15.               impacts on the restored ngau tam mei landfill

Introduction

15.1            The purpose of this assessment is to identify the potential impacts during both construction and operation of the proposed Project tunnels on the restored Ngau Tam Mei Landfill (hereinafter also referred to as the “restored NTML” or “Landfill”); and conversely to determine the potential impacts of the Landfill on the proposed Project tunnels.

15.2            Of particular concern in this regard is the identification and assessment of the potential adverse effects that the proposed XRL tunnels may have on the integrity of various components constructed in fulfilment of the North-west New Territories Landfills Restoration Contract (Contract No. EP/SP/30/95) with the Environmental Protection Department (EPD) (hereinafter referred to as the “Restoration Contract”) to restore the Landfill to a controlled, environmentally sustainable condition.  Furthermore, mitigation measures are proposed for the identified impacts.  Potential impacts that the restored NTML may have on the proposed Project tunnels are also identified and assessed, with mitigation measures proposed.

15.3            The following sections describe the history of the restored NTML; the proposed Project tunnel configuration and construction methods; identification and assessment of the potential impacts of the restored NTML on the proposed Project tunnels, and the proposed Project tunnels on the restored NTML; with mitigation measures proposed for the identified potential impacts; followed by conclusions and recommendations and a list of references.

Ngau Tam Mei Landfill History

15.4            The NTML is located approximately 6km to the northeast of Yuen Long city centre.  It is approximately 1.7ha in plan area and was formed in a natural stream valley generally oriented with the central-axis from northeast to southwest; various developments to the north and west, and open hillside space to the south and east.  To the northwest is the Maple Gardens residential estate, and to the west is the Casa Paradizo residential development (see Figure NOL/ERL/300/C/XRL/ENS/M61/101).

15.5            From the various available records and reports, it appears that waste disposal activities had occurred at the Landfill on an informal basis as early as 1963, with more formal waste placement occurring between 1973 and 1975.  From historic aerial photographs and topographic survey information, it is reported that a total of approximately 90,000m3 of waste was disposed of at the Landfill prior to its closure.

15.6            The NTML is a valley-fill site, generally configured as two platforms (the Upper Platform and Lower Platform) with the Upper Slope between the Upper Platform and the Lower Platform, and the Lower Slope between the Lower Platform and the Landfill toe.  The larger, Upper Platform is generally between elevations +32mPD and +36mPD, and gently slopes from northeast to southwest at nominally a 4% gradient.  The smaller, Lower Platform is between elevations +24mPD and +26mPD, with a slightly steeper slope of approximately 8% across the width toward the southwest.  The toe of the Landfill is located at approximately elevation +16mPD.  The plan view configuration and cross section through the Landfill are shown in Figure No. NOL/ERL/300/C/XRL/ENS/M61/201 and Figure No. NOL/ERL/300/C/XRL/ENS/M61/202, respectively.

15.7            The Landfill was restored in 1999 under the Restoration Contract, with the restoration works generally consisting of placement of a “high integrity” capping system over the two platforms; minor modifications to the existing leachate management system to provide for collection and transport to an off-site treatment facility; installation of a passive landfill gas (LFG) ventilation system; and on-going monitoring of several component features, including surface settlement, groundwater and leachate levels and quality, and landfill gas migration.

Tunnel Configuration and Construction Method

15.8            The Project is an underground railway approximately 26km long, extending from West Kowloon to the boundary at Shenzhen.  A portion of the alignment, from approximately Chainage (Ch) 18+200 to Ch 18+320, passes diagonally beneath the western portion of the restored NTML, specifically the Upper Slope and the Lower Platform.

15.9            The portion of the alignment passing beneath the Landfill consists of twin, parallel tunnels, each 9.35m in external, cut diameter, with 16m of separation, centre-to-centre, between.  The rail level within the tunnels is to be approximately –23.5mPD, making the crown level approximately -16mPD  [Ref 1.]

15.10        Based on the preliminary geological/geotechnical assessment performed to-date, it is expected that rockhead will extend into the tunnel horizon as it passes beneath the Landfill [Ref. 1].  Although various methods will be employed to construct the tunnels throughout their length, including:  drill-and-blast, mining (also referred to as “boring”) and cut-and-cover; it is anticipated that an approximately 120m length passing beneath the Landfill will be bored in rock.  Specifically in this regard, it is anticipated that a closed-face Tunnel Boring Machine (TBM) of the Earth Pressure Balance Machine (EPBM) or slurry-type will be used [Ref 1].

15.11        The design life of the completed railway system is, consistent with MTRC standard practice, 120-years.

15.12        The typical tunnel configuration is shown in Figure No. NOL/ERL/300/C/XRL/ENS/M61/112.

Identification of Impacts

15.13        Consideration is herein given to the potential impacts that the tunnels may have on the restored NTML; and conversely the potential impact that the NTML may have on the tunnels.  A detailed review of the various components of the NTML restoration works has been performed, with a particular emphasis on the construction and operation of the proposed tunnels and the integrity of the restored NTML system components.  Of the various components included in the restoration works (refer to Section 15.7 herein); waste slope stability, ground surface gradient, capping system integrity, leachate and landfill gas management system integrity, and infrastructure (surface drains and road) integrity have been identified as potentially being impacted by the tunnels.  In addition, groundwater laden with waste constituents as it passes through the Landfill and off-site migration of landfill gas have been identified as the potential impacts of the restored NTML on the proposed tunnels.  The potential hazard of landfill gas migration from the restored NTML to the tunnels during the construction and operation phases are discussed in Section 14.  A brief description of the identified impacts follows:

·             Vibrations generated by construction of the tunnels using TBM, and on-going operation of the tunnels will have a potential impact on the stability of the Landfill slopes;

 

·             Formation of the tunnels may impact the settlement of the Landfill surface and consequentially impact the ground surface gradients, the integrity of the capping system components, the leachate and landfill gas management systems, and the infrastructure (surface water drainage network and the road);

 

·             Formation of the tunnels may impact the local hydrogeologic regime, including the groundwater and/or leachate levels and the groundwater flow; and

 

·             Exfiltration of leachate from the Landfill into the groundwater will potentially impact the quantity of drainage into the tunnels and/or the integrity of the materials used to construct the tunnels.

