9.1
Contaminated land refers to the land which has been polluted
by hazardous substances as a result of industrial operations carried out on
site over a number of years. These
contaminants if present, may pose hazardous risks or cause adverse effects to
the land users and the nearby environment.
9.2
The implications of land contamination associated with the Project and its works areas have been assessed with reference to the
ESB. This section summarises the site appraisal results as in the
completed Contamination Assessment Plan (CAP), site investigation results as
reported in the Contamination Assessment Report (CAR), and the recommended
remediation works as in the Remediation Action Plan (RAP) together with the
overall findings and recommendations in EIA perspective.
Environmental Legislation, Standards and Guidelines
9.3
The relevant environmental legislation guidelines and
standards on land contamination aspect include the followings:
(i)
Section 3 (Potential
Contaminated Land Issues) of Annex 19
“Guidelines for Assessment of Impact on Sites of Cultural Heritage and Other
Impacts” of the Technical Memorandum
on Environmental Impact Assessment Process (EIAO-TM).
(ii)
Guidance Note for Contaminated Land Assessment and Remediation”
(Guidance Note 1)
Guidance
Note 1 sets out the requirements for proper assessment and management of
potentially contaminated sites such as oil installations (e.g. oil depots, petrol filling
stations), gas works, power plants, shipyards/boatyards, chemical manufacturing/processing
plants, steel mills/metal workshops, car repairing/dismantling workshops and
scrap yards. In addition, this Guidance Note provides guidelines on how site
assessments should be conducted and analysed and suggests practical remedial
measures that can be adopted for the cleanup of contaminated sites.
(iii)
Guidance Notes for Investigation and Remediation of
Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair
/Dismantling Workshop” (Guidance Note 2)
Guidance
Note 2 specifically sets out guidance for land contamination assessment and
remediation for sites previously used for petrol filling stations, boatyards
and vehicle repair/dismantling workshops.
(iv)
Guidance Manual for Use of Risk-based Remediation Goals for
Guidance
Manual introduces the risk based approach in land contamination assessment and
present instructions for comparison of soil and groundwater data to the Risk-based Remediation Goals (RBRGs) for 54 chemicals of
concern commonly found in
9.4
The first step was to assess and
identify any potentially contaminative sites within the project area. The following tasks have been undertaken to identify and evaluate
the potential land contamination impacts associated with the Project:
·
Desktop study to review the current and historical land
uses;
·
Acquisition of information related to potential land
contamination from Environmental Compliance Division of Environmental
Protection Department (EPD)
and Fire
Services Department (FSD) and
·
Site reconnaissance to identify the existing land uses and
potential.
9.5
In addition, the following
sources of information have been collated and reviewed:
·
Selected
aerial
photographs from Lands Department;
·
the
·
Information of dangerous goods for potentially contaminated
areas from Fire Services Department
(FSD);
·
Records and photographs from site visit; and
·
Relevant approved EIA report (i.e. Kowloon Southern
Link (KSL) EIA (Register No.: AEIAR-083/2005)
and EIA reports for Proposed Comprehensive Development at Wo
Shang Wai, Yuen Long (Register No.: AEIAR-120/2008)).
9.6
According to the findings of site appraisal, the
Contamination Assessment Plan (CAP) as given in Appendix 9.1 was prepared and submitted to EPD. Based on the desktop reviews and site
inspections, sampling locations and sampling depths for soil and groundwater at
the potential contaminated sites have been proposed for the site investigation
(SI) works in this CAP. The CAP also specified
the sampling and testing requirements for the SI works.
9.7
Owing to time and site
constraints, the site investigation is proposed in 2 stages. In Stage 1,
sampling has been conducted at hotspots with the objective to preliminary
assess the soil and groundwater quality through sampling and laboratory testing
at worst case locations of potential contaminated sites. After the completion
of the SI works, the analytical results of the soil and groundwater were
interpreted using RBRGs. The nature,
level and extent of the land contamination at the potential land contaminated
sites were evaluated and the findings were documented in the Contamination
Assessment Report (CAR). Options of
remedial works for contaminated soil have been reviewed and evaluated, and appropriate
remediation option has been recommended.
Details are presented in the Remediation Action Plan (RAP). A copy of the CAR and RAP are given in Appendix 9.2.
9.8
Remediation works to clean up the
contaminated sites if necessary will be carried following the requirements in the
RAP during the construction phase.
9.9
In Stage 2, site investigation
will be conducted at the rest of the site area to assess the site condition in
general. Stage 2 SI will be conducted after the completion of the EIA study/land
resumption and prior to the commencement of construction works at respective
sites. The sites which are infeasible for inspection and/or site investigation
under Stage 1 will also be assessed in this stage. Supplementary CAR(s) and if
contamination found, RAP(s) will be submitted for EPD endorsement.
Description of the Environment
9.10
The Study Area of the land
contamination impact assessment including the railway alignment and boundaries
of all associated works areas under the Project are shown in Figure Nos. NOL/ERL/300/C/XRL/ENS/M50/001-003,
M57/200-228 and M57/300
9.11
Based on
the engineering design available at this stage, the specific sites for this
contaminated land assessment have been classified as follows:
(i)
Railway
alignment
9.12
The railway starts at
Shenzhen-Hong Kong border in Huanggang and ends at West Kowloon Terminus with a
total alignment of
(ii)
9.13
West
Kowloon Cut and Cover (WKCC) Section will cover the area
occupied for West Kowloon Terminal (WKT) and its associated works area,
ventilation building located next to Jordan Road (WKV), the cut and cover
section for the
(iii)
Shek Kong Stabling Sidings (SSS)
9.14
Shek Kong Stabling Sidings (SSS)
is a cut & cover site located at Shek Kong. The works area of SSS will take
approximately
(iv)
9.15
There will be a total of seven
ventilation buildings along the railway corridor for tunnel ventilation and
another one adjacent to the WKT for track fan and terminus ventilation.
