18.1
This chapter presents the implementation
schedule of the proposed mitigation measures for the Project. Table
18.1 summarises the details of mitigation measures, which should be implemented
as far as practicable, in the works areas as specified.
18.2
For each
recommended mitigation measure, both location and timing for the measure have
been identified as well as, the parties responsible for implementing the
measures and for maintenance, where applicable.
Table 18.1 Project
Implementation Schedule
EIA Ref. |
Recommended Mitigation Measures |
Objectives of the Recommended Measures & Main Concern
to Address |
Who to implement the measures? |
Location of the measures |
When to implement the measures? |
Requirements |
||||
Ecological Impact (Detailed design Phase / Pre-construction
Phase) |
|
|
|
|
|
|||||
S3.398 |
- Prior to
commencement of channel works, an ecological
habitat
management plan should be
prepared to provide the detailed specifications for the habitats and
ecological functions to be provided, and control of
colonization of invasive plant species at the mitigation stream habitats and
define the long-term management and ecological monitoring and audit
requirements for these habitats. |
To
mitigate the avoidable loss of watercourse habitat |
MTR |
SSS |
Detailed design phase / Prior to commencement of channel works |
Ecological habitat
management plan |
||||
S3.388 - S3.397 |
- The constructed channel in the SSS site should
include open channel with ecologically friendly stream feature to mitigate
the direct impact due to the loss of a watercourse habitat in Shek Kong. |
To mitigate the avoidable loss of watercourse habitat |
MTR / DDC |
SSS |
Detailed design phase |
Ecological habitat management plan |
||||
S3.410 |
- The implementation details of the impact
monitoring programme should be described in ecological monitoring plan for
EPD approval before commencement of construction activities. |
To outline
details of ecological impact monitoring |
MTR |
MPV, TPP,
SSS / ERS, PHV and TUW |
Before commencement of construction
activities |
Ecological monitoring plan |
||||
S3.327 & |
- A
monitoring and emergency response plan (to be prepared by the Contractor), in
relation to potential impacts due to groundwater drawdown, will form part of
the EM&A requirement in the
EM&A Manual subject to approval by EPD and AFCD before commencement of
the tunnelling and MPV construction in |
To detect
potential impacts due to groundwater drawdown |
Contractor |
MPV |
Before commencement of the
tunnelling and MPV construction |
Groundwater
monitoring and emergency response plan |
||||
S3.413 |
- A
monitoring and emergency response plan, in relation to impacts due to
noise/vibration, should form part of the EM&A requirement in the EM&A
Manual subject to approval by EPD and AFCD before commencement of the
tunnelling and MPV construction in |
To detect and monitor noise / vibration impacts |
Contractor |
MPV |
Before commencement of bore tunnelling and MPV construction |
Monitoring and emergency response
plan on noise and vibration |
||||
Ecological Impact (Construction Phase) |
|
|
|
|
|
|||||
S3.325 - |
-
Implementation of
precautionary measures during tunnelling works. |
To avoid potential hydrogeological impacts |
Contractor |
All works areas |
Construction phase |
-
|
||||
S3.409 to S3.410 |
- Ecological impact monitoring focusing on habitats
and species of conservation interest should be conducted during the
construction phase at the MPV, TPP, SSS / ERS, PHV, and TUW sites where a
number of avifauna of conservation interest (e.g. overwintering bird, Greater
Painted-snipe) and areas of conservation interest (e.g. country parks,
conservation areas, and wetlands) were recorded. - Avifaunal
communities should be surveyed quantitatively along transects. Birds heard or seen along the transects should be identified to species and
counted. The nature of
construction works within works area conducting during each impact monitoring
visit should also be recorded.
The quantitative monitoring results should be compared to
pre-construction condition. The
impact monitoring results should be undertaken by qualified ecologist(s) with
relevant working experience. - Should any
unpredicted indirect ecological impacts arising from the proposed Project be
detected, remedial measures should be developed and implemented by the
Contractor. |
·
To monitor potential
indirect construction impacts to wildlife |
MTR MTR Contractor |
MPV, TPP,
SSS / ERS, PHV, and TUW |
Construction phase |
- |
||||
S3.327 & |
- Implementation of the groundwater monitoring and emergency response
plan. |
·
To detect and minimize hydrological impacts |
Contractor |
MPV |
Construction phase (During
bore tunneling works and construction of |
- |
||||
S3.413 |
- Implementation
of monitoring
and emergency response plan on noise and vibration. |
To detect and minimize noise / vibration impacts |
Contractor |
MPV |
Construction
phase (During bore tunneling works and construction of |
- |
||||
S3.364 -S3.369 |
-
Use of quiet
construction plant and temporary noise barriers. -
Access to the ventilation building sites should follow existing
access roads, such as the maintenance access along the existing drainage channels. -
Site hoarding of about -
Gate and fences should be installed along the
construction accesses that are adjacent to public areas. -
Gates and hoardings should
be provided at the entrances/exits and along the boundary of the works areas
respectively to prevent any trespassers from encroaching or will fully disturbing
any wild animals and their habitats within the works areas. -
A trip-ticket system should
be adopted to monitor the disposal of construction and demolition
materials. CCTV and warning signs
should be provided at the entrance of the proposed temporary and permanent
vehicular access. |
To minimise impacts
to surrounding habitats |
MTR / Contractor |
All works areas |
Construction phase |
- |
||||
3.370 -3.371 and |
-
Vegetation located within the works areas should be preserved as far as practicable. -
To avoid soil compaction, heavy machinery
should not be used in close proximity to vegetation. Soils that become
compacted through the activities of the development should be loosened to an
appropriate depth to allow seed germination. -
All temporarily affected habitats should be
reinstated after the completion of works. -
Placement of equipment or stockpiles should be confined to designated works
areas. Access routes should be
confined on existing disturbed land, where practicable. |
To minimize impacts to vegetation |
MTR / Contractor |
All works areas |
Construction phase |
- |
||||
- Detailed
vegetation survey should be conducted in TSW site prior to commencement of
site clearance. |
To minimize impacts
to vegetation |
MTR / Contractor |
TSW |
Prior to
commencement of site clearance |
- |
|||||
- To
mitigate the loss of the vegetation and habitats, planting of native species
should be provided in the areas affected by the Project in TSW site, and other works area, where
practicable. |
To minimize impacts
to vegetation |
MTR / Contractor |
TSW and all other
works areas |
Construction phase |
- |
|||||
S3.372 |
-
The
affected individuals of Incense Tree within the NTV works area should be transplanted to nearby suitable
habitats prior to the commencement of site clearance at NTV works area as far
as practicable. -
A detailed vegetation survey covering the
affected habitat at NTV works area should be
conducted by a suitably qualified botanist / ecologist to identify and record
the affected individuals in order to provide details for the transplantation
scheme prior to the commencement of site clearance. Feasibility and
suitability of transplanting the affected individuals would be studied and
suitable receptor sites would be identified. The transplantation proposal for the
affected individuals should be
prepared as necessary and transplantation should
be supervised by a suitably qualified ecologist / horticulturist. |
To minimize impacts to vegetation |
MTR / Contractor |
NTV |
Construction phase |
Detailed vegetation survey Transplantation Proposal |
||||
S3.374 - S3.377 |
- Site hoarding of |
To minimize disturbance to wildlife |
Contractor |
All works areas |
Construction phase |
- |
||||
|
-
The erection of
hoarding ( |
KT5 (near TPP) |
Prior to the
construction of access road |
- |
||||||
|
-
The use of noisy construction equipment such as
hydraulic breakers should be avoided at the area with high painted-snipe
occurrence (e.g. the proposed access road next to KT5) during their breeding
season as far as practicable. |
KT5 (near TPP) |
Construction phase |
- |
||||||
|
-
Hoardings of 2.4
m height should be put in place before commencement of construction
activities. Hoarding at the section along the northern boundary of the MPV
works area should be installed first.
The duration of hoarding erection should be kept as brief as
practicable. -
Upon the
erection of site hoarding, all construction activities should be conducted
within the fenced area. |
MPV |
Right after
possession of site |
- |
||||||
-
Major construction site lighting should
point inward and downward.
Unnecessary lighting should be turned off outside working hours of the
construction sites. |
All works area |
Construction phase |
- |
|||||||
S3.378 - S3.380 |
- Excavation works carried out within
waterbodies should be carried out in dry season where practicable. - Excavation
works within the watercourse / drainage channel should be restricted when possible to an enclosed dry
section of the watercourse / drainage channel, with containment measures such
as bunds and barriers used within the watercourse / drainage channel. - Site
runoff should be directed towards regularly cleaned and maintained silt traps
and oil / grease
separators. The silt and oil / grease
separators should be appropriately designed for the local drainage and ground
conditions. Tightly sealed closed grab excavators should
be deployed where material to be handled is wet. - The flow
of the watercourse and drainage channel located with the Project Area should
be maintained throughout the construction phase. |
To minimise pollution to waterbodies |
Contractor |
All works areas |
Construction phase |
- |
||||
Terrestrial Ecological Impact (Post-construction /
Operation Phase) |
|
|
|
|
|
|||||
S3.327 & |
-
Implementation of the
groundwater monitoring and emergency response plan. |
To detect and minimize hydrogeological impacts |
Contractor |
MPV |
Post-construction phase |
- |
||||
S3.381 |
-
The affected agricultural land should be restored to a
condition suitable for agricultural use before handing over to landowners /
operators. |
To minimize impacts
to surrounding habitats |
MTR / Contractor |
All temporarily
occupied agricultural land |
Operation phase |
- |
||||
S3.382 – S3.384 |
-
Vegetation control in the constructed
channels should be implemented to prevent the excessive growth of vegetation
that would impede the drainage capacity of the channel. To minimise sedimentation, de-silting
should be limited to the dry season (November to March). The natural stream bed substrate
should not be removed from the channel during de-silting works. -
For maintenance
de-silting, temporary barrier walls should be used to provide a dewatered
zone for de-silting works. Waste
material produced during de-silting should be disposed of in a timely and
appropriate manner. |
To minimise impacts to constructed channels |
MTR |
All constructed channels in SSS |
Operation phase |
- |
||||
S3.385 & S3.387 |
- Large
areas of reflective material (including glass) should not be used on the
outer surfaces of the buildings. - All the
major lighting sources should point inward and downward to minimise glare
disturbance to wildlife. The
intensity of light should also be controlled to the lowest possible level. |
To minimise impacts to wildlife |
MTR / DDC |
All ventilation buildings in northern section and SSS |
Detailed design and Operation phases |
- |
||||
S3.411 |
-
Implementation of ecological
habitat management plan. -
Ecological monitoring of the
mitigation stream habitats according to ecological habitat management plan. |
To monitor the wildlife use of the mitigation stream
habitat |
MTR |
Mitigation stream
habitat in SSS / ERS |
Operation phase |
- |
||||
Marine Ecological Impact (Construction Phase) |
|
|
|
|
|
|||||
Appendix3.6 (S1.102) |
- The use of high-speed vessels should also be avoided during the
construction and operation of the proposed barging point. |
To minimise the indirect impact to Chinese White
Dolphin habitat |
Contractor |
LKB |
Construction phase |
- |
||||
Appendix3.6 (S1.103) |
- No dumping of rubbish, oil or chemicals would be allowed. |
To minimise the pollution to marine habitats |
Contractor |
LKB |
Construction phase |
- |
||||
Appendix3.6 (S1.104) |
- Deployment of silt curtains around the closed grab dredgers to
minimize the suspended sediment impact due to dredging activities in dredging
region. - To minimize impact on the gorgonians along the coastline near the
dredging area, double silt curtains should be deployed around the works
area. |
To minimise the impact to subtidal habitats |
Contractor |
LKB |
Construction phase |
- |
||||
Appendix3.6 (S1.106) |
- The number of work vessels and small crafts should be minimized. Dredging should be carried out
continuously without unnecessary break to prevent unpredictable or sudden
noise outbursts at random intervals. |
To minimise disturbance impact on Chinese White
Dolphin |
Contractor |
LKB |
Construction phase |
- |
||||
Appendix3.7 (S1.83) |
- Mitigation measures to control water quality impacts proposed under
Section 11 should be adopted. |
To minimise indirect impact to intertidal and
subtidal flora and fauna |
Contractor |
WKT |
Construction phase |
- |
||||
Appendix3.6 (S1.105) |
- Engines of vessels moored at the barging point would be turned off to
minimize unnecessary underwater noise.