 

15.14        A detailed evaluation of these impacts, including the assessment methodology and criteria, is presented in the following sections.

Assessment Methodology and Criteria

Slope Stability

15.15        The stability of the NTML slopes under the vibrations that are determined to be potentially induced during construction and operation of the Project has been assessed by several analytical methods, both qualitatively and quantitatively.  A preliminary assessment employing the infinite slope method provided a conservative, quantitative estimate of the safety factor under static conditions, without consideration of vibrations from the tunnels.  However, due to the nature of the analysis, the infinite slope method is limited to only a qualitative indication of the stability of the slopes under the influence of the induced vibrations.  The more traditional method of analysis by force-moment equilibrium has been used, employing a pseudo-static coefficient to represent the expected maximum vibration levels.  These analytical approaches were supplemented by an empirical method reportedly developed specifically for TBM tunnelling in rock which estimates the upper bound peak particle velocity at a receptor as a function of the distance from the source TBM machine.  This value was then compared to a threshold value below which the induced vibrations were considered to have negligible impact on slopes and structures.

15.16        Each of these methods has been employed on the primary slope through the Landfill, a cross-section extending from the Upper Platform through the Upper Slope, Lower Platform and Lower Slope, extending beyond the toe of waste and Landfill boundary (refer to Figure Nos. NOL/ERL/300/C/XRL/ENS/M61/201 and NOL/ERL/300/XRL/ENS/M61/202).  As may be possible by each analysis method, the potential of both tunnels being formed by TBM’s simultaneously passing beneath the site has been considered.

15.17        An estimate of the magnitude of the ground borne vibrations generated during construction of the tunnels was provided by the Design Engineer in the form of peak particle velocity.  This magnitude has been independently checked, revised and used in the assessment; then converted to another form, a gravitational acceleration coefficient, for use with the force-moment equilibrium analysis method.

15.18        It is herein assumed that the vibrations generated during construction using the TBM will represent the “worst-case” scenario, and it is anticipated that the effect of the vibrations from operations will be less severe, subject to confirmation during the detailed design stage. The vibrations estimated from construction by TBM will therefore be employed throughout this Section.

15.19        Results from the infinite slope analyses performed under the “dynamic” conditions representing the vibrations induced from the formation of the tunnels are qualitative, producing an indication that the slopes will move either in conjunction with the surrounding vibrating ground surface, or that there will be a net displacement between the two features, considered to be a failure of the slope.  A positive indication of the slope moving synchronously with the surrounding ground is required.  The results of the force-moment equilibrium stability analyses under pseudo-static conditions were, because of the quantitative results produced, compared to the minimum Factor of Safety of 1.2 required under the Restoration Contract.  The upper bound peak particle velocity determined from the empirical analysis method was compared to the reported threshold limit value; 5 mm/s; below which the generated vibrations are considered to have negligible effect on slopes and structures [Ref. 1].

Settlement

15.20        The impact of Landfill settlement induced by construction of the tunnels was assessed by first estimating the settlement of only the waste mass due to degradation as a function of time.  This was done by adopting and extending the predictive model developed by the Restoration Contractor [Ref. 6].  The settlement induced by only formation of the tunnels passing beneath the Landfill was estimated by using a commonly employed model for such applications that assumes the shape of the settlement trough resulting from tunnel formation to be an inverted Gaussian curve, the shape of which is dependent on the assumed ground conditions at the tunnel level and in the soil/waste above.  The estimated settlements resulting from each of the waste degradation and tunnel formation components were then superimposed and totalled to develop a composite settlement profile through the Landfill.  This profile was then used to determine:

·         the potential for gradient reversal across the Landfill ground surface, as well as the potential for excessive stresses induced in the geomembrane component of the capping system across the Landfill platforms; and

·         the potential for damage to the existing leachate management and passive landfill gas management systems, surface water drainage features and the road.

15.21        The results of the settlement analyses were compared to various criteria for each of the Landfill features and systems.  In accordance with the Restoration Contract, a minimum ground surface gradient of 1% must be maintained after settlement.  Similarly, positive gradients are to be maintained within the surface water management features.  The estimated stresses/strains potentially developed in the geomembrane capping system component were compared to the commonly adopted conservative maximum; the yield strain; of the specific material installed.  The effect of the estimated settlement on the component materials of the leachate and landfill gas management systems was evaluated.  In each instance, the net effect of the additional settlement caused by only formation of the tunnels was compared to the result of settlement only by degradation of the landfilled waste mass.

Groundwater/Leachate Levels, Flow and Quality

15.22        The potential impacts of the formation and operation of the Project on the local hydrogeologic regime (groundwater and leachate levels and flow) around and within the Landfill were assessed through application of a fundamental drawdown model employing Darcy’s Law and based on the proposed tunnel boring methods and lining design/materials.

15.23        The potential impact of the Landfill on the tunnels was assessed by comparison of the leachate and/or down-gradient groundwater quality; particularly pH, sulphate and chloride concentrations; with known levels of resistance and/or degradation of the materials proposed for construction.  A model was employed to predict the potential corrosion of reinforcing steel that may be used in a concrete tunnel lining from chlorides in the groundwater.

15.24        The criteria to be employed to determine the potential degree of the impact of the groundwater/ leachate on the tunnels vary with the constituent concentration of contaminants as they are present at the tunnel locations.  The commonly accepted ranges of pH and sulphate (less than 5.5 or 6; and 400mg/L, respectively) were used as a basis for comparison and determination of the degree of potential concern for attack of concrete materials that may be used.  The results of the model used for estimating potential corrosion of reinforcing steel exposed to chlorides in the groundwater were used to determine the required level of protection, if any.