Furthermore, an Emergency Access Point (EAP) will also be provided at Tai Kong
Po (TPP). A description of the VB/EAP
involved is provided in Table 9.1
Table 9.1
Location I.D. |
Description |
Reference Figure in CAP (Appendix 9.1) |
|
Northern Section |
MPV |
Ventilation Building Works Area in |
NOL/ERL/300/C/ |
NTV |
|
NOL/ERL/300/C/ |
|
TPP |
Tai Kong Po
Emergency Access Point |
NOL/ERL/300/C/ |
|
PHV |
|
NOL/ERL/300/C/ |
|
Southern Section |
SMV |
|
NOL/ERL/300/C/ |
KCV |
|
NOL/ERL/300/C/ |
|
NCV |
|
NOL/ERL/300/C/ |
|
MKV |
Works area and |
NOL/ERL/300/C/ |
|
WKV |
Ventilation Building next to |
NOL/ERL/300/C/ XRL/ENS/M57/320 |
(v)
Supporting
Works Area
9.16
In addition to WKCC Section, SSS and
VB/EAP Sites, there are fourteen supporting works area required in this
Project, including the temporary construction shafts, nursery and storage areas
and barging points as shown in Table 9.2.
Table 9.2 Supporting Works Area
Location I.D. |
Description |
Reference Figure in CAP (Appendix 9.1) |
Works Areas |
||
TUW |
Tse |
NOL/ERL/300/C/ |
SYW |
Works Area and construction shaft in Shek Yam |
NOL/ERL/300/C/ |
MLW |
Works Area and construction shaft at |
NOL/ERL/300/C/ |
LCW |
Lai Chi Kok Works Area |
NOL/ERL/300/C/ |
HTW |
Works area and construction shaft for |
NOL/ERL/300/C/ |
Nursery and Storage Areas/
Magazine Sites |
||
SLSW |
Works Area in Siu Lang Shui for nursery purpose
only |
NOL/ERL/300/C/ |
SKW |
Magazine Site and works Area in So Kwun Wat for
nursery and storage purpose only |
NOL/ERL/300/C/ |
TSW |
Magazine Site near |
NOL/ERL/300/C/ |
Barging Points |
||
NCB |
|
NOL/ERL/300/C/ |
WKB |
West Kowloon Barging Point and stockpile area
nearby (assessed under WKCC Section) |
NOL/ERL/300/C/ |
RCB |
Barging Point in Rambler Channel |
NOL/ERL/300/C/ |
SLB |
Barging Point in Siu Lam |
NOL/ERL/300/C/ |
LKB |
Barging Point in Lung Kwu Sheung Tan |
NOL/ERL/300/C/ |
TCB |
Tsing Chau Tsai Barging Point |
NOL/ERL/300/C/ |
Identification of Potential
Environmental Impacts
Identification of Impact Sources
9.17
The
Project covers a lot of areas with various existing and historical uses. The Project will resume these areas for the
construction of railway, stations and associated facilities. The existing structures on these areas will
be decommissioned.
9.18
The issue
of land contamination refers to land which has been polluted by hazardous
substances as a result of industrial or commercial operations carried out on
and around the site over a number of years. Very often, these contaminants pose
hazardous risks or cause detrimental effects particularly to the land users.
For example, toxic chemicals used in a chemical processing plant can find their
way into the ground after some time through accidental spills or leaks. These
toxic chemicals can contaminate the soil and groundwater. It is important that
special attention be given to potentially contaminated sites to ensure their
proper management, if necessary.
9.19
The
identification of these potential contaminative areas within the project areas
has been completed in the CAP stage through the site appraisal exercise. The technical details of the CAP are provided
in the Appendix 9.1 and the list of
potential contaminated sites identified in this Project has been summarized in Table 9.3.
Table 9.3 Potential Contaminated Sites Identified in this Project
Location |
Site ID |
|
Shek
Kong Stabling and Sidings (SSS) |
||
SSS |
F |
Construction Equipment Repair & Maintenance Workshop |
G |
Scrap Yard |
|
L |
Vehicle Repair Workshop |
|
M |
Open Area |
|
P |
Storage Area (“Factory”) |
|
Q |
Parking area with minor vehicle repair /maintenance activities |
|
R |
Vehicle Repair Workshop |
|
S |
Vehicle Repair Workshop |
|
|
||
MPV |
D |
Container truck parking area with minor repair/ maintenance activities |
MPV |
E |
Container truck parking area with car wash and paint booth |
KCV |
H |
Scrap Yard |
Supporting
Works Area |
||
NCB |
J |
Container Yard |
MLW |
T |
Car park |
LCW |
K |
Open Area ( A chemical
Storage Area was found nearby) |
9.20
Some areas were not feasible for inspection
on site and further site investigation as these areas were either locked or
access being denied by the occupiers during site appraisal under CAP. Site
inspection should be carried out to ascertain any contaminative sources and
hotspots of contamination within the site when site access is granted and a
revised CAP should then be submitted to EPD for endorsement. Upon completion of
SI and laboratory testing, a CAR and if necessary, a RAP should also be
submitted to EPD for endorsement as well. For sites which are not feasible for
site investigation works, CAR and if necessary, RAP should also be prepared and
submitted to EPD to endorse. Table 9.4 summarizes the areas which are infeasible for
site inspection and further investigations.
Table 9.4 Areas Infeasible for
Site inspection and Further Investigations
Location |
Site ID |
|
AREAS INFEASIBLE FOR ON-SITE INSPECTION AND SITE INVESTIGATION |
||
|
||
WKCC |
X |
Golf course |
Shek Kong Stabling Sidings
(SSS) |
||
SSS |
I |
Suspected vehicle repair workshop |
O |
Suspected excavator parking area with repair /
maintenance activities |
|
B |
Suspected occupied for industrial activities |
|
N |
Suspected occupied for industrial activities |
|
U |
Suspected occupied for industrial activities |
|
V |
Suspected occupied for industrial activities |
|
W |
Suspected occupied for industrial activities |
|
|
||
MPV |
A |
Suspected occupied for recycling industry |
C |
Suspected to have vehicle repair activities
undertaken |
|
WSW |
Review of WSW EIA indicated
the site to be occupied for lorry parking and vehicle and container storage
area. |
|
AREAS INFEASIBLE FOR SITE INVESTIGATION |
||
Shek
Kong Stabling and Sidings (SSS) |
||
SSS |
L |
Vehicle Repair Workshop |
P |
Storage Area (“Factory”) |
|
R |
Vehicle Repair Workshop |
|
|
||
MPV |
E |
Container truck parking area with car wash and paint booth |
Supporting
Sites |
||
NCB |
J |
Container Yard |
MLW |
T |
Car park |
LCW |
K |
Open Area ( A chemical
Storage Area was found nearby) |
Identification of Sensitive Receivers
9.21
Construction
workers are the most likely group to be exposed to any potential contaminated
materials during the decommissioning stage for the identified contaminated
sites. The principle exposure routes for workers include:
l
Direct
ingestion of contaminated soils through eating or drinking/smoking on site; and
l
Dermal
contact with contaminated soils.
