14.               landfill gas hazard

Introduction

14.1            A section of the alignment will be located underneath the Ngau Tam Mei Landfill (NTML) and the Barging Point in Kwai Chung (Rambler Channel) and the Nursery Site in Siu Lang Shui will be located close to the Gin Drinkers Bay Landfill (GDBL) and Siu Lang Shui Landfill (SLSL), respectively (see Figure Nos. NOL/ERL/300/C/XRL/ENS/M61/101 to /103). 

14.2            The section of Project alignment underneath the NTML will be constructed at about -16 mPD ([1])  comprises twin parallel bored tunnels.  There will be no works above ground level in the vicinity of the NTML.

14.3            The Barging Point in Kwai Chung will be used for unloading of plant and equipment and construction materials from barges to trucks for onward transport to the Project sites during the construction phase.   There will be no excavation works or underground structure within the Barging Point site.  There will be a container-type site office which will be raised above ground.  The Barging Point will only be used during the construction phase of the Project.

14.4            The Nursery Site in Siu Lang Shui will be used for transplanting trees affected by the Project during the construction phase.  Shallow excavation by mechanical equipment will be required for placing the trees.  Towards the end of the construction period, the trees within the Nursery Site will be removed and transferred back to the area previously affected by the Project construction works.  The Nursery Site will not be used during the operational phase.

14.5            There are potential risks associated with developments close to a landfill site due to sub-surface migration of landfill gas.  This Section describes the methodology and presents the findings of a qualitative landfill gas hazard assessments of the Project.

Environmental Legislation, Standards and Guidelines

14.6            Under Annex 7 of the EIAO-TM, an evaluation of the potential risk posed by landfill gas is required for any development which is proposed within 250m of the edge of waste of a landfill site, known as Landfill Consultation Zone.  Since a section of the tunnels and two associated work sites fall within the Consultation Zone of NTML, GDBL and SLSL, respectively, a Qualitative Landfill Gas Hazards Assessment (QLFGHA) is required to assess the potential risk due to landfill gas migration from these landfills to the Project Site.

14.7            A Practice Note for Professional Person (ProPECC PN 3/96) ([2]) and Guidance Note([3]) for the assessment of the hazards which landfill gas may present to developments close to landfills have been issued by the EPD.  These documents provide an assessment framework to be followed when evaluating the risks related to developments described under Section 6.5, Chapter 9 of the Hong Kong Planning Standards and Guidelines.  The ProPECC PN 3/96 and Guidance Note apply to all developments proposed within the Landfill Consultation Zone.

Assessment Criteria and Methodology

14.8            In accordance with the Guidance Note on Landfill Gas Hazard Assessment, the risk due to landfill gas may be evaluated based upon the following three criteria:

·        Source - the rate and concentration of gas generation by the landfill;

·        Pathway - the nature of and length of potential pathways through which landfill gas can migrate and leachate flow, such as geological strata, utility services; and

·        Target - the level of vulnerability of various elements of the development to landfill gas.

14.9            Each of these criteria is further described in the sub-sections below.

Source

14.10        The classification of the Source (ie the landfill) is determined as follows:

Major        Recently filled landfill site at which there is little or no control to prevent migration of gas or at which the efficacy of the gas control measures has not been assessed; or

 

Any landfill site at which monitoring has demonstrated that there is significant migration of gas beyond the site boundary.

 

Medium    Landfill site at which some form of gas control has been installed (eg lined site or one where vents or barriers have been retrospectively installed) but where there are only limited monitoring data to demonstrate its efficacy to prevent migration of gas; or

 

Landfill site where comprehensive monitoring has demonstrated that there is no migration of gas beyond the landfill boundary but where the control of gas relies solely on an active gas extraction system or any other single control system which is vulnerable to failure.

 

Minor       Landfill sites at which gas controls have been installed and proven to be effective by comprehensive monitoring which has demonstrated that there is no migration of gas beyond the landfill boundary (or any specific control measures) and at which control of gas does not rely solely on an active gas extraction system or any other single control measure which is vulnerable to failure; or

 

Old landfill sites where the maximum concentration of methane within the waste, as measured at several locations across the landfill and on at least four occasions over a period of at least 6 months, is less than 5% (v/v).

Pathway

14.11        Generally, three types of pathway are considered for the transmission of landfill gas.  They are:

·        Man-made pathways, eg utility connections, stormwater channels, etc,

·        Natural pathways such as rock jointing planes, fissures and other naturally occurring phenomena which may promote or give rise to the transmission of gas over distances; and

·        A combination of the previous two categories.  An example of the latter may be, for instance, where a specific geological feature promotes gas transmission but which stops short of directly linking the landfill and target.  A man made connection, however may also co-exist near the edge of the geological feature, which in combination with the former, may act to link the two sites.  In this instance, careful assessment of the likelihood of the mechanism acting to link the two pathways needs to be undertaken before assigning an appropriate pathway classification.

14.12        The broad classification of a Pathway is as follows:

Very short/direct

Path length of less than 50m for unsaturated permeable strata and fissured rock or less than 100m for man-made conduits

 

Moderately short/direct

Path length of 50 to 100m for unsaturated permeable soil or fissured rock or 100 to 250 m for man-made conduits

 

Long/indirect

Path length of 100 to 250m for unsaturated permeable soils and fissured rock

14.13        In classifying the pathway, however, adjustment to the above general guidelines will often be required to take account of other factors which will affect the extent of gas migration including the following:

·        a broad assessment of the specific permeability of the soil;

·        spacing, tightness and direction of the fissures/joints;

·        topography;

·        depth and thickness of the medium through which the gas may migrate (which may be affected by groundwater level);

·        the nature of the strata over the potential pathway;

·        the number of different media involved; and

·        depth to groundwater table and groundwater flow patterns.

Target

14.14        Different levels of vulnerability or sensitivity of potential targets for landfill gas have been classified as follows:

High Sensitivity

·       Buildings and structures with ground level or below ground rooms/voids or into which services enter directly from the ground and to which members of the general public have unrestricted access or which contain sources of ignition.