|
To minimise disturbance impact on Chinese White
Dolphin |
Contractor |
LKB |
Construction phase |
- |
||||
Pond Fisheries Impact (Pre-construction Phase) |
|
|
|
|
|
|||||
S4.51 |
- A
monitoring and emergency response plan, in relation to potential impacts due
to groundwater drawdown, will form part of the EM&A requirement in the
EM&A Manual subject to approval by EPD and AFCD before commencement of
the tunnelling and MPV construction in |
To detect and minimize
potential hydrological impacts |
Contractor
|
MPV |
Pre-construction
phase (Before commencement
of the tunnelling and MPV construction) |
Groundwater
monitoring and emergency plan |
||||
S4.52 |
- A
monitoring and emergency response plan, in relation to impacts due to
noise/vibration, should form part of the EM&A requirement in the EM&A
Manual subject to approval by EPD and AFCD before commencement of the
tunnelling and MPV construction in |
To detect and monitor noise / vibration impacts |
Contractor |
MPV |
Pre-construction
phase (Before commencement
of bore tunnelling and MPV construction) |
Monitoring and emergency response
plan on noise and vibration |
||||
S4.45 |
- Consultation should
be conducted with fish operators in |
Engagement of stakeholders |
Contractor / MTR |
MPV |
Pre-construction
phase (Before commencement of tunneling works) |
- |
||||
Pond Fisheries Impact (Construction Phase) |
|
|
|
|
|
|||||
S4.51 |
- Implementation
of the groundwater monitoring and emergency response plan. |
To detect and minimize
hydrogeological impacts |
Contractor
|
MPV |
Construction phase (During bore
tunneling works and construction of |
- |
||||
S4.52 |
- Implementation
of the monitoring
and emergency response plan on noise and vibration. |
To detect and minimize
noise / vibration impacts |
Contractor
|
MPV |
Construction phase (During bore
tunneling works and construction of |
- |
||||
S4.40 |
- Good
site practices and proper dust and water quality control measures should be
implemented. These include site
confinement with fencing/hoarding erection at the perimeter of the works
area, stockpile covering by impervious sheeting to avoid spread of construction
dust, and proper handling, storage and disposal of chemical waste to avoid
contamination of the existing water system, etc. |
To minimize the indirect off-site impacts on the
adjacent fishponds |
Contractor |
MPV |
Construction phase |
- |
||||
S4.44 |
Implementation of
good site practices during the construction phase: § Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction program; § Silencers or
mufflers on construction equipment should be utilized and properly maintained
during the construction program; § Machines and plant
(such as trucks) that may be in intermittent use should be shut down between
work periods or should be throttled down to a minimum; § Plant known to emit
noise strongly in one direction should, wherever possible, be orientated so
that the noise is directed away from the nearby fishponds; § Material stockpiles
and other structures should be effectively utilized, wherever practicable, in
screening noise from on-site construction activities; § Use of movable
barrier for certain powered mechanical equipment (PME); and § Use of noise
enclosure or acoustic shed to cover certain stationary PME. |
To minimize disturbance to fishponds by
construction noise |
Contractor |
MPV |
Construction phase |
- |
||||
Pond Fisheries Impact (Post-construction Phase) |
|
|
|
|
|
|||||
S4.51 |
- Implementation
of the groundwater monitoring and emergency response plan. |
To detect and minimize
hydrogeological impacts |
Contractor
|
MPV |
Post-Construction phase |
- |
||||
Marine Fisheries Impact (Construction Phase) |
|
|
|
|
|
|||||
Appendix4.2 (S1.38) |
- Mitigation measures to control water quality impacts proposed under
Section 11 should be adopted. |
To minimize the indirect impact on fisheries
resources |
Contractor |
LKB and WKT |
Construction phase |
- |
||||
Airborne Noise Impact (Construction Phase) |
|
|
|
|
|
|||||
S5.120 |
The following good site practices should be
implemented: § Only
well-maintained plant should be operated on-site and plants should be
serviced regularly during the construction program; § Silencers or
mufflers on construction equipment should be utilized and should be properly
maintained during the construction program; § Mobile plant, if
any, should be sited as far from noise sensitive receivers (NSRs) as
possible; § Machines and plant
(such as trucks) that may be in intermittent use should be shut down between
work periods or should be throttled down to a minimum; § Plant known to emit
noise strongly in one direction should, wherever possible, be orientated so
that the noise is directed away from the nearby NSRs; and § Material stockpiles
and other structures should be effectively utilized, wherever practicable, in
screening noise from on-site construction activities. |
To reduce construction noise impact |
MTR / Contractor |
All works areas |
Construction phase |
Noise Control Ordinance (NCO) |
||||
S5.121-S5.122 and Table 5.22 |
The following quiet PME should be used: §
Pneumatic breaker (SWL=110dB(A)) §
Tracked Excavator Fitted with Hydraulic Breaker (SWL=110dB(A)) §
Truck Mixer (SWL=100dB(A)) §
Tracked Crane (SWL=101dB(A)) §
Dump Truck (SWL=103dB(A)) §
Tracked Excavator/Loader (SWL=105dB(A)) §
Dozer (SWL=111dB(A)) §
Road Roller (SWL=101dB(A)) |
To reduce construction noise impact |
MTR / Contractor |
Works Areas A, B, C, D, E, F, G, H, I, J, K, L, M, N, O, P,
Q, R, S, T, U, V, W, Y, Z, AA, AC, AE, AF, AG and AH |
Construction phase |
NCO |
||||
S5.123 - S5.124
|
Movable noise
barrier should be used for the following PME where practicable: § Mini backhoe § Breaker, mini-robot
mounted § Vibratory poker § Handheld breaker § Excavator § Grab § Tracked Crane |
To reduce construction noise impact |
MTR / Contractor |
Works Areas A, C and D |
Construction phase |
NCO |
||||
S5.125 |
Noise enclosure/acoustic shed should be used for
the following PME where practicable: § Air compressor § Concrete pump § Grout pump § Shotcrete pump |
To reduce construction noise impact |
MTR / Contractor |
Works Areas A, B, C, D, E, F, G, H, I, J, K, L, M, O, P, Q,
S, T, U, V and Z |
Construction phase |
NCO |
||||
S5.125 |
Acoustic enclosure should be used for enclosing drilling
jumbo as fully as possible. |
To reduce construction noise impact |
MTR / Contractor |
Works Areas B, C, F, H and J |
Construction phase |
NCO |
||||
S5.127 |
Silencer should be used for the ventilation fans. |
To reduce construction noise impact |
MTR / Contractor |
Works Areas A, B, C, D, E, F, H, J, L and P |
Construction phase |
NCO |
||||
S5.128 |
Noise insulating fabric should be applied where
practicable to cover the following PME: § Drill rig § Grab and chisel § Oscillator &
casings § Piling rig § Piling, large
diameter bored, reverse circulation drill § Piling, vibrating
hammer |
To reduce construction noise impact |
MTR / Contractor |
Works Areas A, B, C, D, E, G, L, M, N, O, Q, R, S, V |
Construction phase |
NCO |
||||
S5.130 |
Use of “Noise Insulating Cover” to cover the
mucking out points. |
To reduce construction noise impact |
MTR / Contractor |
Works Area L |
Construction phase |
NCO |
||||
S5.131 |
Use of temporary hoardings along the works
boundary. |
To reduce construction noise impact |
MTR / Contractor |
Works Areas B and D |
Construction phase |
NCO |
||||
S5.134-S5.136 |
Use of saw instead of mini-robot mounted
breaker and oscillator pile for removal of
superstructures |
To reduce construction noise impact |
MTR / Contractor |
Works Areas N, O and S |
Construction phase |
NCO |
||||
S5.137 |
Scheduling of construction works outside school
examination periods |
To reduce construction noise impact |
MTR / Contractor |
Works Areas G, J, K, L, N, O, P, Q, Y, U, V and AH |
Construction phase |
NCO |
||||
S5.193 |
Airborne construction noise monitoring should be
conducted in accordance with EM&A Manual to monitor the airborne noise
impact. |
To monitor airborne noise impact |
MTR / Contractor |
Proposed monitoring locations |
Construction phase |
NCO |
||||
Airborne Noise Impact (Operation Phase) |
|
|
|
|
|
|||||
S5.113 and Table 5.21 |
The maximum permissible sound power levels (Max SWLs)
for the fixed plant should be complied with during the selection of equipment
and mitigation measures. |
To comply with the noise criteria of Noise Control
Ordinance |
MTR / DDC |
MPV, NTV, PHV, SMV, KCV, NCV, MKV, WKV and WKT |
Detailed design and operation phases |
NCO |
||||
S5.140 |
Noise barrier should be erected as follow: § A 8m high barrier
along the access road on eastern side of SSS; and § 5.5m barrier along
western boundary facing Leung Uk Tsuen squats. |
To comply with the noise criteria of Noise Control
Ordinance |
MTR / DDC |
SSS |
Detailed design and operation phases |
NCO |
||||
S5.140 |
Installation
of 13m absorptive panels on both sides and full length of ERS. |
To comply with the noise criteria of Noise Control
Ordinance |
MTR / DDC |
ERS |
Detailed design and operation phases |
NCO |
||||
S5.196 |
Noise commissioning test is recommended to monitor the ground-borne
noise level complying with NCO. |
To monitor ground-borne noise impact |
MTR / Contractor |
Proposed monitoring locations |
Operation phase |
NCO |
||||
Ground-borne Noise Impact (Construction Phase) |
|
|
|
|
|
|||||
S6.82 |
Ground-borne construction noise monitoring should be conducted in
accordance with EM&A Manual to monitor the ground-borne noise
impact. |
To monitor ground-borne noise impact |
MTR / Contractor |
Proposed monitoring locations |
Construction phase |
NCO |
||||
S6.85 |
Construction groundborne noise measurement results should be used to
further update the ground-borne noise prediction where appropriate. |
To update the predicted ground-borne noise levels. |
MTR / Contractor |
TBM tunneling section |
Construction phase |
- |
||||
S6.83 |
Conduct tests of the FDL of the train to update the ground-borne noise
prediction and the recommended mitigation measures as necessary. |
To confirm the predicted ground-borne noise levels |
MTR |
- |
Prior to the final design of the trackform
and the extent of each type of trackform, and after the proposed train in
operation outside |
- |
||||
S6.84 |
Conduct vibration borehole testing at two carefully selected locations
along the proposed tunnel alignment to determine the LSR values under certain
geological conditions. The
ground-borne noise predictions and the recommendation on mitigation measures
should be updated as necessary. |
To confirm the predicted ground-borne noise levels |
MTR |
Proposed two locations |
Prior to the commencement of
construction works |
- |
||||
Ground-borne Noise Impact (Operation Phase) |
|
|
|
|
|
|||||
S6.87 |
Noise commissioning test is recommended to monitor the ground-borne
noise level complying with NCO. |
To monitor ground-borne noise impact |
MTR / Contractor |
Proposed monitoring locations |
Operation phase |
NCO |
||||
Landscape and Visual Impact (Construction Phase) |
|
|
|
|
|
|||||
Table 7.10 |
All existing
trees should be carefully protected during construction as far as possible in
accordance with ETWB TCW No. 29/2004 and 3/2006. |
To minimize landscape and visual impacts during
construction phase |
Contractor |
Works
areas |
Detailed design and construction phases |
EIAO-TM Annex 10, 18 ETWB TCW 2/2004 ETWB TCW 3/2006 |
||||
Trees should be
retained on site as far as possible. Should removal of trees be unavoidable
due to construction impacts, trees will be transplanted or felled depending on
stated criteria in the Tree Removal Applications to be submitted separately
in accordance with ETWBC 2/2004 and 3/2006. Wood resulting from
tree removal should be recycled as mulch or soil conditioner which could be