Evaluation of Impacts

Effect of Vibrations on Slope Stability

15.25        Several approaches have been considered and are presented in this assessment of the stability of the restored NTML slopes subjected to the vibration conditions imposed by construction of the tunnels using TBM’s and ultimately operation with the passing of trains.  The methods performed and described in the assessment presented include:

·         a preliminary analysis by the infinite slope method;

 

·         an estimation of the peak particle velocity generated with comparison to an adopted threshold limit value; and

 

·         an analysis by the more traditional force-moment equilibrium method with application of a pseudo static coefficient to simulate the forces contributed by the induced ground vibrations. 

15.26        The details of the assessment by each of these methods are provided below.

15.27        The configuration of the restored NTML is shown in plan view on Figure No. NOL/ERL/300/C/XRL/ENS/M53/001; with the critical cross-section employed for assessment of slope stability shown on Figure No. NOL/ERL/300/C/XRL/ENS/M61/202.

Infinite Slope Method

15.28        Infinite slope stability analyses were performed to provide an initial indication of the potential effect that ground borne vibrations generated from construction and operations of the tunnels may have on the restored NTML waste slopes.  The analyses performed were comprised of two (2) components:

(a)     a quantitative assessment of the minimum Factor of Safety of the waste slopes under “static” conditions based on the conservative assumptions that the slopes are infinitely long and configured at the maximum slope inclination shown in the “as-constructed” drawings produced by the Restoration Contractor [refer to Appendix 15.1 for a copy of select “as-constructed” drawings of the restored NTML]; and

 

(b)    a qualitative assessment of the same slopes under “dynamic” conditions by relative comparison of the anticipated ground acceleration experienced during construction and operation of the tunnels to a maximum allowable ground acceleration.  Note that this assessment is qualitative in nature due to the fact that the infinite slope analysis method is limited to determining non-quantifiable, relative ground movements between the Landfill slope in question and the surrounding ground.

 

15.29        The results of the quantitative infinite slope analysis indicate that the restored NTML slopes are stable to a minimum Factor of Safety of 1.5 under “static” conditions, without consideration of the vibrations induced by external sources such as the tunnel construction or their use by trains.  This is higher than the minimum Factor of Safety of 1.2 required by the Restoration Contract [Ref 5].  As anticipated, because of the conservative nature of the analytical method used in this assessment, the minimum Factor of Safety obtained is less than the value of 1.73 determined by the Restoration Contractor during the works design.

15.30        The subsequent qualitative analysis provides an indication that the waste mass within the Landfill will move together, in synchronization with, the adjacent ground surfaces.  Therefore, there will be no net differential movement or displacement between the Landfill slopes and the surrounding ground under the considered “dynamic” conditions of TBM tunnel construction and train operations.  Under these conditions, the Landfill waste slopes are considered stable.

15.31        A copy of the infinite slope analyses performed for both the “static” and the “dynamic” conditions described herein is included in Appendix 15.2 for reference.

            Peak Particle Velocity Method

15.32        An estimate of the vibrations in the form of peak particle velocities generated during construction was developed and presented in Working Paper No. 42 [Ref. 1].  The estimate made is based on use of the Hiller and Bowers equation, in which the upper bound of the peak particle velocity at the receptor; in this case the restored NTML slopes; is a function of an exponential of the distance between the TBM and the receptor, multiplied by a constant:

                                    V = 180 x-1.3

 

       Where:     V = the upper bound Peak Particle Velocity (PPV) resultant (mm/sec) at the receptor; and

                                    x = the distance (m) between the TBM source and the receptor.

15.33        In performing the same analysis in association with this assessment, the vibration source to receptor separation distance is taken as approximately 32.0m (from -16.0mPD at the crown of the tunnel TBM bore [Ref. 1], to +16mPD at the lowest point along the Landfill base), with the resulting estimate of the generated peak particle velocity being 2.0mm/sec.  Additionally, although the likelihood appears remote, a more conservative scenario would be the condition in which two TBM’s are in operation beneath the Landfill simultaneously.  The effect is assumed to be additive, thus doubling the peak particle velocity to 4.0mm/sec; however still less than the 5mm/sec cited in Working Paper No. 42 [Ref. 1] and implied in GEO Report No. 15 [Ref. 3] as the limiting value below which there is “negligible impact on adjacent slopes and structures.” [Ref. 1].  It could therefore be concluded from this analysis that the vibrations generated from tunnel construction and operation will not have adverse impact on the slope stability of the restored NTML.

Force-Moment Equilibrium Method

15.34        A detailed stability analysis of the restored NTML slopes subjected to the potential vibrations generated from construction and operation of the tunnels was also performed employing the more traditional force-moment equilibrium method, with a pseudo-static coefficient applied to model the disturbing effect of the vibrations generated as an equivalent inertia force.

15.35        An assessment of the magnitude of potential vibrations was first performed.  From recent literature [Ref. 4] it was determined that the magnitude of the particle velocity generated by the TBM during construction could be in the order of 0.25mm/s.  However, more conservatively, and consistent with the peak particle velocity method previously described herein, the maximum peak particle velocity was taken as 2.0mm/s as estimated using the Hiller and Bowers equation.

15.36        The pseudo-static ground acceleration was then determined by considering the vibrations as a single degree of freedom system with a magnification factor applied to the peak particle acceleration while assuming the most conservative conditions for the slope height (6m for the Upper Slope); vibration frequency (30Hz); and damping factor (0.5).  The resulting pseudo-static ground acceleration coefficient was determined to be the 0.019 times gravitational acceleration; most commonly expressed as “0.019g”. This coefficient was then applied directly as an additional force to the slope stability analysis performed using the SLOPE/W computer software.