·       This would include any developments where there is a possibility of additional structures being erected directly on the ground on an ad hoc basis and thereby without due regard to the potential risks.

 

Medium Sensitivity

·       Other buildings, structures or service voids where there is access only by authorised, well trained personnel, such as the staff of utility companies, who have been briefed on the potential hazards relating to landfill gas and the specific safety procedures to be followed.

·       Deep excavations.

 

Low Sensitivity

·       Buildings/structures which are less prone to gas ingress by virtue of their design (such as those with a raised floor slab).

·       Shallow excavations.

·       Developments which involve essentially outdoor activities but where evolution of gas could pose potential problems.

14.15        The above examples of different categories within each criterion are to be used as a general guide only and specific aspects of a development may render it more or less sensitive than indicated.  Account needs to be taken of any particular circumstances when assigning a target to one of the three indicated categories.

Assessment of Risk Criteria

14.16        Following the determination of the categories for the source, pathway and target in which the landfill, pathway and development fall, a qualitative assessment of the overall risk may be made by reference to Table 14.1 which is extracted from the EPD’s Guidance Note on Landfill Gas Hazard Assessment.  The potential implications associated with the various qualitative risk categories are summarised in Table 14.2.  It should be noted that the different levels of risk determine the likely extent of the protection measures required to ensure the safety of a development, but with the possible exception of the very high risk category, development is not precluded for any of the assessed levels of risk.

Table 14.1         Classification of Risk Category

 

Source

Pathway

Target Sensitivity

Risk Category

Major

Very short/direct

High

Very high

 

 

Medium

High

 

 

Low

Medium

 

Moderately Short/direct

High

High

 

 

Medium

Medium

 

 

Low

Low

 

Long/indirect

High

High

 

 

Medium

Medium

 

 

Low

Low

Medium

Very short/direct

High

High

 

 

Medium

Medium

 

 

Low

Low

 

Moderately Short/direct

High

High

 

 

Medium

Medium

 

 

Low

Low

 

Long/indirect

High

Medium

 

 

Medium

Low

 

 

Low

Very low

Minor

Very short/direct

High

High

 

 

Medium

Medium

 

 

Low

Low

 

Moderately Short/direct

High

Medium

 

 

Medium

Low

 

 

Low

Very low

 

Long/indirect

High

Medium

 

 

Medium

Low

 

 

Low

Very low

 

Table 14.2         Summary of General Categorisations of Risk

 

Level of Risk

Implication

Very high

At the very least, extensive engineering measures and alarm systems are likely to be required.  An emergency actions plan should also be developed so that appropriate actions may be immediately taken in the event of high gas concentrations being detected within the development.

High

Significant engineering measures will be required to protect the planned development.

Medium

Engineering measures required to protect the development.

Low

Some precautionary measures will be required to ensure that the planned development is safe.

Very low

No protection or precautionary measures are required.

Assessment of Potential Risk

The Source

Ngau Tam Mei Landfill

14.17        NTML is a 2 hectare landfill site located to the north-east of Yuen Long and to the east of the San Tin Highway.  Adjacent to the site in the north and east is a mountain range rising to a height of about 80 mPD.  Residential developments are located to the north-west (about 130m away), west and south adjacent to the site.  The location of the NTML is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/101.

14.18        The landfill was operated between 1973 and 1975, although uncontrolled dumping occurred prior to 1973.  The amount of waste deposited was estimated to be around 90,000 m3, mainly industrial and domestic waste.

14.19        The landfill was formed in a sloping valley with bow-shaped hills flanking the site along the western, northern and eastern boundaries.  The profile of the landfill comprise two platforms separated by a gentle slope.  The base of the landfill was not lined.  A rock bund was installed at the south-western toe of the landfill for stability purposes and this is likely to facilitate dissipation and venting of landfill gas.

14.20        The landfill was restored between 1999 and 2000 under Contract No. EP/SP/30/95 North West New Territories Landfills and Gin Drinkers Bay Landfill Restoration let by the EPD.  As part of the restoration works, an impermeable cap was installed on the platforms.  Horizontal gas collectors and passive gas vents were installed.

14.21        A number of gas monitoring wells have been installed around the site to monitor the potential landfill gas migration.  The location of these monitoring wells is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/104.  The monitoring data from October 2006 to September 2008 are presented in Appendix 14.1 and are summarised in Table 14.3.

 

Table 14.3         Landfill Gas Monitoring Results in NTML (October 2006 to September 2008)

 

Borehole

Methane (%v/v)

Carbon Dioxide (%v/v)

 

Range

Average

Range

Average

A451

<0.1

<0.1

0.7 – 8.1

6.2

A452

<0.1 – 0.5

0.1

2.4 – 19.7

11.7

A453

<0.1

<0.1

0.6 – 4.2

2.6

A454

<0.1

<0.1

22.7 – 16.9

11.6

A455

<0.1 – 3.8

1.0

0.3 – 12.0

3.3

A456

<0.1

<0.1

2.5 – 3.7

3.7

A457

<0.1

<0.1

0.1 – 3.4

1.8

A457A

<0.1

<0.1

<0.1

<0.1

A458

<0.1 – 4.0

1.6

0.2 – 9.7

2.3

A459

<0.1

<0.1

1.6 – 12.9

9.7

A460

<0.1

<0.1

1.3 – 10.8

7.2

A461

<0.1

<0.1

0.7 – 4.4

2.7

DH403

<0.1

<0.1

0.9 – 9.5

4.4

DH405

<0.1

<0.1

0.3 – 7.9

4.5

DH407

<0.1

<0.1

0.1 – 8.6

1.6

DH408

<0.1

<0.1

<0.1 – 7.9

1.4

 

14.22        As shown in Table 14.3, the methane concentrations in most of the perimeter gas monitoring wells are less than 0.1%.  There have been elevated concentrations of methane in well nos. A455 and A458.  These elevated concentrations were reported to be due to the decomposition of localised deposit of vegetation/waste materials in the area outside the landfill.  The restoration contractor had carried out investigation by setting up gas probes at various location along the boundary of NTML and did not record any gas migration from the landfill. 