used within the Project or in other projects as much as possible. |
Contractor |
|||||||||
Control of
night-time lighting glare. |
Contractor |
|||||||||
Erection of
decorative screen hoarding to screen off undesirable views of the construction
site having consideration of safety and security. |
Contractor |
|||||||||
Reuse of
existing topsoil where possible for new planting areas within the project. |
Contractor |
|||||||||
Landscape and Visual Impact (Operation Phase) |
|
|
|
|
|
|||||
Table 7.11 |
Compensatory
tree planting should be incorporated into the proposed Project where space is
available |
To minimize landscape and visual impacts during operation
phase |
MTR |
Works
areas |
Detailed design and operation phases |
EIAO-TM Annex 10, 18 ETWB TCW 2/2004 ETWB TCW 3/2006 |
||||
|
Landscape and
visual enhancement treatments |
MTR |
||||||||
|
Compensatory
habitat proposal for natural stream course at SSS |
MTR |
||||||||
|
Reinstatement of
works area in |
MTR |
||||||||
|
Tall buffer tree
planting should be incorporated provide screening to ventilation buildings,
engineering structures and associated facilities. |
MTR |
||||||||
|
Roof greening to mitigate
the visual impact of VB on the VSRs at high level. |
MTR |
||||||||
|
Vertical greening
would be incorporated where practicable to visually soften the façade of
ventilation building and/or noise barrier |
MTR |
||||||||
|
Incorporation of aesthetically pleasing streetscape design
which would be responsive to adjacent landscape context. |
MTR |
||||||||
Roadside amenity
trees to enhance the landscape and visual quality of the existing and
proposed road. |
MTR |
|||||||||
|
Reinstatement of
disturbed areas to match adjacent area or to condition to suit future
landuse. |
MTR |
||||||||
|
Aesthetically
pleasing design as regard to the form, material and finishes shall be
incorporated to all buildings, engineering structures and associated
infrastructure facilities so as to blend in the buildings and structures to
the adjacent landscape and visual context. |
MTR |
||||||||
|
Control of
Operation Night-time Glare |
MTR |
||||||||
|
Incorporation of
aesthetically pleasing design to boundary fence so as to blend in the
structure to the adjacent landscape and visual context. |
MTR |
||||||||
|
The scale,
location, disposition and design of the ventilation shafts at WKCD would be
further reviewed and submitted to relevant parties (e.g. WKCDA and PlanD) for
agreement. |
MTR |
||||||||
Cultural Heritage Impact |
|
|
|
|
|
|||||
S8.100 – S8.103 |
l
Conduct further investigation (a minimum of 18 trial
pits, 1m x 1.5m) to confirm any archaeological remains exist in the
inaccessible areas (NOL/ERL/300/C/XRL/ENS/M55/303-
304 & 306-307). If archaeological data collected from these 18 test
pits is insufficient to ascertain the archaeological potential of the inaccessible
areas, additional test pits should be conducted l
Conduct rescue excavation
to preserve archaeological remains by detailed records if found (NOL/ERL/300/C/XRL/ENS/M55/307) |
To confirm any archaeological remains exist in the
inaccessible areas and to preserve archaeological remains if any |
MTR |
Proposed rescue excavation area in SSS and other
archaeological deposit areas identified in the further archaeological
investigation |
Prior to construction phase |
Antiquities and Monuments Ordinance |
||||
S8.103 |
Conduct archaeological watching brief
during construction works at TUW for identification of any historical finds
during construction phase |
To identify any
historical finds in the works area |
MTR |
TPP |
Construction phase |
Antiquities and
Monuments Ordinance |
||||
S8.104 |
Conduct regular site audit during the
construction of barging point to confirm that no excavation works is
conducted at Lung Kwu Sheung Tan archaeological deposit area. |
To avoid direct impact |
MTR |
LKST barging point and
associated access road |
Construction phase |
Antiquities and Monuments Ordinance |
||||
S8.105 |
Restriction of works boundary of TPP to be
extended to relics discovered area outside TPP. |
To avoid direct impact |
MTR |
TPP |
Construction phase |
Antiquities and Monuments Ordinance |
||||
S8.107, S8.128 |
Avoid works areas at the sites of the
identified built heritage structures as far as practicable. Identified earth shines within works boundary
of SSS and TPP will be relocated by local villagers prior to commencement of
construction works at SSS and TPP. |
To avoid direct impact |
MTR |
Earth shines (NHL-04,TKP-02 and LET-07) |
Prior to construction phase |
EIAO-TM |
||||
S8.109, S8.125 |
Vibration
monitoring
at § Prior to
commencement of construction works, the location and installation of the
monitoring stations should be discussed and agreed with AMO, Hong Kong Institution for Promotion of Chinese Culture (the “NPO”,
selected organization for the Revitalisation Scheme), the Commissioner for
Heritage’s Office
and relevant parties before installation. § Compliance
monitoring of vibration limits should be conducted and reported as a
requirement of EM&A programme. |
To monitor vibration impacts on the identified vibration
sensitive historical buildings |
MTR |
Ex-Lai
Chi Kok Hospital |
Before construction phase; Construction phase |
EIAO-TM |
||||
S8.110, S8.126 |
§ A further condition
survey and appropriate consolidation works (e.g. installation of temporary
propping or reinforced timber beam to maintain the stability of structure
etc.), if required, will be carried out on Blocks P Q, W and the inaccessible
area of LCKH prior to construction. It should be discussed and agreed in advance
with AMO, NPO, the Commissioner for Heritage’s Office and relevant parties, |
To minimize vibration impacts on the identified vibration
sensitive historical buildings |
MTR |
Ex-Lai
Chi Kok Hospital |
Detailed design |
EIAO-TM |
||||
S8.112, S8.127 |
§ If consent is given by the property owner, a condition survey will be
carried out at Cheung Yuen prior to the commencement of works in SSS. The survey should be discussed and
agreed in advance with AMO and property owner prior to commencement of
survey. |
To minimize
vibration impacts on the identified vibration sensitive historical buildings |
MTR |
Cheung Yuen |
Prior to
construction phase |
EIAO-TM |
||||
S8.112, S8.127 |
§ If consent is given
by the property owner, vibration monitoring at LET-06 (Cheung Yuen) will be
conducted when excavation works are being conducted within 50m radius from
the house. The monitoring
location should be discussed and agreed with AMO and property owner before
installation. |
To monitor vibration impacts on the identified vibration
sensitive historical buildings |
MTR |
Cheung Yuen |
Construction phase |
EIAO-TM |
||||
S8.113, S8.124 |
§ Control of
vibration levels from the proposed blasting and excavation activities within
a peak particle velocity (ppv) limit of 25mm/s to prevent potential vibration
impact to all identified built heritage resources. |
To minimize vibration impacts on the identified vibration
sensitive historical buildings |
MTR |
All works area where blasting and excavation activities are
involved |
Construction phase |
EIAO-TM |
||||
S8.114 - S8.115 |
§ Use of sensibly
designed screen hoardings for reducing the potential visual impact. |
To minimize visual impacts |
MTR |
All identified heritage buildings in all works areas |
Detailed design and construction phase |
EIAO-TM |
||||
Land Contamination Impact |
|
|
|
|
|
|||||
S9.28
– S9.33 |
Remediation of Contaminated Soil § After
excavation, confirmation sampling and testing shall be conducted from the
sidewalls and at base of the excavations to ensure complete excavation of
contaminated soils. § Bioremediation (biopiling) / ex-situ chemical
oxidation are proposed to remediate the
contaminated soil recorded in Sites H and Q. Remediation Report(s) (RR) for
contaminated works area(s) should be prepared by the Land Contamination
Specialist to detail the remediation process and demonstrate that
contaminated soils are all removed, properly handled and disposal of. The remediated soil should be reused
on site to minimise the waste disposal. |
To remediate
contaminated soil |
Contractor |
Sites
H and Q |
Site remediation |
“Guidance Notes for Investigation and Remediation of Contaminated
Sites of Petrol Filling Stations, Boatyards and Car Repair /Dismantling
Workshop“ |
||||
S9.35(i) |
For
construction works of the alignment close to Ngau Tam Mei Landfill § As a
general precautionary measure, visual inspection of excavated materials
should be conducted to screen soil for signs of contamination (e.g.
discoloration, stains and odour).
The inspection process should also be assisted by a photo ionization
detector (PID) for volatile organics. If suspected materials are encountered
during tunnel boring, sampling and testing for the parameters recommended in Table 6.1 of CAP should be
undertaken to verify any contamination.
The suspected soil bored out during excavation and tunnel boring
should be temporary stockpiled and if laboratory analysis indicated
exceedance of relevant RBRG levels, remediation works, should be undertaken
depending on the quantity and quality of contaminated soil identified. |
Acting
as a general precautionary measure to screen soil for signs of contamination
during tunnel boring works under/close to Ngau Tam Mei Landfill |
MTR/Contractor |
Within the Landfill
Boundary where signs of contamination is identified |
During Tunnel Boring within Ngau Tam Mei Landfill Boundary Section |
“Guidance Note for Contaminated Land Assessment and Remediation” “Guidance Manual for Use of Risk-based Remediation Goals for
Contaminated Land Management |
||||
S9.35(ii) |
For construction works at CLP transformer
station at Lai Cheung Road and Petrol Filling Station at 82 Tai Kok Tsui Road § As a
general precautionary measure, visual inspection of excavated materials
should be conducted to screen soil for signs of contamination (e.g.
discoloration, stains and odour).
The inspection process should also be assisted by a photo ionization
detector (PID) for volatile organics. If suspected materials are encountered
during tunnel boring, further sampling and testing should also be undertaken
to verify any contamination. The soil bored out during excavation and tunnel
boring should be temporary stockpiled and if laboratory analysis indicated
exceedance of relevant RBRG levels, remediation works, should be undertaken
depending on the quantity and quality of contaminated soil identified. |
Acting as a general precautionary measure to screen
soil for signs of contamination during tunnel boring/ excavation at CLP transformer station at |
MTR/Contractor |
Area close to CLP
transformer station at |
During Tunnel Boring/ excavation works near CLP
transformer station at Lai Cheung Road and Petrol Filling Station at 82 Tai
Kok Tsui Road |
“Guidance Note for Contaminated Land Assessment and Remediation” “Guidance Manual for Use of Risk-based Remediation Goals for
Contaminated Land Management |
||||
S9.35
(iii) |
For sites with contamination identified
(Site H and Site Q) the following environmental mitigation measures should be
undertaken during the course of the site remediation: § Excavation
profiles must be properly designed and executed with attention to the
relevant requirements for environment, health and safety; § Excavation
should be carried out during dry season as far as possible to minimise
contaminated runoff from contaminated soils; § Supply
of suitable clean backfill material is needed after excavation; § The
chemical oxidant proposed (RegenOxTM) as a contaminant mass reduction
technology. Comprises a solid oxidant complex (sodium percarbonate/catalytic
formulation) and an activator complex (a composition of ferrous salt embedded
in a micro-scale catalyst gel).
