2.1
The Guangzhou-Shenzhen-Hong Kong
Express Rail Link (XRL) is proposed to connect Hong Kong, Shenzhen and
2.2
The Hong Kong Section of the XRL
(the Project) is approximately
2.3
Ventilation buildings along the
railway corridor needed for fire safety will be located at
2.4
Stabling sidings and a first-line
maintenance facility will be located at Shek Kong Stabling Sidings (SSS) to
provide train stabling, minor maintenance and cleaning activities. An emergency rescue station (ERS) will be
located next to Shek Kong Stabling Sidings for emergency evacuation of
passengers and access by emergency personnel.
2.5
The Project was gazetted under the Railways Ordinance in
November 2008. It is expected that the
construction of the Project will commence in late 2009, and be completed in
2015. A preliminary construction
programme of the Project is provided in Appendix 2.1.
2.6
The XRL will form part of the
National high-speed railway network, connecting Hong Kong with
2.7
The high-speed rail service will not only allow Hong Kong to
have better social and economic integration with cities in the Pearl River
Delta and other major cities in the Mainland, but will also facilitate and
promote business and tourism. It is also expected that the Project will create
about 5,500 employment opportunities during its construction and another 10,000
during its operation. It is therefore concluded
that the Project will generate huge social and economic benefits in terms of
employment and development opportunities as a result of better regional
integration.
2.8
Transportation by rail over the lifetime of the facility is
considered to be more environmentally friendly in terms of energy conservation
and gas emissions. During the operation
of the Project, the public will be encouraged to use an environmentally
friendly public transport, and thus the environment will be benefited by the
reduction of air and noise pollution problem and other associated deleterious
effects generated by automobile usage. Increasing transport by rail will also
provide free access to goods transportation by roads.
2.9
The Project comprises the
following key elements:
·
Approximately
·
A terminus in
·
Seven tunnel
ventilation buildings at
·
Stabling sidings
and maintenance facilities located at Shek Kong (Shek Kong Stabling Sidings (SSS))
to provide for train stabling, minor maintenance and cleaning; and
·
An emergency
rescue station (ERS) located next to the SSS.
2.10
Apart from the above key
elements, site explosive magazine, nursery sites, barging facilities,
supporting works areas and access roads will be required to support the
construction of the Project.
2.11
The information presented below
is a summary available from the preliminary design and will be subject to
further study at the detailed engineering design stage.
Overall
Alignment
2.12
The overall alignment of the Project is shown in
Figure Nos. NOL/ERL/300/C/XRL/ENS/M50/001
to 003 and described below. In developing and selecting alignment
options, environmental factors were fully taken into account. Details of the
selection of the preferred alignment are described in Sections 2.29 to 2.41.
2.13
Table 2.1 summarises the
information of the Project alignment with its horizontal and vertical alignment
presented in Figure Nos. NOL/ERL/300/C/XRL/ENS/M53/200 to 228.
Table 2.1 Summary of Alignment
Tunnel Sections |
Approx. Horizontal Length, km |
Approx. outside Tunnel Diameter, m |
Type of Tunnel |
Approx. Level, mPD (min. to max. meter below local ground) |
Tunnels between Boundary to |
1.5 |
9.3 |
Tunnel Boring Machine
(TBM) - Twin bore single track tunnels |
-31 to -26 (approx. 25 to |
Tunnels between |
2.3 |
9.3 |
TBM - Twin bore single
track tunnels |
-26 to -19 (approx. 25 to |
Tunnels between and |
2.8 |
7.7 to 20.4 |
Drill & Blast
(D&B) - Single track twin bore tunnels / twin track single bore tunnel /
twin track single bore transition cavern |
-20 to -16 (approx. 60 to |
Tunnels between Tai Kong Po Emergency Access
Point and north of Emergency Rescue Station (ERS) |
1.1 |
9.3 |
TBM - Twin bore single
track tunnels |
-19 to 4 (approx. 30 to |
North of ERS to South of ERS |
1.6 |
- |
Cut and cover tunnels |
-4 to 10 (approx. 10 to |
Tunnels between south of ERS and Tse Uk
Tsuen Works Area |
0.4 |
9.3 |
TBM - Twin bore single
track tunnels |
10 to 18 (approx. 18 to |
Tunnels between Tse |
6.5 |
7.7 to 19.6 |
D&B - Single track
twin bore tunnels / twin track single bore tunnel / twin track single bore transition
cavern |
18 to -26 (approx. 12 to |
Tunnels between |
2.5 |
14.8 |
D&B - Twin track
single bore tunnel |
-26 to -30 (approx. 60 to |
Tunnels between Kwai Chung adit and |
3.0 |
7.7 to 19.6 |
D&B - Single track
twin bore tunnels / twin track single bore tunnel / twin track single bore
transition cavern |
-30 to -20 (approx. 270 to |
Tunnels between |
2.5 |
9.3 |
TBM - Twin bore single
track tunnels |
-20 to -15 (approx. 25 to |
Tunnels between |
0.2 |
9.3 |
Cut and cover tunnels |
-15 to -14 (approx. 20 to |
Tunnels between |
0.5 |
15 |
Single twin track cut and cover tunnel |
-14 to -23 (approx. 24 to |
2.1
The WKT is accommodated within Site A on the South West
Kowloon Outline Zoning Plan (OZP) (S/K20/22[1] dated 20 March 2009) with a footprint of about
2.2
WKT will be developed as a gateway to the Mainland, with
distinctive architecture, landmark features and a user-friendly layout to
accommodate co-located HKSAR and Mainland Customs, Immigration and Quarantine
(CIQ) facilities. Schematic layout and
sections are presented in Figure Nos. NOL/ERL/300/C/XRL/ENS/M50/023
to 029.
2.3
The ventilation buildings will not only provide essential
ventilation to the tunnel but also act as Emergency Access Point (EAP) for Fire
Services Department personnel or MTRCL staff to reach the track level in
emergency situations or provide access for maintenance.
2.4
A total of seven tunnel ventilation buildings will be
provided, five in the
2.5
Two ventilation buildings at the northern and southern ends
of the ERS will also provide ventilation to the tunnel and emergency access
during emergency situation.
2.6
Ventilation shafts located on top of the WKT will be
integrated with the future topside development to minimise potential visual
impacts. As the underground structures
of WKT will encroach on eastern portion of WKCD, there will be two ventilation
shafts located in WKCD to serve underground stabling tracks.
Shek Kong
Stabling Sidings (SSS)
2.7
Stabling sidings will be located at Shek Kong. To comply with the operational
requirements, stabling sidings will comprise running maintenance area, stabling
area, store, staff accommodation, permanent way facility locomotive shed,
fuelling facility, gatehouse and access point, E&M plant building, train
wash facility, and traction power feeder substation. Schematic layout and sections are
presented in Figure
Nos. NOL/ERL/300/C/XRL/ENS/M50/017 to 020.
Emergency Rescue Station (ERS)
2.8
The ERS located next to SSS is a depressed box with an open
top for a full train length of approximately
2.9
The following sections present
the consideration of the alternatives for the following key elements of the
Project:
·
Alignment;
·
Terminus;
·
Ventilation
building/Emergency Access Point;
·
Stabling sidings;
·
Emergency rescue
station; and
·
Train System.
Alignment
Background of Alignment Development
2.10
A Preliminary Project Feasibility Study (PPFS)
was conducted from 2006 to 2007 to study the feasibility of using a shared rail
corridor with West Rail (WR) and dedicated corridor with the primary focus
being to establish whether the XRL would share a rail corridor with West Rail
or adopt a dedicated corridor.
2.11
Two alignment options were studied for the
purpose of evaluating the pros and cons of dedicated corridor and shared
corridor schemes (Figure No. NOL/ERL/300/C/XRL/ENS/M50/031):
·
Dedicated corridor
scheme: comprising a 25 km tunnel route from WKT via an underground emergency
rescue station located east of Shek Kong to the boundary crossing point located
west of the Lok Ma Chau Terminus; and
·
Shared corridor
scheme: comprising a 26 km tunnel route sharing the West Rail corridor from
south of Nam Cheong to
2.12
During the study, a number of changes in service
demand, rolling stock and structural gauge were required to be adopted in the
XRL. As a consequence to the above
changes, the overall issues associated with the proposed shared corridor scheme
are summarised below:
·
The evacuation
walkway inside the WR tunnel and platforms would be required to be trimmed back
to accommodate the mainland train gauge. However, this would increase the
stepping gap for the WR passengers to pass over in case of emergency evacuation
inside the tunnel and platform. The
safety of the WR passengers would therefore be compromised during emergency
evacuation and normal daily usage. It was
anticipated that the modification works would take approximately three years,
affecting about 30,000 passengers every day.
·
Increased patronage
and long haul train services for serving mainland cities would significantly
shorten the usable life of the WR in supporting the XRL service. With the current patronage and service
predictions, the shared corridor would be saturated by 2020s. With the commencement of XRL in 2015, the
usable life of the shared corridor would be very short,
and possibly shorter if the XRL service is welcomed by the public. As such, a
dedicated corridor would be required to accommodate the future demand and its
construction would need to commence shortly
after the operation of the shared corridor.
·
Shared corridor would
offer low flexibility in both WR and XRL operation. Hourly interruption to either service would
be expected with little room for recovery after perturbation. WR operation performance would be
significantly inferior to what is currently being achieved and the WR Service
Pledge would be difficult to meet. Similarly,
XRL operation performance would also be significantly inferior to what one
would expect from a modern, premium service railway line. The situation would become unmanageable when
long haul train services frequency approaches
the capacity limit.
·
The shared corridor
scheme was considered as cost-ineffective in terms of operation and usable
life as discussed above.