14.23        The carbon dioxide concentration fluctuates between <0.1% and 19.7% across the monitoring wells.  Elevated carbon dioxide concentrations could be due to background variation or methane being oxidized.  In accordance with the EPD’s Guidance Note, levels of CO2 that exceed 5% above background would be considered “significant” migration.  In the absence of any background CO2 information for reference, it is conservatively assumed that the potential for off-site migration of landfill gas cannot be eliminated.

14.24        The quality of groundwater monitored around the NTML was also reviewed.  The location of the groundwater monitoring wells is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/104.  The monitoring results are presented in Appendix 14.1 and summarized in Table 14.4.  In general, the organic content of the groundwater is low.  Hence, the chance of methane generated from groundwater will be low.

Table 14.4         Groundwater Quality Monitoring Results in NTML (October 2006 to July 2008)

 

Borehole

Chemical Oxygen Demand (mg/L)

Total Organic Carbon (mg/L)

 

Range

Average

Range

Average

GW1

<2 - 16

8

<1 - 1

1

A458

6 - 28

14

2 - 5

4

DH403

2 - 28

8

1 - 3

2

DH404

10 - 70

27

1 - 6

3

DH405

3 - 87

17

1 - 3

2

DH407

4 - 52

15

<1 - 9

6

14.25        Given the small size and age of the landfill, the passive nature of landfill gas control measures and the recent landfill gas and groundwater monitoring results, it would be reasonable to classify the NTML as a “medium” source.

Gin Drinkers Bay Landfill

14.26        Gin Drinkers Bay Landfill (GDBL) occupies an area of approximately 30 ha and is located to the north of container Terminal No. 5 and Tsing Kwai Highway (see Drawing NOL/ERL/300/C/XRL/ENS/M61/102).  Prior to 1960, Gin Drinkers Bay was an open body of water between Pillar Island and Kowloon with a maximum water depth of about 13m.  Before tipping commenced, a rock bund was built connecting the island to the mainland.  Waste was tipped behind the rock bund.  Tipping into the water ceased in 1967 although "open tipping" continued until 1973 when controlled landfilling was adopted. Waste deposition ceased in 1979.  It is estimated that between 8 and 12 million tonnes of domestic and industrial wastes were deposited. The waste covers an area of approximately 30ha with a maximum depth of 55-60 m deep.  At its deepest part, the waste extends 10 - 14 m below sea level.  The site was not lined prior to filling although a perimeter leachate collection system was installed along the toe of the fill that discharges by gravity into the foul sewer system.  The cover material over the waste comprises silty sand and gravel derived from completely decomposed granite (CDG) with additional clayey fill in some locations.  The fill cover generally varies in thickness from 1 to 8m.

14.27        As part of the restoration works of the GDBL under Contract No. EP/SP/30/95 North West New Territories Landfills and Gin Drinkers Bay Landfill Restoration let by the EPD, a number of active gas extraction wells were installed in the waste.  In addition, a horizontal perimeter trench with an active gas collection system was constructed around the entire site to extract and flare or utilise the landfill gas.

14.28        The portion where MTRC's Lantau and Airport Railway cut through the waste have been capped with a polyethylene membrane and restoration soil.  The intention was to control the infiltration of rainwater and the release of landfill gas.

14.29        A number of gas monitoring wells have been installed around the site to monitor the potential off-site landfill gas migration.  The location of the monitoring wells closed to the Barging Point is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/105.  The monitoring data from October 2006 to September 2008 are presented in Appendix 14.1 and are summarised in Table 14.5.

Table 14.5         Landfill Gas Monitoring Results in GDBL (October 2006 to September 2008)

 

Borehole

Methane (%v/v)

Carbon Dioxide (%v/v)

 

Range

Average

Range

Average

GDBGW5

<0.1

<0.1

<0.1 – 3.1

0.6

GW1

<0.1

<0.1

<0.1 – 3.2

1.3

GW2

<0.1

<0.1

0.2 – 12.1

5.5

LF55

<0.1

<0.1

<0.1 – 0.5

0.2

LF56

<0.1

<0.1

0.2 – 0.6

0.4

SVB4

<0.1

<0.1

<0.1 – 0.2

0.2

SVB5

<0.1

<0.1

<0.1

<0.1

 

14.30        As shown in Table 14.5, the methane concentrations in all monitoring wells are less than 0.1%.  The carbon dioxide concentrations are generally well below 5% except for GW2.  In accordance with the EPD’s Guidance Note, levels of CO2 that exceed 5% above background would be considered “significant” migration.  In the absence of any background CO2 information for reference, it is conservatively assumed that the potential for off-site migration of landfill gas cannot be eliminated.

14.31        The quality of groundwater monitored around the GDBL was also reviewed.  The location of the groundwater monitoring wells is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/105.  The monitoring results are presented in Appendix 14.1 and summarized in Table 14.6.  In general, the organic content of the groundwater is low.  Hence, the chance of methane generated from groundwater will be low.

Table 14.6         Groundwater Quality Monitoring Results in GDBL (December 2006 to September 2008)

 

Borehole

Chemical Oxygen Demand (mg/L)

Total Organic Carbon (mg/L)

 

Range

Average

Range

Average

GW1

<25 - 100

61.4

4 - 18

12.5

GDBGW5

<25 - 193

118

8 - 20

13

LF56

122 - 172

147

<1

<1

14.32        Given the large size of the landfill and the landfill is still actively generating landfill gas, the active nature of landfill gas control measures and the recent landfill gas and groundwater monitoring results, it is conservatively classified the GDBL as a “medium” source.

Siu Lang Shui Landfill

14.33        Siu Lang Sui Landfill (SLSL) occupies an area of 12ha and is located south of the Castle Peak Firing Range, adjacent to the old Lung Mun Road.  The location of the SLSL is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/103.

14.34        The landfill was formed in a valley and infilling abutted the steep valley sides.  The landfill was initially infilled as two separate areas – firstly to the east and subsequently to the west.  Two streams that drained the hill slopes were diverted in stages via a box culvert beginning at the north edge of the site, and infilling then continues over the box culvert.  The average depth of the landfill is about 10m, although it reaches a maximum of 40m in some places.