15.37        Two (2) sets of pseudo-static slope stability analyses were performed to model the conditions of a single TBM and, the “worst-case” scenario of a TBM in each of the twin tunnels beneath the Landfill.  The resulting minimum Factors of Safety corresponding to the pseudo-static conditions modelling a single and two TBM’s simultaneously are 1.7 and 1.6, respectively; well above the minimum value of 1.2 required by the Restoration Contract [Ref 5].

15.38        It should be noted that the slope stability analyses under “static” conditions (without application of a pseudo static coefficient to model vibrations) were performed as part of this assessment to serve as a “calibration” and comparison to the analyses submitted in association with the Restoration Contractor design.  The results of the “static” analysis performed herein (Factor of Safety of 1.8), compares favorably with the results reported by the Restoration Contract (Factor of Safety of 1.73) [Ref. 6].

15.39        The results of the pseudo-static slope stability analyses performed are included with the cross-section on Figure No. NOL/ERL/300/C/XRL/ENS/M61/202 with the detailed analytical results included in Appendix 15.2.

Effect of Tunnel Formation on Landfill Settlement

15.40        Settlement of landfill surfaces is a common occurrence, with two primary causes:  in the short-term, due to the consolidation of the waste from the weight of materials placed above; and, in the long-term, due to the decomposition of the disposed waste.  As waste placement ceased in the Landfill in 1975, nearly 35-years ago; and the restoration was performed in 1999, approximately 10-years ago; it can reasonably be assumed that the short-term settlement from waste consolidation has been realized.  Therefore, without additional, external influences, any future settlement would only be from the decomposition of the waste disposed within.  Construction of the tunnels is an additional, external influence to be considered.

15.41        As with any settlement across a Landfill surface, the potential detrimental effects are:

·             Alteration of the ground surface gradients with, in a “worst-case” scenario, a reversal of gradients resulting in ponded water, increased infiltration and therefore increased leachate generation.

 

·             Increased stresses and strains in the waste and/or capping system, particularly the geomembrane component, resulting in rupture (in the form of a hole or tear) and increased infiltration and leachate generation.

 

·             Damage to the existing leachate and landfill gas management systems, surface water drains and road.

 

15.42        Each of these potential effects has been investigated and assessed.  Settlement of the Landfill due to only the decomposition of the waste is first considered; then settlement resulting from only the formation of the tunnels is estimated; and finally the total settlement determined, along with an assessment of the effect on the Landfill surface gradients, the integrity of the capping system components and damage to the leachate and landfill gas management system, surface water drains and road.

Landfill Settlement Due to Waste Decomposition

15.43        Under the Restoration Contract (Contract No. EP/SP/30/95), the platforms and the side slopes of the restored NTML have been restored with a minimum slope inclination of 1% (as measured from the horizontal).  A typical plan view and the corresponding cross section of the “as-constructed” conditions of the restored NTML are provided in Figure No. NOL/ERL/300/C/XRL/ENS/M61/201 and Figure No. NOL/ERL/300/C/XRL/ENS/M61/202, respectively.

15.44        Settlement of the landfilled waste as a function of time was assessed by the Restoration Contractor, through analysis, as part of the Restoration Contract [Ref. 6].  A copy of the analysis is included as Appendix 15.3 for reference and completeness.

15.45        The typical Landfill cross-section presented in Figure No. NOL/ERL/300/C/XRL/ENS/M61/202 has been analyzed for the long-term, “secondary” settlement that has occurred since 1999 and that will occur in the future through year 2049 due to decomposition of the waste.  This analysis is based on the assumption that the predicted settlement rate exceeds the actual, observed rate; and therefore is conservative.  The details of this analysis are included in Appendix 15.3 and the results are presented in Figure No. NOL/ERL/300/C/XRL/ENS/M61/204.

15.46        The results of this analysis, which is based on somewhat conservative assumptions, indicate a slight decrease in the slope inclination through the entire Landfill cross section; this generally due to the decrease in waste thickness from the maximum toward the middle of the Landfill, to a minimum at the toe of the Landfill slope.

15.47        The slope inclination across the Upper Platform generally decreases slightly from the original 4% to approximately 2% through the 50-years of analysis from 1999 through 2049.  Similarly, the slope inclination across the Lower Platform decreases from the original 8% to approximately 6% over the same design-life.  Because of the relatively steep slope inclination prior to settlement, the slope inclination over the side slopes generally decreases only slightly with the estimated settlement.

Settlement Due to Tunnel Formation

15.48        Settlement caused by the tunnels could alter the restored (post-settlement) Landfill surface gradients by potentially increasing them or reducing them; determined as a function of the orientation of the alignment of the tunnels relative to the Landfill configuration (location of the platforms and slopes) as shown in Figure No. NOL/ERL/300/C/XRL/ENS/M61/203.

15.49        A detailed analysis of the potential settlement has been performed based a commonly employed approach attributed to Peck in 1969, with further developments since that time.  The approach assumes that the shape of the settlement trough above the tunnel and perpendicular to the alignment is represented as an inverted Gaussian curve, the ultimate shape of which is dependent on the geologic/ground conditions at the tunnel face and above; and determined based on the assumptions for two parameters:  the volume loss factor (VL); and the trough width factor (k).

15.50        Conservative values have been assumed for both the volume loss factor (VL = 1.2% [Ref. 7]; and the trough width factor (k = 0.5 in the soil and/or rock beneath the Landfill and 1.0 in the waste and soil cover through the Landfill profile.  Additionally, the analysis superimposes the affect of both tunnels, each excavated to a diameter of 9.35m; separated by 16m centre-to-centre [Ref. 1].

15.51        The details of the settlement analysis performed for the tunnels beneath the restored NTML are included in Appendix 15.3 and the results are presented in Figure No. NOL/ERL/300/C/XRL/ENS/M61/204.  In general, the magnitude of settlement anticipated as a result of tunnel construction ranges from a maximum of approximately 30mm along the centreline between the twin parallel tunnels; to nominally 20mm, and 5mm at a distance of 20m, 40m from the centreline, respectively.  This magnitude is minimal when compared to the settlement estimated to result from waste decomposition, which typically ranges from approximately 250mm to 750mm. 