9.22
There would
be no sensitive receivers during the operational phase of the Project provided
that remediation actions if necessary are completed.
9.23
During
the remediation work stage, there may be environmental impacts arisen from the
remediation process (e.g. air emissions and water discharges, etc) that may
affect the surrounding sensitive receivers e.g. human receivers and water
bodies. Proper mitigation measures
should be considered and implemented for remediation work.
Prediction and Evaluation of
Environmental Impacts
Site Investigation Results
9.24
Potentially
contaminated sites have been identified in the CAP (Appendix 9.1) and site investigation involving sampling and testing
of soil and groundwater at identified hotspots have been completed. Laboratory results provide the concentrations
of chemical of concerns for comparison with the RBRGs. To summarize, the results of site
investigation are given in the Table 9.5 below:
Table 9.5 Summary of SI findings
Location |
Site ID |
No. of Drillhole |
No. of Sample Tested |
Compliance to Industrial RBRG |
Planned |
MPV |
D |
1 |
5 |
All sample results
complied |
Railway Facilities |
SSS |
F |
4 |
18 |
All sample results
complied |
Shek Kong Stabling Siding |
SSS |
G |
4 |
14 |
All sample results
complied |
Shek Kong Stabling Siding |
SSS |
Q |
5 |
26 |
2 samples exceed limit
for bis-(2-Ethylhexyl)phthalate |
Railway Facilities |
SSS |
S |
2 |
10 |
All sample results
complied |
Railway Facilities |
SSS |
M |
4 |
20 |
All sample results
complied |
Railway Facilities |
KCV |
H |
3 |
5 |
1 sample exceed limit for
bis-(2-Ethylhexyl)phthalate |
Railway Facilities |
Ngau Tam Mei Landfill |
LF |
2 |
2 |
All sample results
complied |
Railway Alignment |
Total |
- |
25 |
100 |
3 samples exceed limit for
bis-(2-Ethylhexyl)phthalate |
- |
9.25
Most of the
sites are found complied with the relevant RBRGs and hence no adverse impacts
on land contamination are identified.
There are two sites with small volume of contaminated soil not meeting
the RBRB, and their details are given in Table 9.6 below:
Table 9.6 Location, Depth and
Estimated Quantity of Contaminated Soil Found
Location |
Site ID |
Borehole ID |
Depth with Contaminated Soil Found |
Contaminant |
Estimated Contamination Extent |
||
Vertical(m BBC) (Thickness (m)) |
Horizontal (m2) |
Volume |
|||||
KCV |
H |
2108/XRL/EDH27 |
0.5 |
bis--(2-Ethylhexyl) phthalate |
0 |
25 |
17.5 |
SSS |
Q |
2108/XRL/ |
1.50 |
|
25 |
37.5 |
|
Q |
2108/XRL/ |
4.95 |
|
25 |
35 |
||
Estimated
Total Volume of Contamination=~ |
Note:
* Presence of concrete and granite from
**
Sampling at 0.50
***
Sampling at 5.85
9.26
The sites
are located in Kwai Chung Ventilation Building Works Area (KCV) and Shek Kong
Stabling and Sidings Works Area (SSS).
The chemical of concern for both sites are the same, Bis(2-ethylhexyl)phthalate.
9.27
Bis(2-ethylhexyl)phthalate (DEHP), is an organic chemical commonly
abbreviated as DEHP. It is an odourless colourless liquid with the formula
C6H4(CO
Remediation Actions and Mitigation Measures
Review of Remediation Options
9.28
A review of remediation options have
been conducted in the RAP in Appendix
9.2. The options include biopiling, ex-situ chemical oxidation (ESCO), soil
venting, landfarming, natural attenuation and excavation and landfill
disposals.
9.29
Table 9.7 shows
consideration of the characteristics of the two sites and the Chemical of
Concern (COC) identified in order to determine the effective remediation
method. Biopiling and ex-situ chemical oxidation are
identified as the preferred method of remediation. Organic contaminants will be degraded into
non-hazardous chemicals through the enhanced and controlled environment in the
piles.
Table 9.7 Factors for Remediation
Considerations
Site ID |
Depth of Contaminated
Soil (in m Below Base of Concrete) |
Contaminant Identified |
Existing Contamination
Level (mg/ kg) |
RBRG (Industrial) (mg/kg) |
Soil Characteristics |
Time required for Remediation |
Site H at KCV (Scrap Yard) |
0.5 |
bis-(2-Ethylhexl) phthalate |
134 |
91.8 |
Fill
material (gravel sized concrete and tile fragment) |
2-6 months |
3-12 months (for Biopile) |
||||||
Site Q at SSS |
1.50-2.40, |
2540 |
91.8 |
Fill material (sandy clayey silt) |
2-6 months |
|
6-18 months (for Biopile) |
||||||
4.95-5.85 |
356 |
91.8 |
Alluvium (sandy silty clay and clayey silty fine to coarse sand) |
2-6 months |
||
6-12 months |
Note:
*Assuming remediation with biopiling/ ESCO, subject
to further monitoring and enhancement measures.
9.30
As shown in Table
9.6, the volume of contaminated soil identified at
KCV and SSS were
Remediation Method and Remediation Target
9.31
The remediation target for bis-(2-Ethylhexyl)phthalate
is proposed as
l
the industrial landuse of RBRG
i.e. 91.8 mg/kg
The
decontaminated soil will generally reuse and backfill on site. This sites Q and H will be constructed to be
railway related facilities. This target
will be adopted in the project.
9.32
For other
contamination identified after this EIA as in the Stage 2 site investigation,
the remediation target should generally make reference to the “industrial” land
use category.
9.33
The
remediation works will include firstly the excavation of identified
contaminated area and then followed by a closure assessment to verify clearance
of contaminated soil. The excavated
contaminated soil will form piles for either biopiling or chemical
oxidation. During the operation,
monitoring of treatment performance will be carried out in the form of regular
sampling and testing. Once the
monitoring data indicate treatment target is achieved, a closure assessment
sampling and testing will be carried out at a defined sampling frequency for
the treated soil. The acceptance
criterion is defined as the contaminant concentration being complied with the
treatment target. In the event that the samples
still exceed the remediation target, treatment will continue until the soil
target values are achieved. Following
validation of successful soil treatment, a remediation report
(RR)
demonstrating completion of remediation works will be prepared and submitted to
EPD for endorsement prior to the commencement of any construction works.