These chemical will be securely stored, separately and way from
sources of ignition or oxidizable items.
Handling will & will be undertaken by persons specifically trained
and wearing appropriate PPE. § Vehicles
containing any excavated materials should be suitably covered to limit
potential dust emissions or contaminated wastewater run-off, and truck bodies
and tailgates should be sealed to prevent any discharge during transport or
during wet conditions; § Speed
control for the trucks carrying contaminated materials should be enforced;
and § Vehicle
wheel and body washing facilities at the site’s exist points should be
established and used. |
To
minimise the potentially adverse environmental impacts arising from the
handling of potentially contaminated materials. |
Contractor |
Sites
H and Q /during transportation |
Site remediation
and prior to construction phase |
Waste Disposal Ordinance Waste Disposal (Chemical Waste) (General) Regulation Water Pollution Control Ordinance Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes Occupation Safety
and Health Ordinance (OSHO) (Chapter 509) and its subsidiary Regulations |
||||
S9.35(iv) |
In order to
minimise the potentially adverse effects on health and safety of construction
workers during the course of site remediation, the Occupation Safety and
Health Ordinance (OSHO) (Chapter 509) and its subsidiary Regulations should
be followed by all site personnel working on the site at all times. In
addition, the following basic health and safety measures should be
implemented as far as possible: § Set up a
list of safety measures for site workers; § Provide
written information and training on safety for site workers; § Keep a
log-book and plan showing the contaminated zones and clean zones; § Maintain
a hygienic working environment; § Avoid
dust generation; § Provide
face and respiratory protection gear to site workers; § Provide
personal protective clothing (e.g. chemical resistant jackboot, liquid tight
gloves) to site workers; and § Provide
first aid training and materials to site workers. |
To
minimise the potentially adverse effects on health and safety of construction
workers during the course of site remediation |
Contractor |
Sites
H and Q |
Site remediation
and prior to construction phase |
|||||
9.35(v) |
For Areas
Feasible or Infeasible for On-Site Inspection and Site Investigation (i) Phase 2
supplementary SI works § Upon
site access is granted, site inspection should be carried out to ascertain
any contaminative sources and hotspot of contamination within the site. § The
sampling and testing schedule as recommended in the approved CAP should then
be updated based on respective site
situation and the number of sampling locations may be significantly reduced.
A revised CAP should then be submitted to EPD
for endorsement. § For supplementary CARs and RAP(s),
upon completion of SI and laboratory testing, supplementary CARs
should be submitted to EPD for endorsement. If contamination is identified, RAP(s) should also be submitted to EPD for
endorsement. § The
revised CAPs and supplementary CARs and /or RAP(s)
should be submitted in separate packages for different works area depending
on the schedule of land resumption and the commencement of construction works
for each works area. § RR(s) should be submitted to demonstrate
completion of remediation works before construction work starts at the site. (ii) WSW § According to WSW EP Condition 3.14, the Project Proponent of the WSW
development shall prepare and submit CAR/RAP to EPD within 2 months after
commencement of construction of the WSW development and the recommendations
in the endorsed CAR/RAP shall be fully implemented before the commencement of
any construction works that may disturb the ground of the relevant sites. § This project will ensure that the completion of remediation works
before the construction works at contaminated areas start. |
(i) To
identify areas with land contamination concern, report laboratory results and
propose remediation measures if necessary. (ii) To
ensure remediation works have been undertaken to before the commencement of
any construction works of the Project that may disturb the ground of the
south-western portion of the MPV. |
MTR/
Contractor |
Areas Infeasible
for On-Site Inspection and Site Investigation and WSW |
After
land resumption and prior to the construction works commencement at
respective sites |
“Guidance Note for Contaminated Land Assessment and Remediation” “Guidance Manual for Use of Risk-based Remediation Goals for
Contaminated Land Management The Proposed Comprehensive Development at Wo Shang Wai (WSW), Yuen
Long Environmental Impact Assessment Environmental Permit (EP No.:
EP-311/2008) |
||||
Waste Management Implications (Construction Phase) |
|
|
|
|
|
|||||
S10.107 |
Recommendations
for good site practices: § Prepare
a Waste Management Plan approved by the Engineer/Supervising Officer of the
Project based on current practices on construction sites; § Training
of site personnel in, site cleanliness, proper waste management and chemical
handling procedures; § Provision
of sufficient waste disposal points and regular collection of waste; § Appropriate
measures to minimize windblown litter and dust during transportation of waste
by either covering trucks or by transporting wastes in enclosed containers; § Regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors; and § Separation
of chemical wastes for special handling and appropriate treatment. |
To
implement good site practice for handling, sorting reuse and recycling of
C&D materials |
Contractor |
All
works areas |
Construction
phase |
Waste Disposal Ordinance (Cap. 354) Land (Miscellaneous Provisions) Ordinance (Cap. 28) ETWB TC(W) No.31/2004 |
||||
S10.108 |
Recommendations for waste reduction measures: § Sorting
of demolition debris and excavated materials from demolition works to recover
reusable/ recyclable portions (i.e. soil, broken concrete, metal etc.); § Segregation
and storage of different types of waste in different containers, skips or
stockpiles to enhance reuse or recycling of materials and their proper
disposal; § Encourage
collection of aluminium cans by providing separate labelled bins to enable
this waste to be segregated from other general refuse generated by the
workforce; § Proper
storage and site practices to minimize the potential for damage or
contamination of construction materials; § Plan and
stock construction materials carefully to minimize amount of waste generated
and avoid unnecessary generation of waste; and § Training
should be provided to workers about the concepts of site cleanliness and
appropriate waste management procedures, including waste reduction, reuse and
recycle. |
To
implement on-site sorting facilitating reuse and recycling of materials as
well as proper disposal of waste |
Contractor |
All
works areas |
Construction
phase |
Waste Disposal Ordinance (Cap. 354) Land (Miscellaneous Provisions) Ordinance (Cap. 28) |
||||
S10.109 |
The Contractor should prepare and implement a Waste
Management Plan (WMP) as a part of the Environmental Management Plan (EMP) in
accordance with ETWB TCW No. 19/2005 which describes the arrangements for
avoidance, reuse, recovery, recycling, storage, collection, treatment and
disposal of different categories of waste to be generated from the
construction activities. |
To
keep trace of the generation, minimization, reuse and disposal of C&D
materials in the Project |
Contractor |
All
works areas |
Construction
phase |
ETWB TCW No. 19/2005 |
||||
S10.112 |
Storage of materials on site may induce adverse
environmental impacts if not properly managed, recommendations to minimise
the impacts include: § Waste,
such as soil, should be handled and stored well to ensure secure containment,
thus minimising the potential of pollution; § Maintain
and clean storage areas routinely; § Stockpiling
area should be provided with covers and water spraying system to prevent
materials from wind-blown or being washed away; and § Different
locations should be designated to stockpile each material to enhance reuse. |
To
minimise potential impacts of waste storage and enhance reusable volume |
Contractor |
All
work areas |
Construction
phase |
- |
||||
S10.113 |
Waste
hauliers must hold a valid permit for the collection of waste as stipulated
in their permits. Removal of waste should be done in a timely manner. |
To collect and remove waste
generated |
Contractor |
All
work areas |
Construction
phase |
- |
||||
S10.114-115 |
Implementation of trip-ticket system to monitor
waste disposal and control fly-tipping. Set up warning signs at vehicular access points
reminding drivers of designated disposal sites and penalties of an offence. Installation
of close-circuited television at access points of vehicles to monitor and
prevent illegal dumping. |
To monitor disposal of waste and
control fly-tipping |
Contractor |
All
work areas |
Construction
phase |
ETWB TC(W) No.31/2004 |
||||
S10.117 |
Recommendations
for excavated materials within works areas: § Several
ramps should be used for transportation of different materials as far as
practicable (at SSS/ERS site, both soft and hard materials could be generated
with the provision of three ramps, each of them can
be used for single material for primary separation). Each ramp should be used for
transportation of a single material as far as practicable. § If a
conveyor system is used, materials should be transported separately on the
belts, it is therefore proposed that more than one conveyor belt should be
installed if possible. If more
than one material is needed to be transported on a single belt, each material
should be stockpiled separately once they are removed from the excavation
face to the ground and the belt should operate at different times with
different materials as far as practicable. § Enclosure
should also be provided for the conveyor belt, as far as practicable to
minimize the of dust generation. § Different
locations should be designated for each material during stockpiling. Stockpiling may be needed when the
conveyor system is under constraint or when the spoil could not be
transported away from works area immediately after excavation. Cover should
be provided to dusty stockpiles to avoid the materials from being wind-blown
or flushed away by water. It is
expected that water spraying system should also be equipped to moisten the
materials. |
To
mitigate and minimize the potential impacts from the storage and
transportation of materials within works areas |
Contractor |
All
works areas |
Construction
Phase |
- |
||||
S10.119 |
Wet spoil generated from TBM construction,
construction of bored piles and D-wall should be properly handled before
disposal to Taishan and Fill Banks respectively for reuse in other
projects. Dry materials
should be mixed with the wet spoil or by the use of lime to reduce water
content where applicable. |
To
minimise impacts to disposal outlet from reception of wet spoil |
Contractor |
All
works areas |
Construction
phase |
- |
||||
S10.120 |
Wheelwash facilities should be provided before the
trucks leave the works area. |
To
minimise dust impact |
Contractor |
All
works areas |
Construction
phase |
- |
||||
S10.121 |
The Contractor should ensure the on-site separation
from inert portion. The waste delivered to landfill should not contain
any free water or have water content more than 70% by weight. The haulier must ensure suitable amount of waste
would be loaded on different types of trucks used. A one-week notice should be given to EPD with
information on Contractor’s name and respective contact details. |
To
meet the requirement for disposal at landfill |
Contractor
and Waste haulier |
All
works areas |
Construction
phase |
- |
||||
S10.125 |
This
will generally follow the PNAP 25 in handling of dredged/excavated
sediment. The dredged / excavated
sediments would be loaded onto barges and transported to existing designated
disposal sites allocated by the MFC according to their levels of
contamination, as presented below: §
For Type 1 sediment, the sediments will be
excavated/dredged and transport to designated CEDD
Facilities, typically at South Cheung Chau and/or Ninepin. §
For Type 2 sediment, the sediments will be dredged/excavated
and transport to designated CEDD Facilities,
typically at East Sha Chau for confined marine disposal. §
For Type 3 sediment, it would require
special treatment/disposal before confined marine disposal at CEDD
Facilities, typically at East Sha Chau.