15.52        From inspection, the qualitative effect that the potential settlement induced by the construction of tunnels has on the Landfill surface is summarized in Table 15.1.

15.53        The results of the analysis of potential settlement caused by the construction of the tunnels are superimposed on the post-settlement configuration of the Landfill resulting from only waste degradation (Figure No. NOL/ERL/300/C/XRL/ENS/M61/204), to determine the combined long-term affect on the final configuration of the Landfill cross section as shown.

Table 15.1  Summary of the Impact of Only Settlement Resulting from Tunnel Formation

 

Location

Description of Impact on Surface Gradient

Upper Platform

Surface gradients will increase from the centre of the Landfill toward the crest of the Upper Slope.

Upper Slope

Slope inclination will increase as the toe of slope is closer to the centreline of the tunnels and therefore has a higher magnitude of settlement.

Lower Platform

Surface gradients across the northeastern portion of the platform will increase, whereas surface gradients across the northwestern portion of the platform will decrease.

Lower Slope

Slope inclination will decrease as the crest of the slope is closer to the centreline of the tunnels and therefore has a higher magnitude of settlement.

Resulting Landfill Surface Gradients

15.54        In review of the potential final configuration of the Landfill, it is obvious that the settlement caused by the construction of the tunnels alone is minimal by comparison to that resulting from the degradation of waste.  Additionally it appears that the surface gradients across the platform will be reduced to a minimum of nominally 2%; whereas the inclination of the side slopes will be slightly flatter than the original, but remain relatively steep.  The flattening of the slopes and platforms as described is not unexpected and, if it remains within the order of magnitude described herein, is acceptable.

Integrity of Geomembrane Component of Capping System

15.55        Differential settlement of the Landfill surface can result in stresses and strains to be induced in the geosynthetic components of the capping system layers; specifically the geomembrane layer.  The magnitude of strain in the geomembrane resulting from the differential settlement caused by the combined effect of waste degradation and the construction of the tunnels is less than 1% as shown in Figure No. NOL/ERL/300/C/XRL/ENS/M61/204.

15.56        The geomembrane reported to be used in construction of the capping system [Ref. 6] is a linear low density polyethylene (LLDPE) material, also sometimes referred to as “very flexible polyethylene (VFPE)”.  This material is typically considered to have no definable yield stress or strain, and a break elongation in excess of 800% as measured in uni-axial tension.  For application to the NTML, it can very conservatively be assumed that the LLDPE geomembrane material used has the same yield elongation characteristics as high density polyethylene (HDPE), nominally 12%.

15.57        With an estimated potential settlement-induced strain of less than 1% and an allowable strain of at least 12%, the geomembrane component of the capping system should not be adversely affected by the additional settlement caused by tunnel construction or by the total settlement resulting from the combination of waste decomposition and construction of the tunnels.

Integrity of Leachate and Landfill Gas Management Systems and Infrastructure

15.58        The leachate management system consists of a simple piping network installed at the base of the Landfill, and a concrete chamber near the toe of the Lower Slope (refer to Appendix 15.1).  As a result, it will not be subject to settlement from degradation of the overlying waste, but only the settlement caused by construction of the tunnels.  The resulting differential settlement is estimated as less than 0.1% along the pipeline length (refer to Figure No. NOL/ER:/300/C/XRL/ENS/M61/204); a magnitude which is not anticipated to result in significant change in the flow gradient or increased compressive or tensile stresses in the pipe material.

15.59        The existing landfill gas management system consists of a network of vertical passive ventilation wells across the Upper Platform; and horizontal pipes installed in relatively shallow trenches with vertical passive ventilation risers generally aligned around the perimeter of the Upper Platform, along the toe of the Upper Slope and diagonally across and down the Lower Slope (refer to Appendix 15.1).  The vertical ventilation wells across the Upper Platform are likely to be subjected to significant settlement from degradation of the waste, but are located too distant from the tunnel alignment to be significantly influenced by its construction (refer to Figure No. NOL/ER:/300/C/XRL/ENS/M61/204).  Similarly, the network of passive horizontal trenches and vertical risers around the perimeter of the Upper Platform likely have a limited depth of waste beneath and are relatively distant from the tunnel alignment; therefore they will be subject to limited settlement and even less differential settlement.  The horizontal pipes along the toe of the Upper Slope will be subjected to substantial settlement (estimated to be more than 400mm) from waste degradation and less than 30mm from formation of the tunnels, but limited differential settlement.  The horizontal pipe across the Lower Slope is installed at a relatively steep gradient (approximately 13%) and thus will be affected only to a limited extent by both waste degradation and tunnel construction settlement.  The pipe aligned across the width of the Lower Platform will be the most critical in terms of settlement impact; however the settlement resulting from formation of the tunnels is anticipated to result in a gradient reduction of less than 0.1% across an graded at more than 6%, and therefore relatively inconsequential.

15.60        Based on the configuration of the surface water management system (refer to Appendix 15.1) it is anticipated that the performance will be remain relatively unaffected by the settlement resulting from the formation of the tunnels.  Many of the surface water features are oriented across the crest or toe of the Upper and Lower Slope, or directly down-slope.  Again, the most critical location on the site is anticipated to be across the Lower Platform, where formation of the tunnels is estimated to alter the designed gradient only slightly; from the initial design of approximately 6%, remaining at more than 5.9% after settlement.

15.61        The concrete-paved road is generally constructed outside of and along the waste boundary (refer to Appendix 15.1); and therefore is not subject to settlement induced by waste degradation.  It will, however, be subjected to settlement caused by formation of the tunnels.  The resulting differential settlement along the northeast-southwest trending portion of the road is estimated to be less than 0.1% (refer to Figure No. NOL/ER:/300/C/XRL/ENS/M61/204); a magnitude which is not anticipated to result in significant additional tensile or compressive stresses, or significant additional cracking of the concrete surfaces.