2.13
In view of the above,
the dedicated corridor scheme was therefore selected for further study.
2.14
Following the selection of the dedicated
corridor scheme, MTRCL proceeded with further planning and project design. Two dedicated alignment corridors were further studied:
·
Base Scheme utilizing
a direct route from
·
Alternative Scheme to
the west of Base Scheme, utilising the existing West Rail stabling facilities
at Pat Heung as far as possible.
2.15
Both schemes shared a common southern alignment
within the
Criteria for Options Development
2.16
The Project alignment was divided into northern
and southern sections. The criteria presented in Table
2.2 were adopted for the consideration of alignment options for southern
and northern sections.
Table 2.2 Criteria for Option
Development
Criteria |
Description |
Engineering Factors
|
|
Implementation Programme |
Minimisation of construction period. Shorter construction period would
be preferable as it could minimise disruption period to the community |
Operations safety, flexibility
and maintainability |
·
Ease of fire fighting and
evacuation ·
Flexibility for stabling
requirement |
Constructability |
·
Avoidance/minimisation of
constructing soft ground tunnel due to safety and building settlement issues ·
Avoidance/minimisation on
construction risks due to uncertain ground condition and long tunnel |
Land acquisition |
Minimisation of affected areas to avoid disruption to local community |
Environmental
Factors |
|
Ecology |
Avoidance/Minimisation of impact on wetlands, sites of
conservation importance (including |
Other Environmental
considerations |
Avoidance/Minimisation of ·
Airborne and ground-borne noise
impact associated with the trains pass-bys ·
Landscape and visual impact
associated with the above-ground structures; and impact on any significant
landscape and heritage resources ·
Indirect impact (e.g. vibration
impact) on historical buildings ·
Direct impact on graded
buildings and known Archaeological Sites |
Other Factors |
|
Avoidance/Minimisation
of issues/constraints |
·
Minimisation of project areas
encroaching into developed area ·
Minimisation of interface
issues with other projects |
Disruption to the community |
·
Minimisation of impact to local
communities including residential households ·
Minimisation of structural
impact on the buildings along the alignment ·
Minimisation of impact to
business operations |
2.17
A Preliminary Design Study (PDS) was conducted to
further review the PPFS Base Scheme and Alternative Scheme, and identified
alternative route options, basing on the criteria presented in Table 2.2.
Alignment Options
2.18
During the investigation of possible alignment
options, no-dig zones for above-ground
works were identified, including in
2.19
A total of 3 alignment options for the southern
section and 4 alignment options for the northern section were developed in the
PDS stage. The identified alignment
options are described in Table 2.3 and presented in Figure Nos. NOL/ERL/300/C/XRL/ENS/M50/032 to 033.
Option |
Approx. Length (km) |
Description |
Southern Section |
||
S1 (Base Scheme) |
9 |
The southern
alignment starts at West Kowloon, passing beneath |
S2 |
10 |
A new alignment for the southern section adopting a westerly alignment
through |
S3 |
11 |
A new alignment for the southern section running along Lin Cheung Road
and turn further west after passing Nam Cheong Station and then turn east
sharply after passing the proposed Lai Chi Kok DSD Transfer Scheme to Po Lun
Street. After leaving |
Northern Section |
||
N1 (Alternative Scheme) |
21 |
This scheme, from Shing Mun trends west to follow an alignment
parallel with West Rail before trending north, adjacent to the |
N2 |
13 |
A northern alignment located 500m to the west of the PPFS Base Scheme to
place the ERS facility in land zoned for agriculture use |
N3 (Base Scheme) |
17 |
This scheme provided north passing across the middle of the |
N4 |
14 |
A northern alignment located east of the PPFS Base Scheme minimizing
the length of soft ground tunnelling with the tunnel alignment within rock |
Evaluation of Alignment Options
2.20
Based on criteria developed
in Table 2.2, evaluation of each alignment
option was conducted. A summary of options assessment are presented
in Table 2.4.
Table 2.4 Evaluation of Alignment
Options in Preliminary Design Study
Criteria |
Alignment Option |
||||||
Southern Section |
Northern Section |
||||||
S1 (Base Scheme) |
S2(1) |
S3 |
N1 (Alternative Scheme) |
N2(1) |
N3 (Base Scheme) |
N4 |
|
Engineering Factors |
|||||||
Implementation Programme |
Not assessed |
Not assessed |
Not assessed |
· Significantly greater length of tunnel,
requiring longer construction period of about 70 months |
· Construction period of about 64 months |
· Construction period of about 76 – 82 months
|
· Construction period of about 64 months |
Operations safety, flexibility
and maintainability |
Not assessed |
Not assessed |
Not assessed |
· Access for fire fighting and escape for
evacuation is more difficult due to the deeper ERS |
· Better performance with the ease of fire
fighting for an open box ERS · Dual access from |
· Better performance with the ease of fire
fighting for an open box ERS |
· Difficult in fire fighting due to only part
of the box ERS open |
Constructability |
· High risk of deep weathering material in Sham
Shui Po areas · Deep alignment with complex tunnelling
issues · High risk of extensive ground improvement
works in urban |
· Lower risk of deep weathering · Complex interface with Lai Chi Kok
Interchange |
· High risk for intervention for TBM
maintenance at high air pressure of above 3.4 Bar · Difficult to construct
for alignment under a lot of foundations and existing railway lines |
· Extensive soft/mixed ground tunnelling · Complex to construct and higher
construction risk |
· Moderate soft ground tunnelling · Complex to construct and higher
construction risks |
· Moderate soft ground tunnelling · Complex to construct and higher
construction risks |
· Relatively less soft ground tunnelling · Less complex to construct and lower
construction risks |
Land Acquisition |
· Acquire Land for permanent ventilation
buildings · Very few business to be affected · No private land required |
· Acquire Land for permanent ventilation
buildings · Very few business to be affected · Only one CLP spare equipment building to be
resumed |
· Acquire Land for permanent ventilation
buildings · Very few business to be affected · No private land required |
· Mainly agricultural land · Some structures affected |
· Mainly agricultural land · Fewer structures affected |
· Mainly open storage · Some structures affected |
· Mainly open storage · Slightly fewer structures affected |
Environmental Factors |
|||||||
Ecology |
Not anticipated |
Not anticipated |
Not anticipated |
Potential impact on: · natural ecologically important stream KT12(2)
and surrounding Greater Painted-snipe habitat at Cheung Po · Wooded area in CA near Tai Wo · Bat roosting site east of Pat Heung
Maintenance Centre |
Potential impact on: · Wooded area within/immediately outside
Conservation Area (CA) near Tse Uk Tsuen · Stream and agricultural habitats in Shek
Kong |
Potential impact on: · Fung Shui Wood of high ecological values
near |
Potential impact on: · Wooded area in Conservation Area near Chuk
Hang and · Ha Che Egretry stream habitats |
Environmental Considerations |
· Insignificant visual impact from
ventilation buildings and terminus by proper architectural design |
· Insignificant visual impact from ventilation
buildings and terminus by proper architectural design |
· Insignificant visual impact from
ventilation buildings and terminus by proper architectural design |
· Insignificant visual impact from ventilation
buildings and Stabling Sidings by proper architectural design · Potential impact on Ho Pui Archaeological
Site · Cumulative impact from sharing with
existing West Rail Infrastructures |
· Insignificant visual impact from
ventilation buildings and Stabling Sidings by proper architectural design · No known direct impact on cultural heritage
|
· Insignificant visual impact from
ventilation buildings and Stabling Sidings by proper architectural design · Landscape impact on Fung Shui Wood of high
values near · Potential impact on Pat Heung Sheung Tsuen
Archaeological Site |
· Insignificant visual impact from
ventilation buildings by proper architectural design · No known direct impact on cultural heritage · Landscape and visual impact from stabling
sidings due to substantial alteration of natural landform |
Other Factor |
|||||||
Avoidance of issues/constraints |
- |
· Tunnelling in congested Sham Shui Po
avoided |
- |
· Reduction of land take by using existing
West Rail land but affecting densely populated area |
· Avoidance of locating ERS and SSS in
densely populated area |
· |
· Tunnelling impact on above ground
structures minimised · Soft ground tunnelling minimised |
Disruption to the Community |
· Higher structural impacts |
· Lower structural impacts |
· Higher structural impacts |
· Approximately 370 number of households affected · Few businesses affected |
· Approximately 150 number of households
affected · Some businesses affected |
· Approximately 340 number of households
affected · Higher number of businesses affected |
· Approximately 230 numbers of households
affected · Higher number of businesses affected |
Note:
(1) The preferred
alignment options are highlighted for easy reference.
(2) KT12 is classified as
an Ecological Important Stream (EIS) under Environment,
Transport and Works Bureau Technical Circular (Works) No. 5/2005 “Protection of
natural streams/rivers from adverse impacts arising from construction works.
Southern Section
2.21
Alignment option S1 (base scheme in PPFS) would
require the tunnel to pass below densely populated areas in Sham Shui Po, which is built on soft ground. To
ensure the safety of the tunnel and the integrity of the buildings above it, it
would be necessary to maintain the tunnel within competent rock. Based on the
available site investigation information in the PPFS stage, this option
required a deep alignment within rock below the structures. During the PPFS,
project specific site investigation was undertaken and the data indicated that
the rock head was subject to deep weathering, posing a significant risk. An
initial assessment also indicated that settlement from the tunnelling works
could impact on over 200 buildings. The dense urban nature of the area restricted
access from the surface to undertake underground mitigation works and the deep
tunnel alignment posed a significant technical challenge due to the high ground
water pressures within the soft ground portion.