In order to have the least potential of loss of contaminants to the
marine environment, containment of the sediments in geosynthetic containers
is proposed when transporting the sediment. Field
trials are recommended to be undertaken during the detailed design stage to
establish the optimum handling method for this approach. The details of the
disposal methodology could therefore be confirmed during the detailed design
stage, prior to construction. |
To
dispose sediment in an authorized and least impacted way |
Contractor |
All
works areas with sediments concern |
Detailed
Design and Construction phase |
PNAP 252 |
||||
S10.126 |
The
basic requirements and procedures for dredged / excavated sediment disposal
specified under PNAP 252 shall be followed. |
To
dispose sediment in an authorized and least impacted way |
Contractor |
All
works areas with sediments concern |
Construction
phase |
PNAP 252 |
||||
S10.127 |
The
Project Proponent will agree in advance with MFC of CEDD on the site
allocation by submitting a Construction & Demolition Material Management
Plan. The final disposal sites and arrangement will be determined by the MFC
and a dumping permit will be obtained from the DEP prior to the commencement
of the dredging and excavation works.
|
To
determine the best handling and disposal option of the sediments. |
MTR/
Contractor |
All
works areas with sediments concern |
Detailed
Design and Construction phase |
PNAP 252; Dumping at Sea Ordinance |
||||
S10.128 |
The
contractor for the dredging/ excavation works shall apply for the site
allocations of marine sediment disposal based on the prior agreement with
MFC/CEDD. The contractor shall
apply for all necessary permits from relevant authorities for the disposal of
dredged / excavated sediment. |
To
dispose the sediments in an authorized way. |
Contractor |
All
works areas with sediments concern |
Construction
phase |
PNAP 252; Dumping at Sea
Ordinance |
||||
S10.129 |
If
temporary stockpiling of sediments is necessary, the sediment should be
covered by tarpaulin and earth bunds or sand bag barriers should be provided
on site to prevent leachate from entering the drains and surrounding water
bodies. The stockpiling areas
should be completely paved or covered by lining avoiding contaminating the
soil or groundwater underneath. |
To
prevent the cross contamination of surrounding soils and water bodies |
Contractor |
All
works areas with sediments concern |
Construction
phase |
Waste Disposal
Ordinance, |
||||
S10.130 |
The
dredged / excavated sediment should be transported by covering trucks to
designated barging points. The
barge transporting the sediments to the designated disposal site should be
equipped with tight fitting seals to prevent leakage. Besides, the barge should not be
filled to a level that would cause overflow of materials or laden water
during loading or transportation. |
To
prevent overflowing of sediments to the surrounding area and water bodies |
Contractor |
All
works areas with sediments concern / trucks / barges |
Construction
phase |
Waste Disposal
Ordinance Water Pollution Control Ordinance |
||||
S10.131 |
Loading of the dredged / excavated sediment to
the barge should be controlled to avoid splashing and overflowing of the
sediment slurry to the surrounding water. |
To
prevent overflowing of sediments to the surrounding area and water bodies |
Contractor |
Barging
points |
Construction
phase |
Waste Disposal
Ordinance, |
||||
S10.132 |
In order to minimise the potential odour
emissions during the dredging / excavation operation and transportation of
the sediment, the dredged / excavated sediment placed on barges should be
properly covered as far as practicable.
Requirement of the Air Pollution
Ordinance (Construction Dust) Regulation, where relevant, should be
adhered to during the construction phase of the Project. |
To
minimise dust and odor impacts to surrounding environment |
Contractor |
All
works areas with sediments concern / Barging points |
Construction
phase |
Air Pollution Ordinance
(Construction Dust) Regulation |
||||
S10.134 |
Workers should wear protective gloves when
carrying out the dredging / excavation works. Adequate washing and cleaning
facilities should be provided on site. |
To
minimise the exposure to the contaminated sediments |
Contractor |
All
works areas with sediments concern |
Construction
phase |
Occupational Safety &
Health Ordinance |
||||
S10.135 |
For allocation of sediment disposal site and
application of marine dumping permit, another proposal for sampling and
chemical testing of the sediment will be prepared and submitted to the EPD
for approval following the procedures in PNAP 252. The approved detailed
sampling and chemical testing will be carried out prior to the commencement
of the dredging/excavation activities to confirm the sediment disposal
method. The contamination levels of the marine sediment to be dredged /
excavated have to be analysed and recorded. After carrying out the sampling
and testing, a Sediment Quality Report (SQR) will be prepared for EPD
approval as required under the Dumping
at Sea Ordinance to agree and confirm the quantities and extent of the
contamination of the sediments prior to the dredging/ construction contract
being tendered. The SQR will
include the sampling details, the chemical testing results, quality control
records, proposed classification and delineation of sediment according to the
requirements of the Appendix A of PNAP 252. |
To
analyse the sediments quality and determine the best disposal option |
Contractor |
All
works areas with sediments concern |
Construction
phase |
PNAP 252; Dumping at Sea Ordinance |
||||
S10.136 |
If chemical wastes are produced at the
construction site, the Contractor would be required to register with the EPD
as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes. Containers used for storage of
chemical waste should : § Be
compatible with the chemical wastes being stored, maintained in good
condition and securely sealed; § Have a
capacity of less than 450 litres unless the specifications have been approved
by EPD; and § Display
a label in English and Chinese in accordance with instructions prescribed in
Schedule 2 of the Waste Disposal
(Chemical Waste) (General) Regulation. |
To
properly store the chemical waste within works areas |
Contractor |
All
works areas |
Construction
phase |
Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes |
||||
S10.137 |
The
chemical storage areas should: § Be
clearly labelled to indicate corresponding chemical characteristics of the
chemical waste and used for storage of chemical waste only; § Be
enclosed on at least 3 sides; § Have an
impermeable floor and bunding, of capacity to accommodate 110% of the volume
of the largest container or 20% by volume of the chemical waste stored in
that area, whichever is the greatest; § Have
adequate ventilation; § Be
covered to prevent rainfall from entering; and § Be
properly arranged so that incompatible materials are adequately separated. |
To
prepare appropriate storage areas for chemical waste at works areas |
Contractor |
All
works areas |
Construction
phase |
Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes |
||||
S10.138 |
Lubricants, waste oils and other chemical wastes
would be generated during the maintenance of vehicles and mechanical
equipments. Used lubricants
should be collected and stored in individual containers which are fully labelled
in English and Chinese and stored in a designated secure place. |
To
clearly label the chemical waste at works areas |
Contractor |
All
works areas |
Construction
phase |
Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes |
||||
S10.139 |
A trip-ticket system should be operated in
accordance with the Waste Disposal
(Chemical Waste) (General) Regulation to monitor all movements of
chemical waste. The Contractor
should employ a licensed collector to transport and dispose of the chemical
wastes, to either the approved CWTC at Tsing Yi, or another licensed
facility, in accordance with the Waste
Disposal (Chemical Waste) (General) Regulation. |
To
monitor the generation, reuse and disposal of chemical waste |
Contractor |
All
works areas |
Construction
phase |
Waste Disposal (Chemical Waste) (General) Regulation |
||||
S10.140 |
General refuse should be stored in enclosed bins or
compaction units separate from C&D materials and chemical waste. A
reputable waste collector should be employed by the contractor to remove
general refuse from the site, separately from C&D materials and chemical
wastes. |
To
properly store and separate from other C&D materials for subsequent
collection and disposal |
Contractor |
All
works areas |
Construction
phase |
- |
||||
S10.141 |
The recyclable component of general refuse, such as
aluminium cans, paper and cleansed plastic containers should be separated
from other waste. Provision and
collection of recycling bins for different types of recyclable waste should
be set up by the Contractor. The
Contractor should also be responsible for arranging recycling companies to
collect these materials. |
To
facilitate recycling of recyclable portions of refuse |
Contractor |
All
works areas |
Construction
phase |
- |
||||
S10.142 |
The Contractor should carry out a training programme
for workers in avoiding, reducing, reusing and recycling of materials
generation. Posters and leaflets
advising on the use of the bins should also be provided in the sites as
reminders. |
To
raise workers’ awareness on recycling issue |
Contractor |
All
works areas |
Construction
phase |
- |
||||
Waste Management Implications (Operation Phase) |
|
|
|
|
|
|||||
S10.146-10.147 |
Chemical waste: §
The
requirements stipulated in the Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes should be followed in handling of chemical waste as in construction phase. § A trip-ticket system should be operated in
accordance with the Waste Disposal (Chemical Waste) (General) Regulation to monitor all movements of chemical wastes
which would be collected by a licensed collector to a licensed facility for
final treatment and disposal. § The recommendations proposed for the
mitigation of impacts from chemical waste in construction phase should also
be followed (refer to S10.104- S10.106). |
To
avoid environmental impacts in handling, storage and disposal of chemical
waste |
MTR |
Ventilation
buildings, SSS and WKT |
Operation
phase |
Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes Waste Disposal (Chemical
Waste) (General) Regulation |
||||
S10.148-S10.149 |
General refuse: § Provide recycling bins at designated areas
for proper recycling of papers, aluminium cans and plastics bottles. § Separation from other waste types and
collected by licensed collectors at daily basis to minimize the potential
impacts from odour and vermin. |
To
separate general refuse from other waste types and proper disposal of the
refuse |
MTR |
Ventilation
buildings, SSS and WKT |
Operation
phase |
|
||||
S10.150 |
Industrial waste: § Separation of reusable components like
steel before collection by licensed collector |
To
recycle useful materials from industrial waste and proper disposal |
MTR |
Ventilation
buildings, SSS and WKT |
Operation
phase |
|
||||
Water Quality Impact (Construction Phase) |
|
|
|
|
|
|||||
S11.128
- S11.153 |
Construction site run-off and general construction activities: § The mitigation measures as
outlined in the ProPECC PN 1/94 Construction Site Drainage should be adopted
where applicable. |
To
control water quality impact from construction site runoff and general
construction activities |
MTR
/ Contractor |
All works areas |
Construction phase |
EIAO-TM, WPCO |
||||
S11.154 |
Groundwater seepages from uncontaminated area: § In case
seepage of uncontaminated groundwater occurs, groundwater should be pumped
out from the works areas and discharged into the storm system via silt
removal facilities. Uncontaminated
groundwater from dewatering process should also be discharged into the storm
system via silt traps. |
To
control water quality impact from groundwater from uncontaminated area |
MTR
/ Contractor |
All works areas |
Construction phase |
EIAO-TM, WPCO, |
||||
S11.155 |
As the
proposed WKT is near the |
To
control water quality impact from groundwater from uncontaminated area |
MTR
/ Contractor |
WKT |
Construction phase |
EIAO-TM, WPCO, |
||||
S11.156 |
To
monitor the tide and groundwater relationship, it is recommended to install
groundwater level loggers at the nearest tidal areas (i.e. near Mai Po). |
To
monitor the groundwater level |
MTR
/ Contractor |
Mai Po |
Construction phase |
EIAO-TM, WPCO, |
||||
S11.157 - S11.158 |
Site Runoff or Groundwater from contaminated areas: § No
directly discharge of groundwater from contaminated areas should be
adopted. § Prior to
any excavation works within the potentially contaminated areas, the baseline
groundwater quality in the areas should be reviewed based on the past
relevant site investigation data and any additional groundwater quality
measurements to be performed with reference to Guidance Note for Contaminated Land Assessment and Remediation
and the review results should be submitted to EPD for examination. If the
review results indicated that the groundwater to be generated from the
excavation works would be contaminated, this contaminated groundwater should
be either properly treated or properly recharged into the ground in compl § If
wastewater treatment is to be deployed for treating the contaminated
groundwater, the wastewater treatment unit shall deploy suitable treatment
processes (e.g. oil interceptor / activated carbon) to reduce the pollution
level to an acceptable standard and remove any prohibited substances (such as
TPH) to an undetectable range. § All
treated effluent from the wastewater treatment plant shall meet the
requirements as stated in TM-DSS and should be either discharged into the
foul sewers or tankered away for proper disposal. § If
deployment of wastewater treatment is not feasible for handling the
contaminated groundwater, groundwater recharging wells should be installed as
appropriate for recharging the contaminated groundwater back into the ground.