Impact of Groundwater on Tunnels

15.62        There are two potential concerns with regard to the effect that the restored NTML may have on the tunnels; both related to the flow of groundwater.  Specifically in this regard are the concerns of: 

(a)  the quantity; and

 

(b)    the quality of groundwater appearing at the tunnels; with the potential consequences being:

-          the need to manage the inflow volume (during both the construction and operation stages);

-          the collection and discharge of contaminated groundwater (during the construction and operations stages); and

-          degradation of reinforced concrete or other materials/elements used in construction of the tunnels (operations stage). 

15.63        A brief description of a groundwater model and monitoring data available for the Landfill is presented in the following sections, followed by an assessment of these concerns.

Groundwater Model

15.64        Because the restored NTML does not have a base lining system (there is a relatively impermeable component in the capping system, but only across the two platform areas), the local groundwater regime can be modeled as that provided in the Hydrogeological Impact Assessment Report [Ref 8].

15.65        During the wet season the groundwater recharges from the permeation of rainfall through the superficial deposits and weathered rock below the areas of predominantly natural habitat (vegetated hill slopes) and agricultural land [Ref. 8].  During the dry season, there is a reduction in rainfall with a corresponding reduction in permeation through the superficial layers.  As a result, the flows are reduced, with a subsequent decline in the groundwater table.  Regional and localized groundwater flow is from the topographic high areas to the topographic low areas throughout the entire year.

15.66        There is a localized groundwater mound within the hill immediately to the east of the Landfill, with flow radially outward [Ref. 8], and thus generally west to east across the Landfill site.  The unnamed hill therefore represents an area hydrogeologically up-gradient of NTML; with flow toward the relatively flat areas to the west that are down-gradient from the Landfill.  The areas immediately adjacent to the Landfill, particularly to the north, can generally be hydrogeologically considered as side-gradient.

15.67        Based on this model, the areas up-gradient from the Landfill should be free from contamination with waste constituents and thus provide a baseline or background for the concentrations of the various constituent parameters.  Conversely, the down-gradient areas to the west of the Landfill are expected to potentially have traces of the same constituent parameters as the waste mass; the concentrations of which will vary as a function of time and distance, both vertically and horizontally, from the Landfill.  The side-gradient areas will commonly demonstrate concentration levels between that of the up-gradient and down-gradient locations, but typically closer to that of the down-gradient, with the exception of a zone immediately adjacent to the landfilled waste mass.

15.68        Hydrogeologic principles applied generally to landfilled waste, and more particularly the restored NTML, suggest that the flow of contaminants from the disposed waste mass is through a combination of transport mechanisms, including advection, diffusion and dispersion.  Various models, many of them relatively complex, exist to simulate the transport of the various constituents as a function of time and distance from the disposed waste.  However, a more fundamental approach has been taken for the assessment described herein, with the results providing a range which does not warrant more complex modelling.

Available Data

15.69        The Restoration Contract requires that groundwater and leachate levels and quality be monitored at designated locations and at specified frequencies during the contract duration.  There is, as a result, a series of six (6) groundwater monitoring wells around the Landfill:

·         one (1) up-gradient well (Well No. GW1);

 

·         four (4) down-gradient (Well Nos. A458, DH403, DH404 and DH405); and

 

·         one (1) side-gradient (Well No. DH407).

15.70        Information on both the groundwater level/elevation and the quality have been provided by the Restoration Contractor for the period from October 2006 through July 2008, based on select constituent parameters required by the Restoration Contract.  There is also a series of two (2) leachate monitoring wells (Well Nos. DH401 and DH402/402A), for which there is monitoring information on the level/elevation and quality within the waste mass for the same time period.  The locations of the groundwater monitoring wells and the leachate monitoring wells are shown on Figure No. NOL/ERL/300/C/XRL/ENS/M61/203.

15.71        Additional groundwater sampling from a borehole drilled along the alignment and level of the tunnels in the vicinity of the Landfill was performed in early 2009 in conjunction with a supplementary investigation associated with this Project.  The results of the subsequent groundwater quality testing are included in Appendix 15.5.

Quantity of Groundwater

15.72        The quantity of groundwater appearing at the alignment is generally a function of several factors, including:

·                     the local geology;

 

·                     the soil/rock strata in which the tunnel is to be constructed;

 

·                     the depth of the tunnel below the groundwater table; and

 

·                     the overall hydrogeologic setting of the area.

 

15.73        A description of the groundwater regime, including a conceptual groundwater model and a qualitative impact assessment is included in the “Interim Hydrogeological Impact Assessment Report” [Ref. 8].

15.74        Of the factors identified, most (including the local geology, the soil/rock strata along the Project tunnel alignments and the depth of the tunnels below groundwater) are, by their nature, generally unaffected by the presence of the restored NTML.  These therefore do not need to be considered further herein.  The remaining factor, the hydrogeologic setting is considered in this assessment.

15.75        As reported, the general hydrogeologic setting along the tunnel alignment (and all of Hong Kong) has groundwater “…flowing from the high elevation area(s) to the low elevation areas…”.  The “Interim Hydrogeological Impact Assessment Report” [Ref. 8] indicates an inferred groundwater mound in the unnamed hill immediately to the east of the restored NTML; with flow generally radially outward and more locally from east to west across the Landfill area and toward the tunnel alignments.

15.76        The topographic setting of the restored NTML is within a relatively small valley, between approximately elevations +15mPD and +35mPD at the toe of the western slopes of the isolated unnamed hill that rises to an elevation of approximately +85mPD.  This setting, and the groundwater and leachate level data obtained as part of the ongoing monitoring programme of the Restoration Contract, suggests that the groundwater has risen relative to the original level, likely due to the presence of the Landfill; but generally only within the area of the former valley now filled with disposed waste. Therefore, the local and regional hydrogeology remain practically unaffected.