Construction of this alignment option would require very extensive
mitigation measures for ground improvement work in urban
2.22
For alignment option S3, this alignment runs
along
2.23
Alignment option S2, which runs along the
Northern Section
2.24
Alignment option N1 (PPFS Alternative Scheme)
utilizing the West Rail Depot was not supported from a sustainable development
view point. From a social impact perspective, the vacant land adjacent to the
existing West Rail Pat Heung Depot is not sufficient to cater for stabling
requirements, hence, additional land resumption will be required. Affected areas within the vicinity of the
proposed stabling sidings include Tin Sum (Kau Tsuen),
2.25
Alignment option N3 (PPFS Base Case) was not
preferred from a sustainable development perspective. This proposal would
affect Sheung Tsuen, Cheung Uk Tsuen; and the number of households to be
affected was estimated to be approximately 340. Furthermore, the proposed site for stabling
sidings would be located within an area of archaeological importance and
adjacent to the
2.26
Again, for alignment option N4, the location
within the head of the valley where the open storage sites are situated was
initially considered to be desirable from a land perspective. However, a more
thorough investigation revealed that about 230 households would be affected. In
addition, the clearance of the area zoned as “Open Storage” may inflict other
social issues such as impact to businesses and loss of
employment opportunities. This eastern alignment will reduce the length of soft ground
tunnelling and numbers of TBMs required, however the associated works areas may
encroach into the buffer zones of the adjacent Chuk Hang and
2.27
Alignment option N2 addressed many of the
shortfalls identified in the other alignment options. In addition, the land for stabling sidings
has the least number of households (approximately 150) affected within the area. When compared to other schemes, it is
considered that this scheme would bring the least impact to local communities. Moreover, the site spans between
Preferred Alignment
2.28
Based on the evaluation results, the preferred
alignment options comprising a combination of alignment options S2 and N2 were
selected for the Project, taking account of engineering, operational and
environmental constraints. The cost estimation for the different alignment options was considered
to be an insignificant factor and therefore was not considered in the selection
process. For the northern section, alignment option N2
offered clear benefits in terms of operations, environment, construction and
land related impacts. For the southern section, alignment option S2 presented a
number of benefits and a feasible design solution could be developed to address
the constraints.
Principle Functions
2.29
The terminus will be
a principal gateway between
Preferable Location
2.30
The WKT will be
located immediately to the north of the proposed WKCD, with the following benefits envisaged:
·
The terminus location
will form an integrated railway/transport/development hub with Kowloon Station
(Airport Express Line and Tung Chung Line) and Austin Station (Kowloon Southern
Link) and the associated airspace developments, providing point-to-point
connection via the existing MTR network.
·
The terminus will be
integrated into the West Kowloon Reclamation Areas and Tsim Sha Tsui / Jordan
Areas. It is anticipated that the
provision of a terminus in this area will create a continuous people-dominated
living space interlinking buildings, and activity areas, extending to the
harbour front and adjacent districts.
·
The terminus will
partly extend into the underground area of the WKCD to provide better terminal
operations. Integration into the WKCD
will greatly enhance not only the prominence of the rail terminus as a gateway
to the Mainland, but also the WKCD as a regional cultural hub. It is also
anticipated that the WKT site will generate more visits to the proposed art,
culture and tourism facilities in the WKCD thereby promoting cultural
tourism.
Scheme Design
2.31
During the PPFS, the
formulation of the terminus configuration was based on the following generic
planning items:
·
Architecture to
promote the WKT as the gateway to
·
Segregation of
arrival and departure passengers;
·
Convenient station
access and interchange with other transport modes for passengers as well as
those travelling with luggage;
·
Establishment of
focal points for meeting places and greeting at terminus entrances and exits;
·
Departure lounges and
waiting areas;
·
Simple and clear
circulation patterns for passenger access to the terminus and to/from the
platforms; and
·
Provision of
commercial opportunities.
2.32
The operation planning
of the WKT also does not require maintenance of rolling stock, and emptying of
sewage tanks in the terminus. In addition to the
above planning consideration, operation requirements of 6 and 9 platform tracks
for short haul and long haul trains respectively would also be considered in
the scheme design of WKT. The track layout design for WKT was therefore
carefully considered such that the effect of a small delay of a long haul train
would not amplify progressively to one or more ‘knock on’ effects to following
trains.
2.33
Following the PPFS, a Preliminary Design Study
was conducted to develop scheme options for the WKT. With regard to the above considerations,
there are two main new schemes were developed and presented in Table 2.5
and Figure
No. NOL/ERL/300/C/XRL/ENS/M50/034.
Table 2.5 WKT Design Scheme Options
Scheme |
Approx. Required Area (ha) |
Appro. Track Level (mPD) |
No. of Platform |
Remark |
PPFS
Alternative Scheme |
12 |
-20 mPD for both shuttle and long haul |
4 shuttle and 10 long haul
platform tracks |
A refuge siding located on the west side of the long haul facility
will be provided. This scheme could not provide the required operation capacity to match
with the overall line capacity. |
Option
1 F2B |
12 |
-21.5 mPD for both shuttle and long haul |
6 shuttle and 9 long haul
platform tracks |
No conflicts with adjacent road networks. |
Option 2 G2 |
12 |
-19 mPD and |
6 shuttle and 9 long haul
platform tracks |
This scheme, a ‘grade separated’ junction between the shuttle and long
haul services, is developed from Option 1 to further improve the junction
capacity and the number of train conflicts. The provision of grade separated junction minimises any conflict
between incoming shuttle and outgoing long haul and vice versa and maximises
throughput of the junction. However, the length of the overunns at the long-haul and shuttle
tracks is limited to just 55 meters which is too short and will impact on
operational safety. Similar to Option 1, there would be no conflict with adjacent road
networks. |
Preferred WKT
Scheme
2.34
Engineering
constraints and operational requirements were predominant factors in the
selection of the preferred scheme.
Factors including headway and platform capacity, train movement
conflict, extension to WKCD, and feasibility of future expansion to
2.35
During the
Preliminary Design, a review was conducted on the PPFS track layout with
respect to the latest planning, operational, and engineering design
requirements. Improvement for the PPFS scheme was identified and the PPFS
scheme was revised, with the objective to:
·
Minimise major conflict
movements between shuttle and long haul trains (i.e. short haul arrival and
long haul Departure);
·
Improve the junction
arrangement to eliminate the conflict movement encountered in grade separated
junction;
·
Straighten the
platforms as much as possible;
·
Increase the shuttle
platform capacity with additional platforms; and
·
Maximise the
flexibility for a future extension to
2.36
Option 2, which made
use of a grade separated junction for long haul and shuttle trains, were also
not selected because neither could provide the flexibility of extending the
overruns for both long haul and short haul trains, which could be a risk to
operational safety. Option 1 was therefore
selected, as it allows the roadworks to be integrated with the station
structure.
Ventilation Buildings/Emergency Access Points
(EAP)
Principle Functions
2.37
Ventilation buildings will serve several purposes.
In normal operation, they will be the air exchange route for the railway
system. In emergency mode, they will be essential components of the tunnel
smoke control system.
2.38
In addition, the ventilation buildings will
serve as a EAP. EAPs will be activated in the event of train fire or incident
inside tunnel and the EAPs will serve as the access points for firemen and
police into the rail tunnels. Parking
areas are provided next to the ventilation buildings for parking of emergency
vehicles. A permanent Emergency vehicle access (EVA) connecting the existing
road networks and the ventilation building will be provided for access by Fire
Services Department and police vehicles in case of incident inside the rail
tunnels. All these provisions are intended
for the safety measures of the XRL passengers.
Types of
2.39
The height of the building is determined by the
functional and operational requirements of the ventilation building. Plant rooms that can be located below ground
have all been designed to be provided below ground to keep the height of the
building to the minimum. However there are plants that cannot be installed
below ground because of the access problem during installation and the
subsequent maintenance. In addition, the
ventilation louvres shall be located at least 5 m above ground in accordance
with FSD regulations.
2.40
With regard to the above constrains, three
generic types of ventilation buildings, as presented in Table 2.6, have been developed for the Project
and modified to suit the tunnel setting at each particular situation.
Table 2.6 Generic Type of Ventilation Buildings
Type |
Max. Height |
Description |
Remark |
Type 1 – Underground ventilation fans with shaft |
Approx. 14m |
l Ventilation
fans will be located directly above the shaft l Equipment
plant rooms will be located below ground within the shaft |
l
This type of ventilation building has a
sufficiently large underground shaft that could accommodate some of the plant
rooms underground. |
Type 2 – Above ground ventilation fans with
shaft |
Approx. 19m |
l
Ventilation fans will be located either
directly above or immediately to the side of the tunnel shaft. l
The vertical ventilation ducts will connect
vertically to the surface. |
l
This type of ventilation building, due to site
constraint, has a smaller shaft that is sufficiently large for accommodating
the tunnel ventilation duct but cannot accommodate equipment and plant rooms
underground. |
Type 3 – Above ground
ventilation fans with tunnel adit |
Approx. 21m |
l
Ventilation building will consist of a long
sloping adit linking ventilation building to the rail tunnels. |
l
Due to geographic constraints, this type of
ventilation building cannot be located directly above the tunnel alignment
and is away from the tunnel alignment.
As a result, a long inclined ventilation adit is required to link to
the ventilation building at ground level to the rail tunnels underground. l
This type of ventilation building is normally
located adjacent to a steep slope. |
Design Criteria for
2.41
Design criteria developed for ventilation
building are presented in
Table 2.7.