The recharging wells should be selected at places where the groundwater
quality will not be affected by the recharge operation as indicated in
section 2.3 of the TM-DSS. The
baseline groundwater quality should be determined
prior to the selection of the recharge wells, and submit a working plan to
EPD for agreement. Pollution
levels of groundwater to be recharged shall not be higher than pollutant
levels of ambient groundwater at the recharge well. Groundwater monitoring
wells should be installed near the recharge points to monitor the
effectiveness of the recharge wells and to ensure that no likelihood of
increase of groundwater level and transfer of pollutants beyond the site
boundary. Prior to recharge, free products should be removed as necessary by
installing the petrol interceptor.
The Contractor should apply for a discharge licence under the WPCO
through the Regional Office of EPD for groundwater recharge operation or
discharge of treated groundwater. |
To control water quality impact from contaminated
groundwater |
MTR
/ Contractor |
Excavation areas where contaminated ground-water is found |
Construction phase |
EIAO-TM, WPCO, TM-DSS |
||||
S11.128 - S11.136, S11.160 |
Barging points: Mitigation
measures for control water quality impact from surface run-off should be
applied. The
following good site practices should also be adopted: § all
vessels should be sized so that adequate clearance is maintained between
vessels and the seabed in all tide conditions, to ensure that undue turbidity
is not generated by turbulence from vessel movement or propeller wash § all
hopper barges should be fitted with tight fitting seals to their bottom
openings to prevent leakage of material § construction
activities should not cause foam, oil, grease, scum, litter or other
objectionable matter to be present on the water within the site § loading of
barges and hoppers should be controlled to prevent splashing of material into
the surrounding water. Barges or
hoppers should not be filled to a level that will cause the overflow of
materials or polluted water during loading or transportation |
To control water quality impact from barging point |
MTR
/ Contractor |
All barging Points |
Construction phase |
EIAO-TM, WPCO |
||||
S11.161 |
Effluent discharge: There is a need to
apply to EPD for a discharge licence for discharge of effluent from the
construction site under the WPCO. The discharge quality should meet the
requirements specified in the discharge licence. Minimum distances of 100 m
should be maintained between the discharge points of construction site
effluent and the existing seawater intakes. If monitoring of the treated
effluent quality from the works areas is required during the construction
phase of the Project, the monitoring should be carried out in accordance with
the WPCO license which is under the ambit of regional office (RO) of EPD. |
To
control water quality impact from effluent discharge from construction site |
MTR
/ Contractor |
All works areas |
Construction phase |
EIAO-TM, WPCO |
||||
S11.162 |
Accidental spillage of chemicals: Contractor
should register as a chemical waste producer if chemical wastes would be
produced from the construction activities. The Waste Disposal Ordinance (Cap
354) and its subsidiary regulations in particular the Waste Disposal
(Chemical Waste) (General) Regulation should be observed and complied with
for control of chemical wastes. |
To control water quality impact from accidental chemical
spillage |
MTR
/ Contractor |
All works areas |
Construction phase |
EIAO-TM, WPCO, WDO |
||||
S11.163 |
Any
service shop and maintenance facilities should be located on hard standings
within a bunded area, and sumps and oil interceptors should be provided.
Maintenance of vehicles and equipment involving activities with potential for
leakage and spillage should only be undertaken within the areas appropriately
equipped to control these discharges. |
To control water quality impact from accidental chemical
spillage |
MTR
/ Contractor |
All works areas |
Construction phase |
EIAO-TM, WPCO, WDO |
||||
S11.164 |
Disposal
of chemical wastes should be carried out in compl § Suitable
containers should be used to hold the chemical wastes to avoid leakage or
spillage during storage, handling and transport. § Chemical
waste containers should be suitably labelled, to notify and warn the personnel
who are handling the wastes, to avoid accidents. § Storage
area should be selected at a safe location on site and adequate space should
be allocated to the storage area. |
To control water quality impact from accidental chemical
spillage |
MTR
/ Contractor |
All works areas |
Construction phase |
EIAO-TM, WPCO, WDO |
||||
S11.165 |
Surface construction works at or in close proximity of watercourses or
seafront: § The
proposed surface construction works should be carried out in dry season as
far as practicable where the flow in the river channel or stream is low. § The use
of less or smaller construction plants may be specified to reduce the
disturbance to the riverbed or pond deposits. § Temporary
sewerage system should be designed to prevent wastewater from entering the
river, streams and sea. § Temporary
storage of materials (e.g. equipment, filling materials, chemicals and fuel)
and temporary stockpile of construction materials should be located well away
from any water courses during carrying out of the construction works. § Stockpiling
of construction materials and dusty materials should be covered and located
away from any water courses. § Construction
debris and spoil should be covered up and/or disposed of as soon as possible
to avoid being washed into the nearby water receivers. § Construction
activities, which generate large amount of wastewater, should be carried out
in a distance away from the waterfront, where practicable. § Mitigation
measures to control site run-off from entering the nearby water environment
should be implemented to minimize water quality impacts. Surface channels should be provided
along the edge of the waterfront within the work sites to intercept the
run-off. § Construction
effluent, site run-off and sewage should be properly collected and/or
treated. § Any
works site inside the water courses should be temporarily isolated. The water flow should be temporarily
diverted to downstream by using PVC pipes, steel arrays in concrete case or
similar, restricting the excavation works to be conducted within an enclosed
dry section of the channel. This
works arrangement would provide a dry zone for excavation works within the
river channel and would prevent the conveyance of suspended sediment
downstream. Dewatering at works
section should be conducted prior to the commencement of works. Further
limiting or reducing the works area inside the water courses should be
considered during wet season or rainstorm event in order to reduce the area
of exposed surface. § Silt
curtain should be installed around the construction activities at or near the
watercourses to minimize the potential impacts due to accidental spillage of
construction wastes and excavated materials. § Proper
shoring may need to be erected in order to prevent soil or mud from slipping
into the watercourses. § Supervisory
staff should be assigned to station on site to closely supervise and monitor
the works. |
To control water quality impact from construction works at
or in close proximity of watercourses or seafront |
MTR
/ Contractor |
All works areas |
Construction phase |
EIAO-TM, WPCO |
||||
S11.166 |
Surface construction works close to water gathering grounds: § The
conditions as specified in WSD guidelines on protection of Water Gathering
Ground should be followed or observed where practicable |
To control water quality impact from surface construction
works close to Water Gathering Ground
|
MTR
/ Contractor |
Works areas close to water gathering ground |
Construction phase |
WSD guidelines on protection of Water Gathering Ground |
||||
S11.167 |
Dredging of marine sediments at LKST: § Closed
grab dredger should be used to minimize the loss of sediment during the
raising of the loaded grabs through the water column. § No more
than one closed grab dredger should be operated at any one time. § Double
silt curtains should be deployed around the dredging operations as far as
practicable. § The
descent speed of grabs should be controlled to minimize the seabed impact
speed. § Barges
should be loaded carefully to avoid splashing of material. § All
barges used for the transport of dredged materials should be fitted with
tight bottom seals in order to prevent leakage of material during loading and
transport. § All
barges should be filled to a level which ensures that material does not spill
over during loading and transport to the disposal site and that adequate
freeboard is maintained to ensure that the decks are not washed by wave
action. |
To minimize the loss of fine sediment to suspension during
dredging of marine sediments at LKST |
MTR
/ Contractor |
Marine dredging at LKST |
Construction phase |
EIAO-TM, WPCO, WSD Water Quality Criteria |
||||
S11.83 and S11.165 |
Diversion of watercourse: § The
excavation works at the existing stream in Shek Kong/ Kam Tin Nullah should
be carried out by approved methods by the Engineer to minimise erosion. Should excavation works be carried out
at the designated section of water course, temporary river diversion should
be conducted prior to the commencement of works to avoid water flowing into
works area. The temporary diversion of water flow should be performed by
appropriate means, such as completing the construction of the proposed
channel section for carrying diverted flow prior to excavation works, or
other similar methods, as approved by the Engineer to suit the works
condition. This works arrangement
would provide a dry zone for excavation works within the river channel and
would prevent the conveyance of suspended sediment downstream. Dewatering at works section should
also be conducted prior to the commencement of works. § Mitigation
measures for minimizing the water quality impact for surface construction
works at or close to the watercourses should also be applied. |
To control water quality impact due to diversion of
watercourse |
MTR
/ Contractor |
Watercourse to be diverted in Shek Kong |
Construction phase |
WPCO |
||||
S. 11.169 - 11.173 |
Hydrogeological Impact: § Toe
grouting should be applied beneath the toe level of the temporary/permanent
cofferdam walls as necessary to lengthen the effective flow path of
groundwater from outside and thus control the amount of water inflow to the
excavation. § Recharge
wells should be installed as necessary outside the excavation areas. Water pumped from the excavation areas
should be recharge back into the ground. The
bored tunnels should be constructed using a closed face tunnel boring machine
to limit water inflow into the excavation face. The cutter head for the machine will
be sealed during excavation and therefore the water inflow from the face will
be very small. Precast undrained
linings should be installed and back grouted behind the tunnel boring machine
as it advances along the alignment to minimize the potential inflow of water
behind the cutter head. The
Contractor should initially adopt suitable water control strategies while
undertaking the excavation works. The water control strategies are shown as
follow: § Probing
Ahead: As normal practice, the Contractor will undertake rigorous probing of
the ground ahead of tunnel excavation works to identify zones of significant
water inflow. The probe drilling results will be evaluated to determine
specific grouting requirements in line with the tunnel advance. In such zones
of significant water inflow that could occur as a result of discrete,
permeable features, the intent would be to reduce overall inflow by means of
cut-off grouting executed ahead of the tunnel advance. § Pre-grouting:
Where water inflow quantities are excessive, pre-grouting will be required to
reduce the water inflow into the tunnel. The pre-grouting will be achieved
via a systematic and carefully specified protocol of grouting. § In
principle, the grout pre-treatment would be designed on the basis of probe
hole drilling ahead of the tunnel face. § Post-grouting:
Groundwater drawdown will be most likely due to inflows of water into the
tunnel that have not been sufficiently controlled by the pre-grouting
measures. Where this occurs post grouting will be undertaken before the
lining is cast. Whilst unlikely to be required in significant measure, such a
contingency should be allowed for reduction in permeability of the tunnel
surround (by grouting) to limit inflow to acceptable levels. A detailed
groundwater monitoring programme should be developed in detailed design stage
to monitor both the proposed works and the impact of those works on the
adjacent area. |
To control groundwater hydrogeological impact and
groundwater drawdown |
MTR/ Contractor |
All works areas |
Construction phase |
|
||||
Water Quality Impact (Operation Phase) |
|
|
|
|
|
|||||
S11.174 |
Tunnel run-off and drainage: § Track
drainage channels discharge should pass through oil/grit
interceptors/chambers to remove oil, grease and sediment before being pumped
to the foul sewer/holding tank for further disposal. § The silt
traps and oil interceptors should be cleaned and maintained regularly. § Oily
contents of the oil interceptors should be transferred to an appropriate