14.35        The site was operational from November 1978 to December 1983 and approximately 1.2 million tonnes of mostly domestic and industrial wastes, as well as incinerator ash and green wastes, were deposited during this period ([4]).  After closure of SLSL, a soil covering layer of compacted gravely silty sand varying between 2m and 6m in thickness was placed directly onto the deposited wastes, and trees were planted.

14.36        The landfill gas management system comprised vertical and horizontal passive gas vents, which were installed at regular intervals in the waste and extended as tipping progressed.  A gravel layer was placed at the top of each waste platform with interconnecting gas vent pipes prior to placement of the cover soils.  Restoration of the SLSL took place in 1999 to 2000 under Contract No. EP/SP/30/95 North West New Territories Landfills and Gin Drinkers Bay Landfill Restoration led by EPD.  The landfill now relies solely on the vertical and horizontal passive gas vents for venting the landfill gas.

14.37        A number of gas monitoring wells have been installed around the site to monitor the potential off-site landfill gas migration.  The location of monitoring wells is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/106.  The monitoring data from October 2006 to September 2008 are presented in Appendix 14.1 and are summarised in Table 14.7.

Table 14.7         Landfill Gas Monitoring Results in SLSL (October 2006 to September 2008)

 

Borehole

Methane (%v/v)

Carbon Dioxide (%v/v)

 

Range

Average

Range

Average

DH201

<0.1

<0.1

0.7 – 7.9

5.3

DH203A

<0.1

<0.1

0.8 – 11.7

5.7

DH204

<0.1

<0.1

0.1 – 11.7

1.4

DP220

<0.1

<0.1

<0.1 – 0.1

<0.1

DP221

<0.1

<0.1

1.1 – 11.4

6.5

DP223

<0.1

<0.1

2.4 – 15.1

8.3

DP224

<0.1

<0.1

2.0 – 12.4

8.3

14.38        As shown in Table 14.5, the methane concentrations in all monitoring wells are less than 0.1%.  The carbon dioxide concentration fluctuates between <0.1% and 11.4% across the wells.  In accordance with the EPD’s Guidance Note, levels of CO2 that exceed 5% above background would be considered “significant” migration.  In the absence of any background CO2 information for reference, it is conservatively assumed that the potential for off-site migration of landfill gas cannot be eliminated.

14.39        The quality of groundwater monitored around the SLSL was also reviewed.  The location of the groundwater monitoring wells is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/106. The monitoring results are presented in Appendix 14.1 and summarized in Table 14.8.  In general, the organic content of the groundwater is low.  Hence, the chance of methane generated from groundwater will be low.

Table 14.8         Groundwater Quality Monitoring Results in SLSL (October 2006 to October 2008)

 

Borehole

Chemical Oxygen Demand (mg/L)

Total Organic Carbon (mg/L)

 

Range

Average

Range

Average

GW1

<2 - 3

3

<1 - 1

1

GW2

<2 - 8

4

<1 - 2

2

GW3

<2 - 4

3

<1

<1

DH201

16 - 74

34

<1 - 26

11

DH203A

22 - 47

32

<1 - 8

6

DH204

12 - 38

23

5

5

14.40        Given the small size and age of the landfill, the passive nature of landfill gas control measures and the recent landfill gas and groundwater monitoring results, it would be reasonable to classify the SLSL as a “medium” source.

The Pathway

General

14.41        The potential pathways through which landfill gas may enter a Project site are three fold, namely:

·        Through transmission along natural pathways such as fissures or joints in rock;

·        Man-made pathways such as through permeable backfill in utilities trenches; or

·        A combination of both.

NTML to Tunnels

14.42        Parts of the NTML site are underlain by sedimentary and volcanic rocks consisting of coarse ash crystal tuff that is slightly metamorphosed.  On the lowland to the south and to the north there are debris flow deposits, consisting of silt and sand, gravel and clay with cobbles and boulders.  The piezometric levels indicate a steep hydraulic gradient from north-east to south-west.  There is no fault or fissures presence below the landfill.  The geological map of the area is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/107

14.43        Recent groundwater monitoring data has been obtained.  The data is contained in Appendix 14.1.  The location of the groundwater monitoring wells is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/104 and the monitored groundwater level are summarised in Table 14.9.  The minimum groundwater level ranged from 4.74 mPD to 16.06 mPD across the landfill.  The XRL tunnels are located at around -16 mPD, which will be around 21 m to 32 m below the groundwater table as shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/114. 

Table 14.9         Groundwater Level in NTML (August 2003 to August 2008)

 

Borehole

Groundwater Level (mPD)

 

Range

Lowest

Average

DH407

10.51 – 17.54

10.51

12.78

DH408

16.06 - 35.07

16.06

20.97

GW1

11.05 – 27.44

11.05

21.91

DH403

5.05 – 14.43

5.05

7.64

DH404

5.80 – 15.66

5.80

8.72

A458

4.74 – 14.96

4.74

8.68

DH405

5.18 – 11.04

5.18

7.45

 

14.44        As the solubility of methane in water is low, the presence of groundwater generally provide a barrier to the migration of landfill gas.  Based on the geological setting and groundwater table of the NTML area, it is expected that the potential for landfill gas migration via natural pathway is low.  As discussed in Section 15, groundwater flow into the tunnels will be effectively precluded based on the chosen method of construction and the designed tunnel lining system.  Hence, with no groundwater flowing to the tunnels, it is expected that the presence of the tunnels will not alter the existing hydrogeologic regime of the area.  In addition, as methane is lighter than air, any methane in the soil would tend to migrate sideway or upward instead of downward.  The potential of migration of methane from the landfill to the proposed tunnels is considered very low.

14.45        Utility check indicates that there are no underground utilities below the landfill.  There will not be any utility connecting the tunnels and the NTML or in the vicinity of the landfill.

14.46        Based on the vertical profile between the NTML and the tunnels, and the characteristics of the geological and hydrogeological setting, the pathway between the NTML and the tunnels are filled with groundwater, which is a good barrier to landfill gas migration.  Hence, although the vertical separation distance between the NTML and the tunnels is about 36m, the pathway for potential landfill gas migration from NTML to the tunnels is classified as “long / indirect”.