Table 2.7 Design Criteria for
Criteria |
Description |
Functional requirements |
·
Location and orientation within
the site of the tunnel ventilation fan (TVF) will be determined by the
connection to the tunnels below the TVF shafts. ·
Allow vehicular access by relevant
authorities, such as Fire Service Department (FSD), police in case of
emergency; and MTRCL for maintenance of the railway related facilities to the
building. ·
Allow access from the building
into the rail tunnel underground. |
Accessibility |
Suitable EVA for fire appliances with water supply and street fire
hydrant. Access road should also be
capable to allow vehicular access and parking for relevant parties, such as
FSD, ambulance, MTRCL. |
Constructability |
·
Avoidance/minimisation of
constructing soft ground tunnel due to safety and building settlement issues. ·
Avoidance/minimisation on
construction risks due to uncertain ground condition and long tunnel. |
Land Acquisition |
Minimisation of affected areas to avoid disruption to local community. |
Site Formation
Levels |
Adequate site formation level
to protect the building and rail tunnels underneath from flooding. |
Environmental |
Avoidance/Minimisation of impact on wetlands, sites of conservation
importance (including |
Operational
requirements |
·
Functional requirements
include ventilation provision for the tunnel, power provision for tunnels,
telecom provision and fire service provision. ·
Adequate size of E&M and
building services plantrooms to avoid overheating of mechanical equipment. ·
Provision of emergency access
point. ·
Minimal impact to adjacent buildings
during operation of tunnel ventilation system. ·
Easy maintenance with heavy
plantrooms located on G/F. ·
Ventilation louvers at the
top-most portions of the vent building. |
Selection of VB/EAP locations
2.42
The risk to
passengers during emergency situations would be reduced by the lowering the
separation between ventilation buildings. However, due to the very rugged
terrain between
2.43
Land selection for
VB/EAP has avoided important wetlands and wildlife habitats, existing graves
and Fung Shui sight lines. Furthermore, use of land within village area,
conservation area, or private lands has been minimized. In order to keep land
requirement for VB/EAP to an absolute minimum, the total footprint and height
of the ventilation buildings have also been minimized as far as practicable.
2.44
Generally, the sites of ventilation
buildings/EAPs will be used as work sites and/or construction/ventilation
shafts during construction phase to minimise the works areas as well as
disturbance to the public and environment.
Sufficient space will be available for parking of emergency vehicles
during the operation phase. Sites suitable for ventilation buildings are
therefore restricted by engineering constraints, land availability,
accessibility and environmental factors.
2.45
Since the traffic connectivity for the
ventilation buildings in the northern section is generally poor, the temporary
construction access roads provided for northern side would be generally used as
a permanent EVA during the operation phase.
2.46
With regard to the above considerations, nine
viable sites have been proposed at
Table 2.8 Summary of Proposed Ventilation
Buildings/EAPs
Ventilation Building/EAP |
Site Location |
Current Usage |
Land Status (OZP) |
Approx.
size of VB/EAP (m) |
Building Type |
Approx. Building Height |
Major Usages during construction and
operation phases |
Requirement of Tunnel Adit |
|
Mai Po |
Open car park |
Other specified uses annotated “Comprehensive
Development to Include Wetland Restoration Area” |
25 x 33 |
Type 1 - Underground ventilation fans within
launch shaft |
14m |
Ventilation, TBM launching and emergency
access |
No |
|
Ngau Tam Mei |
Unused Land |
Green Belt, |
19 x 54 |
Type 2 - Above ground ventilation fans with
shaft |
21m |
Ventilation, TBM reception and emergency
access |
No |
Tai Kong Po Emergency Access Point (TPP) |
Tai Kong Po |
Abandoned pig farm |
Agriculture |
13 x 16 |
N/A |
8m |
EAP, TBM reception or drill and blast
tunnelling works and emergency access |
Not Applicable |
|
Tai Ling |
Unused Land |
Agriculture |
32 x 42 |
Type 3 - Above ground ventilation fans with
tunnel adit |
13m |
Ventilation, drill and blast tunnelling works
and emergency access |
Yes (Approx. 330m long) |
|
Shing Mun Bus Stop |
Bus Stop |
Residential (A) |
22 x 34 |
Type 1 - underground ventilation fans with
shaft |
21m |
Ventilation, drill and blast tunnelling works
and emergency access |
Yes (Approx. 60 m long) |
|
Site next to |
Open car park |
Industrial |
30 x 35 |
20m |
Ventilation, drill and blast tunnelling works
and emergency access |
Yes (Approx. 650m long) |
|
|
Site in the north of Nam Cheong Station PTI |
Open car park |
Comprehensive Development Area (CDA) |
20 x 42 |
Type 1 - Underground ventilation fans within
launch shaft |
14m |
Ventilation, crossover and emergency access |
No |
|
Site next to |
Open car park |
Road |
21 x 36 |
Type 1 - Underground ventilation fans with
shaft |
13m |
Ventilation and TBM retrieval |
No |
|
Site next to |
Open area |
Open Space |
15 x 74 |
Type 1 - Underground ventilation fans with
shafts, and an Emergency Assembly Area |
19m |
Ventilation and emergency access |
No |
2.47
Apart from the use of a ventilation point and
emergency access point during operation phase, the site will also be used as a
TBM launching shaft towards Ngau Tam Mei and possibly towards Mainland during
construction stage.
2.48
The selected location of MPV is a formed land, which
is currently an open car park for trucks and coaches, to avoid any direct
impact to ecological habitats. The
location of MPV site is constrained by the geological constraints as it cannot
be moved either northwards to Mai Po wetland or southwards to developed private
lands. The currently proposed location
is therefore considered to be the most suitable location which meets the
ventilation and fire safety requirement. The environment in this area will be
enhanced by the architecture and landscape design of the ventilation
building.
2.49
As the site sits on an area of low lying flat
land, flood protection has been considered and thus the site formation level of
ventilation building will be raised about 2m high to allow for a flood
protection level of 1 in 200 years, according Drainage Services Department
(DSD) Stormwater Drainage Manual. Since MPV is located close to Wetland
Conservation Area (WCA), Type 1 ventilation building will be adopted to
minimise the visual and ecological impact.
2.50
Apart from being a permanent ventilation point,
the proposed site of NTV will also be used as a TBM retrieval shaft and a
construction shaft for drill and blast tunnelling works during the construction
phase. It is located near the foot of the northern slopes to Kai Kung Leng and
immediately adjacent to the public access road to Ngau Tam Mei Water Treatment
Works.
2.51
The selection of this site would eliminate the
need for soft ground mined tunnel thereby reducing the construction safety
risk. Apart from minimizing direct
impact on village houses to the practicable extent, formation of a new
construction access road would not be required as the existing WSD access road
can be utilised. In this way,
environmental impacts pertinent to the construction of this ventilation
building could be minimized.
Tai Kong Po
Emergency Access Point (TPP)
2.52
Given the distance between NTV and the
ventilation building to the north of ERS is about 4km, as such only an EAP is
required to be provided at Tai Kong Po for satisfying fire safety strategy and
no ventilation fan will be provided at the TPP.
2.53
The
proposed location of TPP is located in an agriculture zone, currently an
abandoned pig farm. This site will be
used for TBM retrieval and for drill and blast tunnelling works during the
construction phase. As the condition of
the existing access road is poor, road improvement works will be required for
future permanent EVA and temporary construction access.
2.54
The PHV will be located in Tai Ling, away from
Tse Uk Tsuen Works Area, which will be used as a temporary TBM retrieval shaft. The PHV site will be used for the
construction of ventilation adit, which support for drill and blast tunnelling
works of the main tunnels, to minimise the ecological impacts on agricultural
habitats. The PHV is located away from
the existing nearby occupied houses as far as practicable. An ventilation adit will link the ventilation
building with the tunnel. Similar to
other sites, the temporary construction access road will be converted to a
permanent EVA during the operational phase.
2.55
A ventilation building will be required
immediately to the south of Tai Mo Shan in order to achieve the tunnel ventilation
and emergency safety access requirements.
2.56
The SMV was initially located at the northern
end of
2.57
With the proposed works area at Shek Yam, a
shorter adit together with a shaft could be constructed to provide access to
the tunnel. As such, the need for a long adit at Shing Mun could be removed but
the tunnel ventilation requirement still remains. Given the site constraints identified at the
site next to
2.58
The site of KCV will be used as a ventilation
point and emergency access point for the tunnel section during operation, and
an adit for drill and blast tunnelling works will be provided during
construction.
2.59
The site was avoided to be located at
2.60
A TBM launching shaft for two directions (south
towards WKT and north towards
2.61
As NCV will be located in a site of Hong Kong
Housing Authority (HKHA), which will be developed to a residential
development. The site area therefore has
been reduced to absolute minimum, without EVA parking and space for
landscaping. Vehicles attending to an
emergency incident will be parked in future adjacent areas under the planning
by Hong Kong Housing Authority.
2.62
Given the limited available area in Mong Kok
West, the location of MKV will be the vacant site adjacent to
2.63
The proposed ventilation building complex will
serve as a ventilation point, emergency evacuation, emergency assembly area,
accommodation for railway plant facilities, and other supporting facilities.
The WKV will be located in an open area bounded on the west by
Stabling Sidings
Principle
Functions
2.64
In order to
accommodate with increased long haul train services to Hong Kong without
affecting the overall line capacity to
·
Stabling requirements for long haul trains to support the operation of
the West Kowloon Terminus;
·
Overnight stabling for
long haul trains, for return journey back to the Mainland on the following day;
·
Routine maintenance checks and inspections for long haul trains and
shuttle trains during stopping over in
·
Stabling for short
haul trains both at night and daytime off-peak;
·
Central
infrastructure structural maintenance for the XRL and trackside maintenance;
and
·
Cleaning and
inspection services for short haul and long haul trains.