disposal facility, or to be collected for reuse, if possible. |
To control runoff from rail track |
MTR / DDC |
Tunnels and rail tracks |
Operation phase |
WPCO |
||||
S11.175
– S11.176 |
Sewage effluents: § Connection of domestic sewage generated from the Project should be
diverted to the foul sewer wherever possible. If public sewer system is not
available, sewage tanking away services or on-site sewage treatment
facilities should be provided to prevent direct discharge of sewage to the
nearby storm system and all the discharge should comply with the requirements
stipulated in the TM-DSS. § For handling, treatment and
disposal of other operation stage effluent, the practices outlined in ProPECC
PN 5/93 should be adopted where applicable. |
To
control water quality impact from sewage effluent discharge ventilation
buildings, SSS and WKT |
MTR / DDC |
Ventilation buildings, SSS and WKT |
Operation phase |
EIAO-TM, WPCO, TM-DSS, ProPECC PN 5/93 |
||||
S11.177-
S11.181 |
Shek Kong Stabling Sidings (SSS): § All the maintenance areas within the SSS should be housed or covered
to prevent generation of contaminated rainwater runoff. All wastewater generated from the
maintenance and cleaning activities should be collected and diverted to oil
interceptor or other appropriate treatment facilities for proper treatment so
that it satisfies the requirements stipulated in the TM-DSS. § In case there is no pubic sewer available for the SSS during the
operation phase, all wastewater generated or collected in the SSS should be
tankered away for proper disposal to prevent direct discharge of any
wastewater to the nearby surface water system. § Oil interceptors should be regularly inspected and cleaned to avoid
wash-out of oil during storm conditions. A bypass would be provided to avoid
overload of the interceptor’s capacity. § All waste oils and fuels should be collected and handled in compl § Disposal of chemical wastes should be carried out in compl |
To control water quality impacts from the operation of Shek
Kong Stabling Sidings |
MTR/DDC |
SSS |
Operation phase |
EIAO-TM, WPCO, TM-DSS and Waste Disposal Ordinance |
||||
S11.182 |
For any future maintenance desilting of the newly constructed or
diverted watercourses, temporary barrier walls should be used to provide a
dry zone for desilting work. Maintenance
desilting should be carried out during periods of low flow in the dry season. |
To control water quality impact due to maintenance
desilting of the newly constructed or diverted watercourses |
MTR |
Diverted watercourses in Shek Kong |
Operation phase |
- |
||||
Air Quality (Construction Phase) |
|
|
|
|
|
|||||
S 12.78 |
For concrete batching plant, the
requirements and mitigation measures stipulated in the Guidance Note on the Best Practicable Means for Cement
Works (Concrete Batching Plant) BPM 3/2(93)
should be followed and implemented. |
To minimize dust impacts |
MTR / Contractor |
Concrete batching plant at works area V |
Construction phase |
Air Pollution Control Ordinance (APCO) |
||||
Table 12.9 and Table 12.12 |
The design emission concentration of dust
collector for different types of silos for concrete batching plant should be: § Dust collector for each small Cement Silo £ 30 mg/m3 § Dust collector for each Large Capacity Cement
Silo £ 50mg/m3 § Dust collector for each PFA Silo £ 30 mg/m3 § Dust collector for each Mixer £ 40 mg/m3 During operation of concrete batching plant: § The
aggregates should be unloaded from the tipper trucks to the receiving hopper
equipped with enclosures on 3 sides and top cover, and water spraying
system. § The
cement and PFA should be directly loaded into the silo via a flexible
duct. Dust collectors should be
installed at the cement/PFA silo based on the above design emission rates. § The aggregates should be stored in fully enclosed
overhead storage bins.
The top of overhead storage bins should be covered with cladding. Water spraying system should be
installed at the top of storage bins for watering the aggregates, and
aggregate storage bins should be fully enclosed. § The whole process of weighing and mixing of
cementitious material should be performed in a fully enclosed
environment. The mixers shall
equip with the dust collectors based on the above design emission rates. § The concrete should be directly loaded from the
mixer into the transit mixer of a truck in “wet” form. § Haul road within the site should be paved. Wheel washing pit should be installed
at the gate of the concrete batching plant. Water spraying system should be
installed along the haul road. |
To minimize dust
impacts |
MTR / Contractor |
Concrete batching plant at works area V |
Construction phase |
APCO and Guidance
Note on the Best Practicable Means for Cement Works (Concrete Batching Plant)
BPM 3/2(93) |
||||
Table 12.10 |
(1)
Cut & Cover Areas and Stockpiles in the vicinity of adits/shafts: (a)
Heavy construction activities at Cut & Cover Areas, Storage of materials at Stockpiles - Active areas for heavy construction activities, loading & unloading materials at
stockpiles § The specified requirements for cut & cover
areas and stockpiles at (i) Shek
Kong works area – active area minimized to 15% of total area, watering with
complete coverage of active area ten times a day. (ii) Nam
Cheong works area – active area minimized to 30% of total area, watering with
complete coverage of active stockpile area four times a day. (iii)
West Kowloon works area – active area minimized to 15% of total area,
watering with complete coverage of active area eight times a day. § For other sites, the active area would be
minimized to 30% of the total area, water spraying system would be applied on
the active area and watering with complete coverage of active area four times
a day would be required. § The remaining inactive area would be well covered
with impervious sheeting at all work sites. (b) Trucks - Transportation
of materials § Wheel wash facilities provided at the site exit.
The vehicles should be washed before leaving the stockpiles. The spoils should also be well covered
before leaving the site in order to minimise generation of dusty materials. § The haul roads within the site should be paved
and water spraying would be provided to keep the wet condition. § For the Shek Kong works area, watering paved haul
roads once per hour would be provided. (2) Temporary stockpiles within
barging facilities: (a) Loading point - Loading of spoils from
trucks onto stockpile § Water spraying should be provided at the loading
points to suppress the dust impact. (b) Storage of materials - Active
area for loading & unloading materials § Water spraying system should be applied on the
active area and watering with complete coverage of active area four times a day
is required. |
To minimize dust
impacts |
MTR / Contractor |
All works areas |
Construction phase |
APCO |
||||
Table 12.11 |
Barging facilities: (1)
Haul road within barging facilities - Transportation of spoils to the
barging points § All road surfaces within the barging facilities
should be paved and water spraying should be provided to keep the wet
condition. For paved haul roads at (2)
Unloading of materials - Unloading of spoil materials § The unloading process should be undertaken within
enclosed tipping hall. Water
spraying and dust curtain should be provided at the discharge point for dust
suppression. (3)
Trucks - Vehicles leaving the barging
facilities § Vehicle wheel washing facilities should be
provided at site exit. (4)
Transportation of spoils to one of the Nam Cheong Barging Point § Fully enclosed conveyor system should be adopted
for transportation of spoils from shaft to the barging point. |
To minimize dust
impacts |
MTR / Contractor |
All barging points |
Construction phase |
APCO |
||||
S 12.78 |
Dust suppression measures stipulated in the
Air Pollution Control (Construction Dust) Regulation and good site practices: § Use of regular watering, with complete coverage,
to reduce dust emissions from exposed site surfaces and unpaved roads,
particularly during dry weather. § Use of frequent watering for particularly dusty
construction areas and areas close to ASRs. § Side enclosure and covering of any aggregate or
dusty material storage piles to reduce emissions. Where this is not practicable owing to
frequent usage, watering should be applied to aggregate fines. § Open stockpiles should be avoided or
covered. Where possible, prevent
placing dusty material storage piles near ASRs. § Tarpaulin covering of all dusty vehicle loads
transported to, from and between site locations. § Establishment and use of vehicle wheel and body
washing facilities at the exit points of the site. § Provision of wind shield and dust extraction
units or similar dust mitigation measures at the loading points, and use of
water sprinklers at the loading area where dust generation is likely during
the loading process of loose material, particularly in dry seasons/ periods. § Imposition of speed controls for vehicles on
unpaved site roads. 8 kilometers
per hour is the recommended limit. § Where possible, routing of vehicles and
positioning of construction plant should be at the maximum possible distance
from ASRs. § Every stock of more than 20 bags of cement or dry
pulverised fuel ash (PFA) should be covered entirely by impervious sheeting
or placed in an area sheltered on the top and the 3 sides. § Cement or dry PFA delivered in bulk should be
stored in a closed silo fitted with an audible high level alarm which is
interlocked with the material filling line and no overfilling is allowed. § Loading, unloading, transfer, handling or storage
of bulk cement or dry PFA should be carried out in a totally enclosed system
or facility, and any vent or exhaust should be fitted with an effective
fabric filter or equivalent air pollution control system. |
To minimize dust impacts |
MTR / Contractor |
All works areas |
Construction phase |
APCO and Air Pollution Control (Construction Dust)
Regulation |
||||
S12.94 |
Environmental monitoring and audit for dust emission
should be conducted in accordance with EM&A Manual during the
construction phase of the Project to check compliance with legislative
requirements. |
To monitor dust impact |
MTR / Contactor |
Proposed monitoring locations |
Design and operation phases |
EIAO-TM, APCO |
||||
Air Quality (Operation Phase) |
|
|
|
|
|
|||||
S12.48 |
The vent shafts of the stations should be designed to
be sited at more than 5m from any opening at the adjacent building |
To alleviate the adverse air quality impact in the stations |
MTR |
WKT |
Design and operation phases |
Fire Services Department |
||||
S12.50 |
The design of the mechanical air ventilation for PTI
should follow EPD’s ProPECC PN1/98 Control of Air Pollution in Semi-confined
Public Transport Interchanges. |
To alleviate the adverse air quality impact in the PTI |
MTR |
PTI at the ground floor of ventilation building complex at
WKT |
Design and operation phases |
ProPECC PN1/98 Control of Air Pollution in Semi-confined Public
Transport Interchanges |
||||
Hazard
to Life |
|
|
|
|
|
|||||
S13.96/ S13.99 |
Improved truck design to reduce
the amount of combustibles in the cabin and fuel carried in the fuel tank
should be minimised to reduce the duration of any fire. The truck should be
brand new, diesel powered and equipped with fuel and battery isolation
switches, front exhaust spark arrester, 1 x 9 kg water based and 1 x 9 kg dry
chemical powder fire extinguishers. This should be combined with monthly
vehicle inspection |
To meet
the ALARP requirement |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
S13.96 |
The explosive truck accident
frequency should be minimized by implementing a dedicated training programme
for both the driver and his attendants, including regular briefing sessions,
implementation of a defensive driving attitude. In addition, drivers should
be selected based on good safety record, and medical checks. |
To meet
the ALARP requirement |
MTRC/
Contractor |
- |
Construction
phase. |
- |
||||
S13.96 |
The contractor should as far as
practicable combine the explosive deliveries for a given work area. |
To meet
the ALARP requirement |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
S13.96 |
The explosive truck fire
involvement frequency should be minimized by implementing a better emergency
response and training to make sure the adequate fire extinguishers are used
and attempt is made to evacuate the area of the incident or securing the
explosive load if possible. All explosive vehicles should also be equipped
with bigger capacity AFFF-type extinguishers. |
To meet
the ALARP requirement |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
S13.96 |
A minimum headway between two
consecutive truck conveys of at least 10 min is recommended |
To meet
the ALARP requirement |
MTRC/
Contractor |
Along
explosives transport route. |
Construction
phase. |
- |
||||
S13.96/ S13.105 |
Only the
required quantity of explosives for a particular blast should be transported
to avoid the return of unused explosives to the magazines. If disposal is required for small
quantities, disposal should be made in a controlled and safe manner by a
Registered Shotfirer. |
To
reduce the risk during explosives transport |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
S13.97 |
Blasting activities including
storage and transport of explosives should be supervised and audited by
competent site staff to ensure strict compliance with the blasting permit
