06 |
0.06 |
0.05 |
PHA2 |
1.13 |
0.43 |
0.13 |
SSA1 |
0.78 |
0.49 |
0.26 |
SSA1a |
0.36 |
0.30 |
0.21 |
SSA1b |
2.34 |
1.36 |
0.56 |
SSA2 |
1.21 |
1.10 |
0.79 |
SSA3 |
0.48 |
0.41 |
0.28 |
SSA4 |
0.60 |
0.48 |
0.32 |
SSA5 |
0.16 |
0.16 |
0.14 |
SSA7 |
1.42 |
1.13 |
0.65 |
SSA8 |
0.37 |
0.35 |
0.27 |
SSA9 |
2.00 |
0.89 |
0.42 |
SSA10 |
0.94 |
0.78 |
0.47 |
SSA11 |
1.41 |
1.25 |
0.85 |
SSA12 |
0.66 |
0.55 |
0.38 |
TUA1 |
0.37 |
0.30 |
0.20 |
TUA2 |
0.96 |
0.45 |
0.20 |
Note: The
background TSP level is 103 mg/m3.
12.72
The annual average TSP concentrations at the
representative ASRs due to construction activities at Shek
Kong works area are also predicted and presented in Table 12.23. The predicted
maximum contribution to annual average TSP concentrations from the Project would be 2.34 mg/m3
(2.93% of annual TSP AQO) occurring at ASR SSA1b at 1.5m
AGL. The predicted contributions to the
annual average TSP concentrations at other representative ASRs from the Project
would be increased by 0.05 – 2 mg/m3 (0.06 – 2.5% of
annual TSP AQO) only. Since the major
dusty activities, bulk excavation at Shek Kong works
area, would be last for 8 months only, and the predicted maximum hourly and
24-hour average TSP concentrations at all representative ASRs would comply with
the criteria in EIAO-TM and AQO, the dust impact arising from the Project to
the ASRs is considered insignificant.
The contour plots of annual TSP concentrations at
Barging Points at Rambler Channel, Siu
Lam, Lung Kwu Sheung Tan
and Tsing Chau
Tsai
12.73
The potential dust emission sources during
the operation of the barging points at the captioned works areas would be dust
emissions from trucks on the paved haul roads,
unloading of spoils to the barges, materials
handling and wind erosion at the active temporary stockpile areas. With the implementation of dust suppression
measures as mentioned in Tables 12.10 and 12.11, no adverse dust
impacts would be expected at the ASRs in the vicinity of these four barging
points.
Adits / Vent Shafts (excluding
12.74
Except Nam Cheong vent shaft, the size of the
adits/shafts, ventilation buildings and the building
for Tai Kong Po Emergency Access Point are limited. Less dusty
activities to be conducted during construction of the superstructures (for
ventilation buildings). With the implementation of dust suppression measures
stipulated in Air Pollution Control (Construction Dust) Regulation, no adverse
dust impacts would be anticipated at the nearby ASRs.
Shek Kong Stabling Sidings
12.75
The construction of SSS
would involve minor excavation works and filling works. With the implementation of mitigation
measures stipulated in the Air Pollution Control (Construction Dust) Regulation
such as regular water spraying on exposed sandfill
area, significant dust impact on the nearby ASRs is not expected.
Operation
Phase
12.76
There is no
adverse air quality impact expected from the operation of the Project and
proposed diesel locomotive as discussed in Section
12.47 – 12.49.
12.77
The mechanical
ventilation systems would be provided for the semi-confined PTI such that the air quality inside the PTI would comply with EPD
guideline. The directions of the
louvers would be located away from the nearby existing and planned ASRs as
possible (i.e. facing seaside) and meet the
requirements stipulated in EPD Practice Note for Professional Persons – Control
of Air Pollution in Semi-Confined Public Transport Interchange (ProPECC PN 1/98), air pollution problem from arising
is not anticipated.
Recommended Air Quality Mitigation
Measures
12.78
Dust control measures have been incorporated
into the engineering design as presented in Tables 12.9 to 12.14. For concrete
batching
plant, the requirements and mitigation measures stipulated in the Guidance Note on the Best Practicable Means
for Cement Works (Concrete Batching Plant) BPM 3/2(93) should be
followed and implemented. In addition,
implementation of dust suppression measures stipulated in the Air Pollution
Control (Construction Dust) Regulation and good site practices should be
carried out to further minimize construction dust impact.