2.65
Given the limited stabling capacity at the WKT,
an alternative location must be assigned.
In addition, a small scale engineering depot for necessary maintenance
facilities (e.g. maintenance of permanent-way, overhead line, signalling and
control, etc) and engineering trains will be required for maintenance of infrastructures
and buildings, as well as handling of emergency situation such as derailment or
emergency servicing.
Preferable
Location
2.66
The Mainland Section of the XRL would be
busy with networks linking to other cities in
2.67
As discussed in Section 2.41, alignment option N2 is the preferred alignment
with the at-grade stabling sidings provided at
an area in Shek
Kong. With sufficient length of the
alignment between the toe of Tai Mo Shan and Shek Kong, the alignment could be
gradually rise up to a more shallow
alignment in Shek Kong, such that the stabling tracks could be developed within
the proposed site. In addition, the site
is large and flat with
relative low terrain and the least social impact, this site is suitable for
developing stabling sidings and emergency rescue station.
As discussed in Section 2.41, provision of stabling
sidings at Shek Kong would minimise impact to the environment and
public, as compared with other options.
The proposed site will have the least impact to local community in the
Shek Kong area.
Layout and Size of
Stabling Siding
2.68
In order to achieve the operational requirements described
in Section 2.77, the SSS will comprise:
·
Eight stabling
sidings (approx. length 520m each);
·
Four covered running
maintenance sidings (approx. length 480m each);
·
Three permanent-way
sidings (approx. length 300m each);
·
Workshops and plant
rooms;
·
Stores (including
dangerous good stores);
·
One office building
with control centre for the compound, gatehouse and canteen;
·
Stabling siding for
emergency rescue bus;
·
Shunting tracks; and
·
2.69
In addition, a total of six locomotives will be stabled at
the SSS. The associated facilities will
comprise:
·
Two
·
Refuelling tank; and
·
Locomotive
maintenance shed and workshops.
2.70
Only minor maintenance activities and inspection
will be carried out in stabling sidings. The proposed layout of SSS has been designed to minimise the site area to
approximately 20 hectares to accommodate the above-mentioned facilities. Given that the layout is limited by site area
as well as the existence of ERS, the proposed layout is an optimum scheme to
accommodate all the operation requirements of XRL. Schematic layout and sections are presented in Figure Nos. NOL/ERL/300/C/XRL/ENS/M50/017 to 020.
2.71
As the estimated flood levels are higher than
the existing ground levels at the SSS / ERS and cut and cover approach tunnel
to the SSS / ERS, river training and culverting of the existing river on the
west side of the SSS and provision of box culvert along the eastern edge of the
ERS will be required for flood protection.
The SSS site falls within Drainage Basin 9 of Yuen Long, Kam Tin, Ngau
Tam Mei and Tin Shui Wai Drainage Master Plan Study (DMP), in line with the
design principle of the DMP, a flood protection level of 1 in 200 years has
been adopted for drainage design in SSS.
2.72
The peripheral drains - a box culvert along the
eastern edge of the SSS will be provided to take a 200 year storm. Lesser storm will be carried by the widened
existing channel and box culvert along the western edge of the SSS. Such flood protection measure would ease the
potential flooding problem at the future SSS, ERS and adjacent area.
Emergency Rescue Station
Principle Function
2.73
An open air emergency rescue station (ERS) is
required for fire fighting and evacuation of passengers in case of emergency at
approximately the mid-point of the alignment.
2.74
The ERS is designated as a
place for trains to stop and to discharge passengers either to another train in
the event of mechanical problems or evacuation to an open air platform in the
event of a train fire. The ERS will be a depressed box with an open top
for safety reason. Firemen’s lifts and staircases will be provided to allow ease of access for
firemen.
Preferable
Location
2.75
To provide an efficient and immediate
response and rescue for any incident occurring inside
the long tunnel between WKT and Futian Station, the ERS should be located near the
mid-point of the alignment as far as practical.
The ERS will be combined with SSS to minimise the land take by
staggering the approach and the main tunnels, sharing the building maintenance
resources, and to facilitate a prompt response to any incidents/accidents with the site links to convenient public access
(i.e.
Layout and size of
ERS
2.76
The length of the ERS
with open roof is about
Train System
2.77
High-speed rail system is generally defined as
having a maximum speed of over 200 km/h or higher. All types of high-speed trains are
electrically powered via overhead lines.
2.78
The 140-km XRL will
run from the WKT in Hong Kong to Shibi in
2.79
Two types of train
services will be provided by XRL:
·
Short
haul services between WKT and Longhua (LOH) in Shenzhen, Humen (HUM) in
Dongguan and Shibi (SHB) in
·
Long
haul services between WKT and various major cities in the Mainland.
2.80
A maximum operating speed of 200km/h will be
adopted for the Project. This is in line
with the current design of the Mainland Section of the XRL between LOH and the
boundary.
2.81
China Railway High-Speed (CRH) trains will be
used in XRL and will be provided by the relevant operation entities in the
Mainland, and the details of the CRH trains were not available during the
preparation of EIA Report.
2.82
The selection of trackform types will be based
on environmental, operational and maintenance considerations. Discussion with
Mainland counterparts is being conducted to ensure compatibility along the
entire line. The preliminary design of
the trackform type is a trackform of embedded concrete sleepers with slightly
resilient fixings on top. Appropriate
vibrating mitigation trackform for a high-speed railway are being further
studied for areas where ground-borne noise would exceed at sensitive
receivers. A 600mm deep provision will
be provided for the tunnel to allow for further enhancement of mitigation
measures, if later studies confirm such requirement.
Tunnelling Methods
2.83
The primary tunnel
construction forms to be adopted for the Project are:
·
cut-and-cover
construction;
·
drill-and-blast
construction; and
·
bored
tunnelling construction, in which the tunnel would be excavated mechanically
with a tunnel boring machine (TBM).
Cut-and-Cover
Construction Method
2.85
In urban areas, the trench can be covered with a
temporary deck following excavation to maintain traffic management, if
required.
Drill-and-Blast
Construction Method
2.86
Drill and blast methods are the conventional
method of excavation for large face area hard rock tunnels within
2.87
The use of explosive for the bulk excavation of
hard rock is the most efficient method available in the market. As compared with cut-and-cover method, drill
and blast construction will involve less construction plant items and reduce
the duration of overall long term noise from the works, thus reduce impacts on
residents living near construction shafts or above the tunnel route.
2.88
The adoption of mechanical or chemical breaking
systems however requires additional rock drilling and the slow process will
extend the construction period and the noise impact. Rock tunnel boring machines may be a practical
alternative method but the tunnelling machine size is significantly larger than
any utilised in
2.89
With careful control of the quantity of
explosives, the generated vibration levels on existing structures (buildings,
roads, utilities etc) can be well controlled. In addition, the
duration of a blast is very short (less than 6 seconds) and infrequent (every
12 to 16 hours), and therefore both airborne and ground-borne noise impact
induced by blasting would not be a concern compared with the use of power
mechanical plant. Drill and blast is well proven technology for tunnel
construction in hard rock.
Bored Tunneling
Construction Method
2.90
Tunnel boring machines (TBM) will be utilised
for the soft and mixed ground tunnels. The construction methodology eliminates
the need for surface access except at launching and retrieval shafts thus
minimising surface disruption. The machine can be utilised for short lengths of
rock sections of the tunnels but is not as efficient or flexible as tradition
drill and blast techniques.
2.91
The selection of the appropriate
tunnelling machine will depend on many issues, including the ground conditions,
contractor’s experience, tunnel size and tunnel alignment. Given the ground conditions anticipated, a
shielded TBM erecting an un-drained (i.e sealed) segmental lining will be
specified to ensure the stability of the tunnel face, safety of the workers,
minimize the impact to the groundwater regime and limit surface settlement.
Considerations of
Preferred Construction Method
2.92
The preferred construction method would be
predominantly determined by engineering factors including safety, geological conditions, site
conditions/constraints, accessibility, programme and cost-effectiveness.
2.93
Environmental
considerations have also been considered to minimise the potential ecological,
noise, air and water quality impacts as well as waste generation.
General
Geography
2.94
The
General
Description of Site Conditions
2.95
With the exception of
the natural terrain of Kai Kung Leng, within the
2.96
The Shek Kong area,
located to the north of
2.97
With the exception of
Lai King Hill, the area to the south of Tai Mo Shan and
Environmental
Considerations
2.98
Potential environmental issues associated with
each tunnelling methods have been reviewed and a summary of the benefits and
dis-benefits of construction methods is presented in Table 2.9.
Table 2.9 Benefits and Dis-benefits of Construction
methods
Construction Method |
Benefits |
Dis-benefits |
Cut-and-cover construction method |
·
Accommodation of different sizes of works areas |
·
More construction
plants will be involved such that this would generate relatively more noise
and dust impacts ·
Sensitive receivers will be affected over a longer construction period ·
Require recycling of bentonite for diaphragm wall construction ·
Larger amount of spoil required to be disposed of |
Drill and blast construction method |
·
All works underground to minimize the disturbance to
land, wildlife and public activities at ground level throughout the period of
construction ·
Lesser spoil to be disposed of, as compared with
C&C method ·
Above-ground works only required for portal
construction ·
Noise impact could be minimized with the provision
of temporary doors and barriers at the portals and shafts |
·
Higher vibration to adjacent sensitive receivers,
but could be mitigated through blast design and careful monitoring ·
Duration of blasting would be short (less than 6
seconds) and infrequent ·
Require provision of site explosives magazines for
storage of explosives ·
Transportation of explosives on public roads |
Bored tunnelling
construction method |
·
All works underground to minimize the disturbance to
land, wildlife and public activities at ground level throughout the period of
construction ·
Lesser spoil to be disposed of, as compared with
C&C method ·
Noise impact could be minimized by provision of
temporary decks over the portal ·
Above-ground works only required for construction of
retrieval and launching shafts ·
Comparatively lower vibration impact ·
Lesser impact on groundwater level with the
installation of water tight concrete tunnel lining in pre-cast segments |
·
Preferable for 24hr operation to ensure stability of
ground ·
Requires additional land for the handling of slurry
that require processing before disposal ·
Potential adverse ground-borne noise impact when
excavating in rock below existing buildings |
Preferred
Tunnel Construction Methods
2.99
The anticipated
geological conditions along the alignment are critical in the selection of the construction
methods. The type of soil, rock and the
presence of water have a fundamental impact on the selection.