GDBL to Barging Point

14.47        The proposed Barging Point for transportation of plant and equipment and construction material is located at approximately 120m from the GDBL.  No surface work will be carried out at the Barging Point.  The ground separating the Barging Point and the GDBL is paved and comprises the Kwai Chung Incinerator (decommissioned and being demolished), Kwai Yue Lane and Kwai Yue Road with pavements on either side.  The underlying material is fill used in the original land reclamation process.  As such, it is assumed that the unsaturated fill material is porous and conductive to gas migration.  The geological map is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/108.

14.48        While groundwater data at the Barging Point is not available, recent groundwater monitoring data at GDBL has been obtained to identify the groundwater level in the area.   The data is contained in Appendix 14.1.  The location of the groundwater monitoring wells closest to the Barging Point is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/105 and the monitored groundwater level are summarised in Table 14.10.  The average groundwater level ranged from 2.67m to 4.40m below the well head across the landfill.  While information pertaining the well head level is not available, it is conservatively assumed that the unsaturated zone for potential landfill gas could range from 2.67m to 4.40m. 

 

Table 14.10       Groundwater Level in GDBL (December 2006 to September 2008)

 

Borehole

Groundwater Level (m below well head)

 

Range

Average

GDBGW5

2.96 – 4.37

3.66

GW1

3.13 – 4.04

3.77

GW2

0.60 – 3.85

2.67

LF56

4.05 – 4.74

4.40

14.49        The underground utilities between the GDBL and the Barging Point is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/109.  Underground utilities are presence along Kwai Yue Street and Kwai Yue Lane.  However, these utilities do not connect the GDBL and the Barging Point. 

14.50        Based on the distance between the GDBL and the Barging Point, the characteristics of the geological setting and the groundwater level, and the presence of underground utilities, the pathway for potential landfill gas migration from GDBL to the Baring Point is classified as “long / indirect”.

SLSL to Nursery Site

14.51        The Nursery Site is located at approximately 110 m from the SLSL.  Part of the SLSL and the Nursery Site are underlain by volcanic rocks consisting of granite, basalt and quartzphyric rhyolite.  No faults or fissures are presence between the SLSL and the Nursery Site.  The geological map is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/110.

14.52        While groundwater data at the Nursery Site is not available, recent groundwater monitoring data at SLSL has been obtained to identify the groundwater level in the area.  The data is contained in Appendix 14.1 and the monitored groundwater level are summarised in Table 14.11.  The average groundwater level ranged from 3.99m to 18.89m below the well head across the landfill.  While information pertaining the well head level is not available, it is conservatively assumed that the unsaturated zone for potential landfill gas could range from 3.99m to 18.89m. 

Table 14.11       Groundwater Level in SLSL (November 2006 to November 2008)

 

Borehole

Groundwater Level (m below well head)

 

Range

Average

GW1

8.55 – 14.50

12.34

GW2

4.09 – 7.59

6.65

GW3

15.46 – 22.96

18.89

DH203A

5.67 – 6.87

6.50

DH204

3.63 – 4.69

3.99

DH201

4.03 – 7.20

6.51

14.53        The underground utilities between the SLSL and the Nursery Site are shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/111.  Underground utilities are presence along Lung Mun Road.  However, these utilities do not connect the SLSL and the Nursery Site. 

14.54        Based on the distance between the SLSL and the Nursery Site, and the characteristics of the geological setting and groundwater table, the pathway for potential landfill gas migration from SLS to the Nursery Site is classified as “long / indirect”.

The Target

Tunnels

Construction Phase

14.55        About 750m of the alignment will run within the Consultation Zone of NTML and underneath the lower platform of the NTML (see Drawing NOL/ERL/300/C/XRL/ENS/M61/101).  The section of the alignment underneath the NTML comprises twin parallel 8.15m ID TBM bored tunnels and a 400mm thick pre-cast concrete segmental lining is proposed.  The tunnels will be constructed using a 9.325m diameter TBM.  The tunnels will be constructed at around -23.5 mPD by tunnel boring method.  Drawing NOL/ERL/300/C/XRL/ENS/M61/112 presents the preliminary design of the typical bored tunnel section which may be subject to revision in the detailed design stage.

14.56        The design of the permanent tunnel and cavern linings follows the requirements of MTRC’s New Works Design Standard Manual, which has been followed in other MTRC’s railway line in Hong Kong.  The permanent tunnel structure will be formed by dense and low permeability precast concrete with a typical hydraulic conductivity of 10-12 m s-1.  All segments of the tunnel will be fitted with a suitable sealing system consisting of an elastromeric gasket and a hydrophilic seal strip either as single or combined sealing strip.  The sealant will provide waterproofing to groundwater ingress and will also act as a low permeability barrier to gas.  The construction of the tunnel will follow the requirements in MTRC’s Material and Workmanship Specification to ensure that the actual works are implemented as per the design requirements.  Dewatering of the surrounding ground will not be required for the construction of the tunnels.

14.57        Apart from the tunnel alignment, there are no other structure or construction works located within the Consultation Zone of the NTML.

14.58        Since the tunnels are directly underneath the NTML and the tunnel construction works involve workers working in below ground void and contain sources of ignition, the sensitivity of this target is high

Operational Phase

14.59        During the operational phase, the tunnels will be used by the XRL trains.  There will be no unauthorised access to the tunnels.  It is expected that human entry into the tunnels will only be required in case of maintenance and in emergency situation.

14.60        Adequate ventilation will be maintained in the tunnels during their operation by virtue of the mechanical ventilation provided as well as the piston effect of trains to disperse any gas that may accumulate during operational hours.  Mechanical ventilation will also be provided during time of maintenance works.

14.61        Since the tunnels are below ground void directly underneath the NTML and contain sources of ignition, the sensitivity of this target is classified as high.