With the approval of the RR, the decontaminated soil will be used as fill materials for
re-use on site with reference to the land use scenario in the RBRG.
9.34
The
detail requirements of the proposed remediation work are given in the RAP in
the Appendix 9.2. In any case, reference shall be made to the
RAP for remediation works.
Summary of Proposed Mitigation Measures
9.35
The
followings are the summary of mitigation measures proposed (recommended in the
CAP, CAR and RAP) to mitigate the land contamination impacts:
Tunnel Section at Ngau Tam Mei Landfill
(i)
Visual
inspection should be carried out when tunnel boring is conducted at the section
underneath Ngau Tam Mei Landfill, with particular attention on the potential
contamination leaching from the landfill above the tunnel alignment. The inspection process
should also be assisted by a photo ionization detector (PID) for volatile
organics. If
suspected materials are encountered during tunnel boring, sampling
and testing should also be undertaken to verify any contamination. The soil
bored out during excavation and tunnel boring should be temporary stockpiled
and if laboratory analysis indicated exceedance of relevant RBRG levels,
remediation works, should be undertaken with reference to the CAR and RAP.
Alignment Section at
(ii)
Visual
inspection should be carried out at the alignment section near petrol filling
station No. 9 as outlined in Table 5.6 of the CAP (Appendix 9.1) and at works area close to Lai Cheung Road CLP
substation. The
inspection process should also be assisted by a photo ionization detector (PID)
for volatile organics. If suspected materials are encountered during tunnel boring, sampling and
testing should also be undertaken to verify any contamination. The soil
bored out during excavation and tunnel boring should be temporary stockpiled
and if laboratory analysis indicated exceedance of relevant RBRG levels,
remediation works, should be undertaken with reference to the CAR and RAP.
Remediation Works
(iii)
In order
to minimise the potentially
environmental impacts arising from the handling of potentially contaminated
materials, the following environmental mitigation measures are recommended
during the course of the site remediation:
·
Excavation profiles must be properly designed and executed
with attention to the relevant requirements for environment, health and safety;
·
Excavation should be carried out during
dry season as far as possible to minimise contaminated runoff from contaminated
soils;
·
Supply of suitable clean backfill material is needed after
excavation;
·
The chemical oxidant proposed (RegenOxTM)
as a contaminant mass reduction technology. Comprises
a solid oxidant complex (sodium percarbonate/catalytic formulation) and an
activator complex (a composition of ferrous salt embedded in a micro-scale
catalyst gel). These chemical will be
securely stored, separately and way from sources of ignition or oxidizable
items. Handling will & will be
undertaken by persons specifically trained and wearing appropriate PPE.
·
Vehicles containing any excavated materials should be
suitably covered to limit potential dust emissions or contaminated wastewater
run-off, and truck bodies and tailgates should be sealed to prevent any
discharge during transport or during wet conditions;
·
Speed control for the trucks carrying contaminated materials
should be enforced;
·
Vehicle wheel and body washing facilities at the site’s exist
points should be established and used; and
·
Pollution control measures for air emissions e.g. from
biopile blower, noise emissions e.g. from blower, and water discharges e.g.
runoff control should be implemented and complied with relevant regulations and
guidelines.
(iv)
In order
to minimise the potential
adverse effects on health and safety of construction workers during the course
of site remediation, the Occupation Safety and Health Ordinance (OSHO) (Chapter
509) and its subsidiary Regulations should be followed by all site personnel
working on the site at all times. In addition, basic health and safety measures
should be implemented, but not limited to the followings:
·
Set up a list of safety measures for site workers;
·
Provide written information and training on safety for site
workers;
·
Keep a log-book and plan showing the contaminated zones and
clean zones;
·
Maintain a hygienic working environment;
·
Avoid dust generation;
·
Provide face and respiratory protection gear to site workers
if necessary;
·
Provide personal protective clothing (e.g. chemical
resistant jackboot, liquid tight gloves) to site workers if necessary; and
·
Provide first aid training and materials to site workers.
Further Site Investigation
(v)
Owing to
time and site constraints, site investigation is proposed in 2 stages. In Stage
1, sampling has been conducted at hotspots with the objective to preliminary
assess the soil and groundwater quality through sampling and laboratory testing
at worst case locations of potential contaminated sites while in stage 2 site
investigation will be conducted at the rest of the site area to assess the site
condition in general. Stage 2 SI will be conducted after the completion of the
EIA study/land resumption and prior to the commencement of construction works
at respective sites. The sites which are infeasible for inspection and/or site
investigation under Stage 1 will also be assessed in this stage. Table 9.8 summarizes the sites where further investigation
is required. Details can be referred to CAP and CAR/RAP as shown in Appendix 9.1 and 9.2. Upon site access is granted, site inspections will be carried
out to ascertain any contaminative sources and hotspots of contamination within
each site in Table 9.8. Revised CAPs with sampling and testing schedule
updated based on respective site condition should then be submitted to EPD for
endorsement. After completion of sampling
and testing, supplementary CARs and if contamination found, RAP(s) will be
submitted for EPD endorsement. The revised CAPs and supplementary CARs and
RAP(s) should be submitted in separate packages for different works area
depending on the schedule of land resumption and the commencement of
construction works for each works area.