conditions. |
To
ensure that the risks from the proposed explosives storage and transport
would be acceptable |
MTRC /
Contractor |
Works
areas at which explosives would be stored and/or used. |
Construction
phase |
Dangerous
Goods Ordinance |
||||
S13.97 |
Emergency plan (ie magazine
operational manual) shall be developed to address uncontrolled fire in
magazine area and transport. The case of fire near an explosive carrying
truck in jammed traffic should also be covered. Drill of the emergency plan
should be carried out at regular intervals. |
To
reduce the risk of fire |
MTRC/
Contractor |
Explosive
Magazine and along explosives transport route. |
Construction
phase |
- |
||||
S13.97 |
Adverse weather working guideline
should be developed to clearly define procedure for transport explosives
during thunderstorm. |
To
ensure safe transport of explosives |
MTRC/
Contractor |
Along
explosives transport route. |
Construction
phase |
- |
||||
S13.98 |
Delivery vehicles shall not be
permitted to remain within the secured fenced off magazine store area. |
To
reduce the risk of fire within the magazine |
MTRC /
Contractor |
Explosive
Magazine |
Construction
phase |
- |
||||
S13.98 |
Good house-keeping within and
outside of the magazine to ensure that combustible materials (including
vegetation) are removed and not allowed to accumulate. |
To
reduce the risk of fire within the magazine |
MTRC /
Contractor |
Explosive
Magazine |
Construction
phase |
- |
||||
S13.99/ S13.101 |
Use only experienced driver(s)
with good safety record. Training should be provided to ensure it covers all
major safety subjects. |
To
ensure safe transport of explosives |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
S13.99 |
Develop procedure to ensure that
parking space on the site is available for the explosive truck. Confirmation
of parking space should be communicated to truck drivers before delivery. |
To
ensure that the risks from the proposed explosives storage and transport
would be acceptable |
MTRC/
Contractor |
Explosive
magazine |
Construction
phase |
- |
||||
S13.99 |
Detonators shall not be
transported in the same vehicle with other Class 1 explosives |
To
reduce the risk of explosion during the transport of cartridge emulsion |
MTRC /
Contractor |
- |
Construction
phase |
- |
||||
S13.99 |
During transport of the explosives
within the tunnel, hot work should not be permitted in the vicinity of the
explosives offloading or charging activities. |
To
ensure safe transport of explosives |
MTRC/
Contractor |
Along
explosives transport route. |
Construction
phase |
- |
||||
S13.99 |
Ensure that packaging of
detonators remains intact until handed over at blasting site. |
To
reduce the risk of explosion during the transport of detonator |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
S13.99 |
Horizontal fire screen on cargo
deck and vertical fire screen mounted at least 150 mm behind the drivers cab
and 100 mm from the steel cargo compartment, the vertical screen shall
protrude 150 mm in excess of all three (3) sides of the steel cargo compartment. |
To
reduce the risk during explosives transport |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
S13.104 |
Ensure that cartridge emulsion
with high water content should be preferred. Also, the emulsion with
perchlorate formulation should be avoided. |
To
ensure safe explosives to be used |
MTRC/
Contractor |
- |
Construction
phase |
- |
||||
Landfill
Gas Hazard – Design and Construction Phases |
|
|
|
|
|
|||||
S14.73
& S14.86 |
- All
personnel who work on site and all visitors to the site should be made aware
of the possibility of ignition of gas in the vicinity of excavations. Safety notices should be posted
warning of the potential hazards. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone, Barging
Point and Nursery Site |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.73 |
- Those
staff who work in, or have responsibility for “at risk” areas, including all
excavation workers, supervisors and engineers working within the Consultation
Zone, should receive appropriate training on working in areas susceptible to
landfill gas, fire and explosion hazards. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.73 |
-
During all works, safety procedures will be
implemented to minimise the risks of fires and explosions and asphyxiation of
workers (especially in confined space). |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.73 |
-
Safety officers, specifically trained with
regard to landfill gas related hazards and the appropriate actions to take in
adverse circumstances will be present on all worksites throughout the works. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.73, S14.86, S14.87 |
-
Smoking and naked flames will be prohibited
within confined spaces. 'No
Smoking' and 'No Naked Flame' notices in Chinese and English will be posted
prominently around the construction site. Safety notices should be posted
warning of the potential hazards. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone, Barging
Point and Nursery Site |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.73 |
-
Welding, flame-cutting or other hot works
may only be carried out in confined spaces when controlled by a 'permit to
work' procedure, properly authorised by the Safety Officer. The permit to work procedure will set
down clearly the requirements for continuous monitoring of methane, carbon
dioxide and oxygen throughout the period during which the hot works are in
progress. The procedure will also
require the presence of an appropriately qualified person who shall be
responsible for reviewing the gas measurements as they are made, and who
shall have executive responsibility for suspending the work in the event of
unacceptable or hazardous conditions.
Only those workers who are appropriately trained and fully aware of
the potentially hazardous conditions which may arise will be permitted to
carry out hot works in confined areas. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.73 |
-
A mechanical ventilation system must be in
use at all times during which personnel are engaged in works inside the
tunnel or excavation and be evacuated in the event of power outages. Work must not be carried out in the
absence of mechanical ventilation and supervision of adequately trained
safety personnel. In exceptional
case where work is carried out under non-ventilated condition, any electrical
equipment used, such as motors and extension cords, should be intrinsically
safe. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.73 |
-
Adequate fire extinguishing equipment,
fire-resistant clothing and breathing apparatus sets should be made available
on site. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.86 |
- Raising
the site office 500mm above ground. |
Protect the workers from landfill gas hazards |
Contractor |
Barging Point |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.86 |
- Utilities
services connected to the site office and the annulus around these service
entry points should be properly sealed. |
Protect the workers from landfill gas hazards |
Contractor |
Barging Point |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.74 |
-
Construction works to be undertaken in
confined space should follow the relevant Regulations under Chapter 59
Factories and Industrial Undertakings Ordinance and Chapter 509 Occupational
Health and Safety Ordinance. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
Chapter 59 Factories and Industrial Undertakings Ordinance
and Chapter 509 Occupational Health and Safety Ordinance |
||||
S14.73 |
-
Monitoring of methane,
carbon dioxide and oxygen inside the XRL tunnels. |
Protect the workers from landfill gas hazards |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.75 |
-
A walkover
survey to monitor flammable gas at all joints and cracks, if identified, upon
completion of the tunnel work. Rectifications,
such as sealing of cracks and inspection of tunnel seals, shall be carried
out for any signs of the presence of flammable gas. The survey should be conducted under non-ventilated condition and
before starting the work of the day. |
Confirm no landfill gas ingress into the XRL tunnels |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.76 |
-
Weekly monitoring of methane, carbon
dioxide and oxygen in the form of a walkover survey at 20m intervals for
section of tunnels under NTML and 50m interval within the NTML Consultation
Zone should be conducted after completion of the tunnel construction works
and not less than 3 months before commencement of operation. The survey should be conducted under
non-ventilated condition and before starting the work of the day. |
Confirm no landfill gas ingress into the XRL tunnels |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.77 |
- A
summary of the monitoring results should be submitted to EPD for record
before the commencement of operational phase. The results should be reviewed and
agreed with EPD before the commencement of operation to determine the
monitoring requirements during the operational phase |
To review and agree the monitoring requirement during the
operational phase |
MTR/Contractor |
- |
Before operation |
- |
||||
S14.78 |
- Appropriate
sealant will be applied to joints to prevent the ingress of groundwater,
which will also form a low permeability gas barrier. Good workmanship and adequate
construction supervision will be required to ensure the actual works are
implemented as per the design requirements. This will be implemented by MTRC’s
Material and Workmanship Specification. |
Protect the XRL tunnels from landfill gas hazards |
Design Engineer/ Contractor |
XRL tunnels within the NTML Consultation Zone |
Design and Construction phases |
MTRC’s Material and Workmanship Specification. |
||||
S14.79 |
- Adequate
ventilation will be needed as part of the tunnel design to act as an active
gas control when needed. |
Protect the XRL tunnels from landfill gas hazards |
Design Engineer |
XRL tunnels within the NTML Consultation Zone |
Design phase |
- |
||||
S14.80 |
- Upon
completion of the landfill gas protection measures, a report on the
implemented landfill gas protection measures with relevant as-built drawings
and other detailed information showing that the design measures mentioned in
this assessment to protect the tunnels from landfill gas hazard have been
properly incorporated should be submitted to EPD. |
Ensure landfill gas protection measures have been completed |
Contractor |
XRL tunnels within the NTML Consultation Zone |
Construction phase |
- |
||||
Landfill
Gas Hazard – Operation Phase |
|
|
|
|
|
|||||
S14.76 |
-
Ventilation of the tunnels should be
switched on for half an hour before the first train is expected (the
requirement to implement this measure is subject to findings of the review of
landfill gas monitoring data with EPD before the commencement of operation). |
Protect the operation of the XRL from landfill gas hazards |
MTR |
XRL tunnels within the NTML Consultation Zone |
Operation phase |
- |
||||
S14.76 |
-
All maintenance personnel and station staff
working within the tunnels should be educated in the dangers of landfill gas
and the signs and symptoms of asphyxia. |
Protect the workers from landfill gas hazards |
MTR |
XRL tunnels within the NTML Consultation Zone |
Operation phase |
- |
||||
S14.76 |
-
Smoking within the tunnels should be
prohibited at all times. |
Protect the operation of the XRL and workers from landfill
gas hazards |
MTR |
XRL tunnels within the NTML Consultation Zone |
Operation phase |
- |
||||
S14.76 |
-
An assumed presence of landfill gas should
be adopted at all times by maintenance workers and a strictly regulated “work
permit procedure” involving training, ventilation, gas monitoring (as
detailed in the Construction recommendations section), safety tracking and
communication with maintenance staff, enforcement of the no smoking order. |
Protect the workers from landfill gas hazards |
MTR |
XRL tunnels within the NTML Consultation Zone |
Operation phase |
- |
||||
S14.82
& S14.83 |
-
The monitoring requirement during the
operational phase should be discussed with EPD before the commencement of
operation. Weekly monitoring of
methane, carbon dioxide and oxygen in the form of a walkover survey at 20m
intervals for section of tunnels under NTML and 50m interval within the NTML
Consultation Zone is tentatively proposed. The survey should be conducted under
non-ventilated condition and before the first train operates and start-up of
ventilation, if applicable. A summary of the monitoring results
should be submitted to EPD for record at the end of the monitoring period. |
Confirm no landfill gas ingress into the XRL tunnels |
MTR |
XRL tunnels within the NTML Consultation Zone |
Operation phase |
EPD’s Landfill Gas Hazard Assessment Guidance Note |
||||
S14.84 |
- An
annual walkover survey in the tunnels within the Consultation Zone of the
NTML should be conducted to test for the presence of flammable gas at joints
and cracks, if identified. Rectifications, such as sealing of cracks and
inspection of tunnel seals, should be carried out for any signs of presence
of flammable gas. The survey
should be conducted under non-ventilated condition and before the first train
operates and start-up of ventilation, if applicable. |
Confirm no landfill gas ingress into the XRL tunnels |
MTR |
XRL tunnels within the NTML Consultation Zone |
Operation phase |
- |
||||