Barging Point

14.62        The Barging Point is about 1 ha and will be used for unloading plant and equipment and construction material from barges to truck for onward transport to the Project worksites.  The Site is currently vacant and is paved with concrete.  The proposed works within the Barging Point Site include fixing the barge loading ramp along the seawall.  A typical section drawing of the barge loading ramp is shown in Drawing NOL/ERL/300/C/XRL/ENS/M61/113. There will be no excavation works and no underground structure will be installed.  There will be a site office (in container) within the site, which will be raised above ground.

14.63        As the works will not involve excavation and the activities within the Barging Point will essentially be outdoor and the site office will be raised 500mm above ground, the sensitivity of this target is low.

14.64        The Barging Point will not be used during the operational phase.

Nursery Site

14.65        The Nursery Site is about 1. ha and will be used as a nursery site for transplanting trees affected by the Project.  The site is currently vacant and is paved with concrete.  The proposed works within the Nursery Site include removing the paving concrete to expose the soil underneath and to excavate the soil (around 1m deep) for placing the transplanted trees.  The minor excavation process will be done by machinery and no workers will enter the excavated area.  Towards the end of the construction period, the trees within the Nursery Site will be removed and transferred back to the area previously affected by the construction works.  No buildings or structures will be constructed within the Nursery Site.

14.66        As the works will only involve shallow excavation and the construction activities will essentially be outdoor, the sensitivity of this target is low.

14.67        The Nursery Site will not be used during the operational phase.

Source-Pathway-Target Analysis

14.68        On the basis of the source, pathways and targets identified above, a source-pathway-target analysis has been undertaken and is presented in Table 14.12 according to EPD’s assessment framework. 

Table 14.12       Qualitative Assessment of Landfill Gas Hazard Associated with the Project.

 

Source

Pathway

Target

Qualitative Risk

Construction Phase

Ngau Tam Mei Landfill – passive landfill gas control system, comprehensive landfill gas monitoring programme

 

(Category: medium)

Pathway saturated with groundwater, no fault/fissures, no direct man-made pathways

 

(Category: long / indirect)

 

Twin bored tunnels – tunnel construction works involve workers working in below ground void and contain sources of ignition

 

(Category: high)

Medium

Gin Drinkers Bay Landfill – combination of active and passive landfill gas control measures, comprehensive landfill gas monitoring programme

 

(Category: medium)

Distance to waste around 120m, no fault/fissures, large unsaturated zone in fill material, no direct man-made pathways

 

(Category: long / indirect)

 

Barging Point – no excavation, outdoor activities, site office raised above ground

 

(Category: low)

Very Low

Siu Lang Shui Landfill - passive landfill gas control measures, comprehensive landfill gas monitoring programme

 

(Category: medium)

Distance to waste around 110m, no fault/fissures, unsaturated zone in rock, no direct man-made pathways

 

(Category: long / indirect)

 

Nursery Site – minor excavation, outdoor construction activities

 

(Category: low)

Very Low

Operational Phase

Ngau Tam Mei Landfill – passive landfill gas control measures, comprehensive landfill gas monitoring programme

 

(Category: medium)

Distance to waste less than 50m, no fault/fissures, target below groundwater table, no direct man-made pathways

 

(Category: long/ indirect)

 

Twin bored tunnels – below ground void directly underneath the NTML and contain sources of ignition

 

(Category: high)

Medium

 

14.69        The Qualitative Landfill Gas Risk Assessment has indicated the risk of landfill gas ingress into the tunnels is medium while the risk of landfill gas ingress to the Barging Point and the Nursery Site is very low.  According to EPD’s Guidance Note, engineering measures will be required to protect the tunnels and no additional precautionary measures will be required to ensure that the works in the Nursery Site and the Barging Point are safe.

Recommendations

14.70        This section of the report provides general advice and recommendations for the avoidance of landfill gas risks during the construction and operation of the Project.

14.71        In general, the measures taken for the restoration and aftercare of the NTML, GDBL and and SLSL to control of landfill gas should not be relied upon to ensure the safety of adjoining developments.  However, it must also be acknowledged that the restoration works undertaken will have the effect of lowering the potential for an incident to occur off-site when compared to the historical situation.  Allowance for this has been made in the qualitative assessment undertaken. 

General Hazards Related to Landfill Gas

Landfill Gas

14.1            All contractors participating in the works and operational staff should be aware that potential of methane and carbon dioxide present in the soil and all works should be undertaken on the basis of an "assumed presence of landfill gas".  In addition the following properties of landfill gas should be noted.

·        Methane is odourless and colourless, although in landfill gas it is typically associated with numerous highly odoriferous compounds which gives some warning of its presence.  However, the absence of odour should not be taken to mean that there is no methane.  Methane levels can only be reliably confirmed by using appropriately calibrated portable methane detectors.

·        Methane is a flammable gas and will burn when mixed with air between approximately 5 and 15% (v/v) (the Lower Explosive Limit (LEL) and Upper Explosive Limit (UEL) respectively).  If a mixture of methane and air with a composition between these two values is ignited in a confined space, the resulting combustion may give rise to an explosion.  Methane is also an asphyxiant.

·        Carbon dioxide, the other major component of landfill gas is an asphyxiating gas and causes adverse health effects at relatively low concentrations.  The long-term Occupational Exposure Limit (OEL) is 0.5% (v/v).  Like methane, it is odourless and colourless and its presence (or absence) can only be confirmed by using appropriately calibrated portable detectors.

·        Gas density.  Methane is lighter than air whereas carbon dioxide is heavier than air.  Typical mixtures of landfill gas are likely to have a density close to or equal to that of air.  However, site conditions may result in a ratio of methane to carbon dioxide which may make the gas mixture lighter or heavier than air.  As a result, landfill gas may accumulate in either the base or top of any voids or confined spaces.

General Recommended Precautionary and Protection Measures for Tunnels

Construction Phase

14.2            The construction works to be undertaken at the site present construction workers and others with risks resulting from contact with landfill gas and leachate.  Whilst the risks are not expected to be significant, owing to the use of powered mechanical equipment to undertake most of the excavation works, there may still be instances where human exposure may be inevitable.  Precautionary measures to be adopted during construction are outlined in Paragraphs 8.3 to 8.49 of EPD’s Guidance Note (a copy of Chapter 8 of the Guidance Note is enclosed in Appendix 14.2 for reference).  The following recommendations referenced from the Guidance Note should be adopted when the construction of the tunnels is within the Consultation Zone of the NTML:

Safety Measures

·        All personnel who work on site and all visitors to the site should be made aware of the possibility of ignition of gas in the vicinity of excavations.  Safety notices should be posted warning of the potential hazards.