15.77        Groundwater flow into the tunnels during and after construction is related to the method of construction and the designed tunnel lining system, respectively; and is not directly related to the presence of the waste within the restored NTML.  It is understood that groundwater inflow will be “effectively precluded” [Ref. 1] both during construction, by use of a closed-face Tunnel Boring Machine (TBM); and during operations, by a permanent precast concrete tunnel lining.

15.78        With no groundwater or leachate flow into the tunnels, the existing hydrogeologic regime will not be altered.  As a result the groundwater level surrounding the Landfill, the leachate level within the Landfill, and the groundwater and leachate flow will practically be unaffected.

Quality of Groundwater

15.79        The quality of the groundwater is of concern in two (2) regards; the quality of water that could potentially drain into and be discharged from the tunnels during construction and/or operation phases; and the potential impacts that the quality of groundwater may have on the materials selected for construction of the tunnels.

Impact on Collected Groundwater

15.80        It is understood that the inflow of groundwater will be controlled during construction by use of a closed-face Tunnel Boring Machine (TBM); either an Earth Pressure Balance Machine or a slurry type machine.  A closed-face machine of this nature reportedly “…effectively precludes the ingress of water into the tunnel during...construction.” [Ref. 1].  As a result it is anticipated that groundwater inflow into the tunnel during construction will be controlled by the selected boring machine and construction method, to the extent that none will be collected from the area along the alignment immediately adjacent to the restored NTML.

Impact on Tunnel Materials

15.81        It is understood that the tunnels will be lined with a precast reinforced concrete segmental lining having joints sealed with an elastomeric gasket and hydrophilic strip [Ref. 1].  In this regard, there are two (2) construction materials of potential concern for assessment of the impact of the restored NTML on the tunnels, specifically:  the reinforced concrete to be used as the tunnel lining; and the specific materials to be used as the joint sealant.  The detailed assessment of each of these materials is presented as follows.

Precast Reinforced Concrete Material

15.82        Based on the composition of “typical” landfill leachate [Ref. 7] and the leachate quality monitoring data for the restored NTML (refer to Appendix 15.4),  there are three (3) primary leachate constituents of concern with regard to the use of concrete for the tunnel lining:  pH, sulphate, and chloride. 

15.83        It is commonly accepted in landfill engineering that the aggressiveness of most, if not all municipal solid waste leachate constituents decrease with time after placement (increasing “age” of the waste).  This is the case for each of the three parameters of concern.  It should be noted that there is an initial increase of the values of most, if not all parameters, while waste is still being placed and shortly thereafter; say within 1-year; after which time the values decrease through time.

15.84        It is commonly considered that concrete can be vulnerable to acid attack at pH levels of less than approximately 5.5 or 6.  The pH of the groundwater down-gradient of the Landfill was tested in association with the recent supplementary investigation performed for this Project (refer to Appendix 15.5).  The pH was measured at 7.2; therefore it is not anticipated that the concrete tunnel lining will be subject to acid attack. 

15.85        Sulphate attack of concrete can occur when sulphate in the groundwater reacts with the constituents in the cement used to produce the concrete mixture.  This is generally considered of minimal concern when the sulphate concentration in groundwater is less than 400mg/L [Ref. 4].  The results of the recent (May 2009) testing performed in association with this Project indicate sulphate levels of 8mg/L (refer to Appendix 15.5). Therefore there is practically no concern for sulphate attack of the precast tunnel lining.

Impact on Concrete Reinforcement

15.86        The average chloride concentration in the groundwater monitoring wells down-gradient from the restored NTML was approximately 30mg/L as measured from October 2006 through July 2008.  However, the results of the more recent (May 2009) testing performed in association with this Project indicate a chloride concentration of 9mg/L along or near the alignment and level of the tunnels in the vicinity of the Landfill (refer to Appendix 15.5).  These more recent results appear more directly relevant and, for practical considerations, suggest a chloride concentration which is at or only slightly elevated from the background level as measured up-gradient from the Landfill. 

15.87        As the more recently tested chloride concentration levels are, by Hong Kong practice, typically not considered of concern with regard to degradation of steel reinforcement, there is practically no concern for chloride attack of the precast concrete segmental tunnel lining system to be used on this Project.

Joint Sealant Material

15.88        As the tunnel has not yet been designed in detail, the elastomeric gasket and hydrophilic sealant materials between the concrete tunnel lining segments have not yet been specified.  It is therefore recommended that these materials be selected based on proven chemical resistance/chemical compatibility with liquids containing the constituents and in the concentrations found in the Landfill down-gradient monitoring wells or a sample obtained from within the tunnel bore such as has been tested in May 2009.  Based on the typical constituents and concentrations found down-gradient of the restored NTML, and the range of polymeric and natural materials available for production of the sealant materials, it is anticipated that the issue of resistance/compatibility can be appropriately and effectively addressed through the process of design and proper selection.

Mitigation of Potential Impacts

15.89        The assessment performed herein concludes that the anticipated ground vibration generated by the TBM during construction and the trains during operation of the Project will have minimal impact on the restored NTML slopes.  The impact is a slight reduction in the minimum Factor of Safety obtained in analysis of the stability of the slope.  The resulting Factor of Safety remains comfortably above the minimum specified level; therefore no mitigation measures are necessary.

15.90        Similarly, the assessment performed for settlement of the NTML indicates that, even based on conservative assumptions, the potential ground movements generated by formation of the XRL tunnels will have minimal impact on the settlement of the Landfill, particularly compared to the magnitude of settlement resulting from degradation of the waste.  Specifically in this regard, the anticipated settlement from the construction of the Project tunnels is conservatively estimated at a maximum of approximately 30mm as compared with a maximum of 450mm due to waste degradation.  The generally favourable orientation of the Project tunnels with the overlying Landfill configuration; along with the relatively minor magnitude of estimated settlement; is not anticipated to result in a gradient reversal or the generation of excessive stresses:  across the restored final ground surface; with the geomembrane component of the capping system; in the leachate and landfill gas management systems, the surface water management system or the road.  As a result, no mitigation measures of these components and systems are necessary.