·
Use of regular watering, with complete
coverage, to reduce dust emissions from exposed site surfaces and unpaved
roads, particularly during dry weather.
·
Use of frequent watering for particularly
dusty construction areas and areas close to ASRs.
·
Side enclosure and covering of any aggregate
or dusty material storage piles to reduce emissions. Where this is not practicable owing to
frequent usage, watering shall be applied to aggregate fines.
·
Open stockpiles shall be avoided or
covered. Where possible, prevent placing
dusty material storage piles near ASRs.
·
Tarpaulin covering of all dusty vehicle loads
transported to, from and between site locations.
·
Establishment and use of vehicle wheel and
body washing facilities at the exit points of the site.
·
Provision of wind shield and dust extraction
units or similar dust mitigation measures at the loading points, and use of
water sprinklers at the loading area where dust generation is likely during the
loading process of loose material, particularly in dry seasons/ periods.
·
Imposition of speed controls for vehicles on
unpaved site roads. 8 kilometers per hour is the recommended limit.
·
Where possible, routing of vehicles and
positioning of construction plant should be at the maximum possible distance
from ASRs.
·
Every stock of more than 20 bags of cement or
dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting
or placed in an area sheltered on the top and the 3 sides.
·
Cement or dry PFA delivered in bulk should be
stored in a closed silo fitted with an audible high level alarm which is
interlocked with the material filling line and no overfilling is allowed.
·
Loading, unloading, transfer, handling or
storage of bulk cement or dry PFA should be carried out in a totally enclosed
system or facility, and any vent or exhaust should be fitted with an effective
fabric filter or equivalent air pollution control system.
Evaluation of Residual Impacts
Construction Phase
12.79
With the implementation of the mitigation
measures as stipulated in the Air Pollution Control (Construction Dust)
Regulation, dust control measures and good site practices, the predicted
cumulative maximum 1-hour and 24-hour average TSP concentrations (including the
background levels as mentioned in Section 12.59) at the ASRs in the vicinity of
the construction sites would comply with the TSP criterion in EIAO-TM and AQO.
12.80
The predicted annual average TSP
concentrations at the ASRs in the vicinity of West Kowloon works area and Nam
Cheong works area induced by the construction
activities of the Project would be increased by 0.02 to 2.18 mg/m3. There is no EPD monitoring station located in
the vicinity of these work sites, therefore, the annual background TSP level at
West Kowloon works area and Nam Cheong works area make reference to the latest
5-year data (Year 2003 – 2007) of the nearest EPD monitoring station at Sham Shui Po. It is noted
that the annual background TSP level at this monitoring station is 81 µg/m3,
which has exceeded the annual TSP AQO (80 mg/m3).
However, the monitoring data at this station may not fully reflect the
actual situation of the study areas. The
EPD Sham Shui Po monitoring station is located at
inland area but the Project sites at
12.81
The predicted annual average TSP
concentrations at the ASRs in the vicinity of Shek
Kong works area induced by the construction activities of the Project would be
increased by 0.05 to 2.34 µg/m3.
There is no EPD monitoring station located in
the vicinity of Shek Kong works area. The annual background TSP level therefore
makes reference to the latest 5-year data (Year 2003 – 2007) of the nearest EPD
Monitoring Station at Yuen Long. The
annual background TSP level at this monitoring station is 103µg/m3,
which is already in excess of annual TSP AQO (80 mg/m3).
In fact, Shek Kong is a rural area with
village type developments and no any major industries within the area. Nevertheless, Yuen Long is a new town with
industries developments such as Tung Tau Industrial Area and Yuen Long
Industrial Estate. The adoption of the
monitoring data at EPD Yuen Long monitoring station as background TSP level for
Shek Kong works area may not be appropriate. The TSP
levels arising from the dusty construction activities at Shek
Kong works area would be 0.06% – 2.93% of the annual TSP AQO, it is reasonably
concluded that the implementation of the above proposed extensive dust
suppression measures would reduce the contribution impacts from the
construction works to within the acceptable limit.