Table 9.8 Summary of Areas for
Site Appraisal and Investigation in Stage 2
Site ID of Inaccessible
Site |
Review of the available
information |
Initial contamination
evaluation of those inaccessible sites and possible remediation methods |
Confirmation of whether the contamination problem at
this/these site(s) would be surmountable |
Sampling and analysis proposal
which shall aim at determining the nature and the extent of the
contamination of this/these site(s) |
Schedule of submission
of revised CAP (if necessary), CAR, RAP and RR |
AREAS INFEASIBLE FOR ON-SITE INSPECTION AND SITE
INVESTIGATION |
|||||
|
|||||
Site X at WKCC Golf course (NOL/ERL/300/C/XRL/ENS/M57/025 of CAP) |
Site Appraisal The site was located on
reclaimed land. The site is currently occupied
by City Golf Club as a golf course. Access to the site was attempted but was
refused by the reception. |
Initial Contamination
Evaluation The site was
inaccessible for site inspection. The
potential of land contamination is uncertain. As the site was occupied as a
golf course where pesticide might have been used, land contamination concern
cannot be neglected. It is also noted that part of the course is made up of
artificial turf/grass. Possible Contaminants Heavy metals, organic
compounds particularly pesticides. Possible Remediation
Methods Depending
on the contaminated soil quantity and quality, possibly: ·
Bioremediation such as bio-pile and composting for organic
contaminants. ·
Stabilization/solidification for heavy metals. |
The site was occupied as a golf
course during site inspection. The site area is around |
Could be from 0 to 41 boreholes based on a regular grid pattern at this stage
(subject to review) across the site are proposed with reference to Guidance
Note 2 across the golf course. The key
point is to assess any impacts due to the use of herbicides/pesticides. Proposed parameters to
be tested are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Revised CAP Upon site access is granted,
site inspection should be carried out to ascertain any contaminative sources
and hotspot of contamination within the site. The
sampling and testing schedule as recommended in the approved CAP should be
updated based on respective site situation and the area that is potentially
affected by the use of pesticides. Based on the actual site condition, the number of sampling
locations may be significantly reduced. A revised CAP should then
be submitted to EPD for endorsement. CAR and RAP Upon completion of SI
and laboratory testing, a CAR should be submitted to EPD for
endorsement. If contamination is
identified, a RAP should also be submitted to EPD for endorsement. RR A RR should be submitted
to demonstrate completion of remediation works before construction work
starts at the site. |
Shek Kong Stabling Sidings
(SSS) |
|||||
Site I at SSS Suspected vehicle repair workshop (NOL/ERL/300/C/XRL/ENS/M57/018 of CAP) |
Site Appraisal Past land uses of the
site were observed to be farms,
workshop
and garage. Inspection inside the
site was not possible. The
site was
suspected as a vehicle repair/dismantling workshop based on
observation from surrounding. |
Initial Contamination
Evaluation Potential concern
related to current operation with vehicle repair/maintenance activities. Possible Contaminants Petroleum hydrocarbons,
metals and organic solvents. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site has a small area ( |
As specific hotspots of
contamination cannot be identified due to inaccessibility, maximum 4 boreholes based on a regular grid pattern at this stage (subject to
review) across the site are proposed with reference to Guidance Note 2. Proposed parameters are
given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Revised CAP Upon site access is granted,
site inspection should be carried out to ascertain any contaminative sources
and hotspot of contamination within the site. The
sampling and testing schedule as recommended in the approved CAP should then
be updated based on respective site situation and the number of sampling locations may
be significantly reduced. A revised CAP should then be
submitted to EPD for endorsement. CAR and RAP Upon completion of SI
and laboratory testing, a CAR should be submitted to EPD for
endorsement. If contamination is
identified, a RAP should also be submitted to EPD for endorsement. RR A RR should be submitted
to demonstrate completion of remediation works before construction work
starts at the site. |
Site O at SSS Suspected excavator parking area with repair/ maintenance activities (NOL/ERL/300/C/XRL/ENS/M57/016 of CAP) |
Site Appraisal Past land uses of the
site were observed to be farms,
workshop
and garage. Inspection inside the
site was not possible. The site
was
suspected to be an excavator parking area with some maintenance and
refuelling activities based on limited observation
from outside. |
Initial Contamination
Evaluation Potential land contamination
due to suspected excavator maintenance and refuelling. Possible Contaminants Metals, petroleum hydrocarbons and organic solvents. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site has a small area ( |
As hotspot of
contamination cannot be identified due to inaccessibility, from 0 up to 2 boreholes are proposed with reference to Guidance Note
2. Proposed parameters to
be tested are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I above |
Site B at SSS Suspected occupied for industrial uses (NOL/ERL/300/C/XRL/ENS/M57/015 of CAP) |
Site Appraisal The site was occupied by
farms and some low-rise building structure in the past. Currently, the site is occupied
by temporary structures with unknown usage.
Access to those temporary structures was attempted but this was
refused by tenants. Some forms of
industrial activities observed in the temporary structures. However, nature and type of industry were not
known. |
Initial Contamination
Evaluation Site inspection inside
the site was not possible. The site
was suspected to have some forms of industrial activities. Possible Contaminants Not able to determine at
this stage. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Bioremediation such as bio-pile and composting for organic
contaminants. ·
Stabilization/solidification for heavy metals. |
The site was only suspected with industrial
activities at this stage based on the very limited information. The site area is around |
The site activities are
not known. As hotspot of contamination
cannot be identified due to inaccessibility, from 0
up to 51
boreholes based on a regular grid pattern at this stage (subject to review) across
the site are proposed with reference to Guidance Note 2. Since the potential
contaminants were not known, a broad list of parameters to be tested. Details of the sampling
and analysis for this site are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I above
|
Site N at SSS Suspected occupied for industrial uses (NOL/ERL/300/C/XRL/ENS/M57/016 of CAP) |
Site Appraisal The site was occupied by
farms and some low-rise building structure in the past. The site is currently
occupied by temporary structures with unknown usage. Access to those temporary structures was
attempted but this was refused by tenants. Some forms of industrial
activities observed in the temporary structures. However, nature and type of industry were
not known. |
Initial Contamination
Evaluation The site was
inaccessible for site inspection. The
potential of land contamination is uncertain.
However, as the site is suspected be occupied for industrial use,
there might be of land contaminative concern due to contaminative industrial
activities. Possible Contaminants Not able to determine at
this stage. Possible Remediation
Methods Depending
on the contaminated soil quantity and quality, possibly: ·
Bioremediation such as bio-pile and composting for organic
contaminants and cyanide. ·
Stabilization/solidification for heavy metals and PCBs. |
The site was only suspected with
industrial activities at this stage based on the very limited information. The site area is around |
The site activities are
not known. As hotspot of contamination cannot be identified due to
inaccessibility, from 0 up to 14 boreholes based on a regular
grid pattern at this stage (subject to review) across the site are proposed
with reference to Guidance Note 2. Since the potential contaminants were not
known, a broad list of parameters to be tested. Details of the sampling
and analysis for this site are given in
Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I above. |
Site U at SSS Suspected occupied for industrial uses (NOL/ERL/300/C/XRL/ENS/M57/024 of CAP) |
Site Appraisal The site was occupied by
farms and some low-rise building structure in the past. The site is currently
occupied by temporary structures with unknown usage. Access to those temporary structures was
attempted but this was refused by tenants. Some forms of industrial
activities observed in the temporary structures. However, nature and type of industry were
not known. |
Initial Contamination
Evaluation The site was
inaccessible for site inspection. The
potential of land contamination is uncertain.