·        Those staff who work in, or have responsibility for “at risk” areas, including all excavation workers, supervisors and engineers working within the Consultation Zone, should receive appropriate training on working in areas susceptible to landfill gas, fire and explosion hazards.

·        During all works, safety procedures will be implemented to minimise the risks of fires and explosions and asphyxiation of workers (especially in confined space).

·        Safety officers, specifically trained with regard to landfill gas related hazards and the appropriate actions to take in adverse circumstances, will be present on all worksites throughout the works.

·        Smoking and naked flames will be prohibited within confined spaces.  'No Smoking' and 'No Naked Flame' notices in Chinese and English will be posted prominently around the construction site.  Safety notices should be posted warning of the potential hazards.

·        Welding, flame-cutting or other hot works may only be carried out in confined spaces when controlled by a 'permit to work' procedure, properly authorised by the Safety Officer.  The permit to work procedure will set down clearly the requirements for continuous monitoring of methane, carbon dioxide and oxygen throughout the period during which the hot works are in progress.  The procedure will also require the presence of an appropriately qualified person who shall be responsible for reviewing the gas measurements as they are made, and who shall have executive responsibility for suspending the work in the event of unacceptable or hazardous conditions.  Only those workers who are appropriately trained and fully aware of the potentially hazardous conditions which may arise will be permitted to carry out hot works in confined areas.

·        A mechanical ventilation system must be in use at all times during which personnel are engaged in works inside the tunnel or excavation and be evacuated in the event of power outages.  Work must not be carried out in the absence of mechanical ventilation and supervision of adequately trained safety personnel.  In exceptional case where work is carried out under non-ventilated condition, any electrical equipment used, such as motors and extension cords, should be intrinsically safe.

·        Adequate fire extinguishing equipment, fire-resistant clothing and breathing apparatus sets should be made available on site.

 

Monitoring

·        Monitoring of methane, carbon dioxide and oxygen must be carried out using appropriately calibrated portable gas detection equipment.  The actions detailed in Table 14.13 must be carried out in the event of gas trigger levels being breached.

 

Table 14.13       Actions in the Event of Gas Being Detected

 

Parameter

Measurement

Action

O2

< 19% v/v

Increase underground ventilation to restore O2 to >19% v/v

 

 

< 18% v/v

Stop works

Evacuate all personnel

Increase ventilation further to restore O2 to >19% v/v

CH4

> 10% LEL

Prohibit hot works

Increase ventilation to restore CH4 to <10% LEL

 

 

>20% LEL

Stop works

Evacuate all personnel

Increase ventilation further to restore CH4 to <10% LEL

CO2

>0.5% v/v

Increase ventilation  to restore CO2 to <0.5% v/v

 

 

> 1.5% v/v

Stop works

Evacuate all personnel

Increase ventilation further to restore CO2 to <0.5%

 

·        The exact frequency of monitoring should be determined prior to the commencement of works, but should be at lease once per day, and be carried out by a suitably qualified or qualified person before starting the work of the day.  Measurements shall be recorded and kept as a record of safe working conditions with copies of the site diary and submitted to the Engineer for approval.  The Contractor may elect to carry out monitoring via an automated monitoring system.  In this event, the gas levels specified in Table 14.13 shall be so programmed to automate the actions in the table and in the event of the trigger levels being breached, to activate suitable audible and visual warning devices.

·        All measurements taken are to include at a minimum the areas where personnel are operating as well as the highest and lowest elevations within the tunnel.  Measurements are to be carried out with the sensor located not greater than 10mm from the exposed rock surface and at locations where landfill gas has the highest potential to enter the tunnel such as highly fissured areas, dykes, identified faults ([5]), etc.

14.3            In addition, construction works to be undertaken in confined space should follow the relevant Regulations under Chapter 59 Factories and Industrial Undertakings Ordinance and Chapter 509 Occupational Health and Safety Ordinance. 

14.4            A tunnel walkover survey to test for presence of flammable gas at all joints and cracks, if identified, shall be conducted upon completion of the tunnel work within the NTML Consultation Zone.  Rectifications, such as sealing of cracks and inspection of tunnel seals, shall be carried out for any signs of the presence of flammable gas.  The survey should be conducted under non-ventilated condition and before starting the work of the day.

14.5            Weekly monitoring of methane, carbon dioxide and oxygen in the form of a walkover survey at 20m intervals for section of tunnels under NTML and 50m interval within the NTML Consultation Zone should be conducted after completion of the tunnel construction works and not less than 3 months before commencement of operation.  The survey shall be conducted under non-ventilated condition and before starting the work of the day.  Should methane concentration be higher than 10% LEL, mechanical ventilation is required to be switched on 30 minutes before the starting the work of the day and throughout the working day.  In addition, the monitoring frequency should be increased to daily.  If the situation persists in three consecutive occasions, inspection of tunnel seals should be carried out to identify the location of potential gas ingress.  Rectifications, such as sealing of cracks, shall be carried out.  The daily monitoring requirement can be resumed to weekly if the concentration of methane is consistently below 10% LEL in 7 consecutive days and the ventilation requirement can be resumed to normal. 

14.6            A summary of the monitoring results shall be submitted to EPD for record before the commencement of operational phase.  The results shall be reviewed and agreed with EPD before the commencement of operation to determine the monitoring requirements during the operational phase.

Design Phase

14.7            The risk level associated with potential landfill gas hazard at the tunnels is medium.  According to the EPD’s Guidance Note, this requires the use of “semi active’ or enhanced passive gas controls and detection systems in some situation.  As described in para 14.56, the design of the tunnel will incorporate a dense and low permeability precast concrete.  Appropriate sealant will be applied to joints to prevent the ingress of groundwater, which will also form a low permeability gas barrier.  Hence, the tunnel structure itself will provide a good barrier to landfill gas ingress (ie passive gas control).  Good workmanship and adequate construction supervision will be required to ensure the actual works are implemented as per the design requirements.  This will be implemented by MTRC’s Material and Workmanship Specification. 