15.91        The assessment performed for the potential impact of the restored NTML on the tunnels indicates that the groundwater quality down-gradient of the Landfill will likely contain only trace constituents from the waste mass that could potentially cause deterioration of the tunnel concrete lining or the elastomeric joint sealant between segments.  It was determined that each of the three constituents of potential concern; pH, sulphate and chloride; the concentration/level of each is likely to be sufficiently low that there would be no adverse impact on the tunnel concrete lining.

15.92        Assessment of the potential impact of the groundwater quality on the elastomeric gasket and hydrophilic sealant are very dependent on the actual materials selected for use.  It is therefore recommended that the gasket and sealant materials be reviewed for chemical resistance to the various constituents and concentrations in the leachate/groundwater; and potential suppliers of these materials be provided with the chemical composition of the groundwater so as to propose compatible gasket/sealant materials.

Conclusions and Recommendations

15.93        The existing restored NTML slopes are stable (with a minimum Factor of Safety of 1.8).  The calculated minimum Factor of Safety will be reduced slightly to approximately 1.6 under the imposed conditions of conservatively large vibrations assumed during the construction of the tunnels in rock.  As a result, no mitigation measures are necessary.

15.94        Long-term settlement of municipal solid waste placed in landfills results from the naturally-occurring process of decomposition and gas generation.  The surface of the NTML is expected to settle up to 750mm over the course of the modelled duration.  Based on commonly employed modelling methods and under conservative assumptions, it is anticipated that the construction of the tunnels beneath the Lower Platform of the Landfill will not cause more than 30mm of additional settlement.  Given the location of the tunnels beneath the Landfill, the constructed gradients across the Landfill surface, and the anticipated settlement pattern; it is anticipated that the construction of the tunnels will not cause adverse impacts (such as reversal of the ground surface gradients; rupture of the geomembrane component of the capping system, damage to the leachate and landfill gas management systems, additional damage to the surface water management features or damage to the road) to the restored NTML, and therefore no mitigation measures are anticipated to be required.

15.95        It is indicated by others that use of Tunnel Boring Machine (TBM) methods and a permanent segmental concrete liner with elastomeric gasket/hydrophilic sealant will prevent inflow of groundwater into the tunnels during the construction and operation phases.  Based on this design assumption, it is anticipated that the groundwater and leachate levels and flows will remain virtually unaffected and therefore will not require mitigation measures of any kind.

15.96        Furthermore, based on the currently reported leachate quality within the waste and, more specifically, the groundwater quality down-gradient of the Landfill, it is unlikely that leachate will have an adverse impact on the concrete lining of the tunnels; therefore mitigation measures will not be necessary.

References

1.       Arup-Atkins Joint Venture; “Working Paper No. 42 – Tunnelling Impact on Ngau Tam Mei Landfill”; Consultancy Agreement No. NEX/2102; Express Rail Link – Preliminary Design of Tunnels & Associated Structures; January 2009.

 

2.       Arup-Atkins Joint Venture; “Deliverable D3.24A, Draft Preliminary Design Final Report”; Consultancy Agreement No. NEX/2102; Express Rail Link – Preliminary Design for XRL Tunnels and Associated Structures; December 2008.

 

3.       Wong, H.N. and P.L.R. Pang; GEO Report No. 15 – “Assessment of Stability of Slopes Subjected to Blasting Vibrations”; Geotechnical Engineering Office, Civil Engineering Department, The Government of the Hong Kong Special Administrative Region; 2000.

 

4.       Carnevale, M, G. Young and J. Hager; “Monitoring of TBM-induced ground vibrations”; North American Tunneling ’00; Balkema; 2000.

 

5.       Binnie Black & Veatch HK Ltd.; “Design Criteria Design Submission”; Contract No. EP/SP/30/95 – North-West New Territories Landfills and Gin Drinkers Bay Landfill Restoration; GEN/GEN/SUB/001/Issue 1, February 1999.

 

6.       Binnie Black & Veatch HK Ltd.; “Ngau Tam Mei Formation Design Submission”; Contract No. EP/SP/30/95 – North-West New Territories Landfills and Gin Drinkers Bay Landfill Restoration; NTM/STE/SUB/001/Issue 1, March 1999.

 

7.       Guglielmetti, Vittorio; Piergiorgio Grasso; Ashraf Mahtab; and Shuli Xu; “Mechanized Tunnelling in Urban Areas – Design Methodology and Construction Control.

 

8.       Arup-Atkins Joint Venture; “Interim Hydrogeological Impact Assessment Report”, Consultancy Agreement No. NEX/2102; Express Rail Link – Preliminary Design for XRL Tunnels & Associated Structures; Deliverable No. D3.1R; August 2008.

 

9.       Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters.

 

10.   Rowe, R. Kerry; Robert M. Quigley, Richard W.I. Brachman and John R. Booker; “Barrier Systems for Waste Disposal Facilities”; 2nd Edition; Spon Press; 2004.\

 

11.    “Final Civil Engineering Scheme Report”, Consultancy Agreement No. NEX/2102, Express Rail Link; Document No. NEX2102-DED-AAV-CS-0029-101, Deliverable No. D3.10C as cited in email communications.

 

12.   Skalny, Jan; Marchand, Jacques and Odler, Ivan; “Sulfate Attack on Concrete”, 2002.

 

13.   Ismail, Mohamed and Masayasu Ohtsu; “Corrrosion rate of ordinary and high-performance concrete subjected to chloride attack by AC impedance spectroscopy”; Construction and Building Materials; 20 (2006), pgs 458-469.

 

14.   Geotechnical Engineering Office, Civil Engineering and Development Department, The Hong Kong Special Administrative Region; Geoguide 7 – “Guide to Soil Nail Design and Construction”; 2008.