2.100
TBMs are commonly used for the excavation of long
tunnels in soft and hard rock. The
advantages of excavation by TBM in rock tunnelling are relatively high daily
production rates as compared with drill and blast methods, a controlled
excavation profile, and low vibration and noise generation. However, the TBM tunnelling would generally
involve continuous operation, which often would be a main source of
ground-borne construction noise impact. In addition, procurement of TBM is expected to
be about 18 months, due to limited number of suppliers, shortage of
manufacturing capability and overall global demand within the buoyant
tunnelling market. As such, the daily production rate of TBM will be relatively
higher than that for blasting but the overall production rate will be lower for
short tunnel sections.
2.101
Excavation by drill and blast
method is not a
continuous operation and in general has lower daily production rates than TBM
tunnelling. Drill and blast operation will have less lead
time required and there are programme advantages. Drill and blast tunnelling in rock is however
better to manage ground risk issues but magazines and ventilation adits will be
required for supporting the blasting.
2.102
With consideration of
the above-mentioned engineering constraints, environmental benefits and
dis-benefits, and programme risks, drill and blast construction method will be
adopted for rock tunnels while bored tunnelling method will be adopted for
mixed and soft ground tunnels.
Cut-and-cover construction method will be adopted for the areas which
require this conventional method, such as ERS, ventilation building/vent shaft/
EAP.
2.103
The construction
method for each tunnel section has therefore been selected, based on
engineering and site constraints. The
proposed use of TBM and drill and blast tunnelling has been maximised to reduce
impacts from above-ground works. The majority of soft ground and mixed ground
tunnel sections will be constructed by bored tunnelling method. The remainder
of the soft and mixed ground tunnel segments; principally the ERS, the southern
approach to the ERS, the SSS approach, and the tunnels to the south of Hoi Ting
Road will be constructed by cut and cover method. The rest of the alignment
through
2.104
The preferred
construction methods of different tunnel sections is summarised in Table
2.10 and
presented in Figure
No. NOL/ERL/300/C/XRL/ENS/M50/035.
Table 2.10 Preferred Construction methods
Construction Method |
Tunnel Sections |
Selection Reasons |
Cut-and-cover construction method |
· ERS and SSS approach
tunnels · Nam Cheong TBM
launching shaft · WKT approach tunnels |
· Engineering constraints |
Drill and blast construction method |
· Ngau Tam Mei to Tai Kong Po Tunnels · Tse |
· Geological and
engineering constraints · Minimisation of works areas · Avoiding works areas located in ecological sensitive areas, such as · Minimisation of potential disturbance to the public |
Bored tunnelling
construction method |
· From Boundary to Ngau Tam Mei Tunnels · Tai Kong Po to north of
ERS Tunnels · South of ERS to Pat
Heung Tunnels · |
· Geological and
engineering constraints · Comparatively shorter construction period · Minimisation of works areas · Avoiding works areas located in ecological sensitive areas, including
Mai Po wetlands, agricultural land and grasslands at Wo Shang Wai, Mai Po
Inner Deep Bay Ramsar Site, Tai Mo Shan Country Park, · Minimisation of potential disturbance to the public |
2.105
The sequences of works
associated with the proposed tunnelling works are constrained by the
engineering requirements. A shaft is
required for launching and retrieval of TBM, and a portal for drill and blast
construction. Conventional mechanical
sequential excavation & support will be used for the construction shafts
until rock is reached. The drill and
blast construction is likely to be a combination of mechanical, pneumatic or
hydraulic splitting or expanding grout techniques. For cut-and-cover construction, the construction
sequence is discussed in Section 2.97.
Works Areas
Requirements and Locations
2.106
To minimise the
potential disturbance and impact to the public and environment, the works areas
are typically located at the site of the permanent ventilation buildings,
though in the case of works areas in Tse Uk Tsuen and
2.107
Shek Yam Works Area
is used as a main production site for the Tai Mo Shan tunnel due to the
limitation of available space and the problems of deep shaft construction
associated with Shing Mun Works Area.
2.108
Given the large scale of the Project, additional
works areas would be required for supporting the construction and have been
identified for site office, storage of materials, nurseries and site explosives
magazines.
2.109
A summary of works
areas currently envisioned for supporting the construction of the Project is
presented in Appendix 2.2. The locations of works areas have been
selected with consideration of their accessibility and suitability for
construction works and future permanent facilities. The above-ground works
areas have been minimised to reduce and avoid the potential environmental
sensitive areas including Mai Po Inner Deep Bay
Ramsar Site, Deep Bay Wetland Conservation Area and
2.110
The construction
sequence has been designed to minimise concurrent activities so as to reduce
cumulative impacts as far as practicable.
The following sections present the construction methods and sequences of
works proposed for the Project facilities and other supporting facilities
required for the construction of the Project.
2.111
The WKT is
approximately 700m in length and
2.112
The formation level
for the bulk excavation of the terminus will be at approx. -24mPD, which is
approx. 28m in depth. The excavation
works is adjacent to the harbour side, high ground water level regimes owing to
both tidal effects and rainwater infiltration is anticipated. A permanent diaphragm wall will be
constructed to provide lateral support to the ground and limit groundwater
inflow into the construction site. In view of deep excavations, a stiff lateral
support system must be provided to control the lateral movement of the
cofferdam wall, as well as the settlement of adjacent ground.
2.113
The WKT site will be
broadly split into five different zones as presented in Figure No.
NOL/ERL/300/C/XRL/ENS/M50/030. Given the considerations of large site area, depth of excavation, highly
varied site conditions and geology for the construction of the terminus,
different construction methods and lateral support systems will be adopted for
different zones.
2.114
In Zones 1 (WKCD
area), the excavation lateral support is anticipated to be bottom up open cut
method with ground anchors. The typical construction sequence is:
·
Install
diaphragm wall at the boundary of station, and construct piled foundation and
socket H-piles column at region of open cut;
·
Excavate
and install layers of ground anchors stage by stage until the final excavation
level is reached; and
·
Construct
station structure using bottom up method.
2.115
In Zones 2 & 3,
(Site A area), the excavation lateral support is anticipated to be pseudo
top-down open cut method. The typical construction sequence is:
·
Install
diaphragm wall at the boundary of station and construct piled foundation and
socket H-piles at region of open cut;
·
Form
temporary cut slope with angle varying from 26 to 40 degrees depending on
different soil types;
·
Excavate
the central portal of the station and construct central portal of the station
structure by bottom-up method;
·
Cast
ground floor slab at the perimeter of the site;
·
Excavate
soil below ground floor at perimeter of the site until B1 formation level is
reached;
·
Cast
B1 floor slab at the perimeter of the site;
·
Repeat
the excavation sequence at the perimeter of the site downward until the final
formation level is reached; and
·
Cast
the final floor level at perimeter of site (i.e. B3).
2.116
In Zones 4 (Track Fan
Area), the excavation lateral support is anticipated to be a combination of
bottom up and top down method. The typical construction sequence for top down
is:
·
Install
diaphragm wall and construct piled foundation and socket H-piles at ground
level;
·
Cast ground
floor slab as lateral support to the wall with some openings for mucking
out;
·
Install
temporary traffic deck;
·
Excavate
soil from below the ground floor slab until B1 formation level is reached;
·
Cast
B1 slab and repeat the excavation sequence for subsequent levels until the
final formation level is reached; and
·
Cast
the floor slab of track level.
2.117
In Zones 5 (Approach
Tunnel Area), the excavation lateral support is anticipated to be bottom up
method. The typical construction sequence is:
·
Install
diaphragm wall at the boundary of approach tunnel;
·
Excavate
and install layers of struts stage by stage until the final excavation level is
reached. Preloading of steel shoring may
be required to control wall deflection; and
·
Construct
tunnel box structure by bottom up method, and remove steel struts stage by
stage.
2.118
Rock will be
encountered in two areas (Zones 1 and 3). The use of explosives is being
reviewed and might be adopted. This will
be confirmed in further investigation.
In event that explosives are not adopted, drill and splitting of rock by
hydraulic machine will be used for breaking and removing rock.
2.119
The disposal of large
volume of excavated material shall be disposed by means of barges through the
barging point situated at the seafront of
2.120
The anticipated
construction sequence for the intake and outfall units of the seawater cooling
system is summarised below:
·
Install
a floating silt curtain at the locations of the proposed intake and outfall
units to avoid soil from the landside going into
·
Excavate
on the land side of the existing pre-cast wall units and install protective
measures (e.g. grouting, sheetpiles, etc) to avoid fill materials entering the
harbour;
·
Remove
the existing vertical wave absorbing seawall units by cranes and excavate the
fill materials down to the required level for installation of the new culvert
precast units;
·
Place
the precast units (the opening of two outermost precast units sealed off);
·
Rebuild
the seawall with concrete blocks above the precast units and re-construct the
concrete backing and coping;
·
Backfill
the precast units;
·
Complete
the construction of the land side section of the culvert;
·
Remove
the seal off walls in the outermost precast units; and
·
Backfill
to the required level and remove the protective measures.