However, as the site is suspected be occupied for industrial use,
there might be of land contaminative concern due to contaminative industrial
activities. Possible Contaminants Not able to determine at
this stage. Possible Remediation
Methods Depending
on the contaminated soil quantity and quality, possibly: ·
Bioremediation such as bio-pile and composting for organic
contaminants and cyanide. ·
Stabilization/solidification for heavy metals and PCBs. |
The site was only suspected with
industrial activities at this stage based on the very limited information. The site area is around |
The site activities are
not known. As hotspot of contamination cannot be identified due to
inaccessibility, from 0 up to 6 boreholes based on a regular grid
pattern at this stage (subject to review) across the site are proposed with
reference to Guidance Note 2. Since the potential contaminants were not
known, a broad list of parameters to be tested. Details of the sampling
and analysis for this site are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I above. |
Site V at SSS Suspected occupied for industrial uses (NOL/ERL/300/C/XRL/ENS/M57/024 of CAP) |
Site Appraisal The site was occupied by
farms and some low-rise building structure in the past. The site is currently as a vacant area with construction waste material found. |
Initial Contamination
Evaluation The site was
inaccessible for site inspection. The
potential of land contamination is uncertain.
However, as the site share similar nature as a scrap yard, there might
be of land contaminative concern due to contaminative industrial activities. Possible Contaminants Not able to determine at
this stage. Possible Remediation
Methods Depending
on the contaminated soil quantity and quality, possibly: ·
Bioremediation such as bio-pile and composting for organic
contaminants and cyanide. ·
Stabilization/solidification for heavy metals and PCBs. |
The site was only suspected with
industrial activities at this stage based on the very limited information. The site area is around |
The site activities are
not known. As hotspot of contamination cannot be identified due to
inaccessibility, from 0 up to 12 boreholes based on a regular grid
pattern at this stage (subject to review) across the site are proposed with
reference to Guidance Note 2. Since the potential contaminants were not
known, a broad list of parameters to be tested. Details of the sampling
and analysis for this site are given in
Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I above. |
Site W at SSS Suspected occupied for industrial uses (NOL/ERL/300/C/XRL/ENS/M57/024 of CAP) |
Site Appraisal The site was occupied by
farms and some low-rise building structure in the past. The site is currently occupied
by temporary structures with unknown usage.
Access to those temporary structures was attempted but this was
refused by tenants. Some forms of industrial activities observed in the
temporary structures. However, nature
and type of industry were not known. |
Initial Contamination
Evaluation The site was
inaccessible for site inspection. The
potential of land contamination is uncertain.
However, as the site is suspected be occupied for industrial use, there
might be of land contaminative concern due to contaminative industrial
activities. Possible Contaminants Not able to determine at
this stage. Possible Remediation
Methods Depending
on the contaminated soil quantity and quality, possibly: ·
Bioremediation such as bio-pile and composting for organic
contaminants and cyanide. ·
Stabilization/solidification for heavy metals and PCBs. |
The site was only suspected with
industrial activities at this stage based on the very limited information. The site area is around |
The site activities are
not known. As hotspot of contamination cannot be identified due to
inaccessibility, from 0 up to 9 boreholes based on a
regular grid pattern at this stage (subject to review) across the site are
proposed with reference to Guidance Note 2. Since the potential contaminants
were not known, a broad list of parameters to be tested. Details of the sampling
and analysis for this site are given in
Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I above. |
|
|||||
Site A at MPV Suspected recycling like industry (NOL/ERL/300/C/XRL/ENS/M57/013 of CAP) |
Site Appraisal Past land uses of the
site were observed as farms, fish ponds and garages. Inspection inside the
site not possible, suspected waste recycling facility based on observations
from the surroundings. |
Initial Contamination
Evaluation Potential concern due to
current suspected current operation with waste handling/recycling. Possible Contaminants Petroleum hydrocarbons,
metals, PCB, cyanide and organic solvents. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals and PCB. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site has an
area of |
As specific hotspots of
contamination cannot be identified due to inaccessibility, from 0 up to 15 boreholes based on a regular grid pattern across the
site are proposed at this stage (subject to review) with reference to
Guidance Note 2. Proposed parameters to
be tested are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site I above |
Site C (MPV) Suspected Vehicle Repair Workshop (NOL/ERL/300/C/XRL/ENS/M57/013 of CAP) |
Site Appraisal Past land uses of the
site were observed as farms, fish ponds and garages. Inspection inside the site not possible,
suspected having vehicle repair/maintenance activities based on observations
from the surroundings. |
Initial Contamination
Evaluation Potential concern due to
current suspected current operation as a vehicle repair workshop. Possible Contaminants Petroleum hydrocarbons,
metals and organic solvents. Possible Remediation
Methods Depending
on the contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site has an
area of |
As specific hotspots of
contamination cannot be identified due to inaccessibility, from 0 up to 9
boreholes based on a regular grid pattern at this stage (subject to review)
across the site are proposed with reference to Guidance Note 2. Proposed parameters are
given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I
above. |
WSW at MPV (NOL/ERL/300/C/XRL/ENS/M57/013 of CAP) |
Site Appraisal Past land uses of the
site were observed as fish ponds, open storage and garages. Inspection inside the site not possible. Review of WSW EIA
indicated the site to be occupied for lorry parking and vehicle and container
storage area. Review of aerial photo suggested no significant changes in the
site layout with the described land use in WSW EIA. |
Under WSW EIA, the site
was identified to be contaminated with Pb and/or Zn based on Dutch B
criteria. |
The site has an area of
approximately |
NA |
According to WSW EP
Condition 3.14, the Project Proponent of the WSW development shall prepare
and submit CAR/RAP to EPD within 2 months after commencement of construction
of the WSW development and the recommendations in the endorsed CAR/RAP shall
be fully implemented before the commencement of any construction works that
may disturb the ground of the relevant sites. This project will ensure that the completion of remediation works
before the construction works at contaminated areas start. |
Areas Infeasible for Site Investigation |
|||||
Shek Kong Stabling Sidings (SSS) |
|||||
Site P Storage Area (NOL/ERL/300/C/XRL/ENS/M57/017 of CAP) |
Site Appraisal Past land uses of the
site was found to be farms, workshop, factory. The
site is currently used as storage area. |
Initial Contamination
Evaluation Potential concern due to
past industrial use was identified Possible Contaminants Petroleum
hydrocarbons, metals, organic solvents, PCB and