12.82
The following points should be noted with
reference to EIAO-TM Clause
(i) Effects on public health and
health of biota or risk to life
12.83
The nuisance effects associated with elevated
dusts include reduced visibility, coating and soiling of surfaces leading to
annoyance, loss of amenity, coating of vegetation and contamination of soils
leading to changes in growth rates of vegetation, and irritation of the
eyes. In this assessment, the predicted
maximum 1-hour and 24-hour average TSP concentrations
(including background levels) at the ASRs would all well below the EIAO-TM
criterion and AQO. The maximum
contributions to the annual TSP
concentrations at the representative ASRs would
be about 2.18 mg/m3
at
(ii) The magnitude of adverse
environmental impacts
12.84
Based on the modelling results, the predicted
worst annual TSP concentrations at representative ASRs due to dusty construction activities of
the Project are:
Works Area |
|
|
Shek Kong |
Representative ASRs ID |
WKA6 |
NCA8 |
SSA1b |
Predicted Maximum Contribution to Annual TSP Concentration from the Project during construction phase (mg/m3) |
2.18 (2.73% of annual TSP AQO) |
1.99 (2.49% of annual TSP AQO) |
2.34 (2.93% of annual TSP AQO) |
12.85
As mentioned in Section 12.80 and 12.81, the TSP levels arising from the construction phase of the Project would not
pose adverse air quality impact to the ASRs.
(iii) The geographic extent of the
adverse environmental impacts
12.86
As mentioned in Section 12.80 and 12.81,
there are no adverse environmental impacts during the
construction phase of the Project.
(iv) The duration and frequency of
the adverse environmental impacts
12.87
The TSP levels at the ASRs induced from the
construction of the Project would only be 0.02 to 2.34 mg/m3.
The potential dust impacts from
(v) The degree to which adverse
environmental impacts are reversible or irreversible.
12.88
For the Project itself, the potential dust
impacts are not considered as adverse environmental
impacts
as the predicted 1-hour and 24-hour average TSP levels at
all representative ASRs would comply with EIAO-TM criterion and AQO with the
implementation of proposed dust suppression measures. The contribution
to
annual TSP prediction from the
Project would only be 0.03% - 2.93% of annual TSP AQO. It would not have potential dust impacts to the ASRs once the dusty construction activities have completed, it is considered
as short-term impacts.
(vi) The ecological context
12.89
The potential dust impacts arising from the
Project would not involve any ecological context.
(vii) The degree of disruption to
sites of cultural heritage
12.90
The potential dust impacts arising from the
Project would not involve any cultural heritage context.
(viii) International and regional
importance
12.91
The potential dust impacts arising from the
Project would not involve any international and regional importance.
(ix) Both the likelihood and degree
of uncertainty of adverse environmental impacts
12.92
The background TSP concentrations adopted in
the assessment is based on the past 5-year (2003 to 2007) average data recorded
at the nearest EPD air quality monitoring stations
in accordance with EPD’s Guidelines on Assessing the ‘TOTAL’ Air Quality
Impacts. As these
stations are not exactly located at the Project works areas, the past
monitoring data may not be fully reflect the actual background levels at these
works areas.
Operation Phase
12.93
Insignificant air quality impact from
operation of diesel locomotives at SSS is anticipated. No adverse air quality impact during the
operation of the PTI is expected with the
proper design of mechanical air ventilation system.
Environmental Monitoring and Audit
Requirements
12.94
Environmental monitoring and audit for dust
emission should be conducted during the construction phase of the Project so as
to check compliance with legislative requirements. Details of the monitoring and audit programme
are contained in a stand-alone EM&A Manual.
Construction Phase
12.95
Potential air quality impacts from the
construction works for the Project would mainly be related to construction dust
from excavation, materials handling, spoil removal and wind erosion, as well as
operation of concrete batching plant, stockpiles and barging facilities. With the implementation of mitigation
measures in the Air Pollution Control (Construction Dust) Regulation, proposed
dust suppression measures, good site practices and dust control measures for
the Specified Process (concrete batching plant),
no adverse dust impacts on the ASRs would be anticipated.
Operation Phase
12.96
No adverse air
quality impact expected from the operation of the Project and the proposed
diesel locomotive at SSS. The mechanical air ventilation system for the
proposed PTI has been designed in accordance with EPD Practice Note for
Professional Persons – Control of Air Pollution in Semi-Confined Public
Transport Interchange (ProPECC PN1/98), and air
quality impact during its operation is therefore not anticipated.