Shafts, adits and Ventilation Buildings/EAPs
2.121
Shafts and adits to
be provided along the alignment, will be used for tunnel ventilation during the
construction and operational phases.
These structures will also provide access for tunnelling equipment,
permanent material and spoil removal.
2.122
Shafts and adits will be typically located at permanent ventilation buildings to minimise
the potential disturbance and impact to the public and environment. Typically the shaft will be sized for
envisaged construction methods that will require sizable openings and clear access
space for the delivery and removal of equipment (e.g. TBMs), spoil handling,
material delivery and plant maintenance.
Based on requirement of the
construction methods and access needs, the sizes of these works sites have been
minimised as far as practicable.
2.123
Construction shafts
at Tse Uk Tsuen and
Table 2.11 Locations of Construction Shafts and Adits
Shaft/Adits |
Principle Activity |
Occupation |
Future Usage |
Mai Po Shaft |
Launching of TBM |
Permanent |
|
Ngau Tam Mei Shaft |
Retrieval of TBM and drive drill and blast
tunnel |
Permanent |
|
Tai Kong Po Shaft |
Retrieval of TBM and drive drill and blast
tunnel |
Permanent |
Tai Kong Po Emergency Access Point |
Tse |
Retrieval of TBM |
Temporary |
The site will be reinstated and returned to
the Government |
Pat Heung Adit |
Drive drill and blast tunnel south |
Permanent |
|
Shing Mun Shaft |
Shaft construction |
Permanent |
|
Shek Yam Shaft and Adit |
Drive drill and blast tunnel north and south |
Temporary |
Site will be reinstated and
returned to the Government |
Kwai Chung Adit |
Drive drill and blast tunnel north and south |
Permanent |
|
|
Retrieval of TBM |
Temporary |
The site will be reinstated and returned to
the Government |
|
Launching of TBM |
Permanent |
|
|
Retrieval of TBM |
Temporary |
Part of the shaft
will form permanent cut-and-cover tunnel |
Mong Kok West Shaft |
Construction of ventilation shaft |
Permanent |
|
2.124
Shafts and ventilation buildings/EAPs will be typically
constructed by cut-and-cover method, and the adits by drilling method.
Diaphragm wall, sand drains, and struts as the temporary excavation and
lateral support system will be involved during the construction of shaft. Casting of diaphragm wall, which is a
continuous underground concrete wall, will be conducted before excavation
works. This wall would largely limit
groundwater entering into the excavation area, and therefore minimise the
groundwater drawdown outside works boundary.
Subsequent to the completion of diaphragm wall and sand drain
installation, if necessary, a series of observation wells, pump wells and
recharge wells will be installed prior to the commencement of excavation work
for mitigating groundwater drawdown.
2.125
The Ventilation buildings for tunnel ventilation
will be built on top of a shaft or adjacent to an adit which will be in use to
support the tunnel construction. The
buildings will be simple reinforced concrete structures with rooms to house the
ventilation fans and support systems. The construction works will include the
civil structure and all the Mechanical, Electrical & Plumbing (MEP)
provisions. On completion of the structure and initial MEP provisions, the
tunnel ventilation fans, communications systems, security and any other
specialist systems required for the railway will be installed.
SSS and ERS
2.126
The SSS is an
at-grade facility to the west of the ERS box. Preparation of the site will
require a cut-and-fill exercise to level the site to around +14mPD. The
northern part of the site will require some filling. The future buildings within SSS will be
founded on piles or spread footings subject to the loadings and ground
condition to be confirmed in detailed design stage.
2.127
The construction of
the ERS together with the associated approach tunnels will adopt a conventional
bottom up construction within permanent and temporary cofferdams. The ERS cofferdam will be formed by permanent
diaphragm walls with lateral supports.
2.128
River training and
culverting of the existing river on the west and east side of the facility will
be required to prevent flooding. A new
box culvert will also be established to the east of the ERS. Temporary river diversions will be conducted
in sections and phases in order to complete the drainage system for the whole
facility, for minimising water quality impact at the downstream.
2.129
The construction of
roads and buildings are assumed to commence once the excavation of the ERS box
has been completed, along with drainage and traction power facilities. A
suitable formation will be prepared to allow the construction of the ballasted
stabling tracks. The works will include
drainage, ducting and the foundations for the overhead line masts.
Cross Passages Ground Treatment Works
2.130
As a safety requirement, cross passages (CP)
between running tunnels would be provided. In the event of a fire in one of the
tunnels, the non-incident tunnel will provide evacuation route and refuge for
rail passengers.
2.131
Construction method of the CP will depend on the
tunnel type and ground condition. CPs in rock tunnels are mostly in the form of
a cross passage door across the dividing wall between the main tracks. For the CPs in soft or mixed ground
conditions, stabilization works will be required to ensure the ground
stability, the integrity of the tunnel and the safety of the workforce. An appropriate construction method would be
selected for each CP in respect of particular ground conditions to avoid any
potential impacts on environmental sensitive areas such as Mai Po Inner Deep
Bay Ramsar Site,
2.132
The CPs are at a nominal distance of 250m apart
along the route length, there are about 100 cross passages will be formed along
the 26km alignment.
Barging Points
2.133
It is anticipated that the excavation of the
tunnels and associated structures will generate approximate 9.1 Mm3
of spoil from all works areas. Six
barging points have been proposed to transport the spoil generated from the
Project to the Mainland or other locations for reuse/disposal, and an existing
barging point at Pillar Point will be used for transport spoil to Mainland/public fill reception
facilities. A
summary of the proposed new barging points is presented in Table 2.12.
Table
2.12 Proposed New Barging Points
Barging Point |
Location |
No. of Ramp |
Serving Area |
Current Usage |
BP1 |
West Kowloon |
2 (new, same
locations as adopted for KSL construction) 3 (new) |
WKT |
Nil |
BP2 |
Nam Cheong |
3 (new) |
WKT, |
Public cargo
handling |
BP3 |
Rambler Channel |
2 (new) |
Kwai
Chung, |
Nil |
BP4 |
Siu Lam |
2 (new) |
SSS
and ERS |
Nil |
BP5 |
Lung Kwu Sheung Tan |
2 (new) |
Ngau Tam Mei, Tai Kong Po and Mai Po |
Loading and unloading of construction materials |
BP6 |
Tsing Chau Tsai |
2 |
Pak Heung
and Shek Yam |
Loading and unloading of construction materials |
2.134
Cable stayed structure with a jig or similar
method will be adopted for the construction of barging ramps where located
close to sloping seawall at West Kowloon (BP1). A heavy spanning steel truss
hung by cables will be used for the access of trucks to dump excavated material
onto the barge. Since this area prevents barges from mooring against the sea
wall, a pontoon will be kept such that barges can berth against it instead of
against a guide pile allowing discharge of materials from the barging
ramp. This construction method will be
adopted to avoid disturbance of seabed and minimise potential impact on water
quality induced by marine works.
2.135
Loading ramps will be constructed at other
barging points. Enclosed tipping hall
and wheel washing facility will be provided at each barging point to minimise
the construction dust impact.
2.136
Minor dredging works will be required to form a
berthing area in Lung Kwu Sheung Tan.
The dredging depth would be 2m deep from the existing seabed level and a
maximum dredging rate of about 2,000m3/day is anticipated.
Nursery Area
2.137
Temporary nursery areas at Siu Lang Shui and So
Kwun Wat will be provided for the transplanted trees at an early stage of
construction to allow trees to grow during the construction period. Only minor works including erection of
fencing and installation of irrigation pipes and surface drainage will be
carried out in these areas.
Temporary Site Explosives Magazines
2.138
The construction of
the Project will involve substantial amounts of bored tunnel excavation of
which about
2.139
It is estimated that blasting cycle times are
either 12 or 16 hours and therefore over a two-day period there will be three
or four blast cycles per face. Drill and blast tunnel excavation will be
carried out from six work sites, three in the northern
2.140
It is estimated that
the required explosives storage are 8
2.141
With consideration of
above factors, together with the limited daily delivery arrangement
available from Mines Division of Civil Engineering and Development Department
(CEDD), a list of potential
locations for explosives magazine sites have been identified, reviewed and
short-listed for further detailed study and discussion with Mines Division. The
magazine site selection process is documented in Working Paper No. 13A –
Explosives Magazine Site Selection.
2.142
Two project-specific site explosives magazines at
Tai Shu Ha Road West and So Kwun Wat are selected as necessary to store the
explosives (refer to Appendix 13.1 –
Quantitative Risk Assessment for details of explosive storage and delivery
arrangement). A Quantitative Risk Assessment
(QRA) has been carried out to assess potential risks associated with the
preferred site explosives magazines with details given in Section 13 of this EIA study.
2.143
The magazines will be designed in compliance
with the general requirements of Mines Division, as defined in their document
"How to apply for a Mode A Explosives Store Licence".
2.144
The site formation works will include clearance
of vegetation and slope works for both sites, and a stepped site formation
profile will be constructed at So Kwun Wat.
Both sites will be surfaced with hard standing and enclosed with
security fences. Utility connections
will be made to the local networks. The
magazine structures will comprise brick built / reinforced concrete buildings
on shallow foundations. Mounding around
the buildings will be constructed, using sandbags or earth bank.
2.145
The proposed
construction dates are tentatively scheduled as shown in Table 2.13. The construction
works would commence in December 2009 and the overall project completion is
anticipated to be in 2015. A
preliminary construction programme is presented in Appendix 2.1. The
assessments in this report have been based on this construction programme.