cyanide. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals and PCB. ·
Bioremediation such as bio-pile and composting for organic
contaminants and cyanide. |
The site has an
area |
7 sampling locations have been proposed at parking area, oil drum
storage area and around the site in general. Proposed parameters to be tested are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I
above. |
Site R Vehicle Repair Workshop (NOL/ERL/300/C/XRL/ENS/M57/016 of CAP) |
Site Appraisal Past land uses around SSS was found to be occupied as farms, car park,
garage and workshop. The site is currently occupied as vehicle repair
workshop |
Initial Contamination
Evaluation Potential concern due to
current car maintenance and servicing activities. Possible Contaminants Petroleum hydrocarbons,
metals and organic solvents. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site has a small area ( Land contamination causing insurmountable
impacts would not be likely. Moreover,
there are available and commonly adopted remediation methods for the
potential contaminants. |
2 sampling locations are proposed at waste chemical container storage
area and vehicle repair area. An additional 2 are proposed to assess the site
condition in general. Proposed parameters to be tested are given in Table 6.1 of CAP. A total of 4 sampling points are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
Site L Vehicle Repair Workshop (NOL/ERL/300/C/XRL/ENS/M57/018 of CAP) |
Site Appraisal Past land uses around SSS was found to be occupied as farms, car park,
garage and workshop. The site is currently occupied as vehicle repair
workshop |
Initial Contamination
Evaluation Potential concern due to
past car maintenance and servicing activities. Possible Contaminants Petroleum hydrocarbons,
metals and organic solvents. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site has a small area ( Land contamination causing
insurmountable impacts would not be likely.
Moreover, there are available and commonly adopted remediation methods
for the potential contaminants. |
2 sampling locations are proposed at the lube oil drum storage area
and vehicle repair area. Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I
above. |
Site F Construction Equipment
Repair /Maintenance Workshop (NOL/ERL/300/C/XRL/ENS/M57/102 of CAR) |
Site Appraisal Past land uses of the site was found to be farms, workshop, car park and
garages. The site is currently used as a Construction Equipment Repair
/Maintenance Workshop. |
Initial Contamination
Evaluation Potential concern due to current land use was identified. Phase 1 SI has been conducted at the
construction equipment repair area, oil drum storage area and parking area.
Supplementary SI under Phase 2 will be carried out to assess the general site
condition. Possible
Contaminants petroleum
hydrocarbons, metals, Possible Remediation
Methods Depending on the contaminated
soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals. ·
Bioremediation such as bio-pile, composting or ex-situ chemical oxidation for
organic contaminants. |
The Site
was occupied mainly for construction equipment repair / maintenance. Land contamination causing insurmountable impacts
would not be likely. Moreover, there
are available and commonly adopted remediation methods for the potential
contaminants. |
A total of 3 supplementary boreholes have been proposed to assess the
site condition in general Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I
above. |
Site G Scrap Yard (NOL/ERL/300/C/XRL/ENS/M57/103 of CAR) |
Site Appraisal Past land uses of the site was found to be farms, workshop, car park
and garages. The site is currently used as scrap yard. |
Initial Contamination
Evaluation Potential concern due to current land use was identified. Phase 1 SI has been conducted and
Supplementary SI under Phase 2 will be carried out to further assess the
general site condition. Possible Contaminants petroleum hydrocarbons,
metals, organic solvents, PCB and cyanide Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals and cyanide. ·
Bioremediation such as bio-pile, composting or ex-situ chemical oxidation for organic
contaminants and PCB. |
The Site
was occupied mainly for scrap storage.
Land
contamination causing insurmountable impacts would not be likely. Moreover, there are available and commonly
adopted remediation methods for the potential contaminants. |
A total of 2 supplementary boreholes have been proposed to further
assess the site condition in general Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works. |
Same as Site
I
above. |
Site Q Parking area with minor vehicle repair/
maintenance activities
|
Site Appraisal Past land uses of the site was found to be farms, workshop, car park and
garages. The site is currently used as Parking area with minor vehicle
repair/ maintenance activities. |
Initial Contamination
Evaluation Potential concern due to current land use was identified. Phase 1 SI has been conducted at waste
container disposal area and vehicle repair area. Supplementary SI under Phase
2 will be carried out to further assess the general site condition. Possible Contaminants: Petroleum hydrocarbons,
metals and organic solvents. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals. ·
Bioremediation such as bio-pile, composting or ex-situ chemical oxidation for
organic contaminants. |
The Site
was occupied mainly for vehicle parking with some minor repair
activities. Land contamination causing
insurmountable impacts would not be likely.
Moreover, there are available and commonly adopted remediation methods
for the potential contaminants. |
A total of 2 supplementary boreholes have been proposed to assess the
site condition in general. Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
Site M Open Area (NOL/ERL/300/C/XRL/ENS/M57/018 of CAP or NOL/ERL/300/C/XRL/ENS/M57/106
of CAR) |
Site Appraisal Past land uses of the site was found to be farms, workshop, car park
and garages. The site is currently vacant with an aboveground tank of unknown
content. |
Initial Contamination
Evaluation Phase 1 SI has been conducted to assess the general site condition and
the potential impact due to the presence of aboveground tank with unknown content.
Supplementary SI under Phase 2 will be carried out to further assess the
general site condition. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals and cyanide. ·
Bioremediation such as bio-pile, composting or ex-situ chemical oxidation for
organic contaminants and PCB. |
The Site
was occupied mainly an open area. Land contamination
causing insurmountable impacts would not be likely. Moreover, there are available and commonly
adopted remediation methods for the potential contaminants. |
A total of 3 supplementary boreholes have been proposed to assess the
site condition in general. Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
|
|||||
Site D at MPV (NOL/ERL/300/C/XRL/ENS/M57/013 of CAP or NOL/ERL/300/C/XRL/ENS/M57/101
of CAR) |
Site Appraisal Past land uses of the site was
found to be farms, fish ponds and garages. The site is currently used as a
container truck parking with minor repair/ maintenance activities. |
Initial Contamination
Evaluation Potential concern due to current land use was identified. Phase 1 SI has been conducted at
area with used container found and supplementary SI under Phase 2 will be
carried out to assess the general site condition and vehicle repair area. Possible Contaminants petroleum hydrocarbons,
metals and organic solvents, Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals. ·
Bioremediation such as bio-pile, composting or ex-situ
chemical oxidation for organic contaminants. |
The area
occupied mainly for vehicle maintenance.