14.8            Adequate ventilation will be needed as part of the tunnel design to act as an active gas control when needed.  The current design of the mechanical ventilation system can provide at least 4 air change per hour.   Taking account of the low potential of landfill gas migration into the tunnels, this air change will be adequate to prevent accumulation of methane gas to the LEL.

14.9            Upon completion of the landfill gas protection measures, a report on the implemented landfill gas protection measures with relevant as-built drawings and other detailed information showing that the design measures mentioned in this assessment to protect the tunnels from landfill gas hazard have been properly incorporated shall be submitted to EPD. 

Operational Phase

14.10        Adequate ventilation will be maintained in the tunnels during their operation by virtue of the piston effect of trains to disperse any gas that may accumulate during operational hours.  However, during non-operational hours and particularly at the time when the first train travels through the tunnels each day, there is potential for accumulated gas to be ignited by an electrical spark caused by the train.  To reduce the likelihood of this occurrence, the measures outlined below should be adopted in the section of tunnels underneath the NTML and within the NTML Consultation Zone:

·        Ventilation of the tunnels should be switched on for half an hour before the first train is expected([6])([7]) ,.

·        All maintenance personnel and station staff working within the tunnels should be educated in the dangers of landfill gas and the signs and symptoms of asphyxia.

·        Smoking within the tunnels should be prohibited at all times.

·        An assumed presence of landfill gas should be adopted at all times by maintenance workers.   Gas monitoring before the maintenance work to confirm the absence of landfill gas, communication with maintenance staff, enforcement of the no smoking order should be implemented.

14.11        The monitoring requirement during the operational phase shall be discussed with EPD before the commencement of operation.  Weekly monitoring of methane, carbon dioxide and oxygen in the form of a walkover survey at 20m intervals for section of tunnels under NTML and 50m interval within the NTML Consultation Zone is tentatively proposed ([8]).  The survey should be conducted under non-ventilated condition and before the first train operates and start-up of ventilation, if applicable.  Should methane concentration be higher than 10% LEL, mechanical ventilation is required to be switched on at least 30 minutes before the first train operates to sufficiently dilute the concentration of methane to well below the lower explosive limit to ensure that no explosion will occur when the trains pass through the tunnel until the end of the daily operation.  The monitoring frequency should be increased to daily.  If the situation persists in three consecutive occasions, inspection of tunnel seals should be carried out to identify the location of potential gas ingress.  Rectifications, such as sealing of cracks, shall be carried out.  The daily monitoring requirement can be resumed to weekly if the concentration of methane is consistently below 10% LEL in 7 consecutive days and the mechanical ventilation requirement can be resumed back to normal condition. 

14.12        A summary of the monitoring results should be submitted to EPD for record at the end of the monitoring period. 

14.13        It is recommended that an annual walkover survey in the tunnels within the Consultation Zone of the NTML should be conducted to test for the presence of flammable gas at joints and cracks, if identified.  Rectifications, such as sealing of cracks and inspection of tunnel seals, shall be carried out for any signs of presence of flammable gas. The survey should be conducted under non-ventilated condition and before the first train operates and start-up of ventilation, if applicable.

General Recommended Precautionary and Protection Measures for Barging Point

14.14        The following precautionary measures should be implemented at the Barging Point:

·        Site Office should be raised 500mm above ground.

·        Utilities services connected to the site office and the annulus around these service entry points should be properly sealed by means of sealant, collaras or puddle flanges as appropriate.

·        Smoking should be prohibited at the Barging Point.

·        All personnel who work on site and all visitors to site should be made aware of the potential hazards of the landfill gas by posting suitable warning notices of the potential hazards of landfill gas as well as “no smoking” sign.

General Recommended Precautionary and Protection Measures for Nursery Site

14.15        The following precautionary measures should be implemented at the Nursery Site:

·        Smoking should be prohibited within the Site.

·        All personnel who work on site and all visitors to site should be made aware of the potential hazards of the landfill gas by posting suitable warning notices of the potential hazards of landfill gas as well as “no smoking” sign.

Environmental Monitoring and Audit                

14.16        Monitoring is not required at the Barging Point and the Nursery Site.  For the construction and operation at the tunnels underneath the NTML and within the Consultation Zone of NTML, the monitoring requirement specified in Para 14.73 to 14.77 and Para 14.82 to 14.84 shall be followed.

Conclusion 

14.17        This section has provided a qualitative assessment on potential hazards associated with landfill gas migration from NTML to Project tunnels, GDBL to the Barging Point and SLSL to the Nursery Site.  All three landfills are considered as a “medium” source of gas migration.  The source-pathway-target analysis shows that landfill gas risk posed by NTML to the Project tunnels is medium while the landfill gas risk posed by the GDBL and SLS to the Barging Point and the Nursery Site, respectively, is very low.

14.18        Landfill gas protection measures and monitoring requirements have been recommended for the construction and operation of the Project.  It is expected that with the proposed landfill gas protection measures in place, the potential risk of landfill gas migration to the Project will be minimal.


 



([1])      Crown level of the tunnel bore.

([2])     ProPECC PN3/96 Landfill Gas Hazard Assessment for Developments adjacent to Landfills, Dec 1996, EPD.

([3])     Landfill Gas Hazard Assessment Guidance Note, 1997, EPD.

([4])           Agreement CE 10/92 Restoration of North-West New Territories Landfills, August 1995.

([5]) Faults or fissures were not identified from the geological map.  However, if they are identified during the actual construction work, the measurement requirement is applicable.

([6]) It is expected that this will provide at least 2 air change.

([7]) The requirement to implement this measure is subject to the findings of the review of landfill gas monitoring data with EPD before the commencement of operation.

([8]) The requirement to implement this measure is subject to the findings of the review of landfill gas monitoring data with EPD before the commencement of operation.