Table 2.13 Tentative Civil Construction Works Schedule of Key Elements
Location |
Tentative
Commencement Date |
Tentative
Completion Date |
Tunnel |
|
|
Mai Po to Boundary |
August
2010 |
June
2015 |
Mai Po to Ngau Tam Mei |
August 2010 |
December 2014 |
Ngau Tam Mei to Tai Kong Po |
August 2010 |
December
2014 |
Tai Kong Po to Kam Tin |
July
2010 |
December 2014 |
Kam Tin to Shek Yam |
December
2009 |
December 2014 |
Shek Yam to |
March
2010 |
July 2014 |
|
December
2009 |
December 2014 |
Mong Kok West to WKT |
December
2010 |
December 2014 |
Ventilation Building/Emergency Access Point |
|
|
|
August
2010 |
December 2014 |
|
August
2010 |
December
2014 |
Tai Kong Po Emergency Access Point |
December
2009 |
December
2014 |
|
June
2010 |
November
2014 |
|
May
2010 |
June
2014 |
|
May
2010 |
July
2014 |
|
May
2013 |
December 2014 |
|
May
2010 |
June
2014 |
Other Facilities |
|
|
Shek Kong Stabling Sidings and Emergency Rescue
Station |
July
2010 |
December 2014 |
|
December
2009 |
December
2014 |
Concurrent
Projects
2.146
There are several major concurrent designated
projects in the vicinity of the Project’s works areas, as summarised in Table
2.14. At this stage, consideration of
concurrent projects for cumulative environmental impacts will only take into
account those with available implementation programmes. Cumulative impacts from the planned and
existing major concurrent projects, if any, have been assessed in the individual
sections of this EIA study.
Table 2.14 Major Concurrent Projects
|
|
Project |
Planned
Construction Period |
Proposed Comprehensive Development at Wo Shang Wai, Yuen Long |
2008 to 2012 (1) |
Central |
2012 to 2016 (2) |
|
2013 to 2016 (3) |
Road Works at |
2012 to 2014 |
Construction of Cycle Tracks and the associated Supporting Facilities
from Sha Po Tsuen to |
Mid 2009 to Early 2012 |
Upgrading of Remaining Sections of |
2011 to 2016 |
Yuen Long & Kam Tin Sewerage and Sewage Disposal |
2009 to 2013 |
(1)
Section 16
Planning application was submitted in 2008 and approved by TPB on
(2)
Details of construction programme and design of
CKR are not available during the course of EIA study. Cumulative impact from the construction and
operation of CKR could not be evaluated during the course of EIA study.
(3)
Details of construction programme and design of
WKCD are not available during the course of EIA study. Cumulative impact from the construction and
operation of WKCD could not be evaluated during the course of EIA study.
2.147
Considering the importance of views and support
of the community in the development of railways, a public consultation
programme was launched by the Project Proponent in conjunction with the
preliminary design which commenced in May 2008 to consult public on the railway
scheme to design the railway scheme will best suit the needs of the
community. The public consultation
programme consists of two rounds which commenced in May and September 2008
respectively with respective district councils and rural committees, also the
gazette of the railway scheme on 28 November and
2.148
First round of public consultation was conducted
from May to July 2008 with the relevant District Councils (DCs) / Rural
Committees (RCs) as listed below:
·
Sham Shui Po
District Council
·
Yuen Long
District Council
·
Yau Tsim Mong
District Council
·
Sha Tin District Council
- Traffic and Transport Committee
·
Tsuen Wan
District Council - Traffic and Transport Committee
·
Kwai Tsing
District Council
·
Kam Tin Rural
Committee
·
Pat Heung Rural Committee
·
San Tin Rural Committee
2.149
After the commencement of Preliminary Design
Study, further information such as alignment, ventilation buildings and works
areas were provided in the second round of public consultation from September
to November 2008 with the relevant District Councils/Rural Committees as listed
below:
·
Kwai Tsing District
Council
·
Sham Shui Po District Council
·
Tsuen Wan District Council
·
Yau Tsim Mong District Council - Traffic and
Transport Committee
·
Yuen Long District Council
·
Sha Tin District Council - Traffic and
Transport Committee
·
San Tin Rural
Committee
·
Kam Tin Rural Committee
·
Pat Heung Rural Committee
2.150
A total of 33 and 29 meetings/consultations were
conducted with DCs/RCs and local residents respectively, since the planning
stage of the Project. The public was
generally supported the development of the Project and their views/concerns
were also considered in the preliminary design stage and will also be
considered/addressed in detailed design stage.
2.151
In addition to the above-mentioned
meetings/consultation, the gazette conducted in end 2008 also gathered the
views from the public on the Project as well as the views from the residents
along the alignment from the resident briefings.
2.152
Non-Government Organizations (NGOs) have also
been engaged in the EIA process, as early as the PPFS stage. In February
2.153
After selection of the preferred alignment, a further
meeting with NGOs was conducted in October 2008, to introduce the alignment and
latest progress of the Project. A
follow-up site visit was conducted in December 2008 to the key works areas in
the northern area, particularly the SSS site with potential ecological
issues. Based on the completed
ecological surveys, a workshop was conducted in early February 2009 to brief
NGOs on the key findings, focusing on ecological mitigation measures for the
SSS site. A number of their recommendations have been beneficial to the
development of the current design.
2.154
A summary of major environmental concerns from
the community and responses from Project Proponent is presented in Table
2.15.
Table 2.15 Major Environmental
Concerns/Views
|
|
|
Concerned Parties |
Major Environmental Concerns/Views |
Responses and EIA Findings |
Public/Resident along the alignment |
Concern on noise impact due to above-ground construction works |
During the course of developing the construction plants and programme,
key features, including minimization of construction plants, works in phases
and avoidance of simultaneous operation of construction plants, have been
considered as far as practicable to alleviate the construction noise impacts.
Noise sensitive receivers (NSRs) that would be affected by the
construction noise were identified. The construction noise levels at the
representative sensitive receivers have been predicted. Without implementation of mitigation
measures, noise exceedances at some NSRs are envisaged. As such, practicable and feasible
mitigation measures have been explored to minimize the construction noise
impact. Mitigation measures are
recommended though several NSRs would be subject to noise levels exceeding
the noise criteria as a result of mitigation measures exhausted. Community liaison and an Environmental
Monitoring and Audit (EM&A) will be conducted to monitor and minimize the
noise impact to the NSRs during the construction phase. |
|
Concern on dust impact due to the construction works |
Major dust impact would arise from surface ground works, concrete
batching plant, temporary stockpiles on site and barging activities. With the recommended mitigation measures, the dust levels at the air
sensitive receivers (ASRs) would comply with the criteria of EIAO-TM and Air
Quality Objective (AQO). An
Environmental Monitoring and Audit (EM&A) will be conducted to monitor
and minimize the dust impact to the ASRs during the construction phase. |
|
Concern on ground-borne noise impact due to tunneling works |
The potential source of ground-borne noise impact is the operation of
tunnel boring machine (TBM). Assessment has been conducted to evaluate the ground-borne noise
impact at the NSRs and the results, with the inclusion of safety factor,
indicated that there would be noise exceedances for about 2-3 days at only
four representative NSRs. Monitoring at the time of TBM operation will be conducted to confirm
the assessment findings and monitor the ground-borne noise impact at the
NSRs. In addition, An EM&A
programme, together with careful scheduling of the works and close liaison
with the affected parties will be conducted to minimize the noise impact. |
|
Concern on ground water drawdown during construction |
The tunnel sections will be constructed with either “drained” lining
(i.e. water pressure relieve system is provided), or “undrained” lining (i.e.
with fully tanked linings). Both
linings would prevent the groundwater leakage into the tunnel, and therefore
there would be insignificant ground water drawdown during the tunneling
works. Past experience also indicated
that impact on ground water drawdown was not encountered during the tunneling
works. A well designed and managed groundwater monitoring programme will be
developed to monitor the groundwater levels.
Sufficient pre-construction monitoring will also be undertaken such
that baseline groundwater levels can be established and any seasonal (or other)
variations in groundwater level identified.
|
|
Concern on ground-borne noise impact during operation |
The railway tunnel will be located at levels of at least 20m below
local ground, except a small section to the north of ERS. Assessment has been conducted to predict the ground-borne noise levels
at the NSRs on top of/close to the tunnels.
Results indicated that the ground-borne noise levels would comply with
the stipulated noise criteria. Low
noise trackform will however be installed at the selected alignment sections
to further minimise the impact. A
commissioning test will be conducted to monitor the ground-borne noise levels
at the selected NSRs. |
|
Concern on air and noise pollutions from ventilation buildings |
As XRL trains are electrically powered, and so there would not be any
emission from fossil fuel generated from the trains. As such, there would be no air pollutants
exhausted from vent shafts and no air quality impact is envisaged. Prevailing background noise measurements have been conducted to
establish the fixed plant noise criteria.
Maximum sound power levels have been assigned for each vent shaft to
control the potential noise impact from the ventilation buildings. |
Green Groups |
Concern on the potential hydrogeological impact during construction |
As discussed above, past experience indicated that impact on ground
water drawdown was not encountered during the tunneling works. There would be insignificant ground water drawdown during the tunneling
works and thus hydrological disruption is not anticipated. In fact, changes in the water table will be
insignificant as compared with natural fluctuations due to the rainfall
patterns. Ground water monitoring during construction phase will be conducted to
monitor the ground water level. |
|
Concern on the potential ecological impact associated with building
structures in Mai Po |
The size of each ventilation building has been minimised during the detailed
design stage to avoid and minimise any visual and ecological impact. |