Land
contamination causing insurmountable impacts would not be likely. Moreover, there are available and commonly
adopted remediation methods for the potential contaminants. |
A total of 6 boreholes have been proposed to assess the site condition
in general and the vehicle repair area where minor repair/maintenance
activities would be undertaken. Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
Site E at MPV Container truck parking area with car wash and
paint booth (NOL/ERL/300/C/XRL/ENS/M57/013 of CAP) |
Site Appraisal Past land uses of the
site was found to be farms, fish ponds and garages.
The site is currently used as a container truck parking area with car wash
and paint booth. |
Initial Contamination
Evaluation Potential concern due to
current painting process. Possible Contaminants Petroleum hydrocarbons,
metals and organic solvents. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site occupies
an area of Land contamination causing
insurmountable impacts would not be likely.
Moreover, there are available and commonly adopted remediation methods
for the potential contaminants. |
A total of 5 sampling locations have been proposed at paint booth and
around the site to assess the potential contamination aroused from painting
process and assess the site condition in general (2 at paint booth and 3
around the site) Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
Supporting Works Areas |
|||||
Site H Scrap Yard (NOL/ERL/300/C/XRL/ENS/M57/019 of CAP or
NOL/ERL/300/C/XRL/ENS/M57/107 of CAR) |
Site Appraisal Past land uses of the
site was found to be car park, storage area and vacant
area. |
Initial Contamination
Evaluation Potential concern due to current land use was identified. Phase 1SI has been conducted at the
scrap storage area and Supplementary SI under Phase 2 will be carried out to
further assess the general site condition and the scrap packing area. Possible Contaminants petroleum hydrocarbons,
metals , PCB, cyanide and organic solvents, Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals and PCB. ·
Bioremediation such as bio-pile and composting for organic
contaminants and cyanide. |
The Site
was occupied mainly for scrap storage and packing where some oil drums were
also found. Land contamination causing
insurmountable impacts would not be likely.
Moreover, there are available and commonly adopted remediation methods
for the potential contaminants. |
A total of 3 boreholes have been proposed to assess the site condition
in general and the scrap packing area where some oil drums were found. Proposed parameters to be tested are given in Table 6.1 of CAP Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
Site T at MLW Car Park (NOL/ERL/300/C/XRL/ENS/M57/020 of CAP) |
Site Appraisal Past land uses of the
site was found to be car park and oil depot. The site
is currently used as car park. . |
Initial Contamination
Evaluation Potential concern due to
past industrial use was identified Possible Contaminants Heavy metals and
petroleum hydrocarbons. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site has an
area |
Specific
hotspots were not identified on site. 8 boreholes are proposed to assess the site condition in general and
the potential impact due to historical use as an oil depot. Proposed parameters to be tested are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
Site J at NCB Container Yard (NOL/ERL/300/C/XRL/ENS/M57/022 of CAP) |
Site Appraisal Past land uses of the
site was found to be open sea and car park. The site
is currently used as a container yard. |
Initial Contamination
Evaluation Potential concern due to
current fuelling and oil drums storage. Possible
Contaminants Petroleum
hydrocarbons, metals. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Cement stabilization/solidification for heavy metals. ·
Bioremediation such as bio-pile and composting for organic
contaminants. |
The site occupies
an area of |
A total of 8 sampling locations have been proposed at the oil drum
storage area, fuelling area and around the site to assess the site condition
in general.
Proposed parameters to be tested are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
Potential Contaminative Uses
Outside Project Sites |
|||||
Site K near LCW Open Area (NOL/ERL/300/C/XRL/ENS/M57/021 of CAP) |
Site Appraisal Past land uses around LCW was open area, traffic roads and some vacant
land. The site is currently vacant. |
Initial Contamination
Evaluation Potential concern due to
the chemical storage area at close proximity Possible Contaminants Petroleum hydrocarbons,
metals and organic solvents, PCB and cyanide. Possible Remediation
Methods Depending on the
contaminated soil quantity and quality, possibly: ·
Stabilization/solidification for
heavy metals and PCB. ·
Bioremediation such as bio-pile and composting for organic
contaminants and cyanide. |
As
observed, the chemical storage area located at Feoso’s building was concrete
paved. Contamination due to chemical stored may not be significant. Land contamination
causing insurmountable impacts would not be likely. Moreover, there are available and commonly
adopted remediation methods for the potential contaminants. |
Specific
hotspots of contamination were identified on site
at chemical storage area at close proximity to the LCW site. 1 sampling location is proposed to asses the potential impacts due to
the nearby chemical store. Proposed parameters to be tested are given in Table 6.1 of CAP. Sampling and testing are proposed to be conducted in Stage 2
supplementary SI works |
Same as Site
I
above. |
9.36
The
corresponding responsible party for the above mitigation measures and
supplementary site investigation are provided in the implementation schedule of
this EIA.
Evaluation of Residual Environmental Impacts
9.37
In terms
of identified soil contamination, the proposed remediation methods would remove
contaminated soils from the site through excavation followed by degradation of
the contaminants to non-toxic substances by biopiling/ ESCO. After completion
of soil remediation for identified contaminated areas, no residual impact in
respect of land contamination on the future users is anticipated.
9.38
This land
contamination assessment has examined the potential contaminative landuses
within the relevant project area and their potential impacts to future
use. The assessment involved site
appraisal, site investigation, assessment of contamination extent and where
necessary formulation of remedial actions.
No adverse impacts are identified for most of the sites within the
project area. Only two sites with small
amount of soil with bis-(2-Ethylhexyl)phthalate exceeding the relevant RBRBs
are found. The volume of soil is only
9.39
There are
some sites that are not accessible to conduct a detailed assessment or site
investigation at this stage. An
evaluation of the sites reveals that there are no insurmountable impacts
identified. These sites will be followed
up during or before the construction stage when the land is made available for
the assessment.